PLANS QUANTITY ITEMS

PLANS QUANTITY (PQ) ITEMS
This document is provided for information only and is not to be used for bidding or contract purposes.
ITEM
104
105
110
112
132
247
251
260
263
265
275
276
356
PQ means reference to Article 9.2, “Plans Quantity” unless otherwise shown (e.g. Item 502).
DESCRIPTION
COMMENTS
PROPOSED CATEGORY
Removing Concrete
All units
PQ
Removing Stabilized Base and Asphalt
Not PQ but measured in original position with typical on Typical section with lengths
measured in the field.
Pavement
plans for width and depth. Length will be measured in
the field.
Excavation
All units
PQ
Subgrade Widening
All units
PQ
Embankment
For final position CY measurement only
Part PQ
Flexible Base
SY and CY in final position only
Part PQ
Typical section with lengths
Reworking Base Courses
Not PQ but measured to the lines shown on the typical
measured in the field for SY,
section and the lengths measured in the field for SY and
CY in place only.
CY in place. Vehicle and TON is to be measured in the
field.
Lime Treatment (Road Mixed)
Not PQ but lime treatment SY is to the lines shown on
Typical section with lengths
the typical sections and lengths measured in the field
measured in the field for lime
treatment by SY only.
Lime Treatment (Plant Mixed)
SY and CY final position measurement only
Part PQ
Typical section with lengths
Fly Ash or Lime Fly Ash Treatment
Not PQ but LFA and FA treatment by SY is to the lines
measured in the field for LFA
(Road Mixed)
shown on typical section and lengths measured in the
of FA treatment by SY only.
field.
Cement Treatment (Road Mixed)
Not PQ but cement treatment by SY is to the lines shown Typical section with lengths
on typical section and lengths measured in the field.
measured in the field for
cement treatment by SY only.
Cement Treatment (Plant Mixed)
Current draft spec is for PQ for SY and CY in final
Part PQ
position measurement only.
Fabric Underseal
Fabric and pavement joint underseal to be to the widths
Typical section with lengths
shown on the plans and lengths measured in field.
measured in the field for fabric
and pavement joint underseal
by SY only.
1-3
March 8, 2005
PLANS QUANTITY (PQ) ITEMS
ITEM
368
400
420
422
423
425
426
427
428
430
439
442
450
454
460
461
462
464
466
474
476
502
528
DESCRIPTION
Concrete Pavement Terminals
Structural Excavation
Concrete Structures
Reinforced Concrete Slab
Retaining Wall
Precast Prestressed Concrete Structural
Members
Prestressing
COMMENTS
All units
All units
Table 2 listing are PQ for CY only
All units
All units
All units
PQ for cast in place prestressing systems by the product
of the length times force only. Special table for percent
variance from standard 5% PQ.
Surfaces, Finishes for Concrete
All units
Concrete Surface Treatment
All units
Extending Concrete Structures
Refers to Item 420 for measurement.
Concrete Bridge Deck Overlays
PQ for overlay only.
Metal for Structures
All units. Special table for percent variance from
standard 5% PQ.
Railing
All units
Bridge Expansion Joints
Not PQ for header type joints, lengths and widths shown
in plans and depth measured in place. PQ for sealed
expansion joints and armor joints.
Corrugated Metal Pipe
All units
Structural Plate Structures
All units
Concrete Box Culverts and Storm Drains
All units
Reinforced Concrete Pipe
All units
Headwalls & Wingwalls
All units
Slotted Drain
All units
Jacking, Boring, or Tunneling Pipe or Box All units
Barricade Signs & Traffic Handling
Pay quantity shown on the plans but not PQ.
Not PQ
Color Textured Concrete and Landscape
Pavers
2-3
PROPOSED CATEGORY
PQ
PQ
Part PQ
PQ
PQ
PQ
Special PQ
PQ
PQ
Part PQ
Part PQ
Special PQ
PQ
Part PQ.
PQ
PQ
PQ
PQ
PQ
PQ
PQ
Special wording
Not PQ
March 8, 2005
PLANS QUANTITY (PQ) ITEMS
ITEM
618
620
621
622
634
636
647
654
658
662
666
668
672
677
678
684
688
730
DESCRIPTION
Conduit
Electrical Conductors
Tray Cable
Duct Cable
Plywood Signs
Aluminum Signs
Large Roadside Sign Supports and
Assemblies
Sign Walkways
Delineator and Object Marker Assemblies
Work Zone Pavement Marking
Reflectorized Pavement Markings
Prefrabricated Pavement Marking
Raised Pavement Markers
Eliminating Existing Pavement Markings
and Markers
Pavement Surface Preparation for
Markings
Traffic Signal Cable
Pedestrian Detectors and Vehicle Loop
Detectors
Roadside Mowing
COMMENTS
All units
All units
All units
All units
All units
All units
All units
PROPOSED CATEGORY
PQ
PQ
PQ
PQ
PQ
PQ
PQ
All units
All units
All units
All units
All units
All units
All units
PQ
PQ
PQ
PQ
PQ
PQ
PQ
All unites
PQ
All units
All units
PQ
PQ
Strip and full-width mowing by acre only. Spot is not
PQ.
Part PQ
3-3
March 8, 2005