Smart Homes – Wall Insulation Standard Technical Details Effective 3rd December 2014 These standard details should be followed for the Smart Homes project and quotations should confirm whether this is the case. The Smart Advisor will assume these details are being used, unless otherwise indicated, when reviewing the quotes and schedules of works submitted for grant approval. Where there are alternative options given within the standard approach the option used should be stated clearly on the quote or schedule of works. General All installs must be undertaken following the guidance set out in PAS2030 including, but not limited to, treating all critical junctions. Furthermore, installers must follow the system designer’s guidelines for working practices as set out in their BBA Certificate and method statement. Critical junctions’ technical details must be submitted for approval. This is only required once per installer, unless a different system is proposed in subsequent installations. Pipes and Guttering Where a plastic soil pipe or down pipe can be moved, extended and reconnected it must be and it is imperative that the system is run behind to avoid a cold bridge. Additional pipework may be needed, e.g. a swan neck. The only acceptable reason for not extending a plastic pipe is fouling of the driveway or garage, excessive obscuring or fouling of a window or obscuring a public highway. Where a plastic pipe cannot be extended for the above reasons installers must install an appropriate cold bridge solution. Details must be submitted for approval. The system must not be chamfered into the pipe or extended for no valid reason. A cast iron pipe has limited ability to be extended and so installers have the option to either replace with new plastic or install the Thermo Pro Soil Pipe cold bridge solution. An acceptable alternative connection must be provided whilst the installation is being undertaken to ensure continuity of services. All gutters and gulleys should be free of debris and in good working order. Any damage must be repaired or the item replaced. This cost is eligible for Smart Homes funding. Reveals All reveals (both window and door) must be insulated. Proposed technical details must be submitted for approval.. Where a standard insulation product is not suitable due to fouling of the opening, a thinner aerogel based (or equivalent)cold bridge solution must be used. Hacking off existing plaster / render (where applicable) may be needed to provide the required room to insulate these reveals. Please make a note of which of the following approaches you are taking to reveals in the quote/schedule of works: Where a window has suitable amount of clearance to allow, we insist that a 20mm grey EPS (or equivalent) reveal board is installed. Where a window has clearance to allow for a reveal board but not enough to accommodate the EPS, we insist that 10mm Aerogel insulation (or equivalent) is installed. Technical details must be submitted for approval. For both of the above options, it is imperative that the window is not fouled both in terms of operation and ventilation. Please consider removing existing render (where applicable) to allow for the above and to ensure the operation and ventilation is not impeded. Where a window does not allow enough clearance to install either of the first two options and there is no existing render to remove, we insist that installers provide an insulated render solution. Details must be submitted for approval. Whilst the render offers minimal thermal performance it is imperative that the system is finished in this way. It reduces the potential for cold bridging at this junction and ensures the system is weather tight. Please make a note of which of the following approaches you are taking to reveals in the quote/schedule of works. Ventilation All vents must be kept clear and existing flues / vents extended as set out by the HHIC. Additional ventilation may be required. Fuel Burning Appliances/Combustion Air Ventilators All fuel burning appliances require an adequate air supply and a clear flue to operate correctly. With an appliance in good working order the main product of combustion is carbon dioxide. Carbon Monoxide is produced though when a flue is blocked or the air supply is impaired. You cannot see, smell or taste carbon monoxide, but it is an extremely toxic gas. With this in mind it is absolutely imperative that any existing combustion air ventilator is maintained and extended through the solid wall system. If there is a fuel burning appliance within the property and there is no existing combustion air ventilation, then the advice of a qualified Gas Safe engineer should be sought. Air Bricks and Ventilators There are potentially many other air bricks and ventilators on external solid walls and where these continue to serve a purpose they must obviously be maintained. These may include under floor air, room ventilators, extract fans and larder/food storage cupboards. Bathroom and kitchen ventilators should be maintained as should gable end airbricks. Vents serving ducted air systems must not be compromised. Airbricks may have been sealed by the occupants. The installer should be mindful of the Building Regulations Part F and the requirement for permanent low level ventilation in all rooms and should not collude with any action that renders the property worse than before. They should either open the sealed ventilators or else ensure that a suitable alternative is provided. Any decision to block off any existing superfluous vents that have been sealed or decommissioned should be discussed and documented with the homeowner. Additional Ventilation Where condensation already appears to be a problem the homeowner should be advised that they should consider the installation of a mechanical vent or extract fan in the kitchen or bathroom, or the retrofitting of trickle vents to windows at window heads and with suitable adjustable cowls. The cost of these is eligible for grant funding. Please make a note of any additional ventilation that is being installed within the quote/schedule of works. Verge Trims and Eaves Verge trims must be fitted where a roof line does not overhang the system. These must have a minimum overhang of 35mm and are to be sealed. Technical details must be submitted for approval. Where there is 0mm tile overhang you must install flashing on top of the verge trim to ensure water cannot ingress behind the system. Where there is some overhang 2mm-100mm use verge trims Where there is more than 120mm roof overhang no verge trim is required Where barge boards exist and they sit higher than the internal ceiling height, installers should remove these and insulate up to the roof line. If barge boards sit higher that the internal ceiling height it is not essential that this area is insulated but installers must ensure they do not block any existing vents. Where vents are blocked due to system dimensions, new vents must be created to replicate those lost. There is additional consideration in this area: Due to planning restrictions installers may not be permitted to interfere with the barge board if decorative or adjoining decorative features need to be left in situ. Regardless of the approach agreed upon, installers must consider the following three key issues waterproofing, ventilation and cold bridging (in that order). There is the more expensive option of extending the eaves but this would need to be done by a professional. A brief note should be issued as part of the quotation, advising the customer that this area can be extended at additional cost as a good practice option. Technical details must be submitted for approval. Flat roofs – as these will vary in structure and integrity verge trim details for these should be considered on ad hoc basis. Technical details must be submitted for approval. Where loft insulation is installed, additional roof tile ventilation should be installed as standard, to mitigate against risk of condensation. Please refer to the CITB Loft Guidance section 5.1.2 and PAS requirements. Suspended floor insulation Where suspended floor insulation is installed, additional ventilation bricks should be installed as standard, if not already present, so as to mitigate against risk of condensation. Air bricks should be present every 1.8m. Also ensure cross ventilation is maintained/facilitated. Sills Sills tend to be stone and concrete in north London or may be tile sills in Edwardian properties. The agreed standard approach is to oversill and enclose the existing sill with layer of insulation underneath, with EPS as first option and Aerogel as the second option if room is limited. Installers must ensure they do not foul the opening and the ventilation of the window, or obstruct window drainage weep holes (e.g. in uPVC windows). Undersills are an option, but probably not for these properties Composite insulated sills should be presented as an option for properties where a stone/concrete sill is already in place. The original sill would have to be taken out/back with an angle grinder and the new composite cill instated. Whilst this option will better replicate the original appearance it is considerably more costly. Manufacturer’s photos/illustrations to demonstrate the various sill options should be used to present the options available to the customer. Base Details The preferred approach is to treat below DPC, but this is a customer decision. There is no requirement to treat below the DPC unless the property has been built into the side of a hill (i.e. an elevation sits lower that the traditional ground level e.g. properties that are 2 story on one elevation and 3 on another) or properties that have a working, livable basement. Where this is the scenario or a customer chooses to have below dpc insulated, please note that existing vents must be kept clear and extended, additional ventilation may be required. Technical details must be submitted for approval. The homeowner should be made aware of the enhanced base detail option that will prevent cold bridging below dpc. Other No install can begin until the property has been deemed to be structurally sound and any remedial work has been undertaken to a satisfactory level. This includes details such as damp, cracks, damaged / leaking rainwater goods, replacement flues and vents etc. Replacement rainwater goods, flues and vents may be funded as ancillary works from the Smart Homes grant. Any issue that would have a negative effect on the finished system must be treated prior to install. For example, upgrading windows would not be deemed an essential remedial work, replacing / repairing faulty rainwater goods would. All work should comply with Building Regulations. Installation must be completed as per the agreed process and to a satisfactory level. These aspects include detailing around reveals, meeting party walls and roof lines. Any aspect that falls outside of Building Regulations (for example the cold bridging solutions) should be discussed with the customer and, if requested by the customer, must be installed in line with previously approved details. Any installs found not to be following the process as set out in PAS2030, BBA Certificate, agreed details and Building Regulations will be halted until rectified. The homeowner should be advised that scaffold will be provided without an alarm system but should they require an alarm it can be provided at an additional cost. This should be noted within the quote/schedule of works. Where services such as power cables or telephone lines need to be moved please ensure this work is undertaken by the relevant service provider. Do not try to undertake this work yourselves.
© Copyright 2026 Paperzz