Renovation of King Hall Project # J-283 RFQ Questions & Responses October 1, 2015 Addenda # 1 1. Hazardous material abatement. Under section 1. General Project Information, there is a statement that the project will “address the removal of hazardous materials including lead paint and asbestos”. Does this work fall under the Design Professional’s (DP) SOW or the BOR and/or ABAC? RESPONSE: We have a full Hazardous Materials survey that will be shared with the selected firm. 2. Hazardous material abatement procuring and contracting. This question is based on the response provided in the question above. If the hazardous materials abatement falls under the DP’s SOW, will the BOR reimburse the cost to the DP for procuring and contracting this service? RESPONSE: The Hazardous Material abatement, procuring and contracting, will be contracted through ABAC.