Pennies for Progress 3

Pennies for Progress 3
Referendum Passed: August 2011
Tax Collection to begin: 4th Qtr. 2011
Tax Expires: 1st Qtr. 2018
Budget: $161,000,000
Number of Projects: 14
Program Duration: 2011 to 2020
File:
Eng.G:\Pr
Project
Number
Project Type
11-001
Two-lane to fivelane
11-002
Completed Projects
Projects under construction
Projects under design/permitting/right-of-way
Revised
Project Name
Budget (Finance
Reports)
SC Highway 160 West
$8,848,728
5-lane to State line
SC Highway 274 and Pole Branch Rd.
Two-lane to fivelane
11-003
11-004
Sutton Springs Road
Shoulder
widening
11-006
Two-lane to fivelane
11-007
Interchange
Improvement
Gold Hill Road/I-77 Interchange Improvement
70% Right of Way
Right of Way 2016
Construction 2017
70% right of way
plans submitted to
SCDOT for review
Right of Way 2016
Construction 2017
Phase I - 70 %
design plans
Phase II Preliminary design
Anticipated bid Fall
2017
Working toward
70% right of way
plans
Right of way plans
2016
Completed By
SCDOT
SCDOT Awarded bid
in March 2012
Complete
SCDOT
Bid to be awarded
January 2016.
Construction Winter
2016
Award pending bid
approval.
HDR Engineering,
Inc., Rock Hill, SC
Responding to
comments on 70%
right of way plans
from SCDOT
Right of way
acquisition pending
right of way plan
approval
Estimated Construction
Complete - Summer
2019
Kimley-Horn and
Associates, Inc.,
Rock Hill, SC
Construction
Company
SC 160/Gold Hill Road
Intersection under
Campco Engineering,
construction by SCDOT Inc., Rock Hill, SC
2015
Mead & Hunt,
Columbia, SC
Project under redesign
Joel E. Wood &
Associates, York, SC
STV Inc., Rock Hill,
SC
Boggs Paving, Inc.
$5,829,427
Cherry Road to Eden Terrace - 5-lane
Gold Hill Road/I-77
Design Engineer
$3,274,800
SC 5 to SC 49
Cel-River/Red River Road
Comments
$22,425,371
Two-lane to five- Springfield Parkway to NC State line - 4 or 5lane
lane
11-005
Schedule
$2,485,753
Phase I - US 321 to Quinn Street
Phase
II - Quinn Street to Barrett Road
US 21 North Phase I and SC 51
Project Status
$25,775,000
SC 274 5-lane(SC 49 to Pole Branch)
Pole Branch 3-lane(SC 274 to NC Line)
SC 321/Barrett/West Gate Connector
Two-lane new
alignment
January-16
Projects on hold for funding
$11,649,811
Page 1 of 8
1/12/2016
Pennies for Progress 3
Referendum Passed: August 2011
Tax Collection to begin: 4th Qtr. 2011
Tax Expires: 1st Qtr. 2018
Budget: $161,000,000
Number of Projects: 14
Program Duration: 2011 to 2020
File:
Eng.G:\Pr
Project
Number
Project Type
11-008
Completed Projects
Projects under construction
Projects under design/permitting/right-of-way
Revised
January-16
Projects on hold for funding
Project Name
Budget (Finance
Reports)
Intersection and Pedestrian Safety
$28,880,814
Project Status
Schedule
Comments
11-008a
Intersection
Improvement
US 21/Anderson/Cowan Farm Road
Intersection Realignment
$5,000,000
Right of way
Complete
Bid Spring 2016
11-008b
Intersection
Improvement
SC 49 - Congress Street/Lincoln Road
Intersection - Round-a-bout
$1,200,000
Right of way
acquisition
Plans 90% complete
Estimated begin
Construction- Fall 2016
Kimley-Horn and
Associates, Inc.,
Rock Hill, SC
11-008c
Intersection
Improvement
US 321/Johnson Street/Railroad Avenue
Intersection Realignment
$1,000,000
Awaiting survey
completion
Design 2016 by
SCDOT
Awaiting SCDOT
approval
SCDOT
11-008d
Intersection
Improvement
SC Highway 49/Campbell Road Intersection
Realignment
$500,000
Addressing NOI
permit comments
Bid Spring 2016
Estimated Construction
Complete - Fall 2016
Kimley-Horn and
Associates, Inc.,
Rock Hill, SC
11-008e
Sidewalk
Addition
Sullivan Middle School (Pedestrian Safety
Cherry Rd/Eden Terr near Anderson)
$563,840
Complete
11-008e
Pedestrian
Improvements
Cherry Road Pedestrian Safety
$1,195,000
Design
Concept designs
under review
11-008f
Intersection
Improvement
Griggs Road/Bate Harvey/SC 557
Intersection Realignment
$1,000,000
Addressing NOI
permit comments
Bid Spring 2016
11-008g
Intersection
Improvement
4th Street/5th Street/Ross Cannon Street
Intersection Realignment
$846,778
Awaiting survey
completion
Design 2016 by
SCDOT
Awaiting SCDOT
approval
SCDOT
11-008h
Intersection
Improvement
White Street/West Main/Constitution/West
Black Realignment and Round-a-bout
$5,000,000
Under Construction
Under Construction
Complete 2017
By City of Rock Hill
& Campco
11-008i
Road &
shoulder
widening
Paraham Road (SC 55 to SC 161) Base
Stabilization and Shoulder Widening
$6,522,660
NOI permit pending
Bid Spring 2016
Estimated Construction
Complete -Fall 2017
CECS, Inc.,
Columbia, SC
11-008j
Intersection
Improvement
Fort Mill Southern Bypass/Spratt/Sutton
Connector
$4,752,536
Finalizing 30%
design plans
Page 2 of 8
Estimated
Managed by SCDOT for
Construction
a safety project
Complete - Fall 2017
Design Engineer
Construction
Company
HDR Engineering,
Inc., Rock Hill, SC
Campco Engineering,
Inc., Rock Hill, SC
Contract Negotiations
Campco Engineering,
Inc., Rock Hill, SC
Estimated Construction
URS, Greenville, SC
Complete - Fall 2016
Anticipated bid Spring Estimated Construction
2017
Complete -Winter 2017
STV Inc., Rock Hill,
SC
1/12/2016
Pennies for Progress 3
Referendum Passed: August 2011
Tax Collection to begin: 4th Qtr. 2011
Tax Expires: 1st Qtr. 2018
Budget: $161,000,000
Number of Projects: 14
Program Duration: 2011 to 2020
File:
Eng.G:\Pr
Completed Projects
Projects under construction
Projects under design/permitting/right-of-way
Revised
Project
Number
Project Type
Project Name
Budget (Finance
Reports)
Project Status
11-008k
Sidewalk and
Bike Lanes
University Drive (Bike lanes and sidewalk)
$1,300,000
Contract
Negotiations
SC Highway 557
$4,324,400
11-009
Two Lane to fivelane widening
11-010
Working toward
70% right of way
plans
2003 Add-on to 5-lane to Kingsburry
SC 160 East
Two-lane to
three-lane
widening
January-16
Projects on hold for funding
Springfield Pkwy to Lancaster County Line
Schedule
Comments
Design Engineer
Construction
Company
Campco Engineering,
Inc., Rock Hill, SC
Estimated Construction
Final Right of way Complete -Spring 2021.
plans - Spring 2016
Design change per
SCDOT
Mulkey, Charlotte,
NC
$4,793,053
Design
Negotiations
Page 3 of 8
Begin design 2016
STV Inc., Rock Hill,
SC
1/12/2016
Pennies for Progress 3
Referendum Passed: August 2011
Tax Collection to begin: 4th Qtr. 2011
Tax Expires: 1st Qtr. 2018
Budget: $161,000,000
Number of Projects: 14
Program Duration: 2011 to 2020
File:
Eng.G:\Pr
Project
Number
Project Type
11-011a
Completed Projects
Projects under construction
Projects under design/permitting/right-of-way
Revised
January-16
Projects on hold for funding
Project Name
Budget (Finance
Reports)
Gravel Group I
$5,219,936
Project Status
Schedule
Comments
Design Engineer
Construction
Company
Open to Traffic
August 2015
Under Warranty
Keck and Wood,
Rock Hill, SC
Roger Grading
Armstrong Glen
Granite Contracting
Gravel Road
Paving
Arrow Road (Highway 5 to Highway 5
Bypass)
Complete
Gravel Road
Paving
Beersheba Road (Beersheba/Templeton to
Greenleaf)
Working on Right-ofway Acquisition
Gravel Road
Paving
Burns Road (Burns/Highway 5/McGill)
Under Construction
Gravel Road
Paving
Calabash Road (Fairhope Road to Old
Limestone Road)
Working on Right-ofway Acquisition
Gravel Road
Paving
California Road (Kelly Road to Highway 49)
Working on Right-ofway Acquisition
Gravel Road
Paving
Canaan Church Road (Highway 55 to
Highway 5)
Working on Right-ofway Acquisition
Gravel Road
Paving
Carroll Falls Road (Highway 55 to Maynard
Grayson)
Working on Right-ofway Acquisition
Gravel Road
Paving
Devinney Road (Highway 5 to Highway 324)
Working on Right-ofway Acquisition
Gravel Road
Paving
Durree Street (Porter to Rock Grove)
Design & Permitting
Gravel Road
Paving
Faires Road (Mockingbird to Highway 322)
Working on Right-ofway Acquisition
Page 4 of 8
Estimated Complete
April 2016
Bid 2016
1/12/2016
Pennies for Progress 3
Referendum Passed: August 2011
Tax Collection to begin: 4th Qtr. 2011
Tax Expires: 1st Qtr. 2018
Budget: $161,000,000
Number of Projects: 14
Program Duration: 2011 to 2020
File:
Eng.G:\Pr
Project
Number
Completed Projects
Projects under construction
Projects under design/permitting/right-of-way
Revised
January-16
Projects on hold for funding
Project Type
Project Name
Gravel Road
Paving
Budget (Finance
Reports)
Project Status
Schedule
Frontier Road (Agony Acres to Thomas
Road)
Design & Permitting
Bid 2016
Gravel Road
Paving
Garvin Road (Garvin Road to Simpson Road)
Working on Right-ofway Acquisition
Gravel Road
Paving
Greenglen Road (Hawley to W. Chappell)
Working on Right-ofway Acquisition
Gravel Road
Paving
James Harvey Road (Mason Dickson to
Highway 321)
Working on Right-ofway Acquisition
Gravel Road
Paving
Longleaf Road (California Road to Highway
49)
Working on Right-ofway Acquisition
Gravel Road
Paving
Montview Road (Wilson Chapel Road to
Sherer Road)
Working on Right-ofway Acquisition
Gravel Road
Paving
Nivens Road (Tirzah Road to South Shiloh
Road)
Working on Right-ofway Acquisition
Gravel Road
Paving
Piedmont Springs (Highway 55 to Highway 5)
Working on Right-ofway Acquisition
Gravel Road
Paving
Shady Oak Lane (Neely Store to Hopewell)
Working on Right-ofway Acquisition
Gravel Road
Paving
South Fork Road (Percival to Mobley Store)
Working on Right-ofway Acquisition
Gravel Road
Paving
Southbend Road (Fairhope to Old Limestone)
Working on Right-ofway Acquisition
Page 5 of 8
Comments
Design Engineer
Construction
Company
1/12/2016
Pennies for Progress 3
Referendum Passed: August 2011
Tax Collection to begin: 4th Qtr. 2011
Tax Expires: 1st Qtr. 2018
Budget: $161,000,000
Number of Projects: 14
Program Duration: 2011 to 2020
File:
Eng.G:\Pr
Project
Number
Completed Projects
Projects under construction
Projects under design/permitting/right-of-way
Revised
Budget (Finance
Reports)
Project Type
Project Name
Gravel Road
Paving
Traylor Road (Hord Road to North Burris)
Working on Right-ofway Acquisition
Gravel Road
Paving
Turner Road (Ramah Church to C.E.
Stewart)
Working on Right-ofway Acquisition
Gravel Road
Paving
Wilkerson Road (Highway 211 to Highway
97)
Working on Right-ofway Acquisition
11-011b
January-16
Projects on hold for funding
Gravel Group II
Project Status
Schedule
Comments
Design Engineer
Construction
Company
$5,000,000
Gravel Road
Paving
Clinzo Feemster Road (Sawmill Road to end)
Working on Right-ofway Acquisition
Gravel Road
Paving
Creekside Drive (Openwood to end)
Under construction
Estimated Complete
May 2016
Keck and Wood
Granite Contracting
Gravel Road
Paving
Fox Trail Road (Highway 49 to end)
Complete
Complete
York County
Granite Contracting
Gravel Road
Paving
Heatherlock Road (Lester Road to end)
Complete
Armstrong Glen
Granite Contracting
Gravel Road
Paving
Hidden Valley Road (Strait Road to end)
Under construction
Estimated Complete
April 2016
Joel Wood and
Associates
Eagle Construction
Gravel Road
Paving
Hillcrest Road (Sharon Road to California
Road)
Working on Right-ofway Acquisition
Gravel Road
Paving
Hughes Road (Beersheba Road to end)
Working on Right-ofway Acquisition
Gravel Road
Paving
Mereva Road (Burns Road to end)
Under Construction
Estimated Complete
April 2016
Armstrong Glen
Granite Contracting
Page 6 of 8
Punch list items pending
1/12/2016
Pennies for Progress 3
Referendum Passed: August 2011
Tax Collection to begin: 4th Qtr. 2011
Tax Expires: 1st Qtr. 2018
Budget: $161,000,000
Number of Projects: 14
Program Duration: 2011 to 2020
File:
Eng.G:\Pr
Project
Number
Completed Projects
Projects under construction
Projects under design/permitting/right-of-way
Revised
January-16
Projects on hold for funding
Design Engineer
Construction
Company
Estimated Complete
January 2016
Joel Wood and
Associates
Eagle Construction
Under Construction
Estimated Complete
May 2016
Keck and Wood
Granite Contracting
Stonebridge Lane (Riddle Mill Road to end)
Complete
Complete
York County
Granite Contracting
Gravel Road
Paving
Stroupe Road & Entrance Road (Smith Road
to end)
Working on Right-ofway Acquisition
Gravel Road
Paving
Tanners Road (Legion Road to end)
Working on Right-ofway Acquisition
Gravel Road
Paving
Woodstream Road (Lincoln Road to end)
Working on Right-ofway Acquisition
Project Type
Project Name
Gravel Road
Paving
Budget (Finance
Reports)
Project Status
Schedule
Musket Hill Road (Lockhart Highway to end)
Under Construction
Gravel Road
Paving
Shadow Lakes Drive (Jim McCarter Road to
end)
Gravel Road
Paving
11-012
Riverview Road
Two-lane to
three-lane
Add 3-lane to the 2003 PFP Scope
Comments
$7,851,942
Preliminary Design
Page 7 of 8
Campco Engineering,
Inc., Rock Hill, SC
1/12/2016
Pennies for Progress 3
Referendum Passed: August 2011
Tax Collection to begin: 4th Qtr. 2011
Tax Expires: 1st Qtr. 2018
Budget: $161,000,000
Number of Projects: 14
Program Duration: 2011 to 2020
File:
Eng.G:\Pr
Project
Number
Project Type
11-013
Intersection
Corridor
Improvement
11-014
Projects under construction
Projects under design/permitting/right-of-way
Revised
January-16
Projects on hold for funding
Project Name
Budget (Finance
Reports)
Mt Gallant Road
$10,026,668
Celanese Road to Twin Lakes Road Intersection Corridor Improvement (budget is
$2.0 million less than ref)
SC Hwy 72
Two-lane to
three-lane
Totals
Completed Projects
Project Status
Schedule
Comments
Design Engineer
Design begin
February 2016
KCI Technologies,
Inc. Rock Hill, SC
Preliminary Design
CDM Smith,
Columbia, SC
Construction
Company
$10,614,300
SC Highway 901 to Rambo Road - Multilane
(budget is $2.0 million less than ref)
$157,000,003
This information contained above is based on data available at the time this spreadsheet is published.
Data is subject to change without notice. Project Costs are based on both estimates developed in 2010
and actual costs based on bids, payments or encumbered funds from previous projects.
Page 8 of 8