MN E-WIC Projected Planning and Implementation Timeline 2020 2019 2018 UAT, Pilot, and Initiate Statewide Roll-out Implementation planning and preparation; Retailer Procurement enablement and Contracting Complete Statewide Rollout and Full Operation 2017 2014 20122013 2011 HuBERT MIS Roll-Out Completed Statewide Planning and Preparation for EBT •EBT Conferences •Stakeholder visits (Grocery and SNAP) Planning and Preparation for EBT 20152016 Contract Award to EWIC Planning Contractor •Stakeholder engagement •Cost Analysis •IAPD & RFP •PAPD Submitted to FNS Development and Approval •Universal Interface Task Force •UPC Database – begin dev. •RFO for Planning Contractor •MIS – Minnesota Information System •PAPD – Planning Advance Planning Document •RFO – Request for Offer •IAPD – Implementation Advanced Planning Document •RFP – Request for Proposal •UAT – User Acceptance Testing