Hot Water Drilling Manual - to be used on Fimbul Ice Shelf, January 2010 Ole A. Nøst, Per G. Gabrielsen & Lars H. Smedsrud Keith Makinson and Keith Nicholls from British Antarctic Survey hot water drilling the Filchner Ronne Ice-Shelf. This manual is solely based on their experience. 1.0 Equipment Here we describe the equipment to be used in a setup for drilling through the Fimbul Ice Shelf. The planned holes are from 250 to 450 m deep. How the equipment is set-up on the ice shelf, and the drilling sequence will be described in the next section. 1. Flubber (Water tank) The flubber is a large flexible rubber water tank that is to be placed in a shallow snow pit with flat bottom. There is a sheet of the same material that should be used below to protect the flubber, and insulation (~2.5 cm thick) shall be placed underneath these two. It is important that the bottom of the snow pit is flat and level, otherwise it will start tipping over. The flubber can be filled to a maximum of about 12 m3 of water. Snow for the flubber should be taken from an area radiating out from the flubber, but do not dig further down than 0.5 m, as this will make walking difficult in the area. We could use skidoo sledges for transporting snow to the flubber. 2. Pumps There are three CAT pumps powered by diesel engines. We plan to use two at a time, and have one spare. We could however complete the drilling using one pump, but it would take longer. The pumps are to be set up as sketched on Figure 1. We have packed the pumps together with the hoses that will connect the flubber, the pump and the heaters. We have spare parts for these pumps, extra engine oil, hydraulic oil for the pump, air and oil filters. 3. Pressure valves and pulsation dampers These are connected straight after the pumps. The pulsation dampers will even out the pressure pulses from the CAT pumps, and the pressure valves release the pressure if it gets too high. We plan to operate with about 50 bar when drilling, the security valve should then be tested and set at 70 bar. Picture shows Lars Henrik connecting the security valve and pulsation dampers. 4. Pressure and flow meters Pressure sensor and flow meter are connected like shown on the picture below. The maximum flow from each water pump is around 38 litre per minute. The relative flow should be adjusted at the valves of each heater so that the outlet temperature on each heater is approximatly the same. The drill speed formula needs flow to calculate optimal speed, but the added flow from the two pumps are also measured at the drum. 5. Heaters We have 8 heaters. The smallest one should be used in the circuit from the submersible pump, sending warm water down the pump hole. All heaters should be placed on wooden beams, to prevent them melting down into the snow. We will burn air-fuel and it is OK to burn the standard oil that NP has to transfer this air-fuel to diesel. This oil is added as 1% in the fuel drums to lubricate the fule pumps. The heaters run best at 80ºC but stay below 90ºC to avoid damage to hoses. Spare parts are electric igniter electrodes. 6. Flow control valves These valves control the flow back to the flubber, or send it to the drum when drilling. It can also be used to isolate one circuit of heaters when starting to melt snow, or anti-freezing. It is also good to let the air out of the heaters and hose when starting up. 7. Temperature, flow and pressure sensor at drum These sensors are connected to the hose at the drum like shown below. These values are used in the drill speed formula to calculate optimal speed on drum. 8. Sensor-display The display boxes are placed in a big zarges box and shows data from the sensors in (7). Additionally the display show drill speed and drill depth from the sensors on the capstan (11) and the water level sensor placed with the submersible pump (12). The display can be connected to an alarm. The alarm should be used on the water sensor when we approach the ice base, but can also be used to indicate too low/high temperature, pressure and load when drilling. We will hold back the sensor display box, and bring it with us when we fly to Troll in December 2009. 9. Drum The hose connects to the drum like shown in the pictures below and above. The drum rotation is controlled by a yellow hydraulic engine. To get enough hose on the drum we need to lay it very neatly on the drum after it has been assembled. The drum also stands on wooden beams and insulation as it also gets warm during drilling. 10. Capstan The capstan is placed on two 5 m long 10cm×10cm wooden beams. It is further described in the sequence section later. Sensors for drill speed and drill depth, as well as hose tension are connected to the display unit (8). 11. Nozzle and submersible pump. We have three nozzles. Two thin ones to drill the hole. One reaming nozzle to enlarge the hole has a diameter of 17 cm. This is the same diameter as the Aanderaa frames we will deploy. This should not be a problem, as there is significant melting after the reaming nozzle has passed a certain depth on the way down from the warm water rising in the hole. We should make a spare for the reaming nozzle. We plan to build a "tube" to add to one of the drill nozzles. Also change the "jet" to one that spreads the water outwards in this case, with NO forward pointing spray. The nozzles should be secured using a special knot. The name of this knot is "prusik" in Norwegian. We have three submearsable pumps, two new ones, and one old. They come with a control box (starter) each. One of the new start-boxes needs repair. These pumps should be strengthened using two metal rods or a metal tube to prevent the breakage of the pump/motor coupling. 12. Hose from submersible pump. This consists of two hoses; a yellow one for water pumped up, and a black one for heated water going down to prevent freezing around the pump and hose in the hole. Water is taken from the top of the yellow hose, controlled by the return valve (13), and some is passed through a heater before it goes back down the black hose with the remainder going to the flubber. The power to the pump winds around the yellow and black hose as a plait.The water level sensor is attached seperatly just above the submersible pump using elastic string, and the cable for this is only attached an elastic rubber string at the surface, as the hoses will stretch when they are filled with water. 13. Returnvalve. The valve divides the water into the small heater for return down the black hose as noted in (12). It should be easier to regulate the flow using a needle valve rather than a "sphere" valve" as we used in the image below. The flow should be adjusted so that the heater warms the water "significantly" to 40-80ºC but tis depends on the water flow and heater fuel pressure. 14. Generators Two red generators produce electrical power for heaters, electric hydralic engines, and other instruments. We have changed filters and oil, and both are now working properly. 15 Hydraulic power units We have bought a new electrical engine for the blue hydraulic power, and an altogeather new unit. Both these have two outputs, creating hydralic pressure for the drum (9) and the capstan (10). We thus have a spare unit, and also bring the single yellow unit. 2.0 Setup The equipment setup should be done as shown in the sketch. 3.0 Sequence When the position of the bore hole is decided, the average wind direction will decide the layout of the camp. Heaters must be at the lee side of the wind so the exhaust is blown away from the camp. The wind breaks are placed to give maximum shelter for the equipment and ourselves. The rest is layed out as on the sketch below. There should be free way along 0 and 180 degrees away from the hole. The snow will be taken from the sector around 270 degrees, and should be kept clean. This can also be our supply of drinking water. Living and kitchen quarters should be more than 100 m away and along 45 degrees into the wind, this will give the most the lowest noise level. A work tent can be placed near the CTD winch if required. The main hose(s) should be rolled neatly on the drum after its assembly. A way to do this is to dig a hole in the snow, place wooden beams at either side, and roll the wooden drum with its axis at ground level and freely rotating. Make sure that the hose is on the top side of the drum when looking from the capstan. Sketch of the drill site. The front page image is taken looking towards the flubber on the sketch, and the living quarters would be off the upper right corner. Time frame for the drilling is roughly three weeks at first site; ~ 2 weeks for preparing to drilling first hole ~ 2 days drilling ~ 1 day CTD / mooring deployment + 1 day rest Preparation: water and pump Generally, pumps, heaters, and fuel drums stand on wood. This will stop them from tipping over and melting into the snow. Hoses needs to be insulated and additionally placed on insulation sheets as shown in the image to the right. We start off by placing the stainless steel tank near the side of the flubber. The melt tank base gets very hot and needs to stand on metal rods ontop of a wooden board to stop it melting in. We mount the oil burner and shovel in snow, and fire up. When the tank is full of melted snow we transfer the water over to one of the plastic tanks to make up a mixture of antifeeze and water to the correct strength, using either a bucket or the small blue electic ‘Handy pump’. Next, water is transferred to the other plastic tank standing inside the flubber. We carry on shovelling more snow into the melt tank until we have enough water to make it go through a pump and a heater. We make a curcuit from the black plastic tank, to a pump, to a heater, and back to the plastic tank. We can then heat up the water in this tank, and throw in snow that will melt inside it. As it fills water starts overflowing the plastic tank and into the flubber. Once the water level in the flubber is deep enough we can remove the plastic tank and circulate water directly to and from the flubber. Note that hoses must be supported over the side of the flubber to prevent pressing down of the side, causing loss of water and melting under the flubber! The number of heaters can be increased if needed to speed up the melting and digging! They should run at about 80ºC. If they get up to 90ºC the thermostat should turn them off. We continue until the flubber is close to full. We now have more than 10m³ melted water (10000 l). This is more than enough to make a 60 m hole. Using 38 l per minute this water would last for over 4 hours of pumping. When we finish melting, turn off the heaters and anti-freeze the system. Using the antifreeze mixture we pressure test the hoses and heaters and the pressure release valves. Check that the security valve works, and that there are no leaks. Check that the insulation covers everywhere as leaks may be hidden. Test all the drill system pumps and heaters with antifreeze so that if serious problems arise, freezing pipes, hose, valves, pumps etc. are not a problem. When antifreezing the whole hot water drill system do it in small parts. Pump antifreeze through one circuit of heaters only and watch the outflowing water as we pump, and when it changes to blue color place the out-hose back into the plastic tank. Then blow out the ant-freeze from this set of heaters using airpressure. Antifreeze the next heaters circuit also, and empty into the plastic tank. If the submersible pumps have been used, pour a little anti-freeze into both submersible pumps as well until it runs out of the intake. This liquid will be lost. After we have started drilling we also need to ant-freeze the drilling hose. This then requires pumping antifreeze into the hose for as long as we can. As we run out of antifreeze, we stop the pump. Blow the liquid through the entire drill hose using airpressure. Remember the antifreeze mixture will always get weaker, check it regularly and add extra antifreeze as required. Preparation: Hole We start this by digging a narrow trench up to 1.5 m deep. The capstan is placed above this ditch on 10cm*10cm wooden beams to make a stable platform. At the bottom we place a ready made board of plywood. The drilling will start through holes in this plywood board. The trench makes it alot easier to deploy and recover instruments and hoses. The hose to the submersible pump passes over an empty fuel drum, insulated both at the bottom and behind. This prevents the hose from melting/digging into the snow. (The drum will also get warm from sunshine). The setup of the capstan and the hole is shown in the sketch to the right, and also in the images below. Check that the instruments on the capstan works; load and drill speed, as well as drill depth. We make a10m mark on the drill hose, to know it is soon to appear at the surface. We will soon start drilling in the hole at the middle the buried and insulated fuel drum. We will drill quickly in the beginning. The upper snow layer is loose anyway, and we do not want to make a big hole and loose alot of water. Otherwise we will use a formula to set the drill speed, based on water temperature and flow, and the depth we are at the moment. Mount the drill nozzle on the snow infront of the capstan, and lower it down when it has been mounted properly. It shall then hang freely suspended below the capstan. We need to able to adjust the capstan and the plywood board (Directions mentioned is 0 to 180 degrees for capstan and 90 to 270 degrees for plywood board.) We fire up the 8 heaters and are ready to drill the first test hole. Drilling of test hole This hole may be drilled down to 30 m using a cone spray on the nozzle and reamed to make a first drill hole. We can then stop drilling and take a rest, because we have only drilled in the firn layer. This firn layer will not refreeze, and the water we use is lost anyway. Drill quickly in the beginning, and use the formula when we get deeper. The 30 m hole should not take more than an half an hour to drill and 15 minutes to ream using the full drill system. Check the depth in the display box (8). This hole will become the return hole where we deploy the submersible pump. At this stage the flubber can be refilled ready for the main drilling work and the drill system antifeezed, including the drill nozzle. Note: When using hoses intermittently always clear the water and use some antifreeze. If a hose is ready for use next to a valve,e.g. to divert flow, and the valve leaks even a little, the hose will become frozen, so if possible only connect ‘empty’ hoses when needed. Final preperations and practice mooring deployment Using the 30 m test hole practice the deployment of the submersible pump, CTD, and mooring to ensure methods are correct and all people know what they are doing, next time they could be very tired! Install any snow anchors that will be needed to secure the submersible pump, mooring, capstan, CTD winch and get all fuel, equipment and spares ready before the main drilling takes place. We lay the black/yellow hose and the power cable (umbilical) out on the ice in direction 0 degrees. We could use the skidoo to drag it out, and secure it with also. Measure and mark depths on submersible pump umbilical so the deployment depth is known, similarly, do the same with the mooring if required. Test the CTD and the CTD winch, and finally check the instruments and lay them ready assembled out on the snow. Before starting drilling get a full nights sleep. For deeper drilling shifts must be decided, as people need have some sleep. At this stage it is smart to wait for a good weather forcast (call Rothera). When we continue from here there is "no way back". If we have to stop the drilling operation the hole will freeze over with ~1cm per hour. We will loose the water inside the hole, and have to start melting snow again. Drilling of pump hole We continue drilling using the test hole until we are at 60 m. We then make another mark on the hose, and bring the drilling nozzle back up. We close the water flow down the hose at 10 m depth to prevent making a big hole below the capstan. General check procedure during drilling every 15-30 min; Measured Temp and Press on Drum. ~80 ºC, 50 bar Drilling speed. To be reduced as we go deeper according to formula. All heaters working and at similar temperature ? Leaks ? (Water, oil, fuel) Return flow to flubber (should pour in making small water fall) Heat inflow to sub-pump, change temp by regulating flow to heater. Generators and Pumps (Diesel level) Refill drums from back using 1 hand driven mechanical pump and new drums. Water level above the submersible pump (+2 m). Ream the hole and deploy pump Attach the reaming nozzle and antifreeze the first drill nozzle. We use this reamer in the same way, drill fast in the beginning and then slow down gradually. The reaming goes faster than the drilling because it only checks the minumum hole diameter. Back on the 60 m depth mark with the reaming nozzle, we shall make a big ice cavern. This cavern shall be large enough so that when we drill the other hole at the side water shall connect through from the deeper main hole. Leave the reaming nozzle at this depth for up to 20-30 minutes. Make sure the water level in the flubber is not less than ~ 25 %. As the reamer nozzle is left at 60 m depth we prepare the submersible pump. When the pump hole is finished we bring the reaming nozzle back up. We can place the hose inside the flubber, and leave the pump running. Secure the hose carefully because at high flow rates it can ‘jump out’ of the flubber. The heaters should be stopped before we start lowering the submersible pump. The pump is secured and lowered slowly down the hole. The water level sensor cable is lowered by hand at the same time. We need to be very careful at the end, as it grows heavier and heavier. Using the skidoo, or maybe the band wagon to secure it with is good. When it has reached the correct depth we use the rope (Yalegrip) attached to the hose and secure it to the prepared snow anchor. When everything is placed and connected we start the electrical pump by switching it on in the starter box. The water will start flowing up through the yellow hose, and some of it shall be heated and sent back down the black hose. Now secure the water level sensor cable using elastic string at the top of the hole. Keep on pumping warm water back down the hole while we fill the flubber. This may take some time, also have a small rest. At the pump there is a pressure sensor, measuring the water level above. Make sure that there is always some water above the pump (2-3 m minimum). The return water to the flubber should pour in from above water level so that it makes a small waterfall. In this way we hear it flowing all the time, and can see if it stops. If this water stops flowing, first check the power and try to restart, if no restart we need to bring up the pump quickly. Be very careful not to snap the pump at the top of the hole, lift last 5-10 m by hand. Change the nozzle to the drill nozzle and move the capstan over to the other hole in the plywood board. If the flubber becomes full or the water level becomes too low in the hole, we stop the return flow to the flubber and divert all the flow back down the hole through the heater. Drilling of main hole Using water from flubber we start drilling the main hole. We drill slower and slower with depth using the formula. We drill down again to the 60 m depth mark, and hold the drill there for a short time, then bring the drill nozzle back up. Remember to stop water flow at 10 m depth. During this drilling the water level can suddenly increase in the pump hole if a connection is made between the two holes higher in the hole. We change nozzle, and ream the main hole down to the 60 m, the level where the pump is hanging. We should have a connection between the two holes now, and see the water starting to fill up again on the water level display. Otherwise we may leave the reamer at this depth for longer. But with time the connection will open up driven by the warm water ascending inside the hole. Bring up the reaming nozzle. Change to drill nozzle, and resume drilling from 60 m depth. We switch on the full flow when the drill nozzle is approaching the water level depth, 60 m less the water level recorded in the pump hole. Open up the return flow to the flubber as we start drilling. We continue drilling. If the water flow is stopped for some reason we need to bring up the drilling nozzle at once by at least 10 m. It could freeze the nozzle tip very quickly. From the seismic data we have a good estimate on total ice thickness at the site. When we approach this depth we set the alarm on the water level indicator for +/- 20 cm. This sensor tells us how much water there is above the submersible pump, and it will change when we drill through the ice shelf. The water level could either drop or rise, but it will be a permanent and signficant change. For ice 250 m thick the fresh water level in the hole should be around 39 m and 55 m for ice 450 m thick. Stop drilling immediately, and mark the hose at this depth using tape. We bring the nozzle 1 m back up and leave it for 10 minutes. This will help making a better transition for the CTD entering the hole from below. We also run the nozzle a bit up and down to widen the opening. Then bring the drill nozzle up, and change to the reaming nozzle. We then use the reamer mainly to check the hole diameter but also to enlarge the main hole a little as the first drilling should have made the hole the correct size. Once the drill is recovered from the hole we antifreeze the hoses and heaters, and are ready for the CTD. Note: It should be possible to leave the submersible pump running and just recirculate water through the heater during the CTD work. But with a long 60 m power cable next to the CTD cable this may interfer with its communications and the pump must be turned off. In this case, antifreeze the surface hoses and pour about 5 litres of antifreeze down both hoses to the submersible pump. CTD measurements We deploy the CTD using the anchored CTD winch. The CTD wire runs over a metered wheel on the capstan before it descends the hole. Ropes with snow anchors secure the capstan on opposite side to the CTD winch. We do a good number of CTD profiles, and try to get it back up the hole. If it gets stuck, we do not pull very hard, but bring it back down and profile some more. A different directions on the tides will hopefully make the next attempt more succesful. In the worst case we need to cut the CTD cable but as a final try, use the split metal rod to slide down to the CTD to try to release it. It is not possible to drill with the CTD in the main hole as the CTD wire and the hose will get entangled, and we risk loosing both the CTD and the hose/nozzle. The hole is freezing over quite slowly. The reamer makes at least 17 cm diameter hole, and refreezing is not more than about 1 cm in diameter every two hours. So we can keep on taking CTD profiles at least 12 hours (equals loss of 6 cm in diameter). Rig deployment We start everything up once again and ream the main hole once more. After the big nozzle is back on the surface we need to antifreeze the for a last time. We then deploy the current meter rig that has been ready ever since we started drilling on the ice. We need to be careful, drop it nice and slow, avoid long stops because of freezing, and make sure it is secured all the time on the way down. Using the skidoo as an "anchor" and drive slowly towards the hole is a good idea. At the right depth we secure the rig to a snow anchor, and leave wooden beams (4"×4") across the hole to hold the rig. We remove the capstan and the let go of the skidoo. Setup the mooring logger as soon as is possible so that if failures occur some data will have been collected. If the mooring fails is will be difficult to recover, even immediately, but after an hour or two it is likely to be impossilbe because of refreezing of the hole. We then have to bring the submersible pump up slowly using the skidoo. The pump and the single heater have been running until now, because our main priority was to get the rig deployed. When the pump approaches the surface we need to be very careful to not break the pump (but it has been strengthened using metal bars). Suggest lifting the last 5-10 m by hand to avoid breakages. We antifreeze both hoses and empty with air pressure. Pour anti-freeze liquid directly in the outflow connector on the pump to antifreeze that. Rest At this stage we will have worked intensively for 2 weeks, and not slept much the last 24 hours. It is therefore very important to take a proper rest. Shifts and/or rest periods are recommended for drilling the deep hole. Take a day off, and relax as much as possible. We should be very happy if everything has worked as planned. BAS hot water drilling shift pattern with 4 people. This will provide 3 people on site at all times with long handovers and lots of cooked food available: Each person has: 6 hours sleep, 3 hours – make food/rest, 12 hours work, 3 hours – make food/rest. Packing Everything is dis-assembled and packed in boxes. However, we keep as large parts of the drill intact as possible, and make the most of the big snow cats and their trailers. We drain the left over water from the flubber, and role the hoses back on the empty wooden drums in the snow pits. GPS positions are double checked. We then mark the hole with flags and tall poles. We want the current meters to operate for many years, and there is roughly 0.5 m/year snow accumulation.
© Copyright 2026 Paperzz