ASIAN DEVELOPMENT BANK PPA:NEP 18082 PROJECT PERFORMANCE AUDIT REPORT ON THE SEVENTH POWER PROJECT (Loan 1011-NEP[SF]) IN NEPAL June 2004 NRe1.00 $1.00 = = CURRENCY EQUIVALENTS Currency Unit – Nepalese rupee/s (Nre/NRs) At Appraisal At Completion At Operations Evaluation November 1989 June 2000 March 2004 $0.035 $0.014 $0.0135 NRs28.40 NRs71.10 NRs73.55 ABBREVIATIONS ADB EA EIRR ETFC FIRR IPP NEA NRM OEM PCR PPAR PPTA REDT RRP SWER SDR TA TOR VDC – – – – – – – – – – – – – – – – – – – Asian Development Bank Executing Agency economic internal rate of return Electricity Tariff Fixation Commission financial internal rate of return independent power producer Nepal Electricity Authority Nepal Resident Mission Operations Evaluation Mission project completion report project performance audit report project preparatory technical assistance Rural Electrification, Distribution and Transmission Project report and recommendation of the President single wire earth return special drawing right technical assistance terms of reference village development committee WEIGHTS AND MEASURES GWh km kV kWh MVA MW – – – – – – gigawatt-hour (1 million kWh) kilometer kilovolt kilowatt-hour megavolt-ampere megawatt NOTES (i) (ii) The fiscal year (FY) of the Government and the Nepal Electricity Authority ends on 15 July. In this report, “$” refers to US dollars. Director General, Operations Evaluation Department Director, Operations Evaluation Division 2 Evaluation Team Leader : : : Operations Evaluation Department, PE-643 Eisuke Suzuki David Edwards Hong Wang CONTENTS Page BASIC DATA v EXECUTIVE SUMMARY vi MAP ix I. II. III. BACKGROUND 1 A. B. C. D. E. F. 1 1 2 2 3 3 PLANNING AND IMPLEMENTATION PERFORMANCE 4 A. B. C. D. E. 4 5 5 7 8 Formulation and Design Achievement of Outputs Cost and Scheduling Procurement and Construction Organization and Management ACHIEVEMENT OF PROJECT PURPOSE A. B. C. D. E. IV. Rationale Formulation Purpose and Outputs Cost, Financing, and Executing Arrangements Completion and Self-Evaluation Operations Evaluation Operational Performance Performance of the Operating Entity Financial and Economic Reevaluation Sustainability Technical Assistance 9 9 11 13 15 16 ACHIEVEMENT OF OTHER PROJECT IMPACTS 16 A. B. C. 16 16 17 Socioeconomic Impact Environmental Impact Impact on Institutions and Policy Hong Wang, Evaluation Specialist (Team Leader) was responsible for the preparation of this report, and conducted document reviews, key informant reviews, and guided the fieldwork undertaken by the consultants, Geoff Brown and Dilli Dahal. Vivien Ramos, Evaluation Officer, supported the team with research assistance and Anna Silverio, Administrative Assistant, provided secretarial assistance from Manila. iv V. VI. OVERALL ASSESSMENT 17 A. B. C. D. E. F. G. 17 17 17 18 18 18 18 Relevance Efficacy Efficiency Sustainability Institutional Development and Other Impacts Overall Project Rating Assessment of ADB and Borrower Performance ISSUES, LESSONS, AND FOLLOW-UP ACTIONS 18 A. B. C. 18 19 20 Key Issues for the Future Lessons Identified Follow-Up Actions APPENDIXES 1. 2. 3. 4. Engineering Report Operational Performance of the Nepal Electricity Authority Financial and Economic Reevaluation Report on Socioeconomic Survey 21 24 25 27 BASIC DATA Loan 1011-NEP(SF): Seventh Power Project PREPARATION/INSTITUTION BUILDING TA No. TA Project Name 837 Seventh Power 1267 Institutional Support for Distribution Planning and Commercial Operations of NEA KEY PROJECT DATA ($ million) Type PPTA ADTA Amount1 ($) 75,000 780,000 As per ADB Loan Documents Total Project Cost Foreign Currency Cost Bank Loan Amount/Utilization Actual 64.0 42.7 51.0 40.5 (SDR)2 65.8 47.7 55.13 Bank Loan Amount/Cancellation 2.4 KEY DATES Appraisal Loan Negotiations Board Approval Loan Agreement Loan Effectiveness First Disbursement Project Completion Loan Closing Months (effectiveness to completion) KEY PERFORMANCE INDICATORS (%) Financial Internal Rate of Return - Part A - Part B Economic Internal Rate of Return - Part A - Part B Expected Actual 23 Jun–13 Jul 1988 16–20 Oct 1989 11 Jan 1990 28 Feb 1990 18 Sep 1990 18 Jul 1991 Sep 2000 9 Aug 1999 120 28 May 1990 Aug 1994 31 Aug 1995 51 Appraisal 18.8 4.5 22.2 13.5 BORROWER Kingdom of Nepal EXECUTING AGENCY Nepal Electricity Authority MISSION DATA Type of Mission Pre-Appraisal Appraisal Follow-Up Loan Negotiation Project Administration Review Loan Transfer Project Completion Operations Evaluation Approval Date 24 Dec 1986 11 January 1990 No. of Missions 1 1 1 1 8 1 2 1 PCR 13.4 0.8 20.0 11.1 PPAR 11.8 Negative 24.6 19.2 Person-days 72 105 10 12 79 8 35 54 ADB = Asian Development Bank, ADTA = advisory technical assistance, NEA = Nepal Electricity Authority, PCR = project completion report, PPAR = Project Performance Audit Report, PPTA = project preparatory technical assistance, TA = technical assistance. 1 The approved amount of technical assistance. 2 SDR1,791,979 of the loan was cancelled on 9 August 1999. 3 $6 million worth of material was purchased under loan-financed contracts, but not used in the Project. EXECUTIVE SUMMARY The Seventh Power Project (the Project) was formulated to help the Nepal Electricity Authority (NEA) improve the efficiency and reliability of its power system through rehabilitation in urban areas, and to meet the growing energy demand in rural areas through electrification. This was in line with the Government of Nepal’s objectives for power sector development, as described in its Seventh Five Year Plan (fiscal year [FY] 1984–1985 to FY1989–1990). The operational strategy for the Asian Development Bank (ADB) for Nepal at project appraisal in 1988 focused on (i) improvement in agricultural productivity, (ii) containment of factors that cause deforestation, (iii) enhancement of industrial development, and (iv) development of supporting physical and social infrastructure. NEA began commercial operations in August 1985 and, at loan appraisal, had been in operation for fewer than 4 years. Both ADB and the Government recognized the need to develop NEA’s institutional capabilities, so an advisory technical assistance (TA) grant was attached to the Project in order to improve NEA’s capacity for the planning of power distribution, and to strengthen NEA’s newly created commercial department. The main project objectives were to rehabilitate existing distribution networks in five larger towns to improve the quality of electricity supply and to reduce system losses, and to extend subtransmission and distribution networks to rural areas. The Project consisted of Part A: rehabilitation of existing distribution networks in five larger towns, Part B: extension of subtransmission and distribution networks to rural areas, and Part C: construction of a concrete pole factory. The Project was implemented largely as envisaged. Most significant was the use of loan savings to extend the scope of rural electrification. The main factor contributing to the large loan savings was participation of Chinese manufacturers in international competitive bidding after 1992. Other significant factors included depreciation of the dollar against special drawing rights (SDRs), the ability of Nepalese manufacturers to bid for supply of project equipment such as distribution transformers, and increased competitiveness of Nepalese installation contractors. Furthermore, the price contingency was calculated on the assumption of a constant nominal exchange rate, and was high. These factors, taken together, not only kept costs below or near budgeted levels, but also allowed allocation of contingencies for the extension of rural electrification. The Project experienced significant delays. The loan was closed on 9 August 1999, 4 years after the original closing date. Construction of the project works was completed only in 2000. A major cause of implementation delay was ADB’s lengthy process for approval of NEA’s request to use loan savings to extend rural electrification. Other delays were from (i) NEA delays in meeting conditions for loan effectiveness and in mobilizing the consultant for project implementation; (ii) the time required to fully evaluate the use of single wire earth return (SWER) distribution technology; (iii) delays in award of contracts; and (iv) poor contractor performance. Upon completion, the Project achieved the following physical outputs: (i) about 185 megavolt-ampere (MVA) of new 132 kilovolt (kV), 66 kV, and 33 kV substation transformer capacity; (ii) more than 320 kilometers (km) of new 33 kV subtransmission line; (iii) almost 2,500 km of high voltage distribution line; (iv) more than 2,300 km of low voltage distribution line; and (v) a new concrete pole factory with a daily production capacity of as much as 58 prestressed concrete poles. Through the Project, electricity was provided to almost 1,000 previously unelectrified load centers, providing access to electricity to more than 200,000 new customers. vii The quality and reliability of power supply in five major towns and two significant load corridors were improved. Sustainability of project benefits over the longer term will depend on the quality of maintenance, and the availability of technical and financial resources to upgrade and reinforce parts of the system that are loaded to their rated capacity. All work necessary to keep the network operational has been done, but the quality of maintenance varies. Engineering supervision of operation and maintenance is inadequate in some places. NEA’s financial performance was not satisfactory from 1999 to 2003. This was mainly because of NEA’s failure to increase tariffs to more sustainable levels. The average tariff for FY2003 was NRs7.02/kWh—42% lower than envisaged. A further problem was NEA’s failure to reduce system losses to the forecast levels. Actual losses for FY2003 were 24.5%, compared with forecast losses of 18.7%. NEA now faces a difficult operating environment. The Maoist insurgency in Nepal continues unabated, and NEA facilities are an ongoing target. Insurgency damage for FY2003 cost NRs72.4 million. But the insurgency’s impact on NEA operations is more important than the financial cost of physical damage. The insurgency impact involves both the quantifiable costs of protecting NEA assets, and the less-quantifiable costs of having to consider practical and political implications when making management decisions. Electrification in urban areas and areas near sealed roads has affected local economies positively because of its benefits to consumers’ lives, and stimuli for industrial and commercial development. In remote areas, consumers’ benefits from improved lighting, access to radio and television, and the use of fans would not be possible without electricity. Electricity has benefited women greatly. But many poorer households in remote areas have not connected to electrical power because the initial connection is too costly. The Project, as originally designed, had no specific environmental objectives. Construction has been environmentally benign, with most overhead lines located on road reserves. Project beneficiaries have seldom complained about environmental issues. The Project was expected to have an indirect environmental impact by utilizing Nepal’s indigenous hydropower facilities to replace fuelwood and imported fossil fuels. But the Project seems to have done little to reduce the use of fuelwood, although the use of kerosene, and small diesel motors, has decreased. The performance of both ADB and NEA is assessed as partly satisfactory. For ADB, this assessment reflects a failure to take proactive and timely action to respond to implementation problems that arose early in the Project, late decisions regarding the first loan extension, and an aborted decision to transfer project administration to the Nepal Resident Mission (NRM). For NEA, the partly satisfactory assessment is based on unsatisfactory progress over the first 5 years (through 1995), its failure to reduce losses to covenanted levels, and the poor financial performance that continues to threaten the Project’s sustainability. Overall, the Project is rated successful. But TA achievements fell short of expectations because of NEA’s lack of commitment to immediately implement TA recommendations, and to provide sufficient counterpart funds to make the TA more effective. Overall, the TA is assessed as partly successful. The Project has yielded three main lessons. First, delays associated with abandoning the use of SWER might have been avoided if a more substantive project preparatory consultancy had been undertaken, and the technical feasibility of using SWER been researched more thoroughly during appraisal. On one hand, innovation by consultants should be encouraged. But a project of this size and complexity should include a full-scale project viii preparatory TA that includes investigation into the use of new and alternative technologies. Second, annual review missions were insufficient during the first 5 years of project implementation. Third, many problems associated with poor performance of the contractors were not unique to the Project, and should be avoided in future. An ADB procedure to evaluate performance of both international and local contractors, similar to evaluation procedures used for individual consultants, would be useful. The performance of contractors would be recorded in files for eligibility check before qualification for future contracts. An issue relevant to ADB’s ongoing Rural Electrification, Distribution, and Transmission Project (REDT) deserves particular attention. The rural electrification component of REDT will probably further constrain NEA’s financial position, considering NEA’s poor financial performance and the unlikelihood of significant tariff increases in the near future. It may be useful to explore the possibilities of subsidizing initial connection charges for rural customers, and reducing their costs of payment of electricity bills, to raise the tariff for rural electricity supply to at least a break-even level. Eisuke Suzuki Director General Operations Evaluation Department I. A. BACKGROUND Rationale 1. Nepal’s Seventh Power Project1 (the Project) was consistent with the Government’s power sector objectives as described in the Seventh Five Year Plan (FY1984–85 to FY1989–90). The Seventh Plan included development of indigenous energy resources to substitute for imported fuels, providing a reliable power supply, and reducing fuelwood consumption. The Project was to help the Nepal Electricity Authority2 (NEA) improve the efficiency and reliability of its power system through rehabilitation in urban areas, and meet the growing energy demand in rural areas through electrification. The Project aimed specifically at (i) rehabilitating and expanding existing distribution networks to meet continuing load growth, and (ii) electrifying rural areas that had no access to electricity. The Asian Development Bank’s (ADB) operational strategy for Nepal at the time focused on (i) improvements in agricultural productivity, (ii) containment of the causes of deforestation, (iii) enhancement of industrial development, and (iv) development of supporting physical and social infrastructures. 2. NEA began commercial operations in August 1985. At loan appraisal, NEA had operated for less than 4 years. At that time, NEA had no commercial department to provide a focal point for its commercial and loss reduction activities. It was also recognized that detailed planning for distribution development over the next 10 years was a major undertaking, beyond the capability of the limited staff in NEA’s distribution and customer services departments. Work was limited to specific multilaterally financed projects, and was hampered by a lack of basic system data and geographic diagrams of the existing 11-kilovolt (kV) networks. Both ADB and the Government recognized the need to develop NEA’s institutional capabilities. An advisory technical assistance (TA) grant3 was attached to the project loan to support NEA in the development of institutional capability. B. Formulation 3. The Project was initiated through a small-scale project preparatory technical assistance (PPTA)4 under which two consultants developed the project scope and conceptual design. The PPTA was followed by an ADB appraisal mission in mid-1988.5 The scope of the project components was described in some detail in the appraisal report.6 For the rehabilitation component (Part A of the Project), the appraisal report identified the location and size of all transmission and area substation equipment, and provided estimates of the lengths of transmission and distribution lines to be installed. The rural electrification component (Part B) was defined in more detail. The conceptual design included extensive use of single wire earth return 1 2 3 4 5 6 Loan 1011-NEP (SF): Seventh Power Project, for $51 million equivalent, approved 11 January 1990. NEA, created under the National Electricity Act of 1984, is a government-owned corporation responsible for planning, constructing, and operating all public power utilities in Nepal. TA 1267-NEP: Institutional Support for Distribution Planning and Commercial Operations in the Nepal Electricity Authority, for $780,000, approved 11 January 1990. TA 837-NEP: Seventh Power Project, for $75,000, approved 24 December 1986. Due to the Government’s slow pace in resolving key issues before loan negotiation, a short follow-up mission to update the appraisal report was fielded in May 1989. The remaining issues were (i) transfer of the financial responsibilities of the ongoing ADB projects to NEA, (ii) establishment of a commercial directorate in NEA, (iii) commencement of a study on verification and valuation of fixed assets, (iv) submission of a schedule for liquidation of Government arrears, (v) conversion of NEA’s accounts payable to the Government into equity, and (vi) an action plan for timely preparation of audited financial accounts in accordance with the previous loan covenants. Loan negotiation was eventually held in October 1989. ADB. 1989. Appraisal of the Seventh Power Project in Nepal. Manila (Report LAP:NEP 18082). 2 (SWER) technology for electricity distribution, which the PPTA consultant considered an economically effective way to distribute electricity in rural areas where demand is low. Because this would be the first introduction of SWER technology into Nepal, it was considered necessary that the project implementation consultant carried out a detailed technical investigation and construction of a pilot SWER scheme in the Kathmandu Valley was included in the project scope. In both cases the project cost estimates were based on comprehensive bills of quantities. C. Purpose and Outputs 4. The main project objectives were to rehabilitate existing distribution networks in five larger towns to improve their quality of electricity supply and reduce system losses, and to extend subtransmission and distribution networks for rural areas. 5. The Project’s rehabilitation component was to contribute to NEA’s loss reduction targets of 20% and lower from FY1994 onward, to improve the reliability of supply to consumers, and to meet the growing demand for electricity. The Project also included extension and rehabilitation of electricity supplies in two semi-industrial corridors that had poor reliability of supply and high demand growth. Both corridors are along main roads to the Indian border. Thus, continuing industrial development would support Nepal’s export trade with India. The Project’s rural electrification component was to support the connection of about 83,500 new consumers in rural areas. This would support the Government’s objective of bringing electricity to rural areas, and substituting kerosene, diesel fuel and fuelwood by electricity generated from Nepal’s indigenous hydroelectric resources. 6. The Project, as defined at the time of appraisal, had three main parts: (i) Part A: Rehabilitation and extension of the subtransmission and distribution networks in the towns of Hetauda, Birunj, Butwal, Bhairahawa, and Dharan; and in the corridors between Hetauda and Birgunj, and between Butwal and Bhairahawa. (ii) Part B: Electrification of six unelectrified rural areas: Ilam-Damak, Dharan, Siraha, Malangawa-Gaur, Bharatpur-Parasi, and Tamghas-Sandhikarka. The unelectrified areas were to be supplied from the existing interconnected system, and would not require construction of new generation plants. (iii) Part C: Provision of two concrete pole plants in central and eastern Nepal; construction and maintenance equipment, and vehicles; and project support facilities. 7. The attached TA (footnote 3) was to improve NEA’s capacity for planning of electricity distribution, and to strengthen its newly created commercial department. It included (i) preparation of a 5-year rolling distribution development plan to decentralize distribution planning by establishing planning units in regional branch offices; and (ii) provision of on-the-job training in consumer accounting, commercial policy development, and loss reduction. D. Cost, Financing, and Executing Arrangements 8. At appraisal, the estimated project cost was $64.0 million, comprising $42.7 million in foreign exchange and $21.3 million in local currency. ADB was to finance 80% ($51.0 million) of the project cost, including all foreign exchange costs, and $8.3 million of local costs, from its Special Funds resources. The loan terms included a 1% service charge, a 10-year grace period, 3 and a 40-year maturity. The Kingdom of Nepal was the Borrower, and NEA was the Executing Agency (EA). 9. The loan proceeds were made available to NEA under a subsidiary loan agreement. The relending terms to NEA for rehabilitation of distribution systems, supply of materials and equipment, and consulting services included a 10.25% interest rate, a 25-year repayment period including a 5-year grace period.7 Loan proceeds for the rural electrification component were relent to NEA at 1% interest. The Borrower assumed the foreign exchange risk of the entire loan. 10. NEA set up a dedicated project implementation unit in Kathmandu, which was responsible for overall project management, engineering and design, and for contract administration. Subsidiary project offices were established in the eastern, central, and western regions. They were responsible to the project implementation unit for stores management and supervision of the implementation contracts. The regional project offices were also responsible for the operation and maintenance of each subproject until its formal handover to the NEA local branch office. E. Completion and Self-Evaluation 11. ADB’s project completion report (PCR), circulated in July 2001, rated the Project as successful. But the PCR was prepared before local contractors had fully completed project installation, so the final project cost had to be estimated.8 The PCR discussed many problems during project implementation and concluded that the performance of the implementation consultant, and some contractors and suppliers, was unsatisfactory. Accounts of the Project’s environmental and social impacts were limited. The PCR did not assess the relevance, efficacy, efficiency, sustainability, or institutional and other impacts of the Project. Lessons learned were mainly with respect to administrative difficulties during project implementation. Recommendations were made in terms of closely monitoring completion of the unfinished project components, financial health of NEA, and attainment of project benefits. The PCR provided no information on implementation of the attached TA. F. Operations Evaluation 12. This project performance audit report (PPAR) reviews PCR findings and assesses the Project in terms of relevance, efficacy, efficiency, sustainability, and institutional and other developmental impacts. The assessment is based on a review of ADB documents, discussion with ADB staff, and findings of the Operations Evaluation Mission (OEM). The OEM visited Nepal from 25 February to 12 March 2004, and held discussions with representatives of the Ministry of Finance, Ministry of Water Resources, Electricity Tariff Fixation Commission (ETFC), and NEA. The OEM visited some project sites and districts electrified under the Project in the flat areas of the western, central, and eastern regions.9 During the field visits, the OEM had discussions with managers and engineers maintaining project facilities and carried out a reconnaissance-level physical inspection of some facilities constructed under the Project. The OEM also carried out socioeconomic surveys in Siraha, Chitwan, Nawalparasi, and Rupandehi districts. The views of 7 8 9 Both ADB and the World Bank required that the relending terms be on a commercial basis. The PCR mission placed significant emphasis on correctly reporting project costs, and indicated dissatisfaction about not being able to accurately quantify costs. But the estimate of the total project cost is probably reasonably accurate because it was based on the noncompleted amount of the local construction contracts with fixed costs. Nevertheless, there could be inaccuracies in the cost of individual project components since the allocation of some equipment supply contracts to individual project components had to be estimated. Because the cost breakdown in the PCR was comprehensive and the best cost assessment available, it is used in this report. OEM’s planned travel to hill districts of eastern Nepal was restricted because of security problems. 4 concerned ADB departments and offices, and those of the Government and EA, were considered when finalizing the PPAR. II. A. PLANNING AND IMPLEMENTATION PERFORMANCE Formulation and Design 13. The Project was formulated to rehabilitate distribution networks in five major towns in order to improve the quality of electricity supply and reduce system losses, and to extend subtransmission and distribution networks to rural areas in the terai (flat plains) and hills (mountains that are generally not covered by snow). The Project was expected to directly benefit domestic consumers and commercial and industrial users in urban and semi-urban areas, as well as users of the existing irrigation facilities that were using imported fuels, and about 84,000 new consumers in rural areas. The Project conformed to the Government’s strategy for the power sector in the short and medium term, and was in line with ADB’s operational strategy for Nepal. The Project was a continuation of ADB’s long-term involvement in the Nepal power sector.10 14. The extent of SWER to be included in the Project was described in detail. The terms of reference (TOR) for the project implementation consultant included a detailed technical investigation to determine the appropriateness of using SWER technology in Nepal. A comprehensive study into the use of SWER technology in the project areas was undertaken at project inception. Technical problems were found to make successful implementation of SWER difficult. The high population densities in the terai project areas make the use of SWER technology problematic and potentially uneconomic.11 The hill areas in the Project have lower population densities and are better suited to the use of SWER. But ground conditions were found to be such that designing a suitable earth connection would be difficult, making the use of SWER technology potentially hazardous, particularly during the dry season. In retrospect, these technical issues should have been addressed at the project design stage. 15. Once the decision was made not to use SWER technology, it became necessary to revise the design of the rural electrification components. The implementation consultant reviewed the conceptual designs for the six rural electrification areas, and proposed revised designs using conventional three-phase distribution. The review used the best costs available at the time, and reformulated each subcomponent to meet ADB’s financial and economic criteria.12 As a result, some villages were deleted from the Project, and others added. The number of households that could potentially be connected to the rural electrification scheme increased because of the technical reformulation. The consultant’s report estimated that, after 10 years, 144,600 new consumers would benefit from the rural electrification. 10 Of 15 major towns where earlier ADB studies indicated an urgent need for rehabilitation and expansion of existing distribution networks, 4 were rehabilitated under the Fifth Power Project (Loan 670-NEP[SF] for $20.0 million, approved 14 December 1983). Two more towns were rehabilitated under the Sixth Power Project (Loan 708-NEP[SF] for $28.1 million, approved 20 November 1984). Electrification of five previously unelectrified rural areas was also completed under the Sixth Power Project. ADB is now financing further rehabilitation of distribution networks, and electrification of 22 rural areas, under the Rural Electrification, Distribution and Transmission (REDT) Project (Loan 1732-NEP[SF] for $50 million, approved on 21 December 1999). 11 SWER technology is applied most successfully in areas of low population density with few distribution substations per km of line. Safety considerations limit the total load on an SWER circuit. The need for an isolating transformer at the connection to the conventional distribution network means that circuit lengths of less than about 10 km are seldom economical. The project consultant found that, while short-term use of SWER on the terai was technically possible, the forecast load growth indicated that long-term SWER use might not have been sustainable. 12 A positive financial internal rate of return (FIRR) and a minimum economic internal rate of return (EIRR) of 10% were required for the rural electrification subprojects. 5 16. Soon after redesign of the rural component of the Project, and tendering of the main equipment supply contracts, it became apparent that equipment costs would be lower than estimated at appraisal. This was mainly due to participation of Chinese contractors in the international competitive bidding process after 1992. At the same time, depreciation of the US dollar against the special drawing rights (SDR)13 meant that the loan in dollar terms had increased. Hence, an additional $26 million was available. To utilize the loan savings, ADB agreed with NEA proposals for additional rural electrification in 22 areas.14 The rehabilitation component of the Project was largely implemented as designed at appraisal. But only one concrete pole manufacturing plant, instead of the two plants envisaged, was considered necessary and built. B. Achievement of Outputs 17. The Project included installation of the following electricity reticulation: (i) about 185 megavolt-ampere (MVA) of new 132 kilovolt (kV), 66 kV, and 33 kV substation transformer capacity; (ii) more than 320 kilometers (km) of new 33 kV subtransmission line; (iii) almost 2,500 km of high-voltage distribution line; and (iv) more than 2,300 km of low-voltage distribution line. As a result of the Project, electricity was reticulated to almost 1,000 previously unelectrified load centers, providing electricity access to more than 200,000 new customers. In addition, new 11 kV and 400 V distribution lines were constructed or rehabilitated to improve the quality and reliability of supply in five major towns and two significant load corridors.15 Furthermore, a new concrete pole factory was built, with a daily production capacity of as many as 58 pre-stressed concrete poles. A pilot SWER scheme, designed to supply up to 600 domestic customers, was constructed in the Kathmandu Valley using project funds, but was abandoned soon after the decision not to use SWER technology in the Project. The standard of construction observed by the OEM was generally good. But a number of engineering issues and problems were identified (discussed in Appendix 1). C. Costs and Scheduling 18. The actual project cost was $65.8 million. Loan disbursements of $55.1 million included $53.7 million in foreign exchange cost16 and $1.4 million equivalent in local currency. The Government funded the remaining local currency cost of $10.7 million equivalent. An undisbursed $2.4 million equivalent was canceled on loan closure. The disbursement of $4.1 million higher than the appraised loan of $51.0 million was caused by depreciation of the dollar against the SDR. 19. Table 1 compares project cost estimates at appraisal with actual costs at completion. Most significant is the $19.7 million for extension of the rural electrification component. This extension—more than 25% of the total project cost—is explained in the PCR as having been made possible by Chinese contractors’ participation in the bidding, which reduced bid prices. All 13 In 1994, the exchange rate was $1.45: SDR vs $1.25: SDR at appraisal—a 16% depreciation of the dollar against SDR. 14 ADB’s decision was based on a technical and economic study that NEA prepared, using the same methodology that the consultant used in the inception study. 15 The OEM was unable to quantify the extent of the distribution line rehabilitation undertaken under Part A of the Project, but visited three of the rehabilitated areas during the field visit. 16 Material valued at $6 million was purchased under loan-financed contracts, but was not used in the Project. 6 project components had cost overruns, except for the original rural electrification component.17 A substantial component of the project cost was material procured under international competitive bidding, so participation of Chinese manufacturers in these material supply contracts was undoubtedly a contributing factor. Other significant factors were Nepalese manufacturers’ ability to bid to supply project equipment such as distribution transformers, and increased competitiveness of Nepalese installation contractors. Furthermore, the price contingency was calculated assuming a constant nominal exchange rate. These factors, combined, not only kept costs below or near budgeted levels, but also allowed allocation of contingencies to the scope extension in rural electrification. Table 1: Summary of Appraised and Actual Project Costs ($ million) Item Part A Part B Components Appraisal Estimate Foreign Local Total 6.0 1.9 7.9 24.0 9.2 33.2 24.0 9.2 33.2 Foreign 7.3 33.7 22.0 11.7 3.0 Actual Cost Local Total 1.7 9.0 15.0 48.7 6.0 28.0 9.0 19.7 1.3 4.3 Rehabilitation Rural Electrification Original Scope Extension Part C Concrete Pole Plant/Tools & 2.2 0.5 2.7 Equipment Part D Consulting Services 1.7 0.3 2.0 2.2 0.1 2.3 Physical Contingencies 1.7 0.6 2.3 Price Contingencies 6.8 4.4 10.2 Taxes and Duties 1.7 1.7 NEA Project Management 0.3 0.3 Interest During Construction 1.3 2.4 3.7 1.5 1.5 Total 42.7 21.3 64.0 47.7 18.1 65.8 NEA = Nepal Electricity Authority. Source: ADB. 2001. Project Completion Report on the Seventh Power Project in the Kingdom of Nepal. Manila. 20. The loan was approved on 11 January 1990, with an original closing date of 31 August 1995. After three extensions, the loan was closed on 9 August 1999. NEA completed construction of project works in September 2000, after successfully resolving a few difficult right-of way issues.18 A comparison of the appraisal schedule with the actual project implementation is given in Appendix 8 of the PCR. A major cause of implementation delay was the lengthy process within ADB to approve NEA’s request to utilize loan savings for the extension of the rural electrification component.19 The extended project scope required a second round of procurement, which did not begin until early 1996. Other delays arose from (i) delays by NEA in meeting the conditions for loan effectiveness,20 (ii) delays in mobilizing the 17 Cost overruns in Parts A and C may partly reflect the fact that large portions of these components were implemented using turnkey contracts rather than material supply and local installation where successful bidders were mostly Chinese and Nepalese manufacturers. The cost overrun in Part C was in spite of the fact that only one of the two pole plants included in the original project scope was constructed. 18 Project land acquisition was minimal. Compensation for right-of-way of distribution and transmission lines was not included in Nepal’s standard rules and regulations at project implementation. Rights-of-ways were obtained at no cost, mainly through consultation with affected people. No complaints regarding the issue of right-of-way were reported during the field visit. 19 NEA originally made this request in August 1994, and approval took 14 months. A review mission fielded in September 1994 expressed concern about delays in implementing the original scope and recommended that approval be deferred until NEA’s implementation performance improved. A subsequent review mission in June 1995 noted improved implementation performance and recommended that the request be granted. 20 The loan did not become effective until 18 September 1990, 8 months after Board approval. 7 project consultant,21 (iii) the time required to fully evaluate the SWER technology, (iv) delays in award of contracts, and (v) poor performance of some international contractors. A further delay was because ADB did not approve the first extension of the loan closing date until 17 November 1995. That delay stopped project work for 3 months, because contractors would not continue after ADB’s original letters of credit expired. D. Procurement and Construction 21. The Project required 89 different contracts, and project works stretched over almost 700 km from east to west. Bid documents for most project turnkey and equipment contracts as scoped at appraisal were issued in December 1992. Bids were opened in February 1993, but the first contracts were not awarded until August 1993; some contracts were not awarded until mid 1994. Delays were due to the volume of contracts to be processed, and to an exceptionally large number of representations from unsuccessful bidders. In its PCR, NEA alleges that some representations were made on the basis of forged documents supporting the complainant’s ability to complete the contract works. Most of these representations were received before or immediately after ADB received the bid evaluation reports, and before the bid results were made public. At the time, there was a strong suspicion that somebody was prematurely leaking the results of NEA’s bid evaluations to bidders, but there is no record that ADB took action in response. 22. Some contractors performed poorly. First, at least two contractors, after receiving most of their contract payments following successful acceptance inspection at the contractor’s works, did not dispatch the materials to the sites. The matter was resolved in one case, but the equipment was never dispatched in the other case, and the contractor’s bank guarantee was forfeited. Second, an international turnkey contractor was paid the amount of the contract in foreign currency after equipment had been delivered. But the contractor was unable to repatriate sufficient funds back to Nepal to complete the erection work because of its own government’s controls on foreign currency. This caused delays. Third, the contractor for supply and delivery of conductors defaulted, claiming that his costs had increased due to a steep rise in the cost of aluminum. The contractor was bound by a fixed-price contract, so the claim could not be considered. The contract had to be terminated, and the supply of material was re-bid. Finally, single-phase customer meters were found on arrival at site not to meet the specified accuracy requirements. As a result, the contractor sent a team of four technicians with two test benches to Kathmandu to retest and adjust all meters over an 8-month period. This delay led to such an acute shortage of meters that many rural households had to wait more than a year before provision of a requested connection. Such irregularities affected only a few contracts, but had a serious impact on project completion since all required material had to be made available before full completion of erection works. 23. The supervision of contractors was also unsatisfactory in some cases. Personnel who did factory inspections sometimes did not fully understand project requirements, and accepted equipment that did not fully meet project needs. In other cases, contractors delivered the wrong equipment, even after factory inspection. Other delays were caused by inadequate supervision due to a lack of qualified personnel assigned to the Project, and by landowners refusing the contractors access during the monsoon season to prevent crop damage. The PCR also noted that 21 The consultant was appointed in 1989, before loan approval. When the loan became effective, 1 year after contract negotiations, it was necessary to renegotiate parts of the consultant’s contract and approve changes in personnel. NEA initially insisted the original contract should stand unchanged. As a result, a dispute developed between NEA and the consultant, which was only resolved after ADB intervention. Consequently, the consultant was not mobilized until July 1991. 8 the impact of monsoons on line erection was not adequately considered when planning construction works. E. Organization and Management 24. The large number of contracts and widespread project areas made the Project particularly hard to organize and manage. NEA set up a project implementation unit in Kathmandu with overall project responsibility, especially for contract administration. Subsidiary project offices, responsible for construction supervision, were established in the western, central, and eastern regions. Separate project stores were maintained in each subsidiary office. The Project retained responsibility for project works until they were formally handed over to the relevant branch offices. This approach was considered appropriate for a project of this magnitude and complexity. 25. At project completion, about $6.0 million worth of equipment procured through loan funds had not been used in the Project. That equipment was eventually transferred to NEA stores. This was 9% of the total project cost, and 12% of the rural electrification component. Much of the equipment was later used to construct further rural electrification works outside the scope of the Project, which may not have been subject to ADB’s financial and economic approval criteria or safeguard policies. Furthermore, equipment ordered under each contract had to be allocated among different subcomponents. This required a complexity of project accounting that may have been overlooked. Future projects of this type should have better inventory control. 26. NEA satisfactorily complied with covenants related to project and corporate organization, although with some delay in internal audit function. Other loan covenants included (i) electricity losses reduced from 26.5 % in FY1990 to 20% from FY1994 onward, (ii) a self-financing ratio of at least 23% from FY1998, (iii) a 6% rate of return on the gross book value of fixed assets from FY1991, and (iv) a debt service ratio of 1.2 from FY2001. Total system losses remained high throughout project implementation, and are currently 24.5%. According to the PCR, at loan closure in 1999 NEA achieved the required ratios of self-financing and debt service coverage, but its return on rate base was only 5.4%.22 NEA’s financial performance has deteriorated since then, to the extent that NEA has not made a pre-tax profit since FY2000 (Appendix 2). Audited accounts were consistently submitted late throughout project implementation. 27. The project implementation consultant remained on the Project from mid-1991 until mid1995 when the time provided in its contract was expended. According to the PCR, the consultant’s performance was not satisfactory. The PCR noted that revised designs for rural electrification were incomplete and misleading. The consultant was also blamed for delays in several activities, including tender invitation for procurement and erection works. 28. The PCR assessment of the consultant’s performance relies on NEA assessment in its PCR, and is not supported by evidence in ADB files. An ADB review mission in June 1992, 12 months after consultant mobilization, noted a communication problem between the consultant and NEA. The back-to-office report of the next review mission, in May 1993, noted that the situation seemed to have been resolved, and that communication between the two parties was good. The OEM reviewed the consultant’s engineering design report on the first phase of the Project, and 22 There are discrepancies between the financial indicators for FY1999 as reported in the PCR and in the report and recommendation of the President (RRP) for the REDT loan. Most significant is the self financing ratio, which is reported as 28% in the PCR but only 9% in the RRP. The returns on rate base in the two reports also differ but are not comparable because in the RRP it is measured against the revalued fixed asset base, rather than the book value. 9 considered its standard high. This design report was used as a template for subsequent NEA reports seeking approval for scope extensions of rural components.23 29. Throughout the Project, ADB sent review missions roughly on an annual basis. These missions were particularly important before 1996, when project progress was considered unsatisfactory. Extension of the loan closing date, and extension of the project scope to include more rural electrification, appear to have been rolled together.24 But these were two separate issues, and should have been treated as such. Then in mid-1996 it was decided that project administration would be transferred to the Nepal Resident Mission (NRM). The decision was reversed in January 1997, mainly because of constraints in resources at NRM.25 Fifteen boxes of project documents were transferred from Manila to Nepal, then returned to Manila 6 months later. For preparation of this report, only three boxes of project files could be located. Significant documents, which would have given better understanding of problems during the Project, were missing. For example, no documents could be found relating to the demobilization of the project implementation consultant in July 1995. 30. Project implementation suffered from a lack of more proactive supervision when the Project was in difficulty during the early years. In such circumstances, relying on annual review missions for feedback on project performance is unsatisfactory. Regular monthly or quarterly review meetings with the EA, and possibly the consultant, would have been better. This could have provided ADB and the Borrower earlier warning of difficulties, allowing corrective action before the situation deteriorated.26 The improvement in performance after 1995 seems to have been due to a change of NEA project manager, rather than to changes in how ADB administered the Project. III. A. ACHIEVEMENT OF PROJECT PURPOSE Operational Performance 1. Rehabilitation Components and Subtransmission 31. Project’s rehabilitation components were undertaken in strategic locations that were important to the national economy, either through proximity to main border crossings with India or, for Dahran, to important agricultural export industries such as tea. Therefore, the rehabilitated systems have been subject to high load growth, and will probably reach their technical design capacity well before expiration of the life of the assets. Indeed, some subcomponents of the Project reinforced distribution work completed under the Sixth Power Project. Some power transformers installed under the Project have already been replaced with larger units. The Project has ensured that customers in the area continue to receive a power supply of acceptable quality. 23 The one NEA person the OEM spoke with who had worked with the consultant considered the consultant’s work satisfactory. 24 ADB approval for both extending the loan closing date and the project scope was given on 14 November 1995, at a time when little progress had been made on installation of the first phase of rural electrification. The PCR suggests that the main reason for the delay in approving the scope extension was NEA’s failure to provide all required information. But the OEM review of the project files indicates that progress on the Project was the major concern. 25 Another reason was the large number of procurement packages and representations associated with the Project. It was decided that the Project would be managed more efficiently from ADB headquarters. 26 The OEM was informed that NRM started monthly meetings with project managers/directors of ADB-assisted projects to discuss ongoing problems in late 1993. The monthly meetings afterward were intensified by discussing all issues identified in project review missions. The status of each project was reported to concerned departments at ADB headquarters. But the project files include no records of the monthly meetings, nor of correspondence between NRM and ADB headquarters. 10 This is particularly important for industrial customers, who are an important stimulus for continuing economic growth. Sustainability over the longer term will depend on the quality of maintenance, and on availability of technical and financial resources to upgrade and reinforce parts of the system that become loaded to their rated capacities. Until now, all work necessary to keep the network operational has been done. 32. Maintenance quality varies across the network and, especially for area substations, is dependent on the enthusiasm and ability of the local maintenance staff. In places where housekeeping was good, maintenance was clearly proactive and of high standard. In other situations, only the minimum maintenance necessary to keep the equipment operational is done. Of concern is the fact that many staff have little regard for the proactive avoidance of failure in day-to-day network operations. For example, the low-voltage, molded case circuit breakers on distribution substations are not designed for exposure, and are mounted in weatherproof cabinets. But the cabinet doors are routinely left open, or sometimes even removed, so that staff can operate the circuit breakers from the ground using a stick. OEM members also saw a number of instances where temporary repairs had become permanent, either because replacement parts were not available, or through failure to return to the sites to make more permanent repairs. Other sustainability concerns are largely outside the control of management and staff. The 11-kV indoor circuit breakers used throughout the Project are no longer manufactured, so spare parts cannot be obtained. One substation switchyard and control room was flooded to about 1 meter during the 2003 monsoon season. 33. Engineering supervision of operation and maintenance is inadequate in some places. The OEM requested data on the demand and energy growth for all transmission and subtransmission substations constructed under the Project. This information should be readily available, because substation operating staff routinely record it hourly. The necessary data for many substations was provided, although after difficulty, but data for other substations were not available. In another instance, the OEM found load data recorded in a substation log that was clearly erroneous, as it was inconsistent with other data recorded in the same log. Inconsistent data appeared to have been reported to management on a weekly basis—with no one questioning its accuracy—since the substation was commissioned. 2. Rural Electrification 34. The Project’s rural electrification components generally appear to have been installed according to the revised design. But operationally, those components also suffer from many of the same problems as the rehabilitation components, particularly in maintenance quality. Service drops between the low-voltage reticulation and the customer metering points do not have proper connectors, and connections are made by simply twisting the service drop conductors around the distribution line conductors. Over time, this will cause loose and high-resistance connections that will, in turn, cause low voltage for customers and higher system losses. In one case, a weight appeared to have been attached to the service drop conductor in order to improve the connection quality. Illegal connections are endemic in some areas. Many of these connections were easy to detect and, in some villages, the OEM noted at least one illegal connection on each span. Other illegal connections may also be present, but are attached more skillfully, so they appear 11 legitimate. Most poles adjacent to residences had outside lights, probably illegal, connected to the low-voltage conductors.27 35. About 95% of the customers in less-accessible rural villages is residential. NEA claims that 90% of these customers pays the minimum lifeline charge of NRs80 per month, but many do not fully use their entitled 20 units per month. But, based on an inspection of billing records in only one location, the OEM believes the average customer consumption could be higher, particularly in the summer when many households use fans. Nevertheless, few remote residential customers paid more than NRs200 per month. This equates to consumption of 36 units at an average tariff of NRs5.6 per unit. NEA’s average generation cost for electricity generated from its own plants in FY2003 was NRs4.03 per unit. But NEA pays large independent power producers (IPPs) an average of NRs6.1 per unit, which the OEM considers a reasonable proxy for the marginal cost of generation.28 On this basis, revenue from electrification of remote villages is insufficient to cover even the generation cost, and does not provide for other costs resulting from the Project, including system losses, operation and maintenance, and the cost of servicing NEA’s debt to the Government. Therefore, from a financial perspective, the electrification of remote villages is unsustainable at existing tariff levels. The current tariff structure contains some cross-subsidies among various consumer categories, but they are relatively restricted. Considering the importance of rural electrification in both political and economic terms, NEA will do its best to keep these rural systems operational. 3. Concrete Pole Factory 36. The concrete pole factory in Amlekhganj, in southern Kathmandu, continues to produce 8-, 9-, and 11-m prestressed concrete poles of good quality. By January 2004, the factory had produced more than 77,600 units. The factory is financially independent. It sells its poles to NEA at a transfer price that provides an adequate margin over its own operating costs, but is significantly lower than purchasing from the private sector (Table 2). Table 2: Performance of the Pole Factory Poles 8-meter 9-meter 11-meter Total Production to January 2004 45,316 23,910 8,416 Current Production Cost (NRs) 2,014 2,712 4,210 Transfer Price to NEA (NRs) 2,520 3,270 4,945 Market Price for NEA (NRs) 3,474 3,964 8,000 NEA = Nepal Electricity Authority, NRs = Nepalese rupees. Source: Nepal Electricity Authority. B. Performance of the Operating Entity 37. Appendix 2 compares NEA’s financial performance from1999 to 2003 with performance as forecast in the 1999 report and recommendation of the President (RRP) for the Rural 27 When asked about this, an NEA staff explained that village development committees paid for the street lights. But the installation quality of many outside lights was poor, indicating they had not been installed professionally. Furthermore, the monthly tariff for an unmetered street light is NRs1,860 per kVA, equivalent to NRs74 for a 40-watt bulb. This is high compared with the NRs80 minimum charge payable by low-use consumers. 28 NEA’s reported average cost of generation does not include IPP payments. Regardless, rural electrification introduces new load to the network. Therefore, financial analysis should be based on NEA’s marginal generation cost. This cost will vary by season, but NEA’s average IPP cost seems a reasonable proxy for the average marginal financial cost. 12 Electrification, Distribution and Transmission Project (REDT). NEA has consistently underperformed when compared with ADB’s performance expectations. 2000 was the only year in which NEA made a profit. This is primarily because NEA has not increased its tariff to the levels envisaged. NEA’s average revenue for FY2003 was NRs7.02/kWh compared with the RRP forecast of NRs10.09/kWh. A further problem is NEA’s failure to reduce system losses to the forecast levels. Actual losses for FY2003 were 24.5% vs the forecast 18.7%. Another issue affecting NEA’s financial position is the large amount of electricity arrears owned by the Government and municipalities.29 38. NEA currently faces a difficult operating environment. The Maoist insurgency in Nepal continues unabated and NEA facilities are an ongoing target. Insurgency damage in FY2003 was NRs72.4 million. More important than the monetary cost of physical damage is the impact of the insurgency on NEA operations. This impact arises from both the quantifiable cost of protecting its assets and the less-quantifiable cost from having to take practical and political considerations into account when making management decisions. An example of this difficulty is the current requirement for customers to travel to the nearest branch offices to pay their monthly electricity bills.30 This was made necessary by the removal of bank branches from rural villages because of the insurgency. NEA cannot send its staff to collect accounts directly from customers because the staff would obviously be carrying money and thus, be high-risk insurgency targets. 39. ETFC sets NEA’s tariffs, which were last revised in September 2001. NEA filed for a tariff review in mid-2003, requesting a seasonal tariff that would reduce electricity costs in the wet season when river flows are higher. This request was declined; ETFC rejected the concept of seasonal tariffs. NEA is preparing a new tariff filing for likely submission in April 2004. The Government assurances for REDT include semiannual tariff reviews by ETFC, but such reviews are not occurring, at least not in a meaningful way. The perception that tariff rates are high appears widespread in Nepal. The high cost of electricity was a recurring theme in the focus groups discussions that OEM organized. NEA staff and other government officials complained to OEM that electricity tariffs in Nepal were already high compared with those of other countries in the region. This political climate and the extent of government representation on ETFC make significant tariff increases unlikely in the short term. The ETFC chairperson told OEM that NEA should improve its financial performance through efficiency gains rather than relying on tariff increases. But while there is undoubtedly scope for NEA to improve its operating performance, the potential impact of such improvements on NEA’s financial performance is limited by the fact that most NEA costs are outside of its management’s direct control. A high interest rate is one such cost. NEA is lobbying aggressively to reduce the interest rate on its subsidiary government loans.31 40. NEA is making continuing efforts to improve efficiency of its operations. It has disaggregated internally into four business groups (generation, transmission and system operation, distribution and customer services, and engineering services). Each group now operates as a profit center. Managers of the generation, transmission, and distribution groups 29 As a result of policy dialogue with ADB, the Government paid part of the arrears in December 2003. The Government also made a provision in the finance ordinance in January 2004 to directly deduct one sixth of the grants given to municipalities for payment of electricity arrears. NEA is also maintaining dialogue with municipalities to agree on the amounts of arrears. The OEM was informed that, as of March 2004, 25 of 58 municipalities had agreed on the amount of arrears to be paid to NEA. 30 OEM was told that travel to and from the nearest branch office to pay the monthly electricity account takes some customers a day and costs more than NRs50 for public transport—when in many cases the bill itself may be only NRs80. 31 The Government is not free to adjust these interest rates, which are specified in NEA’s loan covenants with ADB and other lenders (see footnote 7). 13 must sign performance contracts that will reward them according to the extent to which they achieve key performance objectives. Within the distribution and customer services group, 19 branch offices have been designated as “distribution centers” and operate as profit centers outside the regional office structure. Distribution center managers are given incentives to achieve results, measured by key performance indicators. According to NEA, a recent audit of distribution center performance was encouraging. 41. High losses on the NEA system are an ongoing problem. NEA’s losses, including electricity consumed for its own use, totaled 24.5% in 2003, down from 27% at appraisal but still significantly higher than the covenanted target of 20% from FY1994 onward. It is widely accepted that NEA’s nontechnical losses are excessive, and that any initiative to reduce losses must target those losses as first priority. Current initiatives include the inclusion of targets for loss reduction in management contracts for the distribution centers; and a scheme, supported by the Danish Government, to sell electricity at discounted wholesale rates to consumer cooperatives, which will assume ownership of the local distribution networks and responsibility for their operation.32 The Government also recently introduced the Electricity Theft Control Act 2058 and the Electricity Theft Control Regulations 2059, which treat electricity theft as a criminal offence and give NEA new powers to deal with the problem. Such initiatives are to be applauded, but OEM found that illegal connections were easy to locate in many rural areas, and that NEA staff accompanying the OEM simply accepted such connections as a fact of life. 42. NEA will no longer contribute to the capital cost of rural electrification programs because they are seen as uneconomic. But rural electrification is an important priority of the Government, which has a rural electrification budget of NRs590 million for FY2004. From now on, the Government will contribute 80% of the capital cost of rural electrification programs to NEA as equity, with beneficiaries funding the remaining 20%.33 In addition to the Danish Government scheme, ADB’s current REDT project includes $18.4 million for rural electrification. But accessible rural areas are now fully electrified, and rural electrification schemes in less-accessible areas are failing to recover the cost of generation. The operation and maintenance of these programs will put increasing pressure on NEA’s financial resources, and will force reliance on subsidy support from NEA’s urban domestic consumers.34 The Government is aware of the problem and is looking to the ongoing TA35 for recommendations on how to manage it over time. C. Financial and Economic Reevaluation 43. The financial and economic reevaluation of the Project is discussed in detail in Appendix 3. Reevaluations were carried out separately for the urban rehabilitation and rural electrification components, using the same approach used at appraisal and in the PCR. The period of analysis was FY1992–FY2021. Given the recent power demand and forecast growth, the facilities rehabilitated or installed under the Project’s urban and rural components are expected to be loaded to full capacities by 2006. After that, further reinforcements will be required to meet the load growth. 32 By March 2003, 170 applications have been received for the program, and 18 contracts signed. It is hoped that the scheme will reduce theft, because consumers will be less likely to steal from their neighbors. But success of this scheme will depend on the ability of the small local cooperatives to operate and maintain the network sustainably. 33 The beneficiary contribution does not have to be in cash; it can be in labor, supply of wooden poles, and other “inkind” contributions. 34 NEA’s current tariff is designed to avoid cross subsidy among different customer groups, but the tariff structure does not prevent cross subsidies within customer groups. In FY2003, domestic customers accounted for 36% of sales and 37% of revenue. 35 TA 3552-NEP: Management Reforms and Efficiency Improvements for NEA, for $0.8 million, approved 27 November 2000. 14 44. Incremental electricity sales in each urban rehabilitation scheme from 1998 to 2003, estimated in the Feasibility Study Report of 1992, were checked against NEA’s overall load increases during the same period and found reasonably realistic. Thus, those data were used in the reevaluation. NEA has estimated that about 200,000 new connections in rural areas were made under the Project from 1998 to 2003. This is about 2.4 times the target number of new connections estimated at appraisal. 45. The financial cost of power for the urban component is assumed to be $0.055/kWh. That is in line with NEA’s supply at 33-kV distribution levels from its own generation plants. Rural electrification introduces new load to the network, so the financial cost of electricity for rural supply is derived from NEA’s marginal generation cost. A reasonable proxy for this would be NEA’s average purchase cost of NRs6.1/kWh from IPPs. The economic cost of power supply is given by the opportunity cost of exporting power to India,36 which at the time of OEM was $0.066/kWh. The system loss, excluding transmission at the distribution level, is assumed to be 15%. 46. NEA’s current average tariff of NRs7/kWh is used as the financial benefit indicator for the urban component. But a rural electrification scheme would not produce this yield because of the high proportion of low-use and lifeline domestic customers. Economic benefits are assumed to be derived mainly from (i) displaced use of kerosene for lighting and of diesel generators for power and (ii) induced electricity consumption. For displaced consumption, the average economic value of electricity consumption to displace kerosene lighting with wick lamps is estimated as $0.2/kWh, and displacement of power generated by diesel generators, as $0.15/kWh. For induced consumption, the willingness to pay for both residential and industrial consumers is assumed to be the weighted average of the unit cost saving and the existing tariff. 47. Table 3 summarises results of financial and economic analyses at project appraisal, completion, and post-evaluation. Table 3: Summary of Financial and Economic Revaluations Item Urban Rehabilitation Rural Electrification Appraisal 18.8 4.5 FIRR (%) PCR 13.4 0.8 PPAR 11.8 Appraisal 22.2 13.5 EIRR (%) PCR 20.0 11.1 PPAR 24.6 19.2 EIRR = economic internal rate of return, FIRR = financial internal rate of return, PCR = project completion report, PPAR = project performance audit report. Source: Appendix 3. 48. The reevaluated economic internal rate of return (EIRR) for the urban component is comparable to the appraisal estimate. The EIRR estimate for the rural component was more favorable, mainly because of the large increase in the number of new connections compared with estimates at appraisal and PCR. The lower recalculated financial internal rate of return (FIRR) for the urban component resulted from inadequate adjustment of tariffs to more sustainable levels. Depreciation of the Nepalese rupee against the dollar also affects the FIRR.37 The FIRR for the 36 Under the Power Exchange Agreement with India, the annual power exchange between Nepal and India is now about 50 MW. Both countries recently agreed to gradually increase the exchange level to 150 MW. 37 The Nepalese rupee has depreciated 159% since appraisal in1988. 15 rural components is negative since the average revenue of NRs5.6/kWh from rural consumers is insufficient to even cover the marginal generation cost of NRs6.1/kWh. D. Sustainability 49. Electricity demand in many project areas, including remote areas reticulated for the first time, is high compared with the forecast at appraisal. Table 4 compares the current peak load at selected area substations constructed under the Project with the available forced cooled transformer capacity. The loads shown include distribution network losses and, in many cases, are undoubtedly elevated due to the level of electricity theft. Nevertheless, none of these substations have been in service for more than 5 years. Table 4: Substation Loads Commissioning Transformer Year Capacity (MVA) Itahari 8 2000 Inaraua 8 1999 Bisnupur 8 1999 Parsa 8 2000 Ilam 3 1999 Chanauli 8 2000 Kawasoti 8 2000 Parasi 8 2000 Palpa 8 1999 Gajuri 3 2001 Gwh = gigawatt hours, MVA = megavolt amps. Source: Nepal Electricity Authority. Substation Energy Supplied FY2003 (GWh) 42.0 16.5 7.9 23.1 7.0 16.6 14.6 13.0 9.0 3.8 Peak Load FY2003 (MVA) 7.5 5.7 3.2 6.8 1.3 5.6 4.5 2.7 2.9 1.6 Peak Load (% of capacity) 94% 71% 40% 85% 43% 70% 56% 34% 36% 53% 50. Ample evidence shows that a reliable and good-quality supply of electricity stimulates industrial and economic development in areas with good road access. For example, NEA supplies more than 20 industries at 11 kV in the region served by the Kawasoti area substation.38 The main sustainability problem in these areas is the availability of capital to increase capacity as the existing distribution system becomes overloaded. Indeed, much of the electrification installed during the Sixth Power Project has already been reinforced. For accessible areas with potential for commercial and industrial development, NEA should take a longer-term view of future load requirements in planning future additions of capacity. The situation is different in areas without good road access, because significant industrial development is unlikely. 51. The rural electrification component of the Project includes some previously unelectrified towns along the east-west highway that will probably benefit from ongoing industrial and commercial development. But all of Nepal’s more accessible areas have now been electrified, and the financial sustainability of project components that serve less-accessible areas is unlikely. Nevertheless, NEA will probably keep all parts of the Project operational because of the Government’s commitment to rural electrification, and the benefits of electrification to individual consumers. 38 The Kawasoti substation is in western Nepal, adjacent to the main east-west highway. The substation was built through the rural electrification component, not only to supply new load but also to support the overloaded 11-kV distribution network built under the Sixth Power Project. The transformer capacity installed under the Project was only 3 MVA, but a larger transformer was installed within 1 year of commissioning the substation. 16 E. Technical Assistance 52. The attached TA was implemented from July 1990 to July 1991, when a distribution and a commercial consultant spent a year in Kathmandu working full time with NEA. The distribution consultant (i) proposed a structure for distribution planning and developed a schedule of distribution requirements, (ii) established a drawing office and started the development of system diagrams, (iii) developed procedures to establish and operate a management information system and a 5-year rolling plan, (iv) developed the structure for a technical standards committee, and (v) ran a training course on distribution planning. The commercial consultant (i) undertook a diagnostic review of NEA’s consumer accounting and billing processes, and (ii) developed a plan to introduce computerized billing, using commercial billing software. The consultants fulfilled their TOR requirements, but TA achievements fell short of expectation because of the lack of NEA commitment to immediate implementation of TA recommendations, and insufficient counterpart funds to make the TA more effective.39 Overall, the TA is assessed as partly successful. IV. A. ACHIEVEMENT OF OTHER PROJECT IMPACTS Socioeconomic Impact 53. The OEM conducted a socioeconomic survey to assess the impact of electrification on individual domestic consumers, particularly consumers that had no electricity before the Project (Appendix 4). In summary, electrification in urban areas and areas near sealed roads has positive impacts on the local economy because of benefits to the lives of individual consumers, and stimuli for industrial and commercial development. This economic development improves the lives of domestic consumers so much that many consumers in such areas pay more than the minimum “lifeline” electricity cost. In remote areas, consumers’ benefits from improved lighting and use of radio, television, and electrical fans would be impossible without access to electricity. Women have been the greatest beneficiaries of electricity. But many poor households in remote areas have not connected to electrical power because the initial connection cost is so high. Furthermore, NEA will not supply electricity to houses with thatch roofs because of high fire risks (although some such households illegally connect to neighbors’ electricity). The industrial use of electricity in remote areas is limited largely to rice and oil mills that were diesel-powered before electrification. A key project objective at appraisal was to use electricity as an energy source for irrigation, particularly for shallow well pumps. This did not materialize, mainly because of the cost of providing a mains connection to each pump site. With diesel engines, there is no connection cost and one engine can service a number of pumps because it can be moved from site to site. B. Environmental Impact 54. The Project was appraised in 1989 and had no specific environmental objectives. The appraisal report noted, however, that the design would take international environmental and safety considerations into account “relevant to the location of transmission and distribution lines and of substations.” Construction of the Project has been environmentally benign, with most overhead lines located on road reserves. As noted in Appendix 4, there have been few beneficiary complaints about environmental issues. But there were some concerns about the safety of 11 kV lines constructed in urban areas. In such cases, NEA took appropriate steps to 39 An example was cancelation of a planned seminar on distribution planning for regional planning staff because NEA,, citing budgetary constraints, would not allow the staff to travel to Khatmandu. In order to keep up the momentum, ADB wanted to continue both components of the consultancy for 12 more months under a new TA, if NEA would use savings from the Fifth Power Project to purchase and implement a pilot billing system. But NEA would not agree. About 4 years later, savings were used for a pilot billing system. 17 alleviate the concerns and allow the Project to proceed. The Project was also expected to have an indirect environmental impact by utilizing Nepal’s indigenous hydropower facilities to replace fuelwood and imported fossil fuels. The Project seems to have done little to reduce fuelwood use, although it has substituted somewhat for imported fossil fuels through reduced use of kerosene and small diesel motors. But NEA operates high-cost diesel generation plants at times of peak loads, and the additional electricity demand caused by the Project requires increased generation from these sources. The engineering report in Appendix 1 also discusses possible design improvements that might further reduce the environmental and safety consequences of future projects.40 C. Impact on Institution and Policy 55. Objectives of the institutional development TA have, by now, mostly been achieved, although more slowly than envisaged at appraisal, and with additional help from ADB and other donors. First, NEA now has a computerized billing system in the larger branches that generate 70% of its revenue. With help of local consultants, NEA has enhanced the original billing software and is now rolling out the enhancements. Under the REDT project, NEA will purchase upgraded billing software with state-of-art technology, which it plans to install in all but its smallest branches. Second, distribution planning is still centralized in Kathmandu, even though detailed design of 11kV distribution network extensions is undertaken at the branch level. NEA has purchased a computerized geographic information system, and has incorporated records of its network assets down to the 11-kV level. NEA has also purchased, with ADB funding, software for analysis of distribution systems, and is interfacing the two packages. Both systems are available only in Kathmandu, which may limit benefits from the geographic information system. V. A. OVERALL ASSESSMENT Relevance 56. The Project conformed to Nepal’s needs for power sector development and ADB’s strategy for assistance at appraisal to support the development of integrated power supply in urban and rural areas. The Project has remained relevant to the achievement of sector development objectives for both the Government and ADB. However, there was a design weakness related to the introduction of SWER. Overall, the Project is assessed as relevant. B. Efficacy 57. The Project achieved its primary objectives of improving quality and reliability of power supply in areas with rapid growth demand, and of extending the availability of a reticulated distribution system. But project goals in terms of NEA’s system loss reduction and financial sustainability, envisaged at appraisal, have not been fully achieved. Overall, the Project is rated efficacious. C. Efficiency 58. Full completion of the Project took more than 10 years. During the early stages, ADB considered it an at-risk project. While credit should be given for the fact that significantly more rural electrification was achieved than envisaged at appraisal, this was made possible by factors 40 The need to design the Project to minimize environmental impact when things go wrong was not specifically noted in the appraisal report. 18 largely outside the control of project participants. Although the rural component is not viable financially, the Project has achieved more favorable EIRRs than estimated at appraisal. Overall, the Project is rated as efficient. D. Sustainability 59. The rehabilitation component and the pole factory are considered highly sustainable. The rural electrification component is sustainable only with a significant and continuing subsidy, which was not envisaged at appraisal. Overall project sustainability is considered less likely on the basis of NEA’s weak financial position and continuous resource injections required to ensure continued operation of project facilities. E. Institutional Development and Other Impacts 60. Through the Project, NEA gained enough experience in distribution planning and design so that external engineering and project implementation consultants were no longer required during later project implementation and for future ADB–funded distribution projects. The Project also facilitated economic growth in project areas by providing reliable power. The institutional development and other impacts of the Project are rated significant. F. Overall Project Rating 61. Overall, the Project is rated successful. This assessment recognizes the Project’s success in terms of physical achievements and socioeconomic impact at project levels, but also takes into account the requirement for ongoing subsidies to sustain the rural electrification component. G. Assessment of ADB and Borrower Performance 62. Despite the much-improved implementation performance by NEA and ADB after 1995, the performance of both ADB and the EA is assessed as partly satisfactory. For ADB, this assessment reflects failure to take proactive and timely action to respond to implementation problems early in the Project, as well as late decisions regarding the first loan extension, and the aborted decision to transfer project administration to NRM. ADB’s partly satisfactory performance reflects the inadequate attention that the project department gave to project administration. For the EA, this assessment is based on the unsatisfactory project progress over the first 5 years through the end of 1995, its failure to reduce losses to covenanted levels, and the poor financial performance that continues to threaten the Project’s sustainability. VI. A. ISSUES, LESSONS, AND FOLLOW-UP ACTIONS Key Issues for the Future 63. NEA’s most pressing problem is its deteriorating financial performance. NEA’s cash operating surplus for FY2003 was only 42% of what ADB forecast in 1999 (Appendix 2). More than 77% of this surplus was required to pay its interest liability. NEA is well aware of this problem, and argues strongly for relief from these interest charges. But the more fundamental cause of NEA’s problems is failure to raise electricity tariffs to more sustainable levels. The average internal electricity tariff in FY2003 was only 70% of the level assumed in ADB’s 1999 forecast, and will not change significantly in FY2004, since no application for a tariff increase has 19 been submitted to the ETFC.41 Tariff setting in Nepal remains a political issue, because all ETFC members are government appointees. The prevailing view, both within the Government and NEA, is that the current average tariff level of NRs7.02 (about $0.10) is high, compared with that in other developing countries in the region. In OEM’s view, significant tariff increases are highly unlikely in the near future. Insurgency problems, which seemed to escalate during the OEM, make it even more difficult for the Government to make meaningful tariff adjustments. 64. There is little doubt that system losses are excessive, and contribute significantly to the current level of electricity tariffs. Total losses in FY2003 were 553 GWh—almost 25% of NEA’s electricity generation. The cost of these losses is estimated at NRs2,500 million, assuming an average generation cost of NRs4.50/kWh, or NRs3,300 million using a marginal generation cost of NRs6.0 per kWh. Using the marginal generation cost, each 5% reduction in total losses would save NEA about NRs660 million in generation costs. A reduction in losses from 25% to 15% would mean an average tariff reduction of NRs0.87/kWh, or 12% if applied to all domestic tariff reductions. Thus, NEA must continue to vigorously address electricity losses, if it seriously wants to reduce tariffs.42 65. Assuming no change in NEA’s operating position, the rural electrification component of ADB’s REDT project will strain NEA’s financial position and further reduce its ability to meet its loan covenants. REDT will fund the installation of rural electrification costing $24.6 million or NRs1,720 million. Incremental electricity sales resulting from REDT are estimated to eventually reach 90 GWh. Based on NEA’s current operating situation, REDT will, at best, generate enough revenue to cover the cost of the incremental generation.43 But, consistent with ADB’s financial covenants, the rural electrification component will create an incremental annual revenue requirement of about NRs420 million.44 Considering the relatively high initial connection charges and the transaction costs of making monthly journey to pay electricity bills (Appendix 4), possibilities of subsidizing the initial connection charges and reducing costs of payment for rural customers should be explored so the tariff might be raised at least to a break-even level for rural supply. B. Lessons Identified 66. The decision not to proceed with the use of SWER technology, while justified on technical grounds, caused delays early in the Project because it necessitated a redesign of the rural electrification component. These delays may have been avoided if a more substantive PPTA consultancy had been undertaken, and if the technical feasibility of using SWER had been more thoroughly researched during appraisal. In this case, the staff consultant who did the project preparation suggested the use of SWER, but was not required to carry out technical investigation of proposed alternative technologies in the TORs. On one hand, innovation by consultants should be encouraged. But on the other hand, for a project of this size and complexity, a full scale PPTA should be mounted and the TORs should include investigation into the use of new and alternative technologies. 41 The most recent tariff increase became effective on 17 September 2001. NEA noted that the insurgency problem makes loss reduction initiatives more difficult to implement. 43 See paragraph 35. Furthermore, alternative approaches give similar results. NEA’s current average tariff is NRs7.02 / kWh, but a rural electrification scheme would not yield this because of the high proportion of low-use and lifeline domestic customers. Thus an average rural electrification tariff of NRs6/kWh, equal to the assumed marginal generation cost, is a reasonable assumption. 44 The analysis assumes that revenue from the rural component of REDT will cover only the incremental cost of energy, and no significant reduction of electricity losses below current levels. 42 20 67. The main implementation problems arose during the first 5 years of the Project. The Project was administered from ADB headquarters in Manila, and the project files show little evidence of any useful input from NRM, even though the Project was considered problematic. Under those circumstances, annual review missions were insufficient and the mechanism for project monitoring at NRM was less than effective (footnote 26). Implementation problems might have been reduced if an NRM officer had taken a more proactive role in monitoring the Project between review missions. Regular monthly or quarterly meetings could have been held with NEA’s project implementation unit, and proper documentation of those meetings might have helped keep the ADB project officer in Manila informed of problems as they arose. This may have allowed quicker corrective actions, and allowed the addressing of problems before they developed into significant issues. 68. Problems associated with poor contractor performance are not unique to the Project, and should be avoided in the future. An ADB procedure for evaluating performance of both international and local contractors, similar to that used for individual consultants, would be useful. The performance of contractors would be recorded in files for eligibility check before prequalification for future contracts. C. Follow-Up Actions 69. Proper and regular maintenance of the project facilities deserves special attention (Appendix 1). In particular, NEA should undertake a technical assessment of the problem of unavailable spare parts for the Indian-manufactured 11-kV indoor switchgears, and ensure that resources are sufficient for continued operation of project facilities. Otherwise, no specific followup actions are suggested. But issues and lessons identified in this PPAR are highly relevant to the successful implementation of the ongoing REDT project. Appendix 1 21 ENGINEERING REPORT A. Subtransmission and Distribution Lines 1. The prestressed concrete poles, which were either manufactured at the pole factory constructed under the Seventh Power Project or purchased from private sector manufacturers, are proving a cost-effective alternative to the steel poles traditionally used in Nepal. The poles used in the Project were still in good condition and showed no sign of deterioration. Concrete poles should be little affected by the climatic conditions and could last more than 50 years. Unfortunately, concrete poles are much heavier than their steel alternatives, and transport difficulties mean that they are not suited to the hill area. These poles were used extensively for the 11 kV distribution lines installed by local contractors. 2. Most 33 kV subtransmission lines were constructed under a turnkey contract, using steel poles. These poles are not adequately protected against corrosion, and already have a surface coating of rust. They are particularly vulnerable where the poles enter the ground because of the presence of stagnant water. The standard design is to extend the concrete foundation above the ground and to slope the top of the foundation with grout so that water will run away—but often, this was not done. 3. Steelwork that was galvanized was generally still in good condition. But there was no consistency with respect to the corrosion protection of steelwork exposed to the elements. Ungalvanized steel pole lines often had galvanized crossarms, while concrete pole lines often had ungalvanized steel crossarms. All steelwork exposed to the elements, including poles, should be galvanized or otherwise adequately protected against corrosion. 4. Lines built under the Project were generally well-designed and -constructed. This was not always the case with new construction undertaken by branch offices after the Project. For example, the branch office has recently completed an extensive new rural electrification project east of Janakpur, possibly using materials left over from the Project. Poles were not upright and crossarms were not straight, because crossarm stays were not used. B. Area Substations 5. The design of area substations was generally adequate, and while some substations were well-maintained, the quality of maintenance varied. Obvious indicators of unsatisfactory maintenance practices were poor housekeeping and graveled switchyards overgrown with weeds. The purpose of a graveled switchyard is to protect personnel during a system fault, but if weeds overgrow the gravel, it becomes ineffective. The key factor affecting maintenance appeared to be the ability and enthusiasm of the substation managers. The Parsa substation was flooded to a depth of about 1 meter during the 2003 monsoon season. While the substation is still operational, remedial maintenance, such as regraveling of the switchyard, is ongoing. 6. Power transformers contain large quantities of oil, but their foundation pads were not bundled to stop oil flowing to the ground in the event of a leak. As area substations are invariably manned, the pads should be bundled with water draining away through a normally open drain valve. In the event of an oil leak, the operator could contain the oil by closing the water drain valve. It was also noted that the power transformers were not fixed to the pad and could topple in an earthquake. Earthquakes are rare—but not unknown—in Nepal, and providing suitable earthquake clamps would be a relatively inexpensive form of protection. 22 Appendix 1 7. The Indian-manufactured 11-kV indoor switchgear used in area substations throughout the Project is no longer manufactured, and the Operations Evaluation Mission (OEM) was advised that spare parts were no longer obtainable. Although all units that the OEM observed appeared in good condition and were still operational, their maintenance will become an increasing problem in the future. Considering the number of these units, the Nepal Electricity Authority (NEA) should undertake a technical assessment of this problem to determine the extent to which suitable replacement parts can be procured from other sources. 8. Some of the power transformers installed under the Project had already been replaced with larger units, having been loaded to their rated capacity within 5 years of installation. The problem appears to be that all parts of the distribution system had been designed for a forecast 10-year load. The use of a longer planning horizon, when determining the appropriate capacity of power transformers, should be considered, particularly in areas where high load growth is forecast. 9. The load recorded in the log of the Bisnupur substation was inconsistent with the 11 kV current levels, and apparently was out by a factor of two. The incorrect load reading seems to have been included in the weekly reports that the operator submitted ever since the station was commissioned, but the error had not previously been noted. The length of time over which this situation continued suggests inadequate engineering supervision. C. Distribution Substations and Low Voltage Distribution 9. The decision not to proceed with the single wire earth return (SWER) system was appropriate. Internationally such systems are generally used only in areas where population and load densities are much lower than the areas reticulated under the Project. Individual customer loads in Nepal are generally much lower than in developed countries, but this is offset by far higher population densities, even in rural areas. Although a SWER system might have been technically feasible, and possibly cheaper, its continuing operation could well have been problematic. The stated purpose of using SWER technology was to reduce costs, but alternative cost-saving opportunities could have been considered. For example, two-wire lines and singlephase transformers do not have the technical problems of single-wire systems and may have been feasible for many spur lines. Also NEA uses a standard two-pole platform structure for its distribution substations, regardless of transformer size, so an alternative design for smaller transformers could have been considered. Also, the use of surge arrestors on every transformer, irrespective of size, is not normal practice in many countries—especially when all high-voltage transformer bushings are already fitted with surge gaps. 10. The distribution substation design included molded case circuit breakers (MCCB) to protect the low-voltage circuits of each transformer. This allows the low-voltage circuits to be isolated without having to pull the high-voltage transformer fuses. The MCCBs were designed for indoor use, but were housed in metal cabinets mounted on the poles beside the transformers. The doors of these cabinets were invariably left open, or were missing, to allow operation of the MCCBs from the ground, using a stick. The MCCBs will clearly deteriorate when exposed to the elements. In some cases, the MCCBs had already been bypassed. Cabinet doors should be kept locked. If necessary, the cabinets should be mounted closer to the ground to allow easier access. The existing arrangement also facilitates electricity theft because it allows easy isolation of low-voltage distribution lines, enabling illegal connections to be made safely. Appendix 1 23 11. Proprietary connectors to secure service drops to low-voltage distribution lines are generally not used. Instead, the service drop conductor is simply twisted around the line conductor. Such connections can become loose over time, causing low customer voltage and increased losses. Furthermore, a loose neutral conductor is a safety hazard because the neutral voltage may rise above ground potential on the load side of the loose connection. In one case, a small weight appeared to have been hung over the service drop conductor, apparently to ensure a better connection. 12. The OEM observed a number of cases where temporary repairs had been made to distribution substations, but they had apparently become permanent either because of a lack of parts or failure to return to make more permanent repairs. 24 1999 Forecast Actual Energy Energy Available (GWh)a Total Energy Sales (GWh)b Losses (%) Average Tariff (Rs/kWh)c Income Statement (NRs million) Electricity Sales Other Total Operating Revenue Operating Expenses Cash Operating Surplus Depreciation (on Asset Book Value) Interest Other Expenses/Adjustments Profit Before Tax 2000 Forecast Actual 2001 Forecast Actual 2002 Forecast Actual 2003 Forecast Actual 1,475 1,113 24.5 4.98 1,475 1,114 24.5 5.05 1,606 1,235 23.1 5.90 1,701 1,269 25.4 5.70 1,746 1,354 22.5 8.41 1,868 1,407 24.7 6.23 2,195 1,779 18.9 10.09 2,066 1,540 25.5 6.52 2,284 1,856 18.7 10.09 2,261 1,708 24.5 7.02 5,421 349 5,770 3,009 2,761 700 5,397 385 5,782 3,180 2,602 976 7,122 370 7,492 3,300 4,192 682 6,856 356 7,212 3,605 3,607 949 11,043 457 11,500 4,910 6,590 824 8,169 593 8,762 6,313 2,449 1,119 15,675 500 16,175 6,424 9,751 1,388 9,476 460 9,936 7,508 2,428 1,420 16,858 523 17,381 6,963 10,418 1,992 11,276 521 11,797 7,292 4,405 1,830 1,312 498 1,141 895 1,327 (739) 1,244 655 1,445 (1,631) 1,188 4,008 4,344 (3,264) 1,396 5,409 4,839 (3,400) 3,410 2,708 499 168 2,030 757 4,263 (2) 3,956 (717) 3,532 (656) GWh = gigawatt hours, kWh = kilowatt hours, NRs = Nepalese rupees. a Includes local generation, purchases from independent power producers, and purchases from India. b Includes sales to India. c Tariff from internal sales only. Source: Asian Development Bank (1999 forecast), Nepal Electricity Authority. Appendix 2 OPERATIONAL PERFORMANCE OF THE NEPAL ELECTRICITY AUTHORITY Appendix 3 25 FINANCIAL AND ECONOMIC REEVALUATION A. Background and Basic Assumptions 1. The financial and economic evaluations of the Seventh Power Project at appraisal and in the project completion report (PCR) were carried out separately for the components on urban rehabilitation and rural electrification. The project performance audit report (PPAR) largely followed the same approach. The period of analysis covered FY1992–FY2021. The economic life of the Project is assumed to be 23 years, from 1998 to 2021. All prices and costs are expressed in 1999 constant values. 2. For financial analysis, capital costs were net of interest during construction. For economic analysis, taxes and duties were excluded and local costs (nontradable) were converted to border price using a standard conversion factor of 0.90. Incremental operation and maintenance costs were estimated annually at 2% of accumulated capital costs for both the rural and urban components. 3. Given the recent demand for power, and forecast growth scenarios, the facilities rehabilitated or installed under the urban and rural components are expected to be loaded to full capacity by 2006. After that, further reinforcements will be required to meet the load growth. Once the full capacity of the distribution facilities is reached, project benefits are kept constant until the end of the evaluation period. B. Urban Rehabilitation Component 4. Incremental electricity sales in each urban scheme from 1998 to 2003, estimated in the Feasibility Study Report of 1992, were checked against the overall load increases of the Nepal Electricity Authority during the same period. The figures were found reasonably realistic, so they were used in the reevaluation. After 2003, incremental sales are projected to increase at 10% per annum until 2006, when project facilities reach their full load capacity, then remain constant afterward. 5. For financial analysis, the actual average tariff rates are used until 2003, adjusted for inflation at 5% annually until 2006. Economic benefits are assumed to be derived from (i) displaced use of kerosene for lighting and diesel generators for power and (ii) induced electricity consumption. The proportion of the displaced: induced energy use is assumed to be 60: 40. For displaced consumption, the average economic value of electricity consumption to displace kerosene lighting with wick lamps is estimated to be $0.2/kWh, and to displace power generation with diesel sets, $0.15/kWh. For induced consumption, the willingness to pay, for both residential and industrial consumers, is assumed to be the weighted average of the unit cost saving and the current tariff. One should note that other economic benefits resulting from reduction in system losses—such as improvements in health and productivity of household members—were not considered in the analysis because available information was insufficient to quantify them. 6. The financial cost of power was assumed to be $0.055/kWh, which was in line with the Nepal Electricity Authority’s (NEA) cost of supply at 33-kV distribution levels from its own plants. The economic cost of power supply is derived from the opportunity cost of exporting power to India, which was $0.066/kWh at the time of the Operations Evaluation Mission. The system loss at the distribution level was assumed as 15%. 26 Appendix 3 7. With these assumed costs and benefits, the financial and economic reevaluation of the urban rehabilitation component resulted in a financial internal rate (FIRR) of 11.8% and an economic internal rate of return (EIRR) of 24.6% (Table A3). C. Rural Electrification Component 8. NEA has estimated that about 200,000 new connections in rural areas were made under the Project from 1998 to 2003. This is about 2.4 times the target number of new connections estimated at appraisal. About 98% of the new connections are rural residential and commercial consumers; the other 2% are industrial users. 9. According to the latest NEA information, 60% of the rural residential users consume less than 20 kWh/month at the lifeline tariff of NRs4/kWh. The others consume an average of 60 kWh/month at a tariff of NRs7.5/kWh. Industrial users consume an average of 1,200 kWh/month. Given these as the current level of electricity consumption of project beneficiaries, project facilities under rural electrification are expected to reach their full capacity by 2006, at an annual sales increase of 10%. Sales are assumed to remain constant afterward. 10. Rural electrification adds new load to the network, so the financial cost of electricity for rural supply should be based on NEA’s marginal generation cost. A reasonable proxy for this would be NEA’s average purchase cost of NRs6.1 per unit from independent power producers. Assuming the proportion of the displaced: induced energy use for the rural component to be 40:60, similar indicators for other costs and benefits described in paras. 5 and 6 above were used. The financial and economic reevaluations of the rural component (Table A3) result in a negative FIRR, and an EIRR of 19.2%. The negative FIRR for the rural component is because the average revenue of NRs5.6/kWh from rural consumers is insufficient to cover even the marginal generation cost of NRs6.1/kWh. The significant EIRR improvement, compared with appraisal estimates, was caused by the large increase in the number of new connections. 11. Table A3 summarises results of financial and economic analyses at project appraisal, completion, and post-evaluation. Table A3: Summary of Financial and Economic Revaluations Component Urban Rehabilitation Rural electrification FIRR (%) Appraisal PPAR EIRR (%) Appraisal PCR PCR PPAR 18.8 13.4 11.8 22.2 20.0 24.6 4.5 0.8 Negative 13.5 11.1 19.2 FIRR = financial rate of return, EIRR = economic rate of return, PCR = project completion report, PPAR = project performance audit report. Source: Report and Recommendation of the President, Project Completion Report and Project Performance Audit Report for Loan 1011-NEP (SF): Seventh Power Project. 27 Appendix 4 REPORT ON THE SOCIOECONOMIC SURVEY A. Background 1. Nine village development committees (VDCs) were visited to assess the socioeconomic impacts of the rural electrification component of the Project.1 The impact assessment was made in a rapid assessment mode, using mostly qualitative techniques, such as focus group discussions (FGD). Table A4.1 gives the regions, districts, and VDCs visited, and the number of participants in the FGDs. Table A4.1: Region, District, VDCs and the Number of Participants in FGD Region Districts Eastern Siraha Central Chitwan Western Nawalparasi, Rupandehi Total 4 VDCs Ram Nagar Michaiya, Bishanpur Jutpanini, Pithuwa, Pipale Badahara Dubaulia, Dev Gaun, Motipur, Semalara 9 No. of Male Participants 8 10 11 10 9 10 9 10 No. of Female Participants 8 5 4 5 5 5 3 2 Total No. of Participants 16 15 15 15 14 15 12 12 72 42 114 FGD = focus group discussions, VDC = village development committees. FGD was conducted together with participants from Motipur. Source: Operations Evaluation Mission. a B. Survey Findings 1. Socioeconomic Background of Participants 2. Almost all participants had some education. Agriculture was the main source of income for most; few are in services or other business. About 90% of the households have bungalowtype houses. Only 5 to 10% of the houses have thatched roofing. 2. Status of Rural Electrification 3. Few participants know how rural electrification started in their areas. In the initial stage of electrification, only a few households could connect to electricity, largely because meter boxes were not available. Table A4.2 gives the current number of households based on the 2001 census and the estimated number of households connected to the electricity in the sample VDCs (except for Motipur). Electricity coverage in the sample VDCs is generally higher than in other rural areas of Nepal. 1 Loan 1011-NEP (SF): Seventh Power Project, for 51 million equivalent, approved on 11 January 1990. 28 Appendix 4 Table A4.2: Number of Households Connected to Electricity Sample VDCs Households (no.) Ram Nagar Mirchaya Bishanpur Jutpani Pithuwa Pipale Badahara Dubaulia Dev Gawa Semalar Total 1,710 855 2,310 1,925 2,380 1,200 875 1,505 12,760 Estimated households connected (no.) 1112 200 1,848a 1,829a 2,142a 228 149 1,430)b 8,930 Household electrification (%) 65.0 23.4 80.0 95.0 90.0 19.0 17.0 95.0 70.0 no. = number, VDC = village development committees. a From 20 to 40% of the households in each of these VDCs use electricity by illegal connection. b Some areas were already electrified before the Seventh Power Project. 3. Electricity Usage The extent of electricity use depends on the socioeconomic conditions of households. In 4. the sample VDCs, the beneficiaries mainly use electricity for the following purposes: (i) Lighting. Every beneficiary household uses electricity for lighting every day. The time of use ranges from 3 to 4 hours per day. In some areas like Chitwan and Rupandehi, beneficiaries also use electricity for about 1 hour each morning. (ii) Television and radio. Almost 80% of the households in Chitwan have television sets and radios. In Rupandehi District, more than 90% of the households have televisions, but only 5 to 10% of the households in Siraha and Nawalparasi districts have televisions. (iii) Electric fans. Use of electric fans during the summer (April–August) is common in all the sample areas that have connection to electricity. The electric fans are used for 4 to 10 hours per day, depending on the temperature. (iv) Ironing clothes. The use of electric irons is limited to about 10% of the households in Chitwan and Ruapnadehi districts. Electric irons are rare in other areas. (v) Cooking. Almost no participants, in any sample VDC, cook with electricity. Most households use firewood or dung cakes for cooking. Firewood, in different forms, is easily available within most village vicinities. The community forestry also supplies some firewood to its members at cheap prices. The firewood can be purchased in the market, or from local people. Depending on the distance from the forest area, a kilogram of firewood costs from NRs0.90 (in Semelar) to NRs2.50 (in Badhara Dubaulia). A family of 5 to 6 people can cook one meal (lunch or dinner) with 2 to 3 kilograms of firewood, which is much cheaper than using electricity. The participants consider electricity expensive for cooking, compared with firewood, kerosene, or gas. (vi) Irrigation. Only a few households use electricity for irrigation. Shallow tube well irrigation, using diesel-fueled pumps, are still used extensively. The advantage of using diesel pumps is that they can be carried to different sites easily. One diesel pump can be used at least in four different places in 1 day. In Badahara Dubaulia alone, more than 100 diesel pumps used for irrigation. Appendix 4 29 (vii) Storing water. Few households use electric pumps for storing drinking water. Electricity is used to pump water from deep wells into storage talks for consumption by 10 to 15 nearby households only in Pithuwa of Chitwan District. Pithuwa has 20 such wells. But the electricity to pump the water is obtained by illegal connections, or “hooking.” FGD participants felt that the Nepal Electricity Authority should provide meter boxes free of charge for such public wells. (viii) Rice and oil mills. From 4 to 13 rice and/or oil mills are run by electricity in each sample VDC. There are 20 to 25 rice and oil mills in Motipur and Semalar of Rupandehi District. Participants noted that running rice and oil mills on electricity is cheaper than by diesel. (ix) Poultry farms. Poultry farms are mushrooming in most of the sample VDCs as a result of electrification. In Pipale alone, about 100 households have poultry farms. Some of the poultry farms have a capacity of raising 20,000 to 25,000 chickens. Owners of poultry farms also use electricity to make chicken feed. These businesses not only provide employment, but also a good income for some families. Participants all agreed that poultry farming would be almost impossible without electricity. Also, furniture factories, saw mills, and beer breweries in Siraha District use electricity. 4. Electricity Consumption 5. Except for factories and poultry farms, electricity consumption for domestic customers is low. Most households consume 20 to 50 units of electricity per month. Few households use florescence lights, because the installation cost is high. Normally. 15- to 40-watts bulbs are used at home. From two to six bulbs are generally used in a household, depending on its income. Normally, electricity is used for 3 to 4 hours a day. In some areas of Chitwan and Ruapndehi, households also use electricity for about 1 hour in the mornings. Electricity consumption is higher in all sample VDCs during the summer because of the use of electric fans. 5. Main Beneficiaries 6. Women have largely benefited from electricity use because (i) electricity makes cooking easier after dark, (ii) electric lights make it easier to go to the bathroom during the night, (iii) rice and oil mills are closer to homes, so that women can sleep later in the morning, and (iv) more women can watch television, either at home or in a neighbor’s home. Students have also benefited from electricity, mainly because they can study longer. 6. Major Complaints 7. All participants considered the electricity tariff high. In all sample VDCs, few consumers want to consume more than the minimum of 20 units so that the lifeline tariff of Nrs4/kWh can be applied. 8. In all sample VDCs, only a few households (30–40%) produce enough food for a year. The others must rely on other activities. Many poor people, although willing to use electricity, could not afford it because of high initial cost for connection. The installation cost is from NRs2,000 to NRs3,000, depending on the distance to the connection point. Many rural people feel that meter boxes should be made available free of charge, so they can afford electricity use in their homes at the lifeline tariff. 30 Appendix 4 9. Paying electricity bills has recently become a serious problem for rural people. Because of the Maoist insurgency, bill payment centers have been moved to either the district headquarters or large towns. Rural customer must visit such centers to pay monthly bills. In some areas, customers must pay more than NRs50 for bus fare, plus spend an entire day to pay a monthly bill of about NRs80. Management Response on the Project Performance Audit Report (PPAR) on the Seventh Power Project in Nepal (Loan 1011-NEP[SF]) On 23 July 2004, the Director General, Operations Evaluation Department, received the following response from the Managing Director General on behalf of Management: “Management takes note of the lessons identified in the PPAR and will take them into account for the design of similar future ADB projects.”
© Copyright 2026 Paperzz