Pennies for Progress 3 Referendum Passed: August 2011 Tax Collection to begin: 4th Qtr. 2011 Tax Expires: 1st Qtr. 2018 Budget: $161,000,000 Number of Projects: 14 Program Duration: 2011 to 2020 File: Eng.G:\Pr Project Number Project Type 11-001 Two-lane to fivelane 11-002 Completed Projects Projects under construction Projects under design/permitting/right-of-way Revised Project Name Budget (Finance Reports) SC Highway 160 West $8,848,728 5-lane to State line SC Highway 274 and Pole Branch Rd. Two-lane to fivelane 11-003 11-004 Sutton Springs Road Shoulder widening 11-006 Two-lane to fivelane 11-007 Interchange Improvement Gold Hill Road/I-77 Interchange Improvement 70% Right of Way Right of Way 2016 Construction 2017 70% right of way plans submitted to SCDOT for review Right of Way 2016 Construction 2017 Phase I - 70 % design plans Phase II Preliminary design Anticipated bid Fall 2017 Working toward 70% right of way plans Right of way plans 2016 Completed By SCDOT SCDOT Awarded bid in March 2012 Complete SCDOT Bid to be awarded January 2016. Construction Winter 2016 Award pending bid approval. HDR Engineering, Inc., Rock Hill, SC Responding to comments on 70% right of way plans from SCDOT Right of way acquisition pending right of way plan approval Estimated Construction Complete - Summer 2019 Kimley-Horn and Associates, Inc., Rock Hill, SC Construction Company SC 160/Gold Hill Road Intersection under Campco Engineering, construction by SCDOT Inc., Rock Hill, SC 2015 Mead & Hunt, Columbia, SC Project under redesign Joel E. Wood & Associates, York, SC STV Inc., Rock Hill, SC Boggs Paving, Inc. $5,829,427 Cherry Road to Eden Terrace - 5-lane Gold Hill Road/I-77 Design Engineer $3,274,800 SC 5 to SC 49 Cel-River/Red River Road Comments $22,425,371 Two-lane to five- Springfield Parkway to NC State line - 4 or 5lane lane 11-005 Schedule $2,485,753 Phase I - US 321 to Quinn Street Phase II - Quinn Street to Barrett Road US 21 North Phase I and SC 51 Project Status $25,775,000 SC 274 5-lane(SC 49 to Pole Branch) Pole Branch 3-lane(SC 274 to NC Line) SC 321/Barrett/West Gate Connector Two-lane new alignment January-16 Projects on hold for funding $11,649,811 Page 1 of 8 1/12/2016 Pennies for Progress 3 Referendum Passed: August 2011 Tax Collection to begin: 4th Qtr. 2011 Tax Expires: 1st Qtr. 2018 Budget: $161,000,000 Number of Projects: 14 Program Duration: 2011 to 2020 File: Eng.G:\Pr Project Number Project Type 11-008 Completed Projects Projects under construction Projects under design/permitting/right-of-way Revised January-16 Projects on hold for funding Project Name Budget (Finance Reports) Intersection and Pedestrian Safety $28,880,814 Project Status Schedule Comments 11-008a Intersection Improvement US 21/Anderson/Cowan Farm Road Intersection Realignment $5,000,000 Right of way Complete Bid Spring 2016 11-008b Intersection Improvement SC 49 - Congress Street/Lincoln Road Intersection - Round-a-bout $1,200,000 Right of way acquisition Plans 90% complete Estimated begin Construction- Fall 2016 Kimley-Horn and Associates, Inc., Rock Hill, SC 11-008c Intersection Improvement US 321/Johnson Street/Railroad Avenue Intersection Realignment $1,000,000 Awaiting survey completion Design 2016 by SCDOT Awaiting SCDOT approval SCDOT 11-008d Intersection Improvement SC Highway 49/Campbell Road Intersection Realignment $500,000 Addressing NOI permit comments Bid Spring 2016 Estimated Construction Complete - Fall 2016 Kimley-Horn and Associates, Inc., Rock Hill, SC 11-008e Sidewalk Addition Sullivan Middle School (Pedestrian Safety Cherry Rd/Eden Terr near Anderson) $563,840 Complete 11-008e Pedestrian Improvements Cherry Road Pedestrian Safety $1,195,000 Design Concept designs under review 11-008f Intersection Improvement Griggs Road/Bate Harvey/SC 557 Intersection Realignment $1,000,000 Addressing NOI permit comments Bid Spring 2016 11-008g Intersection Improvement 4th Street/5th Street/Ross Cannon Street Intersection Realignment $846,778 Awaiting survey completion Design 2016 by SCDOT Awaiting SCDOT approval SCDOT 11-008h Intersection Improvement White Street/West Main/Constitution/West Black Realignment and Round-a-bout $5,000,000 Under Construction Under Construction Complete 2017 By City of Rock Hill & Campco 11-008i Road & shoulder widening Paraham Road (SC 55 to SC 161) Base Stabilization and Shoulder Widening $6,522,660 NOI permit pending Bid Spring 2016 Estimated Construction Complete -Fall 2017 CECS, Inc., Columbia, SC 11-008j Intersection Improvement Fort Mill Southern Bypass/Spratt/Sutton Connector $4,752,536 Finalizing 30% design plans Page 2 of 8 Estimated Managed by SCDOT for Construction a safety project Complete - Fall 2017 Design Engineer Construction Company HDR Engineering, Inc., Rock Hill, SC Campco Engineering, Inc., Rock Hill, SC Contract Negotiations Campco Engineering, Inc., Rock Hill, SC Estimated Construction URS, Greenville, SC Complete - Fall 2016 Anticipated bid Spring Estimated Construction 2017 Complete -Winter 2017 STV Inc., Rock Hill, SC 1/12/2016 Pennies for Progress 3 Referendum Passed: August 2011 Tax Collection to begin: 4th Qtr. 2011 Tax Expires: 1st Qtr. 2018 Budget: $161,000,000 Number of Projects: 14 Program Duration: 2011 to 2020 File: Eng.G:\Pr Completed Projects Projects under construction Projects under design/permitting/right-of-way Revised Project Number Project Type Project Name Budget (Finance Reports) Project Status 11-008k Sidewalk and Bike Lanes University Drive (Bike lanes and sidewalk) $1,300,000 Contract Negotiations SC Highway 557 $4,324,400 11-009 Two Lane to fivelane widening 11-010 Working toward 70% right of way plans 2003 Add-on to 5-lane to Kingsburry SC 160 East Two-lane to three-lane widening January-16 Projects on hold for funding Springfield Pkwy to Lancaster County Line Schedule Comments Design Engineer Construction Company Campco Engineering, Inc., Rock Hill, SC Estimated Construction Final Right of way Complete -Spring 2021. plans - Spring 2016 Design change per SCDOT Mulkey, Charlotte, NC $4,793,053 Design Negotiations Page 3 of 8 Begin design 2016 STV Inc., Rock Hill, SC 1/12/2016 Pennies for Progress 3 Referendum Passed: August 2011 Tax Collection to begin: 4th Qtr. 2011 Tax Expires: 1st Qtr. 2018 Budget: $161,000,000 Number of Projects: 14 Program Duration: 2011 to 2020 File: Eng.G:\Pr Project Number Project Type 11-011a Completed Projects Projects under construction Projects under design/permitting/right-of-way Revised January-16 Projects on hold for funding Project Name Budget (Finance Reports) Gravel Group I $5,219,936 Project Status Schedule Comments Design Engineer Construction Company Open to Traffic August 2015 Under Warranty Keck and Wood, Rock Hill, SC Roger Grading Armstrong Glen Granite Contracting Gravel Road Paving Arrow Road (Highway 5 to Highway 5 Bypass) Complete Gravel Road Paving Beersheba Road (Beersheba/Templeton to Greenleaf) Working on Right-ofway Acquisition Gravel Road Paving Burns Road (Burns/Highway 5/McGill) Under Construction Gravel Road Paving Calabash Road (Fairhope Road to Old Limestone Road) Working on Right-ofway Acquisition Gravel Road Paving California Road (Kelly Road to Highway 49) Working on Right-ofway Acquisition Gravel Road Paving Canaan Church Road (Highway 55 to Highway 5) Working on Right-ofway Acquisition Gravel Road Paving Carroll Falls Road (Highway 55 to Maynard Grayson) Working on Right-ofway Acquisition Gravel Road Paving Devinney Road (Highway 5 to Highway 324) Working on Right-ofway Acquisition Gravel Road Paving Durree Street (Porter to Rock Grove) Design & Permitting Gravel Road Paving Faires Road (Mockingbird to Highway 322) Working on Right-ofway Acquisition Page 4 of 8 Estimated Complete April 2016 Bid 2016 1/12/2016 Pennies for Progress 3 Referendum Passed: August 2011 Tax Collection to begin: 4th Qtr. 2011 Tax Expires: 1st Qtr. 2018 Budget: $161,000,000 Number of Projects: 14 Program Duration: 2011 to 2020 File: Eng.G:\Pr Project Number Completed Projects Projects under construction Projects under design/permitting/right-of-way Revised January-16 Projects on hold for funding Project Type Project Name Gravel Road Paving Budget (Finance Reports) Project Status Schedule Frontier Road (Agony Acres to Thomas Road) Design & Permitting Bid 2016 Gravel Road Paving Garvin Road (Garvin Road to Simpson Road) Working on Right-ofway Acquisition Gravel Road Paving Greenglen Road (Hawley to W. Chappell) Working on Right-ofway Acquisition Gravel Road Paving James Harvey Road (Mason Dickson to Highway 321) Working on Right-ofway Acquisition Gravel Road Paving Longleaf Road (California Road to Highway 49) Working on Right-ofway Acquisition Gravel Road Paving Montview Road (Wilson Chapel Road to Sherer Road) Working on Right-ofway Acquisition Gravel Road Paving Nivens Road (Tirzah Road to South Shiloh Road) Working on Right-ofway Acquisition Gravel Road Paving Piedmont Springs (Highway 55 to Highway 5) Working on Right-ofway Acquisition Gravel Road Paving Shady Oak Lane (Neely Store to Hopewell) Working on Right-ofway Acquisition Gravel Road Paving South Fork Road (Percival to Mobley Store) Working on Right-ofway Acquisition Gravel Road Paving Southbend Road (Fairhope to Old Limestone) Working on Right-ofway Acquisition Page 5 of 8 Comments Design Engineer Construction Company 1/12/2016 Pennies for Progress 3 Referendum Passed: August 2011 Tax Collection to begin: 4th Qtr. 2011 Tax Expires: 1st Qtr. 2018 Budget: $161,000,000 Number of Projects: 14 Program Duration: 2011 to 2020 File: Eng.G:\Pr Project Number Completed Projects Projects under construction Projects under design/permitting/right-of-way Revised Budget (Finance Reports) Project Type Project Name Gravel Road Paving Traylor Road (Hord Road to North Burris) Working on Right-ofway Acquisition Gravel Road Paving Turner Road (Ramah Church to C.E. Stewart) Working on Right-ofway Acquisition Gravel Road Paving Wilkerson Road (Highway 211 to Highway 97) Working on Right-ofway Acquisition 11-011b January-16 Projects on hold for funding Gravel Group II Project Status Schedule Comments Design Engineer Construction Company $5,000,000 Gravel Road Paving Clinzo Feemster Road (Sawmill Road to end) Working on Right-ofway Acquisition Gravel Road Paving Creekside Drive (Openwood to end) Under construction Estimated Complete May 2016 Keck and Wood Granite Contracting Gravel Road Paving Fox Trail Road (Highway 49 to end) Complete Complete York County Granite Contracting Gravel Road Paving Heatherlock Road (Lester Road to end) Complete Armstrong Glen Granite Contracting Gravel Road Paving Hidden Valley Road (Strait Road to end) Under construction Estimated Complete April 2016 Joel Wood and Associates Eagle Construction Gravel Road Paving Hillcrest Road (Sharon Road to California Road) Working on Right-ofway Acquisition Gravel Road Paving Hughes Road (Beersheba Road to end) Working on Right-ofway Acquisition Gravel Road Paving Mereva Road (Burns Road to end) Under Construction Estimated Complete April 2016 Armstrong Glen Granite Contracting Page 6 of 8 Punch list items pending 1/12/2016 Pennies for Progress 3 Referendum Passed: August 2011 Tax Collection to begin: 4th Qtr. 2011 Tax Expires: 1st Qtr. 2018 Budget: $161,000,000 Number of Projects: 14 Program Duration: 2011 to 2020 File: Eng.G:\Pr Project Number Completed Projects Projects under construction Projects under design/permitting/right-of-way Revised January-16 Projects on hold for funding Design Engineer Construction Company Estimated Complete January 2016 Joel Wood and Associates Eagle Construction Under Construction Estimated Complete May 2016 Keck and Wood Granite Contracting Stonebridge Lane (Riddle Mill Road to end) Complete Complete York County Granite Contracting Gravel Road Paving Stroupe Road & Entrance Road (Smith Road to end) Working on Right-ofway Acquisition Gravel Road Paving Tanners Road (Legion Road to end) Working on Right-ofway Acquisition Gravel Road Paving Woodstream Road (Lincoln Road to end) Working on Right-ofway Acquisition Project Type Project Name Gravel Road Paving Budget (Finance Reports) Project Status Schedule Musket Hill Road (Lockhart Highway to end) Under Construction Gravel Road Paving Shadow Lakes Drive (Jim McCarter Road to end) Gravel Road Paving 11-012 Riverview Road Two-lane to three-lane Add 3-lane to the 2003 PFP Scope Comments $7,851,942 Preliminary Design Page 7 of 8 Campco Engineering, Inc., Rock Hill, SC 1/12/2016 Pennies for Progress 3 Referendum Passed: August 2011 Tax Collection to begin: 4th Qtr. 2011 Tax Expires: 1st Qtr. 2018 Budget: $161,000,000 Number of Projects: 14 Program Duration: 2011 to 2020 File: Eng.G:\Pr Project Number Project Type 11-013 Intersection Corridor Improvement 11-014 Projects under construction Projects under design/permitting/right-of-way Revised January-16 Projects on hold for funding Project Name Budget (Finance Reports) Mt Gallant Road $10,026,668 Celanese Road to Twin Lakes Road Intersection Corridor Improvement (budget is $2.0 million less than ref) SC Hwy 72 Two-lane to three-lane Totals Completed Projects Project Status Schedule Comments Design Engineer Design begin February 2016 KCI Technologies, Inc. Rock Hill, SC Preliminary Design CDM Smith, Columbia, SC Construction Company $10,614,300 SC Highway 901 to Rambo Road - Multilane (budget is $2.0 million less than ref) $157,000,003 This information contained above is based on data available at the time this spreadsheet is published. Data is subject to change without notice. Project Costs are based on both estimates developed in 2010 and actual costs based on bids, payments or encumbered funds from previous projects. Page 8 of 8 1/12/2016
© Copyright 2026 Paperzz