Case study 8.1 – Channel regrading following mining subsidence Effect of mining subsidence The gradual collapse of old mine workings causes subsidence of the land above (including rivers and streams). Often the water levels are unchanged, because they are controlled by levels downstream of the area of subsidence. As a result, flow depths increase and the lowered riverbanks give less freeboard, increasing the flood risk to adjacent to land and property. The diagram below shows how a series of mining ‘panels’ can result in a lowered riverbed with ‘spikes’ between the areas of subsidence impounding a series of pools of deeper water. Regrading Original bed profile Subsided bed Reprofiled bed Elevation Regrading involves re-establishing the gradient of the riverbed over a long enough length to restore the channel’s flow capacity and reduce the flood risk to the adjacent land and properties. Regrading is not feasible in all cases, so alternative means of restoring the channel capacity, such as constructing flood embankments, may be necessary. Regrading works require particular attention to structures along the length of works such as bridges, weirs and pipe crossings. These structures may require underpinning or replacing to suit the new bed profile. Distance Silverdale Brook (Staffordshire) Subsidence caused by underground workings at the Silverdale colliery affected the bed gradient of the brook. The lack of freeboard meant that flooding occurred on a regular basis inundating a major road and residential area. 3 This project involved the excavation of 6000m of silt over a 1km length of the brook. A footbridge was replaced with a precast concrete box culvert unit as illustrated. It was also necessary to reroute electric cables running along the bed. New box culvert to replace footbridge Typical water level at culvert before regrading Entrance to same culvert after regrading Case study 8.2 – Vertical retaining wall to arrest erosion Stevenage Brook The Stevenage Brook is very flashy, and can produce high velocity flows with little warning. This erosion took place just downstream of a bridge after a road outfall headwall fell out of the bank and caused an obstruction in the channel. Debris built up rapidly on the obstruction, forcing the floodwater around each side. The left bank had previously been protected by concrete bagwork, but the right bank had no such protection and the resulting erosion removed part of the garden. The solution chosen was a vertical retaining wall formed by dropping timber sleepers into steel Ibeams tied back to anchors, as shown below. Case study 8.3 – Bank protection to arrest erosion River Kennet at Thatcham A sharp bend was causing severe bank erosion, undermining previously installed toe boarding and causing the bank behind to slip. The solution was to install steel sheetpiling to water level, and lay rock rolls in front of this to fill any erosion holes that might subsequently develop. The bank was re-profiled to a stable angle and protected by a seeded coir/polypropylene geotextile, with a planted coir roll at the toe, just behind the piling. The photographs below show the site immediately after completion and exactly one year later. Case study 8.4 – De-culverting and river restoration River Pinn in Hatch End The river ran through an old brick culvert, approximately 1.0m in diameter, which was inadequate for the flood flows being experienced. Immediately downstream the river ran in several lengths of vertical concrete-sided channel. The opportunity was taken to divert about 600m of this constrained river by creating a new course in playing fields and open space. The soil strata mainly comprised heavy clay, although some bands of gravel did exist along parts of the new course. It was realised that the new channel would take a long time to create a natural regime, so it was designed with meanders, pools, riffles, varying bank slopes, and a lowered wetland area where space was available. The two photographs below were taken almost exactly a year apart. All vegetation has been self-established. Case study 8.5 – Weir removal Before the weir removal In the early 1990s, a weir at Tanhouse Farm, Colnbrook, Slough, was rebuilt as part of a flood defence scheme. It was a fixed crest weir with stepped downstream face, incorporating a pooland-traverse fishpass. The brickwork is cladding to the reinforced concrete structure. This weir ponded water upstream, leading to significant silting and excessive summer weed growth. It was therefore decided to lower the weir and remove the fishpass, in conjunction with other works on adjacent channels, in order to lower the retained water level in the upstream reach. During the removal works Most of the fishpass has now been removed and already a narrower stream can be seen upstream. Note the safety precautions being taken despite the shallow depth of water (<0.25m). Note also the good practice of providing oil pollution booms, designed to catch any accidental spills before they pass downstream, although at the time of the photograph only air tools were in use. The completed scheme With the water level now lowered fully, a meandering watercourse appears upstream of the weir, without undertaking any intervention works on the channel whatsoever.
© Copyright 2025 Paperzz