Worst of Times Brings Out Best in People Minnesota Water Operators Respond to the Floods of 1997 Everyone knew they were coming. But no one could anticipate the fury with which they would strike. The floods of 1997 left many cities in Minnesota reeling as they displaced residents and interrupted services. One necessity that persevered almost without fail, however, was a supply of potable water. It was through the heroic efforts of water supply operators in the affected communities— many of whom had their own personal tragedies to deal with—as well as a different type of flood, a flood of volunteers from all parts of the state, that allowed communities to carry on. It wasn’t that no one had prepared. Residents and city officials knew it was going to be a bad spring for flooding and did what they could to keep the waters back. The first cities threatened were those along the Minnesota River, where cresting was expected for the second week in April. But changing weather first moved up the predicted dates for the crest, then exacerbated attempts to fight it. Montevideo Montevideo residents felt everything was under control until noon on Thursday, April 3. It had been a pleasant week for weather—too pleasant as it turned out since it caused heavier than expected snow melts upstream. Not only would this cause the high waters to hit even sooner, it altered Fall 1997 Volume Five/2 This was a too-familiar scene in some parts of Minnesota last spring. the direction from which they would be coming. Byron Hayunga, the city’s utilities superintendent, said they thought the water would come down the Minnesota River—cresting at 21 feet, seven feet above flood stage—backing up the Chippewa River, which converges with the Minnesota River in Montevideo, against a spillway. But warmer temperatures to the northeast of Montevideo created a growing run-off into rivers and creeks that empty into the Chippewa River. “We were prepared for the Minnesota [River] side,” said Hayunga, “but when the weather turned nice to the north of us, it came down the Chippewa, sort of in the back door on us.” The utility had planned on beginning work on a two-foot-high dike to surround the pumphouse on Friday, April 4th, but news of the impending crest caused them to rush the process, completing the initial section on Thursday. “As we were Floods—Continued on page 2 Upcoming Certification Exam Dates October 7, Brooklyn Center October 29, Collegeville October 16, Marshall October 31, Blooming Prairie December 4, Fergus Falls See calendar on back page for more information Inside: School News PWS Profile Waterworks Quiz Floods—Continued sealed off the covers and overflows so if the water did come building the dike, we could see the river coming up,” Hayunga over, nothing would get in,” Opdahl said, adding that, “It was said, “so late afternoon on Thursday, I turned on one of the virtually impossible to seal it off totally.” wells by hand to keep the reservoirs full.” The water did reach the top of the clearwell on Sunday, The rush job on the dike was successful, but workers could April 6, tearing the plastic covering in many places. Opdahl see they weren’t done yet. Four feet were added on Saturcontacted Blomme at home and asked him to survey the day and another two feet on Sunday after word was received situation. Because of concerns over Cryptosporidium and that the crest would be two feet higher than expected. Giardia as a result of the infiltration, Blomme issued a boil “Montevideo went back to the pump station twice to build order, which remained in effect until April 16. the dike up,” said John Blomme, the Opdahl said they sampled Minnesota Department of Health constantly from the clearwell to (MDH) field engineer who serves the The majority of sandbagging was done monitor the turbidity levels and make area. “They realized on Saturday that in brutal conditions over the weekend sure there was adequate chlorination. the dike was still too small, so “The only thing that changed was the with two inches of rain on Saturday overnight they built it up again, barely followed by 50 mile per hour winds that turbidity reading in the clearwell,” he keeping it above the water.” The dike created a ground blizzard on Sunday. said, “but there was no detection of eventually consisted of three sections fecal coliforms in the samples from totaling eight feet in height. the distribution system.” The mild weather that accelerated the flood schedule didn’t As Montevideo and Granite Falls were hanging on, rising last. The majority of sandbagging was done in brutal waters were taking aim at other areas. conditions over the weekend with two inches of rain on Ada became the first Minnesota city to be almost fully Saturday followed by 50 mile per hour winds that created a evacuated on Monday, April 7. Nearly 75 percent of ground blizzard on Sunday. the 1,700 residents cleared out after two normally Montevideo’s water system remained operational, although shallow rivers overran the banks, spread overland, and poured a boil order was issued as a precaution. “Their overflow into homes. If that wasn’t bad enough, temperatures was taking on river water, so it was coming back through the plummeted overnight, creating additional damage as the system through the ground reservoir,” explains Blomme. water froze. “Their biggest problem with the water was that their The freezing weather actually brought relief to residents in overflow was in the water to begin with, so they never had a Ortonville as it eased fears that the Big Stone Lake dam, chance to get down and put a plug in it before the water rose. which controls the flow of water into the Minnesota River, They could bank up to keep the water out, but they couldn’t might wash out. find a way to plug the overflow, so it was taking on water.” However, in most cases, the nasty weather The boil order remained in effect for approximately ten days. worsened, rather than alleviated, already dire conditions. In Breckenridge, three inches of rain and snow that fell Granite Falls overnight on Sunday, April 7, overwhelmed dikes along the Meanwhile, a dozen miles downstream on the Minnesota Red River of the North and caused the evacuation of 400 River, volunteer crews in Granite Falls were underway with residents. similar efforts to save the city and retain services. The weekend storms not only interfered with their sandbagging The Crests Continue but also paralyzed travel in the area, making it difficult for Despite crest predictions that were being revised upward outside help to reach the city. Two neighborhoods in Granite on a daily basis for the Minnesota River at New Ulm, the Falls were evacuated as volunteers worked through the bad city’s water supply continued uninterrupted, thanks to a weather and continued on Monday when the weather cleared. strategic decision to take four wells out of service and Residents, National Guardsman, and out-of-town volunteers concentrate efforts on saving the other wellhouses. labored side-by-side, occasionally gazing skyward to marvel “Based on our demand at that time of the year, we at Comet Hale-Bopp, with their work resulting in 500 didn’t need those wells,” said the city’s water/steam yards of 12-foot levees along Minnesota Avenue and distribution supervisor, George Brown. With the help shorter dikes lining Prentice Avenue across the of the National Guard, crews from the water utility used boats Minnesota River. to sandbag the wellhouses over the weekend of April 6-7. Although the city had been saved, fears over Brown said they remained in regular contact with MDH contaminated drinking water had already led to the issuance engineer Mark Sweers, who twice visited the site, and of a boil order. Blomme emphasized that the boil order was determined there was no need for a boil order. By mid-week, a precautionary measure and not the result of any positive the situation with the water supply had stabilized, and samples. Water superintendent Darrell Opdahl explained that National Guard personnel shifted their efforts to the city’s they were mainly concerned with their clearwell, which is main levee, which was undermined and in danger of failing separated from the river by a retaining wall. Opdahl recalls on Wednesday, April 9. Two hours of furious sandbagging a devastating flood in 1969 when flood waters lapped at the sealed the breach. edges, but did not reach the top, of the clearwell. With that in The same energy was being expended farther north, in the mind, Opdahl and his crews did what they could to protect North Dakota and Minnesota cities adjacent to the Red River the clearwell. “We wrapped the whole thing in plastic and of the North. 2 The efforts increased in Moorhead and Fargo as an ice jam 20 miles downstream (to the north) prompted revisions of earlier forecasts that the river would crest at 6-12 inches below levees to a prediction that the crest would end up 6-12 inches above the levees. Residents who thought they had completed their sandbagging duties were back at it again to raise the dike by another foot. They completed their task, only to learn that an iced-up gauge in the river had overestimated the height of water moving toward the cities, making the final surge of sandbagging unnecessary. Despite this experience, those in the next cities to feel the brunt, East Grand Forks and Grand Forks, were not about to underestimate what was coming. Volunteers worked without interruption to keep the Red River, as well as the Red Lake River in East Grand Forks, within the confines of their growing walls of sandbags. They had been fighting the valiant battle since late March and had persevered through the same brutal storms that had hampered other communities the first weekend of April. However, this was to be a case where even a maximum effort turned out to be not enough. East Grand Forks On Friday, April 18, the Red River of the North turned into a lake as it overcame dikes, leaving vast devastation on both sides. A mass evacuation of East Grand Forks began as most of the city was soon to be underwater. Among those leaving were three water utility workers from Thief River Falls, Allen Lamm, Steve Hams, and Wayne Johnson, who had come down to check on the conditions at the East Grand Forks water treatment plant. Since the afternoon of Thursday, April 17th, they had staffed dike flood pumps, providing relief to exhausted East Grand Forks personnel. By late Friday evening, the pumps were all under water. “The drive out of town was eerie,” recalls Lamm. “Flood water was 18 inches deep in the street. We had to guess where the street actually was.” Exhausted and angry as the river chased them out, the trio swore to come back—with an army. One week later, the army arrived: volunteers from all over the state, coordinated through an effort of the Minnesota Section of the American Water Works Association (AWWA). In between, much happened at East Grand Forks as plant operators worked midnight to midnight shifts, putting aside personal issues (many of these workers lost their own homes) and focusing on continuing to serve their community. While Lamm, Hams, and Johnson were dealing with the pumps, a thinning East Grand Forks crew had worked well into the evening of April 18, erecting a ring dike around the water plant. In addition to utilities general manager Dan Boyce, water plant superintendent Gary Hultberg, and operators Mike Weisinger and Sterling Bottomley, the group included Jeff Olson and Todd Grabinski, who worked with the city’s electrical utility and water distribution. Olson had been recruited to help with water supply during the emergency, and he, in turn, recruited others. One was a friend, Mike Coauette, who had been doing a lot of voluntary sandbagging through the city. Coauette came over to help with the efforts at the water plant that night and has been there ever since. He continues to work on an emergency disaster basis through the Federal Emergency Management Association and hopes to secure full-time employment with the utility in distribution. 3 Dan Boyce and Mike Weisinger check on the ring dike protecting the East Grand Forks water treatment plant. Meanwhile, Dave Ebertowski, the utility’s lone distribution crew member, was ferrying sandbags around town on a forklift in an effort to protect reservoirs and other components of the distribution system. Attempts to maintain water service were abandoned on Monday, April 21, as it was no longer possible to maintain pressure on the system. “We could not hold pressure in the system,” says Hultberg. “The water was going out through leaks as fast as we were putting it into the system.” The initial assessment was that severe watermain breaks were the culprit, but when crews sought to find and isolate the breaks over the coming days, they found that the mains were in good shape. The problem was elsewhere, according to operator Brian Johnson. “The reason we lost the pressure was that we couldn’t hold water in the towers anymore because the vast majority of services into the houses had broken out when the water heaters floated and ripped the plumbing out.” Even though the utility was producing approximately 1,300 gallons per minute of water, it was unable to keep up with demand. With operations suspended, the focus shifted to saving the plant itself. The sandbagging efforts paid off as the structure remained dry and served as a haven, as well as a rallying center, for the comeback. The flood water finally began to recede on Tuesday, April 22, but by this time, few people were still around. “It was a strange feeling being out at that time,” recalls Randy Rapacz, one of the operators who stayed to continue working on the utility, even though his own home had been completely submerged. “There was no traffic in town. Everything was shut down, and the only people there were emergency personnel.” No-wake restrictions were in place for the few boats and vehicles in the city to keep the water from sweeping away sandbags that were protecting emergency locations as well as the water plant. The water plant resumed operations on Friday, April 25. By this time, Jim King, the city’s water and light distribution superintendent, had made the decision to handle electrical service while delegating water restoration to others. Boyce and Hultberg concentrated on operations while Jeff Olson was left to oversee distribution. “It was more than I could fathom,” Olson said of the task facing him. However, he ended up with help in the form of the army that Lamm had promised. Floods—Continued on page 4 and disinfect the reservoir, which could have taken several On Saturday, April 19, the morning after Lamm returned days.” home, he had begun making phone calls around the state, Before dealing with the Point, though, the volunteers only to find that many others in the water industry were began isolating a line extending north to the city’s main water doing the same thing. Gerald Mahon, the public works tower. “Our first priority was the restoration of fire director for St. Cloud, was instrumental in organizing the protection,” said Lamm, who oversaw the volunteers. “Once effort, taking the names of those willing to pitch in, and we had this line isolated, we began filling it. We spent twocoordinating the logistics of getting help to East Grand Forks. and-a-half days trying to keep that line isolated in addition to The response was overwhelming. isolating sections of the neighborhood During the final week of April, a cadre where there was water leaking of volunteers from 11 Minnesota through into the areas we didn’t want cities—Mary Hiber and Dan Ludden it to be in. Once that was done, we of St. Paul; Joe Munn of Crookston; kept spreading through the system, Lyle Stai and Dale Segler of Willmar; taking one section at a time and Jeff Knutson and Dave Olmanson of pressurizing it with heavily chlorinated St. Peter; Jim Sweeney and Dan water. By the time the north half was McManus of Inver Grove Heights; done, the flood water had receded Paul Kuehn, Jeff Beilke, and Marv from the Point, allowing us to Stueber of New Ulm; Ron Woolery continue there. By May 1, we had and Rich Winkels of St. Cloud; Pat restored fire protection to 90 percent Conrad and John Violett of of the city.” of the volunteers, Jim Roskos of Rochester, Bloomington; Wylie Rindels and Jim One Cole explained the process in celebrated his 50th birthday while helping out in Roskos of Rochester; John Thom and East Grand Forks. detail. “Street valves to branch mains Bill LaLonde of Richfield; and Terry all had to be shut off. After they Rewertz, Lamm, Johnson, and Hams of Thief River Falls— started charging the branch watermains, we could loaded trucks with equipment and headed for East Grand determine where there was plumbing damage. At those Forks, not sure of where they would stay, not sure of how places, we shut the curb stop off. We worked from hydrant they would eat, not sure of what would be facing them. The to hydrant, bringing the chlorinated water down to one, then one thing they were sure of was that the community needed moving on to the next one, opening and closing street valves help. to control the flow of water.” In addition to the utility workers, Larry Cole, an MDH After dealing with the line going to the main tower to district engineer, moved into the water plant on Friday, April the north, the volunteers branched out into a residential 25th, and made it his home (Cole and the other temporary area between U. S. Hwy. 2 and the water plant, then residents dubbed their quarters the “Hultberg Hilton” after down toward the business district. The crews tracked their the city’s water plant superintendent) for two weeks, taking progress on maps on the wall at the treatment plant. a one-day break in the middle of the ordeal when he was “At the end of each day, everyone came in and marked spelled by fellow MDH engineer Dave Schultz. Cole and what he or she had gotten done on the map,” said Lamm. Schultz had already been up to the area, in Schultz’s “That way, everyone knew what was completed and what airplane. On Tuesday, April 22, the two had flown over the we had left to do.” area, taking videos that proved to be helpful in determining The volunteers marveled at the energy of the 62-year-old whether reservoirs in East Grand Forks, as well as in towns Ebertowski, who worked long hours in the field, helping the and rural water systems to the north, had been flooded and crews with locating valves and meters. Back at the plant, would have to be disinfected. Terry Spear and Veronica Kostrzewski staffed the phones, The information was valuable, particularly in the case of a which rang continuously, dealing with callers as well as two-million gallon underground reservoir on an area known in-person visitors for both water and electric issues. “These as the Point, a finger of land between the Red River and the two women dealt with distraught customers with Red Lake River, in East Grand Forks. Cole said, in addition compassion, firmness, and professionalism,” Lamm added. to the visual inspection, they took bacterial samples, which “Their’s was probably the toughest job of all.” were negative, and chlorine samples, to ensure that the waFollowing restoration of fire protection, the focus shifted ter still had an adequate residual. They also studied plans to to the potability of the water (a boil order was in effect see if flood water could have backed into the overflow. “We during this period). Virtually all of the more than 400 samples measured down to the water level, measured the invert taken were negative. The areas that produced positive elevation of the overflow, and found the water was three samples were kept isolated and dealt with separately. inches below the overflow,” said Cole, “so we could “Once everything tested clean,” said Lamm, “we went determine that the water hadn’t come into the overflow and back through and started the process again. The plant made backed into the reservoir—and it obviously hadn’t come in the changeover from free residual chlorine to a chloramine, the vent structure or the access manhole. which is what they normally use. “This [knowledge] saved a lot of time since we could save “We worked through the whole system, flushed it all out the two million gallons and begin flushing the Point area with again, until we had it all the way through, and then started this water rather than having to waste the water, then clean sampling again.” Floods—Continued 4 of treating its water, which it did after bringing in reverseosmosis package plants. Communication, with each other and returning residents, was a key part of the recovery—but, like almost anything else during this time, it wasn’t easy. “Communications were difficult if you used anything other than a portable radio or walkie-talkie,” said Olson. “It was virtually impossible to call in or out of the plant. Cellular phones weren’t much better; the circuits were usually tied up by mid-morning.” The city issued press releases and public service announcements, informing residents about the utility’s efforts to restore fire protection by pressurizing watermains. Since this meant that homes with broken plumbing could experience additional flooding, residents were asked to see if they could safely turn off water at their meter, then tie a rag to the front door as a signal to crews who were attempting to close curb-stop valves in the most affected areas. Lyle Stai of Willmar says during his two weeks in East Grand Forks, he operated more than 250 curb stops, either turning them off or turning them on. Mud and debris left behind after the water receded interfered with the simplest tasks. The mud was at first slippery, impeding footing while working on a curb stop. Within days, though, the mud had turned to dust that blew into eyes and noses. But what hit Stai the hardest, at least initially, was the smell of sewage. “It smells and stinks,” he noted while in East Grand Forks. “Man, does it smell around here. You get it [the smell] on your hands, on yourself, but you get used to it.” Despite the tough conditions, the crews kept their spirits up. “Today will be better than yesterday” was the motto— coined by Spear and Kostrzewski—that was posted on the front door of the water plant. Another message appeared after the Grand Forks Herald had a large headline stating, “We’re Coming Back.” The East Grand Forks utility workers responded with a sign proclaiming, “We’re Still Here. We Never Left.” The mottos helped, as did maintaining a sense of humor, according to Steve Hams of Thief River Falls. “It was a drastic situation, and we used a lot of humor to help us get through it,” he says. “We did a lot of joking around while still working hard.” “It was amazing the help we had,” Jeff Olson said of the volunteers who came to help. “We got the best of the best, and we really appreciate what AWWA membership stands for now.” The struggle goes on as cities continue the difficult recovery stage. For some, the worst may still not be over. But the memories of last spring’s battles between people and nature will never be forgotten by anyone involved. All who lived through the floods of 1997 have their own enduring impressions. Lyle Stai’s everlasting memory will be the people of East Grand Forks. “They were beat up so many times by the weather, from the snow and sleet storms to the flood. Yet they were the nicest people you would ever think of working for.” Stai added that his two weeks in East Grand Forks were “the most phenomenal thing I have done in my 26 years working for a utility. Now, looking back on it, I wouldn’t have traded it for anything in the world.” Mary Hiber of St. Paul flushes and tests a main line near the north tower. On Friday, May 9, the final samples proved to be clean, and, at 4:00 in the afternoon, the boil order was lifted. Much work remained for the devastated city, as well as the utility, but the water supply had survived with minimal interruption. It was a remarkable feat in itself, but while dealing with its own crisis, East Grand Forks was able to help its North Dakota neighbor by providing water to Grand Forks, thanks to an interconnection between the two cities that had last been used in 1986. “The first two days the East Grand Forks plant was back in operation [April 25 and 26], maintenance staff were pulling the pump motors and contactors of the transfer station on the Point so we could establish the connection to put water into Grand Forks,” explained Cole. Beginning shortly after midnight on Sunday, April 27, the flow between the cities began, continuing for about three-and-ahalf hours, long enough to allow Grand Forks to purge the air from its lines and get the plant operating again by the next day. Residents returning to East Grand Forks were grateful for the efforts of the volunteers, but there was occasional rancor. Any break in operations was expensive for American Crystal Sugar, a large sugar beet producer and a heavy water consumer. However, fire protection and other priorities had to be taken care of before the business community could again be served. “They wanted to resume operations and needed water,” said Lamm, adding that he could understand their anxiety. However, Lamm began feeling pressure when the company sent an official to city hall, urging the city leaders to restore water to the facility. The situation changed, however, when American Crystal Sugar management met personally with Lamm, who showed them the progress maps and flow charts of the restoration plan. “When they understood the extent of the damage and contamination,” Lamm said of American Crystal Sugar, “they offered the full resources and cooperation of their organization. They became team players.” Jeff Olson explained another concern with American Crystal Sugar. “They put out an edible product. All their processing needed water that was potable.” The water utility finally began charging American Crystal’s fire lines after being assured that the factory had the means 5 PWS Profile John Schnickel alter plans to sleep on a beach when he learned a curfew was in place because of guerilla activity. In 1984 John became the Director of Environmental Health for the city of Minneapolis. His work was diverse; he was involved in or oversaw food and beverage regulations, animal control, housing sanitation, water sampling, pest control, and recycling. For a brief time following this, he headed MDH’s food, beverage, and lodging program and then conducted indoor-air quality investigations for a private consulting firm. John has been diagnosed with lymphoma and has maintained his goal to have his life be the dominant force in overcoming the disease rather than have the disease be dominant in ordering his life. He has finished six months of chemotherapy and now looks ahead to radiation. John says the treatment results have been positive although he is unsure of his next hairstyle. He adds that the thoughts, cards, and prayers he received were important to him, and that he is grateful that he did not ignore a minor but slightly unusual symptom, a pinpoint sore throat, since this brought about an early diagnosis to the lymphoma. “See a doctor when you know something is wrong,” is his advice. Although not admitting to a belief in astrology, John feels his personality is reflected through his Gemini sign. His quiet side is revealed through his love of classical music. In addition, John is a season-ticket holder for the Minnesota Orchestra, Children’s Theater, and Guthrie Theater. He also meets weekly with the oldest active winetasting group in the state. Sports reveal his active side. He especially enjoys downhill skiing, white-water canoeing, and bicycling. John and Susan have now been married for 25 years; Andrew is 18 and Benjamin 15. Andrew challenges himself phyically while Benjamin is the artistic child, displaying a love of acting that has brought about performances at the Children’s Theater, Guthrie Theater, and at his high school. John is the Health Department Program Coordinator for the Drinking Water Revolving Fund and enjoys working with the enthusiastic and creative staff on the program that, in his words, “have don an excellent job in establishing the groundwork for the program.” This is a return to MDH for John. Soon after graduating from the College of Biological Sciences at the University of Minnesota in 1969, he joined the Food Beverage, and Lodging program at MDH, first performing inspections, then coordinating development of local programs and agencies around the state. During this stint, John took a leave of absence to work on a massive project in Saudi Arabia. A new city/port facility was being built on the Red Sea at the terminus of a cross-country oil pipeline. John developed the environmental health program for the project and worked to ensure the quality of the food and water. He reviewed blueprints, established standards, and performed inspections. John says that living and working in Saudi Arabia was an incredibly useful experience. “It really gave me the chance to put to use all that I had learned about environmental health.” While others did not enjoy the extreme heat (with humidity, John adds) and remoteness of life in Saudi Arabia, John and his wife, Susan, focused on the positive aspects of it. Traditional winter sports were out, but they had the chance for some fantastic diving in the Red Sea. They also did a great deal of traveling, along with newborn son Andrew, from their Saudi base. By the time Andrew was three, he had been to Victoria Falls, Mount Everest, the Great Pyramids, and the Taj Mahal. Before moving back to the United States in 1982, John and Susan had another son, Benjamin. Overall, John has been to 30-35 countries but claims his timing in visiting various destinations has been suspect. For example, he was staying a half-block away from a presidential palace when a coup took place, he was a block away from a terrorist bombing, he was mistaken for someone and shot at by riot police as a result, and he had to 1997 Ten States’ Standards Now Available The Recommended Standards for Water Works (Ten States’ Standards) 1997 Edition came out at the end of August and is available by calling Health Education Service at 518/439-7286. The Ten States’ Standards, which is revised every five years, are a valuable resource for both engineers and water operators. APO Issued A forgivable administrative penalty order (APO) was issued last March to Tamarack Court Mobile Home Park, PWS 1730058, for failure to submit lead, copper, bateriological, and nitrate samples. The system did not respond, and the matter was turned over to the attorney general’s office for collection on June 24, 1997. Waterworks Quiz 1. Vertical-turbine pumps that are used in wells may be oil lubricated or water lubricated. Operators should use extreme care not to start any water-lubricated pump before making sure that: a. the bearings are dry. b. the bearings are wet. c. the valve on the discharge side is closed. d. the valve on the suction side is closed. 2. The letters or units “gpm” appearing on a flow-rate indicator in a pumping station means: a. Gallons Per Man. b. Gallons Per Mile of sewer line. c. Gallons Per Minute. d. Gilbert Puked in the Malt. BONUS QUESTION Translate: Scintillate, scintillate asteroid minific. Answers on page 7. 6 The Northwest Water Operators’ School will be held at the Best Western in Fergus Falls from Tuesday, December 2 through Thursday, December 4. The agenda includes an operator breakfast with business meeting (at which a Vice Chair and Director will be elected), product exposition, hands-on workshops at the Fergus Falls Water Treatment Plant, and a panel discussion on last spring’s floods. Registration is $65 ($80 at the door or after November 21). A block of special-rate guest rooms is being held by the Best Western until November 18. Call 1/800/293-2216 and mention the Water Operators to reserve a room. A slew of one-day schools are being held throughout the state this fall. Information on registration is contained at the bottom of the form below with phone numbers for contact people in the Calendar on the back page. 1998 Metro School The 1998 Metro School will be at the Thunderbird Hotel in Bloomington from Wednesday, April 1 through Friday, April 3. An Exam Prep will be held at the Crystal Community Center on Monday, March 23. Registration information will be available in the Winter 1997-98 Waterline with a complete agenda for the school in the Spring 1998 Waterline. 1997-98 AWWA District Officers Northeast District Chair—Floyd Nelson, Hoyt Lakes Vice Chair—Tom Sakry, International Falls Director—Jack Olin, Duluth Central District Chair—Bill Spain, St. Cloud Technical College Vice Chair—Gary Peters, Wadena Director—Dave Schultz, MDH Secretary—Allen Anderson, Thein Well Co. Metro District: Dave Peterson of Brooklyn Center has replaced Mike Lauseng as Vice Chair. Answers to Quiz: 1. b 2. c Bonus Question: Twinkle, twinkle little star. Operator School Training News REGISTRATION FORM You may combine multiple fees on one check if more than one person is attending a school; however, please make a copy of this form for each person. Questions regarding certification, contact Karla Peterson at 612/215-0761. Questions regarding registration, contact LeAnne Workcuff at 612/215-0787. Northwest School, December 2-4, 1997, Best Western, Fergus Falls. Fee: $65 ($80 after November 21 or at the door). Check here if you would like to receive an exam application. (Applications must be submitted at least 15 days prior to the exam.) Check here if you would like to receive a study guide. If you have any special dietary needs, please indicate them here: Please print: Name Address City Zip Day Phone Employer Please enclose the appropriate fee. Make check payable to Minnesota Department of Health. Mail this form and fee to Public Water Supply Unit, Minnesota Department of Health, 121 East Seventh Place, Suite 220, P. O. Box 64975, St. Paul, Minnesota 55164-0975. Registration for the following schools must be sent to the person listed: October 7, Suburban Utilities Superintendent’s School, Brooklyn Center Civic Center. Fee is $20. Send to John Hill, Crystal Utilities, 4141 Douglas Drive North, Crystal, Minnesota 55422 (checks payable to SUSA). October 16, Southwest School, Best Western Marshall Inn. Fee is $20 ($25 at the door). Send to Mark Sweers, Minnesota Department of Health, 410 Jackson Street, Suite 150, Mankato, Minnesota 56001 (Checks payable to Minnesota AWWA). October 29, Central Minnesota School, St. John’s University, Collegeville. Fee is $25. Send to Duane Johnson, St. Cloud Public Utilities, City Hall, 400 2nd Street South, St. Cloud, Minnesota 56301 (checks payable to Minnesota AWWA). October 31, Southeast Minnesota School, Blooming Prairie. Contact Paul Halvorson, 507/285-7289. 7 CALENDAR Minnesota Section, American Water Works Association Annual Conference, September 24-26, Holiday Inn, Detroit Lakes, Contact Jim Haugen, 612/489-1051 *October 16, Southwest Waterworks Operators’ School, Best Western Marshall Inn, Marshall, Contact Mark Sweers, 507/389-2501 *Northwest Waterworks Operators’ School, Best Western, Fergus Falls, December 2-4, Contact Stew Thornley, 612/215-0771 *Suburban Superintendents School, October 7, Brooklyn Center Civic Center, Contact John Hill, 612/531-1166 Teleconferences Contact Jodi Bening, 612/591-5433 November 13, Public Involvement Minnesota Rural Water Association Contact Kyle Kedrowski, 218/685-5197 September 10, Barnum, Distribution Operations and Maintenance September 17, Luverne, Wells— Pumps and Meters October 8, Pine Island, Meters/Leak Detection October 22, Biwabik, Operations and Maintenance *Southeast MinnesotaWaterworks Operators Association(SEMWWOA) Contact Paul Halvorson, 507/2857289 October 31, Blooming Prairie *Central Minnesota Waterworks Operators’ School, October 29, St. John’s University, Collegeville, Contact Duane Johnson, 320/255-7225 Minnesota Pollution Control Agency (Wastewater Operator Training) Contact Emily Armistead, 612/296-7251 September 16-17, Land Application of Biosolids Seminar, Holiday Inn, Willmar September 23-25, Wastewater Treatment Technology Seminar, Grand Rapids October 29-31, Collection System Basics, Maplewood Inn November 4-6, Land Application of Biosolids, Holiday Inn, Brainerd November 18-20, Land Application of Biosolids, Best Western Garden Inn, Mankato December 10-12, Wastewater Treatment Technology Seminar, Maplewood *Schools/meetings marked with an asterisk include a certification exam Waterline Published quarterly by the Public Water Supply Unit of the Minnesota Department of Health Editor: Stew Thornley Waterline staff: Dick Clark, Marilyn Krause, Cindy Swanson, Doug Mandy To request this document in another format,call 612/215-0700; TDD 612/215-0707 or toll-free through the Minnesota Relay Service, 1/800/627-3529 (ask for 612/215-0700). Minnesota Department of Health 121 E. 7th Place Suite 220 P. O. Box 64975 St. Paul, Minnesota 55164-0975 ADDRESS CORRECTION REQUESTED
© Copyright 2026 Paperzz