Section 3 DRAINAGE Page 3.1 Introduction.................................................................................................... 3 - 2 3.2 Public Drainage............................................................................................... 3 - 4 3.3 Private Drainage ............................................................................................. 3 - 5 3.4 Access to Public Drainage ................................................................................ 3 - 6 3.5 Catchment Management Plans ........................................................................ 3 - 7 3.6 Capacity Analysis ............................................................................................ 3 - 8 3.7 Bedding, Laying and Cover ............................................................................ 3 - 10 3.8 Approved Materials ....................................................................................... 3 - 11 3.9 Manholes...................................................................................................... 3 - 12 3.10 Extensions and Upgrades of Public Drainage................................................... 3 - 14 3.11 Building over Public Drainage......................................................................... 3 - 15 3.12 Diverting Public Drainage .............................................................................. 3 - 18 3.13 Parallel Development Funding for Works on Public Drainage ............................ 3 - 19 3.14 Acquiring Access to Land ............................................................................... 3 - 20 3.15 Combined Sewers ......................................................................................... 3 - 21 3.16 Separation of Public Drainage ........................................................................ 3 - 22 3.17 Separation of Private Drainage....................................................................... 3 - 23 3.18 Service Connections ...................................................................................... 3 - 25 3.19 Common Private Drains ................................................................................. 3 - 26 3.20 Easements: Private Drainage on Private Land ................................................. 3 - 28 3.21 Easements: Private Drainage on Public Land................................................... 3 - 29 3.22 Easements: Public Drainage on Private and Public Land .................................. 3 - 30 3.23 Private Pump Stations ................................................................................... 3 - 31 Development and Connection Standards – Water, Wastewater and Stormwater Design and Policy Manual for Auckland City Isthmus, 4th Edition Mar 2009 Copyright © Mar 2009 Page 3 - 1 Section 3 Drainage 3.1 Introduction Section 3 presents issues common to both wastewater and stormwater systems and practices. The emphasis is primarily on public systems, and how private drainage interacts with and impacts on the public drainage system. Key Documents • • • • • • • • • Building Act 2004 http://www.dbh.govt.nz/blc-building-act Building Regulations 1992 (and Amendments) (§ 3) Building regulations - Department of Building and Housing Local Government Act 1974 (and Amendments) http://gpacts.knowledge-basket.co.nz/gpacts/reprint/text/1974/an/066.html Local Government Act 2002 (and Amendments) http://gpacts.knowledge-basket.co.nz/gpacts/public/text/2002/an/084.html District Plan (Isthmus Section) (for Zonings and Land Use to MPD) [Auckland City Council] District Plan - Isthmus section ACC Manual for Development Contribution Rebate Programme For Rainwater tanks. Development contribution stormwater rebate Technical Publication 108: Guidelines for Stormwater Runoff Modelling in the Auckland Region 1999 [Auckland Regional Council] Technical publications 101-150 Code of Urban Subdivision and Development 1999 [Auckland City Council] (Hard Copy Only) • • On-Site Stormwater Design Manual 2002 [Auckland City Council] http://www.aucklandcity.govt.nz/council/documents/onsite/default.asp Wastewater Design Manual 2007 [Metrowater] [Hard copy only] Draft Wastewater Pump Station Design Manual 1999 [Metrowater] [Hard • Foulwater Pump Station Design Manual 1989 [Auckland City Council] [Hard • AMIS/GIS-based Asset Records: Service Plans [Auckland City Council] • Flood Hazards (from Flood Hazard Mapping) refer AMIS/GIS or contact Metrowater – Records to view hard copies of Flood Hazard Mapping reports. Health and Safety in Employment Act 1992 (and Amendments) Health and Safety in Employment Act 1992 No 96 (as at 01 April 2008), Public Act – New Zealand Legislation Health and Safety in Employment Regulations 2003 • • copy only] Until this Manual is operative, it must be consulted in conjunction with: copy only] [Hard copy only] • Health and Safety in Employment (Prescribed Matters) Regulations 2003 (SR 2003/90) (as at 04 September 2007) – New Zealand Legislation.Time Series Modelling - Metrowater Library (hard copies of Flood Hazard Mapping reports). • Standard Specification for Construction of Gravity Drain-pipes 2006, Version 6 [Metrowater Library] Development and Connection Standards – Water, Wastewater and Stormwater Design and Policy Manual for Auckland City Isthmus, 4th Edition Mar 2009 Copyright © Mar 2009 Page 3 - 2 Section 3 Drainage Key Documents (contd) • • AS/NZS 2865:2001: Safe Working in a Confined Space http://www.standards.co.nz/default Site Hazard Identification and Controls: Overview – Working in a Confined Space [Metrowater] [Hard copy only] • • • • • Auckland City Council Draft Bylaws 2008 Part 6 Construction, Part 18 Stormwater Management http://www.aucklandcity.govt.nz/council/documents/bylaw/ Plumbers, Gasfitters and Drainlayers Act 2000 Acts – New Zealand Legislation AS/NZS 3725:2007 Design for Installation of Buried Concrete Pipes. http://www.standards.co.nz/webshop/?action=viewSearchProduct&mod=catalog&pid=3725:2007(AS|NZS) Standard Specification for Construction of Gravity Drain-pipes November 2006 [Metrowater] [Hard copy only] AS/NZS 2566.2:2002 Buried flexible pipelines - Installation http://www.standards.co.nz/default.htm • AS/NZS 2566.1:1998 Buried flexible pipelines - Structural design http://www.standards.co.nz/default.htm • NZS 4404:2004: Land Development and Subdivision Engineering • Parallel Funding Policy and process flow chart (Contact Metrowater Development Services) http://shop.standards.co.nz/productdetail.jsp?sku=4404%3A2004%28NZS%29CADPDF Development and Connection Standards – Water, Wastewater and Stormwater Design and Policy Manual for Auckland City Isthmus, 4th Edition Mar 2009 Copyright © Mar 2009 Page 3 - 3 Section 3 Drainage 3.2 Public Drainage Policy Definition Public drainage referred to in this section generally describes drainage networks that: • • • • are owned and maintained by Auckland City Council or Metrowater, have been designed to accept expected flows as per the design criteria at the time of construction, are constructed by, or for Auckland City Council or Metrowater using controlled engineering methods, serve several sites or premises in separate ownership. This is not an exhaustive description, and there are various technical and legal issues which may be involved in any particular case. Alterations and Additions Alterations or additions to public drains must have specific Engineering Plan Approval from Auckland City Environment’s Development Engineering (DE) who will liaise with Metrowater as required. Public manholes must be constructed on public land where possible. Records Public drainage records are held in various forms: engineering drawings, microfiche, AutoCAD files, Electronic Data Management System (EDMS) and AMIS/GIS systems. Refer to Auckland City Environments’ (ACE) Front-of-House regarding access to these records systems. Development and Connection Standards – Water, Wastewater and Stormwater Design and Policy Manual for Auckland City Isthmus, 4th Edition Mar 2009 Copyright © Mar 2009 Page 3 - 4 Section 3 Drainage 3.3 Private Drainage Policy Definition Private drainage generally describes all drainage systems constructed privately to service a single or small number of ‘private’ developments or sites. These systems are maintained by the respective property owners, and in most cases connect to Auckland City Council’s or Metrowater’s public drainage system. Responsibility Property owners are responsible for their private drainage up to and including the connection to the public line. Requirements Requirements for materials and performance for these private systems are given in the relevant portions of the Building Act 2004, Building Regulations 1992 (Code), Local Government Act 1974, Local Government Act 2002, Plumbers, Gasfitters and Drainlayers Act 2000, and various Bylaws. Auckland City Environments Private systems are controlled through the Building Consent approval process, and are installed to the satisfaction of Auckland City Environments’ Inspectors or approved Building Certifiers. Records The private drainage records held by Auckland City Council are available from Front-of-House at Auckland City Environments (ACE) 35 Graham Street, CBD. These may be in the form of Electronic Data Management System (EDMS), AMIS/GIS from site files, micro fiche cards, drainage packets, or larger scale drainage sheets. Many older properties have only limited (and in some cases no) information held. Key Documents • • • • • Building Act 2004 Building Regulations 1992 (and Amendments) (§ 3) Local Government Act 1974 (and Amendments) Local Government Act 2002 (and Amendments) Plumbers, Gasfitters and Drainlayers Act 2000 Development and Connection Standards – Water, Wastewater and Stormwater Design and Policy Manual for Auckland City Isthmus, 4th Edition Mar 2009 Copyright © Mar 2009 Page 3 - 5 Section 3 Drainage 3.4 Access to Public Drainage Refer also to: • Section 1: Overview, sub-section 1.8 Access to Public Wastewater Pipes and Manholes. Policy Access and Security Unless specifically provided for in a contract with Metrowater or Auckland City Council, no person shall enter confined spaces within the public drainage system (including manholes, pump stations and pipes) without prior written approval from Metrowater. A Planned Work Permit must be obtained from Metrowater prior to commencement of any work (including construction work, manhole entry, videoing or cleaning). Construction work must be carried out by, or under the supervision of a registered drainlayer or Chartered Professional Engineer and in accordance with current Metrowater Health and Safety Policies (refer to Key Documents below). For lifting of lids (for example, to check depths) not involving physical access to the system, a Site Authorization Form for Metrowater Network Access is required. The consultant or contractor must comply with Metrowater’s Health and Safety policies as a minimum. Potential Hazards When entering public drains, potential hazards including (but not limited to): traffic, gases, strong odours, slippery surfaces, cuts or abrasions, airborne and water-borne disease, flooding, noise, falling debris or materials, flash flooding, locked culvert systems must be considered and appropriate controls put in place to eliminate, isolate or minimise these hazards. In any emergency in the public drainage system or water supply system: ⇒ Dial 111 ⇒ Ask for the Fire Service or Ambulance ⇒ Give your name, contact details and the full address of the emergency For More Information For more information regarding the Planned Work Permit or the Site Authorization Form, contact Metrowater, Ph 624-4884. Key Documents • • • • • • Health and Safety in Employment Act 1992 (and Amendments) (Health and Carriageways) Health and Safety in Employment Regulations 1995 (and Amendments) AS/NZS 2865:2001: Safe Working in a Confined Space Site Hazard Identification and Controls: Overview – Working in a Confined Space [Metrowater] [Hard copy only] Site Authorization Form for Metrowater Network Access [Metrowater] Planned Work Permit [Metrowater] Development and Connection Standards – Water, Wastewater and Stormwater Design and Policy Manual for Auckland City Isthmus, 4th Edition Mar 2009 Copyright © Mar 2009 Page 3 - 6 Section 3 Drainage 3.5 Catchment Management Plans Refer also to: • Appendix O: Integrated Catchment Study. Auckland City Council, in partnership with Metrowater, has completed an Integrated Catchment Study (ICS) for the Auckland City Council Isthmus area. The ICS updated the “Type A and Type B” Catchment Management Plans in most of the Drainage Management Areas (DMAs). Information on the Wastewater, Combined and Stormwater systems within the ICS work includes confirmation of drainage assets in an area, contributing sub catchment areas, existing pipe capacities, MPD design flows, self cleansing velocities in wastewater systems and identification of Flood Hazard Mapping (FHM) and Overland Flow Paths etc. Where catchments were not completed during ICS (including parts of Waiheke Island) FHM reports and maps will become available. Time Series Modelling reports are available for most DMA’s within Auckland City. Policy 10, 50 and 100-Year Flood Plains 10, 50 and 100-Year Flood Plains are based on Flood Hazard Mapping and include flood plain levels at various nodes, significant Overland Flow Paths and known surveyed habitable floor levels. If a development is in a Flood Hazard area, the relevant engineering studies must be referred to. For access to and queries regarding Flood Plains or Historical Catchment Management Plans, contact the Duty Development Engineer at Auckland City Environments (ACE). Refer to Appendix O: Integrated Catchment Studies. Flood Risk Areas Flood Risk Areas (formerly: ‘Type B’ Catchment Management Plans) noted on AMIS/GIS provide an indicative assessment of areas prone to flooding. These Flood Risk Areas are constantly under review and updated as new information becomes available and/or flood assessments are carried out. They are only an indication of the best information available at the time of their creation. Known flood hazards are indicated on AMIS/GIS. AMIS/GIS The AMIS/GIS system shows 10, 50 and 100-Year Flood Plains and Flood Risk Areas in its Hazards Object Group and equivalent map output. The 10, 50 and 100Year Flood Plains are identified from Flood Hazard Mapping and Catchment Management Plans. The Flood Risk Areas are known flood risk areas and are identified as a result of consultation with property owners and available historical records. The flood area information is a guide only. Reference to this information and the 10, 50 and 100-Year Flood Plains, should be made in consultation with the Duty Development Engineer at ACE. Key Documents • • Flood Hazard Maps (FHM’S) included in AMIS/GIS FHM Reports and Maps [Auckland City Environments or Metrowater] [Hard • Flood Hazard Area formerly ‘Type A’ Catchment Management Plan) [Auckland City Environments or Metrowater] [Hard copy only] Flood Risk Area (formerly: ‘Type B’ Catchment Management Plan) [Auckland City Environments or Metrowater] [Hard copy only] Time Series Modelling - System Performance reports [Metrowater] [Hard copy • • copy & PDF] only] Development and Connection Standards – Water, Wastewater and Stormwater Design and Policy Manual for Auckland City Isthmus, 4th Edition Mar 2009 Copyright © Mar 2009 Page 3 - 7 Section 3 Drainage 3.6 Capacity Analysis Refer • • • also to: Sub-section 3.5: Catchment Management Plans; Section 5: Stormwater, sub-section 5.3: Design Standards. Appendix O: Integrated Catchment Study A Capacity Analysis of a receiving drainage system is required where a development site is greater than 1,000 m2, involves four or more units or where specifically requested as a result of a Resource Consent, Trade Waste Permit or public drainage extension. This analysis involves a comparison of the capacities of the particular system, combined or separate wastewater and stormwater systems (pipes, watercourses and secondary flow paths). The applicant must obtain sufficient data to complete the analysis. The analysis involves a comparison of the Existing and Maximum Probable Development (MPD) flows from the relevant catchments, including the effects of the development on both upstream and downstream systems and an analysis of known drainage problems. Policy Information held by Metrowater and Auckland City Council The Integrated Catchment Study (ICS) and later studies provide information on the Wastewater, Combined and Stormwater systems including, confirmation of drainage assets in an area, contributing sub catchment areas, existing pipe capacities, MPD design flows, self cleansing velocities in wastewater systems and identification of Flood Hazards and Overland Flow Paths etc. This information is included in Flood Hazard Mapping and System Performance Maps for each Drainage Management Area (DMA). Capacity Analysis Requirements The analysis must be carried out by a suitably qualified engineer in the field of catchment and pipe flow analysis and must comply with the information within the Key Documents below. Costs are to be met by the applicant. Extent of Capacity Analysis The analysis should be carried out for the relevant branches of the system from the subject site to a point where the downstream system clearly has capacity for Maximum Probable Development (MPD) flows. Submission Completed reports must be submitted together with the application to ACE and a copy of the report sent to Metrowater. Infrastructure reports shall be no more than two years old. Under-Capacity of the Public Drainage System Where the Capacity analysis submitted by the developer indicates the downstream drainage system is undersized for the proposed development, the developer must provide a detailed proposal to mitigate these effects, such as upgrading of the existing drainage system or providing detention storage, in the case of undersized stormwater systems. Refer Section 5.9: Stormwater Holding & Re-Use Tanks. Development and Connection Standards – Water, Wastewater and Stormwater Design and Policy Manual for Auckland City Isthmus, 4th Edition Mar 2009 Copyright © Mar 2009 Page 3 - 8 Section 3 Drainage 3.6 (cont) Capacity Analysis Policy (cont.) Capacity of Old Wastewater Pipes Some of the older areas of Auckland have 100mm diameter public wastewater pipes, especially where drainage was installed in the 1940s. Examples include Ellerslie and Onehunga Borough. Ultimately, these drains will be upgraded. In the meantime, connection may be made to these drains, provided a capacity check confirms sufficient capacity is available to cater for the proposed additional flows and the condition of the system is adequate. If the capacity of the existing public 100mm diameter is not sufficient to cater for additional flows from the proposed development, or the condition of the public line is found to be poor, then the wastewater pipe must be upgraded by the developer. Key Documents • • • • • • • • • • District Plan (Isthmus Section) (for Zonings and Land Use to MPD) [Auckland City Council] ACC Manual for Development Contribution Rebate Programme For Rainwater tanks. Technical Publication 108: Guidelines for Stormwater Runoff Modelling in the Auckland Region 1999 [Auckland Regional Council] NZS 4404:2004: Land Development and Subdivision Engineering Code of Urban Subdivision and Development 1999 [Auckland City Council] On-Site Stormwater Design Manual 2002 [Auckland City Council] Wastewater Design Manual 2007 [Metrowater] [Hard copy only] AMIS/GIS-based Asset Records: Service Plans [Auckland City Council] [Hard copy only] 100-Year Flood Plains (formerly: ‘Type A’ Catchment Management Plans) [Auckland City Environments or Metrowater] [Hard copy only] Flood Risk Areas (formerly: ‘Type B’ Catchment Management Plans) [Auckland City Environments or Metrowater] [Hard copy only] System Performance Maps – Time Series Modelling (Metrowater) [Hard copy only] • • Catchment Improvement Plans (since ICS) [Metrowater] [Hard copy only] Flood Hazard Mapping Reports and Maps [Auckland City Environments or Metrowater] [Hard copy only] Development and Connection Standards – Water, Wastewater and Stormwater Design and Policy Manual for Auckland City Isthmus, 4th Edition Mar 2009 Copyright © Mar 2009 Page 3 - 9 Section 3 Drainage 3.7 Bedding, Laying and Cover Refer • • • Policy also to: Section 4: Wastewater, sub-section 4.2: Design Standards; Section 5: Stormwater, sub-section 5.3: Design Standards; Section 7: Standard Drawings, 12908/102. All Public drainage must be constructed to the standards below. Bedding All pipelines must be bedded, haunched and covered with suitable, compacted granular material as shown in Section 7: Standard Drawings, 12908/102 and to manufacturers’ specifications. All pipelines must be designed and constructed to withstand the likely loads placed upon them throughout their service life. The load carrying capacity must be calculated in accordance with AS/NZS 3725. Where a pipeline or manhole is to be constructed through soft ground, the pipeline or manhole must be adequately supported by removing the unsuitable material and replacing it with approved material, or by way of an alternative construction method or design consideration approved by an appropriately qualified engineer. Laying Pipes must be laid at a constant grade and true line between manholes except where curved lines have been specifically approved by Development Engineering or Metrowater. Cover Pipes must have at least: • 900mm cover in private land and under footpaths; • 1200mm cover in road carriageways. Where minimum cover cannot be achieved, protection options maybe considered by Auckland City Environments and Metrowater, which require specific design and approval. Key Documents • • • • • NZS 4404:2004: Land Development and Subdivision Engineering AS/NZS 3725:2007 Design for Installation of Buried Concrete Pipes. Standard Specification for Construction of Gravity Drain-pipes November 2006 [Metrowater] [Hard copy only] AS/NZS 2566.2:2002: Buried flexible pipelines - Installation AS/NZS 2566.1:1998: Buried flexible pipelines - Structural design Development and Connection Standards – Water, Wastewater and Stormwater Design and Policy Manual for Auckland City Isthmus, 4th Edition Mar 2009 Copyright © Mar 2009 Page 3 - 10 Section 3 Drainage 3.8 Approved Materials Refer also to: • Section 7: Standard Drawings; • Appendix R: Approved Materials for Drainage. Policy Materials which can be used for public drainage, and the status of these drainage approved materials are listed in Appendix R: Approved Materials for Drainage. The list applies to new systems and alterations to existing systems, that is, repairs or relays and diversions. Materials used for works outside this policy will not normally be accepted as public drainage. Changes to the current list, or acceptance of use of material not listed can be made only by Metrowater. Materials requiring specific Metrowater approval will only be considered for use where there are compelling technical reasons. Material delivery delays by suppliers or poor planning by the developer will not be a reason for Metrowater to consider alternative noncomplying pipe materials Development and Connection Standards – Water, Wastewater and Stormwater Design and Policy Manual for Auckland City Isthmus, 4th Edition Mar 2009 Copyright © Mar 2009 Page 3 - 11 Section 3 Drainage 3.9 Manholes Refer • • • also to: Section 4: Wastewater, sub-section 4.2: Design Standards; Section 5: Stormwater, sub-section 5.3: Design Standards; Section 7: Standard Drawings, 12908/202 to 12908/224 Manholes are provided for access into the wastewater and stormwater systems for Auckland City Council and Metrowater and their agents. Policy Required Location of Manholes Manholes must be located at the following points: • At all junctions, ends and changes of direction, size or grade of public drains (except as provided elsewhere for catchpit leads); • At spacing of not more than 90m. The maximum spacing may be increased where access is available, that is, pipes of 1800mm diameter or greater; • To cause minimal interference with use of any land. • In public land wherever possible. Required Dimensions of Manholes All manholes must be circular with minimum diameter of 1050mm. Refer to Section 7: Standard Drawings, 12908/202 to 12908/224. All manholes in the road reserve must have a heavy-duty concrete precast lid. Manholes in the carriageway must be fitted with a non-rock cast iron frame and cover. Refer to Section 7: Standard Drawings, 12908/223. Manholes connecting pipes larger than 600mm must be specifically designed and approved. Fall through of Manholes Refer NZS 4404, 5.3.6.4.3 - Internal Falls Through Manholes, Table 5.8 Maximum Allowable Deflections through Manholes and Table 5.9 Minimum Internal Fall through pipes of the same diameter. Where the outlet diameter is greater than the inlet diameter, the minimum fall through of the manhole must not be less than the difference in diameter of the two pipes, which requires pipes to be aligned soffit to soffit (internal pipe top). Minimum internal fall through manholes (pipes of the same diameter): • 0-30º deflection angle at manhole: 30mm • 30-60º deflection angle at manhole: 50mm • 60-120º deflection angle at manhole: 80mm Mini Manholes Chambers of 600mm diameter may be permitted as terminal manholes where: • the line is not likely to ever be extended, • there are no more than two inlets (diameter of inlets must not exceed 100 mm dia) and one outlet of a maximum 225 mm diameter, • the manhole depth does not exceed 1m. All other requirements for standard manholes must be complied with. Development and Connection Standards – Water, Wastewater and Stormwater Design and Policy Manual for Auckland City Isthmus, 4th Edition Mar 2009 Copyright © Mar 2009 Page 3 - 12 Section 3 Drainage 3.9 (cont) Manholes Policy (cont) Connections to Manholes All pipe connections to manholes shall comply with standard drawings 12908/202 to 211. Only Metrowater may approve an internal drop connection as per 12908/211. Continuing Access Property owners must ensure that manholes and other access points to the Auckland City Council or Metrowater pipe systems are accessible at all times. Manholes may not be covered over. This includes light or temporary structures, landscaping, paving, or surrounding structures. Key Documents • • NZS 4404:2004: Land Development and Subdivision Engineering Standard Specification for Construction of Gravity Drain-pipes November 2006, [Metrowater] [Hard copy only] Development and Connection Standards – Water, Wastewater and Stormwater Design and Policy Manual for Auckland City Isthmus, 4th Edition Mar 2009 Copyright © Mar 2009 Page 3 - 13 Section 3 Drainage 3.10 Extensions and Upgrades of Public Drainage Refer • • • • • • • • • • • also to: Sub-section 3.6: Capacity Analysis; Sub-section 3.8: Approved Materials; Sub-section 3.13: Funding Contributions for Works on Public Drainage; Section 2: Development, sub-section 2.4: Testing and Acceptance; Section 2: Development, sub-section 2.5: As-Builts; Section 2: Development, sub-section 2.7: Additional Dwellings; Section 7: Standard Drawings, 12908/201; Appendix E: Declaring Existing Systems as Public; Appendix F: CCTV Inspection Requirements; Appendix G: Form: Vesting Assets with Auckland City Council; Appendix R: Approved Materials for Drainage. Extensions and upgrades to the public system and diversions of existing systems, may be required as part of a development. Engineering Approval for construction must first be obtained from Development Engineering (DE). Policy Extensions to the Public Drainage System Extensions are required in the following situations: • Where the system will serve more than one lot or the proposed line crosses two boundaries; • Where the nearest available connection to a public system is 30m or more from the lot to be served; • Where the nearest available connection to a public system is 60m or more from the building to be served; • Where future upstream catchments could be serviced. Refer to Section 2: Development, sub-section 2.7: Additional Dwellings; • Where three or more dwellings are proposed. Refer to Section 2: Development, sub-section 2.7: Additional Dwellings. Public Drainage Standards Public drainage must be constructed to the relevant standards as presented and referenced in this manual. CCTV Inspection A post construction CCTV inspection of the new public drainage is required as a part of Auckland City Council declaring the drains public. This is normal best practice as per industry standards. Refer to Appendix F: CCTV Inspection Requirements. Key Documents • • • Code of Urban Subdivision and Development 1999 [Auckland City Council] [Hard copy only] Standard Specification for Construction of Gravity Drain-pipes November 2006 [Metrowater] [Hard copy only] New Zealand Pipe Inspection Manual 2006 Development and Connection Standards – Water, Wastewater and Stormwater Design and Policy Manual for Auckland City Isthmus, 4th Edition Mar 2009 Copyright © Mar 2009 Page 3 - 14 Section 3 Drainage 3.11 Building over Public Drainage Refer • • • Policy also to: Sub-section 3.4: Access to Public Drainage; Section 7: Standard Drawings, 12908/252 to 12908/255; Appendix F: CCTV Inspection Requirements. Building over Public Drains Generally speaking, building over (or adjacent to) public drains is not normally permitted. A dispensation may be considered where: • The drain is in good condition (by proof of a CCTV Inspection); • The drain has adequate capacity; • Access, repair and maintenance aspects are satisfactory; • Diversion of the pipe is not necessary; and • The development will not put an additional structural load on the drain. The definition of building includes ‘light’, ‘temporary’ or ‘slab’ structures. All building foundations proposed within 2m of a public sewer or within a 45º load transfer angle from 500 mm below the invert of the pipe, must comply with Auckland City Council’s pipe bridging requirements. Refer to Section 7: Standard Drawings, 12908/253 and 12908/254. Building over Private Drains Building over private drains servicing an adjacent lot is not permitted. Building over private drains servicing buildings on the same lot may be permissible subject to Building Consent approval. Access to Public Drainage Refer to Sub-section 3.4: Access to Public Drainage. Clearances Auckland City Council and Metrowater must always have effective access to manholes. Refer to Section 7: Standard Drawings, 12908/254. For this reason, nothing may be placed in the following areas: • In the ground within 1m horizontally of the outside of a pipe or manhole chamber; or • Above the ground within 1m horizontally of the side of the manhole or lamphole and within 5m vertically above the manhole lid or lamphole. Repairs and Replacements Any repairs required to faults within 2m of the proposed building platform will be at the developer’s cost. Where the pipeline is of a material or construction which is not currently approved (such as asbestos cement pipes), the entire section of the pipeline within 2m of the proposed building platform must be replaced. Fall and capacity checks may be required before relaying. Consideration for Bridging Waiver Bridging for a garage, shed, carport or veranda may be waived subject to ACE Structural Engineers Approval. This waiver only applies where the exiting pipe does not run parallel and directly below a perimeter strip footing. Development and Connection Standards – Water, Wastewater and Stormwater Design and Policy Manual for Auckland City Isthmus, 4th Edition Mar 2009 Copyright © Mar 2009 Page 3 - 15 Section 3 Drainage 3.11 (cont) Building over Public Drainage Policy (cont) The structure must: • be constructed for normal domestic use; • be accurately located on-site; • be stand-alone and light timber-framed; • have a base which inherently spreads the load (for example, a concrete slab foundation); and • cover between 1.2m and 6m of the pipe. The sewer must be in good condition (by proof of a CCTV inspection). Proposed Paving Proposed excavations, driveways and other paving to be located over existing public drains may require a CCTV inspection of the affected public drain and a specific design where the pipe has less than 1.2m of undisturbed cover. CCTV Inspections All drainage DVD’s must follow the CCTV drainage procedures (refer to Appendix F). When proposing to build over or adjacent to a public drain, a CCTV inspection is required regardless of the age or depth of the drain. A post-construction CCTV inspection of new public drainage is required for all drains, prior to Auckland City Council declaring the drains public, this includes pipe relays. A Building Code of Compliance and or a Engineering Completion Certificate will not be issued until the final DVD is received and approved by ACE. ACE sends all DVD’s to Metrowater for filing and possible audit. Refer to Appendix F, CCTV Inspection Requirements. Accurate Location of Drainage on Site Plans Public drains must be accurately located on-site in relation to the proposed building works and shown on the site plans in all cases. Refer to diagram below: Sample Plan: Works Close to Existing Public Wastewater Pipe. CCTV of public drains post pile driving Where pile driving is within 2-3m of a public drain, both pre- and post-pile driving CCTV surveys shall be supplied to ACE for checking to ensure no damage has occurred to the public drainage system as a result of the piledriving. Format of CCTV Inspections The CCTV inspection shall be provided to (ACE) on a DVD in accordance with the requirements set out in Appendix F. Key Documents • • • • • • Local Government Act 1974 (and Amendments) (esp. § 26.451) Local Government Act 2002 (and Amendments) Health and Safety in Employment Act 1992 (and Amendments) Health and Safety in Employment Regulations 1995 (and Amendments) AS/NZS 2865:2001: Safe Working in a Confined Space Code of Urban Subdivision and Development 1999 [Auckland City Council] (Hard Copy only) • • Site Hazard Identification and Controls: Overview – Working in a Confined Space [Metrowater][Hard copy only] New Zealand Pipe Inspection Manual 2006 Development and Connection Standards – Water, Wastewater and Stormwater Design and Policy Manual for Auckland City Isthmus, 4th Edition Mar 2009 Copyright © Mar 2009 Page 3 - 16 Section 3 Drainage 3.11 (cont) Building over Public Drainage Diagrams Sample Plan: Works Close to Existing Public Wastewater Pipes All pipes must be accurately located on-site. Development and Connection Standards – Water, Wastewater and Stormwater Design and Policy Manual for Auckland City Isthmus, 4th Edition Mar 2009 Copyright © Mar 2009 Page 3 - 17 Section 3 Drainage 3.12 Diverting Public Drainage Refer also to: • Sub-section 3.10: Extensions and Upgrades of Public Drainage; • Sub-section 3.11: Building over Public Drainage. Diversion of a public drain around a proposed building is sometimes an effective solution. This is treated the same as any other work on public drainage and requires an Engineering Plan Approval from ACE. Policy Applications An application for an Engineering Plan Approval should be made to Development Engineering (DE). Engineering details including the site plan and longitudinal sections must be provided. Capacity The capacity of the diverted line must be adequate for the predicted future Maximum Probable Development (MPD) design flows. Costs The applicant must pay all costs associated with any diversion work. Consents from Adjacent Property-Owners Where diversion works are required in any adjacent property, it is the applicant’s responsibility to obtain written consent from the affected property-owners. Development and Connection Standards – Water, Wastewater and Stormwater Design and Policy Manual for Auckland City Isthmus, 4th Edition Mar 2009 Copyright © Mar 2009 Page 3 - 18 Section 3 Drainage 3.13 Parallel Development Funding for Works on Public Drainage Where Drainage and Water Supply works planned as part of a private development can be extended to serve other upstream land and offer a ‘public’ benefit (increased size downstream to cater for future downstream development), Metrowater and/or Auckland City Council may consider making a contribution towards the additional cost. Policy Process A Parallel Development Fund is available for funding of extensions to public wastewater and stormwater performed by private developers or pipe upsizing (see Principles below). Granting of funds will be at the discretion of Auckland City Council and Metrowater. The decision will be based on the potential benefits of the extension to the catchment and on future development. The developer must supply a proposal including engineering plans and three cost estimates. Development Engineering (DE) will assess the proposal and may forward it to Metrowater for approval. The fixed amount for the fund opens on 1 July each year and may close when the funds have been exhausted during the financial year. Principles The Code of Urban Subdivision and Development states that Auckland City Council “may make a financial contribution towards any additional works necessary” to service other land. In practice, this might be for increased pipe sizes or extra reticulation to service land outside the development, that is, the extra cost over that of constructing a suitable system to service only the current development. File Records All development contributions or similar commitments made are to be formally recorded and filed to the appropriate site file. This will enable Auckland City Council to recover any funds contributed earlier for future development. Key Documents • • • Parallel Funding Policy and process (Contact Metrowater Development Services) District Plan (Isthmus Section) (esp. § 4B.6, 11.5.5.3) [Auckland City Council] Code of Urban Subdivision and Development 1999 (esp. § 2.15, 5.2.1, 6.2.1) [Auckland City Council] Development and Connection Standards – Water, Wastewater and Stormwater Design and Policy Manual for Auckland City Isthmus, 4th Edition Mar 2009 Copyright © Mar 2009 Page 3 - 19 Section 3 Drainage 3.14 Acquiring Access to Land Refer also to: • Appendix F, CCTV Inspection Requirements; • Appendix I, Gaining Access. The Local Government Act 1974 (§ 460),(461) and 2002 (§ 181 (2-3)) contains various provisions relating to access by Auckland City Council to private land in order to carry out required drainage works. These may be considered in relation to a specific development where it is necessary to obtain access to neighbouring private land for private drainage, or to construct public drainage. Note that the following is a summary only and the relevant legislation should always be referred to. In all but exceptional cases the best solution is for the developer to conclude satisfactory private negotiations with the relevant property owners. Refer also to Appendix I, Gaining Access. Policy Private Negotiation Auckland City Environments(ACE) role is to confirm the appropriate adjacent landowner consents are obtained by the developer. ACE will not become involved with conditions of consent. In all cases the developer is responsible for negotiating and coming to a satisfactory arrangement with affected landowners. This is a private negotiation between individuals and does not involve Auckland City Council. Local Government Act 1974, Section 460 and 461 Where the only practical route of a new private drain is through land owned by persons who will not consent to the drain’s construction, Section 460 of the LGA, outlines a process where Auckland City Council may enter the land and construct such works. The non-consenting owner will have the opportunity to be heard by Auckland City Council and appeal to the District Court before Auckland City Council can enter the land. Auckland City Council‘s costs are recoverable from the developer. Clause 461 relates to the further provisions of the Local Government Act 1974 regarding private drains through adjacent properties. Local Government Act 2002, Section 181 (2-3) Auckland City Council may construct public drains on private land, and associated works as it considers necessary, either with written consent of the land owner, or following compliance with the 12th Schedule of the Act where the land owner will not give written consent. Auckland City Council’s Involvement Whilst Auckland City Council may invoke Section 460 of Local Government Act 1974 or Section 181 of Local Government Act 2002, Auckland City Council will only become involved in such situations involving private development (beyond supplying general information on the process involved), where: • The Developer has requested in writing that consent be given and has received confirmation from the landowner that consent will be withheld. In such situations the developer must supply all details of contact made, including copies of letters, plans and any alternative options available; • Where the proposed works are the optimum engineering solution; • Where the development proposed complies with the District Plan provisions. • Where ACC believe it provides a justifiable ‘public benefit’ to do so. Key Documents • • Local Government Act 1974 (and Amendments) (§ 460) (§ 461) Local Government Act 2002 (and Amendments) (§ 181, 12th Schedule) Development and Connection Standards – Water, Wastewater and Stormwater Design and Policy Manual for Auckland City Isthmus, 4th Edition Mar 2009 Copyright © Mar 2009 Page 3 - 20 Section 3 Drainage 3.15 Combined Sewers Refer • • • also to: Sub-section 3.17: Separation of Private Drainage; Section 5: Stormwater, sub-section 5.2: Approved Discharge Points; Section 5: Stormwater, sub-section 5.9: Stormwater Holding and re-use Tanks. The combined sewer system provides a single point of connection to each property for disposal of stormwater and wastewater in the same pipe. Policy New Combined Public Sewers No applications for new combined public sewers will be considered or approved. Connections to Combined Public Sewers Generally speaking, no new combined connections will be approved. However, dispensation may be granted in the event that the combined sewer is the only option for stormwater disposal. Where dispensation is given, each unit must have an independent combined private connection to the sewer. The private wastewater and stormwater pipes must join together as close as possible to the connection to the combined public sewer to allow for future separation. Stormwater Detention tanks are generally required. Refer to Separation of Private Sewers below and to sub-section 3.17: Separation of Private Drainage. Separation of Private Sewers All existing combined private drainage must be separated where development increases impervious area by more than 20m² or where major re-development of the site is proposed. Where a site development has options for stormwater discharge other than to the combined sewer, those options must be fully explored and used as far as possible. Refer to Section 5: Stormwater, sub-section 5.2: Approved Discharge Points. Separation of Public Sewers All development projects initiated within combined areas are to have separation considered as part of the proposal. A development proposal within a combined area where public sewer separation is in progress, must consider the proposed separation works as part of the proposal. Contact ACE Development Engineering’s (DE) Duty Engineer for areas where public separation projects are in progress. Discharge and associated Consents may be required for stormwater disposal and should be discussed with DE’s Duty Engineer. Consent Applications All Building, Subdivision and Resource Consents are to consider the proposed Metrowater sewer separation programme. Refer to Metrowater for the latest programme details. Key Documents • • • • Building Act 2004 Building Regulations 1992 (and Amendments) Resource Management Act 1991 (and Amendments) Code of Urban Subdivision and Development 1999 (§ 3.3.1) [Auckland City Council] Development and Connection Standards – Water, Wastewater and Stormwater Design and Policy Manual for Auckland City Isthmus, 4th Edition Mar 2009 Copyright © Mar 2009 Page 3 - 21 Section 3 Drainage 3.16 Separation of Public Drainage Policy Year 2010 Targets A review of the DSP in the 2008-09 will clarify the future targets. Key Documents • Focus on the Future 2006: Strategic Plan [Auckland City Council] Development and Connection Standards – Water, Wastewater and Stormwater Design and Policy Manual for Auckland City Isthmus, 4th Edition Mar 2009 Copyright © Mar 2009 Page 3 - 22 Section 3 Drainage 3.17 Separation of Private Drainage Refer • • • also to: Sub-section 3.15: Combined Sewers; Section 5: Stormwater, sub-section 5.2: Approved Discharge Points; Section 5: Stormwater, sub-section 5.9: Stormwater Storage Devices. Each site must have separate private systems for wastewater and stormwater. Separation of private combined drainage is required when a site is developed within a combined catchment. Policy Private Separation Private separation of all private drainage on a site is required for: • All subdivisions; • Any Development that involves work on the wastewater drainage, or works that increase the site’s roof or drained impermeable area by20m² or more. Site and Drainage Plans A detailed site and drainage plan (including all public and private drainage) must be supplied with all Consent applications. These plans must include drainage details of all existing and proposed impermeable areas. New Private Wastewater and Stormwater Drains Where separation of existing drainage is required, the preferred option is to use the existing combined private drain for stormwater, with a new private drain installed for wastewater. However, if satisfactory testing and rehabilitation of the combined private drainage is carried out prior to use, a new private stormwater drain may be installed with the existing combined private drain being used for wastewater. Detention tanks may be required for both options. Refer to Subsection 5.9: Stormwater Detention and Re-use Tanks. Extent of Private Separation All of the site’s private drainage must be separated, with the separate wastewater and stormwater drains taken to approved outlets (including private soakage where applicable – refer to Auckland City Council’s Soakage Design Manual). Where the site must discharge stormwater into a combined drain, the separate private drains must continue as close as possible to the single connection to the combined public sewer or boundary of where the existing combined private drain exits the lot. Refer to diagram On-Site Separation of Private Drainage below. Costs Costs of separating private drainage are to be met by the property-owner or developer. Key Documents • • • • Building Act 2004 Building Regulations 1992 (and Amendments) Resource Management Act 1991 (and Amendments) Code of Urban Subdivision and Development 1999 (§ 3.3.1) [Auckland City Council] (Hard Copy only) Development and Connection Standards – Water, Wastewater and Stormwater Design and Policy Manual for Auckland City Isthmus, 4th Edition Mar 2009 Copyright © Mar 2009 Page 3 - 23 Section 3 Drainage 3.17 (cont) Separation of Private Drainage Diagrams On-Site Separation of Private Drainage Existing - Downpipes and catchpits feed directly into private combined drain. EXISTING Separated - Sewage gully traps feed into new wastewater only line to within 1m of site boundary, then connect into existing private combined drain. All site stormwater flows through holding tank as required. PROPOSED Development and Connection Standards – Water, Wastewater and Stormwater Design and Policy Manual for Auckland City Isthmus, 4th Edition Mar 2009 Copyright © Mar 2009 Page 3 - 24 Section 3 Drainage 3.18 Service Connections Refer • • • Policy also to: Sub-section 3.15: Combined Sewers; Section 2: Development, sub-section 2.7 Additional Dwellings. Section 7: Standard Drawings, 12908/245 to 12908/247. Connections Required and Permitted Each lot must be provided with independent and separate service connections for disposal of stormwater and wastewater. Only one service connection per lot (for each service) is permitted. Procedure Connection to the public stormwater and wastewater systems can only be made by a Registered Drainlayer and only after a Building Consent or Engineering Approval has been obtained from Auckland City Council. Service connections must be connected to the public drain as shown in Section 7: Standard Drawings, 12908/245 to 12908/247. Service connections to wastewater systems deeper than 5m must be specifically designed. Service Connection Sizes Wastewater and stormwater service connections must be 100mm diameter in residential areas, and at least 150mm diameter in business, commercial and industrial areas. Connection Ownership and Responsibility Service Connections are considered to be part of private drainage and are therefore a private responsibility even if located outside the subject property boundary. Abandoned Service Connections Abandoned wastewater service connections must be removed and the connection replaced with a section of public pipe. These replaced sections of public pipe will require inspection by Development Engineering (DE) engineers. For each service connection to be abandoned, the section of pipe affected by the service connection must be cut out and replaced with a straight length of pipe. The cut at either end would be within 300mm of an existing joint, that cut must be taken to the far side of that joint. The joints at each end of the new pipe must use shear ring couplings meeting Type B, AS/NZS 4327: 1995. Key Documents • • • • • • NZS 4404:2004: Land Development and Subdivision Engineering Local Government Act 1974 (and Amendments) (§ 459) Local Government Act 2002 (and Amendments) Consolidated Bylaw 1991 (and Amendments) (§ 6.4) [Auckland City Council] AS/NZS 4327:1995: Metal-Banded Flexible Couplings for Low-Pressure Applications Road Opening Notice [Traffic and Roading Services] [Hard copy only] Development and Connection Standards – Water, Wastewater and Stormwater Design and Policy Manual for Auckland City Isthmus, 4th Edition Mar 2009 Copyright © Mar 2009 Page 3 - 25 Section 3 Drainage 3.19 Common Private Drains In the past, dwellings were constructed that share a ‘common private drain’ – a shared pipe which carries stormwater and/or wastewater into the public drainage system. Any of these drains still existing are the private responsibility of the joint owners. Policy New Common Private Drains In the case of freehold and x-lease subdivision applications, no applications for common private drains will be approved. Each dwelling/unit must have its own connection to the public drainage system. Approved Common Private Drains Where a common private drain has been approved, a binding memorandum must be registered on the titles, and the drain must be recorded as common on Auckland City Council’s public drainage plans. Details of such memorandum are obtainable at Development Engineering. Development on Existing Common Private Drains In older regions (for example, Grey Lynn) 100mm diameter drains may have been laid to serve a number of units/dwellings (not unit titles). These are generally in poor condition. Any future development including new dwellings, cross-leases or subdivisions, where the site is currently served by a common private drain, will require as a condition of consent, that the existing and new dwelling within the development site be serviced by a separate connection to the public system. This may involve construction of a new public wastewater pipe. Refer to diagram New Public Drain to Replace Common Private Drain below. In cases where alterations to an existing dwelling are proposed, the applicant must confirm that the condition of the existing private common drain is adequate and that the drain has capacity for the existing and proposed flows. Key Documents • • • • • Building Act 2004 Building Regulations 1992 (and Amendments) Local Government Act 1974 (and Amendments) (§ 459) Local Government Act 2002 (and Amendments) AMIS/GIS-based Asset Records [Auckland City Council] [Hard copy only] Development and Connection Standards – Water, Wastewater and Stormwater Design and Policy Manual for Auckland City Isthmus, 4th Edition Mar 2009 Copyright © Mar 2009 Page 3 - 26 Section 3 Drainage 3.19 (cont) Common Private Drains Diagrams New Public Drain to Replace Common Private Drain New public 150 mm dia sewer extension required to service existing & proposed dwelling. Property owner consents required from 116-118 Bright Street. Proposed Dwelling Existing dwelling. Bright Street Development and Connection Standards – Water, Wastewater and Stormwater Design and Policy Manual for Auckland City Isthmus, 4th Edition Mar 2009 Copyright © Mar 2009 Page 3 - 27 Section 3 Drainage 3.20 Easements: Private Drainage on Private Land Refer also to: • Sub-section 3.14: Acquiring Access to Land. Where a lot must drain through another lot to connect to an approved discharge point, permission from the affected landowner must be obtained. Policy Local Government Act 1974 Section 461 sets out the landowners’ rights when the drain has been laid through an adjacent property, with permission from the affected landowner (or under Section 460), and specifies that these rights may be noted on the relevant titles. Registration Formal registration of the easement on adjacent property titles or a Section 461 agreement, are required for private drains traversing other properties. Copies of the 461 agreement may be obtained from Auckland City Council Environments’ (ACE) Property Information System. A signed 461 agreement from the affected landowner shall be submitted to ACE prior to approval of the proposal. Alternatives Creation of an ‘inappropriate’ (for example, very short) section of public drainage is not permitted as an alternative to registering an easement or a Section 461 Certificate. Where a proposed private drain will pass through and may be able to serve more than one other lot, constructing a public line should be considered. Key Documents • • • • Local Government Act 1974 (and Amendments) (§ 459) Local Government Act 2002 (and Amendments) Resource Management Act 1991 (and Amendments) (esp. § 108, 224) Code of Urban Subdivision and Development 1999 (§ 3.3.1) [Auckland City Council] ( Hard Copy Only) • Section 461 Certificate [Auckland City Environments] [Hard copy only] Development and Connection Standards – Water, Wastewater and Stormwater Design and Policy Manual for Auckland City Isthmus, 4th Edition Mar 2009 Copyright © Mar 2009 Page 3 - 28 Section 3 Drainage 3.21 Easements: Private Drainage on Public Land Policy Roads Private drainage within the road reserve is not covered by easements. A Road Opening Notice must be obtained from Auckland City Council Transport for any works in the road reserve prior to commencement of works. A record of these works, if drainage related, are kept by Auckland City Environments’ (ACE) Property Information System, in the form of private drainage As-Built plans. Parks and Reserves Formal easements for private drainage through an Auckland City Council Reserve are generally not granted, public drainage is preferred. For all work within parks and reserves, specific approval must be obtained from Arts, Community and Recreation Policy (ACR). When consulting with ACR regarding an application for a private drain on public land, documentation must be provided which clearly demonstrates why it is not feasible to install public drainage works in this instance. ACR Policy may consult with ACR Services who maintain the reserves. Other Land Owned by Auckland City Council Where Auckland City Council is recorded as the owner of the land in question, queries related to easements should be directed to the Property Department Manager who acts as the land owner for this purpose. Regional Land and Esplanade Reserves Any work on land outside of Auckland City Council’s control, requires specific approval from the appropriate authority. Alternatives Where a proposed private drain passes through and may be able to serve more than one other lot, constructing a public line should be considered. Key Documents • • • Local Government Act 1974 (and Amendments) (§ 460, 461) Local Government Act 2002 (and Amendments) (§ 181) Road Opening Notice [Traffic and Roading Services] [Hard copy only] Development and Connection Standards – Water, Wastewater and Stormwater Design and Policy Manual for Auckland City Isthmus, 4th Edition Mar 2009 Copyright © Mar 2009 Page 3 - 29 Section 3 Drainage 3.22 Easements: Public Drainage on Private and Public Land Refer also to: • Sub-section 3.14: Acquiring Access to Land. The Local Government Act 2002 grants comprehensive powers to Auckland City Council to enable it to locate, access and work on its drainage on private land. Policy Public Drainage Easements over private or public land for public drainage systems are not required. Detention Dams Detention dams must be registered on titles of the affected land. Drainage Easements Queries on drainage easements in favour of Auckland City Council should be directed to the applicant’s solicitor in the first instance. Requests to remove stormwater and combined easements should be directed to ACC Environmental and Utility Management (EUM) Manager. Requests to remove wastewater easements should be directed in the first instance to the Metrowater’s Development Team. All related costs will be borne by the applicant. Drainage On Crown Land All negotiations regarding proposed works within or discharges to crown land owned by New Zealand Railways Corporation (ONTRACK) or Transit NZ are to be between the developer and ONTRACK / Transit NZ representatives. Refer to Subsection 3.14: Acquiring Access to Land. Key Documents • • Local Government Act 1974 (and Amendments) Local Government Act 2002 (and Amendments) (§ 181) Development and Connection Standards – Water, Wastewater and Stormwater Design and Policy Manual for Auckland City Isthmus, 4th Edition Mar 2009 Copyright © Mar 2009 Page 3 - 30 Section 3 Drainage 3.23 Private Pump Stations Refer • • • • • Policy also to: Sub-section 3.14: Acquiring Access to Land; Sub-section 3.20: Easements: Private Drainage on Private and Public Land; Sub-section 3.20: Easements: Public Drainage on Private and Public Land; Section 6: Water Supply, sub-section 6.25 Backflow Prevention; Section 7: Standard Drawings, 12908/250. Wastewater Private Pump Stations Specific approval is required for private wastewater pump stations for new development or major re-development. Applications will not be considered unless the development is topographically unable to be drained by gravity means, i.e. the property lies in a local depression or basin. The objective is to achieve a gravity connection to a public system wherever possible. Auckland City Environments (ACE) and Metrowater’s Development Team Leader will consider applications on a case-by-case basis. Stormwater Private Pump Stations New private stormwater pump stations will not be approved for any new development and alternative methods of stormwater disposal must be found. Where such options are unavailable, development may be declined. Secondary Pumps for Stormwater and Wastewater Secondary stormwater and wastewater pumps may be considered for developments of minor dwellings (for example, basement bathrooms, low area paving (not greater than 20m²) or retaining wall drainage), provided the primary dwelling can be serviced by a gravity connection. Maintenance At the subdivision stage, a Consent Notice must be applied to the title of the new lot to ensure any subsequent owner is aware of the proposed method of wastewater and stormwater disposal and the associated pump maintenance requirements. Operation and maintenance of the pump must include provision for preventing backflow into the drainage (both of wastewater and of stormwater). A Backflow Device Consent must be obtained from Metrowater. Pumping to a Public Wastewater System A private rising main must connect to a private manhole or mini chamber, prior to discharge into the public system. The portion of pipe from the private chamber to the public system must be a public pipe and will need Engineering Approval from Auckland City Environments (ACE). Refer to Section 7 Standard Drawings, 12908/250. Directly pumping to public rising mains is not permitted. Key Documents • • • Building Act 2004 Building Regulations 1992 (and Amendments) (esp. § E1.3.3 (a)) Code of Urban Subdivision and Development 1999 (§ 5.2.2) [Auckland City Council] • Draft Wastewater Pump Station Design Manual 1999 [Metrowater] [Hard • Foulwater Pump Station Design Manual 1989 [Auckland City Council] [Hard ( Hard Copy Only) copy only] Until this Manual is operative, it must be consulted in conjunction with: copy only] Development and Connection Standards – Water, Wastewater and Stormwater Design and Policy Manual for Auckland City Isthmus, 4th Edition Mar 2009 Copyright © Mar 2009 Page 3 - 31
© Copyright 2026 Paperzz