Case Study 3 - industrial roofing Essex Commercial cladding Great

ROOF OVERSHEETING AND WALL CLADDING
VALUE £550,000.00
Big Yellow Self Storage at Cambridge
PROJECT DESCRIPTION
The project consisted of oversheeting the existing main roof with Euroclad SF500
 Installation of new gutters, downpipes and a mansafe system
 Installation of a new steelwork frame to front elevation
 Installation of new wall cladding
 Installation of new canopy
Hadleigh Barbour Ltd, Units 1 & 2, 284 Warley Hillm Warley, Brentwood, Essex CM13 3AB
Tel: 01277 235 000 Fax: 01277 235 005 Email: [email protected] www.hadleighbarbour.com
CLADDING WORKS FROM START TO COMPLETION
PRE COMMENCEMENT OF WORK
STRIPPING OF OLD CLADDING
ERRECTION OF STEELWORK AND GALVANISED TOP HATS
INSTALLATION OF COMPOSITE WALL CLADDING
COMPLETION OF WALL CLADDING
PREPARATION FOR CANOPY STEELWORK
ERRECTION OF STEELWORK FOR CANOPY
COMPLETED WORKS