Job Shop Scheduling
1. Modelling Job Shop Problems
2. Shifting Bottleneck Heuristic
3. Branch & Bound
Operational Research & Management
Operations Scheduling
Topic 1
Job Shop Scheduling Problems
Operational Research & Management
Operations Scheduling
Job Shops
Have m machines and n jobs
Jm || Cmax
Each job visits some or all of the machines
–
Only once (or sometimes multiple times if recirculation is allowed)
Customer order of small batches
–
Wafer fabrication in semiconductor industry
–
Hospital
Very difficult to solve
Operational Research & Management
Operations Scheduling
3
Job Shop Example
Constraints
–
Job follows a specified route of operations
(Conjunctive constraints)
–
One job at a time on each machine
(Disjunctive constraints)
Machine 1
Machine 2
(1,1)
(2,3)
Machine 3
Machine 4
Operational Research & Management
(1,2) (1,3)
(2,1)
(2,2)
(3,1)
(4,3)
(3,3)
(4,2)
Operations Scheduling
4
Definitions
A schedule is non-delay if no machine is kept idle (or free
resource is kept unused) when there is an operation available
A schedule is called active if -without delaying other operationsno operation can be completed earlier
For “regular” objectives: at least one optimal schedule is active
(but not necessarily non-delay)
Operational Research & Management
Operations Scheduling
5
Non-active Schedule
Machine 1
(1,1)
Machine 2
(2,3)
Machine 3
(2,1)
(2,2)
(2,1)
(3,2)
0
Operational Research & Management
2
4
6
Operations Scheduling
8
6
Active Schedule, not Non-delay
Machine 1
(1,1)
Machine 2
(2,3)
Machine 3
(2,2)
(2,1)
(3,2)
0
Operational Research & Management
2
4
6
Operations Scheduling
8
7
Non-delay schedule
Machine 1
(1,1)
Machine 2
(2,3)
Machine 3
(2,1)
(2,2)
(3,2)
0
Operational Research & Management
2
4
6
Operations Scheduling
8
8
Graph Representation (J-on-N)
Each job follows a given route through the job shop
–
Picturing each job as a row of nodes: (i,j)=operation on machine i of job j
(Conjunctive arcs A)
Source
(1,1)
(2,1)
(1,2)
(2,2)
(2,3)
(1,3)
Operational Research & Management
(3,1)
(4,2)
(4,3)
Sink
(3,3)
Operations Scheduling
9
Graph Representation
To model the machine constraints, introduce the arc set B (...),
giving ‘a clique’ of bidirected arc-pairs on each machine
(Disjunctive arc-pairs B)
Source
(1,1)
(2,1)
(1,2)
(2,2)
(2,3)
(1,3)
(3,1)
(4,2)
(4,3)
Sink
(3,3)
Full Graph G(N, AB)
Operational Research & Management
Operations Scheduling
10
Solving the Problem
Select one arc from each pair of disjunctive arcs: D out of B
Source
(1,1)
(2,1)
(1,2)
(2,2)
(2,3)
(1,3)
(3,1)
(4,2)
(4,3)
Sink
(3,3)
Longest path in G(D)=G(N, A D) determines the makespan
Operational Research & Management
Operations Scheduling
11
Feasibility of the Schedule
Are all selections feasible?
Source
(1,1)
(2,1)
(1,2)
(2,2)
(2,3)
(1,3)
(3,1)
(4,2)
(4,3)
Sink
(3,3)
Resulting graph G(D) should be acyclic
Operational Research & Management
Operations Scheduling
12
Disjunctive Programming
Minimize Cmax
s.t.
Cmax yij pij
for all operat's (i, j )
ykj yij pij
for all (i, j ) (k , j )
// arcs in A
yij yil pil or yil yij pij
for all (i, j ) and (i, l )
// arcs in B
yij 0
Operational Research & Management
for all (i, j )
Operations Scheduling
13
Solution Methods
Exact solution
–
Branch & Bound
–
20 machines and 20 jobs
Dispatching rules (16+)
–
Shifting Bottleneck
Search heuristics
–
Tabu, SA, GA, etc.
Operational Research & Management
Operations Scheduling
14
Topic 2
Shifting Bottleneck Heuristic for
Job Shop Scheduling Problems
Operational Research & Management
Operations Scheduling
Shifting Bottleneck
Minimize makespan in a job shop
Let M denote the set of machines
Let M0 M be machines for which disjunctive arcs have been
selected
Basic idea:
–
Select a machine in M - M0 to be included in M0
–
Sequence the operations on this machine
Operational Research & Management
Operations Scheduling
16
Example
Three jobs on four machines
Job j
1
2
3
Sequence
1, 2, 3
2, 1, 4, 3
1, 2, 4
Processing Times on Machine i
1
2
3
10
8
4
3
8
6
4
7
-
4
5
3
total
22
22
14
Processing job 1 (or 2) without delay requires 22
Operational Research & Management
Operations Scheduling
17
Iteration 1
M0
(1,1)
10
(2,1)
8
(3,1)
4
0
Source
0
(2,2)
8
(1,2)
3
(4,2)
5
(3,2)
0
(1,3)
4
(2,3)
7
6
Sink
3
(4,3)
Cmax ( M 0 ) 22
Operational Research & Management
Operations Scheduling
18
Selecting a Machine
Set up a non-preemptive single machine maximum lateness
(1||Lmax) problem for Machine 1:
Job j
p(1, j)
r(1, j)
d(1, j)
1
10
0
10
2
3
8
11
3
4
0
12
Optimum sequence is 1, 2, 3 with Lmax(1) = 5
Consider rj as earliest starting time and dj as latest finish time
Operational Research & Management
Operations Scheduling
19
Selecting a Machine
Set up a non-preemptive single machine maximum lateness
(1||Lmax) problem for Machine 2:
Job j
p(2, j)
r(2, j)
d(2, j)
1
8
10
18
2
8
0
8
3
7
4
19
Optimum sequence is 2, 3, 1 with Lmax(2) = 5
Operational Research & Management
Operations Scheduling
20
Selecting a Machine
Similarly,
Lmax (3) 4
Lmax (4) 0
Either Machine 1 or Machine 2 is the bottleneck
Operational Research & Management
Operations Scheduling
21
Iteration 2
M 0 {1}
(1,1)
0
Source
0
10
(2,1)
8
(3,1)
4
10
(2,2)
0
8
(1,2)
3
4
(1,3)
3
(2,3)
(4,2)
7
5
(3,2)
6
Sink
3
(4,3)
Cmax ({1}) Cmax () Lmax (1) 22 5 27
Operational Research & Management
Operations Scheduling
22
Selecting a Machine
Set up a non-preemptive single machine maximum lateness
(1||Lmax) problem for Machine 2:
Old:
Job j
p(2, j)
r(2, j)
d(2, j)
1
8
10
18
2
8
0
8
3
7
4
19
New:
Job j
p(2, j)
r(2, j)
d(2, j)
1
8
10
23
2
8
0
10
3
7
17
24
Optimum sequence is 2, 1, 3 with Lmax(2) = 1
Operational Research & Management
Operations Scheduling
23
Selecting a Machine
Set up a non-preemptive single machine maximum lateness
(1||Lmax) problem for Machine 3:
Job j
p(3, j)
r(3, j)
d(3, j)
1
4
18
27
2
6
18
27
Optimum sequence is 1, 2 with Lmax(3) = 1
Operational Research & Management
Operations Scheduling
24
Selecting a Machine
Similarly,
Lmax (3) 1
Lmax (4) 0
Either Machine 2 or Machine 3 is the bottleneck
Operational Research & Management
Operations Scheduling
25
Iteration 3
M 0 {1, 2}
(1,1)
0
(2,1)
10
0
Source
10
8
0
(1,2)
3
(1,3)
4
(3,1)
4
8
8
(2,2)
8
3
(2,3)
(4,2)
7
5
(3,2)
6
Sink
3
(4,3)
Cmax ({1, 2}) Cmax ({1}) Lmax (2) 27 1 28
Operational Research & Management
Operations Scheduling
26
Shifting Bottleneck Heuristic
1.
M0:=; G=(N, u, v, A); Cmax := longest path-length in G between u and v
2.
iM-M0 do
// solving a single machine problem
a. for all operations o=(i,j) on machine i do
- find longest paths u-o and o-v of lengths lu,o and lo,v, say,
- define release time rij = lu,o, due date dij = Cmax - (lo,v -pij)
b. for this single machine problem on i: determine L*max(i) with choices D*(i)
3.
4.
k := arg max iM0 L*max(i) ;
// decide for bottleneck machine k
Insert arcs D(k)=D*(k) in G and update Cmax
// Cmax may increase
iM0-{k} do
// Re-sequencing ‘decided’ machines
a. remove D(i) from G and recompute Cmax
b.
recompute D*(i) as in step 2 above
c.
insert D(i)= D*(i) in G and update Cmax
// Cmax may decrease
5. M0:= M0 {k}; if M0<M then (add delayed precedence and) return to step 2.
Operational Research & Management
Operations Scheduling
27
Discussion
Procedure continues until all disjunctive arcs have been added
Watch out for cycles, because of other (scheduled) machines
–
delayed precedence constraints may be required, see example in book
Very effective
–
Relatively fast
–
Good solutions
–
More general Job Shop problems can be solved as well
‘Just a heuristic’
–
No guarantee of optimum
–
The subproblem Max. Lateness, 1 | rj , prec | Lmax , is NP-hard
Operational Research & Management
Operations Scheduling
28
Discussion
Shifting bottleneck can be applied generally
Basic idea
–
Solve problem “one variable at a time”
–
Determine the “most important” variable
–
Find the best value of that variable
–
Move on to the “second most important” ….
–
Here we treat each machine as a variable
Operational Research & Management
Operations Scheduling
30
Topic 3
Branch & Bound for
Job Shop Scheduling Problems
Operational Research & Management
Operations Scheduling
Branch and Bound
Minimize makespan
Notation
–
operation (i,j) has duration pij
–
Let W denote operations whose predecessors have all been
scheduled
–
Let rij be the earliest possible starting time of (i,j) in W.
FIRST SUBJECT: How to branch to active schedules
Operational Research & Management
Operations Scheduling
32
Branching
In the optimal schedule each machine has some order for its
operations: let machine i has first (i, j1), then (i, j2) etc.
In partial schedules, B&B subproblems at level k, it is decided for
[some] machines i, in ancestor B&B nodes, which operations are
(i,j1), (i,j2),..., (i, jk(i) ) [possibly k(i)=0 –if i has no decisions yet]
Ancestor choices
New choices:
for some machine i* decide
on a next operation
(i*, jk(i)+1)=(i*, j')
(i*, jk(i)+1)=(i*, j''')
(i*, jk(i)+1)=(i*, j'')
!Avoid partial schedules that are not active!
Operational Research & Management
Operations Scheduling
33
Which operations can be next in active schedule?
{ first of unscheduled operations for each job}
t ( )
min
rij pij ri* j 0 pi* j 0
(i, j )
// first finish
'(i*) {(i*, j ) : operations on i * with release ri* j t ()}
Machine i*
If active,
a schedule can have
(i*, j) ' as
the next i*-operation,
but not (i*,k) '
(i*, j)
(i*, j0)
0 t
Operational Research & Management
(i(i*,k)
*, k ) '
(i*, j0)
ri* j t() ri* k
Operations Scheduling
34
' is a subset of , why?
Suppose (i*, j) in ' is not part of :
i.e., some other operation, say (i1, j) is first for job j.
(i1, j) is by definition in and to be scheduled before (i*, j)
Gant-Chart of operations of j:
and of j0:
Then:
ri* j0 + pi* j0 = t() <= ri1 j + pi1 j <= ri* j,
(i*, j)
(i1, j)
(i*, j0)
t()
showing that (i*,j) is cannot be part of ' {(i*, j) on i*| ri* j t ()}
Operational Research & Management
Operations Scheduling
35
Generating Active Schedules
Step 1. (Initialize)
–
Let contain the first operations of each job; rij = 0 for all (i,j) ;
Step 2. (Machine selection)
–
Compute of current partial schedule: time t ()
–
i* = associated machine
min rij pij
(i, j )
Step 3. (Branching) // extends current schedule in all active ways
ri* j t ()
–
Let ’ consist of operations (i*, j) on machine i* with
–
For each (i*, j) in ’ extend current partial schedule with (i*, j) next on i*
–
For each thus generated, extended partial schedule:
a. delete (i*, j) from , insert immediate follower (k, j) in ,
b. return with this schedule, as current, to step 2.
Operational Research & Management
Operations Scheduling
36
Branching Tree
ancestor choices
Some machine i* decides
on next operation
(i*, jk(i)+1)=(i*, j')
(i*, jk(i)+1)=(i*, j''')
(i*, jk(i)+1)=(i*, j'')
Generating active schedules, that is
not all choices, only operations (i*, j' ) of '
Operational Research & Management
Operations Scheduling
37
On Example
0
Source
(1,1)
0 (2,2) 8
0
10
(1,2)
4
(1,3)
(2,1)
3
(2,3)
8
(4,2)
7
(3,1)
4
5
6
(3,2)
3
(4,3)
Level 1
root
{(1,1), (2, 2), (1,3)}
t () min{0 10, 0 8, 0 4} 4
i* 1
' {(1,1), (1,3)}
Operational Research & Management
Sink
(1,1)
22
(1,3)
Branch at level 1 for possibilities
’ of (1, j1) at i* =1
Operations Scheduling
38
Level 1: when (1,1) is first on machine 1
(1,1)
0
Source
0
10
(2,2)
8
10
(2,1)
(3,1)
4
10
(1,2)
3
0
(1,3)
8
4
(2,3)
(4,2)
7
5
(3,2)
6
Sink
3
(4,3)
Cmax >= 24
Disjunctive Arcs
Operational Research & Management
Operations Scheduling
39
Level 1: when (1,3) is first on machine 1
(1,1)
10
(2,1)
8
(3,1)
4
0
Source
0
(2,2)
0
8
(1,2)
3
(4,2)
5
(3,2)
4
4
4
(1,3)
(2,3)
7
6
Sink
3
(4,3)
Cmax >= 26
Disjunctive Arcs
Operational Research & Management
Operations Scheduling
40
Branching Tree
Start, no disjunctive arcs
LB=22
(1,1) scheduled first
on machine 1
(1,3) scheduled first
on machine 1
LB = 24
LB = 26
Operational Research & Management
Operations Scheduling
41
Next branching: at subproblem (1,1)
(1,1)
10
(2,1)
8
(3,1)
4
0
10
8 10
6
3
5
0
Source
(2,2)
(1,2)
(4,2)
(3,2)
0
3
7
4
(1,3)
(2,3)
(4,3)
Level 2
root
{(2,2), (2,1), (1,3)}
t () min{0 8, 10 8, 10 4} 8
Sink
22
(1,1)
(1,3)
i* 2
' {(2,2)}
Operational Research & Management
(2,2)
Operations Scheduling
42
Level 2: Extending to (2,2) as first on machine 2
As yet no new disjunctive Arcs
(1,1)
0
Source
0
8
8
(2,2)
0
10
10
(1,2)
(2,1)
3
8
(4,2)
(3,1)
5
4
(3,2)
6
Sink
8
(1,3)
4
(2,3)
7
3
(4,3)
Still LB=24
Operational Research & Management
Operations Scheduling
43
Branching Tree
LB=22, no disjunctive arcs
(1,1) scheduled first
on machine 1
LB = 24
(1,3) scheduled first
on machine 1
(1,1) first on M1 and
(2,2) first on M2
LB = 26
LB = 24
Operational Research & Management
Operations Scheduling
44
Lower Bounds
Lower bounds
–
Length of critical path in G(D’).
–
Linear programming relaxation.
–
Very quick but not very tight
Less quick but tighter
Maximum Lmax over all machines
Like in Shifting-Bottleneck Heuristic
slowest (m NP-hard problems), but tightest !
Operational Research & Management
Operations Scheduling
45