Final Intended Use Plan for the State Revolving Fund

State of New York
Department of Health
and
Environmental Facilities Corporation
Final
Intended Use Plan
Drinking Water State Revolving Fund
October 1, 2011 - September 30, 2012
Issued: October 1, 2011
The State of New York
Andrew M. Cuomo, Governor
Department of Health
Nirav R. Shah, M.D., M.P.H.,
Commissioner
Environmental Facilities Corp.
Matthew J. Driscoll
President and CEO
FINAL
INTENDED USE PLAN
for the
NEW YORK STATE
DRINKING WATER STATE REVOLVING FUND
October 1, 2011 - September 30, 2012
Issued: October 1, 2011
INTENDED USE PLAN
TABLE OF CONTENTS
Page
1.0 INTRODUCTION ................................................................................................................. 1 2.0 PROGRAM INITIATIVES AND CHANGES ................................................................... 2 3.0 SHORT- AND LONG-TERM GOALS .............................................................................. 4 3.1 3.2 SHORT-TERM GOALS................................................................................................................................... 4 LONG-TERM GOALS ..................................................................................................................................... 4 4.0 FINANCIAL STATUS ......................................................................................................... 5 4.1 4.2 4.3 4.4 4.5 4.6 4.7 TOTAL DWSRF MONIES ............................................................................................................................. 5 FEES ............................................................................................................................................................. 5 TRANSFER OF FUNDS .................................................................................................................................. 6 ELIGIBLE SYSTEMS AND TYPES OF PROJECTS TO BE FUNDED .................................................................. 6 FINANCIAL PLANNING PROCESS .................................................................................................................. 7 TYPES OF ASSISTANCE AND TERMS ............................................................................................................ 8 PROGRAM FINANCIAL TERMS .................................................................................................................... 10 5.0 AMENDING THE IUP ....................................................................................................... 12 6.0 SET-ASIDE ACTIVITIES ................................................................................................. 12 6.1 ADMINISTRATIVE ........................................................................................................................................ 12 6.2 TECHNICAL ASSISTANCE ........................................................................................................................... 13 6.2.1 Small Water Systems .......................................................................................................................... 13 6.2.2 Comprehensive Performance Evaluation Program ......................................................................... 14 6.3 STATE PROGRAM MANAGEMENT............................................................................................................... 14 6.3.1 Administer the PWSS Program .......................................................................................................... 14 6.4 SPECIAL ACTIVITIES ................................................................................................................................... 15 7.0 DISADVANTAGED COMMUNITY PROGRAM AND HARDSHIP ........................... 17 7.1 7.2 7.3 7.4 7.5 7.6 7.7 INTRODUCTION ........................................................................................................................................... 17 FINANCIAL AVAILABILITY ............................................................................................................................ 18 ELIGIBILITY FOR FINANCIAL HARDSHIP ASSISTANCE ................................................................................ 18 CALCULATING HARDSHIP ........................................................................................................................... 19 HARDSHIP APPLICATION PROCESS ........................................................................................................... 20 CONFIRMATION OF HARDSHIP AVAILABILITY ............................................................................................. 21 CO-FUNDING .............................................................................................................................................. 22 8.0 CAPACITY ASSESSMENT ............................................................................................ 22 8.1 8.2 8.3 8.4 8.5 8.6 TECHNICAL CAPACITY ................................................................................................................................ 22 FINANCIAL CAPACITY ................................................................................................................................. 22 MANAGERIAL CAPACITY ............................................................................................................................. 22 SYSTEMS WITH INADEQUATE CAPACITY .................................................................................................... 23 LONG-TERM CAPACITY .............................................................................................................................. 23 ANNUAL REPORTING REQUIREMENTS ....................................................................................................... 23 9.0 STATE ENVIRONMENTAL REVIEW PROCESS/DETERMINATION OF
EQUIVALENCY PROJECTS .......................................................................................... 24 10.0 PROJECT PRIORITY LISTS .......................................................................................... 25 i
10.1 PROJECT SELECTION PROCESS ................................................................................................................ 25 10.2 DESCRIPTION AND USE OF PROJECT LISTS .............................................................................................. 25 AND
3 Attachment I
Attachment II
-
Attachment III
Attachment IV
Attachment V
Attachment VI
Attachment VII
Appendix 1
-
Project Priority Ranking System
Anticipated Intended Use Plan Schedule for the October 1, 2011 –
September 30, 2012 Funding Period
Financing Fees and Financing Options
Drinking Water State Revolving Fund Pre-application Form
Drinking Water State Revolving Fund Application Checklist
Output and Outcome Measures
Response to Comments on the Draft IUP
Summary of Project List Changes
Acknowledgements:
The development of this Intended Use Plan was made possible through the dedicated effort of the New York State
Department of Health’s Bureau of Water Supply Protection Design Section with special acknowledgements to:
Michael Montysko, PE, Design Section Chief
Christopher Auer, PE, Western Area Team Leader
William Gilday, PE, Southern Area Team Leader
Stephen Marshall, PE, Northern Area Team Leader
David Phillips, PE, Eastern Area Team Leader
ii
1.0
Introduction
The Drinking Water State Revolving Fund (DWSRF) was created in 1996 as a result of New
York State’s enactment of Chapter 413 of the Laws of 1996 (Clean Water/Clean Air Bond Act,
“Bond Act”) and passage of the 1996 Amendments to the Safe Drinking Water Act (Public Law
104-182) by the U.S. Congress. The DWSRF provides a financial incentive for municipally and
privately owned public water systems to undertake needed drinking water infrastructure
improvements (e.g., treatment plants, distribution mains, storage facilities). This program
provides market rate and below market rate financing for the construction of certain eligible
public water system projects. As financings are repaid, money is made available for new
financings - a true revolving fund. For communities with demonstrated financial hardship,
interest rates can be reduced to zero percent. In this federal fiscal year, the State expects to
receive additional federal grants to capitalize the DWSRF. Monies from the Bond Act will be
used to provide federally mandated state matching funds of at least 20%. The program is
administered jointly by the New York State Department of Health (DOH) and the New York
State Environmental Facilities Corporation (EFC).
This Intended Use Plan (IUP) includes:
1. an anticipated financing schedule which covers the period from October 1, 2011 to
September 30, 2012;
2. a description of the goals of the DWSRF program;
3. specifics on how New York State proposes to use available DWSRF funds during federal
fiscal year (FFY) 2012;
4. criteria for selecting projects to receive financial assistance;
5. criteria for determining which communities qualify as disadvantaged communities;
6. an estimate of anticipated funds available for subsidized financial assistance;
7. a procedure to amend this IUP;
8. a description of capacity assessment;
9. a description of the project selection process;
10. criteria for determining equivalency projects;
11. a Project Readiness List which includes eligible projects expected to be ready for shortterm or long-term financing during this IUP period;
12. a Category A List which includes eligible projects of systems serving less than 10,000
people;
13. a Multi-Year List of projects eligible to receive DWSRF financing;
14. a Category C (hardship) List of projects which have received written confirmation that
they qualify for financial hardship;
15. the project scoring and ranking system;
1
16. a description of the fees associated with DWSRF financing; and
17. a copy of the DWSRF pre-application form and application checklist.
18. Output and Outcome measures
19. Summary of Project List Changes between the draft and final IUP
This IUP is based on the use of FFY 2012 federal Capitalization Grant monies and unobligated
funds carried forward from the previous IUP. The anticipated financing schedule for this IUP
period is found in Attachment II.
Under the anticipated financing schedule, leveraged financing funded from bond issues will be
determined. Direct long-term and short-term financings will be originated throughout the year.
2.0
Program Initiatives and Changes
Ongoing Initiative: The DOH and the EFC encourage communities that apply for financing in
this and future IUP periods to prepare and submit an asset management plan to accompany the
engineering report and/or plans and specifications for their project. An asset management plan
would support communities by encouraging the building of sustainable infrastructure. The DOH
reserves the right to require an asset management plan for any project that has shown
deficiencies with respect to Managerial, Technical, and Financial capacity.
Ongoing Initiative: New York State encourages the efficient use of energy in all drinking water
projects. In addition, the US EPA requires that for FFY 2012 a minimum of 20% of the federal
capitalization grant be used for “green” projects. Therefore, the DOH and the EFC are requiring
that all engineering reports and/or plans and specifications submitted to the DOH identify project
components that incorporate green infrastructure, energy efficiency, water efficiency, and/or
other environmentally innovative activity.
Program Change: State Smart Growth Public Infrastructure Policy Act- On August 30,
2010 the New York State Environmental Conservation Law was amended to add the State
Smart Growth Public Infrastructure Policy Act. This law requires that starting September 27th,
2010, any new or expanded public infrastructure project receiving financing from a state
infrastructure agency must be consistent with the relevant smart growth public infrastructure
criteria as they are defined in the law to the extent practicable. DOH will now require, as a part
of the engineers report and/or through other DWSRF application materials that may be
developed, an analysis of each project with respect to its compliance with the criteria of the
smart growth law. Projects that received short term financing or other phased financing prior to
the enactment of the law are exempt.
The Smart Growth Public Infrastructure Policy Act can be viewed at:
http://public.leginfo.state.ny.us/MENUGETF.cgi?COMMONQUERY=LAWS+&TARGET=VIEW
Once there, click on ENV and then click on Article 6
Program Change: Interconnections- Under provisions of the 1996 Amendments to the
Federal Safe Drinking Water Act, DOH is required to ensure that all systems receiving DWSRF
assistance have adequate managerial, technical, and financial capabilities to provide safe
drinking water. The failure to meet this requirement could result in a significant reduction of the
DWSRF federal capitalization grant. Therefore, systems that lack adequate managerial,
technical, and financial capacity may be determined as ineligible by DOH to receive DWSRF
2
assistance unless the project to be financed corrects the managerial, technical, and financial
deficiencies.
DOH will continue to promote the regionalization and interconnections for public water systems
in an effort to enhance managerial, technical, and financial capacity for those systems.
Therefore, when the possibility to interconnect to another public water system exists for a
project seeking assistance, and if that interconnection will address the scope of the project with
respect to its priority health ranking, the interconnection must be a carefully considered
alternative as a part of the State Environmental Quality Review Act process and also be
discussed in detail in the engineering report. If the system applying for DWSRF assistance
decides not to pursue a possible interconnection alternative when it exists and would address
the scope of the project with respect to its priority health ranking, then detailed justification
satisfactory to DOH must be provided demonstrating that the interconnection is a technically,
financially, or managerially disadvantageous option. See Section 8 of this IUP for additional
information regarding capacity requirements.
Program Change: Short-Term Market Rate Financing - In Section 4.6, the conditions under
which Short-Term Market Rate Financing (SMRF) is available is more fully described.
Program Change: Phased Points- DOH will no longer typically assign phased points for any
pre-application received if the prior related portion of the project closed on long term financing
more than five years earlier and the improvements already funded are operational. However,
DOH reserves the right to assign phased points for projects that require additional financing,
regardless of time frames, to address the more serious original public health priorities for which
the project received its score.
Program Change: Minority and Women Business Enterprise/Equal Employment
Opportunity (MWBE/EEO) - DOH will be working with EFC in making significant revisions to
the MWBE/EEO program to reflect statutory changes and to streamline current procedures.
EFC will be strengthening the Disadvantaged Business Enterprise (DBE) requirements in the
revised MWBE/EEO program to offer a seamless solution for our clients to meet both the state
MWBE and Federal DBE requirements. The proposed MWBE/EEO Program changes are
expected to be implemented commencing in FFY 2012. Some of the more significant Program
changes include:
• Professionals services, such as engineering, legal, and financial advisory services, are
now subject to MWBE participation requirements;
• There are new recordkeeping and reporting requirements;
• Information concerning the makeup of the project workforce will be required to be
submitted quarterly; and
• All contracts and agreements that are paid for with DWSRF funds will be required to
contain certain contractual provisions.
Program Change: Davis-Bacon Compliance-As part of the FFY 2011 budget appropriation for
the DWSRF, Congress mandated that federal labor laws regarding prevailing wages, hours of
work, and rates of pay shall apply to construction carried out in whole or in part with assistance
from the DWSRF. These requirements are collectively known as the Davis-Bacon laws. These
requirements are in addition to the requirements of NYS prevailing wage laws.
EPA guidance requires that any DWSRF financings comply with the Davis-Bacon laws and
incorporate these provisions into any project work that has been or will be contracted. Work
done by a municipal applicant’s employees, generally known as “force account” or “work force”,
is not generally subject to Davis-Bacon requirements. For more information on Davis-Bacon
laws, please visit EFC’s website.
3
The President’s budget request for FFY 2012 includes compliance with Davis-Bacon
requirements as part of the DWSRF appropriation. Compliance with Davis-Bacon requirements
for FFY 2012 will not be known until the final budget for FFY 2012 has been enacted.
3.0
Short- and Long-Term Goals
The Safe Drinking Water Act (SDWA) Amendments of 1996 authorize a DWSRF to assist public
water systems with financing the costs of infrastructure needed to achieve or maintain
compliance with SDWA requirements and to protect public health. The DWSRF program will
help ensure that New York State’s drinking water supplies remain safe and affordable, and that
drinking water systems that receive funding will be properly operated and maintained.
3.1
Short-Term Goals
•
Continue to implement the DWSRF program for the State of New York.
•
Receive project pre-applications, score and rank projects based on human health risk
and compliance with the SDWA.
•
Make available short-term financing to help accelerate project development.
•
Make available long-term financing for projects in priority order, taking into account
project affordability.
•
Make available financing and/or financial assistance payments (grants) to help small
public water systems and disadvantaged communities finance needed projects.
•
Make available emergency financing to allow for emergency repairs when no other
funding source is available to the eligible public water system.
3.2
Long-Term Goals
•
Help public water supplies achieve and maintain compliance with federal and state
drinking water standards and enforceable requirements of the SDWA and the New York
State Sanitary Code.
•
Protect and enhance New York’s public drinking water supplies using the financial
incentives provided by the DWSRF and the programs that the DWSRF supports.
•
Administer the DWSRF in a fiscally responsible manner that will ensure its revolving
nature in perpetuity.
•
Assist public water supplies to improve drinking water quality, quantity and dependability
by providing reduced interest rate long-term financing and/or Additional Financing
Subsidies (Grants).
4
4.0
Financial Status
4.1
Total DWSRF Monies
Capitalization for the New York DWSRF program during this IUP funding period will be provided
from the FFY 2012 federal Capitalization Grant and unobligated funds carried forward from the
previous IUP (October 1, 2010 - September 30, 2011). New York State has not yet received a
FFY 2012 DWSRF Capitalization Grant and the Final IUPmay be amended at a future dateto
reflect a different amount depending on negotiations and finalization of the federal budget. The
minimum state match requirement is 20% of each federal award. The minimum state match
requirement is made from Bond Act funds that were provided in excess of the 20% minimum
amount required under the federal SDWA and that have been credited (banked) against future
state match. The 100% state match requirement for the state program management set-aside
will be met with in-kind services. The proposed sources and uses of the DWSRF for this IUP
are presented in Table 1. Total available DWSRF program resources to finance drinking water
projects are $435,924,679 for this IUP period.
Table 1
Proposed Sources and Uses
And Estimated Amount of DWSRF Funds for FFY 2012
Sources
Amount
FFY 2012 Capitalization Grant
Carry-over monies from FFY 2011
Repayments and Interest Earnings
Total Sources
Uses
Amount
Administrative Set-Aside
Technical Assistance Set-Aside
State Program Management Set-Aside
Total Set-Asides
Direct Financing
Grants Expected to Close
Grant Funds Reserved
Grant Funds Available
Reserve Allocation for Leveraged Financing
Total Uses
$52,564,9371
$129,000,000
$49,000,000
$230,564,937
$2,102,597
$1,051,299
$5,256,494
$8,410,3902
$74,000,000
$12,000,000
$9,000,000
$15,769,481
$111,385,0663
$230,564,937
1
This amount is based on an estimated national DWSRF allocation of $829 million for federal fiscal year 2012;
however, this amount has not yet been appropriated.
2
Refer to Section 6.0 for a detailed description of each set-aside.
3
Leveraged three times, these funds will provide financing of $334,155,198 worth of eligible projects. Combined
with Direct Financing, Grants Expected to Close, and Grants the total subsidized financing capacity for this IUP
period is approximately $435,924,679.
4.2
Fees
Up to 4% of the total amount of federal Capitalization Grants (as provided by Section 1452(g)(2)
of the SDWA) can be set-aside to support the cost of administering the DWSRF program.
Costs of DWSRF program administration not covered by the 4% administrative set-aside must
be paid from fees charged to DWSRF recipients. A program administration fee of 1.1% of the
project costs plus an annual fee of 0.11% of the outstanding principal balance of the financing
will be assessed to support the administration of the DWSRF program. The 1.1% program
administration fee may be included as part of the financing. For non-hardship projects that
5
receive short-term financing, an administrative fee equal to 0.6% will be charged and may be
included as part of the short-term financing. A description of the fees is presented in
Attachment III. Fees collected by the DWSRF are held in an account outside of the DWSRF.
For the state fiscal year (SFY) 2011 (4/1/10 to 3/31/11), the DWSRF has recognized and
expects to collect $362,607 in program administration fees and $1,404,042 in annual fees. It is
anticipated that in SFY 2012 a similar amount of fees will be recognized and collected.
4.3
Transfer of Funds
The SDWA Amendments of 1996 offered states the flexibility to meet the funding needs for
drinking water and wastewater facilities by transferring funds from one SRF program to the
other (Section 302 of Public Law 104-182). An amount equal to up to 33 percent of the DWSRF
Capitalization Grant could be transferred from the DWSRF to the CWSRF program, or an
equivalent amount from the CWSRF to the DWSRF program. While the authority expired on
September 30, 2001, Congress extended this provision within EPA’s annual budgets. Transfers
from the CWSRF to the DWSRF were made for FFY 1997 through 2001, totaling $82,443,933.
Pending Congressional approval of an extension within EPA’s proposed budget, transfers
between the CWSRF and the DWSRF programs during current and future IUP periods may be
made. Any funds transferred during this IUP period will be returned using program funds within
this IUP period. Therefore, there will be no effect on the funding line of either the DWSRF
program or the CWSRF program.
4.4
Eligible Systems and Types of Projects to be Funded
Drinking water systems that are eligible for project funding are community water systems, both
public and privately owned, and non-profit, non-community water systems (when funding is
provided, a “recipient”).
“Drinking water infrastructure project” or “water supply project” means the planning, design,
construction, improvement, or acquisition of facilities, equipment, sites, or buildings for the
supply, control, treatment, distribution, and transport of drinking water and the testing and
monitoring to ensure the integrity and quality of such water intended to improve drinking water
facilities including achievement of compliance with the federal SDWA or other applicable federal
law and state drinking water quality goals and standards.
Projects eligible for DWSRF financing include investments to upgrade or replace infrastructure,
address exceedances of federal or state health standards, prevent future violations of such
standards, and provide the public with safe drinking water. Examples of such projects include
but are not limited to:
•
rehabilitation or development of new drinking water sources to replace contaminated
supplies;
•
installation or upgrading of facilities if the project will improve the quality of drinking water to
comply with primary or secondary standards or treatment/performance criteria;
•
installation or upgrading of storage facilities, including finished water reservoirs, to prevent
microbiological contamination or to provide adequate delivery pressures;
•
installation or replacement of transmission and distribution mains to prevent contamination
caused by leaks or breaks;
•
funding and/or construction to promote the consolidation of water supply services,
particularly in circumstances where individual homes or water systems generally have an
6
inadequate quantity of water, the water supply is contaminated, or the system is unable to
maintain adequate compliance for financial or managerial reasons;
•
the purchase of a portion of another system’s capacity, if the purchase is part of a
consolidation plan to bring the system(s) into compliance;
•
capital investments made to improve the security of drinking water systems; and
•
any of the above listed project types which are publicly owned and which were previously
financed subsequent to July 1, 1993, may be eligible for refinancing. Planning, design and
other pre-construction costs incurred prior to July 1, 1993, may be allowed if related to an
otherwise eligible project.
Projects submitted by systems that lack technical, managerial or financial capacity or that are
significant non-compliers are not eligible for funding unless the proposed project will ensure
capacity or compliance.
Also, projects whose primary purpose is fire protection or
growth/development, dams and reservoirs, or acquisition of land not integral to an eligible
project are not eligible.
The EPA issued a notice in the Federal Register (63FR 59299, November 3, 1998) which allows
States to provide DWSRF assistance to projects that solve public health problems for residents
currently served by contaminated sources. This policy allows for the creation of a community
water system (publicly or privately owned) to address an existing public health problem caused
by unsafe drinking water provided by individual wells or surface water sources. This policy also
extends to a situation where a new regional public water system is created by consolidating
several existing public water systems that have technical, financial or managerial difficulties.
Under this policy, a proposed project may only receive DWSRF assistance if the following
conditions are met:
1. upon completion of the project, the entity responsible for the DWSRF financing meets the
definition of a Federal community public water system;
2. the project is on the Project Readiness List and addresses an actual public health problem
with serious risks;
3. the project is limited in scope to the specific geographic area affected by contamination;
4. the project is only sized to accommodate a reasonable amount of growth expected over the
life of the facility (growth cannot be a substantial portion of the project);
5. the applicant demonstrates that sufficient public notice to potentially affected parties was
provided and alternative solutions to addressing the problem were considered; and
6. the project is a cost-effective solution to solving the public health problem.
4.5
Financial Planning Process
Projects submitted for financing will be screened for eligibility, scored, ranked and listed.
Projects can be submitted to the DOH for listing at any time. All eligible projects for which preapplication forms were submitted on or before September 3, 2011 are included in the final IUP.
Eligible projects for which pre-application forms are submitted after September 3, 2011 will be
included in the next IUP (October 1, 2012 – September 30, 2013). Projects for which an
engineering report or plans and specifications were submitted to the DOH or which completed
7
construction by September 3, 2011 are listed on the Project Readiness List. Scheduled
closings for leveraged financing during this IUP period will be determined. Direct long-term and
short-term financings will be originated throughout the year.
4.6
Types of Assistance and Terms
The DWSRF program will offer the following types of financial assistance:
1. Short-Term Financing Program (STFP) – Short-term financing will be offered interest free
and at market rate for terms of up to three (3) years. Before any short-term financing is
provided, an applicant must, among other conditions, receive approval of an engineering
report for the project, complete the State Environmental Review Process (SERP), obtain
approval from the Office of the State Comptroller for any necessary district formation, and
adopt a bond resolution for the project.
•
Short-Term Interest Free Financing (STIFF) - The STIFF program provides short-term
financing to recipients that are developing projects eligible for long-term DWSRF
financing. STIFF is available for projects that are eligible to be funded from the current
Project Readiness List and have not completed construction. The amount available is
limited to one-third of the estimated total project costs as set forth on the Project
Readiness List. Recipients that qualify for hardship assistance are not subject to the
one-third project cost limitation. STIFF is not available to pre-finance any awarded
grants.
•
Short-Term Market Rate Financing (SMRF) – For projects with scores too low to be
eligible for long-term DWSRF financing or projects eligible for STIFF but with financing
needs in excess of the one-third project cost limitation referenced above, short-term
financing may be made available at EFC's short-term cost of funds (market rate). SMRF
may be used to pre-finance third party grants. EFC and DOH encourage applicants to
inquire about SMRF availability as we believe this financial assistance is generally less
expensive and more convenient than traditional bond anticipation note financing.
Funds for SMRF are derived internally, from EFC's short-term financing sources or externally,
through the issuance by EFC of long-term bonds or short-term notes (commercial paper). EFC
expects that its commercial paper program will obtain high short-term credit ratings and pass
through low borrowing costs. EFC tracks the availability of its internal short-term financing
sources by projecting its cash flow month to month over the course of the FFY. For FFY 2012,
EFC and DOH project $75 million to be available for DWSRF SMRF from these internal
sources. Upon reaching this threshold amount of SMRF transactions, DOH and EFC will, if
prudent, revise the threshold or EFC will pursue external funding sources as described above.
In the event EFC determines to pursue external funding sources, applicants may experience
delays in SMRF funding until proceeds of external funding are received by EFC. DOH and EFC
intend to make SMRF available to as many applicants as possible. However, DOH and EFC
have determined that additional considerations may need to be given to the process of SMRF
allocation. Therefore, depending on the number of applications received and the total dollar
amounts associated with them, the following priorities which are in order of public health benefit
may be applied, if necessary, to DWSRF SMRF availability:
1. Projects on the Readiness List with scores above the subsidy funding line requiring
short-term financing in excess of the amount available under the Short Term Interest
Free Financing (STIFF) Program. This can include financings beyond the STIFF for
readiness list projects and pre-financing of third-party grants.
8
2. Projects on the Readiness List that require “interim” financing prior to the next scheduled
pooled financing. These financings typically occur for projects with STIFF that matured
prior to the leveraged financing pool or projects that require additional funds prior to the
leveraged financing pool.
3. Projects on the Readiness List below the Subsidy Line and not reachable for subsidy via
bypass between the Subsidy Line down through 45 points. DOH and EFC, may elect not
to process applications for SMRF for projects with priority health ranking scores of 40
points or lower.
2. Leveraged Financing - Leveraged Financings are DWSRF financings funded from bond
proceeds. Certain bond series issued to fund DWSRF financing will be secured by federal
and state match dollars deposited to and held in program financing indentures. Leveraged
Financings will be at market rate or receive an interest subsidy either from earnings received
from a dedicated reserve allocation equal to one-third of the financing amount or from other
program assets. Certain hardship communities may receive an interest subsidy of more than
one-third of the financing amount. Other program assets or investment earnings from the
reserve allocation will provide a 33 1/3% interest subsidy, based on the market rate of the
related EFC bonds, to certain recipients, thereby resulting in a subsidized interest rate on
the financing. In instances where the project qualifies for a hardship financing, the interest
subsidy may reduce the net interest rate to zero percent. The performance of investments
held in the financing indenture or the general accounts of the program will not impact the net
interest rate on leveraged recipient financings.
3. Regular Reduced Rate Direct Financing - Regular Reduced Rate Direct Financing will be
made available to recipients not eligible for Leveraged Financing. Direct Financing
recipients are determined by EFC and may include non-investment grade borrowers or small
financing requests.
4. Hardship Financing – Direct or Hardship Financing will be made available to qualified
recipients at rates below the regular reduced interest rate. Certain hardship eligible
recipients may receive leveraged financing. If qualified, Hardship Financing may also be
issued for 30 years. A description of the DWSRF Disadvantaged Community Program is
provided in Section 7.0.
5. Additional Financial Assistance (Grants) - Grants may be made available to eligible
recipients if a Direct or Hardship interest free financing does not provide sufficient funding to
lower the Projected Service Charge to the Target Service Charge (TSC). A description of
the DWSRF Disadvantaged Community Program is provided in Section 7.0.
6. Emergency Financing - The emergency financing program allows for the immediate
financing of emergency situations as defined in Attachment I of this IUP, at eligible public
water systems. This funding is only available to water supply systems for emergency
repairs when no other funding source is available to the system. The determination of when
an emergency exists would be made by the DOH. Imminent threats to public health would
include situations that result in the unavailability of a source of potable water for an
extended period of time. Projects that are designed to address such emergency situations
will receive the highest priority ranking and will be added to the Project Readiness List.
These projects would receive the first priority for any funds that are by-passed in
accordance with by-pass procedures authorized in Section 10.2 of this IUP.
7. SRF Bond Market Rate Program - The SRF Bond Market Rate Program provides eligible
financing recipients with project scores below the subsidy funding line on the Project
Readiness List access to the public market at preferred market rates. Projects funded with
9
market rate obligations will be retained, in subsequent years, on the Project Readiness List
of the IUP until such time that they may qualify for subsidy assistance in future years. For
projects with scores that later rise above the subsidy funding line (including through bypass), subsidy assistance will become available at the then target rate for the remaining
term of the recipient financing. For projects that qualify for subsidy assistance, a bond
guarantee may be available to extend repayment terms beyond the previous DWSRF limit
of 20 years from project completion. For recipients opting for longer repayment terms,
subsidy assistance will be limited to that which would have been available had the financing
been structured with such 20 year repayment terms. Subsidy assistance will be made
available, at the target level, on the total financed amount of the project. Consistent with
project useful life, bonds with maturities that exceed 20 years from the project completion
date will be supported solely by SRF guarantee and will carry no subsidy.
8. SRF Bond Guarantee Program - The SRF will provide a bond guarantee for bonds issued
by eligible recipients. The Bond Guarantee Program is available to support eligible projects
for which DWSRF subsidized financing is not available. Bonds issued by recipients and
guaranteed by the DWSRF may be issued for terms of up to thirty years.
4.7
Program Financial Terms
1. Short-Term Financing - Communities will borrow through the STFP by issuing municipal
Bond Anticipation Notes (“BANs”) to the EFC. The EFC will provide funding in the amount
of the BANS on an interest-free or EFC market rate basis. Upon maturity, the BANs may be
retired with long term DWSRF financing, the issuance of long term debt obligations by the
community, or other funding. Applicants other than municipalities will borrow through the
STFP by issuing a promissory note to EFC secured by a letter of credit if not PSC regulated.
Only DWSRF market rate short-term funds will be available to pre-finance any awarded
grants.
2. Leveraged Financing - The financing terms, including the payment of principal and interest,
are based on the terms of the EFC’s bonds, proceeds of which fund the Leveraged
Financing. Principal amortization will be required to commence the earlier of a) within one
year of the project completion or b) no later than two years after closing the financing
(consistent with New York State Local Finance Law). Principal amortization cannot exceed
20 years from the project completion date or the Period of Probable Usefulness, whichever
is sooner. The interest subsidy is provided either from other program assets or interest
earnings on the investment of the reserve allocation. Reserve investments will be limited to
U.S. Treasury securities, U.S. Government guaranteed securities, securities of Government
Service Enterprises (GSE) such as the Federal National Mortgage Association and the
Federal Home Loan Mortgage Corporation, GSE guaranteed securities, investment
agreements collateralized by U.S. Treasury securities, U.S. Government guaranteed
securities, GSE securities, and GSE guaranteed securities and entered into with banks,
broker dealers or insurance companies rated in one of the two highest rating categories by
each nationally recognized rating service that rates their obligations, and state obligations,
state guaranteed securities or other qualified obligations rated in one of the two highest
rating categories by each nationally recognized rating service that rates the bonds. The
Effective Market Rate for leveraged financing made from New York’s DWSRF in 2011 C
financing is 4.09%. The Effective Interest Cost (EIC) for recipient financings based on this
transaction is approximately 2.73% (1/3 subsidy).
3. Regular Reduced Rate Direct Financing – Terms governing principal amortization are the
same as those applicable to Leveraged Financing. Interest payable on the financing will be
set at two-thirds of the interest rate, as determined by the most recent issuance of DWSRF
bonds issued to provide financing to eligible recipients.
10
4. Hardship Financing - For eligible projects the terms governing principal amortization shall be
as long as 30 years from the project completion date or the Period of Probable Usefulness,
whichever is sooner. Any interest payable on Hardship Financing will be set at less than
two-thirds of the interest rate, as determined by the most recent DWSRF financing; rates
may be as low as zero. The actual rate will be determined based on the affordability criteria
(refer to Section 7.0).
5. Additional Financial Assistance (Grants) - Grants will be provided to qualified recipients to
lower the Projected Service Charge to the Target Service Charge. If determined to be
eligible, projects will be ranked according to project priority ranking system score. Projects
with the highest scores will receive confirmation letters for hardship assistance until the
available funding is fully committed (see Section 7.0). To be considered for hardship
assistance, eligible projects must have had a total numerical score greater than (or equal to)
that of the project with the lowest score (excluding bonus points) eligible to be funded from
the Project Readiness List for the October 1, 2011 to September 30, 2012 funding period.
6. Emergency Financing - Emergency financing would be issued as regular reduced rate direct
financing. Interest payable on the financing would be set at two-thirds of the interest rate, as
determined by the most recent issuance of DWSRF bonds for eligible recipient projects.
However, before an emergency financing can be issued the recipient must demonstrate
credit worthiness and fiscal viability in accordance with EFC criteria. Privately owned water
systems regulated by the Public Service Commission would be permitted to apply for
funding only if the Public Service Commission has issued an order allowing the water
system to surcharge its customers to repay the financing.
7. SRF Bond Market Rate Program - Bonds issued by eligible recipients and guaranteed by
the EFC will be purchased by the EFC from proceeds of DWSRF bonds publicly issued by
the EFC to investors. All avenues of recourse currently available to the EFC will apply with
respect to recipient bonds guaranteed by the EFC, including its statutory right to intercept
any state aid annually appropriated by the state to the recipient.
8. SRF Bond Guarantee Program - The SRF will provide a bond guarantee for bonds issued
by eligible recipients. The Bond Guarantee Program is available to support eligible projects
for which DWSRF subsidized financing is not available. Bonds issued by recipients and
guaranteed by the DWSRF may be issued for terms of up to thirty years.
4.8 Fund Management and Long-Term Effects of Funding Decisions – Leveraging
A tremendous need exists for financial assistance for eligible drinking water projects in New
York State. The EPA’s Drinking Water Infrastructure Needs Survey and Assessment – Fourth
Report to Congress dated February 2009 estimated that more than $27.1 billion will be needed
in New York State over the next twenty years to ensure continued delivery of safe public
drinking water. Pre-applications received by the DOH indicate an aggregate need of
approximately $6.4 billion over the next several years. Anticipated project financing needs for
this IUP, ending September 30, 2012, is about $3.8 billion. Based on a comparison of available
resources and anticipated financing needs, New York State plans to leverage the available
DWSRF capital by a factor of three to one. Therefore, with $111,385,066 of capital available for
Leveraged Financing, the total Leveraged Financing capacity for the period of this IUP is
$334,155,198. When combined with Direct Financing, Grants, and Grants expected to close,
the total DWSRF program assistance available during this IUP period is approximately
$435,924,679.
11
All DWSRF financings are made in a fiscally responsible manner that will ensure the revolving
nature of the program in perpetuity. In addition, the fiscal aspects of the program are regularly
evaluated to ensure optimum use of DWSRF resources. Further, the long-term effect of
leveraging the DWSRF three to one will be to extend the reach of financial assistance benefits
to more New York State water systems than could be served if leveraging were set at a lower
level.
5.0
Amending the IUP
This IUP may be amended to reflect changes in specific areas (e.g., increased project costs).
Draft amendment notices will be published in the Environmental Notice Bulletin (ENB). At the
end of the comment period, responses to all significant comments will be made available and
the final amendment notice will be published in the ENB.
6.0
Set-Aside Activities
Section 1452 of the SDWA authorizes states to use a portion of the federal Capitalization Grant
(set-asides) to support various drinking water programs. Section 1452 allows as much as 31%
of a state’s federal Capitalization Grant to be used for administrative activities, technical
assistance activities, state program management activities, and special activities. New York
State proposes to use 16% ($8,410,390) of the $52,564,937 FFY 2012 Capitalization Grant for
set-aside purposes. Table 2 specifies set-aside allocations and is presented at the end of this
section. The State intends to maximize the use of Capitalization Grant monies for water supply
projects. Therefore, only those funds considered essential for DWSRF and water supply
program support have been allocated to set-aside activities. Also, any unused set-aside monies
can be transferred to the project fund after receiving an approved amendment to the
Capitalization Grant. The intended use of funds and expected accomplishments for each setaside are described below.
Descriptions of how the FFY 2012 set-aside monies will be budgeted will be included in the
federal Capitalization Grant Application Set-Aside Work Plans. The State plans to bank some
set-aside funds for use in future IUP funding periods.
6.1
Administrative
The SDWA authorizes states to use up to 4% of the total annual federal Capitalization Grant (as
provided in Section 130 of the SDWA Amendments of 1996) to support the cost of administering
the DWSRF program. The State plans to use 4% of the total annual federal Capitalization
Grant for administrative activities.
Administrative tasks include, but are not limited to: developing and finalizing the Capitalization
Grant application package to secure federal funds; implementing the Operating Agreement (OA)
between the DOH and the EPA; performing technical project reviews and ranking project
proposals in priority order; preparing an IUP which identifies available funding resources and
expenditures and establishes current year and multi-year project priority lists; implementing a
State Environmental Review Process; reviewing and approving engineering reports,
construction plans and specifications; conducting project inspections; evaluating and
determining specific project affordability (hardship); conducting public participation efforts;
conducting database management activities; establishing DWSRF accounts; directing the
investment of DWSRF funds; preparing project financing agreements (including cost summaries
and project financing schedules); preparing necessary financial documents; issuing Corporation
Bonds and originating financing; establishing annual reserve allocations; establishing
disbursement schedules; processing disbursement requests and conducting associated
12
document reviews; collecting and managing repayments; establishing and collecting DWSRF
fees; insuring program and fiscal audits are conducted; and preparing technical and financial
reports to meet federal and state mandates.
6.2
Technical Assistance
Section 1452(g)(2)(D) of the SDWA authorizes states to use up to 2% of the total annual federal
Capitalization Grant to provide technical assistance to small water systems (those with
populations of 10,000 or fewer). This technical assistance may include assistance to potential
DWSRF applicants complying with federal and state drinking water regulations. The State plans
to use 2% of the total annual federal Capitalization Grant to continue to fund the enhancement
of the State’s existing Small Water Systems and Comprehensive Performance Evaluation
Programs and provide for direct technical assistance to small water systems.
6.2.1 Small Water Systems
The DOH has an existing technical assistance program for small water systems. This program
has helped numerous communities improve their drinking water systems while saving money
using self-help techniques. The DOH’s Small Systems Program provides guidance to
communities in considering project alternatives, calculating alternative project costs, preparing
budgets for selected projects and reviewing existing operation and maintenance practices.
Additionally, the program assists communities to develop criteria for consultant selection,
determine project priorities, and select the most sensible project, use inexpensive labor and
materials, improve purchasing practices, use volunteers, avoid duplication of services and
conduct technical assessments to determine the overall needs of the community. These
assessments will be useful to the small water systems in helping them improve their overall
capacity. This program provides statewide coverage and the DOH will:
•
participate in meetings with the public and individual systems to explain the Small Systems
Program and its advantages to local communities;
•
encourage small water systems to consider collaborative or regional approaches to water
supply services, such as consolidating, forming partnerships, and initiating contract
operation and maintenance agreements;
•
oversee the contract to provide on-site “circuit rider” training and other direct technical
assistance to mobile home parks and other small community and nontransient
noncommunity public water systems not currently served by such a program;
•
implement a number of small system projects, focusing primarily on communities applying
for DWSRF financing; and
•
oversee the regional capacity for providing direct assistance to DWSRF communities and to
provide for training and support of local health unit staff.
13
6.2.2 Comprehensive Performance Evaluation Program
The Comprehensive Performance Evaluation (CPE) Program has resulted in detailed
assessments of 142 water filtration plants since November 1994. Although most of these plants
are able to meet the current Filtration Performance Criteria and Maximum Contaminant Levels
(MCLs), the structural, operational and administrative deficiencies noted in the evaluations will
make it difficult for many of these systems to comply with future regulations without
considerable capital improvements. There are approximately 270 filtration plants in New York
State.
The primary CPE program goal is to review and evaluate the capabilities of existing treatment
facilities to determine if they are meeting current standards and performance goals. A
secondary, but equally important goal is to develop a program, based upon the evaluation, for
the optimization of each facility to assure compliance with current and future standards and
regulations.
The CPE program initiative includes:
•
conducting 2 – 3 CPEs per year, complete with a detailed evaluation report with prioritized
recommendations and follow-up meetings with the community to discuss the report, as
needed;
•
continuing to develop and issue comments and recommendations for initial remedial actions
to the community within 14 days after completion of field work, followed by the submission of
the completed evaluation within an average of 90 days after the completion of field work;
•
improving training of field staff responsible for follow-up by including them at CPEs, making
equipment available where needed and holding at least one workshop per year on
troubleshooting and plant evaluation techniques; and
•
conducting 3 – 5 mini performance evaluations per year, with follow-up letter reports, at
communities who had a full CPE and are implementing recommendations or experiencing
new difficulties, or to support communities who are having a specific critical problem.
6.3
State Program Management
The SDWA authorizes states to take up to 10% of the total annual federal Capitalization Grant
to support state program management activities. The State plans to use 10% of the total annual
federal Capitalization Grant to administer the Public Water System Supervision (PWSS)
program. States are required to match these set-asides on a one-for-one basis above and
beyond the 20% match required of all capitalization funds. This amount will be matched with inkind services associated with the State’s existing PWSS and Drinking Water Enhancement
Programs.
6.3.1 Administer the PWSS Program
The PWSS program enables the DOH to continue administration and oversight of the drinking
water program, ensuring consistency in the implementation of and compliance with the
requirements of the New York State Sanitary Code on a statewide basis. Additionally, the
PWSS program assures that public water systems are operated in a manner that ensures
adequate protection of their source water(s) and delivery of potable, aesthetically pleasing
drinking water.
To achieve these objectives during FFY 2012, the DOH will:
14
•
assure compliance with Part 5 of the State Sanitary Code;
•
coordinate with Wadsworth Center for Laboratories and Research (WCL&R) to assure that
State Laboratory capabilities are maintained;
•
provide technical assistance to public water systems in achieving compliance;
•
assure public health protection at public water systems using surface water sources;
•
assure public health protection by developing, adopting and implementing mandatory
federal drinking water regulations into the State Sanitary Code, including development and
submittal of primacy packages;
•
ensure that local health department water supply programs properly implement the program;
•
assure that water supply facilities are built in accordance with proper design criteria by
providing conceptual review and design approval of new construction and major
modifications to water supply systems;
•
continue to assess whether community groundwater systems may be under the influence of
surface water;
•
continue to implement the State’s Capacity Development Program including submitting the
Annual Capacity Development Report to the U.S. EPA by December 31st of each year;
•
continue to implement the Source Water Assessment and Protection Programs and Well
Head Protection Program;
•
continue to perform security inspections of public water systems;
•
assure potable water is provided during water supply emergencies;
•
assure staff are properly trained;
•
assure that water systems are operated by competent operators;
•
continue participation in Child Health Initiative by assisting EPA with collection and analysis
of lead samples from school drinking water outlets in cities around the state;
•
continue to track NYC avoidance compliance; and
•
ensure that all EPA reporting requirements under the grant are met and that EPA proposals
for regulations and policies are promptly commented upon as requested.
6.4
Special Activities
Section 1452(k) of the SDWA authorizes states to take up to 15% of the annual federal
Capitalization Grant for land acquisition, capacity development projects, wellhead protection,
and source water petitions. No more than 10% of the federal Capitalization Grant can be
allotted to any one of these special activities.
New York State is not proposing to take or use any of the allotted set-aside funds from the FFY
2012 DWSRF Capitalization Grant for the following programs.
15
1. Land Acquisition
Funds in the DWSRF can be used to purchase land integral to the construction of facilities, but
not for other purposes such as watershed protection. A separate set-aside of 10%, however,
may be used to establish a separate low-interest fund for land acquisition, particularly for
watershed protection. New York State is not proposing to create such a fund at this time.
There are a number of existing programs that can be used to purchase sensitive watershed
lands. These include the State’s 1986 Environmental Bond Act, the 1996 Clean Water/Clean
Air Bond Act, the New York City Watershed Agreement, the Clean Water State Revolving Fund,
as well as local, regional and private sources. The State will review the need to create
additional capacity for land acquisition as part of its source water assessments and delineation
efforts.
2. Capacity Development Projects
The State has proposed to use a portion of the allotted Program Management set-aside to
implement the statewide capacity development strategy. The DOH with input from the EFC, the
New York State Public Service Commission, the Office of State Comptroller, and other state
agencies will use the capacity development strategy to address non-viable public water supplies
in the State.
3. Wellhead Protection
The DEC developed New York’s Wellhead Protection Program (WHPP), which was approved
by the U.S. Environmental Protection Agency in 1990. The goal of the WHPP is to protect the
ground water sources and wellhead areas that supply public drinking water systems from
contamination. New York’s approach to wellhead protection recognizes and includes the
existing federal, state and county programs that protect groundwater, and compliments these
programs through a combination of activities and efforts using existing public and private
agencies and organizations at all levels. In New York, the WHPP has focused on assisting
municipal community water systems with an interest in developing protection plans for their
ground water supplies.
In October 1998, administration of New York’s WHPP was transferred from the DEC to the
DOH. The basis for the transfer of this program responsibility was due to the creation of the
Source Water Assessment Program (SWAP) under the 1996 SDWA Amendments and the need
to ensure efficiency and compatibility in the administration of these key water supply
management programs. The WHPP and the SWAP share several similar program elements
(e.g., delineation and contaminant inventory) for identifying areas of source water vulnerability to
contamination, and both programs provide a foundation for focusing source water protection
efforts at the local level.
The DOH submitted a Biennial Wellhead Protection Report to the EPA on November 15, 1999
for the October 1997 through September 1999 reporting period. This biennial report was
prepared in accordance with the reporting requirements and criteria outlined in the EPA
guidance provided to states and is consistent with previous New York State submittals on
progress reporting for the WHPP. The DOH submitted a Biennial Wellhead Protection Report,
using the 2001 Source Water Assessment and Protection Reporting Matrix, to the EPA on
November 9, 2001 for the October 1999 through September 2001 reporting period. Future
wellhead protection reporting will be prepared in accordance and be consistent with revised
EPA reporting requirements that are under development.
4. Source Water Petitions
16
As part of the SWAP, the State will assess a variety of options for improving source water
protection throughout the State. The source water petition program outlined in the SDWA is one
such option. It remains premature to develop a financing program to fund source water petition
partnerships at this time.
TABLE 2
DISTRIBUTION OF FFY 2012 SET-ASIDE FUNDS
Drinking Water State Revolving Fund
Set-Aside
SDWA FFY 2012 Maximum Allocation1 NYS FFY 2012
Administration
EFC (0.689740%)
DOH (3.310260%)
4%
$2,102,597
4%
$2,102,597
($362,561)
($1,740,036)
Technical Assistance
DOH
2%
$1,051,299
2%
$1,051,299
($1,051,299)
State Program Management
Administer PWSS Program
DOH
10%
$5,256,494
10%
$5,256,494
Special Activity Set-Asides2
15%
(10%)
(10%)
(10%)
(10%)
$7,884,741
($5,256,494)
($5,256,494)
($5,256,494)
($5,256,494)
0%
31%
$16,295,131
16%
Land Acquisition
Capacity Development
Wellhead Protection
SW Petition Programs
Total Set-Asides3
($5,256,494)
$8,410,390
1
Based on receiving Federal Capitalization Grant of $52,564,937.
2
No more than 10% for any individual component and a total of 15% under Special Activity Set-Asides.
3
The USEPA Safe Drinking Water Act allows for States to use up to 31% of the federal grant for set- asides, NYS intends on using
a total of 16%.
7.0
Disadvantaged Community Program and Hardship
7.1
Introduction
Chapter 413 of the Laws of 1996 (Clean Water/Clean Air Bond Act) provided $355,000,000 to
finance drinking water infrastructure projects in New York State. Of these monies, $90,000,000
was allocated to provide direct financial hardship assistance payments for projects in
disadvantaged communities. As of December 1998, the $90 million available for State
Assistance Payments (Grants) from the Bond Act was fully committed. Prior to FFY 2010, the
DOH and the EFC exercised the federal SDWA Hardship Provision that allowed states to utilize
up to 30% of their annual DWSRF Federal Capitalization Grant to provide Additional Financing
Subsidies (Grants) beyond the interest free financing rate to eligible disadvantaged communities.
In FFY 2010, it became a requirement to provide 30 percent of the Capitalization Grant in
Additional Financing Subsidies and that requirement is carried forward through FFY 2012. Table
3 reflects the cumulative amount of federal grant funds that were provided from the cumulative
federal Capitalization Grants received to date. $15,769,481 will be available to provide Grants to
eligible disadvantaged communities from the FFY 2012 Capitalization Grant.
Federal Fiscal Years
1998 - 2011
2012(Cap Grant pending)
1
2
Table 3
Available Hardship Grant Funds
Capitalization Grant Amounts
$650,629,6001
$52,564,937
Cumulative totals for FFYs 1998 – 2011 (not including ARRA).
Required to be provided for FFY 2012
17
Grants Provided
$186,392,367
$15,769,4812
Hardship applications, submitted by December 1, 2011, will be evaluated using the criteria
outlined herein and if determined to be eligible will be ranked according to project priority
ranking system score. Drinking water projects will be reviewed to determine eligibility for
funding and scored based on the established project priority ranking system (see Attachment I).
Communities whose drinking water projects are listed on the Project Readiness List or the MultiYear List with a total numerical IUP score greater than (or equal to) that of the project with the
lowest score (excluding bonus points) eligible to be funded will be evaluated for financial
hardship. Projects with the highest scores (excluding bonus points) will receive confirmation
letters for hardship assistance until the available hardship allotment plus any unexpended,
previously committed hardship funds are fully committed.
Hardship applications may be submitted after December 1, 2011 for evaluation of a financing
only (no grant) hardship assistance package during the current IUP period (October 1, 2011 September 30, 2012). Applicants that seek additional financial assistance (grants) as part of
their hardship assistance package and submit their hardship application after December 1, 2011
will have to re-apply during the annual call for projects for the next IUP period (October 1, 2012
– September 30, 2013) to be re-evaluated.
7.2
Financial Availability
As defined by § 1452(d)(3) of the SDWA, a disadvantaged community is one in which the public
water system service area meets established affordability criteria. Under the Disadvantaged
Community Program financial hardship assistance may include:
1. Reduced Interest Rate Financing - The rate on a financing can be reduced to as low as
interest free and/or the financing terms increased to as much as thirty years to bring the
Projected Service Charge (PSC) down to the Target Service Charge (TSC) level (see
Calculating Hardship); and
2. Grants Beyond an Interest Free Financing - If an interest free financing does not provide
sufficient funding to reach the TSC, Grants (up to $2 million or 75% of the eligible project
cost, whichever is less) may be used to make up the difference. An applicant may not be
awarded more than $2 million in grants in a particular funding period. Grants will not be
made available to systems with a Median Household Income (MHI) greater than the
statewide MHI of $43,393.
7.3
Eligibility for Financial Hardship Assistance
The following eligibility requirements apply to hardship applicants:
•
The project must be listed on the Project Readiness List or the Multi-Year List with a total
numerical IUP score greater than (or equal to) that of the project with the lowest score
(excluding bonus points) eligible to be funded from the current Project Readiness List.
•
Hardship assistance is available only for drinking water projects for which the notice to
proceed for construction was issued on or after April 1, 1997. Debt issued between July 1,
1993 and March 31, 1997 is eligible only for refinancing through regular subsidized interest
rate financing from the DWSRF program.
•
Only projects that have a total project cost less than $14,000,000 are eligible for hardship
assistance. Projects may not be segmented in order to qualify for hardship financial
assistance.
18
•
An applicant may not be awarded more than $2 million in grants in a particular funding
period.
•
Grants will not be made available to system service areas with a MHI greater than the
statewide MHI of $43,393. However, projects in such areas with a MHI up to 150% of the
current statewide MHI, or $65,090 will be eligible for reduced interest rate financing (to as
low as 0%) and/or extended up to thirty years to bring the PSC down to the TSC. Systems
with a service area MHI greater than $65,090 will not be eligible for hardship financing.
•
Only community water systems, systems that provide drinking water to residential
populations, such as municipal water systems and privately owned water supply companies
that are regulated by the Public Service Commission, are eligible for hardship assistance.
7.4
Calculating Hardship
A hardship determination is made based on the information provided in a completed financial
hardship application and a comparison of PSC and TSC for a typical household. The formula
that establishes the TSC is based on the applicant’s MHI, as indicated in the example and graph
that follow. The PSC is the projected annual service charge of the project per Equivalent
Dwelling Unit (EDU) including existing debt service, projected debt service, and project
operation and maintenance (O&M) costs.
The EDU concept relates all water system usage proportionately to that equivalent to a typical
single family residence. EDUs will be calculated for commercial, industrial and institutional
users based upon the water usage from flow data, number of employees, fixture units, or other
factors that equate usage to that of an equivalent number of residential users. The percentage
of total water use dedicated to institutional/industrial uses is taken into account in calculating the
amount of hardship a particular community will qualify for in grant assistance (see below).
The comparison of PSC to TSC is used to determine which public water systems are eligible for
financial assistance beyond the regular subsidized interest rate financing available through the
DWSRF. The additional benefits will assist economically disadvantaged water systems in the
construction of eligible drinking water projects.
The TSC is based on the service area’s MHI. In calculating the MHI for this IUP period, the
2000 U.S. Census data will be used. Under certain circumstances, an income survey for the
service area may also be considered (contact EFC for income survey guidance). The TSC
calculation and example follow:
TSC=(MHI/10,000)2x36-(MHI/10,000)x52+155
EXAMPLE:
MEDIAN HOUSEHOLD
INCOME ($)
15,000
20,000
25,000
30,000
35,000
40,000
45,000
50,000
55,000
60,000
65,000
TARGET SERVICE
CHARGE ($)
158
195
250
323
414
523
650
795
958
1,139
1,338
19
T A R G E T A N N U A L W A T E R S E R V IC E C H A R G E (T S C )
($ p e r E q u iv a le n t D w e lllin g U n it)
$ 1 ,5 0 0
$ 1 ,4 0 0
$ per Equivalent Dwelling Unit
$ 1 ,3 0 0
$ 1 ,2 0 0
$ 1 ,1 0 0
Q U A L IF IE S F O R H A R D S H IP A S S IS T A N C E
$ 1 ,0 0 0
$900
$800
$700
$600
$500
$400
Q U A L IF IE S F O R R E G U L A R S U B S ID IZ E D IN T E R E S T R A T E
$300
$200
$100
$0
$ 2 5 ,0 0 0
$ 3 0 ,0 0 0
$ 3 5 ,0 0 0
$ 4 0 ,0 0 0
$ 4 5 ,0 0 0
$ 5 0 ,0 0 0
$ 5 5 ,0 0 0
$ 6 0 ,0 0 0
$ 6 5 ,0 0 0
M e d ia n H o u s e h o ld In c o m e
The following factors may be considered including, without limitation, the relative number and
nature of residential, seasonal, commercial, industrial and institutional users when making the
determination regarding hardship assistance.
Once the initial hardship determination is made, a percentage of the calculated grant amount (if
any) equivalent to the percentage of industrial and institutional water use (if that use exceeds
25% of the total water consumption of the applicant service area) will be limited to an interest
free financing. Institutional refers to a facility with dormitory or similar accommodations for
overnight use.
The grant portion of hardship packages will not be provided if the difference between the
projected service charge, based on hardship assistance, and the projected service charge for
the project if financed through a financing only hardship package is calculated to be less than
5%.
7.5
Hardship Application Process
To be considered for financial hardship assistance, an applicant must request a Financial
Hardship Application from the DOH or the EFC and provide the following information when
completing the application:
•
existing population of the project service area;
•
number of EDUs to be served, including commercial, institutional and industrial users, and
the basis on which they were calculated;
•
existing annual debt for the system;
•
existing annual O&M costs;
•
estimated annual O&M costs based upon completion of the project;
•
annual financial reports, audited if available, for the last three years;
•
an analysis of project alternatives for cost effectiveness;
20
•
other revenue of the system (including charges to outside users),
•
estimated project costs; and
•
any other funding sources for the project, including detail on whether such funding is a grant
or a loan, and if a loan, its interest rate, term, and annual debt payment.
The hardship application is different than the DWSRF application. It is recommended that
applicants, meeting the aforementioned eligibility criteria obtain and submit a hardship
application directly to the DOH. Hardship applications submitted after December 1, 2011 will be
evaluated for a financial hardship assistance package (no grant) during the current IUP period.
Applicants that seek grants as part of their financial hardship package will have to re-apply
during the next IUP funding period to be re-evaluated.
7.6
Confirmation of Hardship Availability
Upon review of all hardship applications received in a funding round, projects eligible for
hardship assistance will be ranked in priority order based on their project priority ranking scores.
Projects with the highest project priority scores will receive confirmation letters for hardship
assistance until the available hardship monies and any unexpended previously committed
hardship funds are fully committed. Projects which qualify for financial hardship assistance may
be provided with written confirmation from EFC of such qualification and placed on the next IUP
Hardship List unless already funded during the current IUP funding period. Written confirmation
for financial hardship will remain valid for the term identified in the confirmation letter. The
amount and type of hardship assistance offered may change or be withdrawn if:
•
the applicant fails to demonstrate satisfactory progress towards project implementation;
•
the information on which the determination was first made changes prior to financial closing;
or
•
the applicant fails to demonstrate that it can repay the financing portion of the assistance
package.
If a project has not closed on funding by the expiration date identified in the confirmation letter, it
will be removed from the Hardship List and will have to reapply for hardship assistance, unless
re-qualified for the Hardship List.
Projects which are deemed eligible for hardship assistance and would otherwise be eligible for a
Grant, but are either not reachable due to the limited grant monies available or consist of
multiple projects submitted by a single applicant for which the sum of the grant component
exceeds $2 million, will have to compete each year for the available hardship monies. However,
these projects may be offered a zero interest rate financing upon determination of hardship
eligibility. Projects that accept this financing will still be eligible to compete for Grant money in
future years up to the time of long-term financing.
Projects that receive a financial hardship confirmation letter, that have not closed on their longterm funding package, and whose project costs increase will be able to apply for a reduced
interest rate financing, as low as zero percent, to cover the cost increases as long as direct
financing dollars are available in the current IUP funding period. As an alternative for projects
not yet closed, the project applicant may submit the entire revised project for reconsideration in
a subsequent annual call for projects.
Projects that receive a financial hardship confirmation letter, that have closed on their long-term
funding package, and whose project costs increased can apply during the next IUP funding
21
period for a reduced interest rate financing, as low as zero percent, to cover the cost increases.
In this case, the applicant must file a new pre-application to list the project in the next IUP. The
project will be awarded additional points for project phasing.
7.7
Co-funding
Confirmation that a project qualifies for hardship assistance will help facilitate funding
coordination with other State and Federal agencies that finance drinking water projects. The
New York State Water and Sewer Infrastructure Co-funding Initiative brings together
representatives from the DOH, EFC, DEC, Department of State, Office of Community Renewal,
United States Department of Agriculture Rural Development, Office of the State Comptroller,
and New York State Energy Research and Development Authority to ensure optimum funding
potential and assistance for New York’s communities. For more information about co-funding,
visit the co-funding web site at http://www.nycofunding.org.
Co-funding is anticipated and encouraged by the provision of additional points to a project’s
score in the priority system. A project must receive co-funding assistance of either $25,000 or
5% of the project costs, whichever is less, to qualify for project co-funding points. Coordination
of joint funding of projects will be done on a project by project basis.
8.0
Capacity Assessment
To provide safe and reliable drinking water, the federal and state governments are investing
substantial financial resources in the drinking water infrastructure of New York State. To assure
the DWSRF is invested wisely, each DWSRF applicant must demonstrate that its water system
has adequate technical, financial and managerial capacity.
8.1
Technical Capacity
To assure adequate technical capacity, the applicant must demonstrate adequacy of source
water, adequacy of infrastructure and technical knowledge. The DOH will review central office
and local office records to assure that the system is being properly operated and maintained.
The water system must not have outstanding drinking water compliance problems unless the
project is aimed at correcting those problems. The engineering report and plans and
specifications for the proposed project will be evaluated to insure that the system has a reliable
source for its drinking water and that it is adequately protected; that the project will maintain
system compliance; and that the education, experience, and technical skills and capabilities of
the system operator are appropriate for that system.
8.2
Financial Capacity
To assure adequate financial capacity, the applicant must have sufficient rates, charges and
revenues to cover necessary costs, demonstrate credit worthiness and fiscal condition in
accordance with EFC criteria. The EFC will review the applicant’s financial capacity during the
full application process to determine financial viability before the awarding of financial
assistance. The EFC’s review will include, but not be limited to, the project budget, municipal
bond resolution(s), annual financial reports to the Office of the State Comptroller, and other
financial information to assure adequate financial capacity of the applicant.
8.3
Managerial Capacity
To assure adequate managerial capacity, the water system must have clear ownership identity
and be appropriately staffed by personnel with expertise to administer overall water system
22
policies and operations. The DOH will review the applicant’s managerial capacity to assure that
management is involved in the day to day supervision of the water system, is aware and
responsive to all required regulations, is available to respond to emergencies, is capable of
identifying and addressing all necessary capital improvements, is responsive to their customers
and is capable of keeping accurate records and assures financial viability. The water system
must have a qualified water operator in accordance with the State's existing Operator
Certification Program.
8.4
Systems with Inadequate Capacity
For all systems that seek funding under the DWSRF, the DOH will review any history of
violations, outstanding compliance problems, reported source contamination or inadequacies,
treatment failures, needs survey data, operations and maintenance issues, and operator and
owner coverage to determine whether a system lacks adequate capacity. A system that
requires improvements to obtain adequate capacity can apply to the DWSRF provided the
improvements will ensure compliance and render the water system viable. Using the
procedures outlined in Sections 8.1, 8.2, and 8.3 to evaluate the system’s technical, financial,
and managerial capacity, the DOH will assess whether DWSRF assistance will help to ensure
compliance. In addition, the DOH will consult with the local health department, which provides
the daily oversight and regulation of the water system, to make this assessment.
8.5
Long-Term Capacity
Water systems must maintain adequate capacity. The DOH and EFC will assess whether each
water system has a long-term plan to undertake feasible and appropriate changes in operations
necessary to develop adequate capacity. The DOH will review Water Resource Management
Strategies, Comprehensive Studies, the Needs Survey and other available engineering reports,
as well as consult with the local health departments, in making these assessments. The DOH
and EFC will encourage restructuring efforts when two or more systems can benefit and other
options, such as contract management or partnerships with other communities in their area, in
an effort to improve the overall capacity. The priority ranking criteria provides additional points
to encourage this objective. In addition, restructuring efforts and other cooperative
arrangements among systems will be encouraged as part of the implementation of the statewide
capacity development strategy.
8.6
Annual Reporting Requirements
The State will submit to the EPA and include in the IUP, documentation that summarizes the
results of the capacity assessments conducted on those systems seeking funding under the
DWSRF in the preceding year. The summary will include statistics on the numbers, types, and
sizes of systems assessed to determine technical, managerial, and financial capacity, including
the assessment outcomes; whether DWSRF assistance will ensure compliance for those
systems with inadequate capacity; and whether restructuring efforts will result in both
developing adequate capacity and achieving long-term capacity for systems. Table 4
summarizes the required capacity assessment information.
23
Table 4
Capacity Development Review Summary (10/1/10 – 9/30/11)
Statewide
Capacity Reviews
Totals
System Type: System Size (population served)
CWS NTNC <1000 1,000-3,300
>3300
29
29
0
7
11
11
0
0
0
0
0
0
(Failed) Requiring Restructuring
0
0
0
0
0
0
Systems in SNC
Funded
Requesting
DWSRF
Being Processed
Assistance
1
1
0
1
0
0
8
8
0
3
1
4
Passed
Failed
9.0
State Environmental Review Process/Determination of Equivalency Projects
The State Environmental Review Process (SERP) applies to all projects receiving financial
assistance from the DWSRF. The SERP incorporates environmental review requirements of
the National Environmental Policy Act (NEPA) and its implementing regulations (40 CFR, Part 6
and 40 CFR, Part 1500), the State Environmental Quality Review (SEQR) Act, Article 8 of the
Environmental Conservation Law (ECL) and its implementing regulations under 6 NYCRR, Part
617, as well as the DOH regulations under 10 NYCRR, Part 97. The DWSRF applicant must
complete the SERP before receiving DWSRF financing.
All projects that are financed from the DWSRF are classified by the DOH under the SERP as
either Tier I or Tier II projects. Tier I projects, also referred to as equivalency projects, refer to
those projects that are financed by the DWSRF whose cumulative total is an amount equal to
the federal Capitalization Grant to the State. Tier II projects, (non-equivalency projects), refer to
all other projects that receive DWSRF financial assistance.
Tier I projects must undergo an environmental review consistent with the NEPA.
DWSRF program, Tier I projects will include:
For the
•
projects for which an environmental review consistent with NEPA has already been
completed; and
•
projects that meet the definition of a NEPA categorical exclusion.
If necessary, additional Tier I projects will include:
•
projects for which applicants have voluntarily undertaken to complete a NEPA equivalent
environmental review;
•
projects that have a particular environmental significance, due to the nature and scope of
the projects; and
•
projects for which the environmental review can be considered functionally equivalent to a
NEPA environmental review, with some minor additional elements.
24
Tier II projects are subject to the environmental review requirements of SEQR with additional
requirements imposed by the SERP for the DWSRF program. Applicants will be notified by the
DOH whether their project(s) proposed for financing through the DWSRF program fall under the
category Tier I (equivalency) or Tier II.
10.0
Project Priority Lists
10.1
Project Selection Process
Both federal and state laws require that New York develop a Project Priority Ranking System.
The priority ranking system establishes a list of eligible projects to be funded in a manner
consistent with the SDWA such that the most serious risks to public health are given the highest
priority. The DOH has given the highest priority to acute public health risks, particularly those
related to microbiological organisms. The next priority was given to situations that pose chronic
and longer term risks to consumers, such as organic chemical contamination. The scoring
criteria also consider issues that are related to infrastructure upgrading or replacement. The
project ranking system also considers, as mandated by the SDWA, special allocations and
restrictions on the use of DWSRF monies for disadvantaged and small systems. A detailed
description of the Project Priority Ranking System and Scoring Criteria are included as
Attachment I to this IUP.
10.2
Description and Use of Project Lists
Projects must be included in the IUP to receive DWSRF financing. This IUP includes the
following prioritized lists of eligible projects being considered for financing from the DWSRF:
• The Project Readiness List for this IUP includes all projects for which an engineering report
or plans and specifications are submitted to the DOH or for which construction is
completed by September 3, 2011. A project is deemed “ready” when all technical
submittals have been received by the DOH. Projects that have submitted pre-application
forms, but have neither submitted an engineering report, plans and specifications nor
completed construction have been included on the Multi-Year List.
The Project Readiness List includes a subsidized funding line. Projects listed above this
subsidy funding line comprise the Funding List, which includes all those projects expected
to qualify for long-term financing within the current IUP financing period. Provisions are
made in the Project Priority Ranking System to by-pass projects that may not progress as
expected (see Attachment I). The DOH will proceed with an accelerated by-pass of those
non-hardship projects that have been on the Project Readiness List, above the subsidy
funding line for two or more consecutive IUP periods and fail to submit a complete
application by December 1, 2011. Notification letters will be sent to applicants with such
projects informing them that their complete applications will have to be submitted by
December 1, 2011, or they will receive a by-pass letter.
Funds released by project by-passing will first be used for the Emergency Financing
Program to finance imminent threats to public health. Funds released by project bypassing will then be used to finance cost increases incurred by projects on the IUP above
the subsidy funding line. Any remaining funds available will be used to finance projects
below the subsidy funding line in order of priority ranking.
The project cost presented on the Project Readiness List reflects the applicant’s estimated
project cost.
25
It should be noted that for some larger projects there may not be sufficient funds available
in a single IUP financing period for their complete financing. As necessary, New York
State will segment and/or phase finance (cash flow basis) larger projects over several IUP
financing periods to maintain a statewide program of maximum effectiveness.
• The Category A List consists of projects for small systems serving less than 10,000
people from the Project Readiness List. This list includes a funding line and a line
designating the SDWA minimum funding requirement (15% of the DWSRF) for small
public water systems.
• The Category B List consists of projects for water systems serving greater than or equal
to 10,000 people from the Project Readiness List. This list has not been included in
the IUP.
• The Multi-Year List includes all eligible projects for which pre-application forms have
been submitted and reviewed, including those projects on the preceding Multi-Year
List. The DOH accepts pre-applications on a continuous basis. All eligible projects for
which pre-application forms are submitted on or before September 3, 2010 will be
included on the Multi-Year List in the final IUP.
• The Category C (Hardship) List includes all eligible projects that have received written
confirmation that they qualify for financial hardship assistance.
Copies of the Project Readiness List, the Category A List, the Multi-Year List, and the Category
C (Hardship) List follow at the end of this section.
26
PROJECT READINESS LIST
The Project Readiness List for this IUP begins with
projects that have received a written confirmation letter that
they qualify for financial hardship and are determined to be
ready. These projects are identified by ‘H’ in the column
labeled “score.”
Phased or segmented projects are assigned 2000 points
in addition to their total project ranking system score.
Projects with interest free short-term financing are
assigned 1000 points in addition to their total project ranking
system score and are identified by ‘NOTE: Short-Term Loan
Closed’ in the column labeled “project cost.”
The code box located under each project number
identifies the source of financial assistance for the project, if
known, and also whether the project contains “green”
infrastructure components.
Project #
County
CODES See legend*
17473
Jefferson
NYS Drinking Water State Revolving Fund Final Readiness List
October 1, 2011 to September 30, 2012
System Name/
Borrower
LAFAVE ROAD WATER
DISTRICT / Le Ray (T)
Description
Consolidation of existing public water systems with GUDI wells,
coliform and lead violations., New Distribution System, New System
Consolidation
Pop.
600
Project Cost Score
$0
Cumulative
Total
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown
isRemaining Balance Not Funded With Short Term Loan
17321
Jefferson
WESTCOTTS WATER
DISTRICT / Hounsfield (T)
ARRAF
17456
Westcotts WD to serve along NYS Route 3. Consolidation of PWS
systems addressing SWTR & E-Coli violations. , Upgrade Storage,
New Distribution System, New System Consolidation
300
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown
isRemaining Balance Not Funded With Short Term Loan
Hamilton
INDIAN LAKE WD / Indian
Lake (T)
New Surface Water Treatment Rule Compliance Facility, Upgrade
Water Treatment Plant, New Ground Water Source, Upgrade
Distribution System
900
Essex
PORT KENT WD /
Chesterfield (T)
New Surface Water Treatment Rule Compliance Facility, New
Ground Water Source, New Storage
202
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown
isRemaining Balance Not Funded With Short Term Loan
17388
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown
isRemaining Balance Not Funded With Short Term Loan
15881
Essex
WADHAMS WD / Westport
(T)
New Surface Water Treatment Rule Compliance Facility, New
Inter-Connection, New System Consolidation
140
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown
isRemaining Balance Not Funded With Short Term Loan
17561
Chautauqua
FORESTVILLE VILLAGE /
Forestville (V)
New Surface Water Treatment Rule Compliance Facility, New
Ground Water Source, Upgrade Distribution System
804
Orange
PHEASANT HILL / Pheasant
Hill Water Corp
Rehabilitation of water system to address e-coli contamination,
Upgrade Water Treatment Plant, New Ground Water Source, New
Storage
154
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown
isRemaining Balance Not Funded With Short Term Loan
17461
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown
isRemaining Balance Not Funded With Short Term Loan
15072
Orange
ARRAF
17647
BEAVER DAM LAKE WATER New Surface Water Treatment Rule Compliance Facility, New
Ground Water Source, New Storage, Upgrade Distribution System
CORP. / Beaver Dam Lake
Corp.
487
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown
isRemaining Balance Not Funded With Short Term Loan
Saratoga
STILLWATER VILLAGE /
Stillwater (V)
Alternative Water Source for Surface Water Treatment Rule
compliance., New Transmission, New Inter-Connection
1,572
Otsego
UNADILLA VILLAGE /
Unadilla (V)
Install new well, pumphouse, controls, chlorination system to replace
GWUDI springs, New Surface Water Treatment Rule Compliance
Facility, New Ground Water Source, Upgrade Pump Station, Upgrade
Distribution System
1,350
Extend system to serve area with private contaminated wells,
consolidate public water supply. , Extend Distribution System, New
System Consolidation
1,200
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown
isRemaining Balance Not Funded With Short Term Loan
15343
ARRAF
15204
Oswego
HANNIBAL (T) / Hannibal (T)
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown
isRemaining Balance Not Funded With Short Term Loan
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown
isRemaining Balance Not Funded With Short Term Loan
17543
17576
Saratoga
Chautauqua
Consolidate 3 small CWSs, consolidate WD 1, connect Town with
MOREAU WD
New Storage, Extend Distribution System, New
7/CONNECTION TO SCWA / SCWA,
Inter-Connection, Extend System Consolidation, New Water District
Moreau (T)
CHERRY CREEK VILLAGE / New Surface Water Treatment Rule Compliance Facility, Upgrade
Distribution System
Cherry Creek (V)
1,100
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown
isRemaining Balance Not Funded With Short Term Loan
650
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown
isRemaining Balance Not Funded With Short Term Loan
16261
17538
Oswego
Oswego
New Surface Water Treatment Rule Compliance Facility, New
TOAD
New Pump Station, New Distribution System, New
HARBOR/CONSTANTIA WD / Storage,
Inter-Connection, New System Consolidation
Constantia (T)
2,765
New Surface Water Treatment Rule Compliance Facility, New
Ground Water Source, New Transmission, New Storage, New
Distribution System
1,662
WATER DISTRICT #2 /
Richland (T)
ARRAF
17306
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown
isRemaining Balance Not Funded With Short Term Loan
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown
isRemaining Balance Not Funded With Short Term Loan
Jefferson
WATER DISTRICT #2 /
Henderson (T)
New Surface Water Treatment Rule Compliance Facility, New
Distribution System, New System Consolidation
352
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown
isRemaining Balance Not Funded With Short Term Loan
17382
Allegany
HOUGHTON WATER
DISTRICT / Caneadea (T)
Upgrade Water Treatment Plant, New Ground Water Source, New
Transmission, Upgrade Distribution System
2,000
ARRAF
17457
Erie
CHAFFEE WATER CO /
Chaffee Water Co.
New Surface Water Treatment Rule Compliance Facility, New
Ground Water Source, New Storage
200
ARRAF
16882
H
$0
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown
isRemaining Balance Not Funded With Short Term Loan
Onondaga
LIMELEDGE WD / Marcellus
(T) & (V)
ARRAF
17140
$0
NOTE: Short - Term Loan Closed, Project Cost Shown
isRemaining Balance Not Funded With Short Term Loan
New Water District to serve area with insufficient private wells.
Interconnection with GWUDI system., New Surface Water Treatment
Rule Compliance Facility, Extend Distribution System
700
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown
isRemaining Balance Not Funded With Short Term Loan
St.Lawrence
LOUISVILLE WATER
DISTRICT #2 / Louisville (T)
New Storage, Upgrade Distribution System, System Consolidation
1,000
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown
isRemaining Balance Not Funded With Short Term Loan
CODES Legend *
ARRAF=American Recovery Reinvestment Act Financed
GIC=Green Infrastructure Components
FGP=Funded through SRF Bond Guarantee Program
CAT_G=Green Innovative Grants Program Project
Page 1 of 35
Project #
County
CODES See legend*
NYS Drinking Water State Revolving Fund Final Readiness List
October 1, 2011 to September 30, 2012
System Name/
Borrower
Description
Pop.
5,800
17611
Franklin
SARANAC LAKE V / Saranac New SCADA equipment., New Surface Water Treatment Rule
Compliance Facility, Upgrade Distribution System
Lake (V)
16746
Allegany
CANASERAGA VILLAGE
PUBLIC WATER /
Canaseraga (V)
New Ground Water Source, Upgrade Storage
17497
Montgomery
AMSTERDAM (C) /
Amsterdam (C)
Upgrade Surface Water Treatment Rule Compliance Facility,
Upgrade Water Treatment Plant, Upgrade Water Treatment Plant,
Upgrade Water Treatment Plant
15003
Ulster
ELLENVILLE (VILLAGE)
WATER DIS / Ellenville (V)
17928
Wyoming
18005
Project Cost Score
Cumulative
Total
$12,500,000
H
$12,500,000
$3,666,749
H
$16,166,749
20,700
$737,000
H
$16,903,749
Water system improvements, Upgrade Surface Water Treatment
Rule Compliance Facility, Upgrade Storage, Upgrade Distribution
System
4,323
$7,136,870
H
$24,040,619
CASTILE VILLAGE / Castile
(V)
Upgrade Water Treatment Plant, Upgrade Ground Water Source,
Upgrade Storage
1,135
$5,111,267
H
$29,151,886
Wayne
SAVANNAH WD #1 /
Savannah (T)
New Surface Water Treatment Rule Compliance Facility, New
Storage, Upgrade Distribution System, Extend Distribution System
900
$3,605,000
H
$32,756,886
17425
Chenango
SO. NEW BERLIN WATER
DISTRICT / New Berlin (T)
New Ground Water Source, New Transmission, New Storage,
Upgrade Distribution System, System Consolidation
400
$3,272,000
H
$36,028,886
15603
Jefferson
WATER DISTRICT NO. 5 /
Hounsfield (T)
Extend distribution system to area of insufficient yielding or
cantaminated private wells. Consolidate Watertown International
Airport., New Distribution System, New System Consolidation
345
$4,800,000
H
$40,828,886
17427
Albany
New Surface Water Treatment Rule Compliance Facility, New
NEW SALEM WATER
New Pump Station, New Inter-Connection, New Water
DISTRICT / New Scotland (T) Storage,
District
486
$3,048,000
H
$43,876,886
17442
Erie
BRANDT (T), NORTH
COLLINS (T)&(V) / North
Collins (V)
WTP improvements for lead and copper violations, Fe violations,
Asbestos Main replacement, inadequate pressures, Upgrade Water
Treatment Plant, Upgrade Transmission, Upgrade Distribution
System, New System Consolidation
1,915
$5,430,000
H
$49,306,886
17379
Steuben
COOPERS PLAINS/LONG
ACRES WATER SYST /
Erwin (T)
New Ground Water Source, Extend Distribution System, New System
Consolidation
1,400
$0
H
$49,306,886
17552
Herkimer
NEWPORT VILLAGE /
Newport (V)
New Surface Water Treatment Rule Compliance Facility, New
Ground Water Source, Upgrade Transmission, New Storage,
Upgrade Distribution System
740
$2,175,000
H
$51,481,886
16278
Hamilton
LONG LAKE (T) / Long Lake
(T)
New Ground Water Source, New Storage, Upgrade Distribution
System
750
$3,929,255
H
$55,411,141
16692
Herkimer
VAN HORNESVILLE WATER VanHornesville Water System, New Surface Water Treatment Rule
Compliance Facility, New Storage, Upgrade Distribution System
WORKS / Stark (T)
372
$2,098,150
H
$57,509,291
17625
Oswego
EASTERN SHORE WATER
SYSTEM / Sandy Creek (T)
$13,988,000
H
$71,497,291
17372
Oswego
MEXICO (T) WD#2 / Mexico Extend distribution system to area with contaminated private wells
and consolidate PWS with GWUDI source, New Distribution System,
(T)
New System Consolidation
800
$7,060,000
H
$78,557,291
17637
Chautauqua
NORTH END WD / Pomfret
(T)
Extend distribution system to area with contaminated private wells
and consolidate PWS with Coliform, New Distribution System
900
$4,432,100
H
$82,989,391
16114
Cayuga
CAYUGA VILLAGE / Cayuga New Surface Water Treatment Rule Compliance Facility, Upgrade
Distribution System, New Inter-Connection
(V)
600
$6,875,100
H
$89,864,491
17331
Rensselaer
POESTENKILL (T) WD #1 /
Poestenkill (T)
$0
H
$89,864,491
Cattaraugus
New Surface Water Treatment Rule Compliance Facility, Upgrade
CRYSTAL WATER CO
(WEST VALLEY) / Ashford (T) Ground Water Source
$3,208,500
H
$93,072,991
ARRAF
ARRAF
Consolidation of PWS with GWDI source., New Storage, New
Distribution System, New System Consolidation
New Complete System (New System), New System Consolidation
900
2,503
2,300
ARRAF
17589
880
CODES Legend *
ARRAF=American Recovery Reinvestment Act Financed
GIC=Green Infrastructure Components
FGP=Funded through SRF Bond Guarantee Program
CAT_G=Green Innovative Grants Program Project
Page 2 of 35
Project #
County
CODES See legend*
NYS Drinking Water State Revolving Fund Final Readiness List
October 1, 2011 to September 30, 2012
System Name/
Borrower
Description
18017
Allegany
RICHBURG VILLAGE
PUBLIC WATER / Richburg
(V)
(V) Richburg & (V) Bolivar Consolidation., New Surface Water
Treatment Rule Compliance Facility, New Ground Water Source,
Upgrade Storage, Upgrade Distribution System, New System
Consolidation
17682
Essex
WD#4 / Moriah (T)
16510
Schenectady
17629
Pop.
Project Cost Score
Cumulative
Total
600
$7,038,640
H
$100,111,631
New Surface Water Treatment Rule Compliance Facility, New
Distribution System
78
$1,990,475
H
$102,102,106
DELANSON VILLAGE
WATER WORKS / Delanson
(V)
Upper resevoir raw water transmission main, new intake, new
controls & meters at filter plant., New Transmission, Extend
Distribution System, Upgrade Distribution System
428
$4,594,000
H
$106,696,106
Essex
ESSEX WD / Essex (T)
Address turbidity and organic violations, New Ground Water Source,
Upgrade Distribution System
300
$1,515,954
H
$108,212,060
17367
Steuben
TROUPSBURG WATER
DISTRICT / Troupsburg (T)
New Surface Water Treatment Rule Compliance Facility, Upgrade
Water Treatment Plant
250
$192,000
H
$108,404,060
16618
Dutchess
SHOREHAVEN CIVIC
ASSOC / DCWWA
DCWWA ZONE J SHOREHAVEN WATER SYSTEM, Upgrade
Water Treatment Plant, Upgrade Ground Water Source, Upgrade
Distribution System
300
$3,575,000
H
$111,979,060
17623
Saratoga
CORINTH VILLAGE / Village
of Corinth
New Surface Water Treatment Rule Compliance Facility, Upgrade
Distribution System
4,700
$6,200,000
H
$118,179,060
17931
Cayuga
PORT BYRON VILLAGE /
Port Byron (V)
Joint project with (V) Port Byron, (T) Montezuma & (T) Mentz.,
Upgrade Distribution System, Extend Distribution System, New
System Consolidation
1,400
$5,657,000
H
$123,836,060
17454
St.Lawrence
EAST LOUISVILLE WD#3 /
Louisville (T)
Consolidation of water systems with past coliform detections., New
Storage, New Distribution System, New System Consolidation
1,030
$9,275,000
H
$133,111,060
17444
Greene
COXSACKIE VILLAGE /
Coxsackie (V)
Phase 2 of 15702, Upgrade Water Treatment Plant, Upgrade Water
Treatment Plant
4,010
$3,233,065
3175
$136,344,125
NOTE: Short - Term Loan Closed, Project Cost Shown
isRemaining Balance Not Funded With Short Term Loan
17866
Delaware
Phase 3 of 15624 (Phase 2 was 17228): Treat or Replace GWUDI
GRAND GORGE WATER
DISTRICT / Town of Roxbury Wells, New Surface Water Treatment Rule Compliance Facility
18029
Rensselaer
HOOSICK FALLS (V) PWS /
Hoosick Falls (V)
17773
Chenango
17631
370
$992,000
2245
$137,336,125
Phase 2 of Project 15080 , Upgrade Storage, Upgrade Distribution
System
4,000
$640,000
2225
$137,976,125
SHERBURNE VILLAGE /
Sherburne (V)
Phase 2 of 15237., Upgrade Ground Water Source
1,531
$1,300,000
2210
$139,276,125
Essex
WILMINGTON WD /
Wilmington (T)
Phase 2 (Juniper Hill Road) of DWSRF 15803, New Surface Water
Treatment Rule Compliance Facility, New Storage, Upgrade
Distribution System
980
$406,500
2175
$139,682,625
17515
Orange
NEWBURGH CITY /
Newburgh (C)
Phase 2 of project 16754 Cost overrun, Upgrade Water Treatment
Plant, Upgrade Transmission
28,000
$2,577,162
2165
$142,259,787
17496
Greene
HUNTER VILLAGE / Hunter
(V)
Phase 2 of #16732 - Dolan's Lake Intake and Connection of Wells 1
and 3, Upgrade Water Treatment Plant, New Ground Water Source,
New Transmission
896
$1,518,150
2165
$143,777,937
17800
Orange
KIRYAS JOEL VILLAGE /
Kiryas Joel (V)
Water Treatment Plant Well #28 and mitigation of offsite well
impacts. Phase 2 of 16752, New Water Treatment Plant
21,750
$900,000
2130
$144,677,937
17470
Herkimer
HERKIMER VILLAGE /
Herkimer (V)
Phase 2 of 16676, New Surface Water Treatment Rule Compliance
Facility
7,606
$300,000
2130
$144,977,937
17649
Ulster
PHOENICIA WATER
DISTRICT / Shandaken (T)
Phase 2, see Project #16491 for Phase 1., New Surface Water
Treatment Rule Compliance Facility, Upgrade Ground Water Source
992
$150,000
2130
$145,127,937
$217,962,340
2115
$363,090,277
17983
NY City
NEW YORK CITY - CROTONCroton filtration plant(Phase 8 of 16479), New Surface Water
Treatment Rule Compliance Facility
SYSTEM / NYCMWFA
1,000,000
CODES Legend *
ARRAF=American Recovery Reinvestment Act Financed
GIC=Green Infrastructure Components
FGP=Funded through SRF Bond Guarantee Program
CAT_G=Green Innovative Grants Program Project
Page 3 of 35
Project #
County
CODES See legend*
NYS Drinking Water State Revolving Fund Final Readiness List
October 1, 2011 to September 30, 2012
System Name/
Borrower
Description
Pop.
18022
Cattaraugus
PERRYSBURG (V) /
Perrysburg (T)
Phase 2 (DWSRF 17192) based on cost increase to address
unresolved deficiencies in the initial project construction, New Water
Treatment Plant, Upgrade Ground Water Source, Upgrade Storage,
New Pump Station
404
17449
Orange
HIGHLANDS (T) WD #2 /
Highlands (T)
Phase 2 of DWSRF 16454 to provide well source capacity for Phase
1 which included, Upgrade Water Treatment Plant, New Ground
Water Source, New Storage, Extend Distribution System
17742
Saratoga
MECHANICVILLE CITY /
Mechanicville (C)
17642
Washington
GRANVILLE VILLAGE /
Granville (V)
Project Cost Score
Cumulative
Total
$729,657
2095
$363,819,934
1,379
$4,748,700
2095
$368,568,634
Phase 2 of 15284; Construct additional sludge drying bed capacity,
New Other Expenses, New Water Treatment Plant, New Other (OT)
5,100
$587,100
2090
$369,155,734
New Surface Water Treatment Rule Compliance Facility, Upgrade
Ground Water Source, Upgrade Transmission, Upgrade Distribution
System
2,645
$0
1220
$369,155,734
NOTE: Short - Term Loan Closed, Project Cost Shown
isRemaining Balance Not Funded With Short Term Loan
17163
Essex
TICONDEROGA WD /
Ticonderoga (T)
New Surface Water Treatment Rule Compliance Facility, New
Storage, Upgrade Distribution System
5,000
$13,954,315
265
$383,110,049
18061
Franklin
TUPPER LAKE V / Tupper
Lake (V)
New wells to replace SW source and inadequate DE plant., New
Ground Water Source, Upgrade Distribution System
5,500
$2,979,790
235
$386,089,839
16013
Westchester
New Surface Water Treatment Rule Compliance Facility
BRIARCLIFF MANOR
VILLAGE / Briarcliff Manor(V)
8,831
$0
225
$386,089,839
15862
Putnam
SPRINGHOUSE ESTATES
W.W. CORP. / Southeast (T)
New Ground Water Source, New Storage
212
$1,700,500
200
$387,790,339
18013
Cattaraugus
RANDOLPH VILLAGE /
Randolph (T)
East Randolph and Randolph (V)'s project includes meters, Upgrade
Other Expenses, New Surface Water Treatment Rule Compliance
Facility, New Ground Water Source, New System Consolidation,
Upgrade Other (OT)
1,250
$3,740,000
200
$391,530,339
15996
Delaware
FRANKLIN VILLAGE /
Franklin (V)
New Water Treatment Plant, New Ground Water Source, New
Storage, Extend Distribution System, Upgrade Distribution System
481
$2,301,077
195
$393,831,416
17493
Orange
WARWICK VILLAGE /
Warwick (V)
New Surface Water Treatment Rule Compliance Facility, Upgrade
Water Treatment Plant
6,083
$0
190
$393,831,416
17337
Erie
HUNTERS CREEK MOBILE Address total coliform detections and organic exceedances, Upgrade
Treatment Plant, New Storage, New Pump Station, Upgrade
HOME PARK / Hunters Creek Water
Distribution System
MHP
150
$175,100
185
$394,006,516
15661
Albany
RENSSELAERVILLE WD /
Rensselaerville (T)
200
$990,242
185
$394,996,758
17936
Rensselaer
Distribution Modifications for Flow & Pressure Improvements to
BRUNSWICK WATER
Consecutive System; Emergency Generator, Upgrade Pump
DISTRICT # 6 / Brunswick (T) Support
Station, Upgrade Distribution System
927
$504,000
185
$395,500,758
17529
Jefferson
Serve area with private contaminated wells, New Surface Water
TIBBETS POINT WATER
Rule Compliance Facility, New System Consolidation, New
DISTRICT / Cape Vincent (T) Treatment
Water District
200
$2,645,000
180
$398,145,758
17392
Warren
PIONEER VILLAGE / Pioneer Serve private contaminated wells., New Surface Water Treatment
Rule Compliance Facility, New Inter-Connection, New System
Village Imp. Assoc.
Consolidation
144
$208,575
175
$398,354,333
17562
Jefferson
HERRINGS VILLAGE /
Herrings (V)
Distribution and storage improvements., Upgrade Storage, Upgrade
Distribution System
120
$3,429,000
170
$401,783,333
15557
Herkimer
POLAND VILLAGE / Poland
(V)
Surface Water Treatment Rule Compliance Facility, New Ground
Water Source, New Storage, Upgrade Distribution System
463
$246,000
165
$402,029,333
17621
Allegany
ANGELICA VILLAGE PUBLIC Surface Water Treatment Rule Compliance Facility
WATER / Angelica (V)
950
$1,061,847
165
$403,091,180
17537
Delaware
DOWNSVILLE WATER
DISTRICT / Colchester (T)
500
$92,400
165
$403,183,580
ARRAF
ARRAF
New Ground Water Source, Upgrade Storage, Upgrade Distribution
System
Package Filtration Plant for GWUDI Spring Source and Addition of
Corrosion Control Treatment., New Surface Water Treatment Rule
Compliance Facility, New Water Treatment Plant
CODES Legend *
ARRAF=American Recovery Reinvestment Act Financed
GIC=Green Infrastructure Components
FGP=Funded through SRF Bond Guarantee Program
CAT_G=Green Innovative Grants Program Project
Page 4 of 35
Project #
County
CODES See legend*
NYS Drinking Water State Revolving Fund Final Readiness List
October 1, 2011 to September 30, 2012
System Name/
Borrower
Description
Pop.
New 10 MG storage tank. (Phase 1 of covering city's open finished
water storage, Phase 2 is Proj. # 18023 on multiyear list) , Upgrade
Water Treatment Plant, New Storage, Upgrade Storage
17438
Oneida
ROME CITY / Rome (C)
16991
Chenango
OXFORD WATER DISTRICT Surface Water Treatment Rule Compliance Facility, New
Transmission
#1 / Oxford (T)
16741
Dutchess
PAWLING VILLAGE / Pawling New Surface Water Treatment Rule Compliance Facility, New
Ground Water Source
(V)
15097
Warren
HAGUE HOA / Hague HOA
Hague Home Owners Association, New Surface Water Treatment
Rule Compliance Facility
18060
Orange
HIGHLANDS WATER
DISTRCIT 2 EXTENTION /
Highlands (T)
Extention of the existing WD #2 to serve private wells with
contamination and consolidation of several PWS's, Extend
Distribution System, Extend System Consolidation
18072
Putnam
GIPSY TRAIL CLUB / Gipsy
Trail Club Inc
Develop additional well source capacity, New Ground Water Source,
New Pump Station
15600
Hamilton
ANTLERS OF RAQUETTE
LAKE, INC. / Antlers of
Raquette Lake Inc.
New Surface Water Source, Inter-Connection
16117
Jefferson
ALEXANDRIA TOWN WD #1 Extend Distribution System, Upgrade Distribution System
- OTTER STREET /
Alexandria (T)
17469
Montgomery
FORT PLAIN (V) WATER
WORKS / Fort Plain (V)
17339
Erie
17514
32,000
Project Cost Score
Cumulative
Total
$10,000,000
160
$413,183,580
$122,500
160
$413,306,080
$1,270,000
155
$414,576,080
$119,190
155
$414,695,270
$1,601,238
155
$416,296,508
300
$430,540
150
$416,727,048
120
$243,595
150
$416,970,643
60
$3,600,000
150
$420,570,643
Upgrade Water Treatment Plant, Upgrade Ground Water Source,
Upgrade Storage, Upgrade Distribution System
2,400
$1,565,600
150
$422,136,243
S. EAST ERIE CO.
REGIONAL WATER
PROJECT / Aurora (T)
Aurora WD19, Wales WD's2&3. Extend to serve private
contaminated wells, consolidate public water supplies, eliminate
public water supply with past coliform detections, Storage, Pump
Station, Extend Distribution System, System Consolidation
2,950
$6,400,000
150
$428,536,243
Cattaraugus
DELEVAN VILLAGE /
Delevan (V)
New Surface Water Treatment Rule Compliance Facility, Upgrade
Ground Water Source, Upgrade Storage, Upgrade Distribution
System
1,090
$1,690,350
145
$430,226,593
17289
Wayne
WOLCOTT VILLAGE /
Wolcott (V)
New Water Treatment Plant, Upgrade Ground Water Source
2,200
$1,250,000
145
$431,476,593
17513
Essex
WINEBROOK HILLS WD /
Newcomb (T)
New Ground Water Source, Upgrade Distribution System
250
$5,302,728
145
$436,779,321
17622
Chautauqua
BROCTON VILLAGE /
Brocton (V)
Address turbidity violations, Surface Water Treatment Rule
Compliance Facility, Upgrade Water Treatment Plant
4,000
$2,219,341
145
$438,998,662
17385
Onondaga
NORTHEAST LAFAYETTE
WD / East Syracuse (V)
Inter-connection to eliminate GWUDI source., New Transmission,
New Inter-Connection
250
$535,600
145
$439,534,262
17944
Nassau
MILL NECK ESTATES / Mill
Neck Estates Association
Transmission main to connect with Locust Valley WD and upgrade
distribution, Upgrade Distribution System, New Inter-Connection
230
$2,021,375
145
$441,555,637
16861
Franklin
TUPPER LAKE V / Tupper
Lake (V)
New Storage, Upgrade Distribution System
5,500
$700,000
145
$442,255,637
17535
Saratoga
SOUTH GLENS FALLS
VILLAGE / South Glens Falls
(V)
Proposed Cartridge Filtration Plant with SCADA to treat Village
GWUDI spring sources., New Surface Water Treatment Rule
Compliance Facility, New Surface Water Treatment Rule Compliance
Facility
3,700
$1,565,000
145
$443,820,637
15749
Rensselaer
RENSSELAER CITY PWS /
Rensselaer (C)
New Storage, New Distribution System, System Consolidation
7,500
$7,175,300
145
$450,995,937
17455
Franklin
WATER DISTRICT #3 /
Malone (T)
Consolidate a MHP with nitrate violations, New Distribution System,
System Consolidation, New System Consolidation
300
$1,328,000
145
$452,323,937
50
1,907
18
1,379
** Subsidized Funding Line
CODES Legend *
ARRAF=American Recovery Reinvestment Act Financed
GIC=Green Infrastructure Components
FGP=Funded through SRF Bond Guarantee Program
CAT_G=Green Innovative Grants Program Project
** Subsidized Funding Line-$435,924,679 are available
leaving at least $4,448,086 for project #17513
Page 5 of 35
Project #
County
CODES See legend*
NYS Drinking Water State Revolving Fund Final Readiness List
October 1, 2011 to September 30, 2012
System Name/
Borrower
Description
17645
Washington
GREENWICH VILLAGE /
Greenwich (V)
New Surface Water Treatment Rule Compliance Facility, New
Storage
16339
Jefferson
WELLESLEY ISLAND
WATER CORP. / Wellesley
Island Water Corp.
15220
Westchester
17619
17612
Pop.
Project Cost Score
Cumulative
Total
2,000
$1,100,000
140
$453,423,937
New Water Treatment Plant, New Surface Water Source
548
$2,336,000
140
$455,759,937
CROTON FALLS WATER
DISTRICT / North Salem (T)
Installation of new wells to replace existing wells, New Ground Water
Source
175
$400,000
135
$456,159,937
Livingston
GENESEO VILLAGE /
LCWSA
New Surface Water Treatment Rule Compliance Facility
7,600
$813,000
135
$456,972,937
Onondaga
ELBRIDGE VILLAGE /
Elbridge (V)
New UV treatment for LT2ESWTR compliance., New Surface Water
Treatment Rule Compliance Facility
1,519
$0
135
$456,972,937
NOTE: Financed through SRF Bond Guarantee Program
FGP
16705
Madison
MADISON VILLAGE /
Madison (V)
New Ground Water Source, Upgrade Distribution System
450
$103,500
135
$457,076,437
16106
Greene
TANNERSVILLE VILLAGE /
Tannersville (V)
New Ground Water Source, Upgrade Transmission, Upgrade
Distribution System
448
$1,900,000
135
$458,976,437
15722
Orange
MONROE WD #8 (SKYVIEW Extend system to serve area with private contaminated wells. ,
Upgrade Distribution System
HILLS) / Monroe (T)
544
$1,000,000
135
$459,976,437
17201
Jefferson
ELLISBURG (V) / Ellisburg (V) Extend system to serve area with private contaminated wells,
269
$0
135
$459,976,437
consolidate public water supply, eliminate public water supply with
past total coliform detection. , Extend Distribution System, New
System Consolidation
FGP
Address nitrate contamination, New Ground Water Source, Upgrade
Distribution System
16146
Otsego
MILFORD VILLAGE / Milford
(V)
16279
Steuben
New Chlorination system., Upgrade Ground Water Source
COLONIAL COACH
ESTATES IV (MGRE) / Merlyn
Cavallaro
17617
Orange
BLOOMING GROVE WD
#1-WORLEY HE / South
Blooming Grove (V)
Transmission main with treatment plant to connect Water District 1
and 6 to Orange and Rockland Well., New Water Treatment Plant,
New Transmission
17467
Ulster
SAUGERTIES (VILLAGE)
WATER DIS / Saugerties (V)
17597
Oswego
16912
NOTE: Financed through SRF Bond Guarantee Program
510
$3,502,000
130
$463,478,437
79
$65,900
130
$463,544,337
1,500
$3,193,000
130
$466,737,337
Upgrade water mains and appurtenances; distribution extension to
connect 15 existing homes w/ wells to PWS; upgrade raw water
reservoir., Upgrade Other Expenses, Upgrade Distribution System,
Extend Distribution System, Upgrade Other (OT)
4,100
$3,573,894
130
$470,311,231
AREA 1 WATER SYSTEM /
Schroeppel (T)
Address organic contaminant violations, New Distribution System,
New System Consolidation
3,200
$11,312,382
130
$481,623,613
Chenango
NO. NORWICH (T) WD #1 /
North Norwich (T)
New system to serve area with private contaminated wells,
consolidate public water supply, eliminate public water supply with
past total coliform detection. , New Distribution System
100
$920,300
130
$482,543,913
17516
St.Lawrence
OSWEGATCHIE (T) /
Oswegatchie (T)
Joint water system improvement project between (T) Oswegatchie,
(T) Lisbon and (V) Huevelton, Upgrade Ground Water Source,
Upgrade Storage, Upgrade Distribution System, New
Inter-Connection, New System Consolidation
2,100
$13,973,000
130
$496,516,913
17355
Yates
DRESDEN VILLAGE /
Dresden (V)
New Transmission, Upgrade Storage, New Inter-Connection
700
$515,000
125
$497,031,913
15669
Orange
MONROE WD #12 (MONROE Upgrade Ground Water Source, Upgrade Pump Station, Upgrade
Distribution System
HILLS ESTATES) / Monroe
(T)
120
$1,250,000
125
$498,281,913
17432
Chautauqua
CASSADAGA VILLAGE /
Cassadaga (V)
New Ground Water Source, New Storage, Upgrade Distribution
System
760
$5,047,000
125
$503,328,913
17615
St.Lawrence
NORFOLK WATER
DISTRICT / Norfolk (T)
New Surface Water Treatment Rule Compliance Facility, New
Ground Water Source
2,300
$1,279,000
125
$504,607,913
CODES Legend *
ARRAF=American Recovery Reinvestment Act Financed
GIC=Green Infrastructure Components
FGP=Funded through SRF Bond Guarantee Program
CAT_G=Green Innovative Grants Program Project
Page 6 of 35
Project #
County
CODES See legend*
17143
Saratoga
NYS Drinking Water State Revolving Fund Final Readiness List
October 1, 2011 to September 30, 2012
System Name/
Borrower
Description
SARATOGA GLEN HOLLOW Extend system to serve area with private contaminated wells,
public water supply, eliminate public water supply with
/ Saratoga Glen Hollow W.C. consolidate
past totalcoliform detection. , Extend Distribution System, New
Pop.
Project Cost Score
Cumulative
Total
750
$1,096,804
125
$505,704,717
280
$5,651,000
125
$511,355,717
55,210
$65,000,000
120
$576,355,717
System Consolidation
Consolidate PWS with Coliform contamination, extend to private
contaminated/poor yielding wells, New Complete System (New
System), New System Consolidation
17144
Chemung
CHEMUNG (T) WATER
SYSTEM / Chemung (T)
17488
Westchester
New Surface Water Treatment Rule Compliance Facility
WESTCHESTER JOINT
WATER WORKS /
Harrison&Mamaroneck(T)s&(V
17888
Tompkins
TRUMANSBURG VILLAGE /
Trumansburg (V)
New well to provide source redundancy. New transmission main to
provide adequate CT., New Ground Water Source, New
Transmission
2,300
$1,374,000
120
$577,729,717
18004
Chautauqua
WESTFIELD VILLAGE /
Westfield (V)
Address inadequate source capacity and insuffcient pressure,
Upgrade Storage, Upgrade Distribution System
3,450
$3,977,200
120
$581,706,917
17151
Erie
AURORA WATER DISTRICT Extend system to serve area with private contaminated wells,
consolidate public water supply, eliminate public water supply with
18 / Aurora (T)
past total coliform detection. WD 18., Extend Distribution System
1,288
$15,704,100
120
$597,411,017
17594
Oswego
ROUTE 11 NORTH/FULLER
ROAD WD PHASE D /
Hastings (T)
1,200
$3,106,480
120
$600,517,497
16876
Dutchess
BRETTVIEW ACRES WATER New Surface Water Treatment Rule Compliance Facility
CO / Brettview Water Co. Inc.
$40,800
115
$600,558,297
17728
Onondaga
SKANEATELES VILLAGE /
Skaneateles
Install UV Disinfection for LT2 compliance., Upgrade Water
Treatment Plant
2,610
$793,100
115
$601,351,397
17071
Dutchess
BIRCH HILL MANOR /
DCWWA
DCWWA ZONE K BIRCH HILL WATER SYSTEM, Upgrade Water
Treatment Plant, New Ground Water Source
200
$575,000
115
$601,926,397
17801
Yates
WD #1 / Torrey (T)
New Distribution System
375
$3,079,875
115
$605,006,272
16811
Steuben
RIVERSIDE PARK / Carol
Naar
New chlorination system., Upgrade Ground Water Source
125
$45,735
115
$605,052,007
17986
Orange
PORT JERVIS CITY / Port
Jervis (C)
Addition of clarification, Upgrade Water Treatment Plant
9,000
$3,610,000
115
$608,662,007
16093
Tompkins
TRUMANSBURG VILLAGE /
Trumansburg (V)
New Transmission, New Storage, New Pump Station
2,300
$2,501,000
115
$611,163,007
17068
Rensselaer
SCHAGHTICOKE (V) PWS /
Schaghticoke (V)
Upgrade Water Treatment Plant, Upgrade Storage, Upgrade
Distribution System, Extend Distribution System
675
$6,585,700
115
$617,748,707
17230
Oneida
BENEFITED AREA E / Floyd
(T)
New Distribution System, New System Consolidation
115
$325,000
115
$618,073,707
16298
Rockland
NYACK VILLAGE WATER
SUPPLY / Nyack (V)
Relocation of intake to correct turbidity violations., New Transmission
$1,340,000
110
$619,413,707
17591
Ontario
BLOOMFIELD (V) OAKMOUNT AVE /
Bloomfield (V)
Upgrade Ground Water Source
750
$298,750
110
$619,712,457
17414
Greene
CATSKILL VILLAGE / Catskill Upgrade Water Treatment Plant, New Storage, Upgrade Distribution
System
(V)
8,000
$10,270,000
110
$629,982,457
17686
Clinton
SARANAC WD / Saranac (T)
$112,000
105
$630,094,457
Extend distribution system to area of insufficient yielding or
cantaminated private wells., Extend Distribution System, New
System Consolidation
New Surface Water Treatment Rule Compliance Facility
920
14,700
90
CODES Legend *
ARRAF=American Recovery Reinvestment Act Financed
GIC=Green Infrastructure Components
FGP=Funded through SRF Bond Guarantee Program
CAT_G=Green Innovative Grants Program Project
Page 7 of 35
Project #
County
CODES See legend*
NYS Drinking Water State Revolving Fund Final Readiness List
October 1, 2011 to September 30, 2012
System Name/
Borrower
Project Cost Score
Cumulative
Total
Description
Pop.
15,310
$17,705,600
105
$647,800,057
17614
Chautauqua
DUNKIRK CITY / Dunkirk (C) Upgrade Water Treatment Plant, Upgrade Distribution System
15301
Dutchess
TIVOLI VILLAGE WATER /
Tivoli (V)
Construct new supply well(s), upgrade treatment, new storage,
upgrade storage, upgrade distribution, Upgrade Water Treatment
Plant, New Ground Water Source, New Storage, Upgrade Pump
Station, Upgrade Distribution System
1,303
$3,729,700
105
$651,529,757
17361
Schoharie
COBLESKILL VILLAGE /
Cobleskill (V)
Upgrade Water Treatment Plant, New Storage, Upgrade Distribution
System
4,533
$4,120,000
105
$655,649,757
16446
Sullivan
WOODRIDGE VILLAGE /
Woodridge (V)
Upgrade Water Treatment Plant
902
$351,430
105
$656,001,187
17358
Rensselaer
Connect WD #3 (Maple Crest) to WD #1 (Clearview), Extend
SCHODACK WATER
DISTRICT # 3 / Schodack (T) Distribution System, New System Consolidation
140
$0
105
$656,001,187
17588
Steuben
CORNING MANOR WATER
DISTRICT / Corning (T)
Extend to ontaminated private wells, consolidate 5 small PWS's,
Upgrade Storage, New System Consolidation
350
$1,315,187
105
$657,316,374
18053
Schoharie
COBLESKILL / Cobleskill (T)
Howe Caverns/Route 7 Service Area Extension, Extend Distribution
System
500
$4,899,004
105
$662,215,378
17104
Saratoga
East Side Drive WD connection to CPWA, to serve private
CLIFTON PARK WATER
wells, consolidation of public water supplies, Extend
AUTHORITY / Clifton Park (T) contaminated
Distribution System
29,000
$1,329,730
105
$663,545,108
16169
Greene
ASHLAND WD#1 / Ashland
(T)
New Complete System (New System), New Inter-Connection
300
$2,873,620
105
$666,418,728
17338
Dutchess
DUTCHESS ESTATES INC /
Dutchess Estates Water
Company
Upgrade Ground Water Source, Upgrade Storage, Upgrade Pump
Station
500
$455,388
100
$666,874,116
18067
Otsego
GILBERTSVILLE VILLAGE /
Gilbertsville (V)
New Ground Water Source, New Storage, Upgrade Distribution
System
477
$3,865,000
100
$670,739,116
15958
Greene
PRATTSVILLE WATER
DISTRICT / Prattsville (T)
New Ground Water Source
410
$1,361,800
100
$672,100,916
17062
Wyoming
PIKE VILLAGE / Pike (V)
New Ground Water Source, Upgrade Ground Water Source, Upgrade
Transmission, Upgrade Distribution System
369
$494,596
100
$672,595,512
17313
Rockland
LAKE WELCH BEACH W.S. / New Water Treatment Plant, New Transmission
Palisades Interstate Park
Comm
$20,000,000
100
$692,595,512
17021
Dutchess
ROKEBY HOMES,INC. /
DCWWA
DCWWA ZONE F PROJECT ROKEBY WATER SYSTEM , Upgrade
Water Treatment Plant, Upgrade Ground Water Source, Upgrade
Distribution System, New System Consolidation
160
$495,356
100
$693,090,868
17403
Sullivan
WOODRIDGE VILLAGE /
Woodridge (V)
New Ground Water Source
902
$450,000
100
$693,540,868
16323
Monroe
MCWA EASTSIDE WTP /
MCWA
Eastside WTP Phase 1, Raw Water Intake System and a portion of
Phase 5 finished water transmission main work, New Surface Water
Source, New Transmission
222,503
$0
100
$693,540,868
17554
Chautauqua
PORTLAND (T) WATER
DISTRICT NO. 7 / Portland
(T)
Serve 218 parcels currently on insufficient private wells on portions of
Route 5 and Walker Road. Consolidate DJ's Campground., New
System Consolidation, New Water District
333
$1,700,000
100
$695,240,868
15923
Westchester
Upgrade Water Treatment Plant
OSSINING WATER
DEPARTMENT / Ossining (V)
30,000
$1,400,000
95
$696,640,868
16062
Niagara
BARKER VILLAGE / Barker
(V)
$835,085
95
$697,475,953
ARRAF
ARRAF
Upgrade Distribution System
15,000
577
CODES Legend *
ARRAF=American Recovery Reinvestment Act Financed
GIC=Green Infrastructure Components
FGP=Funded through SRF Bond Guarantee Program
CAT_G=Green Innovative Grants Program Project
Page 8 of 35
Project #
County
CODES See legend*
NYS Drinking Water State Revolving Fund Final Readiness List
October 1, 2011 to September 30, 2012
System Name/
Borrower
Description
New Storage
17492
Clinton
PLATTSBURGH CITY /
Plattsburgh (C)
17855
Onondaga
SYRACUSE CITY / Syracuse Woodland Reservoir UV for LT2SWTR compliance., New Surface
Water Treatment Rule Compliance Facility
(C)
17093
Otsego
HARTWICK WATER
DISTRICT / Hartwick (T) WD
New Ground Water Source, New Storage, Upgrade Distribution
System
16606
Delaware
DELHI VILLAGE / Delhi (V)
16654
Madison
17564
Pop.
Project Cost Score
Cumulative
Total
18,000
$4,550,000
95
$702,025,953
192,000
$10,042,500
95
$712,068,453
416
$1,745,850
95
$713,814,303
Upgrade Distribution System, New System Consolidation
3,833
$1,373,428
95
$715,187,731
MORRISVILLE VILLAGE /
Morrisville (V)
To provide adequate pressure, Upgrade Distribution System
2,456
$1,300,000
95
$716,487,731
Oswego
BERNHARDS BAY WD /
Constantia (T)
Extend Distribution System, New System Consolidation
790
$5,890,000
95
$722,377,731
15933
Seneca
FAYETTE HAMLET WATER
DISTRICT / Fayette (T)
Extend Distribution System
400
$3,198,000
95
$725,575,731
17443
Albany
ALTAMONT VILLAGE /
Altamont (V)
New Brandle Road Wells, Disinfection, and Transmission Main, New
Ground Water Source
2,000
$1,394,550
90
$726,970,281
17458
Onondaga
OCWA / Onondaga County
Water Authorit
Western Reservoir 20 mg storage. Replacing uncovered finished
water storage reservoir with concrete tank, Upgrade Storage
256,000
$0
90
$726,970,281
17638
Onondaga
OCWA / Onondaga County
Water Authorit
Eastern 20 MG Reservoir storage. Replacing uncovered finished
water storage reservoir with concrete tank., Upgrade Storage
256,000
$22,500,000
90
$749,470,281
17460
Onondaga
CLAY WDS / Metropolitan
Water Board
Replace uncovered finished 30 MG Terminal Reservoir with two 15
MG tanks, Upgrade Storage
16,000
$16,050,000
90
$765,520,281
16613
Chautauqua
MAYVILLE VILLAGE /
Mayville (V)
Upgrade Ground Water Source, Upgrade Transmission, Upgrade
Storage, Upgrade Distribution System
1,856
$2,884,000
90
$768,404,281
17992
Cortland
MCGRAW VILLAGE /
McGraw (V)
Upgrade Distribution System
1,306
$4,222,961
90
$772,627,242
17433
Suffolk
SUFFOLK COUNTY WATER New Wells/Upgrade Wells in various locations throughout the system,
Upgrade Ground Water Source, New Ground Water Source
AUTHORITY / SCWA
1,009,264
$9,313,000
90
$781,940,242
17364
Suffolk
SOUTH HUNTINGTON WD / Well 19-2, New Ground Water Source
Huntington (T)
81,760
$1,515,842
90
$783,456,084
17732
Fulton
JOHNSTOWN (C) WATER
WORKS / Johnstown (C)
Replacement of Maylender finished water uncovered reservoir;
automation of water system operations, New Other Expenses, New
Storage, New Other (OT)
8,511
$3,255,000
90
$786,711,084
17870
Saratoga
SCWA STILLWATER
EXTENSION / Saratoga
County Water Authorit
Extend Transmission
2,100
$3,035,000
90
$789,746,084
17925
Schuyler
MONTOUR FALLS / Montour Upgrade Storage, Upgrade Distribution System
Falls (V)
1,800
$5,852,501
90
$795,598,585
15451
Saratoga
STILLWATER WD #1
(STILLWATER VLG) /
Stillwater (T)
New Transmission, New Storage
1,560
$4,912,000
90
$800,510,585
17523
Orange
MONTGOMERY W.D. #1 /
Montgomery (T)
Extend WD #1 to consolidate several water supplies, New System
Consolidation
$13,500,000
90
$814,010,585
ARRAF
605
CODES Legend *
ARRAF=American Recovery Reinvestment Act Financed
GIC=Green Infrastructure Components
FGP=Funded through SRF Bond Guarantee Program
CAT_G=Green Innovative Grants Program Project
Page 9 of 35
Project #
County
CODES See legend*
NYS Drinking Water State Revolving Fund Final Readiness List
October 1, 2011 to September 30, 2012
System Name/
Borrower
Description
New Storage, Extend Distribution System
16390
Ulster
HIGHLAND WATER
DISTRICT / Lloyd (T)
16889
Oneida
New system to serve area with private contaminated wells,
KIRKLAND (T) ROUTE 5
public water supply. , New Complete System (New
WATER DISTRICT / Kirkland consolidate
System)
(T)
17428
Albany
FLAT ROCK ROAD W.D. /
New Scotland (T)
New Water District
17598
Oswego
AREA 3,4 & 8 WATER
SYSTEM / Schroeppel (T)
16262
Broome
15684
Pop.
Project Cost Score
Cumulative
Total
4,000
$2,369,000
90
$816,379,585
300
$1,578,872
90
$817,958,457
149
$2,152,580
90
$820,111,037
New Distribution System, New System Consolidation
1,500
$7,678,916
90
$827,789,953
CONKLIN (T) W.D. / Conklin
(T)
Extend system to serve area with private contaminated wells,
consolidate public water supply. , Inter-Connection, System
Consolidation
1,000
$863,140
90
$828,653,093
Greene
NEW BALTIMORE (T) / New
Baltimore (T)
Extend system to serve area with private contaminated wells,
consolidate public water supply. , Extend Distribution System, New
System Consolidation
1,300
$5,000,000
90
$833,653,093
17375
St.Lawrence
CANTON (T) E. SIDE WD /
Canton (T)
New Ground Water Source, New Storage, New Distribution System
350
$3,112,660
90
$836,765,753
17727
Ulster
KINGSTON (CITY) WATER
DISTRICT / Kingston (C)
Upgrade Water Treatment Plant
$0
85
$836,765,753
24,000
NOTE: Financed through SRF Bond Guarantee Program
FGP
17183
Seneca
SENECA FALLS VILLAGE /
Seneca Falls (V)
Upgrade Water Treatment Plant, Upgrade Pump Station
7,400
$2,885,000
85
$839,650,753
15490
Warren
NORTH CREEK WATER
DISTRICT / Johnsburg (T)
Upgrade Water Treatment Plant, New Ground Water Source,
Upgrade Storage
1,000
$1,112,250
85
$840,763,003
17445
Rensselaer
NORTH GREENBUSH (T)
WATER DISTRICT NO. 18 /
North Greenbush (T)
Purchase existing Private Water System, Connect to Municipal Water
System , New System Consolidation, New Water District
$437,750
85
$841,200,753
16111
Dutchess
BARD COLLEGE / Bard
College
Upgrade Water Treatment Plant, New Storage
1,400
$2,100,000
85
$843,300,753
18043
Chautauqua
BARCELONNA WD /
Westfield (T)
New Town WD to aquire private water system. Other funding sources
may be required to make project viable and eligible for DWSRF,
Upgrade Distribution System, New Water District
128
$1,792,125
85
$845,092,878
17422
Herkimer
HERKIMER (T), WD #3, #4,
#5 / Herkimer (T)
Upgrade Pump Station, Upgrade Distribution System, Extend
Distribution System
320
$299,112
85
$845,391,990
16922
Herkimer
GRAHM, NEWPORT &
BROWN RD WD / Schuyler
(T)
New system to serve area with private contaminated wells. , New
Complete System (New System)
260
$1,280,000
85
$846,671,990
17448
Washington
New water district to serve residents in area of groundwater
KINGSBURY WD
(QUEENSBURY) / Kingsbury contamination , New Distribution System, New Water District
(T)
$845,000
85
$847,516,990
17858
Oswego
WD#3 EXPANSION / Granby Extend Distribution System
(T)
238
$5,315,041
85
$852,832,031
15531
Jefferson
Extend system to serve area with private contaminated wells,
TOWN OF PAMELIA RT. 3,
WATER DISTRICT / Pamelia consolidate public water supply. , Extend Distribution System
(T)
96
$474,160
85
$853,306,191
15810
Steuben
VICTORY PLACE / Merlyn
Cavallaro
Upgrade Ground Water Source
11
$112,800
80
$853,418,991
17298
Putnam
BREWSTER VILLAGE /
Brewster (V)
New Ground Water Source, New Pump Station
$1,610,920
80
$855,029,911
212
1,300
2,000
CODES Legend *
ARRAF=American Recovery Reinvestment Act Financed
GIC=Green Infrastructure Components
FGP=Funded through SRF Bond Guarantee Program
CAT_G=Green Innovative Grants Program Project
Page 10 of 35
Project #
County
CODES See legend*
NYS Drinking Water State Revolving Fund Final Readiness List
October 1, 2011 to September 30, 2012
System Name/
Borrower
Description
16862
Suffolk
SUFFOLK COUNTY WATER Northport Aqueduct Project to reduce nitrate contamination through
source blending, Upgrade Transmission, New Distribution System
AUTHORITY / Suffolk Co.
Water Authority
17900
Nassau
BETHPAGE WD / Bethpage
Water District
17699
Nassau
GARDEN CITY (V) / Village of New Water Treatment Plant, Upgrade Pump Station
Garden City
16139
St.Lawrence
MASSENA VILLAGE /
Massena (V)
16447
Steuben
CORNING CITY / Corning (C) Address total coliform violations, New Storage, New Distribution
17342
Washington
CAMBRIDGE VILLAGE /
Cambridge (V)
17377
Chautauqua
SILVER CREEK (V) / Silver
Creek (V)
15736
Erie
COLLINS WD #3 / Collins (T) Upgrade Transmission, New Storage, Upgrade Distribution System
18051
Montgomery
FULTONVILLE VILLAGE
PWS / Fultonville (V)
Upgrade Water Treatment Plant, Upgrade Ground Water Source,
Upgrade Distribution System
15704
Greene
COXSACKIE VILLAGE /
Coxsackie (V)
Upgrade Transmission, New Storage, Upgrade Distribution System
15236
Chautauqua
SHERMAN VILLAGE /
Sherman (V)
Address total Coli violations., Upgrade Distribution System
15325
Wayne
WOLCOTT VILLAGE /
Wolcott (V)
Upgrade Water Treatment Plant, Upgrade Surface Water Source
17145
Oneida
TIBBITS/SNOWDEN HILL
WD / New Hartford (T)
18002
Steuben
17934
Pop.
1,009,264
Project Cost Score
Cumulative
Total
$22,166,771
80
$877,196,682
33,000
$4,271,616
80
$881,468,298
25,000
$2,221,556
80
$883,689,854
11,209
$3,134,000
80
$886,823,854
10,842
$2,000,000
80
$888,823,854
Aquisition of existing Cambridge Water Works, New Storage,
Upgrade Distribution System
1,524
$2,500,000
80
$891,323,854
New Storage, Upgrade Distribution System
1,000
$4,311,000
80
$895,634,854
760
$625,000
80
$896,259,854
740
$1,262,150
80
$897,522,004
4,010
$6,210,000
80
$903,732,004
$795,000
80
$904,527,004
2,200
$3,300,000
80
$907,827,004
New system to serve area with private contaminated wells. , New
Complete System (New System)
450
$2,400,000
80
$910,227,004
HAMLET OF WOODHULL
MUNICIPAL WS / Woodhull
(T)
System to serve former Village (now hamlet) with private
contaminated wells., New Ground Water Source, New Storage, New
Distribution System
483
$4,489,928
80
$914,716,932
Onondaga
LAFAYETTE (T) / LaFayette
(T)
Creation of Central LaFayette Water District., New Water District
2,000
$5,700,000
80
$920,416,932
17077
Rensselaer
NORTH GREENBUSH WD
#13 / North Greenbush (T)
New system to serve area with private contaminated wells (Snyder's
Lake Area). , New System Consolidation, New Water District
1,050
$4,635,000
80
$925,051,932
17510
Oswego
NORTH AREA WD / Volney
(T)
New Distribution System, New System Consolidation
1,000
$6,604,000
80
$931,655,932
15599
Seneca
FAYETTE WATER PROJECT Extend Distribution System
/ Varick (T)
520
$1,406,800
80
$933,062,732
17567
Steuben
URBANA WATER DISTRICT Proposed WD #3. Extend system to serve private contaminated wells
and consolidate public water supplies., Extend Distribution System,
#2 / Urbana (T)
New System Consolidation, New Water District
33
$3,565,111
80
$936,627,843
17413
Orange
WALLKILL CONSOLIDATED Rykoski Lane Water Treatment Plant, Upgrade Water Treatment
Plant, New Pump Station, New Pump Station
WD / Wallkill (T)
15,000
$7,000,000
75
$943,627,843
Nitrate removal at Plant #1, Upgrade Water Treatment Plant
Upgrade Water Treatment Plant
System
917
CODES Legend *
ARRAF=American Recovery Reinvestment Act Financed
GIC=Green Infrastructure Components
FGP=Funded through SRF Bond Guarantee Program
CAT_G=Green Innovative Grants Program Project
Page 11 of 35
Project #
County
CODES See legend*
NYS Drinking Water State Revolving Fund Final Readiness List
October 1, 2011 to September 30, 2012
System Name/
Borrower
Description
New Ground Water Source, New Storage
16444
Columbia
DARROW SCHOOL / The
Darrow School
17949
Dutchess
HIGH MEADOWS PARK INC New Ground Water Source, Upgrade Storage
/ High Meadows Co-op Corp
17533
Clinton
CHAMPLAIN VILLAGE /
Champlain (V)
Upgrade Water Treatment Plant, New Storage, Upgrade Distribution
System
16381
Orleans
LYNDONVILLE VILLAGE /
Lyndonville (V)
Upgrade Transmission, Upgrade Distribution System
15843
Delaware
MARGARETVILLE VILLAGE / Upgrade Storage, Upgrade Distribution System
Margaretville (V)
17076
Ulster
ELLENVILLE (VILLAGE)
WATER DIS / Ellenville (V)
16273
Suffolk
15718
Pop.
Project Cost Score
Cumulative
Total
150
$169,950
75
$943,797,793
500
$44,577
75
$943,842,370
2,947
$1,883,226
75
$945,725,596
1,418
$1,612,864
75
$947,338,460
700
$737,900
75
$948,076,360
Upgrade Surface Water Source
4,323
$173,600
75
$948,249,960
DERING HARBOR CORP /
Dearing Harbor (V)
Upgrade Water Treatment Plant
250
$20,791
75
$948,270,751
Orange
MONROE WD #10 - PINE
TREE ROAD / Monroe (T)
New system to serve area with private contaminated wells. , New
Transmission
50
$215,000
75
$948,485,751
15950
Albany
GUILDERLAND TOWN WD / Phase III Improvements, New Storage, Extend Distribution System,
Upgrade Distribution System, New Inter-Connection
Guilderland (T)
30,000
$10,146,000
75
$958,631,751
17139
Rensselaer
EAST GREENBUSH
GENERAL W.D. / East
Greenbush (T)
Upgrade Storage, New Storage
10,200
$3,279,680
75
$961,911,431
17633
Steuben
SYLVAN BEACH WANETA
LAKE WATER DISTRICT /
Wayne (T)
New Complete System (New System)
921
$4,175,175
75
$966,086,606
15925
Allegany
TOWN OF WELLSVILLE /
Wellsville (T)
Extend system to serve area with private contaminated wells,
Morningside Area, Extend Distribution System
5,000
$867,106
75
$966,953,712
17229
Rensselaer
NORTH GREENBUSH WD
#14 / North Greenbush (T)
New system to serve inadequate private wells in Northeast corner of
Town , New Inter-Connection, New System Consolidation, New
Water District
3,000
$7,313,000
75
$974,266,712
16899
Oneida
FLOYD BENEFIT (T) AREA
"D" / Floyd (T)
New Complete System (New System)
900
$7,750,000
75
$982,016,712
17979
Jefferson
WATRE DISTRICT NO. 8 /
Watertown (T)
Extend Distribution System, New System Consolidation
119
$1,929,000
75
$983,945,712
17311
Herkimer
MANION HEIGHTS WD /
German Flatts (T)
New Complete System (New System)
105
$152,000
75
$984,097,712
17098
Jefferson
WILNA WD#1 / Wilna (T)
Extend system to serve area with private contaminated wells. , New
Distribution System
85
$569,590
75
$984,667,302
17368
Orange
GOSHEN VILLAGE / Goshen New Water Treatment Plant, New Ground Water Source, New
Transmission
(V)
$5,311,500
70
$989,978,802
16984
Westchester
KITCHAWAN WATER
DISTRICT / Yorktown (T)
240
$500,000
70
$990,478,802
17042
Orange
MONROE VILLAGE / Monroe Upgrade Distribution System
(V)
8,892
$986,000
70
$991,464,802
correct organic exceedances., New Transmission
5,676
CODES Legend *
ARRAF=American Recovery Reinvestment Act Financed
GIC=Green Infrastructure Components
FGP=Funded through SRF Bond Guarantee Program
CAT_G=Green Innovative Grants Program Project
Page 12 of 35
Project #
County
CODES See legend*
NYS Drinking Water State Revolving Fund Final Readiness List
October 1, 2011 to September 30, 2012
System Name/
Borrower
Description
Pop.
Project Cost Score
Cumulative
Total
17082
Ontario
CLIFTON SPRINGS VILLAGE New Storage, Upgrade Distribution System
/ Clifton Springs (V)
2,190
$618,000
70
$992,082,802
17667
Tioga
NEWARK VALLEY VILLAGE / Upgrade Distribution System
Newark Valley (V)
1,253
$4,813,000
70
$996,895,802
15560
Oneida
VERNON VILLAGE (SWP) /
Vernon (V)
New Transmission, New Storage, New Distribution System, New
Inter-Connection
1,155
$5,610,300
70
$1,002,506,102
17761
Genesee
BATAVIA CITY / Batavia (C)
Upgrade Water Treatment Plant, Upgrade Distribution System
16,310
$2,067,500
70
$1,004,573,602
15794
Oneida
MOHAWK VALLEY WATER Shacksbury Storage Tank and Mains, Replacement. , Upgrade
AUTHORITY / Upper Mohawk Storage
Valley Reg. WB
120,000
$400,000
70
$1,004,973,602
17404
Nassau
PLAINVIEW WD / Oyster Bay New air stripper at Plant 7, New Water Treatment Plant
(T)
35,000
$1,287,500
70
$1,006,261,102
17901
Nassau
BETHPAGE WD / Bethpage
Water District
VOC removal at Plant # 4, Upgrade Water Treatment Plant
33,000
$4,056,717
70
$1,010,317,819
17902
Nassau
BETHPAGE WD / Bethpage
Water District
VOC removal at Plant #6, Upgrade Water Treatment Plant
33,000
$2,409,376
70
$1,012,727,195
17911
Nassau
VOC treatment at Well #6, Upgrade Water Treatment Plant
WA OF GREAT NECK
NORTH / Water Auth of Great
Neck North
31,400
$1,400,000
70
$1,014,127,195
17702
Nassau
GARDEN CITY (V) / Village of VOC Removal at Hilton Park Plant (Wells 15 and 16), New Water
Treatment Plant
Garden City
25,000
$2,580,150
70
$1,016,707,345
16245
Albany
COHOES CITY / Cohoes (C)
Upgrade Water Treatment Plant
15,550
$1,975,000
70
$1,018,682,345
17618
St.Lawrence
GOUVERNEUR VILLAGE /
Gouverneur (V)
Upgrade Water Treatment Plant
4,263
$2,160,600
70
$1,020,842,945
17856
Onondaga
SYRACUSE CITY / Syracuse Westcott Reservoir UV for LT2SWTR compliance., New Surface
Water Treatment Rule Compliance Facility
(C)
192,000
$4,805,000
70
$1,025,647,945
17857
Onondaga
SYRACUSE CITY / Syracuse Lead service replacement., Upgrade Distribution System
(C)
192,000
$16,377,000
70
$1,042,024,945
17626
Ulster
Upgrade Water Treatment Plant, New Storage, Upgrade Distribution
NEW PALTZ (VILLAGE)
WATER DIST / New Paltz (V) System
5,600
$5,675,916
70
$1,047,700,861
18009
Tompkins
DRYDEN VILLAGE / Dryden
(V)
New Ground Water Source, New Storage, Upgrade Distribution
System
2,000
$5,924,000
70
$1,053,624,861
15205
Oneida
BOONVILLE VILLAGE /
Boonville (V)
New Transmission, New Storage, Upgrade Distribution System
2,300
$801,144
70
$1,054,426,005
17635
Schenectady
PRINCETOWN WATER
SUPPLY / Princetown (T)
New Transmission, New Storage, New Pump Station, Extend
Distribution System
600
$360,500
70
$1,054,786,505
17972
Cayuga
(T) BRUTUS WATER
DISTRICT #8 / Brutus (T)
New (T) Brutus WD #8 (Cottle Road), Upgrade Distribution System,
New Water District
400
$1,920,334
70
$1,056,706,839
16012
Chautauqua
WESTFIELD VILLAGE /
Westfield (V)
East Main St., Upgrade Distribution System
$950,000
70
$1,057,656,839
3,450
CODES Legend *
ARRAF=American Recovery Reinvestment Act Financed
GIC=Green Infrastructure Components
FGP=Funded through SRF Bond Guarantee Program
CAT_G=Green Innovative Grants Program Project
Page 13 of 35
Project #
County
CODES See legend*
NYS Drinking Water State Revolving Fund Final Readiness List
October 1, 2011 to September 30, 2012
System Name/
Borrower
Description
17571
Ulster
New Complete System (New System)
WEST HURLEY WATER
DISTRICT #1 (PROPOSED) /
Hurley (T)
17359
Madison
LEWIS POINT/PINE RIDGE
ROAD / Lenox (T)
16435
Oneida
DEERFIELD (T), SMITH HILL Extend system to serve area with private contaminated wells,
consolidate public water supply. , Extend Distribution System
EXT. / Deerfield (T)
17526
Allegany
WELLSVILLE WATER
DISTRICT / Wellsville (T)
15435
Washington
FORT EDWARD WD #2 / Fort Extend Distribution System
Edward (T)
17884
Onondaga
MARCELLUS (T) / Marcellus
(T)
17186
Steuben
17655
Pop.
Project Cost Score
Cumulative
Total
450
$4,713,160
70
$1,062,369,999
210
$1,192,230
70
$1,063,562,229
200
$638,000
70
$1,064,200,229
133
$1,192,450
70
$1,065,392,679
126
$650,000
70
$1,066,042,679
Pheasant Valley Road WD., New Distribution System, New
Inter-Connection
93
$782,000
70
$1,066,824,679
REXVILLE WATER
DISTRICT / West Union (T)
New system to serve area with private contaminated wells. , New
Complete System (New System)
60
$100,000
70
$1,066,924,679
Nassau
HICKSVILLE WD / Hicksville
Water District
Nitrate Treatment at Plant No. 8, Upgrade Water Treatment Plant
47,810
$3,144,322
65
$1,070,069,001
17662
Nassau
MANHASSET LAKEVILLE
WD / Manhasset-Lakeville
WD
Nitrate Removal Searingtown Station, Upgrade Water Treatment
Plant
43,000
$3,409,300
65
$1,073,478,301
17663
Suffolk
EAST FARMINGDALE WD /
Babylon East Farmingdale
WD
VOC Treatment at Plant No. 4, Upgrade Water Treatment Plant
7,500
$4,398,512
65
$1,077,876,813
16144
Orange
GOSHEN W.D. #1
(HAMBLETONIAN PARK) /
Goshen (T)
New Ground Water Source, New Storage, Upgrade Distribution
System
509
$2,605,900
65
$1,080,482,713
16737
Dutchess
DOVER RIDGE ESTATES /
Beekman (T)
Upgrade Ground Water Source
250
$266,500
65
$1,080,749,213
17504
Schoharie
CENTRAL BRIDGE WATER
DISTRICT / Central Bridge
WD
DBP Control , Upgrade Water Treatment Plant
1,061
$1,773,000
65
$1,082,522,213
17575
Fulton
NORTHAMPTON (T) WATER Upgrade Storage, Upgrade Distribution System
DISTRICT / Northampton (T)
1,000
$6,303,627
65
$1,088,825,840
17218
Chautauqua
FREDONIA VILLAGE /
Fredonia (V)
Upgrade Water Treatment Plant
10,400
$1,287,500
65
$1,090,113,340
17282
Dutchess
RHINEBECK VILLAGE
WATER / Rhinebeck (V)
Upgrade Water Treatment Plant
4,300
$365,200
65
$1,090,478,540
16762
Cayuga
UNION SPRINGS VILLAGE / New Water Treatment Plant
Union Springs (V)
2,000
$165,000
65
$1,090,643,540
15797
Essex
PORT HENRY V / Port Henry Upgrade Transmission, Upgrade Distribution System
(V)
1,831
$511,910
65
$1,091,155,450
15042
Genesee
ALEXANDER VILLAGE /
Alexander (V)
New Storage
781
$880,425
65
$1,092,035,875
17746
Ontario
RUSHVILLE VILLAGE /
Rushville (V)
Upgrade Surface Water Treatment Rule Compliance Facility
621
$1,969,200
65
$1,094,005,075
New Water District
Extend Distribution System, New Water District
CODES Legend *
ARRAF=American Recovery Reinvestment Act Financed
GIC=Green Infrastructure Components
FGP=Funded through SRF Bond Guarantee Program
CAT_G=Green Innovative Grants Program Project
Page 14 of 35
Project #
County
CODES See legend*
NYS Drinking Water State Revolving Fund Final Readiness List
October 1, 2011 to September 30, 2012
System Name/
Borrower
Description
Replace lead service lines from the watermain to the property line to
correct lead & copper exceedances., Upgrade Distribution System
17389
Onondaga
NORTHEAST LAFAYETTE
WD / East Syracuse (V)
17609
Chenango
NORWICH CITY / Norwich (C) New Water Treatment Plant
17766
Broome
DEPOSIT (V) WATER
DEPARTMENT / Deposit (V)
17417
Delaware
15750
Pop.
250
Project Cost Score
Cumulative
Total
$444,445
65
$1,094,449,520
8,000
$8,652,000
65
$1,103,101,520
Upper NW Quadrant water main reconstruction, new river crossing,
new telemetry system., Upgrade Transmission, Upgrade Distribution
System
2,080
$2,006,336
65
$1,105,107,856
ARKVILLE WATER
DISTRICT / Middletown (T)
Extend distribution, 100,000 gallons of storage, 100 gpm well, system
consolidation., New Ground Water Source, New Storage, Extend
Distribution System, Extend System Consolidation
400
$1,833,375
65
$1,106,941,231
Westchester
CORTLANDT
CONSOLIDATED WD /
Cortlandt (T)
Upgrade Storage, Upgrade Distribution System
28,369
$4,000,000
65
$1,110,941,231
15040
Montgomery
PALATINE BRIDGE (V)
WATER WORKS / Palantine
Bridge (V)
Upgrade Water Treatment Plant, Upgrade Ground Water Source,
Upgrade Distribution System
890
$985,750
65
$1,111,926,981
17610
Montgomery
AMSTERDAM (T) /
Amsterdam(T)
New Storage, New Pump Station, Extend Distribution System
400
$4,506,250
65
$1,116,433,231
17935
Madison
LENOX (T) / Lenox (T)
Water District No. 12., New Water District
750
$5,000,000
65
$1,121,433,231
18016
Steuben
WD #3 / Campbell (T)
Serve private contaminated/poor yielding wells., Extend Water
District
1,025
$908,687
65
$1,122,341,918
16679
Seneca
JUNIUS WATER DISTRICT
#1 / Junius (T)
Extend system to serve area with private contaminated wells. W.D.
Ext. #2., Extend Distribution System
300
$623,607
65
$1,122,965,525
16798
St.Lawrence
EAST NORFOLK WATER
DISTRICT / Norfolk (T)
New system to serve area with private contaminated wells. , New
Complete System (New System)
270
$750,000
65
$1,123,715,525
15183
Orleans
SHELBY (T) / Shelby (T)
Extend system to serve area with private contaminated wells. Water
Improvement No. 4 - Phase I., Extend Distribution System
240
$249,700
65
$1,123,965,225
17826
Lewis
WATER DISTRICT NO. 10 /
Lowville (T)
New Distribution System
240
$507,000
65
$1,124,472,225
16921
Jefferson
ADAMS (T) WD #2 / Adams
(T)
New system to serve area with private contaminated wells. , New
Complete System (New System)
190
$1,509,000
65
$1,125,981,225
15483
Yates
Extend system to serve area with private contaminated wells. ,
BENTON TOWN WATER
DISTRICT NO. 1 / Benton (T) Extend Distribution System
97
$639,000
65
$1,126,620,225
17352
Suffolk
SOUTH HUNTINGTON WD / Plant No. 10 VOC Removal, Upgrade Water Treatment Plant
Huntington (T)
81,760
$3,913,790
60
$1,130,534,015
17891
Suffolk
SOUTH HUNTINGTON WD / Plant 3 VOC Removal, Upgrade Water Treatment Plant
Huntington (T)
81,760
$3,530,840
60
$1,134,064,855
17892
Suffolk
SOUTH HUNTINGTON WD / Plant 7 VOC Removal, Upgrade Water Treatment Plant
Huntington (T)
81,760
$5,575,390
60
$1,139,640,245
17893
Suffolk
SOUTH HUNTINGTON WD / Plant 4 VOC Removal, Upgrade Water Treatment Plant
Huntington (T)
81,760
$973,350
60
$1,140,613,595
16699
Westchester
SUNSET RIDGE WATER
DISTRICT / North Salem (T)
625
$400,000
60
$1,141,013,595
Replacement of pump control equipment, storage tank cleaning &
coating, water main replacement & installation, pump house reapirs,
pump house fencing and driveway, Upgrade Storage, Upgrade Pump
Station, Upgrade Distribution System
CODES Legend *
ARRAF=American Recovery Reinvestment Act Financed
GIC=Green Infrastructure Components
FGP=Funded through SRF Bond Guarantee Program
CAT_G=Green Innovative Grants Program Project
Page 15 of 35
Project #
County
CODES See legend*
NYS Drinking Water State Revolving Fund Final Readiness List
October 1, 2011 to September 30, 2012
System Name/
Borrower
Description
Upgrade Pump Station, Upgrade Distribution System
17548
Albany
MENANDS VILLAGE /
Menands (V)
16474
NY City
3rd City Tunnel, mnhtn borings; Restore shaft 23(C604); Riser Valve
NEW YORK
CITY-CATSKILL/DELAWARE Controls, Delaware system(C347), Upgrade Transmission
SYSTEM / NYCMWFA
16478
NY City
17011
Pop.
3,900
Project Cost Score
Cumulative
Total
$6,936,000
60
$1,147,949,595
6,552,718
$35,000,000
60
$1,182,949,595
3rd City tunnel and shafts, crit redund, dist press,Field
NEW YORK
CITY-CATSKILL/DELAWARE services(C538B CM), Upgrade Transmission
SYSTEM / NYCMWFA
6,552,718
$470,000,000
60
$1,652,949,595
NY City
City tunnel 3 stage 2, shafts19B-22B (C544B, C, E, H, P), Upgrade
NEW YORK
CITY-CATSKILL/DELAWARE Transmission
SYSTEM / NYCMWFA
6,552,718
$35,000,000
60
$1,687,949,595
17167
NY City
City Tunnel 3, Stage 2, Shaft 15B East-Phase 1, Brooklyn-Queens
NEW YORK
CITY-CATSKILL/DELAWARE (C545G), New Pump Station
SYSTEM / NYCMWFA
6,552,718
$8,000,000
60
$1,695,949,595
17203
NY City
City Tunnel 3, Stage 1, Shafts 8B and 15B, Phase 1 - Completion of
NEW YORK
CITY-CATSKILL/DELAWARE Chlorination Booster Stations, Upgrade Distribution System
SYSTEM / NYCMWFA
6,552,718
$1,000,000
60
$1,696,949,595
17193
Essex
AUSABLE FORKS WD / Jay
(T)
900
$5,201,603
60
$1,702,151,198
16576
Chemung
NORTHSTAR MHP / Leading water softener system and, Upgrade Distribution System
Edge Properties
400
$93,113
60
$1,702,244,311
18038
Saratoga
MECHANICVILLE CITY /
Mechanicville (C)
Interconnection to SCWA, Alternative to Project 17742, New
Transmission
5,100
$9,465,623
60
$1,711,709,934
15846
Essex
MORIAH WD / Moriah (T)
Upgrade Distribution System
3,100
$606,876
60
$1,712,316,810
16069
Suffolk
RIVERHEAD WD / Riverhead Upgrade Ground Water Source
(T)
28,000
$1,211,000
60
$1,713,527,810
15213
Nassau
WESTBURY WD / Westbury
W.D.
New Water Treatment Plant
20,500
$4,120,000
60
$1,717,647,810
16653
Delaware
WALTON VILLAGE / Walton
(V)
Upgrade Controls, Upgrade Ground Water Source, Upgrade
Distribution System
$0
60
$1,717,647,810
Upgrade Water Treatment Plant, New Storage
3,070
NOTE: Financed through SRF Bond Guarantee Program
FGP
17037
Nassau
EAST WILLISTON (V) / East
Williston (V)
Replacement of lead service lines to about 120 residences, New
Other Expenses, New Other (OT)
2,503
$456,000
60
$1,718,103,810
16236
Dutchess
RED HOOK VILLAGE / Red
Hook (V)
New Ground Water Source, Upgrade Ground Water Source, New
Storage, Upgrade Distribution System
2,214
$9,328,300
60
$1,727,432,110
17883
Ulster
NEW PALTZ (V) / New Paltz
(V)
Construct mains in Northern portion of Village to loop system,
Upgrade Distribution System
6,000
$759,625
60
$1,728,191,735
18026
Tioga
CANDOR VILLAGE WATER
DEPT. / Candor (V)
Upgrade Storage, Upgrade Distribution System
1,020
$3,047,237
60
$1,731,238,972
17097
Orleans
MEDINA VILLAGE / Medina
(V)
Upgrade Distribution System
6,500
$4,088,085
60
$1,735,327,057
17092
Otsego
LAURENS VILLAGE /
Laurens (V)
New Storage, Upgrade Distribution System
381
$1,236,000
60
$1,736,563,057
15561
Jefferson
WATERTOWN (T) /
Watertown (T)
New system to serve area with private contaminated wells. , New
Complete System (New System), New Storage, New Distribution
System
530
$2,547,476
60
$1,739,110,533
CODES Legend *
ARRAF=American Recovery Reinvestment Act Financed
GIC=Green Infrastructure Components
FGP=Funded through SRF Bond Guarantee Program
CAT_G=Green Innovative Grants Program Project
Page 16 of 35
Project #
County
CODES See legend*
NYS Drinking Water State Revolving Fund Final Readiness List
October 1, 2011 to September 30, 2012
System Name/
Borrower
Description
Pop.
Project Cost Score
Cumulative
Total
17036
Genesee
TOWN OF PEMBROKE
WATER DISTRICT NO. 1 /
Pembroke (T)
Extend system to serve area with private contaminated wells. ,
Extend Distribution System
2,000
$3,860,000
60
$1,742,970,533
16814
Ontario
WEST BLOOMFIELD WD /
West Bloomfield (T)
Extend system to serve area with private contaminated wells. ,
Extend Distribution System
1,500
$231,750
60
$1,743,202,283
16886
Ontario
WEST BLOOMFIELD WD /
West Bloomfield (T)
County Road 35 and Dugway Road. , Extend Distribution System
1,500
$195,513
60
$1,743,397,796
17927
Lewis
CONSOLIDATED WATER
DISTRICT / Watson (T)
New Ground Water Source, New Storage, Extend Distribution System
1,500
$12,389,600
60
$1,755,787,396
16767
Seneca
ROUTE 96 WATER
DISTRICT / Waterloo (T)
Extend system to serve area with private contaminated wells. ,
Extend Distribution System
202
$1,845,512
60
$1,757,632,908
15578
Seneca
BURGESS ROAD WATER
DISTRICT / Junius (T)
Extend system to serve area with private contaminated wells. ,
Extend Distribution System
200
$699,100
60
$1,758,332,008
17616
Oneida
VIENNA (T) / Vienna (T)
New Distribution System
150
$210,000
60
$1,758,542,008
17886
Oneida
HALSTEAD ROAD WD /
Vienna (T)
Extend Distribution System
75
$692,400
60
$1,759,234,408
16516
Suffolk
WEST NECK WATER
SUPPLY / Shelter Island (T)
Upgrade Distribution System
100
$550,000
55
$1,759,784,408
17665
Suffolk
VOC Treatment at Plant No. 11, Upgrade Water Treatment Plant
GREENLAWN WATER
DISTRICT / Greenlawn Water
District
42,000
$1,930,784
55
$1,761,715,192
17664
Suffolk
DIX HILLS WD / Town of
Huntington / Dix Hills
VOC Treatment at Plant No.11, Upgrade Water Treatment Plant
34,522
$2,277,330
55
$1,763,992,522
15811
Onondaga
SKANEATELES VILLAGE /
Skaneateles (V)
Improve disinfection contact time., Upgrade Transmission
2,610
$1,600,000
55
$1,765,592,522
17031
Essex
CROWN POINT WD / Crown
Point (T)
Upgrade Distribution System
995
$2,795,678
55
$1,768,388,200
17437
NY City
Catskill& Delaware UV Disinfection, New Water Treatment Plant
NEW YORK
CITY-CATSKILL/DELAWARE
SYSTEM / NYCWMFA
$1,400,000,000
55
$3,168,388,200
16571
Franklin
HARRIETSTOWN (T) /
Harrietstown (T)
Upgrade Distribution System
5,621
$710,800
55
$3,169,099,000
16957
Franklin
CHATEAUGAY V /
Chateaugay (V)
Upgrade Distribution System
1,100
$2,750,000
55
$3,171,849,000
17547
Broome
WHITNEY POINT VILLAGE / New Wells, Main Street Wellfield/Pumphouse Improvements.,
Upgrade Ground Water Source, New Ground Water Source
Whitney Point (V)
1,054
$569,400
55
$3,172,418,400
18064
Oneida
FORESTPORT WATER
DISTRICT / Foresport (T)
900
$390,000
55
$3,172,808,400
15786
Oneida
MOHAWK VALLEY WATER Gilbert Road Storage Tank., Upgrade Storage
AUTHORITY / Upper Mohawk
Valley Reg. WB
120,000
$150,000
55
$3,172,958,400
15865
Oneida
MOHAWK VALLEY WATER
AUTHORITY / UMVRWB
120,000
$1,600,000
55
$3,174,558,400
New Ground Water Source
Pleasant Street. Upper Mohawk Valley Regional Water Board,
Upgrade Distribution System
6,552,718
CODES Legend *
ARRAF=American Recovery Reinvestment Act Financed
GIC=Green Infrastructure Components
FGP=Funded through SRF Bond Guarantee Program
CAT_G=Green Innovative Grants Program Project
Page 17 of 35
Project #
County
CODES See legend*
NYS Drinking Water State Revolving Fund Final Readiness List
October 1, 2011 to September 30, 2012
System Name/
Borrower
Description
Pop.
Project Cost Score
Cumulative
Total
18015
Yates
WS IMPROVEMENTS /
Dundee (V)
Upgrade Storage, Upgrade Distribution System
1,690
$6,913,360
55
$3,181,471,760
18007
Cortland
MARATHON VILLAGE /
Marathon (V)
New Storage, New Pump Station, Upgrade Distribution System
1,107
$2,947,345
55
$3,184,419,105
17940
Delaware
ROXBURY WATER
DISTRICT / Roxbury (T)
Upgrade Storage, Upgrade Distribution System
755
$1,423,000
55
$3,185,842,105
17599
Sullivan
EDGEWOOD LAKES, INC. /
Edgewood Lakes Inc.
Replace hydropneumatic tank, New Storage
17
$9,000
55
$3,185,851,105
16906
Orange
KIRYAS JOEL VILLAGE /
Kiryas Joel (V)
Pump Station and transmission main from NYC Aqueduct to (V) K.J.,
New Transmission, New Pump Station
21,750
$28,907,400
55
$3,214,758,505
17950
Orange
KIRYAS JOEL VILLAGE /
Kiryas Joel (V)
New wells on Site 1, Site 2, Site 3, Site 4, Site 5, New Ground Water
Source
21,750
$14,246,909
55
$3,229,005,414
17951
Orange
KIRYAS JOEL VILLAGE /
Kiryas Joel (V)
Redevelopment of Wells 6 and 13A and new well at Well 13 Well
Field, New Ground Water Source, Upgrade Ground Water Source
21,750
$3,805,747
55
$3,232,811,161
17952
Orange
KIRYAS JOEL VILLAGE /
Kiryas Joel (V)
Redevelop wells at the Star Expansion Well Field, Upgrade Ground
Water Source
21,750
$1,658,712
55
$3,234,469,873
17027
Oneida
MOHAWK VALLEY WATER The UMVRWB will extend the 12 inch line along Sutliff Road and NYS
233 and connect to Village of Camelot., Extend System
AUTHORITY / Whitestown (T) route
Consolidation
120,000
$629,000
55
$3,235,098,873
17670
Erie
EDEN WD#7 / Eden (T)
Eden WD#7, New Storage, New Distribution System
1,800
$5,460,000
55
$3,240,558,873
17673
Erie
EDEN WD#2 / Eden (T)
Eden WD#2 Shadagee Road Water Project Pump Station and
Waterlines, New Pump Station, New Distribution System
500
$5,280,000
55
$3,245,838,873
17832
Westchester
KENSICO WATER DISTRICT Locust Road Water Main Extension, Extend Distribution System
/ Mount Pleasant
17,857
$8,000,000
55
$3,253,838,873
16501
Erie
BLASDELL VILLAGE /
Blasdell (V)
Consolidation of the Village system with Erie County Water Authority,
Upgrade Distribution System, New System Consolidation
3,200
$2,515,000
55
$3,256,353,873
18071
Cattaraugus
RANDOLPH VILLAGE /
Randolph (T)
East Randolph and Randolph (V)'s Repalcement of Water Mains,
Upgrade Distribution System
1,250
$7,075,000
55
$3,263,428,873
18049
Erie
CONCORD TOWN WATER
SYSTEM / Town of Concord
Extend Distribution System
$335,000
55
$3,263,763,873
18010
Oswego
TOWN/VILLAGE JOINT
WATER PROJECT / Parish
(T)
Serve private contaminated/poor yielding wells., Extend Distribution
System
$10,150,000
55
$3,273,913,873
15109
Seneca
VARICK/ROMULUS WATER
PROJECT / Varick (T)
Extend Distribution System
850
$3,100,000
55
$3,277,013,873
15339
Erie
New Storage, New Pump Station, Extend Distribution System
EAST HILL WATER
DISTRICT NO. 3 / Boston (T)
800
$3,708,000
55
$3,280,721,873
17220
Cayuga
VICTORY (T) WD #2 / Victory Extend Distribution System
(T)
612
$3,389,601
55
$3,284,111,474
15090
Schenectady
PRINCETOWN WATER
SUPPLY / Princetown (T)
Extend Distribution System
600
$929,060
55
$3,285,040,534
125
1,200
CODES Legend *
ARRAF=American Recovery Reinvestment Act Financed
GIC=Green Infrastructure Components
FGP=Funded through SRF Bond Guarantee Program
CAT_G=Green Innovative Grants Program Project
Page 18 of 35
Project #
County
CODES See legend*
NYS Drinking Water State Revolving Fund Final Readiness List
October 1, 2011 to September 30, 2012
System Name/
Borrower
Description
Pop.
Project Cost Score
Cumulative
Total
15092
Schenectady
PRINCETOWN WATER
SUPPLY / Princetown (T)
Extend Distribution System
600
$632,420
55
$3,285,672,954
16949
Schenectady
PRINCETOWN WATER
SUPPLY / Princetown (T)
Extend Distribution System
600
$495,430
55
$3,286,168,384
17636
Schenectady
PRINCETOWN WATER
SUPPLY / Princetown (T)
Extend Distribution System
600
$286,340
55
$3,286,454,724
15613
Livingston
YORK (T) WD NO. 2 / York
(T)
Extend Distribution System
350
$526,330
55
$3,286,981,054
18047
Genesee
RTE 98 WD / Batavia (T)
New Water District the serve areas East and West of Rte. 98, New
Water District
318
$5,322,464
55
$3,292,303,518
16724
Seneca
TYRE (T) WATER DISTRICT Extend system to serve area with private contaminated wells. ,
Extend Distribution System
/ Tyre (T)
260
$992,508
55
$3,293,296,026
16851
Erie
AURORA (T) WATER IMP.
AREA NO. 5 / Aurora (T)
Extend Distribution System
210
$613,500
55
$3,293,909,526
15089
Schenectady
PRINCETOWN (T) - WD#1 /
Princetown (T)
Extend Distribution System
183
$860,050
55
$3,294,769,576
16804
Broome
STILLWATER RD WD#6 /
Conklin (T)
Extend Distribution System
173
$412,782
55
$3,295,182,358
17315
Cayuga
New Pump Station, Extend Distribution System
MORAVIA (T) WATER
DISTRICT NO. 1 / Moravia (T)
162
$663,320
55
$3,295,845,678
15545
Ontario
OAKMOUNT ROAD WATER New Storage, Extend Distribution System
SYSTEM / East Bloomfield (T)
150
$2,224,000
55
$3,298,069,678
18045
Genesee
CREEK RD. WD / Batavia (T) New Water District
136
$1,407,623
55
$3,299,477,301
17189
Jefferson
WATER DISTRICT #5 / Cape New system to serve area with private contaminated wells. , New
Distribution System
Vincent (T)
100
$1,085,200
55
$3,300,562,501
17478
Clinton
ROUTE 11 WD / Champlain
(T)
Extend Distribution System
100
$1,267,380
55
$3,301,829,881
17771
Albany
MARTINS HILL ROAD
WATER DISTRICT /
Coeymans (T)
Extend distribution from Village of Ravena to serve Martins Hill Road
Water District., Extend Distribution System, New Water District
66
$314,150
55
$3,302,144,031
18046
Genesee
PRATT RD. WD / Batavia (T) New Water District
55
$1,067,974
55
$3,303,212,005
17479
Clinton
WEST SERVICE ROAD WD / Extend Distribution System
Champlain (T)
30
$675,284
55
$3,303,887,289
18011
Oneida
ROUTE 5 WD / Vernon (T)
Serve private contaminated/poor yielding wells., Extend Distribution
System
30
$244,000
55
$3,304,131,289
15134
Saratoga
CLIFTON PARK WATER
AUTHORITY / Clifton Park
Water Authority
Inter-Connection
29,000
$252,041
50
$3,304,383,330
15140
Saratoga
CLIFTON PARK WATER
AUTHORITY / Clifton Park
Water Authority
Upgrade Ground Water Source
29,000
$214,327
50
$3,304,597,657
CODES Legend *
ARRAF=American Recovery Reinvestment Act Financed
GIC=Green Infrastructure Components
FGP=Funded through SRF Bond Guarantee Program
CAT_G=Green Innovative Grants Program Project
Page 19 of 35
Project #
County
CODES See legend*
NYS Drinking Water State Revolving Fund Final Readiness List
October 1, 2011 to September 30, 2012
System Name/
Borrower
Description
17584
Westchester
ARBOR HILLS WATER
WORKS / Arbor Hills
Waterworks
New wells, storage and booster pump., New Ground Water Source,
New Storage
15430
Putnam
BREWSTER VILLAGE /
Brewster (V)
New Storage
16211
Niagara
NIAGARA WATER
IMPROVEMENT AREA /
Niagara County
18069
Madison
16188
Pop.
180
Project Cost Score
Cumulative
Total
$725,000
50
$3,305,322,657
2,000
$1,628,000
50
$3,306,950,657
Contract 15G, E., Upgrade Water Treatment Plant, Upgrade
Transmission
8,978
$6,526,857
50
$3,313,477,514
HAMILTON VILLAGE /
Hamilton (V)
New Ground Water Source, Upgrade Distribution System
3,904
$4,100,000
50
$3,317,577,514
Chautauqua
WESTFIELD VILLAGE /
Westfield (V)
Upgrade Water Treatment Plant
3,450
$2,150,000
50
$3,319,727,514
18062
Oswego
CLEVELAND VILLAGE /
Cleveland (V)
Upgrade Ground Water Source, Upgrade Storage, Upgrade
Distribution System
925
$1,576,930
50
$3,321,304,444
17948
Greene
HENSONVILLE (WINDHAM
W.D.) / Windham (T)
Upgrade Ground Water Source
402
$757,050
50
$3,322,061,494
15355
Schenectady
SCHENECTADY CITY
WATER WORKS /
Schenectady (C)
Corrosion Control & Cleaning of Tansmission Mains, Upgrade
Transmission
61,821
$1,248,389
50
$3,323,309,883
16978
Oswego
OSWEGO CITY / Oswego (C) Upgrade Water Treatment Plant
29,400
$4,532,000
50
$3,327,841,883
16760
Nassau
ROCKVILLE CENTRE (V) /
Rockville (V)
Design & construction new iron filtration facility at wellfield # 1,
southside high school, iron removing plant, New Water Treatment
Plant
24,700
$3,012,750
50
$3,330,854,633
16627
Nassau
CARLE PLACE WD / Carle
Place WD
Wells #3 & #4, Terrace Drive, Carle Place, NY, New Water
Treatment Plant
9,005
$1,510,800
50
$3,332,365,433
17191
Yates
PENN YAN VILLAGE / Penn
Yan (V)
Upgrade Water Treatment Plant
5,248
$1,300,000
50
$3,333,665,433
15240
Jefferson
ALEXANDRIA VILLAGE /
Alexandria Bay (V)
Upgrade Surface Water Source, Upgrade Storage, Upgrade
Distribution System
1,900
$3,048,188
50
$3,336,713,621
17982
Steuben
PRATTSBURGH WATER
DISTRICT / Prattsburgh (T)
Upgrade Storage, Upgrade Distribution System
850
$1,485,415
50
$3,338,199,036
17319
Putnam
MOUNTAIN BROOK HOMES New Water Treatment Plant, New Ground Water Source
/ Southeast (T)
176
$427,000
50
$3,338,626,036
16880
Seneca
INTERLAKEN VILLAGE /
Interlaken (V)
Upgrade Ground Water Source
650
$320,807
50
$3,338,946,843
15287
Cortland
VIRGIL (T) / Virgil (T)
Upgrade Ground Water Source, New Storage, Extend Distribution
System, System Consolidation
345
$2,223,234
50
$3,341,170,077
17918
Erie
BUFFALO WATER
AUTHORITY / Buffalo (C)
Upgrade Other Expenses, Upgrade Other (OT)
276,000
$7,945,178
50
$3,349,115,255
15297
Cortland
HOMER VILLAGE-NEWTON Upgrade Distribution System
WATER WORKS / Homer (V)
4,368
$440,000
50
$3,349,555,255
17921
Oneida
EUREKA ROAD WD /
Westmoreland (T)
35
$180,000
50
$3,349,735,255
New Pump Station, New Distribution System
CODES Legend *
ARRAF=American Recovery Reinvestment Act Financed
GIC=Green Infrastructure Components
FGP=Funded through SRF Bond Guarantee Program
CAT_G=Green Innovative Grants Program Project
Page 20 of 35
Project #
County
CODES See legend*
NYS Drinking Water State Revolving Fund Final Readiness List
October 1, 2011 to September 30, 2012
System Name/
Borrower
Description
Pop.
Project Cost Score
Cumulative
Total
17378
Ontario
GORHAM TOWN WD /
Gorham (T)
Extension No. 9., Extend Distribution System
4,500
$732,000
50
$3,350,467,255
16449
Albany
GREEN ISLAND VILLAGE /
Green Island (V)
Extend Distribution System
2,900
$381,100
50
$3,350,848,355
18018
Wyoming
CASTILE VILLAGE / Castile
(V)
Upgrade Other Expenses, Upgrade Storage, Upgrade Distribution
System, New System Consolidation, Upgrade Other (OT)
1,135
$2,444,813
50
$3,353,293,168
17899
Genesee
WD II / Alabama (T)
Extend Water District
1,056
$5,416,206
50
$3,358,709,374
17596
Tioga
SPENCER (V) / Spencer (V)
New Complete System (New System), New System Consolidation
731
$7,865,000
50
$3,366,574,374
17978
Jefferson
NORTHEAST WATER
DISTRICT / Waertown (T)
New Ground Water Source, New Storage, New Distribution System
550
$6,177,300
50
$3,372,751,674
17327
Onondaga
CROSS LAKE/N. ELBRIDGE New Storage, New Pump Station, Extend Distribution System
AREA WD / Elbridge (T)
534
$2,590,450
50
$3,375,342,124
16205
Oswego
SENECA HILLS HEALTH
CAMPUS / Volney (T)
450
$1,115,000
50
$3,376,457,124
16908
Chautauqua
BUSTI (T) WATER DISTRICT Extend Distribution System
#3 / Busti (T)
450
$750,000
50
$3,377,207,124
17223
Cayuga
Extend Distribution System
WEST GENESEE STREET
WATER DISTRICT / Aurelius
(T)
175
$1,198,000
50
$3,378,405,124
17026
Seneca
BOODY'S HILL WD (WATER Extend to serve private contaminated wells. , Extend Distribution
System
DISTRICT #5) / Fayette (T)
151
$788,980
50
$3,379,194,104
17058
Jefferson
HOUNSFIELD (T) WD #2
EXTENSION / Hounsfield (T)
Extend Distribution System
123
$794,439
50
$3,379,988,543
17895
Livingston
LONG POINT ROAD WD /
Geneseo(T)
Extend Water District
100
$1,115,000
50
$3,381,103,543
17326
Onondaga
LAIRD ROAD WATER
DISTRICT / Elbridge (T)
Extend Distribution System
29
$378,000
50
$3,381,481,543
17860
Nassau
JERICHO WD / Oyster Bay
(T)
VOC treatment at Kirby Lane., Upgrade Water Treatment Plant
58,000
$2,215,000
45
$3,383,696,543
17862
Nassau
JERICHO WD / Oyster Bay
(T)
New well at Well #28 site., New Ground Water Source
58,000
$2,150,000
45
$3,385,846,543
16168
Saratoga
SARATOGA SPRINGS CITY / Upgrade Water Treatment Plant, Upgrade Surface Water Source,
New Transmission, New Pump Station
Saratoga Springs (C)
26,525
$15,820,000
45
$3,401,666,543
16136
Westchester
ELMSFORD VILLAGE /
Elmsford (V)
Upgrade Water Treatment Plant
4,600
$1,000,000
45
$3,402,666,543
15834
Wayne
PALMYRA VILLAGE /
Palmyra (V)
New Pump Station
3,550
$102,700
45
$3,402,769,243
17941
Herkimer
MIDDLEVILLE (V) WATER
WORKS / Middleville (V)
Upgrade Ground Water Source, Upgrade Pump Station, Upgrade
Distribution System
$3,453,415
45
$3,406,222,658
Upgrade Distribution System
725
CODES Legend *
ARRAF=American Recovery Reinvestment Act Financed
GIC=Green Infrastructure Components
FGP=Funded through SRF Bond Guarantee Program
CAT_G=Green Innovative Grants Program Project
Page 21 of 35
Project #
County
CODES See legend*
NYS Drinking Water State Revolving Fund Final Readiness List
October 1, 2011 to September 30, 2012
System Name/
Borrower
Description
18058
Ulster
KINGSTON (CITY) WATER
DISTRICT / City of Kingston
Water Dep.
Replacement of Mink Hollow Raw Water Intake, Upgrade Other
Expenses, Upgrade Other (OT)
18052
Jefferson
CAPE VINCENT VILLAGE /
Cape Vincent (V)
Upgrade Water Treatment Plant
17929
Steuben
PINEWOOD ACRES WATER Upgrade Storage, Upgrade Pump Station, Upgrade Distribution
System
DISTRICT / Corning
15353
Schenectady
SCHENECTADY CITY
WATER WORKS /
Schenectady (C)
15986
Niagara
15988
Pop.
Project Cost Score
Cumulative
Total
24,000
$713,000
45
$3,406,935,658
1,500
$3,200,000
45
$3,410,135,658
168
$3,426,552
45
$3,413,562,210
Distribution improvements - Elimination of deadends, Upgrade
Distribution System
61,821
$1,170,150
45
$3,414,732,360
NIAGARA FALLS WATER
BOARD / Niagara Falls (C)
Upgrade Distribution System
55,593
$390,000
45
$3,415,122,360
Niagara
NIAGARA FALLS WATER
BOARD / Niagara Falls (C)
McKoon Ave., West Rivershore Dr., Upgrade Distribution System
55,593
$466,920
45
$3,415,589,280
17914
Nassau
Contruction of new Well #14 at Community Drive, New Ground
WA OF GREAT NECK
NORTH / Water Auth of Great Water Source
Neck North
31,400
$2,000,000
45
$3,417,589,280
16749
Orange
KIRYAS JOEL VILLAGE /
Kiryas Joel (V)
Upgrade Pump Station
21,750
$872,247
45
$3,418,461,527
17945
Sullivan
MONTICELLO VILLAGE /
Monticello (V)
Upgrade storage and distribution piping, Upgrade Storage, Upgrade
Distribution System
8,000
$7,395,000
45
$3,425,856,527
17055
Herkimer
FRANKFORT (V) WATER
WORKS / Frankfort (V)
New Ground Water Source
2,995
$481,691
45
$3,426,338,218
17057
Herkimer
FRANKFORT (V) WATER
WORKS / Frankfort (V)
Upgrade Distribution System
2,995
$1,971,007
45
$3,428,309,225
15547
Allegany
FRIENDSHIP TOWN WATER Upgrade Ground Water Source, Upgrade Storage, Upgrade
Distribution System
DISTRICT / Friendship (T)
1,380
$1,030,000
45
$3,429,339,225
17226
Franklin
CHATEAUGAY (T) WD#1 /
Chateaugay (T)
New Water District
100
$114,075
45
$3,429,453,300
17402
Suffolk
WEST NECK WATER
SUPPLY / Shelter Island (T)
New Well, New Ground Water Source
100
$2,000
45
$3,429,455,300
15724
Chautauqua
LAKEWOOD VILLAGE /
Lakewood (V)
New Transmission, New Pump Station, Inter-Connection
3,258
$870,000
45
$3,430,325,300
16512
Wayne
OLD LYONS-NEWARK
ROAD WATER DISTRICT /
Lyons (T)
New Transmission
300
$207,000
45
$3,430,532,300
17453
Broome
LILIAN DRIVE WD /
Binghamton (T)
New Pump Station, Upgrade Distribution System, New
Inter-Connection, New System Consolidation, New Water District
120
$281,000
45
$3,430,813,300
17953
Montgomery
NELLISTON VILLAGE /
Nelliston (V)
New Storage, Upgrade Distribution System
375
$4,493,000
45
$3,435,306,300
15078
Orange
HOLIDAY MOBILE PARK
INC. / Mid-Hudson Park
Management
Upgrade Distribution System, System Consolidation
250
$412,000
45
$3,435,718,300
16065
Suffolk
RIVERHEAD WD / Riverhead Water District Extension No. 47-Herricks Lane., Extend Distribution
System
(T)
$1,165,000
45
$3,436,883,300
28,000
CODES Legend *
ARRAF=American Recovery Reinvestment Act Financed
GIC=Green Infrastructure Components
FGP=Funded through SRF Bond Guarantee Program
CAT_G=Green Innovative Grants Program Project
Page 22 of 35
Project #
County
CODES See legend*
NYS Drinking Water State Revolving Fund Final Readiness List
October 1, 2011 to September 30, 2012
System Name/
Borrower
Description
Pop.
Project Cost Score
Cumulative
Total
16066
Suffolk
RIVERHEAD WD / Riverhead New Ground Water Source, New Pump Station
(T)
28,000
$1,413,000
45
$3,438,296,300
16071
Suffolk
RIVERHEAD WD / Riverhead Water District Extension No. 49 Middle Rd. & Harrison Ave., Extend
Distribution System
(T)
28,000
$135,600
45
$3,438,431,900
17831
Westchester
KENSICO WATER DISTRICT Hardscrabble Road Water Main, Extend Distribution System
/ Mount Pleasant
17,857
$4,588,500
45
$3,443,020,400
17833
Westchester
KENSICO WATER DISTRICT Choate Lane Water Main Extension, Extend Distribution System
/ Mount Pleasant
17,857
$532,000
45
$3,443,552,400
17755
Genesee
MCWA GENESEE / Byron (T) New Distribution System
13,250
$148,000
45
$3,443,700,400
17764
Genesee
MCWA GENESEE / Byron (T) New Water District
13,250
$161,000
45
$3,443,861,400
15276
Montgomery
GLEN (T) W.D.#1 / Glen (T)
Extend Distribution System
5,000
$950,000
45
$3,444,811,400
15664
Niagara
HARTLAND WD / Hartland (T) Extend Distribution System
4,165
$726,500
45
$3,445,537,900
16612
Ontario
NORTH FARMINGTON WD / Fox Road & County Road 28., Extend Distribution System
Farmington (T)
2,300
$155,128
45
$3,445,693,028
16698
Ontario
GENEVA (T) / Geneva (T)
New Storage, New Distribution System
1,500
$2,541,000
45
$3,448,234,028
17922
Oneida
NORTHEASTERN WD /
Westmoreland (T)
New Storage, New Pump Station, New Distribution System
880
$6,700,000
45
$3,454,934,028
16442
Suffolk
NORTHEAST WOODS / East Northeast Woods, East Hampton (T), Extend Distribution System
Hampton (T)
675
$2,524,278
45
$3,457,458,306
16313
Onondaga
TOWN OF LYSANDER W.D. / Lamson Road Water District., New Distribution System, New Water
District
Lysander (T)
500
$5,284,000
45
$3,462,742,306
17672
Erie
EDEN WD#6 / Eden (T)
Eden WD#6, New Distribution System
500
$420,000
45
$3,463,162,306
16687
Chenango
NORWICH TOWN WATER
DISTRICT #2 / Norwich (T)
Extend Distribution System
200
$390,885
45
$3,463,553,191
17811
Cayuga
CAYUGA COUNTY WATER
& SEWER / Cayuga County
W&SA
New Centerport / Sine Roads WD in (T) Throop., Extend Distribution
System, New Water District
200
$818,850
45
$3,464,372,041
17671
Erie
EDEN WD#5 / Eden (T)
Eden WD#5, New Distribution System
150
$5,880,000
45
$3,470,252,041
17677
Genesee
WATER DISTRICT #5 /
Stafford (T)
Extend Distribution System
123
$927,000
45
$3,471,179,041
16801
Broome
CHENANGO WD #8 /
Chenango (T)
New Water District
100
$121,000
45
$3,471,300,041
16802
Broome
CHENANGO WD #4 /
Chenango (T)
New Water District
100
$112,450
45
$3,471,412,491
CODES Legend *
ARRAF=American Recovery Reinvestment Act Financed
GIC=Green Infrastructure Components
FGP=Funded through SRF Bond Guarantee Program
CAT_G=Green Innovative Grants Program Project
Page 23 of 35
Project #
County
CODES See legend*
NYS Drinking Water State Revolving Fund Final Readiness List
October 1, 2011 to September 30, 2012
System Name/
Borrower
Description
Pop.
Project Cost Score
Cumulative
Total
16884
Monroe
SOUTH CHILI WATER IMP.
BENEFIT AREA NO. 2 / Chili
(T)
Extend Distribution System
100
$386,250
45
$3,471,798,741
17066
Genesee
BYRON (T) WD NO. 3 / Byron Extend to serve private contaminated wells in the Hamlet of North
Byron., Extend Distribution System
(T)
100
$148,000
45
$3,471,946,741
17768
Genesee
WATER DISTRICT #8 /
Stafford (T)
New Distribution System
90
$859,700
45
$3,472,806,441
17601
Putnam
GARRISON LANDING WS /
Philipstown (T)
New Complete System (New System)
84
$325,146
45
$3,473,131,587
15295
Dutchess
BEEKMAN (T) / Beekman (T) New Complete System (New System), New Distribution System
80
$579,478
45
$3,473,711,065
17676
Genesee
WATER DISTRICT #7 /
Stafford (T)
Extend Distribution System
75
$679,700
45
$3,474,390,765
16575
Genesee
BARBARY COAST MHP /
Affordable Great Locations
Extend Distribution System
50
$82,700
45
$3,474,473,465
15417
Albany
Extend Distribution System
KRUMKILL RD. WATER
DISTRICT / New Scotland (T)
45
$2,500,000
45
$3,476,973,465
15969
Broome
VESTAL CONSOLIDATED
W.D. #1 / Vestal (T)
New Water Treatment Plant
20,950
$1,700,000
40
$3,478,673,465
17318
Nassau
AQUA NY OF SEA CLIFF /
Sea Cliff Water Company
New Storage
15,000
$1,371,000
40
$3,480,044,465
15101
Wayne
ONTARIO TOWN BENEFIT
AREA #1 / Ontario (T)
New Transmission, New Storage
10,462
$4,913,000
40
$3,484,957,465
15616
Ulster
PORT EWEN WATER
DISTRICT / Esopus (T)
New Storage
4,800
$2,100,000
40
$3,487,057,465
15895
Warren
CHESTERTOWN WATER
DISTRICT / Chester (T)
Corrosion Control , Upgrade Ground Water Source
1,300
$2,500
40
$3,487,059,965
15629
Steuben
HAMMONDSPORT VILLAGE Upgrade Distribution System
/ Hammondsport (V)
741
$405,000
40
$3,487,464,965
17804
Cayuga
WELLS COLLEGE / Wells
College
Upgrade Water Treatment Plant, Upgrade Distribution System
400
$1,642,850
40
$3,489,107,815
15884
Warren
POTTERSVILLE WATER
DISTRICT / Chester (T)
Upgrade Ground Water Source
325
$14,400
40
$3,489,122,215
17957
Dutchess
BARD COLLEGE / Bard
College
New microfiltration plant.,
1,400
$991,620
40
$3,490,113,835
1,738
$154,039
40
$3,490,267,874
400
$386,250
40
$3,490,654,124
$4,403,400
40
$3,495,057,524
ARRAF GIC
CAT_G
15944
Chenango
OXFORD VILLAGE / Oxford
(V)
New Ground Water Source, Upgrade Distribution System
15229
Orange
SLEEPY HOLLOW MOBILE
PARK / Sleepy Hollow MHP,
LLC
Upgrade Transmission, Upgrade Distribution System
17409
Nassau
PLAINVIEW WD / Oyster Bay Air stripper at Plant 2, New Water Treatment Plant
(T)
35,000
CODES Legend *
ARRAF=American Recovery Reinvestment Act Financed
GIC=Green Infrastructure Components
FGP=Funded through SRF Bond Guarantee Program
CAT_G=Green Innovative Grants Program Project
Page 24 of 35
Project #
County
CODES See legend*
NYS Drinking Water State Revolving Fund Final Readiness List
October 1, 2011 to September 30, 2012
System Name/
Borrower
Description
Pop.
Project Cost Score
Cumulative
Total
17420
Dutchess
POUGHKEEPSIE CITY /
Poughkeepsie (C)
Upgrade Distribution System
28,000
$4,223,000
40
$3,499,280,524
17421
Dutchess
POUGHKEEPSIE CITY /
Poughkeepsie (C)
College Hill Reservoir., New Storage
28,000
$6,746,500
40
$3,506,027,024
16244
Albany
COHOES CITY / Cohoes (C)
Upgrade Distribution System
15,550
$1,025,000
40
$3,507,052,024
15677
Oswego
FULTON CITY / Fulton (C)
Upgrade Storage
15,400
$412,000
40
$3,507,464,024
17827
St.Lawrence
OGDENSBURG CITY /
Ogdensburg (C)
Upgrade Transmission
13,500
$351,250
40
$3,507,815,274
18070
Wayne
TRANSMISSION MAIN
REPLACEMENT / Clyde(V)
Upgrade Transmission
2,270
$357,900
40
$3,508,173,174
16330
Monroe
MCWA SHOREMONT WTP System Consolidation
/ Monroe Co. Water Authority
310,000
$1,772,057
40
$3,509,945,231
15308
Livingston
EAST LAKE ROAD WATER
DISTRICT / Livonia (T)
1,450
$2,093,140
40
$3,512,038,371
15129
Albany
New Complete System (New System)
NORTHEAST WATER
DISTRICT / New Scotland (T)
370
$843,905
40
$3,512,882,276
15209
Ontario
PHELPS (T) - ROUTE 96
WEST WD / Phelps (T)
300
$1,132,000
40
$3,514,014,276
15554
Ontario
Canandaigua. (T), Extend Distribution System
WEST LAKE RD BENEFIT
BASIS DIS / Canandaigua (T)
220
$1,243,100
40
$3,515,257,376
15148
Monroe
OGDEN (T) / Ogden (T)
Extend Distribution System
171
$429,330
40
$3,515,686,706
16799
Broome
CHENANGO WD #25 /
Chenango (T)
New WD to serve private insufficient yielding wells area of Poplar Hill
Road , New Complete System (New System)
100
$383,500
40
$3,516,070,206
15182
Orange
WOODBURY CONS. W.D. /
Woodbury (T)
New Storage, New Pump Station, Upgrade Distribution System
10,105
$1,564,500
35
$3,517,634,706
17917
Onondaga
CAMILLUS CONSOLIDATED Upgrade Distribution System
WD / Camillus (T)
22,000
$5,035,497
35
$3,522,670,203
18056
Orange
WARWICK VILLAGE /
Warwick (V)
6,083
$323,725
35
$3,522,993,928
17974
Steuben
SOUTH CORNING VILLAGE / Upgrade Storage, Upgrade Distribution System
South Corning (V)
1,147
$7,763,007
35
$3,530,756,935
16073
Rensselaer
PETERSBURGH WATER
DISTRICT / Petersburg (T)
Upgrade Ground Water Source
$109,154
35
$3,530,866,089
16209
Niagara
NIAGARA WATER
IMPROVEMENT AREA /
Niagara County
Contract 14A, E, G & H., Upgrade Water Treatment Plant
8,978
$2,859,246
35
$3,533,725,335
16586
Niagara
NIAGARA WATER
IMPROVEMENT AREA /
Niagara (T)
New Transmission
8,978
$400,000
35
$3,534,125,335
Extend Distribution System
Extend Distribution System
Upgrade Water Treatment Plant, New Ground Water Source
240
CODES Legend *
ARRAF=American Recovery Reinvestment Act Financed
GIC=Green Infrastructure Components
FGP=Funded through SRF Bond Guarantee Program
CAT_G=Green Innovative Grants Program Project
Page 25 of 35
Project #
County
CODES See legend*
NYS Drinking Water State Revolving Fund Final Readiness List
October 1, 2011 to September 30, 2012
System Name/
Borrower
Description
Pop.
Project Cost Score
Cumulative
Total
18030
Rensselaer
RENSSELAER CITY PWS /
Rensselaer (C)
Washington Ave Corridor Improvements, Upgrade Distribution
System
7,500
$3,169,952
35
$3,537,295,287
17262
Orleans
HOLLEY VILLAGE / Holley
(V)
NYS Route 31., Upgrade Distribution System
2,150
$210,243
35
$3,537,505,530
17540
Genesee
OAKFIELD VILLAGE /
Oakfield (V)
Upgrade Transmission, Upgrade Storage, Upgrade Distribution
System
1,805
$2,864,100
35
$3,540,369,630
17791
Delaware
STAMFORD VILLAGE /
Stamford (V)
New Storage, Upgrade Distribution System
1,280
$2,575,000
35
$3,542,944,630
16897
Essex
CROWN POINT WD / Crown
Point (T)
Upgrade Distribution System
995
$1,000,000
35
$3,543,944,630
17595
Essex
FOREVER WILD WATER
CO-SIGNOR / Forever Wild
Water Company
Upgrade Ground Water Source, Upgrade Storage, Upgrade Pump
Station
900
$2,247,987
35
$3,546,192,617
16723
Chemung
WELLSBURG VILLAGE /
Wellsburg (V)
Upgrade Distribution System
631
$644,700
35
$3,546,837,317
15062
Oneida
TAURUSEL, INC (POND
HILL) / Taurusel, Inc.
Upgrade Ground Water Source, Upgrade Distribution System,
System Consolidation
54
$164,000
35
$3,547,001,317
15346
Schenectady
SCHENECTADY CITY
WATER WORKS /
Schenectady (C)
Upgrade Pump Station
61,821
$1,800,476
35
$3,548,801,793
15086
Seneca
BORDER CITY WATER
DISTRICT / Waterloo (T)
Upgrade Distribution System
1,600
$161,340
35
$3,548,963,133
17560
Sullivan
THE CALLICOON WATER
COMPANY INC / Callicoon
Water Co., Inc.
Replace water tower on Delvue Road., New Storage
854
$100,000
35
$3,549,063,133
17887
Cayuga
CATO VILLAGE / Cato (V)
New Storage
601
$1,152,505
35
$3,550,215,638
15087
Sullivan
ROUTE 55 WATER
DISTRICT / Liberty (T)
New Storage, New Pump Station, Upgrade Distribution System
500
$400,000
35
$3,550,615,638
17963
Onondaga
SYRACUSE CITY / Syracuse Install hydroturbine at Westcott Reservoir.,
(C)
192,000
$315,000
35
$3,550,930,638
SYRACUSE CITY / Syracuse Install solar power at Westcott Reservoir.,
(C)
192,000
$487,273
35
$3,551,417,911
ARRAF GIC
17964
Onondaga
ARRAF GIC
17967
CAT_G
CAT_G
Rensselaer
ARRAF GIC
TROY CITY PWS / Troy (C)
Installation of leak detection equipment.,
49,170
$450,000
35
$3,551,867,911
CAT_G
15309
Jefferson
WATERTOWN, CITY OF /
Watertown (C)
Upgrade Distribution System
27,861
$152,955
35
$3,552,020,866
16022
Chautauqua
FREDONIA VILLAGE /
Fredonia (V)
New Transmission, Upgrade Distribution System, System
Consolidation
10,400
$716,800
35
$3,552,737,666
17725
Dutchess
DUTCHESS COUNTY
WATER/WASTEWATER
PLANT / DCWWA
New Distribution System, Extend System Consolidation
7,012
$4,417,000
35
$3,557,154,666
17960
Franklin
SARANAC LAKE V / Saranac Installation of water meters.,
Lake (V)
5,800
$1,000,000
35
$3,558,154,666
ARRAF GIC
CAT_G
CODES Legend *
ARRAF=American Recovery Reinvestment Act Financed
GIC=Green Infrastructure Components
FGP=Funded through SRF Bond Guarantee Program
CAT_G=Green Innovative Grants Program Project
Page 26 of 35
Project #
County
CODES See legend*
17969
Steuben
ARRAF GIC
NYS Drinking Water State Revolving Fund Final Readiness List
October 1, 2011 to September 30, 2012
System Name/
Borrower
BATH VILLAGE / Bath (V)
Description
Installation of solar powered storage tank water circulators.,
Pop.
Project Cost Score
Cumulative
Total
5,641
$437,400
35
$3,558,592,066
CAT_G
16138
Oswego
PHOENIX VILLAGE / Phoenix State Street water main replacement., Upgrade Distribution System
(V)
2,138
$90,125
35
$3,558,682,191
16147
Orange
WESTSIDE GREENWOOD
LAKE W.D. / Warwick (T)
Upgrade Distribution System
1,160
$100,000
35
$3,558,782,191
16246
Dutchess
LITTLE SWITZERLAND /
East Fishkill (T)
Upgrade Distribution System, System Consolidation
450
$428,900
35
$3,559,211,091
15938
Dutchess
TACONIC ESTATES WATER New Ground Water Source, System Consolidation
DISTRICT / East Fishkill (T)
185
$148,000
35
$3,559,359,091
16461
Dutchess
STONY CREEK FARMS
(TOWN HOMES / Stoney
Creek Farms Homeowners
New Water Treatment Plant
21
$18,000
30
$3,559,377,091
15635
Orange
WASHINGTONVILLE
VILLAGE / Washingtonville
(V)
Upgrade Ground Water Source, Upgrade Distribution System
7,000
$435,000
30
$3,559,812,091
17324
Tioga
CONSOLIDATED WATER
DISTRICT / Owego (T)
Upgrade Storage, Upgrade Pump Station
10,306
$3,669,000
30
$3,563,481,091
18037
Ulster
MARLBOROUGH WATER
DISTRICT / (T) Marlborough
New Transmission, New Storage, Upgrade Distribution System
3,248
$16,879,640
30
$3,580,360,731
17370
NY City
Reconstruction of Delaware Aqueduct, Shafts 9,10 & 17, Upgrade
NEW YORK
CITY-CATSKILL/DELAWARE Transmission
SYSTEM / NYCMWFA
6,552,718
$35,066,289
30
$3,615,427,020
17371
NY City
Inspection and Rehabilitation of New Croton Aqueduct, Upgrade
NEW YORK
CITY-CATSKILL/DELAWARE Transmission
SYSTEM / NYCMWFA
6,552,718
$28,130,420
30
$3,643,557,440
17397
Erie
ECWA DIRECT / Erie County 36 inch transmission main on Sweet Home Road., New
Transmission
Water Authority
228,869
$5,323,909
30
$3,648,881,349
15365
Sullivan
New 400,000 gallon potable water stand pipe and distribution system
WURTSBORO VILLAGE
WATER SUPPLY / Wurtsboro improvements, New Storage, Upgrade Distribution System
(V)
1,060
$1,545,000
30
$3,650,426,349
17517
Niagara
LOCKPORT CITY WTP /
Lockport (C)
22,279
$640,000
30
$3,651,066,349
17882
Fulton
BROADALBAN (V) / Broadalin Replace Aged Storage Tank, New Storage
(V)
1,500
$1,990,000
30
$3,653,056,349
17787
Schoharie
SCHOHARIE VILLAGE /
Schoharie (V)
Upgrade Distribution System
1,030
$2,570,000
30
$3,655,626,349
17905
Warren
LAKE GEORGE VILLAGE /
Lake George (V)
Upgrade Distribution System
2,160
$1,650,675
30
$3,657,277,024
17956
Delaware
ROXBURY WATER
DISTRICT / Roxbury (T)
Installation of water meters.,
755
$358,178
30
$3,657,635,202
526
$102,935
30
$3,657,738,137
29,000
$586,438
25
$3,658,324,575
ARRAF GIC
Replace waterline on Market St. between Union and Spring ,
Upgrade Distribution System
CAT_G
16720
Wayne
RED CREEK VILLAGE / Red Upgrade Distribution System
Creek (V)
15135
Saratoga
CLIFTON PARK WATER
AUTHORITY / Clifton Park
Water Authority
New Storage
CODES Legend *
ARRAF=American Recovery Reinvestment Act Financed
GIC=Green Infrastructure Components
FGP=Funded through SRF Bond Guarantee Program
CAT_G=Green Innovative Grants Program Project
Page 27 of 35
Project #
County
CODES See legend*
NYS Drinking Water State Revolving Fund Final Readiness List
October 1, 2011 to September 30, 2012
System Name/
Borrower
Description
15966
Orange
CORNWALL-ON-HUDSON /
Cornwall-On-Hudson (V)
Upgrade Water Treatment Plant
17909
Westchester
YONKERS CITY / Yonkers
(C)
17910
Westchester
15123
Pop.
Project Cost Score
Cumulative
Total
9,300
$2,935,257
25
$3,661,259,832
Upgrade electrical service and pumps Nepperhan Ave. and Tuckhoe
Road, Upgrade Pump Station
196,086
$3,968,048
25
$3,665,227,880
YONKERS CITY / Yonkers
(C)
Upgrade electrical service and pumps at Hillview Pump Station,
Upgrade Pump Station
196,086
$3,180,691
25
$3,668,408,571
Saratoga
CLIFTON PARK WATER
AUTHORITY / Clifton Park
Water Authority
New Ground Water Source
29,000
$5,020,918
25
$3,673,429,489
17908
Suffolk
SALTARE WATER DISTRICT Infrastructure upgrade, Upgrade Water Treatment Plant, Upgrade
Storage
/ Saltaire (V)
1,400
$668,000
25
$3,674,097,489
17524
Westchester
NORTH CASTLE WD #2 /
North Castle (T)
1,200
$1,458,695
25
$3,675,556,184
16250
Oneida
J.E. BARRETT WD / Prospect Upgrade Ground Water Source, New Storage, Upgrade Distribution
System
(V)
$326,000
25
$3,675,882,184
17582
Westchester
SCARSDALE WATER
DEPARTMENT / Scarsdale
(V)
20,883
$3,700,000
25
$3,679,582,184
16015
Westchester
Upgrade Distribution System
BRIARCLIFF MANOR
VILLAGE / Briarcliff Manor (V)
8,831
$2,845,400
25
$3,682,427,584
15401
Clinton
PERU WD / Peru (T)
Upgrade Surface Water Source, New Transmission
2,600
$620,000
25
$3,683,047,584
17741
Schenectady
ROTTERDAM WD #3 /
Rotterdam (T)
Construction of new storage tank and transmission main, New
Transmission, New Storage
2,000
$2,060,000
25
$3,685,107,584
17795
Clinton
MORRISONVILLE WATER
DISTRICT / Plattsburgh (T)
Upgrade Pump Station
1,300
$225,320
25
$3,685,332,904
15228
Orange
PINE GROVE MOBILE HOME New Water Treatment Plant, Upgrade Transmission, New Storage,
PARK / Pine Grove MHP, LLC Upgrade Distribution System
516
$484,100
25
$3,685,817,004
15634
Cayuga
SENNETT WD #1 / Sennett
(T)
Upgrade Distribution System
200
$470,339
25
$3,686,287,343
17683
Clinton
PLEASANT RIDGE WD /
Plattsburgh (T)
New Storage
168
$3,190,000
25
$3,689,477,343
17341
Albany
SOUTH ALBANY WATER
DISTRICT / Bethlehem (T)
New Transmission
80
$146,775
25
$3,689,624,118
17340
Clinton
GREATER PLATTSBURGH
WATER DISTRICT /
Plattsburgh (T)
New Other Expenses, New Other (OT)
10,000
$541,000
25
$3,690,165,118
15896
Warren
CHESTERTOWN WATER
DISTRICT / Chester (T)
Well #1 - Rehab and Testing, Upgrade Ground Water Source
1,300
$15,500
25
$3,690,180,618
15893
Jefferson
ADAMS (T) WD #1 & 2
(ADAMS CENTER) / Adams
Center (T)
Upgrade Storage
1,000
$121,954
25
$3,690,302,572
15805
Warren
WARRENSBURG WATER
DISTRICT / Warrensburg (T)
Upgrade Ground Water Source
3,600
$375,000
25
$3,690,677,572
New well and storage, New Ground Water Source, New Storage
Upgrade Ardsley Road Pumping Station, Upgrade Pump Station
150
CODES Legend *
ARRAF=American Recovery Reinvestment Act Financed
GIC=Green Infrastructure Components
FGP=Funded through SRF Bond Guarantee Program
CAT_G=Green Innovative Grants Program Project
Page 28 of 35
Project #
County
CODES See legend*
17965
Oswego
ARRAF GIC
NYS Drinking Water State Revolving Fund Final Readiness List
October 1, 2011 to September 30, 2012
System Name/
Borrower
Description
Pop.
Project Cost Score
Cumulative
Total
RICHLAND TOWN PWS /
Richland (T)
Wind power generation at Schoeller well site.,
2,350
$585,000
25
$3,691,262,572
CAT_G
16481
Jefferson
VILLAGE OF CLAYTON /
Clayton (V)
New Transmission, New Distribution System
2,160
$214,000
25
$3,691,476,572
17939
Herkimer
OLD FORGE (V) WATER
DISTRICT / Webb (T)
Upgrade Distribution System, Extend Distribution System
1,766
$561,350
25
$3,692,037,922
15268
Madison
EARLVILLE VILLAGE /
Earlville (V)
East Main Street., Upgrade Distribution System
790
$96,509
25
$3,692,134,431
17961
Jefferson
LAFARGEVILLE (T.
ORLEANS) / Orleans (T)
Installation of water meters.,
750
$208,078
25
$3,692,342,509
$1,459,374
20
$3,693,801,883
ARRAF GIC
CAT_G
16167
Erie
GRAND ISLAND (T) / Grand
Island (T)
Upgrade Water Treatment Plant
15951
Orange
VALLEY VIEW CTR FOR
NURSING CARE & REHAB /
Orange County
New Water Treatment Plant, New Ground Water Source, New
Storage, Upgrade Distribution System
851
$572,474
20
$3,694,374,357
15538
Tompkins
LANSING WD #2 / Lansing
(T)
New Storage, New Pump Station, Upgrade Distribution System
400
$443,500
20
$3,694,817,857
17785
Nassau
LONG ISLAND AMERICAN
WATER CORP / Long Island
American Water
Plant No. 8 Iron Removal, New Water Treatment Plant
230,300
$7,100,000
20
$3,701,917,857
17840
Westchester
WESTCHESTER JOINT
WATER WORKS / WJWW
York Road Transmission Main, Upgrade Transmission
65,000
$630,000
20
$3,702,547,857
17839
Westchester
WESTCHESTER JOINT
WATER WORKS / WJWW
Flagler Drive Transmission Main, Upgrade Transmission
55,210
$840,000
20
$3,703,387,857
17816
Orange
NEW WINDSOR
CONSOLIDATED WD / New
Winsor (T)
Reactivation of St. Anne's Well, Upgrade Ground Water Source
30,000
$748,000
20
$3,704,135,857
17977
Orange
NEW WINDSOR
CONSOLIDATED WD / New
Windsor (T)
Rehabilitate St. Anne Well Field, Upgrade Water Treatment Plant,
Upgrade Ground Water Source
30,000
$748,000
20
$3,704,883,857
17264
Niagara
LEWISTON WATER
IMPROVEMENTAREA /
Lewiston (T)
Upgrade Transmission, Upgrade Distribution System
16,257
$5,000,000
20
$3,709,883,857
15281
Nassau
ALBERTSON WD / North
Hempstead (T)
Well #4 Replacement of Screen and Well Pump, Upgrade Ground
Water Source
13,500
$188,044
20
$3,710,071,901
15175
Orange
WOODBURY CONS. W.D. /
Woodbury (T)
New Ground Water Source, New Pump Station
10,105
$291,500
20
$3,710,363,401
16053
Niagara
CAMBRIA WATER DISTRICT New Storage, New Pump Station, Upgrade Distribution System
/ Cambria (T)
5,393
$1,000,000
20
$3,711,363,401
16041
Ontario
GORHAM TOWN WD /
Gorham (T)
New Pump Station, Upgrade Distribution System
4,500
$141,280
20
$3,711,504,681
17772
Saratoga
BURNT HILLS-BALLSTON
LK WD (GLENVILLE) /
Ballston (T)
New Pump Station, Extend Distribution System
4,500
$606,052
20
$3,712,110,733
17400
Orange
HIGHLAND FALLS VILLAGE / Water Treatment Plant Filter Upgrades, Upgrade Water Treatment
Plant
Highland Falls (V)
4,400
$800,000
20
$3,712,910,733
18,000
CODES Legend *
ARRAF=American Recovery Reinvestment Act Financed
GIC=Green Infrastructure Components
FGP=Funded through SRF Bond Guarantee Program
CAT_G=Green Innovative Grants Program Project
Page 29 of 35
Project #
County
CODES See legend*
NYS Drinking Water State Revolving Fund Final Readiness List
October 1, 2011 to September 30, 2012
System Name/
Borrower
Description
Pop.
Upgrade Transmission
2,666
18041
Putnam
COLD SPRING VILLAGE /
Cold Spring (V)
17920
Oneida
WESTMORELAND WD NO 1 New Ground Water Source, Upgrade Storage
(GU) / Westmoreland (T)
17565
Orange
BRITTANY TERRACE /
Brittany Terrace, Inc.
New water storage tank, New Storage
18000
Dutchess
BEACON CITY / Beacon (C)
18001
Dutchess
17583
Project Cost Score
Cumulative
Total
$958,000
20
$3,713,868,733
600
$2,850,000
20
$3,716,718,733
169
$215,000
20
$3,716,933,733
Upgrade Distribution System
19,000
$972,907
20
$3,717,906,640
BEACON CITY / Beacon (C)
Upgrade Distribution System
19,000
$509,737
20
$3,718,416,377
Nassau
OYSTER BAY WD / Oyster
Bay (T)
VOC removal at Plant #2., New Water Treatment Plant
8,700
$1,597,530
20
$3,720,013,907
15755
Albany
RAVENA VILLAGE / Ravena
(V)
New Storage
4,500
$497,500
20
$3,720,511,407
15832
Wayne
PALMYRA VILLAGE /
Palmyra (V)
Upgrade Surface Water Source
3,550
$291,050
20
$3,720,802,457
15914
Wayne
PALMYRA VILLAGE /
Palmyra (V)
Upgrade Transmission
3,550
$1,581,250
20
$3,722,383,707
15918
Wayne
PALMYRA VILLAGE /
Palmyra (V)
Upgrade Storage
3,550
$189,750
20
$3,722,573,457
15045
Oneida
CLINTON VILLAGE / Clinton
(V)
Upgrade Distribution System
3,000
$822,000
20
$3,723,395,457
15691
Greene
SLEEPY HOLLOW LAKE
WATER CO. / Sleepy Hollow
Lake Assoc.
Upgrade Surface Water Source, Upgrade Storage
2,000
$1,144,330
20
$3,724,539,787
17383
Genesee
OAKFIELD VILLAGE /
Oakfield (T)
Upgrade Transmission
1,805
$1,661,600
20
$3,726,201,387
16885
Ontario
WEST BLOOMFIELD WD /
West Bloomfield (T)
Cathodic protection system., Upgrade Storage
1,500
$13,390
20
$3,726,214,777
17802
Jefferson
MADISON BARRACKS
WATER SYSTEM / Sackets
Harbor (V)
Upgrade Distribution System
1,000
$1,700,000
20
$3,727,914,777
16758
Erie
W. SENECA WD#3 / West
Seneca (T)
Orchard Park Road Watermain, Upgrade Distribution System
520
$460,000
20
$3,728,374,777
17419
Dutchess
WAPPINGERS FALLS
VILLAGE / Wappinger Falls
(V)
Upgrade Storage, New Storage, Upgrade Distribution System
6,000
$6,238,532
20
$3,734,613,309
17325
Onondaga
MINOA VILLAGE / Minoa (V)
Upgrade Distribution System
3,745
$307,336
20
$3,734,920,645
15897
Warren
CHESTERTOWN WATER
DISTRICT / Chester (T)
Upgrade Distribution System
1,300
$42,200
20
$3,734,962,845
17970
Sullivan
Installation of water meters.,
WURTSBORO VILLAGE
WATER SUPPLY / Wurtsboro
(V)
1,060
$201,438
20
$3,735,164,283
ARRAF GIC
CAT_G
CODES Legend *
ARRAF=American Recovery Reinvestment Act Financed
GIC=Green Infrastructure Components
FGP=Funded through SRF Bond Guarantee Program
CAT_G=Green Innovative Grants Program Project
Page 30 of 35
Project #
County
CODES See legend*
17966
Rensselaer
ARRAF GIC
17968
System Name/
Borrower
Description
Pop.
Project Cost Score
Cumulative
Total
Installation of water meters.,
675
$75,000
20
$3,735,239,283
SHARON SPRINGS VILLAGE Installation of water meters.,
/ Sharon Springs (V)
547
$203,148
20
$3,735,442,431
SCHAGHTICOKE (V) PWS /
Schaghticoke (V)
CAT_G
Schoharie
ARRAF GIC
NYS Drinking Water State Revolving Fund Final Readiness List
October 1, 2011 to September 30, 2012
CAT_G
15312
Westchester
CROTON FALLS WATER
DISTRICT / North Salem (T)
Upgrade Distribution System
175
$121,339
20
$3,735,563,770
16494
Clinton
CHAMPLAIN (T) / Champlain System Acquisition-"Benefit Area #1", New Ground Water Source,
New Distribution System
(T)
50
$497,200
20
$3,736,060,970
15136
Saratoga
CLIFTON PARK WATER
AUTHORITY / Clifton Park
Water Authority
New Water Treatment Plant
29,000
$1,005,713
15
$3,737,066,683
15469
Erie
WILLIAMSVILLE (V) /
Williamsville (V)
Los Robles Street water reconstruction project., Upgrade Distribution
System
6,017
$408,447
15
$3,737,475,130
15556
Tompkins
LANSING WD #2 / Lansing
(T)
Extend Distribution System
400
$117,300
15
$3,737,592,430
17786
Nassau
LONG ISLAND AMERICAN
WATER CORP / Long Island
American Water
Water main replacements, Upgrade Distribution System
230,300
$10,900,000
15
$3,748,492,430
18048
Westchester
YONKERS CITY / Yonkers
(C)
Upgrade Distribution System
196,086
$7,279,450
15
$3,755,771,880
17774
Westchester
WESTCHESTER COUNTY
WD #1 / Westchester County
#1
Shaft 22 Chlorination Facility Security Improvements, Upgrade Water
Treatment Plant
187,004
$1,000,000
15
$3,756,771,880
17351
Suffolk
SOUTH HUNTINGTON WD / Rehabilitation of Plant No. 4, Upgrade Water Treatment Plant
Huntington (T)
81,760
$1,551,077
15
$3,758,322,957
17365
Suffolk
SOUTH HUNTINGTON WD / Contruction of Plant 20, New Water Treatment Plant
Huntington (T)
81,760
$3,270,250
15
$3,761,593,207
17890
Suffolk
SOUTH HUNTINGTON WD / Plant 14 Standpipe Rehabilitation, Upgrade Storage
Huntington (T)
81,760
$1,905,500
15
$3,763,498,707
17837
Westchester
WESTCHESTER JOINT
WATER WORKS / WJWW
Anderson Hill Road Booster Pump Station, New Pump Station
65,000
$400,000
15
$3,763,898,707
17838
Westchester
WESTCHESTER JOINT
WATER WORKS / WJWW
Rye Lake generator, Upgrade Water Treatment Plant
55,210
$475,000
15
$3,764,373,707
16421
Nassau
MASSAPEQUA WD / Oyster
Bay (T)
Well No 3 Replacement of Screen and Well Pump, Upgrade Ground
Water Source
43,000
$237,278
15
$3,764,610,985
17661
Nassau
MANHASSET LAKEVILLE
WD / Manhasset-Lakeville
WD
Thomaston Tank Rehabilitation, Upgrade Storage
43,000
$3,630,750
15
$3,768,241,735
15452
Nassau
PORT WASHINGTON WD /
Port Washington Water
District
Upgrade Storage
34,000
$2,781,000
15
$3,771,022,735
15371
Nassau
WA OF GREAT NECK
NORTH / Water Auth. of
Great Neck No.
Construction of a replacement well for well no. 10, Upgrade Ground
Water Source
31,400
$301,200
15
$3,771,323,935
15377
Nassau
WA OF GREAT NECK
NORTH / Water Auth. of
Great Neck No.
Water Mill Lane, New Storage, New Pump Station
31,400
$2,567,000
15
$3,773,890,935
CODES Legend *
ARRAF=American Recovery Reinvestment Act Financed
GIC=Green Infrastructure Components
FGP=Funded through SRF Bond Guarantee Program
CAT_G=Green Innovative Grants Program Project
Page 31 of 35
Project #
County
CODES See legend*
NYS Drinking Water State Revolving Fund Final Readiness List
October 1, 2011 to September 30, 2012
System Name/
Borrower
15381
Nassau
WA OF GREAT NECK
NORTH / Water Auth. of
Great Neck No.
17913
Nassau
15632
Description
Transmission main from the Weybridge Road tank to Oxford
Boulevard, New Transmission
Pop.
Project Cost Score
Cumulative
Total
31,400
$431,000
15
$3,774,321,935
Replacement of Waybridge Road storage tank,
WA OF GREAT NECK
NORTH / Water Auth of Great
Neck North
31,400
$1,545,000
15
$3,775,866,935
Westchester
Upgrade Storage
OSSINING WATER
DEPARTMENT / Ossining (V)
30,000
$300,000
15
$3,776,166,935
17718
Suffolk
RIVERHEAD WD / River
Head WD / Riverhead (T)
28,000
$2,060,000
15
$3,778,226,935
17698
Nassau
GARDEN CITY (V) / Village of Rehabilitation of Maria Street Tank, Upgrade Storage
Garden City
25,000
$2,575,000
15
$3,780,801,935
15313
Nassau
ROCKVILLE CENTRE (V) /
Rockville Centre (V)
Tank #4 rehabilitation, Upgrade Storage
24,700
$2,500,000
15
$3,783,301,935
15351
Nassau
ROCKVILLE CENTRE (V) /
Rockville Centre (V)
Rehab Wells 4a & 4b, Upgrade Ground Water Source
24,700
$600,000
15
$3,783,901,935
15356
Nassau
ROCKVILLE CENTRE (V) /
Rockville Centre (V)
Rehab tank #2, Upgrade Storage
24,700
$1,900,000
15
$3,785,801,935
15671
Nassau
ROSLYN WD / North
Hempstead (T)
Upgrade Ground Water Source
17,000
$83,224
15
$3,785,885,159
15676
Nassau
ROSLYN WD / North
Hempstead (T)
Roslyn Estate Pressure Zone, New Pump Station
17,000
$852,135
15
$3,786,737,294
15285
Nassau
ALBERTSON WD / North
Hempstead (T)
Wells no. 2 & 3 Replacement of screen and well pump, Upgrade
Ground Water Source
13,500
$386,686
15
$3,787,123,980
15274
Montgomery
GLEN (T) W.D.#2 / Glen (T)
Upgrade Distribution System
7,626
$95,000
15
$3,787,218,980
17344
Nassau
WILLISTON PARK (V) /
Williston Park (V)
Secondary Containment for Caustic Soda, Upgrade Other Expenses,
Upgrade Other (OT)
7,516
$161,350
15
$3,787,380,330
17829
Westchester
PLEASANTVILLE /
Pleasantville (V)
Replacement of water mains., Upgrade Distribution System
7,166
$1,955,000
15
$3,789,335,330
16038
Ontario
GORHAM TOWN WD /
Gorham (T)
Upgrade Storage
4,500
$77,500
15
$3,789,412,830
17835
Orange
MONTGOMERY (V) /
Montgomery (V)
New Storage Tank, New Storage
3,696
$825,030
15
$3,790,237,860
17916
Orange
GREENWOOD LAKE (V) /
Greenwood Lake (V)
Cleaning and painting storage tank, Upgrade Storage
3,400
$245,660
15
$3,790,483,520
17525
Westchester
NORTH CASTLE WD #1 /
North Castle (T)
Rehabilitation of water storage tanks, Upgrade Storage
2,500
$813,500
15
$3,791,297,020
18040
Ontario
BLOOMFIELD VILLAGE /
Bloomfield (V)
Upgrade Distribution System
1,675
$1,340,697
15
$3,792,637,717
15792
Putnam
CONTINENTAL VILLAGE WD Upgrade Distribution System
/ Philipstown (T)
1,509
$1,350,000
15
$3,793,987,717
Rehabiitation of Route 58 Storage Tank, Upgrade Storage
CODES Legend *
ARRAF=American Recovery Reinvestment Act Financed
GIC=Green Infrastructure Components
FGP=Funded through SRF Bond Guarantee Program
CAT_G=Green Innovative Grants Program Project
Page 32 of 35
Project #
County
CODES See legend*
NYS Drinking Water State Revolving Fund Final Readiness List
October 1, 2011 to September 30, 2012
System Name/
Borrower
Description
New Pump Station
15559
Ontario
HOPEWELL WD #2 /
Hopewell (T)
17843
Orange
TUXEDO PARK (V) / Tuxedo West Lake Road Transmission Line, Upgrade Transmission
(V)
17061
Westchester
LAKE KATONAH CLUB INC / Upgrade Storage
Lake Katonah Club Inc
17999
Dutchess
BEACON CITY / Beacon (C)
Upgrade Pump Station
17889
Westchester
Cleaning and lining 36,800 feet of distribution main., Upgrade
MT VERNON BOARD OF
WATER SUPPLY / Mt Vernon Distribution System
B'rd Water Supply
17946
Westchester
MOUNT VERNON (C) / Mt
Vernon Board Water Supply
16815
Erie
15717
Pop.
Project Cost Score
Cumulative
Total
1,148
$435,600
15
$3,794,423,317
1,100
$487,000
15
$3,794,910,317
356
$131,910
15
$3,795,042,227
19,000
$71,379
15
$3,795,113,606
15,000
$3,700,000
15
$3,798,813,606
Upgrade distribution system, Upgrade Distribution System
15,000
$3,700,000
15
$3,802,513,606
LANCASTER (V) / Lancaster
(V)
Upgrade Distribution System
11,940
$1,670,454
15
$3,804,184,060
Rensselaer
EAST GREENBUSH
GENERAL W.D. / East
Greenbush (T)
Distribution extension, loop water main on Gilligan Road to Hays
Road, Upgrade Distribution System
10,200
$409,000
15
$3,804,593,060
17539
Rensselaer
CASTLETON VILLAGE PWS Replacement in-kind of aged water mains., Upgrade Distribution
System
/ Castleton-on-Hudson (V)
2,013
$1,661,400
15
$3,806,254,460
17527
Genesee
OAKFIELD VILLAGE /
Oakfield (V)
Upgrade Transmission, Upgrade Distribution System
1,805
$1,147,575
15
$3,807,402,035
17959
Dutchess
SHOREHAVEN CIVIC
ASSOC / DCWWA
Installation of water meters.,
300
$61,692
15
$3,807,463,727
13
$325,000
15
$3,807,788,727
$5,982,162
15
$3,813,770,889
ARRAF GIC
CAT_G
18003
Erie
New Distribution System, New Water District
CATTARAUGUS STREET
WATER DISTRICT / Concord
(T)
17198
NY City
Test Borings for City Tunnel 3 and Upstate Tunnel Sites, Phase 1
NEW YORK
CITY-CATSKILL/DELAWARE (C554), NYC & Westchester, Upgrade Transmission
SYSTEM / NYCMWFA
6,552,718
17844
Steuben
CAMPBELL WATER
DISTRICT / Campbell (T)
Extend Distribution System
280
$216,744
15
$3,813,987,633
18020
Lewis
WATER DISTRICT #1 /
Denmark (T)
Serve private contaminated/poor yielding wells., Extend Distribution
System
275
$2,603,000
15
$3,816,590,633
15328
Nassau
SOUTH FARMINGDALE WD / Caustic Soda Conversion at Plants 1, 5 & 6, Upgrade Water
Treatment Plant
South Farmingdale W.D.
44,700
$638,000
10
$3,817,228,633
15642
Nassau
WILLISTON PARK (V) /
Williston Park (V)
7,516
$800,000
10
$3,818,028,633
17696
Suffolk
SUFFOLK COUNTY WATER Automated Meter Reading / Leak Detection, Upgrade Distribution
System
AUTHORITY / SCWA
1,009,264
$7,273,000
10
$3,825,301,633
16050
Westchester
WHITE PLAINS CITY / White Previously completed water mains, Upgrade Distribution System
Plains (C)
53,077
$2,221,356
10
$3,827,522,989
17708
Nassau
SOUTH FARMINGDALE WD / Construction of Well 1-5, New Ground Water Source
South Farmingdale Water Dist
44,700
$644,350
10
$3,828,167,339
Upgrade Ground Water Source
CODES Legend *
ARRAF=American Recovery Reinvestment Act Financed
GIC=Green Infrastructure Components
FGP=Funded through SRF Bond Guarantee Program
CAT_G=Green Innovative Grants Program Project
Page 33 of 35
Project #
County
CODES See legend*
NYS Drinking Water State Revolving Fund Final Readiness List
October 1, 2011 to September 30, 2012
System Name/
Borrower
Description
Pop.
Project Cost Score
Cumulative
Total
15264
Nassau
PLAINVIEW WD / Oyster Bay New Pump Station
(T)
35,000
$4,663,248
10
$3,832,830,587
17912
Nassau
Water main replacement, Upgrade Distribution System
WA OF GREAT NECK
NORTH / Water Auth of Great
Neck North
31,400
$500,000
10
$3,833,330,587
15633
Westchester
Cement lining of water lines at various locations, Upgrade
OSSINING WATER
DEPARTMENT / Ossining (V) Distribution System
30,000
$900,000
10
$3,834,230,587
16740
Erie
ORCHARD PARK (T) /
Orchard Park (T)
2000 water system improvements., Upgrade Distribution System
28,000
$7,081,000
10
$3,841,311,587
17717
Suffolk
RIVERHEAD WD / River
Head WD / Riverhead (T)
Contruction of New Wells at Plant no. 15, New Ground Water Source
28,000
$1,973,480
10
$3,843,285,067
15357
Nassau
ROCKVILLE CENTRE (V) /
Rockville Centre (V)
SCADA - Phase I, Upgrade Water Treatment Plant
24,700
$550,000
10
$3,843,835,067
17958
Dutchess
BEACON CITY / Beacon (C)
Installation of leak detection equipment., Upgrade Other Expenses,
Upgrade Other (OT)
19,000
$233,100
10
$3,844,068,167
ARRAF GIC
CAT_G
17830
Westchester
KENSICO WATER DISTRICT Phase VI Water Main Replacement, Upgrade Distribution System
/ Mount Pleasant
17,857
$4,503,500
10
$3,848,571,667
17834
Westchester
KENSICO WATER DISTRICT Cement lining of water mains, Upgrade Distribution System
/ Mount Pleasant
17,857
$4,560,500
10
$3,853,132,167
17783
Westchester
TARRYTOWN WATER
SUPPLY / Tarrytown (V)
Water main improvements, Upgrade Distribution System
11,000
$2,549,250
10
$3,855,681,417
17784
Westchester
TARRYTOWN WATER
SUPPLY / Tarrytown (V)
Cement line existing water main, Upgrade Distribution System
11,000
$1,892,110
10
$3,857,573,527
15180
Orange
WOODBURY CONS. W.D. /
Woodbury (T)
Upgrade Distribution System
10,105
$528,000
10
$3,858,101,527
15507
Westchester
PLEASANTVILLE WATER
DISTRICT / Pleasantville (V)
Refinance '93 bonds for relining water mains, Upgrade Distribution
System
9,500
$4,155,408
10
$3,862,256,935
15514
Westchester
PLEASANTVILLE WATER
DISTRICT / Pleasantville (V)
Water Mains for Sarles Lane, Upgrade Distribution System
9,500
$343,291
10
$3,862,600,226
17817
Orange
WASHINGTONVILLE
VILLAGE / Washingtonville
(V)
Watermain replacement Patricia and Beverly Lane, Upgrade
Distribution System
7,000
$961,000
10
$3,863,561,226
17818
Orange
WASHINGTONVILLE
VILLAGE / Washingtonville
(V)
Replace watermains in Dutch Arms area., Upgrade Distribution
System
7,000
$1,654,700
10
$3,865,215,926
17775
Westchester
WESTCHESTER COUNTY
WD #3 / Westchester County
#3
Lateral Main Rehabilitation, Upgrade Distribution System
6,000
$670,000
10
$3,865,885,926
15131
Livingston
LIVONIA VILLAGE / Livonia
(V)
Upgrade Distribution System
1,360
$1,105,325
10
$3,866,991,251
17907
Nassau
VILLAGE OF PLANDOME /
Plandome (V)
Replace aged mains in distribution system, Upgrade Distribution
System
1,350
$5,113,950
10
$3,872,105,201
17985
Westchester
BEAR RIDGE LAKE WATER
DISTRICT / Mount Pleasant
(T)
Water main replacement-Highland Place, Mountain Trail and
Woodland Road, Upgrade Distribution System
170
$1,436,085
10
$3,873,541,286
CODES Legend *
ARRAF=American Recovery Reinvestment Act Financed
GIC=Green Infrastructure Components
FGP=Funded through SRF Bond Guarantee Program
CAT_G=Green Innovative Grants Program Project
Page 34 of 35
Project #
County
CODES See legend*
NYS Drinking Water State Revolving Fund Final Readiness List
October 1, 2011 to September 30, 2012
System Name/
Borrower
Description
16540
Dutchess
Upgrade Distribution System
CHARLOTTE GROVE
MOBILE HOME CT / Charlette
Grove MH Court
17993
Suffolk
WEST NECK WATER
SUPPLY / Shelter Island (T)
18050
Yates
BENTON WD #1 /
16178
Erie
16182
Pop.
Project Cost Score
Cumulative
Total
112
$302,820
10
$3,873,844,106
Water main replacement, Upgrade Distribution System
100
$669,093
10
$3,874,513,199
Extend Distribution System
308
$731,000
10
$3,875,244,199
Ransom Road waterline improvements., Upgrade Distribution
GRAND ISLAND TOWN
WATER DEPT. / Grand Island System
(T)
19,500
$111,453
5
$3,875,355,652
Erie
Bush Road waterline improvements., Upgrade Distribution System
GRAND ISLAND TOWN
WATER DEPT. / Grand Island
(T)
19,500
$228,113
5
$3,875,583,765
15963
Orange
CORNWALL-ON-HUDSON /
Cornwall-On-Hudson (V)
Upgrade Distribution System
9,300
$520,000
5
$3,876,103,765
17854
Putnam
SOUTHEAST (T)
PEACEABLE WATER
DISTRICT / Southeast (T)
Development new water source instead of continuing to purchase
from Brewster (V), New Ground Water Source
440
$1,700,000
5
$3,877,803,765
17853
Onondaga
OCWA / Onondaga County
Water Authorit
Roof and siding improvements for Water System Maintenance and
Operations Facility., Upgrade Other Expenses, Upgrade Other (OT)
256,000
$1,620,000
5
$3,879,423,765
17781
Rensselaer
WATER DISTRICT 15 / North Extend Distribution System
Greenbush (T)
4,000
$9,785,000
5
$3,889,208,765
18068
Orleans
WATER IMPROVEMENT
BENEFIT AREA #10 /
Clarendon (T)
250
$1,634,949
5
$3,890,843,714
Extend Distribution System
Total # Projects
690
Total Cost
$3,890,843,714
CODES Legend *
ARRAF=American Recovery Reinvestment Act Financed
GIC=Green Infrastructure Components
FGP=Funded through SRF Bond Guarantee Program
CAT_G=Green Innovative Grants Program Project
Page 35 of 35
CATEGORY A LIST
SMALL SYSTEMS LESS THAN 10,000 PEOPLE
NYS Drinking Water State Revolving Fund Final Category A List ( Small Systems Serving < 10,000 People )
October 1, 2011 to September 30, 2012
Project County
17473
17321
17456
17388
15881
17561
17461
15072
17647
15343
15204
17543
17576
16261
17538
17306
17382
17457
16882
Jefferson
Jefferson
Hamilton
Essex
Essex
Chautauqua
Orange
Orange
Saratoga
Otsego
Oswego
Saratoga
Chautauqua
Oswego
Oswego
Jefferson
Allegany
Erie
Onondaga
System Name/
Borrower
Description
Pop.
LAFAVE ROAD WATER
DISTRICT / Le Ray (T)
Consolidation of existing public water systems with GUDI wells,
coliform and lead violations., New Distribution System, New System
Consolidation
600
WESTCOTTS WATER
DISTRICT / Hounsfield (T)
Westcotts WD to serve along NYS Route 3. Consolidation of PWS
systems addressing SWTR & E-Coli violations. , Upgrade Storage,
New Distribution System, New System Consolidation
300
INDIAN LAKE WD / Indian
Lake (T)
New Surface Water Treatment Rule Compliance Facility, Upgrade
Water Treatment Plant, New Ground Water Source, Upgrade
Distribution System
900
PORT KENT WD /
Chesterfield (T)
New Surface Water Treatment Rule Compliance Facility, New
Ground Water Source, New Storage
202
WADHAMS WD / Westport
(T)
New Surface Water Treatment Rule Compliance Facility, New
Inter-Connection, New System Consolidation
FORESTVILLE VILLAGE /
Forestville (V)
New Surface Water Treatment Rule Compliance Facility, New
Ground Water Source, Upgrade Distribution System
PHEASANT HILL / Pheasant
Hill Water Corp
Rehabilitation of water system to address e-coli contamination,
Upgrade Water Treatment Plant, New Ground Water Source, New
Storage
154
BEAVER DAM LAKE WATER
CORP. / Beaver Dam Lake
Corp.
New Surface Water Treatment Rule Compliance Facility, New
Ground Water Source, New Storage, Upgrade Distribution System
487
STILLWATER VILLAGE /
Stillwater (V)
Alternative Water Source for Surface Water Treatment Rule
compliance., New Transmission, New Inter-Connection
UNADILLA VILLAGE /
Unadilla (V)
Install new well, pumphouse, controls, chlorination system to replace
GWUDI springs, New Surface Water Treatment Rule Compliance
Facility, New Ground Water Source, Upgrade Pump Station, Upgrade
Distribution System
1,350
HANNIBAL (T) / Hannibal (T)
Extend system to serve area with private contaminated wells,
consolidate public water supply. , Extend Distribution System, New
System Consolidation
1,200
MOREAU WD
7/CONNECTION TO SCWA /
Moreau (T)
Consolidate 3 small CWSs, consolidate WD 1, connect Town with
SCWA, New Storage, Extend Distribution System, New
Inter-Connection, Extend System Consolidation, New Water District
1,100
CHERRY CREEK VILLAGE /
Cherry Creek (V)
New Surface Water Treatment Rule Compliance Facility, Upgrade
Distribution System
$0
Cumulative
Total
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
140
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
804
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
1,572
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
650
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
New Surface Water Treatment Rule Compliance Facility, New
TOAD
HARBOR/CONSTANTIA WD / Storage, New Pump Station, New Distribution System, New
Inter-Connection, New System Consolidation
Constantia (T)
2,765
WATER DISTRICT #2 /
Richland (T)
New Surface Water Treatment Rule Compliance Facility, New
Ground Water Source, New Transmission, New Storage, New
Distribution System
1,662
WATER DISTRICT #2 /
Henderson (T)
New Surface Water Treatment Rule Compliance Facility, New
Distribution System, New System Consolidation
352
HOUGHTON WATER
DISTRICT / Caneadea (T)
Upgrade Water Treatment Plant, New Ground Water Source, New
Transmission, Upgrade Distribution System
CHAFFEE WATER CO /
Chaffee Water Co.
New Surface Water Treatment Rule Compliance Facility, New
Ground Water Source, New Storage
LIMELEDGE WD / Marcellus
(T) & (V)
New Water District to serve area with insufficient private wells.
Interconnection with GWUDI system., New Surface Water Treatment
Rule Compliance Facility, Extend Distribution System
Page 1 of 28
Project Cost Score
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
2,000
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
200
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
700
$0
H
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
$0
NYS Drinking Water State Revolving Fund Final Category A List ( Small Systems Serving < 10,000 People )
October 1, 2011 to September 30, 2012
Project County
17140
St.Lawrence
System Name/
Borrower
Description
Pop.
LOUISVILLE WATER
DISTRICT #2 / Louisville (T)
New Storage, Upgrade Distribution System, System Consolidation
1,000
Project Cost Score
$0
Cumulative
Total
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
17611
Franklin
SARANAC LAKE V / Saranac
Lake (V)
New SCADA equipment., New Surface Water Treatment Rule
Compliance Facility, Upgrade Distribution System
16746
Allegany
CANASERAGA VILLAGE
PUBLIC WATER /
Canaseraga (V)
New Ground Water Source, Upgrade Storage
15003
Ulster
ELLENVILLE (VILLAGE)
WATER DIS / Ellenville (V)
17928
Wyoming
18005
5,800
$12,500,000
H
$12,500,000
900
$3,666,749
H
$16,166,749
Water system improvements, Upgrade Surface Water Treatment
Rule Compliance Facility, Upgrade Storage, Upgrade Distribution
System
4,323
$7,136,870
H
$23,303,619
CASTILE VILLAGE / Castile
(V)
Upgrade Water Treatment Plant, Upgrade Ground Water Source,
Upgrade Storage
1,135
$5,111,267
H
$28,414,886
Wayne
SAVANNAH WD #1 /
Savannah (T)
New Surface Water Treatment Rule Compliance Facility, New
Storage, Upgrade Distribution System, Extend Distribution System
900
$3,605,000
H
$32,019,886
17425
Chenango
SO. NEW BERLIN WATER
DISTRICT / New Berlin (T)
New Ground Water Source, New Transmission, New Storage,
Upgrade Distribution System, System Consolidation
400
$3,272,000
H
$35,291,886
15603
Jefferson
WATER DISTRICT NO. 5 /
Hounsfield (T)
Extend distribution system to area of insufficient yielding or
cantaminated private wells. Consolidate Watertown International
Airport., New Distribution System, New System Consolidation
345
$4,800,000
H
$40,091,886
17427
Albany
NEW SALEM WATER
DISTRICT / New Scotland (T)
New Surface Water Treatment Rule Compliance Facility, New
Storage, New Pump Station, New Inter-Connection, New Water
District
486
$3,048,000
H
$43,139,886
17442
Erie
BRANDT (T), NORTH
COLLINS (T)&(V) / North
Collins (V)
WTP improvements for lead and copper violations, Fe violations,
Asbestos Main replacement, inadequate pressures, Upgrade Water
Treatment Plant, Upgrade Transmission, Upgrade Distribution
System, New System Consolidation
1,915
$5,430,000
H
$48,569,886
17379
Steuben
COOPERS PLAINS/LONG
ACRES WATER SYST /
Erwin (T)
New Ground Water Source, Extend Distribution System, New System
Consolidation
1,400
$0
H
$48,569,886
17552
Herkimer
NEWPORT VILLAGE /
Newport (V)
New Surface Water Treatment Rule Compliance Facility, New
Ground Water Source, Upgrade Transmission, New Storage,
Upgrade Distribution System
740
$2,175,000
H
$50,744,886
16278
Hamilton
LONG LAKE (T) / Long Lake
(T)
New Ground Water Source, New Storage, Upgrade Distribution
System
750
$3,929,255
H
$54,674,141
16692
Herkimer
VAN HORNESVILLE WATER
WORKS / Stark (T)
VanHornesville Water System, New Surface Water Treatment Rule
Compliance Facility, New Storage, Upgrade Distribution System
372
$2,098,150
H
$56,772,291
17625
Oswego
EASTERN SHORE WATER
SYSTEM / Sandy Creek (T)
Consolidation of PWS with GWDI source., New Storage, New
Distribution System, New System Consolidation
$13,988,000
H
$70,760,291
17372
Oswego
MEXICO (T) WD#2 / Mexico
(T)
Extend distribution system to area with contaminated private wells
and consolidate PWS with GWUDI source, New Distribution System,
New System Consolidation
800
$7,060,000
H
$77,820,291
17637
Chautauqua
NORTH END WD / Pomfret
(T)
Extend distribution system to area with contaminated private wells
and consolidate PWS with Coliform, New Distribution System
900
$4,432,100
H
$82,252,391
16114
Cayuga
CAYUGA VILLAGE / Cayuga
(V)
New Surface Water Treatment Rule Compliance Facility, Upgrade
Distribution System, New Inter-Connection
600
$6,875,100
H
$89,127,491
17331
Rensselaer
POESTENKILL (T) WD #1 /
Poestenkill (T)
New Complete System (New System), New System Consolidation
2,300
$0
H
$89,127,491
15% Minimum Requirement
Page 2 of 28
2,503
NYS Drinking Water State Revolving Fund Final Category A List ( Small Systems Serving < 10,000 People )
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
17589
Cattaraugus
New Surface Water Treatment Rule Compliance Facility, Upgrade
CRYSTAL WATER CO
(WEST VALLEY) / Ashford (T) Ground Water Source
18017
Allegany
RICHBURG VILLAGE
PUBLIC WATER / Richburg
(V)
(V) Richburg & (V) Bolivar Consolidation., New Surface Water
Treatment Rule Compliance Facility, New Ground Water Source,
Upgrade Storage, Upgrade Distribution System, New System
Consolidation
17682
Essex
WD#4 / Moriah (T)
16510
Schenectady
17629
Pop.
Project Cost Score
Cumulative
Total
880
$3,208,500
H
$92,335,991
600
$7,038,640
H
$99,374,631
New Surface Water Treatment Rule Compliance Facility, New
Distribution System
78
$1,990,475
H
$101,365,106
DELANSON VILLAGE
WATER WORKS / Delanson
(V)
Upper resevoir raw water transmission main, new intake, new
controls & meters at filter plant., New Transmission, Extend
Distribution System, Upgrade Distribution System
428
$4,594,000
H
$105,959,106
Essex
ESSEX WD / Essex (T)
Address turbidity and organic violations, New Ground Water Source,
Upgrade Distribution System
300
$1,515,954
H
$107,475,060
17367
Steuben
TROUPSBURG WATER
DISTRICT / Troupsburg (T)
New Surface Water Treatment Rule Compliance Facility, Upgrade
Water Treatment Plant
250
$192,000
H
$107,667,060
16618
Dutchess
SHOREHAVEN CIVIC
ASSOC / DCWWA
DCWWA ZONE J SHOREHAVEN WATER SYSTEM, Upgrade
Water Treatment Plant, Upgrade Ground Water Source, Upgrade
Distribution System
300
$3,575,000
H
$111,242,060
17623
Saratoga
CORINTH VILLAGE / Village
of Corinth
New Surface Water Treatment Rule Compliance Facility, Upgrade
Distribution System
4,700
$6,200,000
H
$117,442,060
17931
Cayuga
PORT BYRON VILLAGE /
Port Byron (V)
Joint project with (V) Port Byron, (T) Montezuma & (T) Mentz.,
Upgrade Distribution System, Extend Distribution System, New
System Consolidation
1,400
$5,657,000
H
$123,099,060
17454
St.Lawrence
EAST LOUISVILLE WD#3 /
Louisville (T)
Consolidation of water systems with past coliform detections., New
Storage, New Distribution System, New System Consolidation
1,030
$9,275,000
H
$132,374,060
17444
Greene
COXSACKIE VILLAGE /
Coxsackie (V)
Phase 2 of 15702, Upgrade Water Treatment Plant, Upgrade Water
Treatment Plant
4,010
$3,233,065
3175
$135,607,125
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
17866
Delaware
GRAND GORGE WATER
DISTRICT / Town of Roxbury
Phase 3 of 15624 (Phase 2 was 17228): Treat or Replace GWUDI
Wells, New Surface Water Treatment Rule Compliance Facility
370
$992,000
2245
$136,599,125
18029
Rensselaer
HOOSICK FALLS (V) PWS /
Hoosick Falls (V)
Phase 2 of Project 15080 , Upgrade Storage, Upgrade Distribution
System
4,000
$640,000
2225
$137,239,125
17773
Chenango
SHERBURNE VILLAGE /
Sherburne (V)
Phase 2 of 15237., Upgrade Ground Water Source
1,531
$1,300,000
2210
$138,539,125
17631
Essex
WILMINGTON WD /
Wilmington (T)
Phase 2 (Juniper Hill Road) of DWSRF 15803, New Surface Water
Treatment Rule Compliance Facility, New Storage, Upgrade
Distribution System
980
$406,500
2175
$138,945,625
17496
Greene
HUNTER VILLAGE / Hunter
(V)
Phase 2 of #16732 - Dolan's Lake Intake and Connection of Wells 1
and 3, Upgrade Water Treatment Plant, New Ground Water Source,
New Transmission
896
$1,518,150
2165
$140,463,775
17470
Herkimer
HERKIMER VILLAGE /
Herkimer (V)
Phase 2 of 16676, New Surface Water Treatment Rule Compliance
Facility
7,606
$300,000
2130
$140,763,775
17649
Ulster
PHOENICIA WATER
DISTRICT / Shandaken (T)
Phase 2, see Project #16491 for Phase 1., New Surface Water
Treatment Rule Compliance Facility, Upgrade Ground Water Source
992
$150,000
2130
$140,913,775
18022
Cattaraugus
PERRYSBURG (V) /
Perrysburg (T)
Phase 2 (DWSRF 17192) based on cost increase to address
unresolved deficiencies in the initial project construction, New Water
Treatment Plant, Upgrade Ground Water Source, Upgrade Storage,
New Pump Station
404
$729,657
2095
$141,643,432
Page 3 of 28
NYS Drinking Water State Revolving Fund Final Category A List ( Small Systems Serving < 10,000 People )
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost Score
Cumulative
Total
17449
Orange
HIGHLANDS (T) WD #2 /
Highlands (T)
Phase 2 of DWSRF 16454 to provide well source capacity for Phase
1 which included, Upgrade Water Treatment Plant, New Ground
Water Source, New Storage, Extend Distribution System
1,379
$4,748,700
2095
$146,392,132
17742
Saratoga
MECHANICVILLE CITY /
Mechanicville (C)
Phase 2 of 15284; Construct additional sludge drying bed capacity,
New Other Expenses, New Water Treatment Plant, New Other (OT)
5,100
$587,100
2090
$146,979,232
17642
Washington
GRANVILLE VILLAGE /
Granville (V)
New Surface Water Treatment Rule Compliance Facility, Upgrade
Ground Water Source, Upgrade Transmission, Upgrade Distribution
System
2,645
$0
1220
$146,979,232
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
17163
Essex
TICONDEROGA WD /
Ticonderoga (T)
New Surface Water Treatment Rule Compliance Facility, New
Storage, Upgrade Distribution System
5,000
$13,954,315
265
$160,933,547
18061
Franklin
TUPPER LAKE V / Tupper
Lake (V)
New wells to replace SW source and inadequate DE plant., New
Ground Water Source, Upgrade Distribution System
5,500
$2,979,790
235
$163,913,337
16013
Westchester
BRIARCLIFF MANOR
VILLAGE / Briarcliff Manor(V)
New Surface Water Treatment Rule Compliance Facility
8,831
$0
225
$163,913,337
15862
Putnam
SPRINGHOUSE ESTATES
W.W. CORP. / Southeast (T)
New Ground Water Source, New Storage
212
$1,700,500
200
$165,613,837
18013
Cattaraugus
RANDOLPH VILLAGE /
Randolph (T)
East Randolph and Randolph (V)'s project includes meters, Upgrade
Other Expenses, New Surface Water Treatment Rule Compliance
Facility, New Ground Water Source, New System Consolidation,
Upgrade Other (OT)
1,250
$3,740,000
200
$169,353,837
15996
Delaware
FRANKLIN VILLAGE /
Franklin (V)
New Water Treatment Plant, New Ground Water Source, New
Storage, Extend Distribution System, Upgrade Distribution System
481
$2,301,077
195
$171,654,914
17493
Orange
WARWICK VILLAGE /
Warwick (V)
New Surface Water Treatment Rule Compliance Facility, Upgrade
Water Treatment Plant
6,083
$0
190
$171,654,914
17337
Erie
HUNTERS CREEK MOBILE
HOME PARK / Hunters Creek
MHP
Address total coliform detections and organic exceedances, Upgrade
Water Treatment Plant, New Storage, New Pump Station, Upgrade
Distribution System
150
$175,100
185
$171,830,014
15661
Albany
RENSSELAERVILLE WD /
Rensselaerville (T)
New Ground Water Source, Upgrade Storage, Upgrade Distribution
System
200
$990,242
185
$172,820,256
17936
Rensselaer
BRUNSWICK WATER
DISTRICT # 6 / Brunswick (T)
Distribution Modifications for Flow & Pressure Improvements to
Support Consecutive System; Emergency Generator, Upgrade Pump
Station, Upgrade Distribution System
927
$504,000
185
$173,324,256
17529
Jefferson
TIBBETS POINT WATER
DISTRICT / Cape Vincent (T)
Serve area with private contaminated wells, New Surface Water
Treatment Rule Compliance Facility, New System Consolidation, New
Water District
200
$2,645,000
180
$175,969,256
17392
Warren
PIONEER VILLAGE / Pioneer
Village Imp. Assoc.
Serve private contaminated wells., New Surface Water Treatment
Rule Compliance Facility, New Inter-Connection, New System
Consolidation
144
$208,575
175
$176,177,831
17562
Jefferson
HERRINGS VILLAGE /
Herrings (V)
Distribution and storage improvements., Upgrade Storage, Upgrade
Distribution System
120
$3,429,000
170
$179,606,831
15557
Herkimer
POLAND VILLAGE / Poland
(V)
Surface Water Treatment Rule Compliance Facility, New Ground
Water Source, New Storage, Upgrade Distribution System
463
$246,000
165
$179,852,831
17621
Allegany
ANGELICA VILLAGE PUBLIC
WATER / Angelica (V)
Surface Water Treatment Rule Compliance Facility
950
$1,061,847
165
$180,914,678
17537
Delaware
DOWNSVILLE WATER
DISTRICT / Colchester (T)
Package Filtration Plant for GWUDI Spring Source and Addition of
Corrosion Control Treatment., New Surface Water Treatment Rule
Compliance Facility, New Water Treatment Plant
500
$92,400
165
$181,007,078
Page 4 of 28
NYS Drinking Water State Revolving Fund Final Category A List ( Small Systems Serving < 10,000 People )
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
16991
Chenango
OXFORD WATER DISTRICT
#1 / Oxford (T)
Surface Water Treatment Rule Compliance Facility, New
Transmission
16741
Dutchess
PAWLING VILLAGE / Pawling
(V)
New Surface Water Treatment Rule Compliance Facility, New
Ground Water Source
15097
Warren
HAGUE HOA / Hague HOA
Hague Home Owners Association, New Surface Water Treatment
Rule Compliance Facility
18060
Orange
HIGHLANDS WATER
DISTRCIT 2 EXTENTION /
Highlands (T)
Extention of the existing WD #2 to serve private wells with
contamination and consolidation of several PWS's, Extend
Distribution System, Extend System Consolidation
18072
Putnam
GIPSY TRAIL CLUB / Gipsy
Trail Club Inc
Develop additional well source capacity, New Ground Water Source,
New Pump Station
15600
Hamilton
ANTLERS OF RAQUETTE
LAKE, INC. / Antlers of
Raquette Lake Inc.
New Surface Water Source, Inter-Connection
16117
Jefferson
ALEXANDRIA TOWN WD #1
- OTTER STREET /
Alexandria (T)
Extend Distribution System, Upgrade Distribution System
17469
Montgomery
FORT PLAIN (V) WATER
WORKS / Fort Plain (V)
17339
Erie
17514
Pop.
50
Project Cost Score
Cumulative
Total
$122,500
160
$181,129,578
$1,270,000
155
$182,399,578
$119,190
155
$182,518,768
$1,601,238
155
$184,120,006
300
$430,540
150
$184,550,546
120
$243,595
150
$184,794,141
60
$3,600,000
150
$188,394,141
Upgrade Water Treatment Plant, Upgrade Ground Water Source,
Upgrade Storage, Upgrade Distribution System
2,400
$1,565,600
150
$189,959,741
S. EAST ERIE CO.
REGIONAL WATER
PROJECT / Aurora (T)
Aurora WD19, Wales WD's2&3. Extend to serve private
contaminated wells, consolidate public water supplies, eliminate
public water supply with past coliform detections, Storage, Pump
Station, Extend Distribution System, System Consolidation
2,950
$6,400,000
150
$196,359,741
Cattaraugus
DELEVAN VILLAGE /
Delevan (V)
New Surface Water Treatment Rule Compliance Facility, Upgrade
Ground Water Source, Upgrade Storage, Upgrade Distribution
System
1,090
$1,690,350
145
$198,050,091
17289
Wayne
WOLCOTT VILLAGE /
Wolcott (V)
New Water Treatment Plant, Upgrade Ground Water Source
2,200
$1,250,000
145
$199,300,091
17513
Essex
WINEBROOK HILLS WD /
Newcomb (T)
New Ground Water Source, Upgrade Distribution System
250
$5,302,728
145
$204,602,819
17622
Chautauqua
BROCTON VILLAGE /
Brocton (V)
Address turbidity violations, Surface Water Treatment Rule
Compliance Facility, Upgrade Water Treatment Plant
4,000
$2,219,341
145
$206,822,160
17385
Onondaga
NORTHEAST LAFAYETTE
WD / East Syracuse (V)
Inter-connection to eliminate GWUDI source., New Transmission,
New Inter-Connection
250
$535,600
145
$207,357,760
17944
Nassau
MILL NECK ESTATES / Mill
Neck Estates Association
Transmission main to connect with Locust Valley WD and upgrade
distribution, Upgrade Distribution System, New Inter-Connection
230
$2,021,375
145
$209,379,135
16861
Franklin
TUPPER LAKE V / Tupper
Lake (V)
New Storage, Upgrade Distribution System
5,500
$700,000
145
$210,079,135
17535
Saratoga
SOUTH GLENS FALLS
VILLAGE / South Glens Falls
(V)
Proposed Cartridge Filtration Plant with SCADA to treat Village
GWUDI spring sources., New Surface Water Treatment Rule
Compliance Facility, New Surface Water Treatment Rule Compliance
Facility
3,700
$1,565,000
145
$211,644,135
15749
Rensselaer
RENSSELAER CITY PWS /
Rensselaer (C)
New Storage, New Distribution System, System Consolidation
7,500
$7,175,300
145
$218,819,435
17455
Franklin
WATER DISTRICT #3 /
Malone (T)
Consolidate a MHP with nitrate violations, New Distribution System,
System Consolidation, New System Consolidation
300
$1,328,000
145
$220,147,435
1,907
18
1,379
Subsidized Funding Line
Page 5 of 28
NYS Drinking Water State Revolving Fund Final Category A List ( Small Systems Serving < 10,000 People )
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Project Cost Score
Cumulative
Total
Description
Pop.
2,000
$1,100,000
140
$221,247,435
17645
Washington
GREENWICH VILLAGE /
Greenwich (V)
New Surface Water Treatment Rule Compliance Facility, New
Storage
16339
Jefferson
WELLESLEY ISLAND
WATER CORP. / Wellesley
Island Water Corp.
New Water Treatment Plant, New Surface Water Source
548
$2,336,000
140
$223,583,435
15220
Westchester
CROTON FALLS WATER
DISTRICT / North Salem (T)
Installation of new wells to replace existing wells, New Ground Water
Source
175
$400,000
135
$223,983,435
17619
Livingston
GENESEO VILLAGE /
LCWSA
New Surface Water Treatment Rule Compliance Facility
7,600
$813,000
135
$224,796,435
17612
Onondaga
ELBRIDGE VILLAGE /
Elbridge (V)
New UV treatment for LT2ESWTR compliance., New Surface Water
Treatment Rule Compliance Facility
1,519
$0
135
$224,796,435
16705
Madison
MADISON VILLAGE /
Madison (V)
New Ground Water Source, Upgrade Distribution System
450
$103,500
135
$224,899,935
16106
Greene
TANNERSVILLE VILLAGE /
Tannersville (V)
New Ground Water Source, Upgrade Transmission, Upgrade
Distribution System
448
$1,900,000
135
$226,799,935
15722
Orange
MONROE WD #8 (SKYVIEW
HILLS) / Monroe (T)
Extend system to serve area with private contaminated wells. ,
Upgrade Distribution System
544
$1,000,000
135
$227,799,935
17201
Jefferson
ELLISBURG (V) / Ellisburg (V) Extend system to serve area with private contaminated wells,
269
$0
135
$227,799,935
16146
Otsego
MILFORD VILLAGE / Milford
(V)
510
$3,502,000
130
$231,301,935
16279
Steuben
New Chlorination system., Upgrade Ground Water Source
COLONIAL COACH
ESTATES IV (MGRE) / Merlyn
Cavallaro
79
$65,900
130
$231,367,835
17617
Orange
BLOOMING GROVE WD
#1-WORLEY HE / South
Blooming Grove (V)
Transmission main with treatment plant to connect Water District 1
and 6 to Orange and Rockland Well., New Water Treatment Plant,
New Transmission
1,500
$3,193,000
130
$234,560,835
17467
Ulster
SAUGERTIES (VILLAGE)
WATER DIS / Saugerties (V)
Upgrade water mains and appurtenances; distribution extension to
connect 15 existing homes w/ wells to PWS; upgrade raw water
reservoir., Upgrade Other Expenses, Upgrade Distribution System,
Extend Distribution System, Upgrade Other (OT)
4,100
$3,573,894
130
$238,134,729
17597
Oswego
AREA 1 WATER SYSTEM /
Schroeppel (T)
Address organic contaminant violations, New Distribution System,
New System Consolidation
3,200
$11,312,382
130
$249,447,111
16912
Chenango
NO. NORWICH (T) WD #1 /
North Norwich (T)
New system to serve area with private contaminated wells,
consolidate public water supply, eliminate public water supply with
past total coliform detection. , New Distribution System
100
$920,300
130
$250,367,411
17516
St.Lawrence
OSWEGATCHIE (T) /
Oswegatchie (T)
Joint water system improvement project between (T) Oswegatchie,
(T) Lisbon and (V) Huevelton, Upgrade Ground Water Source,
Upgrade Storage, Upgrade Distribution System, New
Inter-Connection, New System Consolidation
2,100
$13,973,000
130
$264,340,411
17355
Yates
DRESDEN VILLAGE /
Dresden (V)
New Transmission, Upgrade Storage, New Inter-Connection
700
$515,000
125
$264,855,411
15669
Orange
MONROE WD #12 (MONROE Upgrade Ground Water Source, Upgrade Pump Station, Upgrade
Distribution System
HILLS ESTATES) / Monroe
(T)
120
$1,250,000
125
$266,105,411
17432
Chautauqua
CASSADAGA VILLAGE /
Cassadaga (V)
760
$5,047,000
125
$271,152,411
consolidate public water supply, eliminate public water supply with
past total coliform detection. , Extend Distribution System, New
System Consolidation
Page 6 of 28
Address nitrate contamination, New Ground Water Source, Upgrade
Distribution System
New Ground Water Source, New Storage, Upgrade Distribution
System
NYS Drinking Water State Revolving Fund Final Category A List ( Small Systems Serving < 10,000 People )
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Project Cost Score
Cumulative
Total
Description
Pop.
2,300
$1,279,000
125
$272,431,411
17615
St.Lawrence
NORFOLK WATER
DISTRICT / Norfolk (T)
New Surface Water Treatment Rule Compliance Facility, New
Ground Water Source
17143
Saratoga
SARATOGA GLEN HOLLOW
/ Saratoga Glen Hollow W.C.
Extend system to serve area with private contaminated wells,
consolidate public water supply, eliminate public water supply with
past totalcoliform detection. , Extend Distribution System, New
System Consolidation
750
$1,096,804
125
$273,528,215
17144
Chemung
CHEMUNG (T) WATER
SYSTEM / Chemung (T)
Consolidate PWS with Coliform contamination, extend to private
contaminated/poor yielding wells, New Complete System (New
System), New System Consolidation
280
$5,651,000
125
$279,179,215
17888
Tompkins
TRUMANSBURG VILLAGE /
Trumansburg (V)
New well to provide source redundancy. New transmission main to
provide adequate CT., New Ground Water Source, New
Transmission
2,300
$1,374,000
120
$280,553,215
18004
Chautauqua
WESTFIELD VILLAGE /
Westfield (V)
Address inadequate source capacity and insuffcient pressure,
Upgrade Storage, Upgrade Distribution System
3,450
$3,977,200
120
$284,530,415
17151
Erie
AURORA WATER DISTRICT
18 / Aurora (T)
Extend system to serve area with private contaminated wells,
consolidate public water supply, eliminate public water supply with
past total coliform detection. WD 18., Extend Distribution System
1,288
$15,704,100
120
$300,234,515
17594
Oswego
ROUTE 11 NORTH/FULLER
ROAD WD PHASE D /
Hastings (T)
Extend distribution system to area of insufficient yielding or
cantaminated private wells., Extend Distribution System, New
System Consolidation
1,200
$3,106,480
120
$303,340,995
16876
Dutchess
BRETTVIEW ACRES WATER New Surface Water Treatment Rule Compliance Facility
CO / Brettview Water Co. Inc.
$40,800
115
$303,381,795
17728
Onondaga
SKANEATELES VILLAGE /
Skaneateles
Install UV Disinfection for LT2 compliance., Upgrade Water
Treatment Plant
2,610
$793,100
115
$304,174,895
17071
Dutchess
BIRCH HILL MANOR /
DCWWA
DCWWA ZONE K BIRCH HILL WATER SYSTEM, Upgrade Water
Treatment Plant, New Ground Water Source
200
$575,000
115
$304,749,895
17801
Yates
WD #1 / Torrey (T)
New Distribution System
375
$3,079,875
115
$307,829,770
16811
Steuben
RIVERSIDE PARK / Carol
Naar
New chlorination system., Upgrade Ground Water Source
125
$45,735
115
$307,875,505
17986
Orange
PORT JERVIS CITY / Port
Jervis (C)
Addition of clarification, Upgrade Water Treatment Plant
9,000
$3,610,000
115
$311,485,505
16093
Tompkins
TRUMANSBURG VILLAGE /
Trumansburg (V)
New Transmission, New Storage, New Pump Station
2,300
$2,501,000
115
$313,986,505
17068
Rensselaer
SCHAGHTICOKE (V) PWS /
Schaghticoke (V)
Upgrade Water Treatment Plant, Upgrade Storage, Upgrade
Distribution System, Extend Distribution System
675
$6,585,700
115
$320,572,205
17230
Oneida
BENEFITED AREA E / Floyd
(T)
New Distribution System, New System Consolidation
115
$325,000
115
$320,897,205
17591
Ontario
BLOOMFIELD (V) OAKMOUNT AVE /
Bloomfield (V)
Upgrade Ground Water Source
750
$298,750
110
$321,195,955
17414
Greene
CATSKILL VILLAGE / Catskill
(V)
Upgrade Water Treatment Plant, New Storage, Upgrade Distribution
System
$10,270,000
110
$331,465,955
17686
Clinton
SARANAC WD / Saranac (T)
New Surface Water Treatment Rule Compliance Facility
$112,000
105
$331,577,955
Page 7 of 28
920
8,000
90
NYS Drinking Water State Revolving Fund Final Category A List ( Small Systems Serving < 10,000 People )
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost Score
Cumulative
Total
15301
Dutchess
TIVOLI VILLAGE WATER /
Tivoli (V)
Construct new supply well(s), upgrade treatment, new storage,
upgrade storage, upgrade distribution, Upgrade Water Treatment
Plant, New Ground Water Source, New Storage, Upgrade Pump
Station, Upgrade Distribution System
1,303
$3,729,700
105
$335,307,655
17361
Schoharie
COBLESKILL VILLAGE /
Cobleskill (V)
Upgrade Water Treatment Plant, New Storage, Upgrade Distribution
System
4,533
$4,120,000
105
$339,427,655
16446
Sullivan
WOODRIDGE VILLAGE /
Woodridge (V)
Upgrade Water Treatment Plant
902
$351,430
105
$339,779,085
17358
Rensselaer
SCHODACK WATER
DISTRICT # 3 / Schodack (T)
Connect WD #3 (Maple Crest) to WD #1 (Clearview), Extend
Distribution System, New System Consolidation
140
$0
105
$339,779,085
17588
Steuben
CORNING MANOR WATER
DISTRICT / Corning (T)
Extend to ontaminated private wells, consolidate 5 small PWS's,
Upgrade Storage, New System Consolidation
350
$1,315,187
105
$341,094,272
18053
Schoharie
COBLESKILL / Cobleskill (T)
Howe Caverns/Route 7 Service Area Extension, Extend Distribution
System
500
$4,899,004
105
$345,993,276
16169
Greene
ASHLAND WD#1 / Ashland
(T)
New Complete System (New System), New Inter-Connection
300
$2,873,620
105
$348,866,896
17338
Dutchess
DUTCHESS ESTATES INC /
Dutchess Estates Water
Company
Upgrade Ground Water Source, Upgrade Storage, Upgrade Pump
Station
500
$455,388
100
$349,322,284
18067
Otsego
GILBERTSVILLE VILLAGE /
Gilbertsville (V)
New Ground Water Source, New Storage, Upgrade Distribution
System
477
$3,865,000
100
$353,187,284
15958
Greene
PRATTSVILLE WATER
DISTRICT / Prattsville (T)
New Ground Water Source
410
$1,361,800
100
$354,549,084
17062
Wyoming
PIKE VILLAGE / Pike (V)
New Ground Water Source, Upgrade Ground Water Source, Upgrade
Transmission, Upgrade Distribution System
369
$494,596
100
$355,043,680
17021
Dutchess
ROKEBY HOMES,INC. /
DCWWA
DCWWA ZONE F PROJECT ROKEBY WATER SYSTEM , Upgrade
Water Treatment Plant, Upgrade Ground Water Source, Upgrade
Distribution System, New System Consolidation
160
$495,356
100
$355,539,036
17403
Sullivan
WOODRIDGE VILLAGE /
Woodridge (V)
New Ground Water Source
902
$450,000
100
$355,989,036
17554
Chautauqua
PORTLAND (T) WATER
DISTRICT NO. 7 / Portland
(T)
Serve 218 parcels currently on insufficient private wells on portions of
Route 5 and Walker Road. Consolidate DJ's Campground., New
System Consolidation, New Water District
333
$1,700,000
100
$357,689,036
16062
Niagara
BARKER VILLAGE / Barker
(V)
Upgrade Distribution System
577
$835,085
95
$358,524,121
17093
Otsego
HARTWICK WATER
DISTRICT / Hartwick (T) WD
New Ground Water Source, New Storage, Upgrade Distribution
System
416
$1,745,850
95
$360,269,971
16606
Delaware
DELHI VILLAGE / Delhi (V)
Upgrade Distribution System, New System Consolidation
3,833
$1,373,428
95
$361,643,399
16654
Madison
MORRISVILLE VILLAGE /
Morrisville (V)
To provide adequate pressure, Upgrade Distribution System
2,456
$1,300,000
95
$362,943,399
17564
Oswego
BERNHARDS BAY WD /
Constantia (T)
Extend Distribution System, New System Consolidation
790
$5,890,000
95
$368,833,399
Page 8 of 28
NYS Drinking Water State Revolving Fund Final Category A List ( Small Systems Serving < 10,000 People )
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
15933
Seneca
FAYETTE HAMLET WATER
DISTRICT / Fayette (T)
Extend Distribution System
17443
Albany
ALTAMONT VILLAGE /
Altamont (V)
16613
Chautauqua
17992
Pop.
Project Cost Score
Cumulative
Total
400
$3,198,000
95
$372,031,399
New Brandle Road Wells, Disinfection, and Transmission Main, New
Ground Water Source
2,000
$1,394,550
90
$373,425,949
MAYVILLE VILLAGE /
Mayville (V)
Upgrade Ground Water Source, Upgrade Transmission, Upgrade
Storage, Upgrade Distribution System
1,856
$2,884,000
90
$376,309,949
Cortland
MCGRAW VILLAGE /
McGraw (V)
Upgrade Distribution System
1,306
$4,222,961
90
$380,532,910
17732
Fulton
JOHNSTOWN (C) WATER
WORKS / Johnstown (C)
Replacement of Maylender finished water uncovered reservoir;
automation of water system operations, New Other Expenses, New
Storage, New Other (OT)
8,511
$3,255,000
90
$383,787,910
17870
Saratoga
SCWA STILLWATER
EXTENSION / Saratoga
County Water Authorit
Extend Transmission
2,100
$3,035,000
90
$386,822,910
17925
Schuyler
MONTOUR FALLS / Montour
Falls (V)
Upgrade Storage, Upgrade Distribution System
1,800
$5,852,501
90
$392,675,411
15451
Saratoga
STILLWATER WD #1
(STILLWATER VLG) /
Stillwater (T)
New Transmission, New Storage
1,560
$4,912,000
90
$397,587,411
17523
Orange
MONTGOMERY W.D. #1 /
Montgomery (T)
Extend WD #1 to consolidate several water supplies, New System
Consolidation
$13,500,000
90
$411,087,411
16390
Ulster
HIGHLAND WATER
DISTRICT / Lloyd (T)
New Storage, Extend Distribution System
4,000
$2,369,000
90
$413,456,411
16889
Oneida
KIRKLAND (T) ROUTE 5
WATER DISTRICT / Kirkland
(T)
New system to serve area with private contaminated wells,
consolidate public water supply. , New Complete System (New
System)
300
$1,578,872
90
$415,035,283
17428
Albany
FLAT ROCK ROAD W.D. /
New Scotland (T)
New Water District
149
$2,152,580
90
$417,187,863
17598
Oswego
AREA 3,4 & 8 WATER
SYSTEM / Schroeppel (T)
New Distribution System, New System Consolidation
1,500
$7,678,916
90
$424,866,779
16262
Broome
CONKLIN (T) W.D. / Conklin
(T)
Extend system to serve area with private contaminated wells,
consolidate public water supply. , Inter-Connection, System
Consolidation
1,000
$863,140
90
$425,729,919
15684
Greene
NEW BALTIMORE (T) / New
Baltimore (T)
Extend system to serve area with private contaminated wells,
consolidate public water supply. , Extend Distribution System, New
System Consolidation
1,300
$5,000,000
90
$430,729,919
17375
St.Lawrence
CANTON (T) E. SIDE WD /
Canton (T)
New Ground Water Source, New Storage, New Distribution System
350
$3,112,660
90
$433,842,579
17183
Seneca
SENECA FALLS VILLAGE /
Seneca Falls (V)
Upgrade Water Treatment Plant, Upgrade Pump Station
7,400
$2,885,000
85
$436,727,579
15490
Warren
NORTH CREEK WATER
DISTRICT / Johnsburg (T)
Upgrade Water Treatment Plant, New Ground Water Source,
Upgrade Storage
1,000
$1,112,250
85
$437,839,829
17445
Rensselaer
NORTH GREENBUSH (T)
WATER DISTRICT NO. 18 /
North Greenbush (T)
Purchase existing Private Water System, Connect to Municipal Water
System , New System Consolidation, New Water District
$437,750
85
$438,277,579
Page 9 of 28
605
212
NYS Drinking Water State Revolving Fund Final Category A List ( Small Systems Serving < 10,000 People )
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Project Cost Score
Cumulative
Total
Description
Pop.
1,400
$2,100,000
85
$440,377,579
16111
Dutchess
BARD COLLEGE / Bard
College
Upgrade Water Treatment Plant, New Storage
18043
Chautauqua
BARCELONNA WD /
Westfield (T)
New Town WD to aquire private water system. Other funding sources
may be required to make project viable and eligible for DWSRF,
Upgrade Distribution System, New Water District
128
$1,792,125
85
$442,169,704
17422
Herkimer
HERKIMER (T), WD #3, #4,
#5 / Herkimer (T)
Upgrade Pump Station, Upgrade Distribution System, Extend
Distribution System
320
$299,112
85
$442,468,816
16922
Herkimer
GRAHM, NEWPORT &
BROWN RD WD / Schuyler
(T)
New system to serve area with private contaminated wells. , New
Complete System (New System)
260
$1,280,000
85
$443,748,816
17448
Washington
KINGSBURY WD
(QUEENSBURY) / Kingsbury
(T)
New water district to serve residents in area of groundwater
contamination , New Distribution System, New Water District
$845,000
85
$444,593,816
17858
Oswego
WD#3 EXPANSION / Granby
(T)
Extend Distribution System
238
$5,315,041
85
$449,908,857
15531
Jefferson
TOWN OF PAMELIA RT. 3,
WATER DISTRICT / Pamelia
(T)
Extend system to serve area with private contaminated wells,
consolidate public water supply. , Extend Distribution System
96
$474,160
85
$450,383,017
15810
Steuben
VICTORY PLACE / Merlyn
Cavallaro
Upgrade Ground Water Source
11
$112,800
80
$450,495,817
17298
Putnam
BREWSTER VILLAGE /
Brewster (V)
New Ground Water Source, New Pump Station
2,000
$1,610,920
80
$452,106,737
17342
Washington
CAMBRIDGE VILLAGE /
Cambridge (V)
Aquisition of existing Cambridge Water Works, New Storage,
Upgrade Distribution System
1,524
$2,500,000
80
$454,606,737
17377
Chautauqua
SILVER CREEK (V) / Silver
Creek (V)
New Storage, Upgrade Distribution System
1,000
$4,311,000
80
$458,917,737
15736
Erie
COLLINS WD #3 / Collins (T)
Upgrade Transmission, New Storage, Upgrade Distribution System
760
$625,000
80
$459,542,737
18051
Montgomery
FULTONVILLE VILLAGE
PWS / Fultonville (V)
Upgrade Water Treatment Plant, Upgrade Ground Water Source,
Upgrade Distribution System
740
$1,262,150
80
$460,804,887
15704
Greene
COXSACKIE VILLAGE /
Coxsackie (V)
Upgrade Transmission, New Storage, Upgrade Distribution System
4,010
$6,210,000
80
$467,014,887
15236
Chautauqua
SHERMAN VILLAGE /
Sherman (V)
Address total Coli violations., Upgrade Distribution System
$795,000
80
$467,809,887
15325
Wayne
WOLCOTT VILLAGE /
Wolcott (V)
Upgrade Water Treatment Plant, Upgrade Surface Water Source
2,200
$3,300,000
80
$471,109,887
17145
Oneida
TIBBITS/SNOWDEN HILL
WD / New Hartford (T)
New system to serve area with private contaminated wells. , New
Complete System (New System)
450
$2,400,000
80
$473,509,887
18002
Steuben
HAMLET OF WOODHULL
MUNICIPAL WS / Woodhull
(T)
System to serve former Village (now hamlet) with private
contaminated wells., New Ground Water Source, New Storage, New
Distribution System
483
$4,489,928
80
$477,999,815
17934
Onondaga
LAFAYETTE (T) / LaFayette
(T)
Creation of Central LaFayette Water District., New Water District
2,000
$5,700,000
80
$483,699,815
Page 10 of 28
1,300
917
NYS Drinking Water State Revolving Fund Final Category A List ( Small Systems Serving < 10,000 People )
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost Score
Cumulative
Total
17077
Rensselaer
NORTH GREENBUSH WD
#13 / North Greenbush (T)
New system to serve area with private contaminated wells (Snyder's
Lake Area). , New System Consolidation, New Water District
1,050
$4,635,000
80
$488,334,815
17510
Oswego
NORTH AREA WD / Volney
(T)
New Distribution System, New System Consolidation
1,000
$6,604,000
80
$494,938,815
15599
Seneca
FAYETTE WATER PROJECT
/ Varick (T)
Extend Distribution System
520
$1,406,800
80
$496,345,615
17567
Steuben
URBANA WATER DISTRICT
#2 / Urbana (T)
Proposed WD #3. Extend system to serve private contaminated wells
and consolidate public water supplies., Extend Distribution System,
New System Consolidation, New Water District
33
$3,565,111
80
$499,910,726
16444
Columbia
DARROW SCHOOL / The
Darrow School
New Ground Water Source, New Storage
150
$169,950
75
$500,080,676
17949
Dutchess
HIGH MEADOWS PARK INC
/ High Meadows Co-op Corp
New Ground Water Source, Upgrade Storage
500
$44,577
75
$500,125,253
17533
Clinton
CHAMPLAIN VILLAGE /
Champlain (V)
Upgrade Water Treatment Plant, New Storage, Upgrade Distribution
System
2,947
$1,883,226
75
$502,008,479
16381
Orleans
LYNDONVILLE VILLAGE /
Lyndonville (V)
Upgrade Transmission, Upgrade Distribution System
1,418
$1,612,864
75
$503,621,343
15843
Delaware
MARGARETVILLE VILLAGE /
Margaretville (V)
Upgrade Storage, Upgrade Distribution System
700
$737,900
75
$504,359,243
17076
Ulster
ELLENVILLE (VILLAGE)
WATER DIS / Ellenville (V)
Upgrade Surface Water Source
4,323
$173,600
75
$504,532,843
16273
Suffolk
DERING HARBOR CORP /
Dearing Harbor (V)
Upgrade Water Treatment Plant
250
$20,791
75
$504,553,634
15718
Orange
MONROE WD #10 - PINE
TREE ROAD / Monroe (T)
New system to serve area with private contaminated wells. , New
Transmission
50
$215,000
75
$504,768,634
17633
Steuben
SYLVAN BEACH WANETA
LAKE WATER DISTRICT /
Wayne (T)
New Complete System (New System)
921
$4,175,175
75
$508,943,809
15925
Allegany
TOWN OF WELLSVILLE /
Wellsville (T)
Extend system to serve area with private contaminated wells,
Morningside Area, Extend Distribution System
5,000
$867,106
75
$509,810,915
17229
Rensselaer
NORTH GREENBUSH WD
#14 / North Greenbush (T)
New system to serve inadequate private wells in Northeast corner of
Town , New Inter-Connection, New System Consolidation, New
Water District
3,000
$7,313,000
75
$517,123,915
16899
Oneida
FLOYD BENEFIT (T) AREA
"D" / Floyd (T)
New Complete System (New System)
900
$7,750,000
75
$524,873,915
17979
Jefferson
WATRE DISTRICT NO. 8 /
Watertown (T)
Extend Distribution System, New System Consolidation
119
$1,929,000
75
$526,802,915
17311
Herkimer
MANION HEIGHTS WD /
German Flatts (T)
New Complete System (New System)
105
$152,000
75
$526,954,915
17098
Jefferson
WILNA WD#1 / Wilna (T)
Extend system to serve area with private contaminated wells. , New
Distribution System
85
$569,590
75
$527,524,505
Page 11 of 28
NYS Drinking Water State Revolving Fund Final Category A List ( Small Systems Serving < 10,000 People )
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
5,676
17368
Orange
GOSHEN VILLAGE / Goshen
(V)
New Water Treatment Plant, New Ground Water Source, New
Transmission
16984
Westchester
KITCHAWAN WATER
DISTRICT / Yorktown (T)
correct organic exceedances., New Transmission
17042
Orange
MONROE VILLAGE / Monroe
(V)
Upgrade Distribution System
17082
Ontario
17667
Project Cost Score
Cumulative
Total
$5,311,500
70
$532,836,005
240
$500,000
70
$533,336,005
8,892
$986,000
70
$534,322,005
CLIFTON SPRINGS VILLAGE New Storage, Upgrade Distribution System
/ Clifton Springs (V)
2,190
$618,000
70
$534,940,005
Tioga
NEWARK VALLEY VILLAGE / Upgrade Distribution System
Newark Valley (V)
1,253
$4,813,000
70
$539,753,005
15560
Oneida
VERNON VILLAGE (SWP) /
Vernon (V)
New Transmission, New Storage, New Distribution System, New
Inter-Connection
1,155
$5,610,300
70
$545,363,305
17618
St.Lawrence
GOUVERNEUR VILLAGE /
Gouverneur (V)
Upgrade Water Treatment Plant
4,263
$2,160,600
70
$547,523,905
17626
Ulster
NEW PALTZ (VILLAGE)
WATER DIST / New Paltz (V)
Upgrade Water Treatment Plant, New Storage, Upgrade Distribution
System
5,600
$5,675,916
70
$553,199,821
18009
Tompkins
DRYDEN VILLAGE / Dryden
(V)
New Ground Water Source, New Storage, Upgrade Distribution
System
2,000
$5,924,000
70
$559,123,821
15205
Oneida
BOONVILLE VILLAGE /
Boonville (V)
New Transmission, New Storage, Upgrade Distribution System
2,300
$801,144
70
$559,924,965
17635
Schenectady
PRINCETOWN WATER
SUPPLY / Princetown (T)
New Transmission, New Storage, New Pump Station, Extend
Distribution System
600
$360,500
70
$560,285,465
17972
Cayuga
(T) BRUTUS WATER
DISTRICT #8 / Brutus (T)
New (T) Brutus WD #8 (Cottle Road), Upgrade Distribution System,
New Water District
400
$1,920,334
70
$562,205,799
16012
Chautauqua
WESTFIELD VILLAGE /
Westfield (V)
East Main St., Upgrade Distribution System
$950,000
70
$563,155,799
17571
Ulster
WEST HURLEY WATER
DISTRICT #1 (PROPOSED) /
Hurley (T)
New Complete System (New System)
450
$4,713,160
70
$567,868,959
17359
Madison
LEWIS POINT/PINE RIDGE
ROAD / Lenox (T)
New Water District
210
$1,192,230
70
$569,061,189
16435
Oneida
DEERFIELD (T), SMITH HILL
EXT. / Deerfield (T)
Extend system to serve area with private contaminated wells,
consolidate public water supply. , Extend Distribution System
200
$638,000
70
$569,699,189
17526
Allegany
WELLSVILLE WATER
DISTRICT / Wellsville (T)
Extend Distribution System, New Water District
133
$1,192,450
70
$570,891,639
15435
Washington
FORT EDWARD WD #2 / Fort
Edward (T)
Extend Distribution System
126
$650,000
70
$571,541,639
17884
Onondaga
MARCELLUS (T) / Marcellus
(T)
Pheasant Valley Road WD., New Distribution System, New
Inter-Connection
93
$782,000
70
$572,323,639
Page 12 of 28
3,450
NYS Drinking Water State Revolving Fund Final Category A List ( Small Systems Serving < 10,000 People )
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
17186
Steuben
REXVILLE WATER
DISTRICT / West Union (T)
New system to serve area with private contaminated wells. , New
Complete System (New System)
17663
Suffolk
EAST FARMINGDALE WD /
Babylon East Farmingdale
WD
VOC Treatment at Plant No. 4, Upgrade Water Treatment Plant
16144
Orange
GOSHEN W.D. #1
(HAMBLETONIAN PARK) /
Goshen (T)
16737
Dutchess
17504
Pop.
60
Project Cost Score
Cumulative
Total
$100,000
70
$572,423,639
7,500
$4,398,512
65
$576,822,151
New Ground Water Source, New Storage, Upgrade Distribution
System
509
$2,605,900
65
$579,428,051
DOVER RIDGE ESTATES /
Beekman (T)
Upgrade Ground Water Source
250
$266,500
65
$579,694,551
Schoharie
CENTRAL BRIDGE WATER
DISTRICT / Central Bridge
WD
DBP Control , Upgrade Water Treatment Plant
1,061
$1,773,000
65
$581,467,551
17575
Fulton
NORTHAMPTON (T) WATER
DISTRICT / Northampton (T)
Upgrade Storage, Upgrade Distribution System
1,000
$6,303,627
65
$587,771,178
17282
Dutchess
RHINEBECK VILLAGE
WATER / Rhinebeck (V)
Upgrade Water Treatment Plant
4,300
$365,200
65
$588,136,378
16762
Cayuga
UNION SPRINGS VILLAGE /
Union Springs (V)
New Water Treatment Plant
2,000
$165,000
65
$588,301,378
15797
Essex
PORT HENRY V / Port Henry
(V)
Upgrade Transmission, Upgrade Distribution System
1,831
$511,910
65
$588,813,288
15042
Genesee
ALEXANDER VILLAGE /
Alexander (V)
New Storage
781
$880,425
65
$589,693,713
17746
Ontario
RUSHVILLE VILLAGE /
Rushville (V)
Upgrade Surface Water Treatment Rule Compliance Facility
621
$1,969,200
65
$591,662,913
17389
Onondaga
NORTHEAST LAFAYETTE
WD / East Syracuse (V)
Replace lead service lines from the watermain to the property line to
correct lead & copper exceedances., Upgrade Distribution System
250
$444,445
65
$592,107,358
17609
Chenango
NORWICH CITY / Norwich (C) New Water Treatment Plant
8,000
$8,652,000
65
$600,759,358
17766
Broome
DEPOSIT (V) WATER
DEPARTMENT / Deposit (V)
Upper NW Quadrant water main reconstruction, new river crossing,
new telemetry system., Upgrade Transmission, Upgrade Distribution
System
2,080
$2,006,336
65
$602,765,694
17417
Delaware
ARKVILLE WATER
DISTRICT / Middletown (T)
Extend distribution, 100,000 gallons of storage, 100 gpm well, system
consolidation., New Ground Water Source, New Storage, Extend
Distribution System, Extend System Consolidation
400
$1,833,375
65
$604,599,069
15040
Montgomery
PALATINE BRIDGE (V)
WATER WORKS / Palantine
Bridge (V)
Upgrade Water Treatment Plant, Upgrade Ground Water Source,
Upgrade Distribution System
890
$985,750
65
$605,584,819
17610
Montgomery
AMSTERDAM (T) /
Amsterdam(T)
New Storage, New Pump Station, Extend Distribution System
400
$4,506,250
65
$610,091,069
17935
Madison
LENOX (T) / Lenox (T)
Water District No. 12., New Water District
750
$5,000,000
65
$615,091,069
18016
Steuben
WD #3 / Campbell (T)
Serve private contaminated/poor yielding wells., Extend Water
District
$908,687
65
$615,999,756
Page 13 of 28
1,025
NYS Drinking Water State Revolving Fund Final Category A List ( Small Systems Serving < 10,000 People )
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost Score
Cumulative
Total
16679
Seneca
JUNIUS WATER DISTRICT
#1 / Junius (T)
Extend system to serve area with private contaminated wells. W.D.
Ext. #2., Extend Distribution System
300
$623,607
65
$616,623,363
16798
St.Lawrence
EAST NORFOLK WATER
DISTRICT / Norfolk (T)
New system to serve area with private contaminated wells. , New
Complete System (New System)
270
$750,000
65
$617,373,363
15183
Orleans
SHELBY (T) / Shelby (T)
Extend system to serve area with private contaminated wells. Water
Improvement No. 4 - Phase I., Extend Distribution System
240
$249,700
65
$617,623,063
17826
Lewis
WATER DISTRICT NO. 10 /
Lowville (T)
New Distribution System
240
$507,000
65
$618,130,063
16921
Jefferson
ADAMS (T) WD #2 / Adams
(T)
New system to serve area with private contaminated wells. , New
Complete System (New System)
190
$1,509,000
65
$619,639,063
15483
Yates
BENTON TOWN WATER
DISTRICT NO. 1 / Benton (T)
Extend system to serve area with private contaminated wells. ,
Extend Distribution System
97
$639,000
65
$620,278,063
16699
Westchester
SUNSET RIDGE WATER
DISTRICT / North Salem (T)
Replacement of pump control equipment, storage tank cleaning &
coating, water main replacement & installation, pump house reapirs,
pump house fencing and driveway, Upgrade Storage, Upgrade Pump
Station, Upgrade Distribution System
625
$400,000
60
$620,678,063
17548
Albany
MENANDS VILLAGE /
Menands (V)
Upgrade Pump Station, Upgrade Distribution System
3,900
$6,936,000
60
$627,614,063
17193
Essex
AUSABLE FORKS WD / Jay
(T)
Upgrade Water Treatment Plant, New Storage
900
$5,201,603
60
$632,815,666
16576
Chemung
NORTHSTAR MHP / Leading
Edge Properties
water softener system and, Upgrade Distribution System
400
$93,113
60
$632,908,779
18038
Saratoga
MECHANICVILLE CITY /
Mechanicville (C)
Interconnection to SCWA, Alternative to Project 17742, New
Transmission
5,100
$9,465,623
60
$642,374,402
15846
Essex
MORIAH WD / Moriah (T)
Upgrade Distribution System
3,100
$606,876
60
$642,981,278
16653
Delaware
WALTON VILLAGE / Walton
(V)
Upgrade Controls, Upgrade Ground Water Source, Upgrade
Distribution System
3,070
$0
60
$642,981,278
17037
Nassau
EAST WILLISTON (V) / East
Williston (V)
Replacement of lead service lines to about 120 residences, New
Other Expenses, New Other (OT)
2,503
$456,000
60
$643,437,278
16236
Dutchess
RED HOOK VILLAGE / Red
Hook (V)
New Ground Water Source, Upgrade Ground Water Source, New
Storage, Upgrade Distribution System
2,214
$9,328,300
60
$652,765,578
17883
Ulster
NEW PALTZ (V) / New Paltz
(V)
Construct mains in Northern portion of Village to loop system,
Upgrade Distribution System
6,000
$759,625
60
$653,525,203
18026
Tioga
CANDOR VILLAGE WATER
DEPT. / Candor (V)
Upgrade Storage, Upgrade Distribution System
1,020
$3,047,237
60
$656,572,440
17097
Orleans
MEDINA VILLAGE / Medina
(V)
Upgrade Distribution System
6,500
$4,088,085
60
$660,660,525
17092
Otsego
LAURENS VILLAGE /
Laurens (V)
New Storage, Upgrade Distribution System
381
$1,236,000
60
$661,896,525
Page 14 of 28
NYS Drinking Water State Revolving Fund Final Category A List ( Small Systems Serving < 10,000 People )
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
15561
Jefferson
WATERTOWN (T) /
Watertown (T)
New system to serve area with private contaminated wells. , New
Complete System (New System), New Storage, New Distribution
System
17036
Genesee
TOWN OF PEMBROKE
WATER DISTRICT NO. 1 /
Pembroke (T)
16814
Ontario
16886
Pop.
Project Cost Score
Cumulative
Total
530
$2,547,476
60
$664,444,001
Extend system to serve area with private contaminated wells. ,
Extend Distribution System
2,000
$3,860,000
60
$668,304,001
WEST BLOOMFIELD WD /
West Bloomfield (T)
Extend system to serve area with private contaminated wells. ,
Extend Distribution System
1,500
$231,750
60
$668,535,751
Ontario
WEST BLOOMFIELD WD /
West Bloomfield (T)
County Road 35 and Dugway Road. , Extend Distribution System
1,500
$195,513
60
$668,731,264
17927
Lewis
CONSOLIDATED WATER
DISTRICT / Watson (T)
New Ground Water Source, New Storage, Extend Distribution System
1,500
$12,389,600
60
$681,120,864
16767
Seneca
ROUTE 96 WATER
DISTRICT / Waterloo (T)
Extend system to serve area with private contaminated wells. ,
Extend Distribution System
202
$1,845,512
60
$682,966,376
15578
Seneca
BURGESS ROAD WATER
DISTRICT / Junius (T)
Extend system to serve area with private contaminated wells. ,
Extend Distribution System
200
$699,100
60
$683,665,476
17616
Oneida
VIENNA (T) / Vienna (T)
New Distribution System
150
$210,000
60
$683,875,476
17886
Oneida
HALSTEAD ROAD WD /
Vienna (T)
Extend Distribution System
75
$692,400
60
$684,567,876
16516
Suffolk
WEST NECK WATER
SUPPLY / Shelter Island (T)
Upgrade Distribution System
100
$550,000
55
$685,117,876
15811
Onondaga
SKANEATELES VILLAGE /
Skaneateles (V)
Improve disinfection contact time., Upgrade Transmission
2,610
$1,600,000
55
$686,717,876
17031
Essex
CROWN POINT WD / Crown
Point (T)
Upgrade Distribution System
995
$2,795,678
55
$689,513,554
16571
Franklin
HARRIETSTOWN (T) /
Harrietstown (T)
Upgrade Distribution System
5,621
$710,800
55
$690,224,354
16957
Franklin
CHATEAUGAY V /
Chateaugay (V)
Upgrade Distribution System
1,100
$2,750,000
55
$692,974,354
17547
Broome
WHITNEY POINT VILLAGE /
Whitney Point (V)
New Wells, Main Street Wellfield/Pumphouse Improvements.,
Upgrade Ground Water Source, New Ground Water Source
1,054
$569,400
55
$693,543,754
18064
Oneida
FORESTPORT WATER
DISTRICT / Foresport (T)
New Ground Water Source
900
$390,000
55
$693,933,754
18015
Yates
WS IMPROVEMENTS /
Dundee (V)
Upgrade Storage, Upgrade Distribution System
1,690
$6,913,360
55
$700,847,114
18007
Cortland
MARATHON VILLAGE /
Marathon (V)
New Storage, New Pump Station, Upgrade Distribution System
1,107
$2,947,345
55
$703,794,459
17940
Delaware
ROXBURY WATER
DISTRICT / Roxbury (T)
Upgrade Storage, Upgrade Distribution System
755
$1,423,000
55
$705,217,459
Page 15 of 28
NYS Drinking Water State Revolving Fund Final Category A List ( Small Systems Serving < 10,000 People )
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
17599
Sullivan
EDGEWOOD LAKES, INC. /
Edgewood Lakes Inc.
Replace hydropneumatic tank, New Storage
17670
Erie
EDEN WD#7 / Eden (T)
Eden WD#7, New Storage, New Distribution System
17673
Erie
EDEN WD#2 / Eden (T)
Eden WD#2 Shadagee Road Water Project Pump Station and
Waterlines, New Pump Station, New Distribution System
16501
Erie
BLASDELL VILLAGE /
Blasdell (V)
18071
Cattaraugus
18049
Pop.
17
Project Cost Score
Cumulative
Total
$9,000
55
$705,226,459
1,800
$5,460,000
55
$710,686,459
500
$5,280,000
55
$715,966,459
Consolidation of the Village system with Erie County Water Authority,
Upgrade Distribution System, New System Consolidation
3,200
$2,515,000
55
$718,481,459
RANDOLPH VILLAGE /
Randolph (T)
East Randolph and Randolph (V)'s Repalcement of Water Mains,
Upgrade Distribution System
1,250
$7,075,000
55
$725,556,459
Erie
CONCORD TOWN WATER
SYSTEM / Town of Concord
Extend Distribution System
$335,000
55
$725,891,459
18010
Oswego
TOWN/VILLAGE JOINT
WATER PROJECT / Parish
(T)
Serve private contaminated/poor yielding wells., Extend Distribution
System
$10,150,000
55
$736,041,459
15109
Seneca
VARICK/ROMULUS WATER
PROJECT / Varick (T)
Extend Distribution System
850
$3,100,000
55
$739,141,459
15339
Erie
EAST HILL WATER
DISTRICT NO. 3 / Boston (T)
New Storage, New Pump Station, Extend Distribution System
800
$3,708,000
55
$742,849,459
17220
Cayuga
VICTORY (T) WD #2 / Victory
(T)
Extend Distribution System
612
$3,389,601
55
$746,239,060
15090
Schenectady
PRINCETOWN WATER
SUPPLY / Princetown (T)
Extend Distribution System
600
$929,060
55
$747,168,120
15092
Schenectady
PRINCETOWN WATER
SUPPLY / Princetown (T)
Extend Distribution System
600
$632,420
55
$747,800,540
16949
Schenectady
PRINCETOWN WATER
SUPPLY / Princetown (T)
Extend Distribution System
600
$495,430
55
$748,295,970
17636
Schenectady
PRINCETOWN WATER
SUPPLY / Princetown (T)
Extend Distribution System
600
$286,340
55
$748,582,310
15613
Livingston
YORK (T) WD NO. 2 / York
(T)
Extend Distribution System
350
$526,330
55
$749,108,640
18047
Genesee
RTE 98 WD / Batavia (T)
New Water District the serve areas East and West of Rte. 98, New
Water District
318
$5,322,464
55
$754,431,104
16724
Seneca
TYRE (T) WATER DISTRICT
/ Tyre (T)
Extend system to serve area with private contaminated wells. ,
Extend Distribution System
260
$992,508
55
$755,423,612
16851
Erie
AURORA (T) WATER IMP.
AREA NO. 5 / Aurora (T)
Extend Distribution System
210
$613,500
55
$756,037,112
15089
Schenectady
PRINCETOWN (T) - WD#1 /
Princetown (T)
Extend Distribution System
183
$860,050
55
$756,897,162
Page 16 of 28
125
1,200
NYS Drinking Water State Revolving Fund Final Category A List ( Small Systems Serving < 10,000 People )
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
16804
Broome
STILLWATER RD WD#6 /
Conklin (T)
17315
Cayuga
15545
Description
Extend Distribution System
Pop.
Project Cost Score
Cumulative
Total
173
$412,782
55
$757,309,944
New Pump Station, Extend Distribution System
MORAVIA (T) WATER
DISTRICT NO. 1 / Moravia (T)
162
$663,320
55
$757,973,264
Ontario
New Storage, Extend Distribution System
OAKMOUNT ROAD WATER
SYSTEM / East Bloomfield (T)
150
$2,224,000
55
$760,197,264
18045
Genesee
CREEK RD. WD / Batavia (T)
New Water District
136
$1,407,623
55
$761,604,887
17189
Jefferson
WATER DISTRICT #5 / Cape
Vincent (T)
New system to serve area with private contaminated wells. , New
Distribution System
100
$1,085,200
55
$762,690,087
17478
Clinton
ROUTE 11 WD / Champlain
(T)
Extend Distribution System
100
$1,267,380
55
$763,957,467
17771
Albany
MARTINS HILL ROAD
WATER DISTRICT /
Coeymans (T)
Extend distribution from Village of Ravena to serve Martins Hill Road
Water District., Extend Distribution System, New Water District
66
$314,150
55
$764,271,617
18046
Genesee
PRATT RD. WD / Batavia (T)
New Water District
55
$1,067,974
55
$765,339,591
17479
Clinton
WEST SERVICE ROAD WD /
Champlain (T)
Extend Distribution System
30
$675,284
55
$766,014,875
18011
Oneida
ROUTE 5 WD / Vernon (T)
Serve private contaminated/poor yielding wells., Extend Distribution
System
30
$244,000
55
$766,258,875
17584
Westchester
ARBOR HILLS WATER
WORKS / Arbor Hills
Waterworks
New wells, storage and booster pump., New Ground Water Source,
New Storage
180
$725,000
50
$766,983,875
15430
Putnam
BREWSTER VILLAGE /
Brewster (V)
New Storage
2,000
$1,628,000
50
$768,611,875
16211
Niagara
NIAGARA WATER
IMPROVEMENT AREA /
Niagara County
Contract 15G, E., Upgrade Water Treatment Plant, Upgrade
Transmission
8,978
$6,526,857
50
$775,138,732
18069
Madison
HAMILTON VILLAGE /
Hamilton (V)
New Ground Water Source, Upgrade Distribution System
3,904
$4,100,000
50
$779,238,732
16188
Chautauqua
WESTFIELD VILLAGE /
Westfield (V)
Upgrade Water Treatment Plant
3,450
$2,150,000
50
$781,388,732
18062
Oswego
CLEVELAND VILLAGE /
Cleveland (V)
Upgrade Ground Water Source, Upgrade Storage, Upgrade
Distribution System
925
$1,576,930
50
$782,965,662
17948
Greene
HENSONVILLE (WINDHAM
W.D.) / Windham (T)
Upgrade Ground Water Source
402
$757,050
50
$783,722,712
16627
Nassau
CARLE PLACE WD / Carle
Place WD
Wells #3 & #4, Terrace Drive, Carle Place, NY, New Water
Treatment Plant
9,005
$1,510,800
50
$785,233,512
17191
Yates
PENN YAN VILLAGE / Penn
Yan (V)
Upgrade Water Treatment Plant
5,248
$1,300,000
50
$786,533,512
Page 17 of 28
NYS Drinking Water State Revolving Fund Final Category A List ( Small Systems Serving < 10,000 People )
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Project Cost Score
Cumulative
Total
Description
Pop.
1,900
$3,048,188
50
$789,581,700
15240
Jefferson
ALEXANDRIA VILLAGE /
Alexandria Bay (V)
Upgrade Surface Water Source, Upgrade Storage, Upgrade
Distribution System
17982
Steuben
PRATTSBURGH WATER
DISTRICT / Prattsburgh (T)
Upgrade Storage, Upgrade Distribution System
850
$1,485,415
50
$791,067,115
17319
Putnam
MOUNTAIN BROOK HOMES
/ Southeast (T)
New Water Treatment Plant, New Ground Water Source
176
$427,000
50
$791,494,115
16880
Seneca
INTERLAKEN VILLAGE /
Interlaken (V)
Upgrade Ground Water Source
650
$320,807
50
$791,814,922
15287
Cortland
VIRGIL (T) / Virgil (T)
Upgrade Ground Water Source, New Storage, Extend Distribution
System, System Consolidation
345
$2,223,234
50
$794,038,156
15297
Cortland
HOMER VILLAGE-NEWTON
WATER WORKS / Homer (V)
Upgrade Distribution System
4,368
$440,000
50
$794,478,156
17921
Oneida
EUREKA ROAD WD /
Westmoreland (T)
New Pump Station, New Distribution System
35
$180,000
50
$794,658,156
17378
Ontario
GORHAM TOWN WD /
Gorham (T)
Extension No. 9., Extend Distribution System
4,500
$732,000
50
$795,390,156
16449
Albany
GREEN ISLAND VILLAGE /
Green Island (V)
Extend Distribution System
2,900
$381,100
50
$795,771,256
18018
Wyoming
CASTILE VILLAGE / Castile
(V)
Upgrade Other Expenses, Upgrade Storage, Upgrade Distribution
System, New System Consolidation, Upgrade Other (OT)
1,135
$2,444,813
50
$798,216,069
17899
Genesee
WD II / Alabama (T)
Extend Water District
1,056
$5,416,206
50
$803,632,275
17596
Tioga
SPENCER (V) / Spencer (V)
New Complete System (New System), New System Consolidation
731
$7,865,000
50
$811,497,275
17978
Jefferson
NORTHEAST WATER
DISTRICT / Waertown (T)
New Ground Water Source, New Storage, New Distribution System
550
$6,177,300
50
$817,674,575
17327
Onondaga
CROSS LAKE/N. ELBRIDGE
AREA WD / Elbridge (T)
New Storage, New Pump Station, Extend Distribution System
534
$2,590,450
50
$820,265,025
16205
Oswego
SENECA HILLS HEALTH
CAMPUS / Volney (T)
Upgrade Distribution System
450
$1,115,000
50
$821,380,025
16908
Chautauqua
BUSTI (T) WATER DISTRICT
#3 / Busti (T)
Extend Distribution System
450
$750,000
50
$822,130,025
17223
Cayuga
WEST GENESEE STREET
WATER DISTRICT / Aurelius
(T)
Extend Distribution System
175
$1,198,000
50
$823,328,025
17026
Seneca
BOODY'S HILL WD (WATER
DISTRICT #5) / Fayette (T)
Extend to serve private contaminated wells. , Extend Distribution
System
151
$788,980
50
$824,117,005
17058
Jefferson
HOUNSFIELD (T) WD #2
EXTENSION / Hounsfield (T)
Extend Distribution System
123
$794,439
50
$824,911,444
Page 18 of 28
NYS Drinking Water State Revolving Fund Final Category A List ( Small Systems Serving < 10,000 People )
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Project Cost Score
Cumulative
Total
Description
Pop.
100
$1,115,000
50
$826,026,444
29
$378,000
50
$826,404,444
17895
Livingston
LONG POINT ROAD WD /
Geneseo(T)
Extend Water District
17326
Onondaga
LAIRD ROAD WATER
DISTRICT / Elbridge (T)
Extend Distribution System
16136
Westchester
ELMSFORD VILLAGE /
Elmsford (V)
Upgrade Water Treatment Plant
4,600
$1,000,000
45
$827,404,444
15834
Wayne
PALMYRA VILLAGE /
Palmyra (V)
New Pump Station
3,550
$102,700
45
$827,507,144
17941
Herkimer
MIDDLEVILLE (V) WATER
WORKS / Middleville (V)
Upgrade Ground Water Source, Upgrade Pump Station, Upgrade
Distribution System
725
$3,453,415
45
$830,960,559
18052
Jefferson
CAPE VINCENT VILLAGE /
Cape Vincent (V)
Upgrade Water Treatment Plant
1,500
$3,200,000
45
$834,160,559
17929
Steuben
PINEWOOD ACRES WATER
DISTRICT / Corning
Upgrade Storage, Upgrade Pump Station, Upgrade Distribution
System
168
$3,426,552
45
$837,587,111
17945
Sullivan
MONTICELLO VILLAGE /
Monticello (V)
Upgrade storage and distribution piping, Upgrade Storage, Upgrade
Distribution System
8,000
$7,395,000
45
$844,982,111
17055
Herkimer
FRANKFORT (V) WATER
WORKS / Frankfort (V)
New Ground Water Source
2,995
$481,691
45
$845,463,802
17057
Herkimer
FRANKFORT (V) WATER
WORKS / Frankfort (V)
Upgrade Distribution System
2,995
$1,971,007
45
$847,434,809
15547
Allegany
FRIENDSHIP TOWN WATER
DISTRICT / Friendship (T)
Upgrade Ground Water Source, Upgrade Storage, Upgrade
Distribution System
1,380
$1,030,000
45
$848,464,809
17226
Franklin
CHATEAUGAY (T) WD#1 /
Chateaugay (T)
New Water District
100
$114,075
45
$848,578,884
17402
Suffolk
WEST NECK WATER
SUPPLY / Shelter Island (T)
New Well, New Ground Water Source
100
$2,000
45
$848,580,884
15724
Chautauqua
LAKEWOOD VILLAGE /
Lakewood (V)
New Transmission, New Pump Station, Inter-Connection
3,258
$870,000
45
$849,450,884
16512
Wayne
OLD LYONS-NEWARK
ROAD WATER DISTRICT /
Lyons (T)
New Transmission
300
$207,000
45
$849,657,884
17453
Broome
LILIAN DRIVE WD /
Binghamton (T)
New Pump Station, Upgrade Distribution System, New
Inter-Connection, New System Consolidation, New Water District
120
$281,000
45
$849,938,884
17953
Montgomery
NELLISTON VILLAGE /
Nelliston (V)
New Storage, Upgrade Distribution System
375
$4,493,000
45
$854,431,884
15078
Orange
HOLIDAY MOBILE PARK
INC. / Mid-Hudson Park
Management
Upgrade Distribution System, System Consolidation
250
$412,000
45
$854,843,884
15276
Montgomery
GLEN (T) W.D.#1 / Glen (T)
Extend Distribution System
5,000
$950,000
45
$855,793,884
Page 19 of 28
NYS Drinking Water State Revolving Fund Final Category A List ( Small Systems Serving < 10,000 People )
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
15664
Niagara
HARTLAND WD / Hartland (T) Extend Distribution System
16612
Ontario
NORTH FARMINGTON WD /
Farmington (T)
16698
Ontario
17922
Pop.
Project Cost Score
Cumulative
Total
4,165
$726,500
45
$856,520,384
Fox Road & County Road 28., Extend Distribution System
2,300
$155,128
45
$856,675,512
GENEVA (T) / Geneva (T)
New Storage, New Distribution System
1,500
$2,541,000
45
$859,216,512
Oneida
NORTHEASTERN WD /
Westmoreland (T)
New Storage, New Pump Station, New Distribution System
880
$6,700,000
45
$865,916,512
16442
Suffolk
NORTHEAST WOODS / East
Hampton (T)
Northeast Woods, East Hampton (T), Extend Distribution System
675
$2,524,278
45
$868,440,790
16313
Onondaga
TOWN OF LYSANDER W.D. / Lamson Road Water District., New Distribution System, New Water
District
Lysander (T)
500
$5,284,000
45
$873,724,790
17672
Erie
EDEN WD#6 / Eden (T)
Eden WD#6, New Distribution System
500
$420,000
45
$874,144,790
16687
Chenango
NORWICH TOWN WATER
DISTRICT #2 / Norwich (T)
Extend Distribution System
200
$390,885
45
$874,535,675
17811
Cayuga
CAYUGA COUNTY WATER
& SEWER / Cayuga County
W&SA
New Centerport / Sine Roads WD in (T) Throop., Extend Distribution
System, New Water District
200
$818,850
45
$875,354,525
17671
Erie
EDEN WD#5 / Eden (T)
Eden WD#5, New Distribution System
150
$5,880,000
45
$881,234,525
17677
Genesee
WATER DISTRICT #5 /
Stafford (T)
Extend Distribution System
123
$927,000
45
$882,161,525
16801
Broome
CHENANGO WD #8 /
Chenango (T)
New Water District
100
$121,000
45
$882,282,525
16802
Broome
CHENANGO WD #4 /
Chenango (T)
New Water District
100
$112,450
45
$882,394,975
16884
Monroe
SOUTH CHILI WATER IMP.
BENEFIT AREA NO. 2 / Chili
(T)
Extend Distribution System
100
$386,250
45
$882,781,225
17066
Genesee
BYRON (T) WD NO. 3 / Byron
(T)
Extend to serve private contaminated wells in the Hamlet of North
Byron., Extend Distribution System
100
$148,000
45
$882,929,225
17768
Genesee
WATER DISTRICT #8 /
Stafford (T)
New Distribution System
90
$859,700
45
$883,788,925
17601
Putnam
GARRISON LANDING WS /
Philipstown (T)
New Complete System (New System)
84
$325,146
45
$884,114,071
15295
Dutchess
BEEKMAN (T) / Beekman (T)
New Complete System (New System), New Distribution System
80
$579,478
45
$884,693,549
17676
Genesee
WATER DISTRICT #7 /
Stafford (T)
Extend Distribution System
75
$679,700
45
$885,373,249
Page 20 of 28
NYS Drinking Water State Revolving Fund Final Category A List ( Small Systems Serving < 10,000 People )
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost Score
Cumulative
Total
16575
Genesee
BARBARY COAST MHP /
Affordable Great Locations
Extend Distribution System
50
$82,700
45
$885,455,949
15417
Albany
KRUMKILL RD. WATER
DISTRICT / New Scotland (T)
Extend Distribution System
45
$2,500,000
45
$887,955,949
15616
Ulster
PORT EWEN WATER
DISTRICT / Esopus (T)
New Storage
4,800
$2,100,000
40
$890,055,949
15895
Warren
CHESTERTOWN WATER
DISTRICT / Chester (T)
Corrosion Control , Upgrade Ground Water Source
1,300
$2,500
40
$890,058,449
15629
Steuben
HAMMONDSPORT VILLAGE
/ Hammondsport (V)
Upgrade Distribution System
741
$405,000
40
$890,463,449
17804
Cayuga
WELLS COLLEGE / Wells
College
Upgrade Water Treatment Plant, Upgrade Distribution System
400
$1,642,850
40
$892,106,299
15884
Warren
POTTERSVILLE WATER
DISTRICT / Chester (T)
Upgrade Ground Water Source
325
$14,400
40
$892,120,699
17957
Dutchess
BARD COLLEGE / Bard
College
New microfiltration plant.,
1,400
$991,620
40
$893,112,319
15944
Chenango
OXFORD VILLAGE / Oxford
(V)
New Ground Water Source, Upgrade Distribution System
1,738
$154,039
40
$893,266,358
15229
Orange
SLEEPY HOLLOW MOBILE
PARK / Sleepy Hollow MHP,
LLC
Upgrade Transmission, Upgrade Distribution System
400
$386,250
40
$893,652,608
18070
Wayne
TRANSMISSION MAIN
REPLACEMENT / Clyde(V)
Upgrade Transmission
2,270
$357,900
40
$894,010,508
15308
Livingston
EAST LAKE ROAD WATER
DISTRICT / Livonia (T)
Extend Distribution System
1,450
$2,093,140
40
$896,103,648
15129
Albany
NORTHEAST WATER
DISTRICT / New Scotland (T)
New Complete System (New System)
370
$843,905
40
$896,947,553
15209
Ontario
PHELPS (T) - ROUTE 96
WEST WD / Phelps (T)
Extend Distribution System
300
$1,132,000
40
$898,079,553
15554
Ontario
WEST LAKE RD BENEFIT
BASIS DIS / Canandaigua (T)
Canandaigua. (T), Extend Distribution System
220
$1,243,100
40
$899,322,653
15148
Monroe
OGDEN (T) / Ogden (T)
Extend Distribution System
171
$429,330
40
$899,751,983
16799
Broome
CHENANGO WD #25 /
Chenango (T)
New WD to serve private insufficient yielding wells area of Poplar Hill
Road , New Complete System (New System)
100
$383,500
40
$900,135,483
18056
Orange
WARWICK VILLAGE /
Warwick (V)
Upgrade Water Treatment Plant, New Ground Water Source
6,083
$323,725
35
$900,459,208
17974
Steuben
SOUTH CORNING VILLAGE / Upgrade Storage, Upgrade Distribution System
South Corning (V)
1,147
$7,763,007
35
$908,222,215
Page 21 of 28
NYS Drinking Water State Revolving Fund Final Category A List ( Small Systems Serving < 10,000 People )
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
16073
Rensselaer
PETERSBURGH WATER
DISTRICT / Petersburg (T)
Upgrade Ground Water Source
16209
Niagara
NIAGARA WATER
IMPROVEMENT AREA /
Niagara County
Contract 14A, E, G & H., Upgrade Water Treatment Plant
16586
Niagara
NIAGARA WATER
IMPROVEMENT AREA /
Niagara (T)
18030
Rensselaer
17262
Pop.
240
Project Cost Score
Cumulative
Total
$109,154
35
$908,331,369
8,978
$2,859,246
35
$911,190,615
New Transmission
8,978
$400,000
35
$911,590,615
RENSSELAER CITY PWS /
Rensselaer (C)
Washington Ave Corridor Improvements, Upgrade Distribution
System
7,500
$3,169,952
35
$914,760,567
Orleans
HOLLEY VILLAGE / Holley
(V)
NYS Route 31., Upgrade Distribution System
2,150
$210,243
35
$914,970,810
17540
Genesee
OAKFIELD VILLAGE /
Oakfield (V)
Upgrade Transmission, Upgrade Storage, Upgrade Distribution
System
1,805
$2,864,100
35
$917,834,910
17791
Delaware
STAMFORD VILLAGE /
Stamford (V)
New Storage, Upgrade Distribution System
1,280
$2,575,000
35
$920,409,910
16897
Essex
CROWN POINT WD / Crown
Point (T)
Upgrade Distribution System
995
$1,000,000
35
$921,409,910
17595
Essex
FOREVER WILD WATER
CO-SIGNOR / Forever Wild
Water Company
Upgrade Ground Water Source, Upgrade Storage, Upgrade Pump
Station
900
$2,247,987
35
$923,657,897
16723
Chemung
WELLSBURG VILLAGE /
Wellsburg (V)
Upgrade Distribution System
631
$644,700
35
$924,302,597
15062
Oneida
TAURUSEL, INC (POND
HILL) / Taurusel, Inc.
Upgrade Ground Water Source, Upgrade Distribution System,
System Consolidation
54
$164,000
35
$924,466,597
15086
Seneca
BORDER CITY WATER
DISTRICT / Waterloo (T)
Upgrade Distribution System
1,600
$161,340
35
$924,627,937
17560
Sullivan
THE CALLICOON WATER
COMPANY INC / Callicoon
Water Co., Inc.
Replace water tower on Delvue Road., New Storage
854
$100,000
35
$924,727,937
17887
Cayuga
CATO VILLAGE / Cato (V)
New Storage
601
$1,152,505
35
$925,880,442
15087
Sullivan
ROUTE 55 WATER
DISTRICT / Liberty (T)
New Storage, New Pump Station, Upgrade Distribution System
500
$400,000
35
$926,280,442
17725
Dutchess
DUTCHESS COUNTY
WATER/WASTEWATER
PLANT / DCWWA
New Distribution System, Extend System Consolidation
7,012
$4,417,000
35
$930,697,442
17960
Franklin
SARANAC LAKE V / Saranac
Lake (V)
Installation of water meters.,
5,800
$1,000,000
35
$931,697,442
17969
Steuben
BATH VILLAGE / Bath (V)
Installation of solar powered storage tank water circulators.,
5,641
$437,400
35
$932,134,842
16138
Oswego
PHOENIX VILLAGE / Phoenix
(V)
State Street water main replacement., Upgrade Distribution System
2,138
$90,125
35
$932,224,967
Page 22 of 28
NYS Drinking Water State Revolving Fund Final Category A List ( Small Systems Serving < 10,000 People )
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Project Cost Score
Cumulative
Total
Description
Pop.
1,160
$100,000
35
$932,324,967
16147
Orange
WESTSIDE GREENWOOD
LAKE W.D. / Warwick (T)
Upgrade Distribution System
16246
Dutchess
LITTLE SWITZERLAND /
East Fishkill (T)
Upgrade Distribution System, System Consolidation
450
$428,900
35
$932,753,867
15938
Dutchess
TACONIC ESTATES WATER
DISTRICT / East Fishkill (T)
New Ground Water Source, System Consolidation
185
$148,000
35
$932,901,867
16461
Dutchess
STONY CREEK FARMS
(TOWN HOMES / Stoney
Creek Farms Homeowners
New Water Treatment Plant
21
$18,000
30
$932,919,867
15635
Orange
WASHINGTONVILLE
VILLAGE / Washingtonville
(V)
Upgrade Ground Water Source, Upgrade Distribution System
7,000
$435,000
30
$933,354,867
18037
Ulster
MARLBOROUGH WATER
DISTRICT / (T) Marlborough
New Transmission, New Storage, Upgrade Distribution System
3,248
$16,879,640
30
$950,234,507
15365
Sullivan
WURTSBORO VILLAGE
WATER SUPPLY / Wurtsboro
(V)
New 400,000 gallon potable water stand pipe and distribution system
improvements, New Storage, Upgrade Distribution System
1,060
$1,545,000
30
$951,779,507
17882
Fulton
BROADALBAN (V) / Broadalin Replace Aged Storage Tank, New Storage
(V)
1,500
$1,990,000
30
$953,769,507
17787
Schoharie
SCHOHARIE VILLAGE /
Schoharie (V)
Upgrade Distribution System
1,030
$2,570,000
30
$956,339,507
17905
Warren
LAKE GEORGE VILLAGE /
Lake George (V)
Upgrade Distribution System
2,160
$1,650,675
30
$957,990,182
17956
Delaware
ROXBURY WATER
DISTRICT / Roxbury (T)
Installation of water meters.,
755
$358,178
30
$958,348,360
16720
Wayne
RED CREEK VILLAGE / Red
Creek (V)
Upgrade Distribution System
526
$102,935
30
$958,451,295
15966
Orange
CORNWALL-ON-HUDSON /
Cornwall-On-Hudson (V)
Upgrade Water Treatment Plant
9,300
$2,935,257
25
$961,386,552
17908
Suffolk
SALTARE WATER DISTRICT
/ Saltaire (V)
Infrastructure upgrade, Upgrade Water Treatment Plant, Upgrade
Storage
1,400
$668,000
25
$962,054,552
17524
Westchester
NORTH CASTLE WD #2 /
North Castle (T)
New well and storage, New Ground Water Source, New Storage
1,200
$1,458,695
25
$963,513,247
16250
Oneida
J.E. BARRETT WD / Prospect
(V)
Upgrade Ground Water Source, New Storage, Upgrade Distribution
System
$326,000
25
$963,839,247
16015
Westchester
BRIARCLIFF MANOR
VILLAGE / Briarcliff Manor (V)
Upgrade Distribution System
8,831
$2,845,400
25
$966,684,647
15401
Clinton
PERU WD / Peru (T)
Upgrade Surface Water Source, New Transmission
2,600
$620,000
25
$967,304,647
17741
Schenectady
ROTTERDAM WD #3 /
Rotterdam (T)
Construction of new storage tank and transmission main, New
Transmission, New Storage
2,000
$2,060,000
25
$969,364,647
Page 23 of 28
150
NYS Drinking Water State Revolving Fund Final Category A List ( Small Systems Serving < 10,000 People )
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Project Cost Score
Cumulative
Total
Description
Pop.
Upgrade Pump Station
1,300
$225,320
25
$969,589,967
17795
Clinton
MORRISONVILLE WATER
DISTRICT / Plattsburgh (T)
15228
Orange
PINE GROVE MOBILE HOME New Water Treatment Plant, Upgrade Transmission, New Storage,
PARK / Pine Grove MHP, LLC Upgrade Distribution System
516
$484,100
25
$970,074,067
15634
Cayuga
SENNETT WD #1 / Sennett
(T)
Upgrade Distribution System
200
$470,339
25
$970,544,406
17683
Clinton
PLEASANT RIDGE WD /
Plattsburgh (T)
New Storage
168
$3,190,000
25
$973,734,406
17341
Albany
SOUTH ALBANY WATER
DISTRICT / Bethlehem (T)
New Transmission
80
$146,775
25
$973,881,181
15896
Warren
CHESTERTOWN WATER
DISTRICT / Chester (T)
Well #1 - Rehab and Testing, Upgrade Ground Water Source
1,300
$15,500
25
$973,896,681
15893
Jefferson
ADAMS (T) WD #1 & 2
(ADAMS CENTER) / Adams
Center (T)
Upgrade Storage
1,000
$121,954
25
$974,018,635
15805
Warren
WARRENSBURG WATER
DISTRICT / Warrensburg (T)
Upgrade Ground Water Source
3,600
$375,000
25
$974,393,635
17965
Oswego
RICHLAND TOWN PWS /
Richland (T)
Wind power generation at Schoeller well site.,
2,350
$585,000
25
$974,978,635
16481
Jefferson
VILLAGE OF CLAYTON /
Clayton (V)
New Transmission, New Distribution System
2,160
$214,000
25
$975,192,635
17939
Herkimer
OLD FORGE (V) WATER
DISTRICT / Webb (T)
Upgrade Distribution System, Extend Distribution System
1,766
$561,350
25
$975,753,985
15268
Madison
EARLVILLE VILLAGE /
Earlville (V)
East Main Street., Upgrade Distribution System
790
$96,509
25
$975,850,494
17961
Jefferson
LAFARGEVILLE (T.
ORLEANS) / Orleans (T)
Installation of water meters.,
750
$208,078
25
$976,058,572
15951
Orange
VALLEY VIEW CTR FOR
NURSING CARE & REHAB /
Orange County
New Water Treatment Plant, New Ground Water Source, New
Storage, Upgrade Distribution System
851
$572,474
20
$976,631,046
15538
Tompkins
LANSING WD #2 / Lansing
(T)
New Storage, New Pump Station, Upgrade Distribution System
400
$443,500
20
$977,074,546
16053
Niagara
CAMBRIA WATER DISTRICT
/ Cambria (T)
New Storage, New Pump Station, Upgrade Distribution System
5,393
$1,000,000
20
$978,074,546
16041
Ontario
GORHAM TOWN WD /
Gorham (T)
New Pump Station, Upgrade Distribution System
4,500
$141,280
20
$978,215,826
17772
Saratoga
BURNT HILLS-BALLSTON
LK WD (GLENVILLE) /
Ballston (T)
New Pump Station, Extend Distribution System
4,500
$606,052
20
$978,821,878
17400
Orange
HIGHLAND FALLS VILLAGE / Water Treatment Plant Filter Upgrades, Upgrade Water Treatment
Plant
Highland Falls (V)
4,400
$800,000
20
$979,621,878
Page 24 of 28
NYS Drinking Water State Revolving Fund Final Category A List ( Small Systems Serving < 10,000 People )
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
2,666
18041
Putnam
COLD SPRING VILLAGE /
Cold Spring (V)
Upgrade Transmission
17920
Oneida
WESTMORELAND WD NO 1
(GU) / Westmoreland (T)
New Ground Water Source, Upgrade Storage
17565
Orange
BRITTANY TERRACE /
Brittany Terrace, Inc.
New water storage tank, New Storage
17583
Nassau
OYSTER BAY WD / Oyster
Bay (T)
VOC removal at Plant #2., New Water Treatment Plant
15755
Albany
RAVENA VILLAGE / Ravena
(V)
15832
Wayne
15914
Project Cost Score
Cumulative
Total
$958,000
20
$980,579,878
600
$2,850,000
20
$983,429,878
169
$215,000
20
$983,644,878
8,700
$1,597,530
20
$985,242,408
New Storage
4,500
$497,500
20
$985,739,908
PALMYRA VILLAGE /
Palmyra (V)
Upgrade Surface Water Source
3,550
$291,050
20
$986,030,958
Wayne
PALMYRA VILLAGE /
Palmyra (V)
Upgrade Transmission
3,550
$1,581,250
20
$987,612,208
15918
Wayne
PALMYRA VILLAGE /
Palmyra (V)
Upgrade Storage
3,550
$189,750
20
$987,801,958
15045
Oneida
CLINTON VILLAGE / Clinton
(V)
Upgrade Distribution System
3,000
$822,000
20
$988,623,958
15691
Greene
SLEEPY HOLLOW LAKE
WATER CO. / Sleepy Hollow
Lake Assoc.
Upgrade Surface Water Source, Upgrade Storage
2,000
$1,144,330
20
$989,768,288
17383
Genesee
OAKFIELD VILLAGE /
Oakfield (T)
Upgrade Transmission
1,805
$1,661,600
20
$991,429,888
16885
Ontario
WEST BLOOMFIELD WD /
West Bloomfield (T)
Cathodic protection system., Upgrade Storage
1,500
$13,390
20
$991,443,278
17802
Jefferson
MADISON BARRACKS
WATER SYSTEM / Sackets
Harbor (V)
Upgrade Distribution System
1,000
$1,700,000
20
$993,143,278
16758
Erie
W. SENECA WD#3 / West
Seneca (T)
Orchard Park Road Watermain, Upgrade Distribution System
520
$460,000
20
$993,603,278
17419
Dutchess
WAPPINGERS FALLS
VILLAGE / Wappinger Falls
(V)
Upgrade Storage, New Storage, Upgrade Distribution System
6,000
$6,238,532
20
$999,841,810
17325
Onondaga
MINOA VILLAGE / Minoa (V)
Upgrade Distribution System
3,745
$307,336
20
$1,000,149,146
15897
Warren
CHESTERTOWN WATER
DISTRICT / Chester (T)
Upgrade Distribution System
1,300
$42,200
20
$1,000,191,346
17970
Sullivan
WURTSBORO VILLAGE
WATER SUPPLY / Wurtsboro
(V)
Installation of water meters.,
1,060
$201,438
20
$1,000,392,784
17966
Rensselaer
SCHAGHTICOKE (V) PWS /
Schaghticoke (V)
Installation of water meters.,
675
$75,000
20
$1,000,467,784
Page 25 of 28
NYS Drinking Water State Revolving Fund Final Category A List ( Small Systems Serving < 10,000 People )
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost Score
Cumulative
Total
17968
Schoharie
SHARON SPRINGS VILLAGE Installation of water meters.,
/ Sharon Springs (V)
547
$203,148
20
$1,000,670,932
15312
Westchester
CROTON FALLS WATER
DISTRICT / North Salem (T)
Upgrade Distribution System
175
$121,339
20
$1,000,792,271
16494
Clinton
CHAMPLAIN (T) / Champlain
(T)
System Acquisition-"Benefit Area #1", New Ground Water Source,
New Distribution System
50
$497,200
20
$1,001,289,471
15469
Erie
WILLIAMSVILLE (V) /
Williamsville (V)
Los Robles Street water reconstruction project., Upgrade Distribution
System
6,017
$408,447
15
$1,001,697,918
15556
Tompkins
LANSING WD #2 / Lansing
(T)
Extend Distribution System
400
$117,300
15
$1,001,815,218
15274
Montgomery
GLEN (T) W.D.#2 / Glen (T)
Upgrade Distribution System
7,626
$95,000
15
$1,001,910,218
17344
Nassau
WILLISTON PARK (V) /
Williston Park (V)
Secondary Containment for Caustic Soda, Upgrade Other Expenses,
Upgrade Other (OT)
7,516
$161,350
15
$1,002,071,568
17829
Westchester
PLEASANTVILLE /
Pleasantville (V)
Replacement of water mains., Upgrade Distribution System
7,166
$1,955,000
15
$1,004,026,568
16038
Ontario
GORHAM TOWN WD /
Gorham (T)
Upgrade Storage
4,500
$77,500
15
$1,004,104,068
17835
Orange
MONTGOMERY (V) /
Montgomery (V)
New Storage Tank, New Storage
3,696
$825,030
15
$1,004,929,098
17916
Orange
GREENWOOD LAKE (V) /
Greenwood Lake (V)
Cleaning and painting storage tank, Upgrade Storage
3,400
$245,660
15
$1,005,174,758
17525
Westchester
NORTH CASTLE WD #1 /
North Castle (T)
Rehabilitation of water storage tanks, Upgrade Storage
2,500
$813,500
15
$1,005,988,258
18040
Ontario
BLOOMFIELD VILLAGE /
Bloomfield (V)
Upgrade Distribution System
1,675
$1,340,697
15
$1,007,328,955
15792
Putnam
CONTINENTAL VILLAGE WD Upgrade Distribution System
/ Philipstown (T)
1,509
$1,350,000
15
$1,008,678,955
15559
Ontario
HOPEWELL WD #2 /
Hopewell (T)
New Pump Station
1,148
$435,600
15
$1,009,114,555
17843
Orange
TUXEDO PARK (V) / Tuxedo
(V)
West Lake Road Transmission Line, Upgrade Transmission
1,100
$487,000
15
$1,009,601,555
17061
Westchester
LAKE KATONAH CLUB INC /
Lake Katonah Club Inc
Upgrade Storage
356
$131,910
15
$1,009,733,465
17539
Rensselaer
CASTLETON VILLAGE PWS
/ Castleton-on-Hudson (V)
Replacement in-kind of aged water mains., Upgrade Distribution
System
2,013
$1,661,400
15
$1,011,394,865
17527
Genesee
OAKFIELD VILLAGE /
Oakfield (V)
Upgrade Transmission, Upgrade Distribution System
1,805
$1,147,575
15
$1,012,542,440
Page 26 of 28
NYS Drinking Water State Revolving Fund Final Category A List ( Small Systems Serving < 10,000 People )
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
17959
Dutchess
SHOREHAVEN CIVIC
ASSOC / DCWWA
Installation of water meters.,
18003
Erie
CATTARAUGUS STREET
WATER DISTRICT / Concord
(T)
New Distribution System, New Water District
17844
Steuben
CAMPBELL WATER
DISTRICT / Campbell (T)
18020
Lewis
15642
Pop.
Project Cost Score
Cumulative
Total
300
$61,692
15
$1,012,604,132
13
$325,000
15
$1,012,929,132
Extend Distribution System
280
$216,744
15
$1,013,145,876
WATER DISTRICT #1 /
Denmark (T)
Serve private contaminated/poor yielding wells., Extend Distribution
System
275
$2,603,000
15
$1,015,748,876
Nassau
WILLISTON PARK (V) /
Williston Park (V)
Upgrade Ground Water Source
7,516
$800,000
10
$1,016,548,876
15507
Westchester
PLEASANTVILLE WATER
DISTRICT / Pleasantville (V)
Refinance '93 bonds for relining water mains, Upgrade Distribution
System
9,500
$4,155,408
10
$1,020,704,284
15514
Westchester
PLEASANTVILLE WATER
DISTRICT / Pleasantville (V)
Water Mains for Sarles Lane, Upgrade Distribution System
9,500
$343,291
10
$1,021,047,575
17817
Orange
WASHINGTONVILLE
VILLAGE / Washingtonville
(V)
Watermain replacement Patricia and Beverly Lane, Upgrade
Distribution System
7,000
$961,000
10
$1,022,008,575
17818
Orange
WASHINGTONVILLE
VILLAGE / Washingtonville
(V)
Replace watermains in Dutch Arms area., Upgrade Distribution
System
7,000
$1,654,700
10
$1,023,663,275
17775
Westchester
WESTCHESTER COUNTY
WD #3 / Westchester County
#3
Lateral Main Rehabilitation, Upgrade Distribution System
6,000
$670,000
10
$1,024,333,275
15131
Livingston
LIVONIA VILLAGE / Livonia
(V)
Upgrade Distribution System
1,360
$1,105,325
10
$1,025,438,600
17907
Nassau
VILLAGE OF PLANDOME /
Plandome (V)
Replace aged mains in distribution system, Upgrade Distribution
System
1,350
$5,113,950
10
$1,030,552,550
17985
Westchester
BEAR RIDGE LAKE WATER
DISTRICT / Mount Pleasant
(T)
Water main replacement-Highland Place, Mountain Trail and
Woodland Road, Upgrade Distribution System
170
$1,436,085
10
$1,031,988,635
16540
Dutchess
Upgrade Distribution System
CHARLOTTE GROVE
MOBILE HOME CT / Charlette
Grove MH Court
112
$302,820
10
$1,032,291,455
17993
Suffolk
WEST NECK WATER
SUPPLY / Shelter Island (T)
Water main replacement, Upgrade Distribution System
100
$669,093
10
$1,032,960,548
18050
Yates
BENTON WD #1 /
Extend Distribution System
308
$731,000
10
$1,033,691,548
15963
Orange
CORNWALL-ON-HUDSON /
Cornwall-On-Hudson (V)
Upgrade Distribution System
9,300
$520,000
5
$1,034,211,548
17854
Putnam
SOUTHEAST (T)
PEACEABLE WATER
DISTRICT / Southeast (T)
Development new water source instead of continuing to purchase
from Brewster (V), New Ground Water Source
440
$1,700,000
5
$1,035,911,548
17781
Rensselaer
WATER DISTRICT 15 / North
Greenbush (T)
Extend Distribution System
4,000
$9,785,000
5
$1,045,696,548
Page 27 of 28
NYS Drinking Water State Revolving Fund Final Category A List ( Small Systems Serving < 10,000 People )
October 1, 2011 to September 30, 2012
Project County
18068
Orleans
System Name/
Borrower
WATER IMPROVEMENT
BENEFIT AREA #10 /
Clarendon (T)
Total # Projects
Description
Extend Distribution System
Pop.
250
Project Cost Score
$1,634,949
Total Cost
514
$1,047,331,497
Page 28 of 28
5
Cumulative
Total
$1,047,331,497
MULTI-YEAR LIST OF PROJECTS
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Albany County
17427
Albany
NEW SALEM WATER
DISTRICT / New Scotland
(T)
New Surface Water Treatment Rule Compliance Facility, New Storage,
New Pump Station, New Inter-Connection, New Water District
486
$3,048,000
210
$3,048,000
15661
Albany
RENSSELAERVILLE WD /
Rensselaerville (T)
New Ground Water Source, Upgrade Storage, Upgrade Distribution
System
200
$990,242
185
$4,038,242
17443
Albany
ALTAMONT VILLAGE /
Altamont (V)
New Brandle Road Wells, Disinfection, and Transmission Main, New
Ground Water Source
2,000
$1,394,550
90
$5,432,792
17428
Albany
FLAT ROCK ROAD W.D. /
New Scotland (T)
New Water District
149
$2,152,580
90
$7,585,372
15950
Albany
GUILDERLAND TOWN WD
/ Guilderland (T)
Phase III Improvements, New Storage, Extend Distribution System,
Upgrade Distribution System, New Inter-Connection
30,000
$10,146,000
75
$17,731,372
16245
Albany
COHOES CITY / Cohoes
(C)
Upgrade Water Treatment Plant
15,550
$1,975,000
70
$19,706,372
16670
Albany
ALTAMONT RD. WATER
DISTRICT / New Scotland
(T)
Extension of Village of Voorheesville system into the Town of New
Scotland, New Distribution System
93
$314,000
70
$20,020,372
17548
Albany
MENANDS VILLAGE /
Menands (V)
Upgrade Pump Station, Upgrade Distribution System
3,900
$6,936,000
60
$26,956,372
17771
Albany
MARTINS HILL ROAD
WATER DISTRICT /
Coeymans (T)
Extend distribution from Village of Ravena to serve Martins Hill Road
Water District., Extend Distribution System, New Water District
66
$314,150
55
$27,270,522
16449
Albany
GREEN ISLAND VILLAGE /
Green Island (V)
Extend Distribution System
2,900
$381,100
50
$27,651,622
17299
Albany
RAVENA VILLAGE /
Ravena (V)
Upgrade Water Treatment Plant, Upgrade Transmission, Upgrade
Storage
4,500
$3,090,000
50
$30,741,622
15705
Albany
ALBANY CITY / Albany (C)
Pearl Street Reconstruction, Phase 1, Upgrade Distribution System
101,082
$2,000,000
50
$32,741,622
15698
Albany
ALBANY CITY / Albany (C)
1997 Capital Improvement Program, Upgrade Distribution System
101,082
$1,350,000
45
$34,091,622
15417
Albany
KRUMKILL RD. WATER
DISTRICT / New Scotland
(T)
Extend Distribution System
45
$2,500,000
45
$36,591,622
15747
Albany
ALBANY CITY / Albany (C)
New Transmission
101,082
$10,000,000
45
$46,591,622
16244
Albany
COHOES CITY / Cohoes
(C)
Upgrade Distribution System
15,550
$1,025,000
40
$47,616,622
15395
Albany
WATERVLIET CITY /
Watervliet (C)
New Storage
9,889
$1,548,000
40
$49,164,622
15129
Albany
NORTHEAST WATER
DISTRICT / New Scotland
(T)
New Complete System (New System)
370
$843,905
40
$50,008,527
15720
Albany
ALBANY CITY / Albany (C)
Upgrade Water Treatment Plant
101,082
$960,000
40
$50,968,527
15300
Albany
NORTHEAST WATER
DISTRICT / New Scotland
(T)
Extend Distribution System
45
$267,000
40
$51,235,527
Page 1 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Albany County
15446
Albany
NORMANSKILL RD,
WORMER RD WATER
SYS. / New Scotland (T)
Extend Distribution System
15743
Albany
ALBANY CITY / Albany (C)
Upgrade Distribution System
15397
Albany
WATERVLIET CITY /
Watervliet (C)
15393
Albany
17740
30
$376,000
40
$51,611,527
101,082
$6,000,000
35
$57,611,527
Upgrade Transmission
9,889
$208,500
35
$57,820,027
WATERVLIET CITY /
Watervliet (C)
Replace undersized water mains provided insufficient flow &
pressure-1997, Upgrade Distribution System
9,889
$317,700
30
$58,137,727
Albany
COHOES CITY / Cohoes
(C)
Replace water main on Vliet St. from Main St. to Garner St, Upgrade
Distribution System
15,550
$747,532
30
$58,885,259
15392
Albany
WATERVLIET CITY /
Watervliet (C)
Replace undersized lines - 1998, Upgrade Distribution System
9,889
$795,000
30
$59,680,259
17738
Albany
COHOES CITY / Cohoes
(C)
Reline water mains, Upgrade Transmission
15,550
$1,595,000
30
$61,275,259
17341
Albany
SOUTH ALBANY WATER
DISTRICT / Bethlehem (T)
New Transmission
80
$146,775
25
$61,422,034
15755
Albany
RAVENA VILLAGE /
Ravena (V)
New Storage
4,500
$497,500
20
$61,919,534
15247
Albany
LATHAM WATER
DISTRICT / Colonie (T)
New Storage
78,500
$1,290,000
15
$63,209,534
HOUGHTON WATER
DISTRICT / Caneadea (T)
Upgrade Water Treatment Plant, New Ground Water Source, New
Transmission, Upgrade Distribution System
1175
$63,209,534
Allegany County
17382
Allegany
2,000
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
16746
Allegany
CANASERAGA VILLAGE
PUBLIC WATER /
Canaseraga (V)
New Ground Water Source, Upgrade Storage
900
$3,666,749
220
$66,876,283
18017
Allegany
RICHBURG VILLAGE
PUBLIC WATER / Richburg
(V)
(V) Richburg & (V) Bolivar Consolidation., New Surface Water
Treatment Rule Compliance Facility, New Ground Water Source,
Upgrade Storage, Upgrade Distribution System, New System
Consolidation
600
$7,038,640
180
$73,914,923
17621
Allegany
ANGELICA VILLAGE
PUBLIC WATER / Angelica
(V)
Surface Water Treatment Rule Compliance Facility
950
$1,061,847
165
$74,976,770
15925
Allegany
TOWN OF WELLSVILLE /
Wellsville (T)
Extend system to serve area with private contaminated wells,
Morningside Area, Extend Distribution System
5,000
$867,106
75
$75,843,876
17526
Allegany
WELLSVILLE WATER
DISTRICT / Wellsville (T)
Extend Distribution System, New Water District
133
$1,192,450
70
$77,036,326
15502
Allegany
WELLSVILLE VILLAGE
PUBLIC WATER / Wellsville
(V)
New Storage
5,700
$1,177,000
50
$78,213,326
16636
Allegany
BOLIVAR VILLAGE PUBLIC
WATER / Bolivar (V)
New Storage, Upgrade Distribution System
1,040
$788,500
45
$79,001,826
15547
Allegany
FRIENDSHIP TOWN
WATER DISTRICT /
Friendship (T)
Upgrade Ground Water Source, Upgrade Storage, Upgrade
Distribution System
1,380
$1,030,000
45
$80,031,826
15943
Allegany
ANDOVER VILLAGE
PUBLIC WATER / Andover
(V)
Upgrade Surface Water Source
1,130
$3,299,000
40
$83,330,826
Page 2 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Allegany County
16655
Allegany
GENESEE HEIGHTS
MOBILE HOME PK / Mr. &
Mrs. Anzivine
New Ground Water Source, Upgrade Distribution System
16747
Allegany
CANASERAGA VILLAGE
PUBLIC WATER /
Canaseraga (V)
Upgrade Distribution System
16156
Allegany
BELMONT VILLAGE
PUBLIC WATER / Belmont
(V)
16154
Allegany
15983
17762
65
$69,000
40
$83,399,826
900
$2,039,915
35
$85,439,741
Greenwich St. to Allegany County Office Complex., Upgrade
Distribution System
1,325
$405,827
30
$85,845,568
BELMONT VILLAGE
PUBLIC WATER / Belmont
(V)
Trianna St. & Milton St., Upgrade Distribution System
1,325
$494,452
30
$86,340,020
Allegany
ALMOND VILLAGE PUBLIC
WATER / Almond (V)
Upgrade Distribution System
600
$257,500
25
$86,597,520
Allegany
DISTRIBUTION MAIN
REPLACEMENT / Allegany
(T)
Upgrade Distribution System
500
$121,000
20
$86,718,520
1,000
$863,140
90
$87,581,660
101
$343,200
65
$87,924,860
2,080
$2,006,336
65
$89,931,196
Broome County
16262
Broome
CONKLIN (T) W.D. / Conklin
(T)
Extend system to serve area with private contaminated wells,
consolidate public water supply. , Inter-Connection, System
Consolidation
16175
Broome
CONKLIN WD #1 / Conklin
(T)
Upgrade Ground Water Source
17766
Broome
Upper NW Quadrant water main reconstruction, new river crossing,
DEPOSIT (V) WATER
DEPARTMENT / Deposit (V) new telemetry system., Upgrade Transmission, Upgrade Distribution
System
16804
Broome
STILLWATER RD WD#6 /
Conklin (T)
Extend Distribution System
173
$412,782
55
$90,343,978
16025
Broome
PARK TERRACE WATER
SYSTEM / Binghamton (T)
Extend system to serve area with private contaminated wells. , Extend
Distribution System
455
$1,101,456
55
$91,445,434
17547
Broome
WHITNEY POINT VILLAGE
/ Whitney Point (V)
New Wells, Main Street Wellfield/Pumphouse Improvements.,
Upgrade Ground Water Source, New Ground Water Source
1,054
$569,400
55
$92,014,834
16541
Broome
UNION TOWN WATER
SYSTEM NO. 1 / Union (T)
Extend Distribution System
5,000
$6,400,225
45
$98,415,059
17453
Broome
LILIAN DRIVE WD /
Binghamton (T)
New Pump Station, Upgrade Distribution System, New
Inter-Connection, New System Consolidation, New Water District
120
$281,000
45
$98,696,059
16802
Broome
CHENANGO WD #4 /
Chenango (T)
New Water District
100
$112,450
45
$98,808,509
16801
Broome
CHENANGO WD #8 /
Chenango (T)
New Water District
100
$121,000
45
$98,929,509
16799
Broome
CHENANGO WD #25 /
Chenango (T)
New WD to serve private insufficient yielding wells area of Poplar Hill
Road , New Complete System (New System)
100
$383,500
40
$99,313,009
17852
Broome
ENDICOTT MUNICIPAL
WATER WORKS / Endicott
(V)
Replace Bean Hill Road Tank., New Storage
45,000
$250,000
40
$99,563,009
15969
Broome
VESTAL CONSOLIDATED
W.D. #1 / Vestal (T)
New Water Treatment Plant
20,950
$1,700,000
40
$101,263,009
15215
Broome
DICKINSON WD #2 /
Dickinson (T)
Upgrade Pump Station, Upgrade Distribution System
56
$220,100
35
$101,483,109
Page 3 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Broome County
15489
Broome
BINGHAMTON, CITY OF /
Binghamton (C)
South Side Water Storage Reservoir replacement,Hotchkins St.,
Upgrade Storage
15764
Broome
WINDSOR, VILLAGE OF /
Windsor (V)
Upgrade Pump Station, Upgrade Distribution System
15977
Broome
VESTAL CONSOLIDATED
W.D. #1 / Vestal (T)
New Storage
15905
Broome
CHENANGO
CONSOLIDATED WD #1 /
Chenango (T)
Upgrade Ground Water Source
15975
Broome
VESTAL CONSOLIDATED
W.D. #1 / Vestal (T)
15973
Broome
15971
Broome
47,600
$1,236,000
35
$102,719,109
1,051
$1,660,000
30
$104,379,109
20,950
$1,668,600
10
$106,047,709
9,200
$574,500
10
$106,622,209
Upgrade Pump Station
20,950
$187,718
10
$106,809,927
VESTAL CONSOLIDATED
W.D. #1 / Vestal (T)
Upgrade Pump Station, Upgrade Distribution System
20,950
$319,815
10
$107,129,742
VESTAL CONSOLIDATED
W.D. #1 / Vestal (T)
Upgrade Water Treatment Plant
20,950
$415,296
5
$107,545,038
Cattaraugus County
18022
Cattaraugus
PERRYSBURG (V) /
Perrysburg (T)
Phase 2 (DWSRF 17192) based on cost increase to address
unresolved deficiencies in the initial project construction, New Water
Treatment Plant, Upgrade Ground Water Source, Upgrade Storage,
New Pump Station
404
$729,657
2095
$108,274,695
18013
Cattaraugus
RANDOLPH VILLAGE /
Randolph (T)
East Randolph and Randolph (V)'s project includes meters, Upgrade
Other Expenses, New Surface Water Treatment Rule Compliance
Facility, New Ground Water Source, New System Consolidation,
Upgrade Other (OT)
1,250
$3,740,000
200
$112,014,695
17589
Cattaraugus
CRYSTAL WATER CO
(WEST VALLEY) / Ashford
(T)
New Surface Water Treatment Rule Compliance Facility, Upgrade
Ground Water Source
880
$3,208,500
180
$115,223,195
17514
Cattaraugus
DELEVAN VILLAGE /
Delevan (V)
New Surface Water Treatment Rule Compliance Facility, Upgrade
Ground Water Source, Upgrade Storage, Upgrade Distribution System
1,090
$1,690,350
145
$116,913,545
18071
Cattaraugus
RANDOLPH VILLAGE /
Randolph (T)
East Randolph and Randolph (V)'s Repalcement of Water Mains,
Upgrade Distribution System
1,250
$7,075,000
55
$123,988,545
17770
Cattaraugus
OLEAN CITY / Olean (C)
Upgrade Pump Station, Upgrade Distribution System
15,500
$3,977,087
40
$127,965,632
15763
Cattaraugus
PORTVILLE VILLAGE /
Portville (V)
Upgrade Distribution System
1,040
$437,673
35
$128,403,305
18025
Cattaraugus
SALAMANCA CITY /
Salalmanca (C)
Upgrade Distribution System
7,000
$1,688,000
30
$130,091,305
600
$6,875,100
185
$136,966,405
1,400
$5,657,000
160
$142,623,405
426
$862,457
110
$143,485,862
1,000
$934,500
80
$144,420,362
Cayuga County
16114
Cayuga
CAYUGA VILLAGE /
Cayuga (V)
New Surface Water Treatment Rule Compliance Facility, Upgrade
Distribution System, New Inter-Connection
17931
Cayuga
PORT BYRON VILLAGE /
Port Byron (V)
Joint project with (V) Port Byron, (T) Montezuma & (T) Mentz.,
Upgrade Distribution System, Extend Distribution System, New System
Consolidation
15780
Cayuga
AURORA VILLAGE / Aurora
(V)
New Water Treatment Plant, New Surface Water Source
15127
Cayuga
FAIR HAVEN VILLAGE /
Fair Haven (V)
Upgrade Ground Water Source, New Storage, Upgrade Distribution
System
Page 4 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Cayuga County
17681
Cayuga
NORTH WEEDSPORT
WD#7 / Brutus (T)
Water District #7 (North Weedsport Water District), New Distribution
System
100
$561,000
80
$144,981,362
15970
Cayuga
LOCKE W D / Locke (T)
Upgrade Ground Water Source, Upgrade Distribution System
600
$500,650
80
$145,482,012
15751
Cayuga
GENOA-KING FERRY WD /
Genoa (T)
Upgrade Water Treatment Plant, Upgrade Storage, Upgrade
Distribution System
900
$1,040,000
75
$146,522,012
17972
Cayuga
(T) BRUTUS WATER
DISTRICT #8 / Brutus (T)
New (T) Brutus WD #8 (Cottle Road), Upgrade Distribution System,
New Water District
400
$1,920,334
70
$148,442,346
17803
Cayuga
AUBURN / Auburn (C)
Upgrade Water Treatment Plant, Upgrade Distribution System
29,788
$3,975,262
70
$152,417,608
16762
Cayuga
UNION SPRINGS VILLAGE
/ Union Springs (V)
New Water Treatment Plant
2,000
$165,000
65
$152,582,608
16163
Cayuga
THROOP WD NO1 / Throop
(T)
Extend Distribution System, Upgrade Distribution System
400
$1,960,142
60
$154,542,750
17315
Cayuga
MORAVIA (T) WATER
DISTRICT NO. 1 / Moravia
(T)
New Pump Station, Extend Distribution System
162
$663,320
55
$155,206,070
17220
Cayuga
VICTORY (T) WD #2 /
Victory (T)
Extend Distribution System
612
$3,389,601
55
$158,595,671
17989
Cayuga
FLEMING WD #1 / Fleming
(T)
West Lake Road Water Main Extension. , Extend Distribution System
1,800
$790,499
50
$159,386,170
15904
Cayuga
AURELIUS WD NO 1 /
Aurelius (T)
Extend Distribution System
440
$2,142,690
50
$161,528,860
15026
Cayuga
AUBURN / Auburn (C)
Upgrade Transmission, Upgrade Pump Station
29,788
$321,875
50
$161,850,735
17223
Cayuga
WEST GENESEE STREET
WATER DISTRICT /
Aurelius (T)
Extend Distribution System
175
$1,198,000
50
$163,048,735
15043
Cayuga
AUBURN / Auburn (C)
Reservoir relining and leak repair., Upgrade Storage
29,788
$902,795
45
$163,951,530
17811
Cayuga
CAYUGA COUNTY WATER
& SEWER / Cayuga County
W&SA
New Centerport / Sine Roads WD in (T) Throop., Extend Distribution
System, New Water District
200
$818,850
45
$164,770,380
16759
Cayuga
CAYUGA COUNTY W.S.A. /
Cayuga Co. W. S. A.
waterline installation, storage tank, pump station and WTP for Cayuga
County Water & Sewer Authority, New Water Treatment Plant, New
Storage, New Distribution System
5,900
$25,632,730
45
$190,403,110
15050
Cayuga
AUBURN / Auburn (C)
Upgrade Surface Water Source
29,788
$647,510
45
$191,050,620
17804
Cayuga
WELLS COLLEGE / Wells
College
Upgrade Water Treatment Plant, Upgrade Distribution System
400
$1,642,850
40
$192,693,470
15546
Cayuga
AUBURN / Auburn (C)
Upgrade Distribution System
29,788
$1,098,495
40
$193,791,965
17887
Cayuga
CATO VILLAGE / Cato (V)
New Storage
601
$1,152,505
35
$194,944,470
Page 5 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Cayuga County
17329
Cayuga
OWASCO WATER
DISTRICT / Owasco (T)
Upgrade Water Treatment Plant, New Storage, Upgrade Distribution
System
3,000
$6,180,000
30
$201,124,470
15949
Cayuga
MORAVIA VILLAGE /
Moravia (V)
Upgrade Distribution System
1,950
$789,600
30
$201,914,070
15634
Cayuga
SENNETT WD #1 / Sennett
(T)
Upgrade Distribution System
200
$470,339
25
$202,384,409
17990
Cayuga
FLEMING WD #1 / Fleming
(T)
Upgrade Distribution System
1,800
$3,386,228
20
$205,770,637
15631
Cayuga
SENNETT WD #3 / Sennett
(T)
Upgrade Distribution System
400
$307,760
20
$206,078,397
FORESTVILLE VILLAGE /
Forestville (V)
New Surface Water Treatment Rule Compliance Facility, New Ground
Water Source, Upgrade Distribution System
804
1230
$206,078,397
Chautauqua County
17561
Chautauqua
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
17576
Chautauqua
CHERRY CREEK VILLAGE
/ Cherry Creek (V)
New Surface Water Treatment Rule Compliance Facility, Upgrade
Distribution System
650
$0
1205
$206,078,397
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
17637
Chautauqua
NORTH END WD / Pomfret
(T)
Extend distribution system to area with contaminated private wells and
consolidate PWS with Coliform, New Distribution System
17622
Chautauqua
BROCTON VILLAGE /
Brocton (V)
Address turbidity violations, Surface Water Treatment Rule
Compliance Facility, Upgrade Water Treatment Plant
17481
Chautauqua
CHERRY CREEK VILLAGE
/ Cherry Creek (V)
17432
Chautauqua
18004
900
$4,432,100
200
$210,510,497
4,000
$2,219,341
145
$212,729,838
New well to replace GUDI springs., New Ground Water Source
650
$392,275
125
$213,122,113
CASSADAGA VILLAGE /
Cassadaga (V)
New Ground Water Source, New Storage, Upgrade Distribution System
760
$5,047,000
125
$218,169,113
Chautauqua
WESTFIELD VILLAGE /
Westfield (V)
Address inadequate source capacity and insuffcient pressure, Upgrade
Storage, Upgrade Distribution System
3,450
$3,977,200
120
$222,146,313
17614
Chautauqua
DUNKIRK CITY / Dunkirk
(C)
Upgrade Water Treatment Plant, Upgrade Distribution System
15,310
$17,705,600
105
$239,851,913
17554
Chautauqua
PORTLAND (T) WATER
DISTRICT NO. 7 / Portland
(T)
Serve 218 parcels currently on insufficient private wells on portions of
Route 5 and Walker Road. Consolidate DJ's Campground., New
System Consolidation, New Water District
333
$1,700,000
100
$241,551,913
17279
Chautauqua
SHOREHAVEN WATER
DISTRICT / Westfield (T)
Extend Distribution System, System Consolidation
120
$206,000
100
$241,757,913
16613
Chautauqua
MAYVILLE VILLAGE /
Mayville (V)
Upgrade Ground Water Source, Upgrade Transmission, Upgrade
Storage, Upgrade Distribution System
1,856
$2,884,000
90
$244,641,913
18043
Chautauqua
BARCELONNA WD /
Westfield (T)
New Town WD to aquire private water system. Other funding sources
may be required to make project viable and eligible for DWSRF,
Upgrade Distribution System, New Water District
128
$1,792,125
85
$246,434,038
17377
Chautauqua
SILVER CREEK (V) / Silver
Creek (V)
New Storage, Upgrade Distribution System
1,000
$4,311,000
80
$250,745,038
15236
Chautauqua
SHERMAN VILLAGE /
Sherman (V)
Address total Coli violations., Upgrade Distribution System
917
$795,000
80
$251,540,038
15617
Chautauqua
HANOVER WATER
DISTRICT #1 / Hanover (T)
Extension #4., Extend Distribution System
2,173
$666,300
70
$252,206,338
Page 6 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Chautauqua County
16012
Chautauqua
WESTFIELD VILLAGE /
Westfield (V)
East Main St., Upgrade Distribution System
3,450
$950,000
70
$253,156,338
17482
Chautauqua
WESTFIELD VILLAGE /
Westfield (T)
Extend Distribution System
3,450
$506,700
65
$253,663,038
17218
Chautauqua
FREDONIA VILLAGE /
Fredonia (V)
Upgrade Water Treatment Plant
10,400
$1,287,500
65
$254,950,538
15021
Chautauqua
DUNKIRK CITY / Dunkirk
(C)
Extension to (T) of Sheridan and (V) of Silver Creek., New
Transmission, System Consolidation
15,310
$3,530,000
60
$258,480,538
15124
Chautauqua
DUNKIRK CITY / Dunkirk
(C)
Extension to (T) of Portland and (V) of Brocton., New Transmission,
New Pump Station, System Consolidation
15,310
$2,915,000
60
$261,395,538
16014
Chautauqua
WESTFIELD VILLAGE /
Westfield (T)
New Distribution System
3,450
$520,300
60
$261,915,838
16406
Chautauqua
FORESTVILLE VILLAGE /
Forestville (V)
Upgrade Distribution System
804
$200,000
60
$262,115,838
16559
Chautauqua
HANOVER WATER
DISTRICT #1 / Hanover (T)
Extend Distribution System
2,173
$1,287,500
50
$263,403,338
16188
Chautauqua
WESTFIELD VILLAGE /
Westfield (V)
Upgrade Water Treatment Plant
3,450
$2,150,000
50
$265,553,338
16908
Chautauqua
BUSTI (T) WATER
DISTRICT #3 / Busti (T)
Extend Distribution System
450
$750,000
50
$266,303,338
15724
Chautauqua
LAKEWOOD VILLAGE /
Lakewood (V)
New Transmission, New Pump Station, Inter-Connection
3,258
$870,000
45
$267,173,338
15022
Chautauqua
DUNKIRK CITY / Dunkirk
(C)
Upgrade Water Treatment Plant, Upgrade Distribution System
15,310
$2,726,000
40
$269,899,338
16296
Chautauqua
SINCLAIRVILLE VILLAGE /
Sinclairville (V)
Upgrade Ground Water Source, Upgrade Pump Station
772
$50,000
40
$269,949,338
16183
Chautauqua
WESTFIELD VILLAGE /
Westfield (V)
E. Main Street and Cass Street., Upgrade Distribution System
3,450
$257,206
35
$270,206,544
16022
Chautauqua
FREDONIA VILLAGE /
Fredonia (V)
New Transmission, Upgrade Distribution System, System
Consolidation
10,400
$716,800
35
$270,923,344
16184
Chautauqua
WESTFIELD VILLAGE /
Westfield (V)
Oak St., Upgrade Distribution System
3,450
$90,305
35
$271,013,649
16181
Chautauqua
WESTFIELD VILLAGE /
Westfield (V)
Clean & reconstruct waterlines., Upgrade Distribution System
3,450
$600,000
30
$271,613,649
17483
Chautauqua
RIPLEY WATER DISTRICT
/ Ripley (T)
Upgrade Distribution System
1,300
$609,760
30
$272,223,409
16665
Chautauqua
WESTFIELD VILLAGE /
Westfield (V)
Upgrade Distribution System
3,450
$54,167
30
$272,277,576
16294
Chautauqua
SINCLAIRVILLE VILLAGE /
Sinclairville (V)
Upgrade Distribution System
772
$45,000
30
$272,322,576
Page 7 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Chautauqua County
16609
Chautauqua
HANOVER WATER
DISTRICT #1 / Hanover (T)
Upgrade Distribution System
16024
Chautauqua
FREDONIA VILLAGE /
Fredonia (V)
New Transmission, New Storage
17484
Chautauqua
WD#1 / Carroll (T)
New Storage
17955
Chautauqua
CHAUTAUQUA (T) WD 3 /
Chautauqua (T)
Rte 394 Chautauqua Institution, Upgrade Distribution System
15725
Chautauqua
LAKEWOOD VILLAGE /
Lakewood (V)
New Storage
2,173
$939,000
30
$273,261,576
10,400
$779,200
30
$274,040,776
2,900
$695,250
25
$274,736,026
200
$700,000
25
$275,436,026
3,258
$559,600
15
$275,995,626
Chemung County
17144
Chemung
CHEMUNG (T) WATER
SYSTEM / Chemung (T)
Consolidate PWS with Coliform contamination, extend to private
contaminated/poor yielding wells, New Complete System (New
System), New System Consolidation
280
$5,651,000
125
$281,646,626
17628
Chemung
BEAVER VALLEY WATER
DISTRICT / Catlin (T)
Develop a redundant groundwater source. New auxiliary power source.
recoat storage tank., New Ground Water Source, Upgrade Storage
550
$787,950
100
$282,434,576
16576
Chemung
NORTHSTAR MHP /
Leading Edge Properties
water softener system and, Upgrade Distribution System
400
$93,113
60
$282,527,689
17998
Chemung
HORSEHEADS VILLAGE /
Horseheads (V)
New Storage
11,530
$2,541,709
45
$285,069,398
16560
Chemung
ELMIRA WATER BOARD /
Elmira Water Board
Upgrade Distribution System
65,000
$1,545,000
45
$286,614,398
16260
Chemung
MILLPORT VILLAGE
WATER SUPPLY / Millport
(V)
Upgrade Ground Water Source
292
$125,000
40
$286,739,398
16577
Chemung
BELLAIR MOBILE HOME
PARK / Elmira LLC
Upgrade Distribution System
225
$131,250
35
$286,870,648
16723
Chemung
WELLSBURG VILLAGE /
Wellsburg (V)
Upgrade Distribution System
631
$644,700
35
$287,515,348
16427
Chemung
ROLLING ACRES MOBILE
HOME PARK / Ashford
Management Group, Inc.
Upgrade Distribution System
93
$139,000
10
$287,654,348
1,531
$1,300,000
2210
$288,954,348
Chenango County
17773
Chenango
SHERBURNE VILLAGE /
Sherburne (V)
Phase 2 of 15237., Upgrade Ground Water Source
17425
Chenango
SO. NEW BERLIN WATER
DISTRICT / New Berlin (T)
New Ground Water Source, New Transmission, New Storage, Upgrade
Distribution System, System Consolidation
400
$3,272,000
215
$292,226,348
16991
Chenango
OXFORD WATER
DISTRICT #1 / Oxford (T)
Surface Water Treatment Rule Compliance Facility, New Transmission
50
$122,500
160
$292,348,848
16912
Chenango
NO. NORWICH (T) WD #1 /
North Norwich (T)
New system to serve area with private contaminated wells, consolidate
public water supply, eliminate public water supply with past total
coliform detection. , New Distribution System
100
$920,300
130
$293,269,148
17609
Chenango
NORWICH CITY / Norwich
(C)
New Water Treatment Plant
8,000
$8,652,000
65
$301,921,148
Page 8 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Chenango County
16687
Chenango
NORWICH TOWN WATER
DISTRICT #2 / Norwich (T)
Extend Distribution System
15944
Chenango
OXFORD VILLAGE / Oxford
(V)
200
$390,885
45
$302,312,033
New Ground Water Source, Upgrade Distribution System
1,738
$154,039
40
$302,466,072
1,000
$3,339,464
200
$305,805,536
Clinton County
15569
Clinton
ELLENBURG (T) / Ellenburg
(T)
Development of public water system to serve area with contaminated
water sources, Extend Distribution System
17686
Clinton
SARANAC WD / Saranac
(T)
New Surface Water Treatment Rule Compliance Facility
90
$112,000
105
$305,917,536
17356
Clinton
ARCHIE BORDEAU WD /
Plattsburgh (T)
Extend Distribution System, New System Consolidation
260
$876,000
100
$306,793,536
17492
Clinton
PLATTSBURGH CITY /
Plattsburgh (C)
New Storage
18,000
$4,550,000
95
$311,343,536
17179
Clinton
SOUTH PLATTSBURGH
WATER DISTRICT /
Plattsburgh (T)
New Pump Station, New Distribution System, New System
Consolidation
2,000
$4,575,000
90
$315,918,536
16498
Clinton
CHAMPLAIN (T) /
Champlain (T)
Develop Source for Town Districts (4), New Ground Water Source,
Upgrade Transmission, Upgrade Storage, Upgrade Distribution System
1,350
$2,131,740
85
$318,050,276
17796
Clinton
STANDISH WATER
DISTRICT / Saranac (T)
Upgrade Water Treatment Plant, New Ground Water Source
110
$78,000
85
$318,128,276
17533
Clinton
CHAMPLAIN VILLAGE /
Champlain (V)
Upgrade Water Treatment Plant, New Storage, Upgrade Distribution
System
2,947
$1,883,226
75
$320,011,502
17729
Clinton
PERU WD / Peru (T)
New Other Expenses, New Other (OT)
2,600
$260,000
65
$320,271,502
16371
Clinton
CHAMPLAIN VILLAGE /
Champlain (V)
Distribution Loops, Upgrade Distribution System
2,947
$531,675
65
$320,803,177
17479
Clinton
WEST SERVICE ROAD WD
/ Champlain (T)
Extend Distribution System
30
$675,284
55
$321,478,461
17478
Clinton
ROUTE 11 WD / Champlain
(T)
Extend Distribution System
100
$1,267,380
55
$322,745,841
17391
Clinton
NCCS JUNIOR-SENIOR
HIGH SCHOOL / NCCS
New Inter-Connection, New System Consolidation
1,121
$323,832
55
$323,069,673
17227
Clinton
WATER DISTRICT
EXTENSION NO. 1 / Chazy
(T)
Extend Distribution System
40
$265,000
55
$323,334,673
17477
Clinton
SOUTH STREET WATER
DISTRICT / Champlain (T)
Extend Distribution System
30
$216,300
55
$323,550,973
15660
Clinton
TOWN OF MOOERS
PROPOSED WD#1 /
Mooers (T)
Extend Distribution System
1,250
$6,212,250
50
$329,763,223
17680
Clinton
PLATTSBURGH CITY /
Plattsburgh (C)
Upgrade Water Treatment Plant, Upgrade Transmission
18,000
$7,370,000
50
$337,133,223
17821
Clinton
WATER DISTRICT NO. 1 /
Beekmantown (T)
Extend Distribution System
200
$2,280,875
50
$339,414,098
Page 9 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Clinton County
18027
Clinton
PLATTSBURGH AIRPORT /
Clinton County
Upgrade Distribution System
17309
Clinton
PLEASANT RIDGE
TRAILER PARK / Pleasant
Ridge MHP
17850
Clinton
17687
47,000
$10,402,825
40
$349,816,923
New Storage
50
$8,096
40
$349,825,019
AUSABLE HEIGHTS
WATER SYSTEM / AuSable
(T)
Upgrade Distribution System
40
$425,000
35
$350,250,019
Clinton
CHAMPLAIN VILLAGE /
Champlain (V)
Upgrade Distribution System
2,947
$438,265
30
$350,688,284
17731
Clinton
ROUSES POINT VILLAGE
WD / Rouses Point (V)
Upgrade Surface Water Source
2,550
$1,107,510
30
$351,795,794
15401
Clinton
PERU WD / Peru (T)
Upgrade Surface Water Source, New Transmission
2,600
$620,000
25
$352,415,794
17683
Clinton
PLEASANT RIDGE WD /
Plattsburgh (T)
New Storage
168
$3,190,000
25
$355,605,794
17340
Clinton
GREATER PLATTSBURGH
WATER DISTRICT /
Plattsburgh (T)
New Other Expenses, New Other (OT)
10,000
$541,000
25
$356,146,794
17795
Clinton
MORRISONVILLE WATER
DISTRICT / Plattsburgh (T)
Upgrade Pump Station
1,300
$225,320
25
$356,372,114
16230
Clinton
GREATER PLATTSBURGH
WATER DISTRICT /
Schuyler Falls (T)
New Storage
10,000
$565,000
20
$356,937,114
16227
Clinton
GREATER PLATTSBURGH
WATER DISTRICT /
Schuyler Falls (T)
Upgrade Pump Station
10,000
$142,000
20
$357,079,114
16494
Clinton
CHAMPLAIN (T) /
Champlain (T)
System Acquisition-"Benefit Area #1", New Ground Water Source,
New Distribution System
50
$497,200
20
$357,576,314
147
$233,295
165
$357,809,609
Columbia County
16394
Columbia
MAPLE LANE
ASSOCIATES / Maple Lane
Associates
New Ground Water Source, New Transmission, New Distribution
System
18031
Columbia
VALATIE VILLAGE / Valatie
(V)
New Surface Water Treatment Rule Compliance Facility, New Other
Expenses, New Ground Water Source, Upgrade Transmission,
Upgrade Distribution System, New Other (OT)
2,000
$1,982,750
135
$359,792,359
15532
Columbia
CHATHAM VILLAGE /
Chatham (V)
Upgrade Ground Water Source, Upgrade Storage
2,156
$724,800
85
$360,517,159
16444
Columbia
DARROW SCHOOL / The
Darrow School
New Ground Water Source, New Storage
150
$169,950
75
$360,687,109
16920
Columbia
HAMLET OF EAST
CHATHAM / Chatham (T)
New Complete System (New System)
65
$1,009,745
45
$361,696,854
15765
Columbia
GREENPORT WD NO1 /
Greenport (T)
Charles St., Janis St., Greenport Pkwy., and Rte. 9, Upgrade
Distribution System
4,050
$651,475
40
$362,348,329
15769
Columbia
GREENPORT WD NO1 /
Greenport (T)
Upgrade Pump Station
4,050
$637,313
35
$362,985,642
15535
Columbia
CHATHAM VILLAGE /
Chatham (V)
Upgrade Ground Water Source, Upgrade Distribution System
2,156
$1,240,000
35
$364,225,642
Page 10 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Columbia County
16489
Columbia
HHD CORP. NORTH
SHORE. / HHD
Development Corporation
Upgrade Distribution System
15761
Columbia
GREENPORT WD NO1 /
Greenport (T)
15757
Columbia
15117
Columbia
75
$225,000
35
$364,450,642
Control System Improvements, Upgrade Distribution System
4,050
$354,063
30
$364,804,705
GREENPORT WD NO1 /
Greenport (T)
Upgrade Storage
4,050
$80,443
25
$364,885,148
BREEZY HILLS
COMMUNITY / Hunt's
Homestead MHP
Upgrade Storage
51
$41,200
15
$364,926,348
Cortland County
15294
Cortland
HOMER
VILLAGE-NEWTON
WATER WORKS / Homer
(V)
New Transmission, New Pump Station
4,368
$325,000
100
$365,251,348
17992
Cortland
MCGRAW VILLAGE /
McGraw (V)
Upgrade Distribution System
1,306
$4,222,961
90
$369,474,309
18007
Cortland
MARATHON VILLAGE /
Marathon (V)
New Storage, New Pump Station, Upgrade Distribution System
1,107
$2,947,345
55
$372,421,654
15297
Cortland
HOMER
VILLAGE-NEWTON
WATER WORKS / Homer
(V)
Upgrade Distribution System
4,368
$440,000
50
$372,861,654
15287
Cortland
VIRGIL (T) / Virgil (T)
Upgrade Ground Water Source, New Storage, Extend Distribution
System, System Consolidation
345
$2,223,234
50
$375,084,888
17760
Cortland
MARATHON VILLAGE /
Marathon (V)
New Transmission, New Storage, Upgrade Distribution System
1,107
$1,706,000
40
$376,790,888
17190
Cortland
CINCINNATUS WATER
DISTRICT / Cincinnatus (T)
Upgrade Ground Water Source, Upgrade Transmission
650
$126,500
30
$376,917,388
15298
Cortland
HOMER
VILLAGE-NEWTON
WATER WORKS / Homer
(V)
New Transmission, New Storage
4,368
$528,750
25
$377,446,138
Delaware County
17866
Delaware
GRAND GORGE WATER
DISTRICT / Town of
Roxbury
Phase 3 of 15624 (Phase 2 was 17228): Treat or Replace GWUDI
Wells, New Surface Water Treatment Rule Compliance Facility
370
$992,000
2245
$378,438,138
15996
Delaware
FRANKLIN VILLAGE /
Franklin (V)
New Water Treatment Plant, New Ground Water Source, New Storage,
Extend Distribution System, Upgrade Distribution System
481
$2,301,077
195
$380,739,215
17537
Delaware
DOWNSVILLE WATER
DISTRICT / Colchester (T)
Package Filtration Plant for GWUDI Spring Source and Addition of
Corrosion Control Treatment., New Surface Water Treatment Rule
Compliance Facility, New Water Treatment Plant
500
$92,400
165
$380,831,615
16606
Delaware
DELHI VILLAGE / Delhi (V)
Upgrade Distribution System, New System Consolidation
3,833
$1,373,428
95
$382,205,043
15843
Delaware
MARGARETVILLE
VILLAGE / Margaretville (V)
Upgrade Storage, Upgrade Distribution System
700
$737,900
75
$382,942,943
17417
Delaware
ARKVILLE WATER
DISTRICT / Middletown (T)
Extend distribution, 100,000 gallons of storage, 100 gpm well, system
consolidation., New Ground Water Source, New Storage, Extend
Distribution System, Extend System Consolidation
400
$1,833,375
65
$384,776,318
16653
Delaware
WALTON VILLAGE /
Walton (V)
Upgrade Controls, Upgrade Ground Water Source, Upgrade
Distribution System
3,070
$0
60
$384,776,318
Page 11 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Delaware County
17940
Delaware
ROXBURY WATER
DISTRICT / Roxbury (T)
Upgrade Storage, Upgrade Distribution System
17791
Delaware
STAMFORD VILLAGE /
Stamford (V)
New Storage, Upgrade Distribution System
15316
Delaware
ARKVILLE WATER
DISTRICT / Middletown (T)
15836
Delaware
17956
Delaware
755
$1,423,000
55
$386,199,318
1,280
$2,575,000
35
$388,774,318
Upgrade Ground Water Source
400
$494,400
35
$389,268,718
MARGARETVILLE
VILLAGE / Margaretville (V)
Upgrade Distribution System
700
$1,011,000
35
$390,279,718
ROXBURY WATER
DISTRICT / Roxbury (T)
Installation of water meters.,
755
$358,178
30
$390,637,896
Dutchess County
16618
Dutchess
SHOREHAVEN CIVIC
ASSOC / DCWWA
DCWWA ZONE J SHOREHAVEN WATER SYSTEM, Upgrade Water
Treatment Plant, Upgrade Ground Water Source, Upgrade Distribution
System
300
$3,575,000
160
$394,212,896
15292
Dutchess
WAPPINGER PARK
HOMES / Wappinger (T)
Central Wappinger Water Improvement Area, Ardmore Hills Water
Impr. Area, N. Wappinger Water Impr. Area, Cranberry Hills Water
Impr. Area, & Meadowood and Cedar Ridge Subdiv., New Storage,
System Consolidation
400
$14,676,600
155
$408,889,496
16741
Dutchess
PAWLING VILLAGE /
Pawling (V)
New Surface Water Treatment Rule Compliance Facility, New Ground
Water Source
1,907
$1,270,000
155
$410,159,496
16876
Dutchess
BRETTVIEW ACRES
WATER CO / Brettview
Water Co. Inc.
New Surface Water Treatment Rule Compliance Facility
920
$40,800
115
$410,200,296
17071
Dutchess
BIRCH HILL MANOR /
DCWWA
DCWWA ZONE K BIRCH HILL WATER SYSTEM, Upgrade Water
Treatment Plant, New Ground Water Source
200
$575,000
115
$410,775,296
17574
Dutchess
PLEASANT VALLEY WD /
Pleasant Valley (T)
New Complete System (New System)
2,500
$7,855,000
110
$418,630,296
15301
Dutchess
TIVOLI VILLAGE WATER /
Tivoli (V)
Construct new supply well(s), upgrade treatment, new storage, upgrade
storage, upgrade distribution, Upgrade Water Treatment Plant, New
Ground Water Source, New Storage, Upgrade Pump Station, Upgrade
Distribution System
1,303
$3,729,700
105
$422,359,996
17338
Dutchess
DUTCHESS ESTATES INC
/ Dutchess Estates Water
Company
Upgrade Ground Water Source, Upgrade Storage, Upgrade Pump
Station
500
$455,388
100
$422,815,384
17021
Dutchess
ROKEBY HOMES,INC. /
DCWWA
DCWWA ZONE F PROJECT ROKEBY WATER SYSTEM , Upgrade
Water Treatment Plant, Upgrade Ground Water Source, Upgrade
Distribution System, New System Consolidation
160
$495,356
100
$423,310,740
16534
Dutchess
WAPPINGER PARK
HOMES / Wappinger (T)
Consolidation of Wappinger Park, Tall Trees, and Oakwood Water
Districts, New Transmission, New Inter-Connection
400
$7,649,165
95
$430,959,905
16111
Dutchess
BARD COLLEGE / Bard
College
Upgrade Water Treatment Plant, New Storage
1,400
$2,100,000
85
$433,059,905
17949
Dutchess
HIGH MEADOWS PARK
INC / High Meadows Co-op
Corp
New Ground Water Source, Upgrade Storage
500
$44,577
75
$433,104,482
16737
Dutchess
DOVER RIDGE ESTATES /
Beekman (T)
Upgrade Ground Water Source
250
$266,500
65
$433,370,982
17282
Dutchess
RHINEBECK VILLAGE
WATER / Rhinebeck (V)
Upgrade Water Treatment Plant
4,300
$365,200
65
$433,736,182
16236
Dutchess
RED HOOK VILLAGE / Red
Hook (V)
New Ground Water Source, Upgrade Ground Water Source, New
Storage, Upgrade Distribution System
2,214
$9,328,300
60
$443,064,482
Page 12 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Dutchess County
17868
Dutchess
WOODHILL GREEN /
Woodhill Green Condos
New Water Treatment Plant, Upgrade Ground Water Source
15740
Dutchess
AMENIA WATER DISTRICT
NO 1 / Amenia (T)
New Storage, Upgrade Distribution System
15295
Dutchess
BEEKMAN (T) / Beekman
(T)
New Complete System (New System), New Distribution System
17505
Dutchess
PAWLING WD #2 / Pawling
(T) WD #2
Upgrade Water Treatment Plant, Upgrade Ground Water Source,
Upgrade Pump Station
16803
Dutchess
LAGRANGE/MANCHESTER New Water District
/ LaGrange (T)
18028
Dutchess
POUGHKEEPSIE CITY /
City of Poughkeepsie
17421
Dutchess
17420
483
$1,450,000
55
$444,514,482
1,000
$1,480,000
55
$445,994,482
80
$579,478
45
$446,573,960
225
$218,820
45
$446,792,780
2,500
$7,813,000
40
$454,605,780
Upgrade Other Expenses, Upgrade Other (OT)
28,000
$4,311,035
40
$458,916,815
POUGHKEEPSIE CITY /
Poughkeepsie (C)
College Hill Reservoir., New Storage
28,000
$6,746,500
40
$465,663,315
Dutchess
POUGHKEEPSIE CITY /
Poughkeepsie (C)
Upgrade Distribution System
28,000
$4,223,000
40
$469,886,315
17957
Dutchess
BARD COLLEGE / Bard
College
New microfiltration plant.,
1,400
$991,620
40
$470,877,935
16246
Dutchess
LITTLE SWITZERLAND /
East Fishkill (T)
Upgrade Distribution System, System Consolidation
450
$428,900
35
$471,306,835
16583
Dutchess
LAKE LODGES
APARTMENTS / Lake
Lodge Apts.
New Ground Water Source, Upgrade Pump Station, Upgrade
Distribution System
30
$85,000
35
$471,391,835
17725
Dutchess
DUTCHESS COUNTY
WATER/WASTEWATER
PLANT / DCWWA
New Distribution System, Extend System Consolidation
7,012
$4,417,000
35
$475,808,835
15938
Dutchess
TACONIC ESTATES
WATER DISTRICT / East
Fishkill (T)
New Ground Water Source, System Consolidation
185
$148,000
35
$475,956,835
15645
Dutchess
POUGHKEEPSIE
TOWNWIDE WD /
Poughkeepsie (T)
System Consolidation
40,000
$6,650,000
35
$482,606,835
16845
Dutchess
VICTORY LAKE NURSING
CENTER / Victory Lake
Nursing Center
Upgrade Storage, Upgrade Distribution System
190
$367,092
30
$482,973,927
16297
Dutchess
WINGDALE VILLAGE
PARK / Wingdale Village
Park
Upgrade Water Treatment Plant, New Ground Water Source
150
$74,000
30
$483,047,927
16461
Dutchess
STONY CREEK FARMS
(TOWN HOMES / Stoney
Creek Farms Homeowners
New Water Treatment Plant
21
$18,000
30
$483,065,927
18000
Dutchess
BEACON CITY / Beacon (C)
Upgrade Distribution System
19,000
$972,907
20
$484,038,834
16384
Dutchess
TOWN OF NORTHEAST
WD / Northeast (T)
Upgrade Distribution System, New Water District
411
$100,000
20
$484,138,834
17419
Dutchess
WAPPINGERS FALLS
VILLAGE / Wappinger Falls
(V)
Upgrade Storage, New Storage, Upgrade Distribution System
6,000
$6,238,532
20
$490,377,366
Page 13 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Dutchess County
18001
Dutchess
BEACON CITY / Beacon (C)
Upgrade Distribution System
19,000
$509,737
20
$490,887,103
17999
Dutchess
BEACON CITY / Beacon (C)
Upgrade Pump Station
19,000
$71,379
15
$490,958,482
15662
Dutchess
PINE PLAINS WATER
IMPROVEMENT / Pine
Plains (T)
Upgrade Distribution System
860
$1,617,284
15
$492,575,766
17937
Dutchess
DUTCHESS COUNTY
WATER/WASTEWATER
PLANT / DCWWA
South Tank Rehab, Upgrade Storage
7,012
$679,800
15
$493,255,566
17959
Dutchess
SHOREHAVEN CIVIC
ASSOC / DCWWA
Installation of water meters.,
300
$61,692
15
$493,317,258
15927
Dutchess
RHINEBECK VILLAGE
WATER / Rhinebeck (V)
Upgrade Distribution System
4,300
$1,569,000
15
$494,886,258
17938
Dutchess
DUTCHESS COUNTY
WATER/WASTEWATER
PLANT / DCWWA
North Tank Rehab, Upgrade Storage
7,012
$511,500
15
$495,397,758
15930
Dutchess
RHINEBECK VILLAGE
WATER / Rhinebeck (V)
Remediate backwash "Sludge Pond", Upgrade Water Treatment Plant
4,300
$223,000
15
$495,620,758
17424
Dutchess
LEIGH MANOR / Leona
Darrow
Upgrade Ground Water Source
15
$100,000
15
$495,720,758
17709
Dutchess
DUTCHESS COUNTY
WATER/WASTEWATER
PLANT / DCWWA
Replace asbestos cement water mains, Upgrade Distribution System
7,012
$2,133,000
15
$497,853,758
16514
Dutchess
DUTCHESS CO WATER
AUTH - VALLEYDALE /
DCWWA
Dutchess County Water and Waste Water Authority Zone VDW, New
Ground Water Source, Upgrade Distribution System
500
$1,626,100
15
$499,479,858
17688
Dutchess
WOODHILL GREEN /
Woodhill Green Condos
New Water Treatment Plant, Upgrade Ground Water Source
483
$1,450,000
15
$500,929,858
17705
Dutchess
STAATSBURG WATER
SYSTEM / DCWWA
Replace approximately 19,200 linear feet of aged water main in Zone
C., Upgrade Distribution System
1,072
$6,180,000
10
$507,109,858
15644
Dutchess
POUGHKEEPSIE
TOWNWIDE WD /
Poughkeepsie (T)
Upgrade Distribution System
40,000
$410,000
10
$507,519,858
16540
Dutchess
CHARLOTTE GROVE
MOBILE HOME CT /
Charlette Grove MH Court
Upgrade Distribution System
112
$302,820
10
$507,822,678
17958
Dutchess
BEACON CITY / Beacon (C)
Installation of leak detection equipment., Upgrade Other Expenses,
Upgrade Other (OT)
19,000
$233,100
10
$508,055,778
17703
Dutchess
STAATSBURG WATER
SYSTEM / DCWWA
Rehabilitate approximately 3,000 linear feet of water main in Zone C.,
Upgrade Distribution System
1,072
$773,000
10
$508,828,778
17691
Dutchess
DUTCHESS COUNTY
WATER/WASTEWATER
PLANT / DCWWA
Replace Route 9 water main from Horseshoe Lane to St. Andrews
Road., Upgrade Distribution System
7,012
$3,646,200
10
$512,474,978
17695
Dutchess
DUTCHESS COUNTY
WATER/WASTEWATER
PLANT / DCWWA
Upgrade Distribution System
7,012
$5,677,875
10
$518,152,853
17700
Dutchess
DUTCHESS COUNTY
WATER/WASTEWATER
PLANT / DCWWA
Rehabilitate/replace approximately 35,800 linear feet of water main
associated with Crumwold Acres Subdivision., Upgrade Distribution
System
7,012
$8,806,500
10
$526,959,353
Page 14 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Dutchess County
17693
Dutchess
DUTCHESS COUNTY
WATER/WASTEWATER
PLANT / DCWWA
Replace Route 9 water main from Horseshoe Lane to Vanderbilt Lane.,
7,012
$5,014,200
10
$531,973,553
17707
Dutchess
STAATSBURG WATER
SYSTEM / DCWWA
Replacement of approximately 15,780 linear feet of aged water main,
Upgrade Distribution System
1,072
$4,876,000
10
$536,849,553
CHAFFEE WATER CO /
Chaffee Water Co.
New Surface Water Treatment Rule Compliance Facility, New Ground
Water Source, New Storage
1165
$536,849,553
Erie County
17457
Erie
200
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
17442
Erie
BRANDT (T), NORTH
COLLINS (T)&(V) / North
Collins (V)
WTP improvements for lead and copper violations, Fe violations,
Asbestos Main replacement, inadequate pressures, Upgrade Water
Treatment Plant, Upgrade Transmission, Upgrade Distribution System,
New System Consolidation
17337
Erie
HUNTERS CREEK MOBILE
HOME PARK / Hunters
Creek MHP
Address total coliform detections and organic exceedances, Upgrade
Water Treatment Plant, New Storage, New Pump Station, Upgrade
Distribution System
17339
Erie
S. EAST ERIE CO.
REGIONAL WATER
PROJECT / Aurora (T)
Aurora WD19, Wales WD's2&3. Extend to serve private contaminated
wells, consolidate public water supplies, eliminate public water supply
with past coliform detections, Storage, Pump Station, Extend
Distribution System, System Consolidation
17169
Erie
ECWA DIRECT / Erie
County Water Authority
Consolidation of the (C) Buffalo's system into ECWA,, New System
Consolidation
17151
Erie
AURORA WATER
DISTRICT 18 / Aurora (T)
15922
Erie
17592
1,915
$5,430,000
210
$542,279,553
150
$175,100
185
$542,454,653
2,950
$6,400,000
150
$548,854,653
228,869
$122,000,000
125
$670,854,653
Extend system to serve area with private contaminated wells,
consolidate public water supply, eliminate public water supply with past
total coliform detection. WD 18., Extend Distribution System
1,288
$15,704,100
120
$686,558,753
ALDEN VILLAGE / Alden
(V)
Upgrade Ground Water Source
2,666
$640,003
105
$687,198,756
Erie
TOWN OF NEWSTEAD WD
#10 PHASE 3 / Newstead
(T)
Serve area of private contaminated or poor yielding private wells, New
Distribution System, New System Consolidation
475
$3,250,000
105
$690,448,756
15736
Erie
COLLINS WD #3 / Collins
(T)
Upgrade Transmission, New Storage, Upgrade Distribution System
760
$625,000
80
$691,073,756
15982
Erie
EDEN (T) PROPOSED
WATER DISTRICT / Eden
(T)
Extend Distribution System
300
$725,000
70
$691,798,756
15981
Erie
AKRON VILLAGE / Akron
(V)
Upgrade Water Treatment Plant
2,971
$2,380,000
65
$694,178,756
15880
Erie
EVANS, TOWN WATER
DEPARTMENT / Evans (T)
Angola Service Area of the NYS Thruway Authority., Extend
Distribution System
3,882
$225,000
60
$694,403,756
17980
Erie
WATER DISTRICT NO. 2 /
Colden (T)
New Storage, New Distribution System
1,140
$16,075,000
60
$710,478,756
17395
Erie
ECWA DIRECT / Erie
County Water Authority
Consolidation of the Village of Williamsville's water system into
ECWA's., New System Consolidation
228,869
$3,723,500
60
$714,202,256
18049
Erie
CONCORD TOWN WATER
SYSTEM / Town of Concord
Extend Distribution System
125
$335,000
55
$714,537,256
16851
Erie
AURORA (T) WATER IMP.
AREA NO. 5 / Aurora (T)
Extend Distribution System
210
$613,500
55
$715,150,756
15339
Erie
EAST HILL WATER
DISTRICT NO. 3 / Boston
(T)
New Storage, New Pump Station, Extend Distribution System
800
$3,708,000
55
$718,858,756
17670
Erie
EDEN WD#7 / Eden (T)
Eden WD#7, New Storage, New Distribution System
1,800
$5,460,000
55
$724,318,756
Page 15 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Erie County
17673
Erie
EDEN WD#2 / Eden (T)
Eden WD#2 Shadagee Road Water Project Pump Station and
Waterlines, New Pump Station, New Distribution System
16501
Erie
BLASDELL VILLAGE /
Blasdell (V)
Consolidation of the Village system with Erie County Water Authority,
Upgrade Distribution System, New System Consolidation
17918
Erie
BUFFALO WATER
AUTHORITY / Buffalo (C)
Upgrade Other Expenses, Upgrade Other (OT)
15497
Erie
TOWN OF MARILLA
WATER DISTRICT NO. 4 /
Marilla (T)
Extend Distribution System
16557
Erie
TOWN OF NEWSTEAD
WD#7 / Newstead (T)
Fletcher Road, Extend Distribution System
15508
Erie
TOWN OF MARILLA
WATER DISTRICT #3 /
Marilla (T)
Extend Distribution System
17394
Erie
ECWA DIRECT / Erie
County Water Authority
Consolidation of the Town of Lancaster's water system into ECWA's.,
New System Consolidation
15439
Erie
ANGOLA VILLAGE / Angola
(V)
New Storage, Upgrade Distribution System
17672
Erie
EDEN WD#6 / Eden (T)
17671
Erie
15738
500
$5,280,000
55
$729,598,756
3,200
$2,515,000
55
$732,113,756
276,000
$7,945,178
50
$740,058,934
760
$2,249,845
50
$742,308,779
30
$127,300
50
$742,436,079
1,530
$2,420,500
50
$744,856,579
228,869
$7,480,000
50
$752,336,579
4,200
$4,090,000
45
$756,426,579
Eden WD#6, New Distribution System
500
$420,000
45
$756,846,579
EDEN WD#5 / Eden (T)
Eden WD#5, New Distribution System
150
$5,880,000
45
$762,726,579
Erie
COLLINS WDS #1 AND #2 /
Collins (T)
New Transmission, New Storage, Upgrade Distribution System
1,300
$566,500
45
$763,293,079
15004
Erie
BOSTON (T) WD#2 /
Boston (T)
New Storage, New Pump Station, Extend Distribution System
180
$1,230,000
40
$764,523,079
17724
Erie
GRAND ISLAND TOWN
WATER DEPT. / Grand
Island (T)
Upgrade Water Treatment Plant
19,500
$2,303,000
40
$766,826,079
15898
Erie
GOWANDA VILLAGE /
Gowanda (V)
New Transmission
2,800
$885,250
35
$767,711,329
17757
Erie
HAMBURG - 1 / Hamburg
(V)
Upgrade Distribution System
1,125
$1,261,000
35
$768,972,329
15606
Erie
EVANS WD #3 / Evans (T)
Extend Distribution System
457
$310,000
35
$769,282,329
17758
Erie
HAMBURG - 2 / Hamburg
(V)
Upgrade Distribution System
1,700
$2,844,000
35
$772,126,329
17730
Erie
GRAND ISLAND TOWN
WATER DEPT. / Grand
Island (T)
Upgrade Water Treatment Plant, Upgrade Pump Station
19,500
$3,130,000
35
$775,256,329
15961
Erie
ELMA WATER DISTRICT
NO. 1 / Elma (T)
Upgrade Distribution System
10,287
$145,300
30
$775,401,629
17398
Erie
ECWA DIRECT / Erie
County Water Authority
Parallel 48 inch raw water line between Van de Water raw water pump
station & WTP., New Transmission
228,869
$5,544,000
30
$780,945,629
Page 16 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Erie County
17397
Erie
ECWA DIRECT / Erie
County Water Authority
36 inch transmission main on Sweet Home Road., New Transmission
15534
Erie
COLLINS (T) / Collins (T)
New Pump Station
17396
Erie
ECWA DIRECT / Erie
County Water Authority
Parallel 48 inch transmission mains between Van de Water WTP & Ball
Pump Station., New Transmission
15133
Erie
HOLLAND WATER
DISTRICT / Holland (T)
Upgrade Water Treatment Plant, New Ground Water Source
17399
Erie
ECWA DIRECT / Erie
County Water Authority
36 inch transmission main on Maple Road., New Transmission
16016
Erie
DEPEW VILLAGE / Depew
(V)
Extend Distribution System
15479
Erie
ECWA DIRECT / ECWA/
Amherst (T)
15477
Erie
16167
228,869
$5,323,909
30
$786,269,538
105
$235,000
30
$786,504,538
228,869
$16,620,000
30
$803,124,538
1,680
$200,000
25
$803,324,538
228,869
$17,706,000
25
$821,030,538
7,500
$112,500
25
$821,143,038
Town of Amherst-Sheridan Dr. to Klein Rd., Upgrade Distribution
System
228,869
$550,000
20
$821,693,038
ECWA DIRECT / ECWA/
Amherst (T)
Town of Amherst WD 15C - Country Parkway., Upgrade Distribution
System
228,869
$275,000
20
$821,968,038
Erie
GRAND ISLAND (T) / Grand
Island (T)
Upgrade Water Treatment Plant
18,000
$1,459,374
20
$823,427,412
17759
Erie
WATER MAIN
REPLACEMENT / Hamburg
(T)
Upgrade Distribution System
43,425
$3,103,000
20
$826,530,412
15484
Erie
ECWA DIRECT / ECWA/
Amherst (T)
Town of Amherst WD 15C - Niagara Falls Blvd., Upgrade Distribution
System
228,869
$300,000
20
$826,830,412
16042
Erie
EAST AURORA VILLAGE /
East Aurora (V)
Upgrade Distribution System
7,200
$1,707,950
20
$828,538,362
17620
Erie
WINDOVER WATER CO
WM REPLACEMENT /
Windover Water Co
Upgrade Distribution System
20
$189,000
20
$828,727,362
15486
Erie
ECWA DIRECT / ECWA/
Amherst (T)
Town of Amherst WD 15C - Casey Rd., Upgrade Distribution System
228,869
$250,000
20
$828,977,362
16578
Erie
SPRINGVILLE MOBILE
VILLAGE / Parss Properties
New Ground Water Source
90
$48,600
20
$829,025,962
16758
Erie
W. SENECA WD#3 / West
Seneca (T)
Orchard Park Road Watermain, Upgrade Distribution System
520
$460,000
20
$829,485,962
17726
Erie
GRAND ISLAND TOWN
WATER DEPT. / Grand
Island (T)
New Transmission
19,500
$500,000
15
$829,985,962
15469
Erie
WILLIAMSVILLE (V) /
Williamsville (V)
Los Robles Street water reconstruction project., Upgrade Distribution
System
6,017
$408,447
15
$830,394,409
16815
Erie
LANCASTER (V) /
Lancaster (V)
Upgrade Distribution System
11,940
$1,670,454
15
$832,064,863
15444
Erie
WILLIAMSVILLE (V) /
Williamsville (V)
Northeast quadrant transmission system improvements., Upgrade
Distribution System
6,017
$808,396
15
$832,873,259
Page 17 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Erie County
17734
Erie
GRAND ISLAND TOWN
WATER DEPT. / Grand
Island (T)
Upgrade Storage
18003
Erie
CATTARAUGUS STREET
WATER DISTRICT /
Concord (T)
New Distribution System, New Water District
17694
Erie
DISTRICT #5 / Alden (T)
New Distribution System
17733
Erie
GRAND ISLAND TOWN
WATER DEPT. / Grand
Island (T)
16740
Erie
16187
19,500
$2,100,000
15
$834,973,259
13
$325,000
15
$835,298,259
661
$10,056,625
15
$845,354,884
New Transmission
19,500
$1,250,000
15
$846,604,884
ORCHARD PARK (T) /
Orchard Park (T)
2000 water system improvements., Upgrade Distribution System
28,000
$7,081,000
10
$853,685,884
Erie
GRAND ISLAND TOWN
WATER DEPT. / Grand
Island (T)
Upgrade Water Treatment Plant
19,500
$340,000
10
$854,025,884
17690
Erie
CONSOLIDATED WATER
DISTRICT / Lancaster (T)
Upgrade Distribution System
500
$2,725,000
10
$856,750,884
16396
Erie
ORCHARD PARK VILLAGE
/ Orchard Park (V)
Upgrade Distribution System
3,100
$50,000
10
$856,800,884
17335
Erie
WILLIAMSVILLE (V) /
Williamsville (V)
Upgrade Distribution System
6,017
$2,700,000
10
$859,500,884
15119
Erie
CLARENCE, TOWN
WATER DEPT. / Clarence
(T)
Main Street watermain replacement., Upgrade Distribution System
15,000
$2,650,000
5
$862,150,884
16556
Erie
WILLIAMSVILLE (V) /
Williamsville (V)
Mill Street, Upgrade Distribution System
6,017
$141,000
5
$862,291,884
15120
Erie
CLARENCE, TOWN
WATER DEPT. / Clarence
(T)
Goodrich Road Watermain Extension., Extend Distribution System
15,000
$165,000
5
$862,456,884
15118
Erie
CLARENCE, TOWN
WATER DEPT. / Clarence
(T)
Sheridan Drive watermain replacement., Upgrade Distribution System
15,000
$1,597,700
5
$864,054,584
18012
Erie
WATER IMPROVEMENT
AREA NO. 5 / Alden (T)
Extend Distribution System
1,650
$10,873,000
5
$874,927,584
17531
Erie
BOSTON (T) WD#2 /
Boston (T)
Extend Water District
100
$2,499,100
5
$877,426,684
16178
Erie
GRAND ISLAND TOWN
WATER DEPT. / Grand
Island (T)
Ransom Road waterline improvements., Upgrade Distribution System
19,500
$111,453
5
$877,538,137
15121
Erie
CLARENCE, TOWN
WATER DEPT. / Clarence
(T)
Harris Hill Road & Arondale Drive watermain replacements., Upgrade
Distribution System
15,000
$726,200
5
$878,264,337
16185
Erie
GRAND ISLAND TOWN
WATER DEPT. / Grand
Island (T)
Sandy Beach waterline improvements., Upgrade Distribution System
19,500
$986,154
5
$879,250,491
15627
Erie
HAMBURG (T) WD'S /
Hamburg (T)
New Distribution System
35,000
$1,346,725
5
$880,597,216
17532
Erie
WD#2 / Boston (T)
Extend Water District
100
$2,324,177
5
$882,921,393
Page 18 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Erie County
16182
Erie
GRAND ISLAND TOWN
WATER DEPT. / Grand
Island (T)
Bush Road waterline improvements., Upgrade Distribution System
19,500
$228,113
5
$883,149,506
$406,500
2175
$883,556,006
$0
1240
$883,556,006
Essex County
17631
Essex
WILMINGTON WD /
Wilmington (T)
Phase 2 (Juniper Hill Road) of DWSRF 15803, New Surface Water
Treatment Rule Compliance Facility, New Storage, Upgrade
Distribution System
980
17388
Essex
PORT KENT WD /
Chesterfield (T)
New Surface Water Treatment Rule Compliance Facility, New Ground
Water Source, New Storage
202
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
15881
Essex
WADHAMS WD / Westport
(T)
New Surface Water Treatment Rule Compliance Facility, New
Inter-Connection, New System Consolidation
140
$0
1240
$883,556,006
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
17163
Essex
TICONDEROGA WD /
Ticonderoga (T)
New Surface Water Treatment Rule Compliance Facility, New Storage,
Upgrade Distribution System
17682
Essex
WD#4 / Moriah (T)
New Surface Water Treatment Rule Compliance Facility, New
Distribution System
17629
Essex
ESSEX WD / Essex (T)
17513
Essex
17684
5,000
$13,954,315
265
$897,510,321
78
$1,990,475
180
$899,500,796
Address turbidity and organic violations, New Ground Water Source,
Upgrade Distribution System
300
$1,515,954
165
$901,016,750
WINEBROOK HILLS WD /
Newcomb (T)
New Ground Water Source, Upgrade Distribution System
250
$5,302,728
145
$906,319,478
Essex
KEESEVILLE V / Keeseville
(V)
Upgrade Water Treatment Plant
2,300
$3,442,280
75
$909,761,758
15827
Essex
MINERVA WD / Minerva (T)
New Storage, Upgrade Distribution System
800
$175,000
75
$909,936,758
15797
Essex
PORT HENRY V / Port
Henry (V)
Upgrade Transmission, Upgrade Distribution System
1,831
$511,910
65
$910,448,668
16589
Essex
MORIAH WD / Moriah (T)
Upgrade Distribution System
3,100
$239,450
65
$910,688,118
16659
Essex
PORT HENRY V / Port
Henry (V)
Upgrade Distribution System
1,831
$4,315,148
65
$915,003,266
15846
Essex
MORIAH WD / Moriah (T)
Upgrade Distribution System
3,100
$606,876
60
$915,610,142
15849
Essex
MORIAH WD / Moriah (T)
New Other Expenses, Upgrade Distribution System, New Other (OT)
3,100
$1,573,733
60
$917,183,875
17193
Essex
AUSABLE FORKS WD / Jay
(T)
Upgrade Water Treatment Plant, New Storage
900
$5,201,603
60
$922,385,478
17031
Essex
CROWN POINT WD /
Crown Point (T)
Upgrade Distribution System
995
$2,795,678
55
$925,181,156
15841
Essex
LEWIS WD / Lewis (T)
Upgrade Distribution System
428
$792,076
55
$925,973,232
16045
Essex
NEW RUSSIA WD /
Elizabethtown (T)
Upgrade Water Treatment Plant, New Storage, Upgrade Distribution
System
60
$135,000
45
$926,108,232
17595
Essex
FOREVER WILD WATER
CO-SIGNOR / Forever Wild
Water Company
Upgrade Ground Water Source, Upgrade Storage, Upgrade Pump
Station
900
$2,247,987
35
$928,356,219
Page 19 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Essex County
16897
Essex
CROWN POINT WD /
Crown Point (T)
Upgrade Distribution System
995
$1,000,000
35
$929,356,219
17578
Essex
BOLTONS ACRES / Bolton
Acres MHP
New Ground Water Source, Upgrade Distribution System
100
$90,000
30
$929,446,219
17630
Essex
WILLSBORO BAY WATER
SUPPLY / Willsboro (T)
Upgrade Distribution System
140
$1,091,985
25
$930,538,204
Franklin County
17611
Franklin
SARANAC LAKE V /
Saranac Lake (V)
New SCADA equipment., New Surface Water Treatment Rule
Compliance Facility, Upgrade Distribution System
5,800
$12,500,000
245
$943,038,204
18061
Franklin
TUPPER LAKE V / Tupper
Lake (V)
New wells to replace SW source and inadequate DE plant., New
Ground Water Source, Upgrade Distribution System
5,500
$2,979,790
235
$946,017,994
16861
Franklin
TUPPER LAKE V / Tupper
Lake (V)
New Storage, Upgrade Distribution System
5,500
$700,000
145
$946,717,994
17455
Franklin
WATER DISTRICT #3 /
Malone (T)
Consolidate a MHP with nitrate violations, New Distribution System,
System Consolidation, New System Consolidation
300
$1,328,000
145
$948,045,994
15246
Franklin
ST REGIS MOHAWK
WATER SYSTEM / St.
Regis Mohawk Tribe
Upgrade Water Treatment Plant, New Pump Station
20
$3,897,950
95
$951,943,944
16866
Franklin
TUPPER LAKE V / Tupper
Lake (V)
Upgrade Water Treatment Plant, Upgrade Transmission
5,500
$596,295
90
$952,540,239
17646
Franklin
WEST BANGOR
EXTENSION / Bangor (T)
Extend Distribution System
150
$1,090,000
65
$953,630,239
16571
Franklin
HARRIETSTOWN (T) /
Harrietstown (T)
Upgrade Distribution System
5,621
$710,800
55
$954,341,039
16957
Franklin
CHATEAUGAY V /
Chateaugay (V)
Upgrade Distribution System
1,100
$2,750,000
55
$957,091,039
17304
Franklin
FORT COVINGTON WD /
Fort Covington (T)
Upgrade Ground Water Source, Upgrade Distribution System
900
$1,241,050
50
$958,332,089
17226
Franklin
CHATEAUGAY (T) WD#1 /
Chateaugay (T)
New Water District
100
$114,075
45
$958,446,164
16896
Franklin
SARANAC LAKE V /
Saranac Lake (V)
Upgrade Distribution System
5,800
$180,250
45
$958,626,414
15712
Franklin
SARANAC LAKE V /
Saranac Lake (V)
Upgrade Storage, Upgrade Pump Station
5,800
$582,400
45
$959,208,814
17284
Franklin
MALONE V / Malone (V)
New Transmission
13,000
$498,963
40
$959,707,777
17960
Franklin
SARANAC LAKE V /
Saranac Lake (V)
Installation of water meters.,
5,800
$1,000,000
35
$960,707,777
17184
Franklin
BURKE V / Burke (V)
New Other Expenses, New Other (OT)
273
$250,000
20
$960,957,777
Page 20 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Fulton County
16538
Fulton
TWIN PINES ESTATES /
CVH Charter Corp.
MHP on Hagadorn Mills Road in the Town of Broadalbin, New Ground
Water Source, Upgrade Storage, New Pump Station
17732
Fulton
JOHNSTOWN (C) WATER
WORKS / Johnstown (C)
Replacement of Maylender finished water uncovered reservoir;
automation of water system operations, New Other Expenses, New
Storage, New Other (OT)
15330
Fulton
GLOVERSVILLE (C)
WATER WORKS /
Gloversville (C)
15331
Fulton
17575
45
$39,655
150
$960,997,432
8,511
$3,255,000
90
$964,252,432
Eagle Street Water Storage Tank, New Storage
17,991
$1,963,900
80
$966,216,332
GLOVERSVILLE (C)
WATER WORKS /
Gloversville (C)
Ayers Hill Reservoir water storage tanks, New Storage
17,991
$2,234,600
80
$968,450,932
Fulton
NORTHAMPTON (T)
WATER DISTRICT /
Northampton (T)
Upgrade Storage, Upgrade Distribution System
1,000
$6,303,627
65
$974,754,559
17546
Fulton
SANDYLAND MHP /
Sandyland MHP
Transmission Main of 1200 feet to connect existing MHP to municipal
PWS extension., Extend Transmission
30
$60,000
50
$974,814,559
17545
Fulton
JOCKEYVILLE ESTATES II
/ Saratoga LLC
Install transmission main of 2000 feet length to connect existing MHP
with municipal PWS., Extend Transmission
126
$92,000
50
$974,906,559
15935
Fulton
JOHNSTOWN (T) /
Johnstown (C)
Upgrade Distribution System
50
$86,725
50
$974,993,284
17882
Fulton
BROADALBAN (V) /
Broadalin (V)
Replace Aged Storage Tank, New Storage
1,500
$1,990,000
30
$976,983,284
15253
Fulton
BROADALBIN (V) /
Broadalbin (V)
New Storage, Upgrade Distribution System
1,397
$1,268,960
30
$978,252,244
15793
Fulton
MAYFIELD (V) WATER
WORKS / Mayfield (V)
New Ground Water Source
817
$78,000
30
$978,330,244
17748
Fulton
BROADALBIN (V) /
Broadalbin (V)
New Other Expenses, Upgrade Transmission, New Other (OT)
1,397
$91,207
25
$978,421,451
6,300
$916,000
75
$979,337,451
16,310
$2,067,500
70
$981,404,951
3,300
$119,000
65
$981,523,951
781
$880,425
65
$982,404,376
2,000
$3,860,000
60
$986,264,376
16,310
$19,113,000
60
$1,005,377,376
Genesee County
16162
Genesee
LEROY (V) / Leroy (V)
Upgrade Water Treatment Plant
17761
Genesee
BATAVIA CITY / Batavia (C)
Upgrade Water Treatment Plant, Upgrade Distribution System
15608
Genesee
MCWA, GENESEE WEST /
Corfu (V)
Upgrade Storage
15042
Genesee
ALEXANDER VILLAGE /
Alexander (V)
New Storage
17036
Genesee
TOWN OF PEMBROKE
WATER DISTRICT NO. 1 /
Pembroke (T)
Extend system to serve area with private contaminated wells. , Extend
Distribution System
16112
Genesee
BATAVIA CITY / Batavia (C)
New Water Treatment Plant
18046
Genesee
PRATT RD. WD / Batavia
(T)
New Water District
55
$1,067,974
55
$1,006,445,350
18045
Genesee
CREEK RD. WD / Batavia
(T)
New Water District
136
$1,407,623
55
$1,007,852,973
Page 21 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Genesee County
18047
Genesee
RTE 98 WD / Batavia (T)
New Water District the serve areas East and West of Rte. 98, New
Water District
318
$5,322,464
55
$1,013,175,437
17065
Genesee
BYRON (T) WD NO. 2 /
Byron (T)
Extend to serve private contaminated wells in Hamlet of South Byron.,
Extend Distribution System
315
$1,854,000
55
$1,015,029,437
16610
Genesee
LEROY (V) / Le Roy (V)
Upgrade Water Treatment Plant
6,300
$2,150,000
50
$1,017,179,437
17899
Genesee
WD II / Alabama (T)
Extend Water District
1,056
$5,416,206
50
$1,022,595,643
17885
Genesee
WATER DISTRICT 2 /
Alabama (T)
Connect existing Hamlet to Niag Co WD, Extend Distribution System
1,056
$5,258,452
50
$1,027,854,095
16575
Genesee
BARBARY COAST MHP /
Affordable Great Locations
Extend Distribution System
50
$82,700
45
$1,027,936,795
17066
Genesee
BYRON (T) WD NO. 3 /
Byron (T)
Extend to serve private contaminated wells in the Hamlet of North
Byron., Extend Distribution System
100
$148,000
45
$1,028,084,795
17768
Genesee
WATER DISTRICT #8 /
Stafford (T)
New Distribution System
90
$859,700
45
$1,028,944,495
17764
Genesee
MCWA GENESEE / Byron
(T)
New Water District
13,250
$161,000
45
$1,029,105,495
17755
Genesee
MCWA GENESEE / Byron
(T)
New Distribution System
13,250
$148,000
45
$1,029,253,495
16113
Genesee
BATAVIA CITY / Batavia (C)
New Ground Water Source
16,310
$628,830
45
$1,029,882,325
17676
Genesee
WATER DISTRICT #7 /
Stafford (T)
Extend Distribution System
75
$679,700
45
$1,030,562,025
17677
Genesee
WATER DISTRICT #5 /
Stafford (T)
Extend Distribution System
123
$927,000
45
$1,031,489,025
17032
Genesee
GOLDEN MOBILE HOME
PARK / Crystal Cole
Consolidation of PWS by connecting to (T) Stafford water system,
Upgrade Distribution System
25
$139,050
40
$1,031,628,075
15611
Genesee
MCWA, GENESEE WEST /
Corfu (V)
Upgrade Distribution System
3,300
$477,000
35
$1,032,105,075
17540
Genesee
OAKFIELD VILLAGE /
Oakfield (V)
Upgrade Transmission, Upgrade Storage, Upgrade Distribution System
1,805
$2,864,100
35
$1,034,969,175
17799
Genesee
MCWA GENESEE /
Genesee County
New Transmission, New Storage, New Pump Station
13,250
$8,570,000
25
$1,043,539,175
17383
Genesee
OAKFIELD VILLAGE /
Oakfield (T)
Upgrade Transmission
1,805
$1,661,600
20
$1,045,200,775
17527
Genesee
OAKFIELD VILLAGE /
Oakfield (V)
Upgrade Transmission, Upgrade Distribution System
1,805
$1,147,575
15
$1,046,348,350
COXSACKIE VILLAGE /
Coxsackie (V)
Phase 2 of 15702, Upgrade Water Treatment Plant, Upgrade Water
Treatment Plant
4,010
$3,233,065
3175
$1,049,581,415
Greene County
17444
Greene
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
Page 22 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Greene County
17496
Greene
HUNTER VILLAGE / Hunter
(V)
Phase 2 of #16732 - Dolan's Lake Intake and Connection of Wells 1
and 3, Upgrade Water Treatment Plant, New Ground Water Source,
New Transmission
896
$1,518,150
2165
$1,051,099,565
16106
Greene
TANNERSVILLE VILLAGE /
Tannersville (V)
New Ground Water Source, Upgrade Transmission, Upgrade
Distribution System
448
$1,900,000
135
$1,052,999,565
17414
Greene
CATSKILL VILLAGE /
Catskill (V)
Upgrade Water Treatment Plant, New Storage, Upgrade Distribution
System
8,000
$10,270,000
110
$1,063,269,565
16169
Greene
ASHLAND WD#1 / Ashland
(T)
New Complete System (New System), New Inter-Connection
300
$2,873,620
105
$1,066,143,185
15958
Greene
PRATTSVILLE WATER
DISTRICT / Prattsville (T)
New Ground Water Source
410
$1,361,800
100
$1,067,504,985
15684
Greene
NEW BALTIMORE (T) /
New Baltimore (T)
Extend system to serve area with private contaminated wells,
consolidate public water supply. , Extend Distribution System, New
System Consolidation
1,300
$5,000,000
90
$1,072,504,985
15704
Greene
COXSACKIE VILLAGE /
Coxsackie (V)
Upgrade Transmission, New Storage, Upgrade Distribution System
4,010
$6,210,000
80
$1,078,714,985
16728
Greene
PRATTSVILLE WD #2 /
Prattsville (T)
New Ground Water Source, New Complete System (New System)
25
$468,585
65
$1,079,183,570
17948
Greene
HENSONVILLE (WINDHAM
W.D.) / Windham (T)
Upgrade Ground Water Source
402
$757,050
50
$1,079,940,620
16105
Greene
TANNERSVILLE VILLAGE /
Tannersville (V)
Upgrade Distribution System
448
$467,000
45
$1,080,407,620
16129
Greene
HENSONVILLE (WINDHAM
W.D.) / Windham (T)
Upgrade Transmission, Upgrade Distribution System
402
$467,000
45
$1,080,874,620
15415
Greene
CATSKILL VILLAGE /
Catskill (V)
Other Expenses, New Ground Water Source, New Transmission, Other
(OT)
8,000
$695,250
30
$1,081,569,870
15419
Greene
CATSKILL VILLAGE /
Catskill (V)
Upgrade Distribution System
8,000
$1,390,500
30
$1,082,960,370
17640
Greene
ATHENS VILLAGE / Athens
(V)
Upgrade Distribution System
1,850
$171,700
30
$1,083,132,070
15691
Greene
SLEEPY HOLLOW LAKE
WATER CO. / Sleepy
Hollow Lake Assoc.
Upgrade Surface Water Source, Upgrade Storage
2,000
$1,144,330
20
$1,084,276,400
INDIAN LAKE WD / Indian
Lake (T)
New Surface Water Treatment Rule Compliance Facility, Upgrade
Water Treatment Plant, New Ground Water Source, Upgrade
Distribution System
1255
$1,084,276,400
Hamilton County
17456
Hamilton
16278
Hamilton
LONG LAKE (T) / Long Lake New Ground Water Source, New Storage, Upgrade Distribution System
(T)
15600
Hamilton
ANTLERS OF RAQUETTE
LAKE, INC. / Antlers of
Raquette Lake Inc.
17530
Hamilton
HAMLET OF INLET / Inlet
(T)
Page 23 of 86
900
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
750
$3,929,255
200
$1,088,205,655
New Surface Water Source, Inter-Connection
120
$243,595
150
$1,088,449,250
New Ground Water Source, New Complete System (New System)
490
$2,674,765
65
$1,091,124,015
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Herkimer County
17470
Herkimer
HERKIMER VILLAGE /
Herkimer (V)
Phase 2 of 16676, New Surface Water Treatment Rule Compliance
Facility
7,606
$300,000
2130
$1,091,424,015
16692
Herkimer
VAN HORNESVILLE
WATER WORKS / Stark (T)
VanHornesville Water System, New Surface Water Treatment Rule
Compliance Facility, New Storage, Upgrade Distribution System
372
$2,098,150
200
$1,093,522,165
17552
Herkimer
NEWPORT VILLAGE /
Newport (V)
New Surface Water Treatment Rule Compliance Facility, New Ground
Water Source, Upgrade Transmission, New Storage, Upgrade
Distribution System
740
$2,175,000
200
$1,095,697,165
17499
Herkimer
ILION (V) WATER WORKS
/ Ilion (V)
Construction of Multilevel Water Intake in non-utilized reservoir, replace
old transmission main & valves to address disinfection byproducts,
Upgrade Surface Water Source
8,610
$1,285,777
170
$1,096,982,942
15557
Herkimer
POLAND VILLAGE / Poland
(V)
Surface Water Treatment Rule Compliance Facility, New Ground
Water Source, New Storage, Upgrade Distribution System
463
$246,000
165
$1,097,228,942
17330
Herkimer
VILLAGE OF COLD
BROOK / Cold Brook (V)
New Complete System (New System), New System Consolidation
336
$1,761,961
100
$1,098,990,903
16922
Herkimer
GRAHM, NEWPORT &
BROWN RD WD / Schuyler
(T)
New system to serve area with private contaminated wells. , New
Complete System (New System)
260
$1,280,000
85
$1,100,270,903
17422
Herkimer
HERKIMER (T), WD #3, #4,
#5 / Herkimer (T)
Upgrade Pump Station, Upgrade Distribution System, Extend
Distribution System
320
$299,112
85
$1,100,570,015
16203
Herkimer
EAST FRANKFORT
WATER SYSTEM /
Frankfort (T)
New Ground Water Source, New Storage, Upgrade Distribution System
1,000
$948,000
75
$1,101,518,015
17311
Herkimer
MANION HEIGHTS WD /
German Flatts (T)
New Complete System (New System)
105
$152,000
75
$1,101,670,015
17869
Herkimer
STARKVILLE WATER
SYSTEM / Stark (T)
New Complete System (New System)
250
$1,000,000
65
$1,102,670,015
17639
Herkimer
ILION (V) WATER WORKS
/ Ilion (V)
Upgrade Surface Water Treatment Rule Compliance Facility, Upgrade
Surface Water Treatment Rule Compliance Facility, Upgrade Surface
Water Treatment Rule Compliance Facility
8,610
$4,343,510
60
$1,107,013,525
17280
Herkimer
WEST FRANKFORT
WATER DISTRICT /
Frankfort (T)
New Complete System (New System)
1,100
$5,828,000
55
$1,112,841,525
17055
Herkimer
FRANKFORT (V) WATER
WORKS / Frankfort (V)
New Ground Water Source
2,995
$481,691
45
$1,113,323,216
17057
Herkimer
FRANKFORT (V) WATER
WORKS / Frankfort (V)
Upgrade Distribution System
2,995
$1,971,007
45
$1,115,294,223
17941
Herkimer
MIDDLEVILLE (V) WATER
WORKS / Middleville (V)
Upgrade Ground Water Source, Upgrade Pump Station, Upgrade
Distribution System
725
$3,453,415
45
$1,118,747,638
17048
Herkimer
DOLGEVILLE (V) PWS /
Dolgeville (V)
New Storage
2,166
$1,051,000
40
$1,119,798,638
17096
Herkimer
TRINITY CHRISTIAN
(LITTLE LAMB PRE-SCH) /
Trinity Christian School
New Other Expenses, New Other (OT)
15
$1,400
30
$1,119,800,038
17939
Herkimer
OLD FORGE (V) WATER
DISTRICT / Webb (T)
Upgrade Distribution System, Extend Distribution System
1,766
$561,350
25
$1,120,361,388
16101
Herkimer
MOHAWK (V) WATER
WORKS / Mohawk (V)
Fulmer Creek Stream Crossing., Upgrade Distribution System
2,985
$82,000
25
$1,120,443,388
Page 24 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Herkimer County
16103
Herkimer
MOHAWK (V) WATER
WORKS / Mohawk (V)
Michigan, Green, Henry, Church Streets Main replacement, Upgrade
Distribution System
LAFAVE ROAD WATER
DISTRICT / Le Ray (T)
Consolidation of existing public water systems with GUDI wells,
coliform and lead violations., New Distribution System, New System
Consolidation
600
Westcotts WD to serve along NYS Route 3. Consolidation of PWS
systems addressing SWTR & E-Coli violations. , Upgrade Storage,
New Distribution System, New System Consolidation
300
New Surface Water Treatment Rule Compliance Facility, New
Distribution System, New System Consolidation
352
2,985
$266,000
25
$1,120,709,388
1280
$1,120,709,388
Jefferson County
17473
17321
17306
Jefferson
Jefferson
Jefferson
WESTCOTTS WATER
DISTRICT / Hounsfield (T)
WATER DISTRICT #2 /
Henderson (T)
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
$0
1260
$1,120,709,388
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
$0
1190
$1,120,709,388
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
15603
Jefferson
WATER DISTRICT NO. 5 /
Hounsfield (T)
Extend distribution system to area of insufficient yielding or
cantaminated private wells. Consolidate Watertown International
Airport., New Distribution System, New System Consolidation
345
$4,800,000
210
$1,125,509,388
17529
Jefferson
TIBBETS POINT WATER
DISTRICT / Cape Vincent
(T)
Serve area with private contaminated wells, New Surface Water
Treatment Rule Compliance Facility, New System Consolidation, New
Water District
200
$2,645,000
180
$1,128,154,388
17562
Jefferson
HERRINGS VILLAGE /
Herrings (V)
Distribution and storage improvements., Upgrade Storage, Upgrade
Distribution System
120
$3,429,000
170
$1,131,583,388
16117
Jefferson
ALEXANDRIA TOWN WD
#1 - OTTER STREET /
Alexandria (T)
Extend Distribution System, Upgrade Distribution System
60
$3,600,000
150
$1,135,183,388
16339
Jefferson
WELLESLEY ISLAND
WATER CORP. / Wellesley
Island Water Corp.
New Water Treatment Plant, New Surface Water Source
548
$2,336,000
140
$1,137,519,388
17201
Jefferson
ELLISBURG (V) / Ellisburg
(V)
Extend system to serve area with private contaminated wells,
consolidate public water supply, eliminate public water supply with past
total coliform detection. , Extend Distribution System, New System
Consolidation
269
$0
135
$1,137,519,388
16701
Jefferson
LAFARGEVILLE (T.
ORLEANS) / Orleans (T)
New Ground Water Source
750
$246,731
85
$1,137,766,119
17474
Jefferson
DEPAUVILLE WATER
DISTRICT / Clayton (T)
New Distribution System, New System Consolidation
200
$6,333,529
85
$1,144,099,648
15531
Jefferson
TOWN OF PAMELIA RT. 3,
WATER DISTRICT /
Pamelia (T)
Extend system to serve area with private contaminated wells,
consolidate public water supply. , Extend Distribution System
96
$474,160
85
$1,144,573,808
15909
Jefferson
TOWN OF WILNA WATER
DISTRICTS NOS. 1,2,3, &
4 / Wilna (T)
New Surface Water Source, Upgrade Distribution System
475
$400,000
75
$1,144,973,808
17098
Jefferson
WILNA WD#1 / Wilna (T)
Extend system to serve area with private contaminated wells. , New
Distribution System
85
$569,590
75
$1,145,543,398
17979
Jefferson
WATRE DISTRICT NO. 8 /
Watertown (T)
Extend Distribution System, New System Consolidation
119
$1,929,000
75
$1,147,472,398
16921
Jefferson
ADAMS (T) WD #2 / Adams
(T)
New system to serve area with private contaminated wells. , New
Complete System (New System)
190
$1,509,000
65
$1,148,981,398
15825
Jefferson
CLAYTON (T) WD NO. 1 /
Clayton (T)
New Complete System (New System)
75
$451,217
60
$1,149,432,615
15561
Jefferson
WATERTOWN (T) /
Watertown (T)
New system to serve area with private contaminated wells. , New
Complete System (New System), New Storage, New Distribution
System
530
$2,547,476
60
$1,151,980,092
17189
Jefferson
WATER DISTRICT #5 /
Cape Vincent (T)
New system to serve area with private contaminated wells. , New
Distribution System
100
$1,085,200
55
$1,153,065,292
Page 25 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Jefferson County
17185
Jefferson
WATERTOWN TOWN WD
2 / Watertown (T)
New Distribution System
100
$1,435,865
50
$1,154,501,157
17978
Jefferson
NORTHEAST WATER
DISTRICT / Waertown (T)
New Ground Water Source, New Storage, New Distribution System
550
$6,177,300
50
$1,160,678,457
17924
Jefferson
WD#3 EXTENSION /
Hounsfield (T)
Extend Distribution System
37
$2,635,000
50
$1,163,313,457
17058
Jefferson
HOUNSFIELD (T) WD #2
EXTENSION / Hounsfield
(T)
Extend Distribution System
123
$794,439
50
$1,164,107,896
18006
Jefferson
WATER DISTRICT NO. 6 /
Hounsfield (T)
Extend Distribution System
450
$17,521,000
50
$1,181,628,896
15240
Jefferson
ALEXANDRIA VILLAGE /
Alexandria Bay (V)
Upgrade Surface Water Source, Upgrade Storage, Upgrade
Distribution System
1,900
$3,048,188
50
$1,184,677,084
17466
Jefferson
SACKETS HARBOR
VILLAGE / Sackets Harbor
(V)
Upgrade Water Treatment Plant
1,300
$3,090,000
50
$1,187,767,084
17305
Jefferson
MORGIAS BEACH WATER
SYSTEM / Sackets Harbor
(V)
New Distribution System
65
$500,000
50
$1,188,267,084
17320
Jefferson
HOUNSFIELD WD#2
EXTENSION / Hounsfield
(T)
New Distribution System
200
$3,900,000
50
$1,192,167,084
18052
Jefferson
CAPE VINCENT VILLAGE /
Cape Vincent (V)
Upgrade Water Treatment Plant
1,500
$3,200,000
45
$1,195,367,084
16096
Jefferson
DEXTER VILLAGE / Dexter
(V)
New Storage, Upgrade Distribution System
1,100
$757,125
40
$1,196,124,209
17465
Jefferson
HIGHWAY GARAGE WD /
Hounsfield (T)
Upgrade Distribution System
200
$3,035,853
35
$1,199,160,062
16256
Jefferson
PHILADELPHIA VILLAGE /
Philadelphia (V)
Upgrade Distribution System
1,800
$257,440
35
$1,199,417,502
15309
Jefferson
WATERTOWN, CITY OF /
Watertown (C)
Upgrade Distribution System
27,861
$152,955
35
$1,199,570,457
15789
Jefferson
CHAUMONT VILLAGE /
Chaumont (V)
Upgrade Storage, Upgrade Distribution System
625
$178,961
30
$1,199,749,418
17585
Jefferson
CLAYTON VILLAGE /
Clayton (V)
Upgrade Distribution System
2,100
$551,000
30
$1,200,300,418
15893
Jefferson
ADAMS (T) WD #1 & 2
(ADAMS CENTER) / Adams
Center (T)
Upgrade Storage
1,000
$121,954
25
$1,200,422,372
17308
Jefferson
BROWNVILLE VILLAGE /
Brownville (V)
Upgrade Distribution System
1,200
$574,000
25
$1,200,996,372
16481
Jefferson
VILLAGE OF CLAYTON /
Clayton (V)
New Transmission, New Distribution System
2,160
$214,000
25
$1,201,210,372
17961
Jefferson
LAFARGEVILLE (T.
ORLEANS) / Orleans (T)
Installation of water meters.,
750
$208,078
25
$1,201,418,450
Page 26 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Jefferson County
17802
Jefferson
MADISON BARRACKS
WATER SYSTEM / Sackets
Harbor (V)
Upgrade Distribution System
16549
Jefferson
NORTHLAND ESTATES /
Northland Park Inc.
17464
Jefferson
18021
Jefferson
1,000
$1,700,000
20
$1,203,118,450
New Storage
540
$82,416
20
$1,203,200,866
ROUTE 12F WD /
Hounsfield (T)
Upgrade Distribution System
144
$5,406,750
15
$1,208,607,616
WATER DISTRICT #3 /
Ellisburg (T)
Serve private contaminated/poor yielding wells., Extend Distribution
System
200
$9,000,000
15
$1,217,607,616
240
$507,000
65
$1,218,114,616
1,500
$12,389,600
60
$1,230,504,216
Lewis County
17826
Lewis
WATER DISTRICT NO. 10 /
Lowville (T)
New Distribution System
17927
Lewis
CONSOLIDATED WATER
DISTRICT / Watson (T)
New Ground Water Source, New Storage, Extend Distribution System
16482
Lewis
PORT LEYDEN VILLAGE /
Port Leyden (V)
Upgrade Distribution System
820
$910,000
30
$1,231,414,216
16667
Lewis
TURIN VILLAGE / Turin (V)
Upgrade Distribution System
350
$611,588
25
$1,232,025,804
16683
Lewis
CONSTABLEVILLE
VILLAGE / Constableville
(V)
Upgrade Transmission
310
$1,274,936
20
$1,233,300,740
18020
Lewis
WATER DISTRICT #1 /
Denmark (T)
Serve private contaminated/poor yielding wells., Extend Distribution
System
275
$2,603,000
15
$1,235,903,740
7,600
$813,000
135
$1,236,716,740
Livingston County
17619
Livingston
GENESEO VILLAGE /
LCWSA
New Surface Water Treatment Rule Compliance Facility
17317
Livingston
LIVINGSTON COUNTY
WATER DISTRICT NO . 2 /
Livingston County
Extend Distribution System, System Consolidation
835
$3,200,000
80
$1,239,916,740
17182
Livingston
TOWN OF MOUNT
MORRIS / Mount Morris (T)
Route 408 into Tuscarora., Extend Distribution System
700
$5,824,804
65
$1,245,741,544
15322
Livingston
TOWN OF MT. MORRIS /
Mount Morris (T)
Extend Distribution System
100
$1,574,600
60
$1,247,316,144
15706
Livingston
LIVINGSTON COUNTY
WATER DISTRICT /
Livingston County
Extend water system along swamp road in (T) Conesus to Hamlet of
Scottsburg in (T) Sparta., Extend Distribution System
250
$1,627,400
60
$1,248,943,544
15697
Livingston
LIVINGSTON COUNTY
WATER DISTRICT /
Livingston County
Hamlet of Conesus., Extend Distribution System
230
$1,326,575
55
$1,250,270,119
15613
Livingston
YORK (T) WD NO. 2 / York
(T)
Extend Distribution System
350
$526,330
55
$1,250,796,449
17895
Livingston
LONG POINT ROAD WD /
Geneseo(T)
Extend Water District
100
$1,115,000
50
$1,251,911,449
17897
Livingston
LIMA/NORTH/ELM ROADS
WD / Geneseo (T)
New Distribution System
500
$2,920,000
50
$1,254,831,449
Page 27 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Livingston County
15693
Livingston
LIVINGSTON COUNTY
WATER DISTRICT /
Livingston County
East Lake Rd. in (T) of Conesus., Extend Distribution System
15604
Livingston
COWAN ROAD WATER
DISTRICT / York (T)
15308
Livingston
15154
1,200
$2,306,055
45
$1,257,137,504
Extend Distribution System
120
$885,548
45
$1,258,023,052
EAST LAKE ROAD WATER
DISTRICT / Livonia (T)
Extend Distribution System
1,450
$2,093,140
40
$1,260,116,192
Livingston
NUNDA VILLAGE / Nunda
(V)
Upgrade Ground Water Source, New Transmission
2,000
$640,155
25
$1,260,756,347
16678
Livingston
AVON VILLAGE PWS /
Avon (V)
Upgrade Transmission
2,993
$1,442,000
25
$1,262,198,347
16584
Livingston
GENESEO (T) WD #1 /
Geneseo (T)
New Storage, Upgrade Distribution System
215
$819,000
25
$1,263,017,347
16585
Livingston
GENESEO (T) WD #2 /
Geneseo (T)
New Storage, Upgrade Distribution System
436
$1,377,000
25
$1,264,394,347
16961
Livingston
AVON TOWN WATER
DISTRICT / Avon (T)
Airport Tank to Village of Avon Water Treatment Plant., New
Transmission
3,000
$593,048
20
$1,264,987,395
16689
Livingston
GROVELAND STATION
WATER CO / Groveland
Station Water Corp.
New Ground Water Source
680
$93,730
20
$1,265,081,125
16972
Livingston
AVON TOWN WATER
DISTRICT / Avon (T)
Poplar Hill Road to Bronson Hill Road., New Transmission
3,000
$1,322,712
20
$1,266,403,837
16974
Livingston
AVON TOWN WATER
DISTRICT / Avon (T)
Lima Town Line Storage Tank Cleaning and Repair., Upgrade Storage
3,000
$132,098
15
$1,266,535,935
16973
Livingston
AVON TOWN WATER
DISTRICT / Avon (T)
Route 5&20 Storage Tank Cleaning and Repair., Upgrade Storage
3,000
$139,050
15
$1,266,674,985
16964
Livingston
AVON TOWN WATER
DISTRICT / Avon (T)
Fowlerville Road watermain., New Transmission
3,000
$354,577
15
$1,267,029,562
16958
Livingston
AVON TOWN WATER
DISTRICT / Avon (T)
Agar Road watermain., New Transmission
3,000
$198,842
15
$1,267,228,404
16971
Livingston
AVON TOWN WATER
DISTRICT / Avon (T)
Henty Road Watermain., New Transmission
3,000
$396,988
15
$1,267,625,392
16962
Livingston
AVON TOWN WATER
DISTRICT / Avon (T)
Paper Mill Road., New Transmission
3,000
$757,822
15
$1,268,383,214
17257
Livingston
CALEDONIA VILLAGE /
Caledonia (V)
State Street watermain replacement., Upgrade Transmission
2,510
$528,678
15
$1,268,911,892
16975
Livingston
AVON TOWN WATER
DISTRICT / Avon (T)
Telemetry System., Upgrade Storage
3,000
$243,338
10
$1,269,155,230
16970
Livingston
AVON TOWN WATER
DISTRICT / Avon (T)
Jones Lane/Darby Road., Upgrade Distribution System
3,000
$356,315
10
$1,269,511,545
16968
Livingston
AVON TOWN WATER
DISTRICT / Avon (T)
Genesee Street and Lake Road PRV Station., New Distribution
System
3,000
$18,077
10
$1,269,529,622
Page 28 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Livingston County
16965
Livingston
AVON TOWN WATER
DISTRICT / Avon (T)
Pole Bridge Road., Upgrade Distribution System
3,000
$245,840
10
$1,269,775,462
15131
Livingston
LIVONIA VILLAGE / Livonia
(V)
Upgrade Distribution System
1,360
$1,105,325
10
$1,270,880,787
16967
Livingston
AVON TOWN WATER
DISTRICT / Avon (T)
Lakeville Road PRV Station., New Distribution System
3,000
$111,240
10
$1,270,992,027
450
$103,500
135
$1,271,095,527
2,456
$1,300,000
95
$1,272,395,527
56
$424,923
85
$1,272,820,450
210
$1,192,230
70
$1,274,012,680
12,000
$350,000
65
$1,274,362,680
750
$5,000,000
65
$1,279,362,680
75
$225,000
65
$1,279,587,680
12,000
$1,600,000
60
$1,281,187,680
600
$2,275,000
55
$1,283,462,680
3,904
$4,100,000
50
$1,287,562,680
Madison County
16705
Madison
MADISON VILLAGE /
Madison (V)
New Ground Water Source, Upgrade Distribution System
16654
Madison
MORRISVILLE VILLAGE /
Morrisville (V)
To provide adequate pressure, Upgrade Distribution System
17360
Madison
NEW BOSTON ROAD
WATER DISTRICT / Lenox
(T)
New System Consolidation, New Water District
17359
Madison
LEWIS POINT/PINE RIDGE
ROAD / Lenox (T)
New Water District
16410
Madison
ONEIDA CITY / Oneida (C)
Extend Distribution System
17935
Madison
LENOX (T) / Lenox (T)
Water District No. 12., New Water District
17278
Madison
MOUNT PLEASANT
(CAZ.CNTRY EST) /
Cazenovia (T)
Upgrade Ground Water Source, Upgrade Storage
16408
Madison
ONEIDA CITY / Oneida (C)
New Distribution System
17415
Madison
STOCKBRIDGE WATER
DISTRICT / Stockbridge (T)
Extend Distribution System
18069
Madison
HAMILTON VILLAGE /
Hamilton (V)
New Ground Water Source, Upgrade Distribution System
16404
Madison
ONEIDA CITY / Oneida (C)
Replace lead water lines., Upgrade Distribution System
12,000
$400,000
50
$1,287,962,680
16407
Madison
ONEIDA CITY / Oneida (C)
construct 300,000 water storage tank., New Storage
12,000
$750,000
40
$1,288,712,680
17286
Madison
COBBLEFIELD /
WELLINGTON ESTATES
W.D. / Cazenovia (T)
Upgrade Water Treatment Plant
120
$225,000
30
$1,288,937,680
15268
Madison
EARLVILLE VILLAGE /
Earlville (V)
East Main Street., Upgrade Distribution System
790
$96,509
25
$1,289,034,189
15156
Madison
EARLVILLE VILLAGE /
Earlville (V)
Upgrade Distribution System
790
$665,020
25
$1,289,699,209
16708
Madison
O-WE-RA POINT WATER
SUPPLY / Owera Water
Works Trans. Corp.
Upgrade Distribution System
100
$21,000
15
$1,289,720,209
Page 29 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Monroe County
16325
Monroe
MCWA EASTSIDE WTP /
MCWA
Eastside Water Supply Project Regional Water Treatment Plant Phase
3, Construction of WTP., New Water Treatment Plant
222,503
$60,000,000
100
$1,349,720,209
16324
Monroe
MCWA EASTSIDE WTP /
MCWA
Eastside Water Supply Project Regional Water Treatment Plant Phase
2, Raw Water Pump Station, New Water Treatment Plant, New Pump
Station
222,503
$15,000,000
100
$1,364,720,209
16326
Monroe
MCWA EASTSIDE WTP /
MCWA
Eastside Water Supply Project Regional Water Treatment Plant Phase
4, Raw Water Transmission Main & Backwash Return Line, New
Water Treatment Plant, New Transmission
222,503
$16,000,000
100
$1,380,720,209
16323
Monroe
MCWA EASTSIDE WTP /
MCWA
Eastside WTP Phase 1, Raw Water Intake System and a portion of
Phase 5 finished water transmission main work, New Surface Water
Source, New Transmission
222,503
$0
100
$1,380,720,209
16327
Monroe
MCWA EASTSIDE WTP /
MCWA
Eastside Water Supply Project Regional Water Treatment Plant Phase
5, Finished Water Transmission Mains, New Water Treatment Plant,
New Transmission
222,503
$28,000,000
100
$1,408,720,209
17155
Monroe
ROCHESTER CITY /
Rochester (C)
2006 Watermain Extensions and Improvements., Upgrade Distribution
System
214,000
$1,261,000
75
$1,409,981,209
17153
Monroe
ROCHESTER CITY /
Rochester (C)
2004 Watermain Extensions and Improvements., Upgrade Distribution
System
214,000
$1,219,000
75
$1,411,200,209
16879
Monroe
ROCHESTER CITY /
Rochester (C)
2003 Watermain Extensions and Improvements., Upgrade Distribution
System
214,000
$1,348,000
75
$1,412,548,209
17154
Monroe
ROCHESTER CITY /
Rochester (C)
2005 Watermain Extensions and Improvements., Upgrade Distribution
System
214,000
$1,240,000
75
$1,413,788,209
17812
Monroe
ROCHESTER CITY /
Rochester (C)
Upgrade Storage
214,000
$11,900,000
65
$1,425,688,209
16328
Monroe
MCWA SHOREMONT
WTP / Monroe Co. Water
Authority
Upgrade Surface Water Source
310,000
$1,854,000
55
$1,427,542,209
17721
Monroe
MCWA RIGA WD / Riga
(T)
New Distribution System
25
$4,500,000
55
$1,432,042,209
16884
Monroe
SOUTH CHILI WATER IMP.
BENEFIT AREA NO. 2 /
Chili (T)
Extend Distribution System
100
$386,250
45
$1,432,428,459
16333
Monroe
MCWA MENDON WD /
Monroe Co. Water Authority
Boughton Hill Road., Extend Distribution System
25
$1,085,842
45
$1,433,514,301
16331
Monroe
MCWA MENDON WD /
MCWA/Mendon (T)
Mendon-Ionia Road., Extend Distribution System
25
$342,580
45
$1,433,856,881
16332
Monroe
MCWA MENDON WD /
MCWA/Mendon (T)
Parrish Road., Extend Distribution System
25
$745,662
45
$1,434,602,543
15759
Monroe
MCWA MENDON WD /
MCWA/ Mendon (T)
Semmel Road water main., Extend Distribution System
25
$267,615
40
$1,434,870,157
15035
Monroe
MCWA RIGA WD /
MCWA/Riga (T)
Route 36 - Sanford Road., Extend Distribution System
25
$221,610
40
$1,435,091,767
15198
Monroe
ROCHESTER CITY /
Rochester (C)
Water Main Extensions and Improvements., Upgrade Transmission
214,000
$1,946,200
40
$1,437,037,967
15659
Monroe
MONROE CO. WATER
AUTHORITY / Wheatland
(T)
Wheatland Center Road water extension to Blue Pond and South
Road., Extend Distribution System
250
$1,252,600
40
$1,438,290,567
Page 30 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Monroe County
15623
Monroe
HAMLIN CONSOLIDATED
WATER DIST / Hamlin (T)
Walker - Lake Ontario Road., Extend Distribution System
10,000
$378,657
40
$1,438,669,224
15620
Monroe
HAMLIN CONSOLIDATED
WATER DIST / Hamlin (T)
Route 18., Extend Distribution System
10,000
$876,742
40
$1,439,545,966
16738
Monroe
SPRUCE LANE WATER
DISTRICT / Pittsford (T)
Upgrade Distribution System
30
$60,770
40
$1,439,606,736
16603
Monroe
MCWA MENDON WD /
Mendon (T)
Rte. 251-Rush/Mendon Road., Extend Distribution System
25
$159,650
40
$1,439,766,386
17810
Monroe
ROCHESTER CITY /
Rochester (C)
Upgrade Storage
214,000
$7,025,000
40
$1,446,791,386
15037
Monroe
MCWA RIGA WD /
MCWA/Riga (T)
Betteridge-Griffin Roads., Extend Distribution System
25
$199,893
40
$1,446,991,279
16605
Monroe
MCWA MENDON WD /
Mendon (T)
Main Street Fishers and Mile Square Rd., Extend Distribution System
25
$148,686
40
$1,447,139,965
15148
Monroe
OGDEN (T) / Ogden (T)
Extend Distribution System
171
$429,330
40
$1,447,569,295
17813
Monroe
ROCHESTER CITY /
Rochester (C)
New Other Expenses, New Other (OT)
214,000
$10,090,000
40
$1,457,659,295
16330
Monroe
MCWA SHOREMONT
WTP / Monroe Co. Water
Authority
System Consolidation
310,000
$1,772,057
40
$1,459,431,352
17809
Monroe
ROCHESTER CITY /
Rochester (C)
Upgrade Transmission
214,000
$5,800,000
35
$1,465,231,352
17805
Monroe
ROCHESTER CITY /
Rochester (C)
Upgrade Distribution System
214,000
$1,660,000
35
$1,466,891,352
17808
Monroe
ROCHESTER CITY /
Rochester (C)
Upgrade Distribution System
214,000
$2,040,000
35
$1,468,931,352
17806
Monroe
ROCHESTER CITY /
Rochester (C)
Upgrade Distribution System
214,000
$509,500
35
$1,469,440,852
17542
Monroe
WEBSTER VILLAGE /
Webster (V)
Upgrade Storage
7,500
$400,826
25
$1,469,841,678
17878
Monroe
SWEDEN (T) / MCWA
New Transmission, New Storage
4,400
$4,672,000
20
$1,474,513,678
17881
Monroe
WEBSTER (T) / MCWA
replace 5000 lf of main in Hard Road, Upgrade Distribution System
2,400
$810,170
20
$1,475,323,848
16777
Monroe
HENRIETTA WD #1 /
Henrietta (T)
RIT Backflow Prevention Project., Upgrade Distribution System
36,400
$360,500
15
$1,475,684,348
17216
Monroe
FAIRPORT VILLAGE /
Fairport (V)
Replace distribution main on South Avenue., Upgrade Distribution
System
9,800
$86,310
10
$1,475,770,658
17871
Monroe
BRIGHTON (T) / MCWA
main replacement on Howard Ave, Summitt Dr, Edgeview La, Holyvale
Dr., and Lynwood Dr, Upgrade Distribution System
750
$920,100
10
$1,476,690,758
Page 31 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Monroe County
17880
Monroe
PENFIELD (T) / MCWA
Replace 3900 lf main on Five mile Line Rd., Upgrade Distribution
System
17874
Monroe
GATES (T)& PERITON (T) /
MCWA
Pipe Bridge Rehabilitation Cairn St in Gates & Marsh Rd. in Periton,
Upgrade Distribution System
17879
Monroe
FAIRPORT (V) / MCWA
Replacement 2650 lf main on Summit St., Upgrade Distribution
System
17873
Monroe
BERGEN (V) &
IRONDEQUOIT (T) / MCWA
17877
Monroe
PITTSFORD (T) &
BRIGHTON (T) / MCWA
17875
Monroe
Cement line 23,470 lf mains in (T)'s Pittsford & Brighton & (V) E.
PITTSFORD & BRIGHTON
(T)'S & E. ROCHESTER(V) / Rochester, Upgrade Distribution System
MCWA
17876
Monroe
PERINTON (T) &
FAIRPORT (V) / MCWA
Main replacement Creekside Rd., Potter Pl, Lewis St, E. Church St in
Perinton (T) & Fairport (V), Upgrade Distribution System
17767
Monroe
SHOEMAKER WD EXT. #5
/ Webster (T)
17763
Monroe
600
$607,600
10
$1,477,298,358
90,000
$434,678
10
$1,477,733,036
300
$492,500
10
$1,478,225,536
Cement lining 23,300 lf water main Bergen (V) & Irondequoit (T),
Upgrade Distribution System
3,700
$1,647,500
10
$1,479,873,036
Main replacement Clover Street in Pittsford (T) & Brighton (T),
Upgrade Distribution System
3,300
$739,200
10
$1,480,612,236
12,000
$1,490,455
10
$1,482,102,691
1,500
$668,200
10
$1,482,770,891
New Distribution System
18
$56,000
5
$1,482,826,891
KLEM ROAD WD / Webster
(T)
New Distribution System
25
$200,000
5
$1,483,026,891
20,700
$737,000
220
$1,483,763,891
2,400
$1,565,600
150
$1,485,329,491
Montgomery County
17497
Montgomery
AMSTERDAM (C) /
Amsterdam (C)
Upgrade Surface Water Treatment Rule Compliance Facility, Upgrade
Water Treatment Plant, Upgrade Water Treatment Plant, Upgrade
Water Treatment Plant
17469
Montgomery
FORT PLAIN (V) WATER
WORKS / Fort Plain (V)
Upgrade Water Treatment Plant, Upgrade Ground Water Source,
Upgrade Storage, Upgrade Distribution System
16765
Montgomery
PALATINE WATER
DISTRICT / Palatine (T)
Creation of a water quality treatment district and provision of filtration.,
New Water District
108
$167,000
130
$1,485,496,491
18051
Montgomery
FULTONVILLE VILLAGE
PWS / Fultonville (V)
Upgrade Water Treatment Plant, Upgrade Ground Water Source,
Upgrade Distribution System
740
$1,262,150
80
$1,486,758,641
17610
Montgomery
AMSTERDAM (T) /
Amsterdam(T)
New Storage, New Pump Station, Extend Distribution System
400
$4,506,250
65
$1,491,264,891
15040
Montgomery
PALATINE BRIDGE (V)
WATER WORKS /
Palantine Bridge (V)
Upgrade Water Treatment Plant, Upgrade Ground Water Source,
Upgrade Distribution System
890
$985,750
65
$1,492,250,641
16272
Montgomery
VILLAGE OF FORT
JOHNSON / Fort Johnson
(V)
Extend Distribution System
671
$2,905,751
55
$1,495,156,392
15276
Montgomery
GLEN (T) W.D.#1 / Glen (T)
Extend Distribution System
5,000
$950,000
45
$1,496,106,392
17953
Montgomery
NELLISTON VILLAGE /
Nelliston (V)
New Storage, Upgrade Distribution System
375
$4,493,000
45
$1,500,599,392
16919
Montgomery
CANAJOHARIE (V) WATER
WORKS / Canajoharie (V)
Upgrade Distribution System
2,300
$453,948
35
$1,501,053,340
17751
Montgomery
AMSTERDAM (C) /
Amsterdam (C)
Phase II - Install approximately 6 miles of new water distribution main.,
Upgrade Distribution System
20,700
$5,159,682
35
$1,506,213,022
Page 32 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Montgomery County
17750
Montgomery
AMSTERDAM (C) /
Amsterdam (C)
Phase I - Install approximately 6 miles of new distribution water main
and 30 new hydrants., Upgrade Distribution System
20,700
$5,276,948
35
$1,511,489,970
17752
Montgomery
AMSTERDAM (C) /
Amsterdam (C)
Replace sections of 14 mile transmission main from Glen Wild
Reservoir to City Water Filtration Plant; install new water valves and air
relief valves., Upgrade Transmission
20,700
$2,060,000
35
$1,513,549,970
15274
Montgomery
GLEN (T) W.D.#2 / Glen (T)
Upgrade Distribution System
7,626
$95,000
15
$1,513,644,970
17634
Montgomery
FLORIDA (T) WATER
DISTRICT / Florida (T)
Extend Distribution System
375
$2,977,442
10
$1,516,622,412
230
$2,021,375
145
$1,518,643,787
Nassau County
17944
Nassau
MILL NECK ESTATES / Mill
Neck Estates Association
Transmission main to connect with Locust Valley WD and upgrade
distribution, Upgrade Distribution System, New Inter-Connection
15048
Nassau
MINEOLA (V) / Mineola (V)
New Water Treatment Plant
20,600
$1,855,238
120
$1,520,499,025
17405
Nassau
PLAINVIEW WD / Oyster
Bay (T)
Airstripper and Ion Exchange at Plant 3, New Water Treatment Plant
35,000
$5,889,600
120
$1,526,388,625
17659
Nassau
HICKSVILLE WD / Hicksville Upgrade Water Treatment Plant
Water District
47,810
$4,326,000
105
$1,530,714,625
16791
Nassau
GLEN COVE CITY / Glen
Cove (C)
GAC treatment for wells 30 and 31 Duck Pond Rd., New Water
Treatment Plant, Upgrade Ground Water Source
28,000
$490,486
85
$1,531,205,111
16789
Nassau
GLEN COVE CITY / Glen
Cove (C)
Seaman Road Well., New Water Treatment Plant, Upgrade Ground
Water Source
28,000
$805,059
85
$1,532,010,170
17900
Nassau
BETHPAGE WD / Bethpage
Water District
Nitrate removal at Plant #1, Upgrade Water Treatment Plant
33,000
$4,271,616
80
$1,536,281,786
17406
Nassau
PLAINVIEW WD / Oyster
Bay (T)
Ion exchange treatment at Plant 4., Upgrade Water Treatment Plant
35,000
$3,667,600
80
$1,539,949,386
17699
Nassau
GARDEN CITY (V) / Village
of Garden City
New Water Treatment Plant, Upgrade Pump Station
25,000
$2,221,556
80
$1,542,170,942
15678
Nassau
MANHASSET LAKEVILLE
WD / North Hempstead (T)
Install carbon absorption system at Eden Well, New Water Treatment
Plant
43,000
$477,920
70
$1,542,648,862
15675
Nassau
MANHASSET LAKEVILLE
WD / North Hempstead (T)
Campbell Station, New Water Treatment Plant
43,000
$5,974,000
70
$1,548,622,862
17902
Nassau
BETHPAGE WD / Bethpage
Water District
VOC removal at Plant #6, Upgrade Water Treatment Plant
33,000
$2,409,376
70
$1,551,032,238
17942
Nassau
WATER AUTHORITY OF
WESTERN NASSAU CO. /
Water Auth of Western
Nassau
VOC treatment at Wells 15A & !5B, Upgrade Water Treatment Plant
20,000
$2,817,050
70
$1,553,849,288
17702
Nassau
GARDEN CITY (V) / Village
of Garden City
VOC Removal at Hilton Park Plant (Wells 15 and 16), New Water
Treatment Plant
25,000
$2,580,150
70
$1,556,429,438
17911
Nassau
WA OF GREAT NECK
NORTH / Water Auth of
Great Neck North
VOC treatment at Well #6, Upgrade Water Treatment Plant
31,400
$1,400,000
70
$1,557,829,438
16423
Nassau
MASSAPEQUA WD / Oyster Wells #1, 2R, 3, 8, New Water Treatment Plant
Bay (T)
43,000
$2,895,330
70
$1,560,724,768
Page 33 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Nassau County
16411
Nassau
GLEN COVE CITY / Glen
Cove (C)
New Water Treatment Plant
28,000
$2,100,000
70
$1,562,824,768
17404
Nassau
PLAINVIEW WD / Oyster
Bay (T)
New air stripper at Plant 7, New Water Treatment Plant
35,000
$1,287,500
70
$1,564,112,268
17408
Nassau
PLAINVIEW WD / Oyster
Bay (T)
Air stripper at Plant 1, New Water Treatment Plant
35,000
$6,759,000
70
$1,570,871,268
17901
Nassau
BETHPAGE WD / Bethpage
Water District
VOC removal at Plant # 4, Upgrade Water Treatment Plant
33,000
$4,056,717
70
$1,574,927,985
17657
Nassau
HICKSVILLE WD / Hicksville Reactivation of Plant No. 3, Upgrade Water Treatment Plant
Water District
47,810
$5,459,000
65
$1,580,386,985
17662
Nassau
MANHASSET LAKEVILLE
WD / Manhasset-Lakeville
WD
43,000
$3,409,300
65
$1,583,796,285
17656
Nassau
HICKSVILLE WD / Hicksville Nitrate Treatment at Plant No.1, Upgrade Water Treatment Plant
Water District
47,810
$4,017,000
65
$1,587,813,285
17655
Nassau
HICKSVILLE WD / Hicksville Nitrate Treatment at Plant No. 8, Upgrade Water Treatment Plant
Water District
47,810
$3,144,322
65
$1,590,957,607
17037
Nassau
EAST WILLISTON (V) /
East Williston (V)
Replacement of lead service lines to about 120 residences, New Other
Expenses, New Other (OT)
2,503
$456,000
60
$1,591,413,607
17271
Nassau
ALBERTSON WD / North
Hempstead (T)
New treatment plant, rehab control building, chemical containment,
instrumentation, transmission lines and booster pump, New Water
Treatment Plant
13,500
$3,613,900
60
$1,595,027,507
15213
Nassau
WESTBURY WD /
Westbury W.D.
New Water Treatment Plant
20,500
$4,120,000
60
$1,599,147,507
16267
Nassau
HEMPSTEAD (V) /
Hempstead (V)
Upgrade Storage
56,000
$5,483,200
60
$1,604,630,707
16456
Nassau
EAST MEADOW WD /
Hempstead (T)
New Ground Water Source, Upgrade Distribution System
46,950
$3,100,000
55
$1,607,730,707
17859
Nassau
JERICHO WD / Oyster Bay
(T)
VOC treatment and rehabilitation of pump station # 5 at District office.,
Upgrade Water Treatment Plant, Upgrade Storage
58,000
$1,040,000
55
$1,608,770,707
17660
Nassau
HICKSVILLE WD / Hicksville Upgrade Water Treatment Plant
Water District
47,810
$2,472,000
55
$1,611,242,707
17719
Nassau
PORT WASHINGTON WD /
Port Washington Water
District
34,000
$2,586,330
55
$1,613,829,037
17658
Nassau
HICKSVILLE WD / Hicksville VOC treatment at Plant No. 5, Upgrade Water Treatment Plant
Water District
47,810
$4,429,000
55
$1,618,258,037
15335
Nassau
SOUTH FARMINGDALE
WD / South Farmingdale
W.D.
Iron Removal at Plants 5 & 6, Upgrade Water Treatment Plant
44,700
$2,369,000
50
$1,620,627,037
16760
Nassau
ROCKVILLE CENTRE (V) /
Rockville (V)
Design & construction new iron filtration facility at wellfield # 1,
southside high school, iron removing plant, New Water Treatment
Plant
24,700
$3,012,750
50
$1,623,639,787
16627
Nassau
CARLE PLACE WD / Carle
Place WD
Wells #3 & #4, Terrace Drive, Carle Place, NY, New Water Treatment
Plant
9,005
$1,510,800
50
$1,625,150,587
Page 34 of 86
Nitrate Removal Searingtown Station, Upgrade Water Treatment Plant
Nitrate Removal at Well No.4, New Water Treatment Plant
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Nassau County
15046
Nassau
MINEOLA (V) / Mineola (V)
New Water Treatment Plant
20,600
$846,248
50
$1,625,996,835
17410
Nassau
PLAINVIEW WD / Oyster
Bay (T)
Upgrade booster pump at Plant 6 and new well at Plant 7, New Ground
Water Source, Upgrade Pump Station
35,000
$2,206,200
50
$1,628,203,035
17995
Nassau
WA OF WESTERN
NASSAU CO / WA of
Western Nassau County
VOC removal at Wells 15C and 15E in Elmont, Upgrade Water
Treatment Plant
20,000
$109,200
45
$1,628,312,235
17862
Nassau
JERICHO WD / Oyster Bay
(T)
New well at Well #28 site., New Ground Water Source
58,000
$2,150,000
45
$1,630,462,235
17865
Nassau
MINEOLA (V) / Mineola (V)
VOC removal at Elm Place Well #1., New Water Treatment Plant
20,600
$2,352,900
45
$1,632,815,135
17860
Nassau
JERICHO WD / Oyster Bay
(T)
VOC treatment at Kirby Lane., Upgrade Water Treatment Plant
58,000
$2,215,000
45
$1,635,030,135
17861
Nassau
JERICHO WD / Oyster Bay
(T)
VOC treatment at Well #9., Upgrade Water Treatment Plant
58,000
$730,000
45
$1,635,760,135
17904
Nassau
BETHPAGE WD / Bethpage
Water District
Water District plant control and monitoring system upgrade(SCADA),
Upgrade Other Expenses, Upgrade Other (OT)
33,000
$3,355,328
45
$1,639,115,463
17914
Nassau
WA OF GREAT NECK
NORTH / Water Auth of
Great Neck North
Contruction of new Well #14 at Community Drive, New Ground Water
Source
31,400
$2,000,000
45
$1,641,115,463
17409
Nassau
PLAINVIEW WD / Oyster
Bay (T)
Air stripper at Plant 2, New Water Treatment Plant
35,000
$4,403,400
40
$1,645,518,863
15369
Nassau
WA OF GREAT NECK
NORTH / Water Auth. of
Great Neck No.
2 new well sources, New Ground Water Source
31,400
$6,118,000
40
$1,651,636,863
17318
Nassau
AQUA NY OF SEA CLIFF /
Sea Cliff Water Company
New Storage
15,000
$1,371,000
40
$1,653,007,863
16429
Nassau
MASSAPEQUA WD / Oyster Proposed New Well No 9, New Ground Water Source
Bay (T)
43,000
$1,588,650
25
$1,654,596,513
16630
Nassau
CARLE PLACE WD / Carle
Place WD
Old Country Road, Carle Place, NY, New Storage
9,005
$1,778,200
20
$1,656,374,713
15668
Nassau
MANHASSET LAKEVILLE
WD / North Hempstead (T)
Replace aged and/or undersized mains, Upgrade Distribution System
43,000
$716,880
20
$1,657,091,593
15281
Nassau
ALBERTSON WD / North
Hempstead (T)
Well #4 Replacement of Screen and Well Pump, Upgrade Ground
Water Source
13,500
$188,044
20
$1,657,279,637
17583
Nassau
OYSTER BAY WD / Oyster
Bay (T)
VOC removal at Plant #2., New Water Treatment Plant
8,700
$1,597,530
20
$1,658,877,167
16385
Nassau
HEMPSTEAD (V) /
Hempstead (V)
Upgrade Ground Water Source
56,000
$4,715,340
20
$1,663,592,507
17785
Nassau
LONG ISLAND AMERICAN
WATER CORP / Long
Island American Water
Plant No. 8 Iron Removal, New Water Treatment Plant
230,300
$7,100,000
20
$1,670,692,507
17343
Nassau
WILLISTON PARK (V) /
Williston Park (V)
Replace underground fuel tank, Emergency power Well#4, New Other
Expenses, New Other (OT)
7,516
$415,605
20
$1,671,108,112
Page 35 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Nassau County
15377
Nassau
WA OF GREAT NECK
NORTH / Water Auth. of
Great Neck No.
Water Mill Lane, New Storage, New Pump Station
17706
Nassau
WA OF WESTERN
NASSAU / Water Authority
Western Nassau
Upgrade Transmission
15672
Nassau
MANHASSET LAKEVILLE
WD / North Hempstead (T)
15384
Nassau
15676
31,400
$2,567,000
15
$1,673,675,112
2,000
$109,200
15
$1,673,784,312
Install new water mains to eliminate dead ends, Upgrade Distribution
System
43,000
$1,075,320
15
$1,674,859,632
ROCKVILLE CENTRE (V) /
Rockville Centre (V)
Rehab tank #3, Upgrade Storage
24,700
$911,550
15
$1,675,771,182
Nassau
ROSLYN WD / North
Hempstead (T)
Roslyn Estate Pressure Zone, New Pump Station
17,000
$852,135
15
$1,676,623,317
15663
Nassau
ROSLYN WD / North
Hempstead (T)
Convert Well #3 DWTP to water lubrication, Upgrade Ground Water
Source
17,000
$79,725
15
$1,676,703,042
15378
Nassau
ROCKVILLE CENTRE (V) /
Rockville Centre (V)
Rehab well 2c, Upgrade Ground Water Source
24,700
$257,500
15
$1,676,960,542
15383
Nassau
WA OF GREAT NECK
NORTH / Water Auth. of
Great Neck No.
0.5 MG storage tank, New Storage
31,400
$1,566,500
15
$1,678,527,042
15340
Nassau
SOUTH FARMINGDALE
WD / South Farmingdale
W.D.
Well Rehabilitation & Well Pump/Motor Replacement-Various well
sites, Upgrade Ground Water Source
44,700
$597,000
15
$1,679,124,042
15628
Nassau
MANHASSET LAKEVILLE
WD / North Hempstead (T)
Replace 4 inch mains, Upgrade Distribution System
43,000
$1,075,320
15
$1,680,199,362
15262
Nassau
PLAINVIEW WD / Oyster
Bay (T)
Repair 1.5 MG ground storage tank at Plant 4, Upgrade Storage
35,000
$258,694
15
$1,680,458,056
18032
Nassau
PORT WASHINGTON WD /
Port Washington Water
District
Upgrade Ground Water Source
34,000
$104,300
15
$1,680,562,356
17996
Nassau
WA OF WESTERN
NASSAU CO / WA of
Western Nassau County
Iron removal at Wells 28A and 28B in Elmont, Upgrade Water
Treatment Plant
10,000
$4,429,000
15
$1,684,991,356
17997
Nassau
WA OF WESTERN
NASSAU CO / WA of
Western Nassau County
Iron removal at Well 30 in Franklin Square, Upgrade Water Treatment
Plant
10,000
$2,240,250
15
$1,687,231,606
15380
Nassau
ROCKVILLE CENTRE (V) /
Rockville Centre (V)
Rehab well 4c, Upgrade Ground Water Source
24,700
$257,500
15
$1,687,489,106
15041
Nassau
MINEOLA (V) / Mineola (V)
Upgrade Water Treatment Plant
20,600
$278,409
15
$1,687,767,515
15682
Nassau
MANHASSET LAKEVILLE
WD / North Hempstead (T)
New transmission from wells to the Campbell treatment facility, New
Transmission
43,000
$836,360
15
$1,688,603,875
17786
Nassau
LONG ISLAND AMERICAN
WATER CORP / Long
Island American Water
Water main replacements, Upgrade Distribution System
230,300
$10,900,000
15
$1,699,503,875
16433
Nassau
MASSAPEQUA WD / Oyster Replacement of asbestos cement water mains, Upgrade Distribution
System
Bay (T)
43,000
$1,353,111
15
$1,700,856,986
15261
Nassau
PLAINVIEW WD / Oyster
Bay (T)
Upgrade Water Treatment Plant
35,000
$2,465,614
15
$1,703,322,600
Page 36 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Nassau County
15374
Nassau
ROCKVILLE CENTRE (V) /
Rockville Centre (V)
Rehab well 3a, Upgrade Ground Water Source
24,700
$290,975
15
$1,703,613,575
17913
Nassau
WA OF GREAT NECK
NORTH / Water Auth of
Great Neck North
Replacement of Waybridge Road storage tank,
31,400
$1,545,000
15
$1,705,158,575
15373
Nassau
WA OF GREAT NECK
NORTH / Water Auth. of
Great Neck No.
Construction of a replacement well for well no. 2, Upgrade Ground
Water Source
31,400
$292,600
15
$1,705,451,175
15363
Nassau
ROCKVILLE CENTRE (V) /
Rockville Centre (V)
Rehab. Tank #1, Upgrade Storage
24,700
$999,100
15
$1,706,450,275
15359
Nassau
ROCKVILLE CENTRE (V) /
Rockville Centre (V)
Rehab. wells 1a & 1b, Upgrade Ground Water Source
24,700
$153,017
15
$1,706,603,292
15257
Nassau
PLAINVIEW WD / Oyster
Bay (T)
Repair 2.0 mg ground storage tank at Plant 5, Upgrade Storage
35,000
$309,834
15
$1,706,913,126
15356
Nassau
ROCKVILLE CENTRE (V) /
Rockville Centre (V)
Rehab tank #2, Upgrade Storage
24,700
$1,900,000
15
$1,708,813,126
15351
Nassau
ROCKVILLE CENTRE (V) /
Rockville Centre (V)
Rehab Wells 4a & 4b, Upgrade Ground Water Source
24,700
$600,000
15
$1,709,413,126
17864
Nassau
WEST HEMPSTEAD
WATER DISTRICT / West
Hempstead (T)
Rehabilitation of Birch Street storage tank., Upgrade Storage
32,000
$1,603,710
15
$1,711,016,836
18035
Nassau
PORT WASHINGTON WD /
Port Washington Water
District
New Storage, New Pump Station
34,000
$3,476,250
15
$1,714,493,086
15313
Nassau
ROCKVILLE CENTRE (V) /
Rockville Centre (V)
Tank #4 rehabilitation, Upgrade Storage
24,700
$2,500,000
15
$1,716,993,086
15370
Nassau
ROCKVILLE CENTRE (V) /
Rockville Centre (V)
Rehab well 2b, Upgrade Ground Water Source
24,700
$161,916
15
$1,717,155,002
15673
Nassau
ROSLYN WD / North
Hempstead (T)
Upgrade Water Treatment Plant
17,000
$234,068
15
$1,717,389,070
18034
Nassau
PORT WASHINGTON WD /
Port Washington Water
District
Upgrade Pump Station
34,000
$500,580
15
$1,717,889,650
15366
Nassau
ROCKVILLE CENTRE (V) /
Rockville Centre (V)
Replace treatment pump, Upgrade Water Treatment Plant
24,700
$45,320
15
$1,717,934,970
15285
Nassau
ALBERTSON WD / North
Hempstead (T)
Wells no. 2 & 3 Replacement of screen and well pump, Upgrade
Ground Water Source
13,500
$386,686
15
$1,718,321,656
17698
Nassau
GARDEN CITY (V) / Village
of Garden City
Rehabilitation of Maria Street Tank, Upgrade Storage
25,000
$2,575,000
15
$1,720,896,656
16453
Nassau
GARDEN CITY (V) / Garden
City (V)
New Water Treatment Plant
25,000
$1,601,702
15
$1,722,498,358
15371
Nassau
WA OF GREAT NECK
NORTH / Water Auth. of
Great Neck No.
Construction of a replacement well for well no. 10, Upgrade Ground
Water Source
31,400
$301,200
15
$1,722,799,558
15375
Nassau
WA OF GREAT NECK
NORTH / Water Auth. of
Great Neck No.
Transmission from Weybridge Rd. tank to King Point Rd. and Red
Brook Rd., New Transmission
31,400
$1,934,000
15
$1,724,733,558
Page 37 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Nassau County
16421
Nassau
MASSAPEQUA WD / Oyster Well No 3 Replacement of Screen and Well Pump, Upgrade Ground
Water Source
Bay (T)
15605
Nassau
MANHASSET LAKEVILLE
WD / North Hempstead (T)
Construct a new booster pumping station, New Pump Station
17710
Nassau
OYSTER BAY WD / Oyster
Bay Water District
Rehabilitation of Plant No. 8 Water Storage Tank, Upgrade Storage
15671
Nassau
ROSLYN WD / North
Hempstead (T)
15597
Nassau
17661
43,000
$237,278
15
$1,724,970,836
43,000
$477,920
15
$1,725,448,756
8,700
$1,030,000
15
$1,726,478,756
Upgrade Ground Water Source
17,000
$83,224
15
$1,726,561,980
MANHASSET LAKEVILLE
WD / North Hempstead (T)
Construct new ground level storage tank, New Storage
43,000
$955,840
15
$1,727,517,820
Nassau
MANHASSET LAKEVILLE
WD / Manhasset-Lakeville
WD
Thomaston Tank Rehabilitation, Upgrade Storage
43,000
$3,630,750
15
$1,731,148,570
17711
Nassau
FARMINGDALE (V) / Village
of Farmingdale
Upgrade Storage
8,405
$1,099,010
15
$1,732,247,580
15364
Nassau
ROCKVILLE CENTRE (V) /
Rockville Centre (V)
Rehab. well 4a, Upgrade Ground Water Source
24,700
$337,325
15
$1,732,584,905
15341
Nassau
SOUTH FARMINGDALE
WD / South Farmingdale
W.D.
Filter at Plant 2 Modernization, Upgrade Water Treatment Plant
44,700
$308,000
15
$1,732,892,905
16428
Nassau
MASSAPEQUA WD / Oyster Well No 7 Replacement of screen and well pump, Upgrade Ground
Water Source
Bay (T)
43,000
$335,131
15
$1,733,228,036
16426
Nassau
MASSAPEQUA WD / Oyster Well No 6 Replacement of screen and well pump, Upgrade Ground
Water Source
Bay (T)
43,000
$319,588
15
$1,733,547,624
16417
Nassau
MASSAPEQUA WD / Oyster Well No 1 Replacement of screen and well pump, Upgrade Ground
Water Source
Bay (T)
43,000
$290,769
15
$1,733,838,393
16419
Nassau
SANDS POINT (V) / Sands
Point (V)
Upgrade Ground Water Source, New Ground Water Source
2,800
$1,500,000
15
$1,735,338,393
16458
Nassau
LEVITTOWN WD /
Hempstead (T)
New Ground Water Source, New Transmission
41,800
$4,025,000
15
$1,739,363,393
16425
Nassau
MASSAPEQUA WD / Oyster Well No 4 Replacement of screen and well pump, Upgrade Ground
Water Source
Bay (T)
43,000
$304,906
15
$1,739,668,299
15381
Nassau
WA OF GREAT NECK
NORTH / Water Auth. of
Great Neck No.
Transmission main from the Weybridge Road tank to Oxford
Boulevard, New Transmission
31,400
$431,000
15
$1,740,099,299
17407
Nassau
PLAINVIEW WD / Oyster
Bay (T)
Rehabilitation of Plant 5, Upgrade Water Treatment Plant
35,000
$5,584,500
15
$1,745,683,799
15332
Nassau
SOUTH FARMINGDALE
WD / South Farmingdale
W.D.
Elevated Tank Repairs & Repainting, Upgrade Storage
44,700
$616,000
15
$1,746,299,799
15461
Nassau
PORT WASHINGTON WD /
North Hempstead (T)
New Transmission
34,000
$476,000
15
$1,746,775,799
17344
Nassau
WILLISTON PARK (V) /
Williston Park (V)
Secondary Containment for Caustic Soda, Upgrade Other Expenses,
Upgrade Other (OT)
7,516
$161,350
15
$1,746,937,149
Page 38 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Nassau County
15460
Nassau
PORT WASHINGTON WD /
North Hempstead (T)
Construct New Well #4, Upgrade Ground Water Source
34,000
$1,428,000
15
$1,748,365,149
15452
Nassau
PORT WASHINGTON WD /
Port Washington Water
District
Upgrade Storage
34,000
$2,781,000
15
$1,751,146,149
15939
Nassau
FARMINGDALE (V) /
Farmingdale (V)
Upgrade Water Treatment Plant
8,405
$75,000
15
$1,751,221,149
15459
Nassau
PORT WASHINGTON WD /
North Hempstead (T)
Install new mains to eliminate dead head mains #3, New Distribution
System
34,000
$714,000
10
$1,751,935,149
17782
Nassau
ROCKVILLE CENTRE (V) /
Rockville Center (V)
Water Main Replacement, Upgrade Distribution System
24,700
$1,200,000
10
$1,753,135,149
15456
Nassau
PORT WASHINGTON WD /
North Hempstead (T)
Replace approx. 4000 lf of 4" mains #2, Upgrade Distribution System
34,000
$714,000
10
$1,753,849,149
15376
Nassau
ROCKVILLE CENTRE (V) /
Rockville Centre (V)
Pipeline replacement, Upgrade Distribution System
24,700
$792,588
10
$1,754,641,737
15670
Nassau
ROSLYN WD / North
Hempstead (T)
Upgrade Ground Water Source
17,000
$104,650
10
$1,754,746,387
15642
Nassau
WILLISTON PARK (V) /
Williston Park (V)
Upgrade Ground Water Source
7,516
$800,000
10
$1,755,546,387
15328
Nassau
SOUTH FARMINGDALE
WD / South Farmingdale
W.D.
Caustic Soda Conversion at Plants 1, 5 & 6, Upgrade Water Treatment
Plant
44,700
$638,000
10
$1,756,184,387
15367
Nassau
ROCKVILLE CENTRE (V) /
Rockville Centre (V)
SCADA - Phase 2, Upgrade Water Treatment Plant
24,700
$430,540
10
$1,756,614,927
15382
Nassau
ROCKVILLE CENTRE (V) /
Rockville Centre (V)
Upgrade Distribution System
24,700
$727,600
10
$1,757,342,527
17912
Nassau
WA OF GREAT NECK
NORTH / Water Auth of
Great Neck North
Water main replacement, Upgrade Distribution System
31,400
$500,000
10
$1,757,842,527
17907
Nassau
VILLAGE OF PLANDOME /
Plandome (V)
Replace aged mains in distribution system, Upgrade Distribution
System
1,350
$5,113,950
10
$1,762,956,477
17903
Nassau
BETHPAGE WD / Bethpage
Water District
Construction of new South Park Drive well, New Ground Water Source
33,000
$725,120
10
$1,763,681,597
15372
Nassau
ROCKVILLE CENTRE (V) /
Rockville Centre (V)
Upgrade Distribution System
24,700
$755,307
10
$1,764,436,904
15338
Nassau
SOUTH FARMINGDALE
WD / South Farmingdale
W.D.
Natural Gas Services/Engine-Generator for Plants 2, 3 & 5, Upgrade
Water Treatment Plant
44,700
$603,000
10
$1,765,039,904
15368
Nassau
ROCKVILLE CENTRE (V) /
Rockville Centre (V)
Pipeline replacement, Upgrade Distribution System
24,700
$402,832
10
$1,765,442,736
15379
Nassau
ROCKVILLE CENTRE (V) /
Rockville Centre (V)
Pipeline replacement, Upgrade Distribution System
24,700
$561,549
10
$1,766,004,285
16457
Nassau
LIDO-POINT LOOKOUT
WD / Hempstead (T)
Upgrade Distribution System
6,000
$8,876,000
10
$1,774,880,285
Page 39 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Nassau County
15609
Nassau
MANHASSET LAKEVILLE
WD / North Hempstead (T)
Install computerized remote and local data transmission system,
Upgrade Water Treatment Plant
43,000
$238,960
10
$1,775,119,245
17720
Nassau
PORT WASHINGTON WD /
Port Washington Water
District
Replacement of water mains, Upgrade Distribution System
34,000
$2,575,000
10
$1,777,694,245
17708
Nassau
SOUTH FARMINGDALE
WD / South Farmingdale
Water Dist
Construction of Well 1-5, New Ground Water Source
44,700
$644,350
10
$1,778,338,595
17704
Nassau
WA OF WESTERN
NASSAU / Water Authority
Western Nassau
Replace water mains Franklin Square, Upgrade Distribution System
1,000
$2,169,200
10
$1,780,507,795
18057
Nassau
FREEPORT (V) /
Upgrade Distribution System
43,007
$1,995,624
10
$1,782,503,419
15385
Nassau
WA OF GREAT NECK
NORTH / Water Auth. of
Great Neck No.
Construction of automatic blow off valves for well nos. 2,5,6,7,8,9 & 10,
Upgrade Ground Water Source
31,400
$355,000
10
$1,782,858,419
17962
Nassau
OYSTER BAY WD / Oyster
Bay Water District
Solar power at administration building.,
8,700
$28,005
10
$1,782,886,424
15357
Nassau
ROCKVILLE CENTRE (V) /
Rockville Centre (V)
SCADA - Phase I, Upgrade Water Treatment Plant
24,700
$550,000
10
$1,783,436,424
16290
Nassau
BETHPAGE WD / Bethpage
W.D.
Upgrade Water Treatment Plant
33,000
$200,850
10
$1,783,637,274
16263
Nassau
FARMINGDALE (V) /
Farmingdale (V)
Upgrade Distribution System
8,405
$400,000
10
$1,784,037,274
15476
Nassau
PORT WASHINGTON WD /
North Hempstead (T)
Transfer Services (#8), Upgrade Distribution System
34,000
$89,250
10
$1,784,126,524
15470
Nassau
PORT WASHINGTON WD /
North Hempstead (T)
Construct new back pressure regulating valve vault on Radcliffe
Avenue (#7), Upgrade Distribution System
34,000
$82,600
10
$1,784,209,124
15612
Nassau
MANHASSET LAKEVILLE
WD / North Hempstead (T)
Replace existing asbestos cement pipe, Upgrade Distribution System
43,000
$1,433,760
10
$1,785,642,884
15467
Nassau
PORT WASHINGTON WD /
North Hempstead (T)
Construct new pressure regulating valve vault in West Shore Road
(#6), Upgrade Distribution System
34,000
$119,000
10
$1,785,761,884
15264
Nassau
PLAINVIEW WD / Oyster
Bay (T)
New Pump Station
35,000
$4,663,248
10
$1,790,425,132
18033
Nassau
PORT WASHINGTON WD /
Port Washington Water
District
Upgrade Ground Water Source
34,000
$2,502,900
5
$1,792,928,032
16452
Nassau
GARDEN CITY (V) / Garden
City (V)
Upgrade Distribution System
25,000
$253,287
5
$1,793,181,319
15326
Nassau
WATER AUTH. OF WEST.
NASSAU COUNTY / Water
Auth. of West. Nassau Co
Upgrade Distribution System
85,000
$8,259,240
5
$1,801,440,559
577
$835,085
95
$1,802,275,644
150,000
$20,600,000
65
$1,822,875,644
Niagara County
16062
Niagara
BARKER VILLAGE / Barker
(V)
Upgrade Distribution System
17793
Niagara
CAPITAL IMPROVEMENT
PHASE I / Niagara County
Water District
Upgrade Water Treatment Plant, New Transmission
Page 40 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Niagara County
16420
Niagara
LOCKPORT CITY WTP /
Lockport (C)
Extend Distribution System
22,279
$400,000
55
$1,823,275,644
16009
Niagara
NIAGARA FALLS WATER
BOARD / Niagara Falls (C)
D Street to Falls Street., New Distribution System
55,593
$77,000
55
$1,823,352,644
15990
Niagara
NIAGARA FALLS WATER
BOARD / Niagara Falls (C)
Ontario Avenue., Upgrade Distribution System
55,593
$281,200
55
$1,823,633,844
16211
Niagara
NIAGARA WATER
IMPROVEMENT AREA /
Niagara County
Contract 15G, E., Upgrade Water Treatment Plant, Upgrade
Transmission
8,978
$6,526,857
50
$1,830,160,701
15664
Niagara
HARTLAND WD / Hartland
(T)
Extend Distribution System
4,165
$726,500
45
$1,830,887,201
15986
Niagara
NIAGARA FALLS WATER
BOARD / Niagara Falls (C)
Upgrade Distribution System
55,593
$390,000
45
$1,831,277,201
15988
Niagara
NIAGARA FALLS WATER
BOARD / Niagara Falls (C)
McKoon Ave., West Rivershore Dr., Upgrade Distribution System
55,593
$466,920
45
$1,831,744,121
15989
Niagara
NIAGARA FALLS WATER
BOARD / Niagara Falls (C)
Hydraulic distribution system model., Upgrade Distribution System
55,593
$206,000
40
$1,831,950,121
15995
Niagara
NIAGARA FALLS WATER
BOARD / Niagara Falls (C)
valve replacement., Upgrade Distribution System
55,593
$575,800
40
$1,832,525,921
17166
Niagara
NEWFANE WD NO1,2,3
CONSOL / Newfane (T)
Upgrade Distribution System
3,485
$2,489,200
35
$1,835,015,121
17064
Niagara
MIDDLEPORT VILLAGE /
Middleport (V)
New Storage
1,917
$927,000
35
$1,835,942,121
15994
Niagara
NIAGARA FALLS WATER
BOARD / Niagara Falls (C)
Mckoon Avenue., Upgrade Distribution System
55,593
$593,500
35
$1,836,535,621
16586
Niagara
NIAGARA WATER
IMPROVEMENT AREA /
Niagara (T)
New Transmission
8,978
$400,000
35
$1,836,935,621
16002
Niagara
NIAGARA FALLS WATER
BOARD / Niagara Falls (C)
Niagara Falls Blvd., Upgrade Distribution System
55,593
$650,000
35
$1,837,585,621
16011
Niagara
NIAGARA FALLS WATER
BOARD / Niagara Falls (C)
Niagara Avenue to Parkview., New Distribution System
55,593
$308,000
35
$1,837,893,621
16006
Niagara
NIAGARA FALLS WATER
BOARD / Niagara Falls (C)
Buffalo Avenue Water Main Replacements., Upgrade Distribution
System
55,593
$5,460,000
35
$1,843,353,621
16004
Niagara
NIAGARA FALLS WATER
BOARD / Niagara Falls (C)
Rivershore Drive., Upgrade Distribution System
55,593
$277,200
35
$1,843,630,821
16001
Niagara
NIAGARA FALLS WATER
BOARD / Niagara Falls (C)
Hennepin Avenue., Upgrade Distribution System
55,593
$123,200
35
$1,843,754,021
15998
Niagara
NIAGARA FALLS WATER
BOARD / Niagara Falls (C)
Laughlin Drive., Upgrade Distribution System
55,593
$277,200
35
$1,844,031,221
15997
Niagara
NIAGARA FALLS WATER
BOARD / Niagara Falls (C)
Pierce Avenue., Upgrade Distribution System
55,593
$508,150
35
$1,844,539,371
Page 41 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Niagara County
15992
Niagara
NIAGARA FALLS WATER
BOARD / Niagara Falls (C)
Hydrant repalcement project., Upgrade Distribution System
55,593
$542,300
35
$1,845,081,671
15991
Niagara
NIAGARA FALLS WATER
BOARD / Niagara Falls (C)
Hennepin Avenue., Upgrade Distribution System
55,593
$294,270
35
$1,845,375,941
16209
Niagara
NIAGARA WATER
IMPROVEMENT AREA /
Niagara County
Contract 14A, E, G & H., Upgrade Water Treatment Plant
8,978
$2,859,246
35
$1,848,235,188
15999
Niagara
NIAGARA FALLS WATER
BOARD / Niagara Falls (C)
lead service line replacement., Upgrade Distribution System
55,593
$1,005,000
30
$1,849,240,188
17792
Niagara
W.D. IMPROVEMENTS /
Niagara County Water
District
Upgrade Water Treatment Plant
150,000
$1,125,000
30
$1,850,365,188
17517
Niagara
LOCKPORT CITY WTP /
Lockport (C)
Replace waterline on Market St. between Union and Spring , Upgrade
Distribution System
22,279
$640,000
30
$1,851,005,188
16218
Niagara
NIAGARA COUNTY WD /
Niagara County
Ward-Shawnee Transmission Main., New Transmission
109,000
$2,400,000
25
$1,853,405,188
16217
Niagara
NIAGARA COUNTY WD /
Niagara County
Upgrade Surface Water Source
109,000
$40,000
25
$1,853,445,188
16216
Niagara
NIAGARA COUNTY WD /
Niagara County
New Pump Station
109,000
$200,000
25
$1,853,645,188
16248
Niagara
NIAGARA COUNTY WD /
Niagara County
sludge lagoon modifications., Upgrade Water Treatment Plant
109,000
$220,000
25
$1,853,865,188
15071
Niagara
Upgrade Surface Water Source
NORTH TONAWANDA
CITY / North Tonawanda (C)
33,262
$61,875
25
$1,853,927,063
15064
Niagara
Filter improvments., Upgrade Water Treatment Plant
NORTH TONAWANDA
CITY / North Tonawanda (C)
33,262
$369,675
25
$1,854,296,738
16224
Niagara
NIAGARA COUNTY WD /
Niagara County
carbon feed system., Upgrade Water Treatment Plant
109,000
$100,000
25
$1,854,396,738
16222
Niagara
NIAGARA COUNTY WD /
Niagara County
Filter and valve rehabilitation., Upgrade Water Treatment Plant
109,000
$240,000
25
$1,854,636,738
16220
Niagara
NIAGARA COUNTY WD
IMPROVEMENTS / Niagara
County
Coagulation Basin Refurbishment., Upgrade Water Treatment Plant
109,000
$450,000
25
$1,855,086,738
16214
Niagara
NIAGARA COUNTY WD /
Niagara County
Shawnee-Robinson Transmission main., Upgrade Transmission
109,000
$6,200,000
25
$1,861,286,738
15063
Niagara
Clean coagulation basin piping and water intake conduit., Upgrade
NORTH TONAWANDA
CITY / North Tonawanda (C) Water Treatment Plant
33,262
$236,950
25
$1,861,523,688
15473
Niagara
LEWISTON WATER
IMPROVEMENTAREA /
Lewiston (T)
Upgrade Transmission, Upgrade Distribution System
16,257
$4,842,107
20
$1,866,365,795
16223
Niagara
NIAGARA COUNTY WD /
Niagara County
New lab., Upgrade Water Treatment Plant
109,000
$100,000
20
$1,866,465,795
15060
Niagara
Distribution system improvements, various locations throughout city.,
NORTH TONAWANDA
CITY / North Tonawanda (C) Upgrade Distribution System
33,262
$16,050,000
20
$1,882,515,795
Page 42 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Niagara County
17846
Niagara
LOCKPORT CITY WTP /
Lockport (C)
Repair deteriorated raw water line, intake structure, and chemical feed,
Upgrade Other Expenses, Upgrade Transmission, Upgrade Other (OT)
17692
Niagara
NEWFANE WD NO1,2,3
CONSOL / Newfane (T)
Upgrade Distribution System
15069
Niagara
15065
22,279
$612,850
20
$1,883,128,645
3,485
$300,000
20
$1,883,428,645
Abandon/replace 2" mains., Upgrade Distribution System
NORTH TONAWANDA
CITY / North Tonawanda (C)
33,262
$130,800
20
$1,883,559,445
Niagara
Dead-end main elimination., New Distribution System
NORTH TONAWANDA
CITY / North Tonawanda (C)
33,262
$600,250
20
$1,884,159,695
16053
Niagara
CAMBRIA WATER
DISTRICT / Cambria (T)
New Storage, New Pump Station, Upgrade Distribution System
5,393
$1,000,000
20
$1,885,159,695
17264
Niagara
LEWISTON WATER
IMPROVEMENTAREA /
Lewiston (T)
Upgrade Transmission, Upgrade Distribution System
16,257
$5,000,000
20
$1,890,159,695
17820
Niagara
STORAGE TANKS
REHABILITATION / Porter
(T)
Upgrade Storage
6,920
$504,700
15
$1,890,664,395
17815
Niagara
NIAGARA WATER
IMPROVEMENT AREA /
Niagara(T)
Upgrade Storage
8,978
$206,000
15
$1,890,870,395
16599
Niagara
WILSON TOWN WATER
DISTRICT / Wilson (T)
Sunset Island water main project., Upgrade Distribution System
4,907
$882,400
15
$1,891,752,795
16397
Niagara
LOCKPORT WD#3 /
Lockport (T)
Transit Road., Upgrade Distribution System
19,653
$1,350,000
15
$1,893,102,795
17381
Niagara
YOUNGSTOWN (V) /
Youngstown (V)
Upgrade Transmission
2,021
$544,613
15
$1,893,647,408
17715
Niagara
NEWFANE WD NO1,2,3
CONSOL / Newfane (T)
Upgrade Distribution System
3,485
$2,000,000
10
$1,895,647,408
16398
Niagara
LOCKPORT WD#3 /
Lockport (T)
Sunset Drive., Upgrade Distribution System
19,653
$1,080,000
10
$1,896,727,408
16399
Niagara
LOCKPORT WD#3 /
Lockport (T)
Lincoln Avenue., Upgrade Distribution System
19,653
$765,000
5
$1,897,492,408
16393
Niagara
LOCKPORT WD#3 /
Lockport (T)
Stone Road., Upgrade Distribution System
19,653
$1,305,000
5
$1,898,797,408
NY City County
17983
NY City
NEW YORK CITY CROTON SYSTEM /
NYCMWFA
Croton filtration plant(Phase 8 of 16479), New Surface Water
Treatment Rule Compliance Facility
1,000,000
$217,962,340
2115
$2,116,759,748
17604
NY City
NEW YORK
CITY-CATSKILL/DELAWARE
SYSTEM / NYCMWFA
Hillview Reservoir Chambers Reconstruction-(Phase 4 of 17171),
General Chamber Improvements, Flow Control & New Chemical
Facilities, SCADA (C519A,C519B,C519C,C519D), Upgrade Surface
Water Treatment Rule Compliance Facility
6,552,718
$5,607,922
2110
$2,122,367,670
16999
NY City
Hillview Reservoir Chem Addl. Bldg, Equipment Storage Bldg(C529A
NEW YORK
CITY-CATSKILL/DELAWARE CM, C529A, C545E)Phase3 (Phase1=16265, Phase 2=16463),
Upgrade Storage, New Storage
SYSTEM / NYCMWFA
6,552,718
$5,000,000
2105
$2,127,367,670
16660
NY City
Hillview Reservoir cover, phase 2 of DWSRF #16477 (C565, 566D)
NEW YORK
CITY-CATSKILL/DELAWARE portion of phase 3 brought forward from m.y. list to R.List., Upgrade
Storage
SYSTEM / NYCMWFA
6,552,718
$20,000,000
2105
$2,147,367,670
17607
NY City
Kensico flow control structure(566C, 566CM)(phase 8 of 16875),
NEW YORK
CITY-CATSKILL/DELAWARE Upgrade Storage
SYSTEM / NYCMWFA
6,552,718
$4,092,390
2105
$2,151,460,060
Page 43 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
NY City County
17605
NY City
3rd city tunnel, stage2 Bkln/Qns, shaft19B(C545A)(Qns), crit redund,
NEW YORK
CITY-CATSKILL/DELAWARE dist. press(phase 8 of 16996), Instr. and Tele;Bkln,Qns, Manh (C545D),
New Transmission
SYSTEM / NYCMWFA
6,552,718
$1,071,895
2060
$2,152,531,955
17606
NY City
3rd city tunnel, stage2 Bkln/Qns, shafts 20,21 and 22B(C545B) (Bkln),
NEW YORK
CITY-CATSKILL/DELAWARE Shaft 23B (C545C)(Bkln), crit redund, dist. press(phase 8 of 16266),
New Transmission
SYSTEM / NYCMWFA
6,552,718
$4,271,491
2060
$2,156,803,446
18054
NY City
NEW YORK CITY CROTON SYSTEM /
NYCMWFA
1,000,000
$500,000,000
115
$2,656,803,446
16476
NY City
Transmission to Jamaica area, dist press improv, Upgrade
NEW YORK
CITY-CATSKILL/DELAWARE Transmission
SYSTEM / NYCMWFA
6,552,718
$100,000,000
85
$2,756,803,446
17203
NY City
City Tunnel 3, Stage 1, Shafts 8B and 15B, Phase 1 - Completion of
NEW YORK
CITY-CATSKILL/DELAWARE Chlorination Booster Stations, Upgrade Distribution System
SYSTEM / NYCMWFA
6,552,718
$1,000,000
60
$2,757,803,446
17167
NY City
City Tunnel 3, Stage 2, Shaft 15B East-Phase 1, Brooklyn-Queens
NEW YORK
CITY-CATSKILL/DELAWARE (C545G), New Pump Station
SYSTEM / NYCMWFA
6,552,718
$8,000,000
60
$2,765,803,446
17011
NY City
City tunnel 3 stage 2, shafts19B-22B (C544B, C, E, H, P), Upgrade
NEW YORK
CITY-CATSKILL/DELAWARE Transmission
SYSTEM / NYCMWFA
6,552,718
$35,000,000
60
$2,800,803,446
17009
NY City
City Tunnel 3 stage 2 Mnhtn segment, shaft 18B completion(C541R),
NEW YORK
CITY-CATSKILL/DELAWARE Upgrade Transmission
SYSTEM / NYCMWFA
6,552,718
$35,000,000
60
$2,835,803,446
16478
NY City
3rd City tunnel and shafts, crit redund, dist press,Field services(C538B
NEW YORK
CITY-CATSKILL/DELAWARE CM), Upgrade Transmission
SYSTEM / NYCMWFA
6,552,718
$470,000,000
60
$3,305,803,446
16474
NY City
3rd City Tunnel, mnhtn borings; Restore shaft 23(C604); Riser Valve
NEW YORK
CITY-CATSKILL/DELAWARE Controls, Delaware system(C347), Upgrade Transmission
SYSTEM / NYCMWFA
6,552,718
$35,000,000
60
$3,340,803,446
17437
NY City
Catskill& Delaware UV Disinfection, New Water Treatment Plant
NEW YORK
CITY-CATSKILL/DELAWARE
SYSTEM / NYCWMFA
6,552,718
1,400,000,000
55
$4,740,803,446
17370
NY City
Reconstruction of Delaware Aqueduct, Shafts 9,10 & 17, Upgrade
NEW YORK
CITY-CATSKILL/DELAWARE Transmission
SYSTEM / NYCMWFA
6,552,718
$35,066,289
30
$4,775,869,735
17371
NY City
Inspection and Rehabilitation of New Croton Aqueduct, Upgrade
NEW YORK
CITY-CATSKILL/DELAWARE Transmission
SYSTEM / NYCMWFA
6,552,718
$28,130,420
30
$4,804,000,155
17559
NY City
Reconstruction of Kensico Fluoride Facilities, Upgrade Water
NEW YORK
CITY-CATSKILL/DELAWARE Treatment Plant
SYSTEM / NYCMWFA
6,552,718
$8,048,360
25
$4,812,048,515
17198
NY City
Test Borings for City Tunnel 3 and Upstate Tunnel Sites, Phase 1
NEW YORK
CITY-CATSKILL/DELAWARE (C554), NYC & Westchester, Upgrade Transmission
SYSTEM / NYCMWFA
6,552,718
$5,982,162
15
$4,818,030,677
Croton filtration plant(Phase 9 of 16479), New Surface Water
Treatment Rule Compliance Facility
Oneida County
18023
Oneida
ROME CITY / Rome (C)
Phase 2 of project 17438. Filter plant upgrades and new 20 MG
storage tank., Upgrade Water Treatment Plant, New Storage, Upgrade
Storage
32,000
$20,000,000
160
$4,838,030,677
17438
Oneida
ROME CITY / Rome (C)
New 10 MG storage tank. (Phase 1 of covering city's open finished
water storage, Phase 2 is Proj. # 18023 on multiyear list) , Upgrade
Water Treatment Plant, New Storage, Upgrade Storage
32,000
$10,000,000
160
$4,848,030,677
17487
Oneida
SAUQUOIT
CONSOLIDATED WD
(T/O/PARIS) / Paris (T)
New wells for GUDI source compliance., New Ground Water Source
2,639
$3,100,000
155
$4,851,130,677
17648
Oneida
DEERFIELD RTE 8/28
WATER DISTRICT /
Deerfield (T)
New Surface Water Treatment Rule Compliance Facility, New
Distribution System, New Inter-Connection, New Water District
100
$600,000
130
$4,851,730,677
17230
Oneida
BENEFITED AREA E /
Floyd (T)
New Distribution System, New System Consolidation
115
$325,000
115
$4,852,055,677
Page 44 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Oneida County
17462
Oneida
CLINTON VILLAGE /
Clinton (V)
New Surface Water Treatment Rule Compliance Facility
15139
Oneida
MOHAWK VALLEY WATER
AUTHORITY / Upper
Mohawk Valley Reg. WB
17263
Oneida
17650
3,000
$2,720,000
110
$4,854,775,677
New 6 MG storage tank at Toby Road., Upgrade Storage
120,000
$8,375,000
105
$4,863,150,677
MOHAWK VALLEY WATER
AUTHORITY / Upper M V
Regional WB
New System Consolidation
120,000
$7,210,000
100
$4,870,360,677
Oneida
MOHAWK VALLEY WATER
AUTHORITY / Upper M V
Regional WB
New Storage
120,000
$4,326,000
95
$4,874,686,677
16889
Oneida
KIRKLAND (T) ROUTE 5
WATER DISTRICT /
Kirkland (T)
New system to serve area with private contaminated wells, consolidate
public water supply. , New Complete System (New System)
300
$1,578,872
90
$4,876,265,549
17145
Oneida
TIBBITS/SNOWDEN HILL
WD / New Hartford (T)
New system to serve area with private contaminated wells. , New
Complete System (New System)
450
$2,400,000
80
$4,878,665,549
16588
Oneida
TOWN OF TRENTON /
Trenton (T)
Extend Distribution System
150
$848,900
80
$4,879,514,449
17277
Oneida
CLAYVILLE VILLAGE /
Clayville(V)
New Inter-Connection
445
$220,000
80
$4,879,734,449
16899
Oneida
FLOYD BENEFIT (T) AREA
"D" / Floyd (T)
New Complete System (New System)
900
$7,750,000
75
$4,887,484,449
16806
Oneida
MOHAWK VALLEY WATER
AUTHORITY / Upper M V
Regional WB
Replace undersized and unlined mains in the North Utica and Cornhill
area, Upgrade Transmission, Upgrade Transmission
120,000
$486,200
75
$4,887,970,649
15794
Oneida
MOHAWK VALLEY WATER
AUTHORITY / Upper
Mohawk Valley Reg. WB
Shacksbury Storage Tank and Mains, Replacement. , Upgrade
Storage
120,000
$400,000
70
$4,888,370,649
15560
Oneida
VERNON VILLAGE (SWP) /
Vernon (V)
New Transmission, New Storage, New Distribution System, New
Inter-Connection
1,155
$5,610,300
70
$4,893,980,949
16800
Oneida
MOHAWK VALLEY WATER
AUTHORITY / Upper M V
Regional WB
Wilcox tank renovation and expansion, Upgrade Storage
120,000
$982,800
70
$4,894,963,749
16435
Oneida
DEERFIELD (T), SMITH
HILL EXT. / Deerfield (T)
Extend system to serve area with private contaminated wells,
consolidate public water supply. , Extend Distribution System
200
$638,000
70
$4,895,601,749
15205
Oneida
BOONVILLE VILLAGE /
Boonville (V)
New Transmission, New Storage, Upgrade Distribution System
2,300
$801,144
70
$4,896,402,893
17886
Oneida
HALSTEAD ROAD WD /
Vienna (T)
Extend Distribution System
75
$692,400
60
$4,897,095,293
17616
Oneida
VIENNA (T) / Vienna (T)
New Distribution System
150
$210,000
60
$4,897,305,293
15865
Oneida
MOHAWK VALLEY WATER
AUTHORITY / UMVRWB
Pleasant Street. Upper Mohawk Valley Regional Water Board,
Upgrade Distribution System
120,000
$1,600,000
55
$4,898,905,293
15786
Oneida
MOHAWK VALLEY WATER
AUTHORITY / Upper
Mohawk Valley Reg. WB
Gilbert Road Storage Tank., Upgrade Storage
120,000
$150,000
55
$4,899,055,293
17027
Oneida
MOHAWK VALLEY WATER
AUTHORITY / Whitestown
(T)
The UMVRWB will extend the 12 inch line along Sutliff Road and NYS
route 233 and connect to Village of Camelot., Extend System
Consolidation
120,000
$629,000
55
$4,899,684,293
Page 45 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Oneida County
18064
Oneida
FORESTPORT WATER
DISTRICT / Foresport (T)
New Ground Water Source
18011
Oneida
ROUTE 5 WD / Vernon (T)
Serve private contaminated/poor yielding wells., Extend Distribution
System
15869
Oneida
MOHAWK VALLEY WATER
AUTHORITY / Upper
Mohawk Valley Reg. WB
15878
Oneida
16805
900
$390,000
55
$4,900,074,293
30
$244,000
55
$4,900,318,293
Burrstone Road and Dewey Row, (T) of Whitestone., Upgrade
Distribution System
120,000
$756,000
55
$4,901,074,293
MOHAWK VALLEY WATER
AUTHORITY / Upper
Mohawk Valley Reg. WB
Southern Pump and Chemical Treatment Station, Upgrade Pump and
Chemical Station., Upgrade Pump Station
120,000
$420,000
50
$4,901,494,293
Oneida
MOHAWK VALLEY WATER
AUTHORITY / Upper M V
Regional WB
High Service Zone Interconnecting Mains, Oxford Road, Upgrade
Transmission
120,000
$1,159,000
50
$4,902,653,293
17921
Oneida
EUREKA ROAD WD /
Westmoreland (T)
New Pump Station, New Distribution System
35
$180,000
50
$4,902,833,293
17307
Oneida
NEW LONDON WATER
SYSTEM / Verona (T)
New Storage, New Distribution System
500
$6,150,000
50
$4,908,983,293
15748
Oneida
MOHAWK VALLEY WATER
AUTHORITY / Upper
Mohawk Valley Reg. Water
Upgrade Pump Station
120,000
$120,000
45
$4,909,103,293
16774
Oneida
TOWN OF NEW
HARTFORD / New Hartford
(T)
New Complete System (New System)
450
$1,483,200
45
$4,910,586,493
15077
Oneida
MILLER/WALKER RD. W.D.
- (T)DEERFIELD / Deerfield
(T)
New Complete System (New System), Extend Distribution System
200
$306,400
45
$4,910,892,893
17922
Oneida
NORTHEASTERN WD /
Westmoreland (T)
New Storage, New Pump Station, New Distribution System
880
$6,700,000
45
$4,917,592,893
17652
Oneida
MOHAWK VALLEY WATER
AUTHORITY / Upper M V
Regional WB
New Transmission
120,000
$10,300,000
45
$4,927,892,893
17651
Oneida
MOHAWK VALLEY WATER
AUTHORITY / Upper M V
Regional WB
Upgrade Distribution System
120,000
$9,270,000
40
$4,937,162,893
15062
Oneida
TAURUSEL, INC (POND
HILL) / Taurusel, Inc.
Upgrade Ground Water Source, Upgrade Distribution System, System
Consolidation
54
$164,000
35
$4,937,326,893
17472
Oneida
MOHAWK VALLEY WATER
AUTHORITY / Upper
Mohawk Valley Reg. WB
New Storage
120,000
$4,271,400
35
$4,941,598,293
15703
Oneida
ROME CITY / Rome (C)
Transmission main for western portion of city., New Transmission
32,000
$7,000,000
30
$4,948,598,293
15731
Oneida
ROME CITY / Rome (C)
New Storage
32,000
$1,000,000
30
$4,949,598,293
15700
Oneida
ROME CITY / Rome (C)
Replace two 30" diameter main water transmission lines., Upgrade
Transmission
32,000
$5,000,000
30
$4,954,598,293
15721
Oneida
ROME CITY / Rome (C)
Upgrade Transmission
32,000
$600,000
25
$4,955,198,293
15737
Oneida
ROME CITY / Rome (C)
Water meters., Upgrade Distribution System
32,000
$1,000,000
25
$4,956,198,293
Page 46 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Oneida County
15726
Oneida
ROME CITY / Rome (C)
Upgrade Distribution System
16250
Oneida
J.E. BARRETT WD /
Prospect (V)
Upgrade Ground Water Source, New Storage, Upgrade Distribution
System
15711
Oneida
ROME CITY / Rome (C)
Hydrant replacement., Upgrade Distribution System
15045
Oneida
CLINTON VILLAGE /
Clinton (V)
16693
Oneida
17920
32,000
$2,200,000
25
$4,958,398,293
150
$326,000
25
$4,958,724,293
32,000
$750,000
25
$4,959,474,293
Upgrade Distribution System
3,000
$822,000
20
$4,960,296,293
CLINTON VILLAGE /
Clinton (V)
New Storage
3,000
$521,180
20
$4,960,817,473
Oneida
WESTMORELAND WD NO
1 (GU) / Westmoreland (T)
New Ground Water Source, Upgrade Storage
600
$2,850,000
20
$4,963,667,473
17825
Oneida
VERONA WATER
DISTRICT (SWP) / Verona
(T)
New Transmission
1,050
$26,553,000
20
$4,990,220,473
17485
Oneida
BARNEVELD VILLAGE
(GU) / Barneveld (V)
Upgrade Distribution System
600
$219,000
15
$4,990,439,473
LIMELEDGE WD /
Marcellus (T) & (V)
New Water District to serve area with insufficient private wells.
Interconnection with GWUDI system., New Surface Water Treatment
Rule Compliance Facility, Extend Distribution System
700
1160
$4,990,439,473
250
$535,600
145
$4,990,975,073
Onondaga County
16882
Onondaga
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
17385
Onondaga
NORTHEAST LAFAYETTE
WD / East Syracuse (V)
Inter-connection to eliminate GWUDI source., New Transmission, New
Inter-Connection
17612
Onondaga
ELBRIDGE VILLAGE /
Elbridge (V)
New UV treatment for LT2ESWTR compliance., New Surface Water
Treatment Rule Compliance Facility
1,519
$0
135
$4,990,975,073
17728
Onondaga
SKANEATELES VILLAGE /
Skaneateles
Install UV Disinfection for LT2 compliance., Upgrade Water Treatment
Plant
2,610
$793,100
115
$4,991,768,173
17855
Onondaga
SYRACUSE CITY /
Syracuse (C)
Woodland Reservoir UV for LT2SWTR compliance., New Surface
Water Treatment Rule Compliance Facility
192,000
$10,042,500
95
$5,001,810,673
17638
Onondaga
OCWA / Onondaga County
Water Authorit
Eastern 20 MG Reservoir storage. Replacing uncovered finished water
storage reservoir with concrete tank., Upgrade Storage
256,000
$22,500,000
90
$5,024,310,673
17460
Onondaga
CLAY WDS / Metropolitan
Water Board
Replace uncovered finished 30 MG Terminal Reservoir with two 15 MG
tanks, Upgrade Storage
16,000
$16,050,000
90
$5,040,360,673
17458
Onondaga
OCWA / Onondaga County
Water Authorit
Western Reservoir 20 mg storage. Replacing uncovered finished water
storage reservoir with concrete tank, Upgrade Storage
256,000
$0
90
$5,040,360,673
17934
Onondaga
LAFAYETTE (T) / LaFayette
(T)
Creation of Central LaFayette Water District., New Water District
2,000
$5,700,000
80
$5,046,060,673
16564
Onondaga
NORTHEAST LAFAYETTE
WD / East Syracuse (V)
New well to replace shallow wells and a lead and copper corrosion
control system., New Ground Water Source
250
$227,040
75
$5,046,287,713
17988
Onondaga
OCWA / Onondaga County
Water Authorit
Southern branch pump station improvements. , Upgrade Pump Station
256,000
$2,500,000
70
$5,048,787,713
17884
Onondaga
MARCELLUS (T) / Marcellus Pheasant Valley Road WD., New Distribution System, New
Inter-Connection
(T)
93
$782,000
70
$5,049,569,713
Page 47 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Onondaga County
17856
Onondaga
SYRACUSE CITY /
Syracuse (C)
Westcott Reservoir UV for LT2SWTR compliance., New Surface
Water Treatment Rule Compliance Facility
192,000
$4,805,000
70
$5,054,374,713
17857
Onondaga
SYRACUSE CITY /
Syracuse (C)
Lead service replacement., Upgrade Distribution System
192,000
$16,377,000
70
$5,070,751,713
17025
Onondaga
NORTHEAST LAFAYETTE
WD / East Syracuse (V)
Contruct a building around Gifford finished water reservoir. , Upgrade
Storage
250
$1,990,503
65
$5,072,742,216
17389
Onondaga
NORTHEAST LAFAYETTE
WD / East Syracuse (V)
Replace lead service lines from the watermain to the property line to
correct lead & copper exceedances., Upgrade Distribution System
250
$444,445
65
$5,073,186,661
15811
Onondaga
SKANEATELES VILLAGE /
Skaneateles (V)
Improve disinfection contact time., Upgrade Transmission
2,610
$1,600,000
55
$5,074,786,661
15116
Onondaga
ROUTE 5 WEST W.D. - (T)
ELBRIDGE / Elbridge (T)
Route 5 West WD., New Complete System (New System), New
Distribution System
6,192
$306,966
50
$5,075,093,627
15115
Onondaga
ROUTE 5 EAST W.D. - (T)
ELBRIDGE / Elbridge (T)
Route 5 East WD., New Complete System (New System), New
Transmission, New Storage, New Distribution System
6,192
$2,008,500
50
$5,077,102,127
17328
Onondaga
HALFWAY ROAD WATER
DISTRICT / Elbridge (T)
New Storage, Extend Distribution System
120
$906,400
50
$5,078,008,527
17327
Onondaga
CROSS LAKE/N.
ELBRIDGE AREA WD /
Elbridge (T)
New Storage, New Pump Station, Extend Distribution System
534
$2,590,450
50
$5,080,598,977
17326
Onondaga
LAIRD ROAD WATER
DISTRICT / Elbridge (T)
Extend Distribution System
29
$378,000
50
$5,080,976,977
16565
Onondaga
NORTHEAST LAFAYETTE
WD / Onondaga County
Parks
Jamesville Beach Water Supply Upgrade., New Storage, New
Distribution System
250
$102,000
45
$5,081,078,977
17971
Onondaga
GILLIE BROOK ROAD WD /
Camillus (T)
Gillie Brook Road Water District., Extend Distribution System
27
$432,565
45
$5,081,511,542
16313
Onondaga
TOWN OF LYSANDER
W.D. / Lysander (T)
Lamson Road Water District., New Distribution System, New Water
District
500
$5,284,000
45
$5,086,795,542
18008
Onondaga
CLAY WDS / Clay (T)
Extend Distribution System
16,000
$260,000
45
$5,087,055,542
16644
Onondaga
CICERO WDS / Cicero (T)
Extend Distribution System
14,108
$49,500
45
$5,087,105,042
16177
Onondaga
NORTHEAST LAFAYETTE
WD / East Syracuse (V)
New Pump Station
250
$105,869
45
$5,087,210,911
16308
Onondaga
COYE ROAD W. D. /
Lafayette (T)
New Complete System (New System)
320
$804,000
45
$5,088,014,911
16306
Onondaga
TOWN OF LAFAYETTE /
Lafayette (T)
Tully Valley potable water supply., New Complete System (New
System)
250
$2,000,000
45
$5,090,014,911
15061
Onondaga
TULLY VILLAGE / Tully (V)
New Ground Water Source, Upgrade Distribution System
930
$226,600
45
$5,090,241,511
16669
Onondaga
SOUTH ONONDAGA
WATER DISTRICT /
Onondaga (T)
Extend Distribution System
400
$1,589,000
45
$5,091,830,511
Page 48 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Onondaga County
17024
Onondaga
NORTHEAST LAFAYETTE
WD / East Syracuse (V)
Cleaning and dredging of Gifford Finished WaterReservoir., Upgrade
Storage
17964
Onondaga
SYRACUSE CITY /
Syracuse (C)
Install solar power at Westcott Reservoir.,
17917
Onondaga
CAMILLUS
CONSOLIDATED WD /
Camillus (T)
Upgrade Distribution System
17963
Onondaga
SYRACUSE CITY /
Syracuse (C)
15224
Onondaga
16432
250
$158,862
40
$5,091,989,373
192,000
$487,273
35
$5,092,476,646
22,000
$5,035,497
35
$5,097,512,143
Install hydroturbine at Westcott Reservoir.,
192,000
$315,000
35
$5,097,827,143
OCWA / Onondaga Co.
Water Authority
New Storage
256,000
$2,210,120
35
$5,100,037,263
Onondaga
JORDAN VILLAGE / Jordan
(V)
Upgrade Pump Station
1,400
$63,000
30
$5,100,100,263
15144
Onondaga
BALDWINSVILLE VILLAGE
/ Baldwinsville (V)
Upgrade Ground Water Source, Upgrade Distribution System
8,000
$3,887,530
25
$5,103,987,793
15155
Onondaga
VAN BUREN WDS / Van
Buren (T)
Upgrade Distribution System
10,000
$858,000
20
$5,104,845,793
15145
Onondaga
BALDWINSVILLE VILLAGE
/ Baldwinsville (V)
New Water Treatment Plant, New Ground Water Source, New
Transmission
8,000
$425,390
20
$5,105,271,183
16120
Onondaga
DEWITT WDS - SOUTH /
Dewitt (T)
New Storage, Upgrade Pump Station, Upgrade Distribution System
15,705
$1,750,000
20
$5,107,021,183
17325
Onondaga
MINOA VILLAGE / Minoa
(V)
Upgrade Distribution System
3,745
$307,336
20
$5,107,328,519
17334
Onondaga
CAMILLUS
CONSOLIDATED WD /
Camillus (T)
Upgrade Distribution System
22,000
$2,178,450
15
$5,109,506,969
16616
Onondaga
SKANEATELES VILLAGE /
Skaneateles (V)
Upgrade Distribution System
2,610
$574,000
10
$5,110,080,969
16155
Onondaga
CAMILLUS
CONSOLIDATED WD /
Camillus (T)
Upgrade Distribution System
22,000
$1,613,997
10
$5,111,694,966
16119
Onondaga
DEWITT WDS - SOUTH /
Dewitt (T)
Inter-Connection
15,705
$1,432,000
10
$5,113,126,966
15058
Onondaga
ELBRIDGE VILLAGE /
Elbridge (V)
Upgrade Transmission
1,519
$769,681
10
$5,113,896,646
17853
Onondaga
OCWA / Onondaga County
Water Authorit
Roof and siding improvements for Water System Maintenance and
Operations Facility., Upgrade Other Expenses, Upgrade Other (OT)
256,000
$1,620,000
5
$5,115,516,646
1,100
$1,530,700
170
$5,117,047,346
Ontario County
17522
Ontario
NAPLES VILLAGE / Naples
(V)
Address GWUDI spring sources., New Surface Water Treatment Rule
Compliance Facility, Upgrade Ground Water Source, Upgrade
Distribution System
17591
Ontario
BLOOMFIELD (V) OAKMOUNT AVE /
Bloomfield (V)
Upgrade Ground Water Source
750
$298,750
110
$5,117,346,096
15734
Ontario
MANCHESTER CENTRAL
WATER DISTRICT /
Manchester (T)
New Storage, Extend Distribution System, System Consolidation
581
$2,664,600
85
$5,120,010,696
Page 49 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Ontario County
17082
Ontario
CLIFTON SPRINGS
VILLAGE / Clifton Springs
(V)
New Storage, Upgrade Distribution System
17746
Ontario
RUSHVILLE VILLAGE /
Rushville (V)
Upgrade Surface Water Treatment Rule Compliance Facility
15159
Ontario
NAPLES VILLAGE / Naples
(V)
16886
Ontario
16814
2,190
$618,000
70
$5,120,628,696
621
$1,969,200
65
$5,122,597,896
Upgrade Transmission, New Storage, Upgrade Distribution System
1,100
$1,465,000
65
$5,124,062,896
WEST BLOOMFIELD WD /
West Bloomfield (T)
County Road 35 and Dugway Road. , Extend Distribution System
1,500
$195,513
60
$5,124,258,409
Ontario
WEST BLOOMFIELD WD /
West Bloomfield (T)
Extend system to serve area with private contaminated wells. , Extend
Distribution System
1,500
$231,750
60
$5,124,490,159
15545
Ontario
OAKMOUNT ROAD
WATER SYSTEM / East
Bloomfield (T)
New Storage, Extend Distribution System
150
$2,224,000
55
$5,126,714,159
17378
Ontario
GORHAM TOWN WD /
Gorham (T)
Extension No. 9., Extend Distribution System
4,500
$732,000
50
$5,127,446,159
16792
Ontario
PHELPS (T) WATER
DISTRICT NO. 3 / Phelps
(T)
Extend Distribution System
310
$1,295,000
45
$5,128,741,159
16793
Ontario
PHELPS (T) WATER
DISTRICT NO. 4 / Phelps
(T)
Extend Distribution System
230
$710,000
45
$5,129,451,159
16612
Ontario
NORTH FARMINGTON WD
/ Farmington (T)
Fox Road & County Road 28., Extend Distribution System
2,300
$155,128
45
$5,129,606,287
16698
Ontario
GENEVA (T) / Geneva (T)
New Storage, New Distribution System
1,500
$2,541,000
45
$5,132,147,287
17747
Ontario
CANANDAIGUA-FARMINGT Distribution Main Installation for Canandaigua-Farmington Consolidated
Water District, Upgrade Distribution System
CONSOLIDATED W.D. / C
& F Cosolidated WD
11,400
$2,511,140
45
$5,134,658,427
16040
Ontario
GORHAM TOWN WD /
Gorham (T)
New Pump Station, Extend Distribution System
4,500
$489,370
45
$5,135,147,797
17521
Ontario
RUSHVILLE VILLAGE /
Rushville (V)
New Pump Station
621
$473,800
45
$5,135,621,597
17507
Ontario
SENECA WD NO.1 /
Seneca (T)
New Complete System (New System), New Pump Station, New
Distribution System
75
$1,529,500
45
$5,137,151,097
15549
Ontario
CANANDAIGUA TOWN
CONS. WD / Canandaigua
(T)
Extend Distribution System
6,300
$207,300
40
$5,137,358,397
15541
Ontario
CANANDAIGUA TOWN
CONS. WD / Canandaigua
(T)
Extend Distribution System
6,300
$1,120,537
40
$5,138,478,934
16151
Ontario
NORTH FARMINGTON WD
/ Farmington (T)
Extend Distribution System
2,300
$159,990
40
$5,138,638,924
15210
Ontario
PHELPS VILLAGE / Phelps
(V)
New Transmission
2,118
$862,000
40
$5,139,500,924
15554
Ontario
WEST LAKE RD BENEFIT
BASIS DIS / Canandaigua
(T)
Canandaigua. (T), Extend Distribution System
220
$1,243,100
40
$5,140,744,024
Page 50 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Ontario County
15209
Ontario
PHELPS (T) - ROUTE 96
WEST WD / Phelps (T)
Extend Distribution System
15516
Ontario
MAXWELL WATER
DISTRICT EXT. 1 /
Farmington (T)
County Road 28 from Maxwell Rd. to Fox Rd., Extend Distribution
System
15208
Ontario
PHELPS (T) - ROUTE 14
WD / Phelps (T)
Extend Distribution System
15542
Ontario
COUNTY ROAD 30 - EAST
BLOOMFIELD / East
Bloomfield (T)
System Consolidation
17511
Ontario
CANANDAIGUA CITY /
Canandaigua (C)
Upgrade Storage, New Storage
16072
Ontario
GENEVA CITY / Geneva (C) Upgrade Distribution System
15548
Ontario
NYS RT. 5 EXTENSION EAST BLOOMFIELD / East
Bloomfield (T)
Inter-Connection
15520
Ontario
VICTOR VILLAGE / Victor
(V)
Upgrade Transmission, Upgrade Distribution System
16357
Ontario
CANANDAIGUA CITY /
Canandaigua (C)
New Storage
16885
Ontario
WEST BLOOMFIELD WD /
West Bloomfield (T)
Cathodic protection system., Upgrade Storage
17898
Ontario
RUSHVILLE VILLAGE /
Rushville (V)
15217
Ontario
16041
300
$1,132,000
40
$5,141,876,024
40
$90,813
40
$5,141,966,837
200
$1,125,000
40
$5,143,091,837
60
$86,000
35
$5,143,177,837
11,264
$4,893,145
30
$5,148,070,982
13,617
$1,223,640
30
$5,149,294,622
120
$199,563
25
$5,149,494,185
2,443
$606,387
25
$5,150,100,572
11,264
$1,375,000
25
$5,151,475,572
1,500
$13,390
20
$5,151,488,962
Upgrade Water Treatment Plant
621
$1,969,200
20
$5,153,458,162
BLOOMFIELD (V) OAKMOUNT AVE /
Bloomfield (V)
New Ground Water Source, New Storage
750
$978,500
20
$5,154,436,662
Ontario
GORHAM TOWN WD /
Gorham (T)
New Pump Station, Upgrade Distribution System
4,500
$141,280
20
$5,154,577,942
16358
Ontario
CANANDAIGUA CITY /
Canandaigua (C)
Replacement of water reservoir cover., Upgrade Storage
11,264
$375,000
20
$5,154,952,942
16356
Ontario
CANANDAIGUA CITY /
Canandaigua (C)
Painting of storage tanks., Upgrade Storage
11,264
$450,000
20
$5,155,402,942
16353
Ontario
CANANDAIGUA CITY /
Canandaigua (C)
Upgrade Transmission
11,264
$445,000
20
$5,155,847,942
15559
Ontario
HOPEWELL WD #2 /
Hopewell (T)
New Pump Station
1,148
$435,600
15
$5,156,283,542
17896
Ontario
WHITE ROAD WD / Phelps
(T)
Upgrade Distribution System
45
$213,700
15
$5,156,497,242
17753
Ontario
CANANDAIGUA-FARMINGT Transmisstion Main for Canandaigua-Farmington Consolidated Water
District, New Transmission
CONSOLIDATED W.D. / C
& F Cosolidated WD
11,400
$2,866,490
15
$5,159,363,732
16039
Ontario
GORHAM TOWN WD /
Gorham (T)
4,500
$1,150,000
15
$5,160,513,732
Page 51 of 86
New Storage
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Ontario County
16038
Ontario
GORHAM TOWN WD /
Gorham (T)
Upgrade Storage
4,500
$77,500
15
$5,160,591,232
16037
Ontario
GORHAM TOWN WD /
Gorham (T)
Upgrade Water Treatment Plant
4,500
$108,500
15
$5,160,699,732
18040
Ontario
BLOOMFIELD VILLAGE /
Bloomfield (V)
Upgrade Distribution System
1,675
$1,340,697
15
$5,162,040,429
16355
Ontario
CANANDAIGUA CITY /
Canandaigua (C)
Muar Lakes Water Main Replacement., Upgrade Distribution System
11,264
$110,000
15
$5,162,150,429
16354
Ontario
CANANDAIGUA CITY /
Canandaigua (C)
North Street water main replacement., Upgrade Distribution System
11,264
$294,000
15
$5,162,444,429
16352
Ontario
CANANDAIGUA CITY /
Canandaigua (C)
West Gibson Street water main., Upgrade Distribution System
11,264
$200,000
15
$5,162,644,429
16757
Ontario
SHORTSVILLE VILLAGE /
Shortsville (V)
Upgrade Distribution System
1,320
$134,000
10
$5,162,778,429
15226
Ontario
New Storage
CLIFTON SPRINGS
THRUWAY SERVICE AREA
/ NYS Thruway Authority
1,643
$208,000
10
$5,162,986,429
Orange County
17579
Orange
NEWBURGH
CONSOLIDATED WD /
Newburgh (T)
Delaware Aqueduct Tap Filatration Plant& Chadwick Lake plant
improvements Phase 2 of 17566, New Surface Water Treatment Rule
Compliance Facility
22,800
$19,650,000
2185
$5,182,636,429
17515
Orange
NEWBURGH CITY /
Newburgh (C)
Phase 2 of project 16754 Cost overrun, Upgrade Water Treatment
Plant, Upgrade Transmission
28,000
$2,577,162
2165
$5,185,213,591
17800
Orange
KIRYAS JOEL VILLAGE /
Kiryas Joel (V)
Water Treatment Plant Well #28 and mitigation of offsite well impacts.
Phase 2 of 16752, New Water Treatment Plant
21,750
$900,000
2130
$5,186,113,591
17449
Orange
HIGHLANDS (T) WD #2 /
Highlands (T)
Phase 2 of DWSRF 16454 to provide well source capacity for Phase 1
which included, Upgrade Water Treatment Plant, New Ground Water
Source, New Storage, Extend Distribution System
1,379
$4,748,700
2095
$5,190,862,291
17461
Orange
PHEASANT HILL /
Pheasant Hill Water Corp
Rehabilitation of water system to address e-coli contamination,
Upgrade Water Treatment Plant, New Ground Water Source, New
Storage
154
$0
1220
$5,190,862,291
BEAVER DAM LAKE
WATER CORP. / Beaver
Dam Lake Corp.
New Surface Water Treatment Rule Compliance Facility, New Ground
Water Source, New Storage, Upgrade Distribution System
487
15072
Orange
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
$0
1215
$5,190,862,291
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
17493
Orange
WARWICK VILLAGE /
Warwick (V)
New Surface Water Treatment Rule Compliance Facility, Upgrade
Water Treatment Plant
6,083
$0
190
$5,190,862,291
18060
Orange
HIGHLANDS WATER
DISTRCIT 2 EXTENTION /
Highlands (T)
Extention of the existing WD #2 to serve private wells with
contamination and consolidation of several PWS's, Extend Distribution
System, Extend System Consolidation
1,379
$1,601,238
155
$5,192,463,529
16751
Orange
KIRYAS JOEL VILLAGE /
Kiryas Joel (V)
Expansion of service area to El Roi Estates, Monroe (T), Extend
Distribution System
21,750
$2,245,040
145
$5,194,708,569
15722
Orange
MONROE WD #8
(SKYVIEW HILLS) / Monroe
(T)
Extend system to serve area with private contaminated wells. ,
Upgrade Distribution System
544
$1,000,000
135
$5,195,708,569
16673
Orange
MIDDLETOWN CITY /
Middletown (C)
New Transmission, New Storage, New Distribution System
26,500
$8,000,000
130
$5,203,708,569
17617
Orange
BLOOMING GROVE WD
#1-WORLEY HE / South
Blooming Grove (V)
Transmission main with treatment plant to connect Water District 1 and
6 to Orange and Rockland Well., New Water Treatment Plant, New
Transmission
1,500
$3,193,000
130
$5,206,901,569
Page 52 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Orange County
15669
Orange
MONROE WD #12
(MONROE HILLS
ESTATES) / Monroe (T)
Upgrade Ground Water Source, Upgrade Pump Station, Upgrade
Distribution System
17986
Orange
PORT JERVIS CITY / Port
Jervis (C)
15227
Orange
16075
120
$1,250,000
125
$5,208,151,569
Addition of clarification, Upgrade Water Treatment Plant
9,000
$3,610,000
115
$5,211,761,569
MAYBROOK VILLAGE /
Maybrook (V)
New Water Treatment Plant, New Ground Water Source
3,093
$238,000
110
$5,211,999,569
Orange
CHESTER VILLAGE /
Chester (V)
Upgrade Water Treatment Plant, New Ground Water Source, Upgrade
Storage, New Storage, New Distribution System
3,448
$2,097,850
110
$5,214,097,419
15819
Orange
KIRYAS JOEL VILLAGE /
Kiryas Joel (V)
Upgrade Water Treatment Plant
21,750
$734,500
105
$5,214,831,919
16591
Orange
GREENVILLE (T) MUNI.L
WATER SYSTEM 'A' /
Greenville (T)
Complete System (New System)
400
$2,319,060
90
$5,217,150,979
17523
Orange
MONTGOMERY W.D. #1 /
Montgomery (T)
Extend WD #1 to consolidate several water supplies, New System
Consolidation
605
$13,500,000
90
$5,230,650,979
17294
Orange
MONROE WATER
DISTRICT / Monroe (T)
Upgrade Ground Water Source, New Transmission, Upgrade
Distribution System
15,000
$6,344,800
90
$5,236,995,779
15718
Orange
MONROE WD #10 - PINE
TREE ROAD / Monroe (T)
New system to serve area with private contaminated wells. , New
Transmission
50
$215,000
75
$5,237,210,779
17413
Orange
WALLKILL
CONSOLIDATED WD /
Wallkill (T)
Rykoski Lane Water Treatment Plant, Upgrade Water Treatment
Plant, New Pump Station, New Pump Station
15,000
$7,000,000
75
$5,244,210,779
17042
Orange
MONROE VILLAGE /
Monroe (V)
Upgrade Distribution System
8,892
$986,000
70
$5,245,196,779
17368
Orange
GOSHEN VILLAGE /
Goshen (V)
New Water Treatment Plant, New Ground Water Source, New
Transmission
5,676
$5,311,500
70
$5,250,508,279
16144
Orange
GOSHEN W.D. #1
(HAMBLETONIAN PARK) /
Goshen (T)
New Ground Water Source, New Storage, Upgrade Distribution System
509
$2,605,900
65
$5,253,114,179
17412
Orange
MONROE WD #12
(MONROE HILLS
ESTATES) / Monroe (T)
Upgrade Water Treatment Plant, New Surface Water Source, Upgrade
Storage
120
$1,370,930
65
$5,254,485,109
16027
Orange
BLOOMING GROVE WD
#1-WORLEY HE / Blooming
Grove (T)
New Ground Water Source, Upgrade Storage
1,500
$392,000
65
$5,254,877,109
15816
Orange
KIRYAS JOEL VILLAGE /
Kiryas Joel (V)
New Storage
21,750
$1,000,000
60
$5,255,877,109
16906
Orange
KIRYAS JOEL VILLAGE /
Kiryas Joel (V)
Pump Station and transmission main from NYC Aqueduct to (V) K.J.,
New Transmission, New Pump Station
21,750
$28,907,400
55
$5,284,784,509
17952
Orange
KIRYAS JOEL VILLAGE /
Kiryas Joel (V)
Redevelop wells at the Star Expansion Well Field, Upgrade Ground
Water Source
21,750
$1,658,712
55
$5,286,443,221
17950
Orange
KIRYAS JOEL VILLAGE /
Kiryas Joel (V)
New wells on Site 1, Site 2, Site 3, Site 4, Site 5, New Ground Water
Source
21,750
$14,246,909
55
$5,300,690,130
17951
Orange
KIRYAS JOEL VILLAGE /
Kiryas Joel (V)
Redevelopment of Wells 6 and 13A and new well at Well 13 Well Field,
New Ground Water Source, Upgrade Ground Water Source
21,750
$3,805,747
55
$5,304,495,877
Page 53 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Orange County
16749
Orange
KIRYAS JOEL VILLAGE /
Kiryas Joel (V)
Upgrade Pump Station
15078
Orange
HOLIDAY MOBILE PARK
INC. / Mid-Hudson Park
Management
Upgrade Distribution System, System Consolidation
17450
Orange
HIGHLANDS (T) WD #3 /
Highlands (T)
New Water District
16150
Orange
WARWICK (T) / Warwick
(T)
New Storage, Upgrade Pump Station, Upgrade Distribution System,
System Consolidation
17994
Orange
DEERPARK WATER
DISTRICT #1 / Deerpark (T)
New water system, New Complete System (New System)
17293
Orange
WAYAWANDA WD #1 /
Wawayanda (T)
Extend Distribution System
16321
Orange
NEWBURGH CITY /
Newburgh (C)
Grand Street waterline replacement and lead service removal,
Upgrade Distribution System
15229
Orange
SLEEPY HOLLOW MOBILE
PARK / Sleepy Hollow MHP,
LLC
16036
Orange
17348
21,750
$872,247
45
$5,305,368,124
250
$412,000
45
$5,305,780,124
1,548
$8,105,700
45
$5,313,885,824
300
$312,500
45
$5,314,198,324
2,000
$6,180,000
45
$5,320,378,324
50
$208,941
45
$5,320,587,265
28,000
$4,635,000
40
$5,325,222,265
Upgrade Transmission, Upgrade Distribution System
400
$386,250
40
$5,325,608,515
BLOOMING GROVE WD
#3-TOMAHAWK / Blooming
Grove (T)
New Ground Water Source
208
$306,000
40
$5,325,914,515
Orange
BELLVALE PARK W.D. /
Warwick (T)
Replace wells, upgrade pump house and storage, New Ground Water
Source, Upgrade Pump Station
100
$453,200
40
$5,326,367,715
18056
Orange
WARWICK VILLAGE /
Warwick (V)
Upgrade Water Treatment Plant, New Ground Water Source
6,083
$323,725
35
$5,326,691,440
15440
Orange
NEW WINDSOR
CONSOLIDATED WD /
Windsor (T)
New Storage
30,000
$154,500
35
$5,326,845,940
16147
Orange
WESTSIDE GREENWOOD
LAKE W.D. / Warwick (T)
Upgrade Distribution System
1,160
$100,000
35
$5,326,945,940
15182
Orange
WOODBURY CONS. W.D. /
Woodbury (T)
New Storage, New Pump Station, Upgrade Distribution System
10,105
$1,564,500
35
$5,328,510,440
16312
Orange
NEWBURGH CITY /
Newburgh (C)
Upgrade Distribution System
28,000
$1,545,000
35
$5,330,055,440
15666
Orange
ORCHARD HILL ESTATES
/ Orchard Hill Water Co. Inc.
Upgrade Ground Water Source, New Storage, Upgrade Distribution
System
196
$1,123,730
30
$5,331,179,170
15635
Orange
WASHINGTONVILLE
VILLAGE / Washingtonville
(V)
Upgrade Ground Water Source, Upgrade Distribution System
7,000
$435,000
30
$5,331,614,170
17602
Orange
GREENWOOD LAKE
VILLAGE / Greenwood Lake
(V)
Upgrade Water Treatment Plant
3,411
$395,520
30
$5,332,009,690
17159
Orange
KNOLLS WATER CO., INC.
/ Knolls Water Company
New Ground Water Source, Upgrade Storage, New Pump Station
230
$250,000
25
$5,332,259,690
15674
Orange
SCOTT ACRES / Scott
Acres Water Co.
New Water Treatment Plant, New Ground Water Source, Upgrade
Distribution System
117
$168,920
25
$5,332,428,610
Page 54 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Orange County
15471
Orange
NEW WINDSOR
CONSOLIDATED WD /
Windsor (T)
New Pump Station
30,000
$515,000
25
$5,332,943,610
15465
Orange
NEW WINDSOR
CONSOLIDATED WD /
Windsor (T)
Water filter plant expansion 3 mgd to 6 mgd, Upgrade Water
Treatment Plant
30,000
$15,450,000
25
$5,348,393,610
16621
Orange
HARRIMAN VILLAGE /
Harriman (V)
River Road Pump Station, New Ground Water Source, New Pump
Station
4,500
$128,750
25
$5,348,522,360
15228
Orange
PINE GROVE MOBILE
HOME PARK / Pine Grove
MHP, LLC
New Water Treatment Plant, Upgrade Transmission, New Storage,
Upgrade Distribution System
516
$484,100
25
$5,349,006,460
16389
Orange
NEWBURGH
CONSOLIDATED WD /
Newburgh (T)
Upgrade Pump Station
22,800
$120,000
25
$5,349,126,460
15966
Orange
CORNWALL-ON-HUDSON / Upgrade Water Treatment Plant
Cornwall-On-Hudson (V)
9,300
$2,935,257
25
$5,352,061,717
17038
Orange
WARWICK VILLAGE /
Warwick (V)
Upgrade Storage
6,083
$263,433
20
$5,352,325,150
16529
Orange
WHITLOCK FARMS /
Whitlock Farms Water Corp.
New Water Treatment Plant, Upgrade Distribution System
100
$83,740
20
$5,352,408,890
17977
Orange
NEW WINDSOR
CONSOLIDATED WD / New
Windsor (T)
Rehabilitate St. Anne Well Field, Upgrade Water Treatment Plant,
Upgrade Ground Water Source
30,000
$748,000
20
$5,353,156,890
17816
Orange
NEW WINDSOR
CONSOLIDATED WD / New
Winsor (T)
Reactivation of St. Anne's Well, Upgrade Ground Water Source
30,000
$748,000
20
$5,353,904,890
15175
Orange
WOODBURY CONS. W.D. /
Woodbury (T)
New Ground Water Source, New Pump Station
10,105
$291,500
20
$5,354,196,390
17565
Orange
BRITTANY TERRACE /
Brittany Terrace, Inc.
New water storage tank, New Storage
169
$215,000
20
$5,354,411,390
17551
Orange
ARLUCK WATER
DISTRICT / Wawayanda (T)
Replacement of existing hydropneumatic system for the Arluck WD,
Upgrade Pump Station
118
$85,000
20
$5,354,496,390
16424
Orange
WARWICK VILLAGE /
Warwick (V)
Taste & odor control, Upgrade Water Treatment Plant
6,083
$100,000
20
$5,354,596,390
17400
Orange
HIGHLAND FALLS
VILLAGE / Highland Falls
(V)
Water Treatment Plant Filter Upgrades, Upgrade Water Treatment
Plant
4,400
$800,000
20
$5,355,396,390
17346
Orange
WOODBURY CONS. W.D. /
Woodbury (T)
Repaint Overlook Storage Tank, Upgrade Storage
10,105
$218,360
20
$5,355,614,750
15951
Orange
VALLEY VIEW CTR FOR
NURSING CARE & REHAB
/ Orange County
New Water Treatment Plant, New Ground Water Source, New Storage,
Upgrade Distribution System
851
$572,474
20
$5,356,187,224
17291
Orange
PINE BUSH WATER
DISTRICT / Crawford (T)
New Ground Water Source
7,000
$165,000
20
$5,356,352,224
15178
Orange
WOODBURY CONS. W.D. /
Woodbury (T)
New Water Treatment Plant, New Ground Water Source
10,105
$2,127,000
20
$5,358,479,224
17131
Orange
TUXEDO PARK VILLAGE /
Tuxedo Park (V)
Upgrade Distribution System
1,100
$263,000
15
$5,358,742,224
Page 55 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Orange County
15398
Orange
WASHINGTONVILLE
VILLAGE / Washingtonville
(V)
New Ground Water Source
7,000
$300,000
15
$5,359,042,224
15458
Orange
FLORIDA VILLAGE / Florida
(V)
New Storage
2,757
$515,000
15
$5,359,557,224
16594
Orange
CAMPBELLS WATER
SUPPLY / Campbells Water
Supply
Upgrade Pump Station
40
$115,000
15
$5,359,672,224
15405
Orange
WASHINGTONVILLE
VILLAGE / Washingtonville
(V)
Upgrade Water Treatment Plant
7,000
$50,000
15
$5,359,722,224
15396
Orange
NEW WINDSOR
CONSOLIDATED WD / New
Windsor (T)
Water treatment plant modification raw water treatment, Upgrade
Water Treatment Plant
30,000
$8,050,000
15
$5,367,772,224
17916
Orange
GREENWOOD LAKE (V) /
Greenwood Lake (V)
Cleaning and painting storage tank, Upgrade Storage
3,400
$245,660
15
$5,368,017,884
16548
Orange
WALDEN VILLAGE /
Walden (V)
New Storage
6,164
$716,500
15
$5,368,734,384
17843
Orange
TUXEDO PARK (V) /
Tuxedo (V)
West Lake Road Transmission Line, Upgrade Transmission
1,100
$487,000
15
$5,369,221,384
17841
Orange
TUXEDO PARK (V) /
Tuxedo (V)
East Village Transmission Line Replacement, Upgrade Transmission
1,100
$987,000
15
$5,370,208,384
17842
Orange
TUXEDO PARK (V) /
Tuxedo (V)
Trans-Tuxedo Lake Transmission Line, Upgrade Transmission
1,100
$757,000
15
$5,370,965,384
17835
Orange
MONTGOMERY (V) /
Montgomery (V)
New Storage Tank, New Storage
3,696
$825,030
15
$5,371,790,414
15404
Orange
WASHINGTONVILLE
VILLAGE / Washingtonville
(V)
New Storage
7,000
$665,000
15
$5,372,455,414
16391
Orange
NEWBURGH
CONSOLIDATED WD /
Newburgh (T)
Upgrade Storage
22,800
$45,000
15
$5,372,500,414
17316
Orange
HIGHLAND FALLS
VILLAGE / Highland Falls
(V)
Upgrade Water Treatment Plant
4,400
$464,500
15
$5,372,964,914
17290
Orange
WOODBURY CONS. W.D. /
Woodbury (T)
Upgrade Storage
10,105
$218,360
15
$5,373,183,274
16141
Orange
MONROE VILLAGE /
Monroe (V)
Water meter replacement, Other Expenses, Other (OT)
8,892
$679,800
10
$5,373,863,074
15400
Orange
WASHINGTONVILLE
VILLAGE / Washingtonville
(V)
Upgrade Distribution System
7,000
$1,500,000
10
$5,375,363,074
16545
Orange
WALDEN VILLAGE /
Walden (V)
Upgrade Distribution System
6,164
$1,545,000
10
$5,376,908,074
16547
Orange
WALDEN VILLAGE /
Walden (V)
Replacement of all water meters., Upgrade Other Expenses, Upgrade
Other (OT)
6,164
$536,500
10
$5,377,444,574
16546
Orange
WALDEN VILLAGE /
Walden (V)
New Ground Water Source
6,164
$865,000
10
$5,378,309,574
Page 56 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Orange County
17818
Orange
WASHINGTONVILLE
VILLAGE / Washingtonville
(V)
Replace watermains in Dutch Arms area., Upgrade Distribution
System
7,000
$1,654,700
10
$5,379,964,274
17817
Orange
WASHINGTONVILLE
VILLAGE / Washingtonville
(V)
Watermain replacement Patricia and Beverly Lane, Upgrade
Distribution System
7,000
$961,000
10
$5,380,925,274
16451
Orange
NEW WINDSOR
CONSOLIDATED WD / New
Windsor (T)
Upgrade Distribution System
30,000
$618,500
10
$5,381,543,774
16031
Orange
BLOOMING GROVE WD
#4-TAPPAN HO / Blooming
Grove (T)
New Ground Water Source
500
$97,000
10
$5,381,640,774
15180
Orange
WOODBURY CONS. W.D. /
Woodbury (T)
Upgrade Distribution System
10,105
$528,000
10
$5,382,168,774
17644
Orange
KINGS ESTATES / Warwick
Water Corp
Upgrade distribution system., Upgrade Distribution System
1,144
$125,000
10
$5,382,293,774
16179
Orange
MONROE VILLAGE /
Monroe (V)
Repainting of two water storage tanks, Upgrade Storage
8,892
$134,415
10
$5,382,428,189
16153
Orange
MONROE VILLAGE /
Monroe (V)
500,000 gallon water storage tank, New Storage
8,892
$457,552
10
$5,382,885,741
16076
Orange
CHESTER VILLAGE /
Chester (V)
New Storage
3,448
$566,500
10
$5,383,452,241
16392
Orange
NEWBURGH
CONSOLIDATED WD /
Newburgh (T)
New water quality monitoring equipment, Other Expenses, Other (OT)
22,800
$20,000
10
$5,383,472,241
16035
Orange
BLOOMING GROVE WD
#3-TOMAHAWK / Blooming
Grove (T)
New Ground Water Source
208
$99,000
10
$5,383,571,241
16034
Orange
BLOOMING GROVE WD
#3-TOMAHAWK / Blooming
Grove (T)
New Ground Water Source
208
$99,000
10
$5,383,670,241
16369
Orange
BRAESIDE AQUA
CORPORATION / Braeside
Aqua Corp.
Upgrade Distribution System
330
$500,000
10
$5,384,170,241
16143
Orange
MONROE VILLAGE /
Monroe (V)
Barnett Rd, East & West, Upgrade Distribution System
8,892
$2,626,696
5
$5,386,796,937
16484
Orange
HIGHLAND FALLS
VILLAGE / Highland Falls
(V)
Upgrade Distribution System
4,400
$233,100
5
$5,387,030,037
15347
Orange
PINE BUSH WATER
DISTRICT / Crawford (T)
New Ground Water Source
7,000
$124,500
5
$5,387,154,537
15234
Orange
GOSHEN VILLAGE /
Goshen (V)
Upgrade Water Treatment Plant
5,676
$417,850
5
$5,387,572,387
15937
Orange
MONROE VILLAGE /
Monroe (V)
New Ground Water Source
8,892
$379,555
5
$5,387,951,942
16148
Orange
MONROE VILLAGE /
Monroe (V)
Round Lake Park, Upgrade Distribution System
8,892
$854,902
5
$5,388,806,844
16388
Orange
NEWBURGH
CONSOLIDATED WD /
Newburgh (T)
Upgrade Distribution System
22,800
$80,000
5
$5,388,886,844
Page 57 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Orange County
15963
Orange
CORNWALL-ON-HUDSON / Upgrade Distribution System
Cornwall-On-Hudson (V)
9,300
$520,000
5
$5,389,406,844
Orleans County
16032
Orleans
HOLLEY VILLAGE / Holley
(V)
New Ground Water Source, New Pump Station, Upgrade Distribution
System
2,150
$456,000
130
$5,389,862,844
16381
Orleans
LYNDONVILLE VILLAGE /
Lyndonville (V)
Upgrade Transmission, Upgrade Distribution System
1,418
$1,612,864
75
$5,391,475,708
15183
Orleans
SHELBY (T) / Shelby (T)
Extend system to serve area with private contaminated wells. Water
Improvement No. 4 - Phase I., Extend Distribution System
240
$249,700
65
$5,391,725,408
15185
Orleans
TOWN OF SHELBY /
Shelby (T)
Water Improvement No. 4 - Phase II., Extend Distribution System
240
$166,500
65
$5,391,891,908
17097
Orleans
MEDINA VILLAGE / Medina
(V)
Upgrade Distribution System
6,500
$4,088,085
60
$5,395,979,993
15168
Orleans
MURRAY W.D. #1 / Murray
(T)
Extend Distribution System
225
$154,677
60
$5,396,134,670
15166
Orleans
GAINES W.D. #1 / Gaines
(T)
Extend Distribution System
1,152
$531,885
60
$5,396,666,555
15165
Orleans
CLARENDON W.D. #1 /
Clarendon (T)
Extension to Water District No. 3., Extend Distribution System
600
$1,008,000
50
$5,397,674,555
15164
Orleans
BARRE W.D. #1 / Barre (T)
Extend Distribution System
375
$473,800
50
$5,398,148,355
15167
Orleans
KENDALL W.D. #1 / Kendall
(T)
Extend Distribution System
1,418
$581,950
50
$5,398,730,305
17723
Orleans
WATER SYS.
IMPROVEMENTS /
Clarendon (T)
New Distribution System, Upgrade Distribution System
54
$129,000
45
$5,398,859,305
17262
Orleans
HOLLEY VILLAGE / Holley
(V)
NYS Route 31., Upgrade Distribution System
2,150
$210,243
35
$5,399,069,548
15741
Orleans
CARLTON WATER
DISTRICT / Carlton (T)
Upgrade Transmission
2,800
$250,000
15
$5,399,319,548
18068
Orleans
WATER IMPROVEMENT
BENEFIT AREA #10 /
Clarendon (T)
Extend Distribution System
250
$1,634,949
5
$5,400,954,497
HANNIBAL (T) / Hannibal
(T)
Extend system to serve area with private contaminated wells,
consolidate public water supply. , Extend Distribution System, New
System Consolidation
1,200
1210
$5,400,954,497
TOAD
HARBOR/CONSTANTIA
WD / Constantia (T)
New Surface Water Treatment Rule Compliance Facility, New Storage,
New Pump Station, New Distribution System, New Inter-Connection,
New System Consolidation
2,765
WATER DISTRICT #2 /
Richland (T)
New Surface Water Treatment Rule Compliance Facility, New Ground
Water Source, New Transmission, New Storage, New Distribution
System
1,662
Consolidation of PWS with GWDI source., New Storage, New
Distribution System, New System Consolidation
2,503
Oswego County
15204
16261
17538
17625
Oswego
Oswego
Oswego
Oswego
EASTERN SHORE WATER
SYSTEM / Sandy Creek (T)
Page 58 of 86
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
$0
1200
$5,400,954,497
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
$0
1200
$5,400,954,497
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
$13,988,000
200
$5,414,942,497
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Oswego County
17372
Oswego
MEXICO (T) WD#2 /
Mexico (T)
Extend distribution system to area with contaminated private wells and
consolidate PWS with GWUDI source, New Distribution System, New
System Consolidation
800
$7,060,000
200
$5,422,002,497
17685
Oswego
ORWELL WD / Orwell (T)
New Surface Water Treatment Rule Compliance Facility
150
$115,102
135
$5,422,117,599
17597
Oswego
AREA 1 WATER SYSTEM /
Schroeppel (T)
Address organic contaminant violations, New Distribution System, New
System Consolidation
3,200
$11,312,382
130
$5,433,429,981
17594
Oswego
ROUTE 11
NORTH/FULLER ROAD
WD PHASE D / Hastings (T)
Extend distribution system to area of insufficient yielding or
cantaminated private wells., Extend Distribution System, New System
Consolidation
1,200
$3,106,480
120
$5,436,536,461
17564
Oswego
BERNHARDS BAY WD /
Constantia (T)
Extend Distribution System, New System Consolidation
790
$5,890,000
95
$5,442,426,461
17598
Oswego
AREA 3,4 & 8 WATER
SYSTEM / Schroeppel (T)
New Distribution System, New System Consolidation
1,500
$7,678,916
90
$5,450,105,377
17858
Oswego
WD#3 EXPANSION /
Granby (T)
Extend Distribution System
238
$5,315,041
85
$5,455,420,418
17510
Oswego
NORTH AREA WD / Volney
(T)
New Distribution System, New System Consolidation
1,000
$6,604,000
80
$5,462,024,418
16314
Oswego
MINETTO TOWN WATER
DISTRICT / Minetto (T)
Extend Distribution System
1,589
$412,000
70
$5,462,436,418
16903
Oswego
PARISH (V) / Parish (V)
New Complete System (New System)
600
$2,980,000
60
$5,465,416,418
17285
Oswego
HANNIBAL TOWN WATER
DISTRICT #2 / Hannibal (T)
Extend Distribution System
2,000
$1,715,000
60
$5,467,131,418
18010
Oswego
TOWN/VILLAGE JOINT
WATER PROJECT / Parish
(T)
Serve private contaminated/poor yielding wells., Extend Distribution
System
1,200
$10,150,000
55
$5,477,281,418
16978
Oswego
OSWEGO CITY / Oswego
(C)
Upgrade Water Treatment Plant
29,400
$4,532,000
50
$5,481,813,418
16205
Oswego
SENECA HILLS HEALTH
CAMPUS / Volney (T)
Upgrade Distribution System
450
$1,115,000
50
$5,482,928,418
16173
Oswego
PONDEROSA TRAILER
PARK, INC. / Ponderosa
Trailer Park Inc.
Upgrade Water Treatment Plant
60
$17,400
50
$5,482,945,818
18062
Oswego
CLEVELAND VILLAGE /
Cleveland (V)
Upgrade Ground Water Source, Upgrade Storage, Upgrade
Distribution System
925
$1,576,930
50
$5,484,522,748
15833
Oswego
TOWN OF WEST MONROE
/ West Monroe (T)
New Complete System (New System), Extend Distribution System
500
$979,000
50
$5,485,501,748
15677
Oswego
FULTON CITY / Fulton (C)
Upgrade Storage
15,400
$412,000
40
$5,485,913,748
17187
Oswego
OSWEGO CITY / Oswego
(C)
Upgrade Distribution System
29,400
$734,367
35
$5,486,648,115
15681
Oswego
FULTON CITY / Fulton (C)
Upgrade Pump Station
15,400
$82,700
35
$5,486,730,815
Page 59 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Oswego County
15690
Oswego
FULTON CITY / Fulton (C)
Upgrade Distribution System
16138
Oswego
PHOENIX VILLAGE /
Phoenix (V)
State Street water main replacement., Upgrade Distribution System
17302
Oswego
PULASKI VILLAGE / Pulaski New Transmission, Upgrade Distribution System
(V)
15686
Oswego
FULTON CITY / Fulton (C)
15683
Oswego
16600
15,400
$720,000
35
$5,487,450,815
2,138
$90,125
35
$5,487,540,940
2,398
$762,200
35
$5,488,303,140
New Storage
15,400
$1,000,000
30
$5,489,303,140
FULTON CITY / Fulton (C)
Upgrade Ground Water Source
15,400
$2,300,000
30
$5,491,603,140
Oswego
MEXICO VILLAGE / Mexico
(V)
New Storage
1,600
$1,000,000
30
$5,492,603,140
17965
Oswego
RICHLAND TOWN PWS /
Richland (T)
Wind power generation at Schoeller well site.,
2,350
$585,000
25
$5,493,188,140
15784
Oswego
GRANBY (T) -HANNIBAL
STREET / Granby (T)
New Complete System (New System), Upgrade Distribution System
50
$195,000
20
$5,493,383,140
UNADILLA VILLAGE /
Unadilla (V)
Install new well, pumphouse, controls, chlorination system to replace
GWUDI springs, New Surface Water Treatment Rule Compliance
Facility, New Ground Water Source, Upgrade Pump Station, Upgrade
Distribution System
1215
$5,493,383,140
Otsego County
15343
Otsego
1,350
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
15254
Otsego
EDMESTON WATER
DISTRICT / Edmeston (T)
Upgrade Ground Water Source, Upgrade Transmission, Upgrade
Distribution System
490
$2,065,150
165
$5,495,448,290
16146
Otsego
MILFORD VILLAGE /
Milford (V)
Address nitrate contamination, New Ground Water Source, Upgrade
Distribution System
510
$3,502,000
130
$5,498,950,290
18067
Otsego
GILBERTSVILLE VILLAGE /
Gilbertsville (V)
New Ground Water Source, New Storage, Upgrade Distribution System
477
$3,865,000
100
$5,502,815,290
17093
Otsego
HARTWICK WATER
DISTRICT / Hartwick (T)
WD
New Ground Water Source, New Storage, Upgrade Distribution System
416
$1,745,850
95
$5,504,561,140
17092
Otsego
LAURENS VILLAGE /
Laurens (V)
New Storage, Upgrade Distribution System
381
$1,236,000
60
$5,505,797,140
17987
Otsego
ONEONTA (T) / Oneonta (T) Southside Water System., New Ground Water Source, New Complete
1,570
$8,808,000
60
$5,514,605,140
17976
Otsego
SOUTHSIDE WATER
SYSTEM / Oneonta (T)
New Complete System (New System), New Water District
1,570
$8,808,000
60
$5,523,413,140
17926
Otsego
WEST ONEONTA WATER
DISTRICT / Oneonta (T)
New Complete System (New System)
520
$4,996,000
60
$5,528,409,140
16335
Otsego
MORRIS VILLAGE / Morris
(V)
New Water Treatment Plant, New Ground Water Source, New Storage
642
$268,500
40
$5,528,677,640
16255
Otsego
GILBERTSVILLE VILLAGE /
Gilbertsville (V)
Upgrade Water Treatment Plant, Upgrade Distribution System
477
$206,200
40
$5,528,883,840
15079
Otsego
MILL CREEK AT
RIVERSIDE, LLC MHP /
Riverside Village MHP
Upgrade Distribution System
145
$20,600
25
$5,528,904,440
System (New System), New Storage, New Distribution System, New
Water District
Page 60 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Putnam County
15862
Putnam
SPRINGHOUSE ESTATES
W.W. CORP. / Southeast
(T)
New Ground Water Source, New Storage
212
$1,700,500
200
$5,530,604,940
16598
Putnam
BREWSTER HEIGHTS /
Southeast (T)
Remaining portion of 15857 which was funded 3/26/98., New Water
Treatment Plant
698
$689,650
155
$5,531,294,590
18072
Putnam
GIPSY TRAIL CLUB / Gipsy
Trail Club Inc
Develop additional well source capacity, New Ground Water Source,
New Pump Station
300
$430,540
150
$5,531,725,130
17298
Putnam
BREWSTER VILLAGE /
Brewster (V)
New Ground Water Source, New Pump Station
2,000
$1,610,920
80
$5,533,336,050
16634
Putnam
KENT (T) WD #3 / Kent (T)
New Water Treatment Plant, New Ground Water Source, New Storage,
New Pump Station, New Distribution System
8,000
$15,235,451
75
$5,548,571,501
17790
Putnam
PUTNAM VALLEY (T) /
Putnam Valley (T)
New water system for Croft Corners area, New Complete System
(New System)
11,500
$25,755,000
70
$5,574,326,501
16579
Putnam
WILLIAMSBURG RIDGE
CONDO W.S. /
Williamsburg Ridge HOA,
Inc.
Wiiliamsburg Ridge Condominiums, Mahopac, NY, New Ground Water
Source
230
$40,000
60
$5,574,366,501
16083
Putnam
MILL POND WATER
SUPPLY / Mill Ponds Water
Co.
New Ground Water Source
70
$100,000
60
$5,574,466,501
15430
Putnam
BREWSTER VILLAGE /
Brewster (V)
New Storage
2,000
$1,628,000
50
$5,576,094,501
17319
Putnam
MOUNTAIN BROOK
HOMES / Southeast (T)
New Water Treatment Plant, New Ground Water Source
176
$427,000
50
$5,576,521,501
17601
Putnam
GARRISON LANDING WS /
Philipstown (T)
New Complete System (New System)
84
$325,146
45
$5,576,846,647
17297
Putnam
BREWSTER VILLAGE /
Brewster (V)
Upgrade Distribution System
2,000
$8,102,487
45
$5,584,949,134
16633
Putnam
KENT WD 2 / Kent (T)
Upgrade Water Treatment Plant, Upgrade Storage, Upgrade Pump
Station, Upgrade Distribution System
276
$927,000
20
$5,585,876,134
16632
Putnam
KENT WD 1 / Kent (T)
Upgrade Water Treatment Plant, Upgrade Storage, Upgrade Pump
Station, Upgrade Distribution System
360
$1,152,261
20
$5,587,028,395
18041
Putnam
COLD SPRING VILLAGE /
Cold Spring (V)
Upgrade Transmission
2,666
$958,000
20
$5,587,986,395
15792
Putnam
CONTINENTAL VILLAGE
WD / Philipstown (T)
Upgrade Distribution System
1,509
$1,350,000
15
$5,589,336,395
16506
Putnam
GLENMAR GARDENS
IMPROVMT DIST / Putnam
Valley (T)
Upgrade Distribution System
130
$25,500
15
$5,589,361,895
17411
Putnam
SUNRISE RIDGE / Sunrise
Ridge Water Company
Replace pumps and storage, Upgrade Storage, Upgrade Pump Station
178
$250,000
15
$5,589,611,895
17854
Putnam
SOUTHEAST (T)
PEACEABLE WATER
DISTRICT / Southeast (T)
Development new water source instead of continuing to purchase from
Brewster (V), New Ground Water Source
440
$1,700,000
5
$5,591,311,895
HOOSICK FALLS (V) PWS /
Hoosick Falls (V)
Phase 2 of Project 15080 , Upgrade Storage, Upgrade Distribution
System
4,000
$640,000
2225
$5,591,951,895
Rensselaer County
18029
Rensselaer
Page 61 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Rensselaer County
17936
Rensselaer
BRUNSWICK WATER
DISTRICT # 6 / Brunswick
(T)
Distribution Modifications for Flow & Pressure Improvements to Support
Consecutive System; Emergency Generator, Upgrade Pump Station,
Upgrade Distribution System
17331
Rensselaer
POESTENKILL (T) WD #1 /
Poestenkill (T)
15749
Rensselaer
RENSSELAER CITY PWS /
Rensselaer (C)
17068
Rensselaer
SCHAGHTICOKE (V) PWS / Upgrade Water Treatment Plant, Upgrade Storage, Upgrade
Distribution System, Extend Distribution System
Schaghticoke (V)
17358
Rensselaer
SCHODACK WATER
DISTRICT # 3 / Schodack
(T)
17445
Rensselaer
17077
927
$504,000
185
$5,592,455,895
New Complete System (New System), New System Consolidation
2,300
$0
185
$5,592,455,895
New Storage, New Distribution System, System Consolidation
7,500
$7,175,300
145
$5,599,631,195
675
$6,585,700
115
$5,606,216,895
Connect WD #3 (Maple Crest) to WD #1 (Clearview), Extend
Distribution System, New System Consolidation
140
$0
105
$5,606,216,895
NORTH GREENBUSH (T)
WATER DISTRICT NO. 18 /
North Greenbush (T)
Purchase existing Private Water System, Connect to Municipal Water
System , New System Consolidation, New Water District
212
$437,750
85
$5,606,654,645
Rensselaer
NORTH GREENBUSH WD
#13 / North Greenbush (T)
New system to serve area with private contaminated wells (Snyder's
Lake Area). , New System Consolidation, New Water District
1,050
$4,635,000
80
$5,611,289,645
15580
Rensselaer
CASTLETON VILLAGE
PWS / Castleton-on-Hudson
(V)
Upgrade Ground Water Source, Upgrade Transmission, Upgrade
Pump Station, Upgrade Distribution System
2,013
$2,000,000
80
$5,613,289,645
17139
Rensselaer
EAST GREENBUSH
GENERAL W.D. / East
Greenbush (T)
Upgrade Storage, New Storage
10,200
$3,279,680
75
$5,616,569,325
17229
Rensselaer
NORTH GREENBUSH WD
#14 / North Greenbush (T)
New system to serve inadequate private wells in Northeast corner of
Town , New Inter-Connection, New System Consolidation, New Water
District
3,000
$7,313,000
75
$5,623,882,325
15688
Rensselaer
HOOSICK (T) WD / Hoosick
(T)
Extend Distribution System
400
$1,544,000
70
$5,625,426,325
15907
Rensselaer
TOWN OF SAND LAKE /
Sand Lake (T)
New Complete System (New System)
5,100
$4,738,000
70
$5,630,164,325
15709
Rensselaer
TROY CITY PWS / Troy (C)
New Transmission, Upgrade Distribution System, System
Consolidation
49,170
$387,500
60
$5,630,551,825
17149
Rensselaer
PETERSBURGH WATER
DISTRICT / Petersburgh (T)
Upgrade Water Treatment Plant, New Ground Water Source, Upgrade
Distribution System
240
$842,025
45
$5,631,393,850
16302
Rensselaer
GRAFTON WATER
SYSTEM / Grafton (T)
New Complete System (New System)
1,700
$1,905,000
45
$5,633,298,850
15286
Rensselaer
SCHAGHTICOKE OLD
WATER DISTRICT #1
INACT / Schaghticoke (T)
Extend Distribution System
1,710
$215,644
40
$5,633,514,494
17867
Rensselaer
TROY CITY PWS / Troy (C)
New Transmission
49,170
$1,030,000
40
$5,634,544,494
15216
Rensselaer
VALLEY FALLS WATER
SYSTEM / Valley Falls (V)
New Ground Water Source, New Storage, Upgrade Distribution System
538
$2,277,000
40
$5,636,821,494
17387
Rensselaer
TROY CITY PWS / Troy (C)
Upgrade Distribution System
49,170
$736,000
40
$5,637,557,494
18030
Rensselaer
RENSSELAER CITY PWS /
Rensselaer (C)
Washington Ave Corridor Improvements, Upgrade Distribution System
7,500
$3,169,952
35
$5,640,727,446
Page 62 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Rensselaer County
17967
Rensselaer
TROY CITY PWS / Troy (C)
Installation of leak detection equipment.,
16073
Rensselaer
PETERSBURGH WATER
DISTRICT / Petersburg (T)
Upgrade Ground Water Source
16303
Rensselaer
TROY CITY PWS / Troy (C)
15752
Rensselaer
15766
49,170
$450,000
35
$5,641,177,446
240
$109,154
35
$5,641,286,600
Upgrade Distribution System
49,170
$2,100,000
35
$5,643,386,600
EAST GREENBUSH
GENERAL W.D. / East
Greenbush (T)
Distribution improvements installing four (4) pressure regulators,
Upgrade Distribution System
10,200
$146,200
30
$5,643,532,800
Rensselaer
EAST GREENBUSH
GENERAL W.D. / East
Greenbush (T)
Hampton Manor upper service area, Upgrade Distribution System
10,200
$187,500
25
$5,643,720,300
15771
Rensselaer
EAST GREENBUSH
GENERAL W.D. / East
Greenbush (T)
Distribution improvements to the Hampton Manor lower service area,
Upgrade Distribution System
10,200
$139,000
20
$5,643,859,300
16334
Rensselaer
HOOSICK FALLS (V) PWS /
Hoosick Falls (V)
Upgrade Distribution System
4,000
$569,000
20
$5,644,428,300
16292
Rensselaer
BRUNSWICK WATER
SYSTEM / Brunswick (T)
New Water Treatment Plant, Upgrade Distribution System
10,000
$2,896,500
20
$5,647,324,800
15687
Rensselaer
EAST GREENBUSH
GENERAL W.D. / East
Greenbush (T)
New Storage
10,200
$757,000
20
$5,648,081,800
17966
Rensselaer
SCHAGHTICOKE (V) PWS / Installation of water meters.,
Schaghticoke (V)
675
$75,000
20
$5,648,156,800
15410
Rensselaer
BERLIN WATER DISTRICT
# 2 / Berlin (T)
Upgrade Distribution System
700
$1,232,004
20
$5,649,388,804
16149
Rensselaer
SCHAGHTICOKE (V) PWS / Upgrade Storage, Upgrade Pump Station
Schaghticoke (V)
675
$581,198
20
$5,649,970,002
17506
Rensselaer
NASSAU (V) PWS / Nassau
(V)
Upgrade Storage
1,250
$133,190
20
$5,650,103,192
15717
Rensselaer
EAST GREENBUSH
GENERAL W.D. / East
Greenbush (T)
Distribution extension, loop water main on Gilligan Road to Hays Road,
Upgrade Distribution System
10,200
$409,000
15
$5,650,512,192
17539
Rensselaer
CASTLETON VILLAGE
PWS / Castleton-on-Hudson
(V)
Replacement in-kind of aged water mains., Upgrade Distribution
System
2,013
$1,661,400
15
$5,652,173,592
15679
Rensselaer
EAST GREENBUSH
GENERAL W.D. / East
Greenbush (T)
Distribution extension loop on Red Mill Road and loop through OC
Zoning District, Extend Distribution System
10,200
$2,791,000
10
$5,654,964,592
15564
Rensselaer
NASSAU (V) PWS / Nassau
(V)
Upgrade Distribution System
1,250
$258,600
10
$5,655,223,192
17781
Rensselaer
WATER DISTRICT 15 /
North Greenbush (T)
Extend Distribution System
4,000
$9,785,000
5
$5,665,008,192
Rockland County
16298
Rockland
NYACK VILLAGE WATER
SUPPLY / Nyack (V)
Relocation of intake to correct turbidity violations., New Transmission
14,700
$1,340,000
110
$5,666,348,192
17313
Rockland
LAKE WELCH BEACH W.S.
/ Palisades Interstate Park
Comm
New Water Treatment Plant, New Transmission
15,000
$20,000,000
100
$5,686,348,192
Page 63 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Rockland County
17777
Rockland
UNITED WATER NEW
YORK / United Water NY
Membrand Filtration at Pascack 65 Wel, Upgrade Water Treatment
Plant
270,000
$1,390,500
15
$5,687,738,692
17779
Rockland
UNITED WATER NEW
YORK / United Water NY
Construction of 2 MGD pump station, Upgrade Pump Station
270,000
$2,368,084
15
$5,690,106,776
16018
Rockland
SUFFERN VILLAGE /
Suffern (V)
Upgrade Distribution System
12,000
$603,600
5
$5,690,710,376
$587,100
2090
$5,691,297,476
$0
1215
$5,691,297,476
Saratoga County
17742
Saratoga
MECHANICVILLE CITY /
Mechanicville (C)
Phase 2 of 15284; Construct additional sludge drying bed capacity,
New Other Expenses, New Water Treatment Plant, New Other (OT)
5,100
17647
Saratoga
STILLWATER VILLAGE /
Stillwater (V)
Alternative Water Source for Surface Water Treatment Rule
compliance., New Transmission, New Inter-Connection
1,572
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
17543
Saratoga
MOREAU WD
7/CONNECTION TO SCWA
/ Moreau (T)
Consolidate 3 small CWSs, consolidate WD 1, connect Town with
SCWA, New Storage, Extend Distribution System, New
Inter-Connection, Extend System Consolidation, New Water District
1,100
$0
1210
$5,691,297,476
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
17623
Saratoga
CORINTH VILLAGE /
Village of Corinth
New Surface Water Treatment Rule Compliance Facility, Upgrade
Distribution System
4,700
$6,200,000
160
$5,697,497,476
17535
Saratoga
SOUTH GLENS FALLS
VILLAGE / South Glens
Falls (V)
Proposed Cartridge Filtration Plant with SCADA to treat Village GWUDI
spring sources., New Surface Water Treatment Rule Compliance
Facility, New Surface Water Treatment Rule Compliance Facility
3,700
$1,565,000
145
$5,699,062,476
17143
Saratoga
SARATOGA GLEN
HOLLOW / Saratoga Glen
Hollow W.C.
Extend system to serve area with private contaminated wells,
consolidate public water supply, eliminate public water supply with past
totalcoliform detection. , Extend Distribution System, New System
Consolidation
750
$1,096,804
125
$5,700,159,280
17104
Saratoga
CLIFTON PARK WATER
AUTHORITY / Clifton Park
(T)
East Side Drive WD connection to CPWA, to serve private
contaminated wells, consolidation of public water supplies, Extend
Distribution System
29,000
$1,329,730
105
$5,701,489,010
15451
Saratoga
STILLWATER WD #1
(STILLWATER VLG) /
Stillwater (T)
New Transmission, New Storage
1,560
$4,912,000
90
$5,706,401,010
17870
Saratoga
SCWA STILLWATER
EXTENSION / Saratoga
County Water Authorit
Extend Transmission
2,100
$3,035,000
90
$5,709,436,010
17336
Saratoga
SCHUYLERVILLE-VICTORY New Storage
JWC / Victory (V)
2,170
$430,000
80
$5,709,866,010
18038
Saratoga
MECHANICVILLE CITY /
Mechanicville (C)
Interconnection to SCWA, Alternative to Project 17742, New
Transmission
5,100
$9,465,623
60
$5,719,331,633
15140
Saratoga
CLIFTON PARK WATER
AUTHORITY / Clifton Park
Water Authority
Upgrade Ground Water Source
29,000
$214,327
50
$5,719,545,960
15134
Saratoga
CLIFTON PARK WATER
AUTHORITY / Clifton Park
Water Authority
Inter-Connection
29,000
$252,041
50
$5,719,798,001
16168
Saratoga
SARATOGA SPRINGS
CITY / Saratoga Springs (C)
Upgrade Water Treatment Plant, Upgrade Surface Water Source, New
Transmission, New Pump Station
26,525
$15,820,000
45
$5,735,618,001
17234
Saratoga
REXFORD WD #2
(GLENVILLE #11) / Clifton
Park (T)
Extend Water District
1,200
$183,657
45
$5,735,801,658
15719
Saratoga
CORINTH VILLAGE /
Corinth (V)
New Storage, Upgrade Pump Station, Upgrade Distribution System
4,700
$3,277,000
40
$5,739,078,658
17947
Saratoga
HADLEY SOUTH WD#1 /
Hadley (T)
Upgrade Storage, Upgrade Distribution System
800
$278,239
40
$5,739,356,897
Page 64 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Saratoga County
16946
Saratoga
WATERFORD WATER
WORKS / Waterford (T)
New Water Treatment Plant
16523
Saratoga
CLIFTON PARK WATER
AUTHORITY / Clifton Park
Water Authority
New interconnection CPWA system to Rexford water system, New
Inter-Connection
15277
Saratoga
MECHANICVILLE CITY /
Mechanicville (C)
15449
Saratoga
16524
9,800
$4,635,000
35
$5,743,991,897
29,000
$1,077,000
30
$5,745,068,897
Upgrade Surface Water Source
5,100
$178,000
25
$5,745,246,897
STILLWATER WD #1
(STILLWATER VLG) /
Stillwater (T)
Upgrade Distribution System
1,560
$483,981
25
$5,745,730,878
Saratoga
CLIFTON PARK WATER
AUTHORITY / Clifton Park
Water Authority
New Ground Water Source, New Transmission
29,000
$2,039,420
25
$5,747,770,298
15123
Saratoga
CLIFTON PARK WATER
AUTHORITY / Clifton Park
Water Authority
New Ground Water Source
29,000
$5,020,918
25
$5,752,791,216
15135
Saratoga
CLIFTON PARK WATER
AUTHORITY / Clifton Park
Water Authority
New Storage
29,000
$586,438
25
$5,753,377,654
15289
Saratoga
MECHANICVILLE CITY /
Mechanicville (C)
Upgrade Distribution System
5,100
$236,000
20
$5,753,613,654
17772
Saratoga
BURNT HILLS-BALLSTON
LK WD (GLENVILLE) /
Ballston (T)
New Pump Station, Extend Distribution System
4,500
$606,052
20
$5,754,219,706
16258
Saratoga
WATERFORD WATER
WORKS / Waterford (T)
New Storage, Upgrade Distribution System
9,800
$6,706,875
15
$5,760,926,581
17798
Saratoga
COUNTY
REGIONALIZATION /
Saratoga Cnty W.A.
Extend Saratoga County Water Authority water transmission mains to
the Village and Town of Stillwater, the Village and Town of Waterford,
the Town of Halfmoon, and the Clifton Park Water Authority., Extend
Transmission
5,000
$20,000,000
15
$5,780,926,581
16376
Saratoga
SARATOGA WATER
SERVICES / Saratoga
Water Services
New Storage, New Pump Station
6,000
$434,850
15
$5,781,361,431
15136
Saratoga
CLIFTON PARK WATER
AUTHORITY / Clifton Park
Water Authority
New Water Treatment Plant
29,000
$1,005,713
15
$5,782,367,144
15694
Saratoga
HALFMOON WATER
DISTRICT / Halfmoon (T)
New Storage, Upgrade Pump Station
14,000
$2,074,163
15
$5,784,441,307
15776
Saratoga
REXFORD WD #2
(GLENVILLE #11) / Clifton
Park (T)
New Transmission
1,200
$645,300
10
$5,785,086,607
17754
Saratoga
SARATOGA CWA /
SaratogaCounty Water
Authority
New security system for county water sysem, New Other Expenses,
New Other (OT)
300
$751,900
10
$5,785,838,507
15699
Saratoga
HALFMOON WATER
DISTRICT / Halfmoon (T)
Upgrade Distribution System
14,000
$726,993
5
$5,786,565,500
Schenectady County
16510
Schenectady
DELANSON VILLAGE
WATER WORKS /
Delanson (V)
Upper resevoir raw water transmission main, new intake, new controls
& meters at filter plant., New Transmission, Extend Distribution
System, Upgrade Distribution System
428
$4,594,000
180
$5,791,159,500
17635
Schenectady
PRINCETOWN WATER
SUPPLY / Princetown (T)
New Transmission, New Storage, New Pump Station, Extend
Distribution System
600
$360,500
70
$5,791,520,000
16949
Schenectady
PRINCETOWN WATER
SUPPLY / Princetown (T)
Extend Distribution System
600
$495,430
55
$5,792,015,430
Page 65 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Schenectady County
17636
Schenectady
PRINCETOWN WATER
SUPPLY / Princetown (T)
Extend Distribution System
600
$286,340
55
$5,792,301,770
15092
Schenectady
PRINCETOWN WATER
SUPPLY / Princetown (T)
Extend Distribution System
600
$632,420
55
$5,792,934,190
15090
Schenectady
PRINCETOWN WATER
SUPPLY / Princetown (T)
Extend Distribution System
600
$929,060
55
$5,793,863,250
15089
Schenectady
PRINCETOWN (T) - WD#1 /
Princetown (T)
Extend Distribution System
183
$860,050
55
$5,794,723,300
15713
Schenectady
SCHENECTADY CITY
WATER WORKS /
Schenectady (C)
New Ground Water Source, New Pump Station
61,821
$1,916,000
50
$5,796,639,300
15355
Schenectady
SCHENECTADY CITY
WATER WORKS /
Schenectady (C)
Corrosion Control & Cleaning of Tansmission Mains, Upgrade
Transmission
61,821
$1,248,389
50
$5,797,887,689
15353
Schenectady
SCHENECTADY CITY
WATER WORKS /
Schenectady (C)
Distribution improvements - Elimination of deadends, Upgrade
Distribution System
61,821
$1,170,150
45
$5,799,057,839
15348
Schenectady
SCHENECTADY CITY
WATER WORKS /
Schenectady (C)
Valve replacement program, Upgrade Transmission
61,821
$2,472,000
45
$5,801,529,839
15349
Schenectady
SCHENECTADY CITY
WATER WORKS /
Schenectady (C)
Under sized mains and lead service line replacement, Upgrade
Distribution System
61,821
$1,136,000
45
$5,802,665,839
15955
Schenectady
GLENVILLE WD #11 /
Glenville (T)
Extend Distribution System
15,000
$558,260
45
$5,803,224,099
15967
Schenectady
GLENVILLE WD #11 /
Glenville (T)
Extend Distribution System
15,000
$812,670
40
$5,804,036,769
15346
Schenectady
SCHENECTADY CITY
WATER WORKS /
Schenectady (C)
Upgrade Pump Station
61,821
$1,800,476
35
$5,805,837,245
17741
Schenectady
ROTTERDAM WD #3 /
Rotterdam (T)
Construction of new storage tank and transmission main, New
Transmission, New Storage
2,000
$2,060,000
25
$5,807,897,245
16607
Schenectady
ROTTERDAM WD #5 /
Rotterdam (T)
Upgrade Ground Water Source
28,000
$566,500
15
$5,808,463,745
15964
Schenectady
GLENVILLE WD #11 /
Glenville (T)
Upgrade Ground Water Source
15,000
$622,120
15
$5,809,085,865
15962
Schenectady
GLENVILLE WD #11 /
Glenville (T)
Charlton Road - Lake Hill Road Transmission Main Connection, New
Transmission
15,000
$387,280
10
$5,809,473,145
15957
Schenectady
GLENVILLE WD #11 /
Glenville (T)
Install parallel transmission main from well field to storage facility.,
New Transmission
15,000
$2,266,000
5
$5,811,739,145
15959
Schenectady
GLENVILLE WD #11 /
Glenville (T)
Upgrade Distribution System
15,000
$366,680
5
$5,812,105,825
1,061
$1,045,000
135
$5,813,150,825
500
$4,899,004
105
$5,818,049,829
Schoharie County
15179
Schoharie
CENTRAL BRIDGE WATER
DISTRICT / Central Bridge
WD
New Water Treatment Plant, Upgrade Transmission, Upgrade Storage,
Upgrade Distribution System
18053
Schoharie
COBLESKILL / Cobleskill
(T)
Howe Caverns/Route 7 Service Area Extension, Extend Distribution
System
Page 66 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Schoharie County
17361
Schoharie
COBLESKILL VILLAGE /
Cobleskill (V)
Upgrade Water Treatment Plant, New Storage, Upgrade Distribution
System
4,533
$4,120,000
105
$5,822,169,829
17504
Schoharie
CENTRAL BRIDGE WATER
DISTRICT / Central Bridge
WD
DBP Control , Upgrade Water Treatment Plant
1,061
$1,773,000
65
$5,823,942,829
16068
Schoharie
COBLESKILL VILLAGE /
Cobleskill (V)
New Storage, Upgrade Distribution System
4,533
$2,091,000
55
$5,826,033,829
16691
Schoharie
JEFFERSON WD /
Jefferson (T)
Upgrade Water Treatment Plant, Upgrade Ground Water Source,
Upgrade Transmission, Upgrade Distribution System
198
$150,000
45
$5,826,183,829
16067
Schoharie
COBLESKILL VILLAGE /
Cobleskill (V)
Upgrade Distribution System
4,533
$464,049
45
$5,826,647,878
17572
Schoharie
SHARON SPRINGS
VILLAGE / (V) Sharon
Springs
Water system improvements., Upgrade Water Treatment Plant,
Upgrade Ground Water Source, Upgrade Storage, Upgrade
Distribution System
547
$2,900,000
45
$5,829,547,878
16745
Schoharie
SHARON SPRINGS
VILLAGE / Sharon Springs
(V)
Upgrade Transmission
547
$127,000
35
$5,829,674,878
16492
Schoharie
OORAH RESORT, LLC /
Deer Run Village
Homeowners As
New Ground Water Source, Upgrade Storage
50
$231,507
30
$5,829,906,385
17787
Schoharie
SCHOHARIE VILLAGE /
Schoharie (V)
Upgrade Distribution System
1,030
$2,570,000
30
$5,832,476,385
17968
Schoharie
SHARON SPRINGS
VILLAGE / Sharon Springs
(V)
Installation of water meters.,
547
$203,148
20
$5,832,679,533
150
$1,104,000
105
$5,833,783,533
Schuyler County
16768
Schuyler
SCHUYLER COUNTY
WATER EXTENSION / Dix
(T)
Extend watermain from (V) Watkins Glen to Watkins Glen International
Race Track., Extend Distribution System
17925
Schuyler
MONTOUR FALLS /
Montour Falls (V)
Upgrade Storage, Upgrade Distribution System
1,800
$5,852,501
90
$5,839,636,034
17679
Schuyler
WATKINS GLEN VILLAGE /
Watkins Glen (V)
Upgrade Surface Water Source
2,149
$1,145,000
40
$5,840,781,034
400
$3,198,000
95
$5,843,979,034
7,400
$2,885,000
85
$5,846,864,034
Seneca County
15933
Seneca
FAYETTE HAMLET
WATER DISTRICT / Fayette
(T)
Extend Distribution System
17183
Seneca
SENECA FALLS VILLAGE /
Seneca Falls (V)
Upgrade Water Treatment Plant, Upgrade Pump Station
15599
Seneca
FAYETTE WATER
PROJECT / Varick (T)
Extend Distribution System
520
$1,406,800
80
$5,848,270,834
16679
Seneca
JUNIUS WATER DISTRICT
#1 / Junius (T)
Extend system to serve area with private contaminated wells. W.D. Ext.
#2., Extend Distribution System
300
$623,607
65
$5,848,894,441
15107
Seneca
SENECA FALLS (T) BRIDGEPORT AREA /
Seneca Falls (T)
Extend system to serve area with private contaminated wells. ,
Upgrade Distribution System
35
$256,000
65
$5,849,150,441
16767
Seneca
ROUTE 96 WATER
DISTRICT / Waterloo (T)
Extend system to serve area with private contaminated wells. , Extend
Distribution System
202
$1,845,512
60
$5,850,995,953
Page 67 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Seneca County
16555
Seneca
CENTRAL SENECA
COUNTY WD / Varick (T)
Town of Varick & Town of Fayette, New Transmission
550
$3,267,871
60
$5,854,263,824
15578
Seneca
BURGESS ROAD WATER
DISTRICT / Junius (T)
Extend system to serve area with private contaminated wells. , Extend
Distribution System
200
$699,100
60
$5,854,962,924
15512
Seneca
WATERLOO VILLAGE /
Waterloo (V)
New Transmission, Upgrade Distribution System
7,000
$1,232,500
60
$5,856,195,424
15109
Seneca
VARICK/ROMULUS
WATER PROJECT / Varick
(T)
Extend Distribution System
850
$3,100,000
55
$5,859,295,424
16787
Seneca
YALE FARM RD/ARMY
DEPOT WATER PROJECT
/ Varick (T)
Extend Distribution System
100
$794,800
55
$5,860,090,224
15270
Seneca
SENECA FALLS VILLAGE /
Seneca Falls (T)
Route 414 waterline., Extend Distribution System
7,400
$816,000
55
$5,860,906,224
16724
Seneca
TYRE (T) WATER
DISTRICT / Tyre (T)
Extend system to serve area with private contaminated wells. , Extend
Distribution System
260
$992,508
55
$5,861,898,732
15272
Seneca
SENECA FALLS VILLAGE /
Seneca Falls (T)
Balsey Road., Extend Distribution System
7,400
$257,000
55
$5,862,155,732
17697
Seneca
OVID VILLAGE / Ovid (V)
Upgrade Water Treatment Plant
1,356
$1,632,500
55
$5,863,788,232
15283
Seneca
LODI AREA WATER
SYSTEM / Lodi (T)
New Complete System (New System), New Storage, New Pump
Station, New Distribution System
850
$2,350,000
50
$5,866,138,232
17026
Seneca
BOODY'S HILL WD
(WATER DISTRICT #5) /
Fayette (T)
Extend to serve private contaminated wells. , Extend Distribution
System
151
$788,980
50
$5,866,927,212
16880
Seneca
INTERLAKEN VILLAGE /
Interlaken (V)
Upgrade Ground Water Source
650
$320,807
50
$5,867,248,019
15361
Seneca
OVID VILLAGE / Ovid (V)
Upgrade Distribution System
1,356
$161,000
40
$5,867,409,019
17701
Seneca
OVID VILLAGE / Ovid (V)
Upgrade Distribution System
1,356
$2,068,000
35
$5,869,477,019
15086
Seneca
BORDER CITY WATER
DISTRICT / Waterloo (T)
Upgrade Distribution System
1,600
$161,340
35
$5,869,638,359
17689
Seneca
INTERLAKEN VILLAGE /
Interlaken (V)
Upgrade Distribution System
650
$1,850,000
30
$5,871,488,359
LOUISVILLE WATER
DISTRICT #2 / Louisville (T)
New Storage, Upgrade Distribution System, System Consolidation
1105
$5,871,488,359
St.Lawrence County
17140
St.Lawrence
1,000
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
17454
St.Lawrence
EAST LOUISVILLE WD#3 /
Louisville (T)
Consolidation of water systems with past coliform detections., New
Storage, New Distribution System, New System Consolidation
1,030
$9,275,000
160
$5,880,763,359
17516
St.Lawrence
OSWEGATCHIE (T) /
Oswegatchie (T)
Joint water system improvement project between (T) Oswegatchie, (T)
Lisbon and (V) Huevelton, Upgrade Ground Water Source, Upgrade
Storage, Upgrade Distribution System, New Inter-Connection, New
System Consolidation
2,100
$13,973,000
130
$5,894,736,359
17615
St.Lawrence
NORFOLK WATER
DISTRICT / Norfolk (T)
New Surface Water Treatment Rule Compliance Facility, New Ground
Water Source
2,300
$1,279,000
125
$5,896,015,359
Page 68 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
St.Lawrence County
17375
St.Lawrence
CANTON (T) E. SIDE WD /
Canton (T)
New Ground Water Source, New Storage, New Distribution System
16139
St.Lawrence
MASSENA VILLAGE /
Massena (V)
17618
St.Lawrence
16798
350
$3,112,660
90
$5,899,128,019
Upgrade Water Treatment Plant
11,209
$3,134,000
80
$5,902,262,019
GOUVERNEUR VILLAGE /
Gouverneur (V)
Upgrade Water Treatment Plant
4,263
$2,160,600
70
$5,904,422,619
St.Lawrence
EAST NORFOLK WATER
DISTRICT / Norfolk (T)
New system to serve area with private contaminated wells. , New
Complete System (New System)
270
$750,000
65
$5,905,172,619
16881
St.Lawrence
GOUVERNEUR VILLAGE /
Gouverneur (V)
Upgrade Water Treatment Plant, Upgrade Distribution System
4,263
$857,697
60
$5,906,030,316
15493
St.Lawrence
VILLAGE OF
RENSSELAER FALLS WS
SYSTEM / Rensselaer Falls
(V)
New Complete System (New System), New Distribution System
140
$2,795,420
60
$5,908,825,736
15852
St.Lawrence
MADRID WATER DISTRICT Upgrade Storage, Upgrade Distribution System
/ Madrid (T)
800
$674,000
55
$5,909,499,736
16077
St.Lawrence
LISBON WATER DISTRICT
/ Lisbon (T)
500
$340,695
55
$5,909,840,431
17632
St.Lawrence
CANTON VILLAGE / Canton New Ground Water Source, Upgrade Distribution System
(V)
7,055
$3,612,725
55
$5,913,453,156
15729
St.Lawrence
POTSDAM VILLAGE /
Potsdam (V)
New Storage
9,425
$1,245,000
40
$5,914,698,156
16761
St.Lawrence
OGDENSBURG (C) /
Ogdensburg (C)
New Distribution System
13,500
$566,500
40
$5,915,264,656
17827
St.Lawrence
OGDENSBURG CITY /
Ogdensburg (C)
Upgrade Transmission
13,500
$351,250
40
$5,915,615,906
15732
St.Lawrence
POTSDAM VILLAGE /
Potsdam (V)
Upgrade Distribution System
9,425
$567,000
35
$5,916,182,906
15815
St.Lawrence
WADDINGTON VILLAGE /
Waddington (V)
Upgrade Storage
944
$295,000
30
$5,916,477,906
17906
St.Lawrence
MASSENA VILLAGE /
Massena (V)
Upgrade Distribution System
11,209
$320,000
30
$5,916,797,906
Extend Distribution System
Steuben County
17379
Steuben
COOPERS PLAINS/LONG
ACRES WATER SYST /
Erwin (T)
New Ground Water Source, Extend Distribution System, New System
Consolidation
1,400
$0
205
$5,916,797,906
17333
Steuben
SPAULDING DR/LAKE
SALUBRIA WATER DISTR.
/ Bath (T)
Consolidation of 18 public water systems, eliminate PWS with organic
exceedance., Extend Distribution System, Upgrade Distribution
System, System Consolidation
1,195
$5,460,087
205
$5,922,257,993
17367
Steuben
TROUPSBURG WATER
DISTRICT / Troupsburg (T)
New Surface Water Treatment Rule Compliance Facility, Upgrade
Water Treatment Plant
250
$192,000
165
$5,922,449,993
15555
Steuben
ARKPORT VILLAGE /
Arkport (V)
Upgrade Transmission, Inter-Connection
835
$376,000
150
$5,922,825,993
16279
Steuben
COLONIAL COACH
ESTATES IV (MGRE) /
Merlyn Cavallaro
New Chlorination system., Upgrade Ground Water Source
79
$65,900
130
$5,922,891,893
Page 69 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Steuben County
17668
Steuben
HORNELL CITY / Hornell
(C)
Upgrade Water Treatment Plant, Upgrade Ground Water Source,
Upgrade Storage
16811
Steuben
RIVERSIDE PARK / Carol
Naar
17588
Steuben
17102
9,019
$1,596,000
125
$5,924,487,893
New chlorination system., Upgrade Ground Water Source
125
$45,735
115
$5,924,533,628
CORNING MANOR WATER
DISTRICT / Corning (T)
Extend to ontaminated private wells, consolidate 5 small PWS's,
Upgrade Storage, New System Consolidation
350
$1,315,187
105
$5,925,848,815
Steuben
SHOWBOAT MOBILE
HOME PARK / Affordable
Great Locations Inc
Connect to public water system in Village of Wayland., New System
Consolidation
48
$86,520
85
$5,925,935,335
15810
Steuben
VICTORY PLACE / Merlyn
Cavallaro
Upgrade Ground Water Source
11
$112,800
80
$5,926,048,135
18002
Steuben
HAMLET OF WOODHULL
MUNICIPAL WS / Woodhull
(T)
System to serve former Village (now hamlet) with private contaminated
wells., New Ground Water Source, New Storage, New Distribution
System
483
$4,489,928
80
$5,930,538,063
16447
Steuben
CORNING CITY / Corning
(C)
Address total coliform violations, New Storage, New Distribution
System
10,842
$2,000,000
80
$5,932,538,063
17567
Steuben
URBANA WATER
DISTRICT #2 / Urbana (T)
Proposed WD #3. Extend system to serve private contaminated wells
and consolidate public water supplies., Extend Distribution System,
New System Consolidation, New Water District
33
$3,565,111
80
$5,936,103,174
17633
Steuben
SYLVAN BEACH WANETA
LAKE WATER DISTRICT /
Wayne (T)
New Complete System (New System)
921
$4,175,175
75
$5,940,278,349
17186
Steuben
REXVILLE WATER
DISTRICT / West Union (T)
New system to serve area with private contaminated wells. , New
Complete System (New System)
60
$100,000
70
$5,940,378,349
16047
Steuben
MORNINGSIDE HEIGHTS
WATER DIST / Erwin (T)
Extend Distribution System
2,950
$1,153,260
70
$5,941,531,609
15177
Steuben
AVOCA (T) / Avoca (T)
New Distribution System
96
$294,600
65
$5,941,826,209
18016
Steuben
WD #3 / Campbell (T)
Serve private contaminated/poor yielding wells., Extend Water District
1,025
$908,687
65
$5,942,734,896
16643
Steuben
HORNELLSVILLE (T) /
Hornellsville (T)
Extend Distribution System
300
$1,024,500
55
$5,943,759,396
16383
Steuben
PAINTED POST VILLAGE /
Painted Post (V)
New Storage, Upgrade Distribution System
1,842
$2,480,000
55
$5,946,239,396
17982
Steuben
PRATTSBURGH WATER
DISTRICT / Prattsburgh (T)
Upgrade Storage, Upgrade Distribution System
850
$1,485,415
50
$5,947,724,811
17929
Steuben
PINEWOOD ACRES
WATER DISTRICT /
Corning
Upgrade Storage, Upgrade Pump Station, Upgrade Distribution System
168
$3,426,552
45
$5,951,151,363
15492
Steuben
NORTH HORNELL
VILLAGE / North Hornell (V)
Upgrade Distribution System
851
$850,000
40
$5,952,001,363
17975
Steuben
PINEWOOD ACRES WD /
Corning(T)
Upgrade Distribution System
168
$3,302,438
40
$5,955,303,801
15629
Steuben
HAMMONDSPORT
VILLAGE / Hammondsport
(V)
Upgrade Distribution System
741
$405,000
40
$5,955,708,801
Page 70 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Steuben County
15902
Steuben
ADDISON VILLAGE /
Addison (V)
Upgrade Storage, Upgrade Distribution System
17035
Steuben
MEADOWS PARK (THE) /
The Meadows Park
Upgrade Distribution System
17974
Steuben
SOUTH CORNING
VILLAGE / South Corning
(V)
17969
Steuben
16056
1,797
$1,356,000
40
$5,957,064,801
39
$25,544
35
$5,957,090,345
Upgrade Storage, Upgrade Distribution System
1,147
$7,763,007
35
$5,964,853,352
BATH VILLAGE / Bath (V)
Installation of solar powered storage tank water circulators.,
5,641
$437,400
35
$5,965,290,752
Steuben
CORNING CITY / Corning
(C)
Upgrade Storage
10,842
$80,000
30
$5,965,370,752
16054
Steuben
CORNING CITY / Corning
(C)
New Transmission
10,842
$350,000
30
$5,965,720,752
16046
Steuben
MORNINGSIDE HEIGHTS
WATER DIST / Erwin (T)
New Ground Water Source
2,950
$327,500
25
$5,966,048,252
15550
Steuben
ARKPORT VILLAGE /
Arkport (V)
Upgrade Distribution System
835
$780,850
25
$5,966,829,102
17844
Steuben
CAMPBELL WATER
DISTRICT / Campbell (T)
Extend Distribution System
280
$216,744
15
$5,967,045,846
1,009,264
$3,843,000
110
$5,970,888,846
80
$227,000
100
$5,971,115,846
Suffolk County
16863
Suffolk
SUFFOLK COUNTY
WATER AUTHORITY /
SCWA
Browns Hills Road area. Address nitrate contamination and
consolodate PWS, New Transmission, Upgrade Distribution System
16051
Suffolk
CAMP HERO WATER
DISTRICT / East Hampton
(T)
New Ground Water Source
16850
Suffolk
SUFFOLK COUNTY
WATER AUTHORITY /
Suffolk Co. Water Authority
Bull Path Pump Station, Northwest, New Ground Water Source, New
Pump Station
1,009,264
$1,166,000
90
$5,972,281,846
17433
Suffolk
SUFFOLK COUNTY
WATER AUTHORITY /
SCWA
New Wells/Upgrade Wells in various locations throughout the system,
Upgrade Ground Water Source, New Ground Water Source
1,009,264
$9,313,000
90
$5,981,594,846
17364
Suffolk
SOUTH HUNTINGTON WD
/ Huntington (T)
Well 19-2, New Ground Water Source
81,760
$1,515,842
90
$5,983,110,688
16862
Suffolk
SUFFOLK COUNTY
WATER AUTHORITY /
Suffolk Co. Water Authority
Northport Aqueduct Project to reduce nitrate contamination through
source blending, Upgrade Transmission, New Distribution System
1,009,264
$22,166,771
80
$6,005,277,459
16273
Suffolk
DERING HARBOR CORP /
Dearing Harbor (V)
Upgrade Water Treatment Plant
250
$20,791
75
$6,005,298,250
16926
Suffolk
SOUTH HUNTINGTON WD
/ Huntington (T)
Upgrade Water Treatment Plant
81,760
$1,043,000
70
$6,006,341,250
17663
Suffolk
EAST FARMINGDALE WD /
Babylon East Farmingdale
WD
VOC Treatment at Plant No. 4, Upgrade Water Treatment Plant
7,500
$4,398,512
65
$6,010,739,762
17891
Suffolk
SOUTH HUNTINGTON WD
/ Huntington (T)
Plant 3 VOC Removal, Upgrade Water Treatment Plant
81,760
$3,530,840
60
$6,014,270,602
17892
Suffolk
SOUTH HUNTINGTON WD
/ Huntington (T)
Plant 7 VOC Removal, Upgrade Water Treatment Plant
81,760
$5,575,390
60
$6,019,845,992
Page 71 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Suffolk County
17893
Suffolk
SOUTH HUNTINGTON WD
/ Huntington (T)
Plant 4 VOC Removal, Upgrade Water Treatment Plant
81,760
$973,350
60
$6,020,819,342
16069
Suffolk
RIVERHEAD WD /
Riverhead (T)
Upgrade Ground Water Source
28,000
$1,211,000
60
$6,022,030,342
17352
Suffolk
SOUTH HUNTINGTON WD
/ Huntington (T)
Plant No. 10 VOC Removal, Upgrade Water Treatment Plant
81,760
$3,913,790
60
$6,025,944,132
16516
Suffolk
WEST NECK WATER
SUPPLY / Shelter Island (T)
Upgrade Distribution System
100
$550,000
55
$6,026,494,132
17665
Suffolk
GREENLAWN WATER
DISTRICT / Greenlawn
Water District
VOC Treatment at Plant No. 11, Upgrade Water Treatment Plant
42,000
$1,930,784
55
$6,028,424,916
17664
Suffolk
DIX HILLS WD / Town of
Huntington / Dix Hills
VOC Treatment at Plant No.11, Upgrade Water Treatment Plant
34,522
$2,277,330
55
$6,030,702,246
15831
Suffolk
DIX HILLS WD / Huntington
(T)
Preventative maintenance, Upgrade Ground Water Source
34,522
$459,000
50
$6,031,161,246
16836
Suffolk
SUFFOLK COUNTY
WATER AUTHORITY /
Suffolk Co. Water Authority
Montauk Point State Blvd., Iron Removal, Montauk, New Water
Treatment Plant
1,009,264
$318,000
50
$6,031,479,246
15858
Suffolk
DIX HILLS WD / Huntington
(T)
VOC removal - GAC filters plant #8, Upgrade Ground Water Source
34,522
$1,271,500
45
$6,032,750,746
16715
Suffolk
OCEAN BEACH WATER
DISTRICT / Ocean Beach
(V)
Ground Water Source
4,500
$1,130,000
45
$6,033,880,746
16442
Suffolk
NORTHEAST WOODS /
East Hampton (T)
Northeast Woods, East Hampton (T), Extend Distribution System
675
$2,524,278
45
$6,036,405,024
16202
Suffolk
SUFFOLK COUNTY
WATER AUTHORITY /
Suffolk Co. Water Authority
Lloyds Neck watermain installation, Extend Distribution System
1,009,264
$6,345,254
45
$6,042,750,278
17402
Suffolk
WEST NECK WATER
SUPPLY / Shelter Island (T)
New Well, New Ground Water Source
100
$2,000
45
$6,042,752,278
16071
Suffolk
RIVERHEAD WD /
Riverhead (T)
Water District Extension No. 49 Middle Rd. & Harrison Ave., Extend
Distribution System
28,000
$135,600
45
$6,042,887,878
16066
Suffolk
RIVERHEAD WD /
Riverhead (T)
New Ground Water Source, New Pump Station
28,000
$1,413,000
45
$6,044,300,878
16065
Suffolk
RIVERHEAD WD /
Riverhead (T)
Water District Extension No. 47-Herricks Lane., Extend Distribution
System
28,000
$1,165,000
45
$6,045,465,878
16020
Suffolk
SOUTH HUNTINGTON WD
/ Huntington (T)
treatment modifications to plant No. 5, Upgrade Ground Water Source
81,760
$486,000
40
$6,045,951,878
16274
Suffolk
FISHERS ISLAND WW
CORP / Fishers Island WW
Corp.
Upgrade Ground Water Source, Upgrade Distribution System
2,500
$257,500
30
$6,046,209,378
17908
Suffolk
SALTARE WATER
DISTRICT / Saltaire (V)
Infrastructure upgrade, Upgrade Water Treatment Plant, Upgrade
Storage
1,400
$668,000
25
$6,046,877,378
17366
Suffolk
SOUTH HUNTINGTON WD
/ Huntington (T)
Operations Building Improvements, Upgrade Other Expenses,
Upgrade Other (OT)
81,760
$731,300
25
$6,047,608,678
Page 72 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Suffolk County
15753
Suffolk
SHELTER ISLAND
HEIGHTS ASSOCIATION /
Shelter Island Hgts. Assoc.
Upgrade Storage, Upgrade Distribution System
17890
Suffolk
SOUTH HUNTINGTON WD
/ Huntington (T)
17718
Suffolk
17365
463
$1,813,500
20
$6,049,422,178
Plant 14 Standpipe Rehabilitation, Upgrade Storage
81,760
$1,905,500
15
$6,051,327,678
RIVERHEAD WD / River
Head WD / Riverhead (T)
Rehabiitation of Route 58 Storage Tank, Upgrade Storage
28,000
$2,060,000
15
$6,053,387,678
Suffolk
SOUTH HUNTINGTON WD
/ Huntington (T)
Contruction of Plant 20, New Water Treatment Plant
81,760
$3,270,250
15
$6,056,657,928
17351
Suffolk
SOUTH HUNTINGTON WD
/ Huntington (T)
Rehabilitation of Plant No. 4, Upgrade Water Treatment Plant
81,760
$1,551,077
15
$6,058,209,005
16019
Suffolk
SOUTH HUNTINGTON WD
/ Huntington (T)
caustic tank replacement at various plant sites, Upgrade Ground
Water Source
81,760
$327,500
15
$6,058,536,505
15837
Suffolk
DIX HILLS WD / Huntington
(T)
New Storage
34,522
$1,106,800
15
$6,059,643,305
15835
Suffolk
DIX HILLS WD / Huntington
(T)
Iron removal plant - Well No. 10-1, Upgrade Ground Water Source
34,522
$374,900
15
$6,060,018,205
15854
Suffolk
DIX HILLS WD / Huntington
(T)
Elevated water storage tank #1, Upgrade Storage
34,522
$399,800
10
$6,060,418,005
15851
Suffolk
DIX HILLS WD / Huntington
(T)
Elevated water storage tank #2, Upgrade Storage
34,522
$740,900
10
$6,061,158,905
16915
Suffolk
NAPEAQUE MOBILE
HOME PARK / Napeaque
Camping Club
Upgrade Distribution System
120
$21,000
10
$6,061,179,905
17993
Suffolk
WEST NECK WATER
SUPPLY / Shelter Island (T)
Water main replacement, Upgrade Distribution System
100
$669,093
10
$6,061,848,998
17717
Suffolk
RIVERHEAD WD / River
Head WD / Riverhead (T)
Contruction of New Wells at Plant no. 15, New Ground Water Source
28,000
$1,973,480
10
$6,063,822,478
17696
Suffolk
SUFFOLK COUNTY
WATER AUTHORITY /
SCWA
Automated Meter Reading / Leak Detection, Upgrade Distribution
System
1,009,264
$7,273,000
10
$6,071,095,478
15856
Suffolk
DIX HILLS WD / Huntington
(T)
Double containment - above ground caustic soda tanks - plants #1, 4,
6, 7, 8, 9, 10, Upgrade Ground Water Source
34,522
$411,600
10
$6,071,507,078
Sullivan County
17210
Sullivan
WURTSBORO HILLS
WATER COMPANY /
Mamakating (T)
New Ground Water Source, Upgrade Storage, New Distribution System
120
$8,610,800
125
$6,080,117,878
16446
Sullivan
WOODRIDGE VILLAGE /
Woodridge (V)
Upgrade Water Treatment Plant
902
$351,430
105
$6,080,469,308
17403
Sullivan
WOODRIDGE VILLAGE /
Woodridge (V)
New Ground Water Source
902
$450,000
100
$6,080,919,308
16735
Sullivan
TOWN OF LIBERTY WS /
Liberty (T)
Upgrade Transmission, Upgrade Storage, New Inter-Connection, New
System Consolidation
5,000
$4,890,265
95
$6,085,809,573
16640
Sullivan
BLOOMINGBURG VILLAGE New Water Treatment Plant, New Ground Water Source, New Storage,
New Distribution System
/ Bloomingburg (V)
450
$2,071,985
75
$6,087,881,558
Page 73 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Sullivan County
17401
Sullivan
EMERALD GREEN LAKE
LOUISE MARIE WS / Lake
Louise Marie Water
Water Treatment Plant Upgrade, Upgrade Water Treatment Plant
17599
Sullivan
EDGEWOOD LAKES, INC. /
Edgewood Lakes Inc.
Replace hydropneumatic tank, New Storage
15912
Sullivan
JD WATER COMPANY INC. Upgrade Pump Station, Upgrade Distribution System
/ JD Water Co.
17945
Sullivan
MONTICELLO VILLAGE /
Monticello (V)
18042
Sullivan
16543
1,200
$3,244,500
60
$6,091,126,058
17
$9,000
55
$6,091,135,058
800
$49,000
45
$6,091,184,058
Upgrade storage and distribution piping, Upgrade Storage, Upgrade
Distribution System
8,000
$7,395,000
45
$6,098,579,058
LIBERTY VILLAGE / Liberty
(V)
New Storage
4,800
$975,000
40
$6,099,554,058
Sullivan
MONTICELLO VILLAGE /
Monticello (V)
Upgrade Distribution System
8,000
$285,300
35
$6,099,839,358
15087
Sullivan
ROUTE 55 WATER
DISTRICT / Liberty (T)
New Storage, New Pump Station, Upgrade Distribution System
500
$400,000
35
$6,100,239,358
17560
Sullivan
THE CALLICOON WATER
COMPANY INC / Callicoon
Water Co., Inc.
Replace water tower on Delvue Road., New Storage
854
$100,000
35
$6,100,339,358
17436
Sullivan
MELODY LAKE ACRES /
National Aqueous Corp.
Replace distribution system, Upgrade Distribution System
150
$134,090
35
$6,100,473,448
15365
Sullivan
WURTSBORO VILLAGE
WATER SUPPLY /
Wurtsboro (V)
New 400,000 gallon potable water stand pipe and distribution system
improvements, New Storage, Upgrade Distribution System
1,060
$1,545,000
30
$6,102,018,448
16439
Sullivan
FALLSBURG WHO-LS-SF /
Fallsburgh (T)
Upgrade Distribution System
8,355
$430,000
30
$6,102,448,448
17970
Sullivan
WURTSBORO VILLAGE
WATER SUPPLY /
Wurtsboro (V)
Installation of water meters.,
1,060
$201,438
20
$6,102,649,886
Tioga County
15782
Tioga
WAVERLY VILLAGE /
Waverly (V)
New Ground Water Source
4,830
$865,000
80
$6,103,514,886
17667
Tioga
NEWARK VALLEY
VILLAGE / Newark Valley
(V)
Upgrade Distribution System
1,253
$4,813,000
70
$6,108,327,886
18026
Tioga
CANDOR VILLAGE WATER
DEPT. / Candor (V)
Upgrade Storage, Upgrade Distribution System
1,020
$3,047,237
60
$6,111,375,123
15790
Tioga
WAVERLY VILLAGE /
Waverly (V)
New Transmission, New Storage, Upgrade Distribution System
4,830
$1,999,400
55
$6,113,374,523
17596
Tioga
SPENCER (V) / Spencer (V)
New Complete System (New System), New System Consolidation
731
$7,865,000
50
$6,121,239,523
16170
Tioga
OWEGO W D NO 4 /
Owego (T)
Extend Distribution System
3,196
$1,147,202
45
$6,122,386,725
17324
Tioga
CONSOLIDATED WATER
DISTRICT / Owego (T)
Upgrade Storage, Upgrade Pump Station
10,306
$3,669,000
30
$6,126,055,725
17508
Tioga
BARTON (T) WD#1 / Barton
(T)
New Complete System (New System), New Water District
700
$2,553,000
25
$6,128,608,725
Page 74 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Tioga County
17039
Tioga
OWEGO W D NO 4 /
Owego (T)
Upgrade Distribution System
3,196
$192,610
20
$6,128,801,335
17749
Tioga
OWEGO W D NO 3 /
Owego (T)
Pennsylvania Ave. Water Main Replacement., Upgrade Distribution
System
2,150
$2,215,865
15
$6,131,017,200
16172
Tioga
OWEGO W D NO 3 /
Owego (T)
Inter-Connection
2,150
$312,576
10
$6,131,329,776
17678
Tioga
OWEGO W D NO 3 /
Owego (T)
Upgrade Distribution System
2,150
$525,300
10
$6,131,855,076
Tompkins County
17888
Tompkins
TRUMANSBURG VILLAGE
/ Trumansburg (V)
New well to provide source redundancy. New transmission main to
provide adequate CT., New Ground Water Source, New Transmission
2,300
$1,374,000
120
$6,133,229,076
16093
Tompkins
TRUMANSBURG VILLAGE
/ Trumansburg (V)
New Transmission, New Storage, New Pump Station
2,300
$2,501,000
115
$6,135,730,076
15488
Tompkins
ITHACA CITY / Ithaca (C)
Upgrade Water Treatment Plant, Upgrade Transmission, New Storage,
Upgrade Pump Station, Inter-Connection
29,457
$14,227,569
100
$6,149,957,645
18009
Tompkins
DRYDEN VILLAGE / Dryden New Ground Water Source, New Storage, Upgrade Distribution System
(V)
2,000
$5,924,000
70
$6,155,881,645
15993
Tompkins
LANSING (V) / Lansing (V)
Upgrade Distribution System
3,100
$316,000
50
$6,156,197,645
16095
Tompkins
TRUMANSBURG VILLAGE
/ Trumansburg (V)
Upgrade Distribution System
2,300
$94,700
40
$6,156,292,345
15552
Tompkins
DRYDEN WD / Dryden (T)
New Distribution System
725
$4,286,000
35
$6,160,578,345
16590
Tompkins
WILLIAM GEORGE
AGENCY / George Jr.
Republic, Inc.
New Ground Water Source, New Storage, Upgrade Distribution System
250
$565,799
25
$6,161,144,144
15946
Tompkins
SOUTHERN CAYUGA
LAKE INTERMUN. WC /
Lansing (T)
Town of Lansing, Drake Road., Extend Distribution System
110
$328,200
25
$6,161,472,344
15945
Tompkins
SOUTHERN CAYUGA
LAKE INTERMUN. WC /
Lansing (T)
Town of Lansing, Franklyn and Maple Drives., Extend Distribution
System
140
$463,000
25
$6,161,935,344
15538
Tompkins
LANSING WD #2 / Lansing
(T)
New Storage, New Pump Station, Upgrade Distribution System
400
$443,500
20
$6,162,378,844
16566
Tompkins
SHELTER VALLEY M.H.P. /
Shelter Valley Waterworks
Upgrade Distribution System
175
$23,350
20
$6,162,402,194
15556
Tompkins
LANSING WD #2 / Lansing
(T)
Extend Distribution System
400
$117,300
15
$6,162,519,494
15899
Tompkins
YELLOW BARN WATER
CO / Yellow Barn Water Co
Upgrade Storage
250
$32,000
15
$6,162,551,494
15901
Tompkins
YELLOW BARN WATER
CO / Yellow Barn Water Co
Foot Hill Road., Upgrade Distribution System
250
$37,500
10
$6,162,588,994
15900
Tompkins
YELLOW BARN WATER
CO / Yellow Barn Water Co
Yellow Barn Road., Upgrade Distribution System
250
$25,000
10
$6,162,613,994
Page 75 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Tompkins County
15886
Tompkins
DRYDEN VILLAGE / Dryden Upgrade Distribution System
(V)
2,000
$23,983
5
$6,162,637,977
992
$150,000
2130
$6,162,787,977
Ulster County
17649
Ulster
PHOENICIA WATER
DISTRICT / Shandaken (T)
Phase 2, see Project #16491 for Phase 1., New Surface Water
Treatment Rule Compliance Facility, Upgrade Ground Water Source
15003
Ulster
ELLENVILLE (VILLAGE)
WATER DIS / Ellenville (V)
Water system improvements, Upgrade Surface Water Treatment Rule
Compliance Facility, Upgrade Storage, Upgrade Distribution System
4,323
$7,136,870
215
$6,169,924,847
17467
Ulster
SAUGERTIES (VILLAGE)
WATER DIS / Saugerties
(V)
Upgrade water mains and appurtenances; distribution extension to
connect 15 existing homes w/ wells to PWS; upgrade raw water
reservoir., Upgrade Other Expenses, Upgrade Distribution System,
Extend Distribution System, Upgrade Other (OT)
4,100
$3,573,894
130
$6,173,498,741
16390
Ulster
HIGHLAND WATER
DISTRICT / Lloyd (T)
New Storage, Extend Distribution System
4,000
$2,369,000
90
$6,175,867,741
17727
Ulster
KINGSTON (CITY) WATER
DISTRICT / Kingston (C)
Upgrade Water Treatment Plant
24,000
$0
85
$6,175,867,741
17643
Ulster
PORT EWEN WATER
DISTRICT / Port Ewen
Water District
New Water Treatment Plant
4,800
$2,250,000
85
$6,178,117,741
17076
Ulster
ELLENVILLE (VILLAGE)
WATER DIS / Ellenville (V)
Upgrade Surface Water Source
4,323
$173,600
75
$6,178,291,341
17626
Ulster
NEW PALTZ (VILLAGE)
WATER DIST / New Paltz
(V)
Upgrade Water Treatment Plant, New Storage, Upgrade Distribution
System
5,600
$5,675,916
70
$6,183,967,257
17571
Ulster
WEST HURLEY WATER
DISTRICT #1 (PROPOSED)
/ Hurley (T)
New Complete System (New System)
450
$4,713,160
70
$6,188,680,417
17883
Ulster
NEW PALTZ (V) / New Paltz
(V)
Construct mains in Northern portion of Village to loop system, Upgrade
Distribution System
6,000
$759,625
60
$6,189,440,042
17095
Ulster
EAST KINGSTON WATER
DISTRICT / Ulster (T)
New Complete System (New System)
350
$2,899,450
55
$6,192,339,492
16671
Ulster
NEW PALTZ (TOWN)
WATER DISTRIC / New
Paltz (T)
New source and storage for the Ohioville Water System, New Ground
Water Source, New Storage
810
$2,647,000
55
$6,194,986,492
17581
Ulster
GARDINER TOWN HOUSE
APTS / Gardiner
Townhouses
Upgrade Water Treatment Plant
96
$20,000
55
$6,195,006,492
15160
Ulster
NYS THRUWAY- ULSTER
SERVICE AREA / NYS
Thruway Authority
Extend Distribution System
2,055
$375,000
50
$6,195,381,492
18058
Ulster
KINGSTON (CITY) WATER
DISTRICT / City of Kingston
Water Dep.
Replacement of Mink Hollow Raw Water Intake, Upgrade Other
Expenses, Upgrade Other (OT)
24,000
$713,000
45
$6,196,094,492
16515
Ulster
EAST KINGSTON / East
Kingston
Extend Distribution System
270
$2,472,000
45
$6,198,566,492
16450
Ulster
GLENERIE WATER
DISTRICT / Ulster (T)
New Complete System (New System)
540
$2,636,800
45
$6,201,203,292
15616
Ulster
PORT EWEN WATER
DISTRICT / Esopus (T)
New Storage
4,800
$2,100,000
40
$6,203,303,292
15093
Ulster
ROSENDALE WATER
DISTRICT / Rosendale (T)
New Water Treatment Plant
2,200
$18,911
35
$6,203,322,203
Page 76 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Ulster County
18037
Ulster
MARLBOROUGH WATER
DISTRICT / (T) Marlborough
New Transmission, New Storage, Upgrade Distribution System
3,248
$16,879,640
30
$6,220,201,843
15639
Ulster
NEW PALTZ (VILLAGE)
WATER DIST / New Paltz
(V)
Upgrade Surface Water Source
5,600
$200,000
30
$6,220,401,843
18059
Ulster
HIGHLAND WATER
DISTRICT / Lloyd (T)
Upgrade Water Treatment Plant
4,000
$6,583,451
25
$6,226,985,294
17586
Ulster
GARDINER TOWN HOUSE
APTS / Gardiner
Townhouse/Condo APTS
Upgrade Ground Water Source, Upgrade Distribution System
96
$30,000
25
$6,227,015,294
16527
Ulster
ROSENDALE WATER
DISTRICT / Rosendale (T)
Main St.,Snyder Ave,Hardenburg Lane, Upgrade Distribution System
2,200
$420,000
20
$6,227,435,294
16401
Ulster
MARLBOROUGH WATER
DISTRICT / Marlborough (T)
Upgrade Water Treatment Plant, New Storage, Upgrade Distribution
System
3,248
$1,700,000
20
$6,229,135,294
15088
Ulster
ROSENDALE WATER
DISTRICT / Rosendale (T)
New Transmission
2,200
$158,000
20
$6,229,293,294
17498
Ulster
PORT EWEN WATER
DISTRICT / Esopus (T)
Upgrade Distribution System
4,800
$813,000
20
$6,230,106,294
16537
Ulster
VALLEY VIEW
APARTMENTS / Valley
View Apts.
New Ground Water Source
48
$13,802
15
$6,230,120,096
16525
Ulster
ROSENDALE WATER
DISTRICT / Rosendale (T)
System wide telemetry upgrade, Upgrade Other Expenses, Upgrade
Other (OT)
2,200
$65,000
15
$6,230,185,096
16526
Ulster
ROSENDALE WATER
DISTRICT / Rosendale (T)
New Ground Water Source
2,200
$880,000
15
$6,231,065,096
15503
Ulster
WALLKILL
CONSOLIDATED WD /
Shawangunk (T)
New Ground Water Source
15,000
$660,500
15
$6,231,725,596
16142
Ulster
NEW PALTZ (TOWN)
WATER DISTRIC / New
Paltz (T)
Upgrade Distribution System
810
$1,401,006
15
$6,233,126,602
15091
Ulster
ROSENDALE WATER
DISTRICT / Rosendale (T)
Upgrade Distribution System
2,200
$360,000
10
$6,233,486,602
15478
Ulster
SPRING LAKE MHP /
Mid-Hudson Park
Management
Upgrade Distribution System
420
$311,575
10
$6,233,798,177
Warren County
16969
Warren
HAGUE (T) WATER
DISTRICT #1 / Hague (T)
New Surface Water Treatment Rule Compliance Facility, New Storage,
New Distribution System
480
$4,355,081
180
$6,238,153,258
17392
Warren
PIONEER VILLAGE /
Pioneer Village Imp. Assoc.
Serve private contaminated wells., New Surface Water Treatment Rule
Compliance Facility, New Inter-Connection, New System Consolidation
144
$208,575
175
$6,238,361,833
15097
Warren
HAGUE HOA / Hague HOA
Hague Home Owners Association, New Surface Water Treatment
Rule Compliance Facility
18
$119,190
155
$6,238,481,023
16772
Warren
GORE MT SKI AREA /
Olympic Regional Dev
Authority
New Ground Water Source, New Transmission, New Storage
180
$1,010,945
145
$6,239,491,968
17214
Warren
ARCADY BAY ESTATES /
Arcady Bay Estates
New Surface Water Treatment Rule Compliance Facility, New Ground
Water Source, Upgrade Storage
332
$154,500
130
$6,239,646,468
Page 77 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Warren County
15490
Warren
NORTH CREEK WATER
DISTRICT / Johnsburg (T)
Upgrade Water Treatment Plant, New Ground Water Source, Upgrade
Storage
15798
Warren
QUEENSBURY WATER
DISTRICT / Queensbury (T)
Upgrade Distribution System
15895
Warren
CHESTERTOWN WATER
DISTRICT / Chester (T)
Corrosion Control , Upgrade Ground Water Source
16651
Warren
17823
1,000
$1,112,250
85
$6,240,758,718
21,200
$2,762,400
50
$6,243,521,118
1,300
$2,500
40
$6,243,523,618
GLENS FALLS CITY / Glens Upgrade Distribution System
Falls (C)
13,000
$1,300,000
40
$6,244,823,618
Warren
GLENS FALLS CITY / Glens Upgrade Storage
Falls (C)
13,000
$300,000
40
$6,245,123,618
15884
Warren
POTTERSVILLE WATER
DISTRICT / Chester (T)
325
$14,400
40
$6,245,138,018
17822
Warren
GLENS FALLS CITY / Glens Upgrade Distribution System
Falls (C)
13,000
$1,200,000
35
$6,246,338,018
17905
Warren
LAKE GEORGE VILLAGE /
Lake George (V)
Upgrade Distribution System
2,160
$1,650,675
30
$6,247,988,693
15896
Warren
CHESTERTOWN WATER
DISTRICT / Chester (T)
Well #1 - Rehab and Testing, Upgrade Ground Water Source
1,300
$15,500
25
$6,248,004,193
15805
Warren
WARRENSBURG WATER
DISTRICT / Warrensburg
(T)
Upgrade Ground Water Source
3,600
$375,000
25
$6,248,379,193
15897
Warren
CHESTERTOWN WATER
DISTRICT / Chester (T)
Upgrade Distribution System
1,300
$42,200
20
$6,248,421,393
15894
Warren
CHESTERTOWN WATER
DISTRICT / Chester (T)
Upgrade Storage
1,300
$56,700
20
$6,248,478,093
15891
Warren
CHESTERTOWN WATER
DISTRICT / Chester (T)
Well #1 - New Pump House, Upgrade Ground Water Source
1,300
$108,100
20
$6,248,586,193
15888
Warren
POTTERSVILLE WATER
DISTRICT / Chester (T)
Upgrade Distribution System
325
$619,000
20
$6,249,205,193
15095
Warren
BOLTON WATER
DISTRICT / Bolton (T)
Upgrade Distribution System
1,800
$672,000
10
$6,249,877,193
GRANVILLE VILLAGE /
Granville (V)
New Surface Water Treatment Rule Compliance Facility, Upgrade
Ground Water Source, Upgrade Transmission, Upgrade Distribution
System
2,645
1220
$6,249,877,193
2,000
$1,100,000
140
$6,250,977,193
25
$69,834
95
$6,251,047,027
Upgrade Ground Water Source
Washington County
17642
Washington
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
17645
Washington
GREENWICH VILLAGE /
Greenwich (V)
New Surface Water Treatment Rule Compliance Facility, New Storage
16619
Washington
HULETTS ON LAKE
GEORGE / Huletts on Lake
George
New Water Treatment Plant
17448
Washington
KINGSBURY WD
(QUEENSBURY) /
Kingsbury (T)
New water district to serve residents in area of groundwater
contamination , New Distribution System, New Water District
1,300
$845,000
85
$6,251,892,027
17342
Washington
CAMBRIDGE VILLAGE /
Cambridge (V)
Aquisition of existing Cambridge Water Works, New Storage, Upgrade
Distribution System
1,524
$2,500,000
80
$6,254,392,027
Page 78 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Washington County
15435
Washington
FORT EDWARD WD #2 /
Fort Edward (T)
Extend Distribution System
126
$650,000
70
$6,255,042,027
16240
Washington
PLEASANT VALLEY
INFIRMARY / Pleasant
Valley Infirmary
Upgrade Ground Water Source
160
$8,410
55
$6,255,050,437
17536
Washington
FORT EDWARD VILLAGE /
Fort Edward (V)
Replacement of water main beneath Hudson River to Rogers Island.,
Upgrade Transmission
3,150
$160,200
50
$6,255,210,637
15106
Washington
CAMBRIDGE WATER
WORKS / Cambridge Water
Works/Aqua. Am
New Storage
2,313
$136,000
40
$6,255,346,637
15830
Washington
WHITEHALL VILLAGE /
Whitehall (V)
Upgrade Distribution System
2,800
$576,281
30
$6,255,922,918
900
$3,605,000
215
$6,259,527,918
Wayne County
18005
Wayne
SAVANNAH WD #1 /
Savannah (T)
New Surface Water Treatment Rule Compliance Facility, New Storage,
Upgrade Distribution System, Extend Distribution System
17289
Wayne
WOLCOTT VILLAGE /
Wolcott (V)
New Water Treatment Plant, Upgrade Ground Water Source
2,200
$1,250,000
145
$6,260,777,918
17932
Wayne
ROSE - NORTH ROSE WD
/ Rose (T)
Upgrade Ground Water Source, Upgrade Distribution System, Extend
Distribution System, New System Consolidation
1,950
$11,434,000
120
$6,272,211,918
16415
Wayne
ARCADIA MOBILE HOME
PARK / James Taccone
New Transmission, Upgrade Distribution System, System
Consolidation
75
$180,000
95
$6,272,391,918
15325
Wayne
WOLCOTT VILLAGE /
Wolcott (V)
Upgrade Water Treatment Plant, Upgrade Surface Water Source
2,200
$3,300,000
80
$6,275,691,918
15324
Wayne
LYONS VILLAGE / Lyons
(V)
Upgrade Surface Water Source, New Ground Water Source, Upgrade
Transmission
3,695
$2,550,000
70
$6,278,241,918
16916
Wayne
ARCADIA (T) WATER
SYSTEM / Arcadia (T)
Extend Distribution System
60
$150,000
55
$6,278,391,918
16780
Wayne
MARION WD #1 / Marion
(T)
Northeast Quadrant Water District., Extend Distribution System
2,616
$480,000
55
$6,278,871,918
17743
Wayne
PALMYRA VILLAGE /
Palmyra (V)
Replace existing WTP and RW transmission main., New Water
Treatment Plant, New Transmission
3,550
$8,315,400
55
$6,287,187,318
17712
Wayne
WOLCOTT VILLAGE /
Wolcott (V)
Upgrade Water Treatment Plant
2,200
$2,987,000
55
$6,290,174,318
15834
Wayne
PALMYRA VILLAGE /
Palmyra (V)
New Pump Station
3,550
$102,700
45
$6,290,277,018
16779
Wayne
WALWORTH WD #1 /
Walworth (T)
Extension No. 19 & 20., Extend Distribution System
5,400
$598,000
45
$6,290,875,018
16778
Wayne
TOWN OF ROSE WATER
DISTRICT NO. 2 / Rose (T)
Extend Distribution System
680
$2,317,000
45
$6,293,192,018
16561
Wayne
ROSE - NORTH ROSE WD
/ Rose (T)
Extend Distribution System
1,950
$1,340,000
45
$6,294,532,018
16512
Wayne
OLD LYONS-NEWARK
ROAD WATER DISTRICT /
Lyons (T)
New Transmission
300
$207,000
45
$6,294,739,018
Page 79 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Wayne County
15218
Wayne
WALWORTH WD #1 /
Walworth (T)
Extend Distribution System
5,400
$2,730,000
40
$6,297,469,018
18070
Wayne
TRANSMISSION MAIN
REPLACEMENT / Clyde(V)
Upgrade Transmission
2,270
$357,900
40
$6,297,826,918
17714
Wayne
WOLCOTT VILLAGE /
Wolcott (V)
Upgrade Surface Water Source
2,200
$1,082,000
40
$6,298,908,918
17713
Wayne
WOLCOTT VILLAGE /
Wolcott (V)
Upgrade Storage
2,200
$757,000
40
$6,299,665,918
17716
Wayne
WOLCOTT VILLAGE /
Wolcott (V)
Upgrade Distribution System
2,200
$3,884,000
40
$6,303,549,918
15101
Wayne
ONTARIO TOWN BENEFIT
AREA #1 / Ontario (T)
New Transmission, New Storage
10,462
$4,913,000
40
$6,308,462,918
15480
Wayne
CLYDE VILLAGE / Clyde (V) New Ground Water Source
2,269
$232,780
35
$6,308,695,698
16720
Wayne
RED CREEK VILLAGE /
Red Creek (V)
Upgrade Distribution System
526
$102,935
30
$6,308,798,633
16174
Wayne
NEWARK VILLAGE /
Newark (V)
Upgrade Transmission
9,682
$1,556,038
30
$6,310,354,671
15832
Wayne
PALMYRA VILLAGE /
Palmyra (V)
Upgrade Surface Water Source
3,550
$291,050
20
$6,310,645,721
15914
Wayne
PALMYRA VILLAGE /
Palmyra (V)
Upgrade Transmission
3,550
$1,581,250
20
$6,312,226,971
17745
Wayne
ONTARIO TOWN BENEFIT
AREA #1 / Ontario (T)
Replace Ridge Road Storage Tank., New Storage
10,462
$1,911,500
20
$6,314,138,471
15918
Wayne
PALMYRA VILLAGE /
Palmyra (V)
Upgrade Storage
3,550
$189,750
20
$6,314,328,221
17737
Wayne
WCW&SA / Wayne County
Water&Sewer Auth.
Blaker Hill Storage Tank Improvements (Town of Macedon) Served by
Wayne County Water and Sewer Authority., Upgrade Storage
7,000
$521,000
15
$6,314,849,221
17744
Wayne
ONTARIO TOWN BENEFIT
AREA #1 / Ontario (T)
Clarifier rehabilitation., Upgrade Water Treatment Plant
10,462
$2,550,000
15
$6,317,399,221
17739
Wayne
WAYNE COUNTY
WATER&SEWER
AUTHORITY / Wayne
County Water&Sewer Auth.
Bunker Hill Storage Tank Improvements (Town of Macedon)., Upgrade
Storage
5,000
$310,000
15
$6,317,709,221
17736
Wayne
WAYNE COUNTY W. &S.A.
/ Wayne C'nty Water&Sewer
Auth.
Wallworth Storage Tank Improvements., Upgrade Storage
8,000
$533,000
15
$6,318,242,221
Extention #6 ( Phase III of 16239)Consolidation Amawalk-Shenorock
WD and other small water districts to become Somers W.D, New
Storage, New Distribution System
3,800
$1,042,875
2160
$6,319,285,096
22,400
$5,742,500
2080
$6,325,027,596
8,831
$0
225
$6,325,027,596
Westchester County
16983
Westchester
AMAWALK-SHENOROCK
WATER DIST. / Somers (T)
17849
Westchester
PEEKSKILL CITY / Peekskill Finished Water Storage Tanks (Phase 3 of 17152), New Storage
(C)
16013
Westchester
BRIARCLIFF MANOR
VILLAGE / Briarcliff
Manor(V)
Page 80 of 86
New Surface Water Treatment Rule Compliance Facility
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Westchester County
Installation of new wells to replace existing wells, New Ground Water
Source
15220
Westchester
CROTON FALLS WATER
DISTRICT / North Salem (T)
17488
Westchester
New Surface Water Treatment Rule Compliance Facility
WESTCHESTER JOINT
WATER WORKS /
Harrison&Mamaroneck(T)s&(
15923
Westchester
OSSINING WATER
DEPARTMENT / Ossining
(V)
15626
Westchester
16984
175
$400,000
135
$6,325,427,596
55,210
$65,000,000
120
$6,390,427,596
Upgrade Water Treatment Plant
30,000
$1,400,000
95
$6,391,827,596
GREENBURGH
CONSOLIDATED WD #1 /
Greenburgh (T)
Upgrade Water Treatment Plant
38,489
$1,000,000
75
$6,392,827,596
Westchester
KITCHAWAN WATER
DISTRICT / Yorktown (T)
correct organic exceedances., New Transmission
240
$500,000
70
$6,393,327,596
15750
Westchester
CORTLANDT
CONSOLIDATED WD /
Cortlandt (T)
Upgrade Storage, Upgrade Distribution System
28,369
$4,000,000
65
$6,397,327,596
16722
Westchester
SLEEPY HOLLOW
VILLAGE / Sleepy Hollow
(V)
Upgrade Transmission, Upgrade Storage, Upgrade Pump Station,
Distribution System
8,146
$6,514,750
60
$6,403,842,346
16699
Westchester
SUNSET RIDGE WATER
DISTRICT / North Salem (T)
Replacement of pump control equipment, storage tank cleaning &
coating, water main replacement & installation, pump house reapirs,
pump house fencing and driveway, Upgrade Storage, Upgrade Pump
Station, Upgrade Distribution System
625
$400,000
60
$6,404,242,346
17832
Westchester
KENSICO WATER
DISTRICT / Mount Pleasant
Locust Road Water Main Extension, Extend Distribution System
17,857
$8,000,000
55
$6,412,242,346
18039
Westchester
KHAL ADAS KASHAU /
Khal Adas Kashau
New chlorination system. , New Water Treatment Plant
650
$60,000
50
$6,412,302,346
16572
Westchester
RIPPOWAM CISQUA
SCHOOL - BEDFORD /
Rippowam Cisqua School
Route 22, Bedford(T), Other Expenses, New Water Treatment Plant,
Other (OT)
350
$48,590
50
$6,412,350,936
16098
Westchester
YONKERS CITY / Yonkers
(C)
New Transmission
196,086
$1,325,000
50
$6,413,675,936
17776
Westchester
WESTCHESTER COUNTY
WD #3 / Westchester
County #3
Water District #3 Improvements at Gate of Heaven Cemetery, New
Water Treatment Plant, Upgrade Pump Station
6,000
$9,800,000
50
$6,423,475,936
17584
Westchester
ARBOR HILLS WATER
WORKS / Arbor Hills
Waterworks
New wells, storage and booster pump., New Ground Water Source,
New Storage
180
$725,000
50
$6,424,200,936
15921
Westchester
OSSINING WATER
DEPARTMENT / Ossining
(V)
Upgrade Distribution System
30,000
$7,550,000
50
$6,431,750,936
16684
Westchester
NORTH CASTLE WD #1 /
North Castle (T)
New Transmission, New Transmission, Upgrade Storage, New Pump
Station
2,500
$610,000
45
$6,432,360,936
15527
Westchester
NEW CASTLE/STANWOOD
W.D. / New Castle (T)
New Storage
16,800
$3,979,500
45
$6,436,340,436
17833
Westchester
KENSICO WATER
DISTRICT / Mount Pleasant
Choate Lane Water Main Extension, Extend Distribution System
17,857
$532,000
45
$6,436,872,436
17831
Westchester
KENSICO WATER
DISTRICT / Mount Pleasant
Hardscrabble Road Water Main, Extend Distribution System
17,857
$4,588,500
45
$6,441,460,936
16136
Westchester
ELMSFORD VILLAGE /
Elmsford (V)
Upgrade Water Treatment Plant
4,600
$1,000,000
45
$6,442,460,936
Page 81 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Westchester County
16242
Westchester
TOWN OF NORTH
CASTLE / North Castle (T)
New Distribution System
16102
Westchester
YONKERS CITY / Yonkers
(C)
Upgrade Water Treatment Plant
15239
Westchester
MOUNT VERNON WATER
DEPARTMENT / Mount
Vernon (C)
New Transmission
16400
Westchester
CROTON FALLS WATER
DISTRICT / North Salem (T)
New Storage, Upgrade Distribution System
17910
Westchester
YONKERS CITY / Yonkers
(C)
17909
Westchester
17582
2,500
$1,200,000
40
$6,443,660,936
196,086
$500,000
40
$6,444,160,936
68,381
$7,000,000
35
$6,451,160,936
175
$314,150
30
$6,451,475,086
Upgrade electrical service and pumps at Hillview Pump Station,
Upgrade Pump Station
196,086
$3,180,691
25
$6,454,655,777
YONKERS CITY / Yonkers
(C)
Upgrade electrical service and pumps Nepperhan Ave. and Tuckhoe
Road, Upgrade Pump Station
196,086
$3,968,048
25
$6,458,623,825
Westchester
SCARSDALE WATER
DEPARTMENT / Scarsdale
(V)
Upgrade Ardsley Road Pumping Station, Upgrade Pump Station
20,883
$3,700,000
25
$6,462,323,825
17524
Westchester
NORTH CASTLE WD #2 /
North Castle (T)
New well and storage, New Ground Water Source, New Storage
1,200
$1,458,695
25
$6,463,782,520
17434
Westchester
WESTCHESTER COUNTY
WATER DISTRICT #1 /
Westchester County
Distribution system improvements, Upgrade Distribution System
187,000
$1,000,000
25
$6,464,782,520
16015
Westchester
BRIARCLIFF MANOR
VILLAGE / Briarcliff Manor
(V)
Upgrade Distribution System
8,831
$2,845,400
25
$6,467,627,920
17840
Westchester
WESTCHESTER JOINT
WATER WORKS / WJWW
York Road Transmission Main, Upgrade Transmission
65,000
$630,000
20
$6,468,257,920
15312
Westchester
CROTON FALLS WATER
DISTRICT / North Salem (T)
Upgrade Distribution System
175
$121,339
20
$6,468,379,259
17839
Westchester
WESTCHESTER JOINT
WATER WORKS / WJWW
Flagler Drive Transmission Main, Upgrade Transmission
55,210
$840,000
20
$6,469,219,259
17778
Westchester
UNITED WATER NEW
ROCHELLE / United Water
New Rochelle
Replace Distribution and Transmission, Upgrade Transmission,
Upgrade Distribution System
141,000
$4,120,000
20
$6,473,339,259
17435
Westchester
WESTCHESTER COUNTY
WATER DISTRICT #1 /
Westchester County
Interconnection to service Mt. Vernon and Yonkers, New
Inter-Connection
187,000
$10,000,000
20
$6,483,339,259
17162
Westchester
LARCHMONT VILLAGE /
Larchmont (V)
Replacement of two water storage tanks at 250,000 gallons each/
Byron Place, Upgrade Storage
6,485
$670,000
15
$6,484,009,259
17129
Westchester
WEST EXCEPTIONAL
CHILDRENS SCH /
Westchester Exceptional
Install UV disinfection unit, Upgrade Water Treatment Plant
70
$19,700
15
$6,484,028,959
15423
Westchester
MOUNT KISCO WATER
DEPARTMENT / Mount
Kisco (V)
New Distribution System
9,600
$3,738,900
15
$6,487,767,859
17061
Westchester
LAKE KATONAH CLUB INC
/ Lake Katonah Club Inc
Upgrade Storage
356
$131,910
15
$6,487,899,769
15594
Westchester
IRVINGTON WATER
SUPPLY / Irvington (V)
Upgrade Distribution System
6,631
$435,000
15
$6,488,334,769
Page 82 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Westchester County
16733
Westchester
PLEASANTVILLE WATER
DISTRICT / Pleasantville (V)
Upgrade Water Treatment Plant
18048
Westchester
YONKERS CITY / Yonkers
(C)
Upgrade Distribution System
16672
Westchester
PLEASANTVILLE WATER
DISTRICT / Pleasantville (V)
16608
Westchester
17946
9,500
$78,200
15
$6,488,412,969
196,086
$7,279,450
15
$6,495,692,419
Upgrade Storage, Upgrade Pump Station
9,500
$386,250
15
$6,496,078,669
PACE UNIVERSITY / Pace
University
Pace University, Pleasantville Campus., New Ground Water Source,
Upgrade Ground Water Source
2,753
$143,900
15
$6,496,222,569
Westchester
MOUNT VERNON (C) / Mt
Vernon Board Water Supply
Upgrade distribution system, Upgrade Distribution System
15,000
$3,700,000
15
$6,499,922,569
15407
Westchester
MOUNT KISCO WATER
DEPARTMENT / Mount
Kisco (V)
Upgrade Metered Interconnections w/Town of New Castle, Upgrade
Distribution System
9,600
$343,608
15
$6,500,266,177
17889
Westchester
MT VERNON BOARD OF
WATER SUPPLY / Mt
Vernon B'rd Water Supply
Cleaning and lining 36,800 feet of distribution main., Upgrade
Distribution System
15,000
$3,700,000
15
$6,503,966,177
15632
Westchester
OSSINING WATER
DEPARTMENT / Ossining
(V)
Upgrade Storage
30,000
$300,000
15
$6,504,266,177
17837
Westchester
WESTCHESTER JOINT
WATER WORKS / WJWW
Anderson Hill Road Booster Pump Station, New Pump Station
65,000
$400,000
15
$6,504,666,177
17838
Westchester
WESTCHESTER JOINT
WATER WORKS / WJWW
Rye Lake generator, Upgrade Water Treatment Plant
55,210
$475,000
15
$6,505,141,177
17829
Westchester
PLEASANTVILLE /
Pleasantville (V)
Replacement of water mains., Upgrade Distribution System
7,166
$1,955,000
15
$6,507,096,177
17774
Westchester
WESTCHESTER COUNTY
WD #1 / Westchester
County #1
Shaft 22 Chlorination Facility Security Improvements, Upgrade Water
Treatment Plant
187,004
$1,000,000
15
$6,508,096,177
16005
Westchester
HARRISON WATER
DISTRICT #1 / Harrison (T)
Upgrade Distribution System
6,940
$480,000
15
$6,508,576,177
17525
Westchester
NORTH CASTLE WD #1 /
North Castle (T)
Rehabilitation of water storage tanks, Upgrade Storage
2,500
$813,500
15
$6,509,389,677
16405
Westchester
BRIARCLIFF MANOR
VILLAGE / Briarcliff Manor
(V)
Upgrade Storage
8,831
$50,000
15
$6,509,439,677
16100
Westchester
YONKERS CITY / Yonkers
(C)
New Distribution System
196,086
$1,820,000
15
$6,511,259,677
16402
Westchester
CORTLANDT
CONSOLIDATED WD /
Cortlandt (T)
Upgrade Distribution System
28,369
$14,000,000
15
$6,525,259,677
16003
Westchester
HARRISON WATER
DISTRICT #1 / Harrison (T)
Upgrade Water Treatment Plant
6,940
$520,000
15
$6,525,779,677
15437
Westchester
MOUNT KISCO WATER
DEPARTMENT / Mount
Kisco (V)
Automated water meter reading system, Upgrade Distribution System
9,600
$1,003,014
15
$6,526,782,691
15911
Westchester
OSSINING WATER
DEPARTMENT / Ossining
(V)
Water distribution main replacement - Ellis Place, Upgrade Distribution
System
30,000
$498,500
10
$6,527,281,191
Page 83 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Westchester County
17160
Westchester
LARCHMONT VILLAGE /
Larchmont (V)
Upgrade Distribution System
6,485
$241,000
10
$6,527,522,191
15708
Westchester
BIRCH DRIVE WATER
DISTRICT / New Castle (T)
Upgrade Distribution System
50
$108,700
10
$6,527,630,891
15514
Westchester
PLEASANTVILLE WATER
DISTRICT / Pleasantville (V)
Water Mains for Sarles Lane, Upgrade Distribution System
9,500
$343,291
10
$6,527,974,182
17985
Westchester
BEAR RIDGE LAKE
WATER DISTRICT / Mount
Pleasant (T)
Water main replacement-Highland Place, Mountain Trail and Woodland
Road, Upgrade Distribution System
170
$1,436,085
10
$6,529,410,267
16542
Westchester
TARRYTOWN WATER
SUPPLY / Tarrytown (V)
Upgrade Distribution System
11,000
$10,620,000
10
$6,540,030,267
17836
Westchester
YONKERS CITY / Yonkers
(C)
Water main replacement Mulford Gardens, Upgrade Distribution
System
196,086
$1,259,000
10
$6,541,289,267
15633
Westchester
OSSINING WATER
DEPARTMENT / Ossining
(V)
Cement lining of water lines at various locations, Upgrade Distribution
System
30,000
$900,000
10
$6,542,189,267
17834
Westchester
KENSICO WATER
DISTRICT / Mount Pleasant
Cement lining of water mains, Upgrade Distribution System
17,857
$4,560,500
10
$6,546,749,767
17830
Westchester
KENSICO WATER
DISTRICT / Mount Pleasant
Phase VI Water Main Replacement, Upgrade Distribution System
17,857
$4,503,500
10
$6,551,253,267
17784
Westchester
TARRYTOWN WATER
SUPPLY / Tarrytown (V)
Cement line existing water main, Upgrade Distribution System
11,000
$1,892,110
10
$6,553,145,377
17783
Westchester
TARRYTOWN WATER
SUPPLY / Tarrytown (V)
Water main improvements, Upgrade Distribution System
11,000
$2,549,250
10
$6,555,694,627
17775
Westchester
WESTCHESTER COUNTY
WD #3 / Westchester
County #3
Lateral Main Rehabilitation, Upgrade Distribution System
6,000
$670,000
10
$6,556,364,627
16050
Westchester
WHITE PLAINS CITY /
White Plains (C)
Previously completed water mains, Upgrade Distribution System
53,077
$2,221,356
10
$6,558,585,983
16099
Westchester
YONKERS CITY / Yonkers
(C)
Upgrade Transmission
196,086
$1,024,600
10
$6,559,610,583
15507
Westchester
PLEASANTVILLE WATER
DISTRICT / Pleasantville (V)
Refinance '93 bonds for relining water mains, Upgrade Distribution
System
9,500
$4,155,408
10
$6,563,765,991
16052
Westchester
WHITE PLAINS CITY /
White Plains (C)
Davis and Whitney Ave. replacement and reconditioning, Upgrade
Distribution System
53,077
$1,000,000
10
$6,564,765,991
16007
Westchester
HARRISON WATER
DISTRICT #1 / Harrison (T)
Upgrade Distribution System
6,940
$215,000
10
$6,564,980,991
15929
Westchester
OSSINING WATER
DEPARTMENT / Ossining
(V)
Interconnection with (V) Briarcliff Manor with new 12" water main,
Upgrade Distribution System, Inter-Connection
30,000
$348,000
10
$6,565,328,991
15482
Westchester
ARDSLEY TRAVEL PLAZA
/ NYS Thruway Authority
Upgrade Distribution System
6,000
$770,000
5
$6,566,098,991
CASTILE VILLAGE / Castile
(V)
Upgrade Water Treatment Plant, Upgrade Ground Water Source,
Upgrade Storage
1,135
$5,111,267
215
$6,571,210,258
Wyoming County
17928
Wyoming
Page 84 of 86
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Wyoming County
15733
Wyoming
GARDEAU WATER
DISTRICT / Castile (T)
Upgrade Distribution System
17062
Wyoming
PIKE VILLAGE / Pike (V)
New Ground Water Source, Upgrade Ground Water Source, Upgrade
Transmission, Upgrade Distribution System
15778
Wyoming
ATTICA VILLAGE / Attica
(V)
17919
Wyoming
17845
60
$977,470
105
$6,572,187,728
369
$494,596
100
$6,572,682,324
Upgrade Storage, Upgrade Distribution System
2,700
$1,706,000
55
$6,574,388,324
ARCADE VILLAGE / Arcade
(V)
New Storage, New Distribution System
2,400
$2,458,000
55
$6,576,846,324
Wyoming
NORTH JAVA WATER
DISTRICT / Java (T)
New Ground Water Source
270
$441,190
55
$6,577,287,514
15716
Wyoming
WARSAW VILLAGE /
Warsaw (V)
Upgrade Ground Water Source
3,850
$338,870
50
$6,577,626,384
18018
Wyoming
CASTILE VILLAGE / Castile
(V)
Upgrade Other Expenses, Upgrade Storage, Upgrade Distribution
System, New System Consolidation, Upgrade Other (OT)
1,135
$2,444,813
50
$6,580,071,197
17384
Wyoming
PERRY VILLAGE / Perry (V) Upgrade Transmission, Upgrade Distribution System
3,945
$1,421,200
45
$6,581,492,397
15225
Wyoming
CASTILE VILLAGE / Castile
(V)
Upgrade Ground Water Source, Upgrade Distribution System
1,135
$2,232,401
35
$6,583,724,798
17722
Wyoming
COWLESVILLE WATER
DISTRICT / Bennington (T)
New Other Expenses, New Other (OT)
375
$99,930
35
$6,583,824,728
16074
Wyoming
PERRY VILLAGE / Perry (V) Upgrade Storage, Upgrade Distribution System
3,945
$2,369,188
35
$6,586,193,915
18063
Wyoming
WATER SYSTEM
UPGRADES /
Upgrade Distribution System
400
$775,000
10
$6,586,968,915
Yates County
15592
Yates
FREEDOM VILLAGE U.S.A.
/ Freedom Village USA
New Water Treatment Plant
160
$287,000
125
$6,587,255,915
17355
Yates
DRESDEN VILLAGE /
Dresden (V)
New Transmission, Upgrade Storage, New Inter-Connection
700
$515,000
125
$6,587,770,915
17801
Yates
WD #1 / Torrey (T)
New Distribution System
375
$3,079,875
115
$6,590,850,790
15483
Yates
BENTON TOWN WATER
DISTRICT NO. 1 / Benton
(T)
Extend system to serve area with private contaminated wells. , Extend
Distribution System
97
$639,000
65
$6,591,489,790
18015
Yates
WS IMPROVEMENTS /
Dundee (V)
Upgrade Storage, Upgrade Distribution System
1,690
$6,913,360
55
$6,598,403,150
16568
Yates
PENN YAN FLYING CLUB
INC / Penn Yan Flying Club
Upgrade Distribution System
46
$396,000
55
$6,598,799,150
17191
Yates
PENN YAN VILLAGE / Penn Upgrade Water Treatment Plant
Yan (V)
5,248
$1,300,000
50
$6,600,099,150
16944
Yates
POTTER WATER
DISTRICT NO. 1 / Potter (T)
285
$1,702,900
50
$6,601,802,050
Page 85 of 86
New Complete System (New System)
NYS Drinking Water State Revolving Fund Final Multiyear List
October 1, 2011 to September 30, 2012
Project County
System Name/
Borrower
Description
Pop.
Project Cost
Score
Cumulative
Total
Yates County
15695
Yates
PENN YAN VILLAGE / Penn Upgrade Transmission, Upgrade Distribution System
Yan (V)
5,248
$1,310,300
40
$6,603,112,350
17431
Yates
PENN YAN VILLAGE / Penn Seneca Street water main improvements., Upgrade Distribution
System
Yan (V)
5,248
$412,000
40
$6,603,524,350
17430
Yates
PENN YAN VILLAGE / Penn Sheppard Street water main improvements., Upgrade Distribution
System
Yan (V)
5,248
$590,000
40
$6,604,114,350
18036
Yates
PENN YAN VILLAGE / Penn New Transmission
Yan (V)
5,248
$1,340,000
35
$6,605,454,350
18050
Yates
BENTON WD #1 /
308
$731,000
10
$6,606,185,350
Total # Projects
Extend Distribution System
Total Cost
1696
$6,606,185,350
Page 86 of 86
CATEGORY C LIST
HARDSHIP
Project County
17473
17321
17456
17388
15881
17561
17461
15072
17647
15343
15204
17543
17576
16261
17538
17306
17382
17457
16882
17140
Jefferson
Jefferson
Hamilton
Essex
Essex
Chautauqua
Orange
Orange
Saratoga
Otsego
Oswego
Saratoga
Chautauqua
Oswego
Oswego
Jefferson
Allegany
Erie
Onondaga
St.Lawrence
NYS Drinking Water State Revolving Fund
Final Category C Hardship List for October 1, 2011 to September 30, 2012
System Name/
Borrower
Description
Pop.
Project Cost Score
LAFAVE ROAD WATER
DISTRICT / Le Ray (T)
Consolidation of existing public water systems with GUDI wells,
coliform and lead violations., New Distribution System, New System
Consolidation
600
WESTCOTTS WATER
DISTRICT / Hounsfield (T)
Westcotts WD to serve along NYS Route 3. Consolidation of PWS
systems addressing SWTR & E-Coli violations. , Upgrade Storage,
New Distribution System, New System Consolidation
300
INDIAN LAKE WD / Indian
Lake (T)
New Surface Water Treatment Rule Compliance Facility, Upgrade
Water Treatment Plant, New Ground Water Source, Upgrade
Distribution System
900
PORT KENT WD /
Chesterfield (T)
New Surface Water Treatment Rule Compliance Facility, New
Ground Water Source, New Storage
202
WADHAMS WD / Westport
(T)
New Surface Water Treatment Rule Compliance Facility, New
Inter-Connection, New System Consolidation
FORESTVILLE VILLAGE /
Forestville (V)
New Surface Water Treatment Rule Compliance Facility, New
Ground Water Source, Upgrade Distribution System
PHEASANT HILL / Pheasant
Hill Water Corp
Rehabilitation of water system to address e-coli contamination,
Upgrade Water Treatment Plant, New Ground Water Source, New
Storage
154
BEAVER DAM LAKE WATER
CORP. / Beaver Dam Lake
Corp.
New Surface Water Treatment Rule Compliance Facility, New
Ground Water Source, New Storage, Upgrade Distribution System
487
STILLWATER VILLAGE /
Stillwater (V)
Alternative Water Source for Surface Water Treatment Rule
compliance., New Transmission, New Inter-Connection
UNADILLA VILLAGE /
Unadilla (V)
Install new well, pumphouse, controls, chlorination system to replace
GWUDI springs, New Surface Water Treatment Rule Compliance
Facility, New Ground Water Source, Upgrade Pump Station, Upgrade
Distribution System
1,350
HANNIBAL (T) / Hannibal (T)
Extend system to serve area with private contaminated wells,
consolidate public water supply. , Extend Distribution System, New
System Consolidation
1,200
MOREAU WD
7/CONNECTION TO SCWA /
Moreau (T)
Consolidate 3 small CWSs, consolidate WD 1, connect Town with
SCWA, New Storage, Extend Distribution System, New
Inter-Connection, Extend System Consolidation, New Water District
1,100
CHERRY CREEK VILLAGE /
Cherry Creek (V)
New Surface Water Treatment Rule Compliance Facility, Upgrade
Distribution System
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
140
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
804
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
1,572
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
650
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
New Surface Water Treatment Rule Compliance Facility, New
TOAD
HARBOR/CONSTANTIA WD / Storage, New Pump Station, New Distribution System, New
Inter-Connection, New System Consolidation
Constantia (T)
2,765
WATER DISTRICT #2 /
Richland (T)
New Surface Water Treatment Rule Compliance Facility, New
Ground Water Source, New Transmission, New Storage, New
Distribution System
1,662
WATER DISTRICT #2 /
Henderson (T)
New Surface Water Treatment Rule Compliance Facility, New
Distribution System, New System Consolidation
352
HOUGHTON WATER
DISTRICT / Caneadea (T)
Upgrade Water Treatment Plant, New Ground Water Source, New
Transmission, Upgrade Distribution System
CHAFFEE WATER CO /
Chaffee Water Co.
New Surface Water Treatment Rule Compliance Facility, New
Ground Water Source, New Storage
LIMELEDGE WD / Marcellus
(T) & (V)
New Water District to serve area with insufficient private wells.
Interconnection with GWUDI system., New Surface Water Treatment
Rule Compliance Facility, Extend Distribution System
LOUISVILLE WATER
DISTRICT #2 / Louisville (T)
New Storage, Upgrade Distribution System, System Consolidation
Page 1 of 3
$0
Cumulative
Total
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
2,000
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
200
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
700
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
1,000
$0
H
$0
NOTE: Short - Term Loan Closed, Project Cost Shown is
Remaining Balance Not Funded With Short Term Loan
Project County
NYS Drinking Water State Revolving Fund
Final Category C Hardship List for October 1, 2011 to September 30, 2012
System Name/
Borrower
Description
Pop.
Project Cost Score
17611
Franklin
SARANAC LAKE V / Saranac
Lake (V)
New SCADA equipment., New Surface Water Treatment Rule
Compliance Facility, Upgrade Distribution System
16746
Allegany
CANASERAGA VILLAGE
PUBLIC WATER /
Canaseraga (V)
New Ground Water Source, Upgrade Storage
17497
Montgomery
AMSTERDAM (C) /
Amsterdam (C)
Upgrade Surface Water Treatment Rule Compliance Facility,
Upgrade Water Treatment Plant, Upgrade Water Treatment Plant,
Upgrade Water Treatment Plant
15003
Ulster
ELLENVILLE (VILLAGE)
WATER DIS / Ellenville (V)
17928
Wyoming
18005
5,800
Cumulative
Total
$12,500,000
H
$12,500,000
$3,666,749
H
$16,166,749
20,700
$737,000
H
$16,903,749
Water system improvements, Upgrade Surface Water Treatment
Rule Compliance Facility, Upgrade Storage, Upgrade Distribution
System
4,323
$7,136,870
H
$24,040,619
CASTILE VILLAGE / Castile
(V)
Upgrade Water Treatment Plant, Upgrade Ground Water Source,
Upgrade Storage
1,135
$5,111,267
H
$29,151,886
Wayne
SAVANNAH WD #1 /
Savannah (T)
New Surface Water Treatment Rule Compliance Facility, New
Storage, Upgrade Distribution System, Extend Distribution System
900
$3,605,000
H
$32,756,886
17425
Chenango
SO. NEW BERLIN WATER
DISTRICT / New Berlin (T)
New Ground Water Source, New Transmission, New Storage,
Upgrade Distribution System, System Consolidation
400
$3,272,000
H
$36,028,886
15603
Jefferson
WATER DISTRICT NO. 5 /
Hounsfield (T)
Extend distribution system to area of insufficient yielding or
cantaminated private wells. Consolidate Watertown International
Airport., New Distribution System, New System Consolidation
345
$4,800,000
H
$40,828,886
17427
Albany
NEW SALEM WATER
DISTRICT / New Scotland (T)
New Surface Water Treatment Rule Compliance Facility, New
Storage, New Pump Station, New Inter-Connection, New Water
District
486
$3,048,000
H
$43,876,886
17442
Erie
BRANDT (T), NORTH
COLLINS (T)&(V) / North
Collins (V)
WTP improvements for lead and copper violations, Fe violations,
Asbestos Main replacement, inadequate pressures, Upgrade Water
Treatment Plant, Upgrade Transmission, Upgrade Distribution
System, New System Consolidation
1,915
$5,430,000
H
$49,306,886
17379
Steuben
COOPERS PLAINS/LONG
ACRES WATER SYST /
Erwin (T)
New Ground Water Source, Extend Distribution System, New System
Consolidation
1,400
$0
H
$49,306,886
17552
Herkimer
NEWPORT VILLAGE /
Newport (V)
New Surface Water Treatment Rule Compliance Facility, New
Ground Water Source, Upgrade Transmission, New Storage,
Upgrade Distribution System
740
$2,175,000
H
$51,481,886
16278
Hamilton
LONG LAKE (T) / Long Lake
(T)
New Ground Water Source, New Storage, Upgrade Distribution
System
750
$3,929,255
H
$55,411,141
16692
Herkimer
VAN HORNESVILLE WATER
WORKS / Stark (T)
VanHornesville Water System, New Surface Water Treatment Rule
Compliance Facility, New Storage, Upgrade Distribution System
372
$2,098,150
H
$57,509,291
17625
Oswego
EASTERN SHORE WATER
SYSTEM / Sandy Creek (T)
Consolidation of PWS with GWDI source., New Storage, New
Distribution System, New System Consolidation
$13,988,000
H
$71,497,291
17372
Oswego
MEXICO (T) WD#2 / Mexico
(T)
Extend distribution system to area with contaminated private wells
and consolidate PWS with GWUDI source, New Distribution System,
New System Consolidation
800
$7,060,000
H
$78,557,291
17637
Chautauqua
NORTH END WD / Pomfret
(T)
Extend distribution system to area with contaminated private wells
and consolidate PWS with Coliform, New Distribution System
900
$4,432,100
H
$82,989,391
16114
Cayuga
CAYUGA VILLAGE / Cayuga
(V)
New Surface Water Treatment Rule Compliance Facility, Upgrade
Distribution System, New Inter-Connection
600
$6,875,100
H
$89,864,491
17331
Rensselaer
POESTENKILL (T) WD #1 /
Poestenkill (T)
New Complete System (New System), New System Consolidation
2,300
$0
H
$89,864,491
17589
Cattaraugus
CRYSTAL WATER CO
(WEST VALLEY) / Ashford (T)
New Surface Water Treatment Rule Compliance Facility, Upgrade
Ground Water Source
880
$3,208,500
H
$93,072,991
Page 2 of 3
900
2,503
Project County
NYS Drinking Water State Revolving Fund
Final Category C Hardship List for October 1, 2011 to September 30, 2012
System Name/
Borrower
Description
Pop.
Project Cost Score
18017
Allegany
RICHBURG VILLAGE
PUBLIC WATER / Richburg
(V)
(V) Richburg & (V) Bolivar Consolidation., New Surface Water
Treatment Rule Compliance Facility, New Ground Water Source,
Upgrade Storage, Upgrade Distribution System, New System
Consolidation
17682
Essex
WD#4 / Moriah (T)
16510
Schenectady
17629
Cumulative
Total
600
$7,038,640
H
$100,111,631
New Surface Water Treatment Rule Compliance Facility, New
Distribution System
78
$1,990,475
H
$102,102,106
DELANSON VILLAGE
WATER WORKS / Delanson
(V)
Upper resevoir raw water transmission main, new intake, new
controls & meters at filter plant., New Transmission, Extend
Distribution System, Upgrade Distribution System
428
$4,594,000
H
$106,696,106
Essex
ESSEX WD / Essex (T)
Address turbidity and organic violations, New Ground Water Source,
Upgrade Distribution System
300
$1,515,954
H
$108,212,060
17367
Steuben
TROUPSBURG WATER
DISTRICT / Troupsburg (T)
New Surface Water Treatment Rule Compliance Facility, Upgrade
Water Treatment Plant
250
$192,000
H
$108,404,060
16618
Dutchess
SHOREHAVEN CIVIC
ASSOC / DCWWA
DCWWA ZONE J SHOREHAVEN WATER SYSTEM, Upgrade
Water Treatment Plant, Upgrade Ground Water Source, Upgrade
Distribution System
300
$3,575,000
H
$111,979,060
17623
Saratoga
CORINTH VILLAGE / Village
of Corinth
New Surface Water Treatment Rule Compliance Facility, Upgrade
Distribution System
4,700
$6,200,000
H
$118,179,060
17931
Cayuga
PORT BYRON VILLAGE /
Port Byron (V)
Joint project with (V) Port Byron, (T) Montezuma & (T) Mentz.,
Upgrade Distribution System, Extend Distribution System, New
System Consolidation
1,400
$5,657,000
H
$123,836,060
17454
St.Lawrence
EAST LOUISVILLE WD#3 /
Louisville (T)
Consolidation of water systems with past coliform detections., New
Storage, New Distribution System, New System Consolidation
1,030
$9,275,000
H
$133,111,060
Total # Projects
Total Cost
49
$133,111,060
Page 3 of 3
ATTACHMENTS
TO THE
INTENDED USE PLAN
FOR THE
NEW YORK STATE DRINKING WATER STATE
REVOLVING FUND
ATTACHMENT I
PROJECT PRIORITY RANKING SYSTEM
Project Priority Ranking System for the
Drinking Water State Revolving Fund (DWSRF)
(I) Priority Ranking System and Intended Use Plan
A. Priority Ranking System
The purpose of the priority ranking system is to establish a list of eligible projects to be funded in
a manner that the most serious risks to public health are given the highest priority. The New
York State Department of Health (NYSDOH) proposes that the highest priority be given to acute
public health risks, particularly those related to microbiological organisms. The next priority has
been given to situations that pose chronic and longer-term risks to consumers, such as organic
chemical contamination. The scoring criteria also considers issues that are related to
infrastructure upgrading or replacement. Consistent with these priorities, the numerical scores in
the Drinking Water State Revolving Fund (DWSRF) priority ranking system are based on the
following criteria:
Technical Factors
A. MCL/Treatment Technique Violations
B. Other Sanitary Code Violations
C. System Reliability/Dependability Issues
Non-Technical Factors
D. Governmental Needs
E. Financial Needs
The total numerical score for a project or a project segment will be the sum of the scores for
criteria A, B, C, D and E.
B. Intended Use Plan
The State will prepare a document called the Intended Use Plan (IUP) that describes how the
State intends to use available DWSRF resources for the year to meet the objectives of the Safe
Drinking Water Act (SDWA) and to further the goal of protecting public health. The IUP will
include specific detail on how the State will use all funds available. The IUP will also include a
list of projects expected to qualify for financing within the fiscal period addressed by the IUP. A
project must be listed in an IUP to be eligible for financing.
I-1
(II) Project Ranking
A. Special Allocations and Restrictions
The federal Safe Drinking Water Act Amendments of 1996 (SDWA) require that, on an annual
basis, water systems serving fewer than 10,000 persons must receive a minimum of 15% of the
DWSRF. This minimum allocation for systems serving less than 10,000 persons will occur to the
extent that there are a sufficient number of eligible projects to fund.
The SDWA also states that up to 30% of the annual DWSRF federal capitalization grant can be
used to give loan subsidies to disadvantaged communities.
The State of New York will impose an annual cap or ceiling of 50% of DWSRF resources that
can be received by any single applicant. In addition, the State may limit DWSRF financing to
the demonstrated annual cash flow needs of any single applicant.
The New York State Clean Water/Clean Air Bond Act of 1996 requires the development of a
Memorandum of Understanding among the Governor and Legislative Leaders regarding selection
of projects to be funded from the Drinking Water provisions of the Bond Act. Projects identified
in the Memorandum of Understanding will be incorporated into an annual funding list for Bond
Act financing in conjunction with projects selected according to the Priority Ranking System.
B. Project Ranking Categories
Projects will be placed in categories to allow priority ranking within a specific grouping of
projects. Federal legislation requires that, on an annual basis, a minimum of 15% of the DWSRF
be received by water systems serving fewer than 10,000 people. Also, water systems that qualify
for financial hardship have special conditions that require a separate category for these projects.
Therefore, three priority ranking categories will be created:
1. Category A. Water systems serving > 10,000 people.
2. Category B. Water systems serving < 10,000 people.
3. Category C. Water systems that have received written confirmation of
qualification for financial hardship assistance.
C. Description and Use of the Project Lists
Several lists of projects will be created to organize and manage projects with different levels of
priority and readiness. These listings will display the status of all projects in the system and
indicate the final list of projects that qualify for funding in the current IUP.
1. Multi-Year List:
This list will contain all eligible projects for which pre-application forms have
been submitted and reviewed. This list will contain projects from Categories A
and B. New projects can be added to this list on a continuous basis. Projects must
be on the Multi-Year List to be eligible for short-term loans when short-term loans
are made available.
I-2
Short-term loans for projects listed on the Multi-Year List will be limited to
projects that have a total numerical score greater than (or equal to) the project with
the lowest score (excluding bonus points awarded under Section II.E.2.) eligible to
be funded from the current Project Readiness List. Applications for short-term
loans, when available, will be approved on a first come/first served basis, up to the
total amount reserved in the IUP for that purpose.
NOTE: Short-term loans may not be offered in the initial years of the DWSRF
program.
2. Hardship List:
This list will contain all projects with written confirmation that they qualify for
financial hardship assistance (Category C). This written confirmation will be
limited to projects that have a total numerical score greater than (or equal to) the
project with the lowest score (excluding bonus points awarded under Section
II.E.2.) eligible to be funded from the current Project Readiness List. These
projects will be selected from the Multi-Year List. Written qualification for
financial hardship assistance will remain valid for two consecutive annual federal
funding cycles. If a project has not been selected for funding during this period, it
will be removed from the Hardship List (and re-listed on the Multi-Year List)
unless requalified for the Hardship List.
3. Project Readiness List:
This list will contain Category C projects and the projects from the Multi-Year List
which are anticipated to be ready for long-term financing during the effective
period of the IUP. Applicants for these projects are expected to apply for the funds
projected to be available during the fiscal period addressed by the IUP. Projects
from Categories A and B will be listed in descending order of total numerical score
(resulting from the Priority Ranking System Scoring Criteria).
4. Funding List:
This list will include all projects from the Project Readiness List expected to
qualify for long-term loans within a particular IUP. Projects will be listed
according to the three project categories. All Category C that are on the Project
Readiness List will qualify for funding. Projects in Category A will then be
selected from the Project Readiness List in priority order to meet the 15%
minimum requirement for water systems serving less than 10,000 people. All
remaining projects on the Project Readiness List will be selected in priority order
until the remaining annual DWSRF funding amount is encumbered. The project
selection is subject to Restrictions and Project By-pass Criteria in Sections II.A
and D of this document.
I-3
D. Project By-pass
Projects on the Project Readiness List can be by-passed, upon written notice, if any of the
following occurs:
1. Project is withdrawn by the applicant.
2. Project does not meet the dates and/or conditions in the project schedule or the
Project Financing and Loan Agreement.
3. The applicant has reached the 50% annual DWSRF resources cap for fundable
projects on the Project Readiness List. All other projects for the applicant that
would exceed the 50% cap will be by-passed.
E. Special Priorities
1. Emergencies:
An emergency is a catastrophic situation that results in an imminent threat to
public health. The determination of when an emergency exists will be made by the
NYS DOH. Imminent threats to public health include situations that result in the
unavailability of a source of potable drinking water for an extended period of time.
Projects designed to address emergencies will receive the highest priority ranking.
2. Projects with Prior Funding Agreements:
Projects with executed Project Financing and Loan Agreements for long-term and
short-term DWSRF loans will be given significant additional bonus points when
they are placed on the Project Readiness List. This will help to ensure the
availability of DWSRF financing needed for completion of on-going projects.
Phased or segmented projects for which additional funds have been conditionally
committed in an executed Project Financing and Loan Agreement (PFLA) for
long-term DWSRF financing will be listed, in descending priority score order.
These projects will be assigned 2000 points in addition to their total project
ranking system score.
Projects for which funds have been committed in an executed PFLA for short-term
DWSRF financing will be listed, in descending priority score order. These
projects will be assigned 1000 points in addition to their total project ranking
system score. Other projects will then be listed in descending priority score order.
F. Tie Breaking
In the event of a tie score for projects, the higher total score under Technical Factors (Criteria A,
B and C) will be used as a tie breaker. If this still results in a tie score, the size of the population
served by the system will be used as a tie breaker. The larger population will be given preference.
I-4
G. Eligible Project Limitation
Eligible projects are activities that address critical water system problems. The NYS DOH may
require separation of unrelated project components into separate projects if it is necessary to focus
on critical water system problems. These separate projects will be scored independently. Projects
must be adequately supported by technical documentation, data, reports, etc.
(III)
Priority Ranking System Scoring Criteria
The numerical scores in the DWSRF priority ranking system are based on technical and nontechnical criteria. The technical criteria are A.) MCL/treatment technique violations; B.) Other
sanitary code violations; and C.) system reliability and dependability issues. The non-technical
criteria are D.) governmental needs and E). financial needs. The total numerical score for the
project or project segment being scored shall be the sum of the scores for criteria A, B, C, D and
E. Projects must be adequately supported by technical documentation, data, reports, etc.
Technical Factors
A. MCL/Treatment Technique Violations. Points awarded are based on treatment of MCL
exceedances and/or replacement with an alternate source of supply, and for
interconnection with, or purchase from adjacent water system(s) in lieu of treatment
(more than one item may apply):
1. Microbiological
Score
a) Surface Water Treatment Rule
i. Filtration
100
ii. Filtration Performance Criteria (NTU compliance)
50
iii. CT Disinfection
30
b) E. coli
80
c) Total Coliform
40
2. Organics
Organic chemicals (POC/UOC) and disinfection by-products
40
3. Lead and Copper/Corrosion (mandated)
30
4. Radiological
25
5. Inorganic/Physical
a) Nitrates
50
b) Other health-related
25
c) Aesthetic
10
B. Non-treatment Sanitary Code Violations (more than one item may apply):
The project need must be adequately supported by technical documentation, data,
reports, etc.
1. Inadequate Source Capacity (public health hazard)
2. Inadequate Distribution Pressure (public health hazard)
3. Uncovered Finished Water Storage (public health hazard)
I-5
50
25
25
C. System Reliability/Dependability Issues (more than one item may apply):
The project need must be adequately supported by technical documentation,
data, reports, etc.
Score
1. Complete replacement or major rehabilitation of existing
treatment facility for primary contaminants that has exceeded
design life and/or does not meet the design standards in the
current edition of Recommended Standards For Water Works.
In lieu of treatment, replacement with an alternate source of
supply, and/or interconnection with, or purchase from, adjacent
water system.
20
2. Upgrade, replace and/or install major vulnerable system
components to meet the design standards in the current edition
Recommended Standards For Water Works. Any of the
following apply.
10
a) A principal component integral to an existing filtration
process such as sedimentation, flocculation, filtration,
chemical feed, or backwashing (can only receive points
for Criteria C.2a. or C.1.)
b) Pump stations
c) Existing wells
d) Existing disinfection system for a groundwater/surface water supply
e) Transmission main
f) Finished water or distribution storage
g) Other water treatment systems for secondary contaminants only (or
replacement of source instead of treatment)
3. Aged mains and appurtenances
4. Redundancy of critical components
(pumps, valves, chemical feed-systems, etc.)
5. Asbestos main replacement
6. Control/automation for operational efficiency
(computerization, control valves, metering,
laboratory upgrading)
7. Inadequate source capacity which is not a public
health hazard (can only receive points for Criteria
B1 or C7)
I-6
5
5
5
5
5
Non-Technical Factors:
Score
D. Governmental Needs (more than one may apply)
Additional points will be assigned to a project on the basis of state or local
government needs, policies, and/or requirements.
1. Development of a water system or extending existing
system to service contaminated or insufficient
yielding private wells at existing residential housing
(new systems are not eligible for points under Criteria A,
B or C)
40
2. Consolidation of water systems (can include
improving technical, managerial and financial
capacity development)
25
3. System dependent on a Sole Source Aquifer for
its source. (These points can only be obtained if
system scores points from Criterion A, B, C.1. or C.2.g.)
25
4. A project that has received written commitment
of funding from another governmental source (e.g., co-funded
with Clean Water SRF, Rural Development, HUD, etc.)
These points do not apply to refinancing of projects.
10
5. Consistent with Water Resources Management Strategy
5
6. Proposes operational changes that improve and insure
adequate technical, managerial and financial capacity
of the system in order to insure compliance (guidelines
to be developed)
5
E. Financial Need
The Median Household Income (MHI) of the community in which the water service
area is located is used as a numerator and the Statewide MHI is used as the
denominator in the following equation to determine the financial need factor.
Community MHI x 100
Statewide MHI*
Factor
Points
= Factor
<70 >70 -<77.5 >77.5 - <85 >85 - <92.5 >92.5 - <100
25
20
15
10
5
>100
0
*2000 Statewide MHI is $43,393.
The MHI of the community in which the water service area is located and the Statewide MHI will be determined
from income data in the most recent United States census. If there is reason to believe that the census data are not
an accurate representation of the MHI within the area to be served, the reasons will be documented and the
applicant will furnish, or the Department may obtain, additional information regarding the MHI. Information will
consist of reliable data from local, regional, state or federal sources or from an income survey conducted by a
reliable impartial source.
I-7
Appendix A. Glossary of Terms
CT - The product of the free residual disinfectant concentration (C) in milligrams per liter determined
before or at the first customer, and corresponding disinfectant contact time (T) in minutes, expressed by
the formula (C) x (T) = CT. (10 New York Code of Rules and Regulations (NYCRR) Part 5, Subpart 5-1,
Public Water Systems.)
DWSRF - Drinking Water State Revolving Fund.
construction of drinking water projects.
A fund for financing, planning, design and
E. coli - Escherichia coli. A microscopic organism of fecal origin.
HUD - United States Department of Housing and Urban Development.
MCL - Maximum Contaminant Level. The maximum permissible level of a contaminant in water which
is delivered to any user of a public water system as specified in 10 NYCRR Part 5, Subpart 5-1, Public
Water Systems.
MHI - Median Household Income.
NTU - Nephelometric Turbidity Unit. The system under which measured turbidity is reported.
PFLA - Project Financing and Loan Agreement. An agreement between the NYS Environmental
Facilities Corporation and a loan recipient in order to provide financial assistance from the DWSRF for an
eligible project.
POC - Principal Organic Contaminant. Any organic chemical compound belonging to specific chemical
classes as described in 10 NYCRR Part 5, Subpart 5-1, Public Water Systems.
Primary Contaminants - Any contaminant for which a maximum contaminant level has been established
for protection of public health.
Secondary Contaminants - Any contaminant for which a maximum contaminant level has been
established for reasons other than protection of public health (i.e., aesthetic purposes such as taste, odor
and staining of fixtures).
Surface Water Treatment Rule - A regulation that requires that all surface water be treated in accordance
with 10 NYCRR Part 5, Subpart 5-1, Section 5-1.30, Public Water Systems.
UOC - Unspecified Organic Contaminant. Any organic chemical compound not otherwise specified in 10
NYCRR Part 5, Subpart 5-1, Public Water Systems.
I-8
ATTACHMENT II
ANTICIPATED INTENDED USE PLAN
SCHEDULE FOR THE
October 1, 2011 - SEPTEMBER 30, 2012
FUNDING PERIOD
Anticipated Intended Use Plan Schedule for the
October 1, 2011 to September 30, 2012 Funding Period
October 1, 2011
Start of the financing period
December 1, 2011
Cut-off date for receipt of complete
Hardship Applications by applicants seeking
grants
December 1, 2011
Cut-off date for receipt of complete
applications for non-hardship projects that
have been on the Project Readiness List,
above the subsidized Funding Line for two
or more consecutive IUP periods
March 1, 2012
Cut-off date for receipt of complete
applications for subsidized financings from
this IUP
May 13, 2012
Cut-off date for receipt of complete
applications for unsubsidized financings
from this IUP
To be determined
Leveraged financing
September 30, 2012
End of financing period.
To be determined
Principal Payment Dates for Leveraged
Financing Projects. (Note: Principal and
Interest payments will be required in 2012
on new leveraged financings, and recipients
should contact EFC to discuss payment
schedules and redemption dates on BANs to
be refinanced with the DWSRF.)
II-1
ATTACHMENT III
FINANCING FEES
AND
FINANCING OPTIONS
Financing Fees
Issuance Costs
Fees associated with processing a DWSRF financing are based on the amount financed (i.e., project
costs). Issuance costs are calculated as follows:
Program Administration: This cost is calculated by multiplying the project costs by 1.1%. This fee is
used to support the administration of the DWSRF program. For non-hardship projects that receive shortterm financing, an administrative fee equal to 0.6% will be charged.
Direct Expenses: The direct expense is calculated by multiplying the project costs by 1.0%. Direct
Expenses represent the recipient’s proportionate share of EFC’s costs to complete the transactions
necessary for a bond sale and include bond counsel costs, financial advisor fees, printing costs, rating
agency fees and trustee fees.
State Bond Issuance Charge: Public authorities that sell bonds, including EFC, must collect the State
Bond Issuance Charge. The State Bond Issuance Charge applies only to leveraged financings. The
Division of Budget approved an extension to the State Bond Issuance Charge waiver through March 31,
2011. The rate for leveraged financings through March 31, 2011 is determined as follows:
Financed Amount
Rate
$1,000,000 or less
$1,000,001 - $5,000,000
$5,000,001 - $10,000,000
$10,000,001 - $20,000,000
More than $20,000,000
0.168%
0.336%
0.504%
0.672%
0.840%
Maintenance Charge
An annual fee is charged to defray the cost of maintaining financing accounts during the life of the
financing. This fee is calculated as 0.11 percent of the outstanding financing balance.
Exceptions to the above fees apply to certain financings. EFC will work with the applicant to determine
the appropriate DWSRF financing type. Fees apply to the different types of DWSRF financing as
follows:
Long-Term Leveraged Financing
•
•
•
•
Program administration fee
Direct expenses
State bond issuance charge
Maintenance charge
Long-Term Direct Financing
•
•
•
Program administration fee
Direct expenses
Maintenance charge
III-1
Reduced Interest Rate Direct Financing
•
All fees waived
Short-Term Interest Free Financing
•
Program administration fee for non-hardship projects
Short-Term Market Rate Financing
•
All fees waived
SRF Bond Market Rate Program
•
•
•
Direct expenses
State bond issuance charge
Maintenance charge applies only if, and after, subsidy assistance becomes available
SRF Bond Guarantee Program
•
Direct expenses
Disbursement Requests
Once a financing has closed, the project funds not disbursed at closing will be available on a weekly
basis provided an acceptable disbursement request, supported with proper cost documentation, has been
submitted to EFC. Disbursement request forms will be included in the PFA that the recipient will
execute to obtain financing. The recipient should make certain proper financial coverage is in place in
the event that a disbursement is delayed, denied or adjusted.
Disbursement request forms can be submitted via:
1.
Mail to: NYS Environmental Facilities Corporation, 625 Broadway, Albany, NY 12207-2997
2.
Fax to: (518) 402-7085
3.
E-mail to: [email protected]. Note: This e-mail address should only be used for
the initial submission of each request and related documentation for the initial request. Follow-up
documentation or information should be sent directly to the assigned EFC analyst.
Further information about the disbursement request process is available in the “Disbursement Request
Information Sheet” which is one of the reference and guidance documents in the financing application
package.
III-2
Financing Options
The DWSRF provides short-term and long-term funding for eligible projects. In addition to the
traditional DWSRF interest subsidy for projects, the EFC has developed a second set of financing
options for projects that are either:
a) not reachable on the current Project Readiness List in the DWSRF IUP, or
b) need financing for eligible project costs above the subsidized amount available on the Project
Readiness List.
Please keep the following in mind:
•
•
•
All projects should be listed on the IUP Project Readiness List.
No financings may be for a term in excess of the useful life of the project.
The by-pass process may impact the availability of financing (see IUP for further information).
A project below the subsidized funding line but ready for financing may be financed with the
long-term market-rate or short-term market-rate options, which then may be automatically
converted to interest-subsidized financing if a project becomes reachable following the by-pass
process.
In addition to the Financing Options in the attached matrix, for projects that demonstrate a need for
hardship financing (see the IUP), the DWSRF provides for reduced interest rate financings (as low as
interest-free) and, for qualified projects, grants, to the extent that funds are available. In addition, the
SRF Bond Guarantee Program may be used to provide preferred AAA/Aaa rates for recipients issuing
bonds independently to finance SRF projects.
Short-term financing with either the short-term market-rate or the short-term interest-free program is
intended to provide a seamless transition for project financing (minimizing or eliminating the need for
other funding sources).
III-3
DWSRF Financing Options Matrix
Timing
Long-Term
Option
1. Bond Market Rate
SRF
Project Score
Below the subsidized
Funding Line
Short-Term
2. Subsidized3. Extended Term
Interest
Above the subsidized Funding Line
Benefit
AAA/Aaa Borrowing Rates
Plus 1/3rd interest rate subsidy for 20 years from project
completion
AAA/Aaa Borrowing
Rates
4 Market-Rate
5 Interest-Free
Below the subsidized
Funding Line or for project
costs above the amount
available interest-free
Above the
subsidized
Funding Line
AAA/Aaa Borrowing Rates,
0% Interest
Based on SRF borrowing
costs in the high-grade taxexempt short-term
municipal markets
None
No Interest
Expense
principal amortization may be
extended from 20 up to 30 years
(years 21-30 at unsubsidized Market
Rate)
Economies of scale in pooled bond issue
Interest Rate
Subsidy
Timing
Fees
(as a % of
SRF-Financed
project costs
unless
otherwise
noted)
Availability
Project Status
Not Available Initially,
becomes available in the
year the project score is
above a future funding line
Available from
Closing
Available from Closing
a. 1.0% Direct Expenses
b. Sliding Scale State Bond Issuance Charge
c. Maintenance charge on
outstanding balance (0.25%
if interest-subsidy is
provided)
0.6% Program
Admin Fee
c. 0.11% Maintenance charge on outstanding balance
d. 1.1% Program Admin
Ongoing, may be financed pursuant to a pool schedule.
Repayment term up to 30
Repayment term up to 20
Repayment term up to 30
years from project
years from project
years from project
completion
completion
completion
Final costs known; Project approvals in place.
Plans and Specifications, major contracts awarded, permits in place.
III-4
Available for up to 3 years or readiness for longterm financing, whichever is sooner, for a
recommended minimum term of six months.
Approved Engineering Report, environmental
review completed and other approvals as
necessary for short-term financing. Once final
costs are known, the project will be considered for
long-term financing.
ATTACHMENT IV
DRINKING WATER STATE REVOLVING FUND
PRE-APPLICATION FORM
Drinking Water State Revolving Fund (DWSRF) Pre-Application Form
Preliminary Project Schedule And Cost Estimate
For Intended Use Plan (IUP) Listing Purposes
(Instructions on Back)
DOH Use Only
Date Prepared: ___/___/___
PROJECT INFORMATION
Name of Water System: _________________________________________________________________________
Municipality: _________________________________________________________________________________
County: _____________________________________________________________________________________
Legislative Districts - Congressional:_________ NYS Senate:___________ NYS Assembly: __________________
Project Description/Location:____________________________________________________________________
____________________________________________________________________________________________
Population Served by Water System:_______________________________________________________________
Population Served by Project: ____________________________________________________________________
Has this project been listed in a DWSRF Intended Use Plan (IUP)? Yes or No. If yes, please indicate the DWSRF project
tracking number: ______________________________________________________
Are there other funding sources anticipated for the project: Yes or No. If yes, please attach a separate sheet of paper and
include source of funding, amount of funding, type of funding, and letter of confirmation.
CONTACT INFORMATION
Name of Borrower: __________________________________Consulting Engineer: __________________________
Contact Person, Title: ________________________________Contact Person, Title: _________________________
Address: __________________________________________ Address: ____________________________________
Phone #: __________________________________________ Phone #:________________________
Fax#: _____________________________________________ Fax #: ______________________________________
E-Mail Address: ____________________________________ E-Mail Address: ______________________________
If applicable, on a separate sheet of paper provide contact information for additional parties who should be included on
project mailing list, including system owner (if different than borrower) and person responsible for completing subsequent
application package.
PROJECT SCHEDULE
1. Submit Engineering Report.
PWS I.D. No._______________
Project Tracking No. _________
Date Received: ____/_____/___
Project Cost Estimate
Construction Costs
$_________________
Engineering Fees
$_________________
Other Expenses
$________________
Equipment Costs
$_________________
Land Acquisition
$_________________
Contingencies (___% used) $_________________
Subtotal Project Costs
$_________________
Deduct other funding
sources (HUD, RD, etc.)
$_________________
Add Est. Issuance Costs
$_________________
(Estimated issuance costs are
approximately 3% of project costs)
Total Amount to Finance
$_________________
DATES
(T)TARGET OR(A)ACTUAL
( ) __________
(Date)
2.When will all Technical Submittals be completed?
( ) __________
2. Start of construction date (date Notice to Proceed was issued)?
( )__________
(Date)
(Date)
3. Is this project being submitted for Refinancing? Yes or No (circle correct response)
(Date)__________
If yes, Construction Completion Date (actual date)?
Please return completed form to:
New York State Department of Health
Bureau of Water Supply Protection
547 River Street,Flanigan Square, Room 400
Troy, New York 12180
Phone: (518) 402-7650
Fax:
(518) 402-7659
INSTRUCTIONS
PRE-APPLICATION FORM, DWSRF PROJECT SCHEDULE AND COST ESTIMATE
This form is used to gather preliminary schedule and cost information about your project. It will help us to determine
project eligibility and a target date for providing your DWSRF loan. New York State Department of Health (DOH) staff
may call you to verify this information and to develop a more detailed schedule for completion of all activities needed
for a complete loan application. You should confer with your engineer and financial advisor regarding the schedule and
cost estimate. If you have questions regarding the pre-application form, please call DOH at 1-800-458-1158 (within
NYS State) or (518) 402-7650 for assistance.
PROJECT INFORMATION
This section of the form should include the Name of the Water System, Name of the Municipality serviced by the
water system, and the County and Legislative Districts in which the project is located. A Project Description and the
Location of the project should also be included (e.g., Construct new water treatment plant at 69 Mill Road in Village of
Waterburgh). The applicant should provide information regarding the Population Served by the Water System and
the Population Served by the Project.
Has the project been listed in a previous DWSRF Intended Use Plan (IUP)? If a pre-application has previously been
submitted it is not necessary to complete an additional application form. If project information, contact information,
actual or targeted activity dates, or project cost estimates previously submitted have changed, the applicant may wish to
submit a revised pre-application form. If so, please include the DWSRF project tracking number.
Indicate if other funding sources (i.e., Rural Development, Housing and Urban Development, etc.) are available for the
project. If other sources of funding are available please attach a separate sheet of paper and include the funding source,
funding amount, type of funding (i.e., grant, low interest loan), and date the funding was granted (letter of confirmation).
CONTACT INFORMATION
DOH will be using the contact information provided on the pre-application form to identify the borrower, the consulting
engineer, and other key project contacts (if applicable). Individuals listed on this portion of the pre-application form
may be contacted directly by DOH staff to answer technical questions.
PROJECT COST ESTIMATE
The accuracy of project costs will vary depending on the stage of project development. Please use the best available
estimate when completing the form. Cost estimates should be provided for Construction Costs, Engineering Fees
(planning fees, design fees, and construction fees), Other Expenses (legal expenses, bond counsel costs, force account
costs, fiscal expenses, interest during construction, and miscellaneous expenses), Equipment Costs, Land Acquisition
Costs, and Contingencies. Financial assistance anticipated from other Funding Sources (Rural Utilities, Housing
and Urban Development, etc.) should be subtracted from the Subtotal Project Costs of the above listed cost estimates.
The Estimated Issuance Cost (approximately 3% of project costs) should be added to the subtotal to determine Total
Amount to Finance. If certain cost elements are unknown and cannot be reasonably estimated, please indicate on the
form. Estimates for all expenses will eventually be needed so that sufficient monies for the project are included in the
IUP.
PROJECT SCHEDULE
1. Provide the date (targeted or actual) when an approvable Engineering Report and all Technical Submittals will be
completed. Required Technical Submittals include environmental review documents and findings, final plans and
specifications, engineer’s certification of technical requirements, certification of title to project sites, Minority &
Women’s Business Enterprise - Equal Opportunity (M/WBE-EEO) program documents. Additionally, the borrower
should contact DOH and other responsible permitting agencies (e.g., New York State Department of Environmental
Conservation) for anticipated review and issuance times. Please contact EFC for applicable loan application
deadlines and anticipated loan closing dates.
2. Provide the date (targeted or actual) of Start of Construction (i.e., date Notice to Proceed was issued). Although the
construction schedule may be very tentative when you complete the pre-application, it is important to set target dates
as they indicate when DWSRF financing will be needed.
3. Indicate if the project is being submitted for Refinancing. If the project is being refinanced, include the actual date
of Construction Completion.
ATTACHMENT V
DRINKING WATER STATE REVOLVING FUND
APPLICATION CHECKLIST
The application checklist includes a list of all application items that may apply to a
DWSRF project. The checklist includes boxes to indicate which items have been
submitted to DOH and EFC. There are two (2) application checklists: one for publicly
owned projects, which follows, and one for privately owned projects. The checklists are
also available on the EFC web site at www.nysefc.org (click on "Programs", then
"Drinking Water State Revolving Fund", then "Application Process") or by calling EFC at
1-800-882-9721.
New York State Environmental Facilities Corporation
625 Broadway Albany, New York 12207-2997
(800) 882-9721 within New York State
(518) 402-6971 Fax (518) 402-6972
APPLICATION CHECKLIST – PUBLICLY-OWNED SYSTEMS
NEW YORK DRINKING WATER STATE REVOLVING FUND
This document lists items that relate to applying for financing through the Drinking Water
State Revolving Fund (DWSRF). The type of financing and the status of the project to be
financed will determine which items will be required to be submitted as part of a DWSRF
financing application. Since all items may not be required to apply for financing, it is
important that an Environmental Facilities Corporation (EFC) representative
confirm with you which items do apply. If someone has not reviewed this
Checklist with you, please contact EFC at (800) 882-9721 or (518) 402-7085. This
will save you time and effort.
Part I details the minimum requirements to obtain a DWSRF short-term financing
commitment. Part II details the requirements that may be necessary to release
DWSRF short-term funds or obtain a DWSRF long-term financing commitment.
Items in Part II of this Checklist may be submitted to EFC if they are available when
submitting Part I items. Please keep a copy of the completed form for your
reference.
An explanation of each of these items is provided in the “Description of Application
Components”, found in the paper version of the application package and on EFC’s
website at www.nysefc.org (Click on “Programs”, then “Drinking Water State Revolving
Fund”, then “Application Process”). DWSRF application Forms and Guidance are also
available on EFC’s website.
Please Note: The following important steps should have been accomplished. If
not, please contact EFC before proceeding to work on the financing application.
1. Your project is listed on the Project Readiness List, as published in the
current DWSRF Intended Use Plan (IUP).
An engineering report or
construction plans and specifications for your project should have
previously been submitted to the Department of Health (DOH) for your
project to be listed on the Readiness List.
2. DOH has approved your engineering report or construction plans and
specifications, or the report is under review by DOH.
3. The potential adverse environmental and historic preservation impacts of
the project have been assessed in the manner prescribed by the DWSRF.
4. A water district has been established or expanded, or the maximum amount
to be expended for such district increased, and Office of the State
Comptroller (OSC) approval obtained, as needed (this is only applicable to
towns and counties).
5. A bond resolution has been adopted establishing the legal authority to
issue debt for the project.
Applicant Name:
DWSRF Project No.:
Date Prepared:
APPLICATION CHECKLIST – PUBLICLY-OWNED SYSTEMS
Please call EFC to review the Checklist at the beginning of the application process.
DOH/EFC Project Team Members
DOH Engineering:
EFC Finance:
EFC Legal:
EFC MWBE:
(Team member names will be provided after your application is submitted.)
PART I – Items Necessary Prior to Short-Term Financing Commitment
Please submit items in Part I in order to close a DWSRF Short-Term financing.
Items in Part II can be submitted with Part I items if they are currently available.
Check the appropriate boxes below.
Submitted Earlier
No.
Checklist Item
1.
Application Form 1
2.
Municipal Bond Resolution(s)
a) Bond Resolution (Certified Copy)
b) Proof of Publication of Permissive Referendum (if applicable)
c) Proof of Publication of Estoppell Notice
3.
Environmental Review Documents and Findings 2
(see SEQR/SERP guidance in the “Environmental Review
Requirements” )
OPRHP / SHPO Project Review Letter 2
(Initial or Final Letter)
4.
Engineering Services Contract
a) Executed Contract (for eligibility review)
b) MWBE Utilization Plan or Good Faith Effort Documentation
for Contract (for MWBE approval)
5.
Financial Information
(Only for Applicants other than counties, cities, towns and
villages)
Financial statements (audited if available) for the three (3) most
recent fiscal years.
Submitted with
this Application
No.
Checklist Item
6.
Intermunicipal Agreements
(draft or final agreements critical to the project)
7.
Co-funding Documentation
a)
Awarded Grants
b)
Closed Third Party Loans
c) Co-funding Cost Documentation
Submitted
Earlier
Submitted
with this
Application
Not
Applicable
Please call EFC to review the Checklist at the beginning of the application process
since all items listed below in Part II may not apply to your specific project.
PART II – Items That May Be Necessary Prior to Funds Disbursement or for
Long-Term Financing
Some of the items in Part II will be needed by EFC after closing a short-term financing to
allow release of DWSRF funds and later to roll your project into DWSRF long-term
financing. The type of financing and the project’s schedule and status at the time of
application will determine which of the following items are required for release of
disbursements and as part of a complete application for DWSRF long-term financing.
The disbursement of funds will be contingent upon satisfactory completion of the
following items, as deemed applicable by EFC. Timely availability of DWSRF funds will
be dependent, in part, upon the accuracy and completeness of these submissions, within
a reasonable time frame for EFC to review and comment or request clarification, as
necessary. For this reason, applicants are strongly encouraged to develop and submit
these materials as soon as practicable, to avoid delayed release of disbursement
requests.
Please call EFC to discuss which of the following items apply.
Check the appropriate boxes below.
Submitted Earlier
No.
1.
Checklist Item
Completed Application Checklist 1
2.
Supplemental Municipal Bond Resolution (if needed)
a) Supplemental Bond Resolution (Certified Copy)
b) Proof of Publication of Permissive Referendum
(if applicable)
c) Proof of Publication of Estoppel Notice
3.
Financial Information
Current Adopted Capital and Operating Budgets
4.
OPRHP / SHPO Final Project Review Letter 2
Submitted with this
Application
No.
Checklist Item
5.
Capacity Development Form1
(for small community water systems serving a population
of 3,300 or less)
6.
Consolidation Plan, Agreements and Approval
7.
Construction Plans and Specifications
8.
Agreements for Professional Services
a) Engineering Planning Services
b) Engineering Design Services
c) Engineering Construction Services
d) Local Counsel
e) Bond Counsel
f)
Financial
g) Other (please specify)
9.
Certification as to Title to Project Site1
10.
Lease Agreement to Project Site
11.
Municipal Service Agreements
a) Intermunicipal Agreements (final agreements)
b) Private Operating Agreements
c) Private Use Agreements
12.
Work Force Documentation 1
a) Technical Certification & Proposal
b) Administrative Proposal
13.
Executed Construction Contracts
Contract Change Orders
14.
MWBE Utilization Plan or Good Faith Effort Documentation
(for executed construction contracts)
15.
Notice to Proceed
16.
For Reimbursement of Interfund Borrowings:
a) Interfund Borrowing Resolution (Copy)
b) Cost Documentation (Interfund Borrowings)
17.
For refinancing of existing debt, please attach the following
supporting documents as applicable:
a) Municipal Resolution Authorizing Debt (Original)
b) Bond Anticipation Note (BAN)
c) Opinion of Bond Counsel
d) Official Statement
e) Refunding Resolution (Copy)
f)
Proof of Publication of Estoppel Notice for Resolution
g) Cost Documentation (Refinancing)
h) Statement Specifying Net Interest Earned or Anticipated
Submitted
Earlier
Submitted
with this
Application
Questions regarding engineering and technical items should be addressed to DOH at
(800) 458-1158 ext. 27650 or (518) 402-7650.
1
2
Form included in Application Package.
Guidance included in Application Package.
Not
Applicable
ATTACHMENT VI
OUTPUT AND OUTCOME MEASURES
Environmental Results Grant Requirements
As required by EPA Order 5700.7, Environmental Results under EPA Assistance Agreements,
New York will provide the following output and outcome measures in its DWSRF
Biennial/Annual Reports and IUP:
NATIONAL REPORTABLE OUTPUTS/OUTCOMES FOR DWSRF
1. The annual percentage of assistance agreements to bring entities into compliance.
2. Fund utilization rate [cumulative financing agreement dollars to the cumulative funds
available for projects] for the DWSRF.
3. Return on Federal Investment [cumulative dollar amount of assistance disbursements to
projects divided by cumulative federal outlays for projects].
4. The cumulative number of project completions.
ANTICIPATED OUTPUTS FOR DWSRF
1.
2.
3.
4.
5.
6.
Number of binding commitments (50).
Number of financing agreements (50).
Number of assistance agreements for system compliance (40).
Number, dollar amounts, and/or population served of projects financed (50/$150M).
Our fund utilization rate remaining higher than the national average.
Our rate at which projects progressed as measured by disbursements as a percent of assistance
provided remaining at or higher than the national average.
ANTICIPATED OUTCOMES (SHORT-TERM/LONG-TERM) FOR DWSRF
1. Number of projects initiating operation resulting in improved compliance (25).
2. Improved compliance for systems receiving DWSRF assistance.
ANTICIPATED OUTPUTS FOR SET-ASIDES
1. Small System Technical Assistance
• Number of systems receiving training (600).
• Number of systems receiving on-site technical assistance (100).
2. State Program Management
• Data management system maintained.
• State required updates to primacy made.
3. Source Water Protection Program
• Number of source water strategies in place and implemented (15).
4. Capacity Development Program
• Implement statewide strategy.
ANTICIPATED OUTCOMES (SHORT-TERM/LONG-TERM) FOR SET-ASIDES
1.
2.
3.
4.
Improved compliance for systems receiving Technical Assistance.
Attainment of primacy for new rules.
Improved data quality.
Improvement to capacity development baseline.
VI-1
ATTACHMENT VII
RESPONSE TO COMMENTS
There were no public comments made during the comment period
for the Draft Intended Use Plan. VII‐1 APPENDIX-1
Summary of Project List Changes
I. Project Readiness List
I. A. Project Readiness List Additions
System Name/
Borrower
Project
County
18061
Franklin
TUPPER LAKE V / Tupper
Lake (V)
Description
New wells to replace SW source and inadequate DE plant., New Ground Water
Source, Upgrade Distribution System
18072
Putnam
GIPSY TRAIL CLUB / Gipsy
Trail Club Inc
Develop additional well source capacity, New Ground Water Source, New Pump
Station
18053
Schoharie
COBLESKILL / Cobleskill (T)
18067
Otsego
17949
Project Cost Score Comments
$2,979,790
235
New project with engineering report received after draft IUP printing.
$430,540
150
New Project with engineering report received after draft IUP printing.
Howe Caverns/Route 7 Service Area Extension, Extend Distribution System
$4,899,004
105
New project with engineering report received after draft IUP printing.
GILBERTSVILLE VILLAGE /
Gilbertsville (V)
New Ground Water Source, New Storage, Upgrade Distribution System
$3,865,000
100
New project with engineering report received after draft IUP printing.
Dutchess
HIGH MEADOWS PARK INC /
High Meadows Co-op Corp
New Ground Water Source, Upgrade Storage
$44,577
75
Engineering report received, project now ready. Revised score from 15 to 75 points
based on new information.
17575
Fulton
NORTHAMPTON (T) WATER
DISTRICT / Northampton (T)
Upgrade Storage, Upgrade Distribution System
$6,303,627
65
Engineering report recevied, project now ready. Previously on multiyear list only. Revised
score from 40 points to 65 points based on new information. Revised cost based on new
information.
18064
Oneida
FORESTPORT WATER
DISTRICT / Foresport (T)
New Ground Water Source
$390,000
55
New project with engineering report received after draft IUP printing.
18071
Cattaraugus
RANDOLPH VILLAGE /
Randolph (T)
East Randolph and Randolph (V)'s Repalcement of Water Mains, Upgrade
Distribution System
$7,075,000
55
New Project with engineering report received after draft IUP printing.
18069
Madison
HAMILTON VILLAGE /
Hamilton (V)
New Ground Water Source, Upgrade Distribution System
$4,100,000
50
New project with engineering report received after draft IUP printing.
18062
Oswego
CLEVELAND VILLAGE /
Cleveland (V)
Upgrade Ground Water Source, Upgrade Storage, Upgrade Distribution System
$1,576,930
50
New project with engineering report received after draft IUP printing.
18070
Wayne
TRANSMISSION MAIN
REPLACEMENT / Clyde(V)
Upgrade Transmission
$357,900
40
New pre-application and engineering report received after draft IUP printing.
18068
Orleans
WATER IMPROVEMENT
BENEFIT AREA #10 /
Clarendon (T)
Extend Distribution System
$1,634,949
5
New pre-application received after draft IUP printing.
Total Cost
Total # Projects
12
$33,657,317
Page 1 of 1
I. Project Readiness List
I. B. Project Readiness List Deletions
Project County
System Name/
Borrower
Description
Project Cost Score Comments
16744
Delaware
FLEISCHMANNS VILLAGE /
Fleischmanns (V)
Surface Water Treatment Rule Compliance Facility, New Ground Water Source, New
Storage, Upgrade Distribution System
$2,000,424
1,205
Project closed on long term financing during the prior funding cycle after the printing of the
Draft IUP.
16635
Lewis
COPENHAGEN VILLAGE /
Copenhagen (V)
New Ground Water Source, Upgrade Distribution System
$1,125,670
1,170
Project closed on long term financing during the prior funding cycle after the printing of the
Draft IUP.
15640
Ulster
NEW PALTZ (VILLAGE)
WATER DIST / New Paltz (V)
Upgrade Distribution System
$300,000
40
Project withdrawn per request of applicant.
15638
Ulster
NEW PALTZ (VILLAGE)
WATER DIST / New Paltz (V)
Upgrade Pump Station
$130,000
35
Project withdrawn per request of applicant.
Total # Projects
Total Cost
4
$3,556,094
Page 1 of 1
I. Project Readiness List
I. C. Project Readiness List Modifications
Project County
System Name/
Borrower
Description
17800
Orange
KIRYAS JOEL VILLAGE /
Kiryas Joel (V)
Water Treatment Plant Well #28 and mitigation of offsite well impacts. Phase 2 of
16752, New Water Treatment Plant
17983
NY City
NEW YORK CITY - CROTON
SYSTEM / NYCMWFA
Croton filtration plant(Phase 8 of 16479), New Surface Water Treatment Rule
Compliance Facility
17163
Essex
TICONDEROGA WD /
Ticonderoga (T)
17611
Franklin
16278
Project Cost Score Comments
$900,000
2,130
Revised project cost based on new information.
$217,962,340
2,115
Revised cost based on new infoormation.
New Surface Water Treatment Rule Compliance Facility, New Storage, Upgrade
Distribution System
$13,954,315
265
Revised cost based on new information. Revised score from 90 to 265 based on new
information.
SARANAC LAKE V / Saranac
Lake (V)
New SCADA equipment., New Surface Water Treatment Rule Compliance Facility,
Upgrade Distribution System
$12,500,000
245
Removed Short Term loan closed information, removed 1000 Short Term Points & project
cost adjusted. This project was expected to close short term during the previous funding
cycle and did not.
Hamilton
LONG LAKE (T) / Long Lake
(T)
New Ground Water Source, New Storage, Upgrade Distribution System
$3,929,255
200
Removed Short Term loan closed information, removed 1000 Short Term Points & project
cost adjusted. This project was expected to close short term during the previous funding
cycle and did not.
18013
Cattaraugus
RANDOLPH VILLAGE /
Randolph (T)
East Randolph and Randolph (V)'s project includes meters, Upgrade Other
Expenses, New Surface Water Treatment Rule Compliance Facility, New Ground
Water Source, New System Consolidation, Upgrade Other (OT)
$3,740,000
200
Revised project score from 95 points to 200 points based on ne information. Revised
Borrower, Scope and cost of project.
16114
Cayuga
CAYUGA VILLAGE / Cayuga
(V)
New Surface Water Treatment Rule Compliance Facility, Upgrade Distribution
System, New Inter-Connection
$6,875,100
185
Revised cost based on new information.Revised project description.
17529
Jefferson
TIBBETS POINT WATER
DISTRICT / Cape Vincent (T)
Serve area with private contaminated wells, New Surface Water Treatment Rule
Compliance Facility, New System Consolidation, New Water District
$2,645,000
180
Removed "H" (hardship designation) as project did not qualify and final determination was
made after the printing of the draft IUP.
17562
Jefferson
HERRINGS VILLAGE /
Herrings (V)
Distribution and storage improvements., Upgrade Storage, Upgrade Distribution
System
$3,429,000
170
Revised score from 105 to 170 based on new information.
16741
Dutchess
PAWLING VILLAGE / Pawling
(V)
New Surface Water Treatment Rule Compliance Facility, New Ground Water Source
$1,270,000
155
Revised score from 135 to 155 based on new information.
17645
Washington
GREENWICH VILLAGE /
Greenwich (V)
New Surface Water Treatment Rule Compliance Facility, New Storage
$1,100,000
140
Revised cost and project description based on new information.
17626
Ulster
NEW PALTZ (VILLAGE)
WATER DIST / New Paltz (V)
Upgrade Water Treatment Plant, New Storage, Upgrade Distribution System
$5,675,916
70
Revised score from 65 points to 70 points based on new information.
Page 1 of 2
I. Project Readiness List
I. C. Project Readiness List Modifications
Project County
18030
Rensselaer
System Name/
Borrower
RENSSELAER CITY PWS /
Rensselaer (C)
Total # Projects
Description
Washington Ave Corridor Improvements, Upgrade Distribution System
Project Cost Score Comments
$3,169,952
Total Cost
13
$277,150,878
Page 2 of 2
35
Revised score from 30 to 35 points based on new information.
II. Project Multi-Year List
II. A. Project Mult-Year List Additions
Project County
System Name/
Borrower
Description
18061
Franklin
TUPPER LAKE V / Tupper
Lake (V)
New wells to replace SW source and inadequate DE plant., New Ground Water
Source, Upgrade Distribution System
18072
Putnam
GIPSY TRAIL CLUB / Gipsy
Trail Club Inc
Develop additional well source capacity, New Ground Water Source, New Pump
Station
18053
Schoharie
COBLESKILL / Cobleskill (T)
18067
Otsego
18064
Project Cost Score Comments
$2,979,790
235
New project with engineering report received after draft IUP printing.
$430,540
150
New Project with engineering report received after draft IUP printing.
Howe Caverns/Route 7 Service Area Extension, Extend Distribution System
$4,899,004
105
New project with engineering report received after draft IUP printing.
GILBERTSVILLE VILLAGE /
Gilbertsville (V)
New Ground Water Source, New Storage, Upgrade Distribution System
$3,865,000
100
New project with engineering report received after draft IUP printing.
Oneida
FORESTPORT WATER
DISTRICT / Foresport (T)
New Ground Water Source
$390,000
55
New project with engineering report received after draft IUP printing.
18071
Cattaraugus
RANDOLPH VILLAGE /
Randolph (T)
East Randolph and Randolph (V)'s Repalcement of Water Mains, Upgrade
Distribution System
$7,075,000
55
New Project with engineering report received after draft IUP printing.
18069
Madison
HAMILTON VILLAGE /
Hamilton (V)
New Ground Water Source, Upgrade Distribution System
$4,100,000
50
New project with engineering report received after draft IUP printing.
18062
Oswego
CLEVELAND VILLAGE /
Cleveland (V)
Upgrade Ground Water Source, Upgrade Storage, Upgrade Distribution System
$1,576,930
50
New project with engineering report received after draft IUP printing.
18070
Wayne
TRANSMISSION MAIN
REPLACEMENT / Clyde(V)
Upgrade Transmission
$357,900
40
New pre-application and engineering report received after draft IUP printing.
18063
Wyoming
WATER SYSTEM
UPGRADES /
Upgrade Distribution System
$775,000
10
New pre-application received after draft IUP printing.
18068
Orleans
WATER IMPROVEMENT
BENEFIT AREA #10 /
Clarendon (T)
Extend Distribution System
$1,634,949
5
New pre-application received after draft IUP printing.
Total # Projects
Total Cost
11
$28,084,113
Page 1 of 1
II. Project Multi-Year List
II. B. Project Mult-Year List Deletions
Project County
System Name/
Borrower
Description
16744
Delaware
FLEISCHMANNS VILLAGE /
Fleischmanns (V)
Surface Water Treatment Rule Compliance Facility, New Ground Water Source, New
Storage, Upgrade Distribution System
16635
Lewis
COPENHAGEN VILLAGE /
Copenhagen (V)
15640
Ulster
15638
Ulster
Project Cost Score Comments
$1,770,287
1,205
Project closed on long term financing during the prior funding cycle after the printing of the
Draft IUP.
New Ground Water Source, Upgrade Distribution System
$996,168
1,170
Project closed on long term financing during the prior funding cycle after the printing of the
Draft IUP.
NEW PALTZ (VILLAGE)
WATER DIST / New Paltz (V)
Upgrade Distribution System
$300,000
40
Project withdrawn per request of applicant.
NEW PALTZ (VILLAGE)
WATER DIST / New Paltz (V)
Upgrade Pump Station
$130,000
35
Project withdrawn per request of applicant.
Total # Projects
Total Cost
4
$3,556,094
Page 1 of 1
II. Project Multi-Year List
II. C. Project Mult-Year List Modifications
Project County
System Name/
Borrower
Description
17800
Orange
KIRYAS JOEL VILLAGE /
Kiryas Joel (V)
Water Treatment Plant Well #28 and mitigation of offsite well impacts. Phase 2 of
16752, New Water Treatment Plant
17983
NY City
NEW YORK CITY - CROTON
SYSTEM / NYCMWFA
Croton filtration plant(Phase 8 of 16479), New Surface Water Treatment Rule
Compliance Facility
17163
Essex
TICONDEROGA WD /
Ticonderoga (T)
17611
Franklin
SARANAC LAKE V / Saranac
Lake (V)
16278
Hamilton
LONG LAKE (T) / Long Lake (T) New Ground Water Source, New Storage, Upgrade Distribution System
18013
Cattaraugus
RANDOLPH VILLAGE /
Randolph (T)
16114
Cayuga
17529
Project Cost Score Comments
$900,000
2,130
Revised project cost based on new information.
$217,962,340
2,115
Revised cost based on new infoormation.
New Surface Water Treatment Rule Compliance Facility, New Storage, Upgrade
Distribution System
$13,954,315
265
Revised cost based on new information. Revised score from 90 to 265 based on new
information.
New SCADA equipment., New Surface Water Treatment Rule Compliance Facility,
Upgrade Distribution System
$12,500,000
245
Removed Short Term loan closed information, removed 1000 Short Term Points & project
cost adjusted. This project was expected to close short term during the previous funding
cycle and did not.
$3,929,255
200
Removed Short Term loan closed information, removed 1000 Short Term Points & project
cost adjusted. This project was expected to close short term during the previous funding
cycle and did not.
East Randolph and Randolph (V)'s project includes meters, Upgrade Other Expenses,
New Surface Water Treatment Rule Compliance Facility, New Ground Water Source,
New System Consolidation, Upgrade Other (OT)
$3,740,000
200
Revised project score from 95 points to 200 points based on ne information. Revised
Borrower, Scope and cost of project.
CAYUGA VILLAGE / Cayuga
(V)
New Surface Water Treatment Rule Compliance Facility, Upgrade Distribution System,
New Inter-Connection
$6,875,100
185
Revised cost based on new information.Revised project description.
Jefferson
TIBBETS POINT WATER
DISTRICT / Cape Vincent (T)
Serve area with private contaminated wells, New Surface Water Treatment Rule
Compliance Facility, New System Consolidation, New Water District
$2,645,000
180
Removed "H" (hardship designation) as project did not qualify and final determination was
made after the printing of the draft IUP.
17562
Jefferson
HERRINGS VILLAGE / Herrings Distribution and storage improvements., Upgrade Storage, Upgrade Distribution
System
(V)
$3,429,000
170
Revised score from 105 to 170 based on new information.
16741
Dutchess
PAWLING VILLAGE / Pawling
(V)
New Surface Water Treatment Rule Compliance Facility, New Ground Water Source
$1,270,000
155
Revised score from 135 to 155 based on new information.
17645
Washington
GREENWICH VILLAGE /
Greenwich (V)
New Surface Water Treatment Rule Compliance Facility, New Storage
$1,100,000
140
Revised cost and project description based on new information.
17949
Dutchess
HIGH MEADOWS PARK INC /
High Meadows Co-op Corp
New Ground Water Source, Upgrade Storage
$44,577
75
Engineering report received, project now ready. Revised score from 15 to 75 points
based on new information.
17626
Ulster
NEW PALTZ (VILLAGE)
WATER DIST / New Paltz (V)
Upgrade Water Treatment Plant, New Storage, Upgrade Distribution System
$5,675,916
70
Revised score from 65 points to 70 points based on new information.
Page 1 of 2
II. Project Multi-Year List
II. C. Project Mult-Year List Modifications
Project County
18030
Rensselaer
System Name/
Borrower
RENSSELAER CITY PWS /
Rensselaer (C)
Total # Projects
14
Page 2 of 2
Description
Washington Ave Corridor Improvements, Upgrade Distribution System
Project Cost Score Comments
$3,169,952
35
Revised score from 30 to 35 points based on new information.