OrangeCampus-Road-Carpark-upgrade-2015.pdf

Project: Road Carpark Upgrade, Orange campus
Location:
Carparks 9, 8,7 & 6 and the road way adjacent to
these carparks
Time Line:
23rd December 2015 – 29th January 2016
Project Cost : $350,000.00
Brief:
The Division of Facilities Management is rolling out
the 2015 – 2016 planned program works that
involves upgrades to roads and carparks on the
Orange Campus. The works include Carparks 9, 8,7 &
6 and the road adjacent to these carparks. This area
will be closed to all vehicles for the duration of the
works.
Works will commence from the 23rd December 2015
and that, weather permitting, will be completed by
29th January 2016.
During the construction, traffic management
processes will be in place. Vehicles coming to the
University will have two options:
1: Traffic travelling from Orange along Leeds Parade
and entering via the main entrance or;
2: Traffic travelling from Orange along Leeds Parade
can enter via the Secondary entrance to travel to
CSU Equine, Horticultural and sporting facilities.
(See Figure 2 - Detour Traffic Plan)
Figure 1 – Campus Plan showing the location of the Road & Carpark upgrade.
Further messages will be placed on 'What’s New"
and information including the site and traffic
management plans will be available from the
Divisions website
http://www.csu.edu.au/division/facilitiesm/outages
University Representative:
Stephen Butt
Executive Director, Facilities Management
Primary Contact :
Paul Baker
Senior Coordinating Construction
Project Manger – 0411 407 016
Date: 9th December 2015
Figure 2 - Detour Traffic Plan.