Procedure for obtaining Certificate of Conformity – for Modification

EHS-CSP-04
1.0
Procedure for obtaining Certificate of Conformity – for Modification Works (COC-MW)
Purpose
The purpose of this procedure is to describe and outline the method, how the contractor working Under
TRAKHEES jurisdiction will apply & obtain COC for Modification Works.
2.0
Scope
This procedure will apply to the contractors involved in the modification Works Under TRAKHEES
jurisdiction.
3.0
Procedure to be followed
3.1
All modification works carried out in areas under the jurisdiction of Trakhees, Environment, Health and Safety
must take into consideration with the requirements of EHS regulations and standards. In order to ensure that
Certificates of Conformity – Modification Works must be obtained before starting any modification activities
at site. The flow charts provide a step by step guide to the contractors for familiarizing with the process.
3.2
Certificate of Conformity - COC
Application for COC must be made by the Contractor of the modification works. Application must be made
after the site has been established but before starting any construction activities.
3.3
Safety Advisor/Inspector
Safety supervision is must for all types of modification works as per the attached selection matrix for safety
advisor or Safety inspector.
3.4
Inspection Fees
Inspection fees of AED 1000 should be paid and copy of the payment receipt should be submitted with the
application form.
4.0
Attachments
4.1
Certificate of Conformity Form – Modification Works (CSF-04a)
4.2
Flow Chart for obtaining COC - Modification Works (CSF-04b)
4.3
Selection Matrix for COC Modification Works (CSF-04c)
4.4
Selection Matrix of Safety Advisor/Inspector (CSF-04d)
5.0
Applicable Regulations
5.1
EHS Environmental Control Rules & Regulations
5.2
Health, Safety & Fire Protection Regulations & Standards
5.3
EHS Environmental Nuisance Regulations
5.4
EHS Food Establishment Guidelines(If applicable)
5.5
Green Building Regulations for Dubai World Developments.(If applicable)
5.6
FZ/DM Regulations (where applicable)
6.0
EHS Contacts
All queries with regard to above procedures to be addressed to EHS Administrator / Document Controller via
email: [email protected] or Telephone 04 8811881
REVISION: 01
January 2012
PAGE
Note: Please refer www.ehss.ae to ensure that this document is current and applicable
1 of 1
EHS-CSP-04
CSF-04b
Flow chart for obtaining COC for Modification Works
Contractor /
Consultant /
Client
Contractor
Contractor /
Consultant /
Client
Contractor
Contractor
Contractor
Contractor
EHS
Download COC form for
Modification Works from
www.ehss.ae
Take adequate safety measures at site and
complete COC for Modification works form
Obtain Modification Permit from
Trakhees CED
Submit COC-MW form in PDF (signed &
stamped by Contractor & Consultant)
by email to
[email protected]
Reapply
for COC
Receive payment advice by email & take the
letter copy to Cashier at EHS Main Office or
dragon mart Trakhees office to pay inspection
fees (AED 1000)
Send the scanned copy of payment
receipt along with the letter copy to
[email protected]
EHS will check safety compliance at site as per the
COC-MW form
(within 3 working days) after issuing the tracking
number
Are COC requirements
complied
on the site?
No
Yes
EHS
Issue COC on satisfactory
compliance (within 2 working days
from the inspection date)
)
REVISION: 02
April 2014
Page 1 of 1
EHS-CSP-04
CSF-04c
SELECTION MATRIX - COC MODIFICATION WORKS
Applicable for all type of buildings with building completion certificate from Trakhees
2
Description
Minor Modifications - Internal wall finishes, Furnishings, Low height
partitions, Flooring, Replacing existing windows & doors (in dry walls)
Work involving fixing of ready made units / items
3
Villa landscaping (Soft)
No
4
Installation of A/c Units (Below 4 meter height)
No
5
Relocation of movable furniture’s & Fixtures
No
6
External cleaning of buildings
Yes
7
Structural Modifications / Demolition / Refurbishment
Yes
8
Work involving fixing of hoardings / big sign boards
Yes
9
Commercial units with floor area size ≥ 80 Sq.mt
Yes
10
Renovation of any structure
Yes
11
Renovation of Mezzanine floor of any type
Yes
12
Work involving Hot works
Yes
13
Maintenance on Fragile roof / Warehouse roof
Yes
14
Work in a Confined Space
Yes
15
Work at Height (above 2.0 meter height)
Yes
16
Yes
18
Work involving use of Mechanical Plants & Cranes, Cradles etc.
Work carried out over water (Depth more than 500 mm & width more than 1
meter)
Addition / en-routing, existing/new under ground or buried services
19
Widening / resurfacing of asphalt / concrete roads
Yes
20
Construction of boundary wall / fencing
Yes
21
Excavation with a depth ≥ 1.2 Meter
Yes
22
Opening of concrete floors ≥ 4 Sq. mt
Yes
S. No
1
17
COC Required
No
No
Yes
Yes
A special permission from EHS is required for any other type of construction other than the above
selection matrix. Such requests need to be forwarded to [email protected] and necessary
replies need to be obtained prior starting any construction activities.