Transpower House, 96 The Terrace, PO Box 1021, Wellington, New Zealand Telephone +64-4-495 7000 Facsimile: +64-4-495 7100 Tim George Tel: 04 495 6949 Fax: 04 494 6779 [email protected] www.transpower.co.nz 11 June 2007 Mervyn English General Manager Electricity Commission PO Box 10041 WELLINGTON Dear Mervyn NIGU proposal - final questions Thank you for the opportunity to respond to a number of issues arising from the recent public conference that you addressed in your letter of 5 June 2007 on Transpower’s North Island Grid Upgrade (NIGU) reliability investment proposal. Answers to the various questions and sub-questions are presented as follows: Appendix A – Question 1 of 5 June Letter Appendix B – Question 2 of 5 June Letter Appendix C – Question 3 of 5 June Letter Appendix D – Question 4 of 5 June Letter Appendix E – Question 5 of 5 June Letter Appendix E1 - Recommendation (a) Appendix E2 - Recommendation (b) Appendix E3 - Recommendation (c) Appendix F – Question 1 of 5 June Letter’s Appendix Appendix G – Question 2 of 5 June Letter’s Appendix Appendix H – Question 3 of 5 June Letter’s Appendix Appendix I – Question 4 of 5 June Letter’s Appendix These are followed by two reference appendices: Appendix J – Betterment – Increase in Injurious Effect Appendix K – Transpower Easement Conditions 070606-EC-NIGU-FinalQuestionsD4.doc Mervyn English re: NIGU proposal - final questions Page 2 of 25 11 June 2007 I trust these answers assist the Commission. While appreciating that time is of the essence, my team and I are happy to provide any further clarification that the Commission requires. Yours sincerely Tim George General Manager Grid Investment 070606-EC-NIGU-FinalQuestionsD4.doc Mervyn English re: NIGU proposal - final questions Page 3 of 25 11 June 2007 Appendix A – Question 1 of 5 June Letter Question 1 Please confirm whether Transpower has budgeted within the costs for which approval is sought for likely measures, for example, the use of monopoles, more undergrounding etc, which may be required to mitigate any adverse environmental effects of its Proposal Please provide evidence of how these costs have been budgeted for. Transpower has budgeted for what it considers at this stage are appropriate environmental mitigation measures. The expected or “P50” costs used as a basis for justifying Transpower’s reliability investment proposal for the NIGU were based on the design outlined in that proposal. That design was achieved through application of the ‘ACRE’ (Area-Corridor-Route-Easement) process which provides a framework to identify effects and avoid remedy or mitigate these in accordance with the requirements of the RMA. Extensive consultation was undertaken at various stages through this process. The output represents a proposal that has already sought an optimum solution across the various stakeholders and affected parties, given the information available at the time. For example, while (given a need for a line) some parties prefer lower tower heights, directly affected farmers typically prefer higher tower heights and longer spans. Extensive consultation formed the basis of refining the positions of both the indicative centre lined and associated towers from those originally announced in July 2005. As a result by October 2005 there had been changes to approximately two-thirds of the preliminary tower locations - and therefore to the indicative centre line, while Transpower sought to improve the alignment. In some cases, properties that were not crossed by the indicative centre line back in July 2005 became directly affected. A wide range of factors were taken into account, including visual effects, environmental and heritage issues. Transpower acknowledged in November 2005 that the line had moved to such an extent that landowners needed more time to give feedback on the revised centre-line. As a result consultation was extended further - and the results of this consultation reviewed by Transpower staff and consultants with expert specialist knowledge in the areas of property, engineering, planning, landscape architecture, agriculture, tourism and recreation, environmental, social and cultural issues before a final decision was made on the centre line and tower locations in January 2006. The trade-offs between multiple interests, while maintaining reliability standards and good electricity industry practice, meeting the need date and seeking to minimise project costs, are complex. Transpower acknowledges that new information has emerged and will continue to emerge since then that may affect some of the trade-offs. The lodging of the NOR and the subsequent RMA processes provide the opportunity for all information to be ‘tabled’ and those trade-offs to be made within the appropriate legal framework. Transpower is not yet of the view that use of monopoles and more undergrounding is “likely”, but is entering the RMA process with an open mind to such issues. The “P90” costs for which approval has been sought include a contingency of $105 million to allow for, amongst other things, further design refinement during the RMA process. This contingency amount was increased in the amended proposal by $30 million over the original proposal. Because a project of this scale has not been recently completed under the current RMA processes, it is difficult to determine the probabilities of different design refinement and hence cost outcomes that might arise through the RMA process. Thus, Transpower’s estimates of the contingency amounts required for this may turn out, with the benefit of 070606-EC-NIGU-FinalQuestionsD4.doc Mervyn English re: NIGU proposal - final questions Page 4 of 25 11 June 2007 hindsight, to be overly optimistic or pessimistic. They remain however Transpower’s best estimates. The consequence of this is that the “P90” costs for which approval is sought may have a probability of being exceeded of more or less than 10%. Transpower will endeavour to achieve the most appropriate outcome that satisfies Transpower’s statutory obligations under the RMA, while maintaining reliability standards and good electricity industry practice, meeting the need date and seeking to minimise project costs. If through RMA requirements the approved costs are forecast to be exceeded, Transpower will advise the Commission at the earliest opportunity that it may for this reason seek an amendment of project scope under Rule 17.2. It is possible that some changes resulting from the RMA process would take the project out of the scope of the project that Transpower has sought approval for, described in section 2.1 of Transpower’s October 2006 application. For example, approval has been sought for undergrounding to the vicinity of the South Auckland urban boundary, and for the new line to be of steel lattice tower construction. Significant changes to the amount of undergrounding or tower designs, for example, could fall outside this scope. If such a scope change was required, Transpower would need under Part F to seek Commission approval for it under Rule 17.2, which would include a commensurate change to the approved amount. 070606-EC-NIGU-FinalQuestionsD4.doc Mervyn English re: NIGU proposal - final questions Page 5 of 25 11 June 2007 Appendix B – Question 2 of 5 June Letter Question 2. In particular, the Commission would appreciate Transpower's advice on whether it has adequately allowed for easements and property costs of the type raised by the Perry Group and others, and impacts on farm infrastructure and farming operations as referred to by R Storey and others. Transpower notes comments from a number of submitters, but based on the information that Transpower has, the mitigation measures that Transpower has in place, the historical cost of properties that Transpower has purchased, and the cost of easements that Transpower is currently negotiating, Transpower has adequately allowed for easements and property costs. The construction of the transmission line may have some temporary affects on properties. Permanent affects are compensated through the payments made for the easement and the associated injurious affection to the remainder of the land. Temporary disturbance is generally associated with how construction access is obtained to the tower and stringing sites and what land use the construction company might need to install foundations, prefabricate and install towers. Transpower is proposing to use an Alliance contract for the transmission line, with one driver for this being the ability for such a contract to minimise temporary disturbance to land or farming operations. Alliance contracts permit a more flexible approach which will enable Transpower and the construction company to work with the landowner to achieve an optimum outcome. However, there will be times when temporary disturbance does cause costs for the landowner, and Transpower has allowed for this through the inclusion of an expected variance in the access track costs of up to 100%. The following are comments on the specific issues raised by the submitters Transpower agrees that there will be some disruption to the landowners during construction on the line but not to the extent that has been stated by some submitters. The scale of the expected effects and the mitigation measures have been fully documented in part VIII of the Notice of Requirements (NoR) that has been submitted to the councils. The NoR contains a large amount of information and for brevity a few of the most salient points relating to the impact on farm operations are included here: Vehicular access is required for construction and maintenance and the use of existing farm infrastructure is preferred. Where any new tracks need to be formed the location of the tracks will take account of topography and owners preferences. There will be between 15 and 50 heavy vehicle visits and up to 100 light vehicle visits per site, depending on the site. The work at the sites will be split into a number of distinct phases, tower foundations, tower structure erection and conductor installation: • Tower foundation construction is plant intensive and there will be up to 40 cubic metres (10 truckloads) of material from foundations removed from the site and a similar amount of concrete brought onto the site. Each is expected to take about 7 to 10 days. • The assembly and erection of the tower structures is expected to take about 10 days at each site and the laid out steel members assembled components and working room for plant will take up to 3600 square metres. 070606-EC-NIGU-FinalQuestionsD4.doc Mervyn English re: NIGU proposal - final questions Page 6 of 25 11 June 2007 • The conductor installation will have a very low impact on the majority of properties as the conductor stringing equipment will only need to be positioned every 3 to 5 km. It is also important to look at the size of the problem. Of the 298 landowners there are 85 owners that do not have towers on the properties. Transpower has drafted 90 access reports and presented them to 78 landowners already. Transpower owns or has agreements to buy 57 of the properties and more agreements are pending: most of these are properties that have towers located on them.. Relocation of existing buildings and facilities under the line Part of the ACRE process involved minimising the effects on the existing environment including existing infrastructure. The alignment that has been chosen by Transpower tried to avoid as many existing buildings as possible but, unfortunately all building could not be avoided. In a number of instances they have been properties where the impact on buildings has been significant. One of the recent submissions to the Electricity Commission indicated that there may be a requirement to rebuild a milking shed at a cost of approximately $700,000. Whilst it is not practical to discuss in this letter details of each instance where the works will require the removal of farming infrastructure, each instance will be dealt with in confidence with the property owner. Transpower has identified a number of cases where relocation of existing buildings and facilities under the line is likely to be necessary: the costs of these have been allowed for in Transpower’s cost estimates. 070606-EC-NIGU-FinalQuestionsD4.doc Mervyn English re: NIGU proposal - final questions Page 7 of 25 11 June 2007 Appendix C – Question 3 of 5 June Letter Question 3. Based on the information provided by Regis Park Stage 2 Limited (which the Commission provided at the meeting of 29 May 2007), please confirm whether Transpower considers it has allowed sufficient cost contingency within its application to use GIS at Brownhill Road, if this becomes necessary. Transpower has sought approval to “Plan the works, including the acquisition of designations, consents and easements to allow for future upgrade to 400 kV operation through future addition of […] a new switchyard in the vicinity of the transition station with new 400/220 kV transformers and associated works”. A likely location of this switchyard is Brownhill Road, on land that Transpower owns. Approval is sought only for the acquisition of designations, consents and easements for the switchyard, not for the capital cost of its construction. Its construction is likely to be after 2020, and separate approval will be sought for this as and when necessary. Obtaining approval for easements prior to construction in this manner reflects Transpower’s staged approval approach to grid upgrades, as a means to manage the risk of asset stranding and hence of inefficient costs. The scope of the approval sought does not state whether the switchyard will be AIS or GIS. The costs however are based on the assumption that it will be AIS. A GIS switchyard would cost approximately $12 million more, in 2006 dollars, than AIS. However, this is equivalent to an expected net market benefit difference of only about $2 million, as the additional cost would be incurred in two stages well into the future, nominally in 2021 (220 kV stage) and 2033 (400 kV stage). These costs allow only for capital including earthworks. A detailed assessment of costs and benefits at the time may show that the higher reliability, lower maintenance costs and longer life of the GIS could further compensate for any cost differences. Supporting the NIGU proposal, the capital costs of the switchyard’s construction is a modelled project (or strictly, a sequence of modelled projects) from 2021. The question could also be asked as to whether, if it were assumed to be GIS rather than AIS, this would affect the ranking of the proposal relative to alternatives in the GIT. The maximum effect on expected net market benefit would be a differential change of well under $2 million in favour of the 220kV alternative, as discussed above. However, given the contingency allowed for establishing a substation at Brownhill Road was approximately $4 million (in terms of expected net market benefit), such a change could not be considered significant as it is well within the potential P90 variability of the forecasts costs. In summary, Brownhill Road is the planned site for both the transition station, where the lines go underground, and the nearby switchyard, that will ultimately house the 220/400kV transformers. The issue raised in consultation was GIS for the switchyard, not for the transition station, which is a low and unobtrusive piece of infrastructure. The NIGU application specifies AIS for the transition station, and is silent on the type (AIS or GIS) for the switchyard. Transpower’s NOR provides for the switchyard (when it is finally built around 2021) to be based on either AIS or GIS technologies. Transpower therefore believes it has sufficient contingency in the proposal to allow GIS at the Brownhills site after 2020. 070606-EC-NIGU-FinalQuestionsD4.doc Mervyn English re: NIGU proposal - final questions Page 8 of 25 11 June 2007 Appendix D – Question 4 of 5 June Letter Question 4. In light of new information and issues raised during the conference, please will Transpower confirm the works covered by the proposal, and the 90% limit of project costs in 2011 dollars, which Transpower has previously stated as estimated as $824 million. The works covered by the proposal define the scope of the proposal. Transpower’s view remains that this is the appropriate scope of the proposal based on the best information to hand, noting that no substantiated arguments exist to justify a move away from these estimates. Transpower also notes that if unforeseen information comes to hand, the Rules provide for subsequent scope changes under rule 17.2. Transpower has engaged with stakeholders through the RMA consultation process in an open manner and accepts that some further design refinement is likely through that statutory process. Transpower’s expectation is that that design refinement is likely to stay within the project scope, and that the contingency amounts for which approval is sought will be sufficient with a high level of confidence. However, as noted above, neither Transpower, the Commission nor New Zealand has recent experience on obtaining consents and designations for a project of this nature and scale. It is impossible to predict all possible outcomes, let alone their precise probabilities, and hence despite reasonable endeavours Transpower’s “P90” figure may in reality be a “P80” or a “P95”, or some other, figure. The Rules do not prescribe what level of accuracy any cost cap must be, so this in no way affects the approval process, nor the process for any scope changes including project cost changes under Rule 17.2. Transpower notes that the Commission’s consultants (PBA consultants) estimate lower property costs than Transpower. While Transpower does not necessarily agree with PBA’s analysis, this may increase the Commission’s assurance. In summary, Transpower has made reasonable endeavours to determine an amount that has only a 10% chance of being exceeded, but the actual outcomes may differ from this. If the RMA process takes design refinement outside the project scope, then approval to that scope change will be required and would be sought by Transpower under Rule 17.2 as described under Question 1 above. Transpower requested approval in 2011 dollars at the bequest of Commission staff1. In summary, Transpower confirms that the scope of the project and the “P90” costs for which approval is sought remain appropriate. Transpower has been actively managing the risks from an early stage of the project, and is confident that the mitigation strategies and allowances that are already in place have identified the majority of risks and have been appropriately mitigated and costed. Transpower is confident that the amounts allowed for the easements will be adequate. Transpower has a process for estimating the easement costs that is consistent with the Public Works Act. One of the points brought up in the public conference was that Transpower’s easement calculations were too low because in areas where the existing ARI-PAK line was being replaced by the 400 kV line because Transpower were calculating the increase in injurious affection. In these areas Transpower is deducting the injurious effect of the existing ARI PAK 1 Transpower’s position has always been that ‘now dollars’ are more appropriate. Using future dollars introduces additional and unmanageable risk, which Transpower has endeavoured to allow for in the contingencies for the NIGU project. 070606-EC-NIGU-FinalQuestionsD4.doc Mervyn English re: NIGU proposal - final questions Page 9 of 25 11 June 2007 line from the injurious effect of the new 400 kV line and the easement value in the nett increase in injurious effect. This is consistent with the Public Works Act, with Land Information’s Assessment of Compensation2 (“Accredited Suppliers must offset betterment against compensation payable”), and has also been the approach taken by two independent valuers engaged by landowners. See also Appendix J on Betterment. Another point brought up was the 500 metre fire and burnoff restriction in the easement agreements. This is the subject of another question raised orally by the Commission on 8 June and is addressed in Appendices K. 2 Land Information, Assessment of Compensation, Accredited Supplier Standard 2, July 2002. 070606-EC-NIGU-FinalQuestionsD4.doc Mervyn English re: NIGU proposal - final questions Page 10 of 25 11 June 2007 Appendix E – Question 5 of 5 June Letter Question 5 Please advise whether Transpower accepts the Commission's recommendations to Transpower, as set out in the Commission's Reasons for Decision document dated 23 February 2007. Part F does not provide for the Electricity Commission to place conditions on approval of an investment proposal by Transpower: the Commission either approves, or declines to approve. The Commission's recommendations are therefore not part of the NIGU approval process. Nevertheless, Transpower takes any recommendations from the Electricity Commission, as the regulator of critical aspects of its business, very seriously. Transpower’s responses to the Commission's recommendations in its Reasons for Decision document are as follows. 070606-EC-NIGU-FinalQuestionsD4.doc Mervyn English re: NIGU proposal - final questions Page 11 of 25 11 June 2007 Appendix E1 - Recommendation (a) Recommendation (a) The Commission expects that Transpower will use efficient project management techniques to manage project costs and risks and, on an ongoing basis, will review the need date for the Proposal in light of changing circumstances, keeping in mind the need to avoid unnecessary early expenditure while ensuring that the relevant assets are commissioned before they are needed. As part of efficient project management, the Commission also expects that Transpower will demonstrate the need to incur costs before committing to costs, and will publish regular reports that set out the progress of implementing the Proposal against both expected costs and costs with contingencies, and the reason(s) for any divergence. Transpower has already committed to these matters as part of its application (section 2.2) or during the Grid Upgrade and Investment Review Policy (GUIRP) process: • Will conduct for the Transpower Board independent periodic audits of its project management, procurement and commercial processes to demonstrate that cost controls are in place, with a demonstration of the process of business improvement in response to any issues identified. • Will track and report project progress on its website, and send the Commission copies of those reports. Where it is likely that costs will exceed the approved “P90” amount or scope may need to change, Transpower will advise the Commission of this as soon as reasonable. • Will report periodically to the Transpower Board on progress against both expected costs and cost with contingencies, and reasons for any divergence (e.g. foreign exchange), allowing for indexed escalation or deflation of linked costs. • Acknowledges that to manage the project risk it is essential that a high degree of quality assurance is applied in planning, design, manufacture, commissioning, testing and maintenance activities in accordance with good electricity industry practice. Transpower will review the need date for the Proposal in light of changing circumstances, including information from customers, updated SOOs and the SSF. At this stage, Transpower is not aware of any new information that would cause it to delay the need date but has noted the Auckland rail electrification project timetable would introduce additional load by 2011, potentially bringing the need date forward. 070606-EC-NIGU-FinalQuestionsD4.doc Mervyn English re: NIGU proposal - final questions Page 12 of 25 11 June 2007 Appendix E2 - Recommendation (b) Recommendation (b) The Commission expects Transpower to use reasonable endeavours to obtain consent under the Resource Management Act 1991 for the Pakuranga substation to be equipped with AIS rather than GIS. The Commission notes that it is not clear that GIS will be required at Pakuranga, and although the Commission’s approval will cover the construction and commissioning of a GIS switchyard, the Commission views this as effectively a contingency. The Commission expects Transpower to diligently seek to minimise project costs and, if the construction of an AIS switchyard results in lower overall costs, the Commission expects Transpower to actively seek this outcome. Transpower included costs of GIS in its proposal. However, Transpower as a requiring authority has included AIS for the Pakuranga substation in its NOR. This is then the base from which the RMA process works. Transpower will endeavour to achieve the most appropriate outcome that satisfies Transpower’s statutory obligations under the RMA, while maintaining reliability standards and good electricity industry practice, meeting the need date and seeking to minimise project costs. Transpower notes the residential nature of the land surrounding the Pakuranga site and the relative scale differences between a GIS and AIS development. The relative impacts on the site are shown in the two diagrams below: Figure 1: Possible GIS development at Pakuranga 070606-EC-NIGU-FinalQuestionsD4.doc Mervyn English re: NIGU proposal - final questions 11 June 2007 Figure 2: Possible AIS development at Pakuranga 070606-EC-NIGU-FinalQuestionsD4.doc Page 13 of 25 Mervyn English re: NIGU proposal - final questions Page 14 of 25 11 June 2007 Appendix E3 – Recommendation (c) Recommendation (c) The Commission expects that Transpower will provide to the Commission as soon as possible an asset capability statement regarding the intended rating of the assets to which the Proposal relates, their electrical characteristics, and the reliability and availability expected for the assets. The asset capability statement must be consistent with performance assumed in applying the GIT, for example, the asset capability statement should include the expected single circuit and double circuit forced outage rates, with an expected repair time. The asset capability statement must also be consistent with the proposed interconnection rules. Transpower, as the Grid Owner, will provide asset capability information on its proposed assets at various stages of the construction and commissioning process in accordance with the EGRs: Planning Stage Transpower will submit a preliminary Asset Capability Statement (ACS) to the System Operator at the planning stage up to and including equipment procurement or tender. Pre-Commissioning Stage Transpower will provide an updated ACS to the System Operator once equipment procurement has been committed to. This will include results of compliance testing and an assurance that critical "system" settings have been determined. Post Commissioning Stage During and following the commissioning programme the Asset Owner will provide a further updated ACS. More details can be found in the Asset Capability Information Overview document at www.transpower.co.nz3. Contents of the Grid Owner ACS Note that the ACS spreadsheet provided by the System Operator sets out all the asset capability information that the Grid Owner is required to provide. A downloadable copy can be found at www.transpower.co.nz5. Transpower will of course also provide information as required by new rules such as the proposed interconnection rules as they come info force. 3 http://www.transpower.co.nz/notion/share/download.asp?cid=5962&csid=22691&mdid=&file =%2Fupload%2Fnotion%2Fsectionimages%2F22691%5F19012%5Facs%2Dinformation%2 Doverview%2Epdf 4 http://www.transpower.co.nz/notion/share/download.asp?cid=5960&csid=18999&mdid=&file =%2Fupload%2Fnotion%2Fsectionimages%2F18999%5Fgrid%2Downer%2Dacs%2Exls 5 http://www.transpower.co.nz/notion/share/download.asp?cid=5960&csid=18999&mdid=&file =%2Fupload%2Fnotion%2Fsectionimages%2F18999%5Fgrid%2Downer%2Dacs%2Exls 070606-EC-NIGU-FinalQuestionsD4.doc Mervyn English re: NIGU proposal - final questions Page 15 of 25 11 June 2007 Appendix F – Question 1 of 5 June Letter’s Appendix With reference to drawing AFGL.400.SK14, in calculating the proposed easement widths, can Transpower please advise what assumptions have been made for cross-arm widths for each of the 220 kV and 400 kV cases considered? The following crossarm widths (bottom crossarm) have been used in the calculation of the average span easement widths as shown in drawing ADGL.400.SK14: • 220kV, duplex Chukar 13.4m • 220kV, triplex Sulphur 13.4m • 400kV, duplex Rimu • 400kV, triplex Sulphur 17.1m 17.1m Although these are the same for each set of voltage options, they are considered to be appropriate for the level of analysis undertaken, and are based on preliminary tower head clearance diagrams. These tower head clearance diagrams take account of insulator length, conductor swing, insulator swing angles, safe climbing clearances under everyday wind, electrical clearances under maximum wind and energised working clearances. 070606-EC-NIGU-FinalQuestionsD4.doc Mervyn English re: NIGU proposal - final questions Page 16 of 25 11 June 2007 Appendix G – Question 2 of 5 June Letter’s Appendix What other parameters, including the conductor blow-out (e.g. audible noise), were considered and which of these were key to the final proposed easement widths? As per the submission titled "Response to Electricity Commission Questions of 13 April 2007", Transpower has checked all relevant electrical design parameters, i.e. RFI/EF/MF/AN for their respective limits at the edge of the easement or under the conductor as relevant, and for conductor swing. In all cases except for the original duplex Rimu 400kV option, the key parameter for determining the final proposed easement width is conductor swing. The change to a triplex bundle at 400kV removes audible noise as the limiting factor. Similarly, at 220kV, none of the electrical parameters control for easement width. 070606-EC-NIGU-FinalQuestionsD4.doc Mervyn English re: NIGU proposal - final questions Page 17 of 25 11 June 2007 Appendix H – Question 3 of 5 June Letter’s Appendix In Transpower’s explanation provided on 7 May 2007- paras 26 to 30 Transpower explain that 'purchasing an additional strip of land further from the centreline is less costly, as the majority of the “fixed cost” has already been paid". There is a substantial fixed cost component related to valuation and negotiation costs, visual effects, and effect on the land. However, the explanation given here is at odds with Transpower's treatment of the 220kV alternative when a change of conductor from duplex Chukar to triplex Sulphur was investigated. The document "NIGUP Conductor Options Easement Width Comparison" (a drawing of the conductor easement widths) shows that the increase in easement width is from 51m to 55m, a 4m increase. The Transpower document "FurtherInformationInResponseToECQuestions17January2007" states that the easement width increase is 5m (para 131). That document also shows in Table 13, that the easement cost increased from $55.4M to $63.6M. Assuming the later information on the easement width increase is more accurate (the 4m), then the percentage increase in easement width was 7.8%, but the percentage increase in easement cost was 14.8%. This means the easement cost increased at nearly twice the rate of increase in width - ie more than proportionally, directly contradicting the explanation given. Had easement costs increased at only half the rate of increase of width (arguably more consistent with the explanation given), the easement cost increase would have been $2.17M, not the $8.2M used by Transpower in their evaluation of the triplexed 220kV alternative. The Commission would appreciate receiving Transpower’s response to these points by COB 11 May 2007 to enable the Commission to prepare for the upcoming public conference. Whilst investigating this query from the Commission with respect to property costs assumed for the economic comparison of duplex Chukar and triplex Sulphur conductor configurations for the 220kV option, an error in the original analysis was uncovered. The property cost used for the 220kV option was understated by approximately $5m. The error arose because the property cost used in the economic analysis related to an outdated 220kV conductor configuration. Rather than the selected duplex Chukar configuration, the reported property cost related to a duplex Zebra configuration, with considerably shorter towers. The originally used property costs and amended plus newly calculated costs are summarised in the table below. Property cost, $ million Tower height Easement width Conductor configuration Variable Fixed Total Originally reported 220kV 40 50 duplex Zebra 47.4 8 55.4 55.4 220kV 48 51 duplex Chukar 52.1 8 60.1 220kV 50 55 triplex Sulphur 61.4 8 69.4 63.6 400kV 60 65 triplex Sulphur 72.6 8 80.6 80.0 400kV 61 65 triplex Sulphur 73.5 8 81.5 070606-EC-NIGU-FinalQuestionsD4.doc Mervyn English re: NIGU proposal - final questions Page 18 of 25 11 June 2007 The original numbers were based on rounded numbers, including tower heights and easement widths rounded to the nearest 5m. The recalculated numbers are based on tower heights and easement widths calculated to the nearest 1m. Affect of revised property costs Amending the economic analysis to reflect the correct 220kV property cost, using the Jan 07 NPV model, results in the overall difference between the 400kV proposal and 220kV alternative changing from approximately $11 million to $16 million, in favour of the proposal. With respect to the comparison of duplex Chukar and triplex Sulphur in the 220kV option, the difference between the two, using the Jan 07 NPV model, would change from approximately $4 million, in favour of the duplex Chukar, to $5 million in favour of the duplex Chukar. This again is in favour of the proposal. Further detail of total Property cost For Commission understanding the following table shows a more detailed build-up of the property costs, illustrating how the main three parameters in calculating the compensation cost affect the various elements of the cost. Tower height Easement width Conductor configuration Easement Corridors of Affect Dwelling, Curtilage Total Fixed Total 220kV 40 50 duplex Zebra 14.8 17.1 15.4 47.4 8.0 55.4 220kV 48 51 duplex Chukar 15.1 20.6 16.4 52.1 8.0 60.1 220kV 50 55 triplex Sulphur 16.3 21.4 23.6 61.4 8.0 69.4 400kV 60 65 triplex Sulphur 19.3 25.7 27.6 72.6 8.0 80.6 400kV 61 65 triplex Sulphur 19.3 26.1 28.1 73.5 8.0 81.5 The various cost elements are explained further in the document, “Public Works Act 1981, Guide to Assessing Compensation for Compulsory Acquisition”, dated April 2004. Transpower is prepared to release this document to the Commission for the purposes of this analysis, under a confidentiality agreement. 070606-EC-NIGU-FinalQuestionsD4.doc Mervyn English re: NIGU proposal - final questions Page 19 of 25 11 June 2007 Appendix I – Question 4 of 5 June Letter’s Appendix Submitters have raised with the Commission that that the property rights sought by Transpower are more extensive than such rights sought by other utilities, and, therefore, Transpower has underestimated how much it will cost to obtain these rights. In addition, the recent decision by the Environment Court in relation to the case between Transpower and Fernwood Dairies, has emphasised that the exclusive occupation of land by Transpower gave it an interest in the land that was not merely an easement. The Commission is currently seeking independent advice to: • investigate the issues raised in Perry Group, Manukau City Council and Dianne Allen submissions; and • confirm and/or provide a revised view of easement, property costs and likely non-technical environmental mitigation costs associated with Transpower’s Proposal A preliminary response to question 4 was sent to the EC on Tuesday 15th of May 2007 Further to our response by Email of the 15th of May and our meeting on Friday 11th of May 2007, the following is an updated response on question 4 of the questions emailed by John Gleadow to Tim George on Tuesday 8th of May and a copy of Transpower’s latest easement document was supplied by Email to John Gleadow on Thursday 8th of June 2007. A more comprehensive discussion on the subject is contained in the Appendix to this letter In the proposed easement agreement that the parties are referring there are restrictions to activities than can be undertaken within the easement itself, and the easement agreement also contains a clause regarding the lighting of fires or burnoffs within 500 m of either side of the transmission line easement. This clause was included as fires and burnoffs have been a source of line outages in the past and managing the burnoffs reduces the risk of loss of supply. Our the past few years Transpower has successfully negotiated easement agreements for a number of line upgrades including the easements for the third Islington Kikiwa circuit and the second Blenheim Stoke circuit. The actual distance in the easement agreements has been negotiated with individual landowners but preferred distance is 500 metres either side of the easement The easement agreement does not prevent the lighting of fires or burnoffs within the easement or 500 m either side but it places a requirement on the grantor (landowner / occupier) to get prior written consent to light fires or burnoff within the easement or within 500 metres from the grantee (Transpower), and specifically states that the consent will not be unreasonably withheld or delayed. Transpower’s preferred easement conditions are those lodged with LINZ on the 1st May 2007 that contained the 500 m restriction on lighting fires and burnoffs within 500 metres of the easements to manage the risk of fires under lines causing outages. But as a result of recent discussions with Landowners and Landowner Groups in the South Island, Transpower also has another standard easement agreement that has the words “or within 500 metres of the easement area” removed from the easement agreement. With this easement agreement the fire risk will be managed by having access agreements with adjacent landowners. The agreements will contain requests for landowners to notify Transpower before lighting fires or initiating burnoffs within 500 metres of the easement but it will be voluntary and not mandatory. 070606-EC-NIGU-FinalQuestionsD4.doc Mervyn English re: NIGU proposal - final questions Page 20 of 25 11 June 2007 The 500 metre requirement in the easement agreement was purely related to the requirement to obtain consent from Transpower before lighting fires or burnoffs, which is a prudent risk management exercise and Transpower does not consider that this unduly restricts the activities either side of the easement. All easements will be negotiated with individual landowners and Transpower will attempt to get the 500 metre (or a lesser amount) restriction on lighting fires included in easements but the backup position is the use of the easement terms without the 500 metre restriction included in clause 1.1 (h). As the inclusion of the 500 metre (or lesser amount) clause in the easement agreement will negotiated with individual landowners, Transpower considers that there is definitely no case to claim that there is an unreasonable restriction to activities either side of the easement, and that the assertion by the three parties that the easement costs have been underestimated by Transpower is not justifiable. 070606-EC-NIGU-FinalQuestionsD4.doc Mervyn English re: NIGU proposal - final questions Page 21 of 25 11 June 2007 Appendix J – Betterment – Increase in Injurious Effect The procedure for the assessment of compensation claims in New Zealand is contained within the Part V of the Public Works Act (PWA) 1981. Section 62(1) provides for the assessment of compensation payable under the PWA for: • Land taken • Land injuriously affected; and • Other Injurious affection is the term used to denote a probable loss of value due to a lawful action by a public authority other than the acquisition of the property itself. The provision of betterment is contained within Section 62(e) of the PWA: “The Tribunal shall take into account by way of deduction from that part of the total amount of compensation that would otherwise be awarded on any claim in respect of a public work that comprises the market value of the land taken and any injurious affection to land arising out of the taking, any increase in the value of any land of the claimant that is injuriously affected, or in the value of any other land in which the claimant has an interest., caused before the specific date or likely to be caused after that date by the work or the prospect of the work”. Australian and British case law supports the principal of betterment. Similar in New Zealand, Queensland, Section 20(3), Acquisition of Land Act 1967 provides that in assessing the compensation to be paid, “there shall be taken into consideration , by way of off-set or abatement, any enhancement of the value of interest of the claimant in any land adjoining the land taken or severed there from by the carrying out of the works or purpose for which the land is taken.” By Section 20(4), in no case shall Section 20(3): “operate so as to require any payment to be made by the claimant in consideration of such enhancement of value”. The Queensland provision restricts the enhancement provision to severance of adjoining land and is the only statutory provision governing enhancement in Australia. This is similar to betterment in the Public Works Act and we would expect application of the same provisions to be applied in New Zealand legislation. Betterment relates to the improvement, or enhancement, in the value of real property. For transmission lines, betterment may occur where the activity decreases the negative impact of the transmission lines to the value of the property. Any claim for injurious affection must take into account, by way of deduction from the total amount of compensation that would otherwise be awarded, any increase in the value of the land of the claimant that is injuriously affected or in the value of any land in which the claimant has an interest caused by the work or the prospect of the work. This is commonly referred to as “betterment”. Betterment applies whether the increase in value occurs before the specified date or is likely to occur after the work commences. An example of betterment in the context of the work proposed by Transpower is the removal of the ARI-PAK A line which may be replaced by a new 400kV line or not replaced at all. The 070606-EC-NIGU-FinalQuestionsD4.doc Mervyn English re: NIGU proposal - final questions Page 22 of 25 11 June 2007 removal of the existing line from a property has the potential to increase the value of the land and any increase in value will be offset or abated from the compensation sum assessed. This means that in assessing compensation betterment will be deducted from any increase in value of land caused by the public work. It is also applied that betterment cannot be charged where there is no compensation payable or where the compensation payable is less than the betterment occurring to the land. Transpower having read the submissions relating to this matter, maintain that we have assessed compensation and the issue of betterment in accordance with the provision of the PWA. Transpower has been in discussions with a number of landowners concerning the quantum of compensation that is payable for the proposed works. We have received a number of valuations prepared by independent registered valuers on behalf of landowners and those independent landowner valuations have addressed the betterment offset of the ARI-PAK line. It should be noted that in a number of cases they have applied the same methodology as outlined above and, in our opinion, have correctly interpreted the relevant provisions of the PWA. Useful summaries of these issues are available on the LINZ website. 070606-EC-NIGU-FinalQuestionsD4.doc Mervyn English re: NIGU proposal - final questions Page 23 of 25 11 June 2007 Appendix K – Transpower Easement Conditions Historical Easement Conditions Our the past few years Transpower has successfully negotiated easement agreements for a number of line upgrades including the easements for the 3rd Islington Kikiwa circuit and the 2nd Blenheim Stoke circuit. In the easement agreement there are restrictions to activities than can be undertaken within the easement itself, and the easement agreement does contain a clause regarding the lighting of fires or burnoffs within either side of the transmission line easement. This clause was included as fires and burnoffs have been a source of line outages in the past and managing the burnoffs reduces the risk of loss of supply. The actual distance in the easement agreements has been negotiated with individual landowners but preferred distance is 500 M either side of the easement The clause in the easement agreement on fires and burnoffs within 500 m was originally inserted after discussions with the NZ forest owners association, and was intended to reduce the risk of line outages due to burnoffs near the line. The clause is there to ensure that if there were planned burnoffs within 500 m of the either side of the line then the owners / occupiers would get consent from Transpower before the burnoffs took place. Transpower could then evaluate the risk to the power system and if the was deemed to be too high then Transpower would negotiate a more suitable time with the landowner / occupier or arrange for alternative methods of clearing vegetation. The easement agreement does not prevent the lighting of fires or burnoffs within the easement or 500 m either side but it places a requirement on the grantor (landowner / occupier) to get prior written consent to light fires or burnoff within the easement or within 500 metres from the grantee (Transpower), and specifically states that the consent will not be unreasonably withheld or delayed. Transpower did intend to use the same easement terms going forward, and as such these easement terms (with the 500m fire restriction clauses) were sent to Land Information New Zealand (LINZ) for approval as a memorandum under section 155A of the Land Transfer Act 1952 on 1 May 2007. The easement terms were approved on 3 May 2007 by Warren Moyes as Acting Registrar-General of Land and then registered in the Land Registry Office. Registration was complete on 7 May 2007. The easement terms have also been reviewed by Crown Property Clearances at Land Information New Zealand and no concerns were raised regarding this provision. 070606-EC-NIGU-FinalQuestionsD4.doc Mervyn English re: NIGU proposal - final questions Page 24 of 25 11 June 2007 2 GRANTOR’S OBLIGATIONS 2.1 The Grantor will not, without the prior written consent of the Grantee (which will not be unreasonably withheld or delayed), do or allow the following to be done: (a) alter or disturb the present grades and contours of the surface of the Easement Area except in the course of normal farming and grazing operations (but subject to the restrictions set out in this Easement Instrument) or otherwise with the prior written consent of the Grantee on each occasion; (b) (c) erect any building or other structure (including fences) on the Easement Area; plant any vegetation on the Easement Area that will or may when fully grown exceed 2.5 metres in height or breach any legal requirement applying from time to time regarding vegetation near electricity lines; (d) operate any Equipment or Vehicles on the Easement Area within a minimum clearance distance of 6 metres from any electricity transmission line conductor; (e) excavate or deposit material on the Easement Area; (f) impede the Grantee’s access over the Easement Area and any agreed access routes over the Land or damage the surface of the agreed access routes; (g) knowingly cause or permit flooding of the Easement Area; (h) light any fires or burn off vegetation within the Easement Area; or within 500 metres of the Easement Area: (i) carry out a “subdivision of land” (as defined in section 218 of the Resource Management Act 1991) of the Land; or (j) do any other thing on the Land which may cause damage to the Works or endanger the continuity or safety of the supply and distribution of electricity. Revised Easement Conditions Transpower’s preferred easement conditions are those lodged with LINZ on the 1st May 2007 that contained the 500 m restriction on lighting fires and burnoffs within 500 metres of the easements to manage the risk of fires under lines causing outages. But as a result of recent discussions with Landowners and Landowner Groups in the South Island, Transpower also has another standard easement agreement that has the words “or within 500 metres of the easement area” removed from the easement agreement. With this easement agreement the fire risk will be managed by having access agreements with adjacent landowners. The agreements will contain requests for landowners to notify Transpower before lighting fires or initiating burnoffs within 500 metres of the easement but it will be voluntary and not mandatory. 070606-EC-NIGU-FinalQuestionsD4.doc Mervyn English re: NIGU proposal - final questions Page 25 of 25 11 June 2007 The grantors obligations in the easement agreement lodged on 21st may 2007 now read: 2 GRANTOR’S OBLIGATIONS 2.1 The Grantor will not, without the prior written consent of the Grantee (which will not be unreasonably withheld or delayed), do or allow the following to be done: (k) alter or disturb the present grades and contours of the surface of the Easement Area except in the course of normal farming and grazing operations (but subject to the restrictions set out in this Easement Instrument) or otherwise with the prior written consent of the Grantee on each occasion; (l) erect any building or other structure (including fences) on the Easement Area; (m) plant any vegetation on the Easement Area that will or may when fully grown exceed 2.5 metres in height or breach any legal requirement applying from time to time regarding vegetation near electricity lines; (n) operate any Equipment or Vehicles on the Easement Area within a minimum clearance distance of 6 metres from any electricity transmission line conductor; (o) (p) excavate or deposit material on the Easement Area; impede the Grantee’s access over the Easement Area and any agreed access routes over the Land or damage the surface of the agreed access routes; (q) knowingly cause or permit flooding of the Easement Area; (r) light any fires or burn off vegetation within the Easement Area; (s) carry out a “subdivision of land” (as defined in section 218 of the Resource Management Act 1991) of the Land; or (t) do any other thing on the Land which may cause damage to the Works or endanger the continuity or safety of the supply and distribution of electricity. The 500 metre requirement in the easement agreement was purely related to the requirement to obtain consent from Transpower before lighting fires or burnoffs, which is a prudent risk management exercise and Transpower does not consider that this unduly restricts the activities either side of the easement. All easements will be negotiated with individual landowners and Transpower will attempt to get the 500 metre (or a lesser amount) restriction on lighting fires included in easements but the backup position is the use of the easement terms without the 500 metre restriction included in clause 1.1 (h). As the inclusion of the 500 metre (or lesser amount) clause in the easement agreement will negotiated with individual landowners, Transpower considers that there is definitely no case to claim that there is an unreasonable restriction to activities either side of the easement, and that the assertion by the three parties that the easement costs have been underestimated by Transpower is not justifiable. 070606-EC-NIGU-FinalQuestionsD4.doc
© Copyright 2026 Paperzz