Foreword Compact mobile shelving systems are commonly found in healthcare, office, library, and numerous other occupancies. The advantage to the use of these systems is that aisles are eliminated, with the exception of one moveable aisle, in most cases saving up to 50% of floor area. The 2007 edition (current) of NFPA 13 does not provide specific design criteria for compact storage arrangements. As a result, design engineers are required to utilize protection criteria for either rack storage (storage depth 30 inches or deeper) or shelf storage (storage depth less than 30 inches), depending on the dimensions of the compact storage array. This is problematic because the fire protection design challenges presented by compact mobile shelving units are fundamentally different than those presented by stationary shelf and/or rack storage. In 2007, the Foundation conducted a review of available fire test data for these systems, identified gaps, and made recommendations for future testing to develop rational fire protection criteria for this storage system. This report presents the result of that test program: a filing survey, bench scale and two large scale fire tests were conducted. The Research Foundation expresses gratitude to the report authors and to the Project Technical Panel and Sponsors listed on following page. The content, opinions and conclusions contained in this report are solely those of the authors. Compact Mobile Shelving System Fire Testing Project Technical Panel Carl Anderson, City of Tacoma Fire Department Doug Erickson, American Society for Healthcare Engineering Ralph Gerdes, Architect Gary Lougheed, National Research Council of Canada Joe Noble, Noble Consultants Rich Pehrson, Futrell Fire Consultants John O’Neill, Protection Engineering Group Jim Lake, NFPA staff liaison Sponsor representatives Chris Batterman, Spacesaver Corporation Russ Fleming, National Fire Sprinkler Association Scott Franson, The Viking Corporation James Golinveaux, Tyco Fire and Building Products Roland Huggins, American Fire Sprinkler Association Ken Linder, SwissRe Insurance Tom Multer, Reliable Automatic Sprinkler Company Sponsors American Fire Sprinkler Association National Fire Sprinkler Association Reliable Automatic Sprinkler Company Spacesaver Corporation SwissRe Insurance Tyco Fire and Building Products The Viking Corporation Contributing Sponsor Representative Terry Town, Stelterr Factory Direct Ltd. COMPACT MOBILE SHELVING SYSTEM FIRE TESTING PROJECT THE FIRE PROTECTION RESEARCH FOUNDATION ONE BATTERYMARCH PARK QUINCY, MASSACHUSETTS Prepared For: Ms. Kathleen Almand Executive Director The Fire Protection Research Foundation One Batterymarch Park Quincy, Massachusetts 02169 SEC Project No.: 2007123-002 June 2, 2008 2008© Schirmer Engineering Corporation This report is the property of Schirmer Engineering Corporation. Copies retained by the client shall be utilized only for his use and occupancy of the project, not for the purpose of construction of any other projects. Fire Protection Research Foundation Compact Mobile Shelving System Fire Testing Project i June 2, 2008 SEC Project No.: 2007123-002 TABLE OF CONTENTS EXECUTIVE SUMMARY ............................................................................................................. iii INTRODUCTION / PROBLEM STATEMENT ............................................................................... 1 LITERATURE REVIEW ................................................................................................................ 2 EXPERIMENTAL TEST PLAN...................................................................................................... 5 BENCH SCALE TESTING...........................................................................................................7 FULL ARRAY TESTING .............................................................................................................9 FULL SCALE TEST 1 ..............................................................................................................12 FULL SCALE TEST 2 ..............................................................................................................13 EXPERIMENTAL RESULTS AND ANALYSIS ........................................................................... 15 BENCH SCALE TESTING.........................................................................................................15 FULL SCALE TEST 1 – OPEN ARRAY ......................................................................................17 FULL SCALE TEST 2 – CLOSED ARRAY WITH SOLID BARRIERS ................................................18 CONCLUSION AND RECOMMENDATIONS ............................................................................. 24 INDEX OF TABLES TABLE 1. CEILING SPRINKLER PROTECTION PARAMETERS (FULL SCALE TESTING) .... 11 TABLE 2. BENCH SCALE RESULTS........................................................................................ 15 TABLE 3. SUMMARY OF SIGNIFICANT FULL SCALE TEST RESULTS .............................. 233 Fire Protection Research Foundation Compact Mobile Shelving System Fire Testing Project ii June 2, 2008 SEC Project No.: 2007123-002 TABLE OF FIGURES FIGURE 1. BENCH-SCALE TEST ARRANGEMENT (70% NON-UNIFORM LOADING) ......... 8 FIGURE 2A. FULL SCALE COMPACT MOBILE SHELVING UNIT (SECTION VIEW)............... 9 FIGURE 2B. FULL SCALE COMPACT MOBILE SHELVING UNIT (ISOMETRIC VIEW) ......... 10 FIGURE 3A. FULL SCALE TEST 1 IGNITION LOCATION (ELEVATION VIEW) ..................... 12 FIGURE 3B. FULL SCALE TEST 1 IGNITION LOCATION (PLAN VIEW) ................................ 13 FIGURE 4. FULL SCALE TEST 2 (CLOSED ARRAY WITH LONGITUDINAL BARRIERS) ... 14 FIGURE 5. LOCALIZED BURNING OBSERVED IN NON-UNIFORMLY LOADED SHELF.... 16 FIGURE 6. DEPENDENCE OF FIRE SEVERITY ON EQUIVALENCE RATIO ...................... 16 FIGURE 7. FIRE DAMAGE TO FLUE SPACE BEHIND IGNITION ......................................... 18 FIGURE 8. GAS TEMPERATURES WITHIN THE ARRAY - TEST 2 ...................................... 19 FIGURE 9. SPRINKLER SYSTEM FLOW – TEST 1............................................................... 22 FIGURE 10. STEEL BEAM TEMPERATURES AT CEILING – TEST 2 .................................... 23 APPENDIX APPENDIX A – SUMMARY OF RELEVANT EXISTING EXPERIMENTAL DATA (LITERATURE REVIEW) APPENDIX B - FILING SURVEY RESULTS APPENDIX C - UNDERWRITERS LABORATORIES TEST REPORT Fire Protection Research Foundation Compact Mobile Shelving System Fire Testing Project iii June 2, 2008 SEC Project No.: 2007123-002 EXECUTIVE SUMMARY A series of fire tests, both bench and full scale, was conducted in an effort to solve the problem of how to achieve fire control for paper files stored in compact mobile shelving units. The testing focused on units which are subject to fluid use (non-archival) and protected by automatic sprinklers positioned only at ceiling level (no in-rack protection). Recognizing the importance of file packing density and configuration on fire severity, a series of 5 bench scale tests was conducted preliminarily to the full scale series. A survey of user filing practices was conducted to determine feasible bounds for storage configurations to be studied in the bench scale series (Appendix B). The bench scale tests were then used to determine the sensitivity of the fire severity to the combined effects of ventilation and thermal feedback from the shelving unit. Results indicated that slumping files, which are the result of sparse file storage in any given section of the array, increase the thermal feedback mechanism while also allowing for a smaller fuel to air mass ratio (i.e. equivalence ratio). This creates a synergy between these mechanisms and the rate of reaction is consequently optimized. For conservative design, this phenomenon was exploited to the extent permitted by practical use of compact mobile shelving units as determined in the filing survey. The result was the selection of a 70% packing density distributed uniformly throughout the array in each full scale test (with the exception of the ignition shelf). Two full scale tests were completed, Test 1 with open array, and Test 2 with closed array. The full scale testing component of this series afforded an opportunity to assess the effects of the array configuration on the thermal feedback and air access issues highlighted by the bench scale testing. In both tests, the high density storage configurations yielded relatively quick smoke detection and slow fire growth, thereby potentially affording responding firefighters ample time to produce fire control and suppression. However, the relatively slow growth of the fire in both cases studied was not the result of the automatic sprinkler protection provided. Rather, slow fire growth was generally due to the near balance between the energy generated by the developing fuel-rich fire and the heat losses to the massive fuel structure surrounding the area of burning. In this manner, the high density storage array proved capable of accomplishing the same heat absorption objective of the automatic sprinkler system; however, this mechanism of energy conservation is a delicate balance of several complex variables. The implementation of solid barriers into the shelving unit acts to decrease the flow of oxygen within the structure and also increases the dissipation of heat away from the reaction zone. By minimizing the magnitude of energy generated by the fire while simultaneously maximizing heat losses to other parts of the system, the experimental setup of Test 2 succeeded in providing fire control for 81 minutes following ignition. During this time, no sprinklers were active. However, the energy balance achieved in this test is the product of a specific type and configuration of both the fuel and the shelving unit. The reader should note that the findings of this project applies only to the storage of paper files stored in the manner tested. Storage of other materials could result in a much faster fire development. A third full scale test should be conducted. This test should be a repeat of Test 1, however with horizontal barriers installed as in Test 2. This scenario should be tested to confirm the ability of the horizontal barriers to limit fire damage in a full range of likely shelf positions. Fire Protection Research Foundation Compact Mobile Shelving System Fire Testing Project 1 June 2, 2008 SEC Project No.: 2007123-002 INTRODUCTION / PROBLEM STATEMENT The stated purpose of NFPA 13 is to provide a reasonable degree of protection for life and property from fire through standardization of design, installation and testing requirements for sprinkler systems, including private fire service mains, based on sound engineering principles, test data and field experience. The referenced reasonable degree of protection alludes to the fundamental design objective of automatic sprinkler systems, which is to provide either fire suppression or fire control depending upon the specific application. Fire suppression is defined by the standard as a degree of protection which sharply reduces the heat release rate of a fire and prevents its re-growth by means of direct and sufficient application of water through the fire plume to the burning fuel surface. In contrast, fire control is defined by the standard as a degree of protection which limits the size of a fire by distribution of water so as to decrease the heat release rate and pre-wet adjacent combustibles, while controlling ceiling gas temperatures to avoid structural damage. The difference between these objectives is ultimately a matter of efficiency. In applications where fire suppression by automatic sprinklers is made impractical by parameters such as fuel type, distribution and shielding, the adequacy of a shift to control objectives is explored. The fundamental question of how fire control can be achieved is often approached in terms of the necessary design parameters for automatic sprinkler system protection of the hazard. This approach begins with questions as basic as the appropriate type of sprinkler for the application, the necessary flow rate of water from the device (including other discharge characteristics), the arrangement of sprinklers with respect to the hazard and the total number of sprinklers needed to control or suppress a fire occurring within a given design area. This research into appropriate strategies for achieving fire control in compact mobile shelving systems begins with these same basic questions. Compact mobile shelving systems present a unique challenge to automatic sprinkler protection due to the variability of fuel shielding inherent to the design of the product. This study focuses on a specific unit design which is commonly used in business occupancies where storage is fluid and the overall fire hazard is assumed to be relatively low. In the past, challenges with fuel shielding in rack storage arrangements have been solved by revising the relative geometry of the fire / sprinkler interaction with the use of in-rack sprinklers. However, such an approach is considered impractical for this product for multiple reasons. First, the mobility and fluidity of use of the unit in a business application presents practical challenges for incorporating the necessary network of supply piping to fixed sprinklers within the device. Second, and perhaps more importantly, the product is already widely used in occupancies designed for Light Hazard automatic sprinkler protection. Focusing on a solution incorporating the in-rack sprinkler approach could therefore result in significant logistical obstacles including financial hardship for existing users. Consequently, a means for achieving fire control with sprinklers positioned only at the ceiling level is sought in this effort. One of the most fundamental topics to be resolved in any area of fire research are the relevant characteristics of the fuel being studied in terms of intrinsic (i.e. thermal parameters) and extrinsic properties (i.e. geometric parameters). This issue is especially significant for evaluation in compact mobile shelving systems, which may potentially be used to store fuel loads with some level of variability in these characteristics. A survey of filing practices by existing product users was conducted in an effort to capture realistic measurements of such properties for justification of the experimental setup (Appendix B). During this survey, significant Fire Protection Research Foundation Compact Mobile Shelving System Fire Testing Project 2 June 2, 2008 SEC Project No.: 2007123-002 variability was noted in both the type and arrangement of fuel stored within compact mobile shelving units. For example, although storage of paper files is a common use, there are applications in the health care industry which differ markedly in the way the product is used. Some locations included in the survey utilized compact mobile shelving units to store medicines, garments and plastic-based medical supplies. This is a significant obstacle to achieving a globally applicable solution for fire protection of compact mobile shelving units. The current study is relevant only to protection of paper files. This study addresses means to achieve fire control for paper files stored in compact mobile shelving units, which are subject to fluid use (non-archival) and protected by automatic sprinklers positioned only at ceiling level (no in-rack protection). LITERATURE REVIEW The 2007 edition (current) of NFPA 13 does not provide specific design criteria for compact storage arrangements. As a result, designing engineers are required to utilize protection criteria for either rack storage (storage depth 30 inches or deeper) or shelf storage (storage depth less than 30 inches), depending on the dimensions of the compact storage array. This is problematic because the fire protection design challenges presented by compact mobile shelving units are fundamentally different than those presented by stationary shelf and/or rack storage. In each of these applications, the configuration of the storage arrays obstructs the natural flow field of water from a ceiling level automatic sprinkler to the burning fuel below. The degree to which the water spray is obstructed is a function of the following problem specific parameters: 1. Location of the burning fuel with respect to the location of the nearest sprinklers. 2. Dimensions of the storage array with respect to the dimensions of the surrounding enclosure. This includes height of the array relative to the height of the room as well as clearance between the top of the array and the sprinklers above. 3. Size of longitudinal flue spaces within the storage array. 4. Characteristics of the natural (unobstructed) water flow field including flow streamlines and characteristic droplet momentum as determined by the design of the automatic sprinkler system. 5. Any additional overhead obstructions specific to a given application but unrelated to either the storage array or the sprinkler system. The most significant difference between traditional rack or shelf storage and compact mobile shelving is the internal mobility of the storage array. The ability to save space by manipulating aisle widths adds a new unknown variable to the fire protection design problem. This new unknown creates a set of geometric permutations for the obstruction of overhead sprinkler sprays that is unique to the compact mobile shelving application. In addition, this mobility generates complexity for protection schemes traditionally used in rack storage applications such as in-rack sprinklers. In an effort to mitigate this issue, Section 2.2.4.3 of the Factory Mutual Fire Protection Research Foundation Compact Mobile Shelving System Fire Testing Project 3 June 2, 2008 SEC Project No.: 2007123-002 Global Data Sheet 8-9 “Storage of Class 1, 2, 3, 4 and Plastic Commodities” provides additional guidance. This document calls for protection “…of rack storage in movable racks the same as multiple-row rack storage. Supply in-rack sprinklers via flexible in-rack sprinkler system connections, or other arrangements that provide sufficient water to the in-rack sprinklers.” However, no specific design criteria are provided for compact storage with a depth of 30 inches or less as FM Global considers the position of the array to be always closed, thus resulting in depths which are 30 inches or greater. The objective of the literature review was to analyze existing fire test data on the subject matter and evaluate the need for additional research. The following literature was identified as relevant to the compact mobile shelving application: “Fire Tests in Mobile Storage Systems for Archival Storage” – Prepared for General Services Administration by Factory Mutual Global – June 1978 “Archives II Mobile High Density Shelving Fire Protection System” – Prepared for HOK/Ellerbe Becket by Gage Babcock & Associates (GBA) – November 1989 “Design Criteria for Sprinklered Mobile Shelving Units for the National Library of Canada” (Research Report No. 200) – Prepared for Public Works Canada by National Research Council of Canada – November 2005 Block, J.A. “A Theoretical and Experimental Study of Non-propagating Free-Burning Fires”, 13th Symposium (International) on Combustion. 1971. Pittsburgh, Pennsylvania: The Combustion Institute. Heskestad, G. “Modeling of Enclosure Fires”. Journal of Fire and Flammability, 1975. v6 (3): p. 253 – 273. “Performance Testing of Light Hazard Active Fire Protection of Compact Shelving Systems Containing Class III Commodity (Paper Files in Paper Folders)” – Prepared by Southwest Research Institute – August 31, 2007 “Compact Mobile Shelving System Fire Test Plan” - Prepared by Schirmer Engineering – November 16, 2007 The table provided in Appendix A presents a summary of the data gathered from the first three of these tests. The remaining two publications address more fundamental combustion theory. The data shown in the referenced table illustrates a formidable obstacle to comparison of test results within each individual series as well as between separate test series. This obstacle is the consistent variation of multiple design parameters influential to fire growth and development from test to test. The end result of such variations is a number of stand-alone test results, which are insufficient in providing conclusive evidence of the dependency of fire growth and development on any given independent design variable. For instance: 1. Fuel type, total loading and packing density were varied in each of the three Factory Mutual (FM) tests. In addition to these variations, spacing within the shelving array was manipulated in each test, leading to characteristically different ventilation of the design fires. Therefore, although automatic sprinkler design criteria were held constant, Fire Protection Research Foundation Compact Mobile Shelving System Fire Testing Project 4 June 2, 2008 SEC Project No.: 2007123-002 variations in results can not be definitively attributed to any one of these influential categories. 2. Fuel type, total loading and packing density were varied in the two tests conducted by Gage Babcock & Associates (GBA). In addition to these variations, further manipulations included the size of longitudinal flue spaces, clearance between the sprinklers and the top of the fuel bed, sprinkler design density, the number of shelving modules and the shelf depth. Certain aspects of each influential category were held constant between tests, but variations in results can not be definitively attributed to any one of these influences on the burning rate. 3. Sprinkler type, discharge density and spacing were varied in each of the five tests conducted by the National Research Council of Canada (NRCC). In addition to these variations, additional manipulations included the size of longitudinal flue spaces. Furthermore, mechanical failures of the shelving arrangement during early stages of initial tests likely led to erroneous conclusions. 4. The array itself consisted of solid steel shelves, end panels and tops for both the FM and GBA test series, while the NRCC tests were conducted with open shelving arrays (i.e. no end panels, uprights or tops). This fundamental difference in the test array effected many influential fire growth parameters such as obstruction of the sprinkler spray, oxidizer access to the burning fuel and incident heat flux to adjacent fuels. This difference alone is enough to prevent meaningful comparison of results between the NRCC test series and its counterparts. 5. The aspect ratio of an individual rack or shelf may be defined as the ratio of length to depth. This ratio is important for determining the burning characteristics of fuel within the space. Shallow compartments provide minimal shielding of the burning fuel from a sprinkler spray above. Additionally, well ventilated shallow compartments typically yield flame extensions upward along the face of the unit. In contrast, deeper compartments provide increased shielding and consequently a higher degree of heat transfer internally within the module. Typically a depth of 30 inches is used as the maximum value for defining a shallow compartment (shelf) and the minimum value for a deep compartment (rack). Utilizing this definition, the data in Table A1 (Appendix A) illustrates that all of the FM tests and one of the two GBA tests were rack storage fires. Conversely, the second GBA test together with all of the NRCC tests were shelf storage fires. 6. Gas temperatures at the ceiling level were significantly different throughout the testing review. One of the subtle but significant influences on this result is the ratio of the fuel to sprinkler clearance versus the height of the storage array. As this ratio decreases, the temperature measurement is taken much closer to the source of the fire plume. This geometric comparison between the fuel and its surrounding enclosure illustrate a stark contrast between each of the three testing efforts. Ceiling gas temperatures were consistently significantly higher in the NRCC tests; however it is unclear whether this is due to the decreased clearance between the burning fuel and the ceiling, the lack of enclosed shelves or the performance of the automatic sprinkler system. Perhaps the most meaningful conclusion to be reached from an analysis of the data in Table A1 may be made with respect to the influence of ventilation on the rate of fire growth. Tests 1 and Fire Protection Research Foundation Compact Mobile Shelving System Fire Testing Project 5 June 2, 2008 SEC Project No.: 2007123-002 3 of the FM series contain variations in both the fuel commodity and the ignition location; however, despite these multiple variations, there is evidence of an expected trend in the data. In Test 1, ignition occurs in a module whose front face is open to a wide aisle. This fire is ultimately controlled by 3 sprinklers activating at 17, 17 and 19 minutes, respectively. In Test 3, ignition occurs in module whose front face is open to a ½ inch wide longitudinal flue space. This fire is ultimately controlled by 4 sprinklers activating at 48, 78, 121 and 125 minutes respectively. The effect of changing the fuel commodity on fire growth is uncertain from these results; however, it is expected that the fire open to the aisle would have better access to ventilation thereby producing a more robust fire plume at a faster rate of development. Despite the strength of this plume, the relative decrease in shielding of the burning fuel allows the sprinkler spray to control the fire. It is important to also mention the presence of a catwalk in Test 3, which significantly obstructed the sprinkler spray. To date, researchers have correctly identified that the size of the flue space governs both the degree of fire shielding from sprinklers and also the magnitude of internal heat transfer within the module. However, a key function of these flue spaces that has been overlooked is the access that they provide for oxidizer to reach the burning fuel. For enclosed shelving, the only significant path of air access to the burning fuel is through the longitudinal flue. As the width of the flue is decreased, the dominant influence on the burning rate shifts from the sprinkler spray to a balance between the ratio of fuel to oxidizer and thermal feedback between adjacent shelves. Perhaps the most formative work on free-burning wood crib phenomena was the development of a fundamental theory by a Harvard University researcher named James A. Block. Block was one of the first to derive a relationship between the internal openness of the wood crib, which he termed the porosity, and the burning rate. Block’s theory was essentially that the burning rate within a densely packed crib is limited by airflow through the internal flue spaces. As the porosity is increased, a maximum fuel-limited rate of burning is reached. The limitation in this second case is not the size of the flue spaces, but rather the exposed surface area of the fuel. Further increasing the porosity to an extreme magnitude results in unsustained combustion as the internal radiation is not strong enough to cause the fire to “jump the aisles” between adjacent sticks. It is important to draw an analogy to Block’s theory because compact shelving modules offer the unique fire protection circumstance of the ability to control fuel porosity during a fire event. This is important because fire requires heat, fuel, and oxidizer to sustain itself. Porosity is a parameter within the crib / compact shelving module / unit of solid fuel, which aims to express the interaction of these critical elements to produce a certain rate of burning. This theory suggests potentially unique approaches to achieving fire control. EXPERIMENTAL TEST PLAN Due to the potential for a high level of fuel shielding, fire control is the more feasible design objective for automatic sprinkler system protection of compact mobile shelving units. As identified in the standard definition, one of the primary components of fire control is the limitation of fire size and spread. This in turn leads to reduced heat exposure to the structural elements of the surrounding enclosure. Fire spread in compact mobile shelving units may occur as surface spread along the face of the array, interior spread through the depth of the unit or remote spread via radiant heat transfer Fire Protection Research Foundation Compact Mobile Shelving System Fire Testing Project 6 June 2, 2008 SEC Project No.: 2007123-002 between fuel surfaces separated by aisle space. An independent series of full-scale fire tests conducted by Southwest Research Institute illustrated the importance of the bulk density of fuel within the array in governing the dominant mode of fire spread. These tests were conducted with a fuel bulk density large enough to limit the impetus for interior fire spread to the relatively slow process of heat conduction through a semi-infinite thermally thick solid. A more challenging scenario for fire protection is found when the rate of reaction is increased. Such an increase in the reaction rate may be achieved by manipulating a number of system parameters contributing to the provision of heat, fuel and oxidizer to a single cell (control volume). The control volume may be envisioned from a number of perspectives. In this case, meaningful results may be achieved by focusing on control volumes associated with a single shelf, the shelving array and the surrounding room. According to the results of the filing survey, the bulk density of fuel per shelf in compact mobile storage arrays is typically high. Such tightly packed file storage is conducive to a fuel rich environment within the closed portion of the array. This differs from other common forms of storage, such as rack storage, which even filled to capacity offers ample porosity and exposed fuel surface area to support fire development and growth. A review of existing test data underscores the significance of this fuel packing density variable as a determinant for fire spread interior to the array. Certainly in real world applications, portions of compact mobile shelving units could be less than “full” for many reasons, including the ability to provide future storage capacity. Tests were conducted to establish the density of the commodity that provides the reasonable most severe conditions for interior fire spread and severity. This density was used consistently throughout the array in all subsequent tests as detailed further in the following discussion. The bulk density of the fuel may also be expressed in terms of its porosity. One of the most prominent efforts to estimate the burning rate of a cellulosic fuel as a function of its porosity was a combined theoretical and experimental effort with wood cribs. The results of this effort determined that as the packing density of the wood cribs increases, the burning of the individual sticks constituting the crib more closely resembles the burning of a single large block of wood. In concept, this is not unlike the result observed in the initial Spacesaver test series where individual files and papers were packed together in a way which minimized the porosity of the block of fuel. According to the experimentally validated theory for wood cribs, the optimum reaction rate is proportional to exposed surface area and fuel thickness with the constant of proportionality determined by additional influences from material type (i.e. density and molecular composition) and moisture content.1 The first step toward specifically applying this concept to papers packed inside file folders is to determine a standard unit of fuel thickness that will be used throughout the array. It is suggested for practical reasons that this standard thickness correspond to a single file folder filled to capacity with tightly packed paper. Based on data collected from the filing survey, this standard thickness was chosen to correspond to 110 sheets of paper per folder, which produces an approximate 1 inch thickness with the folder lying flat on its face. The array was consequently be loaded with folders filled uniformly to this capacity. In theory, the condition providing the largest porosity of the bulk fuel would occur with uniform spacing between folders. However, this condition is not realistic as each individual folder would need to be provided with 1 Scale Modeling of the Transient Behavior of Wood Crib Fines in Enclosures, Jonathan Perricone – Interflam Conference, 2007 Fire Protection Research Foundation Compact Mobile Shelving System Fire Testing Project 7 June 2, 2008 SEC Project No.: 2007123-002 its own upright support. The more realistic condition includes a limited number of such supports per shelf (3 per shelf in the Spacesaver units) supporting leaning records. As the population of folders per shelf increases, the spacing between folders will decrease. Fuel porosity was maintained consistent across each shelving section subdivided by upright compacting supports. Bench Scale Testing In order to determine a feasible bulk fuel density which poses the most challenging fire protection scenario, a preliminary series of experiments was conducted with the focus placed upon the burning of fuel inside of a single shelf. The purpose of these preliminary tests was not to derive specifics of fire dynamics with respect to the array, but rather to make relative comparisons of fire severity at the reduced volume. For the arrays considered in this program, a single shelf with a length of 36 inches, a depth of 24.5 inches and a height of 9.75 inches was used. An error in fabrication resulted in a shelf height which differed from those used in the actual array; however, this discrepancy was irrelevant given that the goal of the bench scale testing was to assess relative fire behavior at the bench scale. This goal was achieved by maintaining consistent shelf dimensions for all bench scale tests. The full front and back faces of the compartment were open for each test. Based on the results of the filing survey, it was assumed that the minimum feasible fuel loading would be 70% of the total shelf space. A total of 5 free-burning single-shelf tests were therefore conducted within the range of 70-100% shelf fuel loading. The first four of these tests were conducted with a uniform fuel load across the length of the shelf corresponding to 100% (fully packed) in the first test, 70% in the second, 85% in the third, and 100% in the fourth. The fifth test utilized the same number of files as Test 2, yet concentrated packing to one side of the shelf such that a small section at the extreme end of the shelf was very lightly loaded while the remainder of the shelf was fully packed. Cerawool refractory blanket insulation was provided on the top surface of the shelf to simulate conduction losses to shelving above in an actual assembly, which would be filled with records (Figure 1). Measurements (in addition to video recording) taken during these tests include the following: • • • • • • • Fuel mass loss rate Total heat release rate (tests conducted under hood) Multiple gas temperatures at top center depth of shelf above fuel Solid surface temperatures at all inside and outside surfaces of the shelf Heat flux from one of the open faces of the compartment Heat flux from the flame extension back toward location of shelf above Flame height Fire Protection Research Foundation Compact Mobile Shelving System Fire Testing Project 8 June 2, 2008 SEC Project No.: 2007123-002 FIGURE 1. BENCH-SCALE TEST ARRANGEMENT (70% NON-UNIFORM LOADING)2 Ignition was consistently achieved with one-quarter of a standard igniter, which consisted of a 1.5 inch diameter by 3 inch long cellulosic fuel bundle soaked with 2 fluid ounces of gasoline and wrapped in a polyethylene bag, which was fully inserted between folders at the ignition location. This location was centered along the bottom front face of the shelf and fully inserted for the first 4 tests and moved to the bottom center of the lightly loaded shelving section for the final test. These initial tests were intended to provide an estimate of the most severe fuel loading condition on any given shelf within the array. It is important to note that these results will be specific to the type of fuel used. The introduction of a mixed commodity into the array, such as limited plastics, will change factors as fundamental as the stoichiometric proportions of the reaction. As a result, data regarding the rate of reaction as a function of bulk fuel porosity may be significantly altered. The array itself does pose additional influences on the burning fuel in the form of thermal feedback across and ventilation within individual flue spaces. However, these flue spaces are 2 Photo courtesy of UL Fire Protection Research Foundation Compact Mobile Shelving System Fire Testing Project 9 June 2, 2008 SEC Project No.: 2007123-002 limited to a minimum uniform width of 1 inch throughout the array. Therefore, additional tests to determine the most severe flue spacing were deemed unnecessary. It was recognized prior to this stage of testing that aspects of the full array would produce effects related to heat dissipation and bulk array ventilation which are significant factors in the final solution. However, the bench-scale testing was used simply as a tool for relative comparison of the general fire severity. Full Array Testing These tests focused on the compact mobile shelving systems typically found in offices and other Light Hazard Occupancies. The general dimensions of the compact mobile storage array was held constant with a height of 8 feet, depth of 2 feet (24 inches), and width of 3 feet (36 inches) per shelf. Two 12-inch deep fixed storage units were positioned each at opposite ends of the array as this is the standard for the majority of the compact units. One aisle with a width of 36 inches was provided between the units. The total size of the array, including this aisle space, was approximately 200 square feet (15 feet long by 13 feet 10 inches wide). Unlike the mobile storage units, the fixed storage units were equipped with metal backing. Vertical sheet metal barriers were also provided in the transverse direction between each of the 5 storage bays (i.e. at 3 foot intervals). A total of eight shelf levels were located within the unit as shown in Figures 2A and 2B. All shelving was noncombustible. FIGURE 2A. FULL SCALE COMPACT MOBILE SHELVING UNIT (SECTION VIEW) Fire Protection Research Foundation Compact Mobile Shelving System Fire Testing Project 10 June 2, 2008 SEC Project No.: 2007123-002 FIGURE 2B. FULL SCALE COMPACT MOBILE SHELVING UNIT (ISOMETRIC VIEW) Commodity was letter sized paper inside file folders stored perpendicular to the aisle. These file folders were 12 inches long, requiring a total of 24 inches of shelf depth. Although a 1 inch space was provided between the 24 inch deep mobile shelf units, due to randomness in file loading by lab personnel the paper folders overlapped in some areas of the flue space thereby potentially obstructing vertical flow of air from below and water from above. However, this randomness is assumed to mimic actual storage practices given that the loading personnel were not given specific instructions to avoid such a condition. Based on the results of the bench scale tests, it was decided that all shelves would be loaded to 70% capacity as uniformly as possible. Recognizing that each shelf within the array was divided into 4 sections by vertical file holders, direction was given to laboratory personnel to load uniformly with respect to each section of shelving. It was assumed that the result would yield as uniform a fuel loading condition as could be realistically expected for the array. The laboratory chosen for conducting these tests was the large scale test facility at Underwriter’s Laboratories (UL) located in Northbrook, Illinois (see Appendix C for complete facility description). A small 10,000 square foot section at the center of this 14,400 square foot room was used for these full-scale tests. The ceiling was lowered to the 10 foot elevation. Smoke exhaust capacity was provided at the uppermost corners of the test facility at rates low enough to minimize any potential impact to the test results. A total of 36 automatic sprinklers were provided underneath this simulated ceiling in accordance with the requirements of NFPA 13 for Light Hazard Occupancy. Fire Protection Research Foundation Compact Mobile Shelving System Fire Testing Project 11 June 2, 2008 SEC Project No.: 2007123-002 TABLE 1. CEILING SPRINKLER PROTECTION PARAMETERS (FULL SCALE TESTING) PARAMETER System Type DESCRIPTION Wet pipe ceiling level with looped piping serving 2.5 inch diameter branch lines Sprinkler Type Temperature Rating Nominal Flow Coefficient Orifice Size Sprinkler Spacing Coverage Area per Sprinkler Deflector to Ceiling Clearance Storage to Ceiling Clearance Nominal Flow per Sprinkler Nominal Pressure at Sprinkler Water Delivery Density Closed head quick response standard spray pendant o 155 F 1/2 5.6 gpm/psi 1/2 inch 15 feet 225 square feet 8 inches 18 inches 22.5 gpm 16.1 psig 2 Constant 0.10 gpm/ft Ignition was consistently achieved with one standard igniter, which consisted of a 3 inch diameter by 6 inch long cellulosic bundle soaked with 8 fluid ounces of gasoline and wrapped in a polyethylene bag, which was fully inserted between folders at the ignition location. Measurements (in addition to the video recording) taken during these tests included the following: • • • • • • • • • Gas temperatures at ceiling level at various locations above the array Sprinkler temperatures Gas and solid shelf surface temperatures within the array Total incident heat flux to the target arrays Commodity moisture content Sprinkler activation times Sprinkler system density Building ventilation below the simulated ceiling Activation of an ionization smoke detector centered at ceiling level above ignition Heat flux targets were provided on all four sides for each test. The target arrays were comprised of the same corrugated cardboard material which constitutes Class III commodity boxes. These targets were approximately the same height as the mobile array and separated from the main array by a distance of 3 feet. These targets were utilized in lieu of heat flux gauges in an effort to provide a more comprehensive measurement of critical heat flux level (i.e. ignition of the cardboard) due to the significantly larger viewing angle afforded by the larger target. Fire Protection Research Foundation Compact Mobile Shelving System Fire Testing Project 12 June 2, 2008 SEC Project No.: 2007123-002 Full Scale Test 1 The first full scale test incorporated the standard shelving unit configuration depicted in Figures 2A and 2B with one 36 inch wide aisle located centrally within the array, as shown on the test diagram in Figure 3. A nominal 1 inch flue space was maintained between each of the remaining shelving units within the array with no longitudinal barriers except for the metal backing along the back face of the fixed units at each end of the array. A vertical sheet metal divider support (same metal gage as the rest of the unit) was installed at the center depth of each shelving bay. This divider was approximately 4.75 inches tall and served to hold in place a total of 3 vertical sheet metal dividers per shelving bay (Figure 2B). The shelf where ignition was designed to occur was loaded to mimic the 70% non-uniform fuel loading studied in bench-scale Test 5. This was done in recognition of the results of the bench scale test series which demonstrated most significant fire growth and spread in this configuration. The intent for the full scale test was to provide a robust ignition source consisting of a fully involved shelf for a practical but conservative design scenario. All remaining shelves within the array were loaded at a uniform 70% packing density. The location of the ignition shelf was chosen at the bottom center of the array on the face fronting the open aisle and directly centered between 4 ceiling level sprinklers. Within the ignition shelf, the standard igniter was located in the same manner as the bench scale test with non-uniform fuel loading (Test 5). FIGURE 3A. FULL SCALE TEST 1 IGNITION LOCATION (ELEVATION VIEW)3 3 Figure Courtesy of UL Fire Protection Research Foundation Compact Mobile Shelving System Fire Testing Project 13 June 2, 2008 SEC Project No.: 2007123-002 FIGURE 3B. FULL SCALE TEST 1 IGNITION LOCATION (PLAN VIEW) A B C D E F G H I J Full Scale Test 2 The second full scale test consisted of a closed compact shelving array with a nominal 1 inch flue space between adjacent shelving units. A single 36 inch wide aisle was provided between the fixed shelving unit at the North end of the array and the closest moveable carriage. This was done to utilize the fixed unit as a target array for the measurement of radiant heat flux. In addition to this change, longitudinal vertical sheet metal barriers (same metal gage as the rest of Fire Protection Research Foundation Compact Mobile Shelving System Fire Testing Project 14 June 2, 2008 SEC Project No.: 2007123-002 the unit) running the full height of the shelving array were provided at the locations shown in Figure 4. These barriers were incorporated with the intent of slowing fire spread within the depth of the unit. All other significant experimental parameters remained consistent with those utilized in the first full scale test of the series. This includes the location of the ignition shelf and the fuel loading scheme within that shelf. Consequently, the ignition location for this test did not front an open aisle but rather a nominal 1 inch wide flue space. This location was once again centralized below the nearest 4 sprinklers at ceiling level. FIGURE 4. FULL SCALE TEST 2 (CLOSED ARRAY WITH LONGITUDINAL BARRIERS) A B C D E F G H I Fire barriers J Fire Protection Research Foundation Compact Mobile Shelving System Fire Testing Project 15 June 2, 2008 SEC Project No.: 2007123-002 EXPERIMENTAL RESULTS AND ANALYSIS Bench Scale Testing The results of the bench scale tests were intended to gage fire severity as a function of packing density. The concept of fire severity may incorporate a number of design parameters depending on the application. In this instance, the primary design concern is the rate of fire spread from the ignition cell to all adjacent cells. Therefore, the severity of the fire is most appropriately quantified in terms of the rate of heat release by the burning fuel. Table 2 provides important information regarding experimental inputs affecting this quantity as well as the results in terms of peak values. TABLE 2. BENCH SCALE RESULTS Test ID B-1 B-2 B-3 B-4 B-5 Packing Density All sections 100% All sections 70% All sections 85% All sections 100% Left section = 100% Left-center section = 100% Right-center section = 57% Right section = 29% Moisture Content 5.6% 5.6% 5.6% 5.4% Peak Heat Release Rate (kW) 1.3 16.5 8.9 7.4 5.4% 38.4 The most striking conclusion to be drawn from these results is that they are evidence of the how the efficiency of the combustion process is dependent on the packing density of the fuel within the shelving arrangement. For cases in which the shelf was very densely packed, the process of combustion was observed to be very similar to the burning of a thermally thick solid in which conduction heat losses play an important role. For very sparsely populated shelving, a fundamental change in fire dynamics occurs. Although folders still burn as thermally thick solids, the more significant focus becomes the synergistic effect of increased airflow and thermal feedback from the surrounding metal shelf boundaries. Both of these influences increase in magnitude as slumping files present natural pockets of air within the fuel as well as at the uppermost regions of the shelf. In this latter case, the burning is somewhat analogous to a localized compartment fire (Figure 5). Based on this analogy, the results may be presented in terms of the peak heat release rate (a measure of fire severity) as a function of an estimated ratio of the mass of fuel versus the mass of air stored within the boundaries of the shelf (Figure 6). For the non-uniformly loaded case, the size of the control volume is reduced to focus on the concentrated burning observed almost exclusively in the lightly loaded (29% packing density) quarter of the shelf. The non-linearity observed in this plot in addition to a peak value well below ballpark stoichiometric values is indicative of the thermal feedback to the burning fuel. This influence is most pronounced in the case of the lightly loaded shelf with slumped files, which behaves more like a well-ventilated compartment fire within that section of shelving. Ultimately, these results highlight the potentially significant influence of even localized file arrangement on the anticipated fire severity. Fire Protection Research Foundation Compact Mobile Shelving System Fire Testing Project 16 June 2, 2008 SEC Project No.: 2007123-002 FIGURE 5. LOCALIZED BURNING OBSERVED IN NON-UNIFORMLY LOADED SHELF FIGURE 6. DEPENDENCE OF FIRE SEVERITY ON EQUIVALENCE RATIO Peak Heat Release Rate (kW) 45 40 35 30 25 20 15 10 5 0 0.0 0.2 0.4 0.6 0.8 1.0 1.2 1.4 1.6 1.8 2.0 2.2 Fuel Mass / Air Mass The results of the bench scale test series were utilized to determine the manner in which the full scale compact shelving array would be loaded consistently for the full scale test series. Consequently, a uniform packing density of 70% was chosen for each section of shelving throughout the entire array with the exception of the shelf in which ignition was located. For both full scale tests, this particular shelf was loaded non-uniformly in the same manner as test B-5 which produced the most severe heat release rate. This was done to make the ignition model robust yet with a relatively short duration of influence on burning in the larger array. Fire Protection Research Foundation Compact Mobile Shelving System Fire Testing Project 17 June 2, 2008 SEC Project No.: 2007123-002 Full Scale Test 1 – Open Array The first full scale test incorporated the burning of an entire compact shelving array as described in the experimental setup section of this report. Smoke detection was recorded 44 seconds following ignition. Although ignition occurred in a shelf that fronted an open aisle and was located centrally at the bottom of the array, flame spread during the initial stages of fire growth did not occur vertically along the open face. Instead, as the fire burned within the ignition shelf, added thermal feedback from the fuel mass across the 1 inch flue space at the back of the shelf increased the intensity of the initial fire. This feedback mechanism, with sufficient oxidizer gaining access through the open aisle, quickly resulted in fire spread through the depth of the array and vertically upward within the flue space behind ignition. The fact that this flame spread occurred prior to spread up the vertical face of the open aisle is evidence of the relative significance of thermal feedback as a mechanism to increase fire intensity. Figure 7 presents the observation of more significant damage in terms of steel deformation in the flue space behind ignition than in the area facing the open aisle. This result is indicative of higher heat absorption in this area of the array, due to thermal feedback across the flue. At approximately 10 minutes after ignition, flames protruded from the top of the flue space behind ignition and banked off the ceiling above soon thereafter. Eventually, despite the operation of sprinklers overhead, which began at 36 minutes and 9 seconds after ignition, the fire built such significant inertia within the flue space that auto-ignition of a large area of fuel (several shelves in the central portion of the array) fronting the open aisle was observed over a very short duration. Though additional sprinklers operated following this observation, radiant heat transfer across the 3 foot wide aisle was sufficient to cause remote flame spread (aisle jump) at 54 minutes after ignition. It is important to note that these newly ignited files were exposed to water from operating sprinklers above the aisle prior to their ignition. Within less than 50 minutes after the activation of the first sprinkler, a total of 12 additional sprinklers activated. The sprinkler protection provided was unable to prevent fire spread across the open aisle and to the ends of the array during this time frame. The maximum one-minute average gas temperature at the ceiling above ignition was recorded as 1,460oF with a maximum one-minute average steel beam temperature of 1,063oF. Although these results seem severe at first appraisal, it is noteworthy that the period of fire growth preceding the well-developed stage took place over a relatively benign duration of 36 minutes with smoke detection occurring prior to 1 minute after ignition. There was no fire spread to the target arrays. The Light Hazard sprinkler protection scheme provided for this configuration failed to provide fire suppression or control. Smoke detection coupled with the characteristically slow growth of the fire observed in this case suggests a relatively large response time window for fire department personnel; however, the conclusion that such slow fire growth is characteristic of compact mobile shelving is only as certain as the assumptions on which it is based. It should be highlighted that this result is based largely on the assumption of a specific fuel loading arrangement as a practical worst-case scenario. Results of the bench scale test series indicated that fire severity is highly sensitive to this complex parameter. Fire Protection Research Foundation Compact Mobile Shelving System Fire Testing Project 18 June 2, 2008 SEC Project No.: 2007123-002 FIGURE 7. FIRE DAMAGE TO FLUE SPACE BEHIND IGNITION Full Scale Test 2 – Closed Array with Solid Barriers In an effort to exploit the potentially beneficial result of slow fire growth, the second full scale test was designed to incorporate solid steel barriers to divide the compact array into a series of smaller fuel areas. As an added benefit toward achieving this goal, these barriers theoretically provided resistance to airflow throughout the depth of the array as well as the disruption of thermal feedback across the flue spaces in which they were located (Figure 4). Based largely on the observation of the dominant mode of initial fire growth during the first full scale test, a closed array was utilized for the second experiment. All other significant test variables were held constant with respect to the first full scale experiment. The results of the second full scale test once again yielded early smoke detection. This time, detection occurred at approximately 1 minute and 52 seconds after ignition with visible flaming noted at the top level of storage within the flue space fronting ignition just over three minutes afterward. During the following 76 minutes of slow fire development, perhaps the most important observation was a noticeable flow of buoyant gas at the ceiling yet the absence of flames. Observations of temperatures during the test and damage patterns at the conclusion of this test indicated higher heat exposure surrounding the point of ignition than in the areas above that point (Figure 8). Fire Protection Research Foundation Compact Mobile Shelving System Fire Testing Project 19 June 2, 2008 SEC Project No.: 2007123-002 FIGURE 8. GAS TEMPERATURES WITHIN THE ARRAY - TEST 2 The temperatures profiles depicted in Figure 8 were taken at the top center of each flue space (8th level of shelving), with the exception of one measurement taken at the lowest level of shelving in the flue adjacent to ignition. The information provided facilitates the following significant observations about fire growth within the array which could not be made visually during the test: • For the first 20 minutes of this test, the accumulation of significant amounts of heat was limited in location to the flue spaces directly in front and directly behind the ignition shelf on the lowest level (1st level E). During this time, fire growth within flue space C-D lagged significantly behind growth in flue space E-F. • At approximately the 20 minute mark, the gas temperature at the top of flue space E-F begins to decay toward a new quasi-steady value of 300oC. At the same time, growth within flue space C-D increases. Observations of fire damage at the end of the test reveal that the decay in temperature was not due to the complete consumption of fuel within a certain area. Rather, it is the result of the high density storage burning initially at the surface and eventually lacking sufficient oxygen to continue burning the mass of files at the same rate in the same location. In other words, this is evidence of local ventilation limitations within the array. • For the first 20 minutes of the test, the temperatures at the top of flue space C-D (8th level) are significantly higher than those at the bottom (1st level). After a transition stage of several minutes, the situation reverses for the remainder of the test. Higher heat accumulation at the bottom of the array is evidence of flame quenching by heat absorption within the array at the upper levels. This coincides with the observation of no visual flaming above the array during this time period. • The solid barrier separating shelving bays F and G (Figure 4) assists in slowing the transfer of heat to flue space G-H. During the hour following ignition, the gas Fire Protection Research Foundation Compact Mobile Shelving System Fire Testing Project 20 June 2, 2008 SEC Project No.: 2007123-002 temperatures within this area remain very near ambient. Following this period, towards the end of the test, an approximate rate of gas temperature rise of 25 degrees per minute is observed until a maximum of nearly 300oC is reached. This relatively slow rate of rise suggests an absence of flaming combustion behind the barrier, which would be expected to produce a more severe rate of temperature rise. Together, these observations confirm the mechanism for slow fire growth within the unit. The rate of the combustion process is determined by a delicate balance commonly expressed as the conservation of energy. When the generation of heat by the chemical reaction supersedes the magnitude of heat losses from the system, energy is reinvested in the system and the process is self-sustaining4. In other words, fire needs sufficient heat in conjunction with the right mixture of fuel and oxidizer to sustain itself. For ventilation limited fires, the generation of heat is limited by the diffusion of oxygen into the reaction zone. This limited access to oxygen can slow the rate of heat generated by the system and significantly impact the energy balance, resulting in slower fire growth and spread. For the first full scale test, ample access was provided via close proximity to the open aisle in the middle of the array. With a closed array including solid barriers, the access of air to the fire area was limited thereby resulting in a less intense reaction. Simultaneously, as flaming gases rose vertically within the unit, they lost such significant heat to the surrounding unburned fuel that the flame was quenched at an elevation within the unit. The result was the observation of gasified yet unburned fuel reactants rising to the ceiling. Eventually, by the time the fire was able to spread laterally to the end of the array, additional oxidizer offset the balance. This resulted in rapid flame spread through the premixed gases located at the top of the array. This flame spread fed the fire from the top-down to produce a well developed reaction throughout the array. It was at this point, nearly 81 minutes after ignition, when four ceiling sprinklers activated within the span of 40 seconds. During this most intense time-period of fire growth prior to the termination of the test, the maximum one-minute average steel beam temperature was measured at 846oF with a maximum one-minute average gas temperature of 1560oF above ignition. The results of Test 2 demonstrated that fire control can be achieved for a certain period of time without automatic sprinkler protection, provided that the energy balance is manipulated by minimizing energy generation and maximizing heat losses to the array. Methods of accomplishing these objectives include limiting the access of air into the interior of the unit while also introducing enough energy absorbing material (i.e. densely packed fuel and solid steel barriers) to limit flame height. However, recognizing that the result is a delicate balance among a number of influential parameters, it is prudent to investigate any practical disruptions of this balance that could limit the range of applicability of the solution. Such influences include the following: 4 • Introduction of additional oxidizer into the unit. This could be accomplished by repeating full scale Test 2 in the same open array configuration used for Test 1. Such a test would isolate the energy absorbing contribution of the solid barriers to slow flame spread. • Manipulation of the fuel packing arrangement and density within the array. The results of the bench scale test series demonstrated the sensitivity of fire growth to the specific fuel arrangement. A minimum practical packing density has been assumed in this test Quintiere, J. Fundamentals of Fire Phenomena. John Wiley & Sons, LTD. England, 2006. Fire Protection Research Foundation Compact Mobile Shelving System Fire Testing Project 21 June 2, 2008 SEC Project No.: 2007123-002 series based on limited filing survey information. A uniform arrangement of files has also been assumed throughout the array. • Variation in the type fuel burning within the array (i.e. introduction of plastics) influences the optimal balance of fuel and oxidizer. • Variation of the geometry of fuel burning within the array (i.e. introduction of shapes other than standard file folders) influences thermal feedback within the compartment. • Fuel type and geometry also dictate the energy balance (energy generation and absorption) within the array, which may potentially be used as a means for fire control. The full scale tests were intended to simulate fire behavior for paper files stored in a specific size compact mobile shelving unit subject to frequent use. This was done to mimic an expected use of the product in an office setting. It is therefore appropriate to discuss performance objectives that define what is meant by fire control. The following criteria are often used for such an assessment: • • • The extent of visual fire damage laterally to the ends of the array Sufficient radiant heat transfer to cause remote ignition of a target fuel load The magnitude of heat to which the ceiling / structure is exposed. This may be assessed in terms of gas temperatures at the ceiling. Automatic sprinklers act to control or suppress a fire by applying water and consequently removing heat from the reaction zone. Therefore, evidence of control may be crudely assessed visually by inspection of the extent and magnitude of heat damage to an array of fuel. The general idea behind this method of assessment is that undamaged portions of the array represent areas where enough heat was absorbed by sprinkler water to prevent the advancement of the flame front within close proximity. However, this straightforward method of assessing sprinkler performance becomes potentially very inaccurate in situations where additional heat absorbing influences are present. As evidenced by the results of full scale Test 2 in this series, the relatively high density storage contained within the compact mobile shelving array acts as both a shield to sprinkler water from above as well as an alternative heat absorber for achieving fire control. These characteristics make it difficult to assess sprinkler performance by visual observation of heat damage at the end of a test. However, the recorded system flow shows a consistent positive slope, indicating that the fire growth within the unit is essentially unchecked by the rate of water application (Figure 9). Fire Protection Research Foundation Compact Mobile Shelving System Fire Testing Project 22 June 2, 2008 SEC Project No.: 2007123-002 FIGURE 9. SPRINKLER SYSTEM FLOW – TEST 1 Remote ignition of a target fuel load during a test is evidence that the source fire has grown enough to pose a significant threat to its surroundings. This occurrence is typically defined as a failure point for the attainment of fire control because it requires a significant buildup of heat within the reaction zone, contrary to the action of heat absorption by sprinkler water. Remote ignition of a target fuel load across a 3 foot wide aisle was observed during the first full scale test in this series. However, the event occurred approximately 54 minutes after ignition (53 minutes after smoke detection). Assuming that this result is repeatable, it would provide the fire department with significant response time prior to the onset of such high heat buildup within the array. However, from the perspective of assessing sprinkler performance, it is important to note that this aisle jump occurred following the activation of 5 sprinklers and contributed to the subsequent activation of another 8 within the following 30 minutes. As a result, it is clear that the sprinkler protection did little to control the developing fire. Concerning the second full scale test, it is reasonable to deduce that the lack of target ignition during the second full scale test was principally due to the very low view factor between the targets and the closed array. Assessing the severity of heat exposure to the ceiling necessary includes both the magnitude of the heat flux to the ceiling and the materials comprising the exposed construction. Traditional performance criteria for steel beams at the ceiling level stipulate a maximum steel temperature of 1000oF at any point for the duration of one minute and a gas temperature not to exceed 1000oF for the duration of 5 minutes at any point during the test. These standard criteria are based on a conservative approximation of the heat exposure necessary to significantly reduce the strength of a standalone steel beam (not part of an assembly)5. Such temperatures were measured in the first full scale test with a potential for similar results prior to termination of the second test. However, in both cases, these results were obtained quite late in the experiment (Figure 10). 5 Lie, T.T. Structural Fire Protection, American Society of Civil Engineers, NY: 1992. Fire Protection Research Foundation Compact Mobile Shelving System Fire Testing Project 23 June 2, 2008 SEC Project No.: 2007123-002 FIGURE 10. STEEL BEAM TEMPERATURES AT CEILING – TEST 2 It is important to note here that in an office environment, variations on ceiling construction materials, such as a suspended ceiling, is common. As a result, application of these standard criteria for standalone steel beams is perhaps overly conservative. Acoustic tile, which is a common material used in suspended ceiling construction, would be expected to sustain significant damage under lower levels of heat exposure than those established by the steel criteria. However, a suspended ceiling is not a structural element and could actually afford some degree of thermal insulation to more critical building components. Such interactions were not studied in detail during this test series. Table 3 summarizes significant results with an emphasis on peak and average peak temperatures. Note that both fires eventually exhibit similar maximums. The distinguishing characteristic between the scenarios is the prolonged period of growth in Test 2. TABLE 3. SUMMARY OF SIGNIFICANT FULL SCALE TEST RESULTS PARAMETER Peak Gas Temperature at Ceiling Above Ignition Maximum 1 Minute Average Gas Temperatures at Ceiling Above Ignition Maximum 1 Minute Average Steel Beam Temperature Above Ignition Peak Steel Beam Temperature Period of Fire Growth Preceding Sprinkler Operation Duration of Test Following Last Sprinkler Operation Total Number of Sprinklers Activated Remote Fire Spread (Across Aisle or to Targets) TEST 1 RESULT (Open Array) o 1551 F o 1460 F o TEST 2 RESULT (Closed array, barriers) o 1585 F o 1560 F o 902 F o 1063 F 846 F o 928 F 36 min, 9 sec 4 min, 2 sec 13 Across 3 foot wide aisle at 54 min 81 min, 11 sec 9 sec 4 None Fire Protection Research Foundation Compact Mobile Shelving System Fire Testing Project 24 June 2, 2008 SEC Project No.: 2007123-002 CONCLUSION AND RECOMMENDATIONS Valuable information has been gained from the study of paper files burning in compact mobile shelving units under a 10 foot ceiling with Light Hazard automatic sprinkler protection. The potentially high degree of shielding inherent to the function of these storage units is problematic given the limitations placed on the access of water discharged by ceiling level sprinklers. In addition, significant complexity is introduced by the number of potential permutations of fuel type and storage arrangement within any given unit. A survey of user filing practices was conducted to estimate the range of potential fuel loads to be expected in paper file storage applications. Bench scale testing was utilized to determine relative fire severity as a function of this packing density. The results of this first phase of testing included the following: • Densely packed files burn similar to a solid slab of fuel. In the most extreme cases (100% packed), burning is limited to flame spread across the outside surface of the fuel mass. Very limited burning is possible in sporadic areas where fuel, oxygen and heat are all in sufficient supply. • As the density of storage is decreased uniformly, the “slab” of fuel becomes porous, thereby allowing for fuel, heat and oxidizer to combine in sufficient quantities to produce flames within the shelving unit. • The shelving unit presents a mechanism for thermal feedback to the burning fuel. This exchange of radiant energy intensifies the rate of reaction thereby increasing fire severity. The magnitude of this influence is directly related to the exposed surface area of the fuel with respect to the shelving. This parameter typically increases when files are slumped as opposed to standing perfectly upright. • Slumping files are the result of sparse file storage in any given section of the array. Such a configuration not only increases the thermal feedback mechanism, but also allows for a smaller fuel to air mass ratio (i.e. equivalence ratio). This creates a synergy between these mechanisms and the rate of reaction is consequently optimized. For conservative design, this phenomenon was exploited to the extent permitted by practical use of compact mobile shelving units as determined in the filing survey. The result was the selection of a 70% packing densely distributed uniformly throughout the array in each full scale test (with the exception of the ignition shelf). • The dependence of the peak heat release rate on the equivalence ratio is evidence that the results of these tests with paper files should not be blindly applied to other fuel types with different chemical properties (i.e. plastics). The full scale testing component of this series afforded an opportunity to assess the effects of the array configuration on the thermal feedback and air access issues highlighted by the bench scale testing. In both tests, the high density storage configurations yielded relatively quick smoke detection and slow fire growth, thereby potentially affording responding firefighters ample time to produce fire control and suppression. However, the relatively slow growth of the fire in both cases studied was not primarily the result of the automatic sprinkler protection provided. Rather, slow fire growth was the produce of a near balance between the energy generated by the developing fuel-rich fire and the heat losses to the massive fuel structure surrounding the Fire Protection Research Foundation Compact Mobile Shelving System Fire Testing Project 25 June 2, 2008 SEC Project No.: 2007123-002 area of burning. In this manner, the high density storage array proved capable of accomplishing the same heat absorption objective of the automatic sprinkler system; however, this mechanism of energy conservation is a delicate balance of several complex variables. In addition the following important conclusions have been reached: • The automatic sprinkler system provided cooling of both the ceiling and top of the storage arrays in both tests. However, due to the shielding of the fire, sprinkler discharge could not reach the majority of the commodity. It is unlikely an increase in sprinkler system density would improve the situation due to this shielding. • The implementation of solid barriers into the shelving unit acted to decrease the flow of oxygen within the structure and also increased the dissipation of heat away from the reaction zone. By minimizing the magnitude of energy generated by the fire while simultaneously maximizing heat losses to other parts of the system, the experimental setup of Test 2 succeeded in providing fire control for 81 minutes following ignition. During this time, no sprinklers were active. The energy balance achieved in this test is the product of a specific type and configuration of both the fuel and the shelving unit. • A third full scale test should be conducted. This test should be a repeat of Test 1, however with horizontal barriers installed as in Test 2. This scenario should be tested to confirm the ability of the horizontal barriers to limit fire damage in a full range of likely shelf positions. Submitted by, SCHIRMER ENGINEERING CORPORATION SCHIRMER ENGINEERING CORPORATION ____________________________________ Jonathan Perricone, P.E. Associate Engineer _____________________________________ Garner A. Palenske, P.E. Vice President/Regional Engineering Manager JP:jm S:\SNDGO\PROJECTS\JOB 2007\207123 NFPA Compact Storage Testing\rpjp.161.Fire Testing Project 6.2.08.doc APPENDIX A SUMMARY OF RELEVANT EXISTING EXPERIMENTAL DATA (LITERATURE REVIEW) TABLE A l . COMPACT SHELF STORAGE TEST DATA fire controlled, but in the transverse direction, tier 12 tapes GBA-89-2 NRCC-05-1 Double the amount of plastic computer tapes Paper files in storage boxes vertical steel barriers at 42 inches in the transverse direction, tier 12 inches high Solid steel shelves, end panels and tops. 36 inches in depth, vertical steel barriers at 42 inches in the transverse direction, tier 12 inches high. Additional steel vertical barrier, provided to subdivide the shelf depth from 36 inches to 18 inches Open shelves without end panels or tops. 6 tiers, 10 inches tall, 32 inches wide, 30 inches deep, with steel barrier to subdivide the shelf depth to 15 inches. Open shelves without end panels or tops. 6 tiers, 10 inches tall, 32 inches wide, 30 inches deep, with steel barrier to subdivide the shelf depth to 15 inches. Open shelves without end panels or tops. 6 tiers, 10 inches tall, 32 inches wide, 30 inches deep, with steel barrier to subdivide the shelf depth to 15 inches. Open shelves without end panels or tops. 6 tiers, 10 inches tall, 32 inches wide, 30 inches deep, with steel barrier to subdivide the shelf depth to 15 inches. Open shelves without end panels or tops. 6 tiers, 10 inches tall, 32 inches wide, 30 inches deep, with steel barrier to subdivide the shelf depth to 15 inches. - 36 in 7.833 ft 42 in (45.5 + 48.75) in - l8 in 32 in = 2.33 7.833 ft = 2.13 - l5 in 7.8 in 7.89 ft = 0.48 + 0.52 throughout = 0.48 -+ 0.52 1-2 inches throughout 0.20 None Onloff None = 0.08 minutes. fire controlled % inch, 165 Degree F,QR, 1 0 f t x l O f t spacing Unit closed, no aisle 2 sprinklers operated Q 12 and 60 minutes. fire controlled fire controlled Onloff Unit closed, no aisle Uncontrolled, test terminated Uncontrolled, test terminated 1100 OF sustained with 4 sprinklers operating 0.46 Pendant, QR Unit closed, no aisle Uncontrolled, shelf failure, test terminated Uncontrolled, shelf failure, test terminated 1650 OF sustained prior to shelf failure and termination of test Unit closed, no aisle Fire extinguished 0.70 Sidewall, QR See report for sprinkler layout Fire extinguished 1 inch Ambient to 1650 OF and back to ambient in 1 minute. 0.50, then 0.60 at 25 minutes Sidewall, QR See report for sprinkler layout Unit closed, no aisle Uncontrolled, then extinguished when higher density was applied Uncontrolled, then extinguished when higher density was applied Not reported. 1 inch Unit closed, no aisle Delayed control 0.70 Sidewall, QR See report for sprinkler layout Delayed control 1 inch 1300 OF and climbing until increased sprinkler density suppresses fire. Waffle ceiling assembly. Upright, % inch, 165 Degree F,QR, 1 0 f t x l O f t spacing 700 OF p p p p p p NRCC-05-2 NRCC-05-3 NRCC-05-4 NRCC-05-5 Paper files in storage boxes Paper files in storage boxes Paper files in storage boxes Paper files in storage boxes Test series ID = Agency - Year - Test Number FM = Factory Mutual GBA = Gage Babcock & Associates NRCC = National Research Council of Canada 32 in -= l 5 in 2.13 7.8 in 7.89 ft 32 in 7.8 in l5 in 7.89 32 in 7.8 in l 5 in 7.89 32 in 7.8 in -= 2.13 -- = 2.13 - l5 = 2.13 7.89 ft ft ft = 0.08 = 0.08 = 0.08 = 0.08 ~ APPENDIX B FILING SURVEY RESULTS FILING SURVEY In pursuit of determining a practical range of conditions for the bulk fuel density, a survey of filing practices in compact mobile shelving units was conducted. This survey consisted of visits to a total of three healthcare related sites local to the San Diego area. Locations are referenced herein as Hospitals A, B and C, respectively. It is important to note that the last of these visits (Hospital C) utilized compact mobile shelving units for the purpose of storing medical supplies. A total of 2 units at this facility were surveyed. The first of these units, manufactured by Metro, was 9 feet tall and 8 feet long, with each module subdivided into 4 rows and 2 columns of metal wire rack shelving. The depth of each of the 4 modules comprising the unit was 30 inches. It is estimated that stored commodity types and proportions throughout the unit were as follows: • • • • • • Rubber gloves ~ 10% total fuel load Foam pillows, foam sandles ~ 30% total fuel load Inflatable leg braces ~ 10% total fuel load Electronic pressure monitoring kits ~ 10% total fuel load Neck braces ~ 20% total fuel load Cloth garments ~ 20% total fuel load The second of these units, manufactured by Linco, was located in a separate room. This unit was 6 feet tall and 6 feet long, with each module subdivided into 6 rows of shelves spanning the entire length of the unit. The depth of each of the 5 modules comprising the unit was 30 inches. It is estimated that stored commodity types and proportions throughout the unit were as follows: • • • Stainless steel surgical equipment in plastic bags ~ 75% total fuel load Rubber gloves ~ 15% total fuel load Face masks, doctor’s surgical robes ~ 10% total fuel load Although these findings are not particularly useful in characterizing the storage of file folders in compact mobile shelving units manufactured by Spacesaver, they serve as an important reminder that compact mobile shelving units may be utilized for a much wider range of commodity storage applications. The remaining two site visits focused exclusively on file folder storage in compact mobile shelving units manufactured by Spacesaver. The unit located at the Hospital A storage site was stored in a room with a 9.5 foot tall ceiling. The unit itself was 6 feet and 10 inches tall, leaving a clearance of 32 inches to the underside of the suspended ceiling above. Pendent style automatic sprinkler protection was provided below the suspended ceiling with a roughly estimated deflector to storage clearance of 24 inches. Commodity storage was observed to be limited to manila file folders with plastic tab identification labels. Folders were observed to have a typical thickness of approximately 1.5 inches. Pictures are provided in Figure B1. FIGURE 1. SPACESAVER STORAGE – HOSPITAL A The bulk fuel density for each of the 28 individual shelves in a single module was evaluated based on the number and thickness of file folders present and the total length of available space remaining on the shelf with all files held to one side in the upright position. Prior to this measurement, it was noted that no dividers were observed throughout the entire storage unit. This measurement technique indicated the following distribution of bulk densities for that particular module. This distribution was taken as representative of the entire unit. The mode of this data set was 100% fully packed, which was a value measured for 15 of the 28 shelves. The remainder of the unit was packed at bulk fuel densities ranging from 50% - 95%. The 95% confidence interval for the actual mean of this data yields a range of bulk densities from 83% - 94%. The same survey procedure was undertaken at Hospital B. The compact mobile shelving unit at this location, manufactured by Spacesaver, was stored with an estimated clearance between the top of storage and the sprinkler deflector of approximately 24 inches. The unit contained a total of 10 modules subdivided into 4 rows and 6 columns. The stored commodity consisted of paper files in manila folders with plastic identification tabs as shown in Figure B2. The typical thickness of these folders was estimated as 1.5 inches. One issue of significance as evidenced by this photograph is the prevalence of partial storage across the length of individual shelves. In other words, it was not uncommon for an entire section of any given shelf to be completely void of any files. Furthermore, for the section of such shelves which was loaded, this block was found to be less than fully packed. The bulk fuel density for each of the 24 individual shelves in a single module was evaluated based on the number and thickness of file folders present and the total length of available space remaining on the shelf with all files held to one side in the upright position. Prior to this measurement, it was noted that dividers were present throughout the storage unit. The mode of this data set was 80% fully packed, which was a value measured for 10 of the 28 shelves. The remainder of the unit was packed at bulk fuel densities ranging from 50% - 95%. The 95% confidence interval for the actual mean of this data yields a range of bulk densities from 70% - 79%. FIGURE B2. SPACESAVER STORAGE – HOSPITAL B APPENDIX C UNDERWRITERS LABORATORIES TEST REPORT Fire Performance Evaluation of Nominal K=5.6 Ceiling Sprinklers For Protecting 8-Ft. High Storage of Class III Commodity in Compact Mobile Shelving Under a 10-Ft. Ceiling Technical Report Underwriters Laboratories Inc. Project 07CA64050, NC5756 for the Fire Protection Research Foundation April 3, 2008 Copyright © 2008, Underwriters Laboratories Inc. NC5756 07CA64050 Issued: 04/03/2008 EXECUTIVE SUMMARY A series of five (5) bench scale and two (2) large scale fire tests was conducted to develop data regarding the level of protection provided by nominal K-5.6 (gpm/psi ½) pendent, quick response ceiling sprinklers in protecting an arrangement of paper in standard manila paperboard folders stored in moveable compact mobile shelving units to a nominal height of 8- ft. Bench scale testing consisted of a single 36-in x 24-in x 9.75-in sheet metal shelf loaded with varying densities of commodity. A total of five bench scale fire tests were conducted on a load cell beneath a calorimeter where total heat release rate was measured over the course of each test. Based on the results of these bench scale tests, the project sponsors determined that a 70% loading density by volume would be used as the basis for both large scale fire tests. The tests were conducted under a 10- ft high ceiling with 155°F pendent ceiling sprinklers installed on 15 by 15-ft. spacing with the deflectors positioned 8- in. below the ceiling. The first large scale test was conducted with the moveable compact mobile shelving units in the open position, including a 3-ft. center aisle. The second large scale test was conducted with the moveable compact mobile shelving units in the closed position, and included full- height longitudinal sheet metal barriers in two of the four 24- in deep moveable shelving units. For both large scale tests, the ceiling sprinkler system was supplied with water resulting in a nominal sprinkler discharge density of 0.10 gpm/ft2 . The ignition location for each of the two tests was located between four sprinklers. The large scale fire tests utilized both moveable and fixed compact shelf units. The individual shelving fixtures in the moving units of the systems were nominally 3- ft wide, 2- ft deep, and 8- ft tall. Vertical transverse sheet metal barriers were provided between each of the five (5) storage bays at 3- ft. intervals. There were eight (8) shelf levels positioned with a nominal vertical spacing of 8, 18.5, 29, 39.5, 50, 60.5, 71, 81.5 and 95-in. from the floor. There were five (5) shelf fixtures in each row with a total length of 15- ft. For the first large-scale fire test, an open shelving arrangement was used consisting of six compact shelf units. Five of the compact shelf units were moveable. Four of the moveable units were approximately 24-in. deep and one moveable unit was approximately 12- in. deep. The sixth compact shelf unit was fixed and approximately 12- in. deep. The compact shelf configuration was open with a 36-in aisle space provided in the center of the array. No longitudinal barriers were provided. The target arrangement consisted of cardboard fixed to upright structures. The paper- faced cardboard was positioned across a 36- in. aisle space on the north, south, east and west sides of the compact shelving array. The cardboard affixed to the target assembly spanned 16- ft. long x 8- ft high. The first large scale fire test was conducted for 90 minutes (90:00). A total of thirteen (13) ceiling sprinklers operated during the 90- minute test period. The fire in Test 1 propagated to the east, west and south ends of the main shelving array. However, the fire was contained within the main shelving units and did not spread to the adjacent targets. 1 NC5756 07CA64050 Issued: 04/03/2008 For the second large-scale fire test, a closed shelving arrangement was used consisting of five moveable compact shelf units in the main array and one fixed compact unit as a target. Four of the moveable units were approximately 24- in. deep and one unit was approximately 12- in. deep. Full height longitudinal sheet metal barriers were installed in two of the four 24- in deep moveable units. The sixth compact shelf unit was a target which consisted of a 12- in. deep compact shelving unit positioned across a 36-in aisle on the north side, filled to the same capacity of the main shelving array. Cardboard fixed to upright structures were also placed across a 36- in. aisle space on the south, east and west sides of the compact shelving array. The cardboard target assemblies spanned 16- ft. long x 8- ft. high. The second large scale fire test was conducted for 82 minutes (82:00). A total of four (4) ceiling sprinklers operated during the 82- minute test period. The fire in Test 2 propagated to the east and west ends of the array, but was generally limited to the area between the full- height longitudinal sheet metal barriers. The fire was contained within the main shelving units and did not spread to the adjacent target arrays. A summary of the parameters and results is presented in Table E1. 2 NC5756 07CA64050 Issued: 04/03/2008 FIRE TEST DATE Test Code 01/11/2008 01110802 01/18/2008 01180802 Compact Mobile Shelving Compact Mobile Shelving Parameters Storage Type Shelving Array Configuration Open Closed Commodity Type Paper in manila folders with 70% loading density Paper in manila folders with 70% loading density Nominal Storage Height (ft) 8 8 Nominal Ceiling Height (ft) 10 10 Deflector Clearance to Storage (in) 18 18 Aisle Width (in.) 36 36 Shelf Type Solid Steel Solid Steel Longitudinal Barrier None Solid Steel Transverse Barrier Solid Steel Solid Steel Nominal Shelf Depth (in.) 24 24 Ignition Location Beneath Walkway Sprinklers Between 4 Sprinklers Between 4 Sprinklers Ceiling Sprinkler Temperature Rating °F 155 155 Deflector to Ceiling (in) 8 8 Nominal Ceiling Sprinkler Discharge Coefficient K (gpm/psi ½) 5.6 5.6 Nominal Ceiling Sprinkler Discharge Pressure (psi) 16.1 16.1 2 Nominal Ceiling Sprinkler Discharge Density (gpm/ft ) 0.10 0.10 Ceiling Sprinkler Spacing (ft x ft) 15 x 15 15 x 15 Length of Test (min:s) 90 82 First Ceiling Sprinkler Operation (min:s) 36:09 81:11 Last Ceiling Sprinkler Operation (min:s) 85:58 81:51 Number of Operated Ceiling Sprinklers 13 4 Peak Gas Temperature at Ceiling Above Ignition °F 1551 1585 Maximum 1 Minute Average Gas Temperature at Ceiling Above Ignition °F 1460 1560 Peak Steel Temperature at Ceiling Above Ignition °F 1063 928 Maximum 1 Minute Average Steel Temperature Above Ignition °F 902 846 Fire Spread Across Aisle Yes No Fire Spread To the Ends of the Array Yes Yes Fire Spread to Target No No Results Table E1 – Summary of Test Parameters and Results 3 NC5756 07CA64050 Issued: 04/03/2008 NOTE This Report was prepared as an account of a test sponsored by and under the direction of the Fire Protection Research Foundation. In no event shall UL be responsible for whatever use or nonuse is made of the information contained in this Report and in no event shall UL, its employees, or its agents incur any obligation or liability for damages arising out of or in connection with the use, or the inability to use, information contained in this Report. 4 NC5756 07CA64050 Issued: 04/03/2008 Table Of Contents INTRODUCTION......................................................................................................................... 7 1 TEST FACILITY.................................................................................................................. 7 2 EQUIPMENT AND INSTRUMENTATION ..................................................................... 8 2.1 2.2 2.3 3 8 8 9 TEST ARRANGEMENT ................................................................................................... 11 3.1 3.2 3.2.1 3.2.2 3.3 3.4 3.4.1 3.4.2 4 BENCH SCALE INSTRUMENTATION CEILING SPRINKLER SYSTEMS LARGE -SCALE INSTRUMENTATION BENCH SCALE TESTING AND RESULTS LARGE -SCALE TESTING Test 1 Test 2 TEST METHOD – LARGE SCALE TESTS 1 AND 2 TEST RESULTS Test 1 Test 2 11 14 14 17 20 24 24 24 SUMMARY......................................................................................................................... 45 APPENDIX A ................................................................................................................................ 1 GRAPHICAL PRESENTATION OF HEAT RELEASE RATE DATA FOR BENCH-SCALE TESTING 1 1 1 APPENDIX B ................................................................................................................................ 1 GRAPHICAL PRESENTATION OF TEMPERATURES AND W ATERFLOW - TEST 1 1 1 APPENDIX C ................................................................................................................................ 1 GRAPHICAL PRESENTATION OF TEMPERATURES AND W ATERFLOW - TEST 2 1 1 List of Tables TABLE 1 TABLE 2 TABLE 3 SPRINKLER W ATER SUPPLY PARAMETERS ........................................................................................................ 8 BENCH-SCALE TEST PARAMETERS AND RESULTS.......................................................................................... 11 SUMMARY OF TEST PARAMETERS AND RESULTS........................................................................................... 26 Table Of Figures FIGURE 1 FIGURE 2 FIGURE 3 FIGURE 4 FIGURE 5 FIGURE 6 FIGURE 7 FIGURE 8 FIGURE 9 FIGURE 10 TEST FACILITY ....................................................................................................................................................... 7 NOMINAL K=5.6 PENDENT SPRINKLER.............................................................................................................. 9 SPRINKLER AND INSTRUMENTATION LOCATIONS........................................................................................... 10 BENCH-SCALE TEST A RRANGEMENT – ELEVATION VIEW............................................................................ 12 BENCH-SCALE TEST A RRANGEMENT – PLAN VIEW....................................................................................... 12 BENCH-SCALE TEST A RRANGEMENT ............................................................................................................... 13 PLAN VIEW – TEST 1........................................................................................................................................... 15 PLAN VIEW DETAIL – TEST 1............................................................................................................................. 16 EAST / WEST ELEVATION VIEW – TEST 1........................................................................................................ 17 PLAN VIEW – TEST 2........................................................................................................................................... 18 5 NC5756 07CA64050 FIGURE 11 FIGURE 12 FIGURE 13 FIGURE 14 FIGURE 15 FIGURE 16 FIGURE 17 FIGURE 18 FIGURE 19 FIGURE 20 FIGURE 21 FIGURE 22 FIGURE 23 FIGURE 24 FIGURE 25 FIGURE 26 FIGURE 27 FIGURE 28 FIGURE 29 FIGURE 30 FIGURE 31 FIGURE 32 FIGURE 33 FIGURE 34 FIGURE 35 FIGURE 36 FIGURE 37 FIGURE 38 FIGURE 39 FIGURE 40 FIGURE 41 FIGURE 42 FIGURE 43 Issued: 04/03/2008 PLAN VIEW DETAIL – TEST 2............................................................................................................................. 19 EAST ELEVATION VIEW – TEST 2...................................................................................................................... 20 TEST SET -UP PHOTOS - TEST 1.......................................................................................................................... 21 TEST SET -UP PHOTOS - TEST 1.......................................................................................................................... 22 TEST SET -UP PHOTOS - TEST 2.......................................................................................................................... 23 EXTENT OF FIRE SPREAD – TEST 1 PLAN VIEW .............................................................................................. 27 SPRINKLER OPERATIONS – TEST 1.................................................................................................................... 28 RACK ORIENTATION FOR DAMAGE A SSESSSMENT VIEWS – TEST 1............................................................ 29 DAMAGE – TEST 1, UNIT A................................................................................................................................ 29 DAMAGE - TEST 1, UNIT B................................................................................................................................. 30 DAMAGE - TEST 1, UNIT C................................................................................................................................. 30 DAMAGE – TEST 1, UNIT D................................................................................................................................ 31 DAMAGE - TEST 1, UNIT E................................................................................................................................. 31 DAMAGE - TEST 1, UNIT F ................................................................................................................................. 32 DAMAGE - TEST 1, UNIT G................................................................................................................................. 32 DAMAGE - TEST 1, UNIT H................................................................................................................................. 33 DAMAGE - TEST 1, UNIT I .................................................................................................................................. 33 DAMAGE - TEST 1, UNIT J.................................................................................................................................. 34 POST TEST PHOTOS – TEST 1 ............................................................................................................................. 35 EXTENT OF FIRE SPREAD – TEST 2 PLAN VIEW .............................................................................................. 36 SPRINKLER OPERATIONS – TEST 2.................................................................................................................... 37 RACK ORIENTATION FOR DAMAGE A SSESSSMENT VIEWS – TEST 2............................................................ 38 DAMAGE – TEST 2, UNIT A................................................................................................................................ 38 DAMAGE - TEST 2, UNIT B................................................................................................................................. 39 DAMAGE - TEST 2, UNIT C................................................................................................................................. 39 DAMAGE – TEST 2, UNIT D................................................................................................................................ 40 DAMAGE - TEST 2, UNIT E................................................................................................................................. 40 DAMAGE - TEST 2, UNIT F ................................................................................................................................. 41 DAMAGE - TEST 2, UNIT G................................................................................................................................. 41 DAMAGE - TEST 2, UNIT H................................................................................................................................. 42 DAMAGE - TEST 2, UNIT I .................................................................................................................................. 42 DAMAGE - TEST 2, UNIT J.................................................................................................................................. 43 POST TEST PHOTOS – TEST 2 ............................................................................................................................. 44 6 NC5756 07CA64050 Issued: 04/03/2008 INTRODUCTION This Test Report describes the Special Service Investigation conducted for the Fire Protection Research Foundation to develop fire test data relative to the level of protection provided for a fire scenario involving a compact mobile shelving arrangement of paper in manila folders. 1 TEST FACILITY The fire tests were conducted in Underwriters Laboratories Inc.’s large-scale fire test facility located in Northbrook, Illinois. The large-scale fire test building used for this investigation includes four fire test areas that are used to develop data on the fire growth and fire suppression characteristics of commodities, as well as the fire suppression characteristics of automatic water sprinkler systems. A schematic of the test facility is shown in Figure 1. ADD Test Facility Large Scale Fire Test Facility Heat Release Calorimeter & RDD PDPA Test Facility Conditioning Room Warehouse Figure 1 Test Facility The fire tests were conducted in a 120 by 120 by 54- ft. high room fitted with an adjustable height ceiling. The ceiling was positioned 10-ft above the floor. The test room was equipped with an exhaust system including a regenerative thermal oxidizing (RTO) smoke abatement system. Make-up air was provided through four inlet ducts positioned along the walls of the test facility. The floor of the test facility was smooth, flat and surrounded with a grated drainage trench to insure adequate drainage from the test area. The water runoff from the suppression system drain was collected through a 180,000-gallon water treatment system. 7 NC5756 07CA64050 2 2.1 Issued: 04/03/2008 EQUIPMENT AND INSTRUMENTATION Bench Scale Instrumentation The instrumentation used in the bench-scale fire testing consisted of the following devices: • • • • • • • • 2.2 Three (3) 1/16- in. diameter, Type K inconel sheathed thermocouples attached to the shelving exterior to obtain shelf temperatures Three(3) 1/16- in. diameter, Type K inconel sheathed thermocouples positioned within the shelving to obtain gas temperatures Two (2) Radiometers Moisture meter to measure the commodity moisture content of the fuel package Weigh-scale in the appropriate range Electronic data acquisition system at a two-second-scan rate to obtain the oxygen consumption, temperature, and heat flux data Video and still cameras to capture and record images of the fire test Stopwatches and timing devices located within the data acquisition system were used to monitor and record significant events during the fire tests Ceiling Sprinkler Systems Thirty-six (36) quick-response standard spray pendent style sprinklers having a 155° F temperature rating and a nominal flow coefficient (K) of 5.6 gpm/psi1/2 were installed on 15-x 15-ft. spacing in a closed head, wet pipe, automatic sprinkler system at the ceiling level. The sprinklers were supplied through a looped piping system consisting of 2 ½- in. diameter branch lines. The sprinklers were positioned with the distance between the deflector and ceiling measured to be 8- in. The water supply to the ceiling sprinklers was controlled to achieve the parameters shown in Table 1. Close- up photos of the sprinklers used in this test are shown in Figure 2. A plan view of the sprinkler and instrumentation layout is shown in Figure 3. Table 1 Sprinkler Location Ceiling Sprinkler Water Supply Parameters Nominal flow per sprinkler (gpm) 22.5 8 Nominal pressure at sprinkler (psig) 16.1 NC5756 07CA64050 Issued: 04/03/2008 Figure 2 2.3 Nominal K=5.6 Pendent Sprinkler Large-Scale Instrumentation The instrumentation used in the testing consisted of the following devices: ` • 1/16 in. diameter, Type K inconel sheathed thermocouples located below the ceiling adjacent to each sprinkler to record temperatures. • 1/16 in. diameter, Type K inconel sheathed thermocouples located below the Elevated Access Walkway adjacent to each sprinkler to record temperatures. • 1/16 in. diameter, Type K inconel sheathed thermocouples located 6, 12, and 18-in. below the ceiling above the ignition location. • Five 1/16 in. diameter, Type K inconel sheathed thermocouples embedded in a 50.5-in. long steel beam attached to the bottom of the hard tile ceiling directly above the fire. • Bristol Babcock Model 250815B pressure transducers in a 0-100 psi range were used to measure the water pressure in the sprinkler system. • Fischer Porter model X3311SFD20 – 12 inch magnetic flowmeter in the 0-3200 gallons per minute (gpm) range were used to measure the water flow rate. • Stopwatches and timing devices located within the data acquisition system were used to monitor and record significant events during the fire tests. • Video and Infrared cameras were used to capture and record images of the fire test. 9 NC5756 07CA64050 Issued: 04/03/2008 Figure 3 Sprinkler and Instrumentation Locations 10 NC5756 07CA64050 3 Issued: 04/03/2008 TEST ARRANGEMENT 3.1 Bench Scale Testing and Results Bench scale testing was conducted beneath a 500-kW rated product calorimeter in a test room measuring 50- ft. x 15-ft. x 15-ft. (l x w x h) with a 12.75-ft. x 12.75-ft. square-shaped collection hood located centrally in the room approximately 7- ft. above the floor. Collected combustion products are exhausted by way of a 24- in. x 24- in. plenum into an 18- in. diameter exhaust duct for data measurement. Bench scale testing consisted of a single 36-in x 24-in x 9.75-in sheet metal shelf loaded with varying densities of commodity. A total of six (6) vertical sheet metal dividers approximately 9in. long x 6- in. high were attached to the shelf to evenly space the folders. The shelf enclosure was insulated on the top with a single thickness of Cerawool refractory blanket. The stored commodity consisted of sheet paper in common manila paperboard folders. Stored commodity loading was based on sheet count, folder count, and weight. Ignition was accomplished using a one-quarter standard igniter constructed from a 1.5-in. diameter by 3- in. long cellulosic bundle soaked with two fluid ounces of gasoline and wrapped in a polyethylene bag. Fire tests with a loading density of 100% were conducted twice to confirm baseline weight and folder count, and the loading arrangement ignition location was similar in both tests. Fire tests with a loading density of 70% were conducted twice to gather additional heat release data. In the first 70% loading test, 110 folders were evenly spaced back to back within the 24-in. deep shelf. In the second 70% loading test, the 110 folders were not evenly spaced but were more loosely loaded in the ignition area. With the test commodity samples loaded in the shelf assembly and positioned under the products collector with video and data collection operating, ignition was accomplished and the fire was allowed to burn freely until the fuel was either consumed or no longer sus tained combustion. The bench-scale test parameters and results are presented in Table 2. Test Load Density No. (%) Moisture Initial Weight Weight Loss Test Duration Folder Count Content (%) (lbs) (lbs) (min) Peak HRR (kW) 1 100 5.6 169.2 0.5 153 60 1.3 2 70 5.6 118.4 16.6 110 60 16.5 3 85 5.6 143.1 5 128 30 8.9 4 100 5.4 168.6 0.2 153 40 7.4 5 70 5.4 118.3 22.4 110 78 38.4 Note: All folders contained an average of 110 sheets of standard 8.5-in x 11- in plain white paper Table 2 Bench-Scale Test Parameters and Results 11 NC5756 07CA64050 Issued: 04/03/2008 A diagram of the bench scale shelf mockup and photos of the fire test arrangement are shown in Figures 4, 5 and 6. Figure 4 Figure 5 Bench-Scale Test Arrangement – Elevation View Bench-Scale Test Arrangement – Plan View 12 NC5756 07CA64050 Issued: 04/03/2008 Figure 6 Bench-Scale Test Arrangement 13 NC5756 07CA64050 3.2 Issued: 04/03/2008 Large-Scale Testing The large scale fire tests utilized both moveable and fixed units. The moveable units were assembled on a carriage rail system which was attached to the test room floor. The individual shelving fixtures in the moveable units were nominally 3- ft wide, 2- ft deep, and 8-ft tall. Vertical transverse sheet metal barriers were provided between each of the five (5) storage bays at 3-ft. intervals. There were eight (8) shelf levels positioned with a nominal vertical spacing of 8, 18.5, 29, 39.5, 50, 60.5, 71, 81.5 and 95-in. from the floor. There were five (5) shelf fixtures in each row with a total length of 15- ft. Based on the results of the bench scale tests, the project sponsors determined that a loading density of 70% would be used for both large scale tests. This loading density included 56 folders per 12- in. x 36- in. loading bay, with the folders evenly spaced by partial vertical dividers. There was a nominal 2- in. clear space between the top of the folders and the bottom of the next shelf above the folders. 3.2.1 Test 1 For the first large-scale fire test, an open shelving arrangement was used consisting of six compact shelf units. Five of the compact shelf units were moveable. Four of the moveable units were approximately 24-in. deep and one moveable unit was approximately 12- in. deep. The sixth compact shelf unit was fixed and approximately 12- in. deep. The compact shelf configuration was open with a 36- in aisle space provided in the center of the array. A nominal 1in. flue space was maintained between each shelving unit. No longitudinal barriers were provided. The target arrangement consisted of cardboard fixed to upright structures. The paperfaced cardboard was positioned across a 36- in. aisle space on the north, south, east and west sides of the compact shelving array. The cardboard affixed to the target assembly spanned 16-ft. long x 8- ft high. The individual shelving unit bays were nominally 36-in wide, 10.5- in high and 24- in deep. At the center of each 24- in deep bay, a 4.75- in tall sheet metal divider was located as a backing device and vertical divider support. A total of six (6) vertical sheet metal dividers approximately 9-in. long x 6- in. high were attached to each 36- in wide, 10.5- in high and 24-in deep shelf bay to evenly space the folders. A total of three (3) vertical sheet metal dividers approximately 9-in. long x 6- in. high were attached to each 36- in wide, 10.5- in high and 12- in deep shelf bay. The arrangement is shown in Figures 7,8 and 9. Photos of the arrangement are shown in Figures 13 and 14. 14 NC5756 07CA64050 Issued: 04/03/2008 Figure 7 Plan View – Test 1 15 NC5756 07CA64050 Issued: 04/03/2008 Figure 8 Plan View Detail – Test 1 16 NC5756 07CA64050 Issued: 04/03/2008 TEST Code: 01110802 Main Array from East Project 07CA64050 File NC5756 Figure 9 3.2.2 East / West Elevation View – Test 1 Test 2 For the second large-scale fire test, a closed shelving arrangement was used consisting of five moveable compact shelf units in the main array and one fixed compact unit as a target. Four of the moveable units were approximately 24- in. deep and one unit was approximately 12- in. deep. Full height longitudinal sheet metal barriers were installed in two of the four 24- in deep moveable units. The sixth compact shelf unit was a target which consisted of a 12- in. deep compact shelving unit positioned across a 36-in aisle on the north side, filled to the same capacity of the main shelving array. A no minal 1-in. flue space was maintained between each shelving unit. Cardboard fixed to upright structures was also placed across a 36- in. aisle space on the south, east and west sides of the compact shelving array. The cardboard target assemblies spanned 16- ft. long x 8- ft. high. The individual shelving unit bays were nominally 36-in wide, 10.5- in high and 24- in deep. At the center of each 24- in deep bay, a 4.75- in tall sheet metal divider was located as a backing device and vertical divider support. A total of six (6) vertical sheet metal dividers approximately 9-in. long x 6- in. high were attached to each 36- in wide, 10.5- in high and 24-in deep shelf bay to evenly space the folders. A total of three (3) vertical sheet metal dividers approximately 9-in. long x 6- in. high were attached to each 36- in wide, 10.5- in high and 12- in deep shelf bay. The arrangement is shown in Figures 10, 11 and 12. Photos of the arrangement are shown in Figure 15. 17 NC5756 07CA64050 Issued: 04/03/2008 Figure 10 Plan View – Test 2 18 NC5756 07CA64050 Issued: 04/03/2008 Figure 11 Plan View Detail – Test 2 19 NC5756 07CA64050 Issued: 04/03/2008 TEST Code: 01180802 Main Array from East Project 07CA64050 File NC5756 Figure 12 3.3 East Elevation View – Test 2 Test Method – Large Scale Tests 1 and 2 The nominal 8-ft. high storage array was positioned under a 10-ft. ceiling. The distance from the top of the commodity to the sprinkler deflector was 18- in. Thirty-six upright, nominal K=5.6 ceiling sprinklers were installed on a 15 by 15- ft. spacing for this test. The moveable compact mobile shelving array was assembled between four sprinklers such that the ignition location for each of the two tests, at the base of storage, was located between four sprinklers. The ceiling sprinkler system was supplied with water resulting in a nominal sprinkler discharge density of 0.10 gpm/ft 2 . Ignition was accomplished using one standard igniter constructed from a 3- in. diameter by 6-in. long cellulosic bundle soaked with 8 oz. of gasoline and wrapped in a polyethylene bag. The igniter was located on the base of the south side shelf (Rack E in Figures 18 and 32), within a storage folder. The ignition location was centered between four (4) ceiling sprinklers. 20 NC5756 07CA64050 Issued: 04/03/2008 Shelf Setup Carriage Arrangement Carriage Arrangement Shelf Detail Shelf Detail Figure 13 Loading Detail Test Set-Up Photos - Test 1 21 NC5756 07CA64050 Issued: 04/03/2008 Ignitor Figure 14 Final Test Arrangement Test Set-Up Photos - Test 1 22 NC5756 07CA64050 Issued: 04/03/2008 Divider Detail Barrier Detail Shelf Detail Shelf / Carriage Detail Loading Detail Final Test Arrangement Figure 15 Test Set-Up Photos - Test 2 23 NC5756 07CA64050 3.4 3.4.1 Issued: 04/03/2008 Test Results Test 1 The test was conducted for 90 minutes (90:00). A total of eight (13) ceiling sprinklers operated during the 90- minute test period. The first sprinkler activated at thirty-six minutes nine seconds (36:09) after ignition and the last sprinkler operated at eighty-five minutes fifty-eight seconds (85:58) after ignition. A combination photoelectric / ionization type smoke detector was located at the ceiling level directly above ignition. The detector activated at 0 minutes 44 seconds (00:44) after ignition. Visible flaming was noted at the top level of storage at approximately ten minutes (10:00) after ignition. Flame travel was noted across the ignition aisle at approximately fifty-our minutes (54:00) after ignition. The fire in Test 1 propagated to the east, west and south ends of the main shelving array. The fire was contained within the main shelving units and did not spread to the adjacent target arrays. The maximum one- minute average steel beam temperature measured above ignition was 902 ºF and the maximum one-minute average gas temperature measured above ignition was 1460 ºF. A plan view of the extent of fire is presented in Figure 16 and sprinkler operation times in Figure 17. The test assembly orientation is shown in Figure 18. Elevation views of the extent of fire spread and damage are shown in Figures 19 through 28. Post-test photos are presented in Figure 29. Tabulated test results are presented in Table 3. Temperature data vs. time charts are presented in Appendix B. 3.4.2 Test 2 The second large scale fire test was conducted for 82 minutes (82:00). A total of four (4) ceiling sprinklers operated during the 82- minute test period. The first sprinkler activated at eighty-one minutes eleven seconds (81:11) after ignition and the last sprinkler operated at eighty-one minutes fifty-one seconds (81:51) after ignition. A combination photoelectric / ionization type smoke detector was located at the ceiling level directly above ignition. The detector activated at 1 minute 52 seconds (01:52) after ignition. Visible flaming was noted at the top level of storage at approximately five minutes thirty seconds (05:30) after ignition. The fire in Test 2 propagated to the east and west ends of the array, but was generally limited to the area between the full- height longitudinal sheet metal barriers. The fire was contained within the main shelving units and did not spread to the adjacent target arrays. The maximum oneminute average steel beam temperature measured above ignition was 846 ºF and the maximum one- minute average gas temperature measured above ignition was 1560 ºF. 24 NC5756 07CA64050 Issued: 04/03/2008 A plan view of the extent of fire is presented in Figure 30 and sprinkler operation times in Figure 31. The test assembly orientation is shown in Figure 32. Elevation views of the extent of fire spread and damage are shown in Figures 33 through 42. Post-test photos are presented in Figure 43. Tabulated test results are presented in Table 3. Temperature data vs. time charts are presented in Appendix C. 25 NC5756 07CA64050 Issued: 04/03/2008 FIRE TEST DATE Test Code 01/11/2008 01110802 01/18/2008 01180802 Compact Mobile Shelving Compact Mobile Shelving Parameters Storage Type Shelving Array Configuration Open Closed Commodity Type Paper in manila folders with 70% loading density Paper in manila folders with 70% loading density Nominal Storage Height (ft) 8 8 Nominal Ceiling Height (ft) 10 10 Deflector Clearance to Storage (in) 18 18 Aisle Width (in.) 36 36 Shelf Type Solid Steel Solid Steel Longitudinal Barrier None Solid Steel Transverse Barrier Solid Steel Solid Steel Nominal Shelf Depth (in.) 24 24 Ignition Location Beneath Walkway Sprinklers Between 4 Sprinklers Between 4 Sprinklers Ceiling Sprinkler Temperature Rating °F 155 155 Deflector to Ceiling (in) 8 8 Nominal Ceiling Sprinkler Discharge Coefficient K (gpm/psi ½) 5.6 5.6 Nominal Ceiling Sprinkler Discharge Pressure (psi) 16.1 16.1 2 Nominal Ceiling Sprinkler Discharge Density (gpm/ft ) 0.10 0.10 Ceiling Sprinkler Spacing (ft x ft) 15 x 15 15 x 15 Length of Test (min:s) 90 82 First Ceiling Sprinkler Operation (min:s) 36:09 81:11 Last Ceiling Sprinkler Operation (min:s) 85:58 81:51 Number of Operated Ceiling Sprinklers 13 4 Peak Gas Temperature at Ceiling Above Ignition °F 1551 1585 Maximum 1 Minute Average Gas Temperature at Ceiling Above Ignition °F 1460 1560 Peak Steel Temperature at Ceiling Above Ignition °F 1063 928 Maximum 1 Minute Average Steel Temperature Above Ignition °F 902 846 Fire Spread Across Aisle Yes No Fire Spread To the Ends of the Array Yes Yes Fire Spread to Target No No Results Table 3 Summary of Test Parameters and Results 26 NC5756 07CA64050 Issued: 04/03/2008 Figure 16 Extent of Fire Spread – Test 1 Plan View 27 NC5756 07CA64050 Issued: 04/03/2008 Figure 17 Sprinkler Operations – Test 1 28 NC5756 07CA64050 Issued: 04/03/2008 TEST Code: 01110802 Damage Assessment Orientation Project 07CA64050 File NC5756 Figure 18 Rack Orientation for Damage Assesssment Views – Test 1 TEST Code: 01110802 Damage Assessment - Unit A Project 07CA64050 File NC5756 Figure 19 Damage – Test 1, Unit A 29 NC5756 07CA64050 Issued: 04/03/2008 TEST Code: 01110802 Damage Assessment - Unit B Project 07CA64050 File NC5756 Figure 20 Damage - Test 1, Unit B TEST Code: 01110802 Damage Assessment - Unit C Project 07CA64050 File NC5756 Figure 21 Damage - Test 1, Unit C 30 NC5756 07CA64050 Issued: 04/03/2008 TEST Code: 01110802 Damage Assessment - Unit D Project 07CA64050 File NC5756 Figure 22 Damage – Test 1, Unit D TEST Code: 01110802 Damage Assessment - Unit E Ignition Aisle Project 07CA64050 File NC5756 Figure 23 Damage - Test 1, Unit E 31 NC5756 07CA64050 Issued: 04/03/2008 TEST Code: 01110802 Damage Assessment - Unit F Project 07CA64050 File NC5756 Figure 24 Damage - Test 1, Unit F TEST Code: 01110802 Damage Assessment - Unit G Project 07CA64050 File NC5756 Figure 25 Damage - Test 1, Unit G 32 NC5756 07CA64050 Issued: 04/03/2008 TEST Code: 01110802 Damage Assessment - Unit H Project 07CA64050 File NC5756 Figure 26 Damage - Test 1, Unit H TEST Code: 01110802 Damage Assessment - Unit I Project 07CA64050 File NC5756 Figure 27 Damage - Test 1, Unit I 33 NC5756 07CA64050 Issued: 04/03/2008 TEST Code: 01110802 Damage Assessment - Unit J Project 07CA64050 File NC5756 Figure 28 Damage - Test 1, Unit J 34 NC5756 07CA64050 Issued: 04/03/2008 Ignition Aisle Aisle Opposite Ignition Aisle “A” Aisle “J” Overhead from NE Figure 29 Overhead from NE Post Test Photos – Test 1 35 NC5756 07CA64050 Issued: 04/03/2008 Figure 30 Extent of Fire Spread – Test 2 Plan View 36 NC5756 07CA64050 Issued: 04/03/2008 Figure 31 Sprinkler Operations – Test 2 37 NC5756 07CA64050 Issued: 04/03/2008 TEST Code: 01180802 Damage Assessment Orientation Project 07CA64050 File NC5756 Figure 32 Rack Orientation for Damage Assesssment Views – Test 2 TEST Code: 01180802 Damage Assessment - Unit A Project 07CA64050 File NC5756 Figure 33 Damage – Test 2, Unit A 38 NC5756 07CA64050 Issued: 04/03/2008 TEST Code: 01180802 Damage Assessment - Unit B Project 07CA64050 File NC5756 Figure 34 Damage - Test 2, Unit B TEST Code: 01180802 Damage Assessment - Unit C Project 07CA64050 File NC5756 Figure 35 Damage - Test 2, Unit C 39 NC5756 07CA64050 Issued: 04/03/2008 TEST Code: 01180802 Damage Assessment - Unit D Project 07CA64050 File NC5756 Figure 36 Damage – Test 2, Unit D TEST Code: 01180802 Damage Assessment - Unit E Ignition Aisle Project 07CA64050 File NC5756 Figure 37 Damage - Test 2, Unit E 40 NC5756 07CA64050 Issued: 04/03/2008 TEST Code: 01180802 Damage Assessment - Unit F Project 07CA64050 File NC5756 Figure 38 Damage - Test 2, Unit F TEST Code: 01180802 Damage Assessment - Unit G Project 07CA64050 File NC5756 Figure 39 Damage - Test 2, Unit G 41 NC5756 07CA64050 Issued: 04/03/2008 TEST Code: 01180802 Damage Assessment - Unit H Project 07CA64050 File NC5756 Figure 40 Damage - Test 2, Unit H TEST Code: 01180802 Damage Assessment - Unit I Project 07CA64050 File NC5756 Figure 41 Damage - Test 2, Unit I 42 NC5756 07CA64050 Issued: 04/03/2008 TEST Code: 01180802 Damage Assessment - Unit J Project 07CA64050 File NC5756 Figure 42 Damage - Test 2, Unit J 43 NC5756 07CA64050 Issued: 04/03/2008 Ignition Aisle Aisle Opposite Ignition Aisle A* Aisle H* *Note: Vertical barriers installed between B/C and F/G Aisle C Figure 43 Aisle D Post Test Photos – Test 2 44 NC5756 07CA64050 4 Issued: 04/03/2008 SUMMARY A series of five (5) bench scale and two (2) large scale fire tests was conducted to develop data regarding the level of protection provided by nominal K-5.6 (gpm/ psi ½) pendent, quick response ceiling sprinklers in protecting an arrangement of paper in standard manila paperboard folders stored in moveable compact mobile shelving units to a nominal height of 8- ft. Bench scale testing consisted of a single 36-in x 24-in x 9.75-in sheet metal shelf loaded with varying densities of commodity. A total of five bench scale fire tests were conducted on a load cell beneath a calorimeter where total heat release rate was measured over the course of each test. Based on the results of these bench scale tests, the project sponsors determined that a 70% loading density by volume would be used as the basis for both large scale fire tests. The tests were conducted under a 10- ft high ceiling with 155°F pendent ceiling sprinklers installed on 15 by 15-ft. spacing with the deflectors positioned 8- in. below the ceiling. The first large scale test was conducted with the moveable compact mobile shelving units in the open position, including a 3-ft. center aisle. The second large scale test was conducted with the moveable compact mobile shelving units in the closed position, and included full- height longitudinal sheet metal barriers in two of the four 24- in deep moveable shelving units. For both large scale tests, the ceiling sprinkler system was supplied with water resulting in a nominal sprinkler discharge density of 0.10 gpm/ft2 . The ignition location for each of the two tests was located between four sprinklers. The large scale fire tests utilized both moveable and fixed compact shelf units. The individual shelving fixtures in the moving units of the systems were nominally 3- ft wide, 2- ft deep, and 8- ft tall. Vertical transverse sheet metal barriers were provided between each of the five (5) storage bays at 3- ft. intervals. There were eight (8) shelf levels positioned with a nominal vertical spacing of 8, 18.5, 29, 39.5, 50, 60.5, 71, 81.5 and 95-in. from the floor. There were five (5) shelf fixtures in each row with a total length of 15- ft. For the first large-scale fire test, an open shelving arrangement was used consisting of six compact shelf units. Five of the compact shelf units were moveable. Four of the moveable units were approximately 24-in. deep and one moveable unit was approximately 12- in. deep. The sixth compact shelf unit was fixed and approximately 12- in. deep. The compact shelf configuration was open with a 36-in aisle space provided in the center of the array. No longitudinal barriers were provided. The target arrangement consisted of cardboard fixed to upright structures. The paper- faced cardboard was positioned across a 36- in. aisle space on the north, south, east and west sides of the compact shelving array. The cardboard affixed to the target assembly spanned 16- ft. long x 8- ft high. The first large scale fire test was conducted for 90 minutes (90:00). A total of thirteen (13) ceiling sprinklers operated during the 90-minute test period. The first sprinkler activated at thirty-six minutes nine seconds (36:09) after ignition and the last sprinkler operated at eightyfive minutes fifty-eight seconds (85:58) after ignition. 45 NC5756 07CA64050 Issued: 04/03/2008 The fire in Test 1 propagated to the east, west and south ends of the main shelving array. However, the fire was contained within the main shelving units and did not spread to the adjacent targets. The maximum one-minute average steel beam temperature measured above ignition was 902 ºF and the maximum one- minute average gas temperature measured above ignition was 1460 ºF. For the second large-scale fire test, a closed shelving arrangement was used consisting of five moveable compact shelf units in the main array and one fixed compact unit as a target. Four of the moveable units were approximately 24- in. deep and one unit was approximately 12- in. deep. Full height longitudinal sheet metal barriers were installed in two of the four 24- in deep moveable units. The sixth compact shelf unit was a target which consisted of a 12- in. deep compact shelving unit positioned across a 36-in aisle on the north side, filled to the same capacity of the main shelving array. Cardboard fixed to upright structures were also placed across a 36- in. aisle space on the south, east and west sides of the compact shelving array. The cardboard target assemblies spanned 16- ft. long x 8- ft. high. The second large scale fire test was conducted for 82 minutes (82:00). A total of four (4) ceiling sprinklers operated during the 82- minute test period. The first sprinkler activated at eighty-one minutes eleven seconds (81:11) after ignition and the last sprinkler operated at eighty-one minutes fifty-one seconds (81:51) after ignition. The fire in Test 2 propagated to the east and west ends of the array, but was generally limited to the area between the full- height longitudinal sheet metal barriers. The fire was contained within the main shelving units and did not spread to the adjacent target arrays. The maximum oneminute average steel beam temperature measured above ignition was 846 ºF and the maximum one- minute average gas temperature measured above ignition was 1560 ºF. A summary of the parameters and results is presented in Table 3. Report by: Reviewed by: Christopher Gates Project Engineer 3019INBK Tel: 847-664-2618 Fax: 847-313-2618 Michael McCormick Staff Engineering Associate 3019INBK Tel: 847-664-3303 Fax: 847-313-3303 46 NC5756 07CA64050 Appendix A – Graphs APPENDIX A Graphical Presentation of Heat Release Rate Data for Bench-Scale Testing A-1 Issued 03/31/2008 NC5756 07CA64050 Appendix A – Graphs Issued 03/31/2008 Fire Protection Research Foundation HRR Comparison Bench Scale Loading Density Data 40 35 30 Loading Density HRR (kW) 25 70% Test 1 70% Test 2 20 85% Test 1 100% Test 1 15 100% Test 2 10 5 0 0 10 20 30 40 50 60 Time (min) Fire Protection Research Foundation HRR Comparison Bench Scale Loading Density Data 40 35 30 HRR (kW) 25 Loading Density 70% - Test 1 20 70% - Test 2 15 10 5 0 0 10 20 30 40 Time (m) A-2 50 60 70 80 NC5756 07CA64050 Appendix B – Graphs Issued 03/31/2008 APPENDIX B Graphical Presentation of Temperatures and Waterflow - Test 1 B-1 NC5756 07CA64050 Appendix B – Graphs Issued 03/31/2008 Fire Protection Research Foundation Compact Mobile Shelving - Test 1 Sprinklers 1-6 90 80 70 60 (Deg C) Spk.001 Spk.002 Spk.003 Spk.004 Spk.005 50 40 Spk.006 30 20 10 0 0 10 20 30 40 50 60 70 80 90 Time (Min) Fire Protection Research Foundation Compact Mobile Shelving - Test 1 Sprinklers 7-12 90 80 70 60 (Deg C) Spk.007 Spk.008 Spk.009 Spk.010 Spk.011 50 40 Spk.012 30 20 10 0 0 10 20 30 40 50 Time (Min) B-2 60 70 80 90 NC5756 07CA64050 Appendix B – Graphs Issued 03/31/2008 Fire Protection Research Foundation Compact Mobile Shelving - Test 1 Sprinklers 13-18 90 80 70 60 (Deg C) Spk.013 Spk.014 Spk.015 Spk.016 Spk.017 50 40 Spk.018 30 20 10 0 0 10 20 30 40 50 60 70 80 90 Time (Min) Fire Protection Research Foundation Compact Mobile Shelving - Test 1 Sprinklers 19-24 90 80 70 60 (Deg C) Spk.019 Spk.020 Spk.021 Spk.022 Spk.023 50 40 Spk.024 30 20 10 0 0 10 20 30 40 50 Time (Min) B-3 60 70 80 90 NC5756 07CA64050 Appendix B – Graphs Issued 03/31/2008 Fire Protection Research Foundation Compact Mobile Shelving - Test 1 Sprinklers 24-30 90 80 70 60 (Deg C) Spk.025 Spk.026 Spk.027 Spk.028 Spk.029 50 40 Spk.030 30 20 10 0 0 10 20 30 40 50 60 70 80 90 Time (Min) Fire Protection Research Foundation Compact Mobile Shelving - Test 1 Sprinklers 31-36 90 80 70 60 (Deg C) Spk.031 Spk.032 Spk.033 Spk.034 Spk.035 50 40 Spk.036 30 20 10 0 0 10 20 30 40 50 Time (Min) B-4 60 70 80 90 NC5756 07CA64050 Appendix B – Graphs Issued 03/31/2008 Fire Protection Research Foundation Compact Mobile Shelving - Test 1 Sprinkler System Flow 600 500 GPM 400 Flow 300 200 100 0 30 40 50 60 70 80 90 Time (Min) Fire Protection Research Foundation Compact Mobile Shelving - Test 1 Ceiling Steel Temperature above Ignition Note: TC #1 malfunctioned 700 600 500 400 (Deg C) AMB02 AMB03 AMB04 AMB05 300 200 100 0 0 10 20 30 40 50 Time (Min) B-5 60 70 80 90 NC5756 07CA64050 Appendix B – Graphs Issued 03/31/2008 Fire Protection Research Foundation Compact Mobile Shelving - Test 1 Air Temperature above Ignition 900 800 700 (Deg C) 600 6-in. TC 500 12-in. TC 18-in. TC 400 300 200 100 0 0 10 20 30 40 50 60 70 80 90 Time (Min) Fire Protection Research Foundation Compact Mobile Shelving - Test 1 Ignition Aisle Shelf Steel Temperature 900 800 700 Steel temp 1-bay west of Ignition 600 (Deg C) Steel temp above Ignition 500 TC1 TC3 400 300 200 100 0 0 10 20 30 40 50 Time (Min) B-6 60 70 80 90 NC5756 07CA64050 Appendix B – Graphs Issued 03/31/2008 Fire Protection Research Foundation Compact Mobile Shelving - Test 1 Ignition Aisle Air Temperature 900 Air above Ignition - 8th Level 800 Air above Ignition 700 600 (Deg C) TC2 500 TC4 Shelf 2 above Ignition TC5 400 TC6 TC8 300 200 1 Bay East of Ignition - 8th Level 100 Air temp opposite Ignition (across aisle) 0 0 10 20 30 40 50 60 70 80 90 Time (Min) Fire Protection Research Foundation Compact Mobile Shelving - Test 1 South Aisle Air Temperature 800 700 600 8th Level Air Temp (C) (Deg C) 500 400 TC9 300 200 100 0 0 10 20 30 40 50 Time (Min) B-7 60 70 80 90 NC5756 07CA64050 Appendix C – Graphs Issued 03/31/2008 APPENDIX C Graphical Presentation of Temperatures and Waterflow - Test 2 C-1 NC5756 07CA64050 Appendix C – Graphs Issued 03/31/2008 Fire Protection Research Foundation Compact Mobile Shelving - Test 2 Sprinklers 1-6 90 80 70 60 (Deg C) Spk.001 Spk.002 Spk.003 Spk.004 Spk.005 50 40 Spk.006 30 20 10 0 0 10 20 30 40 50 60 70 80 Time (Min) Fire Protection Research Foundation Compact Mobile Shelving - Test 2 Sprinklers 7-12 90 80 70 60 (Deg C) Spk.007 Spk.008 Spk.009 Spk.010 Spk.011 50 40 Spk.012 30 20 10 0 0 10 20 30 40 Time (Min) C-2 50 60 70 80 NC5756 07CA64050 Appendix C – Graphs Issued 03/31/2008 Fire Protection Research Foundation Compact Mobile Shelving - Test 2 Sprinklers 13-18 90 80 70 60 (Deg C) Spk.013 Spk.014 Spk.015 Spk.016 Spk.017 50 40 Spk.018 30 20 10 0 0 10 20 30 40 50 60 70 80 Time (Min) Fire Protection Research Foundation Compact Mobile Shelving - Test 2 Sprinklers 19-24 90 80 70 60 (Deg C) Spk.019 Spk.020 Spk.021 Spk.022 Spk.023 50 40 Spk.024 30 20 10 0 0 10 20 30 40 Time (Min) C-3 50 60 70 80 NC5756 07CA64050 Appendix C – Graphs Issued 03/31/2008 Fire Protection Research Foundation Compact Mobile Shelving - Test 2 Sprinklers 25-30 90 80 70 60 (Deg C) Spk.025 Spk.026 Spk.027 Spk.028 Spk.029 50 40 Spk.030 30 20 10 0 0 10 20 30 40 50 60 70 80 Time (Min) Fire Protection Research Foundation Compact Mobile Shelving - Test 2 Sprinklers 31-36 90 80 70 60 (Deg C) Spk.031 Spk.032 Spk.033 Spk.034 Spk.035 50 40 Spk.036 30 20 10 0 0 10 20 30 40 Time (Min) C-4 50 60 70 80 NC5756 07CA64050 Appendix C – Graphs Issued 03/31/2008 Fire Protection Research Foundation Compact Mobile Shelving - Test 2 Sprinkler System Flow 250 240 230 220 GPM 210 200 6" Flow 190 180 170 160 150 0 10 20 30 40 50 60 70 80 Time (Min) Fire Protection Research Foundation Compact Mobile Shelving - Test 2 Ceiling Steel Temperature above Ignition Note: TC #1 malfunctioned 600 500 (Deg C) 400 AMB02 AMB03 AMB04 AMB05 300 200 100 0 0 10 20 30 40 Time (Min) C-5 50 60 70 80 NC5756 07CA64050 Appendix C – Graphs Issued 03/31/2008 Fire Protection Research Foundation Compact Mobile Shelving - Test 2 Air Above Ignition 900 800 700 (Deg C) 600 500 6-in. TC 12-in. TC 18-in. TC 400 300 200 100 0 0 10 20 30 40 50 60 70 80 Time (Min) Fire Protection Research Foundation Compact Mobile Shelving - Test 2 Storage Array Steel Temperatures NOTE: TC2 destroyed - 8th Level steel (B); TC6 destroyed - 1st Level steel (F) 1000 Steel above Ignition 900 800 700 (Deg C) 600 TC3 1st Level steel (G) TC5 500 TC9 400 300 200 8th Level steel (C) 100 0 0 10 20 30 40 Time (Min) C-6 50 60 70 80 NC5756 07CA64050 Appendix C – Graphs Issued 03/31/2008 Fire Protection Research Foundation Compact Mobile Shelving - Test 2 Storage Array Air Temperatures 800 1st Level (C-D) 700 600 8th Level (E-F) 8th Level (C-D) TC1 (Deg C) 500 TC4 TC7 400 TC8 TC10 300 200 8th Level (G-H) 100 8th Level (A-B) 0 0 10 20 30 40 Time (Min) C-7 50 60 70 80
© Copyright 2025 Paperzz