Bam confirmed as contractor for sample school 27/2/2015 Expected confirmation of outcome of feasibility study (refurbishment or rebuild) 31/3/2015 Planning Application submitted to DNPA 14/11/2015 2015 Q1 Q2 Q3 Design phase begins with school Construction begins School opens 7/9/2015 31/3/2016 1/4/2017 Q4 Q1 2016 Q2 Q3 Q4 Q1 2017 Q2 2017 Today Design phase with school Design preparation Planning Approval Process Contract Finalisation Construction 7/9/2015 - 16/10/2015 17/10/2015 - 13/11/2015 14/11/2015 - 12/2/2016 13/2/2016 - 30/3/2016 31/3/2016 - 30/3/2017