Estimated Timeline of Tasks for the Roseburg District Pilot Project Updated on 12/15/2011 (from inception to auction; post-project monitoring not included) 0 4 8 12 16 20 24 28 32 36 40 Weeks 44 48 52 56 60 64 68 72 76 80 84 88 Development of Goals & Objectives Development of Process & Timeline Landscape Assessment & Stand Pool Selection Field Reconnaissance of Stand Pool Sample Stand Marking Public Review of Sample Marking Development of Purpose and Need Initial Unit Design S&M Surveys Resource Surveys Public Scoping Meeting Development of NEPA Issues & Purpose & Need Analysis and Writing Public Meeting, Review of Unit Design Synthesis and Document Prep Internal Reiview Revisions based on Review Public review BA Consultation Access & ROW Needs S&M Surveys Round #2 Layout, Buck Rising Marking, Buck Rising Cruising, Buck Rising Appraisal, Contract Prep, & Decision Record, B.R. Advertisement, Buck Rising Auction, Buck Rising Layout, White Castle* Marking, White Castle* Cruising, White Castle Appraisal, Contract Prep, & Decision Record, W.C. Advertisement, White Castle Auction, White Castle *These steps are scheduled for winter and and early spring at high elevation and therefore could be delayed if snow prohibits access to the project 92
© Copyright 2026 Paperzz