Current Estimated Timeline of Tasks for the Roseburg Secretarial Pilot Project

Estimated Timeline of Tasks for the Roseburg District Pilot Project
Updated on 12/15/2011
(from inception to auction; post-project monitoring not included)
0
4
8
12
16
20
24
28
32
36
40
Weeks
44
48
52
56
60
64
68
72
76
80
84
88
Development of Goals & Objectives
Development of Process & Timeline
Landscape Assessment & Stand Pool Selection
Field Reconnaissance of Stand Pool
Sample Stand Marking
Public Review of Sample Marking
Development of Purpose and Need
Initial Unit Design
S&M Surveys
Resource Surveys
Public Scoping Meeting
Development of NEPA Issues & Purpose & Need
Analysis and Writing
Public Meeting, Review of Unit Design
Synthesis and Document Prep
Internal Reiview
Revisions based on Review
Public review
BA Consultation
Access & ROW Needs
S&M Surveys Round #2
Layout, Buck Rising
Marking, Buck Rising
Cruising, Buck Rising
Appraisal, Contract Prep, & Decision Record, B.R.
Advertisement, Buck Rising
Auction, Buck Rising
Layout, White Castle*
Marking, White Castle*
Cruising, White Castle
Appraisal, Contract Prep, & Decision Record, W.C.
Advertisement, White Castle
Auction, White Castle
*These steps are scheduled for winter and and early spring at high elevation and therefore could be delayed if snow prohibits access to the project
92