International Biodeterioration 25 (1989) 87-95 The Application of Bioaugmentation to Waste Water Treatment N. C. A. Stevens International Biochemicals Ltd, Galvin Road, Slough, Berkshire SL1 4DL, UK ABSTRACT The application of bioaugmentation is discussed. Biomass population selection pressures are examined and reactionary measures which can be taken to resolve effluent treatment problems are discussed. Two new case histories on the use of bioaugmentation are presented. INTRODUCTION The successful operation of a biological waste water treatment plant is dependent upon the biomass. This includes bacteria, fungi, protozoa, rotifera, nemotoda and some higher forms (e.g. arthropods). Generally, the basic trophic level is occupied by the bacteria (Hawkes, 1963; Pike & Curds, 1971). The genera of bacteria present are the function of the natural population. Those able to survive in the environmental conditions will persist in the system. The biomass selection pressures which exist in a waste water treatment plant fall into three main categories: (1) Those dictated by the nature of the influent (2) Those resulting from the mode of operation of the treatment system (3) Those which are determined by the design of the treatment system For example, a toxic component could suppress the growth of certain 87 International Biodeterioration 0265-3036/89/$03.50© 1989 Elsevier Science Publishers Ltd, England. Printed in Great Britain. 88 N. C. A. Stevens species, or the lack of an adequate nitrogen source could favour the growth of filamentous rather than fioc-forming organisms. Alternatively, if an activated sludge plant is operated in the mode of increased sludge wastage, there would be a selective pressure for faster growing bacteria. As a result, ammonia removal may suffer as the slower growing nitrifying bacteria are lost from the system. Finally, the design of a treatment system can have an important selective pressure for example much greater diversity of genera within the biomass of a trickling filter compared to that of an activated sludge system. Furthermore, changes to system design will affect operational conditions and hence also have specific selective pressures (Daigger et al., 1985; Jones & Franklyn, 1985). However, despite the inherent ability of the bacteria within a waste water treatment plant to adjust their composition under selective pressures, many treatment plants cannot respond rapidly enough to prevent them failing to produce the required standard of effluent. These failures may be manifested as poor COD/BOD removal, turbidity in the final effluent, poor sludge settlement, foaming, odour problems, loss of nitrification or other effects. In such cases, there are four possible measures which can be taken: (1) Modify influent characteristics (e.g. pH, nutrient addition, physical/ mechanical removal of solids, etc.). (2) Modify mode of operation (e.g. alter sludge return or wastage rates, alter aeration, change beds on alternating double filtration system). (3) Change plant design (e.g. reorganise treatment units, build extra capacity). (4) Introduce new components to the biomass community (e.g. sludge from another works, bioaugmentation). The most common approach would involve either (1) and/or (2) and in some cases this solves the problem, even if only temporarily. These approaches involve increased operating costs, which could be excessive in some cases. Option (3) would be reserved for problems such as massive urban development, or factory expansion. Option (4) is, in many cases, disregarded because of the lack of understanding of waste water treatment biology. Although it is not suitable in all cases, it has been possible to demonstrate significant improvements in treatment plants which have utilised bioaugmentation techniques (Thibault & Tracey, 1979; Chambers, 1981; Saunders, 1985, 1986). Bioaugmentation can often provide a cost advantage over the other reactionary measures considered. Bioaugmentation in waste water treatment 89 APPLICATIONS OF BIOAUGMENTATION The development of selected and adapted bacteria, by high technology techniques provides single species cultures which can degrade specific target substrates. The cultures are harvested and preserved by freezedrying. The process utilises complex cryogenic protectants to ensure the bacterial cell will remain intact ready for rehydration. These strains are then blended to create mixed culture inocula. The use of these cultures can provide benefits by: (1) Providing an abnormally high growth rate. (2) Giving an increased tolerance to toxic materials. (3) Increasing the spectrum of bacteria available for natural selection. (4) Increasing the concentration of desirable bacteria and thus reducing their response time (lag phase) to specific substrates. These traits can provide real benefits in aerobic waste water treatment plants in the following areas: (1) Plant start-up. (2) Organic and hydraulic overloading. (3) Toxic shock/problematic waste water. (4) Poor sludge settlement. DISCUSSION AND CASE HISTORIES Plant start-up The conventional means for biological commissioning of a new effluent treatment plant is by means of tankering sludge from another plant. This can have drawbacks since the influent characteristics may differ from those of the 'parent' plant, producing a long acclamation phase. Also, problems (i.e. poor sludge settlement characteristics) may be inherited from the 'parent' plant and transport costs can be high, particularly where large quantities and long distances are involved. Alternatively, a new plant's biomass may be allowed to evolve naturally without sludge addition by lengthy step feeding, but this process can take months before the required treatment performance parameters are met. It is not usually considered as a viable alternative. The third approach is to consider the use of adapted and selected bacteria to speed up the commissioning process by providing a high performance biomass, 90 N. C A. Stevens This latter approach was that chosen by the South West Water Authority (SWWA) for their Ipplepen Sewage Treatment Works (STW) in South Devon. The effluent plant is a two rotor oxidation ditch system with a volume of 835 m 3, designed for a m a x i m u m flow of 4300 m3/day and a dry weather flow of 665 ma/day. The influent has a BOD of 191 mg/litre and TSS of 168 mg/litre with final effluent standards required of 10 mg/litre BOD, 15 mg/litre TSS, and 5 mg/litre ammoniacal nitrogen. The following was the seeding programme. Days 1 and 2 Using mains water, the final settlement tanks and the oxidation basin were filled to a depth of 1-8 m, a volume of 590 m 3. Over the following 14 h, the ditch was topped up with feed sewage to the lowest rotor setting, producing a BOD load of 47 kg. Rotors and recycle pumps were operated to bring dissolved oxygen levels to a m i n i m u m of 2 mg/litre and, at the same time, the ditch was filled to a m a x i m u m level of 2.5 m. 15 kg of commercially available, freeze-dried bacterial cultures were rehydrated and added to the ditch. Day 3 Without further changes, 7 kg of bacterial cultures were rehydrated and added. Day 4 Feed sewage (9 m3/h) was allowed to enter the ditch and 5 kg of bacterial cultures rehydrated and added. Day 5 A further 5 kg of bacterial cultures were rehydrated and added. Day 6 The full flow of sewage was discharged to the oxidation ditch. Bacterial cultures (5 kg) were rehydrated and added. Days 7-9 Bacterial cultures (1 kg) were rehydrated and added per day. Figure 1 shows the system achieved the required BOD of l0 mg/litre w h e n the MLSS value reached 1000 on day 26. This was a satisfactory buildup of the biomass, even though it was slower than normal because of a period of wet weather and correspondingly low level of substrate. However, the period involved would have been very m u c h longer had the natural processes been allowed to follow their course. Bioaugmentation in waste water treatment 91 Note : The s y s t e m achieved BOD and SS at 1 0 0 0 * M L S S arid BOD. SS. NH3 over 2700 mg/I MLSS - 3O 0 U3 ~3 5 2ooc 20 • g .E x o 10 1000 Effluent BOD S I 10 I 20 I 30 I 40 0 50 6O Days Fig. 1. S t a r t - u p o f l p p l e p e n S T W o x i d a t i o n ditch. Organic and hydraulic overloading Overloading of treatment plants occurs across all industry sectors, but is most c o m m o n in the food industry, where seasonal production and consumer demand can exacerbate the situation. Bioaugmentation to rectify a catastrophic plant failure and ensure that discharge limits could be met even during continued overloading are discussed. This was the situation at the Express Foods Group plant at Ruyton - - XI towns, near Shrewsbury. The extra extended aeration lagoon was originally designed to treat 350 m3/day ofinfluent carrying a total organic load of 1045 kg BOD/day. The final effluent standard was 25 mg/litre B O D and 45 mg/litre TSS. However, following the installation and commissioning of a new cheese 92 N. C. A. Stevens processing line a n u m b e r of severe difficulties were experienced which led to a massive increase in the hydraulic a n d organic levels of waste materials received at the waste water treatment plant. Hydraulic volumes increased from 350 m3/day to in excess of 500 m3/day whilst the organic loadings rose from 1045 kg B O D / d a y to as high as 3000 kg BOD/day. Sludge p r o d u c t i o n was initially high but problems arose with the d e v e l o p m e n t a n d eventual p r e d o m i n a n c e of a filamentous biomass. Dissolved oxygen levels fell to less than 1 mg/litre a n d the sludge volume index rose to 225 ml/g. Final effluent BOD values of > 500 mg/litre were typical. In an effort to reduce the loading on the treatment plant, a hired tanker was brought in to remove a portion of the waste waters for alternative disposal on to agricultural land. This h a d little impact on the total effluent loading, and a remedial p r o g r a m m e utilising bioa u g m e n t a t i o n techniques was introduced. The objective was to establish rapidly an active biomass which would be capable of responding to the excessively high organic loadings a n d the reduced residence time of the polluted waste waters within the treatment system. Additionally, such a biomass would be required to have superior settlement characteristics, that would enable adequate removal of s u s p e n d e d solids in the quiescent zone of the treatment plant, prior to discharge into the river. This requirement was more acute because of the reduced residence time in the settlement zone caused by the 40-50% hydraulic overloading. Furthermore, because of the high cost incurred in the hiring of the tanker for the removal of a portion of the effluent, it was important to achieve an increase in plant efficiency as quickly as possible. The b i o a u g m e n t a t i o n p r o g r a m m e was based on a 14-day initial inoculum, followed by a weekly m a i n t e n a n c e dose spread over 5 days. However, prior to the introduction of the bacteria into the aeration lagoon it was necessary to reduce the MLSS. The objective was to provide some residual dissolved oxygen level, a n d to remove a percentage of the highly filamentous biomass p r e d o m i n a t i n g within the lagoon. The p r o g r a m m e c o m m e n c e d on 21 January with the removal of sludge, bacterial cultures were a d d e d on 11 February, at which time the residual dissolved oxygen level was 1.5 mg/litre a n d the MLSS was 2500 mg/litre. The dosing p r o g r a m m e was as follows: Day 1 58 kg rehydrated microbial culture Days 2-14 12 kg rehydrated microbial culture Thereafter 12 kg per week spread over 5 days. The microbial cultures were successful in bringing the performance of this plant to a satisfactory level. F r o m the start of the p r o g r a m m e the effluent B O D levels fell from 780 to 30 mg/litre within 25 days (see Fig. 2). 93 Bioaugmentation in waste water treatment Commencement of programme Point of application of biolyte system - - - - Consent discharge 80D standard Plant design loading (1045 kg/d) Influent 80D kg/d E f f l u e n t BOD mg/I 32001 3 000 2800 '1200 11100 2200 1000 c~ 2 0 0 0 0 m 1800 90O Q) _~ 1 6 0 0 _c 1400 800 700 1200 0 600 m 1000 o 500 2 800 400 w 600 300 400 200 200 100 5 10 15 20 25 30 35 Time 40 45 50 55 60 65 70 75 (days) Fig. 2. Influent and effluent BOD 5 levels prior to and after commencement of BIOLYTE SYSTEMS programme. The influent BOD levels were variable but were on average 82% (excluding three points) above the designed value. Hydraulic volumes also maintained their excess level of 40-50% > design. The results may be summarised as follows: (1) Despite organic overloading of 180% of plant capacity, within 10 days of the introduction of the microbial cultures, removal efficiency had improved from 80.6% at the commencement of the programme to 98.1%. 94 (2) (3) N. C. A. Stevens The sludge settlement characteristics improved, from SVIs of 276 to 76, within 7 days of introducing microbial cultures. There was no need to transport a portion of the waste waters for alternative disposal on the land and problems associated with odour were overcome. CONCLUSION The two examples show that the application of bioaugmentation techniques can e n h a n c e the efficacy of the natural biomass and give measurable, cost-effective improvements in performance. The success of the programme lies in correct problem definition and the selection of bacteria to assimilate a given effluent stream. The cultures introduced in this way must be able to actively compete for the available food and to respond rapidly to a favourable growth environment - - adaptation and selection techniques can ensure that the bacteria have this advantage. The uses of bioaugmentation will obviously not replace the need for sound engineering and process design, or for proper plant management, but should provide another cost-effective option worth considering when effluent problems occur. ACKNOWLEDGEMENTS I should like to thank the SWWA, and Express Foods Group for permission to publish the data in the case histories. REFERENCES Chambers, J. V. (1981). Improving waste removal performance reliability of a waste treatment system through bioaugmentation. Proceedings of 36th Industrial Waste Conference, Purdue University, Indiana, USA. Daigger, G. T. et al. (1985). The design of a selector to control low F/M filamentous bulking. Journal WPCF,, 57 (3). Hawkes, H. A. (1963). The Ecology of Waste Water Treatment. Pergamon Press, Oxford. Jones, G. A. & Franklyn, B. C. (1985). The prevention of filamentous bulking of activated sludge by operation means at Halgon sewage treatment works. Water Pollution Control, 84 (3). Pike, E. B. & Curds, C. R. (1971). MicrobialAspects of Pollution, Soc. Appl. Bact. Syrup. Academic Press, New York. Bioaugmentation in waste water treatment 95 Saunders, F. J. (1985). Biotechnology and waste treatment. European Water and Sewage, October 1985. Saunders, F. J. (1986). A new approach to the development and control of nitrification. Water and Waste Treatment Journal. Thibault, G. T. & Tracey, K, D. (1979). Demonstration of a mutant bacterial additive for enhancement of operation stability in oxygen activated sludge. Proceedings of 34th Industrial Waste Conference, Purdue University, Indiana, USA.
© Copyright 2026 Paperzz