Int. J. Global Energy Issues, Vol. 35, No. 1, 2011 The costs of power: plutonium and the economics of India’s prototype fast breeder reactor J.Y. Suchitra Centre for Public Policy, Faculty Block A, P-101, Indian Institute of Management, Bangalore, Bannerghatta Road, Bangalore 560076, India E-mail: [email protected] M.V. Ramana* Programme on Science and Global Security and Nuclear Futures Laboratory, Woodrow Wilson School of Public and International Affairs, Princeton University, Princeton, NJ 08540, USA Fax: +1-609-258-3661 E-mail: [email protected] *Corresponding author Abstract: The Indian Department of Atomic Energy plans to expand nuclear power in the country by constructing a large fleet of plutonium fuelled breeder reactors, seen as necessary because of perceived shortage of uranium resources. We analyse the economics of generating electricity at the first such reactor in India, the prototype fast breeder reactor. We find that such electricity will be 80% more expensive than the corresponding cost at pressurised heavy water reactors with our base case assumptions. The economics of breeder electricity is primarily determined by the cost of reprocessing spent fuel to produce plutonium and fabricating it into fuel. Breeder reactors become more competitive as the cost of fuelling heavy water reactors with uranium goes up, but only very slowly. The crossover cost is $1,375 per kilogram of uranium for our base case. At such a high cost, poorer quality ores can be economically mined. We perform an extensive sensitivity analysis to show that the broad conclusions hold even under assumptions that are far more favourable to breeder economics. Keywords: breeder reactors; prototype fast breeder reactor; PFBR; plutonium breeder economics; electricity costs; India energy; Department of Atomic Energy; DAE; DAE breeder programme; uranium availability; reprocessing costs; India nuclear power. Reference to this paper should be made as follows: Suchitra, J.Y. and Ramana, M.V. (2011) ‘The costs of power: plutonium and the economics of India’s prototype fast breeder reactor’, Int. J. Global Energy Issues, Vol. 35, No. 1, pp.1–23. Copyright © 2011 Inderscience Enterprises Ltd. 1 2 J.Y. Suchitra and M.V. Ramana Biographical notes: J.Y. Suchitra received her Master’s in Economics from the University of Hyderabad. She is currently with the Centre for Public Policy at the Indian Institute of Management, Bangalore. She has been working on the economics of nuclear energy for the past five years, and has published academic papers and popular articles in this area. M.V. Ramana is an Associate Research Scholar at the Woodrow Wilson School of Public and International Affairs, Princeton University. He received his PhD in Physics from the Boston University and is the author of a forthcoming book on the Indian nuclear programme. 1 Introduction India plans a major expansion of nuclear energy over the next few decades. Currently installed nuclear capacity in the country is 4,120 MW (megawatts),1 which constitutes 3% of all power generation. The Indian Department of Atomic Energy (DAE) envisions nuclear power growing to 275,000 MW by 2052 (Srinivasan et al., 2005). There have been even higher projections recently. Much of this planned expansion is based on fast breeder reactors.2 For example, out of the 275,000 MW, breeders constitute 262,500 MW (Grover and Chandra, 2006). The DAE has long been interested in breeder reactors. This interest in breeders is not exceptional. Since the 1950s, several countries around the world spent large quantities of money on research and development related to breeders; about half a dozen countries constructed pilot scale or demonstration breeder reactors (IPFM, 2010). However, over the decades, most have suspended their programmes. Even France, the country that has actually gone on from the demonstration level to building and operating the commercial scale superphénix reactor, has not planned for construction of any future breeders. In part, the disenchantment with breeders is due to economic reasons. Several studies have shown that electricity from breeder reactors is expensive in comparison to that from light water reactors that dominate the world’s nuclear capacity (Bunn et al., 2005; Chow, 1995; Cochran, 1974; Feiveson et al., 1979). In contrast, the DAE claims that electricity from breeder reactors is comparable in cost to that from a pressurised heavy water reactor (PHWR), the reactor type that accounts for the largest share of nuclear generation in the country (Bhoje, 2003; Paranjpe, 1991). The DAE, however, has not demonstrated this assessment with rigorous economic analysis. To address this lacuna, we calculate the cost of generating electricity at the 500 MW prototype fast breeder reactor (PFBR) that the DAE is currently constructing. The DAE argues that breeders are important for India because the country has limited uranium reserves, insufficient for a large nuclear programme. To test the argument about uranium scarcity, we perform our cost comparison as a function of the cost of fuelling the PHWR with uranium. This paper is structured as follows. We start with a historical overview followed by a description of the methodology used for economic evaluation. The next section lays out the cost and other assumptions. The results of our analysis and a discussion of their sensitivity to various parameters constitute the subsequent two sections, before we go on to the conclusions. The costs of power 2 3 Historical background Breeder reactors in India were originally conceived of as part of a three phase nuclear programme proposed in the 1950s as a way to expand nuclear power despite the relatively small amounts of uranium ore, and those too of very poor quality, discovered in the country (Bhabha and Prasad, 1958). The first phase involves the use of uranium fuel in PHWRs, followed by reprocessing the spent fuel to extract plutonium. In the second phase, the accumulated plutonium stockpile is used in the nuclear cores of fast breeder reactors. These nuclear cores could be surrounded by a blanket of either depleted uranium or natural uranium, to produce more plutonium; if the blanket were to contain thorium, it would produce Uranium-233. So as to ensure that there is adequate plutonium to fuel these second phase breeder reactors, a sufficiently large fleet of such breeder reactors with uranium blankets would have to be commissioned before thorium blankets are introduced. The third phase involves breeder reactors using Uranium-233 in their cores and thorium in their blankets. The DAE started planning for the PFBR in 1983 when it requested the government for budgetary support (Bidwai, 1983). The first expenditures on the PFBR started in 1987–1988 (DAE, 1991). In 1990, it was reported that the government had “recently approved the reactor’s preliminary design and… awarded construction permits”; at that time, the reactor was supposed to come on line by 2000 (Hibbs, 1990). The reactor is now expected to be commissioned in 2012 (Subramanian, 2010). A public sector company called BHAVINI has been set up to construct and operate the PFBR and future breeder reactors. The PFBR is to be the first of many breeder reactors that the DAE envisions building. Its ‘primary objective’ is said to be “to demonstrate techno-economic viability of fast breeder reactors on an industrial scale” (Chetal et al., 2006). The DAE claims that the “cost of power from PFBR will be comparable to that from…PHWRs” (Bhoje, 2003). This claim should be evaluated rigorously and transparently before large scale construction of breeder reactors begins. 3 Methodology We use the standard discounted cash flow (DCF) methodology to calculate the life cycle cost of producing electricity at the PFBR and a PHWR (Brealey and Myers, 2000). In this approach, all costs are discounted to some arbitrary but fixed reference date; the total cost is the sum of the present values (PV) or future values (FV) of costs discounted to this date. In addition, the benefits, i.e., the electricity generated in different years, are also discounted to the same reference date. Our calculations are all performed in 2004 Rupees, the year when construction of the PFBR started. To convert costs from one year to another, we use the ratio of GDP deflators for the respective years as specified by the World Bank. For future costs, we follow the Indian Nuclear Power Corporation and use a 5% rate of escalation (Thakur and Chaurasia, 2005). We convert all Rupee figures to US $ figures using the conversion rate of $1 = Rs. 44, which was the prevalent rate in 2004. India’s Central Electricity Regulatory Commission has recommended a nominal discount rate of 10.6% for costing power (CERC, 2006). This translates to a real discount rate of about 5%. However, nuclear power plants are financially more risky 4 J.Y. Suchitra and M.V. Ramana (Farber, 1991). This is primarily because these have higher fixed costs as compared to, say, coal plants, which have higher operating costs. For plants with higher fixed costs, the systematic risk is higher (Hamada, 1972; Lev, 1974; Mandlekar and Rhee, 1984). This necessitates the use of a higher discount rate.3 We therefore, use a real discount rate of 6%.4 Our analysis is based on cost figures from Government of India and DAE budget documents as far as possible. Unfortunately, many cost elements were not publicly available. An attempt to acquire some of the information using India’s Right to Information Act succeeded in obtaining annual construction cost estimates and the allocations for waste management, but BHAVINI denied all fuel chain costs, including that of fuel fabrication and reprocessing (Suchitra and Ramana, 2007).5 Therefore, we have extrapolated from international cost figures or made our own calculations based on other Indian data. 4 Cost components and other assumptions We consider the same set of cost components for both the PFBR and a PHWR, namely construction of the reactor (capital cost), fuelling, operations and maintenance, decommissioning, refurbishment, working capital, and management of low level radioactive wastes.6 For the PHWR, the fuelling cost includes those of uranium and fuel fabrication. Also included are the costs of the initial heavy water inventory and of replacing the heavy water that is lost during routine operations. For the PFBR, the fuelling cost includes that of producing plutonium through reprocessing and fabricating it into MOX fuel. We assume that the cost of uranium for the MOX fuel and the blankets is free. This is because there are no strong isotopic requirements for the PFBR fuel, and therefore depleted uranium, which is available in copious quantities from reprocessing as well as uranium enrichment, could be used for this purpose (Ramana and Suchitra, 2007). The plutonium for the initial core as well as for the first few reloads has to come from reprocessing PHWR spent fuel at the DAE’s Kalpakkam Reprocessing Plant (KARP) (Hibbs, 2003). Because the PFBR has a relatively low breeding ratio, it will not be producing excess plutonium in significant quantities.7 Therefore, future breeder reactors with the same design will also have to adopt the same practice of using plutonium from reprocessing PHWR spent fuel for the initial cores and the first few reloads, at least for a couple of decades. Once the breeder reactor is shut down, the value of the plutonium recovered is accounted for at the same cost at which it is assumed to be obtained from KARP. Similarly, the heavy water for the initial loading of the PHWR is assumed to be obtained from DAE and returned when the reactor is shut down. 4.1 Prototype fast breeder reactor 4.1.1 Construction cost The DAE has estimated the total construction cost of the PFBR to be Rs. 34.92 billion, which translates to Rs. 28.41 billion in 2004 Rupees.8 This converts to $645.75 million (in 2004 dollars). As a unit cost, this is $1292/kW. This is roughly half of corresponding estimates of breeder reactor construction costs elsewhere; the Nuclear Energy Agency The costs of power 5 (NEA) gives a range of $2,000–2,800/kW (in 2004 dollars) for MOX fuelled fast reactors [NEA, (2002), p.216]. When compared to these estimates, breeder reactors already constructed have been more expensive. Construction costs for the French phénix reactor totalled FF 800 million (1974 French francs), which translates to $800 million in 2004 dollars or $3,200/kW (IPFM, 2010). The 1,240 MW Superphénix was far more expensive with an initial investment of FF 28 billion (1985 figure, which translates to $4.9 billion in 2004 dollars) [NUKEM, (1997), p.15]. The 300 MW Kalkar reactor in Germany cost DM 7 billion (1985 Deutsche Marks), which translates to $3.6 billion in 2004 dollars (Neffe, 1985). The projected cost of the PFBR falls well below both the NEA’s estimates and actual costs. There are also historical and technical reasons to expect that the PFBR’s cost will turn out to be higher than the DAE’s estimate. The initial cost estimates of all reactors constructed in India have been much lower than the final cost figures (DAE, 1996, 2002). This may be the case with the PFBR too; reports suggest that construction costs have been higher than anticipated because of rising prices of steel, cement, and other raw materials (TOI, 2009).9 Technically, breeder reactors can be expected to be more expensive than PHWRs for two reasons. First, the use of molten sodium as coolant brings with it several operational requirements, such as heating systems to keep the sodium molten at all times, and safety-related requirements, such as extensive fire fighting equipment (Farmer, 1984). Second, accidents at breeder reactors could lead to the release of large quantities of explosive energies (Bethe and Tate, 1956). Therefore, they have to include extensive safety features which are a significant component of the total capital cost of a breeder reactor. Despite these many reasons to expect cost escalation, we use the DAE’s estimate for PFBR’s cost and, as we discuss later on, for the PHWR’s cost as well. 4.1.2 Plutonium-related costs In economic terms, the primary material requirement for the PFBR is plutonium. The PFBR design requires an initial inventory of 1.9 tons of plutonium in its core (IGCAR, 2003).10 It has been estimated that at 75% capacity factor (CF),11 the PFBR requires 1012 kg of plutonium every year for refuelling (Glaser and Ramana, 2007). Taking into account losses at the fuel fabrication stage, usually estimated to be 1% [Benedict et al., (1981), p.150], the total plutonium requirement is 1,022 kg per year. This plutonium is converted to MOX (mixed oxide) fuel by mixing with uranium. Initially, the PFBR requires 6,549 kg of MOX fuel for the core of the reactor and the axial blanket; the radial blankets require an additional 2,622 kg of uranium fuel (Glaser and Ramana, 2007). The fuel fabrication is being done at the Advanced Fuel fabrication facility at Tarapur (Balu et al., 1998). Later on, the fabrication will be done at the fast reactor fuel cycle facility at Kalpakkam once it is constructed (AERB, 2006). No cost estimates are available for either of these. Therefore, we follow the NEA and assume that the cost of fabricating driver fuel is $1,400/kgHM and the cost of fabricating (radial) blanket fuel is $500/kgHM (both in 2000 dollars), or $1,512/kgHM and $540/kgHM (in 2004 dollars) (NEA, 2002). In our sensitivity analysis, we also consider lower values. As mentioned, the plutonium for the initial core as well as for the first few reloads has to come from reprocessing PHWR spent fuel at KARP. In order for it to be ready in time to fabricate the core, this plutonium would have been required in 2007, three years ahead 6 J.Y. Suchitra and M.V. Ramana of starting reactor operations (Hibbs, 1997a).12 The lifecycle cost of reprocessing at KARP has been estimated at about Rs. 29,010/kgHM at a 6% discount rate (Ramana and Suchitra, 2007).13 Assuming losses of 1% of the plutonium in the spent fuel, this translates to a plutonium cost of Rs. 7,814/g or $178/g. This assumption may be optimistic and experience at DAE run reprocessing plants appears to indicate a higher rate of losses, closer to 3% [Tongia and Arunachalam, (1998), p.552]. Subsequently, the plutonium for the PFBR is obtained from reprocessing its own spent fuel. Because of the higher plutonium content of the PFBR spent fuel, the cost of such plutonium would be lower; we estimate it to be $43/g (see Appendix 1). KARP does not have adequate reprocessing capacity to produce enough plutonium in any given year to fuel the PFBR.14 Therefore, much of the plutonium that is used in the PFBR’s initial loading would have been separated several years before it is fabricated into MOX fuel. As the plutonium ages, one of its isotopes, Plutonium-241, decays into Americium-241, another radioactive material that absorbs neutrons and lowers the amount of energy produced by the reactor. This would have to be chemically separated before the plutonium is fabricated into MOX. The americium removal cost would have to be incurred only in the case of plutonium coming from KARP.15 This has been estimated to cost ‘$18 per gram of plutonium’ in 1987 Dollars, which translates to $26.75 per gram in 2004 dollars [NEA, (1989), p.64]. Table 1 summarises the quantities of materials used to fuel the reactor and their costs. Table 1 Quantities and costs related to PFBR fuel chain Plutonium required for initial core (tons) 1.9 Assumed loss at fuel fabrication plant 1% Amount of plutonium required for core per year (mg/kWh) 0.35 Fabrication requirement for core + axial fuel (mg/kWh) 2.24 Fabrication requirement for radial blanket fuel (mg/kWh) 0.89 Cost of plutonium from KARP ($/g) (in 2004 dollars) 178 Cost of plutonium from PFBR spent fuel ($/g) (in 2004 dollars) 43 Cost of fabricating fuel for core ($/kgHM) (in 2004 dollars) Cost of fabricating fuel for blanket ($/kgHM) (in 2004 dollars) Cost of removing americium from KARP plutonium ($/gPu) (in 2004 dollars) 1,512 540 26.75 According to the PFBR design, the reactor has to be refuelled after ‘180 effective full power days’ of operation (Sodhi et al., 1995). For a CF of 75%, this translates to about eight months. As per design, the spent fuel is stored within the reactor for a further eight months. We assume that it is stored under water for an additional 16 months outside the reactor to give a total storage time of two years.16 During this period, the spent fuel becomes cooler and some of the short lived radioactive substances decay. We assume that reprocessing, fuel fabrication, and the necessary transport operations together take an additional year. In all, the total time between when the fuel is removed from the reactor core and when it reappears as a fresh fuel rod is three years. This means that for at least the first three years of operation, PFBR will require plutonium from KARP. This is in addition to the initial loading of fuel. The costs of power 7 However, if the facility to reprocess the spent fuel from the PFBR is not ready by 2015, then plutonium for further loadings would also have to be obtained from KARP. In September 2007, the chairman of the Atomic Energy Commission announced that a reprocessing plant to deal with the PFBR spent fuel has been planned and that its construction was to commence in 2008 (Kakodkar, 2007). As of June 2008, no budgetary allocations seem to have been made (MoSPI, 2008). Even in 2010, an article by three senior officials closely involved with the breeder programme in the trade journal Nuclear Engineering International only says “a dedicated commercial scale reprocessing plant is proposed to be constructed”. Given the complicated nature of reprocessing plants, the DAE’s very limited experience with reprocessing fast breeder spent fuel,17 and the experience of persistent delays in constructing reprocessing plants in India and elsewhere,18 it is quite likely that reprocessing of PFBR spent fuel will not commence in 2015. 4.2 Pressurised heavy water reactor The bulk of operating reactors in India are PHWRs, of either 220 MW or 540 MW capacity. But, “future PHWRs… are planned to be only of 700 MW unit size” [DAE, (2005), p.26]. Four such 700 MW reactors are at an advanced state of planning and early procurement of equipment has started [DAE, (2008), pp.19–21]. We assume that construction of the first of such reactors is completed by 2015. We use the Indian Nuclear Power Corporation’s estimates of Rs. 52 million/MW in 2005 prices for 700 MW PHWRs (Thakur and Chaurasia, 2005).19 Thus, a twin power station with two 700 MW PHWRs will cost Rs. 69.88 billion in 2004 Rs ($1.58 billion). The corresponding unit cost is Rs. 49,914/kW or $1,134/kW (2004 figures). This is comparable to though slightly lower than estimated costs for the PHWRs that were completed after 2005 or are under construction; these have unit costs ranging from $1,154/kW to $1,204/kW [Bohra and Sharma, (2006), Table 5, p.849]. When compared to the lowest of these, the decreased cost for the 2 × 700 MW power station is less than 2%. We emphasise that the cost data and assumptions are those of the DAE. Assuming the distribution of costs across the years used by Thakur and Chaurasia (2005), we estimate a total construction cost of Rs. 103.93 billion (mixed year figure) for a plant which is constructed by 2015. In addition, the costs of the initial loading of heavy water and uranium, which will be incurred a year before commissioning, have to be included. As our base case, we assume that the uranium is purchased at a cost of $200/kg and fabricating it into fuel costs $200/kgHM.20 This is comparable to reported costs of fabricated uranium fuel in India (Subramanian, 2002). The initial requirement for each 1,400 MW station is about 194 tons of uranium metal (Grover and Chandra, 2006). As with MOX fuel fabrication, we assume 1% losses at the fuel fabrication stage. In all, the initial loading costs Rs. 3.44 billion or $78.2 million (in 2004 figures). Once the reactor commences operation, uranium will be consumed at the rate of 20.7 mg/kWh, which corresponds to an average burnup of 7,000 MWtd/tU (megawatt thermal day per ton of Uranium) (Changrani et al., 1998; Hibbs, 1997b).21 The heavy water cost has been estimated to be Rs. 26,466 or $601 per kilogram (in 2004 figures) (Ramana, 2007). The initial loading of heavy water is 850 tons 8 J.Y. Suchitra and M.V. Ramana [Bhardwaj, (2006), p.862], which would cost Rs. 22.49 billion or $511 million. Some of the heavy water is also lost every year due to evaporation and leaks. In 220 MW PHWRs, this amounts to 7 tons/year [Kati, (2003), p.39]. We scale this by the ratio of power outputs to obtain the corresponding figure of 44.5 tons/y for a 1,400 MW plant.22 All fuel quantities and costs are shown in Table 2. Table 2 Quantities and costs related to 1,400 MW of PHWR capacity Uranium required for initial core (tons) 194 Uranium cost ($/kg) 200 Uranium fabrication cost ($/kgHM) 200 Heavy water required for initial core (tons) 850 Heavy water cost ($/kg) 601 Heavy water losses (tons/y) 44.5 Uranium fuel fabrication losses 1% Uranium fuel requirement (mg/kWh) 20.7 4.3 Other cost elements Some amount of power generated by the reactors is consumed on the site itself. This auxiliary consumption is assumed to be 10% for both reactors. We also assume that both the PFBR and the PHWR store a year’s worth of fabricated fuel and heavy water to account for potential supply disruptions, which is equivalent to the working capital component included in standard electricity cost calculations. This will be returned, and the lifecycle cost adjusted accordingly, at the end of the lifetime of the reactor. Both reactors are expected to undergo refurbishments some time during their operating life. In line with Thakur and Chaurasia (2005), we assume that this will cost 5% of the capital cost and is incurred after 15 years of operation. 4.3.1 Annual non-fuel costs Every year, there will be costs incurred towards operations and maintenance (O&M) of the reactor and waste management at the reactor site itself.23 BHAVINI estimates that the annual O&M cost for the PFBR will be Rs. 690 million ($15.7 million), which translates to 2% of the capital cost; it also assumes that a Rs. 0.05/kWh (or 0.01 mills/kWh) charge will suffice for waste management. This is likely to be an underestimate. Because of the use of liquid sodium, actual O&M costs for breeder reactors are typically much higher. For example, the O&M costs for the French superphénix reactor were FF 1.7 billion per year (1994 figure), which translates to about $320/kW (in 2004 dollars), which is about 8% of the capital cost (IPFM, 2010). Nevertheless, in line with our methodology, we adopt the official figure of 2%. For the PHWR, we assume the same fraction of the capital cost (2%) for O&M costs, which amounts to Rs. 1,397.6 million or $31.8 million (in 2004 figures), and a waste management charge of Rs. 0.05/kWh. The costs of power 9 4.3.2 Decommissioning In line with estimates made by the World Nuclear Association, we assume that decommissioning would cost 10% of the initial capital cost (WNA, 2008). This amount is assumed to be spent in the ratios 40:20:40 at the end of the reactor operations, 20 years, and 40 years after end of reactor operations respectively. Decommissioning might be much more expensive. For example, decommissioning the 60 MWt (megawatt thermal) demonstration fast reactor (DFR) that operated from the late 1950s to 1977 in the UK has been estimated to cost £760 million (1.4 billion in 2004 Dollars) (UKAEA, 2007). This is nearly 20 times the decommissioning cost assumed for the PFBR, a reactor that is about 20 times larger in power capacity. 5 Results Based on the methodology described above and the cost figures listed in the earlier section, the key cost components have been calculated and are presented in Table 3. Table 3 Base case comparison of electricity generation cost PFBR PHWR 646 1,588 6 6 Capital cost (present value) ($million 2004) 504 987 Capacity factors (percent) 80 80 Lifetime plutonium or uranium cost (present value) ($million 2004) 1,480 697 Total lifecycle cost ($million 2004 $) 2,212 2,550 Levelised cost (Rs/kWh) 2.77 1.54 Levelised cost (cents/kWh) 6.30 3.49 Capital cost (overnight construction cost) ($million 2004) Real discount rate (percent) Percentage difference (PFBR-PHWR) 80% Even in our ‘base case’, electricity from the PFBR is 80% more expensive than the corresponding cost from PHWR. The main cost component of the PHWR is the capital cost of the reactor, which constitutes 39% of the total lifecycle cost. The corresponding figure for the PFBR is 23%. The main component of the total lifecycle cost at the PFBR turns out to be that of the plutonium used in the reactor (67%). In comparison, the corresponding uranium cost for the PHWR is only 27%.24 This is primarily because of the much higher costs associated with the production and fabrication of plutonium.25 The higher costs relating to plutonium reflect two factors. First, there are substantial costs associated with simply extracting the metal from the spent fuel, because reprocessing plants are very capital intensive. Second, the fabrications of MOX fuel costs much more than the fabrication of uranium fuel. This in turn is related to two characteristics, one of plutonium itself and one of the fuel for fast breeder reactors. Plutonium being more radioactive and toxic than uranium, fabricating it into fuel requires special facilities so that all possible contact with the material is avoided [Farmer, (1983), p.36]. Fuels for fast breeder reactors produce much more heat per unit volume which has 10 J.Y. Suchitra and M.V. Ramana to be efficiently conducted away. Therefore, they have to be far thinner and structured more intricately than uranium fuel rods for PHWRs.26 5.1 Uranium cost Like breeder advocates elsewhere, the DAE’s argument in favour of the breeder programme in India is that uranium supply is limited. The current estimates are of about 60,000 tons of uranium (Kakodkar, 2006). While widely articulated, this formulation is misleading. India’s uranium resource base cannot be represented by a single number. The resource base increases with continued exploration for new deposits as well as technological improvements in uranium extraction.26 In addition, as with any other mineral, at higher prices it becomes economic to mine lower grade and less accessible ores. In other words, if the PHWR operator is willing to bear a higher cost for fuelling the reactor, the amount of uranium available will be much larger. We therefore address the DAE’s argument about limited uranium resources by considering a range of uranium costs in our comparison of electricity generation costs at breeder reactors and heavy water reactors (see Figure 1). The difference in the generation costs decreases because of the increased cost of fuelling the PHWR. Only when the uranium cost goes up to $1,375/kg, nearly seven times the base case of $200/kg, does the difference become zero. Figure 1 Sensitivity to uranium cost (see online version for colours) 100% Percentage 80% 60% Difference in levelised costs of generation 40% 20% 0% 0 200 400 600 800 1000 1200 -20% 1400 1600 Fraction of uranium cost in PHWR generation cost Uranium cost ($/kg) Figure 1 also shows the fraction that the cost of uranium (including that of fuel fabrication) contributes to the PHWR generation cost. While the plutonium-related costs constitute about 67% of the PFBR generation cost in the base case, uranium-related costs exceed 50% of the PHWR generation cost only at around $800/kg. In other words, one can pay a lot more for uranium without affecting the price of electricity from PHWRs significantly. As explained in Appendix 2, when the uranium cost goes up to $1,375/kg, the availability of uranium increases by a factor of at least about 60 and possibly about 120. It is likely that even these factors underestimate the actual availability in the longer term because of technological improvements. In any case, lack of uranium reserves is unlikely to be a limiting factor for the expansion of nuclear power based on PHWRs for decades.27 The costs of power 11 Around 2005–2008, there were numerous reports that stated that the Nuclear Power Corporation was facing a severe shortage of uranium and even the existing PHWRs (with a capacity of approximately 4,000 MW) could not be fuelled adequately (for example Subramanian, 2006). This does not contradict our estimates of increased uranium availability. The shortage was cause not by a lack of uranium deposits under the ground but due to a mismatch between mining capacity and reactor requirements. 5.2 Sensitivity analysis There are a number of variables that affect the cost of electricity from the PFBR. The most important of these relate to the performance of the reactor, the capital cost, and the costs related to the recovery of plutonium. In our base case, we have used values that are favourable to the economics of the PFBR. 5.2.1 Capacity factor Breeder reactors across the world have been plagued with small accidents and other problems, in part due to the use of liquid sodium as coolant.28 It is not surprising, therefore, that they have had relatively low lifetime CFs (Table 4). Of particular importance is the low capacity factor of the superphenix, which was supposed to be France’s first commercial breeder reactor. In India, the fast breeder test reactor (FBTR) has operated for only 36,000 hours over the first 20 years of its life, or 75 days a year, implying that it functioned for only about 20% of the time [DAE, (2006), p.16]. Table 4 Performance of breeder reactors Date of grid connection Cumulative load factor (percent) Phenix PFR BN-600 Superphenix 13-Dec.-73 10-Jan.-75 08-Apr.-80 14-Jan.-86 41.34 23.87 73.48 6.6 Source: Power Reactor Information System Database, International Atomic Energy Agency, Downloaded 22 March 2009 If the PFBR experience were to be similar, a CF of 50% or less might be more plausible. At 50%, the levelised cost of generation at the PFBR would be Rs. 3.67 per unit (8.35 cents per kWh), 139% more expensive than PHWRs (assuming that the PHWR operates at the same 80% CF). The uranium crossover cost for this case is $2,235/kg. 5.2.2 Capital cost The next parameter that we vary is the capital cost of the PFBR, since there are good reasons for it to escalate. We assume that this is on account of delayed construction, and that the PFBR starts functioning two years later than the projected schedule. An additional 10% of the total cost is assumed to be incurred in each of those years. Therefore, the overnight construction cost increases from $1,292/kW to $1,503/kW. Assuming all the other costs are the same as our base case, the levelised cost of generation at the PFBR would be Rs. 2.88 per unit (6.55 cents per kWh), 88% more expensive than the PHWR. Breeder enthusiasts might claim that future reactors would be cheaper to construct because of learning. Historically, however, nuclear construction costs have not reduced 12 J.Y. Suchitra and M.V. Ramana significantly with time. In the USA, the country with the most nuclear reactors, construction costs grew steadily from $1,279/kW (in 2006 dollars) for reactors commissioned between 1966–1967 to $4,377/kW (in 2006 dollars) for reactors commissioned a decade later (CBO, 2008). The steady growth in costs persisted even in later reactors (Hultman et al., 2007). Similarly, during the late 1970s and 1980s, the period when France brought on line most of its current nuclear power plants, the capital costs (measured in constant francs) actually increased with time, roughly at the same rate as construction costs in general (Grubler, 2009). Increases in cost have also been reported in the series of reactors, with somewhat standardised design, that were commissioned in India in the 1990s [Bohra and Sharma, (2006), p.849]. Nevertheless, in order to account for the possibility of future reduction in costs, we also considered the case where the capital cost of the PFBR is lower by 15%. Assuming all the other costs are the same as our base case, the levelised cost of generation at the PFBR would be Rs. 2.67 per unit (6.08 cents per kWh), 74% more expensive than the PHWR. The reason – the expensive nature of dealing with plutonium – has been elaborated earlier. A variable that is related closely to the capital cost is the discount rate. If we hold all fuelling costs (cost of plutonium, uranium, heavy water, and fuel fabrication) fixed, then at a discount rate of 8%, the levelised costs of electricity generation at the PFBR and PHWR increase to 7.55 cents/kWh and 4.06 cents/kWh, up by 20 and 16% respectively from the base case. This shows that the levelised cost depends sensitively on the discount rate, as expected for a capital intensive technology. The difference between the two levelised costs increases to 86%, as compared to the base case of 80%. 5.2.3 Plutonium cost Since the major share of the PFBR levelised cost comes from the charges for plutonium, we now look at different possibilities for the cost of plutonium recovery. There are two separate elements: the cost of plutonium for the initial core and the first few reloads, and the cost of plutonium from reprocessing PFBR spent fuel. Therefore, there are a number of different combinations possible. Finally, there is also the possibility of a lower cost of fuel fabrication compared to what we have assumed. We illustrate the kinds of variations (see Table 5). The first set of possibilities is related to the cost of plutonium for the initial core and the first few reload. At one extreme is the DAE’s methodology, where KARP plutonium, including the americium removal cost, is assumed to be free. The lifecycle cost of all plutonium from KARP, including the discounted cost of plutonium debited after the PFBR stops operating, is Rs. 39.8 billion ($0.9 billion), 1.8 times the lifecycle capital cost of the PFBR itself. As a strategy for a large expansion of breeder reactors, this is unsustainable. It is also methodologically flawed to assume such a large subsidy while evaluating the economics of the PFBR. At the other extreme, it is possible that the PFBR requires the use of KARP plutonium for a much longer period than we have assumed in our base case, ten loadings instead of five. A third and intermediate possibility, which might be applicable to future breeder reactors, is that all plutonium used is derived from reprocessing the spent fuel of other breeder reactors. Therefore, the plutonium for the entire lifetime of the reactor, including the initial loading, is available at $43/g. The costs of power 13 The next set of possibilities corresponds to the cost of recovering plutonium from the PFBR. There is no official cost figure for reprocessing PFBR spent fuel. As an alternative to our estimate of $43/g, we also consider the lower and higher cases of plutonium costing $21/g and $74/g (see Appendix 1 for details). Yet another scenario that we consider is that PFBR spent fuel is used to make weapon grade plutonium for the nuclear arsenal (Glaser and Ramana, 2007).29 In this case, some of the plutonium recovered by reprocessing the blankets of the PFBR will be diverted for military purposes. To compensate, some plutonium from KARP would have to be acquired. This quantity has been estimated at 345 kg/year at 75% CF. We assume that this varies in proportion to the operational CF. Finally, we also consider the possibility that fuel fabrication is less expensive compared to what we have assumed because of lower labour costs in India. Accordingly we assume that the costs of fabricating driver fuel and (radial) blanket fuel are $756/kgHM and $270/kgHM (in 2004 dollars) respectively, 50% of the values suggested by NEA (2002). This is somewhat extreme because labour is typically only a small component of the costs of fabrication. Table 5 Cost differences (percentage) under different assumptions PFBR capacity factor 80% 50% Base case (KARP plutonium for five years) 80 139 Base case with KARP plutonium at zero cost 9 45 All plutonium from reprocessing breeder reactor spent fuel (at $43/g) 24 65 Base case with KARP plutonium for ten years 118 177 Base case with PFBR plutonium at $74/g 107 166 Base case with PFBR plutonium at $21/g 62 121 Base case with weapon grade plutonium extracted from PFBR spent fuel 126 185 Lower fuel fabrication costs (reduced by 50%) 74 131 For all cases, we see that the cost of electricity from the PFBR is more expensive than from the PHWR. In particular, even for the case where the plutonium from KARP is assumed to be completely free, in other words, the cost is borne by the tax payers, the cost difference ranges from 9% to 45% depending on the performance of the PFBR. Likewise, even if several breeder reactors were to be constructed and the excess plutonium generated by these is sufficient for the initial loading of a new breeder reactor, electricity from the breeder will be more expensive than from a PHWR by 24% to 65%. Even at the lowest of these differences, i.e., 9%, the crossover uranium price is $335/kg, at which price about four times more uranium might be available. If KARP plutonium is required for a longer period, the cost difference varies from 118% to 177%. For the cases of lower and higher plutonium recovery costs from the PFBR, we find that the cost difference varies from 62% to 166%. If the PFBR were to be used to make weapon grade plutonium throughout its lifetime, then the cost difference in electricity goes up from between 126% and 185%, reflecting the higher cost of plutonium from KARP. Finally, if the fuel fabrication costs are only 50% of what we have assumed 14 J.Y. Suchitra and M.V. Ramana in our base case, the cost difference goes down to 74% and 131% for the two assumed CFs. 6 Conclusions The Indian DAE has been constructing PHWRs for close to 40 years and these reactors have dominated the nuclear generation capacity in India thus far. However, the DAE’s plans for expanding nuclear power in the country over the next few decades are based primarily on breeder reactors, which are expected to take over from PHWRs by 2025. The first such reactor, the PFBR, is currently under construction. The DAE has claimed that breeder reactors will be economically competitive with PHWRs. This is despite the fact that the PFBR is the first of its kind while the PHWRs are a relatively mature technology.30 Our results show that this claim is not valid and the cost of generating electricity from the PFBR is much higher than the corresponding cost at PHWRs. In our base case, even with optimistic assumptions for the PFBR’s operating parameters, its electricity cost is 80% more expensive than that from PHWRs. Our sensitivity analysis demonstrates that, even though this percentage might decrease or increase with different assumptions about specific cost items, fuel chain assumptions (for example, whether the plutonium comes from other breeder reactors or from PHWRs), and performance, the conclusion about the higher cost of electricity generation at the PFBR is robust. The high cost of breeder electricity is primarily because producing plutonium and fabricating it into fuel for the PFBR are expensive. This in turn is related to both the inherent properties of plutonium – its greater radioactivity and toxicity as compared to uranium – and the stringent design requirements for breeder reactor fuel. Therefore, the cost differences in the fuel chain will persist. The only way that breeder reactors could become competitive is if the cost of uranium goes up. We have therefore compared the generating costs at the two reactor systems as a function of uranium cost and demonstrate that the crossover uranium cost is $1,,375/kg, nearly seven times the uranium cost of $200/kg used in our base case. This is because the cost of generating electricity at PHWRs is only weakly dependent on the uranium cost. A reactor operator willing to incur such high costs for uranium would have access to much larger quantities of uranium than currently considered economically recoverable. The DAE’s assertion about limited uranium in the country assumes a fixed and static figure for the mineral’s reserves. Once the increased availability as the cost increases is taken into account, the argument that breeder reactors make economic sense in the Indian context can be seen to be flawed. The assumption that breeder electricity will be economical is also the basis for the DAE’s pursuit of reprocessing. As we have shown earlier, reprocessing is expensive as a way of dealing with radioactive spent fuel (Ramana and Suchitra, 2007). Our analysis here shows reprocessing is not economically justified even if the value of the recovered plutonium as fuel is taken into account. We also find that the significant cost difference between electricity from the PFBR and PHWRs persists even if breeder reactor construction were to become significantly cheaper. Lowering construction costs might, however, compromise safety. As it is, the PFBR design reflects cost reduction efforts made in the 1990s (Bhoje, 2001). This design makes it more susceptible to catastrophic accidents (Kumar and Ramana, 2008). The costs of power 15 A non-economic argument that the DAE advances is that breeder reactors are the only option for meeting India’s future power needs (Subramanian, 2004). This claim assumes very rapid growth of breeder reactor capacity to keep pace with demand; however, these projections are based on faulty methodology and unrealistic assumptions (Ramana and Suchitra, 2009). In addition, the DAE’s projections do not take economic considerations into account. The high cost of breeder electricity makes it even less likely that there will be large scale construction of breeder reactors; therefore, they are unlikely to be a significant component of India’s electricity sector in the foreseeable future. References AERB (2006) Project Design Safety Committee for Fast Reactor Fuel Cycle Facility, IGCAR, Kalpakkam (DSRC-FRFCF), available at http://www.aerb.gov.in/ cgi-bin/committees/showcomm.asp?T=dsrcfrfcf.htm&V=DSRC-FRFCF (accessed on 19 August 2006). Bagla, P. (2006) ‘On the record: Anil Kakodkar’, Indian Express, February 8. Balu, K., Purushotham, D.S.C. and Kakodkar, A. (1998) ‘Closing the fuel cycle-A superior option for India’, Paper Presented at Fuel Cycle Options for Light Water Reactors and Heavy Water Reactors, 28 April–1 May, Victoria, Canada. Benedict, M., Pigford, T.H. and Levi, H.W. (1981) Nuclear Chemical Engineering, McGraw-Hill, New York. Bethe, H.A. and Tate, J.H. (1956) An Estimate of the Order of Magnitude of the Explosion when the Core of a Fast Reactor Collapses, United Kingdom Atomic Energy Agency. Bhabha, H.J. (1955) ‘The role of atomic power in India and its immediate possibilities’, Paper Presented at the First International Conference on the Peaceful Uses of Atomic Energy, Geneva, Switzerland. Bhabha, H.J. and Prasad, N.B. (1958) ‘A study of the contribution of atomic energy to a power programme in India’, Paper Presented at Second United Nations International Conference on the Peaceful Uses of Atomic Energy, Geneva. Bhardwaj, S.A. (2006) ‘The future 700 MWe pressurized heavy water reactor’, Nuclear Engineering and Design, Vol. 236, pp.861–871. Bhoje, S.B. (2001) ‘Cost competitiveness of breeder reactor’, Indira Gandhi Centre for Atomic Research Newsletter, October. Bhoje, S.B. (2003) ‘Status of fast reactor development in India’, Paper Presented at International Conference on Nuclear Power Technologies with Fast Neutron Reactors, December, pp.8–12, Obninsk. Bidwai, P. (1983) ‘The fast breeder reactor: DAE’s strange nuclear priorities’, The Times of India, August 31. Bohra, S.A. and Sharma, P.D. (2006) ‘Construction management of Indian pressurized heavy water reactors’, Nuclear Engineering and Design, Vol. 236, pp.836–851. Brealey, R.A. and Myers, S.C. (2000) Principles of Corporate Finance, Irwin McGraw-Hill, Boston. Bunn, M., Holdren, J.P., Fetter, S. and Zwaan, B.V.D. (2005) ‘The economics of reprocessing versus direct disposal of spent nuclear fuel’, Nuclear Technology, Vol. 150, pp.209–230. CBO (2008) Nuclear Power’s Role in Generating Electricity, United States Congressional Budget Office, Washington, DC. CERC (2006) Annual Escalation Rates for Bid Evaluation: Central Electricity Regulatory Commission Notification Eco 2/2006-CERC, (accessed on 9 November 2006). 16 J.Y. Suchitra and M.V. Ramana CERI (2004) Levelised Unit Electricity Cost Comparison of Alternate Technologies for Baseload Generation in Ontario, Canadian Energy Research Institute, prepared for the Canadian Nuclear Association, Calgary, Alberta. Changrani, R.D., Bajpai, D.D. and Kodilkar, S.S. (1998) ‘Storage of spent fuel from power reactor in India: management and experience’, Paper Presented at Storage of Spent Fuel from Power Reactors, 9–13 November, Vienna. Chetal, S.C., Balasubramaniyan, V., Chellapandi, P., Mohanakrishnan, P. et al. (2006) ‘The design of the prototype fast breeder reactor’, Nuclear Engineering and Design, Vol. 236, pp.852–860. Chow, B.C. (1995) ‘Plutonium economics and the civilian nuclear future’, Paper Presented at the Global’95, 11–14 September, Versailles, France. Cochran, T.B. (1974) The Liquid Metal Fast Breeder Reactor: An Environmental and Economic Critique, Resources for the Future, Inc., Washington DC. DAE (1991) Performance budget 1990-91, Department of Atomic Energy, Mumbai. DAE (1996) Performance budget 1995-96, Department of Atomic Energy, Mumbai. DAE (2002) Performance budget 2001-2002, Department of Atomic Energy, Mumbai. DAE (2005) Annual Report 2004-2005, Department of Atomic Energy, Mumbai. DAE (2006) Atomic Energy in India: A Perspective, Department of Atomic Energy, Government of India, Mumbai. DAE (2008) Annual Report 2007-08, Department of Atomic Energy, Mumbai. Deffeyes, K.S. and Macgregor, I.D. (1980) ‘World uranium resources’, Scientific American, January, pp.66–76. Farber, S. (1991) ‘Nuclear power, systematic risk, and the cost of capital’, Contemporary Economic Policy, Vol. IX, pp.73–82. Farmer, A.A. (1983) ‘Recycling of fuel’, in Marshall, W. (Ed.): Nuclear Power Technology, pp.1–55, 1986 Reprint ed., Oxford University Press, Oxford. Farmer, A.A. (1984) ‘Assessing the economics of the liquid metal fast breeder reactor’, in Brookes, L.G. and Motamen, H. (Eds.): The Economics of Nuclear Energy, Chapman and Hall, London. Feiveson, H.A., Von Hippel, F. and Williams, R.H. (1979) ‘Fission power: an evolutionary strategy’, Science, Vol. 203, pp.330–337. Glaser, A. and Ramana, M.V. (2007) ‘Weapon-grade plutonium production potential in the Indian prototype fast breeder reactor’, Science and Global Security, Vol. 15, pp.85–105. Grover, R.B. and Chandra, S. (2006) ‘Scenario for growth of electricity in India’, Energy Policy, Vol. 34, No. 17, pp.2834–2847. Grubler, A. (2009) An Assessment of the Costs of the French Nuclear PWR Program 1970-2000, International Institute for Applied Systems Analysis, Laxenburg, Austria. Haire, M.J. (2003) ‘Nuclear fuel reprocessing costs’, Paper Presented at the Advances in Nuclear Fuel Management III, 5–8 October, Hilton Head Island, SC. Hamada, R.S. (1972) ‘The effect of the firm’s capital structure on the systematic risk of common stocks’, The Journal of Finance, Vol. 27, No. 2, pp.435–452. Hibbs, M. (1990) ‘India’s new breeder will be on line by 2000, Iyengar says’, Nucleonics Week, Vol. 31, No. 42, p.11. Hibbs, M. (1997a) ‘Despite chronic delays, DAE maintains prototype breeder to be built soon’, Nuclear Fuel, Vol. 22, No. 24, p.9. Hibbs, M. (1997b) ‘First separation line at Kalpakkam slated to begin operations next year’, Nuclear Fuel, Vol. 22, No. 24, pp.8–9. Hibbs, M. (2003) ‘DAE reprocessing program remains modest in scope’, Nuclear Fuel, Vol. 28, No. 8, p.9. Hultman, N.E., Koomey, J.G. and Kammen, D.M. (2007) ‘What history can teach us about the future costs of U.S. nuclear power’, Environmental Science & Technology, Vol. 40, No. 7, pp.2088–2094. The costs of power 17 IGCAR (2003) Design of Prototype Fast Breeder Reactor, available at http://www.igcar.ernet.in/broucher/design.pdf (accessed on 10 March 2006). IPFM (2010) Fast Breeder Reactor Programs: History and Status, International Panel on Fissile Materials, Princeton, NJ. Kakodkar, A. (2006) ‘Securing our emerging energy needs: what nuclear energy can do’, Energy Security Insights, Vol. 1, No. 1, pp.4–7. Kakodkar, A. (2007) ‘Statement’, Paper Presented at 51st General Conference, September 19, Vienna. Kati, S.L. (2003) ‘Conceptual design of heavy water moderated organic cooled reactor’, Nu-Power, Vol. 17, No. 4, pp.36–39. Kroch, E. (1979) ‘Estimating long-run marginal costs for minerals: the case of uranium’, Resources and Energy, Vol. 2, pp.275–292. Kumar, A. and Ramana, M.V. (2008) ‘Compromising safety: design choices and severe accident possibilities in india’s prototype fast breeder reactor’, Science and Global Security, Vol. 16, pp.87–114. Lev, B. (1974) ‘On the association between operating leverage and risk’, Journal of Financial and Quantitative Analysis, Vol. 9, No. 4, pp.627–641. Lidsky, L.M. and Miller, M.M. (2002) ‘Nuclear power and energy security: a revised strategy for Japan’, Science and Global Security, Vol. 10, pp.127–150. Macfarlane, A. and Miller, M.M. (2007) ‘Nuclear energy and uranium resources’, Elements, Vol. 3, pp.185–192. Mandlekar, G.N. and Rhee, S.G. (1984) ‘The impact of the degrees of operating and financial leverage on systematic risk of common stock’, Journal of Financial and Quantitative Analysis, Vol. 19, No. 1, pp.45–57. MoSPI (2008) Project Implementation Status Report of Central Sector Projects Costing Rs.20 crore & above (April-June, 2008), Ministry of Statistics and Programme Implementation, New Delhi. National Research Council (1996) Nuclear Wastes: Technologies for Separations and Transmutation, National Academy Press, Washington, DC. NEA (1989) Plutonium Fuel: an Assessment, Nuclear Energy Agency, OECD, Paris. NEA (1993) The Safety of the Nuclear Fuel Cycle, Nuclear Energy Agency, OECD, Paris. NEA (1994) The Economics of the Nuclear Fuel Cycle, Nuclear Energy Agency, OECD, Paris. NEA (2002) Accelerator-driven Systems (ADS) and Fast Reactors (FR) in Advanced Nuclear Fuel Cycles, Nuclear Energy Agency, OECD, Paris. NEA (2008) Uranium 2007: Resources, Production and Demand, Nuclear Energy Agency, OECD and International Atomic Energy Agency, Paris. Neffe, J. (1985) ‘Kalkar may fall at last hurdle’, Nature, Vol. 317, p.8. NUKEM (1997) ‘Is the superphenix dream over...or over yonder?’, NUKEM, March, pp.4–17. Paranjpe, S.R. (1991) ‘An update on Indian fast breeder programme’, Paper Presented at International Conference on Fast Reactors and Related Fuel Cycles, October 28–November 1, Kyoto. Raj, B. (2005) ‘The core of stage two’, Nuclear Engineering International, Vol. 50, No. 614, p.36. Ramana, M.V. (2007) ‘Heavy subsidies in heavy water’, Economic and Political Weekly, Vol. XLII, No. 34, pp.3483–3490. Ramana, M.V. and Suchitra, J.Y. (2007) ‘Costing plutonium: economics of reprocessing in India’, International Journal of Global Energy Issues, Vol. 27, No. 4, pp.454–471. Ramana, M.V. and Suchitra, J.Y. (2009) ‘Slow and stunted: plutonium accounting and the growth of fast breeder reactors’, Energy Policy, Vol. 37, pp.5028–5036. Ramana, M.V., D’Sa, A. and Reddy, A.K.N. (2005) ‘Economics of nuclear power from heavy water reactors’, Economic and Political Weekly, Vol. XL, No. 17, pp.1763–1773. 18 J.Y. Suchitra and M.V. Ramana RNPDA (1980) An Estimate of CFR Fuel Reprocessing Costs and Prices for an Ongoing Programme of Fast Reactors, Risley Nuclear Power Development Establishment, United Kingdom Atomic Energy Authority, Risley, UK. Schneider, E. and Sailor, W.C. (2008) ‘Long term uranium supply issues and estimates’, Nuclear Technology, Vol. 162, pp.379–387. Sodhi, B.S., Chander, S., Chetal, S.C., Selvaraj, A. et al. (1995) ‘Conceptual design of core component handling system in PFBR’, Paper Presented at Conceptual Designs of Advanced Fast Reactors, Kalpakkam, India. Srinivasan, M.R., Grover, R.B. and Bhardwaj, S.A. (2005) ‘Nuclear power in India: winds of change’, Economic and Political Weekly, Vol. XL, No. 49, pp.5183–5188. Srinivasan, N. (1985) ‘Indian fuel cycle industry’, Paper Presented at Indo-French Seminar on Nuclear Energy, 1–4 April, Bombay. Subramanian, T.S. (2002) Email Communication. Subramanian, T.S. (2004) ‘A case for breeder reactors’, Frontline, November 6. Subramanian, T.S. (2006) ‘Uranium crisis’, Frontline, January 13, pp.60–65. Subramanian, T.S. (2010) ‘Prototype fast breeder reactor crosses milestone’, Hindu, May 14. Suchitra, J.Y. and Ramana, M.V. (2007) ‘Fast breeder of expenditure?’, Hindustan Times, October 23. Takata, T., Koma, Y., Sato, K., Kamiya, M. et al. (2004) ‘Conceptual design study on advanced aqueous reprocessing system for fast reactor fuel cycle’, Journal of Nuclear Science and Technology, Vol. 41, No. 3, pp.307–314. Thakur, S. and Chaurasia, B.P. (2005) Cost Effectiveness of Electricity Generating Technologies, Nuclear Power Corporation, Mumbai. TOI (2009) ‘India’s first fast breeder reactor to be ready next year’, Times of India, February 1. Tongia, R. and Arunachalam, V.S. (1998) ‘India’s nuclear breeders: technology, viability and options’, Current Science, Vol. 75, No. 6. UKAEA (2007) Dounreay Site Summary, available at http://www.nda.gov.uk/documents/loader.cfm?url=/commonspot/security/ getfile.cfm&pageid=3962 (accessed 13 March 2008). Wilburn, D., Goonan, T. and Bleiwas, D. (2005) Technological Advancement – A Factor in Increasing Resource Use, United States Geological Survey, Reston, VA. WNA (2008) The Economics of Nuclear Power, World Nuclear Association, London. Notes 1 2 3 4 5 Unless otherwise specified, watts refers to electrical power. Fast breeder reactors are thus termed because they are based on energetic (fast) neutrons and because they produce (breed) more fissile material than they consume. The higher discount rate is required because the expected rate of return on an investment is the sum of return on a risk free instrument and the product of the systematic risk, beta, with the difference in the expected rate of return of the risky and risk free investments. Beta is the ratio of the covariance of the investment with the market and the variance of market returns. Since beta is higher for nuclear plants, it would require a higher rate of return on the equity component (Farber, 1991). We thank Professor R. Srinivasan of the Indian Institute of Management, Bangalore for pointing this out to us and for calculating the increase in discount rate on account of the higher systematic risk. Passed in 2005, the Right to information act was intended to enable citizens to access information from public organisations in order to promote transparency and accountability. The costs of power 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 19 In line with the DAE’s philosophy of not treating spent fuel as waste, we do not include the cost of dealing with this highly radioactive material; however, in the case of the PFBR, the cost of reprocessing its spent fuel is indirectly included in the fuelling cost. At 75% capacity factor, assuming losses of 1% each at the reprocessing and fuel fabrication stages, the PFBR will produce about 21 kg of plutonium over and above its own fuel requirement (Glaser and Ramana, 2007). Thus, it would take about 90 years of operation for it to produce enough plutonium for the core of a similar reactor. This does not include the expenditures on the PFBR prior to 2004, which amount to 1.24 billion in mixed year Rupees. Such cost increases could affect the PHWR as well. The details of the different isotopic fractions have not been mentioned here because they are not relevant to our economic analysis, but they can be found in (Glaser and Ramana, 2007). The capacity or load factor is a measure of the efficiency of plant operations and is the ratio of the actual electricity generated in a given period of time to what it could have generated if the plant had been working at maximum power continuously for the same period. In September 2007, it was announced that “production of the mixed oxide fuel for PFBR has already commenced” (Kakodkar, 2007). This is a lifecycle cost and thus costs over an assumed lifetime of 15 years. KARP has a maximum capacity of 100 tons/year. Typical PHWR spent fuel has 3.75 kg of plutonium in each ton of spent fuel. Assuming 1% losses, KARP produces 371 kg of plutonium per year. The annual fuel requirement of PFBR at even 50% CF is 681 kg. The assumption is that the plutonium derived from reprocessing PFBR spent fuel is used almost immediately; if there are delays in such use, there would be further americium removal costs. We neglect this possibility. Reprocessing of the FBTR spent fuel also required a cooling period of two years (Raj, 2005). Likewise, worldwide experience of reprocessing of MOX fuel from fast breeder reactors is also sparse and limited only to pilot scale amounts (tens of tons in all) [NEA, (1993), p.234]. According to various DAE performance budgets KARP took 16 years to construct and the relatively small facility that reprocesses FBTR spent fuel took 13 years to construct. In comparison, coal plants in India are typically estimated to cost Rs. 40 million/MW; so a 500 MW plant like the PFBR will cost about Rs. 20 billion ($455 million). Similar figures for 500 MW of hydropower, wind, and combined cycle gas plants are Rs. 22.5 billion, 21 billion, and 15 billion respectively. These refer to long term contract prices, not spot prices that are typically reported. The latter represent only a small fraction of the total uranium market and tends to have high volatility due to short term mismatches between supply and demand. The burnup is the amount of thermal energy produced per unit of fuel. The thermal efficiency of Indian PHWRs is 0.29. This may be an overestimate because losses typically grow at a rate slower than power rating of reactors. Our use of this assumption is favourable to the economics of breeder reactors. The waste management cost does not include the cost of dealing with highly radioactive spent fuel, which is reprocessed. It only covers the cost of dealing with the low and intermediate level radioactive wastes generated during routine reactor operations. This share of uranium cost is larger than in other countries and studies, for example (CERI, 2004), because we have assumed that uranium is purchased at $200/kg, which is representative of uranium mining costs in India. This is higher than elsewhere (for example, (CERI, 2004) assumes uranium costs of about $15 to $35/kg) because of the poor quality of uranium ore in India. Assuming a lower uranium cost would only make the breeder more uneconomical. For a more elaborate discussion of PHWR generation costs in India, see (Ramana et al., 2005). Note also that our definition of uranium costs includes the cost of the initial fuel loading; other studies, such as (CERI, 2004), include this in the capital cost because it is spent before the reactor is commissioned. 20 25 26 27 28 29 30 31 32 33 34 J.Y. Suchitra and M.V. Ramana The lower cost assumed for the PFBR when compared to other countries is also a factor. Similarly, most comparisons of breeder reactors and LWRs assume much larger reprocessing plants with substantial economies of scale compared to the Indian case. This has been elaborated in Appendix 1. This is reflected in the DAE’s estimates of uranium availability over the decades, which has increased from about 15,000 tons in the early 1950s (Bhabha, 1955), to the current 60,000 tons. In addition to these more definitive resources, there are also resources about which there is greater uncertainty. Including these will double the availability [NEA, (2008), p.207]. The DAE typically does not publicise these additional resources, possibly because it would undermine the rationale for greater emphasis on breeders. This is also borne out by the fact that in spite the continued increase in uranium estimates, the DAE has continued to maintain that only 10,000 MW of PHWR can be supported by the available uranium in the country. We deliberately restrict ourselves to domestic uranium reserves. Though breeder enthusiasts claim that sodium reactor technology is robust, experience around the world has demonstrated that sodium cooled systems often suffer serious disruptions even in the event of relatively minor failures. Sodium reacts violently with air and water. The problem is exacerbated because sodium is opaque, which does not allow for visual detection of faults (unlike reactors that use light or heavy water, which are transparent). These technological problems strongly suggest that any large scale breeder reactor would be prone to problems [Lidsky and Miller, (2002), p.140]. The isotopic composition of the plutonium that will be bred in the blankets of the PFBR is well suited to make nuclear weapons. The DAE has not ruled out this possibility. During the negotiations on the Indo-US nuclear deal, when the issue of putting the PFBR on the civilian list under IAEA safeguards was raised, the DAE’s secretary said: “both, from the point of view of maintaining long-term energy security and for maintaining the minimum credible deterrent [in other words, increasing the size of the nuclear weapons arsenal], the fast breeder program just cannot be put on the civilian list” (Bagla, 2006). However, as argued earlier, there may not be any significant reductions in reactor construction cost due to learning. The original design capacity of the FBTR is 42 MWt (thermal). The spent fuel has been discharged with a burnup of 100,000 MWtd/t or more. Even at a hundred percent capacity factor, therefore, the reactor will discharge only about 150 kg/y of spent fuel. This includes the costs of decommissioning the reprocessing and associated servicing plants. We follow the OECD’s Nuclear Energy Agency and assume that these cost ‘30% of the original capital cost’, and that the expenditure is assumed to start 20 years after the end of the operating life of the plant and is spread out over seven years [NEA, (1994), p.114]. In India, for example, though uranium has been mined only in the state of Jharkand, one can find uranium even in the Himalayan ranges, albeit at concentrations of 1.88 to 28.6 ppm (Macfarlane and Miller, 2007). This is true till the ore grade becomes about 1 ppm, beyond which the availability starts declining. The costs of power 21 Appendix 1 Reprocessing of PFBR spent fuel There are no publicly available cost estimates for reprocessing of spent fuel from PFBR (Suchitra and Ramana, 2007). The only reprocessing plant in India that deals with breeder reactor spent fuel is the one associated with the FBTR. Its capacity, which is not mentioned in DAE documents, does not have to be more than 200 kg/y.31 DAE budgets show that this plant cost Rs. 8.2 billion (28 million in 2004 dollars). To this we have to add the costs associated with waste management and operations and maintenance. Our assumption for the capital cost of the waste management plant is based on the cost of the waste immobilisation plant at Tarapur (Ramana and Suchitra, 2007). The annual recurring costs are assumed to be Rs. 50 million ($1.1 million). We scale these up to obtain the corresponding costs for reprocessing spent fuel from the PFBR, using the standard rule of thumb that costs scale with the plant capacity to the power of 0.6 [National Research Council, (1996), p.421]. Since the DAE has not even mentioned the size of the reprocessing plant it will build to deal with PFBR spent fuel, we start by noting that the PFBR produces about 12.2 tons/year of spent fuel even at 100% CF (Glaser and Ramana, 2007). We assume that this requires a reprocessing plant designed to handle about 17 tons/year. Such a plant could operate at around 70% CF and yet deal with all the spent fuel of the PFBR. For a dedicated plant with capacity 17 tonsHM/year, the reprocessing cost, scaled up from that of the FBTR reprocessing plant, is $5,017 per kgHM (kilogram of heavy metal in spent fuel).32 Since, the FBTR reprocessing plant is co-located with the reactor, scaling up from its cost takes into account the savings resulting from this proximity. Since there are no large reprocessing plants that deal with breeder reactor spent fuel, all available cost figures are only estimates. The most detailed of these that we have come across are for a plant that was proposed to deal with the spent fuel of the commercial fast reactor in the UK, which was ultimately never built. That plant was designed to reprocess 250 tons/y and was to cost £756 million (1979 figures) which translates to about $3.3 billion (2004 figures) (RNPDA, 1980). Its O&M costs were estimated at 40.2 million pounds (1979 figures) which translates to about $177 million/year (2004 figures). At 70% CF, therefore, reprocessing breeder spent fuel would cost $2973 per kgHM (in 2004 Dollars). A more recent estimate for a 50 t/y plant is $5,400 per kgHM of breeder spent fuel (Takata et al., 2004). These two figures are comparable if scaled by a power of 0.6.If the UK cost figure is scaled down to 17 tons/y, then the corresponding reprocessing cost would be $8,714/kgHM. Some have argued on the basis of estimates of costs of reprocessing plants that the rule of thumb typically used, i.e., scaling by a power of 0.6, is not valid when extrapolating from very large units to very small units, i.e., over a large range and that “small plants are disproportionately expensive” (Haire, 2003). This could be avoided by comparing the costs of reprocessing at the 17 tonsHM/year capacity with the estimated cost of a 15 tonsHM/year reprocessing plant, “designed to provide reprocessing services for just one or two demonstration breeder reactors… The cost for such a stand-alone facility, built for and dedicated to reprocessing, was 0.8 ± 0.2 billion 1982 dollars” (Haire, 2003). Just accounting for this capital cost without including any of the O&M costs and decommissioning would result in reprocessing costs of over $11,000/kgHM 22 J.Y. Suchitra and M.V. Ramana (in 2004 dollars). Thus our estimate of $5,017/kgHM is generous to the economics of the PFBR. One could argue that the economies of scale dictate that a much larger reprocessing plant should be built. This would have two problems. One is that there would be additional costs for transportation and other infrastructure, which are avoided by having appropriately sized reprocessing plants at the same site as the reactor. This argument has historically been the reason for the DAE’s preference for smaller plants co-located with the reactor (Srinivasan, 1985). The second problem is that such a plant would lie idle for a significant fraction of its initial years because there is only one breeder reactor under construction at the present. The low level of use during the initial years will drive up the costs of reprocessing. However, to explore the sensitivity to lower costs due to economies of scale, we also assume a plant that is sufficient for five more reactors the same size as the PFBR. The spent fuel discharged by the PFBR has about 12% plutonium when both core and the blanket elements are reprocessed together. At a reprocessing cost of $5,017/kgHM, therefore, the cost of plutonium is about $43/g, provided 99% of the plutonium is recovered from the spent fuel. In our sensitivity analyses, we also considered plutonium costs of $74/g and $21/g, corresponding to reprocessing costs of $8,714/kgHM and $2,500/kgHM (roughly half of our estimate) respectively. The latter corresponds to the cost that would be expected if the reprocessing plant is sufficient to service the fuel from six reactors of the same capacity as the PFBR, the plant operates at the same capacity factor of 70% as assumed for the smaller plant, and there are no additional costs due to transportation of spent fuel to this facility. Appendix 2 Uranium availability and costs There is a general perception that uranium is a scarce resource. However, uranium has an average concentration in the earth’s crust of 2.8 parts per million (ppm), and is more abundant than silver or tungsten [Schneider and Sailor, (2008), p.380]. Uranium deposits are found in several different kinds of rocks, such as sedimentary, igneous, and metamorphic rocks, as well as in seawater.33 Geologists have roughly estimated the amount of uranium present as a function of grade, and find that there is roughly a three hundred fold increase in the estimated amount of recoverable uranium for every ten fold decrease in the ore grade (Deffeyes and MacGregor, 1980).34 This means that the availability of uranium is related to the ore grade by a power law: n ⎛G ⎞ U 2 = U1 ⎜ 1 ⎟ where U is the quantity of uranium available at a certain ore grade G. ⎝ G2 ⎠ The exponent n is the slope of the uranium availability curve, which is estimated at about 2.5 in the range of ore grades that are being currently mined (Deffeyes and MacGregor, 1980). There are different possible relationships between the ore grade and the cost of obtaining uranium from that ore (Schneider and Sailor, 2008). The simplest assumption is that the cost of uranium mining is inversely proportional to the ore grade, and the price of The costs of power 23 uranium is directly proportional to the cost of mining. Then, the relationship between uranium availability and price of uranium becomes: n ⎛P ⎞ U 2 = U1 ⎜ 2 ⎟ where U is the uranium availability at a certain uranium price P. Since ⎝ P1 ⎠ n is rather large, the amount of uranium available goes up sharply as the price goes up. Therefore, if the cost of uranium goes up from our base case value of $200/kg to the base case crossover value of $1,375/kg, then the uranium availability will go up by a factor of: 5 U ($1,375) ⎛ 1,375 ⎞ 2 = = 124 . U ($200) ⎜⎝ 200 ⎟⎠ Other models are somewhat more conservative. One model that includes both the costs of extraction and discovering new resources suggests that 1 ⎛P ⎞ U 2 − U1 = ln ⎜ 2 ⎟ b ⎝ P1 ⎠ where b = 0.00054 and U is the cumulative uranium ore quantity in thousands of tons (Kroch, 1979). In this model, for the same increase of $200/kg to $1,375/kg in uranium price, the uranium availability will go up by a factor of 60.5. The assumption that mining poorer quality ores will necessarily be costlier might not be justified and the price could come down because of technological improvements. This has been the case with other minerals. For example, during the period 1900–1998, world copper production increased by 2,465% while its constant dollar price and the average ore grade decreased by 75% and seven fold respectively (Wilburn et al., 2005).
© Copyright 2026 Paperzz