RUSH ISLAND TO BALDWIN 345kV LINE & MISSISSIPPI RIVER CROSSING MASTERING THE MIGHTY MISSISSIPPI How The L.E. Myers Co. won against America’s Greatest River Few would argue that the Mississippi River has long played a role in America’s history, serving as a source of significant physical and economic growth for our nation. So it has its good points. But when you’re a major electrical contractor trying to construct a transmission line across this massive body of water, many of the mighty Mississipi’s good graces and contributions over the years are temporarily forgotten. As part of an ongoing alliance agreement with Ameren, The L.E. Myers Co., a subsidiary of the MYR Group, was selected to perform the majority of transmission construction services for the Baldwin to Rush Island 345kV transmission line. The project included construction of 28 miles of new 345kV single circuit transmission line on single shaft, steel pole reinforced structures. It also included a 2800’ Mississippi River crossing that required five enormous 400’ steel lattice structures with 10’ x 10’ foundations for each of the lattice tower’s four legs. The five towers were located in wooded wetlands along each side of the Mississippi River. to more easily sequence the work, Ameren and The L.E. Myers Co. could not afford further holdups and worked steadily to carefully coordinate manpower and schedules for the new line. Although easements on some portions of the new transmission line route had not yet been acquired, The L.E. Myers Co. began construction on the new line in June 2009 in areas where proper approvals had been secured. Although this impacted the ability THEN THE RAINS CAME Although some delays related to the river crossing may have been anticipated, no one would have guessed that the spring flooding would wreak such havoc. “We started constuction activities related to the river crossJanuary 2010 VIEW LOOKING EAST The new transmission line crosses the Mississippi River from the Rush Island Power Station on the west side to the Baldwin Power Station near Baldwin, IL. Photo taken during tower erection. ing last November,” said Gary Klocke, The L.E. Myers Co. Construction Manager overseeing the project. “The spring flooding delayed us by 22 weeks on one side of the river and 26 weeks on the other. We expected some flooding, but nothing like this,” he added. “We were unable to work on tower construction inside the levees, and weren’t able to resume construction until the last week of August. We were expecting to be done with the project the first part of August, and now it’s November of 2010 and we are just finishing up the project.” TREMENDOUS SUPPORT FROM AMEREN Because the flooding had a devastating impact to the project’s schedule, Ameren and The L.E. Myers teams to prepare contingency plans in anticipation of continued flooding delays. This planning process resulted in paying huge dividends in completing the project. “Ameren was a tremedous advocate when it came to ensuring we were doing all we could to meet the schedule,” said Klocke. “For example, they were instrumental in work ABOVE AND RIGHT Erection crews construct the 400’ lattice structures on either side of the Mississippi River Co. worked together to adjust the schedule in order to meet Ameren’s requirement of having the project completed before the end of 2010. This collaborative planning process involved weekly meetings beginning in late July between The L.E. Myers Co. and Ameren ing closely with the civil contractor to increase accessability to the site by upgrading roads on each side of the river, which was a tremendous help, “ he added. “Initially, we had planned to use two cranes for the entire project, and move them from one site to the next, using the same crews and manpower,” commented James Eilders, Project Manager for The L.E. Myers Co. “In order to meet the revised schedule, we had to add additional cranes to help us set tops of structures. We had planned to only use helicopters for this but needed the additional equipment. We were fortunate that we had other jobs under construction in the surrounding area, which allowed us to easily mobilize workers between VIEW LOOKING WEST The Rush Island Power Plant , located near Festus, MO can be seen in the background projects as required, without a need to retrain or rehire,” he added. “This ended up saving us time and money, which meant it also saved our client time and money.” Despite the extreme challenges encountered, The L.E. Myers Co. project team of Gary Klocke, James Eilders, Terry Taylor (General Foreman) and Joey Hamlin (General Foreman) did an excellent job of successfully and safely handling all aspects of this project. “I’ve been at this a long time, but this one gave us a run for the money,” said Klocke. “In the end, there’s no greater feeling than knowing we were able to come through for our client.” Story by Paula Frisina LEFT AND ABOVE A view of the 400’ lattice structures, and an example of measures taken to deal with the flooding THE L.E. MYERS CO. a s u b s i d i a r y o f M Y R G r o u p I n c. The L.E. Myers Co., a subsidiary of MYR Group Inc. is one of the largest specialty electrical contractors in the country, making it one of few with the ability to quickly deploy manpower, equipment and resources to projects of varying size and scope throughout the nation. With roots dating to 1891, L.E. Myers provides a complete range of power line construction services to utilities, telecommunications providers, industrial facilities and government agencies throughout the United States. For more information, please visit www.myrgroup.com or call 847-290-1891.
© Copyright 2026 Paperzz