Preliminary Plans Presentation

PRELIMINARY PLANS PRESENTATION
BETHESDA - CHEVY CHASE HIGH SCHOOL
ADDITION
Prepared for
Montgomery County Board of Education
October 2015
Preliminary Plans Presentation
Bethesda - Chevy Chase High School
Addition
4301 East-West Highway
Bethesda, Maryland 20814
Montgomery County Board of Education
Mrs. Patricia B. O’Neill
Mr. Michael A. Durso
Mr. Christopher S. Barclay
Dr. Judith R. Docca
Mr. Philip Kauffman
Ms. Jill Ortman-Fouse
Mrs. Rebecca Smondrowski
Mr. Eric Guerci
President
Vice President
Member
Member
Member
Member
Member
Student Member
Montgomery County Public Schools Administration
Mr. Larry A. Bowers
Mr. James C. Song
Mr. Michael P. Shpur
Mr. James R. Tokar
Ms. Deborah S. Szyfer
Interim Superintendent of Schools
Director, Department of Facilities Management
Architect, Division of Construction
Project Manager, Division of Construction
Facility Planner, Division of Long-Range Planning
Bethesda - Chevy Chase High School Addition
Smolen ■ Emr ■ Ilkovitch Architects Page 1
Facility Advisory Process Involvement
Involvement
The preliminary plans for the Bethesda-Chevy Chase High School addition project were developed based on the educational specifications
prepared by Montgomery County Public Schools (MCPS). Through a series of public meetings, several design alternatives were developed
and evaluated. The proposed plans presented herein were reviewed and subsequently modified in accordance with recommendations
and suggestions received during the schematic design meetings.
Participants in Facility Advisory Process
Dr. Donna Jones
Mrs. Karen Lockard
Mr. Seth Adams Mr. Nick Arnone
Mr. Brian Baczkowske
Mr. John Brammer
Ms. Carole Brand
Mr. Craig Brown
Ms. Stasi Brown
Mr. Luis Carias
Ms. Catlin Corey
Ms. Mary DeFilippes
Ms. Leayne Dempsey
Mr. Matt Dolan
Ms. Carole Edelstein
Mr. Kenny Elias
Ms. Faye Elkins
Ms. Alysa Emden
Mr. Dan Englar
Mr. Gerd Fischer
Ms. Deb Ford
Mr. Rob Ford
Mr. Matt Gandal
Principal
Principal (retired)
Assistant to the Director
Staff
Staff
Staff
Vice President
Parent
Parent
Staff
Staff
Neighbor
Staff
Parish Council
Parent
Parent
Neighbor
Parent
Staff
Parent
Parent
Parent
President
Bethesda - Chevy Chase High School Addition
Smolen ■ Emr ■ Ilkovitch Architects Bethesda-Chevy Chase High School
Bethesda-Chevy Chase High School
Division of Construction - MCPS
Bethesda-Chevy Chase High School
Bethesda-Chevy Chase High School
Bethesda-Chevy Chase High School
Bethesda-Chevy Chase High School Educational Foundation
Bethesda-Chevy Chase High School
Bethesda-Chevy Chase High School
Bethesda-Chevy Chase High School
Bethesda-Chevy Chase High School
Community
Bethesda-Chevy Chase High School
Our Lady of Lourdes Catholic Church and School
Bethesda-Chevy Chase High School
Bethesda-Chevy Chase High School
Community
Bethesda-Chevy Chase High School
Bethesda-Chevy Chase High School
Bethesda-Chevy Chase High School
Bethesda-Chevy Chase High School
Bethesda-Chevy Chase High School
Bethesda-Chevy Chase High School Educational Foundation
Page 2
Facility Advisory Process Involvement
Ms. Allison Gee
Ms. Carolyn Greis
Ms. Kathie Grove
Ms. Claire Helm
Mr. Ricardo Hernandez
Mr. Hunter Hogewood
Ms. Julia Johnson
Mr. John Kelly
Mr. Jeff Kenton
Mr. Patrick Kidd
Ms. Veronica Kidd
Ms. Susan Kitt
Mr. Ed Krauze
Ms. June Lee
Mr. Joel Liss
Ms. Marsha Liss
Mr. Sam Liss
Ms. Lisa Nevans Locke
Mr. Chris McDonald
Ms. Patricia McKain
Ms. Michele McNally
Mr. Jonathan Nataghi-Asli
Mr. Andrew Niebler
Mr. Steve Noyes
Ms. Patricia Parmelee
Mr. Rafe Petersen
Ms. Beth Pincus
Ms. Linda Platt
Ms. Shira Pomeroy
Mr. Tim Price
Ms. Pascale Queffelee
Mr. Jacob Rains
Parent
Parent
Staff
Neighbor
Assistant Principal
Staff
Parent
Neighbor
Staff
Neighbor
Neighbor
Member
Cluster Coordinator
Parent
Neighbor
Neighbor
Neighbor
Neighbor
Staff
Staff
Parent
Staff
Parent
Neighbor
Staff
Cluster Representative
Parent
Neighbor
Staff
Parent
Neighbor
Student
Bethesda - Chevy Chase High School Addition
Smolen ■ Emr ■ Ilkovitch Architects Bethesda-Chevy Chase High School
Bethesda-Chevy Chase High School
Bethesda-Chevy Chase High School
Community
Bethesda-Chevy Chase High School
Bethesda-Chevy Chase High School
Bethesda-Chevy Chase High School
Community
Bethesda-Chevy Chase High School
Community
Community
Bethesda-Chevy Chase High School Educational Foundation
Bethesda-Chevy Chase High School Cluster
Bethesda-Chevy Chase High School
Boy Scouts of America, Troop 1800
Boy Scouts of America, Troop 1800
Boy Scouts of America, Troop 1800
Community
Bethesda-Chevy Chase High School
Bethesda-Chevy Chase High School
Bethesda-Chevy Chase High School
Bethesda-Chevy Chase High School
Bethesda-Chevy Chase High School
Community
Bethesda-Chevy Chase High School
Bethesda-Chevy Chase High School Cluster
Bethesda-Chevy Chase High School
Community
Bethesda-Chevy Chase High School
Bethesda-Chevy Chase High School
Community
Bethesda-Chevy Chase High School
Page 2A
Facility Advisory Process Involvement
Mrs. Ruth Robbins
Ms. Laurie Rosen
Mr. Mike Schweizer
Mr. Jacob Shekter
Mr. Michael Shpur
Mr. Peter Siegel
Mr. Josh Singer
Ms. Jillian Storm
Mr. Kirt Suomela
Ms. Debbie Szyfer
Mr. Jim Tapley
Ms. Theresa Taylor
Mr. James Tokar
Ms. Marietta Vis
Mr. Donald Walker
Ms. Jane Ward
Ms. Kirsten Williams
Mr. Dwain Winter
Ms. Dana Wright
Mr. Max Wright
Ms. Marianne Zweig
Neighbor
Cluster Coordinator
Staff
Neighbor
Architect of School Facilities
Parent
Staff
School Facilities Architect
Neighbor
Facility Planner
Staff
Parent
Project Manager
Parent
Staff
Parent
Parent
Neighbor
Cluster Coordinator
Staff
Staff
Bethesda - Chevy Chase High School Addition
Smolen ■ Emr ■ Ilkovitch Architects Community
Bethesda-Chevy Chase High School Cluster
Bethesda-Chevy Chase High School
Boy Scouts of America, Troop 1800
Division of Construction - MCPS
Bethesda-Chevy Chase High School
Bethesda-Chevy Chase High School
Maryland State Department of Education
Community
Division of Long-range Planning - MCPS
Bethesda-Chevy Chase High School
Bethesda-Chevy Chase High School
Division of Construction - MCPS
Bethesda-Chevy Chase High School
Bethesda-Chevy Chase High School
Bethesda-Chevy Chase High School
Bethesda-Chevy Chase High School
Community
Bethesda-Chevy Chase High School Cluster
Bethesda-Chevy Chase High School
Bethesda-Chevy Chase High School
Page 2B
Project Information
Background/History
Location:4301 East-West Highway, Bethesda, Maryland 20814
Cluster:
Bethesda-Chevy Chase Cluster
History and Square Footage of
Existing Building:
1934
1936
1950
1952
1959
1966
1970
1975
1976
2002
Construction of Original School
Addition
Addition
Addition
Addition
Addition
Addition
Addition
Addition
Revitalization
Total
44,995 square feet
36,515 square feet
(*36,410) 13,206 square feet
*22,396 square feet
*32,408 square feet
*29,023 square feet
*20,295 square feet
*8,378 square feet
*96,166 square feet
213,499 square feet
308,215 square feet
* Demolition during 2002 Revitalization / Expansion Project
Site Size:16.36 acres
Current and Projected School Capacity and Student Enrollment:
Actual
2014-2015
2015-2016
2016-2017
Program Capacity
1683
1683
1683
Enrollment
1992
1989
2067
Space Available/Deficit
(309)
(306)
(384)
Number of Relocatable Classrooms:
8
Current Parking Spaces:
260
Bethesda - Chevy Chase High School Addition
Smolen ■ Emr ■ Ilkovitch Architects Projections
2017-2018
2018-2019
1683
2398
2097
2178
(414)
220
2019-2020
2398
2287
112
2020-2021
2398
2367
32
Page 3
Project Information (continued) Program and Planning Objectives
The purpose of the addition project is to increase the capacity of Bethesda-Chevy Chase High School to accommodate projected student
enrollment. The current student enrollment is 1,989 students and is projected to be 2,367 students by the 2020-2021 school year. The
proposed addition will increase the capacity of the school from the current 1,683 students to 2,398 students with a core capacity for 2,400
students. The project consists of an addition of 34 classrooms and support spaces to meet the program needs of the school.
The flexible building design for the school will accommodate current and future high school programs and delivery models. A philosophy
of adaptable classrooms will facilitate various presentation formats and learning activities. Interactive education computer technology
has been incorporated into the plan. Multi-purpose and flexible spaces will be designed that can be used by both staff and students to
collaborate on projects. Furniture that is easily reconfigurable will be explored to maximize the flexibility in the school.
Stakeholder outreach efforts consisted of five community meetings during the feasibility study phase in Fall of 2012 and five schematic
design work session meetings to elicit student, staff, and community input. Participants were asked to share their ideas, goals and
concerns for the project. Questions related to safety and neighborhood impact are addressed in the architectural design that incorporates
both active and passive security measures. The architectural design also addresses the existing historic buildings by utilizing sympathetic
materials, proportions and rhythms.
Safety during construction will consist of fencing to separate school activities from construction on the site. Full height partitions within
the building will separate construction areas from occupied areas with positive air pressure on the occupied space to control indoor air
quality. Egress paths will be maintained and temporary exits will be created to maintain appropriate safety measures during construction.
All egress paths, construction fencing, access, and contractor staging will be reviewed by the appropriate permitting agencies and
implementation will be closely monitored to ensure safety and security are uncompromised and impact to neighborhood is minimized.
Bethesda - Chevy Chase High School Addition
Smolen ■ Emr ■ Ilkovitch Architects Page 3A
Project Information (continued) Teaching Stations and Spaces Provided When Completed
(Number of teaching stations included in capacity is indicated in parentheses)
New Construction
Summary of Classrooms:
Classrooms
Science Laboratories
Preparation/Project Room
Storage
Ceramics/Sculpture Room
Kiln/Glaze/Prep Room
Ceramic Pug Room
Storage
Digital Art Lab
Storage
Foundation of Technology Lab
Instructional Space
Student Storage
Material Storage
Appied Technology Lab
Student Storage
Material Storage
Multipurpose Laboratory
Office
Storage
2
2
1
1
1
1
1
1
1
2
1
1
1
1
1
(24)
(3)
(1)
(1)
(2)
(1)
(1)
Bethesda - Chevy Chase High School Addition
Smolen ■ Emr ■ Ilkovitch Architects Support Spaces:
Staff Offices
Administration School Assistant
Large Team/Testing Room
School Security Office
Storage Room
Project/Collabration Room
Workroom
Department Office
Technology Education Office
5
1
1
1
2
1
1
1
1
Core Facilities
Dance Room
Storage Closet
1
Reuse of Existing Spaces:
Speech & Language
Conference Room
Counselors’ Office
Signature Coordinator Office
1
1
3
1
Total Teaching Stations
(1)
(34)
Page 3B
Project Information (continued) Site Design
Site Features:
Bethesda-Chevy Chase High School is located at 4301 East-West Highway in Bethesda, Maryland. This property is approximately 16.36
acres and is bounded on the south by East-West Highway (MD-410), on the east by Chelton Road, on the west by Pearl Street and along
the north by Sleaford Road. The site currently includes the existing Bethesda-Chevy Chase High School, athletic fields, and parking for
the school. The site slopes substantially from East-West Highway at its south to the northernmost portions of the property. The slope is
addressed with a series of retaining walls and terraces. The areas of greatest topographic relief, which include slopes greater than a 3:1
ratio, occur between the building and the northern athletic fields and between the tennis courts and the baseball diamond. Repairs to the
football field and track will be required as a result of construction activities. Additionally, a new raised tennis court structure with additional
surface parking below will be constructed. The site currently has 260 parking spaces, including 8 Americans with Disability Act (ADA)
accessible parking spaces. The proposed site improvements will increase on-site parking by 71 spaces for a total of 331 parking spaces,
of which 5 will be ADA accessible spaces, with 2 van accessible spaces, as required by ADA.
Stormwater Management:
There are two existing stormwater management facilities located on-site. A majority of the surface runoff is treated by a structural sand
filter while an underground detention system that handles larger storms flow. The planned parking area and raised tennis courts are
proposed to be connected into the existing stormwater system. Three micro-bioretention facilities will be provided to meet Environmental
Site Design (ESD) requirements to the maximum extent possible to comply with Montgomery County requirements.
Utilities:
The existing utility services are adequate to serve the proposed addition. The existing 8-inch sanitary line that runs from the southwest
side of the existing school and through the area for the proposed addition will be relocated and replaced with a new line that will run
north and west of the stadium and connect to the 10-inch sewer main along Sleaford Road. The existing facility has two domestic water
connections to a 10-inch water main in the Chelton Road and East-West Highway right-of-ways. Existing dry utilities (i.e., gas, electric,
fiber and telephone) are sufficient to service the new addition, and no alterations to building services will be required.
Forest Conservation:
The proposed site improvements have been minimized around the critical root zones of trees in an attempt to retain as many trees as
possible. Stress reduction measures such as root pruning will be performed.
Bethesda - Chevy Chase High School Addition
Smolen ■ Emr ■ Ilkovitch Architects Page 3C
Project Information (continued) Site Design (continued)
Traffic:
On-site and surrounding neighborhood circulation concerns were evaluated through a traffic study. The traffic study revealed that the
proposed classroom addition project at Bethesda-Chevy Chase High School that will increase program capacity at the school to 2,398
students will have minimal impact on traffic operations within the study area, including Pearl Street and Chelton Road.
Bethesda - Chevy Chase High School Addition
Smolen ■ Emr ■ Ilkovitch Architects Page 3D
Project Information (continued) Building Design
General Description:
The proposed addition is designed to achieve the program requirements outlined in the MCPS Educational Specification. The addition
program has been planned in two new wings, to optimize adjacencies to related instructional areas within the existing building. A twostory wing will be constructed along the north face of the existing building. A four-story wing will be constructed directly to the west
of the existing gymnasium. The addition will connect to the existing building at the stairwell behind the gymnasium and loop around
the northwest corner to connect to the front entrance. The front entrance will be modified to connect the addition at three existing floor
levels and provide a more clearly defined main entrance. A new security vestibule will be incorporated requiring all visitors to enter the
building through the administrative suite.
The two-story wing will be elevated one story above grade to enable pedestrians and vehicles to freely pass below. The space below the
addition will be a covered, open air plaza that overlooks the stadium and provides access to the new bleachers. A feature of this wing
will be a new dance room opening to a small atrium lobby that connects both levels with views of the stadium below.
In the four-story wing, the existing stair tower to the west of the gymnasium will be demolished and an open stair will be provided in
its place improving interior circulation and travel times between all levels of the addition and the existing school. Two new stair towers
will be added for the required egress capacity and a new elevator will provide accessibility to all four floor levels and the elevated tennis
deck level. The elevator will be programmed to ensure building security when the building is closed.
The addition’s structure will be steel-framed with all interior spaces defined by masonry partitions. The structural frame will be firetreated, which provides an increase in the allowable building area. A pre-cast concrete structure will elevate the tennis courts above a
new parking area.
Exterior architectural finishes will be a combination of brick and architectural metal panels that relate to the historic materials of the
original facades. The introduction of a glass and metal panel curtain wall system will be used in the raised north facade and west main
entrance to take advantage of its light weight properties in the elevated areas. Shading devices have been integrated into the design of the
elevations to protect glazed surfaces facing a variety of solar orientations. The design of the new facades are directly derived from the
rhythms and proportions of the historic context which have been applied to contemporary building technologies. Alternating materials
in a uniform gridded pattern will break down the mass of the building while presenting a cohesive overall appearance.
Bethesda - Chevy Chase High School Addition
Smolen ■ Emr ■ Ilkovitch Architects Page 3E
Project Information (continued) Building Design (continued)
Classroom Technology:
Classrooms in the building addition will be designed with wireless network access and interactive whiteboard systems to support the
interactive and mobile technologies that allow students to participate in technology enriched learning. The mobile technology will
support flexibility to reconfigure classrooms and learning throughout the instructional day. Full building wireless technologies will
enable students and staff to access digital content, curricular, and instructional resources with greater flexibility and efficiency.
Code Compliance/Accessibility:
All spaces will be designed in compliance with the most current building codes adopted by Maryland and Montgomery County, including
fire, life-safety, and health standards. All new work will fully comply with the Americans with Disabilities Act (ADA).
Exterior Lighting:
The exterior building and site lighting will be designed to shield adjacent residences from intrusive light glare while maintaining light
levels for safety and security. The light fixtures will be 100% down-lighting, dark sky compliant, to minimize light pollution into the
night sky. The exterior light fixtures at canopies, building, security and parking lots will be light emitting-diode (LED) type fixtures that
are long lasting and energy efficient.
Bethesda - Chevy Chase High School Addition
Smolen ■ Emr ■ Ilkovitch Architects Page 3F
Project Information (continued) Building Design (continued)
Sustainable Design Intent:
The project is not required to be registered for Leadership in Energy & Environmental Design (LEED) certification through the United
States Green Building Council (USGBC). However, the addition will be designed in accordance with the 2014 MCPS Environmental
Sustainability Management Plan. By following the principles listed within this plan, MCPS facilities aim to reduce impact on the natural
world, provide healthly learning and working evironments for the community, conserve operational costs, and serve as a teaching tool
for the future leaders of the county. Sustainable aspects of the project include, but are not limited to:
•
•
•
•
•
•
•
•
•
•
•
Locating additions and impervious site work on previously paved surfaces to minimize impact on vegetated areas;
Installing water conserving, low flow plumbing fixtures to conserve potable water;
Installing high performance building envelope materials to reduce heating and cooling loads;
Installing energy efficient HVAC equipment to reduce energy use;
Installing operable windows to encourage the use of natural ventilation;
Installing energy efficient lighting fixtures with occupancy sensors to reduce energy use;
Maximizing natural daylighting within teaching spaces;
Providing shading devices to minimize solar heat gain and glare;
Specifying bulding materials with recycled content to minimize usage of virgin natural resources;
Specifying low-emitting building materials to safeguard occupant health;
Designing acoustically optimized spaces to enhance the functionality of spaces.
Bethesda - Chevy Chase High School Addition
Smolen ■ Emr ■ Ilkovitch Architects Page 3G
Project Information (continued) Building Design (continued)
Mechanical Systems:
Heating, Ventilation and Air-Conditioning System:
The building addition will be heated and air-conditioned by a four-pipe fan-coil unit system. Ventilation airflow for the building addition
will be
provided through a series of rooftop energy recovery units. Fan coil units and energy recovery unit systems will be provided
with chilled water and heating water from new chilled and heating water plants, complete with a high-efficiency air-cooled chiller
and gas-fired condensing boilers. The condensing boilers and associated heating water pumps will be located within the existing
mechanical room. The new air-cooled chiller will be located at the roof level of the addition and positioned adjacent to the existing
chiller and cooling tower. Chilled water pumps for the proposed addition will be located within the existing penthouse mechanical room
and positioned adjacent to the existing chilled and condenser water pumping systems.
Plumbing System:
Domestic cold water for the building addition will extend from the existing school and will include a new gas-fired water heater for
production of domestic hot water within the building addition. Plumbing fixtures will be designed to meet the Americans with Disabilities
Act (ADA) and utilize water conservation features. Water closets will be floor-mounted with dual-flush type valves, urinals will be wallhung with pint flush type valves, and lavatories will be individually wall-hung with self-closing faucets.
Fire Protection System:
The school’s existing fire protection system will be extended to support the addition. The building addition will be fully sprinklered,
provided with standpipes, and comply with the National Fire Protection Code (NFPA 13 and 14) requirements. The existing fire pump
will remain and support the additional building area. New zone valve assemblies will provided at each floor level of the addition; with
sprinkler piping extending from these zone valves to support the addition.
Energy Management Statement:
Building automation system controls for the addition will be an extension of the existing Andover direct digital control (DDC) system.
All new control components will be networked to the central MCPS energy management control system for occupied/unoccupied
settings and other energy management routines.
Bethesda - Chevy Chase High School Addition
Smolen ■ Emr ■ Ilkovitch Architects Page 3H
Project Information (continued) Building Design (continued)
Electrical Systems:
Power Distribution:
The existing 277/480V 4000A main switchboard has adequate spare capacity and will be utilized to serve the building addition. New
circuit breakers will be installed in the existing switchboard to serve new electrical equipment in the addition. The existing 125 kW
outdoor generator will be utilized to serve life-safety and standby loads in the addition.
Public Address System:
The existing intercom/public address systems will be expanded into the addition. New intercom/public address devices include speakers
and call switches in the classrooms and speakers in the corridors.
Security System:
The existing security systems will be expanded for the addition. Door card access control will be installed where required. Intrusion
detection will include motion sensors and door contacts. Video surveillance will include cameras in corridors.
Technology Infrastructure:
Existing data/voice/video will be expanded for the addition. The building addition will be equipped with data, voice-over internet
protocol (VoIP), video, and wireless systems. The network system design will include outlet boxes, conduits, surface raceways, conduit
sleeves, and properly-sized telecommunications closets for the low voltage systems. The infrastructure system will consist of a fiberoptic backbone cable system with category 5E UTP cable for station drop connectivity, supporting switched 10/100/1000 Mbps Ethernet.
With the improved switching systems, these systems have the capability of providing a gigabyte Ethernet system with provisions to
accommodate future changes in technology. For video distribution, a 1,000 MHz bi- directional, broadband distribution system with
coax trunk cable and RG-6 quad-shielded coax drop cable will be utilized. The system allows full video cable spectrum to every part of
the building with five dedicated channels: one channel for school distribution from the studio, two channels for school distribution or
two-way video from any point in the building and two spare channels available for future use.
Bethesda - Chevy Chase High School Addition
Smolen ■ Emr ■ Ilkovitch Architects Page 3I
Vicinity Map
GE
CONNECTICUT AVENUE (MD-185)
D
OR
55)
UE (MD-3
SIN AVEN
WISCON
OL
GE
TO
W
D ROAD
SLEAFOR
RO
AD
(M
D-
18
BETHESDA
CHEVY CHASE
HIGH SCHOOL
T
STREE
ES
WAY
T HIGH
EAST-W
ROAD
PEARL
7)
CHELTON
N
0)
-41
(MD
BETHESDA
0’
250’ 500’
1000’
2000’
NORTH
Bethesda - Chevy Chase High School Addition
Smolen ■ Emr ■ Ilkovitch Architects Page 4
Existing Site Plan
D ROAD
SLEAFOR
FOOTBALL FIELD STADIUM AND TRACK
BASEBALL/SOFTBALL
PARKING
ERS
BLEACH
CHELTON
ET
RE
PEARL ST
ABLE
RELOCAT
OMS
O
R
S
S
A
CL
TENNIS
ROAD
MAIN
ENTRANCE
BUILDING
BUS LOOP/
STUDENT
DROP OFF
PARKING
SERVICE
DRIVE
T
WES
AST-
WAY
HIGH
E
SCALE 1 INCH = 30 FEET
0 30 60
120
240
NORTH
Bethesda - Chevy Chase High School Addition
Smolen ■ Emr ■ Ilkovitch Architects Page 5
Proposed Site Plan
D ROAD
SLEAFOR
FOOTBALL FIELD STADIUM AND TRACK
BASEBALL/SOFTBALL
NEW BLEACHERS
ELEVATED TENNIS DECK
(PARKING BELOW)
ELEVATED
TWO-STORY
ADDITION
CHELTON
REET
PEARL ST
FOUR-STORY
ADDITION
ROAD
EXISTING
BUILDING
MAIN
ENTRANCE
BUS LOOP/
STUDENT
DROP OFF
PARKING
SERVICE
DRIVE
ST
- WE
AST
Y
HWA
HIG
E
SCALE 1 INCH = 30 FEET
0 30 60
120
240
NORTH
Bethesda - Chevy Chase High School Addition
Smolen ■ Emr ■ Ilkovitch Architects Page 5A
Existing Ground Floor Plan
PROJECT COLOR LEGEND
EXISTING
CLASSROOMS
SUPPORT SPACES
CORE FACILITIES
BUILDING SERVICES / MECHANICAL / ELECTRICAL
PROJECT SPACE LEGEND
1 ART ROOM
2 AUDITORIUM
3 AUXILARY GYMNASIUM
4 BOILER ROOM
5 CAREER CENTER
6 CERAMICS/SCULPTURE ROOM
7 CERAMIC PUG ROOM
8 CHILD DEVELOPMENT
9 CLASSROOM
10 COMPUTER LAB
11 CONCESSIONS
12 CONFERENCE ROOM
13 COUSELOR
14 DANCE ROOM
15 DEPARTMENT OFFICE
16 DIGITAL ART LABORATORY
17 DRESSING ROOM
18 ELECTRICAL ROOM / DATA ROOM
19 NOT USED
20 FOOTBALL STORAGE
21 GENERATOR ROOM
22 GYMNASIUM
23 HEALTH SUITE
24 KILN/GLAZE/PREPARATION ROOM
25 KITCHEN
26 LARGE TEAM/TESTING ROOM
27 LOADING DOCK
28 LOCKER ROOM
29 MECHANICAL ROOM
30 MEDIA CENTER
31 MULTIPURPOSE LABORATORY
32 MUSIC ROOM
33 OFFICE
34 OFFICE: ADMINISTRATIVE SCHOOL ASSISTANT
35 OFFICE: IB COORDINATOR
36 OFFICE: IB SECRETARY
37 OFFICE: SIGNATURE COORDINATOR
38 OFFICE: STAFF DEVELOPMENT
39 OFFICE: STAFF SUPPORT
40 PROJECT/COLLABORATION ROOM
41 RECEPTION, ADMINISTRATION SUITE
42 RESOURCE ROOM
43 SCHOOL SECURITY OFFICE
44 SCIENCE LABORATORY
45 SCIENCE PREPERATION/PROJECT ROOM
46 SEMINAR
47 SPEECH & LANGUAGE
48 STAFF ROOM
49 STORAGE
50 STUDENT DINING
51 TECHNOLOGY EDUCATION
52 TECHNOLOGY EDUCATION: APPLIED TECHNOLOGY LABORATORY
53 TECHNOLOGY EDUCATION: FOUNDATIONS OF TECHNOLOGY LABORATORY
54 TECHNOLOGY EDUCATION: INSTRUCTIONAL SPACE
55 TOILET
56 VESTIBULE (SECURE)
57 WORK ROOM
58 WRESTLING
11
55
20
55
9
28
9
9
9
55
33
33
17
12
33
33
Bethesda - Chevy Chase High School Addition
Smolen ■ Emr ■ Ilkovitch Architects 9
4
55
17
49
32
UNEXCAVATED
58
49
28
32
32
49
3
33
18 18
55
55
18
21
CRAWL SPACE
29
0’5’ 10’ 20’ 30’
50’
NORTH
Page 6
Proposed Ground Floor Plan
PROJECT COLOR LEGEND
EXISTING
CLASSROOMS
SUPPORT SPACES
CORE FACILITIES
BUILDING SERVICES / MECHANICAL / ELECTRICAL
PROJECT SPACE LEGEND
UP
COVERED PLAZA
UP
9
9
9
29
1 ART ROOM
2 AUDITORIUM
3 AUXILARY GYMNASIUM
4 BOILER ROOM
49
5 CAREER CENTER
6 CERAMICS/SCULPTURE ROOM
7 CERAMIC PUG ROOM
29
8 CHILD DEVELOPMENT
9
9 CLASSROOM
10 COMPUTER LAB
11 CONCESSIONS
12 CONFERENCE ROOM
13 COUSELOR
14 DANCE ROOM
15 DEPARTMENT OFFICE
16 DIGITAL ART LABORATORY
17 DRESSING ROOM
18 ELECTRICAL ROOM / DATA ROOM
19 NOT USED
20 FOOTBALL STORAGE
21 GENERATOR ROOM
22 GYMNASIUM
23 HEALTH SUITE
24 KILN/GLAZE/PREPARATION ROOM
25 KITCHEN
26 LARGE TEAM/TESTING ROOM
27 LOADING DOCK
28 LOCKER ROOM
29 MECHANICAL ROOM
30 MEDIA CENTER
31 MULTIPURPOSE LABORATORY
32 MUSIC ROOM
33 OFFICE
34 OFFICE: ADMINISTRATIVE SCHOOL ASSISTANT
35 OFFICE: IB COORDINATOR
36 OFFICE: IB SECRETARY
37 OFFICE: SIGNATURE COORDINATOR
38 OFFICE: STAFF DEVELOPMENT
39 OFFICE: STAFF SUPPORT
40 PROJECT/COLLABORATION ROOM
41 RECEPTION, ADMINISTRATION SUITE
42 RESOURCE ROOM
43 SCHOOL SECURITY OFFICE
44 SCIENCE LABORATORY
45 SCIENCE PREPERATION/PROJECT ROOM
46 SEMINAR
47 SPEECH & LANGUAGE
48 STAFF ROOM
49 STORAGE
50 STUDENT DINING
51 TECHNOLOGY EDUCATION
52 TECHNOLOGY EDUCATION: APPLIED TECHNOLOGY LABORATORY
53 TECHNOLOGY EDUCATION: FOUNDATIONS OF TECHNOLOGY LABORATORY
54 TECHNOLOGY EDUCATION: INSTRUCTIONAL SPACE
55 TOILET
56 VESTIBULE (SECURE)
57 WORK ROOM
58 WRESTLING
9
55
29
46
11
55
18 18
20
55
33
9
9
9
9
9
4
17
33
12
29
9
9
28
55
15
29
55
9
33
33
55
17
49
32
UNEXCAVATED
58
49
UNEXCAVATED
Bethesda - Chevy Chase High School Addition
Smolen ■ Emr ■ Ilkovitch Architects 28
32
32
49
3
33
18 18
55
55
18
21
CRAWL SPACE
29
0’5’ 10’ 20’ 30’
50’
NORTH
Page 6A
Existing First Floor Plan
PROJECT COLOR LEGEND
EXISTING
CLASSROOMS
SUPPORT SPACES
CORE FACILITIES
BUILDING SERVICES / MECHANICAL / ELECTRICAL
49
PROJECT SPACE LEGEND
1 ART ROOM
2 AUDITORIUM
3 AUXILARY GYMNASIUM
4 BOILER ROOM
5 CAREER CENTER
6 CERAMICS/SCULPTURE ROOM
7 CERAMIC PUG ROOM
8 CHILD DEVELOPMENT
9 CLASSROOM
10 COMPUTER LAB
11 CONCESSIONS
12 CONFERENCE ROOM
13 COUSELOR
14 DANCE ROOM
15 DEPARTMENT OFFICE
16 DIGITAL ART LABORATORY
17 DRESSING ROOM
18 ELECTRICAL ROOM / DATA ROOM
19 NOT USED
20 FOOTBALL STORAGE
21 GENERATOR ROOM
22 GYMNASIUM
23 HEALTH SUITE
24 KILN/GLAZE/PREPARATION ROOM
25 KITCHEN
26 LARGE TEAM/TESTING ROOM
27 LOADING DOCK
28 LOCKER ROOM
29 MECHANICAL ROOM
30 MEDIA CENTER
31 MULTIPURPOSE LABORATORY
32 MUSIC ROOM
33 OFFICE
34 OFFICE: ADMINISTRATIVE SCHOOL ASSISTANT
35 OFFICE: IB COORDINATOR
36 OFFICE: IB SECRETARY
37 OFFICE: SIGNATURE COORDINATOR
38 OFFICE: STAFF DEVELOPMENT
39 OFFICE: STAFF SUPPORT
40 PROJECT/COLLABORATION ROOM
41 RECEPTION, ADMINISTRATION SUITE
42 RESOURCE ROOM
43 SCHOOL SECURITY OFFICE
44 SCIENCE LABORATORY
45 SCIENCE PREPERATION/PROJECT ROOM
46 SEMINAR
47 SPEECH & LANGUAGE
48 STAFF ROOM
49 STORAGE
50 STUDENT DINING
51 TECHNOLOGY EDUCATION
52 TECHNOLOGY EDUCATION: APPLIED TECHNOLOGY LABORATORY
53 TECHNOLOGY EDUCATION: FOUNDATIONS OF TECHNOLOGY LABORATORY
54 TECHNOLOGY EDUCATION: INSTRUCTIONAL SPACE
55 TOILET
56 VESTIBULE (SECURE)
57 WORK ROOM
58 WRESTLING
3
22
49
2
33
18
41
23
55
55
9
42
12
12
9
57
47
9
1
9
COURTYARD
48
43
9
9
1
12
42
55
29
55
9
6
18
8
27
8
50
25
Bethesda - Chevy Chase High School Addition
Smolen ■ Emr ■ Ilkovitch Architects 0’5’ 10’ 20’ 30’
50’
NORTH
Page 6B
Proposed First Floor Plan
PRESS BOX
PROJECT COLOR LEGEND
EXISTING
CLASSROOMS
SUPPORT SPACES
CORE FACILITIES
BUILDING SERVICES / MECHANICAL / ELECTRICAL
PROJECT SPACE LEGEND
UP
9
9
16
49
29
24
6
14
49 29 7
UP
9
9
29
1 ART ROOM
2 AUDITORIUM
UP
3 AUXILARY GYMNASIUM
DN
4 BOILER ROOM
49
5 CAREER CENTER
29
6 CERAMICS/SCULPTURE ROOM
7 CERAMIC PUG ROOM
9
9
8 CHILD DEVELOPMENT
9 CLASSROOM
10 COMPUTER LAB
11 CONCESSIONS
12 CONFERENCE ROOM
13 COUSELOR
14 DANCE ROOM
15 DEPARTMENT OFFICE
16 DIGITAL ART LABORATORY
17 DRESSING ROOM
18 ELECTRICAL ROOM / DATA ROOM
19 NOT USED
20 FOOTBALL STORAGE
21 GENERATOR ROOM
22 GYMNASIUM
23 HEALTH SUITE
24 KILN/GLAZE/PREPARATION ROOM
25 KITCHEN
26 LARGE TEAM/TESTING ROOM
27 LOADING DOCK
28 LOCKER ROOM
29 MECHANICAL ROOM
30 MEDIA CENTER
31 MULTIPURPOSE LABORATORY
32 MUSIC ROOM
33 OFFICE
34 OFFICE: ADMINISTRATIVE SCHOOL ASSISTANT
35 OFFICE: IB COORDINATOR
36 OFFICE: IB SECRETARY
37 OFFICE: SIGNATURE COORDINATOR
38 OFFICE: STAFF DEVELOPMENT
39 OFFICE: STAFF SUPPORT
40 PROJECT/COLLABORATION ROOM
41 RECEPTION, ADMINISTRATION SUITE
42 RESOURCE ROOM
43 SCHOOL SECURITY OFFICE
44 SCIENCE LABORATORY
45 SCIENCE PREPERATION/PROJECT ROOM
46 SEMINAR
47 SPEECH & LANGUAGE
48 STAFF ROOM
49 STORAGE
50 STUDENT DINING
51 TECHNOLOGY EDUCATION
52 TECHNOLOGY EDUCATION: APPLIED TECHNOLOGY LABORATORY
53 TECHNOLOGY EDUCATION: FOUNDATIONS OF TECHNOLOGY LABORATORY
54 TECHNOLOGY EDUCATION: INSTRUCTIONAL SPACE
55 TOILET
56 VESTIBULE (SECURE)
57 WORK ROOM
58 WRESTLING
9
9
29
9
49
55
18
57
49
DN
55
18
35
36
29
49
39 39 34
38
Bethesda - Chevy Chase High School Addition
Smolen ■ Emr ■ Ilkovitch Architects 3
22
49
2
43
UP
33
56
18
41
23
55
55
9
42
12
12
9
57
47
9
1
9
COURTYARD
48
43
9
9
1
12
42
55
29
55
9
6
18
8
27
8
50
25
0’5’ 10’ 20’ 30’
50’
NORTH
Page 6C
Existing Second Floor Plan
PROJECT COLOR LEGEND
EXISTING
CLASSROOMS
SUPPORT SPACES
CORE FACILITIES
BUILDING SERVICES / MECHANICAL / ELECTRICAL
ROOF
BLUE & GOLD
PROJECT SPACE LEGEND
1 ART ROOM
2 AUDITORIUM
3 AUXILARY GYMNASIUM
4 BOILER ROOM
5 CAREER CENTER
6 CERAMICS/SCULPTURE ROOM
7 CERAMIC PUG ROOM
8 CHILD DEVELOPMENT
9 CLASSROOM
10 COMPUTER LAB
11 CONCESSIONS
12 CONFERENCE ROOM
13 COUSELOR
14 DANCE ROOM
15 DEPARTMENT OFFICE
16 DIGITAL ART LABORATORY
17 DRESSING ROOM
18 ELECTRICAL ROOM / DATA ROOM
19 NOT USED
20 FOOTBALL STORAGE
21 GENERATOR ROOM
22 GYMNASIUM
23 HEALTH SUITE
24 KILN/GLAZE/PREPARATION ROOM
25 KITCHEN
26 LARGE TEAM/TESTING ROOM
27 LOADING DOCK
28 LOCKER ROOM
29 MECHANICAL ROOM
30 MEDIA CENTER
31 MULTIPURPOSE LABORATORY
32 MUSIC ROOM
33 OFFICE
34 OFFICE: ADMINISTRATIVE SCHOOL ASSISTANT
35 OFFICE: IB COORDINATOR
36 OFFICE: IB SECRETARY
37 OFFICE: SIGNATURE COORDINATOR
38 OFFICE: STAFF DEVELOPMENT
39 OFFICE: STAFF SUPPORT
40 PROJECT/COLLABORATION ROOM
41 RECEPTION, ADMINISTRATION SUITE
42 RESOURCE ROOM
43 SCHOOL SECURITY OFFICE
44 SCIENCE LABORATORY
45 SCIENCE PREPERATION/PROJECT ROOM
46 SEMINAR
47 SPEECH & LANGUAGE
48 STAFF ROOM
49 STORAGE
50 STUDENT DINING
51 TECHNOLOGY EDUCATION
52 TECHNOLOGY EDUCATION: APPLIED TECHNOLOGY LABORATORY
53 TECHNOLOGY EDUCATION: FOUNDATIONS OF TECHNOLOGY LABORATORY
54 TECHNOLOGY EDUCATION: INSTRUCTIONAL SPACE
55 TOILET
56 VESTIBULE (SECURE)
57 WORK ROOM
58 WRESTLING
OPEN TO BELOW
Bethesda - Chevy Chase High School Addition
Smolen ■ Emr ■ Ilkovitch Architects OPEN TO BELOW
OPEN TO BELOW
OPEN TO BELOW
55
44
45
55
44
45
9
9
49
9
9
OPEN TO BELOW
30
9
15
57
44
9
44
9
42
9
55
55
44
45
49
9
13
33
13
13
12
5
51
57
13 13
46
9
10
9
13 33
10
15
0’5’ 10’ 20’ 30’
50’
NORTH
Page 6D
Proposed Second Floor Plan
PROJECT COLOR LEGEND
ROOF
EXISTING
CLASSROOMS
SUPPORT SPACES
CORE FACILITIES
BUILDING SERVICES / MECHANICAL / ELECTRICAL
PROJECT SPACE LEGEND
9
9
9
9
29
29
OPEN TO
BELOW
9
29
UP
DN
44
45
1 ART ROOM
2 AUDITORIUM
3 AUXILARY GYMNASIUM
4 BOILER ROOM
5 CAREER CENTER
6 CERAMICS/SCULPTURE ROOM
7 CERAMIC PUG ROOM
8 CHILD DEVELOPMENT
44
9 CLASSROOM
10 COMPUTER LAB
11 CONCESSIONS
12 CONFERENCE ROOM
13 COUSELOR
14 DANCE ROOM
15 DEPARTMENT OFFICE
16 DIGITAL ART LABORATORY
17 DRESSING ROOM
18 ELECTRICAL ROOM / DATA ROOM
19 NOT USED
20 FOOTBALL STORAGE
21 GENERATOR ROOM
22 GYMNASIUM
23 HEALTH SUITE
24 KILN/GLAZE/PREPARATION ROOM
25 KITCHEN
26 LARGE TEAM/TESTING ROOM
27 LOADING DOCK
28 LOCKER ROOM
29 MECHANICAL ROOM
30 MEDIA CENTER
31 MULTIPURPOSE LABORATORY
32 MUSIC ROOM
33 OFFICE
34 OFFICE: ADMINISTRATIVE SCHOOL ASSISTANT
35 OFFICE: IB COORDINATOR
36 OFFICE: IB SECRETARY
37 OFFICE: SIGNATURE COORDINATOR
38 OFFICE: STAFF DEVELOPMENT
39 OFFICE: STAFF SUPPORT
40 PROJECT/COLLABORATION ROOM
41 RECEPTION, ADMINISTRATION SUITE
42 RESOURCE ROOM
43 SCHOOL SECURITY OFFICE
44 SCIENCE LABORATORY
45 SCIENCE PREPERATION/PROJECT ROOM
46 SEMINAR
47 SPEECH & LANGUAGE
48 STAFF ROOM
49 STORAGE
50 STUDENT DINING
51 TECHNOLOGY EDUCATION
52 TECHNOLOGY EDUCATION: APPLIED TECHNOLOGY LABORATORY
53 TECHNOLOGY EDUCATION: FOUNDATIONS OF TECHNOLOGY LABORATORY
54 TECHNOLOGY EDUCATION: INSTRUCTIONAL SPACE
55 TOILET
56 VESTIBULE (SECURE)
57 WORK ROOM
58 WRESTLING
9
9
49
UP
DN
29
ROOF
55
29
BLUE & GOLD
55
18 18
33
49
29
49
44
OPEN TO BELOW
OPEN TO BELOW
OPEN TO BELOW
31
45
Bethesda - Chevy Chase High School Addition
Smolen ■ Emr ■ Ilkovitch Architects OPEN TO BELOW
55
44
45
55
44
45
9
9
49
9
9
OPEN TO BELOW
30
9
15
57
44
9
44
9
42
9
55
55
44
45
49
9
13
33
13
13
ROOF
12
5
13
57
13 13
49
13
13 33
51
13
46
9
10
37
10
0’5’ 10’ 20’ 30’
15
50’
NORTH
Page 6E
Existing Third Floor Plan
PROJECT COLOR LEGEND
EXISTING
CLASSROOMS
SUPPORT SPACES
CORE FACILITIES
BUILDING SERVICES / MECHANICAL / ELECTRICAL
ROOF
PROJECT SPACE LEGEND
Bethesda - Chevy Chase High School Addition
Smolen ■ Emr ■ Ilkovitch Architects 29
ROOF
OPEN TO BELOW
18
49
33 49
33
44
45
55
55
51
45
9
49
OPEN TO BELOW
33
49
49
49
44
54
15
9
44
51
33
49
15
9
ROOF
1 ART ROOM
2 AUDITORIUM
3 AUXILARY GYMNASIUM
4 BOILER ROOM
5 CAREER CENTER
6 CERAMICS/SCULPTURE ROOM
7 CERAMIC PUG ROOM
8 CHILD DEVELOPMENT
9 CLASSROOM
10 COMPUTER LAB
11 CONCESSIONS
12 CONFERENCE ROOM
13 COUSELOR
14 DANCE ROOM
15 DEPARTMENT OFFICE
16 DIGITAL ART LABORATORY
17 DRESSING ROOM
18 ELECTRICAL ROOM / DATA ROOM
19 NOT USED
20 FOOTBALL STORAGE
21 GENERATOR ROOM
22 GYMNASIUM
23 HEALTH SUITE
24 KILN/GLAZE/PREPARATION ROOM
25 KITCHEN
26 LARGE TEAM/TESTING ROOM
27 LOADING DOCK
28 LOCKER ROOM
29 MECHANICAL ROOM
30 MEDIA CENTER
31 MULTIPURPOSE LABORATORY
32 MUSIC ROOM
33 OFFICE
34 OFFICE: ADMINISTRATIVE SCHOOL ASSISTANT
35 OFFICE: IB COORDINATOR
36 OFFICE: IB SECRETARY
37 OFFICE: SIGNATURE COORDINATOR
38 OFFICE: STAFF DEVELOPMENT
39 OFFICE: STAFF SUPPORT
40 PROJECT/COLLABORATION ROOM
41 RECEPTION, ADMINISTRATION SUITE
42 RESOURCE ROOM
43 SCHOOL SECURITY OFFICE
44 SCIENCE LABORATORY
45 SCIENCE PREPERATION/PROJECT ROOM
46 SEMINAR
47 SPEECH & LANGUAGE
48 STAFF ROOM
49 STORAGE
50 STUDENT DINING
51 TECHNOLOGY EDUCATION
52 TECHNOLOGY EDUCATION: APPLIED TECHNOLOGY LABORATORY
53 TECHNOLOGY EDUCATION: FOUNDATIONS OF TECHNOLOGY LABORATORY
54 TECHNOLOGY EDUCATION: INSTRUCTIONAL SPACE
55 TOILET
56 VESTIBULE (SECURE)
57 WORK ROOM
58 WRESTLING
9
48
9
51
44
19
49
33
55
9
44
55
9
45
49
9
9
ROOF
9
9
9
49
9
9
9
48
9
49
9
15
0’5’ 10’ 20’ 30’
50’
NORTH
Page 6F
Proposed Third Floor Plan
PROJECT COLOR LEGEND
EXISTING
CLASSROOMS
SUPPORT SPACES
CORE FACILITIES
BUILDING SERVICES / MECHANICAL / ELECTRICAL
PROJECT SPACE LEGEND
ROOF
ROOF
49
49
52
DN
26
33
ROOF
55
55
DN
29
18 18 49
54
53
29
ROOF
49
49
OPEN TO BELOW
49
Bethesda - Chevy Chase High School Addition
Smolen ■ Emr ■ Ilkovitch Architects 18
49
33 49
33
44
45
55 55
51
45
49
49
49
49
44
54
15
9
OPEN TO BELOW
33
33
9
44
51
49
15
9
ROOF
29
1 ART ROOM
2 AUDITORIUM
3 AUXILARY GYMNASIUM
4 BOILER ROOM
5 CAREER CENTER
6 CERAMICS/SCULPTURE ROOM
53
7 CERAMIC PUG ROOM
8 CHILD DEVELOPMENT
9 CLASSROOM
10 COMPUTER LAB
11 CONCESSIONS
12 CONFERENCE ROOM
13 COUSELOR
14 DANCE ROOM
15 DEPARTMENT OFFICE
16 DIGITAL ART LABORATORY
17 DRESSING ROOM
18 ELECTRICAL ROOM / DATA ROOM
19 NOT USED
20 FOOTBALL STORAGE
21 GENERATOR ROOM
22 GYMNASIUM
23 HEALTH SUITE
24 KILN/GLAZE/PREPARATION ROOM
25 KITCHEN
26 LARGE TEAM/TESTING ROOM
27 LOADING DOCK
28 LOCKER ROOM
29 MECHANICAL ROOM
30 MEDIA CENTER
31 MULTIPURPOSE LABORATORY
32 MUSIC ROOM
33 OFFICE
34 OFFICE: ADMINISTRATIVE SCHOOL ASSISTANT
35 OFFICE: IB COORDINATOR
36 OFFICE: IB SECRETARY
37 OFFICE: SIGNATURE COORDINATOR
38 OFFICE: STAFF DEVELOPMENT
39 OFFICE: STAFF SUPPORT
40 PROJECT/COLLABORATION ROOM
41 RECEPTION, ADMINISTRATION SUITE
42 RESOURCE ROOM
43 SCHOOL SECURITY OFFICE
44 SCIENCE LABORATORY
45 SCIENCE PREPERATION/PROJECT ROOM
46 SEMINAR
47 SPEECH & LANGUAGE
48 STAFF ROOM
49 STORAGE
50 STUDENT DINING
51 TECHNOLOGY EDUCATION
52 TECHNOLOGY EDUCATION: APPLIED TECHNOLOGY LABORATORY
53 TECHNOLOGY EDUCATION: FOUNDATIONS OF TECHNOLOGY LABORATORY
54 TECHNOLOGY EDUCATION: INSTRUCTIONAL SPACE
55 TOILET
56 VESTIBULE (SECURE)
57 WORK ROOM
58 WRESTLING
9
48
9
51
44
19
49
33
55
9
44
55
9
45
49
9
9
ROOF
9
9
9
49
9
9
9
9
49
48
9
15
0’5’ 10’ 20’ 30’
50’
NORTH
Page 6G
Existing Fourth Floor Plan
PROJECT COLOR LEGEND
EXISTING
CLASSROOMS
SUPPORT SPACES
CORE FACILITIES
BUILDING SERVICES / MECHANICAL / ELECTRICAL
PROJECT SPACE LEGEND
1 ART ROOM
2 AUDITORIUM
3 AUXILARY GYMNASIUM
4 BOILER ROOM
5 CAREER CENTER
6 CERAMICS/SCULPTURE ROOM
7 CERAMIC PUG ROOM
8 CHILD DEVELOPMENT
9 CLASSROOM
10 COMPUTER LAB
11 CONCESSIONS
12 CONFERENCE ROOM
13 COUSELOR
14 DANCE ROOM
15 DEPARTMENT OFFICE
16 DIGITAL ART LABORATORY
17 DRESSING ROOM
18 ELECTRICAL ROOM / DATA ROOM
19 NOT USED
20 FOOTBALL STORAGE
21 GENERATOR ROOM
22 GYMNASIUM
23 HEALTH SUITE
24 KILN/GLAZE/PREPARATION ROOM
25 KITCHEN
26 LARGE TEAM/TESTING ROOM
27 LOADING DOCK
28 LOCKER ROOM
29 MECHANICAL ROOM
30 MEDIA CENTER
31 MULTIPURPOSE LABORATORY
32 MUSIC ROOM
33 OFFICE
34 OFFICE: ADMINISTRATIVE SCHOOL ASSISTANT
35 OFFICE: IB COORDINATOR
36 OFFICE: IB SECRETARY
37 OFFICE: SIGNATURE COORDINATOR
38 OFFICE: STAFF DEVELOPMENT
39 OFFICE: STAFF SUPPORT
40 PROJECT/COLLABORATION ROOM
41 RECEPTION, ADMINISTRATION SUITE
42 RESOURCE ROOM
43 SCHOOL SECURITY OFFICE
44 SCIENCE LABORATORY
45 SCIENCE PREPERATION/PROJECT ROOM
46 SEMINAR
47 SPEECH & LANGUAGE
48 STAFF ROOM
49 STORAGE
50 STUDENT DINING
51 TECHNOLOGY EDUCATION
52 TECHNOLOGY EDUCATION: APPLIED TECHNOLOGY LABORATORY
53 TECHNOLOGY EDUCATION: FOUNDATIONS OF TECHNOLOGY LABORATORY
54 TECHNOLOGY EDUCATION: INSTRUCTIONAL SPACE
55 TOILET
56 VESTIBULE (SECURE)
57 WORK ROOM
58 WRESTLING
Bethesda - Chevy Chase High School Addition
Smolen ■ Emr ■ Ilkovitch Architects ROOF
ROOF
ROOF
ROOF
ROOF
29
55
29
55
ROOF
9
9
9
46 49
9
9
57
9
9
9
49
46
15
33
0’5’ 10’ 20’ 30’
50’
NORTH
Page 6H
Proposed Fourth Floor Plan
PROJECT COLOR LEGEND
ROOF
EXISTING
CLASSROOMS
SUPPORT SPACES
CORE FACILITIES
BUILDING SERVICES / MECHANICAL / ELECTRICAL
ROOF
PROJECT SPACE LEGEND
1 ART ROOM
2 AUDITORIUM
3 AUXILARY GYMNASIUM
4 BOILER ROOM
5 CAREER CENTER
6 CERAMICS/SCULPTURE ROOM
7 CERAMIC PUG ROOM
8 CHILD DEVELOPMENT
9 CLASSROOM
10 COMPUTER LAB
11 CONCESSIONS
12 CONFERENCE ROOM
13 COUSELOR
14 DANCE ROOM
15 DEPARTMENT OFFICE
16 DIGITAL ART LABORATORY
17 DRESSING ROOM
18 ELECTRICAL ROOM / DATA ROOM
19 NOT USED
20 FOOTBALL STORAGE
21 GENERATOR ROOM
22 GYMNASIUM
23 HEALTH SUITE
24 KILN/GLAZE/PREPARATION ROOM
25 KITCHEN
26 LARGE TEAM/TESTING ROOM
27 LOADING DOCK
28 LOCKER ROOM
29 MECHANICAL ROOM
30 MEDIA CENTER
31 MULTIPURPOSE LABORATORY
32 MUSIC ROOM
33 OFFICE
34 OFFICE: ADMINISTRATIVE SCHOOL ASSISTANT
35 OFFICE: IB COORDINATOR
36 OFFICE: IB SECRETARY
37 OFFICE: SIGNATURE COORDINATOR
38 OFFICE: STAFF DEVELOPMENT
39 OFFICE: STAFF SUPPORT
40 PROJECT/COLLABORATION ROOM
41 RECEPTION, ADMINISTRATION SUITE
42 RESOURCE ROOM
43 SCHOOL SECURITY OFFICE
44 SCIENCE LABORATORY
45 SCIENCE PREPERATION/PROJECT ROOM
46 SEMINAR
47 SPEECH & LANGUAGE
48 STAFF ROOM
49 STORAGE
50 STUDENT DINING
51 TECHNOLOGY EDUCATION
52 TECHNOLOGY EDUCATION: APPLIED TECHNOLOGY LABORATORY
53 TECHNOLOGY EDUCATION: FOUNDATIONS OF TECHNOLOGY LABORATORY
54 TECHNOLOGY EDUCATION: INSTRUCTIONAL SPACE
55 TOILET
56 VESTIBULE (SECURE)
57 WORK ROOM
58 WRESTLING
DN
ROOF
Bethesda - Chevy Chase High School Addition
Smolen ■ Emr ■ Ilkovitch Architects ROOF
ROOF
ROOF
ROOF
ROOF
29
55
29
55
ROOF
9
9
9
46 49
9
9
57
9
9
9
49
46
15
33
0’5’ 10’ 20’ 30’
50’
NORTH
Page 6I
Existing Elevations
AUDITORIUM
East Facade
West Facade
North Facade
0’
Bethesda - Chevy Chase High School Addition
Smolen ■ Emr ■ Ilkovitch Architects 20’
40’
80’
160’
Page 7
Proposed Elevations
AUDITORIUM
East Facade
South Facade
West Facade
North Facade
0’
Bethesda - Chevy Chase High School Addition
Smolen ■ Emr ■ Ilkovitch Architects 20’
40’
80’
160’
Page 7A
Project Team, Schedule, and Estimated Construction Costs
Design Team Members
Architect:
Civil Engineer:
Structural Engineer
Mechanical, Electrical and Plumbing Engineers:
Smolen ■ Emr ■ Ilkovitch Architects
ADTEK Engineers
ADTEK Engineers
James Posey Associates
Project Schedule
Preliminary Plans Presentation:
Construction Documents Completed:
Award Construction Contract:
Project Completed:
October 2015
March 2016
July 2016
August 2018
Estimated Construction Costs
Existing Building:
Demolition
Renovation
New Construction:
Total
308,215
(3,710)
2,337
87,804
392,309
Construction Cost Estimate for Building and Site:
$32,000,000.00
Bethesda - Chevy Chase High School Addition
Smolen ■ Emr ■ Ilkovitch Architects square feet
square feet
square feet
square feet
square feet
Page 8