Transitional Registration Plan Transitional Registration Plan 17 th May 2017 Version 4.0 © EirGrid 2017. Commercial In Confidence. Page 1 Transitional Registration Plan Revision History Summary of Changes Version Date Revised By First Publication 1.0 14th Oct 2017 I-SEM Project Second Publication 2.0 6th Dec 2017 I-SEM Project Correction of Table 1 NEMO Trading Application Date to 07/08/2017 2.1 17th Jan 2017 I-SEM Project Updates based on Finalisation of I-SEM Programme Change Request 3.0 13th February 2017 I-SEM Project 3.1 6th March 2017 I-SEM Project 3.2 20th March 2017 I-SEM Project 4.0 17th May 2017 I-SEM Project Provisional version with re-planned dates based on stocktake outcome. Changes are subject to I-SEM Programme Change Request Approval - Update of all timeline diagrams (Figures 2, 3, 4, 5, 6, 7), particularly Figure 7 for Capacity Market correction of dates in tables (Tables 1, 2, 3, 7) - Included Level 2 milestone references in [brackets] - Section 6.4.3 clarification on Parameter Decisions narrative Minor updates throughout the document e.g. reference to SEMOpx as official name for EirGrid/SONI Exchange; correction of typos. Figure 3 & 5, and Table 5: Update to clarify that “SEMOpx application deadline” is the deadline for inclusion in Market Trial. Figure 5 – amended typo in date for “New Member NCM/DCP Documentation Deadline” to 1st Dec 2017 Update to Transitional Accession process for TSC and CMC. Figure 2, 3, 4, 7 – added in draft Framework Agreement (FWA) send to Party and returned by Party, removed Accession Deed dates and updated TSC FWA deadline. Table 1 – added draft FWA submission date (unsigned), removed Accession Deed dates, and updated TSC FWA deadline. Table 2 –added draft FWA issue date. Section 4.4.5, 6.1.3, 6.4.3 – under “Framework Agreements” heading. Updated text to represent revised process. Table 3 - removed Accession Deed dates, and updated and added TSC FWA dates. Section 5.1.1. under “General” heading. Updated assumption 4 to need to revalidate Parties as part of FWA signing. Table 4 & 7– added draft FWA send to Party and returned draft FWA from Party, removed Accession Deed dates, and updated TSC FWA deadline. Section 1 – addition of NCM to glossary Section 4.3 Figure 2 – added Market Trial Agreement milestones, adjusted AoLR registration timelines, added intermediary application deadline, added banking arrangements confirmation deadline. Section 4.4.2.1 Table 1 – reordered entries to be in deadline chronological order, added in intermediary application deadline based on new Level 2 milestone #159, amended intermediary approval milestone based on Level 2 plan CR, amended AoLR application deadline, included SEMOpx Framework Agreement signing milestones, included Market Trial Agreement signing deadline, included banking arrangements confirmation deadline. Section 4.4.4.1 Table 2 – included issuing of Market Trial Agreement and draft SEMOpx Framework Agreement Section 4.4.4.2 Table 3 – amended intermediaries milestone to match change in I-SEM level 2 milestone © EirGrid 2017. Commercial In Confidence. Page 2 Transitional Registration Plan Summary of Changes Version Date Revised By Section 4.4.5 Framework Agreements – added text to say separate SEMOpx Framework Agreement needed NEMO Markets – added text to convey that banking arrangements do not need to be in place for 7th August 2017 but by the 7th Feb 2018 and that SEMOpx Framework Agreement needs to be signed. Added Market Trial Registration heading and text. Section 5 Figure 3 – added details on market trial registration, added details on SEMOpx framework agreement signing process, amended AoLR registration timelines, amended existing ECC member documentation deadline, included banking agreement confirmation deadline, added in intermediary application deadline, amended intermediary approval milestone RA approval milestone. Section 5.1.3 – included assumption that on SEMOpx Framework Agreement signing. Section 5.1.4 – amended dates for AoLR activities Section 5.1.5 – amended duration of first capacity auction and footnote on same. Section 6.1.1 Table 4 – included draft Framework Agreement issued for signing date, included intermediary application deadline, included intermediary confirmation submission deadline. Section 6.1.2 Figure 4 - added Market Trial Agreement milestones, added intermediary application deadline, RA approval date for intermediaries, additional activities for Framework Agreement Signing. Section 6.1.3 Framework Agreements - added more detail on Framework Agreement signing process and dates. Intermediary Arrangements – included heading and text on intermediary approval process and dates. Section 6.2.1 Table 5 – included dates related to SEMOpx Framework Agreement Signing, included Banking Confirmation Deadline, amended Existing ECC Member application deadline Section 6.2.2 Figure 5 – amended diagram in line with changes made to Table 5 Section 6.2.3.1 SEMOpx Trading Rules - elaborated on details for signing up to SEMOpx Trading Rules Section 6.2.3.2 Deadlines for Go-Live Registration – amended date for Existing ECC member’s application deadline line. Confirmation of Banking Agreements – added heading and text to describe milestone ECC Registration Deadlines – added heading, text and Table 6 to explain milestone dates. Section 6.3.1 Table 6 – adjusted dates relate to AoLR key dates. Section 6.3.2 Figure 6 – amended diagram in line with changes made to Table 6. Section 6.4.1 Table 7 – added additional date related to Framework Agreement signing, added in new intermediary application deadline, clarified that unit qualification includes confirmation of intermediary. Section 6.4.2 Figure 7 – amended diagram in line with changes made to Table 7. Section 6.4.3 Framework Agreements - added more detail on Framework Agreement signing process and dates. Intermediary Arrangements – included heading and text on intermediary approval process and dates. © EirGrid 2017. Commercial In Confidence. Page 3 Transitional Registration Plan 1. Glossary of Terms Acronym/Abbreviation Definition AoLR Agent of Last Resort BLG Business Liaison Group CCC Coordinated Capacity Calculation CCQT Communication Channel Quality Testing CER Commission for Energy Regulation (Ireland) CFD Contract for Difference CM Capacity Market CMC Capacity Market Code DAM Day Ahead Market DCP Direct Clearing Participant DSU Demand Side Unit ECC European Commodity Clearing (DAM/IDM Clearing House) FTR Financial Transmission Rights IDM Intraday Market I-SEM Integrated Single Electricity Market JAO Joint Allocation Office KYC Know Your Customer MDP Meter Data Provider MO Market Operator NCM Non-Clearing Member NEMO Nominated Electricity Market Operator RAs Regulatory Authorities SEMO Single Electricity Market Operator SONI System Operator Northern Ireland TOD Technical Offer Data TSC Trading and Settlement Code TSO Transmission System Operator UR Utility Regulator (Northern Ireland) © EirGrid 2017. Commercial In Confidence. Page 4 Transitional Registration Plan 2. Contents 1. GLOSSARY OF TERMS .............................................................................................................................. 4 3. INTRODUCTION ....................................................................................................................................... 6 3.1 3.2 3.3 4. HIGH LEVEL (ALL MARKETS) PLAN ............................................................................................................ 8 4.1 4.2 4.3 4.4 5. CONSIDERATIONS ....................................................................................................................................... 8 PRINCIPLES ............................................................................................................................................... 8 HIGH LEVEL OVERVIEW ............................................................................................................................. 10 KEY DATES .............................................................................................................................................. 11 DETAILED (ALL MARKETS) PLAN............................................................................................................. 18 5.1 5.2 6. PURPOSE .................................................................................................................................................. 6 BACKGROUND ........................................................................................................................................... 6 SCOPE...................................................................................................................................................... 6 ASSUMPTIONS ......................................................................................................................................... 20 PRINCIPLES ............................................................................................................................................. 22 PLANS BY MARKET/SERVICE .................................................................................................................. 23 6.1 6.2 6.3 6.4 BALANCING MARKET ................................................................................................................................ 23 NEMO MARKET...................................................................................................................................... 27 AOLR SERVICE......................................................................................................................................... 31 CAPACITY MARKET ................................................................................................................................... 34 7. REGISTRATION FEES .............................................................................................................................. 38 8. FURTHER INFORMATION ....................................................................................................................... 39 © EirGrid 2017. Commercial In Confidence. Page 5 Transitional Registration Plan 3. Introduction 3.1 Purpose The purpose of this document is to clearly define the Transitional Registration Plan to be used for the transition from the SEM to I-SEM arrangements. It is intended to provide a basis for ensuring a common understanding between the TSO’s ISEM Project, Participants, Regulatory Authorities, and other Stakeholders on the transitional registration plan including activities, deadlines, timelines, and stakeholders’ obligations. 3.2 Background A transition is required from the SEM arrangements to the new I-SEM arrangements. One component of this is the registration of Parties, Participants and Units from the SEM to ISEM. In order to participate in the I-SEM, Participants will need to register: 1) Fully, including providing the required registration data and documentation, and having this information validated and approved; and, 2) In a timely manner, in order to participate in the mock auctions, Market Trial, official auctions and the I-SEM market Go-Live. The transition from SEM to I-SEM involves ensuring the registration of Parties, Participants and Units for a number of different markets each of which are subject to different governance arrangements. The I-SEM markets being: Forwards, Financial Transmission Rights, Day Ahead Auctions, Intraday Auctions and Continuous, Capacity. In addition the ISEM includes an Agent of Last Resort Service1. Therefore the transition is not simply transferring data from the old to new systems. It also involves Participants considering how they wish to set themselves up in the I-SEM under a new entity model, providing new registration data and supporting information, as well as potentially amending their existing registration data. 3.3 Scope This document focuses on the Transitional Registration Plan required for the markets which are administered by EirGrid and SONI as Market Operators, EirGrid and SONI as NEMO2, and EirGrid and SONI as Transmission System Operators. These markets are shown in Figure 1 circled in red. A single ‘I-SEM Registration Team’ will be created to administer the registration processes for these markets. The Forwards and Financial Transmission Rights markets are planned to be administered by other organisations and are considered out of scope for discussion in this document.3 1 The AoLR is technically a service provided by SEMO to facilitate renewable and smaller Units participation in the DAM/IDM markets. For simplicity, when the term ‘market’ is used in this document it refers to both true markets i.e. Balancing, Capacity and DAM/IDM, as well as the AoLR service. 2 For simplicity NEMO is used in this document to refer to both the Day Ahead and Intraday Markets (Auctions and Continuous) as they are markets covered by the NEMO and for registration purposes are treated effectively as one. 3 However, the FTR market will was covered as part of the Registration Business Liaison Group scheduled for the 19th October 2016. © EirGrid 2017. Commercial In Confidence. Page 6 Transitional Registration Plan Figure 1: Markets and Registration Organisations Registration activities involve the collection, validation and approval of registration data, and other related supporting documentation, which are needed to run the market systems and processes for DAM/IDM Trading, Balancing Market and Imbalance Settlement and the Capacity Market, as well as the AoLR Service. This document excludes from its scope other activities that are required for a successful GoLive which are covered by other TSO I-SEM Project work streams, including – but not limited to – Market Readiness, Market Trial, and Cutover. © EirGrid 2017. Commercial In Confidence. Page 7 Transitional Registration Plan 4. High Level (All Markets) Plan 4.1 Considerations There are a number of considerations that have influenced the development of the Transitional Registration Plan. Namely: • • • • • • • • • Multiple markets (Balancing, DAM, IDM, Capacity) New services (AoLR) Different organisations involved in provision of services ( SEMO, ECC, SEMOpx, TSOs) A revised entity model for the Balancing Market and different entity setups for different markets Registration data needing to be transitioned e.g. Balancing Market New registration data required e.g. Capacity Auction, NEMO, AoLR, new unit types Additional or new requirements e.g. Capacity qualification criteria Existing agreements needing to be re-signed e.g. Framework Agreements The Capacity Auction being prior to I-SEM Go-Live and near the start of Market Trial These considerations mean that the transitional registration from SEM to I-SEM is not a simple transfer of data between systems, but requires dedicated and concerted registration plan and activities. However, in achieving this transition, the Transitional Registration Plan aims to minimise the repetition of the submission of data and make the registration process as efficient as possible. 4.2 Principles In preparing the Transitional Registration Plan there were a number of principles which were considered. References to dates and activities in this section are outlined further in section 4.3. 4.2.1 Reuse of Registration Data Where possible, information will not be asked repeatedly for each market. Any registrations for additional markets should build on previously submitted information and not require resubmission of the same information. Where possible, the existing SEM data will be used as the basis for the I-SEM. Participants will be required to confirm the accuracy of the data. This will help to reduce the registration burden for Participants transitioning to the I-SEM. 4.2.2 Registration Data Ready prior to Mock Auctions/Market Trial For the Capacity Market, the intention is to have the registration/qualification process completed prior to the mock auctions to allow for more realistic mock auctions and also to mitigate risks of delays in the first auction arising from registration data issues. For Balancing, NEMO and AoLR, the goal is to have registration data ready for the Market Trial. This will allow the Market Trial to be based on data that is as close to final registration data as possible; allowing better quality trialling and less risk in the transition to Go-Live. © EirGrid 2017. Commercial In Confidence. Page 8 Transitional Registration Plan 4.2.3 Submission Deadlines Deadlines will be identified for the submission of registration information to ensure that the relevant registration activities are completed in time for participation in the Market Trial and/or Go-Live. 4.2.4 Market Trial will become Go-Live Systems Once approved, the registration data used in the Market Trial will become the Go-Live registration data. This will avoid the need for duplicate registration processes and mitigate risks of associated with a different Go-Live set of systems, logins etc. to those used for the Market Trial. 4.2.5 Formal Registration Approval after Market Trial (but prior to Auction/GoLive) There will also be a need for ‘Final Registration Requirement’ activities e.g. collateral in place, bank accounts confirmed. These must be in place prior to issuing Commencement Notices (toward the end of Market Trial). These registration requirements are not necessary for the start of Market Trial. This will reduce the registration requirements of Participants and the I-SEM Registration Team in the lead up to the Mock Auctions and Market Trial, and will prioritise the validation of registration data required for these Mock Auctions and the Market Trial. © EirGrid 2017. Commercial In Confidence. Page 9 Transitional Registration Plan 4.3 High Level Overview The high level plan below provides a broad indication of the timings and the key Participant deadlines for the registration in the I-SEM Markets Figure 2: I-SEM Transitional Registration (High Level Overview) © EirGrid 2017. Commercial In Confidence. Page 10 Transitional Registration Plan 4.4 Key Dates 4.4.1 Transitional Registration Types Three different types of registration approaches have been identified based on the status of the Party, Participant and Units during the Transitional Registration Process. These three types and the intended approach to each are provided below. Registration Type Existing SEM Participant (In SEM already) New SEM Participant (Will be effective after Submission Deadlines but prior to I-SEM Go-Live) New I-SEM Participant (Not in SEM at all) 4.4.2 Registration Approach • Transitional Registration Process applies • Registration Data/Information by Submission Deadlines • Inclusion in Market Trial and for I-SEM Go-Live • Enduring registration process applies • Must meet SEM and I-SEM requirements to obtain effective date (to avoid discontinuity in market participation) • Not guaranteed for inclusion in Market Trial4 • Will be included for Go-Live • Must be cognisant of Registration Lockdown Period • Enduring registration process applies • Will be effective after I-SEM Go-Live • Must be cognisant of Registration Lockdown Period Submission Deadlines The Transitional Registration Plan includes deadlines for the submission of registration information to ensure that the relevant registration activities are completed in time for participation in the Market Trial and/or Go-Live. Any applications received after the submission dates will follow the enduring registration process and, although reasonable endeavours will be taken, they cannot be assured of registration to take part in the Market Trial nor be registered before the first Capacity Auction or I-SEM Go-Live. The following are the main submission deadlines for each market/service as defined further in section 4.4.2.1. Registrations submitted after these dates will follow the enduring process and are not guaranteed of being completed for Market Trial or Go-Live. • 16th June 2017 for Balancing (for Units) (Market Trial) • 7th August 2017 for NEMO (Market Trial) • 28th July 2017 for Capacity Unit Participation in 2017/2018 Capacity Auction • 1st September 2017 for AoLR • 1st December 2017 for NEMO (Go-Live) – New Members (participation in Market Trial not guaranteed) 4 New Participants are not guaranteed of being able to participate in the market trial. However, reasonable endeavours will be made to include them at some point in the market trial. © EirGrid 2017. Commercial In Confidence. Page 11 Transitional Registration Plan 4.4.2.1 Participant Submission Deadlines The following table provides the key submission deadlines for Participants, as well as the dates the relevant forms or data will be made available on the I-SEM website, or ECC’s website for ECC forms. Table 1: Participant Submission Deadlines Submission Market/Function KYC Registration of NEMO Interest5 BAL Registration Data Balancing Draft Framework Balancing Agreements Submitted Capacity (unsigned) BAL Supporting Balancing Information Intermediary Balancing Applications (new Capacity intermediaries only) [159] TSC Framework Balancing Agreement Signed Capacity (Existing Parties) CMC Framework Balancing Agreement Signed Capacity (Existing Parties) CMC Unit Application Capacity NEMO SEMOpx NEMO Trading Application (for Market Trial) NEMO ECC KYC, New NEMO(ECC) Member, Existing Member Document Deadline (Market Trial) SEMOpx Draft NEMO Framework Agreement (SEMOpx) Submitted (unsigned) SEMOpx Framework NEMO Agreement Signed (SEMOpx) AOLR Application AoLR Market Trial Agreement ALL Signed NEMO ECC KYC & NEMO(ECC) New Member Document Deadline (Go-Live) NEMO ECC Existing NEMO(ECC) Member Document Deadline (Go-Live) NEMO ECC Banking NEMO(ECC) Confirmation Forms Available n/a Deadline Date 31/12/2017 18/11/2016 n/a 01/05/2017 15/05/2017 14/04/2017 16/06/2017 n/a 30/06/2017 14/04/2017 28/07/2017 14/04/2017 28/07/2017 14/04/2017 14/04/2017 28/07/2017 07/08/2017 28/02/2017 07/08/2017 01/09/2017 27/09/2017 01/09/2017 27/10/2017 01/09/2017 01/09/2017 27/10/2017 27/10/2017 28/02/2017 01/12/2017 28/02/2017 07/02/2018 14/04/2017 07/02/2018 5 The KYC registration of interest has been changed based on feedback from the Registration BLG. IT is now just a request to contact the I-SEM registration team to confirm the party may have an interest in being part of the DAM/IDM markets. The full KYC application form is not required until August 2017. © EirGrid 2017. Commercial In Confidence. Page 12 Transitional Registration Plan 4.4.3 Registration Lockdown Periods Based on feedback from the Registration BLG in October 2017, a shortening of the registration lockdown period has been made. From mid-April 2018 to 2 weeks after Go-Live no structural entity changes will be allowed e.g. new Parties, Participants, Units. This provides stability for the unscripted phase of Market Trial, cutover and avoids the risks of changes impacting on the operation of the market directly after Go-Live. This is seen as prudent as major changes in registration data are, from experience, the most common cause of production system issues. 4.4.4 Other Key Dates In addition to key dates relating to Participants, there are also key dates that relate to I-SEM Registration Team and Regulatory Authorities. These key dates are outlined below. 4.4.4.1 I-SEM Registration Team Key Dates The key dates for the publication of information needed by Participants to register for the different markets are shown in Table 2: Numbers in [brackets] indicate references to the Level 2 I-SEM Programme Plan Milestones. Table 2: I-SEM Registration Team Key Dates Publication Existing Entity Model Mapping to I-SEM Application Forms Issued Supporting Information Application Forms Issued Application Forms Issued Draft Framework Agreements Issued Auction Information Pack Issued Application Forms Issued Market Trial Agreement Issued Draft Framework Agreements Issued © EirGrid 2017. Commercial In Confidence. Market/Function Balancing NEMO ECC Balancing Issue Date 18/11/2016 28/02/2017 14/04/2017 NEMO SEMOpx Capacity Balancing Capacity Capacity AoLR ALL SEMOpx 14/04/2017 01/05/2017 03/07/2017 01/09/2017 01/09/2017 01/09/2017 Page 13 Transitional Registration Plan 4.4.4.3 Regulatory Key Dates The key dates for the Regulatory Input or approvals are: Table 3: Regulatory Key Dates Activity Capacity Parameters Decisions Published [133] TSC Approved Approval of Intermediaries for TSC and Capacity [162] CMC Approved Approval of Final Auction Parameters [165] Approval of Final Auction Qualifications [164] 4.4.5 Market/Function Capacity Issue Date 06/04/2017 Balancing Balancing Capacity Capacity Capacity Capacity 15/03/2017 14/07/2017 02/06/2017 01/12/2017 01/12/2017 High Level Overview Narrative The following narrative is provided with reference to Figure 2: I-SEM Transitional Registration (High Level Overview) on page 10. Go-Live Dates The key Go-Live dates are: a) Capacity Auction 15th December 2017 b) I-SEM Go-Live 23rd May 2018 The Capacity Auction occurs well before the official I-SEM Go-Live, at the start of the Market Trial. This constrains when Framework Agreements (both Trading and Settlement Code (TSC) and Capacity Market Code (CMC)) must be signed by, and when registration and qualification activities must be completed for the CMC. Interim Key Dates There are three major interim key dates: a) The approval of the CMC on 2nd June 2017 b) The approval of the TSC on 15th March 2017 c) The start of Market Trial on 1st December 2017 The Code approval dates impact on when official legal documentation (such as framework agreements) can be signed. The Market Trial start date impacts on when the registration data needs to be validated and approved. Sequential Registration Approach The registration process is not a ‘one-off’ event, but a sequential process that builds on the core Balancing Market registration, through to the NEMO and Capacity Market registrations, and finally the AoLR Service registration. The order of these registration submissions is based on the need to revise and update the core Balancing Market Unit information prior to using these Units in the DAM/IDM and Capacity Market. It also aligns with the timeline for the relevant market rule approvals, following which Participants will be able to consider their participation in the relevant markets and registration data requirements are confirmed. © EirGrid 2017. Commercial In Confidence. Page 14 Transitional Registration Plan This approach also distributes the workload for Participants and the I-SEM Registration Team more evenly over the time available, rather than requiring significant sets of registration applications to be submitted all at once. This will help to avoid the need to resubmit registrations where rules and data requirements change. The blue arrows in Figure 2 indicate how the information from one registration process feeds into the next, particularly for the Capacity Auction and Market Trial. Mapping of Existing Data The I-SEM Registration Team will extract the existing Balancing registration data, map it to the new I-SEM entity model, identify any new data needed, and provide this data to Participants in mid-Nov 2016 for validation. This allows the months of November-April (prior to the submission deadline at the start of May 2017) for Participants to obtain the additional data required and discuss any of their core entity setup requirements (i.e. Party, Participant, Units) with the I-SEM Registration Team and Regulators (if necessary). This approach also means that the bulk of the data required for registration is validated and approved as early as possible. Supporting Application Forms In April 2017, the I-SEM Registration Team will issue the supporting application forms required for the Balancing, NEMO SEMOpx and Capacity Market. These application forms will outline the information required to meet the registration and qualification criteria for these markets, providing plenty of time ahead of submission deadlines to collect information. The AoLR application forms will be provided later, in late May 2017. The NEMO ECC forms application forms will be available from the end of February 2017. Code Approvals The timing of many activities and approvals is highly dependent on the approval of the relevant Codes. This means that some activities can only be completed after the Codes come into force e.g. signing Framework Agreements. © EirGrid 2017. Commercial In Confidence. Page 15 Transitional Registration Plan Framework Agreements Parties must accede to the CMC separately to the TSC as these are agreements with different entities (i.e. TSO for CMC and MO for TSC). Therefore, Parties will be required to sign an updated CMC Framework Agreement by the 28th July 2017. In addition, there are changes to the TSC Framework Agreement proposed, which means that Parties will be required to sign the new TSC Framework Agreement by the 28th July 2017 as well. The timing of the TSC Framework Agreement has been changed to align with the CMC, in order to make the process as efficient as possible. The intention is that existing Parties to the TSC, as well as new Parties who are ready, will sign the two new Framework Agreements, with any new Parties signing up after the Framework Agreement signing to follow the enduring accession process. These Framework Agreements cannot be signed until the Code is approved. A separate Framework Agreement will also need to be signed with SEMOpx in order to participate in the NEMO markets. NEMO Markets This plan relates to registration with the SONI and EirGrid NEMO, namely SEMOpx. While the other registration processes covered by this plan relate to monopoly activities, NEMO Services are open to competition. At present, SONI and EirGrid are the only providers designated to offer these services in the I-SEM. These designations are based on SONI and EirGrid jointly delivering this service. In the absence of competition, this transitional registration plan aims to minimise the administrative burden on Participants. This plan will be reviewed6 if another NEMO is designated by UR and CER, or if a NEMO active in other markets passports into the I-SEM during the transition period. The NEMO markets are different to the other markets in that a high proportion of the registration process involves interaction and meeting registration requirements with ECC7. ECC advise that, given the number of Participants and the newness of the I-SEM, this process will take a considerable number of months. It involves Participants being able to meet ECC’s “Know Your Customer” criteria and also negotiate agreements with Settlement Banks/Clearing Member. Hence, these activities are shown as starting early but will end later than most of the other registration processes. In addition, ECC have defined a deadline for applications of early August 2017 if Participants wish to be ready for inclusion in the Market Trial (with the exception of banking agreements being in place).Based on participant feedback a later deadline has been added of early February 2018 for confirmation of banking agreements with a Clearing Member or Settlement Bank. It has been determined that participants will need to sign up to the SEMOpx rules using a similar legal instrument to the TSC and CMC. Namely signing of a Framework Agreement. Timelines are Sept/Oct 2017 6 This review will ensure that all NEMOs are operating on a level playing field, as required by CACM ECC (European Commodity Clearing) is the organisation that will provide the clearing house services for the DAM/IDM. This includes settlement and clearing of the completed trades. 7 © EirGrid 2017. Commercial In Confidence. Page 16 Transitional Registration Plan AoLR Registration The AoLR registration process dovetails with the NEMO registration process, as it is a prerequisite that Participants have their NEMO registration in place prior to the AoLR Service. Given this, AoLR registration, which should be fairly light in terms of content, will commence later in the timeline. Capacity Registration The Capacity Market registration is dependent on the registration setup of the Parties, Participants and Units will have in the Balancing Market, especially for the first T-1 Capacity Auction planned for December 2017. Therefore, the submission deadlines for the Capacity Market are later than those of the Balancing Market. As this is a new type of market involving an auction, it is anticipated Participants may take time to consider how they wish to approach this market. Generators8 will need to register their Units for the Capacity Market. Both Suppliers and Generators will need to sign the CMC Framework Agreement. Market Trial Registration In order to participate in the Market Trial a Party must sign the Market Trial Agreement. This is a formal agreement setting out the basis for the conduct of, and their participation in, the Market Trial. The deadline for completion of this activity in order to ensure inclusion in the Market Trial is the 27th October 2017. Final Registration Requirements There are a number of registration requirements that are not needed for the Market Trial, but are needed ahead of the actual Go-Live. These include the posting of collateral, amendments to bank accounts etc. The Transitional Registration Plan Overview in Figure 2 includes these as part of the ‘Final Registration Requirements’ activity. Commencement Notices will be issued in the last month of the Market Trial, once all final registration requirements have been met. This timing distributes the Transitional Registration activities, making them more manageable for Participants and the I-SEM Registration Team. It also eliminates the associated costs of having collateral in place too early. Registration Lockdown Based on feedback from the Registration BLG in October 2017, a shortening of the registration lockdown period has been proposed. The Transitional Registration Plan also includes a Registration Lock Down period. During this period, which starts toward the end of Market Trial and continues until after Go-Live, there will be no significant registration changes allowed in order to mitigate risks around the entry of new or changed registration data. Further details on this are provided in section Error! Reference source not found.. 8 Generators in this context refers to Generators, DSUs and Interconnectors © EirGrid 2017. Commercial In Confidence. Page 17 Transitional Registration Plan 5. Detailed (All Markets) Plan The Detailed (All Markets) Plan in Figure 3 below provides an in depth look at the overall ISEM transitional registration timeline and the interdependencies between the registration processes for each market. The Detailed (All Markets) Plan includes lower level milestones and detail on the activities required. It also includes differentiation of the activities based on the owner e.g. Participants, I-SEM Registration Team, ECC etc. A narrative has not been provided with the Detailed (All Markets) Plan as this is covered by the narratives under each market Transitional Registration Plan provided in Section 6 “Plans by Market/Service”, and is not repeated here. © EirGrid 2017. Commercial In Confidence. Page 18 Transitional Registration Plan Figure 3: I-SEM Transitional Registration Plan (All Markets - Detailed) © EirGrid 2017. Commercial In Confidence. Page 19 Transitional Registration Plan 5.1 Assumptions The following sections outline the key assumptions which the Transitional Registration Plan is based on. 5.1.1 General The CMC will be approved by 2nd June 2017. The TSC will be approved by the 15th March 2017. The signing of Framework Agreements cannot occur before the relevant Code comes into effect. Existing Parties to the TSC will need to re-accede to the TSC by signing the new Framework Agreement. Validation of these re-accessions will require review of the legal status of the Party and confirmation of the validity of the signatories to the Framework Agreement. The Market Trial systems will transition directly into the Go-Live production systems. Therefore, registration data setup in the Market Trial system will become the production registration data. All parameters required by the Regulators or other sources will be available before the application deadline. There will be no explicit fees related to the registration of Parties and Units for the Capacity and Balancing Markets for existing SEM Participants who complete applications in line with the registration submission deadlines. Collateral will need to be provided separately for the NEMO markets, and the Balancing/Capacity markets. 5.1.2 Balancing Market Existing Parties to the TSC will need to resign a Framework Agreement. Approximately 104 Parties and 390 Units will need to go through the registration process. The submission deadline for Balancing Market supporting information is the 16th June 2017. Registrations submitted after this date will follow the enduring process and are not guaranteed to be completed for Market Trial or Go-Live. Participants will need to setup new collateral accounts and letters of credit for the ISEM Balancing/Capacity collateral requirements due to different trust arrangements to the SEM. 5.1.3 NEMO I-SEM Registration will deal with the NEMO Exchange9 registration and the collection and validation of initial registration forms for the registration with the central counterparty, ECC. However, Participants will deal directly with ECC for the completion of registration with ECC and Clearing Members/Settlement Banks. 9 The NEMO consists of both the trading exchange (SEMOpx) and the central counterparty (ECC). In addition the SEMOpx utilises the services of EPEX to provide and operate the DAM/IDM trading systems . © EirGrid 2017. Commercial In Confidence. Page 20 Transitional Registration Plan Registration fees for the NEMO are likely to apply in the transition to I-SEM and Participants will need to pay these as part of the registration requirements (potentially as part of their first fee invoice after Go-Live). Parties will need to sign a SEMOpx Framework Agreement as part of the registration for the NEMO markets. 5.1.4 AoLR Registration fees for AoLR are likely to apply in the transition to I-SEM and Participants will need to pay these as part of the registration requirements (potentially as part of their first fee invoice after Go-Live). The AoLR will use the EirGrid and SONI NEMO for trading. Therefore, Participants wanting to use this service must be registered with SEMOpx. The submission deadline for AoLR applications is the 27th October 2017. Registrations submitted after this date will follow enduring process and are not guaranteed of being completed for Market Trial or Go-Live. 5.1.5 Capacity The signing of the CMC Framework Agreement can be completed at the same time as the TSC to minimise workload for Participants. Suppliers, Generators and Interconnectors will need to sign the Framework Agreement prior to the First Auction. The first auction will be a T-110 auction only, for capacity related to the May 2018 to Sept 2019 period11. Only capacity that is existing or will be commissioned before May 2018 will be qualified to register. Subsequent T-1, T-2, T-3, T-4 auctions will not be scheduled until Q1 2018. Therefore, registration and qualification activities for these auctions will not occur until Q4 2017 at the earliest. New Capacity applications for the first CMC auction will be minimal. It is assumed that most of the applicants will have Units that are already effective in the market. All parameters required for submission by Participants will be consulted on, agreed and available before the Qualification Application Deadline. The deadline for Capacity Market Qualification for the T-1 2018 auction is the 28th July 2017. Applications submitted after this date will not be included in the T-1 2018 auction. 10 T-1 refers to the Capacity Auction held the year before the actual Capacity Auction Year e.g. T-1 auction held for the Capacity Auction Year Sept 2018 to Sept 2019. 11 It is has been confirmed that an extended Capacity Year for the first auction May 2018 – Sept 2019 (ie. 16 months) will be used. © EirGrid 2017. Commercial In Confidence. Page 21 Transitional Registration Plan 5.2 Principles The Transitional Registration Plan is based on the following principles. A common I-SEM Registration Team will be created by the TSO’s I-SEM Project to manage the registration process for all of the following markets/functions: Capacity; Balancing; NEMO; and AoLR. In the interests of efficiency, there will be no requirement to separate out the NEMO registration process from the other markets12(unless another NEMO becomes active in the market). ECC will have their own registration process for the registration with the central counterparty. EirGrid and SONI, acting as MO or TSO, will facilitate the registration of customers to other NEMOs without undue discrimination. Where a Participant wishes to register with another NEMO who becomes active in the I-SEM (either before Go-Live or later) the data that are common across market timeframes will be provided, on request, in a suitable format by SONI or EirGrid to that Participant to facilitate their registration with the other NEMO. EirGrid/SONI will not seek to take competitive advantage of a monopoly role as Balancing Market operator. 12 The costs associated with NEMO registration will be captured separately and will be recovered through future NEMO charges, as required by CACM © EirGrid 2017. Commercial In Confidence. Page 22 Transitional Registration Plan 6. Plans by Market/Service The following sections provide detailed Transitional Registration Plans for each market. These ‘by market’ plans will be useful for determining the exact timing and series of steps that need to be performed by the Stakeholders. 6.1 Balancing Market The following provides a Transitional Registration Plan focusing on the Balancing Market. 6.1.1 Key Dates The key dates for the Balancing Market registration process are: Table 4: Balancing Market Key Dates Key Date 19/10/2016 18/11/2016 29/11/2017 15/03/2017 14/04/2017 01/05/2017 01/05/2017 15/05/2017 06/06/2017 16/06/2017 30/06/2017 28/07/2017 28/07/2017 01/12/2017 23/05/2018 Title Business Liaison Group on I-SEM Registration I-SEM Registration Team provides existing registration data, proposals for adjustments to meet new entity model, and additional fields need to complete registration. BLG on validating Balancing Registration Data TSC Code Approved [68] I-SEM Registration Team issue registration supporting information application forms Registration Data Submission Deadline Draft Framework Agreements Issued for review Draft Framework Agreements Submitted (unsigned) Draft Framework Agreement Issued for signing Registration Supporting Information Submission Deadline [161] New Intermediary Applications Deadline (to RAs) [159] TSC Framework Agreement Signed Intermediary Confirmation Submission Deadline Market Trial Start [85] Go-Live [250] © EirGrid 2017. Commercial In Confidence. Page 23 Transitional Registration Plan 6.1.2 Balancing Plan The timelines and key milestones for the Transitional Balancing Market Plan are shown in Figure 4. Figure 4: Balancing Market Plan © EirGrid 2017. Commercial In Confidence. Page 24 Transitional Registration Plan 6.1.3 Balancing Plan Narrative Mapping of Existing Data The I-SEM Registration Team will extract the existing Balancing registration data, map it to the new I-SEM entity model, identifying any new data needed, and provide this to Participants mid-Nov 2016 for validation. This allows the months of Nov to April - prior to the submission deadline at the start of May 2017 - for Participants to obtain the additional data required and discuss any of their core entity setup (i.e. Party, Participant, Units) with the ISEM Registration Team and Regulators. This approach also means that the bulk of the data required for registration is validated and approved as early as possible. Supporting Application Forms In mid-April 2017 the I-SEM Registration Team will issue the supporting application forms required for the Balancing, SEMOpx and Capacity Market. The AoLR application forms will be available later, at the end of May. These application forms will outline the information required to meet the registration and qualification criteria for these markets, providing plenty of time ahead of submission deadlines to collect this information and submit it. Submission of Registration Data Participants will be required to review and submit their updated registration data (as provided in Nov 2016) by the 1st May 2017. This will allow the I-SEM Registration Team and related Parties (MDPs, TSOs, and DSOs) to validate and approve the data for Market Trial and as the basis for the Capacity and NEMO registrations. Trading and Settlement Code Approval The TSC is planned to be approved on the 15th March 2017. This date is critical as there are a number of registration activities, including signing of Framework Agreements, which are dependent on the TSC being approved. Framework Agreements Based on the assumption that existing Parties and new Parties who are ready will be able to sign a revised TSC Framework Agreement, the deadline for signing the TSC Framework Agreement is revised to 28th July 2017: Four and a half months after the TSC is approved. The Framework Agreement signing process involves SEMO issuing draft Framework Agreements for review by the 1st May 2017, Parties reviewing and confirming these draft agreements by the 15th May 2017, SEMO issuing the final Framework Agreements for signing by the 6thJune, Parties then signing and returning the Framework Agreements by the 28th July 2017. These timelines coincide with the CMC Framework Agreement signing process for efficiency. Any Parties, who do not meet the Framework Agreement signing deadline, will need to follow the enduring formal accession process for the TSC. © EirGrid 2017. Commercial In Confidence. Page 25 Transitional Registration Plan Supporting Information Deadlines Where documentation is required from the Participant to verify any data submission they have made this supporting information will need to be submitted by the 16th June 2017 to ensure approval of the registration data ahead of the 30st June 2017 milestone. Intermediary Approvals In accordance with the Regulatory Authorities decision “SEM-17-25 Intermediary Transitions to I-SEM Decision” where existing intermediary arrangements are to be maintained for the ISEM the licensed Generator and their associated Intermediary need to submit a new Form of Authority along with a copy of the “old” regulatory consent to SEMO as part of their Balancing and Capacity market registration. For licensed Generators who are entering into arrangement with a new intermediary for ISEM they will need to submit a new Form of Authority and application for intermediary approval to the Regulatory Authorities by the 30th June 2017. The Regulatory Authorities will then confirm their approval, or otherwise, of the intermediary arrangement by the 14th July 2017 ahead of the TSC and CMC intermediary confirmation deadline of the 28th July 2017. Final Registration Requirements Although the intention is to complete the majority of registration requirements prior to the Market Trial, there will be registration requirements which will not be required until closer to the Go-Live. e.g. submission of collateral. The Final Registration Requirements will be dealt with during the Market Trial and completed prior to issuing a Commencement Notice13. Changes in Registration Data during Market Trial Once Market Trial starts, the intention is that any changes to registration data should follow the enduring registration change processes. This will serve two purposes: 1) Ensuring a controlled and orderly modification of registration data prior to Go-Live. 2) Exercising these enduring processes as part of the Market Trial. 13 A Commencement Notice is issued by the Market Operator to a Participant officially confirming that a Unit has met all pre-requisites and can trade in the I-SEM from the effective date specified in the Notice. © EirGrid 2017. Commercial In Confidence. Page 26 Transitional Registration Plan 6.2 NEMO Market This section provides a transitional registration plan focusing on the EirGrid and SONI NEMO market. 6.2.1 Key Dates The key dates for the NEMO market registration process are outlined in Table 5. Table 5: NEMO Market Key Dates Key Date 19/10/2016 19/10/2016 31/12/2016 28/02/2017 14/04/2017 07/08/2017 07/08/2017 01/09/2017 15/09/2017 29/09/2017 27/10/2017 01/12/2017 01/12/2017 01/12/2017 07/02/2018 07/02/2018 23/05/2018 Title Business Liaison Group on I-SEM Registration NEMO (ECC) KYC Form Available Deadline for KYC registration of interest ECC Application Forms Available SEMOpx Application Forms Available SEMOpx Application Deadline (for inclusion in Market Trial) [11] ECC KYC, New Member Application, Existing Member Application Deadline (for Market Trial) [11] Draft Framework Agreements Issued for review Draft Framework Agreements Submitted (unsigned) Draft Framework Agreement Issued for signing SEMOpx Framework Agreement Signed KYC Documentation Deadline (for Go-Live) New Member Application Deadline (for Go-Live) Market Trial Start NEMO ECC Banking Confirmation Deadline Existing Member Application Deadline (for Go-Live) [85] Go-Live [250] © EirGrid 2017. Commercial In Confidence. Page 27 Transitional Registration Plan 6.2.2 NEMO Plan The timelines and key milestones for the Transitional NEMO Market Plan are shown in Figure 5. Figure 5: NEMO Market Plan © EirGrid 2017. Commercial In Confidence. Page 28 Transitional Registration Plan 6.2.3 NEMO Plan Narrative The NEMO registration process involves not only the I-SEM Registration Team for the SEMOpx registration, but also ECC for the clearing house service. The ECC registration process is the most involved due to the need for Participants to complete “Know Your Customer” processing to ensure they meet ECC’s membership criteria. In addition, there are a number of agreements with Clearing Members or Settlement Banks that must be signed as part of the on-boarding process. 6.2.3.1 NEMO Trading SEMOpx Registration The application deadline for registering for SEMOpx is the 7th August 2017. This will allow sufficient processing time to enable Participants to take part in the trading activities on the NEMO markets as part of Market Trial. The I-SEM Registration Team will collect and approve the SEMOpx applications. This information will be provided to EPEX for setup of the trading system. SEMOpx Trading Rules Parties will need to sign a SEMOpx Framework Agreement as part of the registration for the NEMO markets. The SEMOpx Trading Rules are not planned to be finalised until 26th May 2017. Therefore, the signing up to these rules will not occur until after these rules and the associated SEMOpx Framework Agreement are finalised. The SEMOpx Framework Agreement signing process involves SEMOpx issuing draft Framework Agreements for review by the 1st September 2017, Parties reviewing and confirming these draft agreements by the 15th September 2017, SEMOpx issuing the final Framework Agreements for signing by the 29th September 2017, Parties then signing and returning the SEMOpx Framework Agreements by the 27th October2017. 6.2.3.2 ECC The timelines shown for the ECC registration process are very broad in the NEMO plan. This is due to ECC’s rigorous process and the required time to complete checks and approvals. Participants have been introduced to the registration process for ECC through the NEMO Business Liaison Group. Participation in Market Trial ECC require Participants to have submitted registration applications by the 7th August 2017 in order to ensure they can be processed for the start of Market Trial. Applicants after this date may not be able to take part in the Market Trial, or (if time allows) would need to enter later than the start of Market Trial. Deadlines for Go-Live Registration ECC have also provided deadline dates for applications in order to meet the Go-Live timeframes. These deadlines are different for new and existing ECC members: 1st December 2017 and 7th February 2018 respectively. © EirGrid 2017. Commercial In Confidence. Page 29 Transitional Registration Plan Confirmation of Clearing Bank Agreements As part of the registration with ECC, Parties must decide which clearing option they wish to use, either Non-Clearing Member (NCM) or Direct Clearing Participant (DCP). Parties must enter into an agreement with a Clearing Member or Settlement Bank respectively related to the clearing option. ECC have confirmed that this confirmation is required by the 7th February 2018 to allow Parties to participate in both the Market Trial and Go-Live. The 7th February 2018 is also the last date that a Participant can change their clearing option before the I-SEM Go-Live and be guaranteed inclusion. ECC Registration Deadlines The table below provides details of the deadlines for submission of ECC forms and Banking Confirmations dependent on a) whether the Party is new to ECC or an existing member, and b) whether the Party wants to participate in Market Trial or not. Table 6: ECC Registration Deadlines 6.2.3.3 Both NEMO Trading and ECC Final Registration Requirements Although the intention is to complete as many of the registration requirements as possible prior to the Market Trial, some registration requirements will not need to be met until closer to the Go-Live. For example, submission of collateral etc. These requirements will be processed during the Market Trial period, ahead of the issuing of a Commencement Notice. Changes in Registration Data during Market Trial Once Market Trial starts, any changes in registration data will follow the enduring registration change processes. This will serve two purposes: 1) Testing these enduring processes as part of the Market Trial. 2) Ensuring a controlled and orderly modification of registration data prior to Go-Live. © EirGrid 2017. Commercial In Confidence. Page 30 Transitional Registration Plan 6.3 AoLR Service This section provides a Transitional Registration Plan focusing on the AoLR Service. 6.3.1 Key Dates The key dates for the AoLR registration process are listed in the table below: Table 7: AoLR Service Key Dates Key Date 01/09/2017 27/10/2017 30/11/2017 01/12/2017 Title Publish AoLR registration applications forms AoLR Application Deadline AoLR Applications Complete Market Trial Start [85] © EirGrid 2017. Commercial In Confidence. Page 31 Transitional Registration Plan 6.3.2 AoLR Plan The timelines and key milestones for the Transitional AoLR Service registration process are shown in Figure 6. Figure 6: AoLR Service Plan © EirGrid 2017. Commercial In Confidence. Page 32 Transitional Registration Plan 6.3.3 AoLR Plan Narrative AoLR Application Submission Deadline The application for the AoLR Service requires the Participant to have completed, or at least started, the application process with the NEMO (both the SEMOpx and ECC). Therefore, the AoLR applications can afford to be received later in the registration process while still being able to be processed by the Market Trial start. Final Registration Requirements While the AoLR application must contain the relevant information to setup the AoLR Service in the market systems, there may be other requirements which can be completed during the Market Trial. © EirGrid 2017. Commercial In Confidence. Page 33 Transitional Registration Plan 6.4 Capacity Market This section provides a Transitional Registration Plan focusing on the Capacity Market. 6.4.1 Key Dates The key dates for the Capacity Market transitional registration process are listed in the table below: Table 8: Capacity Market Key Dates Key Date 19/10/2016 27/02/2017 14/04/2017 01/05/2017 15/05/2017 02/06/2017 06/06/2017 30/06/2017 03/07/2017 14/07/2017 28/07/2017 28/07/2017 01/12/2017 04/12/2017 15/12/2017 © EirGrid 2017. Commercial In Confidence. Title Business Liaison Group on I-SEM Registration RA approval of Capacity parameters I-SEM Registration Team issue registration/qualification application forms Draft Framework Agreements Issued for review Draft Framework Agreements Submitted (unsigned) CMC Code Approved Draft Framework Agreement Issued for signing New Intermediary Applications Deadline (to RAs) [159] Auction Information Pack issued Opt-Out Notification Deadlines CMC Framework Agreement Signed Unit Qualification Application Deadline [33] (including confirmation of intermediary) Final Qualification Results Approved [165] Capacity Mock Auction [182] T-1 Auction for 2018 [36] Page 34 Transitional Registration Plan 6.4.2 Capacity Plan The timelines and key milestones for the Transitional Capacity Market Plan are shown in Figure 7. Figure 7: Capacity Market Plan © EirGrid 2017. Commercial In Confidence. Page 35 Transitional Registration Plan 6.4.3 Capacity Plan Narrative Parameter Decisions There are a number of parameter decisions that are needed as input to the Capacity registration/qualification process, including Locational Issues, Derating and Capacity requirements, Allowable Tolerances, New Capacity Invest Rate Threshold, Stop Loss Limits, Value and Timing of Performance Bonds, Administered Scarcity Price, etc. Some of these decisions are relevant to the submission of Unit qualification/registration data by Participants. In cases where Participants wish to use different values to those defined in the RA decisions, they will need to have these exemptions submitted to the Regulatory Authorities by the 28th July 2017, with decisions on exemptions providing by the 6th October 2017 in time for the publication of the Provisional Qualification Results. Framework Agreements Based on the assumption that existing Parties and new Parties who are ready will sign the Capacity Framework Agreement, the deadline for signing is planned for 28th July 2017: Two months after the CMC is approved. The Framework Agreement signing process involves SEMO issuing draft Framework Agreements for review by the 1st May 2017, Parties reviewing and confirming these draft agreements by the 15th May 2017, SEMO issuing the final Framework Agreements for signing by the 6th June, Parties then signing and returning the Framework Agreements by the 28th July 2017. These timelines coincide with the TSC Framework Agreement signing process for efficiency. Any Parties, who do not meet the Framework Agreement signing deadline, will need to follow the enduring formal accession process for the CMC. If the Framework Agreement is not signed they will not be able to qualify Units for the first Capacity Auction. Intermediary Approvals In accordance with the Regulatory Authorities decision “SEM-17-25 Intermediary Transitions to I-SEM Decision” where existing intermediary arrangements are to be maintained for the ISEM the licensed Generator and their associated Intermediary need to submit a new Form of Authority along with a copy of the “old” regulatory consent to SEMO as part of their Balancing and Capacity market registration. For licensed Generators who are entering into arrangement with a new intermediary for ISEM they will need to submit a new Form of Authority and application for intermediary approval to the Regulatory Authorities by the 30th June 2017. The Regulatory Authorities will then confirm their approval, or otherwise, of the intermediary arrangement by the 14th July 2017 ahead of the TSC and CMC intermediary confirmation deadline of the 28th July 2017. Submission of Unit Registration/Qualification Formal Unit qualification/registration applications are due by 28th July 2017, to allow processing of these applications in sufficient time before the first auction. © EirGrid 2017. Commercial In Confidence. Page 36 Transitional Registration Plan Formal Qualification Although the formal qualification process is expected to be performed on existing Units, this will be the first time the process has been performed and it is anticipated that there will be certain registration/qualification details that will need to be resolved The registration/qualification process will be performed on 300+ Units. Monitoring and Approvals The Capacity Transitional Registration Plan includes a number of inter-dependent dates around provisional qualification results, review by an Auction Monitor, and Regulatory/SEMC approvals of both provision and final results. These dates are predominantly over the October-November period. The qualification process needs to allow for a review and resolution period where Participants can request a review of the qualification results. This time must be factored into the registration timelines. The number of such reviews are expected to be low, enabling approved results to be published earlier. However, the timelines must allow for a full review process. Mock Auctions Current plans are to include a mock auction ahead of the first T-1 Auction. There will be work involved in setting up the auction data based on the registered and qualified Units. Qualification Process for Next Auction There is an expectation that ‘catch up’ auctions will be required to ensure T-4, and perhaps T-3/T-2, auctions are completed ahead of the respective auction years. Although auction timelines are to be confirmed, it is likely that the preparation and qualification processes will start in late 2017/early 2018. Therefore, these activities have been shown the Capacity Plan starting from the T-1 Auction in December 2017. © EirGrid 2017. Commercial In Confidence. Page 37 Transitional Registration Plan 7. Registration Fees The following table outlines the methods by which the Transitional Registration costs are to be recovered. Table 9: Registration Fees Market/Service Balancing Capacity NEMO AoLR Approach No transitional registration fee, costs socialised in MO charges 2018/2019 No transitional registration fee, costs socialised in MO or TSO charges 2018/2019 Individual registration fee (dependent on final fee structure) Individual registration fee (dependent on final fee structure) The Balancing and Capacity Market arrangements will apply to Parties and Units who are in the SEM already, or will be effective in the SEM before the I-SEM Go-Live, and therefore would have paid registration fees under the existing arrangements. Parties or Units who plan to become effective after the I-SEM Go-Live date will be charged an explicit registration fee based on the approved registration fee structure. If this approved fee structure is not available at the time of a new Party/Unit’s application, then the transitional arrangements will apply for fees. The rationale for this approach is that a Participant should only pay one set of registration fees. © EirGrid 2017. Commercial In Confidence. Page 38 Transitional Registration Plan 8. Further Information Any further enquires on the Transitional Registration Plan should be directed to the TSO’s ISEM Project Email: [email protected] Information on the Transitional Registration will be made available from the TSO’s I-SEM Project website. Web: http://www.sem-o.com/isem/Pages/Home.aspx © EirGrid 2017. Commercial In Confidence. Page 39
© Copyright 2025 Paperzz