[CH10] Monitoring dan kontrol 1. Based on the following table: Month BCWS BCWP 0 0 1 10 2 20 3 25 4 30 5 40 6 50 7 66 8 70 9 75 10 80 11 90 12 100 ACWP 0 0 9 15 15 25 20 35 25 40 30 50 40 65 50 75 60 85 65 90 70 100 75 115 80 130 (a) Draw the earned value chart (b) By the month 6, find the Budget variance (ACWP – BCWS) Schedule variance (BCWP – BCWS) Cost Variance (BCWP – ACWP) Performance Ratio (CPI = BCWP/ACWP and SPI = BCWP/BCWS) 2. Below is Brigette’s timeline chart at he end of week six. Based on the chart above, if the rest of the project goes according to plan, what will Brigette’s timeline chart look like when the project is completed. 3. A change in a program specification will normally be carried through into changes to the program design and then changed code. What other products might need to be modified?