Project: Binya Way Upgrade, Wagga campus Location: Binya Way adjacent to the following Buildings 253,261,262&263 Time Line: 11th January 2016 – 2nd February 2016 Project Cost : $180,000.00 Brief: The Division of Facilities Management is rolling out the 2015 – 2016 planned program works that involves upgrades to roads on the Wagga Campus. The works include Binya Way road adjacent to the following Buildings 253,261,262&263.This area will be closed to all vehicles for the duration of the works. Works will commence from the 11th January 2016 and that, weather permitting, will be completed by 2nd February 2016. During the construction, traffic management processes will be in place. Vehicles coming to this precinct area of the University will have two options: 1: CSU personnel will still have access CSU vehicle compound via Binya Way for pickup/drop off. Once inside the compound proceed to Transport Building via the designated route to key pick up/drop-off. (See Figure 2 - Detour Traffic Plan) 2: For CSU Personnel, Supplies & Contractors have to entry/exit via Nathan Cobb Drive to access Transport, Stores and DFM Operations. (See Figure 2 - Detour Traffic Plan) Further messages will be placed on 'What’s New" and information including the site and traffic management plans will be available from the Divisions website http://www.csu.edu.au/division/facilitiesm/outages Figure 1 – Binya Way Road showing the location of the Road upgrade. Attached: 1. Road Pavement & Draining Design 2. Construction Program University Representative: Stephen Butt Executive Director, Facilities Management Primary Contact : Paul Baker Senior Coordinating Construction Project Manger – 0411 407 016 Date: 17th December 2015 Figure 2 - Detour Traffic Plan. Wagga Wagga Charles Sturt University Binya Way Pavement Works ID Task Name 1 Binya Way Civil Works 2 Duration Site Establishment Start Finish 20 days Thu 7/01/16 Wed 3/02/16 Predecessors 2 days Fri 8/01/16 Mon 11/01/16 3 Install temp fencing 1 day Fri 8/01/16 Fri 8/01/16 4 Deliver site sheds 1 day Fri 8/01/16 Fri 8/01/16 3 5 Connect services to sheds 2 days Fri 8/01/16 Mon 11/01/16 4 6 Pavement works Binya Way 15 days Mon 11/01/16 Fri 29/01/16 Thu 7/01/16 Thu 7/01/16 7 Services locations 8 Strip asphalt from site 1 day 3 days 4 Jan '16 11 Jan '16 18 Jan '16 25 Jan '16 1 Feb '16 un 3 Januar Mon 4 Januarue 5 Januar Wed 6 Januahu 7 JanuarFri 8 January Sat 9 Januarun 10 Januaon 11 Januaue 12 Januaed 13 Janua hu 14 Januari 15 Januarat 16 Januaun 17 Januaon 18 Januaue 19 Januaed 20 Janua hu 21 Januari 22 Januarat 23 Januaun 24 Januaon 25 Januaue 26 Januaed 27 Janua hu 28 Januari 29 Januarat 30 Januaun 31 Januaon 1 Februaue 2 Februaed 3 Februahu 4 Februari Mon 11/01/16 Wed 13/01/16 7 9 Proof roll existing sub grade 1 day Thu 14/01/16 10 Remove existing gate post 1 day Thu 14/01/16 Thu 14/01/16 8 Thu 14/01/16 9 11 Install new gate post & make good fence 2 days Fri 15/01/16 Mon 18/01/16 10 12 Excavate for dish drain 1 day Mon 18/01/16 Mon 18/01/16 11 13 Excavate and install S/W pits & pipework 2 days 14 Form & pour dish drain 3 days Thu 21/01/16 Sat 23/01/16 13 15 Prepare sub grade 3 days Sun 24/01/16 Tue 26/01/16 14 16 Proof roll sub grade 1 day Wed 27/01/16 Wed 27/01/16 15 17 Lay Hot Mix 1 day Thu 28/01/16 Thu 28/01/16 16 18 Install new gate 1 day Fri 29/01/16 Fri 29/01/16 17 Tue 19/01/16 Wed 20/01/16 12 19 20 14 days Thu 7/01/16 21 Pavement Works Laneway Services locations 1 day Thu 7/01/16 22 Strip asphalt from site 1 day Mon 11/01/16 Mon 11/01/16 8,21 23 Proof roll existing sub grade 1 day Tue 12/01/16 Tue 12/01/16 22 24 Excavate for dish drain 1 day Wed 13/01/16 Wed 13/01/16 23,16FS-17 days,1 25 Form & pour dish drain 26 Make good concrete footpath 27 28 29 30 Tue 26/01/16 Thu 7/01/16 7 3 days Thu 14/01/16 Sun 17/01/16 24,14 1 day Mon 18/01/16 Mon 18/01/16 25 Prepare sub grade 4 days Tue 19/01/16 Proof roll sub grade 1 day Sat 23/01/16 Sat 23/01/16 27 Tue 26/01/16 28 Lay 2 coat seal Demobilisation of site 31 Remove temp fences 32 Remove site sheds & seal off services Project: Wagga Wagga CSU Binya Wa Date: Thu 17/12/15 Fri 22/01/16 26,15 2 days Mon 25/01/16 3 days Mon 1/02/16 1 day Tue 2/02/16 Tue 2/02/16 29 2 days Mon 1/02/16 Tue 2/02/16 31 Wed 3/02/16 Task Summary External Milestone Inactive Milestone Duration-only Start-only Split Project Summary Inactive Task Inactive Summary Manual Summary Rollup Finish-only Milestone External Tasks Inactive Task Manual Task Manual Summary Progress Page 1 Deadline
© Copyright 2026 Paperzz