Baseline 3

Reference:
NEPT/ERTMS/REQ/0008
Issue/ver:
3.0
Date:
31st March 2017
Electronic File Location
CCMS ref: 64153205
Version History
Issue
Date
Comments
1.0
14/06/13
Initial draft – for internal review and comment
1.1
24/09/13
Updated for further internal review
1.2
21/11/13
Updated by Harv Bhatia & Arvind Bali
1.3
09/06/14
Updated from Reference Design for internal review
1.4
26/06/15
Updated by Arvind Bali from Consolidation Workshop and Reference
Design
1.5
05/08/15
Extract from DOORS database for Technical Author review
1.6
12/08/15
Updated by Arvind Bali after Technical Author review
1.7
17/01/16
Updated after ORRG, SRSG, NRT and internal review
1.8
16/03/16
Updated post Requirements Consolidation Workshop for telecoms. For
Technical Author review
2.0
31/03/16
First Issue
2.1
29/04/16
Update following Reference Design requirement harmonisation
2.2
18/08/16
Update for SRSG
2.3
29/08/16
Update from SRSG
2.4
22/09/16
Update for SRSG
2.5
30/09/16
Release for ESB / OSG review
2.6
16/01/17
Update from Industry review
3.0
31/03/17
Formal issue
Disclaimer
Network Rail has used its best endeavours to ensure that the content, layout and text of this
document are accurate, complete and suitable for its stated purpose. It makes no warranties,
expressed or implied, that compliance with the contents of this document shall be sufficient to ensure
safe systems of work or operation. Network Rail will not be liable to pay compensation in respect of
the content or subsequent use of this document for any purpose other than its stated purpose or for
any purpose other than that for which it was prepared except where it can be shown to have acted in
bad faith or there has been wilful default.
NETWORK RAIL
Page 2 of 18
Reference:
NEPT/ERTMS/REQ/0008
Issue/ver:
3.0
Date:
31st March 2017
Contents
INTRODUCTION .............................................................................................................. 4 1 2 1.1 Purpose of this Document ............................................................................................................................ 4 1.2 Scope ................................................................................................................................................................... 4 1.3 Context ................................................................................................................................................................ 4 1.4 Abbreviations .................................................................................................................................................... 5 1.5 Requirements: Form, Applicability and Identification ......................................................................... 5 1.6 Requirements Assurance ............................................................................................................................. 6 1.7 Requirements Change .................................................................................................................................. 6 1.8 Areas for Development ................................................................................................................................. 6 REQUIREMENTS ............................................................................................................. 7 APPENDIX A: ABBREVIATIONS..................................................................................15 APPENDIX B: LIST OF REFERENCES .......................................................................16 APPENDIX C: OPTIONS LOOKUP TABLE .................................................................17 APPENDIX D: AREAS FOR DEVELOPMENT.............................................................18 NETWORK RAIL
Page 3 of 18
1
INTRODUCTION
1.1
Purpose of this Document
Reference:
NEPT/ERTMS/REQ/0008
Issue/ver:
3.0
Date:
31st March 2017
This document provides a specification that is intended to promote effective implementation of
the ETCS. It is applicable to ETCS installations, and provides requirements that are optimised
for operation on the GB rail network.
As stated in the industry-agreed and issued National ETCS Requirements Management
Strategy [RD1] and Plan [RD2], the document provides the requirements which have been
developed as part of a suite of ETCS requirements covering all elements required to optimise
performance and operation of an ETCS railway. The document can be utilised as a
standalone specification for the Telecoms aspect of the ETCS; further details of the parent
requirements that drive the development of this specification are included within the System
Requirements Specification [RD3] and the other Sub-system Requirements (Trackside,
Onboard, and Operations [RD4], [RD5] & [RD6]).
This Specification for the ETCS Telecoms sub-system has been written to complement the
European Union Agency for Railways specification for Baseline 3 ETCS1 [RD7] & [RD8].
Every effort has been made to avoid conflict with the Baseline 3 specification but, in case of
conflict, the Baseline 3 specification takes precedence.
The document is set out in the form of standard requirements with the ETCS Telecoms
Requirement (ETCSS) identifier, followed by rationale and guidance notes where appropriate.
1.2
Scope
This document consists of requirements which describe the functionality and application of
the ETCS Telecoms sub-system optimised for application on the GB rail network at all
required levels of operation.
These requirements do not prevent the ETCS operating in conjunction with an Automatic
Train Operation (ATO) system. Requirements will be added at a later date once the European
specification for adding ATO to an ETCS sub-system has been finalised. Projects are
encouraged to seek advice from the ERTMS Systems Body if there is a wish to facilitate early
introduction of ATO.
These requirements do not prevent the ETCS operating in conjunction with a Traffic
Management (TM) system. No specific TM requirements have been identified for inclusion to
date.
Specific requirements and domain knowledge for a particular application are not included
within this document, and will need to be defined by the Contracting Entity or their appointed
Agent.
Nothing in this document obviates any legal requirement with which any of the parties must
comply. Furthermore, it does not preclude operation of a TSI-compliant vehicle on the GB rail
network, nor a vehicle compliant to this specification operating on TSI-compliant infrastructure
outside the GB rail network.
1.3
Context
This document has been developed from a number of sources.
1
Note: This suite of requirements has been written to meet Baseline 3 Release 2, although the ETCS
DOORS requirements database has the capability of producing a suite of requirements to meet Baseline
3 Maintenance Release 1. Should a suite of Baseline 3 Maintenance Release 1 requirements be
needed, or if any background information be required for any specific requirement, then an e-mail with
specifics should be sent to: [email protected]
NETWORK RAIL
Page 4 of 18
Reference:
NEPT/ERTMS/REQ/0008
Issue/ver:
3.0
Date:
31st March 2017
Input from the ETCS programme, ETCS suppliers, and the wider rail industry has been used
to develop the requirements. A series of workshops and industry consultations have identified
new requirements. Guidance has been added to justify changes.
Requirements amended and deleted through this development process have been captured
within the requirements database, along with justification for their amendment or removal.
1.4
Abbreviations
Abbreviations are explained in full where used in Requirements. A fuller explanation of Terms
and Abbreviations can be found in Appendix A: and the ERTMS Glossary [RD9].
1.5
Requirements: Form, Applicability and Identification
1.5.1
Requirement Functionality
Requirements may be functional or non-functional:

Functional Requirements - Technical details that define what a system needs to
accomplish, i.e. how suppliers’ equipment will be applied, what it needs to do, and
what processes, procedures and rules need to be in place to achieve that.

Non-Functional Requirements - Constraints on the design or implementation, such
as performance, security, competence, training, and reliability requirements.
Functional requirements have been derived through the Reference Design generation
process [RD10], whereas non-functional requirements have been derived from the Cambrian
Requirements suite and supplemented by workshop input [RD11].
1.5.2
Basic Requirement Form
All requirements are in the following form:
Safety
Requirement text.
Unique ETCSS-Identifier
Status:
Normative/Application-Specific/Preferred. (See Section 1.5.4 below).
Rationale: Shows applicability of the requirement.
Guidance: Supplementary
satisfaction.
Options:
1.5.3
information
to
support
Requirement
interpretation
and
Reference Design Topics (If applicable). (See Section 1.5.5 below).
Safety Requirement
Where a requirement has been associated with a Safety Measure, this is identified.
1.5.4
Normative / Application-Specific / Preferred status
Each requirement within this document is identified as one of: normative, preferred, or
application-specific. These are defined as follows:

NETWORK RAIL
Normative
o
Necessary to achieve compatibility or optimisation of the system in relation to
the GB rail network, or
o
A system feature that is deemed to be cost-effective and universally
beneficial.
Page 5 of 18
Reference:
NEPT/ERTMS/REQ/0008
Issue/ver:
3.0
Date:
31st March 2017
Satisfaction of normative requirements in compliance with this document is expected
to be a requirement of individual delivery contracts.

Application-Specific
o
A requirement which may not be relevant or applicable to every
implementation of the ETCS. It is expected that, where a requirement is
applicable, it will be applied.
Satisfaction of application-specific requirements in compliance with this document is
expected to be a requirement of individual delivery contracts, as appropriate to the
implementation being considered.

Preferred
o
A requirement of lower importance which, whilst not essential, the industry
would prefer were satisfied. It is expected that, where a requirement is
applicable, it will be applied.
Satisfaction of preferred requirements in compliance with this document is not
expected to be a requirement of individual delivery contracts unless explicitly
specified within the relevant contract.
1.5.5
Options
Where applicable, the Reference Design Topic has been identified, as detailed in the Topics
Lookup Table in Appendix C:.
1.6
Requirements Assurance
Requirements assurance has been explained in the ETCS Requirements Assurance
Statement [RD12].
1.7
Requirements Change
The ETCS Requirements Change Management Process [RD13] will be used to raise Change
Requests (CRs) to amend existing requirements or add new requirements.
1.8
Areas for Development
Noting that this document represents the best understanding of the needs of GB’s rail network
at the time of publishing, it is recognised that there are a number of areas where the
document may be deficient. New deficiencies may be identified as understanding of the ETCS
develops, as well as areas being closed out through further work being undertaken. The
current known areas of deficiency are listed in Appendix D:
NETWORK RAIL
Page 6 of 18
2
Reference:
NEPT/ERTMS/REQ/0008
Issue/ver:
3.0
Date:
31st March 2017
REQUIREMENTS
The GSM-R infrastructure shall, as a minimum, meet the Telecommunications Reliability,
Availability & Maintainability (RAM) requirements specified in the ERTMS Reliability
Specification (NR/AM/SA/SPE/00147) [RD14].
ETCSS-1
Status:
Normative
Rationale: NR/AM/SA/SPE/00147 defines ETCS reliability and availability targets, which are
then apportioned to the respective Onboard, Trackside and Telecommunications
elements.
Guidance: RAM Requirements for the network sub-systems are specified in the ERTMS
Reliability Specification NR/AM/SA/SPE/00147 Issue: A07 [RD14]. The
specification only considers single GSM-R components; however, it is
acknowledged that the overall network architecture needs to be considered
holistically, and the Guidance Note 'GSM-R Availability Assessment for ETCS
Traffic' (NEPT/ERTMS/HBK/0402 ver1.1) [RD15] addresses how to meet the
availability requirement of the route.
Options:
A1-1, A1-2, A2-1, A2-2, O2-1, O2-2, HH
Whole life Service Level Agreements (SLAs) and procedures related to planned telecoms
infrastructure system maintenance outages shall be reviewed and updated before each ETCS
route deployment.
ETCSS-2
Status:
Normative
Rationale: System outages will be required in order to carry out system maintenance and
upgrades to the Fixed Telecommunications Network (FTN) and Global System for
Mobile Communications – Railway (GSM-R) networks and their supporting
systems, e.g. power supplies. The procedures for handling such outages need to
be discussed with Industry and agreed at the National level as part of the ETCS
life cycle plan.
Guidance: SLAs will be agreed at the National level and will have to be in place before each
route commissioning.
Options:
None
Unambiguous procedures shall be provided for degraded and abnormal telecoms conditions.
ETCSS-65
Status:
Normative
Rationale: Telecoms personnel must advise operations personnel so that operators can
safely and efficiently manage the situation in degraded working.
Guidance: In the event of any service affecting failure of the telecoms network, operational
procedures will be implemented immediately by the Telecommunications network
provider to advise the signallers of the nature of the failure and ensure that they
are aware of the operational implications and projected recovery times.
Options:
None
Operation of the ETCS on the Telecommunications network shall not have a detrimental
impact on existing services using the Telecommunications network.
ETCSS-70
Status:
Normative
Rationale: The introduction of ETCS must not adversely impact other existing users.
NETWORK RAIL
Page 7 of 18
Reference:
NEPT/ERTMS/REQ/0008
Issue/ver:
3.0
Date:
31st March 2017
Guidance: Existing services using the Telecommunications network include GSM-R voice,
Supervisory Control & Data Acquisition (SCADA), level crossings, etc.
Options:
None
In the event of failure of voice communications following application of the ETCS, there shall
be an alternative means of voice communication with the signaller.
ETCSS-61
Status:
Normative
Rationale: To provide a suitable method of communication with the signaller to meet
operational or safety obligations.
Guidance: Drivers, track workers and members of the public may need to maintain
communications with the signaller regardless of the availability of the GSM-R.
Locations can include platforms, level crossings, tunnels and key junctions.
Options:
A4, HH
The characteristics and performance of the data bearer services provided by the GSM-R
network shall satisfy Subset 093.
ETCSS-3
Status:
Normative
Rationale: Subset 093 is currently a non-mandatory specification within the Control,
Command and Signalling Technical Specification for Interoperability (CCS TSI)
[RD8] and needs to be applied in the absence of any other Quality of Service
(QoS) specification.
Guidance: Subset-093 provides end-to-end service requirements for GSM-R networks.
Subset-093 provides end-to-end minimum QoS, including establishment of a
connection, the connection loss rate, and re-establishment of connection.
Options:
A1-1, A1-2, A2-1, A2-2, O2-1, O2-2, R1
Subset-037 and A 11 T 6001 configuration parameters for communications shall be
optimised.
ETCSS-12
Status:
Normative
Rationale: Subset-037 and A 11 T 6001 specify the parameters that need to be optimised.
Guidance: Subset-037 version 3.2.0 (Euroradio FIS) and A 11 T 6001 version 13.0.0 (Radio
Transmission FFFIS for EuroRadio) contain parameters that need to be optimised
to take into account GSM-R network behaviour.
Options:
R1
Processes and procedures shall be in place to maintain the levels of GSM-R network service
throughout the lifetime of the GSM-R system.
ETCSS-9
Status:
Normative
Rationale: Loss of the GSM-R has an immediate impact on an ETCS railway.
Guidance: The levels of service are as specified in Subset-093 and network coverage
requirements are contained in the European Integrated Railway Radio Enhanced
Network (EIRENE) System Requirements Specification (SRS) [RD8].
Options:
A1-1, A1-2, A2-1, A2-2, A4, O2-1, O2-2, EE2
NETWORK RAIL
Page 8 of 18
Reference:
NEPT/ERTMS/REQ/0008
Issue/ver:
3.0
Date:
31st March 2017
Safety
A quality of service monitoring system shall be implemented across the telecoms
infrastructure.
ETCSS-10
Status:
Normative
Rationale: This is required for gathering service statistics to predict potential performance
degradation. Safety requirement for hazard N-H028.
Guidance: Service statistics required for ETCS operations include, but are not limited to, the
number of successful ETCS calls, the number of failed ETCS calls, and the cell
handover success rate for ETCS calls encountered. The following should also be
included, but not be limited to: ETCS Connection Establishment Delay, ETCS
Connection Errors, ETCS Connection Loss Rate, delayed Subset-026 messages,
High-Level Data Link Control (HDLC) Frame Error, Cyclic Redundancy Check
(CRC) error, retransmitted frames, and lost frames.
Options:
N2-1, O2-1, O2-2
The Telecommunications system shall be supported by a life cycle management plan.
ETCSS-16
Status:
Normative
Rationale: To ensure that budgets and system design deliver whole-life cost-efficiency.
Guidance: The telecoms lifecycle management plan will need links into a life cycle
management strategy for the ETCS as a system on the rail network to enable
effective management of configuration and reliability through industry Data
Recording Analysis and Corrective Action System (DRACAS) processes.
Options:
None
The GSM-R network capacity shall support ETCS data and voice traffic for normal, degraded
and emergency operations on the route.
ETCSS-4
Status:
Normative
Rationale: To provide Telecommunications traffic capacity that will be required to support
the ETCS and voice communications. This will include the capacity required to
support online key management.
Guidance: The Guidance Note 'GSM-R Capacity Assessment for ETCS Traffic' [RD17]
provides instruction on what needs to be considered when identifying the data
capacity requirements, taking into consideration future increase in rail operations,
Radio Block Centre (RBC) handovers, ‘Start of Mission’, degraded operations,
etc. The Operational Concept for ERTMS [RD18] defines normal operations as
situations expected to be encountered entering, exiting, and making train
movements in the ETCS, and any setting up or closing down arrangements as
part of start of service or end of service. Degraded operation is defined as
planned or unplanned reduction in the ability of the ETCS to operate in its normal
manner. This could include a partial degradation where it remains acceptable to
continue to operate the ETCS.
Options:
A1-1, A1-2, A2-1, A2-2, A4, C, J3, J4, N1-1, N2-1, N2-2, O2-1, O2-2, S5-1, U1,
U2, U4, U5, U6, V1, V2, EE2, JJ1, JJ2, JJ3, JJ4, JJ5, JJ6, JJ7, JJ8
The Telecommunications network shall satisfy the route's apportioned availability requirement
for the telecoms network.
ETCSS-64
NETWORK RAIL
Page 9 of 18
Reference:
NEPT/ERTMS/REQ/0008
Issue/ver:
3.0
Date:
31st March 2017
Status:
Normative
Rationale: To support the route in selecting a system configuration that is suitable for that
route. Expenditure on telecoms availability needs to be considered against the
impact of loss of service on the route.
Guidance: The route will have a business plan for delay reduction when the ETCS is
operational. Applying apportionment modelling will derive a budget of ‘allowable’
delay for the route and the system. The Guidance note 'GSM-R Availability
Assessment for ETCS Traffic' [RD15] provides guidance on the process to
support the route in selecting a suitable system configuration.
Options:
A1-1, A1-2, A2-1, A2-2, O2-1, O2-2
The Telecommunications network shall allow trains to register and de-register from the ETCS
at any location which is ETCS data-enabled.
ETCSS-72
Status:
Normative
Rationale: GSM-R coverage is required in all locations where ETCS-fitted trains plan to
operate under ETCS control.
Guidance: The Guidance Note 'GSM-R Coverage Assessment and Cell Planning' [RD16]
provides guidance on operational areas that need to be considered. Locations
include terminus / turnback stations, ETCS level transition points, and relevant
depots / sidings. De-registration in areas not fitted with the ETCS will be achieved
through timeout.
Options:
B, C, G1-1, G1-2, G2, G4-3, I, O1, O2-1, O2-2, O3
Where there is a requirement to provide General Packet Radio Service (GPRS) for capacity
reasons, the whole of the RBC operational area shall be provided with GPRS capability,
including the RBC to RBC handover zones.
ETCSS-71
Status:
Normative
Rationale: This aligns with Subset 037 version 3.2.0.
Guidance: Once in an RBC area, it is not possible for the Onboard to switch automatically
from packet-switched data to circuit-switched data.
Options:
R1
GSM-R network coverage shall be provided in all areas where ETCS-fitted trains will enter,
operate in, and exit Level 2.
ETCSS-13
Status:
Normative
Rationale: GSM-R data coverage is required in all areas where ETCS-fitted trains enter,
operate in, and exit Level 2.
Guidance: This includes associated depots, maintenance facilities and sidings, as well as
possessions, and during emergency degraded and abnormal conditions.
Coverage is also required to support online key management. The Guidance
Note 'GSM-R Coverage Assessment and Cell Planning' [RD16] provides
guidance on signal strengths in the operational areas that need to be considered.
The Guidance Note asks for higher levels than those defined in the EIRENE
System Requirements Specification and provides target coverage levels by
location, including major stations, junctions, tunnels, and urban and rural lines. It
also provides coverage guidance for RBC handovers, Start of Mission, transition
into Level 2, etc.
Options:
A1-1, A1-2, A2-1, A2-2, A4, G1-1, G1-2, G2, G4-1, G4-2, J2, J3, J4, J5, L1, N1-1,
N2-1, O2-1, O2-2, S5-1, V1, V2, HH
NETWORK RAIL
Page 10 of 18
Reference:
NEPT/ERTMS/REQ/0008
Issue/ver:
3.0
Date:
31st March 2017
The Telecommunications network shall provide sufficient GSM-R signal strength and
overlapping coverage at locations where marginal coverage or loss of coverage would cause
significant disruption to railway operations.
ETCSS-73
Status:
Normative
Rationale: Loss of coverage or marginal coverage in key areas would cause significant
disruption to railway operations.
Guidance: The Guidance Note 'GSM-R Coverage Assessment and Cell Planning' [RD16]
provides guidance on operational areas that need to be considered. Although
minimum levels are defined by the EIRENE SRS, this requirement is to make
sure that critical areas have the best coverage.
Options:
A1-1, A1-2, A2-1, A2-2, I
The Telecommunications network shall provide sufficient GSM-R signal strength to mitigate
against interference from Mobile Network Operator (MNO) interferer sites.
ETCSS-74
Status:
Normative
Rationale: To minimise the likelihood of interference from MNO sites disrupting railway
operations.
Guidance: The GSM-R network design should take into consideration that the base-stations
are authorised to operate only within the power limits defined in the Wireless
Telegraphy Act licence. Coordination and cooperation with MNOs could provide
additional measures to minimise interference.
Options:
A1-1, A1-2, A2-1, A2-2, I
The Telecommunications network shall provide coverage overlap between adjacent GSM-R
cells to allow successful circuit-switched handovers or General Packet Radio Service (GPRS)
re-selections to take place at line speed at the required signal level.
ETCSS-75
Status:
Normative
Rationale: GSM-R coverage is required in all locations where ETCS-fitted trains will operate.
Guidance: The Guidance Note 'GSM-R Coverage Assessment and Cell Planning' [RD16]
provides guidance on operational areas that need to be considered.
Options:
EE1, EE2
The Telecommunications system shall support the testing associated with the introduction of,
and future changes to, ETCS installations.
ETCSS-62
Status:
Normative
Rationale: There are locations that will need ETCS coverage purely to test GSM-R
functionality on its introduction, or as a result of maintenance.
Guidance: This will be needed at test tracks, in depots, and on the mainline and would cover
General Packet Radio Service (GPRS), Enhanced Data rates for GSM Evolution
(EDGE), and the complex rail environment.
Options:
None
The telecoms application design shall facilitate ease of maintenance, repair and replacement,
and configuration control of components.
ETCSS-66
NETWORK RAIL
Page 11 of 18
Reference:
NEPT/ERTMS/REQ/0008
Issue/ver:
3.0
Date:
31st March 2017
Status:
Normative
Rationale: Ease of maintenance and installation contributes to whole-life cost reduction.
Guidance: The design should enable ease of installation and maintenance activities for rapid
fault resolution.
Options:
None
The Telecommunications system shall be protected from threats with sufficient physical,
procedural and technical controls to minimise damage and security risks.
ETCSS-67
Status:
Normative
Rationale: Telecommunications systems can be compromised at several levels. This
requirement addresses intended and unintended consequences of the system
being compromised.
Guidance: Access to systems must be controlled to avoid unauthorised access, either
unintentional or deliberate. Consideration should be given to the location and
environment of the equipment to be protected.
Network Rail’s Security Assurance Framework (SAF) [RD19] should be used to
assess GB operational rail systems (including communications networks) for risk.
Options:
None
The Telecommunications sub-system equipment, processes and people shall not give rise to
unacceptable and unmanageable safety risks.
ETCSS-68
Status:
Normative
Rationale: To ensure that the complete system of systems is safe.
Guidance: The Telecommunications sub-system equipment and processes will interact with
other systems. The interaction encompasses intentional interaction via a defined
interface and unintentional interaction where there is no defined interface.
Options:
None
The Telecommunications network provider shall provide profiled Subscriber Identity Module
(SIM) cards to support deployment of the ETCS.
ETCSS-5
Status:
Normative
Rationale: The Telecoms network provider intends to procure a large number of SIM cards
in advance and profile them in time for deployment on the route.
Guidance: The SIM cards will be profiled for the desired service, e.g. data, testing, voice,
etc. The total number of SIM cards for end-user equipment will need to be
specified for each application. All the necessary SIM cards for the lifetime of the
project will be made available before the deployment of the route.
Options:
None
All Subscriber Identity Module (SIM) cards shall be profiled for both Circuit Switched and
Packet Switched communications modes.
ETCSS-92
Status:
Normative
Rationale: The TSI specifies the GSM-R SIM card as an Interoperability constituent.
Guidance: The SIM needs to be profiled for both circuit switched and packet switched
modes to allow the ETCS Data Only Radio (EDOR) to use packet switching
where required.
NETWORK RAIL
Page 12 of 18
Options:
Reference:
NEPT/ERTMS/REQ/0008
Issue/ver:
3.0
Date:
31st March 2017
None
The Telecommunications network provider shall manage the provision of Subscriber Identity
Module (SIM) cards and configuration databases throughout the lifetime of the ETCS.
ETCSS-76
Status:
Normative
Rationale: To support Railway Undertakings (RUs) in replacing defective ETCS Data only
Radios (EDORs).
Guidance: Replacement SIM cards will need to be profiled for the desired service (e.g. data,
test, etc.) and the GSM-R configuration database will need to be maintained to
enable the EDOR to work on the GSM-R network.
Options:
None
Packet switched data communications shall be available at all locations where online key
updates are required to take place.
ETCSS-77
Status:
Normative
Rationale: To enable keys to be updated when required.
Guidance: To provide packet switched data communications at locations where key
transfers are required to take place. These include ETCS running lines,
maintenance depots and stabling points attached to ETCS running lines,
maintenance depots where ETCS equipped trains will be maintained, private
sidings and facilities, and other locations, as required.
Options:
EE1, EE2
Safety
The Telecommunications system shall record system event data suitable for use to monitor
system performance and investigate incidents effectively.
ETCSS-78
Status:
Normative
Rationale: Speedy investigation and resolution of incidents is critical to keep the service
running. Safety requirement for hazard N-H028.
Guidance: It must be possible to understand how the whole system has behaved (including
those who operate it) in order to determine the underlying causes of any incident
or performance failure. Therefore, data from the Onboard, Trackside and
Telecommunications sub-systems must be collected and synchronised.
Information relating to the human element would be managed through review of
written records and interviews as well as actions at the human machine interfaces
recorded by sub-systems.
Options:
None
GSM-R network coverage shall be provided when the train's reporting of position or
requesting of Movement Authority updates might be used to influence the operation of the
level crossing.
ETCSS-79
Status:
Normative
Rationale: Good coverage is required where ETCS is used to influence the operation of the
level crossing.
Guidance: The coverage would be from a point which allows the ETCS and the level
crossing system to react, taking into consideration the braking distance of the
NETWORK RAIL
Page 13 of 18
Options:
Reference:
NEPT/ERTMS/REQ/0008
Issue/ver:
3.0
Date:
31st March 2017
train. This can be approximated to 4 minutes running time at linespeed from the
crossing.
A1-1, A1-2, A2-1, A2-2, JJ1, JJ2, JJ3, JJ4, JJ7
There shall be no designed radio holes from a point 200m on the approach to an End Of
Authority (EOA) protecting a level crossing and the level crossing itself.
ETCSS-80
Status:
Normative
Rationale: Trains crossing a failed level crossing need to be able to receive the movement
authority and mode profile in this area.
Options:
JJ8
NETWORK RAIL
Page 14 of 18
APPENDIX A:
Reference:
NEPT/ERTMS/REQ/0008
Issue/ver:
3.0
Date:
31st March 2017
ABBREVIATIONS
The following abbreviations are used within this document, and can also be found in the
ETCS Glossary [RD9].
ATO
Automatic Train Operation
CCS
Control, Command & Signalling
CRC
Cyclic Redundancy Check
DRACAS
Data Recording Analysis and Corrective Action System
EDGE
Enhanced Data rates for GSM Evolution
EDOR
ETCS Data Only Radio
EIRENE
European Integrated Radio Enhanced Network
ERTMS
European Rail Traffic Management System
ESB
ERTMS Systems Body
ETCS
European Train Control System
FTN
Fixed Telecommunications Network
GPRS
General Packet Radio Service
GSM-R
Global System for Mobile Communications - Railway
HDLC
High-Level Data Link Control
MNO
Mobile Network Operator
QoS
Quality of Service
RAM
Reliability, Availability & Maintainability
RBC
Radio Block Centre
RU
Railway Undertaking
SCADA
Supervisory Control And Data Acquisition
SIM
Subscriber Identity Module
SLA
Service Level Agreement
TM
Traffic Management
TSI
Technical Specification for Interoperability
VBS
Voice Broadcast Service
NETWORK RAIL
Page 15 of 18
APPENDIX B:
Reference:
NEPT/ERTMS/REQ/0008
Issue/ver:
3.0
Date:
31st March 2017
LIST OF REFERENCES
Note: Unless otherwise stated, reference should be made to the most recent authorised version of the
document.
[RD1]
National ETCS Requirements Management Strategy, NEPT/ERTMS/REQ/0003
[RD2]
ETCS Requirements Management Plan, NEPT/ERTMS/REQ/0001
[RD3]
ETCS – Baseline 3 - System Requirements Specification, NEPT/ERTMS/REQ/0005
[RD4]
ETCS – Baseline 3 – GB Trackside Subsystem Requirements,
NEPT/ERTMS/REQ/0006
[RD5]
ETCS – Baseline 3 – GB Onboard Subsystem Requirements,
NEPT/ERTMS/REQ/0007
[RD6]
ETCS – Baseline 3 – GB Operational Subsystem Requirements,
NEPT/ERTMS/REQ/0009
[RD7]
COMMISSION REGULATION (EU) 2016/919 of 27 May 2016 on the technical
specification for interoperability relating to the ‘control-command and signalling’
subsystems of the rail system in the European Union
[RD8]
Baseline 3 Release 2 (TSI CCS Annex A set of specifications #3, which includes
GSM-R Baseline 1 (EIRENE FRS V8.0.0 & SRS V16.0.0))
[RD9]
ERTMS Programme Glossary of Terms, ERTMS/PGM/D0115
[RD10] ERTMS Reference Design, NEPT/ERTMS/SYS/0032
[RD11] National ETCS Requirements Consolidation Process, CCMS: 64883540
[RD12] ETCS Requirements Assurance Statement, CCMS No: 65842637
[RD13] ETCS Requirements Change Management Process, NEPT/ERTMS/REQ/0013
[RD14] ERTMS Reliability Specification NR/AM/SA/SPE/00147 Issue: A07.
[RD15] Guidance Note 'GSM-R Availability Assessment for ETCS Traffic',
NEPT/ERTMS/HBK/0402 version 1.1
[RD16] Guidance Note 'GSM-R Coverage Assessment and Cell Planning',
NEPT/ERTMS/HBK/0403 version 2.1
[RD17] Guidance Note 'GSM-R Capacity Assessment for ETCS Traffic',
NEPT/ERTMS/HBK/0401 version 1.1
[RD18] Operational Concept for ERTMS, RSSB-ERTMS-OC, Issue 2
[RD19] NR Security Assurance Framework, NRT/SY/2015/036
The TSI and Class 1 Specifications are obtainable from the European Union Agency for Railways.
NETWORK RAIL
Page 16 of 18
APPENDIX C:
Reference:
NEPT/ERTMS/REQ/0008
Issue/ver:
3.0
Date:
31st March 2017
OPTIONS LOOKUP TABLE
Note: (W) indicates a Working Version and not a Release Version.
Topic ID
Topic Title
Version
A
Continuing Movement
3.0
B
Operation in Possession
6.0
C
End of Mission
2.0
D
Train Dispatch
2.0
E
Stopping at an End of Authority (EOA)
3.0
F
Applying Speed Restrictions
3.0
G
Starting
3.1
H
Permissive Moves
3.0
I
Attaching and Detaching
3.0
J
Stopping Trains
3.0
K
Changing Driver ID and TRN mid-journey
3.0
L
ETCS Route Release
3.0
M
Neutral Sections, Traction Changeover and Pantograph Management
5.0
N
Entering ETCS
3.0
O
Exiting ETCS (Leaving Level 2 and 3)
3.0
R
Boundaries
4.0
S5
Degraded or Abnormal Working, Route Not proved
5.0
T
Inhibition of Transition
5.0
U
System Controls for Issue of Movement Authorities
4.0
V
Provision of Routing Information
5.0
Y
Miscellaneous
4.0
Z
Non trackside
2.0
AA
Consistent Provision of Lineside Signage
4.0
CC
Utilisation of Packet 44 in ETCS Areas
3.0
EE
Key Management
2.7
HH
Train Maintenance and Testing
4.0
II
Balise Configuration Rules
4.0
JJ
Level Crossing Operation and Protection
5.0
KK
Transmission of National Values
3.0
LL
Use of Track Condition Functions
5.0
NETWORK RAIL
Page 17 of 18
APPENDIX D:
Reference:
NEPT/ERTMS/REQ/0008
Issue/ver:
3.0
Date:
31st March 2017
AREAS FOR DEVELOPMENT
No.
Issue
Description
1
Reference Design
The Specification Requirements need to
be updated to incorporate the latest
requirements from the Release Versions
of the Reference Design Topics Z and EE,
which are identified as (Provisional).
2.4
2
Automatic Train
Operation
When Automatic Train Operation has been
developed and European standards
published further requirements may need
to be included.
2.4
3
ETCS Level 3
When ETCS Level 3 has been developed
and European standards and GB
application rules published further
requirements may need to be included.
2.4
4
Remaining
comments from
Industry Review
Remaining comments from the Industry
review need to be closed out.
3.0
5
Operational Test
Scenario input
There will be consequential amendments
required arising from the output from the
OTS work.
3.0
NETWORK RAIL
Identified
in version
Closed in
version
Page 18 of 18