Earned Value Management at Saab Naval Systems Division Sweden -Planning Package conversion and Performance Measurement Techniques Rasmus Vestberg Supervisors: Dag Swartling, Linköping Institute of Technology Michael Trochez, Saab AB Master Thesis LiTH-IEI-EX—07/??—SE Department of Management and Engineering at Linköping Institute of Technology and Saab Naval Systems Division Sweden Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden Vestberg, Rasmus Abstract Abstract In traditional Project Management one determines the budget and measures the cost against that budget as project goes on. In Earned Value Management, which has been adopted by Saab’s Naval Systems Division less than two years ago, one also measures the actual performance by assigning finished work a value. As a consequence of the recent adoption of the Earned Value Management the Planning Department asked for a study of following two questions; How far can one do detailed planning and how should the value be measured? The report is based on a studious literature study combined and analyzed together with historical data from existing projects at Naval Systems Division. The result indicates that the Naval Systems Division is not using Earned Value Management at its full potential. A lot of money is spent to get the management system working, but many things are not implemented in the best way. The figures provided to Naval Systems Division is not showing the true Earned Value as could be if the system was used in a different way. One can argue that the Naval Systems Division is still using traditional project management only dressed in Earned Value figures. This is in large extent a consequence of not measuring the value in the right way. By using other measurement methods the system will measure the true performance instead of doing subjective judgment as per today. As a consequence of this flawed use of Earned Value Management many of the people working in the project does not accept the system. Also a lot of work is spent clearing up the Earned Value figures to the customer, instead of using them as a helpful tool in the project management. By adapting the entire Earned Value concept several benefits will follow. Today the forecasting of a projects final outcome is made in a time consuming traditional project management way instead of using the mathematical approach provided by Earned Value Management. The Earned Value Management forecasting method is very easy to use and will save a lot of work and money for Naval Systems Division. This study shows that in this case, the easier method even provides better accuracy. 2 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden The research also implies that detailed planning could be done very far in advance. No figures provided by the investigation indicates that detailed planning of nearby work packages are more accurate than work packages planned far away. 3 Vestberg, Rasmus Table of Contents Table of Contents 1 2 INTRODUCTION ....................................................................................................................................... 8 1.1 ABOUT SAAB AB.................................................................................................................................. 8 1.2 BACKGROUND ...................................................................................................................................... 8 1.3 PURPOSE ............................................................................................................................................... 9 1.4 DISPOSITION ......................................................................................................................................... 9 METHOD................................................................................................................................................... 12 2.1 THEORY .............................................................................................................................................. 12 2.1.1 Four Dimensional Studies............................................................................................................. 12 2.1.2 Quality of the Research ................................................................................................................. 13 2.1.3 Interviews ...................................................................................................................................... 13 2.2 USED METHODS .................................................................................................................................. 14 2.2.1 Frame of Reference ....................................................................................................................... 14 2.2.2 Empirical Study............................................................................................................................. 15 2.2.2.1 Interviews ............................................................................................................................................ 15 2.2.2.2 Analyzing historical data..................................................................................................................... 15 2.3 3 METHOD CRITICISM ............................................................................................................................ 19 2.3.1.1 Literature ............................................................................................................................................. 19 2.3.1.2 Interviews ............................................................................................................................................ 19 2.3.1.3 Analyzing historical data..................................................................................................................... 20 FRAME OF REFERENCE ...................................................................................................................... 22 3.1 TRADITIONAL PROJECT MANAGEMENT ............................................................................................... 22 3.2 EARNED VALUE MANAGEMENT ......................................................................................................... 23 3.2.1 History of EVM ............................................................................................................................. 23 3.2.2 This is EVM ................................................................................................................................... 24 3.2.2.1 SPI and CPI ......................................................................................................................................... 27 3.2.2.2 Baseline - Scope the Project ................................................................................................................ 29 3.2.2.3 Scheduling........................................................................................................................................... 31 3.2.2.4 Performance Measurement Techniques............................................................................................... 33 3.2.2.4.1 Weighted Milestones...................................................................................................................... 33 3.2.2.4.2 Fixed Formula ................................................................................................................................ 34 3.2.2.4.3 Percent Complete Estimates........................................................................................................... 35 3.2.2.4.4 Percent Complete and Milestones .................................................................................................. 35 3.2.2.4.5 Equivalent Completed Units .......................................................................................................... 36 3.2.2.4.6 Apportioned Relationship .............................................................................................................. 36 3.2.2.4.7 Level of Effort................................................................................................................................ 37 3.2.2.5 Forecasting .......................................................................................................................................... 38 3.2.2.5.1 Mathematical EAC – Best Case Scenario ...................................................................................... 38 3.2.2.5.2 Cumulative Cost Performance Index – Most Likely ...................................................................... 39 4 Earned Value Management at Vestberg, Rasmus 4 3.2.2.5.3 Cumulative CPI times SPI – Worst Case Scenario ........................................................................ 39 3.2.2.5.4 Predicting completion date............................................................................................................. 40 3.3 EARNED SCHEDULING ........................................................................................................................ 40 3.4 GOLD PRACTICE ................................................................................................................................. 44 EMPIRICAL STUDY ............................................................................................................................... 46 4.1 EVM AT NAVAL SYSTEMS DIVISION .................................................................................................. 46 4.1.1 Project Organization..................................................................................................................... 46 4.1.2 Earned Value................................................................................................................................. 48 4.1.2.1 Planning Packages.......................................................................................................................... 48 4.1.2.1.2 Work Packages............................................................................................................................... 49 Performance Measurement Techniques............................................................................................... 49 4.1.2.2.1 Percent Complete Estimates........................................................................................................... 50 4.1.2.2.2 Level of Effort................................................................................................................................ 50 4.1.2.3 Scheduling........................................................................................................................................... 51 4.1.2.4 Forecasting and Predicting Completion Date ...................................................................................... 51 4.2 FORECASTING ACCURACY AT NSDS .................................................................................................. 52 4.2.1 Accurateness Relative Entire Work Package ................................................................................ 52 4.2.2 Accurateness Relative Remaining Work........................................................................................ 55 4.3 NSDS FORECASTING VS. CUMULATIVE CPI FORECASTING ................................................................ 57 4.3.1 Relative Entire Work Package ...................................................................................................... 58 4.3.2 Relative Remaining Work.............................................................................................................. 62 ANALYSIS................................................................................................................................................. 68 5.1 PLANNING PACKAGE CONVERSION ...................................................................................................... 68 5.1.1 Relative Entire Work ..................................................................................................................... 68 5.1.2 Relative Remaining Work.............................................................................................................. 69 5.2 6 Scoping the Project at Naval Systems Division................................................................................... 48 4.1.2.1.1 4.1.2.2 5 Saab Naval Systems Division Sweden PMT ................................................................................................................................................... 70 5.2.1 Analyze based on Frame of Reference .......................................................................................... 71 5.2.2 Analyze based on Empirical Study ................................................................................................ 71 DISCUSSION............................................................................................................................................. 74 6.1 PMT ................................................................................................................................................... 74 6.1.1 Automatic Earned Value ............................................................................................................... 74 6.1.2 NSDS subjective Measurement Technique .................................................................................... 75 6.1.3 Level of Effort................................................................................................................................ 76 6.2 PLANNING PACKAGE CONVERSION ..................................................................................................... 77 6.2.1 Forecasting ................................................................................................................................... 77 6.2.2 Rolling planning’s affect on EVM ................................................................................................. 79 6.3 6.3.1 MISCELLANEOUS ................................................................................................................................ 81 Earned Scheduling ........................................................................................................................ 81 5 Vestberg, Rasmus 6.3.2 7 Table of Contents Earned Value Acceptance ............................................................................................................. 82 CONCLUSIONS........................................................................................................................................ 84 7.1 PLANNING PACKAGE CONVERSION ..................................................................................................... 84 7.2 PMT ................................................................................................................................................... 84 7.3 FORECASTING ..................................................................................................................................... 85 7.4 MISCELLANEOUS ................................................................................................................................ 85 8 REFERENCES .......................................................................................................................................... 88 9 APPENDICES ........................................................................................................................................... 92 9.1 APPENDIX 1 ........................................................................................................................................ 92 6 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden 7 Vestberg, Rasmus Chapter 1 - Introduction 1 Introduction This chapter will treat the background and subject of this master thesis. 1.1 About Saab AB SAAB (Svenska Aeroplane Aktiebolag) was originally founded in the spring 1937. During the first years SAAB only produced airplanes for the Swedish military defense. Today the SAAB brand is closely related to the cars which they started to manufacture in the 1940’s. However the car division was sold to General Motors a couple of years ago who are using the brand through a license. This means that Saab AB has nothing to do with the SAAB cars today. In the fifties and sixties SAAB increased the direction to also include computers, missiles, space technology etcetera. 1 Today SAAB has changed its name to Saab AB and is in popular speech called Saab Technologies. The direction of the company has been further increased and Saab AB is today split into three different segments; Defense and Security Solutions, Systems and Products and Aeronautics. These different segments are further split into several business units. One of the business units included in Defense and Security is Saab Systems, with over 1300 employees, which is further split into five divisions. One of those divisions is the Naval Systems Division Sweden (NSDS). 2 The Naval Systems Division is the division for this thesis. 1.2 Background The Earned Value Management (EVM) is quite recently adopted at Naval Systems Division. The model is in use but without wide acceptance and cooperation from the staff. The level of detail planning when setting up a project is subject for constant discussion. Guidance regarding planning package conversion and overall Earned Value Management is needed so projects can have a shorter start-up time without loosing quality. 1 http://saabnet.saabgroup.com 2 http://saabnet.saabgroup.com 8 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden 1.3 Purpose The purpose of this master thesis is to study the use of Performance Measurement Techniques (PMT) and Planning Packages in Earned Value Management at Saab Systems Naval Systems Division. Different PMT will be compared to each other to tell which ones are best suited for Saab Systems Naval Systems Division. Studying the accuracy of the project planning and measuring aims to provide guidance for conversion of Planning Packages. The thesis aims to answer the following two main questions: • In which time frame is the knowledge regarding future work high enough to breakdown planning packages into work packages? • How should NSDS measure the work to attain most valid Earned Value metrics? 1.4 Disposition In chapter 2 the different methods used during this thesis is discussed in detail. The pros and cons with used methods are discussed to provide the reader with information regarding subject of errors in the work. Chapter 3 treats the Frame of Reference subjective to the purpose of the thesis. Common knowledge and facts found in literature is described in detail to give the reader a basic background of Earned Value Management. Chapter 4 will present the figures received from analyzing the historical data. The presented figures will be described and analyzed in chapter 5. The connection between the analyzed figures and the frame of reference is made first in chapter 6, where furthermore my own reflections and ideas are presented. Also a description of how work is conducted today at Naval Systems Division is displayed in chapter 4. In chapter 7 the conclusions based on chapter 3 to chapter 6 are presented in relative compact form aiming to answer the main questions in the purpose. 9 Vestberg, Rasmus Chapter 1 - Introduction For people with wide knowledge about NSDS and EVM it is possible to skip chapter 3. Focus in the reading should then be at chapter 2.2.2 and chapter 4 to chapter 7. However I recommend reading the entire report for best understanding of conclusions made. 10 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden 11 Vestberg, Rasmus Chapter 2 - Method 2 Method This chapter will describe the different methods used for conducting this study. The chapter is divided into three parts. The first part will cover the theory behind the used methods followed up by an illustration of how they have been used. The last part will discuss the possible disadvantages with the chosen methods. 2.1 Theory This part will present a few theories behind some of the used methods. 2.1.1 Four Dimensional Studies A study can consist of many different methods. Common for all different methods is that they have to be either one or the other of all the following four dimensions. 3 Qualitative or Quantitative Research The research approach can be either qualitative or quantitative. The qualitative approach is focused on one or a few objects studied in detail. The quantitative approach concentrates on several objects which could be analyzed with mathematical methods. Primary or Secondary Information Information could be divided into two categories, primary and secondary information. The primary information is collected by one self while the secondary information is collected by someone else. The important difference is who makes the collection from the originally source. Observing something or interviewing the source is example of primary information while reading about something is example of secondary information. Case or Overall Study A case study focuses on one case only. The case could have very varying extension but is still limited to that specific case. An overall study aims to provide a picture of the common approach for all similar cases. 3 Lekvall and Wahlbin (2001) 12 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden Time Series or Fixed in Time Analyze A fixed in time analyze is based on the circumstances at one specific moment. The moment could be either today or some earlier point. A time series analyze extent over several time periods. The analyzing could be made currently or afterwards based on historical measurements. The important concern is to se, measure and analyze the changes over the chosen period. 2.1.2 Quality of the Research The quality of the research can be split into the reliability and the validity of the research. Reliability Reliability is the probability of obtaining the same results if the research was conducted in the same way once again. High reliability means that the result would be pretty much the same. In qualitative surveys it might be difficult to obtain the same results again since for example the interviewed persons might answer different from time to time. Quantitative research is more likely to be of high reliability because of the mathematical methods used.4 Validity The validity tells how well the research reflects the reality. A high level of validity indicates that the research reflects the reality in a good way. Inversely from reliability the validity is usually higher in qualitative research because of simplifications made in the quantitative research.5 2.1.3 Interviews Interviews can be made in several ways; for example personal interviews, telephone interviews, written questionnaire etcetera. In a personal interview there are some things to think about; the degree of standardization is one of them. A completely standardized interview consists of identical questions posed in the 4 Lekvall and Wahlbin (2001) 5 Lekvall and Wahlbin (2001) 13 Vestberg, Rasmus Chapter 2 - Method same order for all interviewed. The level of structuring is another thing to determine. Structuring means to what extent the questions have predefined replying options.6 It is also important to gain the trust from the interviewed person if the answers should be really truthful. Therefore the most sensitive questions should come in the end of the interview, when as much trust as possible has been gained.7 2.2 Used Methods This chapter will describe the used methods during this research. 2.2.1 Frame of Reference To gain basic knowledge about Earned Value Management existing literature has been studied. The basics behind Earned Value Management have been gathered from literature published by the Project Management Institute, PMI. Their ideas about Earned Value Management are directly connected to the American National Standard Institute/Electronic Industry Association (ANSI/EIA) standard concerning EVM. Also the ANSI/EIA standard has been used to further support the understanding of EVM basics. Several articles have been used to extend the picture provided by PMI. Different alternative theories about and complementing EVM has been studied in the search for the best suited method for the Naval Systems Division. The internal document “Projekthandbok” has been studied to get a basic knowledge about the routines at the Naval Systems Division. This document describes when, why and how a project should be managed at Naval Systems Division. It could have been possible to attain knowledge regarding Earned Value Management from people working at Naval Systems Division. However, this has been ignored to prevent any influence of the understanding and conclusions. 6 Patel and Davidsson (2003) 7 Cassel and Symon (2004) 14 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden 2.2.2 Empirical Study When the Naval Systems Division introduced Earned Value Management, in the beginning of 2006, they also started saving EVM reports. One report for each project each month is displaying the EVM figures at WBS-level. The reported figures are; Planned Value, Earned Value, Actual Cost, Schedule Variance and Cost Variance for both current period and cumulative to date. For the completion; the Budget, the Latest Revised Estimate and the Variance is displayed. Those reports have served as the platform for this study. To fully understand NSDS’s project organization several interviews have been made. 2.2.2.1 Interviews To make sure the understanding, provided from the “Projekthandbok”, of the project work at Naval Systems Division is the truly used and not just the hoped-for, personal interviews have been conducted. This has provided the research with primary information. The above mentioned “Projekthandbok” has not been updated since the introduction of Earned Value Management, why this supplementation was absolutely necessary. The interviews have been made with people at different positions to get the entire scope. All the interviews have been made with a very low degree of standardization and structuring. Basically the interviews consisted of a conversation where the interviewed was asked to describe their work, their contact with the project organization and their contact with Earned Value Management. If the interviews would have been made with high standardization and structuring I do not think I would have got the entire picture. The results would have been relying on my capability to ask the right questions. Since many of the interviews were held early in the process I did most likely not have had the understanding needed to ask the right questions, at that time. 2.2.2.2 Analyzing historical data To be able to tell how far in advance knowledge about the work is vast enough, to tell when we can convert planning packages into work packages, we can look at the forecast. The 15 Vestberg, Rasmus Chapter 2 - Method forecast is based on the knowledge about the work to be done, thus the same thing as when to convert planning packages. See 3.2.2.5. When the forecast is stabile within 10% of the Actual at Completion (the final outcome) the Naval Systems Division would feel satisfied with the knowledge of the work to be done.8 This means that if we can, based on the EVM reports, show any trend indicating when the forecasting stabilizes within 10% of its final outcome, this would give a scientific/statistical point for planning package conversion. 8 Michael Trochez 16 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden Figure 1 is an example of the method. Each line represents the forecasting relative the Actual at Completion for different work packages. The broken line highlights the 10% limit. As seen in the figure, the forecasting stabilizes below 10% somewhere between 5-7 months before its completion date (all work packages has their completion date at the end of the graph). This would mean that we could plan at work package level 6 months ahead (the median in the figure). 40% 20% 10% jun-0 7 maj07 7 apr-0 mar-0 7 7 feb-0 jan-0 7 d e c06 6 6 okt-0 nov0 6 sep-0 06 aug- 6 jul-0 jun-0 6 maj06 6 0% apr-0 Forecast relative Actual at Completion 30% -10% -20% -30% Date Figure 1 Example of hoped-for data. The work packages to be studied had to be finished. This is the only way to know the precise outcome of the work package. To determine which work packages that really where finished I have studied the project Cost Performance Reports. Finished work packages have an Earned Value equaling the Planned Value, regardless of the performance of that specific work package. When the work packages to be measured were selected the graphs were built through the following formula: 17 Vestberg, Rasmus Forecasting Accuracy = Chapter 2 - Method Estimated Cost at Completiontime of measurement − Actual Cost at completion Actual Cost at completion Formula 1 It is obvious that as the work package are approaching completions there will be less work left to forecast. Therefore the estimate will always approach the actual when the work package reaches completion. If we use Formula 1 with following figures; Actual Cost Cumulative = 900, Actual Cost at Completion = 1000 and Estimated Cost at Completion = 1100. Then the Forecasting Accuracy will be 10% from perfect. Since there is only 100 hours left of work but estimated 200 hours, it is obvious that the estimate is pretty bad although the figure looks okay. That also makes it interesting to look at the ability to forecast the work packages relative the amount of remaining work. Forecasting Accuracy relative remaining work = = Actual Cost at completion − Estimated Cost at Completiontime of measurement Actual Cost time of measurement − Actual Cost at completion Formula 2 Using Formula 2 the simple example above will be 100% wrong instead of 10%. This second method will be difficult to use when the baseline has been changed, why the periods in the study with this problem have been left out. Also the case when the final cost has been achieved is left out, since the formula will give division with zero and the work package is finished anyway. It could have been possible to determine the time frame of planning package conversion by interviewing people responsible for the plans. This would however only represent the wished for time frame without any scientific support. 18 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden 2.3 Method Criticism This section will highlight some things to have in mind when looking at the research. Some of them might have affected the results of the study. 2.3.1.1 Literature There is always a good thing to establish the facts from several independent sources. This could perhaps have been done more thoroughly by using even more different sources. However, it is not likely that result from the literature study would have been different even if more sources would have been used. The sources used are the fundamental source for the subject in mind. And the publisher is in some way one of the owner of the method available in Earned Value Management. The literature study about EVM could be said to be of both high reliability and validity. The internal “Projekthandbok” is not updated for a couple of years which could affect the understanding of the situation at the Naval Systems Division. The main concept of this study is anyway focused on EVM which is not included in the “Projekthandbok”. Therefore the interviews have been the main source of this information and confusion based on non updated documents would be no issue. Based on this the validity could be questioned but should anyway not affect the study in general. 2.3.1.2 Interviews It is always a risk of missing vital information while conducting an interview alone. One might for example miss important body language while taking notes. Since the interviews were made with very low level of standardization and structuring the reliability is low and there is a great risk that one might get different answers doing a new interview. However the validity is high since the interviews were made to build the entire picture of the situation at Naval Systems Division. Several people have contributed to the understanding of NSDS’s project management why the gathered picture would be very valid. 19 Vestberg, Rasmus Chapter 2 - Method 2.3.1.3 Analyzing historical data The analyzed data origins from one type of report being available since the beginning of 2006. Only a couple of the projects at Naval Systems Division have been reported with this method. Among those projects there is only one that have reached so far that some work packages have been completed. This is an obvious problem. The analyzed data is of far too small quantity to be statistical. Old finished project have been studied to see if they could contribute to the gathering of data but without success. Very little information is stored regarding old projects. When there is information stored about old projects it is not the wanted, or the information is at a too high level telling us nothing about the work packages. Although the findings can not be called statistical they should work as a warning signal indicating a very obvious trend. 20 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden 21 Vestberg, Rasmus Chapter 3 – Frame of Reference 3 Frame of Reference This chapter will treat the Frame of Reference subjective to the purpose of the thesis 3.1 Traditional project management In traditional project management the most important measurements are today’s date and the actual amount of money spent on the project. The amount of money spent is compared to the budgeted cost for the reached date to measure the performance of the project. The actual performance is never measured.9 Thinking about it, the data displayed in Figure 2 does not say anything about the projects performance. To determine the true performance of the project one would have to look at the schedule result in the same format as the cost. Often the financial people breaks out the cost by function while scheduling people develop their displays from tasks in the Work Breakdown Structure (WBS). Although many companies use this approach these two does not match.10 1600 Budget 1400 1200 Cost 1000$ 1000 800 600 400 200 0 jan feb mar apr maj jun jul Date Figure 2 Traditional Project Management Performance 9 ANSI/EIA-748-A-1998 10 Fleming and Koppelman (2005) 22 aug sep okt nov dec Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden 3.2 Earned Value Management Earned Value Management is a method used for handling of medium and large scaled projects. The details about EVM and the differences between EVM and traditional project management systems will be displayed in this section. 3.2.1 History of EVM The Earned Value concept is not in anyway new, in fact the basics and the ideas have been used for more than a century. In the late nineteenth century the industrial workers in the American factories started using the concept of earned value. The workers measured their earned work and actual expenses which they compared to the planned standards. These measurements were their way to control the work in the factories. Since they also had defined the cost variance, consisting of the actual money spent relative to the work achieved, they used the core of earned value although they did not address it that way. One could say that this basic definition of cost variance is what characterizes earned value.11 In the end of the 1950’s the United States Navy introduced the Program Evaluation Review Technique (PERT) as a network scheduling and risk management device. In 1962 PERT was extended to PERT/costs aiming to add resources to the time scheduler. Since the computers back then was not powerful enough PERT did not live on for many years. However PERT left something to the afterworld. The implementation of PERT/costs had required some new reporting formats from the contractors. One of those formats contained “value of work performed” versus “actual cost”. By the second half of the 1960’s the United States Air Force made a new effort to oversee the industry performance. Instead of imposing a specific management control system they wanted the industry to satisfy some criteria with their existing management control systems. The result was an earned value concept called Cost/Schedule Control Systems Criteria (C/SCSC) which comprise 35 criteria that one had to adapt while being a contractor for the Department of Defense (DoD). 11 Fleming and Koppelman (2005) 23 Vestberg, Rasmus Chapter 3 – Frame of Reference During the next three decades the C/SCSC evolved to be more and more difficult to use. The basic criteria were added with implementation guidelines, surveillance manuals and implementation checklist which were intended to be used as guidelines used with good judgment. However the guidelines were not always used as guidelines but instead as peremptory rules. Furthermore the private sector never adapted the C/SCSC. One of the main reasons why the industry never adopted the C/SCSC, except the rigid guidelines, was the new vocabulary. Instead of calling things what they are C/SCSC used their own expressions and abbreviations. For example earned value was called “Budgeted Cost of Work Performed”, BCWP, or simply “p”. Overrun was called OTB which stood for “Over Target Baseline”. Some of those expressions are still used today by some people, although there are simpler expressions meaning the same thing. In 1995 the National Defense Industrial Association, NDIA, accepted the task of rewriting DoD’s formal earned value criteria. The objective of the rewriting was to make the criteria more practicable for the private industry. The 35 criteria became 32 and terms as Budgeted Cost Work Performed (BCWP) and Budgeted Cost Work Scheduled (BCWS) where changed to Earned Value and Planned Value. But the main change was in the attitude of all parties. The private company was now adopting the technique since it had proven to be best-practice instead of something that where forced from the government to their contractors. The restriction of EVM to DoD was removed and in 1998 the new technique became accepted as an ANSI/EIA document. 12 3.2.2 This is EVM The main concept of Earned Value Management is to add the amount of work actually performed when measuring the project. The work actual performed provide the managers with more accurate information on the status of the project which leads to better forecasting and corrective actions.13 If a project e.g. is overspending, the traditional project management measures will indicate that the project is performing badly. If the actual cost is higher than budget the project might be overspending but there is now way to tell unless you measure 12 Fleming and Koppelman (2005) 13 Christensen David S (1998) 24 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden what has actually been performed. If the actual work is in the same magnitude as the actual cost, the project is ahead of schedule and not really overspending. In the same way a project that is spending less money than budget might not be as successful as it seems. If the actual work performed also is less than planned the project is in fact behind schedule and not only cost effective as traditional project measurement would say. Let us look at an easy example to make things even clearer. We have a project extent over ten months (see Figure 3) with a total budget of $1,000,000. Each month has a budget of $100,000 and distinct milestones for each budgeted $100,000. Once a milestone is accomplished the project will earn $100,000. The budget is labeled the “Planned Value” which consists of two elements, the work scheduled and the budget for that work. 1200 Planned Value 1000 1000$ 800 600 400 Actual Cost Earned Value 200 0 jan feb mar apr maj jun jul aug sep okt nov Date Figure 3 Earned Value Example After four months the project has spent the planned $400,000 and would by traditional project management be performing well. The Actual Cost is therefore $400,000. When also looking at the work performed, as in EVM, you notice that only three of the four milestones have been achieved and the Earned Value is only $300,000. One could immediately see that the project 25 Vestberg, Rasmus Chapter 3 – Frame of Reference is running behind and have a negative Schedule Variance at $100,000 (Schedule Variance = Earned Value – Planned Value, see Figure 4). Also shown in Figure 3 is the Actual Cost, $400,000. The Actual Cost is greater than the Earned Value which tells us that the project is not cost effective. The Cost Variance is defined as the Earned Value – Actual Cost (see Figure 4). Earned Value is recommended to help managing company’s different projects and act as a comparison between a company’s different projects. (Also other company’s projects using Earned Value can be compared)14 Although some of the basics and theories behind Earned Value can be used for continues business it is not recommended to use the entire Earned Value Management method for that purpose.15 Voices have been raised against the Earned Value method, saying it is one of the larger cost drivers in a project.16 So why should one use Earned Value? There are several benefits with employing Earned Value and among others it can be said that; it provides reliable data. It provides early warning signals. It makes reliable predictions possible etcetera.17 Also there is a general phobia about Earned Value complexity which undermines the acceptance.18 The core basics of Earned Value is the measurement of actual work performed compared to a baseline plan.19 Perhaps the most advantageous thing about Earned Value is the, through measurement of performance, provided possibility of reliable prediction of the project. Some people would say that this measurement requires too much effort compared to the advantageous with the system.20 Those people are most likely just prejudice based on old times complexity in Earned Value. Those doubters tell us that there are reasons to keep 14 Averstad, Dan (2003) 15 Fleming and Koppelman (2005) 16 Fleming and Koppelman (2005) 17 Christensen David S (1998) 18 Kondur, Mohan (2007) 19 Christensen David S (1999) 20 Fleming and Koppelman (2005) 26 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden Earned Value as simple as possible.21 To keep Earned Value simple should not be a problem. The concept of Earned Value is often used as a daily routine. For example, when shopping grocery many people look at the price per kilo. Concerns about what you get for the money could in some extent be equal to Earned Value. Shopping based only at the total cost is more similar to the traditional project management. The concept of Earned Value requires a performance plan, the Planned Value, which combined with the physical Earned Value and the Actual Cost provides the cost performance. 3.2.2.1 SPI and CPI The three-dimensional way of looking at the project gives us further possibilities to evaluate the project. We have earlier spoken about the Cost Variance and the Schedule Variance (see Figure 4). Those two measurements could be used in a slightly different way. We call them Schedule Performance Index, SPI, and Cost Performance Index, CPI. The Schedule Performance Index is calculated as the Earned Value divided with the Planned Value. The Cost Performance Index is calculated as the Earned Value divided with the Actual Cost. If looking at a similar example as the one above (PV and EV is the same but AC is $500,000 instead of $400,000) that gives us an SPI of 0.75 (EV $300,000 / PV $400,000 = SPI 0.75) and a CPI of 0.6 (EV $300,000 / AC $500,000 = CPI 0.6). 21 Kondur, Mohan (2007) 27 Vestberg, Rasmus Chapter 3 – Frame of Reference 1200 Planned Value 1000 1000$ 800 600 Actual Cost Cost Variance 400 Schedule Variance Earned Value 200 0 jan feb mar apr maj jun jul aug sep okt nov Date Figure 4 Earned Value Basics The SPI and CPI can then be used to predict the rest of the project. With an SPI of only 0.75 you could say that for every dollar of physical work this project had planned to achieve only $0.75 was accomplished. With an original budget of $1,000,000 this project will take $1,333,333 to finish. That is more than three months of extra work. Note that the schedule is measured in money but can be directly transformed to man hours or time in Gant-chart. This is at first sight at bit confusing but will after a while feel perfectly naturally. The CPI in our example is 0.6 which in the same way as the SPI can tell us something about the future of the project. For every dollar spent we have only got a value of $0.6 which gives us the final cost of $1,666.666 for the project. CV = AC − EV , SV = PV − EV , CPI = EV , AC SPI = EV PV Formula 3 a-d With these figures you can make the correct decisions about the project. It is not likely that the estimated total cost of the project is possible to improve, unless you change the scope. However the duration of the project can perhaps be improved by adding extra funds. Research 28 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden from hundreds of projects within the DOD, shows that the performance of a project at 20% of completion is very accurate for the entire project. Very seldom a projects performance improves after the 20% completion. If the performance changes it often gets worse and not better.22 Therefore management no longer must wait until the total funds have been spent to determine that additional budget is needed. 3.2.2.2 Baseline - Scope the Project The baseline or the Planned Value is the guiding value for the project. Therefore it is very important to carefully develop the baseline. Actually you can not use the Earned Value technique if there is not any Planned Value. Knowing what is included and, perhaps more important, what is not included is essential for managing of the project.23 The generated Performance Measurement Baseline (PMB) is the total time-phased budget for the project. It is important to update this baseline when the scope of the project is changed. Otherwise the measurement will take place against an invalid reference.24 A useful tool for scooping the project is the Work Breakdown Structure (WBS). A WBS can be developed in different kind of ways and take different shapes; the important thing is that it helps grasping the scope.25 The type of WBS discussed further will be the one described in PMBOK.26 A WBS looks like an organizational chart but it is important to realize that it is not. However the WBS is for the project leader what the organizational chart is for the company executive.27 The WBS represents the project work to be done and the deliverables of the project. The WBS is separated into different products or work in several levels. Either one chose to do a 22 Fleming and Koppelman (2005) 23 A Guide to the Project Management Body of Knowledge (2005) 24 ANSI/EIA-748-A-1998 25 Wenell, Torbjörn (2004) 26 A Guide to the Project Management Body of Knowledge (2005) 27 Fleming and Koppelman (2005) 29 Vestberg, Rasmus Chapter 3 – Frame of Reference product or a work oriented WBS (se Figure 5 and Figure 6).28 A success factor is to let the WBS reflect the way the manager actually plans to manage the project.29 Figure 5 Work oriented WBS Figure 6 Product oriented WBS At the top levels the product or work is described very briefly, called planning packages. It is not uncommon that the owner of the project specifies the three top levels of the WBS. The lower levels are extended by the project leader to contain work, costs and schedule, the work packages. It is first at work package level that one can accurately estimate cost and schedule and it is also at this level the Earned Value is computed.30 In very large projects it can be hard 28 Wenell, Torbjörn (2004) 29 Fleming and Koppelman (2005) 30 ANSI/EIA-748-A-1998 30 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden to plan everything on work package level from the beginning. The manager then has to do a rolling planning bye and bye.31 It is also common that the WBS is reassessed from time to time when the knowledge gets wider or when requirements changes.32 Each company must determine its own standard for the conversion of planning package into work packages.33 Different deliverables need different levels of breakdown to clearly define the work. More detailed breakdown gives better opportunities to control and manage the work. In the same time too detailed breakdown will inhibit the productivity and lead to ineffective work. It is of most importance for the project manager to keep the breakdown at a balanced level. 34 For the breakdown of the WBS-element it takes that different subprojects and deliverables is split into its basic elements. Each element must be clearly defined and assigned to a specific unit taking the responsibility for the task. When work has been defined it is possible to assign the tasks to personnel through an Organization Breakdown Structure, OBS. The lowest level of the WBS is expanded with more details into a WBS-dictionary. This dictionary is the Statement of Work (SOW) for the project. Of course there are other techniques used than the WBS to scope the work. The important thing is naturally not which technique one chooses to use, but the result when grasping the project. Since WBS is the superior most used technique and also the one used at Naval System Division there is no reason to study other techniques further. 3.2.2.3 Scheduling Independent of which management techniques are being used all projects has to schedule the work, so also the ones applying Earned Value. Perhaps the ones using Earned Value especially needs it.35 Larger projects may have multiple schedules correlated to each other 31 A Guide to the Project Management Body of Knowledge (2005) 32 ANSI/EIA-748-A-1998 33 ANSI/EIA-748-A-1998 34 A Guide to the Project Management Body of Knowledge (2005) 35 Kondur Mohan (2007) 31 Vestberg, Rasmus Chapter 3 – Frame of Reference with a formal scheduling system. But also the smallest project needs at least a project master schedule, PMS, containing the most important tasks to be performed.36 To implement Earned Value Management there are two basic needs. First, as earlier discussed, one must define the project and all the work which has to be done. Second, the work has to be put into a time frame so that performance can be measured against it.37 The time based schedule together with the WBS is evidently the spinal column of the projects baseline. The Earned Value Project Management implies that there is no other way to establish a time schedule except the Critical Path Method (CPM).38 The Critical Path Method is a technique used for analyzing web plans. There are some different kinds of web planning methods although they are all very similar. The concept of them all is to display the tasks in the project in a web, showing the connections between the different tasks.39 The CPM and the dependencies between the tasks are then used to show the shortest possible duration of the project. The difference between cost variance and schedule variance takes some extra attention except what has been told earlier. A negative cost variance is always a serious matter telling us that the project is not performing as planned. A negative schedule variance on the other hand does not have to be a big issue. The schedule variance only tells us how much of the planned work we have accomplished. That could of course be a big problem if we for example have a tight schedule and an important deadline to keep. But it could also be the result of a late start, either on some of the work packages or on the entire project. If the negative schedule variance is a consequence of some single work packages starting late, and those not being on the critical path, the variance in fact could be insignificant.40 36 Fleming and Koppelman (2005) 37 Fleming and Koppelman (2005) 38 Fleming and Koppelman (2005) 39 Project Management Body of Knowledge (2005) 40 Fleming and Koppelman (2005) 32 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden Most of the time schedule variance can also be compensated. In the best case it is enough to reorganize the schedule to get back on track. Otherwise one can ad extra money to speed up the work. A negative cost variance is seldom to compensate for. The basic reason for this difference in cost and schedule variance is that the scope is almost never dependent on what date the work is being done. 3.2.2.4 Performance Measurement Techniques The Earned Value is based on measuring the performance of the project. To measure the performance a couple of different techniques have been developed. Below we will take a careful look at the pros and cons with following techniques. • Weighted Milestones • Fixed Formula • Percent Complete Estimates • Percent Complete and Milestones • Equivalent Completed Units • Apportioned Relationship • Level of Effort Different techniques might suite different projects. The choosing of technique, to make it fit the projects various work packages, is up to the project leader. One does not have to use the same technique over the entire project. The important thing is to decide at planning stage which technique to use and be consistent to that.41 3.2.2.4.1 Weighted Milestones Weighted milestones are as it sounds a method where different milestones in the project are assigned a value. When the milestone has been achieved the project earns the value of that milestone. The milestones can be set to be the entire work packages if they are small, otherwise one would like to have several milestones in each work package. If the work 41 Fleming and Koppelman (2005) 33 Vestberg, Rasmus Chapter 3 – Frame of Reference packages are divided into several different milestones one must distribute the planned value of that work package among the milestones. This could be done in a simple method where you divide the planned value equal over all milestones. Since a milestone is unique and measurable, for example a specific task being finished, the equal division might not fit. It is therefore ok to divide the planned value uneven between the milestones. The important thing is that the assigned value for each milestone reflects the actual planned work for achieving that specific milestone.42 This method is preferred when looking at the performance measurement.43 However it is the most difficult method when initially planning the project. It takes close cooperation between scheduling people, resource-estimating functions and work packages managers to get the milestones meaningful and correctly weighted. 3.2.2.4.2 Fixed Formula The idea of this method is that one earns a certain value when the work package starts and the rest when it finishes. The most commonly used values are 25/75, 50/50 and 75/25 meaning that the percent of the planned value is earned when starting and completing a task respectively. There is nothing to keep you from choosing different relations as long as they ad up to 100%. Worth noting is, that if one uses the same values on all work packages and they are equivalent in size and ff most of the work packages then are closely scheduled afterwards, this method will work as if you always earn all the planned value when completing a work package, only with a slight displacement. Simply because you earn the start and end value at the same time, although not from the same work package. This method will act well, as long as the work packages are short in duration. If the work packages span over several report periods, this method will give a lag in the Earned Value. On the positive side it is one of the simplest methods both to plan and measure. A suited application for this method is purchased materials, earning 25% of the value when order has been done and 75% when the material has been delivered. 42 ANSI/EIA-748-A-1998 43 Fleming and Koppelman (2005) 34 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden 3.2.2.4.3 Percent Complete Estimates The Percent Complete method is a subjective judgment of the completed work. The person in charge of the work packages simply estimate the percent of work completed against the full planned value of that work package. Sometimes the estimation can be limited with a “ceiling”. The ceiling means that the person making the subjective estimate only is authorized to award up to for example 80%. The rest of the value is earned when the work package is 100% completed.44 This method is the easiest of them all to administer which is probably why it have received increasingly wide acceptance in the private industry.45 But it also has obvious disadvantages. If one would like to play games with the Earned Value this method is the most vulnerable. The person in charge of each work package is obviously able to put a gloss on the completed work. Especially when the pressure is high from the senior managers, the estimates tend to be a little bit on the large side. To minimize this phenomenon some companies have developed procedures to incorporate some objectivity into the subjective estimate. Another disadvantage is that it can sometimes be difficult to actually know how much work has been accomplished. Of course the situation could be the other way around. The responsible manager underestimates the performance since they know their reputation might be at stake. It is always easier to defend modesty than exaggerations. Also, underestimating the progress will give a buffer for the next report period. 3.2.2.4.4 Percent Complete and Milestones Combining two techniques, Percent Complete Estimates and Weighted Milestones, provide yet another way to measure the performance. The value is earned based on the subjective estimates of the person in charge of the work package. Added to this there is one or several milestones, or perhaps they should be looked at as toll gates. The manager can only award up to the predefined value of the next milestone. Only when the milestone has been achieved the project can earn more value. 44 ANSI/EIA-748-A-1998 45 Fleming and Koppelman (2005) 35 Vestberg, Rasmus Chapter 3 – Frame of Reference This method is said to be the best out of two methods, the ease of Percent Complete and the assured Milestones.46 This seems to work well in any industry and any type of project. Especially it is a suited method for project with large work packages. 3.2.2.4.5 Equivalent Completed Units This method can be used when the project consists of several similar units to be delivered. The value is earned for a full unit and can be rewarded when either a full unit is completed or when fractions adding up to a full unit is completed. For example if you have ten similar work packages and you have finished 10% of each of them. Then the sum of the work earned is equivalent to a full work package which is earned. This method is often used in construction industry to make progress payment. 3.2.2.4.6 Apportioned Relationship Using this method on a task means that the value is earned directly related to another work packages earned value. The other work package is called the measurement base. The measurement technique of the measurement base could be any of the ones mentioned above.47 This technique could be used when two tasks are closely related to each other. For example if a work package (the measurement base) consists of code design, then the continuous code testing could be a separate work package measured with Apportioned Relationship. This means that the code testing has a separate budget but is rewarded with Earned Value related to code design. Of course the Earned Value is related in percent. So if the code design has earned 35% of its Planned Value the code testing has also earned 35%, but of its own Planned Value. If the apportioned task takes place somewhat after the measurement base, for example the code testing is done after the code design, then it is ok to let the apportioned task trail the base task with one reporting period. The schedule position for the apportioned task and the base task will always be the same (except for the possible trail). This is natural since any positive or negative schedule variance 46 Fleming and Koppelman (2005) 47 ANSI/EIA-748-A-1998 36 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden will be similar in the apportioned task. However, the cost variance is individual for the related tasks, since the cost is incurred for the apportioned task itself. 3.2.2.4.7 Level of Effort Level of Effort (LOE) is used to measure those tasks that are necessary for the project but do not have any deliverables or performance easy to measure. Examples could be project management, support functions, security guards etcetera. The value is always earned automatically according to the Planned Value in Level of Effort measuring.48 Using Level of Effort means that there could be no Schedule Variance, ever. But, since the cost is still measured the same way as in all measurement techniques, the Cost Variance could be very big. This is not good at all and it is doubtful that this even qualifies as Earned Value.49 In every project using Level of Effort on some work package, one should quantify the value of Level of Effort. The quantification is made by dividing the value of Level of Effort with the value of the total baseline. If the value of Level of Effort tasks exceeds 5-10% the project is measuring the passage of time instead of true performance.50 A way of dealing with this is to “quarantine” the Level of Effort tasks. That simply means you remove all task measured with Level of Effort from the baseline and place them in a separate budget. Those tasks should not be bothered to measure, since they reflect nothing but the passage of time. 51 One could also replace the Level of Effort with subjective Percent Complete measurements. The Percent Complete method has its disadvantages as well, but it is still preferable to Level of Effort52 48 ANSI/EIA-748-A-1998 49 Fleming and Koppelman (2005) 50 Fleming and Koppelman (2005) 51 Fleming and Koppelman (2005) 52 Fleming and Koppelman (2005) 37 Vestberg, Rasmus Chapter 3 – Frame of Reference 3.2.2.5 Forecasting The Earned Value Management is a very helpful tool when predicting the outcome of the project. To make accurate predictions, it is very important that the plan is of good quality. If the plan is not credible the same thing will be evident for the predictions. Therefore the managers really have to develop a plan that they do believe is possible to keep up with. If the measurement of a project in progress shows a cost overrun or a schedule variance the manager has to take aggressive actions. Unfortunately managers often do not like or accept the final forecast results and choose not to take necessary action. If the managers did believe in the plan they created, they should also believe in the predictions given to them concerning their plan and statistic figures. In traditional project management an Estimate at Completion (EAC) is calculated as the sum of Cumulated Actual Cost and a new Estimate to Complete (ETC). The new ETC is prepared by the project manager based on the experience from the project in progress. This gives a quite accurate image of the projects future and is probably the most reliable forecasting method. However, there is one disadvantage with this approach. The work to develop a new ETC takes time and is most likely not in the scope of the project. That is why the use of Earned Value Managements easy forecasting is so favorable.53 When using any of the three formulas below, one uses the EV, AC and BAC at the same level as the forecast is made at. For example, if one would like to forecast the entire project, the EV, AC and BAC for the entire project are used. 3.2.2.5.1 Mathematical EAC – Best Case Scenario This forecasting formula is very simple and easy to understand. The EAC is calculated as the Actual Cost, plus the Budget at Completion, less the Earned Value. That simply means the Actual Cost today, plus the rest of the budgeted work. Estimate at Completion = Actual Cost + ( Budget at Completion − Earned Value) Formula 4 53 Fleming and Koppelman (2005) 38 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden This formula can be looked upon as a best case scenario. The project has incurred an overrun which not likely will go away. Assuming that the rest of the project will follow the plan, this gives the accurate estimate. Almost never the project will underrun in the future and compensate the early overrun.54 3.2.2.5.2 Cumulative Cost Performance Index – Most Likely This Formula is based on the experience of the project given by the CPI (se 3.2.2.1). When calculating the EAC one assumes that the remaining work will be done with the same efficiency as the performed work. Estimate at Completion = Actual Cost + Budget at Completion − Earned Value Cost Performance Index Formula 5 To smoothen out the varieties of the project performance the used CPI is the cumulative to date. This will not give the project team a perfect picture of their recent work, but it will provide an accurate long-term forecasting. The Formula 5 can be simplified as follows. Estimate at Completion = Budget at Completion Cost Performance Index Formula 6 This method is often referred to as the “most likely” outcome of the project.55 Studies of several projects show that the CPI at 20% completion will be stable for the rest of the project.56 3.2.2.5.3 Cumulative CPI times SPI – Worst Case Scenario As the heading implies this method uses both the CPI and the SPI. 54 Fleming and Koppelman (2005) 55 Fleming and Koppelman (2005) 56 Christensen and Heise (1993) 39 Vestberg, Rasmus Estimate at Completion = Actual Cost + Chapter 3 – Frame of Reference Budget at Completion − Earned Value Cost Performance Index * Schedule Performance Index Formula 7 Since it is very common that project team strive to be on track with the schedule, this formula is appropriate. If a project is behind schedule, it will take extra effort and probably also money to get it on track again. By multiplying the CPI and SPI one gets a good performance factor. If both the SPI and CPI is less than one (1), the outcome will be worse than in ordinary cumulative CPI forecasting. This is perfectly natural, since it will take extra funds to compensate the schedule slippage. On the other hand, if one of CPI or SPI is above one (1), the performance factor indicates that the better of the two compensates the worse. This calculation method is often referred to as the worst case scenario. Although, there are some people claiming this to be the most likely outcome of the project.57 3.2.2.5.4 Predicting completion date Formula 4 and Formula 6 can also be used to predict the final completion dates of the project. Instead of using CPI one uses SPI to get the forecast in aspect of schedule. There is no statistic data provided showing this to be a valid forecasting method. Actually some would say this is a to simplified way of predicting the completion date and that it takes careful Critical Path work to do this properly. The SPI only indicates the status of the project based on time and is not sufficient to forecast the completion date itself. Analyzing the Critical Path combined with SPI calculation is the recommended method.58 3.3 Earned Scheduling As earlier written, the schedule performance is measured in money. That might be a little bit difficult to grasp in the beginning, but will eventually make perfectly sense. This is easy to 57 Fleming and Koppelman (2005) 58 Fleming and Koppelman (2005) 40 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden measure and it correlates well with the cost performance which naturally also is measured in money. However, this way of measuring the schedule performance has disadvantages. Since the Schedule Variance and the Schedule Performance Index is calculated based on the planned value, some false results will occur. When the project is supposed to be finished the Planned Value will not change any more.59 This means that no matter how late the project actually finishes, the Schedule Variance will approach zero and the Schedule Performance Index approaches one. This is simply because the Earned Value always equals the Planned Value at completion of a project; otherwise the project would not be completed.60 Because of this flaw, Earned Value Management is sometime labeled as a cost management system.61 The remedy for this is to use Earned Scheduling. This is the same thing as Earned Value but the Schedule Performance is measured in time instead of in money. The Earned Schedule, ES, is reflecting the time at when the achieved work should have been done according to plan. The Actual Time, AT, is the time of today. The planning of the project is exactly the same as with Earned Value and one prepares a baseline to measure against. The only difference is that one calculates the Schedule Variance as the horizontal difference against the baseline, instead of a vertical difference against the baseline (see Figure 7). That is, the vertical axis represents money while the horizontal axis represents schedule time. That will give us the following formula for calculating SV(t) and SPI(t).62 Schedule Variance(t ) = ES − AT Schedule Performance Index(t ) = ES AT Formula 8 a and b The classic Schedule Variance, SV($), shows the difference between the amount of achieved work and planned work. The SV(t) shows the difference in calendar time between today’s 59 Corovic Radenko (2007) 60 Lipke Walt (2003) 61 Lipke Walt (2006) 62 Lipke Walt (2003) 41 Vestberg, Rasmus Chapter 3 – Frame of Reference date and the date when one should have accomplished the amount of work being finished of today (se Figure 7).63 1600 Budget 1400 1200 SV($) SV(t) Cost 1000$ 1000 800 600 400 200 0 jan feb mar apr maj jun jul aug sep okt nov dec Date Figure 7 SV(t) and SV($) Even if analyzing the Critical Path is probably the best way of forecasting the completion date, this extension to Earned Schedule provides a tool suited also for time prediction. The benefit with Earned Schedule against analyzing the Critical Path is the simplicity. In large projects the network schedule is often of very high complexity, therefore a simple analyzing tool as Earned Schedule suits well.64 Studies have been made, although not as extensive as DoD’s EVM-study, showing that this new approach correlates well with the Earned Value basics. Not only do they work together with EVM’s cost analyze, they also behave correctly over the entire project.65 This makes it 63 Abba Wayne (2002) 64 Henderson Kym (2005) 65 Henderson Kym (2003) 42 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden possible to forecast the outcome of the project, as well on schedule basis, without analyzing the critical path.66 If one agrees that Earned Schedule provides the true picture of the Schedule Performance, we can use it to see how incorrect the SV($) can be. All practitioners agree in that SV($) give erroneous figures after the completion date. But, one can show that SV($) is unreliable over the entire project when compared to SV(t). This is in the case when the project has a non linear baseline (see Figure 8). 1600 Budget 1400 Earned Value 1200 1000$ 1000 SV($)2 800 600 SVt)2 400 200 SV($)1 SV(t)1 0 1 2 3 4 5 6 7 8 9 10 11 12 Date Figure 8 Erroneous behaviour in a non linear baseline If looking at a project with perfect performance, only starting one month late, the problem becomes obvious. The SV(t) is constant over the entire project (SV(t)1 = SV(t)2), while the SV($) changes radically (SV($)1 ≠ SV($)2). A project with perfect performance would have the same Schedule Variance through the entire project. If the baseline is perfectly linear, the two different measurement techniques will provide the same data.67 66 Henderson Kym (2004) 67 Corovic Radenko (2007) 43 Vestberg, Rasmus Chapter 3 – Frame of Reference 3.4 Gold Practice The Data & Analysis Center for Software, DACS, is a Department of Defense in USA. DACS is collecting data from different software development projects to compile the “best practice” which they have chosen to call Gold Practice. Gold Practice instead of Best Practice is simply because there can not be only one right way for every company. The intent of DACS Gold Practice Community is to share experience with each other. The following part will present the recommendations made in Gold Practice website regarding Earned Value Management.68 This section has been added based on a wish from the Manager at Naval Operations Project Office. Defining the work and developing a Work Breakdown Structure, WBS, is essential for the successful use of EVM according to DACS. Each work package in the WBS must have a short duration or be divided into measurable milestones. Further more it is important to keep the WBS on the right level. To detail planning will create an overload of data which is hard to track while lack of details may mask important information. The Gold Practice suggests 3-4 levels in the WBS for regular projects and up to 6 levels for very large and complex projects. The Earned Value is suggested to be calculated as either 0% or 100% where 100% is given when the task is completed and validated. The Gold Practice also suggests that one should establish specific exit criteria for each task to make the measurement easier. Doing subjective assessment to gain the earned value is strongly not recommended. Later in the project when the work breakdown is done, the baseline is set according to that specific planning package. Then you can not change the baseline and as a consequence not either the budget of that working package. That means that the breakdown and detail planning comprise splitting the budget on different work packages. 68 www.goldpractices.com 44 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden 45 Vestberg, Rasmus Chapter 4 – Empirical Study 4 Empirical Study This chapter will present the results from the analyzed work packages and the mapping of how project work is conducted at NSDS. The figures used to compute the data is shown in Appendix 1. All results are presented in graphs to increase the visibility. 4.1 EVM at Naval Systems Division Earned Value Management was adopted in the beginning of 2006. This part will describe the situation at Naval Systems Division regarding the project organization and the Earned Value Management. 4.1.1 Project Organization All development at Naval Systems Division is made in project organization, although the project organization is not really the traditional one. In traditional terms a project is supposed to have a limited extension in time, a fixed budget and temporary staff.69 At Naval Systems Division all project are limited in time even if some of them is extended to up to ten years. The budget, as well, is often very large but still fixed. So at those issues there is nothing odd about the project organization, although the projects are extraordinary large. The big difference in the Naval Systems Divisions project management is in the organization. The projects consist of only one or two persons, the project manager and sometimes a system engineering manager. The rest of the resources in the projects are bought from the functional organization. This would not have been strange if it was the staff that was bought but in this case it is the component that is bought. That means that the project manager has no responsibility over the handling of the staff. Instead the project manager goes to a Program Project Leader, PPL, who has a functional responsibility over one component. They make an agreement over what is supposed to be delivered and at what time and cost.70 After that it is up to the PPL to plan and produce the agreed component. That means that it is the PPL that updates the plan according to the progress. If the work with one component is delayed or 69 Project Management Body of Knowledge (2005) 70 Henrik Olsson 46 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden more expensive than agreed there is not much the project leader can do. This type of project model is called procurement model.71 The Naval Systems Division has been running projects in a more standardized way earlier but a couple of benefits with today’s organization led to the changes. First of all, many of the projects at Naval Systems Division develop or use the same technology or product. Roughly you could say that the Naval Systems Division has a couple of systems that are developed or tailor-made for special applications and customers. Therefore there are very much of the work that is similar or perhaps exactly the same in different projects. The Naval Systems Division uses something they have chosen to call “the Family”, which is a collection of existing solutions for different problems. If someone improves something they got from “the Family” this improvement will be saved to provide others with the latest solution. Hence the existing organization makes double work less common.72 This type of organization also makes it easier to develop or use new technology since it is more flagrant where and by whom the technology should be adapted. By the same reason it is easier to merge organizations since the functions and responsibilities are more obvious.73 Much of the reasons can probably be referred to the size of the projects. The benefits with the more traditional project organization were not very appreciable since the size made the project leader loose control anyway. A fact is that the Naval Systems Division has increased its result considerably with the new organization.74 Since the beginning of this study NSDS has made some changes in the project organizations. These are not dealt with since they do not affect the purpose of the study and the analyzed data derives from the described organization.75 71 Projekthandbok, SAAB Systems 72 Henrik Olsson 73 Person A 74 Person A 75 Trochez Michael 47 Vestberg, Rasmus Chapter 4 – Empirical Study 4.1.2 Earned Value In the early 2006 the Naval Systems Division started using Earned Value as a measurement tool for project management. Earlier most of the project was managed without knowing the exact status of today.76 But the Earned Value concept should not be considered as news for the Naval Systems Division. The thoughts behind Earned Value have been present since the beginning of the eighties. 77 At that time the concept was called Performance Measurement System, PMS, which still can be found referenced in some steering documents at the Naval Systems Division. In the “Projekthandbok” (project guidelines) at SAAB Systems it is stated that PMS is a tool recommended to use.78 (The “Projekthandbok” has not been updated since 2002) Since that time the basics of Earned Value has been used by different people at different levels in the organization, shifting dependent on normal reorganizations and interest. The main difference today is the manifest throughout the entire organization that the Earned Value Method should be embraced. The reason for this change is as simple as a customer demand. The largest customer in Sweden stated in 2003 that Earned Value should be used as a reporting technique in all their projects. At the same time there was a need in a project to be able to produce reports in Earned Value figures to the Australian Division. In Australia the Department of Defense has been demanding their supplier to use Earned Value for quite a time. Those facts combined with the wish from SAAB Group’s management to get reports based on Earned Value figures lead to the manifestation of the change.79 4.1.2.1 Scoping the Project at Naval Systems Division When scoping the project at NSDS the work is planned either in planning packages or work packages. 4.1.2.1.1 Planning Packages At the project start the entire project is broken down into a big WBS-chart and WBSdictionary. The WBS is principally product oriented although some activities can be stated as 76 Ulf Karlsson 77 Stefan Larsson 78 Projekthandbok, SAAB Systems 79 Michael Trochez 48 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden work oriented WBS-elements. The work is planned in planning packages assigned to individual documents stating the work to be done. Those documents constitutes the agreement between the Project Management and the Functional Organization and defines the scope of work to be done, the inputs, interdependencies and outputs, key milestones and allocated budget. The packages should be broken down at a level well suited for delegation.80 4.1.2.1.2 Work Packages There is no specific rule about how far in advance the planning packages should be converted into work packages at the Naval Systems Division. The conditions for each activity must be decisive for the time chosen. The time needed to allocate wanted resources is a good guidance according to the “Projekthandbok”, which also indicates that there is no reason to plan non critical activities far in advance.81 The common attitude among the Project Managers at Naval Systems Division is that approximately six months ahead should be planned at work package level. The breakdown into work packages is made as a Bottom-Up planning. This means that the sum of the work packages does not always equal the corresponding planning package. If the difference is insignificant, no action is taken at all. If the difference is of major size, relative the project, the baseline can be changed. If the baseline needs to be changed that decision has to go through the managerial body.82 4.1.2.2 Performance Measurement Techniques Two Performance Measurement Techniques are used at NSDS, Percent Complete Estimates and Level of Effort. 80 Projekthandbok, SAAB Systems 81 Projekthandbok, SAAB Systems 82 Henrik Olsson 49 Vestberg, Rasmus Chapter 4 – Empirical Study 4.1.2.2.1 Percent Complete Estimates In Naval Systems Division the earned value is achieved in some automatic kind of way. All employees working at Naval Systems Division reports their hours into a computer system. The time reported into each work package generates the earned value based on the time spent and the planned value. No regard is taken to the earlier cost performance when calculating the value. The system has limitation to prevent the Earned Value to exceed 100% in case the time reported would be more than the time planned.83 Periodically, at least once a month, the person responsible for each work package updates the plan and the planned cost for the work package. To make Earned Value Management work changes in the original baseline is not recommended, SAAB uses therefore several baselines. The original baseline is named “Baseline 10” and can only be changed if there is a change of scope, the changing baseline will simply be denoted as “baseline”. If the work package has used 50% of its time planned in the baseline the work package has earned 50% of the baseline10. This means that as long as the plan is updated and the baseline is the latest estimated cost and duration for each work package, the Earned Value will be automatically generated based on the reported hours. Earned Value = ActualWork * Baseline10 Actual Work + Estimated Remaining Work Formula 9 If the “Baseline 10” is budgeted as 500 hours, the actual work is 300 hours and the updated baseline is set to 600 hours, then the Earned Value will be 250 hours. The actual work represents 50% of the latest estimate of that specific work package, this means that the project earns 50% of the original baseline; the “Baseline 10”. 4.1.2.2.2 Level of Effort The performance measurement method Level of Effort is used at the Naval Systems Division for work packages in which it is difficult to measure the progress. Example could be Project 83 Yngve Henriks 50 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden Management, Configuration Management or Quality Management. At the Naval Systems Division the proportion of Level of Effort varies between 9.4% and 46.8% depending on which project one looks at. The average proportion of Level of Effort is 19.7% at Naval Systems Division.84 4.1.2.3 Scheduling The planning group has the responsibility to schedule projects tasks. As the base of the scheduling the planning group uses Microsoft Project Server, where all task are gathered and connected with interdependencies. This Microsoft Project schedule contains for example information about start and finish dates, budgeted costs and apportioned resources. This data, as the core of Earned Value, is exported to another system handling the Earned Value data and metrics. Since the Naval Systems Division project organization is put together the way it is, one of the major tasks for the planning group is to manage resources amongst the different projects. This means keeping track on the covering of staff. Making sure each project gets its required staff and keeping individuals from being over scheduled. The constant updating of the project plans is necessary to schedule the resources associated with each work package. This information is not provided when using performance indexes.85 4.1.2.4 Forecasting and Predicting Completion Date Neither the Cost Performance Index nor the Schedule Performance Index is used to forecast a project. Instead of using the formulas described above (3.2.2.5) the forecasting at Naval Systems Division is based upon the updated baseline as described above (4.1.2.2.1). This makes the forecasting very simple concerning both time and money since the plan is updated with the latest revised estimates. That is since the plan has already been updated based on the experience and the subjective judgment of the responsible person for each work package.86 84 Michael Trochez 85 Yngve Henriks 86 Björn Lindberg 51 Vestberg, Rasmus Chapter 4 – Empirical Study Estimate at Completion = Actual Work + Estimate to Complete Formula 10 The Managers at Naval Systems Division believe that using the CPI and SPI when predicting the projects outcome is not justifying. A late start will have to large impact on the Estimate at Completion when using the traditional Earned Value Management forecasting methods. The experience and subjective judgment from the Project Leader is a much more reliable way of predicting the projects future.87 4.2 Forecasting Accuracy at NSDS As earlier mentioned the forecasting at Naval Systems Division is based on the subjective judgement from the people responsible for each work package. The following graphs represents the accurateness of those prediction based on the final outcome of the work package. Worth noting is that when there has been a change of scope this has been filtered to still show the accurateness of the predictions. That means, bad predictions can not be explained by change of scope. 4.2.1 Accurateness Relative Entire Work Package The easiest and most obvious approach to show the accuracy of the prediction is to compare the final outcome of the work package with the estimated outcome at each time. The difference between the prediction and the true outcome is the searched value. This is displayed in the following graphs relative the final entire work for each work package. Forecasting Accuracy = Forecast time of measurement − Actual Cost at completion Actual Cost at completion Formula 11 87 Yngve Henriks 52 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden In Figure 9 each line represents one work package. The x-axis represents the timeline in months based on the true dates for the studied work packages. The y-axis represents the Forecasting Accuracy in percent of the entire work package. The dots on each curve represents the time when each work package finished. The finish date is set when the Earned Value has reached 100%. Some of the work packages have smaller changes after the finish date, which is a consequence from the use of Level of Effort (see 6.1.3). 400,00% 200,00% 100,00% jun-0 7 maj07 7 apr-0 7 mar-0 feb-0 7 jan-0 7 6 6 okt-0 dec-0 6 sep-0 nov06 6 aug-0 jul-06 jun-0 6 maj06 6 0,00% apr-0 Forecast relative Actual at Completion 300,00% -100,00% -200,00% Date Figure 9 Difference in Forecast and Actual at Completion relative entire work package, true finish dates 53 Vestberg, Rasmus Chapter 4 – Empirical Study In Figure 10 the work packages has been horizontally displaced so that all work packages end in June 2007. This displacement is made to make the analysing of forecasting accuracy trends easier. As seen in Figure 10 the different curves start at different points. Those points are not the true start date of the work packages; it is only the start date of the available historical data. 400% 200% 100% jun-0 7 maj07 7 apr-0 07 mar- feb-0 7 jan-0 7 6 dec-0 6 okt-0 6 6 sep-0 nov-0 6 aug-0 jul-06 jun-0 6 maj06 6 0% apr-0 Forecast relative Actual at Completion 300% -100% -200% Date Figure 10 Difference in Forecast and Actual at Completion relative entire work package, finish dates displaced to jun-07 54 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden Figure 11 is a more detailed through zoom example of Figure 10 to further increase the clarity of the graphs. In Figure 11 two broken lines have also been inserted at ±10%. Before the study took place the principal stated that when the forecasting is within 10% we can say that the knowledge of the outcome is acceptable. 30% 10% 7 jun-0 maj07 apr-0 7 7 mar-0 7 jan-0 feb-0 7 6 dec0 n o v06 6 okt-0 6 sep-0 aug06 jul-0 6 6 jun-0 maj06 0% apr-0 6 Forecast relative Actual at Completion 20% -10% -20% -30% Date Figure 11 Difference in Forecast and Actual at Completion relative entire work package, finish dates displaced to jun-07, zoomed in 4.2.2 Accurateness Relative Remaining Work A second approach when looking at the accuracy of the predictions is to measure the difference between the forecasted and the actual values based on the remaining work. The only difference in this approach is that the quota is based on the remaining work instead of the total work at each time. Forecasting AccuracyRe lative remaining work = Actual Cost at Completion − Estimated Cost at Completiontime of measurement Actual Cost time of measurement − Actual Cost at Completion Formula 12 55 Vestberg, Rasmus Chapter 4 – Empirical Study In Figure 12 each line represents one work package. The x-axis represents the timeline in months based on the true dates for the studied work packages. The y-axis represents the Forecasting Accuracy in percent of the real remaining work. The work packages have been horizontal displaced making them all end in June 2007. 1000% 600% 400% 200% jun-0 7 maj07 7 apr-0 7 mar-0 feb-0 7 jan-0 7 6 dec-0 nov06 6 okt-0 sep06 aug06 6 jul-0 jun-0 6 maj06 6 0% apr-0 Forecast relative Actual at Completion 800% -200% Date Figure 12 Difference in Forecast and Actual at Completion relative remaining work, finish dates displaced to jun-07 56 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden Figure 13 is a more detailed through zoom example of Figure 12 with the broken lines inserted to highlight the ±10% area. 100% 80% 40% 20% 7 jun-0 maj07 apr-0 7 7 jan-0 mar07 6 dec-0 feb-0 7 6 nov-0 6 okt-0 6 sep-0 aug-0 6 jul-06 6 jun-0 -20% maj06 0% apr-0 6 Forecast relative Actual at Completion 60% -40% -60% -80% -100% Date Figure 13 Difference in Forecast and Actual at Completion relative remaining work, finish dates displaced to jun-07, zoomed in 4.3 NSDS Forecasting vs. Cumulative CPI Forecasting The available historical data, used to present the accuracy of the forecasting at Naval Systems Division, can be used to generate Cumulative CPI Forecasting for the same work packages. The reports providing us with historical data also contain the Actual Cost at each time. The Cumulative CPI is calculated with the following formula. Estimate at Completion = Budget at Completion Budget at Completion = Cost Performance Index Earned Value Actual Cost Formula 13 Provided those data we can compare the accuracy of the subjective method used at NSDS and the mathematical CPI method. 57 Vestberg, Rasmus Chapter 4 – Empirical Study 4.3.1 Relative Entire Work Package In Figure 14 to Figure 21 the graphs display the accuracy relative the entire Work Package as in 4.2.1. Each figure represents one work package forecasted in the two different ways. The red line represents the CPI method while the black line represents the subjective method used today at NSDS. In each graph the average inaccuracy for each work package and method is displayed. The following graphs are meant to show trends and should not be analyzed in detail one by one. 12% 10% 8% 6% 4% Forecast using NSDS method Average: 2% 2% 15 14 13 12 11 10 9 8 7 6 5 4 3 2 0% 1 Forecast relative Actual at Completion Forecast using CPI Average: 3% -2% Date Figure 14 Work package 1, Forecast using CPI vs. Forecast using NSDS method, relative entire work package 58 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden 40% 30% 10% Forecast using NSDS method Average: 9% 15 14 13 12 11 10 9 8 7 6 5 4 3 2 0% 1 Forecast relative Actual at Completion 20% -10% -20% -30% -40% Forecast using CPI Average: 19% -50% -60% Date Figure 15 Work package 2, Forecast using CPI vs. Forecast using NSDS method, relative entire work package 60% 20% Forecast using NSDS method Average: 18% 15 14 13 12 11 10 9 8 7 6 5 4 3 2 0% 1 Forecast relative Actual at Completion 40% -20% -40% -60% Forecast using CPI Average: 39% -80% Date Figure 16 Work package 3, Forecast using CPI vs. Forecast using NSDS method, relative entire work package 59 Vestberg, Rasmus Chapter 4 – Empirical Study 10% Forecast relative Actual at Completion 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1 0% -10% -20% Forecast using CPI Average: 14% -30% -40% -50% Forecast using NSDS method Average: 16% -60% Date Figure 17 Work package 4, Forecast using CPI vs. Forecast using NSDS method, relative entire work package 90% Forecast using NSDS method Average: 75% 80% Forecast using CPI Average: 61% 60% 50% 40% 30% 20% 10% 15 14 13 12 11 10 9 8 7 6 5 4 3 2 0% 1 Forecast relative Actual at Completion 70% Date Figure 18 Work package 5, Forecast using CPI vs. Forecast using NSDS method, relative entire work package 60 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden 80% Forecast using NSDS method Average: 12% 70% Forecast relative Actual at Completion 60% 50% 40% 30% 20% Forecast using CPI Average: 5% 10% 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1 0% -10% -20% Date Figure 19 Work package 6, Forecast using CPI vs. Forecast using NSDS method, relative entire work package 100% Forecast using NSDS method Average: 25% 60% 40% 20% 15 14 13 12 11 10 9 8 7 6 5 4 3 2 0% 1 Forecast relative Actual at Completion 80% -20% Forecast using CPI Average: 10% -40% Date Figure 20 Work package 7, Forecast using CPI vs. Forecast using NSDS method, relative entire work package 61 Vestberg, Rasmus Chapter 4 – Empirical Study 40% 30% 10% 15 14 13 12 11 10 9 8 7 6 5 4 3 2 0% 1 Forecast relative Actual at Completion 20% -10% -20% -30% Forecast using NSDS method Average: 22% -40% -50% Forecast using CPI Average: 16% -60% Date Figure 21 Work package 8, Forecast using CPI vs. Forecast using NSDS method, relative entire work package For the eight work packages represented in the graphs above, the total average inaccuracy is 22% respectively 21% for the subjective NSDS’s method and the CPI method. 4.3.2 Relative Remaining Work In Figure 22 to Figure 29 the graphs display the accuracy relative the remaining work as in 4.2.2. Each figure represents one work package forecasted in the two different ways. The red line represents the CPI method while the black line represents the subjective method used today at NSDS. In each graph the average error for each work package and method is displayed. The following graphs are meant to show trends and should not be analyzed in detail one by one. 62 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden 1000% Forecast relative Actual at Completion 800% 600% 400% 200% Forecast using CPI Average: 170% 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1 0% Forecast using NSDS method Average: 247% -200% Date Figure 22 Work package 1, Forecast using CPI vs. Forecast using NSDS method, relative remaining work 80% 60% 20% Forecast using NSDS method Average: 30% 15 14 13 12 11 10 9 8 7 6 5 4 3 2 0% 1 Forecast relative Actual at Completion 40% -20% -40% Forecast using CPI Average: 35% -60% -80% -100% Date Figure 23 Work package 2, Forecast using CPI vs. Forecast using NSDS method, relative remaining work 63 Vestberg, Rasmus Chapter 4 – Empirical Study 300% 250% Forecast relative Actual at Completion 200% 150% 100% 50% Forecast using NSDS method Average: 67% 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1 0% -50% Forecast using CPI Average: 62% -100% Date Figure 24 Work package 3, Forecast using CPI vs. Forecast using NSDS method, relative remaining work 40% 15 14 13 12 11 10 9 8 7 6 5 4 3 2 0% 1 Forecast relative Actual at Completion 20% -20% -40% Forecast using CPI Average: 43% -60% -80% Forecast using NSDS method Average: 42% -100% Date Figure 25 Work package 4, Forecast using CPI vs. Forecast using NSDS method, relative remaining work 64 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden 600% Forecast relative Actual at Completion 500% 400% 300% 200% Forecast using NSDS method Average: 236% Forecast using CPI Average: 156% 100% 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1 0% Date Figure 26 Work package 5, Forecast using CPI vs. Forecast using NSDS method, relative remaining work 400% 350% Forecast using NSDS method Average: 102% 250% 200% 150% 100% Forecast using CPI Average: 59% 50% 15 14 13 12 11 10 9 8 7 6 5 4 3 2 0% 1 Forecast relative Actual at Completion 300% -50% -100% Date Figure 27 Work package 6, Forecast using CPI vs. Forecast using NSDS method, relative remaining work 65 Vestberg, Rasmus Chapter 4 – Empirical Study 250% 150% Forecast using NSDS method Average: 73% 100% 50% 15 14 13 12 11 10 9 8 7 6 5 4 3 2 0% 1 Forecast relative Actual at Completion 200% -50% Forecast using CPI Average: 37% -100% Date Figure 28 Work package 7, Forecast using CPI vs. Forecast using NSDS method, relative remaining work 150% 50% Forecast using CPI Average: 28% -50% 15 14 13 12 11 10 9 8 7 6 5 4 3 2 0% 1 Forecast relative Actual at Completion 100% Forecast using NSDS method Average: 42% -100% Date Figure 29 Work package 8, Forecast using CPI vs. Forecast using NSDS method, relative remaining work 66 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden For the eight work packages represented in the graphs above, the total average inaccuracy is 102% respectively 72% for the subjective NSDS’s method and the CPI method. 67 Vestberg, Rasmus Chapter 5 – Analysis 5 Analysis This chapter contains the analyze of the result of the empirical study and the frame of reference concerning Naval Systems Division. Deeper discussion about the findings will be done in chapter 6 Discussion. 5.1 Planning package conversion The purpose of studying the accuracy of the forecasting at Naval Systems Division was to provide statistic data telling us how far in advance we can make plans at work package level. The attempt was to find a trend showing when the forecasting is stabile within 10% from the final outcome. Through the way of measuring performance at NSDS the forecasting could be used for this purpose. In the empirical study there have been two different approaches of how the forecasting accuracy should be measured. Either one measures the accuracy relative the entire work (Figure 9-Figure 11) or relative the actual remaining work (Figure 12 and Figure 13). 5.1.1 Relative Entire Work When measuring the forecasting accuracy relative the entire work package the size of the work package will have great influence on the result. In a large work package there can be a significant amount of work left, having great impact on the entire project, still constitute only a smaller part of the work package. This means that bad predictions are excused thanks to the size of the work package. This way of measuring will always approach perfect prediction. The remaining work and therefore also the prediction offset, approaches zero during the progress of the work package. Since the entire work eventually will be much larger than the prediction offset the relative offset will approach zero. This approach could be looked upon as the measure of how well one could predict the entire work package at different points. 68 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden Figure 9 displays the work packages in an authentic timeline. This is a little bit roundabout to analyze. Therefore we look at Figure 10 and Figure 11 instead. Those display the same data only displaced in time to ease analyzing. Figure 11 is a more detailed through zoom example of Figure 10. If starting to look at Figure 10 one can see that one year before completion, seven out of eleven work packages are close to or more than 100% wrong. This means that the estimation is less than half or more than twice the actual. At some point between seven and nine months before completion the curves starts to close up on the zero line although they are not within the 10% limit. Worth noticing is that it is more common with overestimates than underestimates. It is most likely that the close up depends on the relative entire work instead of the better knowledge. Since the curves relative remaining work do not show the same trend at the same point of time (see 5.1.2). It is more likely that the trend shows that seven to nine months before completion there is not much work left on the work packages closing up on the final outcome, instead of showing that the predictions are more valid within this time period. If looking at the zoomed in Figure 11 we can see that more than a third of the work packages do not enter within the 10% limit until the work is completed. For the rest of the work packages they are within the 10% area between 3.5 and 9 months before completion with a median of 5 months. The work packages entering within the limit at completion is probably subject for trick based on individuals wish to always under run. 5.1.2 Relative Remaining Work When measuring the forecasting accuracy relative the remaining work the finished work is ignored. This makes this method equal the forecasting of a small work package with the same size as the remaining work. In the beginning of the work package this approach will give almost the same results as measuring against the entire work package. This is because the remaining work is close to the 69 Vestberg, Rasmus Chapter 5 – Analysis entire work. When work precedes the difference between the entire work and the remaining work will increase, consequently the methods will give different results. One should be aware of the possibility of extreme data in the very end of the project or when there is very small amount of work left. If the remaining work is very small, insignificant forecasting errors could give large turns on the relative value. Because of this one might not pay to much attention to the figures provided by this method in the very last phase of the projects. This approach could be looked upon as the measure of how well one could predict the remaining work at different times. Figure 12 and Figure 13 displays the work packages relative the remaining actual work. The figures are displaced in time to ease analyzing and Figure 13 is a detailed through zoom example of Figure 12. If looking at Figure 12 we can see that some work packages are very poor forecasted. At worst one is more than eight times overestimated. One can also see the phenomena in the last two months mentioned above. If ignoring the last two months and looking at Figure 13 we would hopefully be able to distinguish some trends suggesting the time frame for planning at work package level. Unfortunately it is impossible to tell from the curves that the forecasting is getting better in a certain time frame. In fact all work packages are only occasionally inside the 10% which might as well be luck as good predictions. 5.2 PMT One of the purposes of studying literature about Performance Measurement Techniques was to provide suggestions of improvement within this area at Naval Systems Division. Combining the information from the literature and the situation at NSDS provides the fundament for later given suggestions. Some of those suggestions can be supported by some comparing made in the empirical study. 70 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden 5.2.1 Analyze based on Frame of Reference If the plans are not running updated the whole Earned Value Concept at Naval Systems Division will fall apart. Since the generating of Earned Value is based on the updated plan this must work. If not, the measurement becomes in practice the same as in traditional project management; the Earned Value equals the money spent. The way of measuring equals the Percent Complete method with subjective judgement. The only difference is that if the judgements are not made the NSDS method will earn the planned value while the Percent Complete method will earn no value at all. Earning no value at all will most likely force the manager to update their plans. Earning perfect value as a consequence of not doing anything at all does not encourage correct behavior. The Gold Practices suggest that one should use Fixed Formula with the value 0% and 100%, earning 100% when the work package is finished. This method is in practice the same thing as Weighted Milestones. In Weighted milestones the work packages are a little bit bigger and one chooses to split the work into measurable parts with the different milestones. In the Fixed Formula method one splits the work at the milestones into separate small work packages. In the Gold Practices there is strongly recommend not to use the subjective percent complete method. The use of Level of Effort is not recommended based on the non real value quality. If the Level of Effort exceeds 5-10% of the work packages one measures the passage of time instead of true performance. At NSDS the average of all work measured using LOE is 19.7%. In the worst project the amount of LOE is 46.8%, that is almost half the project. Those figures truly indicate that one is not using EVM at its best capacity at Naval Systems Division. 5.2.2 Analyze based on Empirical Study Since the forecasting and calculation of Earned Value is closely related at Naval Systems Division, in fact the precise same thing, we can use the forecasting method to evaluate the used Performance Measurement Technique. Since the forecasting is, as stated above, very inaccurate the Earned Value must be as well. This implies that we must consider changing the Performance Measurement Technique to get the correct Earned Value. 71 Vestberg, Rasmus Chapter 5 – Analysis One of the great advantages with Earned Value is the easy forecasting provided by the performance indexes. If NSDS changes the Performance Measurement Technique they will no longer have the forecasting provided “for free”. They could of course continue with the subjective judgments to predict to future work packages, this is in literature stated as probably the best forecasting method. However, this method takes a lot of time (see 3.2.2.5). Instead of sticking to the old forecasting one could start using the simple index based method recommended by PMI. The method mentioned as the “most likely” is the Cumulative CPI method (see 3.2.2.5.2). Therefore this method has been compared with NSDS forecasting method in Figure 15 to Figure 29. Figure 15 to Figure 21 shows the forecasting error relative entire work package while Figure 22 to Figure 29 shows the error relative remaining work. The end points for all the curves are set to the time when all the work packages have reported 100% Earned Value. If first looking at the figures displaying relative entire work, we can see the following things: The endpoint for the NSDS method does not always equal zero. This is because the Earned Value has been reported as 100% although the estimates still indicating that there is some work left. The reason for this is the problem behind Level of Effort. Although the Level of Effort package has been displaced in time and the manager estimate the work to be not finished, the value will be earned according to the original baseline. This is why the NSDS method does not always equal zero in the end, as it is supposed to do with the relative entire work approach. The CPI method always equals the actual at completion when 100% value has been earned. Besides this there is no larger difference in the precision of the two methods. The average error for the CPI respectively the NSDS method is 21% and 22%, which shows an insignificant difference. If looking at the figures showing the errors relative the remaining work the differences becomes more evident. The NSDS method is no longer expected to end at a zero error (see 5.1.2) but the CPI method still does. This makes the CPI method more stabile and the average error for the CPI respectively the NSDS method is 72% and 102%. The CPI method is then proven to be more valid in this case. Important to notice is that this is only valid for this specific Division or perhaps only this specific case. One also has to keep in mind that the CPI is based on the Earned Value. This gives a circle relation in this case since the Earned Value is related to the forecasting. The 72 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden Earned Value has already been condemned why also the CPI method will be flawed. However, if the Earned Value were more valid the CPI method would also provide better accuracy. 73 Vestberg, Rasmus Chapter 6 – Discussion 6 Discussion This chapter will discuss the findings made in the Frame of Reference and the Empirical study. In this chapter I will also present my own ideas and conclusions based on the earlier presented information and data. 6.1 PMT This section will discuss findings concerning Performance Measurement Techniques. 6.1.1 Automatic Earned Value At first sight it might seem to be a good idea to make the earned value automatic in some way. For example one could use the time reported on each work package and transfer the figures to earned value. If one uses the cost performance index to date, and assume that the index is the same for this work package, the estimated earned value would most likely be pretty accurate. To prevent the possibility that one receives more than 100% earned value of planned value one could perhaps say that the last 20% only can be awarded by the project manager or at completion of a task as in Percent Complete Estimates with a ceiling. However, on second thought, one might ask oneself, is this really earned value? Is this not in fact only the traditional project follow-up dressed in earned value? If we do not measure the value but instead calculate the value based on work performed we can not really tell anything about the status of that particular work package. The only thing this will give us is the planned value updated based on the projects performance so far. This is in fact the estimated budgeted cost for work scheduled. The usage of cost performance index in this example does not help as much as one might think. Since the cost performance index originate from the previous earned value and the previous actual cost we will have a problem since the earned value was not really earned value. Only the fully completed work packages will help with providing a correct cost 74 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden 6.1.2 NSDS subjective Measurement Technique This measurement between “Baseline 10” and baseline means that one can lose already earned value. Let us say the work package’s “Baseline 10” has been apportioned 800 hours, the baseline has not been changed and the persons working with the work package has spent 400 hours. Then we have an earned value of 50% of the baseline which gives 400 hours from the “Baseline 10”. When updating the plan the manager realizes that the work package in fact will spend 1000 hours. The change of the baseline can originate from many things e.g. bad plan, unexpected problems, errors etc. Since there has not been any change in scope the “Baseline 10” is unchanged. This means that we have only done 40% of the baseline which in turn means that we can only receive 40% earned value from the “Baseline 10”, 320 hours. So the earned value has decreased from 400 to 320 hours. The way of measuring the Earned Value at Naval Systems Division is in reality the same as Percent Complete Estimates. Instead of estimating how much of the work already been done, one estimates the amount of work still remaining. This gives the exact same result and is only different in the approach of using the Performance Measurement Technique. In both approaches it is possible to “lose” already earned value; however, I believe that it would be greater probability for this to happen with the Naval Systems Divisions approach. It would be contradictory for a manager to state one week that we have accomplished 40% of the planned work and the next week decrease it to 35%. In the Naval Systems Divisions approach, it is not very contradictory to state that one has realized that there is more work left than what was expected the week earlier, although it has the exact same affect on the Earned Value. Is it good that the measurement technique makes it possible to lose Earned Value? On the one hand it must be a good thing. Since the Earned Value obviously was not achieved one should not be able to profit what one does not have. On the other hand the reports will be uncertain if the Earned Value can fluctuate. Also, it must be annoying for the personnel to work in a project where the progress is not certain. Further, if the value really has been achieved, then it might be tragic that one can loose it because of complications in the remaining work. The already earned value might in fact be valid and should not change at all. 75 Vestberg, Rasmus Chapter 6 – Discussion The measurement technique used at NSDS is very vulnerable to old plans. If the plan is not running updated the method will equal traditional project management without EVM. In traditional Percent Complete estimates bad updates will result in no Earned Value, why the incentive to update the plans are probably higher in this method than in NSDS’s method. The way of measuring the Earned Value has its advantages concerning scheduling of resources, but I still do not think it is true Earned Value. Also, if the forecast is as bad as the Empirical Study shows, then it is pointless to use it for resource allocations. These circumstances emphasize the importance of having a measurement technique that one can truly trust. And I believe, based on the flaws with the different Performance Measurement Techniques, that the only ones with true Earned Value is Weighted Milestones and Fixed Formula. If the work is done and can be measured, then the value is earned. 6.1.3 Level of Effort Level of Effort makes it possible to have earned all value although there is still work remaining. In fact the value can be earned before the work package even started, if the work package has been moved in time. This is simply because at NSDS the “Baseline 10” does not change even if the work does. It is only the baseline used for estimates that is affected of increases or delays in the work package measured with Level of Effort. This means that it can look like a work package is finished but there is still work to be done. This is obviously not good. The simple solution to this is to change the “Baseline 10” every time the LOE work package is changed. Since LOE always should perform well this is the only solution if one wants to use this measurement technique. In the curves in Figure 10 some effects of NSDS’s wide use of Level of Effort is evident. Not even when the work packages have earned 100% of its value the forecast is correct. This is simply caused by the corruption made by Level of Effort measurement. The average project at NSDS measures 19.7% of the work with LOE. The LOE work packages are made up by overhead costs, such as support, quality, management, planning etc. 76 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden To reduce the amount of level of effort to be able to use EVM for real one could separate those work packages and handle them as business overhead cost. This might not be the best solution since different project might use those functions differently. Another way of dealing with it is to use Apportioned Relationship or Percent Complete. The Percent Complete is not recommended in ordinary cases, but it is still much more preferable than LOE. The apportioned relationship is well suited as long as one could find related work packages to connect the measurement to. Note! Instead of only changing PMT for today’s LOE tasks the amount of LOE might work as a warning signal. Is it really healthy to use 46.8% (the worst case at NSDS) of the time in a project to management and support? Possibly the entire project resource allocation needs revisiting. 6.2 Planning Package Conversion It is a common fact that there is not possible to plan every work packages from the beginning in a large scaled project. The gathered literature agrees that one should do the planning on higher level and bye and bye do what is called a rolling planning. However there is no one mentioning in what timeframe the detailed breakdown should be done. And perhaps most important there is no discussion what so ever about how this rolling planning influence the Earned Value. 6.2.1 Forecasting The forecasting at Naval Systems Division is very simple thanks to the way of using Earned Value calculation. In fact, forecasting using a revised plan is mentioned to be the most reliable forecasting method of them all (3.2.2.5). However, this means that the Naval Systems Division is using the forecasting method used in traditional project management instead of the easy mathematical method provided by Earned Value Management. Since this feature is one of the greatest advantages with Earned Value Management one loses some of the merits in EVM by using this approach. 77 Vestberg, Rasmus Chapter 6 – Discussion It might be that the estimate from a Project Leader or a Program Project Leader is more valid than the estimate made using performance indexes. However, as earlier spoken, the way of measuring Earned Value at Naval Systems Division is not real Earned Value. The Performance Measurement Technique will need to be revised. If the constant updating of the plan is no longer needed to generate the Earned Value this work would only be done based on forecasting needs. That means we are back in the choice between the time-consuming and accurate classic forecasting method and the almost as reliable but very easy EVM forecasting method (more reliable in our case). Instead of as today, when one gets the classic forecasting method on top of the not fully implemented Earned Value Management System. In the empirical study the forecasting relative the entire work package is far better than the one relative the remaining work. Which one should we then pay attention to? It would be the same thing to predict the entire work package as predicting the remaining of the work package. However I believe that the mind can be tricked to do different predictions based on the way the question is put. No matter if the results would be different or not the fact remains; at Naval Systems Division the question is always “How much work remains?” This means that there is no excuse for not looking at the predictions based on the remaining work. Hence we can conclude that the predictions of today are very poor. If we use this approach to determine the time frame for conversion of planning packages, it is important that the remaining of a work package can be equalled with a smaller work package. One could argue that the remaining should not be equalled with a smaller work package, since there could be things that one states as finished although their not. That would mean that there is more work left to do than expected. There are two obvious counter-arguments for this statement. First of all, if we are not certain on the Earned Value achieved we can seriously question the entire method. Second, the same thing could be valid for smaller work packages, the inputs from earlier work packages are not correct and there will be more work than expected. The reason for using NSDS forecasting method is based on the necessity to have updated plans in order to make correct resource allocation. One might ask one self this question; is it likely that the Project Leader or the Program Project Leader will perform better in updating the far term plans than they did with the nearby work packages? If not, the index of how the 78 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden nearby work packages fall out might be at least as good as the subjective judgment. This line of argument must also support the idea that it is possible to do long term resource planning based on performance index. If the index indicates that one needs 1.25 hours for every planned hour then that would be enough information for the resource planning. At least as long as we agree in that the performance indexes are good enough to replace the updated plans concerning estimates and long term planning. The big difference in the Empirical Study between the forecast and the Actual at Completion in some work packages can be explained in several ways. It could be that the person in charge has very bad control over the entire work package. More likely is that some individuals prefer to purposely overestimate the remaining work to be able to under run in the end. For them it is more important to look good in the end than to have a realistic plan during the work. This is confirmed likely based on the curves in Figure 11. All the work packages that first at completion have a realistic picture are subject for under runs. Large overestimates are a larger problem than one might think. This leads to higher prize to the customer and perhaps loss of business. It is interesting to see that the easy CPI method provides better accuracy than the strenuous method used at NSDS today. It should also be mentioned at this point that the figures used to generate the Cumulative CPI forecast is not true Earned Value as stated earlier. The fact that the subjective judgment provides insecure figures strengthens the theory that there is not real Earned Value measured when not using measurable defined work. 6.2.2 Rolling planning’s affect on EVM The “Projekthandbok” at NSDS indicates that there is no reason to do detail planning far in advance. Then they are not taking into consideration the affect that detailed plan might have on the EV curves. Neither do one care about the correct figures that might be needed for decisions concerning the project. The baseline for the entire project (the core of EV) must be set in the beginning, although the later part of the project is only planned briefly. As said in the Earned Value Project 79 Vestberg, Rasmus Chapter 6 – Discussion Management88 the work package is what gives the baseline. How can one then determine the later baseline when one has not done the breakdown into work packages yet? The answer is at first sight pretty simple, one lets the planning packages generate the baseline! However, at second thought one realizes this way of solving the problem has a flaw. The first part of the baseline is composed by the work packages in detailed plan, but the second part originates in les detailed plans and assumptions. Can one then really use the CPI and SPI that has been calculated based on one type of figures and then apply it to a different kind of figures? According to DoD and their massive research this seams to work. To solve this problem I would suggest NSDS to do planning at work package level for the entire project from the beginning. This is in somewhat controversial but can be supported by some basic arguments. First of all the empirical study does not show any signs indicating that people at NSDS do better plans concerning the near future than far term work packages. Approximately one third of the studied work packages are probably flawed by deliberate overestimates. However, the rest of the studied work packages do not show any better trends. Breakdown of a planning package tends to consist of adjusting the work packages to sum up the original planning package. This means that the later planned work packages are of the same granulate as the respective planning package. Planning on a higher level is likely to provide overestimates because of the safety margin put in the plan. Most of the work in the project at NSDS is not research and development why one should have pretty good knowledge about what to do. If you know how to do it, why not plan it. If one chooses to do detailed plan one might not need to schedule exactly when it should be done. But what and at what cost should not be a problem. The difference in the EVM-curves will then be only according time and not money. That is, the CPI is still ok but the SPI might show bad figures. 88 Fleming and Koppelman (2005) 80 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden If one anyway chooses to do rolling planning I believe it might be a good idea to be a bit more flexible about the baseline. The beginning of the baseline is made up by work packages. The beginning of the baseline is what makes the CPI and SPI which is why those also are based on figures from work package level. If the later part of the baseline is made up by planning packages one would combine data from different origin. This is why I suggest that one should not be too afraid of changing baseline when planning packages is broken down. 6.3 Miscellaneous This part will discuss findings outside the original problem. 6.3.1 Earned Scheduling The problem with SV($), shown in Figure 8, further support the idea that the SV($) is not to recommend. The case in Figure 8 is based on a perfect performance only starting one month late. It is obvious that the schedule variance should be one month over the projects entire life cycle. One can argue that the slippage is not constant based on the amount of money needed to retain the original schedule. As it looks in Figure 8 there would be much less money needed to catch up with the baseline in the beginning and in the end of the project. This would indicate that the Schedule Variance should not be constant anyway, and that the SV($) is the right way of measuring Schedule Variance. However, there is a reason why most projects baseline is S-shaped. In the beginning of the project the activities consists of planning, scoping, specifying requirements and so on. In the end of the project the task consists of testing, delivery, installation etcetera. In neither of the case it would be possible to double the output by doubling the resource. As an example, a meeting with the buyer is not likely to take half the time if one doubles the people participating. SV(t) can if wanted be recalculated to $ again. It might sound a little odd to first replace the measurement based on money with a measurement based on time, and then convert the time into money again. Still it will not be the same thing. The SV($) is the vertical difference between baseline and performance while the SV(t) is the horizontal difference. Converting the SV(t) into money will not change this difference between the two approaches, only display the variance in another unit. I would not recommend this conversion since it only complicates 81 Vestberg, Rasmus Chapter 6 – Discussion a well working easy technique. The reason for doing this anyway would be if one must display the figures in the same unit. The more intuitive approach of the Schedule Variance combined with the less defective result compared to the SV($) makes this method an obvious choice. Changing into Earned Scheduling would not mean any revision of the plans or anything. The changes do only comprise the way of calculating the variance when computing the Earned Value figures. Unfortunately the system used at NSDS to manage Earned Value does not support Earned Scheduling. However, all the data needed to calculate Earned Schedule is available in the system and the only thing needed is the implementation of a new formula. Based on the insignificant change in the system (probably only some few lines of code) and the size of NSDS as a customer to the system provider, would make it possible to do this implementation instantly. 6.3.2 Earned Value Acceptance The mutual understanding at NSDS is that Earned Value Management is something bright new, which it is not, not even for NSDS. The main concept of EVM has been present at NSDS since the beginning of the eighties, only under different names. The name of the concept is insignificant, the important thing is that people at NSDS do not seem to like it or know anything about it. Perhaps it is not even necessary to call the measurement technique by some specific name. The important thing is the figure provided from the system. By using a simple method as Milestone Measurement and the basics of Earned Scheduling the functions are well covered. Using several milestones in each work package makes it easier to really determine the status of the project, in the same time they serve the purpose of engaging the staff. Having frequent milestone will visualize the progress of the work. 82 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden 83 Vestberg, Rasmus Chapter 7 – Conclusions 7 Conclusions This chapter will in condensed form present the conclusions and suggestions for adaptations at NSDS. The Empirical study is because of the quantity not statistical in any way. However, the suggestions would be valid anyway based only on the Frame of Reference. The small quantity of research does nevertheless support all conclusions. 7.1 Planning Package Conversion The empirical study can be interpreted in two ways; either one do not have to plan at all or we can plan the entire work at work package level from the beginning. Since the first option is unthinkable this must mean that we can plan all work packages in the start of the project. For those cases where there are impossible to plan at a more detailed level than planning packages the later breakdown must be followed by a consideration of a baseline change. This consideration of baseline change is direct opposite to recommendations made by PMI. However I think it is wrong to measure against a baseline consisting of careless high level plans made perhaps several years ago. If one is more admissive with changes in the baseline it is important that the changes are made as early as possible. If the changes are made to late the affect will be perfect performance. 7.2 PMT The only true Earned Value is the objective measurable value. Therefore the Measurement Technique to be used must be Weighted Milestones or Fixed Formula. This should be used with very small work packages or larger work packages divided into several measurable milestones. All Level of Effort task must be separated from the project baseline and measured separately. In cases where separation is not possible the work most preferably should be measured with Apportioned Relationship and secondary Percent Complete. This will provide a measurement on those tasks which is not present at all today. 84 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden 7.3 Forecasting The forecasting should be made as described in 3.2.2.5 with some of the mathematical approaches preferably using all three together as described. The method is easy and provides data good enough (and some times even better than today). Changing this routine is easy and could be made instantly without any revision of the plans. 7.4 Miscellaneous Today I would say that NSDS is not using Earned Value at all. This is mainly based on the very high level of LOE measurement. Also the shocking reliability in the subjective Earned Value measurement supports that point of view. One would probably provide more accurate Earned Value by guessing. Even if other projects than the measured would be more accurate I still would not say that NSDS is measuring true Earned Value. Using a subjective method will in my mind never provide assured information. Thinking about it, measuring the performance with subjective method is what has always been done in traditional project management. The only difference is that in this case it is taken to a lower level and displayed in graphs. By adapting this recommendations there will most likely be several benefits. The work with Earned Value Management will be less. The data provided will be more reliable and therefore useful. Valid data will most likely yield a much wider acceptance for the system. Detailed measurable milestones will make it more difficult to strongly overestimate the work. If there still are large overestimates they will be noticed early when a couple of milestones has been achieved. The cause of the extreme portion of LOE should be further investigated. Not necessarily, but it could indicate bad use of resources. If half of the LOE tasks are misuse of resources (the amount of LOE is twice the maximum recommended) there is 10% of the total project budget to save. Doing the changes in forecasting would mean that one could no longer use the same data as above to determine the time frame for planning package breakdown. Instead, if adopting all purposed changes, one could measure the accuracy against the original plan, since all work 85 Vestberg, Rasmus Chapter 7 – Conclusions packages is recommended to be planned right away at project start. If there is a special time frame telling how far in advance it is possible to plan, this will be obvious. Measuring the accuracy in forecasting should be made running in the same way as in this report. This provides a good indication of how well the used techniques work, both for planning and measuring of Earned Value. 86 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden 87 Vestberg, Rasmus Chapter 8 – References 8 References Books Cassell, C. and G. Symon (ed.) (2004) Essential Guide to Qualitative Methods in Organizational Research. London. SAGE Publications Ltd Fleming Q. and Koppelman J. (2005), Earned Value Project Management, third edition, Pennsylvania, Project Management Institute, Inc. Lekvall, P. snd Wahlbin, C. (2001). Information för marknadsföringsbeslut – 4:e upplagan. Göteborg: IHM Publishing. Patel R. and Davidsson B. (2003), Forskningsmetodikens grunder, 2nd edition, Studentlitteratur, Lund Wenell T (2004), Wenell om projekt, Uppsala, Uppsala Publishing House AB (2005), A Guide to the Project Management Body of Knowledge: PMBOK guide. – 3rd ed., Pennsylvania, Project Management Institute, Inc. Articles Abba Wayne (2002), June 2002, Emerging Ideas, Relating EVM to “Real” Schedules, unpublished presentation National Contract Management Journal (1993), Spring 1993, Cost Performance Index Stability, Christensen, D. S., Heise, S. Acquisition Review Quarterly (1998), Fall 1998, The Cost and Benefits of the Earned Value Management Process, Christensen David S. Ph.D. Acquisition Review Quarterly (1999), Summer 1999, Using The Earned Value Cost Management Report to Evaluate the Contractor’s Estimate at Completion, Christensen David S, Ph.D. 88 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden The Measurable News (2007), Winter 2006-2007, Why EVM Is Not Good for Schedule Performance Analyses, Corovic Radenko The Measurable News (2003), Summer 2003, A Breakthrough Extension to Earned Value Theory?, Henderson Kym The Measurable News (2004), Spring 2004, Further Developments in Earned Schedule, Henderson Kym The Measurable News (2005), Spring 2005, Earned Schedule in Action, Henderson Kym The Measurable News (2007), Summer 2007, Earned Value Business Solutions: Implementation, Lessons Learned and Best Practices, Kondur Mohan The Measurable News (2003), Mars 2003, Schedule Is Different, Lipke Walt Proceedings of the 3rd International Conference on Project Management (2006), September 2006, Earned Schedule Leads to Improved Forecasting, Lipke Walt Interviews Person A, Manager Naval Operations Project Office Henriks Yngve, Manager Project Management Office, Naval Systems Division Sweden Karlsson Ulf, Project Planer, Naval Systems Division Sweden Larsson Stefan, Senior Project Planner, Naval Systems Division Sweden Lindberg Björn, Controller, Naval Systems Division Sweden Olsson Henrik, Project Manager, Naval Systems Division Sweden 89 Vestberg, Rasmus Chapter 8 – References Trochez Michael, Head for the Planning and Control Function, Naval Systems Division Sweden Internet http://saabnet.saabgroup.com/SaabSystems/About/index_sv.htm?NavigationType=SiteNaviga tionDataSource, Accessed June 2007 https://www.goldpractices.com/practices/tev/index.php, Accessed September 2007 Others ANSI/EIA-748-A-1998, Arlington, Electronic Industries Alliance Averstad D (2003), Projektstyrning med Earned Value – en metod under FMV uppdragsledningsprocess, Försvarets Materialverk Projekthandbok, SAAB Systems, serie av interna dokument rörande projektmetodik, Uppdaterad 2002-2003 90 Earned Value Management at Vestberg, Rasmus Saab Naval Systems Division Sweden 91 Vestberg, Rasmus Chapter 9 – Appendices 9 Appendices 9.1 Appendix 1 The chart displays the analyzed work package’s monthly figures. 92
© Copyright 2026 Paperzz