Risk Register PDF 162 KB - Meetings, agendas and minutes

Meeting:
Enterprise Partnership Board
Date:
17 November 2010
Report Title:
Risk Register
Report of:
Marc Dorfman, Assistant Director, Regeneration &
Planning
Purpose
To provide a full update of the Enterprise Board’s risk register.
Summary
•
•
•
•
•
•
The Haringey Strategic Partnership (HSP), at its meeting on 3 July 2008,
formally approved a Risk Management Strategy. This strategy requires
each HSP theme board and the Performance Management Group to
produce a risk register, which identifies the key risks and remedial actions
associated with delivering the LAA targets they lead on (National
Indicators and stretch targets).
The Enterprise Board decided at its meeting on 10 December 2008 to
receive full updates on its risk register at every other meeting. However,
due to the current economic climate it was agreed that the Board would
receive an update on NI 153 at every meeting. This report provides a full
update of the risk register.
Due to the stretch targets expiring the risks associated to them have been
removed from the risk register.
The inherent and residual risks associated to NI 153 and NI 171 have
been upgraded to High due to the current economic uncertainty following
the results of the Comprehensive Spending Review and planned changes
to the welfare system.
The controls for NI 153 and NI 171 have been updated to reflect, for
example, the planned introduction of the Work Programme and Local
Enterprise Partnerships
The full risk register is appended to this report.
Legal/Financial Implications
N/A
Recommendations
1. That the Enterprise Board approves its updated risk register
For more information contact:
Name: Ambrose Quashie
Title: Policy Officer
Tel: 020 8489 6914
Email address: [email protected]
Appendix 1: Enterprise Board Risk Register
01. Lack of continuity of membership across the theme board
Risk
Likel RAG
Impa
ihoo Statu Internal Controls
ct
d
s
Lack
of
continuity
of
membership impacts on the
ability
to
deliver
on
outcomes/targets
•
•
•
L
L
•
•
Agreed recruitment procedures
for Theme Board membership
Enterprise Board membership
reviewed on an annual basis
Responsibility for filling posts
identified
Training & Development for
Theme Board members
Reporting processes to highlight
and identify vacancies and/or
non-attendance
Risk
and
Ownership
Control
Further Action(s)
Due Date
On
target?
Risk
Owner:
Enterprise Action plan to address identified gaps to 31 Mar 2011
Board Chair; Control Owner: be drawn up
Enterprise
Board
Coordinator
02. Data Quality and/or information management arrangements
Risk
Likel RAG
Impa
ihoo Statu Internal Controls
ct
d
s
Data are not robust and/or
timely enough to effectively
monitor
and
manage
performance
•
•
M
L
•
Effective quality monitoring of
internal performance data e.g.
Haringey Guarantee employment
outcomes by using Meganexus.
External validation of monitoring
data e.g. the Greater London
Enterprise
monitoring
the
Haringey Guarantee
Lobby central Government for
improvements to external data
e.g. employment and business
start ups.
Risk
and
Ownership
Control
Further Action(s)
Due Date
Risk
Owner:
Assistant Review of existing data collection and 31 Mar 2011
Director
Planning
& monitoring processes and action plan to fill
Regeneration;
Control gaps
Owner: Assistant Director
Planning & Regeneration
On
target?
03.Governance arrangements
Risk
Likel RAG
Impa
ihoo Statu Internal Controls
ct
d
s
Lack of strategic direction
impacts on the ability to
deliver on outcomes/targets;
Lack
of
continuity
of M
membership impacts on the
ability
to
deliver
on
outcomes/targets
•
•
L
•
Terms of Reference are reviewed
on an annual basis
Positions of Chair and Vice Chair
are reviewed on an annual basis
Enterprise Board membership is
reviewed on an annual basis
Risk
and
Ownership
Control
Further Action(s)
Due Date
On
target?
Risk
Owner:
Enterprise Action plan to address identified gaps to 31 Mar 2011
Board Chair; Control Owner: be drawn up
Enterprise
Board
Coordinator
04. Non delivery of outcomes; allocation of resources, commissioning, spend, linkages to other theme boards/cross cutting work not identified
Risk
Likel RAG
Impa
ihoo Statu Internal Controls
ct
d
s
LAA
outcomes
are
not
delivered; Delivery projects
do not meet spend profile;
Enterprise Board membership
is not wide enough to ensure
linkages to other theme H
boards/cross cutting work
•
•
L
•
•
Delivery partners are regularly
monitored on outcome and
financial performance.
Performance
and
progress
reports are received at every
Enterprise Board meeting.
Enterprise Board membership is
reviewed on an annual basis
Enterprise Board representative
attends the HSP Co-ordinators
meetings.
Risk
and
Ownership
Control
Risk
Owner:
Assistant
Director
Planning
&
Regeneration;
Control
Owner: Assistant Director
Planning & Regeneration
Further Action(s)
Due Date
Action plan to address identified gaps to 31 Mar 2011
be drawn up
Evaluating the role of delivery partners 31 Mar 2011
where appropriate
On
target?
05. Working age people claiming out of work benefits in the worst performing neighbourhoods
Risk
Likel RAG
Impa
ihoo Statu Internal Controls
ct
d
s
Continued increase in working
age people claiming out of
work benefits in the worst
performing
neighbourhoods
(NI 153)
•
•
•
•
•
H
H
•
•
•
Used
ABG
allocation
to
commission employment and
skills interventions (Haringey
Guarantee and Families into
Work).
Delivery partners are regularly
(and independently) monitored
on performance.
Performance
and
progress
reports are received at every
Enterprise Board meeting.
Increasing the role of the
Haringey Guarantee to support
people
who
have
recently
become unemployed.
Agreeing a SLA with JCP that
allows JCP advisers to make
referrals
to
the
Haringey
Guarantee.
Agreeing a SLA with Reed in
Partnership
that
will
allow
incapacity
related
benefit
claimants to have access to a
more comprehensive package of
support.
Delivering the North London
Pledge,
which
will
support
approximately 440 people into
sustained employment across
Barnet, Haringey, Enfield and
Waltham Forest.
Submitting a successful Council
led Future Jobs Fund bid that will
create up to 221 jobs for longterm benefit claimants.
Risk
and
Ownership
Control
Further Action(s)
Risk Owner: Regeneration •
Manager (Employment &
Skills) & External Relations
Manager
(JCP);
Control
•
Owner:
Regeneration
Manager (Employment &
Skills) & External Relations
Manager (JCP)
•
Due Date
Conduct further research into the 31 Mar 2011
impact of the current economic
climate on Haringey.
Evaluating the role of Haringey 31 Mar 2011
Guarantee delivery partners where
appropriate.
Conduct a monthly review of pre 31 Mar 2011
employment training to ensure it is
meeting the needs of employers and
customers.
On
target?
Risk
Likel RAG
Impa
ihoo Statu Internal Controls
ct
d
s
•
•
•
•
•
•
•
•
Working with JCP and potential
prime
contractors
of
the
forthcoming Work Programme to
ensure that planned delivery is
effective and appropriate for
Haringey residents.
Working with North London
Business and NLSA to develop a
North London Local Enterprise
Partnership.
JCP offer a Rapid Response
Service where JCP can intervene
to help when businesses are
making people redundant. This
service
funding
has
been
doubled to £6m nationally and
will be doubled again to £12m to
extend the service to smaller
companies and localities affected
by multiple redundancies
In and Out of work programme
roll out on 26 October 2009.
Jobcentre Plus has appointed
borough partnership manager to
improve the links between the
services provided to customers
throughout the borough by the
local authority, community or
voluntary groups. Their role
incorporates the drug, mental
health and carer agendas.
Support for young people to
include;
Rapid Response Group, which
includes JCP, Haringey Council
and LSC, meets on a 6 weekly
basis to ensure co-ordinated and
effective response.
Options & Choices events for
lone parents
Risk
and
Ownership
Control
Further Action(s)
Due Date
On
target?
06. New business registration rate
Risk
Likel RAG
Impa
ihoo Statu Internal Controls
ct
d
s
No increase to new business
registration rate (NI 171)
•
•
H
H
•
Using
ABG
allocation
to
commission business support
interventions
Identify new markets that are
viable
during
an
economic
downturn and focus business
start-up programmes in those
areas.
Working with North London
Business and the North London
Strategic Alliance to develop a
North London Local Enterprise
Partnership.
Risk
and
Ownership
Control
Further Action(s)
Due Date
Risk Owner: Business & Evaluating the role and performance of 31 Mar 2011
Enterprise Manager; Control delivery partners in business support and
Owner:
Business
& advice provided within the borough.
Enterprise Manager
On