Addendum - Bidder's Conference: Support Team Funding Availability Solicitation (FAS) #15658 - Questions and Answers

Delivery System Reform Incentive Payment (DSRIP) Program
Bidder’s Conference: Support Team Funding Availability Solicitation (FAS) #15658
QUESTIONS AND ANSWERS - ADDENDUM
The following question is amended:
Q42. Success of the DSRIP program requires not only careful and thoughtful planning, but also
close attention to the complexities of system reform implementation. Performing Provider
Systems will likely require outside assistance with their implementation initiatives. In that
regard, will the firm awarded the DST contract be permitted to provide direct consulting
services to PPSs following the conclusion of the DST contract as of 4/15/2014 [sic]?
A. Yes, provided that no proprietary products of the Department developed during the Support
Team contract are used after the expected end of the DST contract period on 4/1/2014
4/1/2015.