Fall/Winter 1997 Volume 13 No.2 5420 Old Orchard Road Skokie, IL 60077-1083 phone: (847) 966-6200 Fax: (847) 966-8389 I Overtopping Protection RCC Overtopping Protection In Harsh Conditions By Douglas M. Yadon, P.E., ESA Consultants Inc. In 1978, a significant storm event occurred in southeastern Montana, resulting in a peak inflow of approximately 17,000 cfs (480 cms) into the Tongue River Reservoir. The resulting spillway and outlet works discharges caused $1 million in erosion damage around the existing concrete spillway and threatened to breach the Tongue River Dam. In 1980 the U.S. Army Corps of Engineers conducted an inspection and designated the dam as unsafe because of inadequate spillway capacity and, because of downstream residents, the dam was classified as high hazard. The Tongue River Dam is owned by the State of Montana and was constructed between 1937 and 1940 for flood protection and to store irrigation water. Funding for the rehabilitation of the dam was secured with the passage of the North- f F ern Cheyenne Indian Reserved Water Rights Settlement Act of 1992, which set cost sharing arrangcments between the state and federal governments. In 1995, the Montana Department of Natural Resources and Conservation (DNRC) selected ESA Consultants Inc. to provide design and construction contract administration services. Schedule requirements in agreements between sponsoring organizations and in the funding legislation, plus the need to maintain normal reservoir operations for irrigation and flood control purposes, presented significant challenges that led to an expedited design and construction process. Because of topographic constrain& the only practical location to achieve additional spillway capacity was over the top and down the face (continued on page two) of the existing zoned earth dam. To minimize hydraulic loads and scour at the toe and downstream of the dam, a stair-step configuration for the spillway was selected. A scaled physical model was constructed to test the hydraulic properties of the spillway and verify the design of the ogee weir, stair-steps and stilling basin size and shape. The maximum capacity of the spillway is 109,000 cfs (3085 cms), equating to a unit flow rate of 168 cfs/ft (1.5 cms/m) with an overflow height of 12.5 ft (3.8 m). Because of locally available aggregate, RCC was selected for use wherever practical in both the new RCC emergency spillway and in the rcconstructed primary spillway. The emergency spillway was designed with a width of 650 ft (198.2 m) with 22 steps (2.83 ft [.86 m] rise by 6.75 ft [2.06 m] tread). The steps, together with a 4.ft- (1.2-m) thick approach apron and 10.5.ft- (3.2-m) thick stilling basin slab (sized to resist “floating” at peak discharge), required 58,600 cy (44,750 m3) of RCC. There were three RCC mix designs for the primary components of the emergency spillway. The mix design for the lower 8.5 ft (2.6 m) of the stilling basin was as follows: 150 lb (89 kg) cement (Type I-II low alkali) 3708 lb (2195 kg) aggregate 176 lb (104 kg) water 6 oz (.23 I) water-reducing agent 18 oz (.69 I) air entrainment agent per cubic yard (m3) For the top 2 ft (.6 m) of the stilling basin, the cement content was increased to 275 Ib/cy (163 kg/ m3) because of exposure to harsh climatic conditions. The steps used 150 lb/cy (89 kg/m3), protectcd as described later; and the approach apron utilized a cement content of 325 lb/cy (192 kg/m3) to resist damage due to partial inundation and harsh climatic conditions. The two stilling basin mixe5 had anticipated one-year compressive strengths of 1700 psi (11.7 MPa) and 3200 psi (22.1 MPa). Due to the extreme climatic condition and hydraulic loads from the high unit flow rates, the riser fact of the steps are precast concrete panels and the treads have an X-in. 20.cm) cover of conventional concrete. The aggregate for the RCC and conventional concrete was processed and stockpiled under a separate Phase I contract awarded to Empire Sand and Gravel Co., Inc. of Billings, Mont. This contract was for $7,077.000 which also included access roads, a temporary bridge, site preparations, and state park mitigation resulting from a four-foot raise to the normal pool. The aggregate processing was scheduled for late fall so that the aggregate would be cool (35° to 40°F [2° to 5°C]) when used the following year to maximize the permissible time for RCC laccment. The Phase II construction contract was awarded in February 1997 to Barnard Construction Co., Inc., of Bozeman, Mont. The total price of about $8 million included approximatelv 8,000 cy (6,110 m3) of conventional concrete, and the 58,600 cy (4,750 m3) of RCC. The cost of the RCC was $17.50/cy ($22.90/ m3) for mixing, transporting, spreading, compacting. and curing. The unit price for cement for RCC was $112/ton. The precast panels were fabricated on site at a cost of $11. ft2($125.45/m2). Gears, Inc., of Crested Butte, Colo, provided an Aran 280 pugmill to mix the RCC, which was then transported to the placing surface using conveyors and Superswingers provided by Rotec Industries of Elmhurst, III. The conveyor system was designed for a capacity of 130 cy / hr (99 m3 / hr) but did peak at 160 cy/hr (122 m3/hr) after a breaking-in period. The original specifications required that the contractor work two IO-hour shifts per day, six days a week. However, because of hot weather conditions and other technical considerations, the contractor worked a single night shift each day during the hotter months of August and September 1997. RCC placement began in the stilling basin in mid-May with the steps completed by late August. The last of the RCC was placed for the approach apron in late September. To minimize RCC surface damage and lift joint cleaning, a Case 55OE rubber tracked dozer was used to spread the RCC. The reconstruction of the principal spillway is currently in process under a Phase III contract awarded to Empire Sand and Gravel for $14.4 million, and is to be completed b y spring of 1999. Weak fractured rock locally referred to as “clinker”) will be excavated from beneath the new conventional concrete labyrinth weir and flip bucket and replaced with 46,000 cy (35,145 m3 of RCC with a cement content of 140 lb/cy (83 kg/m3). This RCC was bid at an equivalent unit cost of $21.09/cy ($27.60/m3) for mixing, transporting, spreading, compacting, and curing. Cement for RCC was bid at $1 IO/ton. The RCC will provide a positive upstream Cutoff beneath the weir, a firm foundation for anchoring the conventional concrete floor slab, and a stabilizing mass at the flip bucket discharge. An additional 10,000 cy (7,646 m3) of conventional concrete will be used to construct the labyrinth weir, spillway chute, flip bucket, and 700 ft (213 m) of liner for a 9-ft (2.7-m) diameter tunnel FalllWinfer 1997 RCC Newsletter Concrete Batch Plant is Key for Warehouse Pavements warehouse Specialists, Inc. (WSI), a premier owner and operator of warehouse facilities in the U.S., is also one of the most innovative and cost conscious. WSI recently selected roller compacted concrete as the replacement pavement for four Wisconsin facilities totaling over 57,000 sy (47,658 m2). This, however, was RCC with a twist. The contractor, Murphy Concrete & Construction (MCC), mixed the RCC in its ready mix concrete plant. In addition, MCC’s asphalt crews were trained to place the concrete pavement. This use of available equipment and personnel provided significant savings for WSI and resulted in the largest series of RCC placements to use ready mix concrete batch facilities. with PCA and the O’Hare site visit helped solidify WSI’s decision to go with RCC. However, a major concern remained regarding the ability of MCC to properly place RCC pavement without having prior RCC construction experience. RCC. Typically, RCC is produced in a high-volume pug mill mixing plant. However, with MCC’s modem ready mix plants nearby, plans were made to use one of the MCC plants. The plant was a Rex Model S concrete paving plant with a batch Cost and Performance Bring RCC to Wisconsin WSI has been in the warehouse business since 1966. Virtually all of its facilities are paved with asphalt or unsurfaced aggregate. These flexible pavements have not held up to the year and tear of warehouse operations resulting in frequent repairs and high maintenance costs. In an effort to improve operations, WSI looked for a high-performance pavement at a reasonable cost. The design criteria called for a lowmaintenance pavement to withstand heavy truck loading of over 400 vehicles per day. RCC pavement, with engineering properties similar to conventional concrete, proved to be the right choice. Intrigued but needing more solid information, WSI, under the direction of Kevin Wentland, investigated carefully. With help from Bill Gault of Medusa Cement, WSI and MCC spoke with cement industry experts, culminating in a visit to the Portland Cement Association headquarters. They learned about RCC’s cost benefits, design considerations and construction techniques through a personal presentation by PCA staff. WSI found that thousands of square yards (m2) of RCC for industrial applications have been placed in Canada, with similar harsh climatic conditions as those found in Wisconin. These pavements have provided years of productive service life. In addition, WSI visited the completed RCC pavement for the O’Hare Reservoir project (see RCC Newsletter Spring/Summer 1997). Discussions ‘< Industry Team Assembled Although MCC was an experienced concrete and asphalt paving contractor, they had never worked with RCC. WSI and MCC realized that for the highest quality RCC pavement, the proper paving equipment and expertise in placing the RCC would be necessary. WSI contacted Tim McLaughlin of Standard General Construction Inc. (SC), Birmingham, Ala. SG had both RCC paving experience and an available heavyduty RCC paver. Ron Peltz of Peltz Contracting Inc., Alliance, Neb., another RCC specialty contractor, also provided valuable assistance during construction. Thus WSI had gathered a strong industry team of MCC, SG and Peltz to bring RCC pavement technology to Wisconsin Concrete Batch Plant Mixes RCC For the initial project, WSI chose to replace a deteriorated asphalt pavement for a warehouse facility in Appleton One of the unique aspects of this project was the use of MCC’s ready mix batch plant to mix the capacity of 12 cy (9.2 m3). Procedures for mixing the RCC in a rotary drum ready mix plant had to be altered, especially mixing time and batch size. The dry consistency of RCC (only 6.1% water content) required that the mixing time be increased from the normal 60 second batch time to 3 to 4 minutes per batch. Because of the bulking tendency of the zero-slump RCC, individual batches were reduced from 12 cy (9.2 m3) t o 8 to 9 cy (6.1 to 6.9 m3). After mixing, the RCC was discharged directly into dump trucks and hauled to the nearby placement site. Asphalt Crew Takes on Concrete Pavement Using a ready mix plant was not the only unusual aspect of this project. MCC’s skilled asphalt paving division now had the task of placing a concrete pavement. However, the nature of RCC made the operation not much different from placing asphalt. Tim McLaughlin of SG (continued on page four) PORTLAND CEMENT ASSOCIATION 5420 Old Orchard Road Skokie, IL 60077-1083 Route to: Pavements continued from page 3 trained MCC’s asphalt crew to operate SG’s ABG 511 paver, which is a heavv-duty asphalt type paver with a vibrating screed and dual tamping bars. It is capable of producing RCC compacted to greater than 90% modified proctor density prior to any rolling. Ron Peltz of Peltz Construction provided additional assistance in the paver’s operation resulting in improved surface appearance. RCC was placed at full-depth, from 5 in. (127 mm) for car parking areas, to 7-11 in. (178-279 mm) in the shipping dock and truck parking lot. Paving widths varied from 10 to 15 ft (3 to 4.6 m). Dual steel drum rollers compacted the RCC to a minimum 9 8 % density. Gene Vandemark, General Manager of MCC’s Concrete Division, noted that this was the first time the concrete and asphalt divisions had ever worked together in a single paving project. Both divisions were able to modify and integrate their operations to successfully manufacture and place the RCC pavement. More RCC to Come The first project in Appleton was considered a trial project. By the e n d of the project, WSI saw that the construction team had produced a high-quality, densely-compacted concrete pavement with excellent surface texture. WSI felt confident that they would avoid the high maintenance expenses previously experienced with flexible pavements, at an initial cost only slightly above asphalt. Because of this success, two more facilities were constructed in Appleton. Not to miss out on a cost-saving opportunity, the ARG; paver was then transported 80 miles (129 km) west to Wisconsin Rapids to pave a fourth warehouse. Each of these facilities was approximately 14,000 sy (11,700 m2). With warehouse operations throughout the U.S., WSl is considering use of RCC at many of these facilities. m RCC Newsletter is published by the Portland Cement Association, an organization of cement companies in Canada and the United States. Direct comments, address changes and subscription requests to Wayne Adaska, Portland Cement Association, 5420 Old Orchard Road, Skokie, Illinois 60077-1083 (847/966-6200). Items from this newsletter may be reprinted, with acknowledgement, without prior permission. RCC Seminar/Construction Tour A technical seminar on RCC dam and dam rehabilitation methods is scheduled for May 18-19, 1998, in Allentown/Bethlehem, Pa. This seminar will feature a construction tour of the New Penn Forest Dam which incorporates many current design and construction’concepts for RCC dams. The seminar will begin with a day-long technical session presented by a variety of speakers experienced in both the design and construction of RCC gravity dams and RCC overtopping protection projects. The construction tour the following day will give participants the opportunity to observe the actual construction of the largest volume RCC dam east of the Mississippi River, which will utilize an all-conveyor delivery system. Don’t miss this opportunity to learn from the experts and see a major RCC dam under construction For more information, including a copy of the program, contact Randy Bass, Portland Cement Association, 517 Haralson Dr., Lilburn, Georgia 30047, phone 770-921-5894. rE
© Copyright 2026 Paperzz