Matakuliah Tahun : Manajemen Keuangan 1 : 2009 PERMASALAHAN PEMERINGKATAN PROYEK Pertemuan 18 Capital Rationing • You could rank the projects by IRR: IRR Our budget is limited so we accept only projects 1, 2, and 3. 25% 20% 15% 10% 5% 1 2 3 4 $X Bina Nusantara University 5 $ 3 Capital Rationing • Ranking projects by IRR is not always the best way to deal with a limited capital budget. • It’s better to pick the largest NPVs. • Let’s try ranking projects by NPV. Bina Nusantara University 4 Bina Nusantara University 5 Bina Nusantara University 6 Bina Nusantara University 7 Bina Nusantara University 8 Bina Nusantara University 9 Bina Nusantara University 10 Bina Nusantara University 11 Step 2 Calculate the EAA ) (Equivalent Annual Annuity • NPV : PVIFA • EAA1 = 1.433/2,322= $617 • EAA2 = 1.664/3.889= $428 • Decision Rule: Select the highest EAA. We would choose machine #1. Bina Nusantara University 12 Bina Nusantara University 13