Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study A study for Merseytravel by MDS Transmodal with GHD, JLL & Gleeds Final Report April 2015 Ref: 215013r11 CONTENTS EXECUTIVE SUMMARY ................................................................................................................. 1 1. INTRODUCTION .................................................................................................................... 3 2. HISTORY AND PROSPECTS ..................................................................................................... 4 3. THE CANADA DOCKS BRANCH ITSELF ..................................................................................... 9 4. INFRASTRUCTURE OPTIONS AVAILABLE ............................................................................... 11 5. POTENTIAL TRAIN MOVEMENT SCHEDULES ......................................................................... 14 6. LONGER TERM ASSOCIATED DEVELOPMENT ........................................................................ 19 7. CONNECTIONS TO NETWORK RAIL AND MODE OF OPERATION ............................................ 20 8. CAPITAL CONSTRUCTION COSTS .......................................................................................... 26 9. LAND ASSEMBLY ................................................................................................................. 27 10. OPERATIONAL COSTS .......................................................................................................... 29 11. OTHER COSTS AND BENEFITS............................................................................................... 31 12. OVERALL COMPARISON ...................................................................................................... 32 13. CONCLUSION AND NEXT STEPS............................................................................................ 33 APPENDIX 1: APPENDIX 2: APPENDIX 3: APPENDIX 4: APPENDIX 5: APPENDIX 6: APPENDIX 7: INFRASTRUCTURE LAYOUT DRAWING ................................................................... 37 POTENTIAL TRAIN MOVEMENT SCHEDULE TIMINGS............................................... 38 CAPACITY CONTRIBUTION OF B1/B2 INFRASTRUCTURE ......................................... 43 HGV DELAY DUE TO PASSING TRAINS .................................................................... 46 CAPITAL COSTS ..................................................................................................... 50 LAND ASSEMBLY PLANS ........................................................................................ 58 JOB SPECIFICATION ............................................................................................... 62 © MDS TRANSMODAL LIMITED 2015 The contents of this document must not be copied or reproduced in whole or in part without the written consent of MDS Transmodal Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study Page 1 EXECUTIVE SUMMARY Peel Ports aspires to significantly increase rail freight traffic to and from the Port of Liverpool over the coming years – increasing from today’s daily 9-12 departures (with 9-12 arrivals) to 38 daily departures (with 38 arrivals). This would include rail-connecting the Canada Dock and the southern zone of the port, which currently has no rail connection. We estimate that the rail freight potential for the Canada Dock area is likely to be around 3 trains departing per day (with 3 arrivals). Historically the Canada Dock branch line directly linked the wider rail network (via the Bootle Branch line) to the Canada Dock area with a terminal to the East of Regent Road. See Figure 1. This disused route includes a tunnel and 2 disused road bridges. It has been suggested that rail-connecting the Canada Dock area may be best achieved by reinstating the Canada Dock branch line, either with a terminal to the East of Regent Road (as previously existed), or by curving to the North and running to the west of Regent Road in order to accommodate modern-length trains (A in figure 1). An alternative approach to rail-connecting the Canada Dock area is to build tracks from the existing reception sidings in the Alexandra Dock area, to the south – also using a route to the west of Regent Road (B in figure 1). If this re-instated Canada Dock branch line route is not required, the land associated with it can be released for other uses. There is also the option to not build any new infrastructure in the Canada Dock area. In order to cater for rail traffic, cargo could be transported within the port by rubber-tyred (road) vehicles between an existing or new rail terminal in the Alexandra Dock area, and the Canada Dock area. For each option we have produced high level estimates for construction, land assembly and operational costs, impacts on other port users (e.g. blocked roads and gates as trains pass) and have considered other impacts including traffic, environmental, local economy, to arrive at an overall Net Present Value (NPV) for each option (using the DfT WebTAG’s suggested 60 year appraisal period and 3.5% discount rate for public sector projects). Cost comparison for options A3, B2 and C. £ million in NPV Cost component Construction Land values HGV delay cost (road access blocking) (NPV) Operational costs (NPV) Total (NPV) 30/04/15 16:09 Our Ref: 215013r11 A B C 22.7 8.6 2.1 6.4 39.7 10.8 0.2 6.4 17.3 50.5 50.5 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study Page 2 A: Re-instating the Canada Dock branch line, curving to the North and running to the west of Regent Road. Note that the option of terminating directly to the East of Regent Road is discarded because the allowable train lengths would be too short. B: Build tracks south from the existing Alexandra Dock rail freight sidings C: Build no new infrastructure in the Canada Dock area and rely on within-port road shuttling of cargo between the Canada Dock area and a rail terminal in the Alexandra Dock area to cater for rail freight potential. If the Canada Dock area is to be rail-connected, approaching from the existing sidings in the Alexandra Dock area (B) is therefore a much cheaper option than re-instating the Canada Dock branch (A). Re-instating the Canada Dock branch is therefore not required, and the land it would require east of Regent Road (which includes land in the ownership of HCA) can be released for other non-rail uses without fear of compromising the future rail potential of Liverpool port. The Canada Dock area should instead be reconnected from the existing rail facilities in the Alexandra Dock area once Canada Dock rail freight potential approaches around 2 trains (into the port and then departing) per day. To offer rail capability to the southern docks zone in the short term, rail terminal capacity could be made available to all users (open access) to allow potential rail freight in the Canada Dock area to use rail with a short within-port road journey. We have assumed that the section of Regent Road affected by the new rail route would become unadopted, and become part of the port estate. Regent Road remaining public while building a railway in its western margin such that there would be train, HGV, pedestrian, car and bicycle movements along the same route would present increased safety, construction and operational costs. The case for rail-connecting the Canada Dock area is much harder to make if Regent Road does not become part of the port estate. 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study 1. Page 3 INTRODUCTION Rail access to Liverpool Docks is now limited to the Bootle branch line, connecting the mainline at Edge Hill with the docks adjacent to Alexandra Docks. However, in the past, Liverpool North Docks was also connected to the mainline via branches from Canada Dock and Princes Dock (further south) while the whole length of the North Docks was connected by a railway that ran the length of Regent Road. Peel Ports’ plans for the Docks1 assume a substantial increase in the volume to be carried by rail. City region stakeholders and local communities are also expressing a desire to see modal shift from road to rail. Given these aspirations, the issue has arisen as to whether the access from Canada Dock should be at least protected from development that would prevent its reopening. The Canada Dock branch line is, in this context, defined as the length of railway line between Kirkdale and the route of the dock railway that used to run the length of the Liverpool North Docks. It was abandoned many years ago. Part of the route now lies under a deep layer of fill, the remainder being in tunnel or as part of a brownfield site that is currently the subject of a land transaction. Various interested parties need to establish whether there is (or could be) a case for reestablishing this route. Our method to assess the case for protecting the route and described in this report has been to: 1. Forecast future potential demand for rail freight to/from the southern port zone 2. Consider infrastructure options for rail-connecting the Canada Dock area (the southern zone) 3. Estimate construction and operational costs of each of a number of options 4. Include impacts on other port users (e.g. blocked roads and gates as trains pass) 5. Consider other impacts (traffic, environmental, local economy) 6. Compare overall costs of each option 7. Conclude whether there are any realistic circumstances whereby reinstating the Canada Dock branch might be the best option Our conclusions take into account as to whether reopening the Canada Dock branch would impact on Peel Ports’ ability to reach its targets for rail volumes. 1 Mersey Ports Master Plan 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study 2. Page 4 HISTORY AND PROSPECTS Figure 1 describes the geography of the area. The line leading to the Canada Dock branch line (A) was built from Tuebrook on the Liverpool – Manchester railway in 1861 and connected the Liverpool North Docks with the mainline system, supplementing the line that already linked Edge Hill with Princes Dock (south of the map). 20 years later, an extension of this line was made from Kirkdale to reach Alexandra Dock (B) in Bootle following a shallower gradient and it is this link that continues to be used. The Princes Dock branch closed in the early 1970s. The Canada Dock branch line (A) closed in 1982. All three branches had direct links with a dock railway that ran the length of the North Docks until around 40 – 50 years ago. The current facilities in the Alexandra, Gladstone and Seaforth Docks areas cater for coal, biomass, steel and scrap metal trains. They can also cater for container trains although there are currently no services. On weekdays, there are typically 9-12 departures from Liverpool port. These are typically: 5-6 coal trains to Fiddlers Ferry or Ratcliffe power stations 4-5 biomass trains to Ironbridge a weekly steel train from Sheffield an occasional scrap metal train. The present double track Bootle branch line itself is capable of handling 2 trains per hour per direction, has a W10 loading gauge (capable of handling standard 9’6” high ISO containers on metre high (standard) wagons) and RA10 axle weight standards (the heaviest available). A Chord (Olive Mount chord) was replaced some years ago so that trains can now move directly eastwards onto the mainline towards Earlestown. There is currently a capacity to forward 2 freight trains per hour per direction along the mainline and there is a reasonable expectation this will be protected after passenger service frequencies rise once the current electrification and Northern Hub schemes are completed. Network Rail’s long-term plans (as stated in their Freight Market Study2) are to cater for approximately 30 train paths per day per direction to and from the port, and they are aware of Peel’s aspirations for 38 trains per day per direction. When it becomes clearer in the future that Peel’s aspirations are approaching fruition, Network Rail are likely to adjust their plans to cater for this demand. See section 7.7 for more detail on capacity. We therefore believe that the rail network should be able to accommodate the Port’s long term forecasts of being able to generate up to 38 trains per day per direction. These 38 daily train departures reflect the long term rail freight potential of the port of Liverpool as a whole. This potential was forecast in a separate report for Peel Ports. There is an implicit 2 www.networkrail.co.uk/improvements/planning-policies-and-plans/long-term-planning-process/market-studies/freight/ 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study Page 5 assumption that additional rail infrastructure would be required within the port estate to cater for this level of traffic. These 38 daily train departures include realising the rail potential of the Canada Dock and southern zone area (south of Alexandra Dock), along with the additional infrastructure required. 30/04/15 16:09 Our Ref: 215013r11 To Seaforth and Liverpool 2 Existing freight railway Figure 1: Map describing the geography of the area Rail A1 / B1 Rail A2/A3 Rail B1/B2 w ngs sidi New B2: Rail Both A2/A3 & B1/B2 Gladstone Dock New Level Crossing A roads ver sso cro ith Coal & biomass t oin id-p at m B Alexandra Dock EMR - scrap orth A3:N A2/ Seatruck Roro ferry e Liv y Rd ds Lee Derb N Scrap terminal e Bran ch Bank Hall A St field Bank Disused rail terminal St hall Bank br ck o D da Cana n hall L Bank 500 m Boo tl gs Canada Dock l ana ol C th sd 3:Sou A2/A rpo d nt R Rege New Steel Terminal 0 Rd s sdg Cargill idge d Stanley R Langton Dock r r's B Mille nn l tu rai ed us Dis i ne l h anc l i ne el Kirkdale Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study Page 7 The Port’s expectation is that this cargo will be made up of biomass, coal and container trains plus a handful of scrap, steel and automotive trains. Two of the key drivers of this growth are due to two major investments. These are: The Liverpool2 (L2) container terminal, which will be able to accommodate the highest capacity container vessels in the world (not necessarily at full draft) and raise port volumes to around 1.3m containers per annum. Because the Port’s ‘reach’ is expected to be national and not just regional, some 15% of throughput can be expected to be by rail (around 200,000 units per annum) which corresponds to some 15 trains per day per direction. A large biomass terminal whose throughput will be entirely by rail to power stations (approximately 12 departing trains per day, matched by empty return trains). In addition we expect: residual coal traffic, unlikely to be run-down until around 2024, but (say) 3 departing trains per day in the long term, (matched by empty return trains). Steel trains (1 per day departing) via a new steel terminal in Canada Dock, replacing one located at Gladstone Dock. Scrap trains carrying 15 – 20% of the Port’s anticipated throughput of 2.5 – 3m tonnes per annum (2 – 3 trains per day arriving (with the empty return trains departing)). All these trains will pass as far east as Earlestown. Beyond Earlestown, some will go north and some south along the West Coast Main Line and some will continue eastwards into Yorkshire. Most of this potential rail traffic passes through Alexandra Dock and docks further north, and this will remain the case. However the steel terminal is relocating to the Canada Dock area, with potential for 1 train departing per day. Large volumes of scrap metal traffic are processed in the Canada Dock area too (700,000 tonnes in 20143). If we assume that in future around half the scrap will pass through docks south of Alexandra Dock then that reflects up to 2 scrap trains per day per direction. In addition, long term redevelopment of the land between Regent Road and Derby Road as a port linked distribution park can be expected to eventually accommodate around 150,000m2 of buildings (say 200,000 pallet capacity). If devoted entirely to maritime traffic that would generate around 100,000 container arrivals per annum and, if sharing the same 15% rail share as for the container terminal, this traffic could generate another 2 train loads per day per direction of containers. 3 Source: Peel 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study Page 8 This distribution park traffic could either be loaded locally onto trains at a small intermodal terminal in the Canada Dock area, or could be moved by rubber-tyred vehicles to the intermodal terminal at Seaforth. For the purposes of designing rail layouts, we have assumed that any rail traffic generated by a distribution park between Regent Road and Derby Road would travel by rubber-tyred vehicle to the terminal at Seaforth to be loaded to a train because, overall, we expect this to be the cheaper and least disruptive option. Our rail layouts for the Canada Dock area therefore do not include an intermodal terminal. However if a small local intermodal terminal was required for a particular warehouse occupier, the designs for the main options could be added to in order to incorporate such a terminal. There may also be automotive trains in the future if the Port’s target to attract car traffic succeeds, although we have not included these in the Canada Dock rail freight potential. Taken together, we therefore estimate that the section of port south of Alexandra Docks has the potential to generate demand for around 3 trains per day per direction. Two or three local terminals would be required: one for scrap, one for steel (tracks running into a shed) and potentially one small intermodal terminal. 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study 3. Page 9 THE CANADA DOCKS BRANCH ITSELF In the event of it being reopened, the junction with the ‘Bootle’ branch at Kirkdale (Atlantic Dock junction) would need to be re-created and the track re-laid along a tunnel of around 400 metres that appears to drop around 8 metres (approximate gradient 1:60) before passing under the Leeds – Liverpool canal and emerging through a portal at the level of Regent Road that is currently beneath around 5m depth of fill, running to the south of Bankhall Street. That fill is continuous between the Canal and the site of the old rail freight terminal east of Regent Road and entirely encloses the bridge arches that carried both Bankhall Lane and Derby Road over the railway. Whether these bridges would retain their integrity if the fill was removed is unknown, as is the state of the tunnel. The length of level railway formation between the canal and Regent Road is limited to around 400m. Once length is allowed for switches to create a number of reception loops, no more than 300 metres of train length could be accommodated. Trains of this short length are costly to operate per tonne of cargo moved and are generally not viable. As a result we have not given any further consideration to a rail freight terminus east of Regent Road. This discounted option is referred to as option A1 in Merseytravel’s Specification. However it would be possible to receive trains of a competitive length if the rebuilt route crossed Regent Road and trains were brought to a halt parallel to (alongside) Regent Road. Given that cargo generating sites will be generally north of this crossing, the curve also would face northwards. To be able to operate long trains under modern conditions, a curve of 200 metres radius would be expected, requiring as a result a substantial area of land. In the event of electrification of the wider network this would imply that such overhead electrification would need to extend across Regent Road. The current connection to the Docks at Alexandra Dock involves the railway crossing Regent Road immediately beyond the point of transfer between Network Rail and Peel Ports. There is no longer a level crossing; the railway simply severs the roadway, which already limits free circulation even though the roadway is no longer adopted highway4. While a rail crossing of Regent Road in the Canada Dock area could be organised as a level crossing across an adopted road, the required curvature is such that Bankfield Street would also have to be crossed, making a highly complex arrangement. Network Rail believes the Office of Rail and Road (ORR) may take issue with the introduction of new level crossings on the public highway, whether or not the rail infrastructure was privately (Peel) or publicly (Network Rail) owned. It is therefore difficult to envisage such an arrangement without closing Regent Road and Bankfield Street to public 4 The intention is to re-instate this level crossing. This would be in conjunction with the planned dualling of this part of the branch line. The level crossing would serve part of the LIFT Zone (port-centric warehousing). One of the units on the other side of the level crossing is currently being built. 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study Page 10 traffic. It is Peel Port’s aspiration under its Master Plan that Regent Road is absorbed within the Dock Estate to better serve the re-development of the Regent Road – Derby Road corridor as an employment site for distribution (150,000m2 of distribution sheds would be expected to employ around 1,500 people). In that event there would be no need for a level crossing because both Bankfield Street and Regent Road could be closed at this point and road access to the port area north of Bankfield Street would be via Millers Bridge Road. For trains entering the Port through a re-instated Canada Dock branch line, the operational connection between Network Rail’s network and that of Peel Ports could be at the Regent Road end of the route because the length of the branch (approximately 700m from the connection to the Bootle branch at Kirkdale and the level crossing over Bankfield Street) exceeds the length of the trains likely to be serving the Canada Dock area. The rear of an arriving train brought to a halt at a level crossing across Bankfield Street would be clear of the junction with the Bootle branch. However for departing trains, as we shall discuss in section 5, a train held on tracks alongside Regent Road awaiting release onto the Network Rail network will block several road accesses into the Docks which would be unacceptable. It would be essential that the Port is able to forward a complete train through the Regent Road and Bankfield Street level crossings onto the branch line towards Kirkdale at a time of its choosing. This means the branch between Bankfield Street level crossing and Kirkdale must be under the Port’s control and the connection agreement between Peel ports and Network Rail must be adjacent to the junction with the existing Bootle branch near Kirkdale station. While it would be possible for Regent Road to remain a public road and for there to be level crossing arrangements that are acceptable for ‘uncontrolled’ public access and for the crossing to be operated by Peel Ports, such an arrangement would be most unusual. This is particularly the case because the crossing would have to cater for several different vehicle manoeuvres (Regent Road North to Regent Road South, Regent Road South to Bankfield Street and Regent Road North to Bankfield Street and the reverse). 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study 4. Page 11 INFRASTRUCTURE OPTIONS AVAILABLE The infrastructure options to provide rail connectivity to the Canada Dock area that we have considered are: A1: Re-open the Canada Dock branch with a direct route towards Regent Road, terminating east of Regent Road. This would require restoring the tunnel and rebuilding (or restoring) 2 roadover-rail bridges (Bankhall Lane and Derby Road). A2/A3: As A1 but instead of terminating east of Regent Road, build a 200m radius north-facing curve crossing Bankfield Street and Regent Road towards Miller’s Bridge Road (with tracks terminating some 900 – 1000 metres to the north near Miller’s Bridge Road, which is a train length plus switches allowing train splitting and locomotive return). A short headshunt south of Canada Dock would allow a new scrap terminal to be served. This option is later referred to as option A2 or A3 depending on the land ownership of Regent Road. B1/B2: Instead of reopening Canada Dock Branch, replace the Dock railway alignment from reception tracks at Alexandra Dock for some 1500 metres southwards to Canada Dock. This would follow the same alignment as for A2/A3 above along Regent Road plus an additional 400 metres of track between Miller’s Bridge road and the current rail crossing of Regent Road. This option is later referred to as option B1 or B2 depending on the land ownership of Regent Road. C: Do nothing. This option is most simply interpreted as assuming all traffic to/from the Canada Dock area goes by road. However it would still be possible for traffic suitable for rail in the Canada Dock area to travel by rail, if it first travelled by road to an existing or adapted rail terminal in the Alexandra / Gladstone Dock area. For options A2 and B1, Regent Road is retained as a public road. For A3 and B2, the Regent Road area becomes part of the port estate, as per Peel’s aspirations in their port Master Plan. Fuller details of all the options are given in the job specification: Appendix 7 to this report. Sketches for the A and B options are described in figure 1.We have produced potential track layout designs reflecting these options. These are shown in Appendix 1. In order to produce these designs, we have considered (A2/A3) and (B1/B2) in turn from an operational perspective in order to cater for the likely demand (up to a total of 3 scrap and steel trains arriving and then departing each day). These potential train movement schedules are described in section 5. 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study Page 12 In options B1/B2, it is assumed that the existing rail route into Alexandra Docks is used. This would use up capacity in the area. In a future scenario with a significantly larger number of trains, using this capacity for Canada Dock trains could be to the detriment of other trains. The A2/A3 option has no such detrimental impact on other rail freight traffic in the Alexandra Dock area. Therefore, in order to make a fair comparison between A2/A3 and B1/B2, for the B1/B2 option we need to include some infrastructure enhancement in the Alexandra Dock area that will reflect the capacity usage of the Canada Dock trains. We believe that a fair contribution to address that additional demand would be to build an extra reception track alongside the existing route to Seaforth (to the east of the coal terminal), with a crossover at the mid-point onto the existing route to Seaforth. This can be seen in the track layout design (Appendix 1) (“B1/B2: New siding – with crossover at mid-point”). Our calculation is that the capacity contributed by this option is broadly equivalent to the capacity used (shown in Appendix 3). However we have also considered a more generous infrastructure contribution to the Alexandra Dock rail network which contributes more capacity than the Canada Dock trains would use. This involves: Double-tracking the route from the Bootle branch into the Alexandra Dock area (as per Peel’s existing plans) Continuing this extra track northwards to become a dedicated route to Seaforth which would never be blocked by the marshalling of the Canada Dock trains. This more generous infrastructure enhancement is drawn in the layout designs (Appendix 1) and has been costed as a worst-case infrastructure-cost scenario. The future daily rail freight potential for the Port of 38 trains arriving (and 38 departing) implies that the present double track Bootle branch needs in any case to be extended into the Alexandra Dock area so that trains can depart the Docks independently from trains arriving. There would be no need to create an active level crossing at this point but to instead use the width of Regent Road at that point for extra reception tracks. In the long run, these could be electrified as no cargo handling will take place near them and they could even be fenced (see long term plans for freight electrification to Liverpool2 in ‘Northern Sparks’, Rail North, March 2015). However, this arrangement would still require an internal level crossing if road vehicles are to pass southwards along the dock road that is not currently in position. This could be provided by retaining an internal road connection west of the steam pipeline and creating an inland level crossing at a skew across a new single railway line immediately south of the present crossing of Regent Road by passing under the steam pipeline within the dock estate. This will mean that the level crossing is 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study Page 13 only used by relatively infrequent short trains that could be conducted entirely by a Port operated shunting locomotive. This would be far easier to manage than one where full length trains are received from the Network Rail network over ‘public’ roads. This solution would not itself require the transfer of the full width (see below) of any current public road. Whichever option is selected, however, because there is existing plant adjacent to the current Port boundary (covering some of the width once occupied by the dock railway), the most sensible approach may be to reduce the current width of Regent Road so that a single track railway supplemented by loops can be laid, along what is presently public highway, alongside the current Port boundary. This would not affect the functionality of the road but would require fencing if public access to the highway is to be retained. 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study 5. Page 14 POTENTIAL TRAIN MOVEMENT SCHEDULES Modern freight trains within the Docks are limited to a trailing weight of around 2,000 tonnes and to a length of around 600 metres. Weight constrained trains (scrap, coal, steel etc.) will be limited to a length of around 500 metres. If bulk trains much longer than 500 metres were used, they would be very heavy and would need to be hauled by more powerful (non-typical) locomotives. These powerful locos would be required to ensure that the train could accelerate fast enough to minimise the extent to which they obstruct other faster trains on the wider network. Trains will enter and leave the Network Rail network complete but can be subdivided once within reception sidings. With the exception of the track that serves the coal terminal (and the biomass terminal that will be adjacent) none of the terminals within the Docks can be expected to handle unbroken trains, either because the individual sites within the Docks are too small or because holding long trains would block roadways essential to the circulation of Docks traffic. Reception tracks have to be more or less flat because wagons will not be attached to manned locomotives at all times. We have assumed trains of up to 510 metres trailing length + 25m for the locomotive, so that these can be split into 3 x 170 metre wagon lengths (front, middle and rear train-thirds). Such 170 metre long portions of train are typical for steel and scrap terminals. They are not too long so as to require too large a terminal area and they are not too short so that they require excessive shunting movements to process a full train. In each infrastructure option (A2/A3) and (B1/B2), we propose a train movement approach whereby port terminals are only briefly obstructed by trains and at no time are blocked by a train for more than a few minutes where possible. Apart from (A2/A3) arrival and departure, to minimise the time the various road access points are closed, all movements across the road access points to port areas are either a sole loco or a loco hauling (not propelling) a short section (one third) of train. For scrap trains, we have assumed that the steel terminal track is available to store one train-third. Similarly for steel trains, we have assumed that the scrap terminal loop is available to store one train-third and for running the loco around. For both infrastructure options (A2/A3 and B1/B2), if it was preferable for the steel and scrap terminals to be independent of each other, this could be achieved with (for example) an additional track alongside the scrap terminal loop. Train movement processes below should be read in conjunction with the track layout designs (Appendix 1). The locations are marked on these designs. 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study Page 15 5.1 Option (A2/A3) operations: Canada Dock Branch re-instatement. Movements associated with arrival, processing in steel terminal, and then departure. 1. Close Regent Road and Bankfield Street level crossings to road traffic 2. Close Cargill and new steel terminal road access 3. Cross Bankfield Street and Regent Road over level crossings 4. Just clear Regent Road with back of train and stop 5. Open Regent Road and Bankfield Street level crossings to road traffic 6. The front end of the train blocks Cargill and new steel terminal road access 7. Uncouple the back 2/3 of the train (340m of wagons) (which lies between Regent Road level crossing and the new steel terminal’s road access) 8. Haul front train-third forward into A2/A3 Northern sidings so no road access points are blocked 9. Open Cargill and new steel terminal road access 10. Run loco round and attach to northern end of rear 2 train-thirds 11. Propel rear 2 train-thirds so that the rear train third is in the scrap terminal loop 12. Split the middle and rear train-thirds by uncoupling 13. Haul the middle train-third (170m of wagons) into A2/A3 Southern sidings. Decouple 14. Attach to southern end of rear train-third and propel into the steel terminal 15. Once processed, haul this train-third into the scrap terminal loop. Decouple 16. Attach to middle train-third, haul and propel into steel terminal 17. Once processed, return the middle train-third to the A2/A3 Southern sidings. Decouple 18. Attach to front train-third, haul and propel into steel terminal. Decouple 19. Haul rear train-third to A2/A3 Northern sidings. Decouple and return to steel terminal 20. Once processed in steel terminal, haul this train-third into the scrap terminal loop 21. Propel new rear train-third and attach to middle train-third 22. Close Cargill and new steel terminal road access 23. Propel middle and rear train-thirds together northwards to attach to the front train-third in A2/A3 Northern sidings to assemble the full train 24. Conduct brake test 25. Close Regent Road and Bankfield Street level crossings to road traffic 26. Depart – crossing Regent Road and Bankfield Street up to NR boundary at eastern end of Canada Dock tunnel 27. Open Cargill and new steel terminal road access 28. Open Regent Road and Bankfield Street level crossings to road traffic These movements are described in more detail in Appendix 2 with distances and timings for each movement. 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study Page 16 We estimate the time that a train would be on-site (from the closing of Bankfield Street level crossing to road traffic when the train arrives to the re-opening of the level crossing after the train leaves) would be approximately 5 hours. Several of these movements involve the blocking of roads while the trains, train-thirds or sole locomotives pass. Appendix 4 notes each such blocking manoeuvre along with the time that the road is blocked and shows the calculations for the overall HGV delay per train. The total delay caused to HGVs is dependent on both the number of railway movements, and the level of HGV traffic across each level crossing and road access point. We have made tentative estimates of future HGV traffic volumes at each level crossing and road access point. For example for the future, we estimate 800 HGVs per day through the Seatruck gate, including some sole HGV tractors without trailers. In total, we calculate the overall HGV delay caused by one train arriving and departing to be 2 hours 40 minutes of HGV time per day. Most of this is due to the full train when fully assembled awaiting departure and conducting a brake test. This blocks both the Cargill and the new steel terminal’s road access points, during which time a queue will build up. A stationary HGV with driver on-board costs around £35 per hour (principally depreciation and driver’s wages). Therefore a 2 hour 40 minute HGV delay equates to approximately £93 in HGV cost per day, along with a decrease in reliability and a need for the space for these HGVs to queue. At public sector discount rates typically used for rail projects this would equate to a capitalised value of £0.7m. Arrival, processing in SCRAP terminal, and then departure. Equivalent movements to those described above for the steel terminal can be performed to process scrap trains. The steel terminal is used to store a train-third after processing in the scrap terminal. 5.2 Option (B1/B2) operations: Extending from existing rail terminal (Alexandra Docks area) south to Canada Dock. The movements described below relate to the less generous infrastructure contribution to the Alexandra Docks area – intended to match capacity provided with capacity used (see Appendix 3) – i.e. they do not include the double-tracking from the Bootle branch or the dedicated route to Seaforth. 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study Page 17 Movements associated with arrival, processing in steel terminal, and then departure. 1. Arrive into northern end of new reception track (to the east of the coal terminal and alongside the existing route to Seaforth) 2. Train blocks one potential road access point to a factory until the rear third is moved, and when the train is reassembled to depart. There is an alternative road access point to this factory, so we have not included HGV delays for this point 3. Split the wagons into 3 train-thirds by uncoupling 4. Run loco around and attach to southern end of rear train-third 5. Haul this rear train-third (170m of wagons) south until the back end clears the route to the steel terminal 6. Propel the rear train-third into the steel terminal 7. Once rear train-third is processed, haul to the scrap terminal loop and run around 8. Haul the rear train-third north and leave it on the route to Seaforth – adjacent to the southern end of the new reception track. Decouple 9. Return to the new reception track via the crossover at the mid-point and attach to middle train-third 10. Haul and propel into steel terminal 11. Once middle train-third is processed, haul to the scrap terminal loop and run around 12. Haul the middle train-third north and enter the new reception track 13. Crossover onto the original adjacent route to Seaforth and pull alongside front trainthird 14. Propel middle train-third to attach to rear train-third. Decouple 15. Return to the new reception track via the crossover at the mid-point and attach to front train-third 16. Haul and propel into steel terminal 17. Once front train-third is processed, haul to the scrap terminal loop and run around 18. Haul this front train-third north and enter the new reception track 19. Crossover onto the original adjacent route to Seaforth 20. Propel front train-third to attach to middle and rear train-thirds to re-form the full train 21. Run round and attach loco to southern end of train 22. Conduct brake test and depart Again, these movements are described in more detail in Appendix 2 with distances and timings for each movement. We estimate the time that a train would be on-site would be approximately 5 hours 30 minutes. Again, several of these movements involve the blocking of roads while the trains, train-thirds or sole locomotives pass. Appendix 4 notes each such blocking manoeuvre along with the time the road is blocked for. 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study Page 18 In total, we calculate the overall HGV delay caused by one train arriving and departing with the B1/B2 infrastructure to be just 12 minutes, equating to £7 in HGV cost (a capitalised value of £50,000). This is far less disruptive in terms of HGV delay than option A2/A3. This is largely because the train does not have to be re-formed and readied for departure while blocking road accesses. Arrival, processing in SCRAP terminal, and then departure. A similar operation can be performed for scrap trains. If a quicker turnaround is required, while the first train-third is being processed in the steel terminal, the loco can haul the next train-third from the reception sidings to the scrap terminal loop, so that when the steel terminal has finished with the first train-third, the second train-third can be quickly propelled into the steel terminal. Extra capacity usage at the existing Alexandra Dock terminal area is compensated for by allowing other trains to use the extra reception track when Canada Dock trains are not there. – e.g. container trains. This is discussed in more detail in Appendix 3. There appears to be space to create other sidings nearer to Seaforth for other additional container trains, so this extra siding is not using up space that would necessarily be required to cater for the forecast increase in container trains serving Seaforth. We conclude that either approach (A2/A3 or B1/B2) is operationally viable. For both options (A2/A3 or B1/B2), higher volumes of trains could be catered for by building additional sidings. 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study 6. Page 19 LONGER TERM ASSOCIATED DEVELOPMENT The re-development of the area north of Bankfield Street between Derby Road and Regent Road by the construction of around 150,000m2 of warehousing would generate some 400,000 heavy vehicle movements per annum, as follows: area available: equivalent pallet positions: vehicles/40’ containers: turnover: loaded arrivals per annum: empty departures per annum: empty arrivals per annum: loaded departures per annum: Total movements per annum Movements per day (5 day week): Movements per hour (2 shift day): 150,000m2 200,000 8,000 4 weeks 100,000 100,000 100,000 100,000 _______ 400,000 1,600 100 This length of Regent Road would become extremely busy, given there is likely to also be some 2m tonnes of steel, scrap and edible oil traffic plus freight ferry traffic in and out of the Seatruck terminal. Altogether we estimate that up to 3,000 HGV movements per day could be generated in addition to rail freight train movements and in many hours of the day there could be 200 HGV movements, all of which would be making turning movements in and out of terminals or warehouses. 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study 7. Page 20 CONNECTIONS TO NETWORK RAIL AND MODE OF OPERATION As volumes of trains rise the need for enhanced safety systems/procedures within the port will increase. If the only extra traffic were the handful of Canada Dock trains we estimate, there is an argument to retain the form of operation that exists today. However, when one takes into account the dock operation as a whole and the potential for 38 trains per day per direction there is a stronger argument for an enhanced level of control and improvement of reception and departure arrangements. 7.1 Canada Dock The connection to the Bootle Branch from Canada Dock no longer exists. Civil engineering required to reinstate the junction is considered significant, with cost estimates given in Appendix 5. No assessment of the signalling and control arrangements has been made at this time. However the proximity and complexity of the level crossing arrangements that would be required on the public highways suggest this option would present significant challenges in developing a form of protection to both road and rail users that would be acceptable. Given the risk of trespass and other safety issues, Network Rail and the ORR would consider the level crossings at Bankfield Street and Regent Road unacceptable if the roads remained public. The HGV movements across the road access points to Seatruck, Cargill and the new Steel terminal would generally be gate controlled. For HGVs arriving along the road the simultaneous movement of a train section would be self-evident. The gates could all be equipped with sensor equipment so that exiting HGVs could be briefly held in the event of a passing train section. Such an environment with train movements, many HGVs and HGV turning movements would not be well suited to also catering for a large numbers of pedestrians and cyclists. 7.2 Alexandra Dock The existing layout provides for the double track Bootle Branch to run through the Alexandra Dock Tunnel where it becomes a single line. The single to double track connection is shown in the Network Rail record as trailable sprung points configured for the departure direction and trailed when entering the port. The double track section and the beginning of the single track section are under the control of Edge Hill Signal Box. The Bootle Branch is operated using track circuit block principles with two aspect signalling. The single line within the dock is under the control of the Person In Charge (PIC). Operation within the dock appears to be through manual instruction and hand point operation. A level crossing at Regents Road (AOCL Type – Automatic Open Crossing Locally Monitored) is shown on the Network Rail Records but is out of use with the road blocked off adjacent to the railway line. Track circuit controls are provided locally for the operation of the level crossing. 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study Page 21 Trains arriving at the Dock are signalled up to a Stop Await Instructions board by the Network Rail Signaller. Track circuit controls and indications are provided to Edge Hill Signal Box to prove the absence of trains on the approach to the stop board. Movement authority into the dock is granted verbally by the Person in Charge. Trains departing the dock require the Person in Charge to obtain a Line Clear release from the Network Rail Signaller before verbal movement authority can be given allowing the train to advance to ML62 signal at Bootle Junction. The existing access arrangements are only suitable for low volumes of traffic and slow speed movements. 7.3 Creation of Reception and Departure Roads The creation of Reception and Departure Roads under the control of the Person in Charge would require re-designation of the lines, relocation of the control boundary and revision to the local operating procedures through negotiation and agreement with Network Rail. Additional controls and indications would be required to inform the Person in Charge that the route up to ML62 Signal and its overlap is clear. Trains arriving at the dock could do so under the same method as exists today though agreement on control boundaries and adaptation of the local instructions would be required. Maintenance boundaries associated with the infrastructure assets do not need to align with the control boundaries but would need to be agreed. 7.4 Mode of operation within the dock Low volumes of train movements at slow speeds are commonly managed through manual operation and verbal movement authority. As the volume of train movements within the dock increases, exacerbated by the need to split and join trains, manual operation becomes increasingly time consuming and unsafe. Careful consideration would need to be given to determining the appropriate level of automation of point operation and control of movement authority to ensure train movements are made efficiently but safely. 7.5 Segregation of road traffic from train movements As the volume of trains increases the risk of collision with road vehicles will increase. It is considered likely that the adopted roads (Regent Road and Bankfield Street) would need to be taken back into port control and conflict management employed in a form of level crossing control to protect movements on road / rail crossing points within the port implemented. The proximity of dock access points and the length of trains being manoeuvred make it likely that crossings may be required to close in sequence or simultaneously. This would form a constraint on how train movements are 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study Page 22 authorised within the dock area and the locations that they are authorised to move between. If this is not under some form of signal control system then local operating procedures would need to be developed, informed by risk assessment where appropriate, to ensure safe movements of train and lorry are able to be made whilst maintaining efficiency and performance within the dock. It may be necessary to define “block sections” through which trains are authorised to move and within which conflicts with the train movement are prevented. 7.6 On-site shunter locomotive method of operation in the Canada Dock area Once the intensity of train movements increases beyond a threshold, instead of using expensive main-line locomotives to shunt trains and train-sections within the Canada Dock area, a more efficient option may be for within-port movements to be hauled by an on-site shunter locomotive. This would free up the main-line locomotives to depart soon after arriving with a different set of wagons. This could be an added service that Peel Ports supply to the rail freight sector for an appropriate fee. Peel Ports could either purchase a shunter themselves or hire one through a spot hire company.. Alongside implementation of a “Rail Traffic Management System” within the port’s rail network, this would enable equitable treatment of freight train operators using the port (currently two freight operators DB Schenker and GB Railfreight) rather than the current situation whereby DB Schenker informally manage operations for all operators. This is only an efficient method of working if there is sufficient rail traffic at the port for there to be a fully formed train waiting to depart soon after a main-line locomotive arrives, such that freight train operators can achieve better and more efficient usage of their main-line locomotives. Using an on-site shunter opens up the possibility of electrification of the Bootle branch - into the Alexandra reception sidings, from which point the on-site shunter(s) can haul the trains and train sections to their final destinations within the port. There are plans for electric locomotives with “last mile” diesel capability (i.e. incorporating a low power diesel engine) such as the Class 88s ordered by Direct Rail Services. These hybrids open up the possibility of running “principally-electric” trains to Alexandra Dock reception sidings even without electrifying the Bootle branch line, by relying on the low-power diesel engine between Alexandra Dock and the recently-electrified main line (Chat Moss route between Liverpool and Manchester). However journey times along the non-electrified Bootle branch would be significantly longer due to relying on the low power diesel engine. In principle, in the absence of a dedicated on-site shunter, it would be possible to use these hybrids as on-port shunters, as main-line diesel locomotives are now. However away from electrified lines, they are low-powered and expensive assets: not ideal for conducting such shunting operations. The volumes of traffic in the Canada Dock area will be sufficiently low to be serviced by one on-site shunter, which may also spend some time in other parts of the port, when not required in the Canada Dock area. 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study Page 23 In the Canada Dock area, this on-site shunter could operate an arrangement similar to the tram management system on Manchester Metrolink. Each tram operates independently – controlling level crossings to give it priority as it passes. 7.7 Capacity The potential train movement schedules in section 5 describe a movement schedule that takes approximately 5 hours (option A2/A3) or 5 hours 30 minutes (option B1/B2) between arrival and departure for each train. This allows sufficient time for 3 trains to arrive and then depart per day. For option B1/B2 the extra infrastructure required to be built in the Alexandra Dock area is discussed in Appendix 3. If more than 3 trains (to arrive and then depart per day) were required in the Canada Dock area, additional infrastructure (for example additional loops or a small intermodal terminal) could be built. There are also capacity constraints on Network Rail’s wider network. On the Bootle branch line, there is capacity for 2 trains to run per hour in each direction5. This is confirmed in practice because trains do sometimes arrive within 30 minutes of each other (and similarly sometimes depart within 30 minutes of each other)6 – both in terms of timetabled timings and actual timings along the Bootle branch route. This is despite the current low volume of trains. 2 trains per hour per direction is just sufficient capacity to cater for 38 departures per day, if the trains could be organised to arrive at a consistent rate throughout the day. To provide more capacity and therefore flexibility (to better integrate with timetabling requirements on the wider network) and robustness, Network Rail plan to improve the Bootle branch line-speed7, and capacity (by adding intermediate signals in each direction8 and dualling the route into the Alexandra Dock reception sidings9), which is entirely independent of the reopening of the Canada Dock Branch. Whether the trains leave the Bootle Branch at the existing Regent Road level crossing to Alexandra Dock (B1/B2), or at a re-instated Atlantic Dock junction directly to the Canada Dock area (A2/A3) makes little difference to the branch line capacity. 5 Page 7 of Strategic Freight Network Steering Group: Trans-Pennine and Northern Network Rail, Dec 2014 6 Source: MDST analysis of actual timings of trains in and out of Liverpool port 7 Page 8 of Strategic Freight Network Steering Group: Trans-Pennine and Northern Network Rail, Dec 2014 8 Page 7 of Strategic Freight Network Steering Group: Trans-Pennine and Northern Network Rail, Dec 2014 9 Page 6 of Strategic Freight Network Steering Group: Trans-Pennine and Northern Network Rail, Dec 2014 30/04/15 16:09 Our Ref: 215013r11 Ports Freight Capacity. Ports Freight Capacity. Ports Freight Capacity. Ports Freight Capacity. Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study Page 24 Beyond the Bootle branch, trains reach the route towards Earlestown and Manchester (the Chat Moss route). Network Rail’s “Northern Hub” scheme involves significantly more passenger trains along this route. There is therefore a danger that capacity may become limited for freight trains to and from Liverpool port. However we have analysed a Northern Hub Indicative Train Service Specification (ITSS)10 from Network Rail along the Chat Moss route. This included 2 paths per hour per direction between Liverpool port and Earlestown. Figure 2 describes this proposed train schedule, with the freight paths highlighted. More recently, in their North of England Programmes (Northern Hub and North West Electrification) Network Rail have only considered 1 freight train path per hour per direction between the port and Earlestown (for the West Coast Main Line), but the Northern Ports and Transpennine Freight Study will also be testing the robustness of options required for 2 freight train paths per hour per direction against the full North of England service specification (known as Configuration State 7). It is easier to include freight paths if these paths are part of the timetabling exercise from the beginning, rather than trying to fit additional freight trains into a timetable optimised around passenger services. Network Rail’s long-term plans (as stated in their Freight Market Study11 for 2043) are to cater for approximately 30 train paths per day per direction to and from the port, and they are aware of Peel’s aspirations for 38 trains per day per direction and have agreed to consider it as a scenario as part of the Liverpool City Region Strategic Rail Study. When it becomes clearer in future that Peel’s aspirations are approaching fruition, Network Rail are likely to adjust their plans to cater for this demand. We therefore believe that the rail network should be able to accommodate the Port’s long term forecasts of being able to generate up to 38 trains per day per direction (i.e. 2 per hour x 19 hours). The Liverpool City Region’s Long Term Rail Strategy (Summer 2014) represents a long term vision for the region including the possibility of re-opening the Bootle branch line to passenger trains serving new stations. If this were to happen, there may be a need for further infrastructure enhancement to improve capacity to cater for this mixed use. 10 ITSS 06/12/12 (Modified) (Version 5) 11/03/13. A later version (CS7 ITSS. PROPOSED TO IPG 07 NOVEMBER 2013. (SUB GROUP VERSION 28.10.13) ) also included these 2 paths per hour per direction between Liverpool port and Earlestown 11 www.networkrail.co.uk/improvements/planning-policies-and-plans/long-term-planning-process/market-studies/freight/ 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study Page 25 Figure 2: Northern Hub proposed train schedule for one hour with Liverpool port freight paths shown in red 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study 8. Page 26 CAPITAL CONSTRUCTION COSTS Gleeds has provided estimates of the capital construction costs for options A3 and B2. The breakdown of these costs is shown in detail in Appendix 5. The results are: £23m for A3: Reinstatement of the Canada Dock branch with curve and route alongside Regent Road. £11m for B2: Access from existing Alexandra Dock area, providing one new reception track in Alexandra dock (sufficient capacity to compensate for the extra Alexandra dock area rail capacity used) £18m for B2b: As B2 but with generous infrastructure provision: double-tracking the route from the Bootle branch and providing a dedicated new track to Seaforth (generous capacity to compensate for the extra Alexandra dock area rail capacity used) These costs do not include land values – see section 9. The estimate for A3 is tentative because the state of the tunnel under Kirkdale and the road bridges (Bankhall Lane and Derby Road) is not clear. This estimate assumes the road bridges have to be rebuilt. A best-case scenario whereby the existing bridges were in a good condition and did not need rebuilding may reduce costs by up to £3m. However an optimistic view of the state of the tunnel has been taken with little structural work required to the tunnel. As the state of the tunnel is unknown, the costs could be much higher – up to say £7m more expensive in a worst case scenario. These costs do not include the cost of the terminals themselves. These terminal costs are common to options A2, A3, B1 and B2. For option C (no direct rail access to the Canada Dock area), there would also be costs associated with either adapting an existing terminal (e.g. the EMR terminal), or creating a new terminal in the Alexandra Dock area if any rail potential demand in the Canada Dock area is to be satisfied. On-going maintenance costs for the rail-connecting options are not included. Having the equivalent traffic going by road to/from the Canada Dock area also involves maintenance costs due to wear and tear on the roads. 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study 9. Page 27 LAND ASSEMBLY In relation to delivery of the options considered within this report JLL has undertaken an analysis of the relevant land ownerships that would be affected by each option and has considered the indicative land assembly costs associated with each of these options. Plans showing the relevant land required to facilitate options A1 and A2/A3 are included at Appendix 6. In relation to the land that would be required to deliver options within the Port of Liverpool estate and the public highway, we have consulted with Peel Ports and the highway authorities of both Liverpool City Council and Sefton Council, to establish respective land ownerships. For all other land ownerships required to deliver the options, ‘on line’ Land Registry searches have been undertaken to establish the ownership. The approach adopted in relation to the calculation of land assembly costs specifically excludes any land assembly costs associated with land within the ownership of Peel Ports or highway land within the control of Liverpool City Council or Sefton Council. The justifications being: that the economic benefit of the introduction of this heavy rail link supports the growth of Superport and the Port of Liverpool, which are key economic drivers for the City Region; and the environmental benefits (including reduced road congestion) of encouraging a switch from road to rail. Regent Road and Bankfield Street are adopted highways, and are unregistered, and as such we are unable to comment upon whether there are no encumbrances, restrictions, easements or other matters of an onerous nature, which would have a material effect on the deliverability of the options reliant upon use of the public highway. We recommend that verification be obtained from lawyers representing Liverpool City Council and Sefton Council. Set out in the table below is the indicative third party land assembly costs associated with the delivery of Options A1 and A2/A3. As the balance of the land required to deliver the options is in either Peel Ports or local authority ownership (Options A2/A3, B1 and B2) no land assembly cost has been included for these land interests for the reasons set above. This Peel Ports or local authority land in question relates to the potential rail route on the western side of Regent Road. In arriving at our assessment of indicative land assembly costs we have had regard to recent comparable land transactions in the Merseyside area and have adjusted these to reflect the proximity of the land in question to the Port of Liverpool. Where sites contain operational buildings we have included an additional allowance within the overall land assembly costs to take account of these. 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study Page 28 Indicative third party land assembly costs associated with the delivery of Options A1 and A2/A3 Option Number of registered legal interests Approximate total site area Ha (Acres) Approximate site area required for rail infrastructure Indicative land assembly cost* A1 5 3.80 (9.44) 1.31 (3.24) £2,500,000 A2/A3 9 6.76 (16.73) 1.04 (2.57) £8,560,000 *Assumes total site area acquired taking into account both land and buildings where applicable. It is worth highlighting that the indicative land assembly costs do not take into account the costs of disturbance or business relocation / extinguishment costs that may apply in relation to the delivery of each option as this goes beyond the scope of this study. Clearly, the impact of the introduction of a heavy rail line on affected existing business operations could result in substantial disturbance / relocation/ extinguishment payments being justified. Incorporating these would increase the land assembly costs. However to balance this, the total land area associated with each affected site would not necessarily be required to build the rail routes. There also may be some flexibility over the design of the curve for options A2/A3. For example a tighter curve could potentially be built that would reduce the impact on the land north of Bankfield Street. 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study 10. Page 29 OPERATIONAL COSTS The operational rail costs associated with options A3 and B2 are similar. Option C (do nothing) has zero capital costs if all the traffic travels by road. However for traffic that is suitable for rail, travelling by road instead incurs additional operational cost depending upon the length of haul. For such traffic that is suitable for rail, there is a halfway house option: to travel by road to an existing or adapted rail terminal in the Alexandra / Gladstone Dock area, and we have estimated that cost. The EMR scrap metal terminal may be an appropriate choice of existing terminal that could be used for such operations. Terminal operators that have available capacity are required by law to allow third parties to use their terminals on request. The EMR terminal has 3 sidings and low traffic volumes (less than one train arriving and then departing per day). Assuming Peel were able to make changes to EMR’s lease, they would be able to require that the terminal becomes an open access terminal, serving both the existing EMR rail traffic and traffic from the Canada Dock area. This should not affect EMR’s ability to use the terminal. In such circumstances, the capital costs for option C would be small. However the additional operational costs per tonne would be significant as compared to options A3 and B2. A daily train (in one direction - assuming an empty return) typically represents the capacity to move around 250,000 tonnes per year. Internal road haulage and double-handling would cost around £2.70 per tonne. Therefore the operational cost of transferring a daily train of cargo between the EMR sidings and Canada Dock by road would be around £675,000 per year. The equivalent operational costs for A3 and B2 using rail would be around an eighth of this: around £85,000 per year per daily train (in one direction - assuming an empty return) based upon one internal shunting locomotive, fuel and staff costing £250,000 per annum. The operational costs of catering for the 3 daily trains (arriving and then departing) we are considering here can be assumed to be 3 times the cost for a single daily train arriving and then departing. 10.1 Net Present Value (NPV) In order to compare the operational costs of option C to the capital costs of options A3 & B2, ongoing operational costs over future years need to be added together to generate a Net Present Value (NPV). To make this calculation requires a defined appraisal period - over which the comparison should be made. It also requires a discount rate to be defined. 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study Page 30 The DfT’s WebTAG (Web-based Transport Analysis Guidance)12 suggests that a typical appraisal period for long term public sector infrastructure should be 60 years after scheme opening, with a discount rate of 3.5%. This means that a project saving £1 million (real terms) every year for 60 years, opening 1 year in the future (to represent construction time) is worth £25 million in NPV. Therefore an annual operational cost of £675,000 for one daily train (arriving and then departing) represents an NPV (long term public sector infrastructure) cost of £16.8m. For 3 daily trains (arriving and then departing), the NPV cost is £50.5m. Similarly an annual operational cost of £85,000 represents an NPV (long term public sector infrastructure) cost of £2.1m. We have used this long term public sector infrastructure approach to NPV calculations for the comparisons of the various options. However it should be noted that the private sector is likely to aim to have a faster return on investment with a higher discount rate. A typical private sector NPV calculation for infrastructure may be 30 years with a discount rate of around 6%. This would mean that a project saving £1 million (real terms) every year for 30 years, opening 1 year in the future would be worth £14 million in NPV. This is 45% lower than the NPV for long term public sector infrastructure. 12 TAG UNIT A1.1: https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/372519/TAG_Unit_A1.1__Cost_Benefit_Analysis_November2014.pdf 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study 11. Page 31 OTHER COSTS AND BENEFITS The building of the rail link of option A3 or B2 would offer employment in the construction phase, along with some employment in operations. However the additional operational costs of option C (shuttling between Canada and Alexandra Dock by road, or not using rail at all) are partly due to the costs of employing HGV drivers. The Canada Dock area being rail-connected is likely to make that area of the port more attractive to potential occupiers with rail-suitable cargo, because the operational costs of using rail will be reduced. These reduced rail operational costs are likely to mean that more traffic will go by rail. If this extra rail traffic was instead going by road, it would cause additional road congestion and emissions, both locally and across the country. However congestion (or available capacity) is also becoming an increasingly troublesome issue across the rail network. Re-instating the Canada Dock branch from Kirkdale (A3) involves a steep incline in the tunnel and requires a new connection to be made (re-instated) to Network Rail’s network, involving a crossover, turnout, signals etc. This is avoided if Canada Dock is served from the existing connection at Alexandra Dock (B2). The operation of trains in the Canada Dock area poses safety issues and is unlikely to be compatible with plans outlined in the North Liverpool Key Corridors major scheme for Regent Road involving enhanced facilities for pedestrians and bicycles. This is particularly the case on the section of Regent Road between Sandon Dock and Millers Bridge which is already heavily used by port traffic such as HGVs. These interactions will therefore need careful consideration should the rail connections be implemented. One solution would be to bring Regent Road between Sandon Dock and Millers Bridge into the port estate and unadopt it as public highway as has been done with the section further north within Sefton. The costs and benefits in this section have not been quantified. 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study 12. Page 32 OVERALL COMPARISON Below we quantify and compare the overall costs of options A3, B2 and C, catering for 3 trains per day arriving, being processed and then departing. Cost comparison for options A3, B2 and C. £ million in NPV Cost component A3 B2 C Construction 22.7 10.8 - Land values 8.6 - - HGV delay cost (road access blocking) (NPV) 2.1 0.2 - Operational costs (NPV) 6.4 6.4 50.5 Total (NPV) 39.7 17.3 50.5 Construction and Land values are costs that would need to be paid up front. Operational costs are translated into an NPV using the typical long term public sector infrastructure NPV approach (3.5% discount rate over 60 years). The HGV delay costs are taken from section 5. These show £93 per train for A3, and £7 per train for B2. We are assuming 3 trains (arriving and then departing) per day and 300 operational days per year. The comparison table above does suggest that Option C (no rail infrastructure in the Canada Dock area) is by far the worst option. However it should be noted that the 3 daily trains (arriving and then departing) of cargo we are assuming for all options would not necessarily all materialise in option C. Any marginal rail freight potential in options A3 and B2 would in all likelihood simply travel by road for the entire journey in option C at lower cost rather than paying the cost of road transfer to a rail terminal in the Alexandra Dock area. Therefore the NPV of option C is a worst case cost – assuming that all the rail freight potential of options A3 and B2 would experience the full operational cost of travelling by road to the Alexandra Dock area, and that none would find direct road-without-rail, a cheaper option. In terms of cost, the best case cost for option C would be that the rail freight potential traffic of options A3 and B2 could all use road-without-rail if Canada Dock was not directly rail-connected, and that this road cost was similar to the cost of using rail in the A3 and B2 options. In such circumstances the NPV for option C would be small and there would be little cost-based justification for rail-connecting Canada Dock. Despite the higher operating costs of using rail in option C and the opportunity to use road, if demand for one daily train (arriving and then departing) could be found (i.e. a third of the estimated rail freight potential of options A3 and B2), this would represent one third of the full NPV cost of option C: £16.8m. This NPV broadly matches that of building the rail link under option B2. 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study 13. Page 33 CONCLUSION AND NEXT STEPS We have considered various options to serve the Canada Dock area by rail as set out in the Specification (Appendix 7). Option A1 (re-instating the Canada Dock branch line from Kirkdale directly to a terminal east of Regent Road) offers too short a length of track to be able to process modern trains. Options A3 (re-instating the Canada Dock branch line from the Kirkdale area and then running north to the west of Regent Road) and B2 (running south from the existing Alexandra Dock rail terminal area) offer very similar rail capability. A3 (£39.7 million) is significantly more expensive than option B2 (£17.3 million). For option B2, even if we were to build a generous contribution to capacity in the Alexandra Dock area (option B2b: £7 million more expensive than B2), it is still significantly cheaper than option A3. A3 also causes more delay to road users than B2. If the Canada Dock area is to be rail-connected, approaching from the existing sidings in the Alexandra Dock area (B2) is a much better option than re-instating the Canada Dock branch (A3). Re-instating the Canada Dock branch is therefore not required, and the land it would require east of Regent Road (which includes land in the ownership of HCA) can be released for other non-rail uses without fear of compromising the future rail potential of Liverpool port. Option A2 is the same as A3, and option B1 is the same as B2 except that Regent Road is retained as a public road. Regent Road remaining public while building a railway in its western margin such that there would be train, HGV, pedestrian, car and bicycle movements along the same route would present increased safety, construction and operational costs. The new level crossings required to reach a reopened Canada Dock Branch would be a trespass and safety risk such that Network Rail and the ORR would object to the scheme. The case for rail-connecting the Canada Dock area is much harder to make if Regent Road does not become part of the port estate. The comparison between B2 and C (do nothing) depends on the level of traffic in the Canada Dock area suitable for rail. This high level analysis suggests that if the rail potential of the Canada Dock area is less than 1 train per day (into the port and then departing), it is unlikely that the operational cost savings of a direct rail connection justify the capital costs and that therefore rail connecting the Canada Dock area is difficult to justify. Once the rail potential reaches around 2 trains per day (into the port and then departing), rail connecting the Canada Dock area with a connection from the existing Alexandra Dock area (option B2) becomes worthwhile. 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study Page 34 The above conclusions assume a long term public sector infrastructure approach to an NPV calculation (3.5% discount rate over 60 years). However if a typical private sector infrastructure NPV approach is used (6% discount rate over 30 years), the infrastructure required to directly rail-connect the Canada Dock area is harder to justify. 13.1 Could re-instating the Canada Dock branch ever be the best option? In the event that: Land in the Alexandra Dock area became very constrained such that rail freight capacity was very limited And the Seatruck area had a huge increase in HGV traffic, such that briefly blocking the road access caused significant delay And the current Regent Road level crossing became a through-road-route again such that extra rail traffic was problematic And Bankfield Street and nearby Regent Road became part of the port estate and had very little road traffic, such that building new level crossings wouldn’t be problematic. And the branch line re-instatement was not too expensive – the road bridges and tunnel were found to be in good condition And there was a very high rail freight potential in the Canada Dock area and the rest of the southern zone, it is conceivable that re-instating the Canada Dock Branch line (A3) could be judged as broadly similar to running south from Alexandra Dock (B2). However, this is an extremely unlikely outcome. Even in these extreme circumstances an alternative based on the B options would probably still be more attractive than re-instating the Canada Dock branch line. 13.2 Recommended preferred option In our opinion the preferred option for consideration to take forward should be option B2: extending the rail lines south from Alexandra Dock to serve the Canada Dock area. Our high level estimate as to the total NPV cost of this is £17 million including enhanced infrastructure in the Alexandra Dock area to compensate for capacity usage in the Alexandra Dock area. Once the rail potential in this part of the port reaches around 2 trains per day (into the port and then departing), rail connecting the Canada Dock area with a connection from the existing Alexandra Dock area (option B2) becomes worthwhile. This preferred option comprises the following essential components: 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study Page 35 a) Extend rail lines south from Alexandra Dock along the Regent Road corridor to serve the Canada Dock area plus associated capacity enhancements to existing port rail sidings. b) Take Regent Road (Sandon Dock to Millers Bridge) into the port estate and remove it as adopted public highway. This would resolve potential operational and safety concerns regarding interactions between trains, HGVs, cars, pedestrians and cyclists on the Regent Road corridor north of Sandon Dock. c) On-site shunter locomotive provided by Peel Ports to increase the efficiency of on-port rail movements, thereby separating operationally the internal port rail network from mainline movements off Bootle Branch. d) Implementation of a “rail traffic management system” to better control movements on the port internal rail network. In turn these measures outlined in the preferred option will open up the potential for the following complementary rail improvements at the Port of Liverpool: a) Electrification of the Bootle Branch from Olive Mount / Edge Hill as far as the Port of Liverpool reception sidings near Alexandra Dock. b) Extension of the internal port rail network from Seaforth to directly serve the new Liverpool 2 Container Terminal. 13.3 Next steps In order to continue to promote and expand the use of rail freight to and from the Docks a number of steps could be considered which include: Proceed with negotiations with Network Rail to create a continuous double track access to the Port and consider means whereby road access between the northern and southern parts of the docks can be achieved without creating a new level crossing at the end of the Bootle Branch. Action for Peel Ports with Network Rail. Plan to expand reception track capacity in the Alexandra Dock area. Action for Peel Ports. Implement a “rail traffic management system” to better control movements on the port internal rail network. Action for Peel Ports. The route of the old Canada Dock branch line to the east of Regent Road which includes land in the ownership of HCA can be released for other non-rail uses without fear of compromising the future rail potential of Liverpool port. Action for HCA 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study Page 36 To offer rail capability to the southern docks zone in the short term, ensure current rail terminal capacity is available to all users (open access) to allow potential rail freight in the Canada Dock area to use rail with a short within-port road journey. Action for Peel Ports Seek the land required to realise option B2 – largely the land in the western margin of Regent Road. Action for Peel Ports with Merseytravel, Liverpool City Council, Sefton Council Plan to rail-connect the Canada Dock area from the Alexandra Dock area (option B2) once rail freight potential approaches around 2 trains (into the port and then departing) per day. This will be made easier once Regent Road has become part of the port estate. Action for Peel Ports with Merseytravel, Liverpool City Council, Sefton Council. Consider the acquisition or lease of an on-site shunter to increase the efficiency of on-port rail movements. An on-site shunter opens the door to electrification of the Bootle branch route incorporating electrified reception sidings in the Alexandra Dock area. Action for Peel Ports. In our opinion the abandonment of the Canada Dock Branch alignment does not in any way reduce the Port’s potential to use rail freight. Much more important is the ability to create a railway corridor along Regent Road which will in turn be safer, cheaper and more straightforward if the road became part of the Dock Estate. Regardless of the rail capacity available on the Bootle branch line and the wider network to reach the Port of Liverpool, re-opening the Canada Dock branch line would not increase this capacity. 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study APPENDIX 1: INFRASTRUCTURE LAYOUT DRAWING 30/04/15 16:09 Our Ref: 215013r11 Page 37 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study Page 38 APPENDIX 2: POTENTIAL TRAIN MOVEMENT SCHEDULE TIMINGS In section 5, potential train movement schedules are summarised for options A2/A3 and B1/B2. These schedules are shown below in more detail – with locations, movement speeds, times and cumulative times A2/A3 Potential train movement schedule timings serving the steel terminal Ctr 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 Event description for locomotive movements Start from stationary at Former Atlantic Dock Jn (NR (Kirkdale)) Close Regent Road & Bankfield Street level crossings to road traffic Cross Bankfield Street & Regent Road over level crossings Close Cargill and new steel terminal road access Just clear Regent Road with back of train and stop Open Regent Road & Bankfield Street level crossings to road traffic The front end of the train blocks Cargill and new steel terminal road access Uncouple the back 2/3 of the train (340m of wagons) (which lies between Regent Road level crossing and new steel terminal road access) Haul front train-third forward into A2/A3 Northern sidings so no road access points are blocked Open Cargill & new steel terminal Decouple Run loco to Northern headshunt Driver switch ends Run loco to northern end of rear 2 train-thirds Couple Driver switch ends Propel rear 2 train-thirds so that the rear train third is in the scrap terminal loop Split the middle and rear train-thirds by uncoupling Haul the middle train-third (170m of wagons) into A2/A3 Southern sidings Decouple Run to just north of A2/A3 Southern sidings Driver switch ends Run loco to Southern-most headshunt Driver switch ends Run to southern end of rear train-third Couple Propel into the steel terminal Process train third in terminal Once processed, haul this train-third into the scrap terminal loop Decouple Run loco to Southern headshunt Driver switch ends Run to southern end of middle train-third 30/04/15 16:09 Our Ref: 215013r11 Location * Speed m/s Time * Cumulative time * 4.47 4.47 349 78 00:05:49 00:07:07 -850 620 880 00:07:07 00:07:07 1,204 4.47 1,252 4.47 680 4.47 480 1.34 620 4.47 680 4.47 29 4.47 66 4.47 730 1.34 66 4.47 29 4.47 350 4.47 60 00:08:07 93 00:09:39 60 31 60 148 60 60 00:09:39 00:10:39 00:11:10 00:12:10 00:14:38 00:15:38 00:16:38 169 00:19:27 60 00:20:27 51 00:21:18 60 33 60 166 60 28 60 515 3,600 00:22:18 00:22:52 00:23:52 00:26:38 00:27:38 00:28:06 00:29:06 00:37:41 01:37:41 169 01:40:30 60 28 60 92 01:41:30 01:41:58 01:42:58 01:44:30 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study Ctr Event description for locomotive movements 34 35 36 37 38 48 Couple Driver switch ends Haul to 2nd scrap terminal loop Propel into the steel terminal Process train third in terminal Once processed, haul this train-third into the 2nd scrap terminal loop Propel into A2/A3 Southern sidings Decouple Run loco to south of A2/A3 Southern sidings Driver switch ends Run to southern end of front train-third Couple Driver switch ends Haul this train-third south until the back end clears the route to the steel terminal Propel into the steel terminal 49 Start processing train-third in terminal 50 Decouple Run to northern end of rear train-third in scrap terminal loop Couple Driver switch ends Haul rear train-third to A2/A3 Northern sidings Decouple Run to north of A2/A3 Northern sidings Driver switch ends Run to just south of steel terminal Driver switch ends Run into steel terminal Couple Driver switch ends Once processed in steel terminal, haul this train-third into the scrap terminal loop Propel this train-third into A2/A3 Southern sidings where middle train-third is Couple to middle train-third Close Cargill and new steel terminal road access Propel these 2 train-thirds together northwards into A2/A3 Northern sidings where the other train-third is Couple to re-form the full train Conduct brake test. Close Regent Road & Bankfield Street level crossings to road traffic Depart – crossing Regent Road & Bankfield Street up to NR boundary at eastern end of Canada Dock tunnel Open Cargill & new steel terminal Open Regent Road & Bankfield Street level crossings to road traffic Front of train reaches Former Atlantic Dock Jn (NR (Kirkdale)) End of train clears Former Atlantic Dock Jn (NR (Kirkdale)) 39 40 41 42 43 44 45 46 47 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 *Notes: 30/04/15 16:09 Our Ref: 215013r11 Page 39 Location * Speed m/s 60 60 84 515 3,600 Cumulative time * 01:45:30 01:46:30 01:47:53 01:56:29 02:56:29 Time * 66 730 4.47 1.34 66 4.47 169 02:59:17 350 1.34 292 4.47 960 4.47 232 60 33 60 169 60 60 03:03:09 03:04:09 03:04:42 03:05:42 03:08:32 03:09:32 03:10:32 292 4.47 169 03:13:21 730 1.34 Time overlap* 347 03:19:08 3,600 04:19:08 04:19:08 292 4.47 04:19:08 04:19:08 04:19:08 04:19:08 04:19:08 04:19:08 04:19:08 04:19:08 04:19:08 04:19:08 04:19:08 04:19:08 1,204 4.47 1,252 4.47 580 4.47 730 4.47 66 4.47 169 04:21:56 166 1.34 95 04:23:31 60 04:24:31 04:24:31 329 04:30:00 60 600 04:31:00 04:41:00 580 1.34 04:41:00 04:41:00 66 4.47 135 04:43:15 04:43:15 -850 4.47 205 04:46:40 -1,380 4.47 119 04:48:39 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study Page 40 Location: Location of Northern end of locomotive. Metres from Southern end of tracks (by Canada branch dock 1) Time: Seconds after previous event Cumulative time in hours:minutes:seconds Time overlap: The loco makes the following manoeuvres while the train-third is being processed in the steel terminal Assumptions for specific operations (also applies to B1/B2 movements below) Coupling / Decoupling Run to headshunt Driver change ends Brake test Process train-third in terminal Speed on site (10mph) Propel speed (3mph) 30/04/15 16:09 Our Ref: 215013r11 60 30 60 600 3600 4.47 1.34 seconds seconds seconds seconds seconds m/s m/s Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study Page 41 B1/B2 Potential train movement schedule timings serving the steel terminal Ctr 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 Event description for locomotive movements Start from stationary at NR/Peel boundary Arrive into northern end of B1/B2 New siding reception track (to the east of the coal terminal and alongside the existing route to Seaforth) Train blocks one road access point to a factory until the rear third is moved, and when the train is reassembled to depart. There is an alternative road access point to this factory Split the wagons into 3 train-thirds by uncoupling Run loco to Northern headshunt Driver switch ends Run to parallel to EMR sidings Driver switch ends Run to southern end of rear train third Couple Driver switch ends Haul this rear train-third (170m of wagons) south until the back end clears the route to the steel terminal Propel the rear train-third into the steel terminal Process train third in terminal Once rear train-third is processed, haul to the scrap terminal loop Decouple Run loco to Southern headshunt Driver switch ends Run to north end of scrap terminal loop to turn round Reverse to attach to front train-third Couple Haul the rear train-third north and leave it on the route to Seaforth – adjacent to the southern end of the B1/B2 New siding reception Decouple Run north to the crossover at the mid-point of the B1/B2 New siding Reverse through crossover to new reception track Run to southern end of middle train third Couple Driver switch ends Haul this middle train-third (170m of wagons) south until the back end clears the route to the steel terminal Propel the middle train-third into the steel terminal Process train-third in terminal Once middle train-third is processed, haul to the scrap terminal loop Decouple Run loco to Southern headshunt Driver switch ends Run to north end of scrap terminal loop to turn round Reverse to attach to middle train-third Couple Haul the middle train-third north via the B1/B2 New siding reception track and crossover to the route to Seaforth Propel towards and attach to rear train third 30/04/15 16:09 Our Ref: 215013r11 Location * Speed m/s Time * Cumulative time * 4.47 285 00:04:45 1,361 2,547 00:04:45 60 40 60 249 60 85 60 60 00:05:45 00:06:26 00:07:26 00:11:34 00:12:34 00:14:00 00:15:00 00:16:00 4.47 382 00:22:21 730 1.34 347 3,600 00:28:08 01:28:08 66 4.47 169 01:30:56 29 4.47 350 292 4.47 4.47 60 28 60 92 33 60 01:31:56 01:32:25 01:33:25 01:34:56 01:35:30 01:36:30 1,909 4.47 382 01:42:51 60 01:43:51 2,639 4.47 1,617 4.47 1,909 4.47 292 2,182 4.47 81 01:45:12 2,091 2,182 1.34 4.47 88 40 60 60 01:46:40 01:47:21 01:48:21 01:49:21 292 4.47 443 01:56:44 730 1.34 347 3,600 02:02:30 03:02:30 66 4.47 169 03:05:19 29 4.47 350 292 4.47 1.34 60 28 60 92 64 60 03:06:19 03:06:47 03:07:47 03:09:19 03:10:22 03:11:22 2,347 4.47 480 03:19:22 2,091 1.34 210 03:22:53 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study Ctr Event description for locomotive movements 41 42 43 44 45 46 Decouple Run to the crossover at the mid-point Reverse through crossover to new reception track Run to southern end of front train third Couple Driver switch ends Haul this front train-third (170m of wagons) south until the back end clears the route to the steel terminal Propel the front train-third into the steel terminal Process train third in terminal Once front train-third is processed, haul to the scrap terminal loop Decouple Run loco to Southern headshunt Driver switch ends Run to north end of scrap terminal loop to turn round Reverse to attach to front train-third Couple Haul the front train-third north via the B1/B2 New siding reception track and crossover to the route to Seaforth Propel towards and attach to middle train third Decouple Run loco to Northern headshunt Driver switch ends Run to parallel to EMR sidings Driver switch ends Run to southern end of rear train third Couple Driver switch ends Brake test Depart End of train clears NR/Peel boundary 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 30/04/15 16:09 Our Ref: 215013r11 Page 42 Location * Speed m/s 60 40 88 77 60 60 Cumulative time * 03:23:53 03:24:33 03:26:01 03:27:18 03:28:18 03:29:18 2,182 2,091 2,347 4.47 1.34 4.47 292 4.47 480 03:37:18 730 1.34 347 3,600 03:43:04 04:43:04 66 4.47 169 04:45:53 29 4.47 350 292 4.47 1.34 60 28 60 92 64 60 04:46:53 04:47:21 04:48:21 04:49:53 04:50:56 04:51:56 2,347 4.47 480 04:59:56 2,182 1.34 2,639 4.47 1,617 4.47 1,682 4.47 142 60 122 60 249 60 35 60 60 600 851 4.47 05:02:19 05:03:19 05:05:21 05:06:21 05:10:29 05:11:29 05:12:04 05:13:04 05:14:04 05:24:04 05:24:04 05:27:30 Time * 206 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study Page 43 APPENDIX 3: CAPACITY CONTRIBUTION OF B1/B2 INFRASTRUCTURE For options B1/B2 it will be necessary to use rail facilities in Alexandra Dock to hold sections of trains while other sections are taken to and from the Canada Dock area terminals. This uses up capacity at Alexandra Dock. If this was done using only the current rail infrastructure of Alexandra Dock, the extra trains would get in the way of existing movements and would be detrimental to current operations. Therefore we need to provide additional capacity in Alexandra Dock. This should be such that the overall impact of the capacity used by our Canada Dock trains is balanced by the additional capacity we provide. The rail layout designs shown in Appendix 1 show a generous amount of new-build infrastructure associated with option B1/B2, including double-tracking the route from the Bootle branch and providing a dedicated new track to Seaforth. This new infrastructure (and perhaps more) may well be required to cater for the significant growth in rail freight potential – up to 38 departures per day. However it is doubtful that costs of all this new infrastructure should be borne by the Canada Dock area traffic. Using the potential train movement schedule timings from Appendix 2, we seek to demonstrate that a more modest infrastructure new-build broadly compensates for the capacity used by our trains for the Canada Dock area. This modest infrastructure new-build includes an extra reception track alongside and to the east of the coal terminal and directly alongside the existing single track route to Seaforth, with a crossover at the mid-point to the existing route to Seaforth. This can be seen in the track layout design (Appendix 1). Each train that follows the B1/B2 train movement schedule takes 5 hours 30 minutes from the train arriving to the train departing. Throughout this time, one track to Seaforth is blocked to through traffic or the storing of other trains. However while the locomotive is in the Canada Dock area, a through route to Seaforth is always available, even if this means using the cross-over at the midpoint of the new B1/B2 siding to avoid sections of trains standing either in the new B1/B2 siding or the original route to Seaforth. When the locomotive is in the Alexandra Dock area, both routes to Seaforth are blocked. For each Canada Dock train, this is the case for around 1 hour in total. When the locomotive is passing between Canada Docks and Alexandra Docks, no trains can enter or leave Liverpool Docks. For each Canada Dock train, this is the case for around 30 minutes. 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study Page 44 If no trains at all were going to Canada Dock, we would effectively be contributing a passing loop for trains to/from Seaforth – available 24 hours a day. If 1 train per day was going to Canada Dock, the modest infrastructure proposed would contribute a passing loop for trains to/from Seaforth, but it would only be available for 18 hours 30 minutes per day (while our trains were not on site). We would be consuming 1 hour of capacity blocking the Seaforth route and 30 minutes of capacity blocking all access to Liverpool port. Assuming a demand for Seaforth traffic such that offering a passing loop is useful, this is a net contribution to capacity. If 2 trains per day were going to Canada Dock, the proposed modest infrastructure would contribute a passing loop for trains to/from Seaforth, but it would only be available for 13 hours per day (while our trains were not on site). We would be consuming 2 hours of capacity blocking the Seaforth route and 1 hour of capacity blocking all access to Liverpool port. Again, this is a net contribution to capacity. If 3 trains per day were going to Canada Dock, the proposed modest infrastructure would contribute a passing loop for trains to/from Seaforth, but it would only be available for 7 hours 30 minutes per day (while our trains were not on site). We would be consuming 3 hours of capacity blocking the Seaforth route and 1 hour 30 minutes of capacity blocking all access to Liverpool port. This appears to be broadly neutral: we are contributing broadly the same amount of capacity as we are consuming. Further more detailed analysis would be required to establish the precise balance for 3 trains per day. If 4 trains per day were going to Canada Dock, the proposed modest infrastructure would contribute a passing loop for trains to/from Seaforth, but it would only be available for 2 hours per day (while our trains were not on site). We would be consuming 4 hours of capacity blocking the Seaforth route and 2 hours of capacity blocking all access to Liverpool port. With 4 trains per day, we are clearly consuming more capacity in Alexandra Dock than we are contributing. If 5 trains per day were going to Canada Dock, our train movement schedule would require more than 24 hours per day. Therefore a different schedule would be required: If capacity in the Alexandra Dock area was becoming a problem, it would be possible to build more infrastructure in the Canada Dock area (extra loops) such that the whole Canada Dock train could be taken to the Canada Dock area as soon as it arrived at Alexandra Dock, such that the train sectioning could be done in the Canada Dock area. However this would contribute more HGV delay as full trains would pass the road accesses instead of part-trains. This could be a similar arrangement to the train sectioning for option A2/A3. Trains for Seaforth would in any event pass through Alexandra sidings and be held further north before being sectioned into the 400m long container terminal tracks. There is adequate ‘width’ next to the existing single track towards Seaforth to add a second track so that one can be used to receive and one to dispatch trains while a fourth terminal track could be added. This would allow the 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study Page 45 existing site to receive a container train every 2 hours and for at least 3 hours to be available to turn each train around. Another alternative (option B3) to avoid the Alexandra Dock altogether would be to build a triangular junction on approach to Alexandra Dock with a new south-bound curve. This would allow direct access to Canada Dock from the Bootle branch. However this curve uses up a large amount of new land, not required in B1/B2, for which Peel already have plans with a significant value. Arriving and departing trains would also block Seatruck and Cargill for a couple of minutes and a new level crossing would be required across Regent Road near Seatruck. We therefore believe it is unlikely that this curve (B3) would be preferable to the B1/B2 options already described. 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study Page 46 APPENDIX 4: HGV DELAY DUE TO PASSING TRAINS As described in section 5, several of the movements in the potential train movement schedules involve the blocking of roads as the trains, train-thirds or sole locomotives pass. The total delay caused to HGVs is dependent on both the number of railway movements, and the level of HGV traffic across each level crossing and road access point. HGV traffic at each level crossing and road access point We have made tentative estimates of future HGV daily traffic volumes at each level crossing and road access point. Seatruck currently has 147,156 units (source: Peel ports for 2014). We are assuming most of these are operated whereby no sole HGV tractors pass through the gate (an arriving HGV tractor hauls a trailer in and a different trailer out), and the rest require an extra HGV tractor movement. Incorporating the proposed Langton roro terminal to match some trade growth we forecast an approximate 240,000 HGV movements across the gate. Per weekday (dividing by 300 operational days per year) this gives 800 daily HGVs through the gate. We make simple assumptions relative to Seatruck for the other roads and road access points. From North to South these are: 800 HGVs at B1/B2: Regent Road/Network Rail Level Crossing (LC) 800 HGVs at B1/B2: New potential LC south of current Regent Road/NR LC 800 HGVs at B1/B2: Seatruck 800 HGVs at A2/A3/B1/B2: Cargill: During the site visit there appeared to be broadly similar volumes of HGV traffic to Seatruck 400 HGVs at A2/A3/B1/B2: New Steel terminal. 800 HGVs at A2/A3 Regent Road LC 400 HGVs at A2/A3 Bankfield Street LC These are not robust estimates – particularly for the various level crossings over Regent Road and Bankfield Street. If we assumed that current traffic levels continued along Bankfield Street and Regent Road, then trains crossing the level crossing would have a large delay impact on road traffic: In 2013 there were 1,349 vehicles per day along Bankfield Street and 8,475 along Regent Road13. However if there were trains crossing, many of these vehicles may choose alternative routes when the road was blocked, and if Regent Road became part of the port estate, traffic volumes could be controlled and reduced – with no public through-traffic. If the A3 option (including the Bankfield Street and new Regent Road level crossings, and the area becoming part of the port estate) was being taken forward, then the impact of this re-routing of traffic would have to be modelled in the knowledge that Bankfield Street is one of the few right turns planned for the A565 once dualling has been completed. There would also be a need to consider alternative coach parking because 13 Source: DfT AADF traffic counts 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study Page 47 Bankfield Street has 8 medium-stay coach parking bays. Option B2 also involves the re-routing of road traffic as Regent Road (but not Bankfield Street) becomes part of the port estate. A more detailed study should include the modelling of such diverted road traffic. Similarly if the current Regent Road LC was open to road traffic, there would be more than the current zero flow of HGV traffic – we cannot pretend that the current rail route across Regent Road does not cause delay to some HGVs by forcing them to re-route. We have simply assumed that the Regent Road level crossing would have broadly similar flows to Seatruck and the Bankfield Street LC would be half that. Another unknown is who the occupiers of the various port facilities are likely to be in the long term. For example it is possible that a new potential occupier of a site in the Canada Dock area may wish to generate a large volume of HGV movements and want their own new road access to Regent Road, thus requiring an additional level crossing. Closure durations We have also estimated the duration of each closure based on train length and speed (10mph). A sole locomotive crosses and clears a 50 metre crossing in 16 seconds. A locomotive hauling 1 train-third crosses and clears a 50 metre crossing in 54 seconds. A locomotive hauling a full train crosses and clears a 50 metre crossing in 130 seconds. Adding 20 seconds to each of these times (for gate closure and safety margin) gives an estimate of the road-closure durations: 36 seconds for a sole locomotive 74 seconds for a locomotive hauling 1 train-third 150 seconds for a locomotive hauling a full train Total HGV delay estimates per train The delay per closure does not increase linearly with time. Consider the following example: One HGV arrives every minute and the road is closed for 5 minutes. We could expect 5 HGVs to arrive in this 5 minute period. Each would wait for 4.5, 3.5, 2.5, 1.5, 0.5 minutes respectively before the road re-opened. The total delay is 12.5 HGV minutes. However if the road closed for 10 minutes, we could expect 10 HGVs to arrive in this 10 minute period. Each would wait for 9.5, 8.5, 7.5, 6.5, 5.5, 4.5, 3.5, 2.5, 1.5, 0.5 minutes respectively before the road re-opened. The total delay is 50 HGV minutes – i.e. instead of doubling the HGV minutes, the total HGV delay is quadruple the delay of the 5 minute closure. 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study Page 48 A formula representing this HGV delay is: 0.5 X Average HGV flow X Closure-time squared The following table summarises the estimates of total HGV delay by estimating the closure time and therefore the HGV delay associated with each train movement crossing a road access point, and then adding all these HGV delays up to give a total HGV delay per train arrival, processing and then departure. The crossing movements are derived from the potential movements schedule in Appendix 2. A2/A3 Total HGV delay estimates per train Cargill Daily HGVs through gate Hourly HGVs through gate Minutely HGVs through gate Average HGV flow per second Movements 2 Loco + full-length train Each movement blocking time (s) Each movement HGV delay (s) All movements Train arriving, stopping, decoupling 1 and moving Each movement blocking time (s) Each movement HGV delay (s) All movements Train re-forming, coupling, brake 1 testing and moving Each movement blocking time (s) Each movement HGV delay (s) All movements 3 Loco Each movement blocking time (s) Each movement HGV delay (s) All movements 2 Loco + train-third Each movement blocking time (s) Each movement HGV delay (s) All movements Total HGV delay per train (s) 800 33.3 0.6 0.009 New Steel terminal 400 16.7 0.3 0.005 A2/A3 Regent Rd LC 800 33.3 0.6 0.009 A2/A3 Bankfield St LC 400 16.7 0.3 0.005 HGV delay (seconds) No 150 104 208 Total 150 52 104 311 231 246 246 231 123 123 369 1,124 5,852 5,852 1,124 2,926 2,926 8,779 36 6 18 36 3 9 26 74 25 50 74 13 25 75 9,561 9,561 seconds equates to 2 hour 40 minutes. A stationary HGV with driver on-board costs around £35 per hour (principally depreciation and driver’s wages). Therefore the 2 hour 40 minute total HGV delay equates to approximately £93 in HGV delay cost per train, along with a decrease in reliability and a need for the space for these HGVs to queue. 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study Page 49 B1/B2 Total HGV delay estimates per train Daily HGVs through gate Hourly HGVs through gate Minutely HGVs through gate Average HGV flow per second No 2 6 Movements Loco + full-length train Each movement blocking time (s) Each movement HGV delay (s) All movements Loco + train-third Each movement blocking time (s) Each movement HGV delay (s) All movements Total HGV delay per train (s) Regent Rd/NR LC 800 33.3 0.6 0.009 Potential LC south of current LC 800 33.3 0.6 0.009 Seatruck 800 33.3 0.6 0.009 Cargill 800 33.3 0.6 0.009 New Steel terminal 400 16.7 0.3 0.005 HGV delay (seconds) Total 150 104 208 208 74 25 74 25 74 25 74 13 151 151 151 75 528 736 736 seconds equates to 12 minutes, which equates to £7 in HGV cost per train. This is far less disruptive in terms of HGV delay than option A2/A3. This is largely because the train does not have to be re-formed and readied for departure while blocking road accesses. 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study APPENDIX 5: CAPITAL COSTS Gleeds have provided high level cost estimates for the key infrastructure options: A3: Re-instating the Canada Dock branch: £22.7m B2: Serve Canada Dock from the North (Alexandra Dock): £10.8m B2b: As B2 but with generous infrastructure in Alexandra Dock area: £18.0 The breakdown of these costs is shown below 30/04/15 16:09 Our Ref: 215013r11 Page 50 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study Page 51 Option A3: Re-instating the Canada Dock branch Estimate No. Revision Estimate Date 26-Mar-15 Estimate Stage GRIP 1 Rev 01 Price 'Base date' Anticipated Start Date 1Q15 Anticipated Finish Date Project No. Project Title / Location Canada Dock Branch Line - Option A2/A3 WBS Estimate Breakdown Escalation (Y/N) Value % age of Point Estimate Remarks Contractor's direct costs 1.01 Railway Control Systems 1.02 Train Power Systems 467,438 1.03 Electric Power and Plant 1.04 Permanent Way 1.05 Telecommunication Systems 1.06 Buildings and Property 1.07 Civil Engineering 1.08 Enabling Works - Contractor's Base Construction Cost inc OH&P: Sub-Total A Y 2.88% Y 0.00% 734,628 Y 4.53% 3,669,466 Y 22.61% 44,762 Y 0.28% - Y 0.00% 5,519,926 Y 34.01% 90,000 Y 0.55% 10,526,221 64.86% Client's "direct costs" tbc NDS - Materials Y 0.00% tbc NDS - Fleet Y 0.00% tbc - Engineering trains Y 0.00% tbc - Tampers Y 0.00% tbc NDS - Possession/Isolation Management 0.00% Sub - Total B - Total Base Construction Cost inc OH&P: Sub-Total C (A+B) 10,526,221 64.86% Contractor's indirect costs tbc Preliminaries 20% 2,105,244 Y 12.97% tbc Design 15% 1,578,933 Y 9.73% tbc Testing & Commissioning 175,903 Y 1.08% tbc Training - Y 0.00% tbc Spares 40,000 Y 0.25% tbc Other - Y 0.00% Sub - Total D 3,900,080 24.03% Total Construction Cost E (C+D) 14,426,301 88.89% 12.5% 1,803,288 Client's indirect & other costs tbc tbc Project Management (COWD) Project Management (forecasted remaining costs) tbc Compensation charges (TOC & FOC) tbc TWA Charges tbc Land/Property Costs & compensation tbc Escalation (see Note 1) tbc Other (state) 30/04/15 16:09 Our Ref: 215013r11 0% % - N Y 0.00% To be advised 11.11% Y 0.00% Y 0.00% To be advised Y 0.00% To be advised NA 0.00% Sub - Total F 1,803,288 11.11% Point Estimate - Sub - Total G (E+F) 16,229,588 100.00% See Note 1 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study Page 52 Uplift for Risk and Contingency tbc To Mean (see Note 3) % 40% 6,491,835 Project Budget (Point Estimate + Uplift to Mean) 22,721,423 See Note 3 for Project Manager's reference tbc QRA Value - at P50 (see Note 3) £ Sponsor to advise if P50 or P80 value shall apply tbc QRA Value - at P80 - incremental on P50 value (see Note 3) £ Sponsor to advise if P50 or P80 value shall apply tbc Adjustment for residual factors (see Note 2) Uplift on Point Estimate Value (excluding the Cost of Work Done) % Project Anticipated Final Cost (AFC) 22,721,423 Authorised AFC Other Costs to the Customer tbc Allowance for Escalation (see Note 1) See Note 1 tbc - tbc provided by Sponsor tbc Allowance for Insurance Top-up 01/05/2002 Cost to Customer 22,721,423 APPROVAL & ENDORSEMENT Estimate Produced by :Name :Position :- Estimate Approved by :- Estimate Endorsed by :- Jeremy Evans Associate Director Signed :Date :Notes:1. Escalation will only be included within the Project Anticipated Final Cost (Project AFC) where the Project AFC is in excess of £50m and where the site works will be over 2 years duration; escalation shall be calculated using RPI indices from the estimate 'base date' to the mid-point of the construction phase. Where the project AFC is below £50m or the construction phase will be shorter than two years, escalation shall not be included but it shall be calculated as described herein and shown in the Estimate Summary Report under "Other Costs to the Customer". 2. An 'Adjustment for residual factors' has been applied in accordance with the Guidance Notes on Estimating and Supplementary Note (dated 18th March 2010). 3. The project team or Risk & Value Manager should provide the values for uplifts to Mean, P50 and P80. The uplifts to Mean and P50 should be entered in the spaces provided; the incremental value to P80 (beyond P50) should be shown in the box provided (i.e. P80 value - P50 value) 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study Page 53 Option B2: Serve Canada Dock from the North (Alexandra Dock) Estimate No. Revision Estimate Date 19-Mar-15 Estimate Stage GRIP 1 Rev 00 Price 'Base date' Anticipated Start Date 1Q15 Anticipated Finish Date Project No. Project Title / Location Canada Dock Branch Line - Option B1/B2 WBS Estimate Breakdown Escalation (Y/N) Value % age of Point Estimate Remarks Contractor's direct costs 1.01 Railway Control Systems 1.02 Train Power Systems 303,796 1.03 Electric Power and Plant 1.04 Permanent Way 1.05 Telecommunication Systems 1.06 Buildings and Property 1.07 Civil Engineering 1.08 Enabling Works - Contractor's Base Construction Cost inc OH&P: Sub-Total A Y 3.93% Y 0.00% 448,507 Y 5.80% 3,665,297 Y 47.41% - Y 0.00% - Y 0.00% 474,602 Y 6.14% 90,000 Y 1.16% 4,982,203 64.45% Client's "direct costs" tbc NDS - Materials Y 0.00% tbc NDS - Fleet Y 0.00% tbc - Engineering trains Y 0.00% tbc - Tampers Y 0.00% tbc NDS - Possession/Isolation Management 0.00% Sub - Total B - Total Base Construction Cost inc OH&P: Sub-Total C (A+B) 4,982,203 64.45% Contractor's indirect costs tbc Preliminaries 20% 996,441 Y 12.89% tbc Design 15% 747,330 Y 9.67% tbc Testing & Commissioning 105,610 Y 1.37% tbc Training - Y 0.00% tbc Spares 40,000 Y 0.52% tbc Other - Y 0.00% Sub - Total D 1,889,381 24.44% Total Construction Cost E (C+D) 6,871,584 88.89% 12.5% 858,948 Client's indirect & other costs tbc tbc Project Management (COWD) Project Management (forecasted remaining costs) tbc Compensation charges (TOC & FOC) tbc TWA Charges tbc Land/Property Costs & compensation tbc Escalation (see Note 1) tbc Other (state) 30/04/15 16:09 Our Ref: 215013r11 0% % - N Y 0.00% To be advised 11.11% Y 0.00% Y 0.00% To be advised Y 0.00% To be advised NA 0.00% Sub - Total F 858,948 11.11% Point Estimate - Sub - Total G (E+F) 7,730,532 100.00% See Note 1 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study Page 54 Uplift for Risk and Contingency tbc To Mean (see Note 3) % 40% 3,092,213 Project Budget (Point Estimate + Uplift to Mean) 10,822,744 See Note 3 for Project Manager's reference tbc QRA Value - at P50 (see Note 3) £ Sponsor to advise if P50 or P80 value shall apply tbc QRA Value - at P80 - incremental on P50 value (see Note 3) £ Sponsor to advise if P50 or P80 value shall apply tbc Adjustment for residual factors (see Note 2) Uplift on Point Estimate Value (excluding the Cost of Work Done) % Project Anticipated Final Cost (AFC) 10,822,744 Authorised AFC Other Costs to the Customer tbc Allowance for Escalation (see Note 1) See Note 1 tbc - tbc provided by Sponsor tbc Allowance for Insurance Top-up 01/05/2002 Cost to Customer 10,822,744 APPROVAL & ENDORSEMENT Estimate Produced by :Name :Position :- Estimate Approved by :- Estimate Endorsed by :- Jeremy Evans Associate Director Signed :Date :Notes:1. Escalation will only be included within the Project Anticipated Final Cost (Project AFC) where the Project AFC is in excess of £50m and where the site works will be over 2 years duration; escalation shall be calculated using RPI indices from the estimate 'base date' to the mid-point of the construction phase. Where the project AFC is below £50m or the construction phase will be shorter than two years, escalation shall not be included but it shall be calculated as described herein and shown in the Estimate Summary Report under "Other Costs to the Customer". 2. An 'Adjustment for residual factors' has been applied in accordance with the Guidance Notes on Estimating and Supplementary Note (dated 18th March 2010). 3. The project team or Risk & Value Manager should provide the values for uplifts to Mean, P50 and P80. The uplifts to Mean and P50 should be entered in the spaces provided; the incremental value to P80 (beyond P50) should be shown in the box provided (i.e. P80 value - P50 value) 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study Page 55 Option B2b: As B2 but with generous infrastructure in Alexandra Dock area Estimate No. Revision Estimate Date 26-Mar-15 Estimate Stage GRIP 1 Rev 01 Price 'Base date' Anticipated Start Date 1Q15 Anticipated Finish Date Project No. Project Title / Location Canada Dock Branch Line - Option B1/B2 WBS Estimate Breakdown Escalation (Y/N) Value % age of Point Estimate Remarks Contractor's direct costs 1.01 Railway Control Systems 1.02 Train Power Systems 1,034,511 1.03 Electric Power and Plant 1.04 Permanent Way 1.05 Telecommunication Systems 1.06 Buildings and Property 1.07 Civil Engineering 1.08 Enabling Works - Contractor's Base Construction Cost inc OH&P: Sub-Total A Y 8.06% Y 0.00% 540,799 Y 4.22% 5,842,134 Y 45.54% - Y 0.00% - Y 0.00% 715,941 Y 5.58% 90,000 Y 0.70% 8,223,386 64.11% Client's "direct costs" tbc NDS - Materials Y 0.00% tbc NDS - Fleet Y 0.00% tbc - Engineering trains Y 0.00% tbc - Tampers Y 0.00% tbc NDS - Possession/Isolation Management 0.00% Sub - Total B - Total Base Construction Cost inc OH&P: Sub-Total C (A+B) 8,223,386 64.11% Contractor's indirect costs tbc Preliminaries 20% 1,644,677 Y 12.82% tbc Design 15% 1,233,508 Y 9.62% tbc Testing & Commissioning 260,982 Y 2.03% tbc Training - Y 0.00% tbc Spares 40,000 Y 0.31% tbc Other - Y 0.00% Sub - Total D 3,179,167 24.78% Total Construction Cost E (C+D) 11,402,554 88.89% 12.5% 1,425,319 Client's indirect & other costs tbc tbc Project Management (COWD) Project Management (forecasted remaining costs) tbc Compensation charges (TOC & FOC) tbc TWA Charges tbc Land/Property Costs & compensation tbc Escalation (see Note 1) tbc Other (state) 30/04/15 16:09 Our Ref: 215013r11 0% % - N Y 0.00% To be advised 11.11% Y 0.00% Y 0.00% To be advised Y 0.00% To be advised NA 0.00% Sub - Total F 1,425,319 11.11% Point Estimate - Sub - Total G (E+F) 12,827,873 100.00% See Note 1 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study Page 56 Uplift for Risk and Contingency tbc To Mean (see Note 3) % 40% 5,131,149 Project Budget (Point Estimate + Uplift to Mean) 17,959,022 See Note 3 for Project Manager's reference tbc QRA Value - at P50 (see Note 3) £ Sponsor to advise if P50 or P80 value shall apply tbc QRA Value - at P80 - incremental on P50 value (see Note 3) £ Sponsor to advise if P50 or P80 value shall apply tbc Adjustment for residual factors (see Note 2) Uplift on Point Estimate Value (excluding the Cost of Work Done) % Project Anticipated Final Cost (AFC) 17,959,022 Authorised AFC Other Costs to the Customer tbc Allowance for Escalation (see Note 1) See Note 1 tbc - tbc provided by Sponsor tbc Allowance for Insurance Top-up 01/05/2002 Cost to Customer 17,959,022 APPROVAL & ENDORSEMENT Estimate Produced by :Name :Position :- Estimate Approved by :- Estimate Endorsed by :- Jeremy Evans Associate Director Signed :Date :Notes:1. Escalation will only be included within the Project Anticipated Final Cost (Project AFC) where the Project AFC is in excess of £50m and where the site works will be over 2 years duration; escalation shall be calculated using RPI indices from the estimate 'base date' to the mid-point of the construction phase. Where the project AFC is below £50m or the construction phase will be shorter than two years, escalation shall not be included but it shall be calculated as described herein and shown in the Estimate Summary Report under "Other Costs to the Customer". 2. An 'Adjustment for residual factors' has been applied in accordance with the Guidance Notes on Estimating and Supplementary Note (dated 18th March 2010). 3. The project team or Risk & Value Manager should provide the values for uplifts to Mean, P50 and P80. The uplifts to Mean and P50 should be entered in the spaces provided; the incremental value to P80 (beyond P50) should be shown in the box provided (i.e. P80 value - P50 value) 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study Page 57 Assumptions 1. 2. 3. 4. 5. The estimate base date is 1Q 2015. Allowances have been made for adverse ground conditions and service diversions. Assumes all construction materials including p/way elements will be brought to site by lorry. Assumes all excavated material to be removed from site by lorry. Assumes extensive structural/remedial work will be required to bring the tunnel back into operational use. 6. Assumes the existing road over rail bridges at Derby Road and Bankhall Lane will need to be demolished and replaced with new structures. 7. Assumes a 5m depth of dig to track formation level along Bankfield St (South Side) to west tunnel portal. Exclusions 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. Excludes any allowance for Optimism Bias. Escalation allowance is excluded from the "Cost to Customer" figure. VAT is excluded. Excludes 3rd party compensation charges. Excludes planning and approval charges. Excludes permanent land purchases. Excludes costs associated with Statutory Fees (e.g. HMRI, Local Authority, etc.). Excludes costs associated with taxes and levies, including VAT. Excludes costs associated with licences and all associated costs and fees. Excludes costs associated with changes in legislation and any form of applicable standards. Excludes costs associated with changes in legislation, regulation and interpretation covering discriminatory, specific and general issues that may lead to design and cost changes. 12. Excludes allowances for ground stabilisation works. 13. Excludes costs associated with working during Christmas and Bank Holidays. 14. No signalling or telecoms equipment has been included, unless specifically identified. 30/04/15 16:09 Our Ref: 215013r11 Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study APPENDIX 6: LAND ASSEMBLY PLANS 30/04/15 16:09 Our Ref: 215013r11 Page 58 Canada Dock Railway Option A1 Railway Land 3.24 acres (1.31 ha) W F Doyle Holdings Ltd (MS399675) 3.81 acres (1.52 ha) Homes and Communities Agency (MS376672) 2.54 acres (1.02 ha) Liverpool City Council (MS402768) 0.11 acres (0.05 ha) Blue Property and Investments Ltd (MS480048) and SGB Services Ltd (MS527230) 2.98 acres (1.21 ha) Canada Dock Railway Option A2 / A3 Railway Land 2.57acres (1.04 ha) W F Doyle Holdings Ltd (MS399675) 3.81 acres (1.52 ha) Homes and Communities Agency (MS376672) 2.54 acres (1.02 ha) Liverpool City Council (MS402768) 0.11 acres (0.05 ha) Blue Property and Investments Ltd (MS480048) and SGB Services Ltd (MS527230) 2.98 acres (1.21 ha) S Norton & Co (MS311611) 7.05 acres (2.85 ha) Conor & Daragh McDonald (MS360037) 0.05 acres (0.02 ha) John Conlan (MS206130) 0.12 acres (0.05 ha) Mark Davies & Anthony Smith (MS198075) 0.07 acres (0.03 ha) Rail Connectivity to the Canada Dock Area. Feasibility and Demand Study APPENDIX 7: JOB SPECIFICATION 30/04/15 16:09 Our Ref: 215013r11 Page 61 Specification Port of Liverpool (Southern Zone) Rail Connectivity to Canada Dock Area Feasibility & Demand Study 1 245 Canada Dock (Rev6 FINAL VERSION) 5th February 2015 1. Introduction 1.1 This study is to develop the business case for the reinstatement of rail connectivity to the Canada Dock area and the Port of Liverpool Southern Zone more generally (including Sandon Dock, Huskisson Dock, Canada Dock, Brocklebank Dock and Langton Dock) and for specific site options for rail freight terminals in the same area. This needs development in the light of interest related to land currently protected in regard to one potential option for provision of this rail link. 1.2 Merseytravel, on behalf of key stakeholders of the Liverpool City Region (Homes & Communities Agency, Peel Ports, Liverpool City Region LEP, Liverpool City Council, Sefton Council and Merseytravel), wishes to commission a Feasibility and Demand Study to determine the potential benefits of reconnecting the Canada Dock area to the rail network and to gain an understanding of the practical, regulatory, operational, land and cost implications of the possible options. 1.3 As part of the Feasibility & Demand Study there will be a requirement to develop costs, the capital cost element will need to consider the cost of reinstating the connection to this area of the port including any related land assembly costs. Two separate main route options are to be considered as part of this study with sub options identified. 1.4 The options and sub-options will need to be evaluated in terms of ease of operation for freight movements both qualitatively and quantitatively in terms of potential effects on demand and on the existing rail freight operations within and to/from the port. Likely freight terminal or terminals and their locations will depend on the needs and cargos of existing or future businesses located in the port estate or local area. 1.5 As part of this study there will be a requirement to review current timetables and to identify the potential freight paths in and out of the locality and identify whether this would constrain demand. 1.6 The Feasibility & Demand Study will need to determine the Benefit Cost Ratio (BCR) and Net Present Value (NPV) of the options. 1.7 Finally it will need to identify a preferred route option for rail connectivity to Canada Dock and the Port of Liverpool (Southern Zone) including costs, next steps and indicative implementation timescales. This will establish a clear evidence based rationale for going forward in regard 2 245 Canada Dock (Rev6 FINAL VERSION) 5th February 2015 to why the rail connectivity to this area of the Port of Liverpool is needed (the challenge), implementation issues / costs / timescale (the solution) and what objectives / outputs / outcomes / benefits such rail connectivity will deliver for the port and wider city region (the outcome). 2. Background 2.1 Historically the Port of Liverpool had an extensive network of rail lines within the port estate. The LNWR Canada Dock goods yard, located on the eastern side of Regent Road, had a dedicated rail link to the Bootle Branch as well as connections on to the internal rail lines within the port estate at Canada Dock to the west of Regent Road. In recent years these lines were lost as the rail network was rationalised. 2.2 Today the main rail line into the Port of Liverpool is the Bootle Branch and within the port estate the area from Alexandra Dock to Royal Seaforth Dock is rail connected. However the rail lines within the port estate south of Alexandra Dock have been removed so the Port of Liverpool Southern Zone (including Langton Dock, Brocklebank Dock, Canada Dock, Huskisson Dock and Sandon Dock) is no longer rail connected. The Canada Dock rail link off the Bootle Branch which served the port estate and the former LNWR Canada Dock goods yard to the east of Regent Road closed in 1982. Since then parts of the former Canada Dock goods yard have been infilled between the Canada Dock Tunnel and Derby Road with different surface levels created. However the former LNWR Canada Dock Goods Terminal buildings still exist on the land between Regent Road and Derby Road. 2.3 There is an aspiration outlined in the draft Port Master Plan to connect the Canada Dock area and the Port of Liverpool (Southern Zone) to the rail network for freight movements to serve port related businesses in this area and the wider local area that do not presently have the option of rail connectivity. 2.4 A previous study is available for information only and cannot be relied upon by the Consultant in this study. The study is “Canada Dock Rail study v1 0 July 2008” by Steer Davis Gleave for English Partnerships (predecessor to the Homes & Communities Agency). Other relevant items of information that are available and in the public domain are: Access to the Port of Liverpool Study (2010/11) by WSP http://www.letstravelwise.org/files/1832000440_PortOfLiverpoolStudy_Stage1 Report_May2010.pdf http://www.letstravelwise.org/files/636125410_PortOfLiverpoolStudy_Stage2R eport_Nov2011.pdf 3 245 Canada Dock (Rev6 FINAL VERSION) 5th February 2015 Mersey Ports Master Plan – Consultation Draft 2011 by Peel Ports http://peelports.com/wp-content/uploads/2014/01/Consultation-Draft.pdf http://peelports.com/wp-content/uploads/2014/01/Plans-1-6.pdf Historical Background to LNWR Canada Dock Goods Yard (Disused Stations) http://www.disused-stations.org.uk/c/canada_dock_goods/index.shtml The former LNWR Canada Dock Goods Terminal buildings still stand on one of the proposed rail alignment options on the land between Regent Road and Derby Road. So there may be potential for these buildings and their site footprint to form the basis for a new freight terminal. (Disused Stations http://www.disused-stations.org.uk/c/canada_dock_goods/index.shtml) 4 245 Canada Dock (Rev6 FINAL VERSION) 5th February 2015 This is the former LNWR Canada Dock Goods Terminal which still survives intact. This gate was where the rail line once exited the former LNWR Canada Dock Goods Terminal and went across Regent Road into the Peel Ports dock estate on the western side of Regent Road. (Disused Stations http://www.disused-stations.org.uk/c/canada_dock_goods/index.shtml) This is the western portal of the Canada Dock Tunnel as it was in the 1930s. This double track tunnel survives intact and is owned by Network Rail. But this portal is no longer visible due to infilling of the former Canada Dock Goods Yard site here to street level. (Disused Stations http://www.disused-stations.org.uk/c/canada_dock_goods/index.shtml) 5 245 Canada Dock (Rev6 FINAL VERSION) 5th February 2015 3. Study Requirements 3.1 Merseytravel, on behalf of key stakeholders, wishes to commission a Consultant to undertake a high level Feasibility & Demand Study for the construction of a rail connection into Canada Dock and the Port of Liverpool (Southern Zone). This work will involve identifying and quantifying the capital costs (including land or lease costs), revenue cost, operational aspects and constraints and demand for the route options and scenarios for rail connectivity that are outlined. 3.2 The capital costs shall be based on typical high level industry rates applied in relation to the Consultant’s knowledge of the area. Where there are conditions that are unknown the Consultant shall apply a reasonable assumption to the development of the cost and consider upper and lower bounds. The uncertainties in cost will be developed into a sensitivity analysis for each of the options with, median, upper and lower bound costs being prepared. The Consultant shall provide sufficient detail to show how costs are derived and demonstrate that these are robust with appropriate historic or other documentary evidence in support. 3.3 The Consultant shall list all the assumptions made in developing the costs and identify the work that can be undertaken, if required or appropriate, at a future date, so as to provide better cost certainty. 3.4 The Revenue Costs shall include any charges and costs incurred in the provision of the rail freight service and any operational costs associated with the freight handling facility. The costs should be based on typical industry rates. The Consultant shall provide sufficient detail to show how costs are derived and demonstrate that these are robust with appropriate historic or other documentary evidence in support. This will need to be informed also by the likely commodities and tonnages likely to be handled by rail from this part of the Port of Liverpool. 3.5 Revenue Costs shall also include any savings associated with reducing the road transport element as well as potential carbon savings. 3.6 The Consultant shall consider the options suggested and carry forward only those that are considered acceptable in terms of operations. Acceptable in this context means that Freight Operators would be able to develop an operating pattern that is in accordance with normal industry practice and is reasonably practical to implement. 3.7 The Consultant shall develop freight paths in and out of the proposed rail freight terminal(s) for each of the options. This shall be considered with the current timetables and any constraints that apply. Freight 6 245 Canada Dock (Rev6 FINAL VERSION) 5th February 2015 paths will look at local constraints as well as the path to the origins/destinations. The demand study side of the work and likely commodities will inform this element in terms of potential origins/destinations. Current road transport and origins/destinations out of the dock area shall also be considered. This element of the study is intended to be a high level study with the primary focus being on a detailed consideration of local constraints to freight movement. Additionally it will include a secondary focus on a less detailed overview of potential constraints further afield to possible origins/destinations. 3.8 The Consultant shall develop a demand model that considers current usage of the dock area and develops this to identify any current and increasing demand with the provision of these new rail freight facilities. 3.9 The capital cost shall include land purchase costs or amendments to current leases. The Consultant will need to highlight those land parcels that are likely to be impacted upon as a result of the proposed rail link options. This will enable the key stakeholders to consider further any impacts on occupiers with leases within the port estate and elsewhere in a sensitive manner. The costs should be based on typical land costs in the area. The Consultant shall provide sufficient detail to show how these costs are derived and demonstrate that these are robust with appropriate historic or other documentary evidence in support. 3.10 The Consultant shall also undertake the following as part of the study. A high level review of the existing infrastructure in terms of constraints to implementing the options and the works required to remove constraints. An overview feasibility of undertaking the works to implement the individual options with high level risks identified. A detailed comparison of the various infrastructure options detailing risks, benefits, and relevant merits of each of the proposals, with the preferred option clearly identified as a way forward. Consider fully any planned infrastructure improvements in the area including highway improvements, e.g. the planned improvements to Regent Road by Liverpool City Council, and Peel Ports proposed Langton In-River Ro-Ro Terminal, ensure any improvements are integrated into option development for the Canada Dock rail links The study shall consider known and planned local growth and shall consider the opportunity to link in with other business in the location. Likely terminal locations will depend on the cargo requirements of existing and future businesses located in the port estate and local area. 7 245 Canada Dock (Rev6 FINAL VERSION) 5th February 2015 Provide relevant advice on further studies required to remove unknowns, reduce risks or develop more robust costs. Outline timescales for the potential implementation of the preferred route option with key milestones including land acquisition, planning, Network Rail procedures and the like. High level consideration of the wider economic benefits such as potential impacts on, local job and wealth creation, on the local Gross Value Added (GVA) and improved accessibility to business. High level consideration of environmental effects of options required including any positive or negative impacts on the reduction of accidents as well as noise, carbon and air quality improvements as a result of removing freight from the roads and other relevant issues. A high level consideration of benefits to other stakeholders. Risks associated with the options and any necessary sensitivity analysis to quantify the risks. High level overview of the policy context and business aspirations for the area of the Port of Liverpool and related port businesses with leases in the area (particularly in port estate south of Alexandra Dock including Langton Dock, Brocklebank Dock, Canada Dock, Huskisson Dock and Sandon Dock in the Port of Liverpool Southern Zone). Liaison with the stakeholders to understand and quantify the land and lease constraints, identify the likelihood of approval of a level crossing and the potential for taking the public highway into private ownership. Qualitative analysis of the options and related benefits with a commentary on the results with a specific focus of the necessity or desire of a rail connection as appropriate to the findings of the study. Drawing showing land ownership boundaries and detailed data of ownership for the options evaluated. Calculate Net Present Value (NPV) and Benefit Cost Ratios (BCR) utilising WEBtag guidance in so far as this is possible or relevant. Identify a preferred route option and indicative timescale for implementation of this route option and suggest likely next steps. 8 245 Canada Dock (Rev6 FINAL VERSION) 5th February 2015 3.11 There are a number of separate infrastructure options to consider. The map on p12 shows an overview of the two main route scenarios. ROUTE A: New dedicated rail link off Bootle Branch to Canada Dock and various other docks within the Port of Liverpool Southern Zone Option A1: This option includes the following elements – Reinstate points at the former Atlantic Dock Junction between Westminster Tunnel and Oriel Road Tunnel on the Bootle Branch; project will need to provide a trailing crossover at the reinstated Atlantic Dock Junction, for trains departing Canada Dock area of port to allow them to access the Up Bootle Branch, (this is likely to involve three point ends in total). All new and modified signalling as necessary to facilitate rail link Re-commission Canada Dock Tunnel under Leeds Liverpool Canal with single or double track line reinstated as necessary New single or double track line as necessary from tunnel to run parallel to Bankfield Street with new or revived crossings under Bank Hall Lane and Derby Road. These two roads historically were carried over the former Canada Dock goods yard on multiple arched bridges which may still be intact. Rail alignment should be future proofed to cater for implementation of a double track capability if necessary. Single or double track as necessary from terminal to buffer stop Suitable length of track with associated sets of points to allow typical freight train length and to allow loco to run around Termination to the east of Regent Road with new freight terminal created on part of the former LNWR Canada Dock goods yard site including hard standing area suitable for cargo handling Option A2 Option A2 is as per Option A1 but with the following additions: Rail line extended into the port estate to west of Regent Road through the creation of a level crossing of Regent Road before curving northwards and / or southwards in the vicinity of the Canada Dock area to serve the various docks as necessary. Suitable length of track with associated sets of points to allow typical freight train length and to allow loco to run around Run around facilities within the Peel Ports estate to the west of Regent Road and various freight terminals located as necessary to serve the relevant port businesses and cargos. This will enable the rail line to serve the Port of Liverpool (Southern 9 245 Canada Dock (Rev6 FINAL VERSION) 5th February 2015 Zone) including Sandon Dock, Huskisson Dock, Canada Dock, Brocklebank Dock and Langton Dock. Location of new freight terminal(s) within the port estate will need to be informed by the port businesses and those in the local area and the likely cargo / commodities. Regent Road is to remain a public highway in this option. As a result there will be a need to explore impact of level crossing on the highway network and journey times in the area. Option A3 This is as Option A2 except for the last point in regard to Regent Road: Regent Road in this option is brought into the Peel Ports estate and so will no longer be public highway but will become private. This scenario for Regent Road is proposed in the medium to long term by Peel Ports in the draft Mersey Ports Master Plan. As a result there will be a need to explore impact of level crossing on the highway network and journey times in the area. Various combinations of the above options may also be worth considering if the consultant feels this is necessary. For example there may be merit in having both a freight terminal to east of Regent Road on former Canada Dock Goods Yard site as well as ones to west within the Peel Ports estate serving key docks in the southern part of the Port. ROUTE B: Extension of rail lines within port estate southwards from Alexandra Dock area to serve Canada Dock and Port of Liverpool Southern Zone Option B1: This option includes the following elements – New sets of points to the Bootle Branch and existing rail lines within port estate close to Alexandra Dock to the west of Regent Road New single or double track running to the west of Regent Road within port estate or alternatively within or adjacent to the highway itself in a southerly direction to buffer stops at Canada Dock or other docks depending on cargos and needs of port businesses. Hard standing area suitable for cargo handling Suitable length of track with associated sets of points to allow typical freight train length and to allow loco to run around 10 245 Canada Dock (Rev6 FINAL VERSION) 5th February 2015 Location of freight terminal(s) within the port estate will need to be informed by the port businesses and those in the local area and the likely cargo / commodities. This option will need to examine the impact on rail capacity of the existing rail lines within the port estate due to the shunting of trains up to the northern end of port in this option from the southern end that will be required prior to them exiting the port via Bootle Branch Regent Road is to remain a public highway in this option. As a result there will be a need to explore impact of rail line in this corridor on the highway network and journey times in the area. Option B2: This is as option B1 except for the last point in regard to Regent Road – Regent Road in this option is brought into the Peel Ports estate and so will no longer be public highway but will become private. This scenario for Regent Road is proposed in the medium to long term by Peel Ports in the draft Mersey Ports Master Plan. As a result there will be a need to explore impact of rail line in this corridor on the highway network and journey times in the area. ROUTE C: Do nothing approach and retain the status quo This option includes the following elements – Do not proceed with any rail link to this part of port and accept the consequent limits on rail access and impact on the ability to promote multi-modal access to the Port of Liverpool. Current safeguarding provisions are retained indefinitely 11 245 Canada Dock (Rev6 FINAL VERSION) 5th February 2015 Freight Rail Line to Port of Liverpool Northern Zone (Alexandra Dock to Royal Seaforth Dock) Merseyrail to Southport and disused North Mersey Branch to Aintree and Ormskirk Northern Zone Seatruck Ferries Ro-Ro Terminal at Langton Dock Southern Zone Millers Bridge FREIGHT ONLY Bootle Branch from Port of Liverpool to Chat Moss Line and the WCML Bankfield Street Port of Liverpool Southern Zone (Langton Dock to Sandon Dock) NOT RAIL CONNECTED Merseyrail to Ormskirk and Kirkby A565 Derby Road Regent Road Leeds Liverpool Canal 12 Merseyrail to 245 Canada Dock (Rev6 FINAL VERSION) 5th February 2015 Liverpool Central and Hunts Cross 3.12 Freight movement by rail out of the Canada Dock area and other docks in the Port of Liverpool (Southern Zone) cannot currently take place so new freight paths will need to be identified as part of this study to enable the trains to go onto the Bootle Branch and beyond. This will need to take into account the rail freight forecasts for the Port of Liverpool (Northern Zone) which predict 38 freight trains per day outbound from the Port of Liverpool via the Bootle Branch (therefore 76 train movements in total overall including outbound and inbound). 3.13 Key stakeholders include: Merseytravel Liverpool City Region Local Enterprise Partnership Sefton Council Network Rail Homes & Communities Agency (HCA) Liverpool City Council Peel Ports Various Freight Operators All businesses in and adjacent to the port estate, particularly in the Port of Liverpool (Southern Zone) which is currently not rail connected i.e. the area encompassing Langton Dock, Brocklebank Dock, Canada Dock, Huskisson Dock and Sandon Dock that are all located south of Alexandra Dock in the Port of Liverpool. 3.14 The Consultant shall facilitate and manage an inception meeting presenting an understanding of the brief. The Consultant shall produce a brief report following this meeting confirming his approach and understanding. This report shall include a programme 3.15 The Consultant shall produce a two weekly headline progress report detailing completion of items against programme and highlighting any issues and developing risks to the programmed service. 3.16 The Consultant shall plan to produce and issue a draft report for comment followed by facilitating and managing a meeting to review the content of the draft report. The Consultant shall record all comments made and detail actions based on comments. 3.17 The Consultant shall issue the final report following comments. The Consultant shall present the findings to the stakeholders to be facilitated and managed by the Consultant. 13 245 Canada Dock (Rev6 FINAL VERSION) 5th February 2015 3.18 4. 5. 6. The Consultant should be aware that the indicative headline budget for this study work should not exceed £30,000 if possible. Deliverables 4.1 Inception meeting summary. 4.2 Agreed and revised programme following inception meeting. 4.3 Draft Report. 4.4 Final Report. Timescales 5.1 The Consultant shall provide a programme following the inception meeting on 27 February 2015. 5.2 The Consultant shall complete the work in accordance with this programme which shall be for completion of the draft report by end of March 2015 and completed final report by end of April 2015. 5.3 The study is intended to provide outline baseline data to determine the future direction for work in this area and is intended to be a high level study. All data produced should be based on evidenced data with assumptions clearly identified. Project Management The Consultant shall maintain a single point of contact throughout the contract. Merseytravel shall identify a single point of contact following award. 7. Report Content The precise format, layout and sections are as determined by the Consultant. 14 245 Canada Dock (Rev6 FINAL VERSION) 5th February 2015
© Copyright 2026 Paperzz