Development Review Process Timeline (PDF doc)

GREAT LAWN FACTS
Development Review Process Timeline
The Gardens on Spring Creek is committed to making The Gardens completion project, including the Great Lawn, a
success for the greater Fort Collins community as well as the surrounding neighborhoods and businesses.
ACTION ITEM
DATE
OUTCOMES
Design Charrette
March 2014
Gathering ideas and feedback.
Public Meeting #1
July 24, 2014
Public Meeting #2
Sept. 8, 2014
Changed location of sound walls to further east.
Rental policies changed to prohibit DJ’s. All music must end
by 8 p.m.
Sounds walls moved east and lowered.
Sound levels monitored for all events with music.
Policy Changes
Sept. 2014-Sept. 2015
City changes process for City projects in development review.
Neighbor Mailing
Oct. 19, 2015
Gardens send a letter and FAQ sheet.
Planning and Zoning
Board Meeting #1
Dec. 17, 2015
Project pending. Planning and Zoning Board asks Gardens
and City Staff to reach out to neighbors.
City Staff and Small
Neighbor Stakeholder
Group meeting
Jan. 19, 2016
Public Meeting #3
Feb. 8, 2016
Host neighborhood meeting.
Neighbor presents a draft MOU to Gardens staff for review.
An additional sound wall was added.
Permanent Sound meters positioned along fence/sound wall
Override system confirmed.
Possibility of temporarily closing portion of Lilac Park adjacent
to Gardens during concert events.
Neighbor Mailing
March 23, 2016
Planning and Zoning
Board Meeting #2
April 7, 2016
Letter outlines results of Public Meeting #3.
Update 3/25/16
For more project information, visit fcgov.com/gardens