ROOF OVERSHEETING AND WALL CLADDING VALUE £550,000.00 Big Yellow Self Storage at Cambridge PROJECT DESCRIPTION The project consisted of oversheeting the existing main roof with Euroclad SF500 Installation of new gutters, downpipes and a mansafe system Installation of a new steelwork frame to front elevation Installation of new wall cladding Installation of new canopy Hadleigh Barbour Ltd, Units 1 & 2, 284 Warley Hillm Warley, Brentwood, Essex CM13 3AB Tel: 01277 235 000 Fax: 01277 235 005 Email: [email protected] www.hadleighbarbour.com CLADDING WORKS FROM START TO COMPLETION PRE COMMENCEMENT OF WORK STRIPPING OF OLD CLADDING ERRECTION OF STEELWORK AND GALVANISED TOP HATS INSTALLATION OF COMPOSITE WALL CLADDING COMPLETION OF WALL CLADDING PREPARATION FOR CANOPY STEELWORK ERRECTION OF STEELWORK FOR CANOPY COMPLETED WORKS
© Copyright 2026 Paperzz