NSF Division of Astronomical Sciences (AST) Report November 12, 2015 Jim Ulvestad, Division Director, MPS/AST @UlvestadNSF Outline 11/12/2015 AAAC and NSF Background Recent Highlights Budget Status and Outlook Decadal Survey and Portfolio Review Summary 2 AAAC 11/12/2015 3 AAAC Background Established by Congress in 2002 Three duties Assess and make recommendations regarding coordination of astrophysics among NSF, NASA, and DOE Assess and make recommendations regarding status of activities from 2000 decadal survey and other similar NRC reports Report findings and recommendations on these items, by March 15 of each year, to NSF, NASA, DOE, and both houses of Congress Membership: 13 members (typically 3-yr terms) 4 each appointed by NSF and NASA; 3 by DOE; 2 by OSTP Minimum of four meetings per year Committee activities are governed by Federal Advisory Committees Act 11/12/2015 4 Some Past AAAC Actions Task Forces: Dark Energy Task Force, Exoplanet Task Force, Task Force on CMB Research, Dark Matter Scientific Assessment Group Recommended recent NSF study of Optical/Infrared Telescope System in era of LSST Recommended Principles of Access to Data and Large Projects in Astrophysics AAAC members and other community members are currently working on an assessment of proposal pressures in the three federal agencies 11/12/2015 5 NSF Background 11/12/2015 6 NSF Background Only ~100% basic research agency in federal government FY 2015 budget was $7.3 billion, and President’s Request Budget for FY 2016 is $7.7 billion (+5.2%) AST is in Directorate for Mathematical and Physical Sciences (MPS), which has ~$1.3B budget AST is the lead organization for federally funded, groundbased astronomy and astrophysics Annual budget this decade has ranged from $232M to $246M Major construction projects (>$130 million) are funded from a separate budget line, Major Research Equipment and Facilities Construction (MREFC) Related research supported in Physics Division (PHY, in MPS) and Directorate for Geosciences (GEO) 11/12/2015 7 What is AST? Staff consists of ~20 Ph.D. astronomers, 7 administrative support staff Most scientists are permanent federal employees, while a few are “rotators” (Intergovernmental Personnel Act; Visiting Scientist, Engineer, and Educator; Fed Temp) Roughly 60% of AST budget is spent on operations of major national facilities, while the remaining 40% is spent on mid-scale projects and smaller individual investigator awards 11/12/2015 8 NSF Funding History Amount (Millions)* 1998 1985 *(Constant 2014$) 2004 ARRA 1995 Fiscal Year 11/12/2015 9 Recent Highlights 11/12/2015 10 Atacama Large Millimeter/Submm Array (ALMA) 1990 and 2000 decadal surveys Construction of ALMA was officially completed in 2015. ALMA is a joint project of North America (led by NSF), the European Southern Observatory, and East Asia, with a total construction cost of $1.4 billion. At upper right, an optical image of the merging “Antennae” galaxies is shown, progressively zoomed into a compact but intense source of millimeter radiation imaged with ALMA. This massive, dense, star-free cloud may be the first known example of a globular star cluster about to be born. 11/12/2015 Credit: B. Saxton (NRAO/AUI/NSF); Images from NASA/ESA Hubble, B. Whitmore (STScI); K Johnson (U.Va.); ALMA (NRAO/ESO/NAOJ). (ApJ, 2015, 806, 35) 11 Gemini: GPI First Results The GPI spectra, of HR8799c and d, shown here, indicate large differences in atmospheric clouds or composition Credit: Ingraham, Marley, Saumon, & GPI Team Credit: Marois, Ingraham, & GPI Team 2.0 2.2 Wavelength (μm) Commissioning data from GPI, above left, show three exoplanets circling the nearby star HR8799 The image to the right shows the exoplanet 51 Eridani b (bottom of frame); this object is the most similar to our Solar System’s gas giants of any known exoplanet (Macintosh et al., Science, August 13, 2015). 11/12/2015 2.4 Credit: J. Rameau (UdeM) and C. Marois (NRC Herzberg) 12 Daniel K. Inouye Solar Telescope MREFC project, with total construction budget of $344 million Scheduled for completion in 2019 11/12/2015 13 South Pole CMB Telescopes SPT and BICEP3/Keck Array Photo by Dennis Perkins • 2015 SPT highlights Best constraints on the B-mode power spectrum at sub-degree scales. • High s/n mass maps from gravitational CMB lensing, including polarization data. • High s/n tomography of mass in the universe from cross correlation of SPT CMB lensing and Dark Energy Survey galaxy density. • Final SZ galaxy cluster catalog from the SPT/SZ survey and cosmological constraints. 11/12/2015 14 Photo by Todd Veach Budget Status and Outlook 11/12/2015 15 NWNH Budget vs. Actual AST Budget 400 FY16Req. 300 ~NSF input to A2010 Forecast A2010 $M 200 ScenA ScenB 100 0 FY10 11/12/2015 FY13 FY16 FY19 16 AST Budget Breakdown, 1995-2016 250 200 150 IIA Midscale $M Faciliites 100 50 0 1995 2001 2008 2011 2016 (req.) Facility fraction was 62%-65% from 1995-2001, dropped as low as 53% in 2008, and rose gradually to 60% in 2016 request 11/12/2015 17 FY 2016 Budget Status President’s Request Budget for NSF was $7.72 billion Congressional committee marks were $7.39 billion (House) and $7.34 billion (Senate) Recent Congressional action on discretionary budget levels relieves sequester caps for FY 2016 and 2017 Funding marks not yet given to individual committees President’s Request Budget for AST in FY 2016 is $246.5 million, a $2.4 million increase over FY 2015, and essentially equal to the AST budget in FY 2010 Also $120 million in MREFC line for DKIST and LSST Appropriation bills needed by the time the Continuing Resolution expires on December 11 11/12/2015 18 FY 2016 Congressional Language-1 Congressional committee language needs to be resolved in final appropriation House CJS language 70% of Research & Related Activities line to four directorates: MPS, CISE, ENG, and BIO “NSF shall not implement any final divestment of infrastructure tied to the findings of its 2012 Astronomical Sciences Portfolio Review without first reporting such actions to the Committee. Further, such actions shall be carried out in accordance with any relevant reprogramming requirements.” 11/12/2015 19 FY 2016 Congressional Language-2 Senate CJS language: No language about specific funding to directorates “The Committee encourages NSF to sustain support for the programs and scientific facilities funded by the Astronomical Sciences division, including the National Radio Astronomy Observatory. NSF is also directed to report to the Committee no later than 1 year after enactment of this act on a 5-year transition plan for the continued use of existing solar observatories. Additionally, NSF is expected to request sufficient funding to maintain operations at both new and existing observatories as additional facilities come online in future years.” 11/12/2015 20 Astronomy & Astrophysics Research Grants AAG 55 NWNH target (no inflation assumed) 50 45 $M 40 35 30 2012 11/12/2015 2014 2016 (req.) 21 AAG Funding History, 1990-2015 79.6 AAG Budget, $M 32.4 30.7 34.0 29.4 38.9 49.4 48.1 41.5 42.1 44.5 42.4 43.7 48.4 20.9 22.7 20.2 18.6 17.5 19.3 19.7 18.8 16.2 17.0 18.2 17.1 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 50.4 48.0 45.1 Proposal Success Rate, % 45.1 29.5 31.2 29.3 24.9 27.6 26.7 31.2 34.3 38.1 36.8 36.3 28.8 28.5 24.4 23.9 20.7 22.4 19.9 16.7 18.0 14.8 15.4 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 11/12/2015 22 Proposals in AAG, 1990-2015 770 280 311 319 307 270 219 238 78 119 88 78 49 62 87 58 76 72 50 52 96 73 59 80 89 18 12 126 13 134 19 108 41 126 33 96 36 82 112 43 134 58 104 41 128 48 119 38 131 41 113 32 124 76 104 40 122 107 100 31 138 72 136 74 112 105 48 64 223 259 242 243 102 170 91 115 44 118 144 107 122 113 60 124 91 96 135 148 160 66 57 58 157 91 200 52 227 54 274 60 239 90 145 159 135 136 1 9 9 01 9 9 11 9 9 21 9 9 31 9 9 41 9 9 51 9 9 61 9 9 71 9 9 81 9 9 92 0 0 02 0 0 12 0 0 22 0 0 32 0 0 42 0 0 52 0 0 62 0 0 72 0 0 82 0 0 92 0 1 02 0 1 12 0 1 22 0 1 32 0 1 42 0 1 5 1990 11/12/2015 2015 23 NSF/NASA Coordination on Grants NSF/AST and NASA Astrophysics Division are discussing coordination issues for research grant programs What information can and should be shared to facilitate reviews and reduce duplication of effort? Can/should we better constrain boundaries between agencies, and funnel proposers to appropriate agency? Examples of possible boundaries between NSF/NASA NSF could decline to accept proposals that are primarily based on analysis of space astronomy data (new or archival) NASA could no longer accept proposals for ground-based exoplanet studies that don’t directly support NASA missions Are there any logical boundaries in laboratory astrophysics or theoretical/simulation studies? 11/12/2015 24 Decadal Survey Status 11/12/2015 25 High-Level Look at the Decade So Far AST has successfully started the two highest priority “Large Ground-Based Projects” from New Worlds, New Horizons in Astronomy and Astrophysics (NWNH) Budgetary realities have prevented realization of most other recommendations that require additional funding Available funding has been far less than envisioned by NWNH NWNH, p. 240: “If the realized budget is truly flat in FY 2010 dollars, … very few new activities could be started within NSF-AST” 11/12/2015 26 NWNH Response Summary Complete summary of AST response to NWNH is in a Dear Colleague Letter (DCL), NSF 15-044, available at http://www.nsf.gov/publications/pub_summ.jsp?ods_key=nsf15044 Includes status of all major, actionable recommendations, plus status of Portfolio Review response 11/12/2015 27 NWNH Large Ground Projects-1 1. Large Synoptic Survey Telescope (LSST) NSF construction award in August 2014 Strong NSF/DOE partnership in construction and operations 11/12/2015 28 LSST Cost Profile and Future Schedule Total estimated NSF project cost of $473.0 million, including contingency Survey start planned for October 2022 Expect operations proposal in late 2016 Annual operations cost at FDR was $37 million in FY 2013 dollars, ~$50 million in FY 2023 dollars NSF aiming to cover half the cost, consistent with NWNH recommendation 11/12/2015 29 NRC/CAA OIR System Study “A Strategy to Optimize the U.S. Optical and Infrared System in the Era of the Large Synoptic Survey Telescope (LSST)” Recommended by AAAC in 2013 Committee chaired by Debra Elmegreen, Vassar College Three face-to-face meetings July 31/August 1; October 12-13; December 2-3 Report delivered in April 2015 NSF initial response in Dear Colleague Letter NSF 15-115, issued in August 2015 Extensive discussions and planning ongoing, with both NOAO and LSST 11/12/2015 30 NWNH Large Ground Projects-2 2. Mid-Scale Innovations Program (MSIP) AST Portfolio Review Committee recommended rolling University Radio Observatories (UROs), Telescope Systems Instrumentation Program (TSIP), and large-facility design and development into MSIP Solicitation issued in 2013, with categories modified from NWNH. Six awards were made at various levels, including co-funding of a Physics Frontiers Center Necessary to enable start of MSIP Total AST funding of $27.1M in FY 2014 and 2015 Second solicitation was released in June 2015, with pre-proposals received in September 2015, and conclusion of two-stage evaluation expected in summer 2016 11/12/2015 31 Next “Senior Review” NWNH, p. 32: “NSF-Astronomy should complete its next senior review before the mid-decade independent review that is recommended elsewhere in this report, so as to determine which, if any, facilities NSF-AST should cease to support in order to release funds for (1) the construction and ongoing operation of new telescopes and instruments and (2) the science analysis needed to capitalize on the results from existing and future facilities.” This became the AST Portfolio Review (PR), with committee report delivered in August 2012 11/12/2015 32 Portfolio Review Status 11/12/2015 33 AST Portfolio Scenarios 300 LSST enters here Assuming No Divestment 250 200 With Max. Divestment Individual Investigator+ Mid-scale DKIST ALMA AST $M 150 100 50 Facility Budget Reductions, FY10-FY13 Existing Facilities Assumes 2.5% inflation/yr for existing facilities 0 FY10 FY13 Fiscal Year FY16 FY19 FY17 FY19 Chart above shows the maximum impact of divestment (or non-divestment) within a likely budget scenario 11/12/2015 34 General Portfolio Review Comments Portfolio review report recommended significant facility divestment to enable support of NWNH priorities Process is inevitably slower than hoped NSF (through a contractor) is currently concluding engineering studies and baseline environmental surveys for a number of telescopes and observatories recommended for divestment. Results of these studies will inform more detailed assessments. Most divestments are not clean 100% divestments, but are evolutionary changes to new partnership arrangements Less financial free energy than recommended by PR More complexity in management and oversight To date, most capabilities have remained available for science in some form Open access availability has inevitably been reduced 11/12/2015 35 Facility Futures Telescope Status KPNO 2.1m Caltech took over operations for 3 yr, starting October 2015 Mayall 4m Slated for DESI, pending DOE funding; bridge from NSF WIYN 3.5m NOAO share to NASA-NSF Exoplanet Observational Research Program GBT Partner discussions; Breakthrough Prize Foundation partnership starting in 2016; engineering study under way VLBA Partner discussions in progress; engineering study under way McMath-Pierce Bridging to university-led consortium; engineering study GONG/SOLIS SOLIS moved off Kitt Peak; GONG MOU with NOAA in development Dunn Solar Tel. Partner discussions in progress; engineering study under way Arecibo Post-2016 status in discussion; Dear Colleague Letter released SOAR Post-2020 status to be reviewed 11/12/2015 36 Summary 11/12/2015 37 Primary Interagency Activities NSF/DOE Large Synoptic Survey Telescope Dark Energy Survey: DOE camera on Blanco 4m telescope Dark Energy Spectroscopic Instrument: Future DOE spectrometer on Mayall 4m telescope PHY collaborations on LHC, Dark Matter, VERITAS, HAWC NSF/NASA NASA-NSF Exoplanet Observational Research Program (NN-EXPLORE) NASA to fund spectrometer for use in NSF share of WIYN 3.5m telescope Theoretical and Computational Astrophysics Network Planetary Radar on Arecibo Telescope (NASA Planetary Division) Discussion of coordination on grant funding 11/12/2015 38 Status Summary Outstanding new science opportunities ALMA, EVLA, Gemini/GPI, Blanco/DECam, DKIST, LSST ~110 research awards/yr in AAG, plus MSIP, ATI, AAPF, REU, PAARE Interagency: DES, DESI, NN-EXPLORE, LSST Beyond AST division budget, NSF spent over $100 million on construction of AST facilities in FY 2015 No expectation for significant budget increases this decade Divestment process to date does not cover ramp to DKIST ops LSST operations will begin ramp in FY 2019 to ~$25M/yr by FY 2023 Ongoing AST budget shift toward facilities in flat-budget era Partnerships with NASA and DOE have strengthened Data-enabled science continues to grow in importance Challenges are many, but our community continues to make progress at the science frontiers 11/12/2015 39 Some Upcoming Strategy Issues Impact of facility divestment Positive: some financial resources freed up; intellectual benefits of increased partnerships Negative: partnership complexity, loss or restriction of some community capabilities Relation among NSF OIR observatories in Chile after initiation of LSST operations? Relations among LSST and WFIRST (and EUCLID)? Future of astronomy in Hawaii? Facility choices take 5-10 years to implement, and are based on unknowable budgetary futures. What level of risk to individual investigator programs funds is appropriate in order to commit to operations of additional new facilities? What assumptions should be made for next decadal survey? 11/12/2015 40
© Copyright 2025 Paperzz