Peace Project Water Use Plan Williston Debris Removal Physical Works Implementation Year 7 Reference: GMS WORKS 22 2015 Debris Removal Annual Report Study Period: June 2015-October 2015 Chu Cho Industries L.P. 1877 Queensway Prince George, BC V2L 1L9 Dan Wiebe General Manager (250) 613-6566 January 12, 2016 WILLISTION RESERVOIR DEBRIS REMOVAL 2015 FINAL REPORT Prepared for: BC Hydro Prepared by: Chu Cho Industries L.P. Worked Preformed: June 14, 2015 - October 1, 2015 Beaches Worked: Lafferty North & Lafferty South Collins South, Moody Hydro Creek, TKD Beach Overview: On June 4, 2015 Chu Cho Industries L.P. (Chu Cho) began preparations for the 2015 Williston Reservoir Debris Removal Program (Debris Program). Chu Cho and BC Hydro representatives completed an aerial reconnaissance of the Williston Reservoir to prioritize treatment areas. While selecting the treatment areas the factors for consideration were: accessibility, operational feasibility and priority debris accumulation areas. Upon agreement to specific treatment areas Chu Cho began preliminary work. This work comprised of: data collection sheets for environmental and archeology assessments (“Field Monitor Forms”), Site Specific Safety Management Plans (SSSMP), EMP, budgets and cost tracking programs, along with other logistical considerations. Real time costing allowed work to be completed on budget. The proposed work for the 2015 Debris Program focused on creating large debris piles at predetermined locations. For future operations the debris piles were located in areas that may be accessible by barge. Chu Cho also ensured that moves between sites were planned and executed in the most logistical and cost effective manner. Prior to machine access all sites were assessed by an Environmental and Archeology Monitor to determine any environmental and or archeological significance. Millennia also reviewed these sites for high potential and AOA.The monitors marked out any areas deemed significant as machine free zones. To reduce the environmental impact haul roads were minimized and, where operationally feasible, equipment operators traveled back and forth on the same tracks. These proactive approaches ensured minimal disturbance to soil and wildlife habitat. Work commenced on June 15th, 2015 when Chu Cho began mobilizing equipment at Moody Beach. Work wrapped up at Moody Beach on June 22nd, 2015 and transportation of the equipment to Lafferty Beach began. A sizable amount of debris along Lafferty was removed from the shoreline resulting in three large piles being created at this site. On July 21st, 2015, the debris crew began moving equipment to Collins Bay and worked south of the camp until August 5th, 2015. After completing the planned Debris Program at Collins Bay Beach equipment was moved to Hydro Creek and Tsay Keh Dene Beaches. Moving forward weather played a key role in the daily work plan at the Hydro Creek site and on occasion the debris flow was impacted by extreme winds. During this time crews worked both areas, taking advantage of days where the weather would permit them to work primarily in the Hydro Creek site. Demobilization for the Debris Program began on October 1st, 2015. This year a new application for debris removal in creeks was attempted by Chu Cho. Large three-pronged hooks with a tow rope attached were custom fabricated. Due to shallow water around creeks the tug was not operationally feasible to use in conjunction with these hooks. Therefore an alternative was attempted. The hooks were tossed into the debris flow and slowly pulled out with an excavator. The process was somewhat slower but minimal impact around any creek banks was achieved as the equipment was able to remain outside of the machine free zones. Although this method was not as productive as we originally planned, additional modifications and further trials is recommended to determine actual effectiveness. Pile Locations: 1. 2. 3. 4. 5. 6. Moody Lafferty Lafferty Lafferty Collins Bay Pelly Dump 56 20' 4.92"N 56 20' 38.58"N 56 20' 34.26"N 56 22' 1.26"N 56 25' 56.86"N 56 51' 47.60" N 124 20' 3.42"W 124 20' 8.04"W 124 21' 12.00"W 124 20' 42.96"W 124 24' 8.90"W 124 58' 15.30"W Debris Pile - Lafferty Beach Equipment Utilized: 30-Tonne Rock Truck (2) 20-Tonne Rock Truck (2) 330 Excavator 320 Excavator D4 Dozer Pick-ups (2-4) Barge & Tug Boat Yamaha side by side ETV Production: Production was steady throughout the duration of the project. To ensure this Chu Cho implemented a new shift schedule this year and, as in past years, had a mechanic make regular site visits. The schedule consisted of five days on five days off. There were two crews of an average of 10 workers per shift. allowing for the work to continue every day. The new schedule also employed more workers and allowed for the training of new workers. As encountered in previous seasons the volume of debris was dependent on weather. Down time was minimal as Chu Cho’s mechanic was on site regularly. Load counts varied from day to day, as this was dependent on the distance between debris and the pile location. The volume of debris was calculated differently this year. Load counts were tallied on a daily basis and Chu Cho brought in a local log scaler and several rock truck loads were scaled in order to determine a more accurate amount of debris volume being removed from the beaches. The average scaled debris truck load was 6m3 which was performed during a total of 90 working days. Date June 15 - 22 June 22 - July 21 July 21 - Aug 5 Aug 5 - Oct 1 Location Loads Moody 193 Lafferty 899 Collins Bay 465 TKD Beach /Hydro Creek 300 TOTAL 1,857 Cubic Meters 1,158 5,394 2,790 1,800 11,142 Lafferty North - before Debris Removal Program Lafferty South - after Debris Removal Program Safety: Building on previous years safety initiatives the Chu Cho debris crew conducted themselves with a proactive approach towards safety. Through the duration of the Debris Program the crew actively participated in daily tail gate meetings and Chu Cho’s preventative maintenance program. This ensured that all safety concerns were communicated with the crew, as well as equipment being properly maintained to minimize the chances of any malfunctions. Along with a Notice of Project being submitted prior to project start, reegular site and equipment safety inspections were also completed by the Site Safety Coordinator. The primary safety concerns faced during the operations were similar to those encountered in prior years, which gave experienced crew members an advantage as they were able to foresee and mitigate hazards before they became an issue. These concerns include, but are not limited to: weather conditions, wildlife, and new and young workers. Weather conditions that caused safety concerns during operations included risk of thermal exposure and/or fire during the dry hot spell encountered in late June and into July. During this time workers were encouraged to take micro-breaks and drink plenty of water. They were also instructed to smoke in designated areas and ensure cigarette butts were disposed of in a safe manner to avoid any risk of igniting a fire. Spark watch was also initiated as needed during this time. As the operations progressed the weather turned to rain, causing the piles that rock truck operators reversed onto to become slippery, and also caused access roads to deteriorate. Workers were encouraged to periodically reassess their work area and to communicate any concerns. At times the rock truck operators used alternate areas of the debris piles to dump their loads to avoid the slippery conditions encountered when reversing onto the pile. Drivers and operators used extreme caution to ensure the safety of themselves and their coworkers while these conditions were present. As the operations were conducted during calving season the risk of encountering aggressive wildlife was also a concern. To mitigate this hazard the buddy system was used and workers communicated all wildlife sighting either through the morning tail gate meeting or by radio during the work day. This season four new workers joined the debris crew. Chu Cho supervision ensured that a comprehensive site safety orientation was completed and new workers were partnered with an experienced employee until supervisors deemed them ready to work on their own. During 2015 Debris Program there were no loss time injuries, and any incidents were reported to BC Hydro. Workers submitted approximately 23 hazard ID cards throughout the project, identifying daily hazards on the work site. These hazards were discussed at the daily tail gate meetings. Safety and Maintenance Inspections Environmental: Prior to commencing debris removal at the selected sites Chu Cho’s environmental monitors reviewed the Environmental Management Plan (EMP) prepared by DWB Consulting Services Ltd. Reference material from similar projects was also reviewed. This material was provided by BC Hydro and included: Draft Guidelines for Machine Operators Removing and Burning Debris from BC Hydro Reservoirs prepared by Golder and Associates Ltd., correspondence between Department of Fisheries- Jayson Kurtz and BC Hydro- Gordon Boyd in regards to 2005 Arrow Reservoir Debris Management and the BC Hydro Reservoir Debris Removal Guidebook. The environmental monitors also attended training with DWB’s QEP, Mark Thompson in Prince George, which covered blue listed amphibians known to inhabit the general area in which debris removal was scheduled. Following training Chu Cho environmental monitors requested a follow up site visit to review environmental practices. DWB QEP was able to accommodate this request and came for a site visit while the crew was working at Collins Bay beach. To ensure consistency of the information being recorded and shared, Chu Cho worked closely with DWB Consulting and Millennia Research to develop “Field Monitors Forms”. This effort improved the accuracy and consistency of the information being gathered from the field. This newly implemented process will require additional and on-going training to maximize accuracy and consistency. A copy of this form is attached at the end of this report. Throughout the course of the project Chu Cho’s environmental monitors walked each work site and marked out areas of environmental significance as no work zone buffers. Vegetated areas, piles with advanced stages of decay with vegetation growing throughout the pile and wildlife corridors were some of the criteria for no work zones. These buffered areas were marked out to ensure all piles with advanced decomposition were not disturbed, along with areas of shoreline that were at risk of further erosion. Areas with high amounts of vegetation and drainages into the reservoir were also marked out as machine free zones. Chu Cho’s environmental monitors recorded a variety of species as using the shoreline in which debris removal was slated for, this activity was identified through tracks, feces and visual sighting. Some areas were frequented more than others, most notably Lafferty beach. Although these areas were often utilized by a number of species they were of a transient nature and no dens or nests were observed in or near the immediate worksites. Dash areas were also strategically established in high traffic areas so wildlife could utilize the cover of piles when accessing the shoreline. Some piles were also left in their original location due to advanced decomposition and/or advanced vegetation present around it; all piles that were proposed for relocation were inspected and no signs of dens or nest were observed. Throughout the course of the debris removal two non-reportable spills occurred on the Moody Beach and one reported spill into the Williston Reservoir at Collins Bay Beach. All spills were contained and cleaned by qualified spill responders. Chu Cho environmental monitors noted that the area on Lafferty Beach where a barrier of large woody debris had been placed in previous years to mitigate small woody debris from floating out into the reservoir during the high water, had been somewhat effective. Although the barrier showed obvious signs of erosion, the immediate area behind the barrier still had a fair amount of small woody debris behind it along with vegetation, primarily grass and small willows further back towards the tree line. This area was just outside of the work area and created desirable wetland habitat for wildlife such as Sandhill Cranes. It is important to note the reservoirs highest level in years prior, as this year the reservoir was extremely high resulting in the barrier not providing the same protective result as observed early in the season. Archeology: As in prior years of the debris program, no equipment operations were permitted until Chu Cho’s archeology assistant evaluated the work site. This year’s archeology assistant underwent an intensive one-on-one training with Millennia Research Archeologists. This was a comprehensive hands on training covering both the theory, which consisted of a variety of background data of the project and all applicable legislation, as well as the field work portion, which covered identification of artifacts and data collection. Chu Cho’s archeology assistant was also provided with maps and a Garmin GPS showing previously documented sites along with areas that had a high potential to contain undocumented sites. These areas were avoided to ensure no disturbance of any existing or potential artifacts. Chu Cho’s archeology assistant walked each site prior to machine access checking for any artifacts. An egress survey for each site was also completed to ensure that any artifacts that may have been brought to the surface due to equipment operations would be captured. It is important to note that the concentration of recent artifact discoveries documented around the Williston Reservoir are on the exposed beaches that are most accessible when the reservoir is low. The high water levels experienced during the debris program this year did not leave these areas accessible. The machines worked in the exposed areas that were in close proximity to the tree line. Each proposed haul road was surveyed by the archeology monitor prior to access by the machines as stated above. While completing an egress survey on Collins Bay beach the Archeology Monitor identified a flake. Upon the discovery an informal tail gate meeting was held communicating the discovery to the machine operators as an area to avoid and a thirty meter buffer area was established as a machine free zone. Coordinates of the discovery were taken and the discovery reported to Millennia Research. Haul Road and Vegetated Leave Areas Clean Up in Front of Collins Bay Conclusion/Recommendations: An initial aerial survey is required to assess operational working areas and locations for 2016 work plan. A mid project aerial survey is also recommended to determine where the moving debris flows are located. This would assist in determining if modification to the present work plan is necessary. For example, changing from land to water based operations or vice versa. Explore the possibility of increased access to beaches that have not previously been treated. For example, Manson Arm. This could potentially minimize some of the large debris flows because this appears to be where a substantial amount of debris originates from. As each beach has unique characteristics a flexible work plan is required for effective debris operations. Characteristics influencing the specific approach include: terrain, water depth and accessibility. The aerial survey will identify potential work sites, however a detailed physical assessment at ground level is necessary to determine which approach would be most effective. The option of focusing on stream inlet debris removal needs further exploration. This has been an area of concern for a variety of reasons such as; fish habitat, recreational use, wildlife and overall bio-diversity of streams. Further discussion and review is suggested in regard to future disposal of existing debris piles. BC HYDRO ENVIRONMENTAL MANAGEMENT PLAN WILLISTON RESERVOIR DEBRIS REMOVAL Project Name: QEP: QEP Contact: May 29, 2015 Action Taken/Recommended Description of Event Environmental Incident Review Issue Description Date Completed Causal Factors Target Completion Date Mitigation Measures [email protected] O: 250.562.5541, C: 250.961.9520 Mark Thompson WILLISTON RESERVOIR DEBRIS REMOVAL ENVIRONMENTAL MONITORING SUBMISSION REPORT Location Location Environmental Issue Report Period: Environmental Monitors on Site: Responsible Date Identified Environmental Tracking Date Status Issue Tracking ID No. Event # Weather Weather Conditions Other WILDLIFE SIGHTINGS SUMMARY OF CONSTRUCTION ACTIVITIES (Including names of contractors on site) SUMMARY OF ENVIRONMENTAL MANAGEMENT AND ISSUES DWB CONSULTING SERVICES LTD. PLANNED FUTURE ACTIVITIES FOR NEXT REPORTING PERIOD File: 15142-025 07/07/2015 BC HYDRO ENVIRONMENTAL MANAGEMENT PLAN WILLISTON RESERVOIR DEBRIS REMOVAL INCIDENT REPORT SUMMARY SITE PHOTO LOG (Identify with ID No. and/or Event # above) Photo 2: Site Photo Log Photo 1:. Photo 4: DWB CONSULTING SERVICES LTD. Photo 3: File: 15142-025 07/07/2015
© Copyright 2026 Paperzz