Case Study April 2016 D352384X012 Capacity Expansion for Transportation Project San Antonio’s Project, Bolivia Using PipelineStudio® from Emerson (formerly Energy Solutions International), Transierra S.A. has successfully planned and optimized a capacity expansion for a critical natural gas pipeline Margarita Natural gas field output is connected through a 10“ set line (17km) with Sabalo GASAN gas field export lines 28“ OD (20km), which goes to Villamontes GASYRG compressor station (MOP 1440 Psig) and is connected with Yabog. Average Volume Margarita = 1.43 Mmcd Average Volume San Antonio = 13.39 Mmcd total Volume SAN + MGT = 14.82 Mmcd Pressure out San Antonio = 1080 Psig Pressure in Villamontes = 1030 Psig Midstream Oil and Gas Solutions April 2016 “Gasan” Maximun Transport Capacity The maximum design transport capacity is 21 MMCD. To achieve this, an output pressure of 1080 Psi (Sabalo) is required and arrival pressure of 1030 Psig (Villamontes) as shown in the simulation below. To increase transport volume and meet the GTCS, we propose the following alternatives based on simulation: 1. Independent booster system 2. Integrated booster system 3. Loop + booster independent/integer Current Transportation System Transport Capacity with System Compression Booster Installing a booster compression system, at operating conditions of: Suction Pressure = 850-900 Psig Discharge Pressure = 1030 Psig Sabalo Pressure = 1073 Psig Required Power (Approx.) = 8400 Hp is reached at 34 Mmcd Transport Capacity 2 www.EmersonProcess.com/Remote April 2016 Midstream Oil and Gas Solutions Operating Condition Alternative - 1 Alternative - 1 28/34 Mmcd www.EmersonProcess.com/Remote 3 Midstream Oil and Gas Solutions April 2016 Alternative - 1 28/34 Mmcd Transport System’s Simulation, Using PipelineStudio, Ver. 3.1 4 www.EmersonProcess.com/Remote April 2016 Midstream Oil and Gas Solutions Gasan with Loop 28 Mmcd As has been mentioned before, it is required to build a 7Km Loop and 28 OD to increase the transport capacity. The simulation shows that, to achieve an arrival pressure of 1036 Psig (Villamontes) with a 28 Mmcd Flow and an output pressure 1080 Psig (Sabalo Gas Plant), it is not necessary to use compression for this volume, because the conditions of delivery are achieved at this point. Gasan with Loop 7 KM The simulation shows that, to achieve an arrival Pressure of 979/940 Psig (Villamontes) with a 34 Mmcd Flow and an output pressure 1050/1080 Psig (Sabalo Gas Plant), it is necessary to use compression for this volume, because the conditions of delivery required are not achieved at this point. Gasan with Loop 7 KM with Booster The simulation shows that, to achieve an arrival Pressure of 1030 Psig (Villamontes) with a 34 Mmcd Flow and an output pressure 1080 Psig (Sabalo Gas Plant), it is necessary to use a system compression booster with a power of 3000 Hp. www.EmersonProcess.com/Remote 5 Find us around the corner or around the world For a complete list of locations please visit us at www.EmersonProcess.com/Remote Global Headquarters North America and Latin America Emerson Process Management Remote Automation Solutions 6005 Rogerdale Road Houston, TX, USA 77072 T +1 281 879 2699 F +1 281 988 4445 www.EmersonProcess.com/Remote Europe Emerson Process Management Remote Automation Solutions Unit 8, Waterfront Business Park Dudley Road, Brierley Hill Dudley, UK DY5 1LX T +44 1384 487200 F +44 1384 487258 © 2016 Remote Automation Solutions, a business unit of Emerson Process Management. All rights reserved. Emerson Process Management Ltd, Remote Automation Solutions (UK), is a wholly owned subsidiary of Emerson Electric Co. doing business as Remote Automation Solutions, a business unit of Emerson Process Management. FloBoss, ROCLINK, ControlWave, Helicoid, and OpenEnterprise are trademarks of Remote Automation Solutions. AMS, PlantWeb, and the PlantWeb logo are marks owned by one of the companies in the Emerson Process Management business unit of Emerson Electric Co. Emerson Process Managment, Emerson and the Emerson logo are trademarks and service marks of the Emerson Electric Co. All other marks are property of their respective owners. The contents of this publication are presented for informational purposes only. While every effort has been made to ensure informational accuracy, they are not to be construed as warranties or guarantees, express or implied, regarding the products or services described herein or their use or applicability. Remote Automation Solutions reserves the right to modify or improve the designs or specifications of such products at any time without notice. All sales are governed by Remote Automation Solutions’ terms and conditions which are available upon request. Remote Automation Solutions does not assume responsibility for the selection, use or maintenance of any product. Responsibility for proper selection, use and maintenance of any Remote Automation Solutions product remains solely with the purchaser and end-user. Find us in social media RemoteAutomationSolutions Emerson_RAS Remote Automation Solutions Community Remote Automation Solutions D352384X012 / Printed in USA / 04-16 Middle East and Africa Emerson Process Management Remote Automation Solutions Emerson FZE PO Box 17033 Jebel Ali Free Zone - South 2 Dubai, UAE T +971 4 8118100 F +1 281 988 4445 Asia Pacific Emerson Process Management Asia Pacific Private Limited Remote Automation Solutions 1 Pandan Crescent Singapore 128461 T +65 6777 8211 F +65 6777 0947
© Copyright 2026 Paperzz