Minnesota Leads the Way in CCR Compliance Underway in Virginia The first Consumer Confidence Reports (CCR) were due on October 19, and the Minnesota Department of Health (MDH) by that date had received a report from more than 875 of the 957 community water systems in the state. Although it’s not 100 percent, we believe it is as good as any. The MDH is continuing its efforts to get reports from the remaining systems. Systems that don’t turn in a report will be issued a Notice of Violation and reported to the Environmental Protection Agency’s Safe Drinking Water Information System. Overall, the reports were done well although a few reports contained portions that were not done correctly. However, unless the errors and omissions were blatant, MDH chose not to reject the reports this year. The MDH will be contacting these systems and letting them know of the corrections that will need to be made on next year’s report. There were some problems that were common to several reports. For example, some systems listed the table of detected contaminants along with all the contaminants that were not detected. This is not allowed. Nondetections can be listed, but they must be in a separate table from the detections. A common problem with distribution dealt with the systems that had the option of publishing the report in the newspaper rather than individually distributing it. If this option is used, the entire report must be published along with a notice that a copy of the report is available to anyone who requests it. Some systems published only a summary of the report with the notice of its availability. This does not satisfy the requirement. (Note: systems serving populations of 500 or fewer do have the option of merely publicizing the availability of the report; however, systems serving a population between 500 and 10,000 must publish the report in its entirety if they choose to follow this option in lieu of individual distribution.) After the report has been distributed, a water system must send a copy of the report along with the completed certification form to MDH. Some systems sent only one or the other. Both are needed before the system is in compliance. Work proceeds on a new filtration building for the water treatment plant in Virginia, Minnesota, part of a $6-million project to upgrade the city’s water system. See the full story on page 4. Upcoming Certification Exam Dates March 9, St. Cloud March 30, Rochester April 7, Bloomington April 20, New Ulm May 12, Two Harbors June 16, Deerwood See calendar on back page for more information Consumer Confidence Reports—Continued on page 6 Winter 1999-2000 Volume Seven/3 Inside: News on the Drinking Water Academy Contact Hours Primer Drinking Water Message Center School News Radium Over $75 Million in DWRF Projects Awarded to Date Where Are We Now? By Karla Peterson By John Schnickel I’m sure most of you have heard the history behind On July 17, 1998 the city of Fulda was awarded the first compliance with the radium rule (old hat). So here’s the drinking water revolving fund (DWRF) loan. It was for a latest on the supplies that are currently working to comply new well and the replacement of loop existing watermains. with the maximum contaminant level (MCL). Now over $75 million in loans have been awarded to As of October 1999, 12 public water supplies have approximately 45 water suppliers. Additional loans are exceeded the MCL for combined Radium 226 and 228. These being awarded each month. supplies will remain on quarterly monitoring until the Initial proposals were evenly distributed among water combined Radium 226 and 228 is consistently and reliably supply, treatment, storage, and distribution projects. below the MCL. This means the supplies will need to optiTreatment plants, however, are being constructed at a mize existing treatment, develop new treatment, or disconsignificantly higher rate than other projects. Distribution tinue use of the well(s) that caused the exceedance. projects, on the other hand, are being constructed at a lower The 12 supplies are similar in that all are located in eastrate. central Minnesota; aquifers with exceedances include the The very good news is that 71 percent of the high priority Mt. Simon, Hinckley, Dresbach, Jordan, and Sioux Quartzite. projects initially submitted to MDH are either in the If your supply fits the above criteria for suspect wells, construction stage or have been completed. Not all of these you should learn about the proposed revision to the projects are receiving DWRF funding, but the fact that so Radionuclides Rule and how it may affect you. The many major problems are being addressed, whatever the proposed Radionuclides Rule is not available yet, but here funding source, is comforting. are a few significant changes that the U. S. Environmental The most expensive project funded through the Protection Agency may include: DWRF was a $16.5-million St. Paul chemical handling and storage facility. The smallest project was for Lynd’s 1. The distribution sampling point may change to an entry point sampling point. As a result, many more $28,976 emergency electrical generator. No loans have supplies will exceed the MCL. Those supplies that have been made to private water systems. Most have been made benefitted from blending within the distribution system, to municipalities and some to utilities and water system boards. knowingly or unknowingly, will no longer be able to do so. Future DWRF loans will be scaled back to $20 to 25 You’ll want to keep this in mind when constructing a new million per year to match the more limited money that will well or when building or rehabilitating a treatment plant. become available. Lending criteria will be much more Uranium may be added to the list as a contaminant. selective, but water suppliers are still encouraged to submit 2. It won’t be known what the MCL may be until December proposals for the project priority list. Other lending agencies 2000, but keep in mind that the deeper aquifers are sometimes use the list to help determine their priorities. suspect. When considering treatment options, realize that some of the options used for the removal of radium will Research Needs not remove uranium. and MDH Support Several treatment options are available to supplies. Fortunately for those supplies that currently have iron/ Public water supplies that are interested in conducting manganese filtration, it may merely be a matter of research may contact the Minnesota Department of Health optimizing existing treatment. In fact, some iron/manganese for assistance with sampling analysis needs. The research filtration plants are removing 19 to 63 percent of Radium 226 must be of interest to MDH and applicable to other public and 23 to 82 percent of Radium 228 (and that’s without water supplies in Minnesota. optimization). The proposals, which should be submitted by the water If a supply chooses to optimize iron/manganese filtration system, will be reviewed on a case-by-case basis. Funding to remove radium, it has several different options. These is limited and should be taken into consideration. The include improving pre-oxidation with aeration or chemical research results will be submitted to MDH in a format that is addition, feeding manganese sulphate or hydrous manganese useful to other water systems (such as a short summary of oxides, increasing detention time for potassium results, a paper, or a poster). For more information, contact permanganate, and using a different filter media to improve Lih-in Rezania at 651/215-0763 or Karla Peterson at 651/ removal efficiencies. 215-0761. In addition, other treatment alternatives include lime softening, ion exchange, Waterline membrane filtration, and electrodialysis Published quarterly by the Drinking Water Protection Section reversal. of the Minnesota Department of Health If you have any questions about Editor: Stew Thornley radium removal or if you would like to To request this document in another format, call 651/215-0700; obtain a manual on treatment TDD 651/215-0707 or toll-free through the Minnesota Relay Service, technologies, please contact me at 651/ 1/800/627-3529 (ask for 651/215-0700). 215-0761. 2 Contact Hours Primer Fun at the Fair By Cindy Cook Are you confused about your certificate renewal hours? You’re not alone. We’ve been getting many calls from operators who aren’t sure how to renew their water or wastewater certificate. To put it simply, if you want to keep your operator certificate, you need to earn renewal contact hours. One of your responsibilities as a certified operator is to demonstrate professional growth by attending approved water and wastewater industry-related training to acquire contact hours within a three-year period. Your certificate expires three years from the date of issue. About a month before your certificate expires, you will receive a renewal notice in the mail. You must fill in the name and the date of the course(s) you attended during the past three years. It is also your responsibility to make sure you receive and return the renewal to the certification office, along with a $23 renewal fee. At least 50 percent of renewal contact hours for your water certificate must be direct water operations training, and at least 50 percent of the renewal contact hours for your wastewater certificate must be direct wastewater training. The other training hours may be indirect hours from disciplines closely related to the profession such as safety training, laboratory courses, and pre-approved vendor training programs. For example, if you have a Class D water certificate, you will need 8 total hours to renew your water certificate. You must have at least 4 hours from direct water training to renew your water certificate, but the other 4 hours may be from indirect hours such as safety or wastewater courses. If you have a Class D wastewater certificate, you will need 8 total hours to renew your wastewater certificate. You must have at least 4 hours of direct wastewater training to renew your wastewater certificate, but the other 4 hours may be from indirect hours such as safety or water courses. Operators cannot use the same contact hours to renew both their water and wastewater certificate. For example, if you have a Class D water and a Class D wastewater certificate, you will need 8 hours to renew your water certificate and 8 hours to renew your wastewater certificate, or a total of 16 hours to renew both. Renewal hours required for each water and wastewater operator certificate: The Minnesota Section of the American Water Works Association was again on hand at the Minnesota State Fair, offering free water to fairgoers as well as information on drinking water. The fountain was a hit as fairgoers sucked up more than 11,000 gallons of water. In addition to the drinking fountain, the AWWA booth had a couple of posters showing water towers from around Minnesota. Drinking Water Academy Takes Off Amendments made to the federal Safe Drinking Water Act (SDWA) in 1996 created many new opportunities. Along with those opportunities, however, came new responsibilities for states and the U. S. Environmental Protection Agency (EPA). In response to the issues that will require attention because of the new provisions within the SDWA, the EPA’s Office of Ground Water and Drinking Water created the Drinking Water Academy (DWA), a long-term training initiative intended to expand EPA’s capability to support states and other organizations as they implement the 1996 amendments to the federal Safe Drinking Water Act. The Drinking Water Academy will assist the EPA, states, and tribes to build the capability within their programs to carry out the SDWA, which will, in turn, promote increased program compliance and greater public health protection. The Academy will use a curriculum to meet the training needs of the Public Water System Supervision (PWSS), Underground Injection Control (UIC), and Source Water Protection programs. The Academy is initially focusing on EPA staff. After the training program has been developed, the training audience will be expanded to include states, tribes, and industry. The Academy consists of three major components: • Training courses, developed by regulatory implementation teams to be under the stewardship of the DWA • Training materials, including a DWA reference handbook • A web site, an electronic clearinghouse for SDWArelated training resources The DWA has developed and pilot-tested courses on the Safe Drinking Water Act and Source Water Protection as well as introductions to the UIC and PWSS programs. The courses are modular in structure and may be used together or as stand-alone courses. For more information, check the Academy’s web site at: http://www.epa.gov/safewater/dwa.html. Class A—32 contact hours Class B—24 contact hours Class C—16 contact hours Class D—8 contact hours The American Water Works Association (AWWA), Minnesota Rural Water Association (MRWA), and the Minnesota Pollution Control Agency (MPCA) have developed training courses that are offered several times a year throughout the state. For more information about training sessions or renewal hours, call the appropriate certification office. Wastewater operators may contact Dianne Navratil at the MPCA at 651/296-9269. Water operators may contact me at 651/215-0751. 3 Virginia Gets an Upgrade Although its water system, including the treatment plant, has characteristics of a groundwater system, the city of Virginia—in the heart of Minnesota’s Mesabi Iron Range—gets its supply from a surface source. Like many other Range cities, Virginia draws its water from an abandoned mine pit. Originally, the surface-water source came from the dewatering process when the mine was in operation; in the ensuing years, as the mine stands dormant and mine pumping has stopped, the level of the water in the pit has risen significantly. Instead of a standard intake to draw the water, the city has drilled vertical wells and a horizontal shaft within the taconite bluffs to reach the water. In essence, wells are used to take the water from the surface source. “I look at it as exposed groundwater,” says Mike Appelwick, the executive vice president of Northeast Technical Services of Virginia, which operates the city’s water system on a contract basis. As for the plant, which has pressure filters, it was designed for groundwater. That’s changing now as major upgrades are underway that include the replacement of the pressure filters with gravity filters. Two 12-Inch Supply Lines to Water Treatment Plant New Pumphouse Elevation: 1,416’ New Drilled Wells Virginia gets its water from the Missabe Mountain Pit History of Virginia Water Supply A series of wells served the community in the early part of the 20th century. When the wells started to lose productivity in the mid-1920s, the city made a connection to the Oliver Iron Mining Company’s drainage pumps in the Missabe Mountain Mine at the east end of the city. Although the mine water was intended to be used only for emergency purposes, by 1931 approximately 90 percent of the municipal water was being supplied from the Missabe Mountain pit. The Oliver Mining Company discontinued mining in the Missabe pit in 1942, and the Virginia Department of Public Utilities (DPU) was allowed to continue using the pit pumps. Two years later, the DPU purchased the pump station from the mining company. At an elevation of 1,145 feet, the pump station was located near the edge of the lake that had developed inside the pit and over a 12 x 14 foot vertical shaft. A horizontal drift shaft, approximately 140 feet below the pump station, connected the vertical shaft to the water. The entrance to the horizontal shaft was covered by a thin overburden of unsorted iron ore, bearing rock, gravel, and clay till to filter the water before it entered the vertical shaft. The pump station housed two deep-well vertical turbine pumps. From the pump station, the raw water was then pumped up the west wall of the pit to the water treatment plant, which was approximately threequarters of a mile away and at an elevation of 1,440 feet. By this time, the water was being filtered, the result of a pair of horizontal pressure filters that were added to the treatment process in 1938. Hydraulic flocculators, sedimentation basins, and a filter pump building were added in 1949 and a 1-million gallon elevated reservoir constructed in 1956. Demand for water increased during this period, bringing about a need for greater storage and filter capacity. In 1963, the DPU added a standpipe as well as four pairs of piggy-back filters (one on top of another). Old Missabe Mountain Pump Station Removed December 1990 Missabe Mountain Mine Pit Water Level in 1990 Elevation: 1,146’ Old Pump Station Elevation: 1,147’ New Drift The level of water in the Missabe Mountain Mine Pit has risen another 90 feet since the new pump station was constructed in 1990. 4 Old Drift Virginia now has pressure filters in its treatment system. The vertical piggyback filters are shown in the photo to the left. The upgrade to the water system will include gravity filters that will replace the pressure filters. viruses, and an ultrafiltration system that would filter particles as small as .001 microns. The membrane filtration performed well, but cost considerations caused the DPU to instead decide to go with gravity filters. The project encompasses the removal of the existing pressure filters and highservice pumps as well as the portion of the building that housed this equipment. A new filtration building is being constructed across the street to the south of the existing building. The new building will house four sand-and-anthracite gravity filters, three high-service pumps, and a filter backwash retention tank. It will be connected by pipes to the existing plant and clearwell. The work will also include the renovation of the existing treatment plant building and the replacement of existing piping, valves, and filter pumps as well as the installation of new chemical feed equipment and controls. The existing flocculator, sedimentation basin, and clearwell will be renovated and cleaned. Work began last July with the demolition of a boiler building to make way for the new filtration building, which is expected to be on-line by next July. Concrete work was completed by the end of October, in time for masons to get the structure enclosed so construction can continue through the winter. A period of interim treatment is planned after the new filtration building is completed and while the old filters are being demolished and the remaining portion of the existing plant is being renovated. The utility will be performing direct filtration during this time. Completion of the entire project is anticipated by November of 2000. The $6-million project, which will allow the city to maintain compliance with drinking water regulations, is being funded in part by the IRRRB with the bulk of the money coming from a below-market-rate loan from the Minnesota drinking water revolving loan fund. Silver Lake Power Plant Power Plant Renovation of Demolition Existing Water of Filter Treatment Plant Room DPU Garage 1-millon gallon Clearwell 6th Avenue West Existing Water Treatment Plant DPU Garage 2nd Street South DPU Office No. 2 Power Plant (Boiler) Bldg. Malone Hall 6th Avenue West Silver Lake Filter Building By the mid-1980s, problems associated with the supply and the pit pumps started to emerge. The exposed (and uninsulated) raw-water supply lines extending up the west face of the pit were susceptible to both rock slides and extreme temperatures. To guard against freezing during the winter, the utility had to continuously pump water, resulting in an excess of water (sometimes as much as 40 percent of the total amount pumped) being routed to a storm sewer. In addition, the water level in the pit had risen more than 50 feet between 1977 and the late 1980s, threatening the existence of the pump station. After investigating several options to deal with the problem, the utility decided to construct a new pump station on the upper perimeter of the pit rim and to drill two vertical wells and a horizontal drift shaft to connect the wells to the lake. With help from the Iron Range Resources and Rehabilitation Board (IRRRB), the city was able to complete the $940,000 project in the summer of 1989. In addition to the new pumphouse, the work included the installation of a 7 x 8 x 300 foot horizontal drift, the drilling of two 24-inch wells to intersect the drift, and the installation of two 225-horsepower, 2,000 gallon-per-minute submersible pumps. This solved the problems related to the source and supply, but the need for an upgrade in the treatment process continued to be an issue. The pressure filtration system in place was nearing the end of its useful life, and replacement with a similar system was not an option since the Minnesota Department of Health was no longer approving pressure systems for the treatment of surface water. In 1994, the DPU contracted with Bonestroo Rosene Anderlik & Associates of St. Paul to perform a plant evaluation and feasibility study. From this came a recommendation to overhaul the entire treatment system and to explore the possibility of incorporating membrane filtration in the treatment process while still considering a more conventional gravity sand filtration system. In 1998, the city pilot tested two types of membrane systems: a microfiltration system that could filter particles as small as .10 microns, which would include Giardia and Cryptosporidium but not 1-millon gallon Clearwell 2nd Street South DPU Office Construction of New Filtration Building Malone Hall Demolition of No. 2 Power Plant (Boiler) Bldg. The before-and-after layout of the Virginia Water Treatment Plant. 5 Y2K Update Drinking Water Message Center The survey conducted by the Minnesota Department of Health to determine if public water supplies are prepared for potential Year 2000 (Y2K) problems has been completed, and a report of the findings is being prepared for the legislature and the Division of Emergency Management of the Minnesota Department of Public Safety. Preliminary results show that responses were received from 91 percent of the water systems that were required by state law to complete the survey. As expected, the survey indicated that large systems were likely to be taking steps to determine if they would be affected by Y2K and correcting problems to minimize disruptions. Small systems, for the most part, were not as concerned about the Y2K problem because computer-related technology was not integral to their operation. The biggest concern of small systems was the loss of electrical power. Some small systems have access to generators, but for those that do not, the cost of obtaining one is prohibitive, especially given the apparent low risk that there will be a power failure. The following table summarizes the responses to the survey as it applies to 3 phases of a Y2K readiness program. The meaning of the phases is: Assessment—determining if there is a problem. Remediation—fixing the problem. Testing—testing the fixes made. The responses in the table are broken down by total systems, large systems (serving a population of greater than 3,300), and small systems (serving a population of 3,300 or fewer). Phase System Size 75%100% complete < 75% complete No response, blank, or no Y2K involvement Assessment Total Large Small Total Large Small 64% 97% 59% 46% 82% 41% 4% 1% 5% 9% 7% 9% 32% 1% 36% 45% 11% 50% Remediation The MDH drinking water program has established a voice-mail message center. Utilities may leave messages to indicate a need for or questions about such things as consumer confidence reports, sample bottles, lab sheets, and certification information. Twin Cities Metro Area: 651/215-1324 Toll-free: 1/800/818-9318 Public Information Committee to Produce Calender The Minnesota Section—AWWA Public Information Committee would like to issue a calendar featuring pictures of Minnesota water towers starting in 2001. If your system has a tower you would like considered for inclusion in the calendar, please send a photo of it to the committee in care of Ewald Consulting Group, 26 E. Exchange Street, 5th floor, St. Paul, Minnesota 55101. Consumer Confidence Reports—Continued from page 1 A few other reminders: If lead and/or copper need to be listed, the table must contain both the 90th percentile level and the number of sites over the action level. Since the columns for lead and copper will have headings different from most of the other contaminants, it might not be a bad idea to separate this table from the other table; the same is true with turbidity for systems that have to report it since the headings are “Highest single measurement” and “Lowest monthly percentage.” Regardless of the type of distribution that was done on the report, systems must maintain a supply of the complete report and be ready to send it to any resident who requests a copy. Many of the reports contained additional information and graphics, which help to promote understanding about drinking water to their customers. A number of cities— including Cambridge, Richfield, and Woodbury—inserted a checkmark by the listing of each detected contaminants to indicate that it met the standard. Cambridge included a history of its utility with some “Did You Know?” items. Richfield listed a number of secondary contaminants and other water characteristics. Richfield listed the levels from both raw and finished water, which gives their customers an idea of the effectiveness of the treatment. Systems that submitted a report on time are having their reports automatically entered into a contest. Following an initial screening, the reports will be evaluated by a citizens’ committee and a plaque awarded to the best report in each of the six AWWA districts in the Minnesota Section with a grand prize for the best report in the entire state. In 2000, MDH will again be providing water systems with a ready-made report. The reports will not be mailed until late March or early April (the same time they went out this year), although the deadline for systems to distribute their reports will be July 1 (three-and-a-half months earlier than in 1999). Systems will have to plan ahead to make sure they can get their reports distributed by the July 1 deadline. Testing Total 43% 11% 46% 77% 10% 13% Large 38% 11% 51% Small Survey results for individual systems are available on the Minnesota Department of Health web site at: www.health.state.mn.us/y2k/. The Division of Emergency Management will be setting up a 24-hour Y2K emergency center from December 30, 1999 to January 4, 2000, to assist systems that encounter problems. The phone number for the hotline, along with other pertinent Y2K information, will be released through the news media shortly before the end of the year. The Minnesota Rural Water Association (MRWA) will also have a 24-hour hotline to provide assistance to systems. The MRWA hotline number is 1/800/367-6792 and will be staffed over the New Year’s holiday weekend. 6 Spring 2000 Schools The 2000 Metro Waterworks Operators’ School will be held from Wednesday, April 5 through Friday, April 7 at the Thunderbird Hotel in Bloomington. The certification exams will be offered on Friday afternoon. Participants in the school will receive 16 credit hours for their attendance. Competent Person training will again be offered. It will consist of classroom training on Thursday morning and on-site training on Thursday afternoon. There will be an additional $30 registration fee required for those taking the Competent Person training, and attendance will be limited to the first 50 people to register. The registration for the school (without the Competent Person training) will be $100 ($130 after March 20 or at the door). Other spring schools: Southeast School, March 28-30, Best Western Apache, Rochester Southwest School, April 20, New Ulm Northeast School, May 10-12, Superior Shores Resort, Two Harbors Central School, June 14-16, Ruttger’s Bay Lodge, Deerwood Below is a registration form for the Metro and Southwest schools. The Spring 2000 Waterline will have the entire Metro School agenda with another registration form that will include the other three-day spring schools. MRWA Conference 2000 Teleconferences The 2000 Minnesota Rural Water Association (MRWA) Technical Conference will be held at the St. Cloud Civic Center from Tuesday, March 7 through Thursday, March 9. For more information, contact the MRWA office at 218/685-5197 or via e-mail at [email protected]. The American Water Works Association has set the dates for its 2000 teleconferences. Taste and Odor: Basics and Beyond will be the topic of the teleconference on Thursday, March 9. The other teleconference, with no topic yet assigned, will be on Thursday, November 2. The downlink locations serving the Minnesota Section will be at the Earle Brown Continuing Education Center in St. Paul and Memorial Union Hall on the campus of the University of North Dakota in Grand Forks. All AWWA members will receive registration information in the mail. A registration form for the March 9 teleconference is below. REGISTRATION FORM You may combine multiple fees on one check if more than one person is attending a school; however, please make a copy of this form for each person. Questions regarding certification, contact Cindy Cook at 651/215-0751. Questions regarding registration, contact Jeanette Boothe at 651/215-0755. AWWA Teleconference: Taste and Odor: Basics and Beyond, March 9, 2000, $60 ($80 after March 1 or at the door). Check location you wish to attend: ____ Earle Brown Continuing Education Center, St. Paul ____ Memorial Union Hall, University of North Dakota, Grand Forks. Southeast School, March 28-30, 2000. Best Western Apache, Rochester. Fee: $75 ($90 at the door) Metro School, April 5-7, 2000, Thunderbird Hotel, Bloomington. Fee: $100 ($130 after March 20 or at the door) Check here if you want to attend the Competent Person Training (must include an additional $30). Check here if you would like to receive an exam application. (Applications must be submitted at least 15 days prior to the exam.) Check here if you would like to receive a study guide. Please print: Name Address City Zip Day Phone Employer Please enclose the appropriate fee. Make check payable to Minnesota Department of Health. Mail this form and fee to Public Water Supply Unit, Minnesota Department of Health, 121 East Seventh Place, Suite 220, P. O. Box 64975, St. Paul, Minnesota 55164-0975. 7 CALENDAR Minnesota Section, American Water Works Association *March 28-30, Southeast Waterworks Operators’ School, Best Western Apache, Rochester, Contact Paul Halvorson, 507/292-5193 *April 5-7, Metro Waterworks Operators’ School, Thunderbird Hotel, Bloomington, Contact Stew Thornley, 651/215-0771 *April 20, Southwest Waterworks Operators’ School, New Ulm, Contact Mark Sweers, 507/389-2501 *May 10-12, Northeast Waterworks Operators’ School, Superior Shores Resort, Two Harbors, Contact Stew Thornley, 651/215-0771 *June 14-16, Central Waterworks Operators’ School, Ruttger’s Bay Lodge, Deerwood, Contact Dick Nagy, 320/ 587-5151 Minnesota Rural Water Association Contact Kyle Kedrowski, 1/800/3676792 *March 7-9, Technical Conference, St. Cloud April 12, Operation & Maintenance, Elbow Lake April 26, Operation & Maintenance, Pequot Lakes AWWA Teleconference March 9, Taste and Odor: Basics and Beyond, St. Paul and Grand Forks, Contact Stew Thornley, 651/215-0771 Basic Water Operations 11-week courses on Monday and Thursday nights starting in January, Twin Cities locations, Contact John Thom, 612/861-9168 Minnesota Pollution Control Agency (Wastewater Operator Training) Contact Emily Armistead, 651/296-7251 December 15-17, Wastewater Treatment Technology Seminar, Maplewood Inn January 19-21, Annual Collection System Operators Conference, Thunderbird Hotel, Bloomington February 17-18, Land Application of Biosolids, Residuals, and Effluents Conference, Thunderbird Hotel, Bloomington March 22-24, Annual Wastewater Operators Conference, Thunderbird Hotel, Bloomington April 5-7, Land Application of Biosolids—Basic, Holiday Inn, St. Cloud April 11-13, Stabilization Pond Seminar, Americinn, Marshall April 25-27, Stabilization Pond Seminar, Northern Inn, Bemidji *Schools/meetings marked with an asterisk include a certification exam To be eligible to take a certification exam, applicants must have hands-on operations experience at a drinking water system. Minnesota Department of Health 121 E. 7th Place Suite 220 P. O. Box 64975 St. Paul, Minnesota 55164-0975 ADDRESS SERVICE REQUESTED
© Copyright 2026 Paperzz