Projects Communication Plan

Project: Binya Way Upgrade, Wagga campus
Location:
Binya Way adjacent to the following Buildings
253,261,262&263
Time Line:
11th January 2016 – 2nd February 2016
Project Cost : $180,000.00
Brief:
The Division of Facilities Management is rolling out the
2015 – 2016 planned program works that involves
upgrades to roads on the Wagga Campus. The works
include Binya Way road adjacent to the following
Buildings 253,261,262&263.This area will be closed to
all vehicles for the duration of the works.
Works will commence from the 11th January 2016 and
that, weather permitting, will be completed by 2nd
February 2016.
During the construction, traffic management processes will
be in place. Vehicles coming to this precinct area of the
University will have two options:
1: CSU personnel will still have access CSU vehicle
compound via Binya Way for pickup/drop off. Once inside
the compound proceed to Transport Building via the
designated route to key pick up/drop-off.
(See Figure 2 - Detour Traffic Plan)
2: For CSU Personnel, Supplies & Contractors have to
entry/exit via Nathan Cobb Drive to access Transport,
Stores and DFM Operations.
(See Figure 2 - Detour Traffic Plan)
Further messages will be placed on 'What’s New" and
information including the site and traffic management
plans will be available from the Divisions website
http://www.csu.edu.au/division/facilitiesm/outages
Figure 1 – Binya Way Road showing the location of the Road upgrade.
Attached:
1.
Road Pavement & Draining Design
2.
Construction Program
University Representative:
Stephen Butt
Executive Director, Facilities Management
Primary Contact :
Paul Baker
Senior Coordinating Construction
Project Manger – 0411 407 016
Date: 17th December 2015
Figure 2 - Detour Traffic Plan.
Wagga Wagga Charles Sturt University Binya Way Pavement Works
ID
Task Name
1
Binya Way Civil Works
2
Duration
Site Establishment
Start
Finish
20 days
Thu 7/01/16
Wed 3/02/16
Predecessors
2 days
Fri 8/01/16
Mon 11/01/16
3
Install temp fencing
1 day
Fri 8/01/16
Fri 8/01/16
4
Deliver site sheds
1 day
Fri 8/01/16
Fri 8/01/16 3
5
Connect services to sheds
2 days
Fri 8/01/16
Mon 11/01/16 4
6
Pavement works Binya Way
15 days
Mon 11/01/16
Fri 29/01/16
Thu 7/01/16
Thu 7/01/16
7
Services locations
8
Strip asphalt from site
1 day
3 days
4 Jan '16
11 Jan '16
18 Jan '16
25 Jan '16
1 Feb '16
un 3 Januar
Mon 4 Januarue 5 Januar
Wed 6 Januahu 7 JanuarFri 8 January
Sat 9 Januarun 10 Januaon 11 Januaue 12 Januaed 13 Janua
hu 14 Januari 15 Januarat 16 Januaun 17 Januaon 18 Januaue 19 Januaed 20 Janua
hu 21 Januari 22 Januarat 23 Januaun 24 Januaon 25 Januaue 26 Januaed 27 Janua
hu 28 Januari 29 Januarat 30 Januaun 31 Januaon 1 Februaue 2 Februaed 3 Februahu 4 Februari
Mon 11/01/16 Wed 13/01/16 7
9
Proof roll existing sub grade
1 day
Thu 14/01/16
10
Remove existing gate post
1 day
Thu 14/01/16
Thu 14/01/16 8
Thu 14/01/16 9
11
Install new gate post & make
good fence
2 days
Fri 15/01/16
Mon 18/01/16 10
12
Excavate for dish drain
1 day
Mon 18/01/16
Mon 18/01/16 11
13
Excavate and install S/W pits &
pipework
2 days
14
Form & pour dish drain
3 days
Thu 21/01/16
Sat 23/01/16 13
15
Prepare sub grade
3 days
Sun 24/01/16
Tue 26/01/16 14
16
Proof roll sub grade
1 day Wed 27/01/16 Wed 27/01/16 15
17
Lay Hot Mix
1 day
Thu 28/01/16
Thu 28/01/16 16
18
Install new gate
1 day
Fri 29/01/16
Fri 29/01/16 17
Tue 19/01/16 Wed 20/01/16 12
19
20
14 days
Thu 7/01/16
21
Pavement Works Laneway
Services locations
1 day
Thu 7/01/16
22
Strip asphalt from site
1 day
Mon 11/01/16
Mon 11/01/16 8,21
23
Proof roll existing sub grade
1 day
Tue 12/01/16
Tue 12/01/16 22
24
Excavate for dish drain
1 day Wed 13/01/16 Wed 13/01/16 23,16FS-17 days,1
25
Form & pour dish drain
26
Make good concrete footpath
27
28
29
30
Tue 26/01/16
Thu 7/01/16 7
3 days
Thu 14/01/16
Sun 17/01/16 24,14
1 day
Mon 18/01/16
Mon 18/01/16 25
Prepare sub grade
4 days
Tue 19/01/16
Proof roll sub grade
1 day
Sat 23/01/16
Sat 23/01/16 27
Tue 26/01/16 28
Lay 2 coat seal
Demobilisation of site
31
Remove temp fences
32
Remove site sheds & seal off
services
Project: Wagga Wagga CSU Binya Wa
Date: Thu 17/12/15
Fri 22/01/16 26,15
2 days
Mon 25/01/16
3 days
Mon 1/02/16
1 day
Tue 2/02/16
Tue 2/02/16 29
2 days
Mon 1/02/16
Tue 2/02/16 31
Wed 3/02/16
Task
Summary
External Milestone
Inactive Milestone
Duration-only
Start-only
Split
Project Summary
Inactive Task
Inactive Summary
Manual Summary Rollup
Finish-only
Milestone
External Tasks
Inactive Task
Manual Task
Manual Summary
Progress
Page 1
Deadline