NOT PROTECTIVELY MARKED Railway Guidance Document RGD-2008-04 ROGS: further guidance on unusual and complex issues Date of issue/ last review Date of next review December 2011 RGD postholder/owner June 2012 Trevor Kent RGD cleared by Caroline Wake, Deputy Director (Railway Operators) RGD type Policy_____________________ Information________________ Procedure_________________ Target audience RSD_____________________ Policy____________________ RPP_____________________ Inspectors________________ Admin___________________ Keywords Safety certificate, safety authorisation, operator, infrastructure manager, shunting, engineering possession, functionally separate, safety verification, competent person Summary This RGD provides further guidance to inspectors on issues arising from the interpretation and application of ROGS (certification, authorisation and safety verification only) in complex and unusual situations. Original consultation RSD Operations, Legislative Development & Policy Section, Interoperability and Standards Section, Rail companies team, Legal Team Subsequent consultation (reviews only) Page 1 of 6 Doc # 347397.05 NOT PROTECTIVELY MARKED Detail INTRODUCTION 1. There now exists a substantial body of guidance for the various aspects of ROGS (see paragraph 3). However since the introduction of the regulations, a range of more unusual and/or complex issues have arisen in relation to Parts 2 and 3, particularly concerning interpretation matters. This RGD aims to document the advice given on these in one place for future convenient reference. It is primarily aimed at Railway Safety Directorate staff but can be used by other parties in ORR and can also be provided to outside stakeholders. 2. Because the ROGS regulations implement a European Directive, where there is an ambiguity they are interpreted so as to give effect to the purpose of the Directive. Otherwise the normal rules of legislative interpretation apply. If words are defined in ROGS, HSWA or in the Safety Directive then that is the meaning that they have. If they are not defined in legislation, then words have their natural meaning. This guidance is based on those principles. ROGS GUIDANCE AND MANUALS 3. The main ROGS guidance and manuals can be found at ROGS: Office of Rail Regulation. Also see: Guidance on functionally separate Guidance on sidings Guide to the application of safety verification: inspector guidance RGD-2007-04: Railways & Other Guided Transport Systems (Safety) Regulations 2006 (ROGS): Transfer of Deemed Certificates/Authorisations ROGS - Guidance on Safety Critical Work Terms RGD-2007-09: Railways & Other Guided Transport Systems (Safety) Regulations 2006 (ROGS): Part 4 Safety Critical Work CERTIFICATION/AUTHORISATIONWho is the operator? 4. In most situations this will be straightforward. It will be the company which owns and runs the service. However in some circumstances, contractual arrangements may split responsibilities between different parties and make this more difficult to determine. Regulations 3 and 4 require that ‘no person shall operate a train/vehicle in relation to any infrastructure on a mainline railway/transport system’ without a SC/A. The question of who is the operator is therefore a factual question: who, on the facts of the particular case, comes within the meaning of “operator”? 5. Although the actual day to day operation of a train may be undertaken by one „person‟, it is possible that another person may have responsibilities for the operation as a whole which may impact on that day to day operation. All the relevant facts need to be taken into account in determining which of the two is „the operator‟. A key issue will be to determine under whose overall SMS the operation takes place. 6. In situations where Company A contracts out the operation of the service or part of the service to Company B, and if it is carried out under Company B‟s SMS then it will be Company B which needs to have a certificate even if the wider strategic (nonsafety) aspects of the operation (e.g. type of service, routes, timetabling etc.) are determined by Company A. If, however, Company A contracts in trains or vehicles for a specific purpose within its wider operations to operate under its own SMS, then it is Company A which should hold the certificate. The examples given in paras 8 and 9 help illustrate this. Page 2 of 6 Doc # 347397.05 NOT PROTECTIVELY MARKED 7. However some situations can involve very complex contractual relationships, especially where franchising responsibilities for a particular service have been awarded to more than one party, and it may be difficult to determine where overall safety management responsibility lies. Where such a situation occurs, the account holder should refer it to the Legislative Development Team, who will consider it with ORR Legal section, and as appropriate, ORR Licensing & Network Regulation team and DfT, before coming to a conclusion. 8. Example 1: a quarry operator (Company A) moves stone by rail from its quarry down a privately owned branch line to a junction with the mainline where another operator (Company B) is contracted to transport it via the mainline network to various destinations. ROGS does not apply to railways within quarries, while the ROGS status of the branch line will depend on a number of factors which may vary from case to case. However, for the mainline part of the operation it will be Company B which needs to hold the mainline certificate. 9. Example 2: a mainline operator (Company A) contracts in shunting locomotives and drivers from Company B to shunt its trains, including shunting movements on the mainline. The shunting activity as a whole is managed under Company A‟s SMS, but the actual movements are undertaken by Company B. Company A should therefore hold the certificate which covers this activity. Who is the infrastructure manager (IM)? 10. Again this is usually straightforward but contractual relationships can obscure matters. In terms of „infrastructure other than a station‟, the IM is the person who is responsible for „developing and maintaining‟ that infrastructure. The term „developing‟ implies something more than the day-to-day running of the infrastructure and that a strategic responsibility is held for the whole infrastructure. The body or organisation with this role should therefore hold the authorisation, even if it does not manage dayto-day running. 11. The following example illustrates this: a light railway company independent of the mainline railway operates with one main contractor (franchisee) which operates trains, manages and operates stations and carries out routine and major maintenance on large parts of the infrastructure. Other smaller contractors (concessionaires) design, construct and maintain designated parts of the infrastructure. One overarching company is responsible for managing the franchises/concessions across the whole operation, commissioning new projects and making overall decisions with regards to management and maintenance. It is this company which has the legal role of the infrastructure manager. Mainline/non-mainline 12. ROGS provides a definition of mainline railway in regulation 2 (http://www.opsi.gov.uk/si/si2006/20060599.htm). However, that definition relies on the meaning of phrases such as “local use” and “functionally separate” which do not necessarily have a clear application in every case. In this context, it should be understood that the railway system in Britain as a whole is very complex, where demarcations between different networks or sub-networks are not always absolutely clear, particularly in relation to suburban, urban and metro networks. 13. Therefore, in addressing specific instances of what is mainline or not, if it is not clear how the reg.2 definition applies, you should then consult the guidance on functionally separate and local use (see below). If this still does not provide a clear answer, you should contact the Legislative Development Team, which will consult with others in ORR as is necessary. Functionally separate Page 3 of 6 Doc # 347397.05 NOT PROTECTIVELY MARKED 14. Guidance on functionally separate is given at ROGS Regulations 2006 : Office of Rail Regulation. However, the question has been raised on whether a part of an infrastructure can be regarded as functionally separate in terms of time, that is, if mainline traffic normally runs on that part of the infrastructure but does not do so for a significant period of time (e.g. at night.) ORR‟s view is that it cannot, as this goes beyond the intention of both ROGS and the Directive. Local use 15. Guidance is given in the ROGS assessment manual (ROGS Regulations 2006 : Office of Rail Regulation). Part B certificates – which network? 16. The question has arisen over what the „network‟ may comprise for a Part B application. ROGS does not provide any indication here. Article 10 (1) of the Railway Safety Directive states that „The safety certificate may cover the whole railway network of a Member State or only a defined part thereof ‟ but makes no distinction here between the scope of Part As and Part Bs. If, therefore, a company wishes to make a Part B application which includes the whole national network then it is allowed to do so, so long as the Part A covers an equivalent operation in terms of type and extent and the application provides evidence demonstrating compliance with all standards and relevant requirements which may apply to different parts of the network. 17. The stated „network‟ however cannot extend beyond the boundaries of Great Britain either into another EU member state, Northern Ireland or beyond the Channel Tunnel boundary. In each case a separate part B application must be submitted to the relevant authority. 18. If, on the other hand, an operator wishes to apply for separate Part Bs for different parts of the national network, it can. Shunting 19. Any shunting only operation will require its own certificate if operations are carried out anywhere on the infrastructure outside depots or sidings. If an operator already has a certificate for its wider operations, it will not need an additional certificate for its shunting activities so long as these are adequately covered by its SMS arrangements, which are described in its application. Additionally, if an operator makes an arrangement with an existing certificate holder to carry out shunting movements on its behalf, then it will not need its own certificate so long as shunting is described in the holder‟s application. 20. For clarification, shunting is defined in the Rule Book (module GE/RT8000/SS) as: „any movement of a train or vehicle other than a train passing normally along a running line.‟ Engineering possessions 21. Operators of trains/vehicles within an engineering possession are exempt from the need to have either a certificate or a ROGS SMS. However ROGS requires that the SMS of an IM should ensure the control of all categories of risk associated with the operation in question. This includes risks which arise from activities within engineering possessions, whether these are risks to the wider transport system or to the workforce employed within the possessions, and whether or not the activities are contracted out to another party or parties. 22. ROGS defines an engineering possession as a ‘section of track which is closed to normal traffic and where the closure is for the purpose of carrying out maintenance which shall include any repair, alteration, reconditioning, examination or testing of Page 4 of 6 Doc # 347397.05 NOT PROTECTIVELY MARKED infrastructure...‟. Both conditions must apply which means that a section of track which is closed to normal traffic for reasons other than described above, cannot be regarded as being an engineering possession. Substantial changes and testing 23. If there is to be a substantial change preceded by a testing phase involving vehicle movements on the infrastructure, is the amended SC/A required before or after the testing takes place? 24. In general the amended SC/A should be issued before any such testing takes place. The only time that testing can take place before an amended SC/A has been issued is if it takes place within an engineering possession (see para. 22 for definition), but that can only be on the infrastructure alone not on any vehicle. If the testing is for the purpose of testing both the infrastructure and the vehicle, as well as the interaction between them, then this does not meet this condition. 25. This can be confused with the situation with regard to testing and safety verification. Regulation 5(4) requires that as part of its SMS arrangements a transport operator should have safety verification arrangements (but see also paras. 28-29), for the „placing into service‟ of new/altered vehicles or infrastructure which meets the conditions of regulation 5(1)(d)(iii), but regulation 5(6) states that the actual „placing into service‟ does not include any testing. In other words, the duty holder will need to have the amended certificate/authorisation for its substantial change before any testing takes place, but any safety verification which is required as part of the substantial change does not need to have been shown to have been completed until after any necessary testing. The situation with regard to new infrastructure and rolling stock and compliance with the Interoperability regulations mirrors this. 26. The relationship between substantial changes and safety verification can appear very complex, so in cases where there is doubt or confusion, you should refer these to the Legislative Development Team for further advice. SAFETY VERIFICATION 27. See also the Guide to the application of safety verification - inspector guidance (ROGS Regulations 2006 : Office of Rail Regulation.) Safety verification (SV) and the SMS 28. Does every SMS under ROGS need to include arrangements for carrying out SV? 29. Strictly speaking, if a duty holder claims that it does not intend to introduce new equipment likely to attract the requirement to have a SV scheme over the lifetime of the certificate, then it would not need to include arrangements for setting one up. Its SMS would however still need to include change management arrangements which should be capable of recognising if there were any change to this situation. If there were any subsequent introduction of a project which met the conditions for SV, the holder should then notify ORR under regulation 13 of its proposed SV arrangements as a major change to its means of meeting SMS requirements. Whether it would need to apply for an amended certificate or not, would depend on whether the project itself introduced a substantial change to the operation. How are interface issues dealt with? 30. The Independent Competent Person (ICP) will need to help the duty holder ensure that interface issues (e.g. between rolling stock and infrastructure) that have implications for the safe introduction of the equipment being verified have been adequately addressed. The responsibility for managing safety risks including interface risks lies with the duty holder introducing the change. The ICP only provides advice to Page 5 of 6 Doc # 347397.05 NOT PROTECTIVELY MARKED help the duty holder ensure that the risks arising from the introduction of new equipment will be adequately controlled. On track machines (OTMs) and the application of SV 31. As OTMs do not operate a passenger or freight service it has been questioned whether SV applies to them, as they do not provide a „transport service‟. (ROGS Regs. 5(6) and 6(5): In this regulation placing in service shall mean first placed in service for the provision of a transport service…..) 32. OTMs operating outside possessions come within the scope by virtue of regulations 3 (Use of infrastructure on the mainline) and 4 (Use of infrastructure on other transport systems) and as a result those operating them must comply with all SMS requirements including SV. It is not regulations 5 & 6 which bring them within scope, whatever interpretation is placed on „transport service‟. Infrastructure Manager (IM) role in SV of vehicles 33. Unless an IM places vehicles into service and operates them itself, it has no direct responsibility for the SV process applied to vehicles although it will need to make some input to ensure compatibility with the infrastructure. The duty to comply with regulation 3(1) and 4(1) of ROGS (and the concomitant duty to apply SV) falls on the person who is the "operator of a train in relation to any infrastructure on the mainline railway/other transport system", not on the IM. Therefore, if an IM owns a rail vehicle but places it into service via someone else‟s operation, it would not be required to be certificated as the operator of a train. However, if the IM chose to operate the vehicles itself, it would need to be certificated and apply the SV process as appropriate. CONTACTS 34. Any questions or queries on this guidance should be addressed to: Certification/authorisation. Trevor Kent, Permissioning & Divisional Support Team Manager, Tel ext. 3772; [email protected]. or Safety verification. Paul Hooper, Interoperability and Standards Manager; Tel ext. 2191; e-mail: [email protected] Action (optional) No action required. Page 6 of 6 Doc # 347397.05
© Copyright 2026 Paperzz