9.5 Scheduling
Gantt charts:
1
9.5.notebook
November 02, 2016
P.E.R.T. Charts
Task
Length
a) Create Budget
8 weeks
b) Hire Director
4 weeks
c) Hire Actors
4 weeks
b
2 weeks
a
d) Hire Production Staff
e) Advertise and Contact Agents
Dependency
3 weeks
f) Scout Locations
2 weeks
c, d, e
g) Build Sets
4 weeks
f
h) Film Non­set­
12 weeks
dependent Scenes
i) Film Set­dependent 9 weeks
Scenes
j) Pick Conductor and 3 weeks
Music
k) Edit Film
4 weeks
l) Write Press Release, 2 weeks
Create Preview
m) Prescreen with 2 weeks
Audiences
n) Create Soundtrack 1 week
CD
f
g
h, i
h, i
h, i
k
j
2
9.5.notebook
November 02, 2016
Vocab: "Limiting Task"
a
d
e
g
i
n
j
f
L
h
b
c
k
m
Vocab: "Critical Path"
Vocab: "Completion Time"
3