Environmental Statement Volume I Environmental Statement and Figures February 2013 NEMO LINK UK ONSHORE COMPONENTS Prepared by: Sophie Clayton/Bobby Clayton TEP Genesis Centre Birchwood Science Park Warrington WA3 7BH Tel: 01925 844004 Fax: 01925 844002 e-mail: [email protected] for National Grid Nemo Link Limited Written: Checked: Approved: SC/BC IJG IJG Table of Contents 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0 11.0 12.0 13.0 14.0 15.0 16.0 17.0 18.0 INTRODUCTION PROJECT DESCRIPTION OPTIONS AND ALTERNATIVES CONSIDERED PLANNING POLICY REVIEW LAND USE GROUND CONDITIONS AND CONTAMINATION HYDROLOGY AND FLOOD RISK ECOLOGY ARCHAEOLOGY AND CULTURAL HERITAGE LANDSCAPE AND VISUAL EFFECTS TRAFFIC AND TRANSPORT NOISE AND VIBRATION AIR QUALITY COASTAL TOURISM, RECREATION AND SOCIO-ECONOMICS ELECTRIC AND MAGNETIC FIELDS AND ELECTROMAGNETIC COMPATIBILITY PROJECT-WIDE ASSESSMENT OF EFFECTS ASSESSMENT OF EFFECTS OF THE NATIONAL ELECTRICITY TRANSMISSION SYSTEM CONNECTION SUMMARY AND CONCLUSIONS Appendices (see ES Volumes 2 and 3) 1.1 1.2 3.1 4.1 6.1 7.1 8.1 8.2 8.3 8.4 8.5 8.6 8.7 8.8 8.9 8.10 9.1 10.1 10.2 11.1 11.2 12.1 16.1 ES Scoping and Pre-Application Consultation Table Statement of Community Involvement Review of Options The Horlock Rules Ground Conditions and Contamination Phase 1 Environmental Study (Main report only – see Planning Application CD for full data version) Flood Risk Assessment (Main report only – see Planning Application CD for full data version) Desktop Records Extended Phase 1 Habitat Survey Saltmarsh NVC Survey Reptile Survey Water Vole Survey Wintering Bird Survey Breeding Bird and Nesting Redshank Survey Sediment and Invertebrates Survey Information for Habitats Regulations Assessment (HRA) Information for HRA Signposting Document Archaeology and Cultural Heritage Baseline Report Verified Photomontage Method Visual Effects Assessment Tables Abnormal Indivisible Load Investigations Construction Traffic Air Quality Assessment Substation and Converter Station Sound Power Levels and Assumptions Belgian Onshore and Marine Environmental Assessment Non-Technical Summary Documents and Marine Scoping Responses 3 4 1.0 INTRODUCTION Project Overview 1.1 The Nemo Link (the Project) is a proposed high voltage direct current (HVDC) electrical interconnector with an approximate capacity of 1,000 megawatts (MW) which will allow the transfer of electrical power via subsea cables between the UK and Belgium. The power would be bi-directional, able to flow in either direction at different times, depending on the supply and demand in each country. The project will bring both short and long term local economic benefit, wider benefit to electricity consumers in the UK and Europe and enhanced opportunities for the integration of renewable energy to meet climate change targets. 1.2 The proposed subsea cables would run from Pegwell Bay at Richborough in Kent to Zeebrugge in Belgium (Figure 1.1) passing through English, French and Belgian waters. 1.3 The UK onshore elements of the Project for which planning permission is being sought comprise a converter station and substation at the site of the former Richborough Power Station, and HVDC and fibre optic cables installed below the ground between the converter station and mean low water at Pegwell Bay. These elements of the Project are referred to in this Environmental Statement (ES) as ‘the Proposed Development’. The cables will connect to the other parts of the interconnector which are the subsea cables from low water across the North Sea and onshore underground cables and a converter station in Belgium. 1.4 The Project is being developed by National Grid Nemo Link Ltd (NGNLL), part of the National Grid group, and Elia Asset S.A. (Elia) which is part of the national electricity transmission company in Belgium. The proposed substation at Richborough would be owned and operated by National Grid Electricity Transmission (NGET). 1.5 The majority of the Proposed Development falls within the administrative boundary of Thanet District Council (TDC). Approximately 720m of the HVDC cable and a small area at the south east corner of the proposed converter station compound (outdoor hard landscape and security perimeter fencing) is within the administrative boundary of Dover District Council. This ES accompanies a single hybrid application for planning permission under the Town and Country Planning Act 1990 as follows: Outline Permission Proposed HVDC converter station and 400kV substation – matters of landscaping and access are provided. Matters of appearance, layout and scale are reserved. Full Permission 1.6 Proposed HVDC, HVAC and fibre optic cables - all matters are provided. A full description of the Proposed Development is detailed at Chapter 2. The hybrid planning application has been submitted to both TDC and Dover District Council (DDC); through pre-application discussions with both Local Planning Authorities, it has been agreed that TDC is to adopt the lead with regards the coordination and 5 determination of the hybrid planning application. Decision notices are to be issued by both LPAs. Further details as to the approach to, and the provisions of the hybrid planning application are included in the planning application covering letters to TDC and DDC. 1.7 This ES covers the UK onshore elements of the Project and presents the results of surveys and assessments of potential environmental effects. 1.8 A separate UK Marine ES has been prepared for the installation of the subsea cables from the mean high water spring (MHWS) tide mark on the Kent coast out to the median line between England and France as these works require consent under the Marine and Coastal Access Act 2009. 1.9 The potential environmental effects of the other elements of the Project (comprising the marine cables in French and Belgian waters, and the converter station in Belgium) have been assessed separately, and these assessments will be submitted to the relevant authorities in France and Belgium with the consent applications for each of these elements. 1.10 As these non-UK elements form part of the Project for EIA purposes, a description of these components is included within this ES as well as a summary of their effects on the environment. Project Justification 1.11 The UK has two key environmental targets relating to renewable energy and greenhouse gas emissions. The first of these targets is part of the European Union’s (EU) integrated energy/climate change proposal. This proposal sets a target of 20% of European Energy (including electricity, heat & transport) to come from renewable sources by 2020 (known as the EU 20/20/20 vision (http://www.energy.eu/directives/com2008_0030en01.pdf). The Renewable Energy Strategy published in July 2009 (http://www.decc.gov.uk/en/content/cms/what_we_do/uk_supply/energy_mix/renew able/res/res.aspx) identified that, for the UK to meet its share of the EU target (UK’s share is 15% of energy sources including electricity, heat and transport), 30% of UK’s electricity would have to come from renewable sources. 1.12 The second target is incorporated in the Climate Change Act 2008. This goes further than the EU 20/20/20 vision, and sets a target of 80% reduction in UK greenhouse gas emissions from 1990 levels by 2050. This equates to a 34% reduction in greenhouse gas emissions by 2020 as specified by the Climate Change Committee (http://www.theccc.org.uk/). 1.13 European strategy recognises the urgent need to upgrade Europe's energy infrastructure and to interconnect networks across borders to meet the EU’s core energy policy objectives of competitiveness, sustainability and security of supply (“Europe 2020” EC Communication (2010). 1.14 These objectives are supported by European policy which facilitates the urgent upgrading and extension of electricity networks, including interconnectors, to maintain existing levels of security of supply and, in particular, to transport and balance electricity from renewable sources, which is expected to more than double in the period 2007 to 2020. 6 1.15 Interconnectors enable power to flow between member state transmission networks and are vital for ensuring a competitive and well-functioning integrated market for energy. Despite the existence of common rules for the internal market in electricity, the European Commission recognises that the internal market remains fragmented due to insufficient interconnections between national energy networks. 1.16 In 2002 the EU Council set a target for all Member States to have electricity interconnection capacity equivalent to at least 10% of their installed production capacity by 2005. The UK is still failing to meet this target. Total UK interconnection capacity amounts to 3.5GW which represents just over 4% of the 85 GW of installed generation capacity. 1.17 In December 2009 the UK and Belgium both became signatories to the North Seas Countries Offshore Grid Initiative (NSCOGI) with the objective to coordinate offshore wind and infrastructure developments in the North Sea. Interconnection between countries is a prerequisite to achieving this ambition. 1.18 The UK Government’s vision to ensure safe, secure and affordable supplies for the future involves the construction of a new fleet of nuclear generation, rapid expansion of renewable energy (mainly through offshore wind), and the development of interconnector projects. Specifically, the UK is committed to the European Commission’s 3rd energy package which states that 15% of the UK’s demand for energy needs to be generated from renewable sources by 2020. To meet this target, the UK will need an energy portfolio of 34% wind generating capacity by 2020, rapidly building on 4% wind capacity of today. 1.19 The vast majority of this wind capacity is expected to be obtained from the Crown Estate’s licensed Round 3 Development Zones which has the aim to install 25GW of offshore wind capacity by 2020. This huge investment into the UK renewables sector is part of an aspiration to develop a large-scale green industry to boost the UK economy and create jobs. 1.20 By its nature, wind generation is intermittent. It is therefore necessary to have plant and equipment that can respond to rapid changes in generating output. Interconnectors, such as the one proposed between the UK and Belgium, provide an effective way to manage these fluctuations in supply and demand. 1.21 An industry consultation carried out by National Grid Interconnectors Ltd, Elia and RTE in 2008 concluded that there was significant demand for new interconnection between Great Britain and Continental Europe. Respondents considered interconnection to be an important means to: 1.22 Respond to intermittency of wind generation, which varies according to the strength of the wind; Respond to periods of excess power, specifically when wind generation is greater than electricity demand; Help meet the challenge of retiring fossil fuel and nuclear plants in the UK; and Support neighbouring wholesale and supply markets and, in the case of DC interconnectors, the provision of balancing and ancillary services. Currently the UK has three interconnectors providing a total of up to 3,500MW of power transfer capability: UK – France: Known as IFA (Interconnexion France Angleterre). This is a 2000MW HVDC connection commissioned in 1986. It is jointly owned and 7 1.23 operated by National Grid Interconnectors Limited and Reseau de Transport d’Electricite. The UK landing point is at Baker’s Gap near Folkestone and a connection made to the high voltage transmission system at Sellindge. UK – Netherlands: Known as BritNed. This is a 1000MW HVDC connection commissioned in 2011. It is owned and operated by BritNed Development Limited which is a joint venture between NLink International BV, a subsidiary of Tennet Holding B.V and National Grid International Ltd. The UK landing point is at the Isle of Grain, Kent and a connection made to the high voltage transmission system at the Grain substation. Scotland – Northern Ireland: Known as the Moyle interconnector. This is a 500MW connection between Auchencrosh, South Ayrshire, Scotland and Ballycronan More, Northern Ireland. It was commissioned in 2001 and is operated by SONI (System Operator Northern Ireland) on behalf of Northern Ireland Energy Holdings. The proposed Nemo Link between the UK and Belgium is one of a small number of interconnector projects currently under development/construction. Other projects include: Republic of Ireland – UK, 500MW interconnector, known as the East – West Interconnector, linking the Republic of Ireland (RoI) with Deeside, North Wales. This project has been constructed by Eirgrid, the Transmission System Operator for the RoI and is anticipated to be in operation in early 2013. The UK landing point is at Barkby Beach, Prestatyn, North Wales and a connection made to the high voltage transmission system at Deeside. UK – Norway: Approximately 1400MW interconnector linking the north east of England with Norway. This project is jointly being developed by National Grid International Ltd and Statnett, the Transmission System Operator for Norway. 1.24 Taking into account these other projects, the Nemo Link provides further diversity to the UK’s interconnection portfolio and will contribute 15% of total interconnection capacity of 5.4GW which in turn represents 6.4% of installed generation capacity. 1.25 Belgium is particularly suitable for a new interconnector not only because of its geographical proximity to the UK, but also because its electricity transmission system is highly connected to Central Europe. The Nemo Link will therefore provide enhanced opportunities for the UK to trade with wider European power markets. There is no existing connection between the UK and Belgian transmission systems, so the construction of a new connection is required to achieve these objectives. 1.26 South East England is the most suitable location for an interconnector between the UK and Belgium. The South East offers the shortest route between the two countries and, therefore, reduces the environmental effects, costs and construction risks associated with the installation of subsea HVDC cables. In addition, the South East region (including London) represents the highest centre of electricity demand in the UK. 1.27 A need case document for the development of the interconnector between the UK and Belgium has been produced by NGNLL and Elia and this can be found on the Project website (www.nemo-link.com). 8 Legislative and Regulatory Framework Electricity Act 1989 1.28 NGNLL has applied for an interconnector licence under the Electricity Act 1989 to operate the Nemo Link. The holder of such a licence will be under statutory obligations imposed by section 9 and Schedule 9 of the Electricity Act 1989. These include the following obligations which apply when the licence holder is developing any proposals: ‘To have regard to the desirability of preserving natural beauty, of conserving flora, fauna and geological or physiographical features of special interest and of protecting sites, buildings and objects of architectural, historic or archaeological interest; and Do what he reasonably can to mitigate any effect which the proposal would have on the natural beauty of the countryside or on any such flora, fauna, features, sites, buildings or objects.’ Environmental Impact Assessment 1.29 Environmental Impact Assessment (EIA) is a process by which information about the potential environmental effects of a proposed development is collected, evaluated and presented to facilitate consultation and to enable decision makers to take account of these effects (both beneficial and adverse) when determining whether or not a project should proceed. EIA seeks to identify the potential sources of environmental effects during the design of a project and to avoid or minimise adverse effects through appropriate mitigation. It also seeks to compensate unavoidable effects, for example by providing replacement for environmental features which are lost or changed due to development. 1.30 European Community Directive 85/337/EEC sets out formal requirements for member states to implement EIA for projects. Subsequent Directives (1997/11/EC and 2003/35/EC) have been issued with subsequent amendments. The United Kingdom Government has implemented these Directives through a series of regulations. The Town and Country Planning (Environmental Impact Assessment) Regulations 2011 apply to projects regulated through the planning system in England. 1.31 The report of EIA submitted under the relevant Regulations is called an Environmental Statement (ES). The Regulations include specific requirements as to the content of an ES. 1.32 The Regulations include two Schedules of development which are derived from the Directives. Applications for projects described in Schedule 1 must be accompanied by an EIA. Applications for projects described in Schedule 2 may require EIA, depending on the scale of the development, its characteristics and the sensitivity of the environment in which the development will take place. The decision as to whether or not EIA applies to a development is called the ‘Screening Opinion’. The Local Planning Authority or the relevant Secretary of State can decide whether an application comprises EIA development under the Regulations. Alternatively, a developer can decide that its application will be accompanied by an ES, making it EIA development. 1.33 The Proposed Development set out in this planning application is not considered to fall under Schedule 1 or Schedule 2 of the Town and Country Planning 9 (Environmental Impact Assessment) Regulations 2011 and therefore EIA is not required. 1.34 Taking into account Schedule 9 and Section 9 commitments under the Electricity Act and the relationship of the Proposed Development (subject to this planning application) to the proposed works in Belgium (which are subject to EIA under Belgian law), NGNLL and Elia have decided to prepare and submit a voluntary ES to accompany this application for planning permission. An EIA screening request was therefore not submitted to either TDC or DDC. A scoping report was prepared to determine the extent of the matters to be covered in the ES (see below for further details). Habitats Regulations 1.35 Development within or adjacent to an existing or candidate Special Protection Area (SPA) or Special Area of Conservation (SAC) is subject to the provisions of the Conservation of Habitats and Species Regulations 2010. Under Regulation 21 of these Regulations, the competent authority is required to undertake an ‘appropriate assessment’ of any proposed development which is likely to have a significant effect on a designated site to determine the impact of the proposal on the designated site’s conservation objectives and determine whether the site’s integrity would be adversely affected. 1.36 The proposed onshore underground HVDC cables pass through Thanet Coast and Sandwich Bay SPA/Ramsar Site, Sandwich Bay SAC. In determining the application for planning permission, Thanet District Council and Dover District Council, as the competent authorities, are required under the above Regulations to consider whether an ‘Appropriate Assessment’ is required. To allow the Council to do this, a document entitled ‘Information for Habitat Regulations Assessment’ which includes an Assessment of Likely Significant Effects (ALSE) has been produced and included as part of this application. The document details the development activities that could potentially directly and indirectly affect the internationally designated areas of the site and the methods that will be used to avoid impacts, or mitigate and compensate for those that cannot be avoided. Environment Statement Preparation 1.37 The main activities undertaken in the preparation of this ES have included: The evaluation of potential cable routes and converter station and substation sites and consultation with statutory and non-statutory consultees to gain an initial understanding of any issues associated with the Proposed Development; The preparation of a scoping document incorporating recommendations from the consultees. This document outlined the surveys and assessments to be undertaken and the potential impacts of the Proposed Development; Carrying out desk-based assessments and site surveys; Identifying and assessing the likely significant impacts of the Proposed Development; Devising appropriate mitigation measures; and Assessing the significance of residual and cumulative impacts. 10 Scoping of the EIA 1.38 Scoping is the process of determining the extent of the matters which should be covered in the EIA. The purpose of the scoping stage is to identify any potential significant impacts arising from the proposed development and to scope out any impacts that can be considered insignificant, which do not warrant further consideration in the EIA. The scoping report brings together the results of early consultations, desk-based assessments and field surveys already undertaken and presents proposals for the EIA. 1.39 The scoping stage provides the opportunity for statutory bodies and other consultees to comment on the identified impacts, the proposed methodologies for assessment and the scope of the assessment considered necessary and appropriate. A number of discussions have been held with consultees, particularly regarding potential effects on the designated sites of Pegwell Bay. In July 2012, a Scoping Report was prepared and used to provide information to consultees about the Proposed Development and the proposed approach to the EIA. Thanet District Council and Dover District Council have issued ‘scoping opinions’ and these have guided the contents of this ES. The scoping opinions together with consultation responses from statutory consultees and how they have been addressed in this planning application can be viewed at Appendix 1.1. Surveys and Fieldwork 1.40 Studies and surveys were carried out to gather environmental and engineering information for the ES. These included the following: 1.41 Ecological surveys including a Phase 1 Habitat Survey, saltmarsh National Vegetation Classification (NVC) survey and preliminary protected species surveys; A baseline noise monitoring study; A traffic assessment; An archaeological desk-based assessment and walkover survey; and Landscape and visual assessment. The results of the surveys conducted have resulted in changes being made to the cable route alignment and construction methods under consideration. Where changes have been made, these have been taken into consideration within the EIA process and necessary surveys conducted in order to assess the likely environmental impacts. Assessment of Impact Significance 1.42 Best practice guidance has been used for individual chapters where available and appropriate. In carrying out the assessment, a general method for the presentation of environmental impacts has been adopted to ensure consistency in the evaluation of significance across all specialist topic areas. 1.43 Significance is considered as a function of the two variables: sensitivity of receptor, and magnitude of effect, giving rise to a significance of impact scale ranging from minor, through moderate to major. Impacts can be beneficial (positive) or adverse (negative) as well as neutral (where there is either no impact, or where positive and negative impacts balance) or indeterminate. 11 1.44 In this ES, impacts assessed as moderate (adverse or beneficial) or above are considered to be ‘significant’. Minor (adverse or beneficial) and neutral impacts are not considered significant. However, they are included in the assessment as they should be considered throughout the decision-making process and may be important in terms of cumulative impacts. 1.45 Where the judgement of impact significance is not based on these criteria alone, a quantitative or qualitative assessment of the impact is given depending on the specialist discipline, the type of information that can be collected from the site and the professional’s own judgement. Notwithstanding this, impact significance always takes into account the impact’s deviation from the established baseline conditions (impact magnitude) and the sensitivity of the receptor. Identification of Mitigation Measures 1.46 Measures to reduce negative impacts (or enhance positive impacts) are termed mitigation. Best practice techniques to minimise the environmental impacts of installing the onshore underground cables and constructing and operating of the converter station and substation have been identified where appropriate. These include for example: 1.47 Routeing the cables to avoid or reduce impact on sensitive features; Reducing the working width along the cable route where there are sensitive features such as hedges, to reduce impact; Controlling risk by following published best practice guidelines, such as for the storage of oil and fuels. In addition, site and project specific mitigation measures have been identified where generic, best practice mitigation measures are not suitable. Assessment of Significance of Residual Impacts 1.48 Any impact remaining after mitigation is the residual impact. An assessment has been made of the significance of residual impacts, based on the characteristics of the impact and the receptors’ sensitivity, using professional judgement and relevant standards and criteria, where available. Cumulative Impact Assessment 1.49 Cumulative effects are those that may result from the combined or incremental effects of the past, present or future development activities. A single development or activity may itself result in an effect which in itself is not significant but when combined with other effects (significant or not) in the same geographical area and occurring at the same time, result in a cumulative impact which is significant. 1.50 The cumulative impact assessment has been designed to ensure that it covers all of the following: Wider cumulative impacts which are the combined impacts that may occur between the UK onshore components of the Nemo Link with other non-related developments that do not form part of the Nemo Link; Project wide cumulative impacts which arise from the combined impacts (additive or interactive) of the UK onshore elements of the Nemo Link project 12 with other components of the Nemo Link i.e. UK, French and Belgian subsea cables and Belgian onshore infrastructure; and Project related cumulative impacts which are the combined impacts that may occur between the UK onshore elements of the Project with development required to facilitate the connection of the Nemo Link. Within this ES, this relates specifically to the grid connection which will be required to the National Electricity Transmission System. 1.51 Chapter 2 provides details of the Nemo Link components that do not form part of this planning application as well as an explanation of the grid connection that will be required. Project wide and project related cumulative effects are discussed in Chapters 16 and 17 respectively. 1.52 To identify non-related projects that potentially needed to be considered within the cumulative impact assessment, all submitted planning applications for developments that have been consented within a 1km radius of the onshore infrastructure within the last two years and also any that are still pending determination, were identified through a planning search. 1.53 Following this, a scoping exercise was undertaken whereby developments with the potential to interact with the onshore elements of the Nemo Link were either scoped ’in’ or ‘out’ of the detailed impact assessment. 1.54 Projects that were considered so minor in nature and scale that there could never realistically be the potential for them to contribute to significant cumulative effects, for example household applications, were scoped out from further assessment. 1.55 For those developments ‘scoped in’, an information gathering exercise was undertaken to collect relevant data that would allow a cumulative impact assessment be undertaken. Table 1.1 presents details of the unrelated developments considered. Figure 1.2 shows the locations of the planned unrelated developments. All of the developments are expected to be completed prior to commencement of the construction of the Nemo Link. 1.56 An assessment of the wider cumulative impacts that may occur between the UK onshore components of the Nemo Link with non-related developments are documented at the end of each technical chapter. An assessment of other parts of the Nemo Link (i.e. the subsea cables and Belgian onshore infrastructure), together with any cumulative impacts of those works and the Proposed Development, is set out in Chapter 16 below. Further, an assessment of the other related development (i.e. the connection to the UK transmission system), together with any cumulative impacts of those works and the Proposed Development, is set out in Chapter 17 below. 13 Table 1.1: Proposed Unrelated Development Application Number Application Status Submitted December 2012 N/A N/A F/TH/12/0690 KCC/TH/0351/2010 or DO/10/954 N/A F/TH/12/0832 F/TH/12/0144 Submitted December 2012 Approved November 2012 Approved by KCC July 2011 Future Application Submitted October 2012 Approved by TDC June 2012 Development Proposals Peaking plant facility at the former Richborough Power Station site (TR329623). Facility is designed to provide top-up supply to the local distribution network at short notice, for example during periods of high electricity demand or low energy generation. Anticipated the plant will operate for up to 720 hours a year (30 days equivalent spread throughout the year). Development will comprise of 53 diesel fired generators with approximately 40 megawatts (MW) output, along with associated fuel storage, parking and access. The site will occupy an area of approximately 3.37 hectares (ha) and is anticipated to be operational by 2014. A 2.60 ha internal road network and structural/estate landscaping around the perimeter of the former Richborough Power Station site. The internal road network is anticipated to be constructed by 2014. Pegwell Bay Flood Defence Scheme. Installation of new concrete wall 141 metres (m) long and up to 1.2m high to the north of Pegwell Bay Service Station and installation of an earth embankment, 257m long and up to 1m high to the south of the service station where the 256 and flood defences are at their lowest elevation. Construction 2013. Waste related development on land west of Ramsgate Road, Richborough. Construction of a materials recycling facility, soil washing plant, anaerobic digestion plant and inert materials processing facility plus a building to house the anaerobic digester. A 5MW Solar Farm on land to the west of the River Stour adjacent to the former Richborough Power Station site. Site area is 13.36 ha. Proposals to include rows of photovoltaic panels, ancillary equipment, security fencing and associated landscaping. The Solar Farm is anticipated to be operational by 2014. Erection of glasshouses, three water storage tanks and pack house at Ebbsfleet Lane, Ebbsfleet, Ramsgate, CT12 5TJ (TR335626). Erection of an anaerobic digestion plant, silage clamp building, bund, two drainage ponds, and associated hardstanding and landscaping. The site area is approximately 1.5 hectares. 14 Consultation 1.57 A range of consultations have been undertaken in order to ascertain the interests and concerns of relevant organisations and authorities and to collect baseline environmental information for the development area. 1.58 The list of organisations contacted is given below: Thanet District Council; Dover District Council; Kent County Council; Natural England; Environment Agency; English Heritage; River Stour (Kent) Internal Drainage Board; Kent Wildlife Trust; Kent Reptile and Amphibian Group; Kent Bat Group; and Kent Ornithological Society. 1.59 Information received from consultees has been taken into consideration when assessing the potential environmental impacts of the Proposed Development and when formulating avoidance and mitigation measures to be implemented to help reduce the impacts of greatest significance. A summary of consultee responses is provided in Appendix 1.1 1.60 Public information events were held on the 15th and 16th June 2012 at Cliffs End Village Hall and the Bell Hotel, Sandwich, respectively. Information regarding the proposals for the Nemo Link was displayed and feedback was invited from local residents. Information on the Richborough Energy Park was also displayed at the events. 1.61 A publicity leaflet was delivered to 8,953 residents to publicise the event. The mailout area was the same as that used previously to inform the local community of proposals for the Energy Park. 106 residents who had previously engaged with the Energy Park developers either by attending their earlier consultation events or by contacting the developers directly to discuss the Energy Park proposals, received a personalised letter. Elected members received a separate letter notifying them of a stakeholder preview which was held at the public information event on the 15th June. Elected members also received the letter via email. 1.62 In addition a quarter page colour advert was placed in the following publications to increase the visibility of the public information events 1.63 East Kent Mercury and Thanet Extra (Thursday 1st May and Thursday 7th June); and Kent Messenger (Friday 1st June and Friday 8th June). 167 local residents, elected members and interested parties attended the public information events over the two dates. Twenty seven residents completed feedback forms at the information event. The project team has responded to enquires from residents who were unable to attend the public information events. 15 1.64 Main concerns gained from the public information events included the following: The visual impact of the onshore infrastructure, in particular the converter station; Impact on local residents, notably how disruption on local traffic can be avoided or reduced and how to ensure residents are kept informed of progress; The effects of the proposals on wildlife; and Whether the connection between the proposed converter station and the existing transmission system will require overhead lines. 1.65 NGNLL has also held meetings to discuss the proposals with Local MPs and Councillors from Thanet, South Thanet Liberal Democrats in the Guildhall in Sandwich, Sandwich Town Council, Minster Parish Council. 1.66 Further consultation has included presentations to elected members of Thanet and Dover District Councils and a newsletter. Feedback from the public and elected members is summarised within a Statement of Community Involvement which is included in Appendix 1.2. Structure of the ES 1.67 This Environmental Statement comprises the following volumes: 1.68 Volume 1 - A document drawing together relevant information about the scheme and containing figures relating to the detailed technical information for each of the environmental topics assessed; Volume 2 - Appendices Part 1; Volume 2 – Appendices Part 2; and Volume 3 – Non-Technical Summary. Volume 1 of the ES is divided into the following chapters: Chapter 1 – Introduction. Chapter 2 - Project Description. Chapter 3 – Options and Alternatives Considered. Chapter 4 - Planning Policy Review. Chapter 5 - Land Use. Chapter 6 - Ground Conditions and Contamination. Chapter 7 - Hydrology and Flood Risk. Chapter 8 – Ecology. Chapter 9 - Archaeology and Cultural Heritage. Chapter 10 - Landscape and Visual Effects. Chapter 11 - Traffic and Transport. Chapter 12 - Noise and Vibration. Chapter 13 - Air Quality. Chapter 14 – Coastal Tourism, Recreation and Socio-Economics. Chapter 15 – Electric and Magnetic Fields (EMF) and Electromagnetic Compatibility (EMC). Chapter 16 – Project Wide Assessment of Effects. 16 Chapter 17 – Assessment of Effects of the National Electricity Transmission System Connection. Chapter 18 – Summary and Conclusions. Availability of the Environmental Statement 1.69 This ES along with other supporting documents are available on the project website at: www.nemo-link.com 1.70 The ES is also available for viewing at the following locations: Table 1.2: ES Viewing Public Locations Thanet District Council Planning Offices – Cecil Street, Margate, Kent, CT9 1XZ Dover District Council Planning Offices – White Cliffs Business Park, Dover, CT16 3PJ Thanet Gateway Plus – Cecil Street, Margate, Kent, CT9 1RE Dover Gateway – 71 Castle Street, Dover, CT16 1PD Aylesham Area Office – Aylesham Health Centre, Queens Road, Aylesham, CT3 3BB Sandwich Area Office – Sandwich Area Office, The Guildhall, Sandiwch, CT13 9AH Deal Library (and area office) – Broad Street, Deal, Kent, CT14 6ER Minster-in-Thanet Library – 4A Monkton Road, Minster, Ramsgate, Kent, CT12 4EA Sandwich Library – 13 Market Street, Sandwich, Kent, CT13 9DA Dover Library – Dover Discovery Centre, Market Square, Dover, Kent, CT16 1PH St. Margarets at Cliffe – St. Margarets Library Community Centre, Kingsdown, St. Margarets at Cliffe, CT15 6BB Ramsgate Library – Guildford Lawn, Ramsgate, Kent, CT11 9AY Newington Library – Marlowe Academy, Marlowe Way, Ramsgate, Kent, CT12 6NB Ash Library – Ash Village Hall, Queens Road, Ash, Canterbury, Kent, CT3 2BG Westgate Library – Minster Road, Westgate-on-Sea, Kent, CT8 8BP 1.71 Further information about the Proposed Development including hard copies of the ES can be requested by email, Freephone or post at the details below for a cost of £150.00 per report. Copies of the Non-Technical Summary are available free of charge. Copies of the ES and other project documents are also available to download from the project website. Email: [email protected] Telephone: 0800 083 3149 between 9am - 5pm, Monday to Friday (answerphone service available outside of these hours) In writing from Freepost RSLG-YXEU-BJUC, Nemo Link, PO BOX 68215, London, SW1P 9UJ 17 18 2.0 PROJECT DESCRIPTION Introduction 2.1 This chapter provides a description of the UK onshore elements of the Nemo Link (The Proposed Development) (see Figure 2.1). A description of the other components of the Nemo Link (i.e. the project-wide components, which include the subsea cables in UK, French and Belgian waters, and the Belgian onshore infrastructure) is also included. 2.2 Although it is separate to the Nemo Link Project and does not form part of this application, a brief overview of the National Grid Electricity Transmission (NGET) infrastructure, required to connect the Nemo Link is provided at the end of the chapter. Proposed Development 2.3 The Nemo Link components in the UK which require planning permission under the Town and Country Planning Act 1990 (TCPA 90) comprise: 2.4 Two high voltage direct current (HVDC) cables between the landfall and the mean low water mark; Two HVDC onshore underground cables from the converter station to the landfall on the coast at Pegwell Bay where they will be joined to the subsea HVDC cables; Fibre optic cables installed with the HVDC cables for the purposes of operational telemetry and communications; An HVDC converter station on part of the site of the former Richborough Power Station which would convert the HVDC power used in the link to high voltage alternating current (HVAC) for use in the national transmission system and vice-versa; A 400 kilovolts (kV) electricity substation on part of the site of the former Richborough Power Station; and Three 400kV HVAC underground electricity land cables to connect the above substation to the HVDC converter station and up to two telecommunications cables for telemetry, control and protection purposes only. The Nemo Link will operate at a nominal voltage of +/- 350-400 kV. Converter Station and Substation Site 2.5 The converter station and substation will be constructed on part of the site of the former Richborough Power Station off Ramsgate Road, Sandwich (A256) (Figure 2.2). The Power Station was decommissioned in 1996. The site is approximately 4 kilometres (km) southwest of Ramsgate, 3.5km north of Sandwich and 1.6km inland from the east Kent coastline. 19 2.6 Thanet District Council (TDC) and Dover District Council (DDC) granted planning permission for the demolition of the chimney and cooling towers at the site in January 2012. Demolition took place in March 2012. 2.7 Planning applications were submitted in December 2012 by Richborough A Ltd for the parts of the former power station site adjacent this application site. One application is for a ‘peaking’ power generation plant. Another application is for roads and landscape works around the perimeter of part of the former power station site. 2.8 Access to the converter station and substation would be via the existing former power station entrance from the roundabout on Ramsgate Road (A256). This access has been improved to contemporary highway standards by work undertaken in 2011. 2.9 There will be permanent roads around the perimeter of the converter station and internal roads to provide access to the different building units. The perimeter road will be constructed ahead of construction of the converter station and substation and it is being developed under a separate application submitted by Richborough A Limited (see Table 1.2, Chapter 1). The roads will be used to provide access for regular and ad hoc maintenance activities and for the delivery of materials to site. 2.10 Landscaping will be implemented around the perimeter of the converter station and substation to help integrate the proposed development site into the landscape setting. Landscaping will largely consist of tree planting at the eastern boundary with existing shrub and poplar trees at the northern boundary being retained and enhanced. Species rich grassland, areas for a mixture of native and fruit tree planting and ecological corridors are also proposed as part of the wider landscaping works. The landscaping will be implemented at the same time as the perimeter road and is being developed under a separate planning application (see Table 1.2, Chapter 1). Converter Station Design 2.11 The converter station will occupy a site of 4.85 hectares (ha) contained within a secure fenced compound. The majority of electrical equipment will be indoors to prevent exposure to saline pollution which can lead to damage and the need to replace equipment. 2.12 The converter station will comprise the following components: Main Building: This will contain specialist HVDC electrical equipment including the power electronics equipment that converts electricity from AC to DC (and vice-versa). The main building will be constructed in part around the steel frame of the former Richborough Power Station’s turbine hall which was left in situ following demolition works. The main building will comprise three main parts. The tallest part to a maximum height of approximately 30.8m will be based around the former turbine hall frame and will be approximately 38.3m long and 20 93m wide. The remaining two parts will be approximately 25m high, 65.1m long and 93m wide (main extension) and 18m high, 45.7m long and 65.5m wide (transformer extension). The total length of the main building will be approximately 149m. Lightning conductors will be installed approximately 5m higher than the roof of the main building. 2.13 Service Building: There will be a service building attached to the eastern extent of the northern face of the main building which will house the control room, workshop, auxiliary power supply and cooling system. This building will be approximately 27.4m long, 13.6m wide and 14.5m high. Storage Building: This will be attached to the western extent of the northern face of the main building and will be used for the storage of equipment spares and tools. The dimensions are the same as the Service Building. Single Phase Converter Transformers: Each transformer is approximately 10.2m long, 8.2m wide and 9.8m high. These transform the voltage from the national transmission system voltage level to the DC converter station voltage level. The transformers will be outdoors north of the main buildings. There will be four transformers on site. Three will be in use at any one time and one will be a spare in case of a fault arising on one of the operational transformers. Each of the transformer bays will be separated from the adjoining one by concrete fire walls and acoustic enclosures. The transformer bays may have a system of rails constructed in the footings to allow quick removal and replacement of a transformer in the event of failure in service. The transformer bays will be provided with bunding, drainage and an underground oil containment system to prevent any transformer oil escaping into the environment. Mechanically Switched Capacitor (MSC): This compound will be used to regulate and stabilise transmission voltages. This will be approximately 30.2m long by 25m wide with a height of approximately 11.8m. Shunt reactor: This has similar dimensions to a Single Phase Transformer and will also be used to regulate voltages. Outdoor High Voltage Electrical Equipment: This connects the transformers, MSC compound, shunt reactor to the electrical plant in the Main Building and also to the underground cables that connect the converter station to the substation. The equipment includes busbars, circuit breakers, switches, insulators and other connecting equipment. The tallest equipment will be overhead gantries at approximately 15m high. Distribution Network Operator Substation: This will provide low voltage (11kV) supplies to the converter station from the local electricity network. Diesel Generator: This will be approximately 8m long, 3m wide and 3.5m high and will be used to provide back-up electricity supply in the event of a failure of the low voltage electricity supply from the Distribution Network Operator. Figure 2.3 shows a layout of the component parts of the converter station. The converter station building will be constructed of brick to a height of approximately 21 3m. The remaining sections of the buildings will be formed by a steel frame clad with metal panels and insulated. Panels will graduate from dark green to light green to the roofline. 2.14 The converter station will be designed for a 40 year lifespan, with only control equipment expected to require replacement during that time. 2.15 Lighting will only operate when access to the site is required during maintenance activities or emergencies; infra-red CCTV will trigger lights to be switched on by intruder detection. Lighting will be controlled to avoid the unnecessary illumination of areas beyond the development. Glare and the spread of upward light will be kept to a minimum to reduce sky glow and minimise visual intrusion within the open landscape. The need to illuminate the whole perimeter is not necessary. The entrance and walkways for access/egress and emergency exits will however need illuminating for safety reasons. Consultation with Manston Airport has confirmed that beacons are not required on the converter station. 2.16 The perimeter and internal roads will be used to provide access for regular and ad hoc maintenance activities and for the delivery of materials to site. The main access into the converter station and substation from the site access off the A256 will be constructed so that it can accommodate the delivery of transformers by large vehicles which comprise Abnormal Indivisible Loads (AILs). Access off the A256 roundabout at the entrance of the former power station site will have areas of ‘overrun’ in excess of a standard junction design to allow the wide track required for the transformer delivery vehicles. The proposed road layout is shown on Figure 2.3. 2.17 Transformers for the converter station and substation will be delivered during construction under a Transport Order. The route to each part of the site will remain able to accommodate these loads. Reliability data on transformers of this nature indicates that failures would not be anticipated at intervals of less than 10 years. In the event of transformer failure at the converter station, the spare transformer held on site would be installed and the failed transformer removed to the ‘spare’ storage area. Transportation of the failed transformer to a contractor’s factory for repair would then be arranged including the appropriate Transport Order from the Highways Agency for the abnormal movement. 2.18 Sixteen car parking spaces plus two disabled spaces will be provided. These are divided into two areas of parking to the east and west of the converter station building. These will be for operations staff who will be required to monitor and maintain electrical equipment and plant at the converter station. The spaces are in excess of normal daily requirements to accommodate visitors and contractors visiting the converter station and substation site during periods of maintenance. 2.19 The converter station will be surrounded by a 2.4m high palisade security fence. Electrified security fencing will be installed immediately inside the fence increasing the overall height of fencing to 4m (Figure 2.4). The completed site will be surfaced with stone chippings. Substation Design 2.20 A new 400kV substation is required to connect the converter station to the national grid electricity transmission system. The 400kV substation forms part of this 22 planning application, however, the connection between the substation and the national grid is still in early development and does not form part of this planning application. The connection project is being promoted separately by National Grid Electricity Transmission (NGET). 2.21 The 400kV Gas Insulated Switchgear (GIS) substation will be built in a separately fenced compound immediately west of the proposed converter station. The substation will be connected to the converter station by underground high voltage alternating current (HVAC) cables. 2.22 The proposed substation will occupy a footprint of approximately 2.65 ha, and will contain indoor and outdoor electrical equipment. It includes a GIS Hall containing the switchgear, outdoor Gas Insulated Busbars (GIB), overhead line gantries, two Supergrid Transformers (SGTs), along the southern extent of the site, a Mechanically Switched Capacitor (MSC) and a Static Var Compensator (SVC) compound in the northern part of the substation compound. The MSC and SVC are specific types of equipment used to regulate and stabilise transmission voltages and will be located on the north west corner of the substation site. The SVC compound will contain a transformer and outdoor electrical equipment with a building for control and operation of the equipment (Figure 2.3). 2.23 The GIS Hall will be approximately 52.2m long, 21.5m wide and 15m high, central to the substation site and will take the form of a structural steelwork frame, clad with profiled metal panels, similar to the external appearance of the converter station. 2.24 The Supergrid transformers are approximately 22.5m long by 13.3m wide with a height of 10.6m. The MSC enclosure is approximately 30.2m long, 25m wide and approximately 11.8m for the tallest equipment. The SVC equipment would be approximately 52.6m long, 39m wide and 6.3m high for the tallest equipment. There are 3 buildings connected to the SVC equipment these would be approximately 12m long, 10.2m wide and 4.4m high. 2.25 The substation compound will also contain an amenity building 16m long, 12m wide and 4.2m high, a diesel generator building comprised of a single storey prefabricated modular unit 8m long, 3m wide and 3.5m high and a fire water tank, 6m high. 2.26 The layout of the substation includes two overhead line gantries in the south west corner of the site approximately 12.7m in height. NGET is currently assessing options for the connection between the substation and the national grid electricity transmission system. The connection would be the subject of a separate consenting process. The layout of the substation has included two overhead line gantries, on the basis that of the technology types that could be utilised for the connection, the use of overhead line gantries to provide the terminal connection to the substation, would be the tallest equipment that could be proposed within the substation to perform this function. 2.27 The maximum height of the remaining outdoor electrical equipment required to connect the above equipment together, will be approximately 8m. 2.28 All outdoor areas where plant is installed will be surfaced in stone chippings. The substation will be enclosed by a 2.4m high palisade fence with a 4m high electrified 23 pulse security fence installed on the internal side of the palisade fence. Internal surfaced roads will be required to access the buildings, for maintenance and car parking. 2.29 External lighting will be installed within the fenced compound containing the substation. This will only operate when access to the site is required, during maintenance activities or emergencies outside daylight hours. Lighting will be controlled to avoid the unnecessary illumination of areas beyond the development. 2.30 Permanent access to the substation will be a continuation of the permanent access developed to the converter station. Direct access into the substation compound is to the north of the converter station site. Thirteen car parking spaces will be provided. Construction of Converter Station and 400kV Substation 2.31 The construction of the converter station and substation is planned to be undertaken over a period of 36 - 42 months from mid-2014 to mid-2018. Both the converter station and the substation will be commissioned in October 2018. 2.32 Construction will include the activities summarised below: Preliminary Works: Further site investigation and preconstruction surveys required to be undertaken in advance of construction; Site Preparation and Establishment: Vegetation clearance if required, development of internal site access and establishment of all temporary facilities including site offices, storage areas and welfare facilities and development of electricity and water supplies and erection of security fencing or hoarding. It is proposed that a laydown area will be established and will occupy a site of approximately 1.6ha adjacent to the substation site on its western edge; Earthworks: This will include the development platforms on which the converter station will be located and infill works to create a level site for the converter station and substation consisting of fill material in the existing cooling tower and pump room voids. It is anticipated that piled foundations will be required with footings in construction platforms founded in natural ground or in compacted fill. Piles will be lifted into position and driven in by a piling rig. A concrete mixing plant will be installed on site to mix concrete for the foundations and footings. Crushed rock base course material will be required for hard-standing areas. Final ground levels will between 3.166 and 3.637mAOD for the substation compound to alleviate flood risk for 1:200 year and 1:1000 year flood events plus climate change (see Chapter 7 for further details) and 3.166mAOD for the converter station compound; Civil Engineering Works: Construction of building platforms on the piled foundations, development of the site’s permanent drainage system and construction of permanent access, internal roads and car parking arrangements; Buildings Construction: Construction of all buildings including erection of steel frames and cladding; 24 Cable Installation: Installation of underground DC cables from horizontal direction drilling (HDD) location to the converter station. Installation of underground AC cables to connect the converter station to the substation. Installation of underground 11kV cables within the converter station for auxiliary supplies; Mechanical and Electrical Works: Installation of high voltage AC and DC electrical equipment in both the converter station and substation and delivery of transformers; Commissioning: Following completion of all construction works there will be a period of commissioning and testing; and Site Reinstatement and Landscape Works: Removal of site offices and temporary facilities, land reinstatement and landscape works. Construction Access Arrangements 2.33 Prior to commencement of construction, a Traffic Management Plan (TMP) will be prepared in consultation with Kent County Council’s Highways Department. This will set out all construction access arrangements including agreed access points, delivery routes and times. 2.34 The access roads into the converter station and substation site will be constructed prior to the commencement of converter station and substation construction works. 2.35 During the construction period a range of vehicles will be accessing the site including flatbed trucks delivering plant and equipment, plant including excavators, bulldozers and cranes as well as cars and vans associated with construction staff movement. 2.36 Equipment will be delivered to the site, erected and connected using mobile cranes and hydraulic access platforms. The switchgear and busbars will be delivered to site in modules, using normal road transport. The modules would be stored on site in designated storage areas until required for erection. 2.37 Transformers will be delivered to site on heavy-load low loaders and would be classed as abnormal indivisible loads. The transformers may be factory fitted with wheels, and lowered from the low loaders using hydraulic jacks direct onto a permanent rail system built into the transformer footings. Each transformer will then be winched into position on the rail system to allow a rapid transformer change. Alternatively the transformers will be skidded into position by the use of a hydraulic system. Further information about the delivery of transformers to site is included at Chapter 11 (Traffic and Transport) and Appendix 11.1. Construction Site Layout 2.38 The construction site for the converter station and substation will be securely fenced during the construction period. During the construction period there will be a number of temporary facilities including: Site offices including offices and meeting room; 25 Staff welfare facilities including portable chemical toilets, kitchen and mess room; A laydown area for storage areas for construction vehicles, plant, equipment and other construction materials; Appropriately bunded areas to be used for the storage of oils and other fuels; Wheel washing facilities to be used by construction vehicles and plant; Rock crushing and concrete batching facilities; and Segregated waste management storage areas. HVDC Cables in the Pegwell Bay Intertidal Area Cable Design 2.39 The Nemo Interconnector will include two subsea HVDC cables between the landfall points at Pegwell Bay to mean low water and continuing to Zeebrugge. The cables will be one of two subsea cable types: Cross Linked Polyethylene (XLPE) or Mass Impregnated (MI). The cables will be rated between 350kV and 400kV. The size of the subsea cables will depend on the final design and rating but will be approximately 15cm diameter. 2.40 Extruded HVDC cables use XLPE for their insulation. The insulation is extruded over a copper or aluminium conductor (copper has a lower resistance and thus a higher power density, although it is heavier and more expensive than aluminium) and is covered with a water tight sheath. The sheath is generally extruded seamless lead for subsea cables Subsea cables have an additional layer of galvanised steel wire armour to increase the cable’s tensile strength to help it withstand the stresses of submarine installation. This armour is usually a single layer of wires, helically wound around the cable (although in deeper waters or over rocky sea beds this may be a double layer), and covered in a sleeve of bitumen impregnated polypropylene yarn to inhibit corrosion. 2.41 MI cable type cable has been widely used on major interconnector projects in service to date including but not limited to: UK-France interconnector (IFA); BritNed, linking the UK and the Netherlands; Basslink, linking Australia with Tasmania; and NorNed, linking Norway with the Netherlands. 2.42 The MI cable is a stranded type single copper core cable that has paper insulation impregnated with high viscosity mineral oil. This cable type is not pressurised like a fluid-filled cable (which has low viscosity oil) and has no free oil to leak out in the event of a cable sheath rupture. 2.43 The MI cable core has a concentric construction comprising a central stranded low resistivity copper conductor with a screen, mass impregnated paper insulation layers, and an outer dielectric screen made of semi-conducting paper. The core is 26 contained in a lead sheath to protect the insulation from water ingress and a polyethylene sheath is extruded over this to protect it from corrosion. One, and sometimes two, layers of galvanised steel armour wires are applied in a helix to provide mechanical strength during cable handling and installation and protection from external damage. The armour wires are bedded into a layer of bituminised jute strings and a layer of polypropylene string is applied over them to bind them in and provide abrasion resistance and to improve handling. Cable Installation 2.44 The cables will be bundled together in the same trench and jointed to the HVDC onshore underground cables in the transition joint pit (TJP). The approximate distance between Low Water and the TJP will be 1,800m. 2.45 The TJP will be an excavated pit (15m long x 5m wide x 2.5m deep) with a reinforced concrete plinth laid in its base. The cables will be jointed on the plinth and once this is undertaken, the excavation will be backfilled to original ground levels. On completion of works, there will not be any visible sign of the TJP on the surface. 2.46 The TJP will be above High Water close to Pegwell Bay Service Station (Figure 2.7) in Sandwich Bay Special Area of Conservation (SAC), Sandwich Bay Special Protection Area (SPA) and Ramsar site, Sandwich Bay to Hacklinge Marshes Site of Special Scientific Interest (SSSI) and Sandwich and Pegwell Bay National Nature Reserve (NNR). These sites of nature conservation have predominantly been designated for their bird and habitat interest (see Chapter 8, Ecology). 2.47 Access to the site of the TJP off the A256 will be required for mechanical excavator, concrete deliveries, winches and similar equipment. TJP construction will be completed well in advance of cable landing operations to avoid any possibility of delay to the landing operation. 2.48 In preparation for the subsea cables being hauled ashore, the works area, comprising approximately 1300sqm will be marked off with a tape or a buoy line to protect the site and the public (Figure 2.5). On the rising tide a shallow water cable laying vessel will move into position as close to the top of the beach as the tidal conditions allow. A pulling device, either a winch or a tracked vehicle, and rollers and quadrants necessary to guide the hauling rope and subsequently each cable, will be put in place. The cables will be laid from the vessel to the shore individually A hauling rope will be installed between the beach pulling device and a cable end on the vessel running through the TJP. Access to this works area will be via the A256. 2.49 Depending on the state of the tide, the intervening distance between the vessel and the TJP may be entirely water, entirely dry (with the installation vessel resting on the seabed) or more probably a combination of both scenarios. Each cable will be supported at the sea surface by floats attached as the cables leave the vessel and supported on rollers placed on the seabed where it is above the water line. 27 2.50 Each cable will be hauled towards the TJP with floats being removed as necessary. When sufficient length of each cable has been passed to the shore to allow for its correct alignment for jointing to the land cable, it will be secured in the TJP. 2.51 Once the cables have been secured at the TJP and tested to confirm that no damage has occurred during the installation process, each cable will be manoeuvred into its correct alignment in relation to the pre-determined route between the TJP and low water. For cable sections still afloat, the manoeuvring will be accomplished using workboats, before the remaining floats are removed and the cables allowed to sink to the seabed. Any cables on dry land leading up to the TJP will be manoeuvred using excavators or similar prior to burial. 2.52 The experience of Thanet Offshore Wind Farm installing its cables in this area suggests that the subsea cables can be buried by the main installation vessel offshore up to a point approximately 1.5km to 2km from the beach. Inshore from this point, including the intertidal area between low water and high water, other burial methods will be needed. The methods described below are similar to those used for the installation of the Thanet Offshore Wind Farm cables. 2.53 In dry areas of the beach, a single trench will be excavated alongside the cables using conventional mechanical excavators adapted for working on soft soils. The excavated material will be placed to one side for re-use. Rollers will be used in the base of the trench to pull the cables along it. The cables installation trench will be approximately 1-2m wide and the cables will be buried to a target depth of circa 23m. The temporary works footprint will be approximately 10m. A cofferdam may be required to keep water from entering the trench during excavation. 2.54 Using mechanical excavators the cables will be manoeuvred into the trench bottom and buried with the material excavated from the trench. 2.55 On completion of trench backfilling in the saltmarsh area on the seaward side of the TJP, a post and rail and post and wire fence will be erected around the area subject to works, similar to that erected around the Thanet Offshore Wind Farm cables installation. Appropriate signage will be fixed to the fence warning that the land may be unstable. 2.56 The landing operation including landfall preparation and subsea cables installation is expected to take approximately 4 weeks. HVDC Onshore Underground Cables Onshore Underground Cables Design 2.57 HVDC onshore underground cables will connect the subsea cables to the converter station. The onshore underground cables will be of the same type as the HVDC subsea cables (XLPE or MI) which will minimise the complexity of the joint at the TJP. The additional layer of galvanised steel wire armour required for the subsea cables is not required for the onshore cables. The diameter of each of the onshore underground cables will be approximately 15cm. The distance from the TJP to the converter station is approximately 2.1km. The fibre optic cables will be installed with the onshore underground cables and will be approximately 50mm in diameter. 28 Onshore Underground Cables Installation 2.58 The HVDC onshore underground cables will be delivered to a temporary contractor’s compound of approximately 30m x 50m in Pegwell Bay Country Park (Figure 2.5). Access to the compound will be via an existing access route into the Park. It is anticipated that each drum would weigh approximately 20 tonnes and would hold around 500m of power cable. The compound will form the base for the cable installation works from which the main items of plant and workers will travel, minimising the need for transport. 2.59 The HVDC onshore underground cables will run from the TJP on the coastal side of the existing cycle track which runs parallel to the A256 Sandwich Road, through Pegwell Bay Country Park (a former landfill site), then into Stonelees Nature Reserve and the BayPoint sports complex (the former Pfizer Sports Ground). From the sports complex, the cables will be routed beneath the A256, Minster Stream, and a compartment of Hacklinge Marshes SSSI by HDD. The onshore underground cables will terminate in the converter station site (Figure 2.6). 2.60 Prior to commencement of works along the cables route, a photographic inventory will be taken and in particular records of the presence and condition of items such as fences and gates will be made and, where possible, agreed with the landowner prior to commencement. 2.61 Secure temporary fencing will be erected around the working area (which will vary as the cables installation progresses). The fencing will define the working area, protect any sensitive areas and prevent third party access. Access gates will be installed suitable for both personnel and for movement of plant and equipment. As vehicle movement will be restricted to one side of the cables trench, a one-way system with entrance and exit gates or a turning circle will be established at the end of the fenced section. When each section is complete the fence will be extended or removed and re-erected around the next work section. 2.62 The onshore underground cables will be installed onshore in three distinct ways along the length of the route. 2.63 Standard trenching; Surface laid with capping; and Horizontal directional drilling (HDD). The description of installation techniques below refers to the different parts of the cables route from the TJP to the converter station (see Figure 2.6). Between TJP and Pegwell Bay Country Park 2.64 Between the TJP and Pegwell Bay Country Park, the cables will be installed using standard trench methods. Prior to excavation, the surface will be cleared of vegetation. Trenches will be excavated by hydraulic excavators, except where any risk to existing services is identified where digging by hand will verify the position of existing services. The trench cross section will be 1.5m at the surface and will taper 29 to 1m at the bottom of the trench. Excavated topsoil and subsoil will be stored separately for reinstatement. 2.65 The trench integrity will be assessed in different soil types, and where required the sides will be shuttered with timber or metal sheets secured by cross braces. This will prevent collapse and will protect personnel during the works. Where appropriate, scaffold poles will be placed around the trench to create a safe working environment for personnel. 2.66 Prior to the onshore underground cables being laid, a layer of cement bound sand (CBS) will be placed in the bottom of the trench (approximately 60cm deep) to protect the cables and to help dissipate heat generated when the cables are in operation. 2.67 Rollers will be placed in the trenches at 2m-3m intervals for cables installation. Pushing machines will also be placed along the route at appropriate distances. A winch will be placed at the end of each section. A wire from the winch will be connected to the cable via a pulling eye. This will guide the cable between the pushing machines. 2.68 The cables will be pulled into the trench, the cable rollers removed and the cables placed at the bottom of the trench with a separation distance of approximately 50cm. 2.69 Concrete slabs will be installed 60cm above the top of each cable and plastic warning tape will be laid directly over the slabs. The material excavated from the trench will be used to complete backfilling of the trench. The topsoil will be used to ensure that the upper profile of the backfilled trench is restored to the previous condition. Any excess subsoil will be removed from site. 2.70 A 10-15m working width for cables installation and a permanent easement of approximately 5m will be required. Pegwell Bay Country Park (Northern Section) 2.71 In the northern part of Pegwell Bay Country Park, the cables will be laid on the existing land surface and chalk will be used to cover them (Figure 2.6). This method of installation will avoid the risk of disturbing any potentially contaminated ground of this former landfill site and opening up potential contamination pathways during cable installation. 2.72 To form a level surface, vegetation and minor undulations will be removed. Cables will be laid on top of the existing ground within concrete troughs that will be covered with a concrete lid. Warning tape will then be used to protect the cables. 2.73 A chalk capping layer with 1:5 slope and 1m wide flat section on top will then be built up over the concrete capping to marry in with existing levels. A cellular 30 confinement system (to manufacturer’s recommendation) will be used to prevent slippage and potential exposure of cables. 2.74 The chalk cap will be seeded with approved seed mix, for example lowland limestone mix (British seed houses RE4) or general landscaping wildflower mix for calcareous soils (WFG5). Where available, local seed will be used rather than a proprietary seed mix. This will improve the vegetation and biodiversity interest of the Country Park. 2.75 Much of the land in Pegwell Bay Country Park has already been subject to a ‘capping’ treatment to further cover the landfill below and to allow native vegetation to establish. The proposed method of cables installation will effectively replicate this treatment which has been successfully implemented in other parts of the Country Park. 2.76 A joint pit is required within Pegwell Bay Country Park. This is shown on Figure 2.5. This will be created using a similar technique to that described for the TJP in Figure 2.7 (joint between the subsea and onshore cables). Joints between onshore cables require less space and can be achieved more quickly than for the joint between the subsea cables and the onshore cables. The onshore cables joint pit will be approximately 15m long and 4m wide. Cable jointing will take approximately 5 days. Pegwell Bay Country Park (Southern Section) 2.77 This part of the Country Park has previously been subject to capping with chalk. Trial pits will be dug prior to commencement of works to ascertain the depth of existing chalk cap over the former landfill site. 2.78 If chalk depth is greater than 1m, the standard trench method described above will be used. If chalk depth is less than 1m, a hybrid method of trenching and further capping similar to the method employed in the northern section of the Country Park will be employed. Stonelees Nature Reserve 2.79 Standard trenching methods will to be used in this Section. The alignment of the onshore underground cables will be very close to the edge of the existing cycleway through Stonelees Nature Reserve to minimise disturbance to adjacent land. BayPoint Sports Complex to Converter Station 2.80 The onshore underground cables will be installed by open trenching into BayPoint sports complex. Horizontal Directional Drilling (HDD) will be used from BayPoint sports complex directly into the converter station to avoid surface disturbance of a newly constructed roundabout on the A256, avoid disturbance to Minster Stream and also avoid disturbance to a compartment of Sandwich Bay to Hacklinge Marshes Site of Special Scientific Interest (SSSI). 2.81 The drilling requires a ‘launch pit’ working area from which the main driving of the rig will be undertaken and a ‘receptor pit’ working area which will receive the drill 31 driven from the launch pit. The launch pit will be on the converter station site and comprise of a working area approximately 25m x 40m.The receptor pit on the BayPoint sports complex will comprise of a working area of approximately 30m x 50m. Access to the launch pit working area will be along the A256 and will utilise the existing entrance to the former power station site. Access to the receptor pit working area will be via the A256 and existing sports complex entrance. 2.82 The receptor pit working area will require some temporary roadways to be constructed to provide suitable access for drilling plant and associated equipment. The launch pit working area has sufficient access for working and does not require temporary roadways. 2.83 Installation of conduits by directional drilling is described below and comprises drilling the pilot holes; reaming (to make the holes bigger); and pulling the conduits through the reamed holes. 2.84 The following typical equipment will be mobilised to the site and used in the operation of directional drilling: • • • • • • • Excavator; Drill Rig; Generator; Bowsers; Mud Pump; Tool and Spares Container; and Auxiliary pumps. 2.85 The hydraulic drilling process would be undertaken from existing ground level. The drill string would utilise a drill of approximately 85mm diameter and approximately 6m long with a bend radius of approximately 60m. The head at the end of the drill string would eject a jet of drilling fluid or ‘mud’, emulsifying the material in front as the drilling rig pushes the drill string forward. The drill head is slightly bent so that the jet of mud is slightly off-centre. The direction of drilling is steered by rotating the drill string and head. The spoil produced would be suspended in mud and washed back up the bore to the entry point. The location of the drill head will be monitored with an In Ground Positioning System (IGPS). 2.86 To control water ingress, a short section of oversized bore (approximately 600mm) would be drilled initially at the entry point. This section will be plugged with concrete. The main 400mm diameter bore will be drilled through this plug. The plug will be fitted with a water control valve, through which the drill string passes. The valve controls the passage of mud and would stop any ingress of water. 2.87 The project will require 3 ducts to be drilled: 2nr 400mm medium density polyethylene (MDPE) ducts for the HVDC cables and 1nr 355mm MDPE duct for pilot and fibre optic cables. These will be drilled at approximately 2.5m centres with the smaller fibre optic duct drilled on the centre line. 2.88 There would be a small pit at the drill launch point to contain the mud and cuttings exiting from the bore. This will be approximately 6m x 2m x 2m, depending on ground conditions and the required drilling technique. The drilling system would 32 use a closed-circuit mud management system and the mud would be constantly pumped out of the pit for processing and re-use. 2.89 The bore would be drilled to within approximately 1m of the exit point and then the mud circulated out and replaced with water. The water would be used to drill the last section and ‘punch out’ through into a receiving pit approximately 6m x 2m x 2m. At the last point before emergence of the drill head the drilling fluid pressure can be reduced and the thrust of the rig can be used to punch out the drill head. There would be a limited escape of water as the drill string punches out but then the mud pumps would be turned off. 2.90 If required, the bore can be reamed to make it larger enough to accept the duct. The drill string would be pulled back through the bore with a reamer attached to make the hole larger. This will be repeated until the bore is the appropriate size. 2.91 Each duct will be constructed from pipe lengths of MDPE. The pipes would be laid out and welded together on site to form a duct of sufficient length for the bore. 2.92 The duct may be ‘pushed’ through the bore or pulled from the exit point into the bore. A ‘tremie’ pipe would be pulled in at the same time on the outside of the conduit to fill the annulus between the duct and the bore with grout (clay or a cement mix). The material would be pumped down the tremie pipe as it is slowly withdrawn from the bore. 2.93 The depth of the bore will depend on the surface features. From the launch pit, the bore will be at a depth of 1.2m. This will increase to approximately 8m under the SSSI and 9m under Minster Stream. A depth of 8-10m will be maintained along the rest of the route with the depth gradually decreasing until it reaches the receiving pit where it will be at 1.2m. 2.94 The HDD operation between BayPoint sports complex and the proposed converter station is for a total length of approximately 330m and will comprise 2 HVDC cables and 1 fibre optic cables (3 bores in total). Each bore will be drilled continuously at a rate of approximately 20m per hour giving an installation time of 16.5 hours per bore. This will be doubled to 33 hours per bore to allow for any unforeseen complications during drilling. There will be a rest period of 1 day (i.e. no drilling at all) between each of the cable installation phases. HDD is anticipated to take approximately 1 week. 2.95 At the end of the drilling operation, a draw wire would be left in each duct and the ducts would be plugged to await cables installation. Drilling fluids and any wastes would be cleared from the site and excavations backfilled. Any contaminated waste will be taken to a certified waste site. 2.96 HDD and ducts installation would be completed well in advance of cables delivery to avoid any possibility of delay to the installation. 2.97 As the cables installation approached the ducts, the duct ends would be excavated, the plugs removed and draw wire retrieved. The cables trench would be excavated to the ducts on each side and the cables pulled through the ducts and along the trench. 33 2.98 The void between the cable and the duct will be filled with bentonite material to seal the void and aid heat dissipation. HVAC Land Cables 2.99 Three 400 kV HVAC cables and two telecommunications cables will connect the converter station to the 400 kV substation. The HVAC cables will be cross-linked polyethylene (XLPE) type and will be approximately 150mm in diameter. The total length of the HVAC cables route is approximately 200m. General Construction Information Environmental Management 2.100 During construction, the appointed Contractors will be required to operate under a detailed site specific Construction Environmental Management Plan (CEMP). It will, as a minimum, set out the requirements to implement the mitigation measures identified within this ES. The CEMP will set out a variety of control measures for managing the potential environmental effects of construction works including control and management of noise, dust, surface water runoff, waste and pollution control. In addition, the site environmental management will be audited by the developer and appropriate specialist environmental consultants. Contractor Responsibilities and Communication 2.101 Contractors will be required to conform to all relevant legislative and statutory requirements and to comply with British Standards and relevant codes of good practice during construction works. 2.102 Communication will be undertaken with local residents and communities which may be affected by or interested in the works. Typical communications include the delivery of leaflets to local properties, newspaper advertisements and the establishment of a ‘freephone’ telephone number for interested persons to call with questions or observations on the works. 2.103 The approach to communications during the works is intended to ensure that potential causes for complaints or disturbance are avoided where possible and that if any issues of concern arise, there is a means of communicating with the developer on that issue. Staffing and Employment 2.104 The number of staff on site will vary according to the construction phase and activities being undertaken. 2.105 Staff levels will be at their highest during the earthworks and civil engineering works phases. Staffing levels will generally decrease as construction is progressed through to the commissioning phase. 34 2.106 The appointed Contractors will employ a Site Environmental Manager (SEM) or Environmental Clerk of Works (ECoW) who will be responsible for the preparation and implementation of the CEMP ensuring that mitigation measures identified in this ES are appropriately implemented. The SEM or ECoW will be supported by environmental specialists such as ecologists or archaeologists as required. Hours of Working 2.107 For the purposes of the Environmental Appraisal it has been assumed that construction activities will in general be undertaken during daytime periods only, however, exact arrangements will be agreed with Thanet District Council and Dover District Council. On weekdays this is anticipated to involve work from 07:00 to 19:00. At weekends, the working hours will be approximately 07:00 to 14:00. There will be some periods where 24 hour working will be required. Construction Waste and Spoil 2.108 Subject to geotechnical testing, all excavated materials will be re-used on site wherever possible. Where waste materials are to be disposed of off-site, this will be at licensed waste disposal facilities in accordance with a Site Waste Management Plan (SWMP). The SWMP will be prepared by the Contractor in consultation with the Environment Agency (EA). A high level SWMP has been prepared as an accompanying document to this planning application. General Operation and Maintenance 2.109 The 400kV substation will be an unmanned site subject to infrequent inspections and maintenance visits whilst in operation. The frequency and duration of maintenance visits will be dependent on the manufacturer’s recommendations related to the equipment installed on-site. 2.110 The converter station is likely to operate with approximately 6 personnel per day divided between 3 shifts over a 24 hour period. 2.111 Inspections and safety checks of the converter station and substation will be undertaken periodically so it is likely that a small number of staff will be present on site on a regular basis. National Grid Nemo Link Limited (NGNLL) will be responsible for on-going maintenance and upkeep of the converter station and NGET will be responsible for the 400kV substation. This will include regular inspection of the site and equipment as well as safety checks. From time to time during refurbishments, detailed inspections and replacement of some components, there may be larger numbers of personnel on the converter station or substation sites. 35 Decommissioning 2.112 The anticipated operational life of the converter station, substation and cables is approximately 40 years. This could however be extended should components be replaced. It is likely that after 40 years a refurbishment of the equipment will be undertaken rather than decommissioning. 2.113 Should decommissioning of the converter station and substation be required, the activities undertaken would be similar in nature to those described previously for construction. The main components would be dismantled and removed for recycling wherever possible or for disposal in accordance with the relevant waste disposal regulations at the time of decommissioning. Wider Project Components 2.114 The Proposed Development for which planning permission is being sought forms part of a wider project known as the Nemo Link. The elements of the Project that fall outside the jurisdiction of the local planning authorities in Kent comprise high voltage direct current (HVDC) subsea cables passing through UK, French and Belgian waters, and onshore infrastructure in Zeebrugge, Belgium consisting of a converter station, substation and onshore cables (see Figure 1.1). 2.115 Applications for consent for the other elements of the Project are being submitted to the relevant national authorities and each element has been subject to environmental assessment. Non-technical summaries of the environmental assessment documents for the other elements of the Project are appended to this ES (see Appendix 16.1). The full environmental assessment documents for all elements of the Project can be viewed at http://www.nemo-link.com Subsea Cables in UK, French and Belgian Waters 2.116 The subsea cables will be the same as those described for the intertidal area. The cables will be installed in a bundled configuration, comprising two cables buried in the same trench. 2.117 Two significant preparation activities are likely to be undertaken prior to installation of the cables system. These are: 2.118 Clearance of out-of-service telecommunications cables that cross the cables route; and Preparation and deposit of bridging and separation structures over any cables and pipelines that the interconnector cables route crosses. The cables will be buried into the seabed either by a plough or trenching machine deployed by the main laying vessel directly or by a support vessel following behind. To ensure cable protection is immediate, operations may be simultaneous with burial equipment being deployed by either the cable layer or the support vessel. 36 Alternatively cables may be buried in a ‘post-lay burial’ (PLB) operation, where a burial machine is deployed days or even weeks later by a separate vessel. 2.119 The programme for the commencement of installation has not yet been agreed but it is likely that installation of the subsea cable will begin between 2015 and 2017. In general, installations in European waters are undertaken in the summer season, broadly between April and October. This period is determined primarily by the high probability of adverse weather occurring outside of this period. 2.120 The schedule will also be affected by factors such as the requirement for any ecological mitigation, cable delivery and the availability of vessels. Belgian Onshore Components of the Nemo Link 2.121 Onshore infrastructure in the UK will be mirrored in Belgium. Components will include: Two HVDC subsea cables to make landfall at the beach to the north of the De Fonteintjes nature reserve, west of the Port of Zeebrugge, Belgium; Two HVDC onshore underground cables from the converter station to the landfall on the coast in Zeebrugge where they will be joined to the subsea HVDC cables; Fibre optic cables installed with the onshore and subsea HVDC cables for the purposes of operational telemetry and communications; A HVDC converter station is proposed for a former military site west of the Port of Zeebrugge on the eastern side of the N31 national road; A 400kV electricity substation, called Stevin, on another former military site on the western side of the N31 national road; and Three 400 kilovolts (kV) high voltage alternating current (HVAC) underground electricity land cables to connect the Stevin substation to the high voltage direct current (HVDC) converter station and up to two telecommunications cables for telemetry and control purposes only. Proposed Connection of Interconnector to the National Electricity Transmission System (NETS) 2.122 New infrastructure will be required to enable the 1000MW capacity of the interconnector to be connected to the existing National Electricity Transmission System (NETS). A site has been selected by NGNLL at Richborough for the proposed converter station and substation. There is no existing National Grid Electricity Transmission (NGET) 400kV infrastructure in the area surrounding Richborough to enable a connection to be made. There is therefore a requirement for a high voltage transmission connection from the proposed substation to a point on the existing NETS. 2.123 Although they are both part of the National Grid group, National Grid Nemo Link Limited (NGNLL) and NGET are separate legal entities and their statutory roles are 37 clearly segregated under the Electricity Act 1989. The development of the grid connection is the responsibility of NGET and is part of its statutory functions as the holder of a licence to transmit electricity under section 6(1)(b) of the Electricity Act 1989. The operation of an electricity interconnector is a separately licensable activity under section 6(1)(e) of the Electricity Act. The Act expressly provides that the same person or company may not hold an interconnector licence and a transmission licence. It is also important to understand that under the Act, NGET is obliged to enter into a Bilateral Connection Agreement with NGNLL as would be the case for all other customers seeking a NETS connection. 2.124 This NETS connection is the responsibility of NGET and will require relevant consents to be obtained in due course. The form and route of the grid connection are not yet known, do not form part of this planning application under the TCPA 90 and will be promoted separately by NGET. The type of consent required will depend on the type(s) of technology proposed for the connection. If an overhead line is proposed for all or part of the connection, a development consent order (‘DCO’) will be required under the Planning Act 2008. If an underground cable is proposed for all of the connection, the proposed installation would be undertaken as permitted development under Part 17, Class G of the Town and Country Planning (General Permitted Development) Order 1995. Should a combination of overhead line and underground cable be proposed for the connection, a DCO would be required for the entire route. 2.125 In developing the NETS connection, NGET assesses and examines strategic options and based on this develops route corridors options before the selection of the preferred route corridor option. As part of developing the NETS connection, NGET would carry out appropriate consultation and environmental studies. If an application for development consent under the Planning Act 2008 is required, NGET would undertake the consultation process prescribed under the Planning Act 2008 and Environmental Impact Assessment as set out in the Infrastructure Planning (Environmental Impact Assessment) Regulations 2012. NGET anticipates that, if a DCO application is required, it will be submitted to the Planning Inspectorate in the third quarter of 2015. Should a proposed connection consist entirely of underground cables installed as permitted development, EIA would not be an automatic statutory obligation. In those circumstances, NGET would come to a view as to whether an EIA was required under the Town and Country Planning (Environmental Impact Assessment) Regulations 2011. Appropriate consultation and environmental studies would be undertaken in the event that EIA was not applicable for underground cables. 2.126 Although it does not form part of the Nemo Link project for EIA purposes, the need for a grid connection arises as a direct result of the Nemo Link. Accordingly, the likely significant effects of the grid connection need to be considered as part of this ES. On the basis that NGET is considering a range of different connection options. This ES therefore includes an assessment of the likely significant effects of a connection from Richborough to what NGNLL considers to be likely connection 38 points on the national electricity transmission system (Canterbury North, Cleve Hill and Kemsley). The effects of a connection to each of these locations using either overhead line or underground cable is considered and set out at Chapter 17. 39 40 3.0 OPTIONS AND ALTERNATIVES CONSIDERED Introduction 3.1 This chapter summarises the work carried out to identify and assess suitable sites, shore landings and cable routes for the Nemo Link which led to the decision to locate the Proposed Development at Richborough. 3.2 The chapter presents a review of the factors that influenced the choice of landfall and the cable route for the proposed interconnector and the site of the converter station. Technology options considered are also discussed. 3.3 A full account of the process that led to the development of the current proposals is set out in the ‘Nemo Link: Review of Options Report’ (February 2013) which is provided at Appendix 3.1. Siting of the Nemo Link 3.4 In all, 28 potential converter station sites were considered by the Nemo Consortium, along with associated cable landings and routes and connections to the national electricity transmission system. The work was carried out in a number of phases during the period 2006 to 2011. 3.5 Prior to 2006, the Nemo Consortium identified 10 locations where an interconnector might be connected to the high voltage national electricity transmission system. These were either adjacent to existing NGET substations or in areas where a substation could be considered feasible. The locations are listed in Table 3.1 below and shown at Figure 3.1. 3.6 During 2006-7 the Nemo Consortium considered sites and potential landfalls for each of the 10 potential connection points. The feasibility of a grid connection point at Richborough was then considered as an 11th option, and Richborough subsequently formed the basis of an application in 2008 to National Grid Electricity Transmission (NGET) for a connection to the national electricity transmission system. 3.7 The potential landfall sites were in locations where there appeared to be sufficient absence of built development to allow cables to be brought ashore and to be routed to the potential connection point. 41 Table 3.1: Potential Grid Connections and Landfalls Considered in 2006/2007 Ref Grid Connection Points Landfall 1 2 3 4 5 6 7 Sizewell NGET 400kV substation Bramford NGET 400kV substation Bradwell NGET 275kV substation Rayleigh NGET 400kV substation Shellhaven (Thames Gateway) Grain NGET 400kV substation Kemsley NGET 400kV substation 8 9 10 11 Cleve Hill NGET 400kV substation Canterbury North 400kV NGET Sellindge NGET 400kV substation Richborough Sizewell Vicinity of Felixstowe Bradwell Shellhaven Shellhaven Grain Swale estuary or north of the Isle of Sheppey Cleve Hill Richborough Folkestone area Richborough 3.8 The first marine routeing studies and site studies investigating potential converter station sites and cable routes were undertaken in 2006. These studies were undertaken primarily using desktop analysis, supplemented by visits to areas and sites which showed good potential from the desktop studies. 3.9 The issues considered important for a potential converter station site were: A site of approximately 4 hectares; The potential for securing the necessary consents and licences; The scale of anticipated environmental effects and the sensitivity of the environment; Whether appropriate interest in land may be available for each potential converter station site (purchase or long lease); The feasibility of an appropriate high voltage alternating current (HVAC) connection to the grid system from the converter station; and The feasibility of an appropriate high voltage direct current (HVDC) connection between the converter station and a suitable subsea cables landfall. 3.10 During 2007, land ownership of some sites was investigated. For sites that appeared to show potential for a converter station development after the desktop study and site visits, further information and stakeholder opinion was sought from local planning authorities, Natural England and the Environment Agency. This culminated in the development of an interim report of the feasibility of all options, enabling a short list of sites to be taken forward by the Nemo Consortium. 3.11 Subsequent to this, in respect of the short listed sites, further liaison was undertaken in 2007 with the local planning authorities (Canterbury City Council, Dover District Council, Swale Borough Council and Thanet District Council), Natural England, the Environment Agency and Kent Wildlife Trust. 3.12 Details of the findings in respect of each of the shortlisted locations listed above are set out in the Options Report at Appendix 3.1. 42 Short List of Sites – Kemsley, Shellhaven and Richborough 3.13 Of the 28 site options identified in 2006/7, the Nemo Consortium concluded that the sites to take forward were Shellhaven, Kemsley and Richborough. Of the three sites, Richborough was not an existing grid connection point, and therefore the evaluation needed to recognise the requirement for an onward connection to the national electricity transmission system from that location. The Nemo Consortium considered that a connection could feasibly be made to a number of locations in the region, although the development of the connection would be a matter for NGET to determine through its strategic options process. 3.14 The announcement of the Thames Gateway development in 2007 ruled out Shellhaven as an option, leaving a short list of two sites: (i) Kemsley and (ii) Richborough. 3.15 In 2006, Metoc completed a desktop study of marine routes on behalf of the Nemo Consortium and concluded that there were feasible marine routes to support the short-listed sites and that any risks to consent being granted should be manageable within project timescales. Metoc confirmed that the shortest marine route for the project was between Richborough and West Zeebrugge and it was noted that the costs of addressing marine risks were likely to be insignificant in relation to the capital expenditure of the project. 3.16 Taking the short listed sites forward, in 2007 the Nemo Consortium wrote to relevant local planning authorities, the Environment Agency, Natural England and Kent Wildlife Trust specifically regarding the potential sites at Kemsley, Richborough and Canterbury. Considerations Leading to Preferred Site – Richborough 3.17 In 2006, the vicinity of Kemsley offered distinct advantages to the Nemo Link in that there seemed to be useable land suitable for a converter station site close to the Kemsley NGET 400kV substation, making the AC connection short subject to detailed routeing. Sites in this area also had good access to the highway and there were some large industrial buildings in the vicinity. However, the local planning authority advised that it would find it difficult to support an application for permission for a converter station in this area because of its anticipated adverse effects on areas designated for nature conservation and for employment. Additionally, there are particular challenges to the landing or onshore routeing of DC cables at Kemsley because of the extensive areas of wetlands designated for nature conservation value, where installation would be difficult and could cause disturbance. Land ownership was investigated in 2007, and it was concluded that there appeared to be no obvious land parcel suitable for the converter station in the Kemsley vicinity. 3.18 In contrast, in late 2007, the former Richborough power station site seemed to have the most favourable planning prospects for gaining consent for a converter station of all the 28 sites considered. It had the advantage of being a ‘brown field’ site allocated for re-use. Land was also available at this site with a landowner willing to sell, subject to satisfactory commercial negotiation. It was also close to a suitable landfall (at Pegwell Bay) and it supported the most direct, least distance subsea cables connection to West Zeebrugge within acceptable risk parameters. However, 43 in 2007 the former Richborough power station site presented two potential issues of concern. 3.19 First, the landfall for DC subsea cables at Pegwell Bay is a site with similar nature conservation designations to the Swale estuary close to Kemsley. However, there was high confidence that there was an acceptable cable route close to the route of the Thanet Offshore Wind Farm cables which have been successfully consented and installed in the bay. The landfall and immediate onshore cables routes would not be through mudflats, creeks and wetlands which pose higher risk at the Swale estuary. A review of risks confirmed that the subsea cables route and proposed landfall at Pegwell Bay posed relatively low risk for the project. 3.20 The second issue of potential risk was the AC connection between the converter station at Richborough and the national electricity transmission system. The existing 132kV overhead line between Richborough and Canterbury would not offer sufficient capacity for the Nemo Link, so a new 400kV connection would be required. 3.21 If the Richborough site was selected, NGET would undertake a full appraisal of all potential routes and technology options for the connection in accordance with its approach to the design and routeing of new electricity transmission lines. However, as part of its options assessment for the converter station site, the Nemo Consortium considered the potential for a connection between the Richborough site and NGET’s 400kV substation at Canterbury and whether there appeared to be any technical or environmental constraints to indicate that such a connection would not be feasible. 3.22 There are a number of ecological constraints in the area which would have to be taken into account by NGET in developing a new connection. In particular, a new connection could potentially affect a number of designated nature conservation areas between Richborough and Canterbury including the Stodmarsh Special Protection Area (SPA), Special Area of Conservation (SAC) and Ramsar, and East and West Blean Woods SSSI and Thorndon Woods SSSI. Effects on landscape and views would also have to be considered carefully as there are a number of settlements and sensitive areas between Richborough and Canterbury including the Kent Downs AONB, the North Kent Plain National Character Area and the North Downs National Character Area. There is the potential for an overhead line to be viewed from within the AONB; however, the OHL would not be routed directly through it and would be unlikely to affect its wider setting. 3.23 A connection by overhead line could have impacts on the setting of important heritage assets including the World Heritage Site of Canterbury and the Scheduled Monument of Richborough Castle, and these impacts would have to be considered by NGET when developing its connection options. An underground connection could also have effects on important heritage assets which would require consideration when developing connection options. 3.24 The Nemo Consortium also noted the presence of residential and business development and sensitive woodland in the vicinity of the Canterbury North substation which could present difficulties for the routing of a new line. 44 3.25 Whilst recognising these potential constraints, the Nemo Consortium did not consider that they would prevent a connection from Richborough to Canterbury from being made. Although NGET would carry out a strategic assessment of all options for the connection to the transmission system, the Nemo Consortium considered that a connection to Richborough was feasible. 3.26 On the basis of this assessment of the short listed sites, the Nemo Consortium selected Richborough as the preferred site to progress further. The Richborough site offered suitable land availability, a proven cable landing point and onshore route to the converter station, and a potential connection to the national electricity transmission system. In 2008 the Nemo Consortium therefore applied to NGET for a grid connection at Richborough (and not Canterbury North). In early 2009, NGET responded with an offer to connect the interconnector to a new substation at Richborough with a connection date of 2019; the connection date has since been brought forward to 2018 following a modification application to NGET in December 2010 based on a 1000MW interconnector connection at Richborough using voltage source conversion (VSC) technology. Landfall Options near Richborough 3.27 A summary of the cable landfall areas that were considered near to Richborough are illustrated at Figure 3.2 and detailed below. 1. Service Station North: This is the area to the north of the petrol station on the A256 at the west of Pegwell Bay. The Thanet Offshore Wind Farm (TOWF) cables make their landfall in this area and it is expected that installation of the Nemo Link cables is technically feasible using similar open cut trenching methods as used by TOWF. This landfall location is less ecologically sensitive than other areas of the bay as it would involve minimal crossing of saltmarsh. The area to the north, Cliff End Beach is important for a population of a protected bird species (turnstone); the area to the south west has extensive areas of salt marsh; the area to the south of river mouth (Sandwich Flats) has sensitivities including ancient dune pasture and is also an area where sand lizards have been re-introduced. However, a landfall at Service Station North would require crossing the TOWF cables both offshore and onshore which would introduce risks to both sets of cables and risk that excavation and disturbance during installation would be prolonged. 2. Service Station South: This is the area to the south of the petrol station located at the west of Pegwell Bay on the A256. This location shares the benefits of the Service Station North landfall noted above but avoids the need to cross the TOWF cables. The quality of saltmarsh that would be disturbed in this location is poorer than other areas of saltmarsh within Pegwell Bay. 3. Cliff End Beach: This area is in the northern part of Pegwell Bay. Cable installation would require Horizontal Directional Drilling (HDD) through the cliffs at the back of the bay which may disturb a population of turnstone, a species for which Thanet Coast and Sandwich Bay SPA is designated. An offshore crossing of the TOWF cables would also be required for this option and the onshore route cables route would be longer than that required than for other options. 45 3.28 4. Sandwich Flats: This landfall is to the southern extent of the bay south of the mouth of the River Stour. There are considerable disadvantages with this landfall owing to its remoteness, difficulty in obtaining access, ecological sensitivities including the presence of ancient dune pasture and the adjacent sand lizard re-introduction area. 5. Country Park: This landfall is located in the southern extent of the bay north of the mouth of the River Stour. This area is a former landfill site for which records are incomplete. This option would present considerable engineering challenges to avoid opening a possible pathway for any contaminants in the landfill to escape and would pose environmental risks. 6. River Stour: This would involve installation of the cable in the mouth of the River Stour, making landfall at Richborough Port. The width of the river channel and estuarine environment present considerable risk to the environment and the Project. In the event that there was any future development of the Port or riverside which could involve changes to the channel including dredging, the cables would pose a substantial obstacle or would require removal. Based on technical and environmental assessment of the alternatives, the proposed cable landfall is in the area of the Service Station South option. The subsea cables would be installed beneath the inter-tidal mudflats from low water to a Transition Joint Pit (TJP) south of the Pegwell Bay Service Station in an area of degraded saltmarsh. The subsea cables would be connected by joints to the onshore underground cables. Onshore Underground Cable Route Options 3.29 The optimum onshore underground cables route from the landfall to the former Richborough Power Station site was identified from an initial feasibility study. Specific factors taken into account included: 3.30 Designated sites of nature conservation; Presence of protected species; Proximity to residential areas; Archaeology; Highways; Planning proposals; Watercourses; Risk of encountering contamination; Utilities and services; and Land use. Routeing along Sandwich Road (A256) offered the shortest route and would avoid potential direct effects on Pegwell Bay nature designations including Sandwich Bay Special Area of Conservation (SAC), Sandwich Bay Special Protection Area (SPA) and Ramsar site, Sandwich Bay to Hacklinge Marshes Site of Special Scientific Interest (SSSI) and Sandwich and Pegwell Bay National Nature Reserve (NNR). The road also comprises made ground, so trenching would be unlikely to impact upon archaeological features as these would previously have been unearthed. A utilities search demonstrated that the ground beneath the road is already congested 46 with electricity and telecommunications cables and foul water and drinking water pipelines. Thanet Offshore Wind Farm cables have also recently been routed beneath Sandwich Road from its landfall north of Pegwell Bay Service Station to where it connects to a substation on the former Richborough Power Station site. There is insufficient space to accommodate the two HVDC cables along the A256. 3.31 The verge on the landward side of the A256 within St Augustine’s Golf Course offered an alternative routeing option. Potential direct effects on designated sites of nature conservation would be avoided. However installation would cause disruption to the use of land for golf. Future development plans to raise and remodel the golf course with an unknown overburden also make this option unsuitable for the burial of the HVDC cables. The onshore underground cables for each project are designed to function efficiently within a series of parameters including the known depth of burial. Where land above the cables would change substantially, this would affect the capacity or rating of the cables, limiting the effectiveness of the Nemo Link. If the cables are buried deep below ground it can be very difficult to repair them in the event of failure. 3.32 Routeing further inland, directly across the Golf Course to Cottington Road and around Ebbsfleet Lane would mean a longer route but would result in fewer direct effects on the present golf course. However, this area is also planned for improvement including an, as yet, undefined overburden. There are also ‘pinch points’ around which it would be difficult to route at St Augustine’s Golf Course Club House, Weatherlees Hill Wastewater Treatment Works and the East Kent Access Road. 3.33 The preferred route of the HVDC onshore underground cables will run from the TJP on the coastal side of the existing cycle track which runs parallel to the A256 Sandwich Road, through Pegwell Bay Country Park, then into Stonelees Nature Reserve and BayPoint sports complex. From the sports complex, the cables will be routed by horizontal directional drilling (HDD) beneath the A256, Minster Stream, and a compartment of Sandwich Bay to Hacklinge Marshes SSSI terminating in the converter station. The overall length of the onshore cable route from the TJP to converter station site is approximately 2.3km. This route offers a short, technically and environmentally acceptable route which minimises disturbance to local residents, landowners and environmental features. Technology Options 3.34 There are a number of technology options for the design and principal components of the Nemo Link and these are outlined in brief below with reasons for the selection of the technology chosen. HVAC or HVDC 3.35 In order to connect the national high voltage grid systems of Belgium to that of the UK, a subsea cables connection is required. The only method of efficiently transferring electricity over the distance between the two countries is HVDC technology (as opposed to HVAC technology). For HVAC cable lengths in excess of a few tens of kilometres, the charging current creates a reactive power component that reduces the capability of the system to transmit power. In the terrestrial environment intermediate shunt compensation reactors (SCRs) can be 47 stalled in HVAC cable systems to compensate for the reactive power and restore the power transfer efficiency. SCRs contain assemblies of electrical components of considerable physical size which would be impractical to install in the subsea environment. 3.36 HVDC does not suffer from reactive power losses and, by optimising the operating voltage and copper conductor cross-sectional area, system losses can be minimised and the link made highly efficient. 3.37 The higher cost of an HVAC connection also makes HVDC transmission the most appropriate option to economically exchange power flows between the UK and Belgium. HVAC-HVDC Conversion Technologies 3.38 There are two HVAC-HVDC conversion technologies available that could meet the power rating required for the Nemo Link. These are self-commutated voltage source conversion (VSC) and line-commutated current source conversion (CSC). The Nemo Link will use VSC technology in a symmetrical monopole configuration. The main benefit of VSC technology is that less reinforcement work is necessary on the UK and Belgian transmission networks in order to provide assurance of a connection date in 2018. Monopole or Bipole Configuration 3.39 HVDC Interconnectors can be configured either as monopole or bipole systems. The configuration dictates the number of HVAC/HVDC converter valves in the converter station and also the type of return path used to complete the electric circuit. 3.40 Bipole systems transmit power via a closed circuit of two high-voltage conductors of opposite polarity connected to four HVAC/HVDC converter valves. 3.41 Monopole systems have a single high-voltage conductor, at either negative or positive polarity connected to a single converter at each end. The return path maybe through the earth (and sea) or via a second cable. Using an earth return requires large copper electrodes to be placed near each end of the link to feed the return current into the earth and sea. Although monopole interconnectors with earth returns operate successfully in a number of locations without adverse effects on local environments, concern has sometimes been expressed in respect of recent possible similar installations. These concerns generally relate to the effects on the marine environment of electrolysis products from the electrodes and the possible effects on metallic structures (such as pipelines) of stray currents. 3.42 If a return conductor, known as a metallic return cable is used this is usually a cable with a lower voltage rating, although it carries the same current as the pole cable. Monopole systems may also use a metallic sheath around the main conductor as the return path (known as an integrated return conductor or IRC). Monopole systems with an IRC metallic return cable are often confused with bipolar systems. Monopole systems with metallic return presently available do not have the necessary power rating required for the Nemo Link. 48 3.43 HVDC means the most efficient link can be constructed. The use of HVDC technology for the link means that a converter station is required at each end of the link to convert between HVDC power and HVAC power, as used in the national grid transmission system. HVDC Overhead or Underground 3.44 The HVDC transmission between the subsea cables landfall and the converter station could be achieved by overhead transmission (overhead lines suspended from lattice steel towers (pylons) or other supports) or by underground cables. The key factors in considering whether underground or overhead transmission is used are cost, both capital and operational, and environmental effects. Underground transmission is generally more expensive than overhead transmission. 3.45 Operational costs relate to the risk of the link being unavailable, due to the repair of damage or maintenance requirements, and the costs of the repairs and maintenance required. Once the connection point was identified, an assessment was made of the most appropriate means of transmission from the landfall to the converter station. 3.46 When considering whether underground or overhead transmission is appropriate, technical reasons are explored why one means is preferred to the other and also whether there are environmental reasons which justify the additional costs incurred in installing and maintaining underground rather than overhead transmission equipment. 3.47 Experience of operating outdoor above-ground HVDC electrical equipment in coastal locations indicates a relatively high level of faults due to the combinations of salt-laden air and pollution causing insulation problems. Underground transmission would be technically advantageous, reducing the need for maintenance and the risks of faults, for routes up to 3km inland from the landfall. 3.48 Changing from underground cables (as will be present at the landfall) to overhead transmission is costly. The high costs are due to the sealing-end compounds required where the cable is brought to the surface and connected to conductors suspended from overhead line supports. A sealing end compound would also be required to allow a cable connection from an overhead line at the converter station site. The costs of the sealing end compounds, and land for tower footprints, are generally offset by the lower costs of the subsequent overhead line as compared to underground cables over the same route. This cost saving is not apparent where there is only a very short distance of overhead line between sealing end compounds. There is, therefore, relatively little cost benefit in transferring from underground to overhead transmission for a short distance. 3.49 As the converter station site is less than 3km from the coast at the former Richborough Power Station site, the connection from the landfall to converter station site will be by underground cables. 49 Conclusions 3.50 Alternative converter station sites, underground cable routes, landfalls and subsea cable routes were considered as part of the development of the Nemo Link. This established that a converter station site at Richborough and an underground cables route to a landfall at Pegwell Bay was the preferred option as this best meets the project objective relating to technically feasibility, economic viability, deliverability and the least disturbance to the environment and people. 3.51 Following selection of the preferred option, further detailed environmental and technical studies as well as consultation have been used to refine the preferred option and further reduce the potential environmental effects of the Nemo Link project including the substation which the convertor station is required to connect to. This included considering emerging results from environmental assessments with initial technical designs and results of consultation with stakeholders, land owners and local communities. 3.52 The following chapters provide a detailed assessment of the effects of the preferred option on the environment and identify mitigation measures which will minimise effects of installing the proposed onshore underground cables and constructing and operating the proposed converter station and substation. 50 51 52 4.0 PLANNING POLICY REVIEW Introduction 4.1 An application for the Proposed Development will be made under the Town and Country Planning Act (TCPA) 1990. Planning applications must be determined in accordance with the development plan unless material considerations indicate otherwise 4.2 This chapter presents an assessment of the national, regional and local planning policies that are relevant to the Proposed Development. National Planning Policy National Policy Statement for Energy (EN-1) 4.3 The National Policy Statements, approved by Parliament in July 2011, set out the most recent Government policy for the delivery of major energy infrastructure. These will be a material consideration in England and Wales, including those which fall under the Town and Country Planning Act 1990 (as amended). 4.4 The Overarching National Policy Statement for Energy (EN-1) notes that it is critical that the UK continues to have secure and reliable supplies of electricity as we make the transition to a low carbon economy. This means ensuring that: 4.5 There is sufficient capacity (including a greater proportion of low carbon generation) to meet demand at all times, including a safety margin of spare capacity to accommodate fluctuations in supply or demand; This capacity is reliable enough to meet demands as it arises; There is a diverse mix of technologies and fuels (including primary fuels imported from a wide range of countries); and There are effective price signals, so that the market can react in a timely way to minimise imbalances between supply and demand. The Government’s objectives for energy and climate change will require further diversification of the UK’s energy sources and much greater use of renewable and other low carbon forms of generation. It recognises the important role that interconnection can play in compensating for the intermittency of renewable generation. The NPS notes that ‘existing transmission and distribution networks will have to evolve and adapt in various ways to handle increases in demand’ and the fact that generation is now occurring in a greater diversity of locations. National Policy Statement for Electricity Networks Infrastructure (EN-5) 4.6 The National Policy Statement for Electricity Networks Infrastructure (EN-5) highlights that the new electricity generating infrastructure that the UK needs to move to a low carbon economy, while maintaining security of supply, will be heavily dependent on the availability of a fit for purpose and robust electricity network. That network will need to be able to support a more complex system of supply and demand and cope with generation occurring in locations of greater diversity. 53 4.7 The NPS sets out the basis for assessing proposals. It advises for a variety of topic areas (including many of those normally covered in an Environmental Impact Assessment) that the applicant's own assessment should address. It also advises on the weight to be given to certain issues and on the treatment of mitigation measures, particularly how these may be enforced through conditions or obligations. Any assessment will also need to cover those issues raised in the Overarching NPS for Energy (EN-1). The Environmental Statement (ES) submitted with this hybrid planning application addresses the issues raised in the NPS. National Planning Policy Framework 4.8 The Government published the National Planning Policy Framework (NPPF) in March 2012. The NPPF sets out the Government’s planning policies for England and replaces the majority of planning policy guidance notes including Planning Policy Guidance (PPG) and Planning Policy Statements (PPS).Some PPSs remain in place such as PPS 10 (Planning for Sustainable Waste Management) which was recently published. Guidance contained in many other PPSs and PPGs is no longer relevant and development must now be considered in relation to the NPPF (along with any retained PPSs and PPGs). 4.9 The NPPF is a material consideration in planning decisions and guides the development of Local Plans. Policies from the NPPF relating to the Proposed Development are outlined below. 4.10 The NPPF emphasises the importance of delivering and planning for sustainable development and is based on 12 principles that should under-pin plan making and decision taking. The following four principles are particularly relevant to the Proposed Development: 4.11 ‘seek to secure high quality design and a good standard of amenity for all existing and future occupants of land and buildings.’; ‘support the transition to a low carbon future in a changing climate....and encourage the reuse of existing resources including conversions of existing buildings…’ ‘contribute to conserving and enhancing the natural environment…prefer[ing] land of lesser environmental value where consistent with other policies in this framework.’ ‘encourage the effective use of land by reusing land that has been previously developed (brownfield land), provided that it is not of high environmental value.’ The NPPF sets out 13 sub-topics beneath the goal of Delivering Sustainable Development. The most relevant of these to the Proposed Development are set out below. Building a Strong, Competitive Economy 4.12 The Government is committed to ‘meeting the twin challenges of global competition and of a low carbon future’ using the planning system to support economic growth. Delivery of the Project would support the move towards a low carbon future as the benefits of interconnectors between countries include supporting the use of renewable power generation such as wind power. The ability to trade electricity between countries allows better use of renewable energy when resources are 54 available and support increased security of supply which sustains the economic growth of the nation. 4.13 The proposed converter station and substation would be built on the site of the former Richborough Power Station which is derelict brownfield land. The Proposed Development is consistent with and reinforces plans for the future development of the Richborough Energy Park. The construction work will create jobs and increase economic activity in the area. The agglomeration of energy industries on the former Power Station site will create a cluster of high technology energy industry. Requiring Good Design 4.14 The NPPF establishes the importance of achieving high quality design that has a positive effect on the environment. It states that permission should be refused for development of poor design that fails to take the opportunities available for improving the character and quality of an area and the way it functions. Local planning authorities should not refuse planning permission for building or infrastructure that promotes high levels of sustainability because of concerns about incompatibility with an existing townscape. 4.15 The Proposed Development demonstrates good design through the location of the converter station and substation on derelict brownfield land. As part of the design process, assessments of the impact of the Proposed Development on landscape and views and on archaeology and cultural heritage have been undertaken to ensure the effects of the development are as low as possible. The siting of the substation and convertor station seeks to use the existing turbine hall and has also been considered in accordance with National Grid’s guidelines for substation location, the Horlock Rules which are presented in Appendix 4.1. The external appearance of the buildings located with convertor station and substation will be similar in colour and style. 4.16 The converter station and substation will be adjacent to the proposed Richborough Energy Park and will create a hub of energy infrastructure. The buildings at the converter station and substation will be similar to those already in the local area and those of the proposed Energy Park. The site will be subject to a landscaping scheme proposed for the Richborough Energy Park (pending planning application submitted by Richborough A Limited); a Section 106 agreement will ensure the delivery of a scheme separate from that development if required. Meeting the Challenge of Climate Change, Flooding and Coastal Change 4.17 The NPPF sets out the importance of the planning system in securing reductions in greenhouse gas emissions, minimising vulnerability and providing resilience to the impacts of climate change. Decision making can also support the delivery of renewable and low carbon energy, and associated infrastructure, which is central to the economic, social and environmental dimensions of sustainable development. 4.18 The Project helps to meet the challenge of climate change by supporting the use of renewable energy as described in paragraph 3.7 above. 4.19 The converter station and substation will be constructed on the former Richborough Power Station site. The site is not in an area at risk of flooding. Sections of the 55 cable route travel through Flood Zones 2 and 3. A Flood Risk Assessment has been carried out to ensure the risk of flooding in the local area or elsewhere would not increase as a result of the development. Conserving and Enhancing the Natural Environment 4.20 The planning system has a role to contribute to and enhance the natural and local environment. Valued landscapes and ecosystems should be protected, with development prevented from adversely affecting soil, air or water, or from causing noise pollution and land instability. Effective use of land by re-using land that has been previously developed should be encouraged. 4.21 The potential effects on the natural environment as a result of the Project have been assessed within this EIA particularly in Chapter 8 (Ecology), Chapter 10 (Landscape and Views) and Appendix 8.9 (Information for Habitats Regulations Assessment). 4.22 The subsea cables will fall to land and connect with the onshore underground cables in Pegwell Bay which is part of a larger designated site comprising: Thanet Coast and Sandwich Bay Special Protection Area (SPA) and Ramsar Site; Thanet Coast SAC; Sandwich Bay Special Area of Conservation (SAC); Sandwich Bay and Hacklinge Marshes Site of Special Scientific Interest (SSSI); and Sandwich and Pegwell Bay National Nature Reserve (NNR). 4.23 There is a Local Wildlife Site immediately southwest of the power station site, and a Roadside Nature Reserve east of the A256 Sandwich Road, adjacent to Pegwell Bay Country Park, designated for its botanical interest. 4.24 There is also a Regionally Important Geological Site (RIGS) in the National Nature Reserve, close to Cliffs End. The site is an infilled dry valley and is one of only two sites where a section through a filled dry valley is available for study. The site demonstrates the effects of Ice Age periglacial processes on the chalklands of Britain. 4.25 Where any impacts have been identified during ecological assessments, appropriate mitigation measures have been included to reduce the adverse effect of the Project and, where appropriate such as in Pegwell Bay Country Park, to provide enhancement of existing conditions. Localism Act 2011 4.26 The Localism Act contains provisions to alter the planning system and allow the Secretary of State to make orders revoking Regional Spatial Strategies (RSS). Orders have not yet been made for the revocation however the Government is currently carrying out sustainability appraisals for the revocation of RSSs in due course. 56 Regional Planning Policy The South East Plan (2009) 4.27 At the time of writing, the South East Plan continues to be a material consideration in the planning process, although relatively little weight should be given to the policies it contains. The following policies are noted from this plan as relevant to the Proposed Development. CC1: Sustainable Development 4.28 Based on the guiding principles of the UK Sustainable Development Strategy 2005, this policy states that local development documents should ensure development meet obligations in relation to greenhouse gas emissions and take a precautionary approach to climate change. Development should relate to environmental limits and ensure that physical and natural environment is conserved. The Project supports renewable energy which is important in delivering sustainable development. CC2: Climate Change 4.29 This policy states that measures to mitigate and adapt to current and forecasted effects of climate change will be implemented through application of local planning policy and other mechanisms. The policy establishes levels for a reduction of the emission of carbon dioxide for the region to 2050. The Project supports renewable energy which is likely to displace less-efficient carbon-based generation. CC4: Sustainable Design and Construction 4.30 The design and construction of all new development, and the redevelopment and refurbishment of existing building stock will be expected to adopt and incorporate sustainable construction standards and techniques. This will include high standards of sustainable development including aspects such as energy, water efficiency, biodiversity gain and securing increased recycling of construction and demolition waste. 4.31 The Proposed Development is on a brownfield site re-using an area previously used for power generation. The steel frame of the former turbine hall of Richborough Power Station has been incorporated into the design, seeking re-use of the structure. There will be biodiversity gain along the cables route from new chalk grassland. CC6: Sustainable Communities and Character of the Environment 4.32 Policy CC6 states that actions and decisions associated with the development and use of land will actively promote the creation of sustainable and distinctive communities. This will be achieved by developing and implementing a local shared vision which respects, and where appropriate enhances, the character and distinctiveness of settlements and landscapes throughout the region, and uses innovative design processes to create a high quality built environment which promotes a sense of place. This will include consideration of accessibility, social inclusion, the need for environmentally sensitive development and crime reduction. 57 C4: Landscape and Countryside Management 4.33 This policy places a responsibility on local authorities to recognise and protect and enhance diversity and local distinctiveness of the countryside character. In exceptional circumstances where damage to the landscape character is unavoidable, mitigation should be included as part of development. The siting of the proposed converter station and substation would avoid damage to landscape character. NRM1: Sustainable Water Resources and Groundwater Quality 4.34 Policy NRM1 ensures that water supply and groundwater will be maintained and enhanced through avoiding adverse effects of development on the water environment. The ES demonstrates no adverse effects on water supply and groundwater. NRM4: Sustainable Flood Risk Management 4.35 Coastal and river flooding is a significant risk in parts of the South East of England. The priorities are to defend existing properties from flooding and locate new development where there is little or no risk of flooding. The assessment of flood risk presented in the ES demonstrates that the siting of the converter station and substation would not present a risk of flooding. The underground cables would not pose risks of flooding. NRM5: Conservation and Improvement of Biodiversity 4.36 Local authorities should ensure that internationally and nationally designated sites are given the strongest level of protection to avoid development that has adverse effects on the integrity of sites of European or international importance for nature conservation. The Project’s subsea cables fall to land in designated site. Careful design and assessment of potential effects has ensured that there would be no adverse effects on the integrity of the Pegwell Bay site which is of European and national importance. NRM15: Location of Renewable Energy Development 4.37 Local development documents should encourage the development of renewable energy in order to achieve the regional and sub-regional targets. Renewable energy development, particularly wind and biomass, should be located and designed to minimise adverse impacts on landscape, wildlife, heritage assets and amenity. Priority should be given to development in less sensitive parts of countryside and coast, including on previously developed land and in major transport areas. BE6: Management of the Historic Environment 4.38 Planning authorities should identify, protect, conserve, and where appropriate, enhance the historic environment of the region and its historic assets which contribute to the local and regional distinctiveness of the South East of England. There would be views of the proposed converter station and substation from the Scheduled Monument of Richborough Fort although no significant adverse effects are forecast. 58 Local Planning Policy 4.39 The majority of the Proposed Development falls within the administrative boundary of Thanet District Council (TDC). Approximately 720m of the onshore HVDC cable and a small area at the south east corner of the proposed converter station compound (outdoor hard landscaping and security perimeter fencing) is within the administrative boundary of Dover District Council. 4.40 Development control decisions in Thanet District are based on saved policies from the 2006 Thanet Local Plan. Thanet District Council is in the process of preparing a Core Strategy, which will establish policies for the future development of the Thanet District. The Thanet Core Strategy – Preferred Options Consultation Document although not yet adopted, is a material consideration in determining planning applications. Saved planning policies from the Thanet Local Plan and the Core Strategy Preferred Options Consultation Document have been assessed against the Proposed Development in Tables 4.1 and 4.2 respectively. Table 4.1: Relevant Policies from the Thanet District Local Plan Adopted 2006 Thanet District Local Plan Adopted 2006 – Saved Policies Policy Policy Summary Assessment of Policy TR4: New Road and Highway Improvements The Council will seek the implementation of improvements to dual carriageway standard to the A256 and A299 between Richborough, Lord of the Manor and Mount Pleasant known as Phases 1 and 2 of East Kent Access. TR8: Rail Link Safeguarding Direction Safeguarding direction for development affecting the route corridor for the Channel Tunnel Rail Link (CTRL) and any additional land required for associated works. TR12: Cycling The Council wishes to promote the use of cycling through implementing a network of cycle routes. 59 Phase 2 of the East Kent Access is complete and this route will be included in the Transport Plan for construction traffic. The use of a major road network will reduce the risk of adverse effects of construction traffic on the local road network. Access for the construction of the converter station and substation site will be from the site access off the A256. The cable route will cross beneath the A256 using HDD so that the new bypass and other land uses nearby are not disturbed. Land at the former Richborough Power Station was safeguarded because it provides access to sidings which were needed for storage of ballast during the construction of the CTRL. The Directions have not yet been withdrawn although the CTRL is complete; the Proposed Development is not anticipated to cause any substantial harm to Policy TR8. The converter station and substation will require a maximum of 6 personnel on site per day. The site is adjacent to the Viking Coastal Trail (Sustrans Route 15) suitable for access on foot or by bicycle. Cycle parking is proposed on site. Thanet District Local Plan Adopted 2006 – Saved Policies Policy Policy Summary Assessment of Policy TR16: Parking Provision Proposals for development will be required to make satisfactory provision for the parking of vehicles (including, where appropriate, service vehicles). HE11: Archaeological Assessment The Council may require the applicant to provide an assessment of archaeological or historic importance of the site in question and the likely impact of development. Archaeological sites will be preserved and protected. On those sites where permanent preservation is not warranted, planning permission will only be granted if arrangements have been made by the Developer to ensure that time and resources are available to allow satisfactory archaeological investigation and recording by an approved archaeological body to take place in advance of and during development. Development which would result in the loss or obstruction of geological features of importance for study and research purposes will not be permitted. HE12: Archaeological Sites and Preservation NC6: RIG (Regionally Important Geological) Sites 60 Car parking on site needs to consider occasional operational requirements which mean that there needs to be sufficient space for workers attending for refurbishment or emergency works to equipment. 18 parking spaces are proposed for the converter station (including 2 disabled spaces); 13 parking spaces are proposed for the substation (including 1 disabled space). An archaeological assessment has been provided at Chapter 9 of the ES. No significant adverse effects are anticipated. An archaeological assessment is provided at Chapter 9 of the ES. No significant adverse effects are anticipated. The development is distant from and will not affect any RIGS. A geological assessment has been carried out and details are presented in Chapter 6 of the ES. Thanet District Local Plan Adopted 2006 – Saved Policies Policy Policy Summary Assessment of Policy EP5: Local Air Quality EP9: Light Pollution Policy SR10: Public Open Space Permission will not be granted for new development proposals that exceed the National Air Quality objectives. Development proposals that might lead to such an exceedance resulting in unacceptable effects on human health, local amenity or the natural environment will require the submission of an Air Quality Assessment. Development that includes the provision of new outdoor lighting should be designed to minimise light glare, light trespass, spillage and sky glow so as to preserve residential amenity, the character of the surroundings and prevent disturbance to identified wildlife areas. Development will only be permitted on public open space in very exceptional circumstances and only if the proposed use is of a temporary or seasonal nature and cannot be accommodated elsewhere without conflict with areas of nature conservation or other development plan policies. The land shall be reinstated as public open spaces immediately after the temporary or seasonal use is ceased. 61 There will be no effects on air quality following the implementation of mitigation measures during the construction of the Proposed Development. No operational air quality effects are anticipated. An air quality assessment is provided at Chapter 13 of the ES. Outdoor lighting at the converter station and substation site will be used for security and emergency use only. Lighting will not impact on designated wildlife areas. Lighting will be designed and installed in accordance with the Institute or Lighting Engineers Guidance Reduction on Obtrusive Light. The onshore underground cable route includes areas of Public Open Space including Pegwell Bay Country Park. There will be a temporary diversion of the Thanet Coastal Path and the Viking Coastal Trail during installation of the cables and land will be reinstated to its former use. Thanet District Local Plan Adopted 2006 – Saved Policies Policy Policy Summary Assessment of Policy SR20: Undeveloped Beaches On or adjacent to beaches identified as undeveloped, priority will be given to the maintenance and enhancement of their natural and undeveloped character. The intertidal underground cables will cross an undeveloped beach. During construction there will be a visual impact on the undeveloped beach however, following reinstatement and during operation there will be no visible impact of the cable affecting the character of the area. An assessment of Landscape and Views is presented in Chapter 10 of the ES. 62 Thanet District Local Plan Adopted 2006 – Saved Policies Policy Policy Summary Assessment of Policy D1: Design Principles All new development is required to provide high quality and inclusive design, sustainability, layout and materials. New development will only be permitted if it: Respects or enhances the character or appearance of the surrounding area, particularly in scale, massing, rhythm and use of materials appropriate to the locality; Is compatible with neighbouring buildings and spaces and does not lead to unacceptable loss of amenity though overlooking noise or vibration, light pollution, overshadowing, loss of natural light, or sense of enclosure; Incorporates provision for disables access; Incorporates new landscape as an integral part; Incorporates measure to prevent crime and disorder, promotes the perception of public safety and security; Provides safe and satisfactory means of pedestrian and, where provided, vehicle access; and Incorporates sustainable drainage systems. 63 As part of the design process, assessments of the impact of the Proposed Development on landscape and views and on archaeology and cultural heritage have been undertaken to ensure the effects of the Proposed Development are as low as possible and avoid severe adverse effects. Part of the proposed converter station will re-use the existing frame of the old turbine hall. The scale of the converter station buildings will be broken up by treatment to the cladding so that there is a gradual fading of colour from the bottom to the top. A recessive green colour is proposed, lightening gradually to off-white on the upper elevations which will be seen against the sky. This will reduce the apparent bulk of each converter station building in general views. The substation, lower in height than the converter station will be finished in a recessive green cladding to match the lower sections of the converter station. The converter station and substation buildings will be similar to those already in the local area and those of the proposed Energy Park. The site will be subject to a landscaping scheme proposed for the Richborough Energy Park with provision for its implementation separate from the proposed Energy Park if necessary. Additional native landscaping is proposed at the south western elevation as part of this planning application. Sustainable Drainage System (SUDS) has been designed for the converter station and substation site. A security fence will be installed surrounding the converter station and substation site to prevent unauthorised access to the converter station and substation. Appropriate access and parking provision (including provision for disabled access and parking) is included with the proposals. Thanet District Local Plan Adopted 2006 – Saved Policies Policy Policy Summary Assessment of Policy D2: Landscaping The following elements will be required as part of landscaping proposals for any new development: The enhancement of the development site in the setting; The retention and protection of as many of the existing trees and hedges and other habitat features as possible on sites of one hectare of more the setting aside of 10% of the development site for the planting of native tree species either within or at the boundary of the development site; and The maximising of nature conservation opportunities where development is proposed in proximity to existing open space or wildlife habitats and where both appropriate and possible the provision of landscaping in advance of new development to facilitate the assimilation of new development into the landscape. 64 The effects of the Proposed Development on landscape and views and ecology have been assessed and are presented at Chapters 10 and 8 of the ES respectively. The converter station and substation will benefit from a landscape scheme presented as part of the Richborough Energy Park proposal and will be implemented in the event that the Energy Park is not built. The Proposed Development includes landscape works with cables reinstatement to increase the area of calcareous grassland which is a priority habitat for the Kent region. Additional native landscaping is proposed at the south western elevation as part of this planning application. Thanet District Local Plan Adopted 2006 – Saved Policies Policy Policy Summary Assessment of Policy CC1: Development in the Countryside CC2: Landscape Character Areas The Thanet countryside is defined as those areas of the district outside the identified urban and village confines. Within the countryside new development will not be permitted unless there is a need for the development that overrides the need to protect the countryside. Within the following landscape character areas the following principles will apply unless development is essential for the economic or social wellbeing of the area: Pegwell Bay (east of power station) – priority is given to conservation and enhancement of the natural beauty of the landscape; Former Wantsum Channel Area (covering power station) – new development will not normally be permitted; Wantsum Channel Northshore Area (north of Former Wantsum Channel Area) – development will only be permitted that would not damage the setting of the Wantsum Channel, and long views of Pegwell Bay, the Wantsum Channel, the adjacent marshes and the sea. 65 Although outside the defined urban area, the converter station and substation will be built on derelict brownfield land located adjacent to the proposed Richborough Energy Park and will not impact on unspoilt countryside. There is a national need for investment in electricity infrastructure. The converter station and substation will be on the site of the former power station in a locale where there are existing commercial and industrial buildings along the A256. The converter station and substation buildings and associated outdoor equipment will be adjacent to the proposed Richborough Energy Park which will be of similar character. An assessment of the effects of the Proposed Development on landscape and views is presented at Chapter 10 of the ES. Thanet District Local Plan Adopted 2006 – Saved Policies Policy Policy Summary Assessment of Policy CC7: Rural Lanes Development that would adversely affect the landscape, amenity, nature conservation, historical or archaeological interest of the rural lanes identified will not be permitted: Way Hill, Minster; Wayborough Hill, Minster; Grinsell Hill, Minster; Marsh Farm Road, Minster; Chambers Wall, St. Nicholas; and Shuart Lane, St. Nicholas. 66 The converter station and substation site at the former Richborough Power Station is to the south of the allocated Rural Lanes. An assessment of the effects of the Proposed Development on landscape and views is presented at Chapter 10 of the ES. Table 4.2: Relevant Policies from Thanet District Council Core Strategy Preferred Options Consultation Document Thanet Core Strategy – Preferred Options Consultation Document Policy Policy Summary Assessment of Policy DCS19 DCS20: DCS22: The Council will seek to strengthen Thanet’s economic employment base and promote access for residents to a good range of community facilities while safe guarding: The distinctiveness and attractive character, townscape and setting of Thanet towns and villages; The health, economic well-being and safety of the community; The character and quality of the coast, the beaches, local landscape, the wider countryside and biodiversity; The quality of natural resources including water supply and drainage, air and soil; Against the effects of climate change and flood risk; Historic and cultural features of acknowledged importance; and Provision of essential services to the public. Development outside urban and village confines and not otherwise allocated for development will not be permitted. New development will be of a high quality inclusive design and employ sustainable construction methods and layout. It should: • Relate to the surrounding development form and layout and strengthen links to the adjacent areas • Be well-designed, respect and where possible enhance the character, context and identity of its location: particularly in scale, massing, rhythm, and use of materials appropriate to the locality; • Be compatible with neighbouring buildings and spaces and not lead to unacceptable loss of amenity through overlooking, noise or vibration, light pollution, overshadowing, loss of natural light, or sense of enclosure; 67 The converter station and substation site at the former Richborough Power Station is to the north west of Richborough and the south west of Ramsgate and will not affect the character of either of these towns. The Proposed Development will strengthen the employment base and promote an energy hub around the Energy Park. A drainage strategy for the site has been developed which includes measures to ensure that the Proposed Development will not increase flood risk and can operate safely in the event of a flood. Surface water run-off will be no greater than currently experienced by the vacant site. Assessments of the effects of the Proposed Development on a number of environmental topic areas are presented in Chapters 5-15 of the ES. Although outside the urban and village confines, the converter station and substation site at the former Richborough Power Station is an allocated brownfield site adjacent to the proposed Richborough Energy Park. The proposed converter station and substation will be similar in scale and nature to surrounding development including the Thanet Offshore Wind Farm Substation. The scale of the converter station buildings will be broken up by treatment to the cladding so that there is a gradual fading of colour from the bottom to the top. A recessive green colour is proposed, lightening gradually to off-white on the upper elevations which will be seen against the sky. This will reduce the apparent bulk of each converter station building in general views. The substation, lower in height than the converter station will be finished in a recessive green cladding to match the lower sections of the converter station. Thanet Core Strategy – Preferred Options Consultation Document Policy Policy Summary Assessment of Policy DCS23: • Incorporate where practical a high degree of permeability for pedestrians and cyclists and also consider access for public transport and provide safe and satisfactory means of pedestrian and vehicle access including provision for disabled access; • Retain and enhance features that contribute to biodiversity and the quality of the local environment including open spaces, gaps in development, mature trees, and other vegetation • Incorporate new landscaping as an integral element, including, where appropriate, wildlife habitats, wildlife corridors and initiatives for their long term management; • Incorporate measures to prevent crime and disorder, promote public safety and security and the perception of public safety and security; • Incorporate, where practical and appropriate, high quality integrated public art which is relevant to the site and locality; • Provide for discreetly located service areas for development including cycle stores, clothes drying facilities and refuse disposal/dustbin storage; • Incorporate sustainable drainage systems. • Incorporate challenging sustainable design and construction standards contributing towards achieving zero carbon emissions, improving water efficiency and minimizing waste. Proposals to improve energy efficiency including decentralised and renewable or low carbon energy developments will be supported unless they result in unacceptable environmental impact. 68 The site will be subject to a landscaping scheme proposed for the Richborough Energy Park with provision for its implementation separate from the proposed Energy Park if necessary. Additional native landscaping is proposed at the south western elevation as part of this planning application. The converter station and substation will require a maximum of 6 personnel on site per day. The site is adjacent to the Viking Coastal Trail (Sustrans Route 15) suitable for access on foot or by bicycle. Cycle parking is proposed on site. There will be 6 spaces for bicycles included within the converter station and substation site. A security fence will be installed surrounding the converter station and substation site to prevent unauthorised access to the converter station and substation. Sustainable Drainage System (SUDS) has been designed for the converter station and substation site. Sustainable design and construction standards have been considered at a high level and are detailed in the accompanying BREEAM assessment. Details with regards sustainable design and construction will be considered further (should planning permission be granted) when a contractor is appointed. The Project will allow electricity exchange between Belgium and the UK which will support energy efficiency and low carbon generation from renewable sources by helping to manage fluctuations in generation and demand. 4.41 The cables route from the BayPoint sports complex to the proposed converter station and substation site and the southern corner of the site falls within the planning control of Dover District Council. Development control decisions in Dover District are based on saved policies from the 2002 Dover District Local Plan and the 2010 Dover District Core Strategy. Saved planning policies from the Dover District Local Plan and the Dover District Core Strategy have been assessed against the Proposed Development in Tables 4.3 and 4.4 respectively. Table 4.3: Relevant Saved Policies from Dover District Local Plan Dover District Local Plan Adopted 2002 - Saved Policies Policy Policy Summary Assessment of Policy AS14: Area Specific Policy Within the Ramsgate Road area, shown on Sheet 2 and the Sandwich Inset of the Proposals Map, the Council will permit B1/B2/B8 employment uses on the proposals map: All development provides for the visual upgrading of the A256/Ramsgate Road, including structural landscaping at the main site boundaries and a 10m landscape buffer zone fronting the A256/Ramsgate Road; Any new buildings or extensions along the A256 are low rise; A survey and evaluation is carried out to determine the extent of contamination and remedial measures proposed to ensure that the development of any site does note post a risk to human health or adjacent nature conservation interests; Development does not increase the risk of flooding; and Provision is made for an archaeological evaluation in advance of any planning decision and for the consequent appropriate level of archaeological mitigation in accordance with the Historic Environment policies of this plan. 69 This policy provides criteria to enable, in principle, the development of land for B1, B2 and B8 uses. The criteria do not apply to other proposed land uses, nor does the policy preclude other such land uses from being granted planning permission in principle. However, notwithstanding the above, the Proposed Development is in accordance with this policy for the following reasons: The proposed converter station and substation site is not immediately along the A256 or within the 10m landscape buffer zone. The proposed onshore underground cable will be installed using HDD which will not sterilise the 10m landscape buffer zone. The site will be subject to a landscaping scheme proposed for the Richborough Energy Park with provision for its implementation separate from the proposed Energy Park if necessary. Additional native landscaping is proposed at the south western elevation as part of this planning application An assessment of ground conditions and hydrological, ecological and archaeological effects of the Proposed Development is detailed at Chapters 7, 8 and 9 of the ES respectively. No significant adverse effects are anticipated. Dover District Local Plan Adopted 2002 - Saved Policies Policy Policy Summary Assessment of Policy Policy TR12: Land safeguarded at Richborough Power Station for CTRL (Channel Tunnel Rail Link) development Land at the former Richborough Power Station was safeguarded because it provides access to sidings which were needed for storage of ballast during the construction of the CTRL. The Directions have not yet been withdrawn although the CTRL is complete; the Proposed Development is not anticipated to cause any substantial harm to Policy TR12. Table 4.4: Relevant Policies from Dover District Core Strategy Dover District Core Strategy Adopted 2010 Policy Policy Summary Assessment of Policy Policy CP 7: Green Infrastructure Network (relevant to part of the underground cable connection) During construction, the Viking Trail Sustrans Route, the Thanet Coastal Path Long Distance Route (part of the Green Infrastructure Network) and some minor informal paths will need to be temporarily diverted. Following completion of the works all routes will be reinstated and reopened for use. Policy DM 15: Countryside Protection The integrity of the existing network of green infrastructure will be protected and enhanced through the lifetime of the Core Strategy. Planning permission for development that would harm the network will only be granted if it can incorporate measures that avoid the harm arising or sufficiently mitigate its effects. Proposals that would introduce additional pressure on the existing and proposed Green Infrastructure Network will only be permitted if they incorporate quantitative and qualitative measures, as appropriate, sufficient to address that pressure. Development that would result in the loss of, or adversely affect the character or appearance of the countryside will only be permitted if it is: In accordance with allocations made in Development Plan Documents, or Justified by the needs of agriculture; or Justified by a need to sustain the rural economy or a rural community; It cannot be accommodated elsewhere; and It does not result in the loss of ecological habitats. Provided that measures are 70 Although outside the defined urban area, the converter station and substation will be built on derelict brownfield land located adjacent to the proposed Richborough Energy Park and will not impact on unspoilt countryside. The layout of electrical equipment is designed for optimum efficiency and requires a large site. As the converter station will allow the exchange of electricity between the UK and Belgium, the site is required to be located close to the coast. Potential effects on ecology and landscape character are discussed at Chapters 8 and 10 of the ES respectively. No significant Dover District Core Strategy Adopted 2010 Policy Policy Summary Policy DM16: Landscape Character Policy DM 25: Open Space incorporated to reduce, as far as practicable, any harmful effects on countryside character. Development that would harm the character of the landscape, as identified through the process of landscape character assessment will only be permitted if: It is in accordance with allocations made in Development Plan Documents and incorporates any necessary avoidance and mitigation measures; or It can be sited to avoid or reduce the harm and/or incorporate design measures to mitigate the impacts to an acceptable level. Proposals for development that would result in the loss of open space will not be permitted unless: i. there is no identified qualitative or quantitative deficiency in public open space in terms of outdoor sports sites, children's play space or informal open space; or ii. where there is such a deficiency the site is incapable of contributing to making it good; or iii. where there is such a deficiency the site is capable of contributing to making it good, a replacement area with at least the same qualities and equivalent community benefit, including ease of access, can be made available; or iv. in the case of a school site the development is for educational purposes; or v. in the case of small-scale development it is ancillary to the enjoyment of the open space; and vi. in all cases except point 2, the site has no overriding visual amenity interest, environmental role, cultural importance or nature conservation value. Assessment of Policy adverse effects are anticipated. The substation and converter station development will be consistent with the character of nearby development and with the proposed Richborough Energy Park and its landscape scheme. An assessment of the Proposed Development on landscape and views is presented at Chapter 10 of the ES. The onshore underground cable route in Dover District crosses the BayPoint sports complex which is allocated in the 2002 Local Plan as Open Space. Effects would be temporary and the installation of the onshore underground cables will not result in the long term loss of open space. An assessment of the impacts of the Proposed Development on land use is detailed at Chapter 5 of the ES. Kent Minerals and Waste Plan 1998 Saved Policies 4.42 Kent County Council produces Minerals and Waste Plans which set out policies for managing minerals and waste in the County. Policies from the Kent Minerals and Waste Plan that relate to the Proposed Development are set out in Table 4.5 below. 71 Table 4.5: Kent Waste Local Plan 1998 Saved Policies Kent Waste Local Plan 1998 – Saved Policies Policy Policy Summary Assessment of Policy W7 – Reuse W9 – Waste separation and transfer W11 – Waste to Energy 4.43 The following locations are considered to be suitable in principle for proposals to prepare Category A waste for re-use: For permanent development - Richborough The following locations are considered to be suitable in principle for proposals for waste separation and transfer: xviii Richborough (N) The following locations are considered to be suitable in principle for proposals for a waste to energy plant: iv The Stour at Richborough. The former Richborough Power Station site was identified as a site which could be used for the reuse of demolition waste, was one of a number of sites considered suitable in principle, but was not reserved exclusively for this type of development. Land is rarely allocated in development plans for electricity infrastructure. The Proposed Development is similar in type and scale to waste uses and is comfortably located on the site and in the context of its surroundings. The Proposed Development is not in full accordance with these policies, comprising a particularly bespoke sui generis form of development. However, it is not considered to cause substantial harm to Policies W7, W9 and W11. Kent County Council is in the process of preparing a Core Strategy, which will establish policies for the future development of Minerals and Waste sites in the Kent County. The Strategy and Policy Directions Consultation, although not yet adopted, is a material consideration in determining planning applications although will carry less weighting than adopted development plan documents and saved policies. Planning policies from the Strategy and Policy Directions consultation have been assessed in Table 4.6 below. 72 Table 4.6: Kent County Council Minerals and Waste Core Strategy: Strategy and Policy Directions 2011 Kent County Council Minerals and Waste Core Strategy – Strategy and Policy Directions Consultation, May 2011 Option Policy Summary Assessment of Policy 11B – Possible Options for Strategic Waste Sites The former Richborough Power Station has been identified as a site that could accommodate a large scale Mechanical Biological Treatment (MBT) plant which could receive household and non-household waste for treatment by rail or water. The former Richborough Power Station site was one of a number of sites considered suitable in principle, but was not reserved exclusively for this type of development. A Waste biomass fuel can also be delivered to a power/Combined Heat and Power (CHP) station from the site by rail or water. The Proposed Development is not in full accordance with these policies, comprising a particularly bespoke sui generis form of development. However, it is not considered to cause substantial harm to Policy 11B. Land is rarely allocated in development plans for electricity infrastructure. The Proposed Development is similar in type and scale to waste uses and is comfortably located on the site and in the context of its surroundings. Conclusions 4.44 The Proposed Development will allow the transfer of electrical power between the high voltage grid systems of Belgium and the United Kingdom. The power would be able to flow in either direction at different times, depending on the supply and demand in each country. The Project contributes to a low carbon future by allowing better use of renewable energy when resources are available and the ability to trade electricity over the link will contribute to a downward pressure on wholesale electrcity prices. The Project is consistent with EU and UK policy. 4.45 The site of the proposed converter station and substation is at the former Richborough Power Station adjacent to Thanet Offshore Wind Farm substation and the proposed Richborough Energy Park. The proposed converter station and substation site is located on derelict brownfield land part of which is currently occupied by the frame of the former turbine hall of the defunct Richborough Power Station. Development plans seldom make allocations for electricity infrastructure such as converter stations or substations and these infrastructure assets are classified as sui-generis development. 4.46 In considering where developments of this nature could be located, developers typically seek locations where the existing character shows similarity with those of the development, such as where there are existing industrial uses which are unlikely to be adversely affected by such development. The location of the proposed converter station and substation in part of the former Richborough Power Station site is consistent with this approach and consistent with proposals for the development of the Richborough Energy Park. 4.47 The site is off the A256 which offers excellent access to the trunk road network and the M2 motorway for construction traffic and deliveries. The operational site can be 73 accessed from sustainable transport routes such as the Viking Coastal Trail (Sustrans Route 15). The levels of traffic generated during the construction phase of the development are unlikely to have any significant adverse effects on the local highway network especially with the increased carrying capacity following the completion of the East Kent Access Phase 2. 4.48 The subsea and onshore underground cables can be installed without causing long term disturbance or harm to land and would result in benefits to habitats from the creation of new chalk grassland. No significant adverse environmental effects are anticipated regarding contaminated land, the generation of noise or from electric and magnetic fields. The ES provides an assessment of likely environmental effects together with proposed mitigation measures to avoid or reduce potential effects. 4.49 The proposed substation and converter station on the former Richborough Power Station site are within 1km of a number of internationally and nationally designated nature conservation areas. An ecological assessment of the Proposed Development has been completed and the findings are presented in Chapter 8 of the ES and ES Appendix 8.9. No significant adverse effects are predicted. 4.50 Although the development is not in full accordance with the development plan, comprising a particularly bespoke sui generis form of development, it does not conflict with the policies and aims of the development plan. 74 75 76 5.0 LAND USE Introduction 5.1 This chapter describes the existing land use at the proposed converter station and substation site and along the onshore underground cables route and adjacent areas. It considers the potential permanent and temporary effects that the Proposed Development (i.e. the UK onshore infrastructure of the Nemo Link - see Chapter 2, Project Description) may have on existing and future land use and identifies mitigation measures that will be incorporated into the construction and operation of the development to avoid, reduce or offset potential adverse effects or enhance potential beneficial effects on land use. 5.2 Potential effects on land use are interrelated with Archaeology and Cultural Heritage (Chapter 9), Landscape and Views (Chapter 10), Traffic and Transport (Chapter 11), Noise and Vibration (Chapter 12) and Air Quality (Chapter 13). 5.3 Consideration of land use planning policies relevant to this planning application is presented in Chapter 4 (Planning Context). Method 5.4 The geographic scope of the assessment is based on the boundary of the converter station and substation site and the route of the onshore underground cables to which this planning application relates. 5.5 Baseline conditions were established by a desk-based assessment (DBA) of published information and a site walkover survey. The DBA included the following: Review of Ordnance Survey Mapping and aerial photography to establish existing land use within the boundary of the proposed converter station and substation site and the onshore underground cables route; Review of land use planning policy to identify future development and planning allocations in or close to the development area; and Review of planning policy to identify walking and cycling routes and other Rights of Way within the development area. 5.6 The findings of the DBA were supplemented by a walkover survey undertaken in September 2011 which focused on the converter station and substation site, the route of the onshore underground cables and land immediately adjacent. The walkover survey was used to verify and supplement the findings of the DBA. Further observations have been made from subsequent site visits to the converter station and substation site and the cable route. Discussions have also been held with owners of land which would be affected by the Proposed Development. 5.7 Potential effects on land use resulting from the installation and operation of the onshore underground cables and construction and operation of the proposed converter station and substation broadly fall into two categories: Land-take: Temporary or permanent requirement for land currently used for other purposes; and 77 Disturbance: Disturbance to existing or future land uses or activities including reduced access. 5.8 There is no existing guidance directly applicable to the assessment of the effects of electrical infrastructure on land use. A qualitative approach to the assessment has been taken based on professional judgement and discussion with landowners. The assessment evaluates relative importance of other effects on land use related to the value of existing uses and whether or not these can continue. 5.9 Effects were assessed by predicting changes in baseline conditions that would be caused by the construction and operation of the converter station and substation and the installation and operation of the onshore underground cables. 5.10 Effects have been assessed as significant or not significant, adverse or beneficial in relation to whether they are temporary or permanent. Minor effects are those of very small magnitude and those considered to be temporary, short-term, reversible effects which would not affect an on-going land use. Minor effects are manageable and are not significant. An effect which disrupts a land use permanently or for a long period of time may be judged to be a major or moderate effect, depending on the scale of effect and the extent of disruption. Moderate and major effects would be significant. Existing Environment Proposed Converter Station and Substation Site and its Surrounds 5.11 The converter station and substation are proposed to be constructed on the site of the former Richborough power station which is approximately 4 kilometres (km) southwest of Ramsgate, 3.5km north of the town of Sandwich and 1.6km inland from the east Kent coastline. The power Station was constructed in the late 1950s and early 1960s and it began production in 1962 as a 342 megawatt (MW) coal fired station, using coal from the Kent coalfields. It subsequently burnt Orimulsion as a fuel before its closure. In 1989 a 1MW wind turbine was constructed on the site to aid the research and development of wind energy technology. Thanet Offshore Wind Farm is connected to a substation which is also present on site. 5.12 The power station closed in 1996 and the decommissioning, which included a programme of asbestos removal and partial demolition process, was completed in 2000, leaving the largest structures including the cooling towers and stack. In 2012, Thanet District Council (TDC) and Dover District Council (DDC) approved a planning application for the demolition of the remaining above ground buildings with the exception of the frame of the former turbine hall. Demolition took place in March 2012. The site is now derelict brownfield land and is part of wider future proposals for the development of Richborough Energy Park. The steel frame of the turbine hall has been left in situ and it is proposed that this would be used as part of the converter station building. 5.13 The River Stour runs along the south west boundary of the power station site. To the west of the river, the land is predominantly agricultural and is currently used as grazing pasture. Immediately north of the power station site is a compartment of Sandwich Bay to Hacklinge Marshes SSSI and beyond this, a recently constructed 78 solar farm, Weatherlees Hill Wastewater Treatment Works, an anaerobic digester currently under construction and further agricultural land. 5.14 The A256 (Ramsgate Road), southeast of the former power station, separates the proposed converter station and substation site from the Kent coast and Pegwell Bay. Pegwell Bay is part of the larger Sandwich Bay which is of international nature conservation interest. The section of A256 which runs past the entrance to the former power station site has recently been widened to create a dual carriageway as part of the East Kent Phase 2 Access Scheme. 5.15 The road improvement scheme has involved constructing a new bypass which connects to the widened A256 at a new roundabout approximately 200m northeast of the Power Station site. The bypass bisects arable farmland as it passes north to connect to the A299 and it separates the Power Station site from Stonelees Golf Course and St. Augustine’s Golf Course to the north of the site. Stonelees Golf Course has a driving range and three courses and is open to the general public whilst St. Augustine’s Golf Course is an 18 hole members only course. The A256 Sandwich Road forms the eastern boundary to Stonelees and St Augustine’s Golf Courses and separates these areas from the coast. 5.16 In addition to the golf courses, BayPoint sports complex and Pegwell Bay Country Park also provide recreational areas. These are on the coastal side of the A256 and the onshore underground cables route will pass through these sites. The sports complex, approximately 190m northeast of the power station site provides corporate and private events facilities and a range of sports facilities including football pitches, tennis courts, gymnasium, squash courts and exercise studios. Pegwell Bay Country Park is recorded on the Environment Agency website as an historic landfill. The site was licensed for inert material although there have been anecdotal comments that there may potentially be contaminated waste, possibly from the former Richborough power station, or putrescible wastes. 5.17 Pegwell Bay is used by visitors including dog walkers, wildlife enthusiasts and bait diggers. Facilities within the Country Park include a large car park, a picnic area and a toilet block. The main path through the Country Park is close to the verge of the A256 Sandwich Road and this is also part of a long distance cycle track called ‘the Viking Trail’. The Thanet Coastal Path long distance footpath also runs through the Country Park. 5.18 Further tracks on the salt marsh between the Country Park and Pegwell Bay Service Station have been created by walkers, bait diggers and other recreational users of the mudflats. 5.19 Stonelees Nature Reserve, currently grazed by cattle, separates the sports complex from Pegwell Bay Country Park. The Reserve is owned and managed by Kent Wildlife Trust and is used for walking and enjoying scenery and nature. 5.20 The nearest residential dwellings to the former power station site are four detached properties on Ebbsfleet Lane approximately 350m to the north. Cliffs End village is the closest settlement to the proposed converter station and substation site, approximately 2.5km north east. 79 Onshore Underground Cable Route 5.21 The HVDC onshore underground cables will run from the landfall on the coastal side of the existing cycle track which runs parallel to the A256 Sandwich Road, through Pegwell Bay Country Park, then into Stonelees Nature Reserve and BayPoint sports complex. From the sports complex, the cables will be routed by horizontal directional drilling (HDD) beneath the A256, Minster Stream, and a compartment of Sandwich Bay to Hacklinge Marshes SSSI (which is designated for the botanical interest of its ditches). The cables will have no direct or indirect effects on any of these features and will surface and terminate within the former power station site adjacent to the converter station (Figure 2.1). The overall length of the cable route is approximately 2.3km. 5.22 The landfall site, close to Pegwell Bay Service Station, is within Sandwich Bay Special Area of Conservation (SAC), Sandwich Bay Special Protection Area (SPA) and Ramsar site, Sandwich Bay to Hacklinge Marshes Site of Special Scientific Interest (SSSI) and Sandwich and Pegwell Bay National Nature Reserve (NNR). The majority of the cable route is in the administrative district of Thanet District Council. A small part of the cables route and the entrance to the former power station site is in Dover District Council’s administrative boundary. Land Use Allocations 5.23 Kent Waste Local Plan 1998 has a number of saved policies that allocate the former Richborough power station site as being suitable in principle for waste proposals. Policy W7 identifies it as a site which can be used for the reuse of demolition waste; Policy W9 names the site as suitable in principle for waste separation and transfer and Policy W11 states that the site is suitable for a waste to energy plant. 5.24 Parts of the former Richborough power station site are to be developed as energyrelated infrastructure as part of the wider Richborough Energy Park development. Two planning applications were submitted by Richborough A Ltd in December 2012: the first is for a gas-fired ‘peaking’ plant immediately south of the proposed converter station and substation site; the second is for a road system around the perimeter of the proposed Energy Park off the A256 roundabout - this will serve as the access from the local highway network to the proposed converter station and substation forming this planning application. Both the external road and the peaking plant are expected to be operational by 2014 prior to the commencement of site enabling works for the proposed converter station and substation site. Additional energy-related proposals may come forward for other parts of the Richborough Energy Park; however, at present, such proposals are unknown and as such sufficient details cannot be provided. 80 Prediction and Assessment of Potential Impacts Construction 5.25 Construction of the proposed converter station and substation and installation of the onshore underground cables would result in temporary effects as described below. 5.26 Land will be used during construction for compounds, the laydown area, temporary access roads, and for the installation of onshore underground cables and associated joint pits. A working width will be required for cables installation of between 5m and 10m. HDD between BayPoint sports complex and the Richborough power station site will require a temporary launch pit working area where the main driving of the drilling equipment will be undertaken and a temporary receptor pit working area which will receive the drill driven from the launch pit. 5.27 The launch pit will be on the former Richborough power station site and will comprise of a working area approximately of 30m x 50m. The receptor pit on land at BayPoint sports complex will be approximately 30m x 50m. Access to the launch pit and the receptor pit working areas will be from the existing entrances along the A256. 5.28 HDD from the sports complex will avoid surface disturbance of a newly constructed roundabout on the A256, Minster Stream and a compartment of Hacklinge Marshes to Sandwich Bay SSSI. 5.29 Effects on land use during construction will be highly localised and temporary so will be of minor significance. Where open space and land which is available for recreation and walking is disturbed, there will be alternative routes available and the absence of any facility will be short term and reversed after reinstatement of land. 5.30 An increase in traffic from workers and materials arriving on site will result in some disruption to road users, which is addressed in Chapter 11 Traffic and Transport. 5.31 Grazing within Stonelees Nature Reserve may also be temporarily restricted. 5.32 During construction of the TJP and installation of marine cables to low water, part of the foreshore will have to be closed to ensure public safety making a small area used for bait digging and walking temporarily unavailable. 5.33 Effects on disturbance during construction will be within highly localised areas and temporary, so will be of minor significance. Operation 5.34 The converter station and substation will result in the permanent loss of approximately 8 hectares of derelict brownfield land. The converter station will occupy the footprint of the existing turbine hall and adjacent land. However, there is no defined on-going land use; the site and the surrounding land is part of the Richborough Energy Park proposals. The Proposed Development would make a positive contribution as it would result in the re-use of derelict land contributing to national and local policy sustainability objectives. There would be no adverse effects from the loss of the derelict land to the Proposed Development. 81 5.35 On completion of the cables installation, the present land uses above the cables will resume as previously. A permanent 5m cable easement will be required and this also will not affect current land use; however, there may be temporary effects on land use associated any required onshore cable repairs or maintenance. The onshore underground cables have been routed so that they will not prevent any future development proposals within Pegwell Bay Country Park related to recreation and education. However, there will be restrictions on planting above the cables route. 5.36 No significant adverse effects on land use on and around the cable route are anticipated. Mitigation 5.37 The absence of potentially significant effects indicates that no specific mitigation is required. The following measures will be put in place as part of the overall working methods to ensure that effects on land use are acceptable: The working width associated with cables installation will be kept to a minimum to reduce disturbance to adjacent land; Temporary working areas and access roads will be fully reinstated following construction; The laydown area will be reinstated to its current standard and it will be made available for future use by the developers of Richborough Energy Park; Access to the Viking Trail and Thanet Coastal Path will be retained where possible during the construction period. Where there is a Health and Safety requirement to prevent or reduce access, appropriately signed diversions will be agreed and put in place; Any public access restrictions will be minimised as much as possible and limited only to periods of major construction activity such as earthworks; Temporary signage advising visitors of construction activities will be erected. This will include signs within the car park of Pegwell Bay Country Park to ensure that visitors are aware of construction activities being undertaken; Contractors will prepare a Construction Environmental Management Plan (CEMP) prior to the commencement of construction. This will include measures to ensure good construction practices are adopted on site; Measures to ensure construction activities do not result in any disturbance to land users surrounding the former power station site will be developed in consultation with the site owners and operators. This will include on-going communication and liaison, measures to address site access and movement and working hours; A Transport Management Plan (TMP) will be prepared and implemented prior to the commencement of construction activities; In order to minimise construction disturbance, working hours during periods where recreational activity is greatest (i.e. evenings and weekends) will be limited as much as possible; and Measures to control dust and noise will be adopted during the construction period in order to reduce the potential for disturbance and indirect effects on land use. 82 Residual Impacts 5.38 The assessment of effects considered the above measures to be in place and there is no change to the assessment. Cumulative Impacts 5.39 Potential cumulative effects on land use from the onshore elements of the Nemo Link in combination with other components of the Project (i.e. UK, French and Belgian subsea cables and Belgian onshore infrastructure) are described in Chapter 16. 5.40 Potential cumulative effects of the Nemo Link UK onshore infrastructure in combination with the grid connection required to facilitate the operation of the Nemo Link are described in Chapter 17. 5.41 There is little scope for cumulative operational effects on land use arising from the UK onshore elements of the Nemo Link in combination with unrelated planned developments described in Table 1.2, Chapter 1. The proposed use and change of use of land for other development detailed in Table 1.2 is not considered to result in any significant cumulative effects in terms of overall land use. 5.42 There is the potential for temporary cumulative effects on land use should the construction of the Proposed Development overlap with the proposed external access road and the peaking plant. Such effects would be restricted to the land at the former Richborough power station site through the establishment and use of working compounds and would be highly unlikely to result in disturbance to publicly accessible land. 5.43 An increase in traffic from workers and materials arriving on site will result in some disruption to road users, which is addressed in Chapter 11 Traffic and Transport. 5.44 Any potential effects on land use and disturbance during construction will be highly localised and temporary so will be of minor significance. 83 84 6.0 GROUND CONDITIONS AND CONTAMINATION Introduction 6.1 This chapter reviews the potential impacts of the Proposed Development i.e. the UK onshore elements of the Nemo Link (see Chapter 2 – Project Description) with reference to soils, geology and hydrogeology. The assessment is made primarily on the effect of disturbance on the ground by construction activities and potential contamination that may arise as a result of cables installation and construction of the converter station and substation. Potential sources of ground contamination within the development site are examined to determine the likelihood of significant levels of contamination affecting the development. 6.2 The chapter provides a review of historical studies and includes information collected from the following elements: 6.3 Visual findings from a walkover survey; Desk study, including site history, geology, hydrogeology and hydrology; and Search of environmental information using Landmark Envirocheck. Best practice techniques to minimise the environmental impacts of construction on contamination risk to humans and the environment are well developed and are outlined within the chapter. In addition, site specific mitigation measures are described where generic, best practice mitigation measures are not suitable. Suitable mitigation techniques to minimise contamination during operation are also proposed. Legislation and Planning Policy Context 6.4 Relevant legislation, planning policy and guidance is summarised in Tables 6.1 to 6.3. Relevant Pollution Prevention Guidelines issued by the Environment Agency are outlined in Table 6.4. Table 6.1: National Legislation and Policy Context Policy/Legislation National Planning Policy Framework The Water Framework Directive 2000/60/EC Environmental Protection Act:1990 Part IIA Key Provisions Specifies planning policies to help achieve sustainable development, the protection and enhancement of geological conservation interests and soils. The 1980 Groundwater Directive 80/68/EEC and the 2006 Groundwater Daughter Directive 2006/118/EC of the WFD are the main European legislation in place to protect groundwater. Requires all Local Authorities to inspect their areas for contaminated land, and produce a strategy outlining how they approach this task. Under s.78B(1) the Council is required to maintain a Public Register of Contaminated Land. 85 Table 6.2: Regional Legislation and Policy Context Policy/Legislation The South East Plan (May 2009) Regional Spatial Strategy for the South East of England Key Provisions To improve and conserve the region’s environment by ensuring the protection and enhancement of the region’s environmental assets, including the built and historic environment, landscape and water. Table 6.3: Local Strategies and Guidance Policy/Legislation Thanet District Council Contaminated Land Strategy Dover District Council Contaminated Land Developers Guide Key Provisions It is the developer’s responsibility to ensure that the development is safe and that the Local Planning Authority is satisfied that any risks from potential contamination have been adequately addressed. To this end, the developer should carry out a satisfactory assessment of the Site, considering the potential for contamination, including a ground investigation, where necessary, to confirm the level and extent of any contamination. Where development of contaminated land, or land suspected of being contaminated, is proposed, the Council will require the submission of details of site investigations and proposed remedial action. Planning permission will be refused unless an appropriate and acceptable level of remedial action can be achieved. Table 6.4: Pollution Prevention Guidelines Guidance Control of Water Pollution from Construction Sites (2001) PPG1: General Guidance to the Prevention of Pollution (2001) PPG6: Working at Construction and Demolition Sites (2010) PPG21: Pollution Incident Response Planning (2009) Key Provisions Provides practical help and guidance for consultants and contractors on how to plan and manage construction projects to control water pollution. Provides an introduction to a series of Pollution Prevention Guidance notes (PPGs), which provide practical advice to help developers and contractors avoid causing pollution, minimise waste and comply with the law. Provides detailed guidance on construction and demolition activities, including requirements for discharges of water from dewatering operations to controlled waters and foul sewers, and the safe discharge of silt-laden water. Provides guidance on the development of a pollution incident response plan and includes a template plan. 86 Method 6.5 Full details on ground conditions associated with the development area are provided in the Phase 1 Environmental Report in Appendix 6.1. The Report contains information from an Envirocheck Report, a site inspection carried out on 6th April 2012 and information from Thanet District Council and Dover District Council Environmental Health Departments and the Environment Agency. The Phase 1 Report contains information on the underlying ground conditions available from previous site investigation reports including: A contaminated land site assessment report relating to land adjacent to the cable landfall at the northern end of Pegwell Bay, (Royal Haskoning Ltd, June 2007); A geoenvironmental site investigation report covering the full extent of the former Richborough Power Station (URS Corporation Ltd, January 2009); and A detailed quantitative risk assessment for Richborough Power Station (URS Corporation Ltd, June 2009). 6.6 The Phase 1 study was undertaken to meet the objectives of a preliminary (Phase 1) investigation, as defined by BS 10175:2011 ’Code of Practice for the Investigation of Potentially Contaminated Sites’. The Phase 1 report adopts the technical approach presented in Contaminated Land Report 11 ’Model Procedures for the Management of Land Contamination’ (Environment Agency 2004) for applying a risk management process when dealing with land affected by contamination. 6.7 The desk study has included the development of a Conceptual Site Model (CSM) providing a depiction of likely sources of contamination, pathways and receptors, resulting in the identification of potential pollutant linkages. 6.8 The potential effects in relation to land quality and geology were assessed using guidelines given in CIRIA document 552 ‘Contaminated Land Risk Assessment, A Guide to Good Practice’. CIRIA is the construction industry research and information association. 6.9 This chapter summarises information in the Phase 1 Environmental Report included in Appendix 6.1. No intrusive investigations of land within the application site have been undertaken as part of the assessment. These will be undertaken prior to construction. Assessment of Significance 6.10 Effects were assessed by predicting changes in baseline conditions that would be caused by the construction and operation of the converter station and substation site and the installation of the onshore underground cables and subsea cables between low water and the Transition Joint Pit (TJP). A qualitative approach to the assessment has been taken which is based on professional judgement and experience from similar developments on sites with comparable environmental sensitivity. 6.11 The sensitivity of receptors has been determined using criteria in Table 6.5. 87 Table 6.5: Method for Determining Sensitivity/Importance of the Environment Receptor Sensitivity Description High Designated sites, such as geological and groundwater SSSIs. Regionally important geological and geomorphological sites (RIGS) and geological conservation review sites (GCRs) Areas of critical topography, including steep slopes and historic landslip locations Areas of existing mineral extraction and areas designated in Local Authority Plans as preferred areas for mineral extraction Inner groundwater source protection zones (SPZ 1) Areas of high groundwater vulnerability Principal aquifers Areas of known/confirmed contaminated land/groundwater Rivers with a Grade A water classification Areas of flood risk Neighbouring properties and residents Medium Low 6.12 Typical rural topography Areas of search for minerals Outer groundwater source protection zones and total catchment areas (SPZ 2 and SPZ 3) Secondary aquifers Areas with intermediate groundwater vulnerability Intertidal marine environment Rivers with a Grade B water classification. Industrial site topography Areas without known mineral resources Rivers with a Grade C or D water classification Unproductive strata Areas with low groundwater vulnerability. The generic criteria for determining levels of magnitude of change on the physical environment are indicated in Table 6.6. A major magnitude of change would be one that is likely to cause a direct adverse permanent or long-term effect on the integrity or value of the receptor, whereas a small change would be one that is likely to have a minor adverse effect on a receptor, but from which a recovery is expected in the short term. 88 Table 6.6: Magnitude of Effect Magnitude Definition Major Total loss or substantial alteration to key elements or features of the baseline (pre-development) conditions such that the postdevelopment character, composition or attributes will be fundamentally changed. Moderate Minor Negligible 6.13 Loss or alteration to one or more key elements/features of the baseline conditions such that post development character, composition or attributes of the baseline will be materially changed. A minor shift away from baseline conditions. Change arising from the loss or alteration will be discernible but not material. The underlying character, composition or attributes of the baseline condition will be similar to the pre-development circumstances or situation. Very little change from baseline conditions. Change barely distinguishable, approximating to a 'no change' situation. The categories used when classifying the overall significance of potential effects by considering sensitivity of receptor and magnitude of effect are shown in Table 6.7. Table 6.7: Effect Significance Matrix Magnitude 6.14 High Medium Low Major Major Moderate Minor Moderate Moderate Moderate Minor Minor Minor Minor Negligible Negligible Minor Negligible Negligible/None The significance of effect can be described as follows: 6.15 Sensitivity of Receptor Minor: Slight, very short or highly localised; Moderate: Limited effect in terms of extent, duration or magnitude; or Major: Considerable effect in terms of extent, duration or magnitude or more than local significant or in breach of recognised acceptability, legislation or policy or standards. The nature of an effect can be classified as adverse, negligible (or no effect), or beneficial: Adverse: Classifications of significance indicate disadvantageous or negative effects to an environmental receptor, which may be of Minor, Moderate, or Major significance; 89 6.16 Negligible/None: Classifications of significance indicate imperceptible effects to an environmental receptor; Beneficial: Classifications of significance indicate advantageous or positive effects to an environmental receptor, which may be of Minor, Moderate or Major significance. Timescales associated with effects are categorised as follows: Short to Medium Term: Timescales where the effect is temporary and last for the period of the construction works or less; and Long Term: Timescales where the effect remains for a substantial time, perhaps permanently, after construction even though the activity that created it may be ceased some time ago. Existing Environment Site Description 6.17 From low water to the TJP the subsea cables route runs across tidal mudflats. From close to the TJP, the onshore underground cables route runs parallel to the seaward side of the Sandwich Road, initially through reclaimed land associated with Pegwell Bay foreshore and then through an area of historical landfilling comprising Pegwell Bay Country Park. In the Country Park there are a number of gas monitoring wells which indicate the presence of underlying landfill materials. The onshore underground cables route then runs through Stonelees Nature Reserve and into BayPoint sports complex from where the cables will be installed by horizontal directional drilling (HDD) beneath the A256, Minster Stream, and a compartment of Sandwich Bay to Hacklinge Marshes SSSI. The cables will terminate in the converter station site (Figure 2.2). Habitats along the cable route and at the proposed converter station and substation site are described in Chapter 7 (Ecology) which gives a description of present ground surfaces. 6.18 The proposed converter station and substation will be constructed on part of the site of the former Richborough Power Station which is currently a derelict brownfield site. 6.19 The topography of the development area is predominantly flat and shows very limited variation. Ground levels are generally 2-3m above ordnance datum (AOD) across the Pegwell Bay foreshore, 3-6m AOD across the remainder of the cables route and 2-4m AOD across the site of the former Richborough power station. 6.20 A number of sensitive land uses are present in the vicinity of the application boundary including: Thanet Coast and Sandwich Bay Special Protection Area (SPA)/Ramsar Site; Sandwich Bay Special Area of Conservation(SAC); Thanet Coast SAC; Sandwich Bay to Hacklinge Marshes Site of Special Scientific Interest; (SSSI); and Sandwich and Pegwell Bay National Nature Reserve (NNR). 90 6.21 Further details on the above sites are contained in Chapter 8, Ecology. 6.22 The nearest residential dwellings to the former power station site are four detached properties on Ebbsfleet Lane, approximately 340m to the north. Cliffs End village is the closest settlement to the proposed converter station and substation site, approximately 2km to the northeast. 6.23 The A256 (Ramsgate Road), southeast of the power station, separates the proposed converter and substation site from the Kent coast and Pegwell Bay and Sandwich Bay. The section of A256 which runs past the entrance to the former power station site, has been widened to create a dual carriageway as part of the East Kent Phase 2 Access Scheme. The road improvement scheme has also involved constructing a new bypass which connects to the widened A256 at a new roundabout approximately 200m northeast of the former Richborough Power Station site. The bypass bisects arable farmland as it passes north to connect to the A299 and it separates the former power station site from Stonelees Golf Course and St.Augustine’s Golf Course to the north of the Site. 6.24 A number of industrial features are present within the immediate surroundings of the converter station and substation application boundary, most notably to the south, in the vicinity of Richborough Port, on the northern bank of the River Stour. Three petrol filling stations are present within 100m of the application boundary, comprising Pegwell Bay Service Station 20m north of the TJP and TCS Richborough and Richborough Service Station, 55m south and 60m south of the proposed HDD section of the cable route respectively. Previous Land Use 6.25 Pegwell Bay Country Park was established on an area of landfill created during the 1960s and early 1970s. A number of large excavations were present through this area during the early 1960s, initially through southern and central areas of the present day Country Park and later spreading through the full extent of the Park. Associated with the staging of these excavations, different phases of landfilling are understood to have taken place, resulting in southern areas of the park being capped to a greater degree than the northern half of the park. Chalk has been used to cap the southern area. Further information on the landfill activity is detailed in the Phase 1 Report (Appendix 6.1). 6.25 The former Richborough Power Station was originally commissioned in 1962 as a coal-fired facility and subsequently converted to burn oil in 1971. The power station was modified for a second time in 1989, this time to burn a proprietary oil and water emulsion known as Orimulsion. During the power station’s operational phase, significant infrastructure was present, including numerous unspecified storage tanks, which have subsequently been removed. 6.26 Richborough Power Station closed in 1996 and the decommissioning, which included a programme of asbestos removal and partial demolition process, was completed in 2000, leaving the largest structures including the cooling towers and stack. In 2012, Thanet District Council (TDC) and Dover District Council (DDC) approved a planning application for demolition of the majority of above ground buildings most notably three cooling towers and a chimney. Demolition took place in March 2012, although some of the debris from the demolition currently remains on 91 site. The steel frame of the turbine hall has been left in situ and it is proposed that this will be used as part of the converter station building. 6.27 Richborough Port, south of the former Power Station Site, has reduced in size and activity, having been a major industrial hub during the Second World War when numerous warehouse and railway sidings were present. More recently, fuel oil was imported and transferred to the power station via a pipeline, which passed beneath Ramsgate Road and into the power station site. Geology 6.28 The published geological map of the area indicates that the northern two-thirds of the onshore cable route are underlain by Marine Beach Deposits whilst southern areas are predominantly underlain by Marine and Estuarine Alluvium. Through the BayPoint sports complex area, Storm Beach Deposits are present overlying the boundary between the strata detailed above. The superficial deposits are anticipated to attain a thickness of between 2.5m and 4.0m at the northern end of the cable route, but potentially increasing in depth towards the south as the cables route moves inland. 6.29 Beneath the superficial deposits, geological records indicate the solid geology to comprise the basal Thanet Sand Formation with the White Chalk Sub-group at depth. Previous site investigation works at the northern end of the cable route did not encounter the Thanet Sand Formation, instead encountering White Chalk directly beneath shallow drift deposits. At the southern end of the cable route, from Stonelees Nature Reserve, the Thanet Sand Formation is anticipated to extend to a depth of 30 metres below ground level (mbgl). 6.30 To the east of the former power station, in the vicinity of Sandwich Bay to Hacklinge Marshes SSSI, superficial deposits are absent and the Thanet Sand Formation outcrops at the surface. 6.31 Made ground is anticipated to be present along the cable route where historical development has taken place. In addition, landfill materials are anticipated to be present throughout the full extent of Pegwell Bay Country Park. 6.32 Beneath the proposed converter station and substation site, previous investigations (undertaken by URS in 2009) have encountered a ground profile comprising made ground to a depth of between 1.5mbgl and 6.3mbgl overlying Marine and Estuarine Alluvium to a depth of between 9.4mbgl and >11.0mbgl. These strata were found to overly the Thanet Sand Formation, which extended to the full depth of investigation at 20mbgl. 6.33 Extensive deposits of made ground are present associated with the site’s historical development and the presence of numerous sub-surface structures and basements. Hydrogeology 6.34 The Marine Beach Deposits underlying approximately the northern two-thirds of the cables route, between the TJP and Stonelees Nature Reserve, are designated as a Secondary (undifferentiated) aquifer whilst the Marine and Estuarine Alluvium underlying the southern section of the cables route and the proposed converter station and substation site are designated as Unproductive Strata. Where Storm 92 Beach Deposits are present (beneath BayPoint sports complex) these have been classified as a Secondary A aquifer. Further information on the aquifer classification is detailed in the Phase 1 Report (Appendix 6.1). 6.35 The underlying Thanet Sand Formation (which outcrops to the east of the former Power Station site in the vicinity of Hacklinge Marshes) is classified as a Secondary A aquifer whilst the underlying White Chalk Sub-group has been classified as a Principal aquifer. 6.36 The shallow aquifer associated with the superficial deposits extending across the application area, with the exception in the vicinity of Hacklinge Marshes, has been classified with a High vulnerability rating (i.e. they readily transmit liquid discharges and a wide range of pollutants) whilst the outcrop of the Thanet Sand Formation has been classified with an Intermediate vulnerability rating (i.e. soils which can possibly transmit liquid discharges and a wide range of pollutants). 6.37 The application site is located within a sensitive area with respect to groundwater. However, in the immediate vicinity of the cables route and converter station and substation site, shallow groundwater is unlikely to form an important resource owing to natural saline intrusion. The published hydrogeological map for the area indicates that chloride concentrations within the White Chalk aquifer are four times greater than the limit specified within the UK Drinking Water Standards associated with natural saline intrusion. 6.38 There are no groundwater abstractions for potable water supply within a 2km radius of the application boundary. The proposed development area is not located within a currently designated groundwater Source Protection Zone. 6.39 In the vicinity of the proposed converter station and substation site, previous investigation works, undertaken by URS in 2009, have encountered perched water through the made ground at depths ranging between 0.061mbgl and 1.008mbgl with groundwater encountered between 0.657mbgl and 3.472mbgl. Along the cable route groundwater is anticipated to be present at depths of between 2-3mbgl with the notable exception of the Pegwell Bay foreshore. 6.40 Across the proposed converter station and substation site, groundwater flow is anticipated to be in a southerly or easterly direction dependent upon the proximity of the River Stour and Pegwell Bay. Groundwater flow is also likely to be influenced by tidal variation, which is expected to be active at either end of the application site (i.e. beneath the converter station and substation site and in the vicinity of the TJP). 6.41 Information available on the Environment Agency website indicates that the full extent of the application site does not lie within a groundwater source protection zone. Surface Waters 6.42 Between the landfall and the proposed HDD works, the cable route is on the seaward side of the Sandwich Road, just above the mean high water level of Pegwell Bay. A large tidal lagoon is present 10m south of the cable route between the TJP and Pegwell Bay Country Park. 93 6.43 The tidal River Stour is present 10m west of the proposed substation footprint, flowing in a southerly direction along the western edge of the former power station site. To the south of the proposed converter station and substation site, the River Stour flows in a large loop around Great Stonar (extending for 3.4km south) before heading north again and passing within 400m of the cable route, close to the river’s confluence with Pegwell Bay. 6.44 Several small watercourses are present in the vicinity of the development area. These are described in detail in Chapter 7, Hydrology and Flood Risk. The largest of these is the Minster Stream, which flows in a linear drainage channel to the west of the new A256 bypass. HDD will be used to route the cable beneath this watercourse. An unnamed drainage channel follows the cable route through the southern areas of Pegwell Bay Country Park and Stonelees Nature Reserve, before discharging into a small pond at the northwestern corner of BayPoint sports complex. 6.45 The River Stour is monitored under the Environment Agency’s General Quality Assessment Scheme. The EA classification of the water quality at the closest compliance point, 3km downstream of the application site’s most southerly point, is Grade B (good). 6.46 There are eighteen surface water abstractions within a 1km radius of the application boundary comprising the cables route from low water and the converter station and substation site. None of these abstractions are for potable purposes. 6.47 The indicative floodplain map for the area, published by the EA, shows that the northern two-thirds of the cables route between the TJP and Stonelees Nature Reserve are within the footprint of an extreme flood event from the sea. In addition, a thin strip of land susceptible to an extreme flood event is present at the southern end of the cable route along the banks of Minster Stream. The proposed converter station and substation within the former Richborough Power Station site are within an area at low risk of flooding. Detailed information on flood risk is presented in Chapter 8, Hydrology and Flood Risk. Sources of Contamination beneath the Former Power Station 6.48 Previous site investigations have indicated that, whilst low level contamination is present beneath the former power station, including heavy metals, sulphates, polycyclic aromatic hydrocarbons and polychlorinated biphenyls, this does not present a risk to end users of the site or nearby controlled waters. As such, the principal pollutant linkage within this area is considered to relate to potential accumulations of ground gases within excavations during the construction phase and within the proposed structures. 6.49 Pollutant linkages are also considered to exist in relation to construction materials, particularly concrete placed in the ground where elevated concentrations of sulphate have been encountered. Potential Sources of Contamination along Cable Route 6.50 Along the proposed cable route, on-site sources of potential contamination have been identified. These include: 94 The presence of landfill materials beneath Pegwell Bay Country Park with the potential to generate landfill gases and leachate; and The possible presence of made ground through areas of historical development, most notably at BayPoint sports complex and the adjoining A256 bypass, resulting in the potential for elevated concentrations of heavy metals, sulphates, polycyclic aromatic hydrocarbons and ground gases to be present. 6.51 In the immediate vicinity of the cables route, sources of potential contamination have been identified which may pose a risk to the environment. The most relevant of these sources relates to evidence of free-phase hydrocarbon products in the ground 20m north of the cable landfall, together with dissolved phase hydrocarbon contamination in the groundwater indicative of diesel and petrol contamination. Information supplied by the Environment Agency makes reference to remedial works having been undertaken, including small scale pumping trials and passive removal of free-phase hydrocarbon products. Whilst the works are acknowledged to have addressed any significant risk to the wider environment, the Environment Agency is yet to receive a final verification report to detail the full extent of works undertaken and effectiveness of the remediation. 6.52 An additional source of potential contamination relates to a pollution incident to controlled waters associated with the rupture of a below ground fuel pipe beneath BayPoint sports complex, which resulted in the release of diesel or fuel oil into the ground. Information supplied by the Environment Agency has suggested that whilst the bulk of the contamination was removed, subsequent monitoring to assess the natural attenuation of hydrocarbons within groundwater did not take place. Groundwater monitoring conducted by the former landowner in 2011 revealed the presence of hydrocarbon contamination within groundwater beneath the BayPoint sports complex, which is likely to be associated with the historical spill. It is understood that there is a plan for remediation of the site in production. 6.53 The presence of three petrol filling stations within 60m of the cable route is considered to represent a potential source of contamination, particularly given the proximity of two of these features to the HDD section of the cables route. The presence of these features gives rise to a potential source of various hydrocarbon compounds together with chlorinated and non-chlorinated solvents, asbestos, sulphuric acid and heavy metals. Assumptions and Uncertainties 6.54 Intrusive works undertaken across the footprint of the converter station and substation site were carried out as a general assessment of the wider power station site and were not targeted to assess the proposed features or cable trench through the power station site specifically. 6.55 Potential sources of contamination have been identified along the cables route associated with hydrocarbon spills from a petrol station adjacent to the TJP and also within BayPoint sports complex. Whilst the Environment Agency has supplied information relating to remedial activities, they are not in receipt of verification reports to confirm the extent of the works undertaken and the completion of subsequent monitoring to confirm the adequacy of the works. The Environment Agency has alluded to an assessment of BayPoint sports complex in 2011, which 95 confirmed that groundwater contamination is still present, presumably associated with the historical spill. However, more detailed information was not available. 6.56 Across the remainder of the site, no intrusive investigation works have been undertaken to date to determine the baseline conditions with respect to shallow soil contamination, groundwater or surface water quality along the cable route. Prediction and Assessment of Significance of Potential Impacts Receptors at Risk 6.57 The assessment has identified potential receptors within four categories: End users of the site, who may have an acute exposure to sources of contamination on a regular and predictable basis; Controlled water, being defined as all surface water, groundwater or perched water; Construction materials placed in the ground, including concrete used in the joint transition pits; and Other targets such as the “environment”, including any flora and fauna on or near the construction corridor and construction and maintenance workers who will have chronic but potentially higher levels of exposure than end users. Pathways for Migration 6.58 Based on the current land uses along the cables route and at the former Power Station site, and the anticipated ground conditions through the area, the following contaminant pathways are considered potentially viable: Ingestion, inhalation of soil/dust particulates or contaminant vapours, dermal contact (absorption through skin); Mobile/leachable contaminants will generally migrate vertically downward through the superficial drift deposits until meeting the water table, after which free/dissolved phases would be expected to migrate towards Pegwell Bay or the River Stour, dependent upon the location within the site; Buried concrete and other construction materials placed into the ground will be susceptible to attack via contact with aggressive/contaminated ground, especially if mobile groundwater is present; Pathways for gas migration are considered to exist through superficial drift deposits and sources of gas generation; and Vegetation and other ecological targets may be affected by contact with contaminated soils via plant uptake routes. Pre-Construction Investigation Works 6.59 Prior to construction works commencing, investigation works will be undertaken to confirm the ground conditions and extent of potential contamination along the route of the proposed HDD, including the HDD receptor pit within the sports complex and the launch pit on the former Power Station site. Investigation works will also be undertaken within the footprint of the TJP at the cable landfall. 96 6.60 Through Pegwell Bay Country Park, investigation works will determine the depth, nature and extent of the chalk-capping layer overlying historical landfill materials. 6.61 Within the footprint of the convertor station and substation targeted investigation works should be undertaken to assess the ground conditions in the area of the cable trench and associated structures. 6.62 No adverse effects on ground conditions or contamination will arise from the above investigations given the localised and short-lived nature of the work. Construction Phase 6.63 Heavy plant will be used during construction works on the converter station and substation site and on the cables route. Temporary fuel storage and refuelling facilities will be required. 6.64 A TJP will be constructed where the marine cables are joined to the onshore cables. A chamber will be constructed below ground to allow for future access to inspect the joints, with the access cover buried to allow natural colonisation with vegetation. 6.65 The general method of construction will involve the placement of cables through open trenches measuring 1m deep by 1m wide at the base and battered back to 1.5m wide at the surface. Following placement of the cables at 0.5m centres the trench will be backfilled with a minimum of 0.6m of cement bound sand (CBS) followed by excavated topsoil. 6.66 Through Pegwell Bay Country Park, construction methods will be modified given the anticipated presence of landfill materials. Through the northern half of the park, where capping is unproven, the cable will be laid upon the existing ground surface (following removal of vegetation and minor undulations) with a 1.0m thick capping layer placed over the cables. The capping layer will be constructed to taper at a 1:5 slope with a 1.0m wide flat section at the top and will include a cellular confinement system to prevent slippage and exposure of the cables. A minimum of 0.6m of CBS will be used within the capping layer. Through the southern half of the park a hybrid method of trenching and capping will be used, dependent upon the depth of chalk capping present over landfill materials. 6.67 Horizontal directional drilling (HDD) will be used to place the cables between BayPoint sports complex and the former power station to avoid disturbance of the A256 bypass, Minster Stream and Hacklinge Marshes. The installation of conduits will involve the drilling of pilot holes, reaming (to make the holes larger) and pulling the cable conduits through the reamed holes. This process will involve the construction of a launch pit within the former power station site and a receptor pit within BayPoint sports complex. During the drilling of the pilot holes and reaming process, a drilling fluid or ‘mud’ is used to loosen the materials in front of the drill and carry it back to the entry point suspended in the mud. Ultimately the drilling fluid will ‘break-out’ into the receptor pit. At the end of the drilling operation drilling fluids and any wastes will be cleared from the site to a suitably licensed facility and the excavations backfilled. 6.68 Along the cable route, jointing pits will be required in Pegwell Bay Country Park and also in BayPoint sports complex to connect the HDD and trenched underground cables sections. 97 6.69 Temporary access roads will be required along much of the route and through BayPoint sports complex to provide access for the necessary plant and equipment. The working width along the cable route will be between 15m and 25m with the working area of the HDD launch and receptor pits taking up a maximum area of 25m by 40m. 6.70 On land adjacent to the converter station and substation within the former power station site, a contractor’s compound and laydown area will be established. This will require any loose materials and vegetation to be stripped out. 6.71 Within the convertor station and substation site a construction platform will be required for switchgear equipment, transformers and buildings and will contain oil spill containment facilities in line with National Grid’s standard specifications. It is anticipated that the construction platform will utilise piled foundations placed into the natural strata or compacted fill, where suitably competent ground is present. The finished construction platform will require the importation of crushed natural stone for use through areas of hardstanding. The completed site will be surfaced partially with stone chippings. 6.72 During creation of the construction platform, the bases of the former cooling towers and any remaining underground pipe-work will be removed and the basement located beneath the former turbine hall will be backfilled with suitably competent imported materials. 6.73 Works that could potentially affect ground conditions or create contamination effects during the construction phase of the development include: Disturbance of contaminants exposing these to sensitive environments and receptors from trenching and installation of the cables and excavation of the TJP and joint pit within Pegwell Bay Country Park; Excavation of the receptor and launch pits associated with HDD works and the use of drilling fluids; Creation of temporary access roads and construction compounds; Disturbance of contaminants within the footprint of the convertor station and substation associated with the demolition and removal of former below ground structures and excavation and piling activities associated with construction of new infrastructure. Importation of contaminated materials from off-site; and Spillage from fuelling and other operations. 6.74 The potential effects of the above works on the outlined receptors are assessed below. 6.75 With respect to the underlying unconfined aquifer within the Marine Beach deposits, Storm Beach deposits and Thanet Sand Formation, the following effects could potentially occur from construction activities: Creation of preferential pathways for the migration of contaminants; Risk of contamination from mobile contaminants associated with imported materials such as crushed stone for access roadways and construction compounds, sub-base materials placed beneath hardstanding, capping 98 materials for use in Pegwell Bay Country Park and cement bound sand for cable protection; and Risk of pollution to groundwater from fuel, oil and chemical spills. 6.76 The sensitivity of the underlying aquifers is considered to be of Medium importance and the magnitude of effects associated with the release of contaminants into groundwater is considered to be Minor. The overall significance of the above effects on aquifers and groundwater will be Negligible. 6.77 With respect to the surface water quality of the River Stour, Minster Stream and smaller drainage channels, together with the marine environment, the following effects could occur from construction activities: Creation of preferential pathways for the migration of contaminants into water bodies; Risk of pollution to surface water from spills of fuels, oils, chemicals and siltcontaminated water; and Potential discharge of silt-contaminated water, from surface water run-off and dewatering activities. 6.78 The sensitivity of water bodies, is considered to be of Medium importance and the magnitude of effects associated with the release of contaminants to surface water is considered to be Moderate. The overall significance of effects on surface water is categorised as Minor Adverse. 6.79 With respect to neighbouring properties and residents, the following effect could arise as a result of construction activities: Risk of release of contaminated dust during the movement of construction vehicles. 6.80 The sensitivity of neighbouring properties and residents is considered to be of High importance and the magnitude of effects associated with the release of airborne contaminants is considered to be Minor. The significance of the above effect is categorised as Negligible. 6.81 With respect to areas of flood risk, the following risks of contamination could potentially arise through construction activities: 6.82 The potential risk of flooding of fuel or chemical storage areas, resulting in the migration of contaminants to the surface water bodies and groundwater; and The potential risk of flooding excavations where contaminated groundwater may be present. Using the significance criteria outlined earlier in the chapter, the sensitivity of flood risk areas is considered to be of High importance and the magnitude of effects associated with the release of contaminants into the controlled waters is considered to be Minor. The significance of these potential effects is categorised as Minor Adverse. 99 Operational Phase 6.83 During the operation of the onshore underground cables and subsea cables, no effects are anticipated related to contaminated land. However, inspection of joint pits along the cable route may be required if a fault occurs. This would involve temporary excavation of soils at joint pits and subsequent reinstatement. 6.84 Occasional maintenance works may be required through Pegwell Bay Country Park should the capping layer placed over the cables become eroded. If necessary, these works would involve the importation and placement of fresh capping materials in accordance with the original specification. 6.85 The converter station and substation will have back-up generators to provide an electrical supply in the event of mains failure. Oil and diesel to power the generators will be stored on site so there is a potential for leakage of these contaminants into surface water and groundwater. Spillage or leakage of oil from transformers could also occur during operation. The operation of the converter station and substation will require minimal maintenance works 6.86 The following impacts are potentially associated with the operation of the proposed development, with respect to human health: The potential risk of site users and maintenance workers coming into contact with contaminated ground or groundwater in the vicinity of the converter station and substation site. The potential risk of explosive of harmful ground gases, including landfill gases, entering small buildings and confined spaces such as entry into the launch and receptor pits of the TJP. 6.87 The sensitivity of human health is considered to be of High importance and the magnitude of effects associated with the direct contact with contaminated ground or groundwater is considered to be Moderate. Therefore, the significance of these potential effects is categorised as Moderate Adverse. 6.88 With respect to routine inspection and maintenance works, the potential effects are considered to replicate those associated with the operational phase (see above) given that the works will be of a similar nature, albeit on a much smaller and localised scale. Mitigation 6.89 Within the footprint of the convertor station and substation targeted investigation works will be undertaken to assess the ground conditions in the area of the cable trench and associated structures. 6.90 Prior to construction works commencing, targeted investigation works will be undertaken in agreement with an Environmental Health Officer to assess the nature and extent of potential groundwater contamination associated with the historic pollution incidents at the northern and southern ends of the cable route. Where pollutant linkages are identified, a robust remediation method statement will be compiled to detail the necessary mitigation measures. 100 6.91 Within Pegwell Bay Country Park, investigation works will be undertaken to assess the nature and depth of capping materials overlying the landfill area. Should investigation works identify a need for the construction phase to penetrate the landfill materials (i.e. in the vicinity of the proposed joint pit) then a robust remediation method statement will be compiled to detail the necessary mitigation measures. 6.92 Fuels, lubricants, and chemicals required during construction and operation will be stored in secure bunded areas at appropriate distances from watercourses with refuelling restricted to these areas. Spill kits will be available on site in case of emergency and drip trays will be used for static plant and refuelling areas. 6.93 Some of the components (e.g. transformers) within the substation and converter station site will contain oils and lubricants as well as other potentially contaminated materials. Standard design criteria will ensure such components are contained within bunded areas. 6.94 Pollution prevention measures will be adopted to prevent contamination including measures to intercept and treat run-off prior to leaving site including the use of cutoff ditches and filtration systems. 6.95 A Construction Environmental Management Plan (CEMP) will be prepared which will set out methods which contractors will be required to undertake as a minimum to ensure pollution control throughout the construction works. 6.96 The CEMP will include quality control procedures to be employed by contractors for the import and export of materials to and from site. Methods for controlling surface water run-off and dust and measures to remove contaminated materials off site to licensed treatment or disposal sites will also be detailed. Refer to Chapter 7 (Hydrology and Flood Risk for further details of pollution prevention measures). 6.97 The CEMP will also include a Silt Management Strategy to address programming and management of silt generating activities. 6.98 Should apparently contaminated material be found during excavation works, where this has previously not been identified, work will cease until the material has been characterised and appropriate measures to dispose of contaminated materials have been identified. Contaminated materials will be characterised both chemically and physically in line with BS EN 14899:2005 –‘Characterization of Waste - Sampling of Waste Materials - Framework for the Preparation and Application of a Sampling Plan’. Registered waste carriers will only be used to convey any contaminated waste materials off site to suitably permitted facilities. All relevant documentation will be completed and kept in line with regulations. 6.99 Laying cables over the surface of the ground within Pegwell Bay Country Park will prevent potential contamination pathways being opened and prevent migration of landfill gas and leachate if these are present within the landfilled area. 6.100 Measures will be undertaken to reduce the amount of water entering excavations so as to minimise dewatering activities. Should de-watering be required, the Environment Agency will be consulted and appropriate abstraction and discharge licences will be obtained if necessary. Prior to disposal to surface water bodies, water will be treated to ensure it meets appropriate water quality standards. Further 101 details on water management techniques are discussed within Chapter 6 Hydrology and Flood Risk. 6.101 Soils excavated through areas of open trenching will be monitored to ensure they are free from contamination and suitable for re-use. 6.102 Upon completion of the HDD works, surplus-drilling fluids will be pumped out of the launch and receptor pits by vacuum tanker and removed from site to a suitable registered waste disposal facility by a registered waste carrier. 6.103 Where elevated concentrations of sulphates have been identified through the area of the proposed converter station and substation, resistance to potential sulphate attack can be mitigated by the selection of an appropriate class of concrete. Residual Impacts 6.104 Potential adverse effects will be eliminated through the application of the mitigation measures identified above. Consequently, there will be no residual effects associated with the development proposals on ground conditions and contamination. Cumulative Impacts 6.105 Potential cumulative effects on ground conditions and contamination from the onshore elements of the Nemo Link in combination with other components of the Project (i.e. UK, French and Belgian subsea cables and Belgian onshore infrastructure) are described in Chapter 16. 6.106 Potential cumulative effects of the Proposed Development in combination with the connection required to facilitate the operation of the Nemo Link are described in Chapter 17. 6.107 There is little scope for cumulative effects relating to ground conditions and contaminated land arising from the Proposed Development in combination with the other unrelated development as detailed in Table 1.2 at Chapter 1. All unrelated development is programmed to have been completed before work commences on the proposed onshore elements of the Nemo Link subject to this planning application. Any contamination found during construction of the other unrelated development will have been addressed before the work commences on the proposed onshore elements of the Nemo Link. Industry standard pollution control measures in accordance with statutory guidelines (typically monitored and controlled through a site construction management plan) are likely to be implemented throughout construction works for all unrelated development. No significant cumulative effects relating to ground conditions and contamination are anticipated to arise. 102 References Contaminated Land Developers Guide, Dover District Council. Contaminated Land Risk Assessment: A Guide to Good Practice, CIRIA C552, 2001. Contaminated Land Strategy, Thanet District Council. Control of Water Pollution From Construction Sites - Guidance for Consultant and Contractors, CIRIA C352, 2001. Environmental Protection Act, Part IIA Contaminated Land, Parliament of the United Kingdom, 1990. Investigation of Potentially Contaminated Sites: Code of Practice, British Standards Institution, BS10175, 2011. Model Procedures for the Management of Land Contamination. Environment Agency, Contaminated Land Report 11, 2004. National Planning Policy Framework, Department for Communities and Local Government, March 2012 Planning Policy Guidance 1: General Guidance to the Prevention of Pollution, Environment Agency 2001. Planning Policy Guidance 6: Working at Construction and Demolition Sites, Environment Agency 2010 Planning Policy Guidance 21: Pollution Incident Response Planning, Environment Agency 2009. The South East Plan, Regional and Spatial Strategy for the South East of England, Government Office for the South East, May 2009. Water Protection and Management (The Water Framework Directive), Directive 2000/60/EC, European Parliament and Council of 23rd October 2000. 103 104 7.0 HYDROLOGY AND FLOOD RISK Introduction 7.1 This chapter describes the existing water environment and identifies and assesses the potential effects of the proposed UK onshore elements (the Proposed Development) of the UK-Belgium Interconnector (the Project) on surface and ground water resources. It describes the mitigation measures that will be incorporated into the construction and operational phases of the Proposed Development to avoid, reduce or offset potential adverse effects or enhances potential beneficial effects. Legislation and Policy Context 7.2 Relevant national legislation and policy is outlined in Table 7.1, regional policy in Table 7.2 and local policy in Table 7.3. Table 7.1: National Legislation and Policy Policy/Legislation Key Provisions National Planning Policy Framework (NPPF) and supporting technical guidance Flood and Water Management Act (2010) The NPPF supersedes the previous applicable Planning Policy Statement 25: ‘Development and Flood Risk’ and its accompanying practice guide. Section 10 of the NPPF discusses ‘meeting the challenge of climate change, flooding and coastal change’. In particular, under paragraph 99 – 104, the NPPF mentions that inappropriate development should be avoided in areas at risk of flooding. Where development is necessary, it is essential to make it safe without increasing flood risk elsewhere. It also states that advice should be sought from the Environment Agency (EA) and other relevant flood risk management bodies, including lead local flood authorities and internal drainage boards and stresses that a sequential test should be applied to avoid development in areas at possible risk to people and property. The Act responds to the findings of the Pitt Review (2008) into flooding and sets out measures to co-ordinate control of drainage and flood issues. There are a number of increased responsibilities for developers, Lead Local Flood Authorities and the EA within the Act that affect adoption of SuDS (Sustainable Drainage Systems) features including the establishment of SuDS Approving Bodies (SAB’s) to review and consent surface water drainage works. The role of the EA is also to expand on the mapping data they provide both in terms of sources of flooding and condition of flood protection assets. Much of the Act is to come into force over the next few years. 105 Policy/Legislation Key Provisions The EU Water Framework Directive and River Basin Management Plans The WFD (2000) requires all inland and coastal waters to reach ‘Good’ chemical and biological status by 2015. Flood risk management is unlikely to have a significant effect on chemical water quality except where maintenance works disturb sediment (such as de-silting) or where pollutants are mobilised from contaminated land by floodwaters. The main effect of the WFD on flood risk management, both now and in the future, relates to the ecological quality of water bodies. The principal issues relating to fisheries and development addressed in the Directive are: Water quality problems caused by industrial and agricultural discharges and diffuse run-off; Land management practices that cause siltation to waterways, destroying fish spawning areas and the food sources and habitat on which fish depend; Acidification due to inappropriate tree planting, and; Water quantity and flow problems caused by, for example, abstractions. Water Resources Act (1991) as amended by The Water Act (2003) and Flood and Water Management Act (2010) The Act requires consent to be obtained for any discharges to controlled waters. The Act further states that works in, over, under or adjacent to main rivers will need the consent of the EA. From April 2012 in England and Wales, responsibility for consents and enforcement in respect of Ordinary Watercourse (i.e. not Main Rivers) passed from the EA to Local Authorities, in the most part, except where there is an Internal Drainage Board. Consent is required before carrying out any work that will, or could, block the waterway, including all work on culverts so as to reduce flood risk. The Freshwater Fish Directive The EC Directive on Freshwater Fish is designed to protect and improve the quality of rivers and lakes to encourage healthy fish populations. It sets water quality standards and monitoring requirements for areas of water, which are chosen, or 'designated' by the Department for Environment, Food and Rural Affairs (Defra). These designated areas of water are selected because they are significant bodies of water, which are capable of supporting fish populations. In the UK the directive is implemented through the Surface Waters Regulations 1997. The Shellfish Water Directive (adopted in 1979) outlines the requirements for the quality of designated waters, which support shellfish (defined as bivalve and gastropod molluscs) and aims to protect these shellfish populations from the harmful consequences resulting from the discharge of polluting substances into the sea. This Directive has been transcribed into UK legislation under the Surface Waters (Shellfish) (Classification) Regulations 1997 and The Surface Waters (Shellfish) Directions 1997. 106 Policy/Legislation Key Provisions The Groundwater Directive Groundwater Regulations (1998) Environmental Permitting Regulations 2010 The Groundwater Directive (80/68/EEC) aims to protect groundwater from pollution by controlling discharges and disposals of certain dangerous substances to groundwater. In the UK, the directive is implemented through the Environmental Permitting Regulations (EPR) 2010. The EA protects groundwater under these regulations by preventing or limiting the inputs of polluting substances into groundwater. Substances controlled under these regulations fall into two categories: Hazardous substances are the most toxic and must be prevented from entering groundwater. Substances in this list may be disposed of to the ground, under a permit, but must not reach groundwater. They include pesticides, sheep dip, solvents, hydrocarbons, mercury, cadmium and cyanide. Hazardous substances replace the previous List 1 substances, which came under the 1998 Groundwater Regulations (GWR). Non-hazardous pollutants are less dangerous, and can be discharged to groundwater under a permit, but must not cause pollution. Examples include sewage, trade effluent and most wastes. Non-hazardous pollutants include any substance capable of causing pollution and the list is much wider than the previous List 2 substances. For example, nitrate is included as a pollutant but it was excluded from List 2 in the 1998 GWR. 107 Table 7.2: Regional Policy Policy/Legislation Key Provisions Regional Spatial Strategy for the South East (The South East Plan) Policy NRM1: Sustainable Water Resources and Groundwater Quality – water supply and groundwater will be maintained and enhanced through avoiding adverse effects of development on the water environment. Policy NRM4: Sustainable Flood Risk Management – The Sequential approach to development in flood risk areas set out in PPS25 (updated to the NPPF) will be followed. The flood zones as defined within the NPPF Technical Guidance are the starting point for this sequential approach. Zones 2 and 3 are shown on the EA published flood map with Flood Zone 1 (low probability) being all the land falling outside Zones 2 (medium probability) and 3 (3a – high probability and 3b – functional floodplain). These flood zones refer to the probability of sea and river flooding only, ignoring the presence of existing defences. Inappropriate development should not be allocated or permitted in Flood Zone 2 and 3, areas at risk of surface water flooding (critical drainage areas) or areas with a history of groundwater flooding, or where it would increase flood risk elsewhere, unless there is over-riding need and absence of suitable alternatives. Policy CC2: Climate Change – measures to mitigate and adapt to current and forecast effects of climate change will be implemented through application of local planning policy and other mechanisms. 108 Table 7.3: Local Policy Policy/Legislation Key Provisions Thanet Local Plan The Thanet District Adopted Local Plan 2006 shows that the former Richborough Power Station site is under the policy of Wantsum Flood Risk Area (EP10) and Former Wantsum Channel (CC2). EP10 has not been saved and expired in June 2009. Policies related to Flood Risk and Surface Water Run-off have not been saved beyond June 2009. The Dover District Council Core Strategy 2010 Policy DM 17: Groundwater Source Protection – Within Groundwater Source Protection Zones, shown on the Proposals Map, the following will not be permitted in Zones 1 and 2 unless adequate safeguards against possible contamination are provided: i. Septic tanks, storage tanks containing hydrocarbons or any chemicals, or underground storage tanks; ii. Proposals for development which may include activities which would pose a high risk of contamination unless surface water, foul or treated sewage effluent, or trade effluent can be directed out of the source protection zone; iii. Proposals for the manufacture and use of organic chemicals, particularly chlorinated solvents; iv. Oil pipelines; v. Storm water overflows; vi. Activities which involve the disposal of liquid waste to land; and vii. Sustainable urban drainage systems. Method 7.3 Hydrology has been assessed in terms of the natural drainage patterns, base flows and volumes, run-off rates, geomorphology and water quality. Potential effects resulting from the Proposed Development on surface water, groundwater and flood risk both during construction and operation have been assessed having regard to the mitigation measures already integrated into the design. 7.4 The assessment has been carried out in consultation with the EA and it follows best practice guidelines as listed below: EA Pollution Prevention Guidelines; Sewer for Adoption (6th edition) and interim technical addendum, 2011; British Standard BS 8533:2011 Assessing and managing flood risk in development Code of practice; The SuDS Manual (CIRIA C697); Catchment Flood Management Plans; Thanet District Strategic Flood Risk Assessment; and Kent Preliminary Flood Risk Assessment. 109 7.5 In accordance with EA policy regarding scale of development and site location in respect of flood zones, a Flood Risk Assessment (FRA) has also been undertaken. The FRA establishes the risk associated with the Proposed Development and proposes suitable mitigation (where required) to eliminate or reduce the risk to a more acceptable level. The FRA is contained in Appendix 7.1. Results from the FRA are summarised in this chapter. 7.6 The FRA has been prepared in accordance with the requirements of the NPPF and considers flood risk on-site and flood risk elsewhere as a result of the Proposed Development. The FRA has also been prepared in accordance with the Interim Code of Practice for Sustainable Drainage, BS 8533 and accompanying guidance published by the Communities and Local Government Office. The guidance advises the following steps: Obtain information on the hydrology, hydrological and hydrogeological regime in and around the site; Obtain the view of the EA including scope, location and impacts; Determine the extent of change to flooding provisions and the influence on the site; Review all potential sources of flooding and identify risk; Review the surface water drainage based upon the proposed layouts, and determine the extent of the infrastructure required; and Assess the impact on the site from climate change and anticipated increases in rainfall over the lifetime of the development. 7.7 During consultation, the EA provided details of flood modelling contained in the ‘Lower Stour Areas Benefiting from this Defence (ABD) and Hazard Mapping Study Updates’ (undertaken by JBA Consulting in April 2012) and confirmed that the Thanet District Strategic Flood Risk Assessment (SFRA, 2008) should be used for the assessment. 7.8 The River Stour (Kent) Internal Drainage Board confirmed that ‘the Board does not hold records of any flooding at this location, as all details are kept by the EA’. Assessment of Significance 7.9 The evaluation and determination of significance has been carried out using identified criteria, including published EA standards and flood risk assessment guidelines. 7.10 The assessment of significance of potential effects of the Proposed Development has taken into account: 7.11 The sensitivity of the receiving environment; and The potential magnitude of effect. A further consideration regarding sensitivity which has been taken into account for the Proposed Development is that of ‘Critical Infrastructure’ as defined by the Cabinet Office. CIRIA document C688 ‘Flood Resilience and Resistance for Critical Infrastructure’ contains recommendations for the standard of flood protection for different asset categories. These are defined in Tables 7.4 and 7.5 below. 110 Table 7.4: Concise Definition of Asset Categories (Courtesy of Cabinet Office) Asset Category Concise Definition 5 Assets, the loss of which would have catastrophic impact on the UK 4 Assets, the loss of which would affect millions of people 3 Assets, the loss of which would affect hundreds of thousands of people 2 Assets, the loss of which would affect tens of thousands of people 1 Assets, the loss of which would affect thousands of people Table 7.5: Examples of Resistance/Resilience Standards and Performance Levels that may be Appropriate for Critical Infrastructure Assets in some Sectors Indicative Design Standard Events Target Asset Performance Level Restricted Unaffected Operation (resistant) (resilient) Safe but Not Operational (resilient) Near Failure 1 in 10 - 1 in 75 year CAT 1 1 in 75 - 1 in 100 year CAT 2 CAT 1 1 in 100 - 1 in 200 year CAT 3 CAT 2 CAT 1 1 in 200 - 1 in 1,000 year CAT 4 CAT 3 CAT 2 CAT 1 > 1 in 1,000 year CAT 5 CAT 4 CAT 3 CAT 2 7.12 This criterion suggests that a CAT 1 asset should be unaffected for all flood events up to a 1 in 75 year event but could operate at a restricted level for more extreme events and may not need to be designed to be operational for events beyond a 1 in 200 year flood. A CAT 5 installation however, is to be unaffected for all events up to and including the 1 in 1,000 year event and beyond. 7.13 Sensitivity, in terms of quality, value and rarity is defined in Table 7.6. Magnitudes of effect are set out in Table 7.7 and have been determined by consideration of the scale and extent of impact in terms of duration, the likelihood of occurrence and reversibility. 111 7.14 The overall significance of potential effects considering sensitivity of receptor and magnitude of effect is shown in Table 7.8. Table 7.6 Sensitivity of the Water Environment Receptor Description Sensitivity High Area of international designations i.e. Ramsar site, Special Protection Areas (SPAs) and Special Areas of Conservation (SACs) EA designated main river i.e. River Stour and Minster Stream EA water quality Class A and B EA groundwater Source Protection Zone 1 – Inner protection zone EA defined Principal Aquifers Flood Zone 3 Water sensitive and highly vulnerable development in the area Local flood defences/embankments for major rivers CAT 3, 4 and 5 Critical Infrastructure Asset Medium Area of national and regional importance i.e. Site of Special Scientific Interest (SSSI) and National Nature Reserves (NNR) and Marine Nature Reserves (MNR) Local drains i.e. ordinary watercourses and water bodies EA water quality Class C and D EA Groundwater Source Protection Zone 2 – Outer protection zone EA defined Secondary Aquifers Flood Zone 2 More vulnerable development in the area (including temporary works and workforces) Local flood defences/embankment for drains CAT 2 Critical Infrastructure Asset Low Area of local importance which are not designated Minor local drainage network/ land drains EA Water Quality Class of E and F EA groundwater Source Protection Zone 3 – Source catchment protection zone EA defined Unproductive Strata Flood Zone 1 Less vulnerable and water compatible development Local embankments for minor drains CAT 1 Critical Infrastructure Asset 112 Table 7.7 Magnitude of Effect Magnitude Definition High Total loss or major alternation to key elements of features of the baseline conditions to the extent that post-development character or composition of baseline conditions will be fundamentally changed. Medium Loss or alternation to one or more key elements/features of the baseline conditions to the extent that post-development character or composition of the baseline conditions will be materially changed. Low Minor shift away from baseline conditions. Changes arising will be detectable but not material; the underlying character or composition of the baseline conditions will be similar to the pre-development situation. Negligible Very little change from baseline conditions. Change is barely distinguishable, approximating to a ‘no change’ situation. Table 7.8 Significance of Effect Magnitude 7.15 High Medium Low High Major Moderate Minor Medium Moderate Moderate Minor Low Minor Minor Negligible Negligible Minor Negligible Negligible/None The significance of effect can be described as follows: 7.16 Sensitivity Minor: Slight, very short or highly localised; Moderate: Limited effect in terms of extent, duration or magnitude; or Major: Considerable effect in terms of extent, duration or magnitude or more than local significant or in breach of recognised acceptability, legislation or policy or standards. The nature of an effect can be classified as adverse; negligible (or no effect); or beneficial: Adverse: Classifications of significance indicate disadvantageous or negative effects to an environmental receptor, which may be of Minor, Moderate, or Major significance Negligible/None: Classifications of significance indicate imperceptible effects to an environmental receptor; Beneficial: Classifications of significance indicate advantageous or positive effects to an environmental receptor, which may be of Minor, Moderate or Major significance. 113 7.17 Timescales associated with effects are categorised as follows: Short to Medium Term: Effects associated where the effect is temporary and last for the period of the construction works or less; and Long Term: Effects associated where the effect remains for a substantial time, perhaps permanently, after construction even though the activity that created it may be ceased some time ago. Uncertainty and Technical Difficulties Encountered 7.18 The assessment is based on desk study conducted in May 2012 and updated in September/October 2012 due to additional information being issued related to a planning application for new flood defence works alongside the A256 Sandwich Road, that included new flood modelling work carried out by Halcrow on behalf of the EA. For completeness, although the flood defence works are scheduled for construction in 2013, the flood risk benefits provided by the proposed works has also been considered within the cumulative impact assessment (see end of this Chapter) in the unlikely event the construction of the flood defence works is not complete before construction of the Proposed Development commences. 7.19 Climate change modelling of flood events undertaken by the EA does not cover the more extreme events of 1 in 1,000 years or above. Following discussions with the EA, the NPPF recommendations for climate change increases in flood levels have been applied in this assessment. 7.20 NPPF considers both sea level changes and rainfall intensity changes that are related to potential future changes in climate. Climate change influence will include changes to rainfall and the resultant changes to the surface water flows from the site. As the proposed converter station and substation site is adjacent to the tidal influenced river, there is a risk of the tidewater rising and posing an increased risk to the site. Table 7.9 and 7.10 summarises the current NPPF recommendations. Table 7.9: Recommended Contingency Allowances for Net Sea Level Rises Net Sea Level Rise (mm per year) Relative to 1990 1990 to 2025 to 2055 to 2085 to 2025 2055 2085 2115 East of England, east midland, London, south4.0 east England (south of Flamborough Head) South-west England 3.5 North-west England, north-east England (north 2.5 of Flamborough Head) 114 8.5 12.0 15.0 8.0 11.5 14.5 7.0 10.0 13.0 Table 7.10: River Flow Recommended National Precautionary Sensitivity Ranges for Peak Rainfall Intensities, Peak River Flows, Offshore Wind Speeds and Wave Heights Parameter Peak rainfall intensity Peak River flow Offshore wind speed Extreme wave height 7.21 1990 to 2025 +5% +10% +5% +5% 2025 to 2055 +10% +20% 2055 to 2085 +20% 2085 to 2115 +30% +10% +10% From NPPF Technical Guidance Document Table 4 (recommended contingency allowances for net sea level rises), for the 60 years from 2010 to 2070 the following is considered applicable for a site in South-East England:2011 – 2025 (14 years @ 4mm per year) = 56mm 2025 – 2055 (30 years @ 8.5mm per year) = 255mm 2055-2070 (15 years @ 12mm per year) = 180mm Total = 491mm 7.22 In addition, it is possible that rainfall intensity will increase by 20% with a corresponding 20% increase in peak river flow. 7.23 The EA supplied flood modelling data as a set of Node locations with estimated flood levels associated with each Node where the flood model predicted that flooding would occur. 7.24 Many of the Nodes show ‘0’ values for some or all modelled flood events. This is due to the model outputs not producing flood levels for these locations suggesting the modelled flood events do not reach these locations. The confidence limits of the EA data have been stated as +/- 150mm for the modelled flood node data. This is due to the inherent inaccuracies of topographical data used in the model together with model limitations and assumptions regarding tidal event prediction. Reference should be made to the EA Standard Notice regarding data (contained within the FRA – Appendix 7.1). Existing Environment Topography 7.25 Existing ground levels are approximately 3.0m AOD close to the Transition Joint Pit. The land rises to 4.0m AOD alongside the cycle track at the northernmost extent of the cable route and rises to 4.5m AOD as the route passes to the east of the Pegwell Bay Country Park car parking area. The southern extent of the Country Park, reaches 5.0m AOD. Within the BayPoint sports complex, ground levels fall slightly towards the south to a low point of 4.7m AOD. The cables route crosses Sandwich Road, which is at a height of 4.6m AOD. 7.26 The banks of Minster Stream are at approximately 2.0m AOD and the ground level rises towards the former Richborough Power Station site boundary to 3.0m AOD. 115 7.27 Ground levels within the converter station and substation site vary due to the former structures and the presence of some voids on the site. The general ground level is at approximately 3.5m AOD within the converter station site. The levels fall slightly to just below 3.0m AOD within the substation site; the proposed laydown area is east of and approximately 500mm below the substation and converter station site levels. Hydrology 7.28 The Transition Joint Pit (TJP) is located on the foreshore within approximately 40m of the mean high water mark of Pegwell Bay. A tidal lagoon is between the TJP and Pegwell Bay Country Park immediately south of the proposed cables route. 7.29 Main rivers are watercourses shown on the statutory main river maps held by the EA, the Department of Environment, Food and Rural Affairs (in England) and the Welsh Assembly Government (in Wales). They can include any structure or appliance for controlling or regulating the flow of water into, in, or out of the channel. The EA has permissive powers to carry out works of maintenance and improvement on these rivers with their formal consent required for works that affect a main river. All other watercourses are defined under the Flood and Water Management Act 2010 as ordinary watercourses. 7.30 On 6 April 2012, when a further phase of the Flood and Water Management Act 2010 was implemented, responsibility for regulating activities on ordinary watercourses in most areas of England and Wales transferred from the EA to Lead Local Flood Authorities (LLFA) unless the watercourse is within an Internal Drainage District where Internal Drainage Boards (IDBs) will retain their existing powers. 7.31 Figure 7.1 is annotated with the main water features in and around the proposed converter station and substation site and onshore cable route. 7.32 The closest ’Main River’ to the proposed converter station and substation site is the River Stour, 10m west of the proposed substation footprint at its closest point. The River flows in a southerly direction along the western edge of the former power station site. To the south of the proposed converter station and substation site, the River Stour flows in a large loop around Great Stonar (extending for 3.4km south) before heading north again. The River passes within 400m to the east of the cable route, close to the river’s confluence with Pegwell Bay where the River discharges in to the North Sea. The River is tidal from the coast to Plucks Gutter some 6km west of the former power station site. 7.33 Minster Stream, also designated as a ‘Main River’, is less than 100m to the northeast of the converter station site. The Stream flows in a linear man-made drainage channel westward and passes beneath the A256. The onshore cables will be routed beneath Minster Stream by Horizontal Directional Drilling (HDD). The topographical data (Greenhatch Group topographical survey dated 1st February 2012) shows Minster Stream to be approximately 10.0m wide from top of bank to top of bank. The water surface is shown at around 4.0m wide with water levels recorded at a level of 0.25m AOD on the topographic survey. 7.34 There are a number of ‘ordinary watercourses’ consisting of interlinked drains in the area located immediately to the west of Sandwich Road and the cable route. An unnamed drainage channel (highways drainage) follows the cable route through the 116 southern areas of Pegwell Bay Country Park and Stonelees Nature Reserve, before discharging into a small pond at the northwestern corner of the BayPoint sports complex. The proposed onshore cables will be horizontally drilled beneath an ordinary watercourse (unnamed) identified by the IDB alongside the northeast boundary of the former Richborough Power Station at OS Grid Reference TR3341 6220. 7.35 Kent County Council Highways were contacted regarding existing highways drainage within and around Sandwich Road and the proposed cables route however at the time of preparing this assessment, no details have been provided. 7.36 The new A256 bypass (Phase 2 of the East Kent Access) was opened in May 2012 and includes a new section of road close to the application site between Richborough Power Station (A256), Minster Roundabout (A299) and Lord of the Manor Junction at Cliffsend. This highway link includes a new culverted crossing of the Minster Stream to the east of the former Richborough Power Station site. In addition, the road scheme includes a number of surface water balancing ponds (attenuation ponds). The attenuation pond closest to the Proposed Development is immediately to the west of the new Ebbsfleet Roundabout, approximately 150m north of the converter station site. A second attenuation pond is Weatherlees Pond on land to the northeast of the Weatherlees Hill Wastewater Treatment Works. Discharges from both ponds will be into the local minor ditches that flow to the Minster Stream that runs parallel to the new road scheme. 7.37 A further small pond is located within the northwest corner of the BayPoint sports complex immediately west of the onshore cable route. Drainage Public Sewers – Southern Water 7.38 Details of the sewers from the sewer record plan are contained within the FRA (Appendix 7.1). Surface Water 7.39 Information provided by Southern Water does not show any public surface water sewers in the locality. The nearest surface water sewers are within the residential settlement in Cliffs End to the north of the proposed Transition Joint Pit. None of these sewers are crossed by the cable proposals. Foul Water 7.40 Weatherlees Hill Wastewater Treatment Works lies immediately north of the converter station and substation site and off Ebbsfleet Lane (TR330628) (Figure 7.1). The treatment works is owned by Southern Water and receives foul water flows from the north via two large diameter rising mains; one receiving partially treated wastewater from Broadstairs and Margate (incoming from the north) and the second from Cliffs End and Ramsgate via Sandwich Road. 7.41 Southern Water plans indicate that there is currently a pair of 500mm diameter cast iron rising mains within the A256 carriageway to the east of the former Power Station site. These then run to the north of the former Power Station site and for part 117 of their length, parallel to Minster Stream. These foul sewers continue north until reaching the southern corner of Weatherlees Hill Wastewater Treatment Works. This is the foul flow inlet feed from the urban areas of Sandwich to the south. Private Drainage 7.42 The former Richborough Power Station site does not connect surface water to a public network. The area is drained via a private on-site drainage network with direct discharges into the surrounding land drains and the River Stour to the south and west. 7.43 A 1,200mm diameter outfall from the existing concrete apron area to the west of the power station site is approximately 220m west of the Laydown Area on the northern bank of the River Stour. It is unlikely that all existing site drainage will be directed to this point due to the site levels. This outfall is indicated as having an invert level of – 0.33m AOD suggesting it would be tide locked on a regular basis. 7.44 The Laydown area is within the eastern portion of a wider concrete apron that has a fall westward to a 400mm outfall approximately 80m west of the southwest corner of the proposed access road around the Laydown Area. This outfall is shown leading to a pump house and tank. 7.45 Outfalls to the north and east of the power station site will discharge into the minor unclassified watercourses that lead to Minster Stream. 7.46 There are five discharge consents from the former power station site as identified in the Envirocheck Data contained as part of a Phase 1 Environmental Study (Appendix 6.1). These are shown at Table 7.11 below: Table 7.11: Discharge Consents from the Former Richborough Power Station NGR Issued Date 633200,1 June 62100 1985 633160,1 July 1993 62060 Revoked Date August 1999 633050,1 62150 633050,1 62150 633050,1 62150 August 1999 Trade Effluent August 1999 Sewage Discharges – Final/ Treated Effluent Trade Discharges – Cooling Water June 1985 June 1985 June 1985 March 1997 August 1999 118 Discharge Type Trade Discharges – Cooling Water Trade Discharges – Cooling Water Discharge Into Saline Estuary Freshwater Stream/ River Saline Estuary Saline Estuary Saline Estuary 7.47 The Envirocheck Data also contains details of surface water abstractions within 1km of the site. These are listed in Table 7.12 below. Each of these permitted abstraction locations are for agricultural supplies and are located along the Minster Stream upstream (northwest) of the cable route, substation and converter station sites. The nearest abstraction point to the Proposed Development is located approximately 100m northwest of the proposed horizontally drilled section of the onshore cable route and 125m north of the converter station site. Table 7.12: Surface Water Abstraction Consents NGR Issued Date 633430, 16-03-11 162330 20-10-06 633270, 16-03-11 162750 20-10-06 633150, 13-02-09 163000 01-12-06 01-12-06 01-12-06 17-05-89 632700, 20-10-06 163000 Operator Abstraction For St Nicholas Court Farms Ltd Dyas Farms 1988 Ltd St Nicholas Court Farms Ltd Dyas Farms 1988 Ltd Mr T Robertson Messrs Robertsons Mr Sg Robertson Mr P.E. Dyas Mrs B.E. Young Mr Sg Robertson General Agriculture: Spray Irrigation Abstraction From Point A, Watercourse At Ebbsfleet. General Agriculture: Spray Irrigation Point B, Watercourse At Ebbsfleet. General Agriculture: Spray Irrigation Point R, Watercourse At Ebbsfleet. General Agriculture: Spray Irrigation and Storage Points A-C, Minster Stream & Tributaries At Minster Marshes Surface Water Quality 7.48 The nearest historic water quality monitoring records available on the EA web based database are for the River Stour at Plucks Gutter approximately 6km west of the former power station site. This is within the non-tidal section of the river and not representative of the tidally influenced section in the vicinity of the former power station site. The EA classification of the water quality at the closest compliance point, 3km downstream of the former Power Station site, is Grade B (good). 7.49 Three Local Authority Pollution Prevention and Controls are noted within the Envirocheck Report (Appendix 6.1). Of these licences, two are shown to be associated with petrol filling stations within a 100m radius of the site. 7.50 Within a 500m radius of the site, there are nine records of Pollution Incidents to Controlled Waters, as detailed in Table 7.13 below: 119 Table 7.13: Summary of Pollution Incidents to Controlled Waters Incident Date Nov 1995 Dec 1999 Oct1994 Dec 1999 Feb 1997 June 1992 Sep 1999 May 1997 April 1993 7.51 Distance From Site (Approximate Direction) 14m (Southwest) Car Park 38m (South) Behind Texaco Garage 132m (South) BP Service Station 176m (South) Pfizer Sports Ground (BayPoint sports complex) 317m (West) 349m (South) Shipyard 398m (South) 420m (South) 428 m (East) Water Company Sewage Outfall Receiving Water Incident Severity Not given Minor Incident Not given Minor Incident Crude Sewage Not given Minor Incident Organic Chemicals – Diesel Fuels (Pipe failure below ground Potential River Significant Incident Unknown Sewage Not given Minor Incident Not given Minor Incident Pollutant Tip Leachate (Culvert discharging orange liquid into stream) Organic Chemicals – Mixed / Unidentified / Waste Mineral and Synthetic Oils Rubble Litter or Solids – Building Debris Deposited on Saltings Organic Chemicals – Paints / Varnishes Potential River Chemicals Unknown Not given Oils Not given Minor Incident Minor Incident Minor Incident Of these incidents, the most pertinent relates to the emergence of leachate materials 14m from the onshore cable route which is associated with a landfill within Pegwell Bay Country Park and a significant pollution incident within the former Pfizer Sports Ground (Baypoint sports complex) associated with the failure of an underground pipe releasing diesel. Flood Risk 7.52 EA online flood maps show the proposed converter station and substation within the former Richborough Power Station site are within an EA Flood Zone 1 area (low risk of flooding). The River Stour (Kent) IDB confirmed that it is not aware of any recent history of flooding in the area. 120 7.53 From the proposed Transition Joint Pit southward to the northern extent of the Pegwell Bay Country Park as well as the section of route following the Thanet Coastal Path are shown to be within the tidally influenced Flood Zone 3 (High Risk) – see Appendix 7.1, FRA Figure 8. The section from the Coastal Path to the proposed joint position (Location C) is within Flood Zone 2 (Medium Risk). From Location C southwards to Stonelees Cottage and Location D (within the Baypoint sports complex sports fields), the route is shown to be within Flood Zone 3. The remaining section of the cable route is within Flood Zone 1 (low risk) with the exception of the section immediately adjacent to the Minster Stream that is indicated as lying within Flood Zone 2 (based on historic flood event mapping). 7.54 The Flood Risk Assessment (Appendix 7.1) clarifies the extent of the flood risk zones and assesses the risk of flooding on the development as well as the potential effect of the development on flood risk. The EA flood map is provided in Figure 7.2. 7.55 The FRA considered the following flood risk elements as defined as the ‘Forms of Flooding’ by BS 8533. These are: Flooding from Rivers (fluvial flood risk); Flooding from the Sea (tidal flood risk); Flooding from Land; Flooding from Groundwater; Flooding from Sewers (sewer and drain exceedance, pumping station failure etc); and Flooding from Reservoirs, Canals and other Artificial Structures. 7.56 The FRA concluded that the principal flood mechanism for the area within and surrounding the application boundary (cable route as well as converter station and substation locations) is that of tidal flooding both directly from the coast and from the upstream tidal sections of the River Stour. 7.57 Table 7.14 outlines EA flood level data for the ‘defended’ (predicted flood levels considering the influence of flood defence structures). The EA Node locations are shown on Figure 7.3. 7.58 In general, the ground levels along the cable route are below predicted extreme tidal flood levels at the northern end of the cable route and at the TJP. This is indicated by positive values in Table 7.14. Ground levels rise above flood levels (negative values in Table 7.14) for the main section of the cables route, except for a small section close to the power station that will dip below flood levels. This area is the section that will be horizontally directional drilled (HDD) beneath Minster Stream. 7.59 The A256 bypass is considered to partially mitigate the direct coastal flood risk to the converter station site and substation site for current events and predicted extreme events up to the 1 in 1,000 year tidal flood event with climate change to 2070. Following the implementation of the proposed coastal flood defence schemes in tandem with the A256 works now in place, the coastal flood risk to the converter station and substation site will be mitigated for current events and predicted events up to the 1 in 1,000 year tidal flood event with climate change to 2070. 7.60 However, given that the proposed flood defence works do not form part of the current baseline situation, the FRA considers the potential impact to the site of two 121 locations where it is considered likely that overtopping of the A256 could result in the inundation of the land to the west and potentially the converter station and substations site. 7.61 The nearest tidal flood level to the site is EA Node 29. Based on the current 1 in 1000 year flood level of 4.366mAOD, the impact of climate change, as defined within the NPPF Technical Guidance, would result in an increase in the current tidal flood level to 4.857mAOD (+491mm, refer to Section 7.22). 7.62 The first ‘overtopping location’ is along Sandwich Road close to Node 29 as predicted by the EA modelling for the 1 in 200 and 1 in 1,000 year tidal events. Floodwaters would cross the road and flow west to the Stonelees golf course. The LiDAR information suggests a low point close to the access to the existing sewage treatment works that could direct the flood flows south towards Minster Stream and the site. With the construction of the bypass partly as an elevated structure and incorporating a raised bund along the eastern side, the low point is effectively closed at this point with the exception of land drainage and culverts beneath the new road that link drainage to the Minster Stream. Floodwaters would, as a result, be contained within areas to the north and east of the bypass (including the golf course). 7.63 The second ‘overtopping location’ is the Kingfisher Sluice to the east of the former power station site. The topography suggests that a flood surge at a level 4.857mAOD would just overtop (by around 50-100mm) the ground around and above the sluice and be conveyed west upstream along Minster Stream and also the lower ground to the immediate south of the stream( as indicated as occurring during the 2000 and 2001 flood events). Any overland flood flow that does not enter and is contained by the stream would flow west towards the A256 roundabout at the access to the former power station site. The flood depths would be very shallow as the hard standing levels are flat and any floodwater would be spread across a wider area. In a similar way to surface water flooding caused by extreme rainfall exceeding pipe and gully capacities that may lead to shallow flooding close to the Richborough Roundabout, the tidal event flooding would be much more rapid but likely to be contained within the highway by the kerbs. This is not viewed as a significant flood pathway and at the most leads to only shallow localised flooding around the Port Richborough site and roundabout. 7.64 There are a number of EA modelled flood levels alongside the southern boundary of the site associated with the River Stour. As with the other levels, the increased risk for the extreme event due to climate change has not been modelled by the EA. The appropriate EA data Nodes (Figure 7.3) with identified flood levels are Nodes 8, 20, 21, 22 and 23 as detailed in Table 7.15; climate change effects are also shown in this table. When considering the application of climate change effects on these flood levels the following predicted flood levels above Ordnance Datum (AOD) could be inferred from the NPPF calculation. 122 Table 7.14: Predicted Flood Levels Location Location A – Transition Joint Pit (Figure 7.3 - EA Node 45) Location B – To north of Country Park where cycle track meets Sandwich Road (TR34356363) (Figure 7.3 - EA Node 39) Location C – Joint Pit to west of Country Park car park and access (TR34256348) (Figure 7.3 - EA Node 36 – nearest with level data) Location D – South of Country Park in northern corner of Stonelees Nature Reserve (Figure 7.3 - EA Node 29) Location E – Joint Pit within Sports Ground for HDD (Figure 7.3 - EA Node 29 – nearest with level data) Location F – Exit of HDD within former power station site (Figure 7.3 - EA Node 29 – nearest with level data) Laydown Area – within concrete apron (Figure 7.3 - EA Node 8) River Stour – Southwest of Converter Station (Figure 7.3 - EA Node 20) Predicted Tide Flood Levels – Defended (m AOD) 1 in 1 in 200 1 in 200 (2070) 1,000 (2010) Existing Ground Level (m AOD) Water to Ground Level Difference 1 in 1,000 year event (max. m + / -) 4.540 5.035 5.040 3.000 +2.040 4.544 5.030 5.037 5.000 +0.037 2.183 3.703 3.710 4.800 -1.090 4.152 4.355 4.366 4.700 -0.334 4.152 4.355 4.366 4.700 -0.334 4.152 4.355 4.366 3.500 0.866 None 2.772 2.654 2.070 -0.702 2.438 2.846 2.866 3.210 -0.344 123 River Stour – South of boundary of Converter Station and Substation sites (Figure 7.3 - EA Node 21) River Stour – South of boundary of Substation site and Laydown area (Figure 7.3 - EA Node 22) River Stour – West of Laydown area (Figure 7.3 - EA Node 23) 2.400 2.826 2.846 3.010 -0.164 2.401 2.823 2.842 2.650 0.192 2.402 2.829 2.849 2.750 0.099 Table 7.15: Predicted Flood Levels (Tidal River Stour) EA NODE Ref. 8 20 21 22 23 0.5% Flood Level (1 in 200 year event – EA model) (m) 2.438 2.400 2.401 2.402 0.5% Flood Level + CC (1 in 200 year event with climate change - EA) (m) 2.772 2.866 2.846 2.842 2.849 0.1% Flood Level (1 in 1,000 year event – EA model) (m) 2.654 2.846 2.826 2.823 2.829 0.1% Flood Level + CC (1 in 1,000 year event with climate change - NPPF) (m) 3.145 3.337 3.317 3.314 3.320 NB all levels quoted in the above table will be subject to +/- 150mm EA model tolerances. 7.65 Although much of the main former power station site (including the converter station and substation sites) is bounded to the south by a concrete wall approximately 1m in height, the wall does not extend the full length of the area adjacent to the river and in particular the laydown area. The anticipated extreme flood would overtop the southern boundary at this location and inundate the existing concrete apron area and floodwaters would flow north and east across parts of the areas within the substation site (based on the topographical levels supplied). Figure 7.4 shows the topographical survey overlain with the proposed site layout and annotated with the predicted extent of the extreme event flooding. Groundwater 7.66 Groundwater is considered in detail in Chapter 6, Ground Conditions and Contamination and is summarised in this chapter. 7.67 The EA online groundwater map (Figure 7.5), which is based on the British Geological Survey Aquifer data, illustrates that the application site (cable route and proposed converter station and substation site) is not located within an EA Groundwater Source Protection Zone (SPZ). This was confirmed by the EA within Thanet District Council’s EIA Scoping Opinion. 124 7.68 The Marine Beach Deposits underlying approximately the northern two-thirds of the cable route are designated as a Secondary (undifferentiated) aquifer whilst the Marine and Estuarine Alluvium underlying the southern section of the cable route and the proposed converter station and substation site are designated as Unproductive Strata. Where Storm Beach Deposits are present (beneath BayPoint sport complex) these have been classified as a Secondary A aquifer. 7.69 The underlying Thanet Sand Formation (which outcrops to the east of the former power station site in the vicinity of Sandwich Bay to Hacklinge Marshes SSSI) is classified as a Secondary A aquifer whilst the underlying White Chalk Sub-group has been classified as a Principal aquifer. 7.70 Secondary A aquifers are identified on the EA website as ‘permeable layers capable of supporting water supplies at a local rather than strategic scale, and in some cases forming an important source of base flow to rivers’. These are generally aquifers formerly classified as minor aquifers. 7.71 The shallow aquifer within the superficial deposits (predominately the cable route) has been classified with a High vulnerability rating whilst the outcrop of the Thanet Sand Formation (former Power Station site) has been classified with an Intermediate vulnerability rating. 7.72 Whilst the cable route crosses a sensitive area with respect to groundwater, in the vicinity of the cable route, substation and converter station sites, shallow groundwater is unlikely to form an important resource for potable supply owing to saline intrusion. The published hydrogeological map for the area (Institute of Geological Sciences, ‘hydrogeological Map of the Chalk and Lower Greensand of Kent) indicates Chloride concentrations within the White Chalk aquifer to be approximately four times greater than the limit specified within the UK’s Drinking Water Standards. 7.73 The Envirocheck Data contained as part of a Phase 1 Environmental Study (Appendix 6.1) includes details of the two permitted groundwater abstraction consents at a single location within 1km of the site. Both consents are for a single location for general farming use and domestic supplies. These are listed in Table 7.16 below. The location of this well is approximately 815m due north of the former Power Station site and 660m from the closest part of the on-shore cable route (at the southern tip of the Pegwell Bay Country Park). Table 7.16: Groundwater Abstraction Consents NGR Issued Date 633240, 01-04-08 163090 18-02-93 Operator Abstraction For Abstraction From Mr J R S Tapp General Farming And Domestic Borehole At Ebbsfleet Farm Chardon Developments Ltd 125 Prediction and Assessment of Significance of the Potential Impacts 7.74 The key components of the development are detailed in Chapter 2, Project Description. The greatest risks of potential effects to the water environment would occur during the construction phase. The main construction activities that may give rise to effects on the water environment include; temporary access roads, transportation of construction materials to both the onshore cable works as well as the works within the former Power Station site (substation and converter station sites); excavation of cables trench, HDD and associated excavation of launch and receptor pits and construction traffic. Construction Effects – General 7.75 The following potential effects on the water environment have been identified: 7.76 Hydrological change, including potential disturbance and modification of watercourses, existing drainage patterns, overland flow routes and groundwater recharge and flows; An increase in surface water overflow as a result of changes in impermeable area; Sediment or chemical pollution of watercourses and land drains during construction; Interruption or disturbance of public or private water supplies; Effects on aquatic ecology due to pollution, obstruction of land drains and watercourses or change in hydrological regime; and Disturbance and alterations to existing flood defences and floodplain. The construction of impermeable surfaces will have a number of potential effects to the water environment. The main effects would relate to: Site drainage; Surface water flow route; Increased surface water discharge volume into nearby drains, the River Stour and Minster Stream; Possible contamination of nearby drains and watercourses due to runoff from impermeable surfaces during construction; and Mobilisation of silt and materials during sudden rainfall events, if not controlled, will be conveyed to the surrounding ditch network. Construction Effects – Surface Water 7.77 The use of HDD is proposed for the section of cable between the sports fields (at BayPoint sports complex) and the converter station site. This is proposed to avoid surface disturbance of a newly constructed roundabout on the A256, avoid disturbance to Minster Stream and also avoid disturbance to a compartment of the Sandwich Bay to Hacklinge Marshes Site of Special Scientific Interest (SSSI). The embedded mitigation in terms of hydrology is that the cable route is to pass beneath the Minster Stream and the flood risk zone associated with the low lying ground immediately adjacent to the watercourse. The installation of the cables will not require modifications (temporary or permanent) to the stream or interruptions in its flow. The HDD will also pass beneath the minor watercourse identified by the IDB. As a result, the magnitude of impact related to blockage or disturbance to the 126 watercourses and their hydrology is low. The sensitivity of the watercourses is high, therefore the overall impact is minor adverse. 7.78 Impermeable areas associated with the cable route will be created as a result of construction compounds and other associated infrastructure. As a result, less rainfall is able to infiltrate into the ground, which will lead to an increase in surface water runoff. As the construction compounds will only be temporary during the construction phase and will be limited in footprint, the magnitude of effect is therefore classed as low. The sensitivity of the River Stour, Minster Stream, local ditches, SSSI, tidal ponds and BayPoint sports complex pond are classed as high in terms of flood risk. The overall significance of effect is classed as minor adverse. 7.79 Impermeable areas associated with the works within the former Power Station will be dependent on the method of construction and extent of new hard standing, roadways and buildings. The areas within the former Power Station site (predemolition of the cooling towers) to be occupied by the laydown, converter station and substation sites, based on the topographical survey, have a high existing proportion of hard standing (buildings, towers, roadways and hard surfaces) accounting for approximately 82% of the total area. 7.80 The levels on the converter station and substation sites and infilling of voids and other structures are to be provided by the import of materials (achieving a 6F2 grading). It is considered that the filling material, once compacted, will represent a reasonably impermeable surface and thus generate a high proportion of surface water runoff during rainfall events. Table 7.17 identifies the anticipated changes in permeable surfaces. 7.81 The resultant impermeable areas associated with the substation and converter station works will have varying degrees of magnitude dependent on the existing ground conditions. Table 7.17 has been annotated to include an assessment of the magnitude of change. The magnitudes of the effect are therefore classed as between negligible and medium. The sensitivity of the River Stour, Minster Stream, local ditches, SSSI, tidal ponds and BayPoint sports complex pond are classed as high in terms of flood risk. The overall significance of the effect is classed as between minor to moderate adverse. 7.82 Four surface water abstraction locations have been identified along Minster Stream upstream of the cable route, laydown area, converter station and substation sites. These abstractions are classed as high sensitivity receptors. The magnitude of effect due to discharges from or change to the drainage of any part of the works is negligible. The overall significance of the effect is classed as minor adverse. 127 Table 7.17: Impermeable Areas Site Laydown Site Substatio n Site (main area) Substatio n Site (North eastern area) Converte r Station Site Total Area (Ha) 1.62 Impermeable Area (Ha) 2.64 2.16 (access roads, cooling towers, buildings) 0.27 (buildings and access roads) 82 3.65 (access roads, cooling towers, buildings – assumed as topographical survey does not fully identify surfaces) 75 0.30 4.85 1.62 (concrete apron) % Impermeable Area 100 90 Proposed Impermeable Area (Ha)* 1.62 (access and retained apron areas) 2.64 (in-filled towers, realigned accesses etc) 0.3 (access road, car park, buildings etc) Proposed % Impermeable Area 100 Magnitude of Impact 100 (assumed subject to detail design) Low 100 (possible landscaped area could be introduced) Low 4.85 (assumed whole site raised by DoT Type 2 or 6F2 fill) 100 Medium Negligible NB Proposed values in the table above assume ‘impermeable’ characteristics of fill material based on Mott MacDonald DoT Type 2 specification 7.83 There is a potential effect on the overland flow routes being disturbed due to construction compounds, materials storage and open trench work. Diverted flows can interrupt the existing drainage pattern and result in surface water draining to other areas. The potential effects are likely to be short-term and the magnitude of effect is classed as medium. The local receiving catchments and downstream environment is principally the Country Park, SSSI and the areas immediately around the substation and converter station sites. Therefore; the receptor sensitivity is classified as high related to changes in surface water flow rates. The overall significance is classed as moderate adverse. Construction Effects – Water Quality 7.84 There is a potential risk of contamination of the local drains and watercourses with silt-laden run-off. Silt-laden run-off can be generated during the construction phase from a variety of sources including excavation works, dewatering activities, washing plant and equipment and runoff from material stockpiles. Run-off can be exacerbated by compacted and bare earth and is generally instigated by rainfall. Surface-water run-off with high silt content can flow overland or via existing drainage pathways into watercourses and water bodies where adverse effects may occur including into the River Stour, Minster Stream and Pegwell Bay. When runoff enters watercourses, the elevated levels of suspended solids may cause siltation within aquatic ecosystems, resulting in the removal of oxygen from the water column and have indirect impacts on fish, invertebrates and plants. Although the potential effects are likely to be localised and short-term, the magnitude of effect is classed as medium. The tidally influenced River Stour, Minster Stream, Pegwell Bay and other ditches are classed as high sensitivity receptors. The overall significance of potential effects is classed as moderate adverse. 128 7.85 To a lesser degree, the potential risk of accidental spillages of construction materials, drilling fluids, oils and fuel will be present. Cement, in particular, if leached into a watercourse or water body, will potentially have detrimental effects by drawing oxygen from the water which could have a significant knock-on effect on aquatic ecosystems by causing deterioration to the local water quality. In addition, there is the potential for historic contaminates to be exposed and potentially released (washed out) by shallow groundwater or rainfall events. The magnitude of effect is considered to be low. The nearest water quality information available is for the River Stour (which is tidal and saline); this information indicates a ‘good’ water quality class and is therefore a receptor of high sensitivity. In the absence of quality data for the local ditches and Minster Stream, these are also classed as having high receptor sensitivity. The overall significance of the effect is minor adverse. 7.86 The surface water bodies close to the cable route include the balancing pond for the bypass, which will be a low sensitivity body (as it is designed to accommodate potentially contaminated runoff from highways), two salt-water tidal ponds and the pond within the BayPoint sports complex. With the exception of the balancing ponds, these water bodies are classed as medium sensitivity receptors based primarily on ecological value and their establishment over a number of years. The magnitude of either pollution or accidental spillage from any works associated with the cable route, which passes close to the BayPoint sports complex pond, and tidal ponds will be medium due to their close proximity and potential direct surface water runoff linkage between the cable works and the ponds. The overall significance of effect is moderate adverse. 7.87 The magnitude of either pollution or accidental spillage from works associated with the converter station and substation construction will be low due to the separation of these works from the ponds and interception of surface waters by the local ditch networks. The overall significance of this effect is negligible. Construction Effects – Groundwater 7.88 Similar to the potential effects identified for surface water, spills or leaks of fuels, oil and building materials may have the potential to contaminate groundwater if a pathway is present. 7.89 As there will be foundation construction works required for the TJP and excavations for the HDD sections, vertical migration pathways through the superficial geology may be introduced allowing surface contamination to affect the deeper groundwater regime during excavation. The excavation will however be limited in depth (maximum around 3m with the main trench works between 1-2m), with foundations restricted to the bases of the structures (including the substation and converter station). The potential effect on groundwater quality is therefore considered to be low. The site is not located within the EA designated Source Protection Zone nor within major aquifers; the receptor sensitivity is therefore also classed as low. The overall significance of effect is negligible. 7.90 Works within the converter station and substation sites will include foundations for new buildings as well as new drainage and utility trenches. In addition, fill operations will be undertaken to provide suitable construction platform levels. Groundwater is anticipated to be shallow and could be exposed during works on these sites. The potential effect on groundwater quality is considered to be low. The site is not 129 located within the EA designated Source Protection Zone nor within major aquifers, the receptor sensitivity is also classed as low. The overall significance of effect is negligible. 7.91 One groundwater abstraction point has been identified approximately 815m due north of the former Power Station site and 660m from the closest part of the onshore cable route. As discussed above, the potential effect on groundwater quality is considered to be low. The abstraction is classed as a high sensitivity receptor. The overall significance of effect is minor adverse. Construction Effects – Flood Risk 7.92 Trench excavation works close to the TJP will be within Flood Zone 3 (high flood risk, tidally influenced) with other sections of the cable works within Flood Zone 2 (medium risk). The potential effect of any stockpiling of excavated materials or storage will be short-term with a low magnitude in terms of water displacement and unlikely to alter the extent of the tidal flooding by any perceptible amount. The receptor in this case is the Flood Zones 2 and 3 and can be classified as medium as works are short-term and can be re-programmed to take account of weather and tide conditions. The overall significance of effect is considered to be minor adverse. 7.93 The laydown area will be within Flood Zone 2 (medium flood risk, tidally influenced). The potential effect of any stockpiling of excavated materials or storage will be short-term with a low magnitude in terms of water displacement and is unlikely to alter the extent of the tidal flooding by any perceptible amount. The receptor in this case is the flood zone and can be classified as medium as works are short-term. The overall significance of effect is considered to be minor adverse. 7.94 For the main converter station and substation sites, the flood risk is classed as low. The potential effect of any stockpiling of excavated materials or storage will be short-term with negligible magnitude in terms of water displacement and unlikely to alter the extent of the tidal flooding by any perceptible amount. The receptor in this case is the workforce and the trenching work during construction and can be classified as medium as works are short-term and can be re-programmed to take account of weather and tide conditions. The overall significance of effect is considered to be negligible. Operational Effects 7.95 Activities following construction will be limited to a small operational presence on the converter station and substation sites, with the exception of occasional maintenance and site inspection. However, there are some activities, which could pose a potential risk to the local water environment; these are discussed below. Operational Effects – Surface Water 7.96 There is a potential risk of increased surface water runoff from the substation and converter station site into the local watercourses and drains during storm events. This has the potential to cause localised flooding and increase the risk of flooding downstream. 7.97 The magnitude of this effect for the cable route is considered to be negligible with very small development footprint associated with the Transition Joint Pit. The 130 sensitivity of the receptors, Pegwell Bay is considered low in terms of surface water volumes. As a result, the overall significance of effect is considered to be negligible. 7.98 The impermeable areas associated with the substation and converter station works will have varying degrees of magnitude dependent on the existing ground conditions. Table 7.17 has been annotated to include an assessment of the magnitude of change in impermeable surfacing. The magnitudes of the effect are therefore classed as between negligible (laydown area) and medium (converter station and substation sites). The sensitivity of the River Stour, Minster Stream, local ditches, SSSI, tidal ponds and BayPoint sports complex pond are classed as high in terms of flood risk. The overall significance of the effect is classed as between minor to moderate adverse. Operational Effects – Water Quality 7.99 There is the potential for spills or leaks of fuel and oil to be deposited by vehicles accessing the site during the maintenance operation. This accidental spillage of fuels, oils and lubricants has the potential to cause pollution of the watercourses. Maintenance visits will be carried out infrequently. The magnitude of effect is considered to be low. The receptors are the River Stour, Minster Stream, local watercourses, SSSI, tidal ponds and BayPoint sports complex pond with a high sensitivity in terms of water quality impacts. The overall significance of effect is minor adverse. 7.100 For the substation and converter station sites the principle influence on water quality would be the new runoff from roadways and new access roads within the development. Untreated runoff from these surfaces could contain a number of pollutants deposited by vehicles (rubber from tyres, oil and fuel, metals etc.) as well as provide a route for runoff from storage areas. As the internal operational traffic is anticipated to be of low volumes, the magnitude of effect is considered to be low. The receptors are the River Stour, Minster Stream, local ditches, SSSI, tidal ponds and BayPoint sports complex pond with a high sensitivity in terms of water quality impacts. The overall significance of effect is minor adverse. 7.101 With operational staff present on the converter station and substation sites, there is a requirement to provide foul drainage to a number of the buildings. The proposal is to contain the flows with septic tanks and regular off-site disposal. There will be no direct linkages to watercourses but spillages could be mobilised by rainfall to the surface water drainage networks within the sites and ultimately to the River Stour to the south or local ditches and Minster Stream to the north. The quantities involved will be low. The sensitivity of any of the receiving watercourses is high. The overall significance of effect is minor adverse. 7.102 Some of the components (e.g. transformers) within the substation and converter station sites contain oils and lubricants as well as other potential contaminant materials. The transformers are likely to be plumbed to an underground dump tank; a containment system will be adopted to ensure risk of spillage is minimised in accordance with the Pollution Prevention Guidelines. There are no direct linkages to watercourses but spillages due to extreme rainfall events and poor maintenance of the containment areas could mobilise pollutants to the surface water drainage networks within the sites and ultimately to the River Stour to the south or local ditches and Minster Stream to the north. The quantities involved will be low and the 131 combination of events required leading to a spillage would reduce the potential for harmful releases. The sensitivity of any of the receiving watercourses (River Stour to the south or local ditches and Minster Stream to the north) is considered high. The overall significance of effect is minor adverse. Operational Effects – Groundwater 7.103 Similar to the potential effects discussed for surface water, there is a potential risk that contaminants from spills or leaks or fuels and oils, may enter the superficial geology and reach the groundwater. As there will be limited traffic anticipated during the operational stage, with only maintenance works to be undertaken and small numbers of staff movements, the magnitude of effect is considered to be negligible. Groundwater in the area is not within any EA designated Source Protection Zones or major aquifer zones, and is therefore classed as having a low sensitivity. The overall significance of effect is negligible. Operational Effects - Flood Risk 7.104 As there are no above ground structures associated with the cable route, flood risk will not be affected by proposed cables works. The magnitude of effect is considered to be negligible. The sensitive receptors to flood water level changes will be the Country Park, which is classified as of high sensitivity. The overall significance of effect is minor adverse 7.105 For the substation and the converter station sites, the new impermeable areas would be within the former Power Station site. These works are within a low flood risk (Flood Zone 1) area. For the current predicted flood events up to and including the 1 in 1,000 year tidal flood, the magnitude of effect is considered to be negligible. In accordance with CIRIA C688 - Flood Resilience and Resistance for Critical Infrastructure (2010) the substation and convertor station are considered to be CAT 5 and CAT 3 installations respectively, which are defined as high sensitivity receptors in accordance with the definitions set out within Table 7.6. The overall significance of effect is minor adverse 7.106 The predicted flood risk in the longer term (climate change to 2070) increases the area within the substation and the converter station sites potentially affected by extreme flooding (see Figure 7.4). The predicted depths of floodwater are relatively shallow across much of the site and as a result the magnitude of effect is considered to be high in terms of maintaining a resistant (unaffected) site and medium in terms of maintaining a restricted operational site. The receptors being the CAT 5 and CAT 3 installations involved on the substation (CAT 5) and the converter station (CAT 3) sites are both considered high sensitivity receptors. The overall effect is therefore major adverse for the substation site (CAT 5 installation) and moderate adverse for the converter station site (CAT 3). 132 Summary of Potential Effects Table 7.18: Potential Effects Effects Magnitude of Effects Construction Effects Surface Water Blockage or Low disturbance to watercourses Increase in surface Low water runoff from impermeable surfaces – Cable Route compounds and storage areas Increase in surface Negligible to water runoff from Medium impermeable surfaces – Converter Station and Substation sites Construction Medium material stockpiles and operations changing overland flood flow pathways Impact on Surface Negligible Water Abstractions Water Quality Risk of silt-laden Medium water entering the local drainage system Accidental spillage Low of construction materials into nearby watercourses Risk of silt-laden water or accidental spillage of construction materials into nearby water bodies – bypass balancing pond Low 133 Receptor Sensitivity Overall Significance of Effect High Minor – Adverse High Minor – Adverse High Minor – Adverse to Moderate Adverse High Moderate Adverse High Minor – Adverse High Moderate Adverse High Minor – Adverse Low Negligible Effects Risk of silt-laden water or accidental spillage of construction materials into nearby water bodies – Tidal Ponds and BayPoint sports complex pond Groundwater Contamination to groundwater through vertical migration Impact on Groundwater Abstractions Flood Risk Construction works within flood risk areas (Flood Zones 2 and 3) – Cable Route Construction works within flood risk areas (Flood Zone 2) – Laydown Area Construction works within flood risk areas and impact on works and workers – Converter Station and Substation sites Overall Significance of Effect Moderate – Adverse Magnitude of Effects Receptor Sensitivity Medium Medium Low Low Negligible Low High Minor – Adverse Low Medium Minor – Adverse Low Medium Minor – Adverse Negligible Medium Negligible Low Negligible/None High Minor – Adverse to Moderate Adverse Operational Effects Surface Water Increase in surface Negligible water runoff due to new impermeable surfaces – Cable Route Increase in surface Negligible to water runoff due to Medium new impermeable surfaces – Substation and Converter Station Sites 134 Effects Water Quality Accidental spills or leaks of fuels from maintenance vehicle Changes in drainage network and new surfaces with vehicle use Staff requirement for foul water drainage Drainage of bunded areas Groundwater Effects of spills and leaks to groundwater Flood Risk Introduction of cable route structures within identified high risk flood zones Introduction of substation and converter station structures within identified high risk flood zones – current flood zones Introduction of substation and converter structures within identified high risk flood zones – climate change effects Magnitude of Effects Receptor Sensitivity Overall Significance of Effect Low High Minor – Adverse Low High Minor – Adverse Low High Minor – Adverse Low High Minor – Adverse Negligible Low Negligible Negligible High Minor – Adverse Negligible High Minor – Adverse Medium to High High Moderate – Adverse (CAT 3) to Major Adverse (CAT 5) Mitigation 7.107 If not adequately controlled, construction activities may have a number of short-term effects on the water quality of the surface water environment. Appropriate measures will be put in place prior to and during construction works in accordance with legislative requirements and good practice guidance, 7.108 Measures to prevent pollution of the water environment (including measures to control and manage silt-laden run-off, control mud deposits and prevent spillages/leaks) will be in place during the construction phase and these will be set 135 out within a Construction Environmental Management Plan (CEMP). Good practice guidance will be based on EA Pollution Prevention Guidance: Identified construction and operational effects can be effectively mitigated by planning and management of construction techniques and by incorporating mitigation measures in the final design of the Proposed Development. 7.109 Potential environmental effects and any necessary mitigation measures have been identified as a result of information received from data collection and knowledge of the effects and appropriate mitigation measures from similar construction projects. 7.110 Many of the short-term effects arising from the Proposed Development can be effectively mitigated by adopting construction techniques and practices outlined in a CEMP based on addressing the EA Pollution Prevention Guidance (PPG) as listed below: 7.111 PPG 1 – General guide to the prevention of pollution; PPG 2 – Above ground oil storage tanks; PPG 3 – Use and design of oil separators in surface water drainage systems; PPG 4 – Treatment and disposal of sewage where no foul sewer is available; PPG 5 – Works and maintenance in or near water; PPG 6 – Pollution prevention guidance for working at construction and demolition sites; PPG 7 – Refuelling facilities; PPG 8 – Safe storage and disposal of used oils; PPG 13 – Vehicle washing and cleaning; PPG 18 – Managing fire water and major spillages; PPG 20 – Dewatering underground ducts and chambers; PPG 21 – Pollution incident response planning; PPG 22 – Dealing with spills; and Managing concrete wash waters on construction sites guidance. The CEMP will set out methods which contractors will be required to undertake as a minimum. The following measures will be included in the CEMP: Where feasible, suitable construction techniques will be adopted to ensure that no migration pathways are created to jeopardise groundwater quality; Appropriate storage and handling measures for all hydrocarbon fuels and lubricating oils, including the use of bunded storage areas or the use of doubleskinned storage tanks; The use of drip trays for static plant and designated refuelling areas for mobile plant; The implementation of appropriate spillage contingency measures to mitigate the effect of such spillages on the surface water; and Appropriate personnel awareness training of the potential environmental implications of all construction work on site. The prevention of silt-laden run-off and mud entering the surrounding surface water drains and watercourses by: o Timely site phasing and engineering, thus minimising un-surfaced and unvegetated areas of the site; o The provision of measures to intercept and treat run-off prior to it leaving site, including the use of peripheral cut-off ditches, settlement facilities, 136 o 7.112 To minimise the risk of spillages resulting in a serious pollution incident, a Storage and Spillage Emergency Response Plan will be in place, which will include: 7.113 filtration and/or use of flocculants to effect the removal of water borne particulates; and The provision of wheel-cleaning equipment for site plant to prevent the tracking of mud onto the public highway and therefore into the off-site surface water drainage systems. The storage and use of fuel and oils on site in accordance with the Control of Pollution (Oil Storage) (England) Regulations 2001; Fuel and other potentially polluting chemicals stored well away from watercourses in a secure impermeable and bunded storage area (minimum capacity 110% of the storage capacity of the tank); Refuelling of plant in a designated area at the site compound only; Maintenance of vehicles in a designated area at the site compound only; Fixed plant will be self bunded and/or part of a controlled containment system in accordance with EA Pollution Prevention Guidance; Mobile plant will be in good working order, kept clean and fitted with drip trays where appropriate; Spillage kits and absorbent material will be carried by mobile plant; The site will be secured to prevent vandalism that could lead to a pollution incident; Designated concrete wash out areas will be constructed in accordance with good practice guidance and will be clearly identified and used; An Emergency Response Plan will be prepared and construction workers trained to respond to spillages; and Construction waste or debris will be prevented from entering any waterbody. Discussions with the EA and their response contained within the Thanet District Council Scoping Opinion states that the River Stour and Minster Stream are designated main rivers and are under EA jurisdiction for the purposes of its land drainage functions. Written consent is required under the Water Resources Act 1991 and associated Byelaws prior to carrying out any works to these watercourses, including works: In, over, or under the channel of these watercourses; On their banks; Within 15m of the top of their banks; and Within 15m of the landward toe of any flood defence (where one exists). Surface Water 7.114 HDD is proposed for the cables between the BayPoint sports complex sports fields and the former power station. This will avoid surface disturbance of the recently constructed roundabout on the A256, avoid disturbance to Minster Stream and also avoid disturbance to a compartment of Hacklinge Marshes Site of Special Scientific Interest (SSSI). The cable route will pass beneath the Minster Stream and the flood risk zone associated with the low lying ground immediately adjacent to the water course. Cables installation by HDD will not require modifications (temporary or permanent) to the stream or interruptions in its flow. 137 7.115 If suitable outfalls are not available for the drainage of areas within the former power station site (re-use of existing outfalls), a new outfall may be required. As such a Flood Defence Consent from the EA as described above will need to be obtained. 7.116 All utility services associated with the development, including re-use of existing surface water outfalls from the former power station site, will be designed to ensure their long-term fitness for the purpose, and will be appropriately tested prior to commission to demonstrate their integrity and maintained throughout their use. 7.117 The discharge criteria for the proposed works has been adopted based on best practice guidance and advice received from the EA. The EA has stated that they would like to see the application of Sustainable Drainage measures where possible and a consideration of the effects of high tides on submerged outfalls. As infiltration is not a viable option due to existing ground conditions and proposed infilling, storage and on-site attenuation should be considered. The overarching criterion is not to cause an increase in flood risk off site. 7.118 The following table considers the attenuation required to match the existing predicted runoff rates into the receiving watercourses. For the areas draining to the north it has been assumed that discharge will be restricted to a ‘greenfield’ rate in order to provide a worst-case estimation of the attenuation volume required. However, the greenfield flow rate falls well below the BRE recommended lower limit for effective and manageable flow control. As a result the areas are too small in isolation to require control or attenuation as the total peak flows are below 5 l/sec. Table 7.19: Discharge Rates and Attenuation (Free Discharge) Site Current Free Discharge (l/sec) 1 in 1 1 in 30 1 in 100 Discharge Limitations Proposed Discharge (l/sec) 1 in 1 in 1 30 Laydown Site 171 386 457 Free discharge to tidal water 171 386 386 0 1 47 1 in 100 +CC 61 Substation Site (main area) 232 528 634 Free discharge to tidal water 232 528 528 0 33 120 156 Substation Site (North eastern area) 0.8 2.1 3.0 Attenuated discharge to north to minor ditches 5 5 5 0 0 0 0 Converter 311 Station Site 640 771 Free discharge to tidal water 330 634 640 0 167 354 460 138 Free Attenuation Volume Existing Rates (m3) 1 in 100 1 in 1 1 in 30 1 in 100 to Comments Due to site layout – discharge may require pumping – see comments below Proposed discharge limited to existing 1 in 30 - Storage provided within site Proposed discharge limited to minimum effective controllable value of 5l/sec – BRE Proposed discharge limited to existing 1 in 30 - Storage Site Current Free Discharge (l/sec) 1 in 1 1 in 30 1 in 100 Discharge Limitations Proposed Discharge (l/sec) 1 in 1 in 1 30 Free Attenuation Volume Existing Rates (m3) 1 in 100 1 in 1 1 in 30 1 in 100 to Comments 1 in 100 +CC provided within site 7.119 For the outfalls to the south, Table 7.16 below considers the free discharge situation with Table 7.19 considering a surcharged outfall event (such that an outfall with an invert at 0.0m AOD is submerged by the extreme tidal flood level in the River Stour (approximately 2.80m AOD)). This would then generate the peak on-site storage requirements. 7.120 The proposed discharge rates listed in Table 7.20 below are the resultant flow rates taking into account the surcharging effects. Hence, the rates are lower than the free discharge rates and on-site attenuation will be required. Table 7.20: Discharge Rates and Attenuation (Surcharge Discharge) SITE Laydown Site Current Free Discharge (l/sec) 1 in 1 1 in 1 in 30 100 171 386 457 Surcharged discharge to tidal flood water (2.8m) 232 Substation Site (North eastern area) Converter Station Site Not applicable - Discharge to north to minor ditches 640 771 Surcharged discharge to tidal flood water (2.8m) Tide Locked Discharge (l/sec) 1 in 1 in 1 in 1 30 100 147 293 304 Substation Site (main area) 31 1 528 634 Discharge Limitations Surcharged discharge to tidal flood water (2.8m) 234 69 426 331 139 Tide Locked Volume(m3) 1 in 1 1 in 30 Comment s 0 38 453 0 90 1 in 100 1 in 100 +CC 92 120 Due to site layout – discharge may require pumping – see comments below 186 242 Proposed discharge control to existing 1 in 30 but tide locking effect reduces discharge Storage provided within site 397 274 1,278 1,778 2,311 Proposed discharge control to existing 1 in 30 but tide locking effect reduces discharge Storage provided within site 7.121 As can be seen from the tables above, it is the more extreme events that require accommodation on site, primarily due to the capacity constraints resulting from surcharging outfalls. This allowance also provides control of the peak discharge during non-tide locked events and meets the more sustainable goals of the drainage solution. Figure 7.6 highlights potential mitigation options. Surface Water Mitigation - Laydown Area 7.122 The Laydown Area is the eastern extent of a wider concrete apron area that extends further to the west and ultimately to the identified 400mm outfall that leads to a pumping station. The western boundary of the proposed Laydown Area will be formed by the proposed access road. In order to contain and control runoff from the temporary laydown facility and provide pollution control, it is recommended that a low bund be incorporated alongside the access road between the road and the storage areas. Due to the existing falls in the concrete apron (which are westward), an informal settlement basin would be formed. Surface water from this area can then be pumped to a suitable outfall within the main substation site or by agreement to an outfall further west. Pumping will necessitate the agreement to a suitable economic discharge rate, as pumping at the calculated free discharge rate would require large pumping equipment. The alternative would be to create a new outfall through the southern river wall and discharge into the River Stour. 7.123 The pumping option is considered the most appropriate solution due to the temporary nature of the Laydown Area. No attenuation will be required on the substation site for this flow as it will be restricted to a greenfield (and manageable) rate by the pumping operation. Calculations for this area suggest that the greenfield discharge rates would be around 11.4 l/sec for the 1 in 30 year event. If the discharge were to be restricted via pumping to this value then the maximum volume of storage required to contain the 1 in 100 year event would be approximately 800m3. If existing ground levels are to be maintained then this could result in shallow flooding at a maximum depth of around 250mm located to the south and west of the Laydown Area (mainly within the substation Laydown Area) and covering approximately 5,000m2. Lower volume storm events would be restricted to smaller areas and shallower depths. It is therefore possible to contain the flood volume within the Laydown area with careful management of the storage and handling of materials. Surface Water Mitigation - Substation Site 7.124 It is proposed to discharge surface water from this site to the tidal River Stour to the south. It should be noted that any outfall would need to pass beneath the proposed service/access road and the land between the access road and potentially require a new outfall through the river wall. Further detailed surveying of existing drainage networks is recommended to confirm or otherwise existing surface water outfall locations, conditions and suitability for re-use. 7.125 The tables above show that flow could be restricted to the 1 in 30 year existing flow rate with a nominal 156m3 of storage required on site. However, when considering the extreme tide lock situation and the surcharging of the outfall, approximately 242m3 would be required to contain the 1 in 100 plus climate change rainfall events. This storage could be provided in areas within the south of the site. The introduction of filter strips and infiltration trenches alongside the proposed roads should also be 140 considered. Although infiltration to the underlying soils will be limited, the trenches would temporarily store surface runoff before conveying flows to the main storage area prior to discharge at the 1 in 30 year rate. Thus, a sustainable approach to water management would be provided and the trench will also provide an additional level of water quality treatment prior to passing through an oil interceptor at the discharge point. 7.126 The combination of trenches alongside access roads with a potential consideration of harvesting rainwater from roof areas for use on site would reduce the total volume required to accommodate storm water runoff within any attenuation basin. It should be noted however, that the water demand from this site is small and would limit such benefits with regards to reducing total attenuation volumes. 7.127 Any attenuation basin could also serve as a reservoir for firewater storage when combined with a permanent water storage facility with back-up mains water supplies. 7.128 The part of the substation site located to the north of the converter station site may require a separate drainage system, discharging to the local minor ditches adjacent to the northern site boundary. As discussed above in Table 7.20, the rates of runoff from this area are small and on-site attenuation for this area would not be required. 7.129 The use of permeable surfacing is to be considered for the car park area within this part of the substation site and, if possible incorporate soft landscaping to the areas between the access roads, car parking and buildings. This would reduce the runoff much further and is consistent with the first principle of SuDS drainage design, which is to minimise the volume of runoff generated at source. The use of permeable paving will also enhance the pollution control provision by treating highway runoff prior to discharge. Surface Water Mitigation – Converter Station Site 7.130 In a similar way to the substation site, surface water can be attenuated by a combination of infiltration trenches alongside the access roads and a main attenuation basin to the south of the site with an outfall at the south-western corner of the converter station site. Firewater storage and rainwater harvesting could also be incorporated. The maximum total storage required, when considering tide locking of the converter station outfall, would be 2,311m3 (also allowing for climate change effects). Due to this larger volume requirement, consideration should be given to providing the main storage for the 1 in 30 year storage volume (1,278m 3) using features such as trenches and basin/s. The higher and rarer storage volumes could be contained within areas that could be allowed to flood in these rare events such as car parking and hard standing areas (areas that would not lead to increased pollution risk or affects operational plant etc.). 7.131 Water conservation measures in accordance with good practice and modern building regulations will be considered. Water Quality 7.132 The surface water drainage design is to be based on best practice guidance such as CIRIA ‘SuDS Manual’ and advice received from the EA. The EA has stated that they would like to see the application of Sustainable Drainage measures where possible 141 and a consideration of the effects of high tides on submerged outfalls. As infiltration is not a viable option due to existing ground conditions and proposed infilling, storage and on-site attenuation should be considered. The overarching criterion is not to cause an increase in flood risk off site. 7.133 Contamination related to the storage and handling of materials on site is relatively minor in nature and in accordance with the draft Sustainable Drainage Standards, would require at least three levels of treatment prior to discharge to a sensitive watercourse (River Stour identified by the EA as sensitive). These levels could be provided by: a) b) c) The infiltration trench; Settlement/containment lagoon; and Petrol interception prior to the outfall. 7.134 This methodology should be applied for both the substation and converter station sites. 7.135 For the Laydown Area, the runoff would be contained via proposed bunded areas (treatment level 1) prior to pumping. The pumped water will be passed through a containment basin (treatment level 2) located within the substation site and then through a petrol interceptor (treatment level 3) prior to discharge into the river to the south. As the flow from this site is to be limited by pumping, no additional storage should be required within the substation site. 7.136 Foul drainage will be required. The total staffing of the combined sites is very low. Flows are to be separated (substation, converter station and temporary workforce) thus reducing the total flows at any location. No discharge to the river or watercourses is to be made. A self-contained septic tank option for each site is to be provided with the effluent contained and transported off site at appropriate intervals. In the longer term, consideration will be given to linking these sources and providing a (possibly pumped) discharge to Southern Water public sewers located to the east. 7.137 A further source of potentially contaminated waters will be the oily water associated with the petrol interceptors and sumps within the main sites. Each will be a contained structure and will require off-site removal to a suitably licensed disposal facility (or ultimately to a suitable off-site foul sewer, subject to Southern Water approval). Flood Risk 7.138 Appropriate mitigation measures will be put in place during construction works in accordance with legislative requirements and good site practice guidance to prevent flooding during construction from the risks identified. 7.139 Measures will be put in place during construction to ensure that the runoff from site is not increased. Temporary drainage systems may be required to ensure that this is met. The temporary drainage systems and systems of work will also take account of the potential for overland flow from outside of the site to cause flooding on site. 7.140 Measures will be implemented during construction to prevent debris and other material entering temporary or permanent drainage systems or watercourses. This 142 can be achieved through provision of temporary drainage, construction stage SuDS, and appropriate site management. 7.141 During the construction phase, if groundwater levels are high, appropriate techniques will be utilised to mitigate the risk, such as dewatering and ground freezing. If groundwater dewatering is required, it is likely pumps will be used to abstract the water from the excavations, and it is likely that the pumped water will be discharged into the River Stour. Consent will be sought from the EA for any temporary discharge to the watercourse. 7.142 The proposed construction works will take account of the location of existing water mains and drains to ensure that construction does not impact upon these assets. Any necessary works to divert or make use of these assets will be agreed in full with the appropriate authority at the earliest opportunity and carried out in accordance with their requirements. 7.143 The FRA undertaken for the site (Appendix 7.1) has outlined a number of mitigation measures that could be adopted for this site. 7.144 The Construction management plans will include a Construction Environmental Management Plan (CEMP) and within this will be described the main construction compound locations and storage areas. Flood risk is to be part of the consideration in determining the locations of these elements of the works. 7.145 A Flood Plan will be provided for both the construction and maintenance staff as recommended in the FRA. A Flood Plan will detail appropriate actions in the event of a flood and will include suitable evacuation procedures, safe egress route and a plan showing the location of assembly points. The assembly point in this case, should be outside the floodplain, which should be located toward the west with a muster point located within the former power station site (a low flood risk area). 7.146 An important recommendation of the CIRIA C688 document ‘Flood Resilience and Resistance for Critical Infrastructure’ is the setting of resilience/resistance standards for key infrastructure based on its asset category (importance to the UK) as defined by the Cabinet Office. 7.147 C688 suggests that for a CAT 5 asset such as the proposed substation site, the target performance criteria is that the site should remain unaffected by all flood events up to and exceeding the 1 in 1,000 year event. A CAT 5 site should therefore remain in operation and be unaffected during these severe flood events. The guidance suggests that, when considering the flood profile in this area, the vital operating equipment should be raised above the prediction of the long-term flood level. The appropriate design flood level is 3.337m AOD which is the highest of the River Stour 1 in 1,000 year plus climate change levels as indicated in Table 7.13 above. This is approximately 100mm above current ground levels to the north of the substation site increasing to around 500mm at the southern end with a maximum of 890mm alongside the southwest corner of this site. 7.148 The converter station components would not fall under a CAT 5 asset but could consider a lower resilience standard. A CAT 3 classification (assets, the loss of which would affect hundreds of thousands of people) might be more suited. In this case the suggested performance level would be that the site remain unaffected by flooding up to the 1 in 200 year flood event with a restricted operational capability for 143 events up to the 1 in 1,000 year event and safe (but potentially not operational) for events in excess of the 1 in 1,000 year event. Essential operational equipment within the converter station site is to be protected during the more extreme events. 7.149 Due to inaccuracies in flood modelled data, it is normally a requirement to add a ‘freeboard’ allowance to the modelled flood levels. This freeboard would normally be 300-600mm above the flood level (normally required by the EA to be applied to the 0.5%AEP plus climate change tidal levels). As the 0.1%AEP plus climate change flood level is above the required standard of protection for the EA, the application of a freeboard on this level is likely to be discretionary. However, National Grid have an ‘Internal and Contract Specific Policy Statement (Transmission) Flood Mitigation Policy (PS(T)095 – Issue 1 – January 2011)’. Notwithstanding the requirements and recommendations of statutory authorities such as the EA, the requirements of this policy state that for new sites the target resilience level for transmission infrastructure shall be 1 in 1000 year flood resilience with a suitable allowance for climate change. The policy also suggests the addition of a further 300mm freeboard to resilience levels to allow for any errors in the data used. The EA for this project have already confirmed that the model levels provided have a +/- 150mm tolerance. Thus the recommended minimum design level for the critical infrastructure elements for the substation site will be set at 3.637m AOD. 7.150 The predicted flood events that impact the substation and converter sites are those in excess of the 1 in 200 plus climate change and the current predicted 1 in 1,000 year tidal flood events. As such the impact on the extent of flooding outside the site area due to land raising will be negligible for most flood events. For the extreme climate change events the extent of flooding in the areas would include both the River Stour and Minster Stream and the displaced volume from the proposed land raising would have a minimal impact of flood depths or off site areas. 7.151 It is not anticipated that further mitigation measures will be required as minor to negligible effects are not considered to be significant in the current EIA regulations. Groundwater 7.152 The main mitigation measure to prevent adverse impacts on groundwater during all phases of development is to ensure good site practice and management. To prevent pollution, a CEMP will be produced as described above. Residual Impacts and Conclusion 7.153 Provided that the mitigation measures are implemented properly, it is not anticipated that there will be significant residual effects to the water environment during the construction and operation phases of this development. Table 7.21 details the influence of the mitigation on the adverse impacts identified above. For clarity minor impacts and below (not Significant in terms of EIA Regulations) are not shown. 144 Table 7.21: Residual Significance Effects Potential Significance Construction Effects Surface Water Construction Moderate – material stockpiles Adverse and operations changing overland flood flow pathways Proposed Mitigation Residual Significance Construction will be carried out in accordance to current guidance and EA PPGs and the CEMP as well as consider storage locations within the EMP Construction will be carried out in accordance to current guidance and EA PPGs and the CEMP as well as consider early establishment of surface water storage facilities within the EMP Minor – Adverse Construction will be carried out in accordance to current guidance and EA PPGs and the CEMP Construction will be carried out in accordance to current guidance and EA PPGs and the CEMP as well as consider storage locations within the EMP Minor – Adverse Construction will be carried out in accordance to current guidance and EA PPGs and the CEMP as well as include a Flood Plan within the EMP and awareness training for all site staff. Groundwater – No Significant Impacts Minor – Adverse Increase in surface water runoff from impermeable surfaces – Converter and Substation sites Water Quality Risk of silt-laden entering the local drainage system Moderate – Adverse Moderate – Adverse Risk of silt-laden water or accidental spillage of construction materials into nearby water bodies – BayPoint sports complex pond Flood Risk Moderate – Adverse Construction works within flood risk areas and impact on works and workers – Laydown Area Moderate – Adverse Operational Effects Surface Water 145 Minor – Adverse Minor – Adverse Increase in surface Minor – Construction of water runoff due to Adverse to attenuation facilities, new impermeable Moderate SuDS and drainage surfaces – Adverse management to cater for Substation and increases and tide-locking Converter Station of outfalls Sites Flood Risk Introduction of Moderate – Provision of minimum substation and Adverse design platform level converter station (CAT 3) to 300mm above predicted structures within Major tidal flood level – design identified high risk Adverse level to be 3.637m AOD flood zones – (CAT 5) climate change effects Groundwater – No Significant Impacts Minor – Adverse Minor – Adverse Cumulative Impacts 7.154 Potential cumulative effects on hydrology and flood risk from the onshore elements of the Nemo Link in combination with other components of the Nemo Link i.e. UK, French and Belgian subsea cables and Belgian onshore infrastructure are described in Chapter 16. 7.155 Potential cumulative effects of the Nemo Link UK onshore infrastructure in combination with the connection required to facilitate the operation of the Nemo Link are described in Chapter 17. 7.156 There is the potential for cumulative effects to arise during the construction and operation phase of the proposed works due to the construction and operation of other developments as detailed in Table 1.2. 7.157 Development of the converter station and substation sites will result in a minor change in water flow, however, this will not increase the overall discharge rate from the site as the surface water flow will likely be designed to infiltrate into the adjacent ground immediately prior to reaching the local watercourses or attenuated in order to improve discharge water quality, hence it is not anticipated that water quality in the local watercourses and drains will be affected. 7.158 Neighbouring development works at the proposed Richborough Energy Park may require changes to the drainage network in the area and cumulative effects may occur if these are not regulated. 7.159 Current planning policy, government and EA guidance (PPS, NPS and EA PPGs) would impose similar constraints on other developments in terms of attenuation, flood protection levels and discharge quality that are applicable to this site. In addition, there will be an increasing requirement to meet WFD quality standards and the introduction in due course of the National SuDS Standards. Hence, in hydrological terms, there would not be any significant cumulative effects. Any overland flow will therefore be localised and should not have an effect to the surrounding area. 146 7.160 In September 2012, during the preparation of this assessment, Thanet District Council submitted a planning application (Ref. F/TH/12/0690) for the Pegwell Bay Flood Defence Scheme. Details of the scheme are enclosed as part of the FRA in Appendix 7.1. It should be noted that this application does not include its own FRA but includes a number of Halcrow produced flood maps. 7.161 Also during the preparation of this assessment, details of the construction of new flood defences and improvements to existing defences with associated works, landscaping, creation of two flood relief areas and wetland habitat were submitted by the EA in August 2012 to Dover District Council. 7.162 The two recently submitted flood defence schemes (Pegwell Bay Flood Defence Scheme and Sandwich Town Tidal Defences) will assist in maintaining and improving the current level of tidal flood protection within the area of the proposed cable route, substation and converter station. These defence schemes do not have any detrimental impact on the site proposals and the site proposals do not impact on the defence schemes. 7.163 As development poses no significant effect in relation to flooding, drainage and water quality (assuming mitigation measures discussed above are implemented properly) to the surrounding area, no cumulative effects are considered likely to occur as a result. References CIRIA ‘The SUDS Manual’ C697, Mar 2007. CIRIA ‘Flood Resilience and Resistance for Critical Infrastructure’ C688, 2010 Communities and Local Government, ‘East of England Plan, The Revision to the Regional Spatial Strategy for the East of England’, May 2008 Communities and Local Government ‘National Planning Policy Framework’ NPPF, Mar 2012. Communities and Local Government ‘Technical Guidance to the National Planning Policy Framework’, Mar 2012. DEFRA ‘Interim Code of Practice for Sustainable Drainage Systems’ National SUDS Working Group, July 2004. Entec ‘Thanet District Strategic Flood Risk Assessment, Volume 1 – Thanet SFRA Report’, April 2009 The Flood and Water Management Act 2010 The Pitt Review ‘Learning lessons from the 2007 flood – the independent review by Sir Michael Pitt’, June 2008 The Thanet District Adopted Local Plan 2006 147 The Water Framework Directive 2000/60/EC, 2000 The Water Resources Act 1991 148 149 150 8.0 ECOLOGY Introduction 8.1 This chapter provides an assessment of the potential ecological effects of the Proposed Development (i.e. the onshore elements of the Nemo Link - see Chapter 2 – Project Description) during construction and operation. The assessment has been undertaken by appropriately qualified and experienced ecologists from TEP based on findings of a range of ecological surveys and information from identified sources. Mitigation measures that will be adopted to minimise potential affects, and opportunities to enhance biodiversity are described. Legislation and Planning Policy Context 8.2 The provisions of the following Statutory Instruments and Acts of Parliament are relevant to the assessment: Wildlife and Countryside Act 1981 (as amended); The Conservation of Habitats and Species Regulations 2010; Countryside and Rights of Way (CRoW) Act 2000; and Natural Environment and Rural Communities Act 2006. National Planning Policy 8.3 The National Planning Policy Framework (NPPF) was published on 27 March 2012, coming into immediate effect and replacing the majority of previous Planning Policy Guidance Notes (PPGs) and planning Policy Statements (PPSs). The NPPF has been considered in the preparation of the ecology assessment. 8.4 Chapter 11 of the NPPF states that ‘The planning system should contribute to and enhance the natural and local environment by: ‘Protecting and enhancing valued landscapes, geological conservation interests and soils; Recognising the wider benefits of ecosystem services; and Minimising impacts on biodiversity and providing net gains in biodiversity where possible, contributing to the Government’s commitment to halt the overall decline of biodiversity, including by establishing coherent ecological networks that are more resilient to current and future pressures;’ Local Policy 8.5 The Proposed Development is predominantly within the administrative boundary of Thanet District Council. However, a section of cable within the BayPoint sports complex and the south eastern corner of the proposed converter station and substation site are in the administrative boundary of Dover District Council. 151 8.6 Thanet District Council Local Plan 2006 ‘Saved Policies’ relevant to this assessment include: 8.7 Policy CC1 - Development in the Countryside; Policy CC2 - Landscape Character Areas; Policy NC3 – Local Wildlife Sites; and Policy SR20 - Undeveloped Beaches. Relevant Dover District Council policies from Dover Core Strategy, 2010 include: Policy CP7 - Green Infrastructure; Policy DM15 - Protection of the Countryside; Policy DM16 - Landscape Character; and Policy DM25 - Open Space. Biodiversity Action Plans (BAPs) 8.8 The signing of the Convention on Biological Diversity at the Rio Earth Summit in 1992 placed an obligation on the UK Government to produce a Biodiversity Action Plan (the UK BAP). The UK BAP describes actions that need to be undertaken by which the conservation status of a targeted list of habitats and species can be maintained or enhanced. 8.9 The UK BAP objectives and targeted actions to protect, maintain and enhance listed habitats and species are implemented at regional and local level by the Kent Biodiversity Action Plan (LBAP). Birds of Conservation Concern 8.10 Bird species that have undergone a population decline in the UK over the last 25 years are included on the Red and Amber Lists of Birds of Conservation Concern (RSPB, 2009): Red List species are globally threatened and have experienced a population decline in Britain of greater than 50% in the last 25 years; and Amber List species are internationally rare or have localised populations and have experienced a population decline in Britain of 25% to 49% in the last 25 years. Method 8.11 The assessment of potential effects has been carried out in accordance with the Institute of Ecology and Environmental Management’s (IEEM) Guidelines for Ecological Impact Assessment (2006). This chapter should be read in conjunction with Appendices 8.1 to 8.8 (survey results). 152 Desk Study 8.12 Information on designated nature conservation sites, protected and otherwise notable species within 2km of the application site boundary were obtained from the following sources: Multi-Agency Geographical Information for the Countryside (http://www.MAGIC.gov.uk); Nature on the Map website (http://www.natureonthemap.org.uk); Kent Wildlife Trust (KWT); Kent and Medway Biological Records Centre (KMBRC); Kent Reptile and Amphibian Group (KRAG); Kent Bat Group (KBG); Kent Ornithological Society (KOS); and Royal Society for the Protection of Birds (RSPB). website 8.13 Information received from the above organisations is included in Appendix 8.1. 8.14 Comprehensive studies have also been undertaken for a number of recent major schemes in the vicinity of the application boundary. Publicly available information has been reviewed as part of this assessment. This includes ecological assessments undertaken in support of: Thanet Offshore Wind Farm (2005); East Kent Access Phase 2 (2004); and Richborough Power Station Demolition (URS Scott Wilson, August 2011). Field Survey 8.15 A range of field surveys have been undertaken along the proposed onshore underground cables route and at the site of the proposed converter station and substation to establish baseline conditions in respect of habitats and species. Phase 1 Habitat Survey 8.16 A Phase 1 Habitat Survey was undertaken by TEP during August and September 2011 to map the habitat types present along the proposed onshore cable route to low water in accordance with the Handbook for Phase 1 Habitat Survey (JNCC, 2007). 8.17 The Phase 1 Habitat Survey of the converter station and substation site was undertaken during April 2012 following demolition of the cooling towers and chimney associated with the former power station. Site clearance of the proposed converter station and substation site continued since the survey was undertaken and repeat site visits since the site clearance have confirmed the findings of the initial survey. 8.18 The Phase 1 Habitat Survey included an inspection of suitable areas for the presence of badger setts and other field signs of badger, and an inspection of trees for the potential to support roosting bats. All habitats were assessed for their potential to support protected species and any evidence was recorded. 153 8.19 Detailed results from the Phase 1 Habitat Survey are in Appendix 8.2 and are summarised later in this chapter. National Vegetation Classification (NVC) Survey 8.20 A National Vegetation Classification (NVC) survey of saltmarsh area surrounding the proposed cables route north of Pegwell Bay Country Park was undertaken during August 2011. Quadrats were recorded using standard NVC methodology. The NVC survey results are in Appendix 8.3. Reptile Survey 8.21 A reptile survey was undertaken during late August and September 2011 to determine the presence and distribution of reptiles along the proposed cable route. Reptile surveys generally use ‘artificial cover objects’ such as old carpet tiles or tins which are left on a site and subsequently inspected to identify reptiles beneath them. The proposed cables route is well-used by members of the public and there would be high risk of tampering with artificial cover objects; surveys were undertaken using direct observation methods. 8.22 A reptile survey was not undertaken at the proposed converter station and substation site due to the lack of suitable habitat. The proposed converter station and substation site is dominated by hard standing. The small areas of vegetation that are present consist of sparse and short modified grassland, which shows evidence of disturbance from the demolition activities, and patches of ephemeral vegetation. This area of the site therefore does not possess habitats that could offer foraging or refuge opportunities for reptiles. 8.23 Full details of the Reptile Survey are in Appendix 8.4. Water Vole Survey 8.24 A water vole survey of Unit 11 of Sandwich Bay to Hacklinge Marsh SSSI located to the north of the former power station site was undertaken during early October 2011. The survey followed methods detailed in The Water Vole Survey Handbook 2nd Edition (Strachen and Moorhouse, 2006). The area contains a number of wet ditches and is also bordered by Minster Stream to the north. 8.25 Ditches adjacent to the A256 Sandwich Road within Pegwell Bay Country Park and ditches in Stonelees Nature Reserve were not included as they were dry at the time of survey in 2011 and were also considered to have a low likelihood of supporting water voles. 8.26 Further details of the water vole survey are in Appendix 8.5. Winter Bird Survey 8.27 A winter bird survey was undertaken between November 2008 and May 2009 within the saltmarsh and mudflat habitats of Pegwell Bay to determine the use of the area by overwintering and migrating species of birds. Data obtained from Kent Ornithological Society, has also provided a large amount of data regarding habitat use by birds within the Pegwell Bay Area. Impacts on wintering birds will be avoided 154 through the timing of cable installation works outside of sensitive periods and repeat surveys are therefore not necessary. 8.28 The winter bird survey entailed two surveyors mapping wader and wildfowl distributions in Pegwell Bay on an hourly basis for a complete tide cycle, i.e. high to low tide or low to high tide. A total of seven visits were completed for this survey. Survey visits were undertaken once a month from November 2008 to March 2009. An additional visit was undertaken in February 2009 to target the mid-winter period when birds are most sensitive to disturbance. Survey days were chosen to ensure that three surveys were undertaken as the tide was going out (high to low tide) and three surveys were undertaken as the tide was coming in (low to high tide). Impacts on wintering birds will be avoided by undertaking cable installation works outside of sensitive periods so repeat surveys are not necessary. Consultation with Natural England (NE) and Kent Wildlife Trust (KWT) will be used to identify the most appropriate timing of the cable installation works. This is consistent with the approach used for the installation of the Thanet Offshore Wind Farm cables across Pegwell Bay. 8.29 The winter bird survey report is in Appendix 8.6. Breeding Bird Survey and Nesting Redshank Survey 8.30 A breeding bird survey was undertaken across the saltmarsh areas of Pegwell Bay and also in Pegwell Bay Country Park and Stonelees Nature Reserve. The survey was undertaken on two separate visits on 8th May and 22nd June 2009 to determine the importance of the area for breeding birds. No breeding bird survey was undertaken within the site of the proposed converter station and substation due to the lack of suitable nesting habitats and highly disturbed nature of the site. 8.31 The breeding bird survey entailed two surveyors walking a series of line transects through peripheral habitats adjacent to the saltmarsh in the north half of the Bay; suitable bird breeding habitats, including areas of plantation, scrub and tall areas of herbs in Pegwell Bay Country Park; and an area to the southwest extent of Sandwich and Pegwell Bay Kent Wildlife Trust Reserve, known locally as Stonelees Nature Reserve. 8.32 As part of the breeding bird assessment, a separate redshank survey was undertaken. This entailed two surveyors walking transects within saltmarsh habitats to determine the presence of nesting redshank. 8.33 Full details of the breeding bird survey and nesting redshank survey are in Appendix 8.7. Sediment and Invertebrate Survey 8.34 A survey of the sediment and invertebrate communities of the intertidal mudflat areas of Pegwell Bay was undertaken during August 2009 to determine the distribution and abundance of prey items that may be used by waders and wildfowl that affect their distribution within the intertidal area. 8.35 In total four transects were taken at right angles to the shoreline associated with Cliffs End and the A256. Samples were taken at four points along each transect in the upper, mid-upper, mid-lower and lower shore. 155 8.36 Details of the sediment and invertebrate survey are in Appendix 8.8. Assessment of Significance Determination of Ecological Value 8.37 The habitats and species recorded have been valued in accordance with the criteria presented in Table 8.1. The Institute of Ecology and Environmental Management (IEEM) Guidelines for the assessment of ecological impacts aim to establish a standard in the evaluation of the effects of potential development on wildlife receptors. Deviating away from the traditional significance matrix, IEEM guidelines require ecological receptors to be valued (or to have the potential to be valued) according to a geographical scale. Table 8.1: Criteria for Evaluation of Ecological Features Level of Value International National Regional/ County Local Site Negligible Ecological Features Internationally designated sites or candidate sites (e.g. Special Areas for Conservation (SACs), Special Protection Areas (SPAs), Ramsar sites); Nationally designated sites (e.g. Sites of Special Scientific Interest (SSSIs), National Nature Reserves (NNRs)); Local Nature Reserves (LNRs); Local Wildlife Sites (formerly Sites of Importance for Nature Conservation), ancient woodlands; habitats or species populations of importance for Kent Significant ecological features such as old hedgerows, woodlands, ponds of importance for the Kent Wildlife Trust reserves; Features with ecological value of significance within the application site only Areas of built development, active mineral extraction, or intensive agricultural land. Determination of Significant Effects 8.38 An ecological impact is determined as being significant if it affects the integrity of a site or the favourable conservation status of a valued feature. Significance is considered in relation to the value of the receptor. The significance can be positive, if the effect supports or promotes favourable conservation status, or negative, if it contradicts or decreases the ability of the feature to maintain its conservation status. A significant impact, in ecological terms, is defined in the IEEM guidelines as: ’an impact (adverse or positive) on the integrity of a defined site or ecosystem(s) and/or the conservation status of habitats or species within a given geographical area, including cumulative impacts.’ 8.39 The Government Circular ODPM 2005/06 defines site integrity as: 156 ’the coherence of its ecological structure and function, across its whole area, that enables it to sustain the habitat, complex of habitats and/or the levels of populations of species for which it was classified’. 8.40 The conservation status of a species is defined in Article 1(i) of the Habitats Directive as favourable when: ’population dynamics data on the species concerned indicate that it is maintaining itself on a long term basis as a viable component of its natural habitats; and the natural range of the species is neither being reduced nor is likely to be reduced in the foreseeable future; and there is, and will probably continue to be, a sufficiently large habitat to maintain its population on a long-term basis’. 8.41 The IEEM guidelines also highlight the importance of considering the likelihood that a change/activity will occur as predicted, and the degree of confidence in that impact assessment on ecological structure and function. A four point scale, used to standardise the degree of certainty in a prediction, is stated as follows: Certain/Near Certain: probability estimated at 95% chance or higher; Probable: probability estimated at or above 50% but below 95%; Unlikely: probability estimated at or above 5% but below 50%; and Extremely Unlikely: probability estimated at less than 5%. 8.42 When describing changes and activities and impacts on ecosystem structure and function, the following parameters are characterised: Positive or Negative: is the impact positive or negative? Magnitude: refers to the size or “amount” of the impact; Extent: the area over which the impact occurs; Duration: the time for which the impact is expected to last prior to recovery or replacement of the resource or feature; Reversibility: an irreversible (permanent) impact is one from which recovery is not possible within a reasonable timescale: a reversible (temporary) impact is one from which spontaneous recovery is possible or for which effective mitigation is possible; and Timing/Frequency: some changes may only cause an impact if they happen to coincide with critical life-stages or seasons (e.g. bird nesting season). 8.43 Wherever possible, conservation status has been determined by reference to literature, including the UK BAP and LBAP objectives and targets, and by professional judgement in the absence of clear guidance. The geographic scale at which a significant effect matters is indicated by the feature’s value. 8.44 Only those habitats and species of at least local value have been considered in this assessment as significant effects on ecological features of lower value are not considered material to the decision to proceed with the Proposed Development. Habitat Regulations Assessment 8.45 The potential impacts of the proposals on the specific features of European protected areas within the proposed cable route have been assessed within a document entitled ‘Information for Habitat Regulations Assessment’ (HRA). This assessment is provided in Appendix 8.9 and is referred to when assessing the 157 impacts of the proposals. A HRA Signposting Document has also been included in Appendix 8.10 detailing the sections of the Ecology Chapter relevant to HRA. Existing Environment Designated Nature Conservation Sites 8.46 Table 8.2 summarises the designated areas within 2km of the application boundary and these are shown on Figures 8.1 and 8.2. Some of the designations overlap with one another such that some areas that fall within the application boundary are covered by multiple designations. Further details of each designated site are in Appendix 8.1. Table 8.2: Conservation Designations Site Designation Name Ramsar SPA SAC Description Thanet Coast and Sandwich Bay A coastal site, consisting of a long stretch of rocky shore, adjoining areas of estuary, sand dune, maritime grassland, saltmarsh and grazing marsh. The wetland habitats support 15 British Red Data Book invertebrates, as well as a large number of nationally scarce species. The site attracts internationally important numbers of turnstone Arenaria interpres and nationally important numbers of nationally important wintering populations of four wader species: ringed plover, golden plover, grey plover and sanderling, as well as Lapland bunting. The site is used by large numbers of migratory birds. Thanet Internationally important populations of Coast breeding little tern (Sterna albifrons) and and overwintering European golden Sandwich plover (Pluvialis apricaria) and Bay turnstone (Arenaria interpres). Sandwich Sandwich Bay supports a dune system Bay consisting of four Annex I habitats. Other general site characteristic habitats include tidal rivers, estuaries, mud flats, sand flats, lagoons, saltmarshes, salt pastures, salt steppes, coastal sand dunes, sand beaches, machair, inland waterbodies, bogs, marshes, water-fringed 158 Development Components in Designation Onshore cables including TJP. Subsea and onshore underground cables including TJP. Subsea and onshore underground cables including TJP. Designation Site Name Description Development Components in Designation vegetation, fens, humid grassland, mesophile grassland, improved grassland and coniferous woodland. SAC SSSI NNR Thanet Coast Thanet Coast represents the UKs longest stretch of coastal chalk, and contains 4 Annex I habitats, including reefs, submerged/partially submerged sea caves, submerged sandbanks and mudflats/sand flats exposed at low tide which support specialised algal communities. Sandwich This site contains the most important Bay to sand dune system and sandy coastal Hacklinge grassland in South East England and Marshes also includes a wide range of other habitats such as mudflats, saltmarsh, chalk cliffs, freshwater grazing marsh, scrub and woodland. Associated with the various constituent habitats of the site are outstanding assemblages of both terrestrial and marine plants with over 30 nationally rare and nationally scarce species, having been recorded. Invertebrates are also of interest with recent records including 19 nationally rare, and 149 nationally scarce species. These areas provide an important landfall for migrating birds and also support large wintering populations of waders, some of which regularly reach levels of national importance. Sandwich The NNR is a mix of natural, semi and natural; and artificial habitats. Natural Pegwell habitats include; eroding chalk cliffs Bay and wave cut platforms to the north of Pegwell Bay, intertidal mudflats developing beaches, sand dunes and saltmarsh. Semi-natural habitats include; ancient dune pasture and coastal scrubland while the re-created grassland of the Pegwell Bay Country Park, along with ponds, dykes and ditches are artificial habitats. 159 None (150m north of subsea cables route) Subsea and onshore underground cables including TJP. Subsea and onshore underground cables including TJP. 8.47 An assessment of the effects of installation of the subsea cable has been included as part of the Marine cable installation assessment which forms part of the Marine Application. However, the assessment of the onshore cable also includes the section of subsea cable that passes through the intertidal area from the low water mark. 8.48 The subsea cable route passes through approximately 1,900m of the designated areas including Thanet Coast and Sandwich Bay SPA and Ramsar, Sandwich Bay and SAC, Sandwich Bay to Hacklinge Marshes SSSI and Sandwich and Pegwell Bay NNR. The subsea cable does not however pass through the Thanet Coast SAC the boundary of which is approximately 150m north of the proposed subsea cable route. The habitats crossed by the subsea cables route are primarily tidal mudflats and approximately 180m of saltmarsh. 8.49 Sandwich and Pegwell Bay NNR also incorporates Pegwell Bay Country Park and Sandwich and Pegwell Bay Kent KWT Reserve. The proposed onshore cables route passes through Pegwell Bay Country Park which consists of a mosaic of rough grassland, plantation and scrub. Sandwich and Pegwell Bay Reserve, managed by KWT, incorporates a swathe of habitats around the Country Park. A small part of the southwest corner of the Sandwich Bay and Pegwell Bay Reserve is owned by KWT. This part of the larger reserve is known locally as Stonelees Nature Reserve. Local Wildlife Sites 8.50 Local Wildlife Sites (LWS) are county designations and have no legal protection. However, they are material considerations within the planning process. 8.51 There are two Local Wildlife Sites (LWS) within 2km of the proposed converter station and substation site: Ash Level and South Richborough Pasture; and Woods and Grassland, Minster Marshes. 8.52 Ash Level and South Richborough Pasture LWS is approximately 15m southwest of the proposed converter station and substation site boundary. The LWS consists of a large complex of grazing marsh including botanically species rich ditches which support invertebrates and wetland birds. Several landowners are now in Natural England’s Higher Level Stewardship schemes with options for grazing marsh restoration such as scrape creation to improve wildlife interest of the site. 8.53 The Woods and Grassland, Minster Marshes LWS consists of a mosaic of grassland, scrubs ponds and woodland habitats, important for supporting a range of species. This LWS is approximately 500m west of the proposed converter station and substation site. 8.54 A single Roadside Nature Reserve (RNR) is also present approximately 25m west of the proposed onshore underground cables route. The RNR is located along a 450m stretch of the A256 Sandwich Road and comprises the road verge, which is designated for its botanical interest. RNRs do not receive legal protection but are a material consideration within the planning process. 160 Biodiversity Action Plans 8.55 The following UK BAP Priority Habitats are listed as present on the Nature on the Map website within and immediately adjacent to parts of the proposed onshore underground cables route, converter station and substation. Fen; Reedbeds; Lowland Meadows; Woodland; Coastal and Floodplain Grazing Marsh; and Mudflats. Habitats 8.56 The habitats present within the application site are illustrated in Figure 8.3. Habitat descriptions and species lists are provided at Appendix 8.2. The description of habitats below refers to the different parts of the cables route from low water to the converter station and substation. Low Water to TJP Mudflats 8.57 The area between low water and the proposed TJP dominated by intertidal mudflat habitat which borders the saltmarsh habitats closer to the shore. Saltmarsh 8.58 The subsea cables route approaching the TJP and the pit are in an area dominated by saltmarsh habitat. The saltmarsh communities support typical saltmarsh species of the local area such as sea purslane (Atriplex portucaloides), common cord-grass (Spartina anglica), sea aster (Aster tripolium) and glasswort (Salicornia sp). The NVC survey of the saltmarsh habitats identified five saltmarsh communities within the subsea cable route and TJP. Details of the NVC saltmarsh habitats are provided in Appendix 8.3 and are illustrated in Figure 8.4. 8.59 North of the subsea cables route there is stock proof fencing which defines the working area of the Thanet Offshore Wind Farm (TOWF) cable, which also runs through saltmarsh habitat. The fencing of the TOWF working area following completed installation of the cable has resulted in positive recolonisation by saltmarsh species. Monitoring of the progress of the saltmarsh recolonisation is still underway. TJP to Pegwell Bay Country Park (adjacent A256 and Cycle Path) Saltmarsh 8.60 There is saltmarsh on the lower partly intertidal land west of the TJP. A further small area of saltmarsh on the landward side of the proposed TJP gives way to modified neutral grassland close to the A256 and cycle path. The cycle path is embanked from the level of the saltmarsh and the land falls from this level to the saltmarsh on 161 the coastal side. Degradation of saltmarsh habitats at the foot of the cycle path slope has occurred due to members of the public using desire lines across the saltmarsh vegetation to avoid walking on the cycle path. 8.61 The NVC survey of the saltmarsh habitats identified three saltmarsh communities within the onshore cable route. Details of the NVC saltmarsh habitats are provided in Appendix 8.3 and are illustrated in Figure 8.4. Modified Neutral Grassland 8.62 There is modified neutral grassland adjacent to the A256 Sandwich road and cycle path. Species present in the diverse sward are typical of verge habitats in the area, dominated by false oat-grass (Arrhenatherum eliatus), red fescue (Festuca rubra) with abundant buck’s horn plantain (Plantago coronopus), fennel (Foeniculum vulgare), and Alexanders (Smyrnium olusatrum). There are also some saltmarsh species that have established at the foot of the slope close to the saltmarsh, including sea sandwort (Honckenya peploides). Desire lines have been created parallel to the cycle path where members of the public attempt to avoid using the cycle path. This has resulted in degradation of the vegetation due to erosion and compaction. Water Bodies 8.63 There is a large pool in the saltmarsh habitat on lower ground below this section of the onshore underground cables route. The pool is tidal and is filled during high tides that inundate the surrounding saltmarsh. There is no aquatic vegetation within the pool but saltmarsh vegetation surrounds the pool. The onshore cables are routed to the northwest of this water body. Hardstanding 8.64 The cycle path comprises a linear length of hardstanding. Pegwell Bay Country Park Semi-Improved Grassland 8.65 Expanses of semi-improved grassland with poor sward diversity occur across Pegwell Bay Country Park. This grassland was created following capping of the landfill site, which was the previous land use prior to conversion into a Country Park. Areas of grassland to the east of the cycle path are periodically grazed by cattle as part of the management of the Country Park habitats undertaken by KWT. 8.66 The cycle path runs through the grassland in a northeast-southwest direction. The sward west of the cycle path is dominated by false oat-grass with red fescue, cock’s-foot (Dactylus glomerata) and a range of locally common species such as Alexanders, wild carrot (Daucus carota) and yarrow (Achillea millefolium). Management in this area consists of regular mowing of a 2m wide strip along the western edge of the cycle path which produces a slightly wider corridor for users of the cycle path. 162 Plantation Woodland 8.67 There are extensive areas of plantation woodland in Pegwell Bay Country Park. The woodland provides landscaping around the car park areas within the northern section of the Country Park, and along the majority of the western boundary, the woodland acts as screening from the busy Sandwich Road. The most common species are sycamore (Acer pseudoplatanus), holme oak (Quercus ilex), aspen (Populus tremula) and field maple (Acer campestre). Amenity Grassland 8.68 There is an area of amenity grass in the north of the Country Park associated with the car parking and picnic areas. Scattered Trees 8.69 Scattered trees are present along proposed onshore cable route. They are mainly concentrated within semi-improved grassland in the northern section of the Country Park. Scattered/Dense Scrub 8.70 There is an extensive area of bramble scrub present within the Country Park, west of the cycle path. Scattered scrub, dominated by hawthorn, is also present in grassland areas. Tall Ruderal Herb 8.71 Tall ruderal herbs in the Country Park tend to be associated with fence lines, ditches and plantation edges. These areas are generally dominated by species such as Alexanders (Smyrnium olusatrum), fennel (Foeniculum vulgare), nettle (Urtica dioica), bindweed (Convolvulus arvensis) and teasel (Dipsacus fullonum). Ditches 8.72 Ditches are present within the western section of the Country Park adjacent to the A256 Sandwich Road. The ditches were dry for the majority of 2011, but due to the wetter conditions experienced between January and July 2012, they have been observed to hold water. Vegetation is generally absent but dense stands of common reed (Phragmites australis) and reedmace (Typha latifolia) are present in some sections of the ditch within the Country Park. Hardstanding 8.73 The cycle path, access road and car parking areas are areas of hardstanding in the Country Park. Stonelees Nature Reserve Unimproved Coastal Dune Pasture 8.74 The unimproved grassland along the proposed onshore cable route within Stonelees Nature Reserve route is generally rough with a high proportion of tall herbs and 163 scattered scrub. Southern marsh orchid is also widely present within this area of grassland. Tall Ruderal Herb 8.75 More extensive areas of tall ruderal herbs are located within ungrazed areas of Stonelees Nature Reserve. Water Bodies 8.76 A number of ephemeral ponds have been created within Stonelees Nature Reserve by KWT to reintroduce natterjack toads. The ponds have been designed to be shallow and to hold water for only part of the year making them suitable for the species. A further ephemeral pond is present along the ditch line in the west of the Stonelees Nature Reserve. The pond is dominated by reedmace and is generally dry but holds water periodically. Scattered/Dense Scrub 8.77 Scattered scrub, comprising mainly hawthorn, is also present in Stonelees Nature Reserve. Ditches 8.78 There are ditches adjacent to the A256 Sandwich Road and similarly for those described in the Country Park, these were dry for the majority of 2011, but due to the wetter conditions experienced between January and July 2012, they have been observed to hold water. Vegetation is generally absent but dense stands of common reed (Phragmites australis) and reedmace (Typha latifolia) are present in some small sections of the ditch within the Stonelees Nature Reserve. Semi-Natural Broad-Leaved Woodland 8.79 An area of semi-natural broad-leaved woodland is present within the southern section of Stonelees Nature Reserve. The woodland consists of mature sycamore and ash trees with an understorey of scrub species including hawthorn. KWT have undertaken some clearance of this woodland habitat during winter 2011/2012. Hardstanding 8.80 The hardstanding cycle path runs through Stonelees Nature Reserve continuing along the new bypass to the south. 8.81 The cables route crosses the A256 road which has recently been widened to form a dual carriageway. BayPoint Sports Complex to Converter Station 8.82 This part of the onshore underground cables route passes from the BayPoint sports complex to the converter station site. The cables would be installed by HDD which will involve a pit and working area on the sports complex and another pit and working area at the converter station site with no disturbance to the ground between these points. The ground above the cables route comprises the A256, arable land, 164 Unit 11 of the Sandwich to Hacklinge SSSI, Minster Stream and part of the former Richborough Power Station site. Scattered Trees 8.83 This habitat occurs within the BayPoint sports complex where pollarded poplars are present along the north and west boundaries. Amenity Grassland 8.84 The BayPoint sports complex is dominated by maintained sports fields which are regularly mown to maintain a short sward. Hardstanding 8.85 The A256 is dual carriageway and has a tarmacadam surface. Bare Ground and Ephemeral Species 8.86 Areas of bare ground with ephemeral species are present alongside the widened section of the A256 associated with the recent road improvement works. These areas have been seeded and are developing into grass verges. Arable Grassland 8.87 Arable grassland extends west of the newly widened section of the A256 and south of the new bypass. The area has been cleared for the development of an anaerobic digester scheme. This development is separate to the scheme described in this document. Unimproved Neutral Grassland 8.88 Within the SSSI, unimproved neutral grassland along the proposed cable route is generally dominated by dense scrub. 8.89 Areas of semi-improved neutral grassland are also present within Unit 11 of Sandwich Bay to Hacklinge Marshes SSSI, to the north of the proposed converter station and substation site. Water Bodies 8.90 An area dominated by dense reedmace is located in the southeast corner of Unit 11 of the Sandwich Bay to Hacklinge Marshes SSSI. Ordnance Survey maps indicate that this has historically been a waterbody but it currently does not hold any water. The base of the waterbody is now filled with reedmace roots and is becoming colonised by other vegetation. Scattered/Dense Scrub 8.91 There is an area of dense hawthorn (Crataegus monogyna), blackthorn (Sambucus nigra) and willow (Salix sp.) scrub in Unit 11 of the Hacklinge Marshes SSSI. 165 Ditches 8.92 There are ditches within Unit 11 of the Sandwich Bay to Hacklinge Marshes SSSI north of the proposed converter station and substation site. A ditch in the north of the SSSI holds water and is shaded by dense scrub. Aquatic vegetation occurs in less shaded parts of the ditch. Watercourse 8.93 The onshore underground cables route crosses Minster Stream along the north boundary of Unit 11 of the Sandwich Bay to Hacklinge Marshes SSSI. The south bank is shaded by overhanging scrub and the north bank is managed though grass cutting. Some aquatic vegetation is present in the stream. Converter Station and Substation Site Modified Neutral Grassland 8.94 Small areas of modified neutral grassland are present around the bases of the demolished cooling towers within the former power station site. The sward is short and has been subject to disturbance from the demolition activities. Scattered Trees 8.95 A small area of scattered trees is located in the southeast corner of the site, north of the existing site entrance from the A256 Ramsgate Road. There are no other trees within the boundaries of the proposed converter station and substation site but there are several around the perimeter of the site. Bare Ground and Ephemeral Species 8.96 Following demolition works at the former power station site, there are areas of bare ground within the proposed converter station and substation site which are being colonised by ephemeral species. Standing Water 8.97 Since the demolition and clearance of the cooling towers within the site, the bases of the cooling towers have filled with water creating isolated basins containing water within the site. Flora 8.98 There are records of five Schedule 8 (WCA) plant species within 2km of the Proposed Development. These species are: Bluebell (Hyacynthpides non-scripta); Lizard Orchid (Himantoglossum hirsinum); Deptford Pink (Dianthus armeria); Martin’s Ramping fumitory (Fumaria reuteri); and Bedstraw Broomrape (Orobanche caryophillacae). 166 8.99 The majority of records for lizard orchid are from Pegwell Bay Country Park, with a single record of the species within each of the Stonelees Nature Reserve and the site of the former power station. Single records for Martin’s ramping fumitory and bedstraw broomrape originate within the Country Park. 8.100 None of the above species were identified along the proposed cable route or within the footprint of the converter station and substation site. It is possible that these species may be present in isolated areas or may appear within the working areas prior to the commencement of works within suitable habitats such as those present within the Country Park and Stonelees Nature Reserve. Amphibians 8.101 A single record of great crested newt approximately 2km northeast of the proposed onshore underground cable route within Pegwell Bay was received from KRAG. The record originates from a residential garden in the urban area of Pegwell. No other records of great crested newts were received within 2km of the search area. 8.102 Records of smooth newt approximately 2km northeast of the proposed cable route were also received from KRAG originating from the same location as the great crested newt record. A single record of common frog approximately 60m west of the proposed cable route was also received. 8.103 Rough grassland, scrub and plantation/woodland habitats within the proposed onshore cable route within Pegwell Bay, Pegwell Bay Country Park and Stonelees Nature Reserve provide suitable terrestrial habitat for use by amphibians. The proposed converter station and substation site consists of hardstanding, short modified grassland and ephemeral vegetation, and does not provide suitable terrestrial habitats for amphibians. Although standing water is now present within the converter and sub-station site, following demolition of the cooling towers, the standing water is isolated due to its location within the site, surrounded by unsuitable terrestrial habitats. 8.104 Surveys undertaken in support of the Thanet Offshore Wind Farm (TOWF) cable installation (2005), East Kent Access Road Phase 2 (2004) and Richborough Power Station Demolition (2011) have not identified great crested newts in any ponds within 500m of the proposed converter station and substation site and cable route. It is therefore concluded that it is unlikely that there are great crested newts within the Proposed Development areas of the converter station and substation site or cable route. 8.105 The TOWF surveys identified the presence of smooth newt, common frog, and common toad in ponds within 250m of the converter station and substation site. The presence of these species is therefore possible. 8.106 No records of natterjack toads within 2km of the cables route and converter station and substation site have been identified other than that associated with reintroduction. KWT has been undertaking a reintroduction scheme of natterjack toads into Stonelees Nature Reserve since 2008, completing annual surveys of ephemeral pools to determine the success of the reintroduction. During surveys undertaken in 2011 a single natterjack toad was identified. However, 2011 was a very dry year and the ponds dried out rapidly. Toadlets resulting from the introductions were identified in 2009 and 2010. 167 8.107 The locations of the ephemeral pools used for the reintroductions are not currently public knowledge and have not been identified in this assessment. 8.108 Terrestrial habitat suitable for natterjack toads is present within the proposed cable route. Reptiles 8.109 Records of grass snake, common lizard and slow worm within 2km of the application boundary have been received from both KMBRC and KRAG. Reptiles are known to be widespread within the area and can therefore be expected to be present in any suitable areas of habitat, which includes mosaics of rough grassland, scrub and woodland or plantation edges. 8.110 A reptile survey undertaken during September 2011 identified common lizard in suitable habitats along the entire cable route between the landfall to the southern boundary of Stonelees Nature Reserve. A common lizard was also identified on the north bank of Minster Stream during water vole surveys undertaken in October 2011. The results of the 2011 reptile survey are provided in Appendix 8.4 and illustrated in Figure 8.5. 8.111 The maximum number of common lizards counted during any single survey visit was 14 (2nd September 2011, indicating that the survey area has a good population of common lizards. 8.112 Virtually all parts of the cable route and adjacent habitats are suitable for reptiles. The exceptions include amenity grassland (in the Country Park and the BayPoint sports complex), and large areas of hardstanding (car parking areas in the north of the Country Park). 8.113 There are no areas of suitable reptile habitat within the proposed converter station and substation site. The site has been cleared and consists of large expanses of hard standing with short mown modified grassland, which lack foraging shelter and refuge opportunities. Habitats in the western part of the former power station site, outside of the application boundary, remain undisturbed by demolition activities and have high potential to support reptiles. Bats 8.114 No records of confirmed roosts were received within 2km of the proposed converter station and substation site or the proposed cable route. Only 7 records of bats in flight were identified by Kent Bat Group (KBG) within 2km of the proposed cable and converter station and substation site. These records are all north and west of the converter station and substation site and were associated with Ebbsfleet Farm, Cliff’s End and Cottington Road. 8.115 There were bats previously recorded in former office buildings at the power station site prior to their demolition. 8.116 The records received from KBG indicate nine species of bat are present in the locality: 168 Serotine bat (Eptescus serotinus); Daubentons bat (Myotis daubentonis); Whiskered bat (Myotis mystasinus); Natterer’s bat (Myotis nattereri); Noctule bat (Nyctalus noctula); Nathusius’ pipistrelle (Pipistrellus nathusii); Common pipistrelle (Pipistrellus pipistrellus); Soprano pipistrelle (Pipistrellus pygmaeus); and Brown long-eared bat (Plecotis auritus). 8.117 The assessment for suitable bat roost habitat was undertaken as part of the Extended Phase 1 Habitat Survey and is reported in Appendix 8.2. 8.118 No trees suitable for supporting bat roosts were identified during the extended Phase 1 surveys. The majority of trees are of insufficient size and do not have suitable features such as rot holes, cracked limbs and lifted bark that bats may use as roosting habitat. Exceptions to these include a group of mature trees in the woodland in the southwest of Stonelees Nature Reserve where mature sycamore and ash trees are present. Despite their more mature character, no features suitable to support bats were identified on these trees. These trees are approximately 10m from the onshore underground cables route. 8.119 No trees are present in the proposed converter station and substation site. There are trees in other areas of the former power station site, outside the application boundary on the north and east boundaries and to the southwest. The trees to the southwest have some potential to support roosting bats as they possess woodpecker holes. These holes are used by ring necked parakeets as nesting sites and are currently unsuitable for use by roosting bats. 8.120 A bat barn was created west of the former power station site to mitigate the loss of a roost in the former office buildings which were demolished. The bat barn is approximately 600m west of the proposed converter station and substation site and will not be affected by the proposals. 8.121 Habitats along the proposed cable route provide commuting and foraging opportunities for bats. Plantation edges, scattered scrub and grassland occur across the Country Park, Stonelees Nature Reserve and also within Unit 11 of the Sandwich Bay to Hacklinge Marshes SSSI. 8.122 There is no bat foraging or commuting habitat within the converter station and substation site. The area is dominated by extensive hardstanding areas and lacks suitable vegetation structure. The River Stour (southwest of the former power station site), tree lines on the east and north boundary of the former power station site, and Unit 11 of Sandwich Bay to Hacklinge Marshes SSSI are of high value for foraging and commuting bats. Badgers 8.123 One record of badger was obtained within 2km of the proposed cable route, converter station and substation development, but this dates from 1968 and is not considered relevant to this assessment. 169 8.124 No evidence of badger was identified within or adjacent to the Proposed Development area during the site survey. It is concluded that badgers are most likely absent from the development area and will not be affected by the proposals. Water Voles 8.125 There are 30 records of water voles within 2km of the Proposed Development indicating a good local population of the species. 8.126 During surveys in October 2011, water voles were confirmed to use ditch habitats within Unit 11 of Sandwich Bay to Hacklinge Marshes SSSI which are approximately 40m from the converter station and substation site. Water voles were not confirmed to be present within Minster Stream, which borders the SSSI to the north, but it is likely that water voles are present due to the proximity of evidence within the SSSI and surrounding populations identified through desktop searches. The results of the water vole survey are provided in Appendix 8.5 and illustrated in Figure 8.6. 8.127 Surveys completed in 2005 for the TOWF cables installation identified water voles within ditches running parallel with Sandwich Road in the Country Park and Stonelees Nature Reserve. During 2011 these ditches were dry for much of the year and are considered to provide sub-optimal water vole habitat. Given the historic presence of water voles within these ditches, for the purposes of this assessment, water voles are assumed to be present. 8.128 Surveys undertaken during 2009 and 2010 in support of the demolition of structures on the former power station site found no evidence of water vole presence on the River Stour. Otters 8.129 There are six records of European otter within 2km of the proposed converter station and substation site, associated with the River Stour and tributaries, although the most recent of these records dates back to 1997. 8.130 No evidence of otter was identified during surveys of Sandwich Bay to Hacklinge Marshes SSSI, or the adjacent Minster Stream. 8.131 Surveys completed in 2005 for the TOWF cable installation identified an otter footprint on the bank of the River Stour, west of the proposed converter station and substation site. No evidence of otter was recorded during surveys undertaken during 2009 and 2010 in support of the Richborough Power Station demolition impact assessment or during the site walkover. Wintering Birds 8.132 The area surrounding Pegwell Bay is used by large numbers of migratory birds as they make landfall in Britain in spring or depart for continental Europe in autumn. These include nationally important numbers of ringed plover (Charadrius hiaticula) and greenshank (Tringa nebularia) during their migration and red-throated diver (Gavia stellata) during the winter period. The area is also of importance for several other species including wintering populations of dunlin (Calidris alpina), curlew (Numenius arquata), oystercatcher (Haematopus ostralegus), redshank (Tringa tetanus), sanderling (Calidris alba) and grey plover (Pluvialis squatarola) as well as 170 breeding populations of shelduck (Tadorna tadorna), redshank (Tringa tetanus) and oystercatcher (Haematopus ostralegus). 8.133 The subsea conservation designations Ramsar site. 8.134 Thanet Coast and Sandwich Bay SPA consists of a long stretch of rocky shore, adjoining areas of estuary, sand dune, maritime grassland, saltmarsh and grazing marsh (JNCC, 2001). Specifically the area is designated for supporting populations of birds of European importance as listed below: 8.135 Ringed plover, 649 individuals representing 2% of the Great British (GB) population; and Common greenshank, 35 individuals representing 5.8% of the GB population. The following species occur at nationally important levels in winter (JNCC, 2008): 8.137 Little tern (Sterna albifrons) – 0.3% of the British breeding population; European golden plover Pluvialis apricaria – 0.2% of GB overwintering population; and Turnstone (Arenaria interpres) – 1.4% of GB overwintering population. Thanet Coast and Sandwich Bay Ramsar site covers a similar area to the SPA, covering 2,169 hectares. The wetland habitats support 15 British Red Data Book invertebrates, as well as a large number of nationally scarce species. The site attracts nationally important numbers overwintering bird populations including Lapland buntings (Calcarius lapponicus) and several wader species including ringed plover, golden plover, grey plover and sanderling. The site is used by large numbers of migratory birds. The following species occurred at levels of national importance during migration periods in spring and autumn 2008 (JNCC 2008): 8.136 cables will fall to land in an area consisting of several nature designations (see Table 8.2 and Figures 8.1 and 8.2). The that apply to this area include Special Protection Area (SPA) and Each of these designations relate to important bird species. Red-throated diver, 57 individuals, representing an average of 1.1% of the GB population; Great crested grebe (Podiceps cristatus cristatus), 218 individuals, representing an average of 1.3% of the GB population; European golden plover, 4190 individuals, representing an average of 1.6% of the GB population; and Sanderling 598 individuals, representing an average of 2.9% of the GB population. The most numerous bird species recorded during the winter bird survey, carried out in 2008 and 2009 included lapwing and golden plover followed by dunlin and oystercatcher (TEP, 2010). The survey identified a number of specific areas within Pegwell Bay that are used regularly by certain wader and wildfowl species for roosting or feeding. These areas are listed below and detailed in Appendix 8.6: The mudflats near the north bank of the River Stour; The large area of saltmarsh immediately to the east of Stonelees; Shellness; Saltmarsh and grazing marsh on the south bank of the River Stour; and 171 The mudflats at the south-east end of Pegwell Bay. 8.138 It is likely that the distribution of wader species is dictated by the abundance of invertebrate prey species. The Inter-tidal Sediment and Invertebrate Survey (Appendix 8.8) recorded 42 different invertebrate taxa and distinct areas of Pegwell Bay could be identified based on the invertebrate species present. Certain species have widespread distributions within the Bay including Annelid species and the common cockle (Cerastoderma edule), which was found to be widespread and abundant. These species are considered important prey for several wader species. 8.139 Table 8.3 summarises species information for birds that occur at nationally or internationally important levels at the SPA and Ramsar sites. Table 8.3: Birds Occurring at Internationally or Nationally Important Levels in Thanet Coast and Sandwich Bay SPA and Ramsar site Bird Species Turnstone Species Information Turnstone feed on sandy beaches and rocky shores along the northeast Kent coast particularly in areas of loose stones or seaweeds. Their preferred food includes peeler crabs, small crustaceans such as shrimps, and barnacles, as well as marine molluscs. Roosting within the SPA occurs from Swalecliffe to Pegwell Bay mainly on areas of sand and shingle but also on man-made structures such as the sea wall. Golden Golden plover overwinter on land around Sandwich Bay. Mudflats Plover and sandflats in Pegwell Bay and Sandwich Bay provide roosting grounds for golden plover. In recent years golden plover has taken to roosting in large numbers on the intertidal mudflats of the bay itself. It is likely that, whilst there, some feeding takes place but this is not their prime feeding habitat, which is in arable fields and grazing marsh located inland of the dunes of Sandwich Bay. . Ringed Over winter, ringed plover are not observed in high numbers in Plover Pegwell Bay. When present, they appear to feed near the mouth of the River Stour. Greenshank Greenshank are rarely seen in the bay in winter and were not observed during the TEP winter bird survey. Greenshank tend to feed on worms, snails and fish. RedOutside of the breeding season, red-throated divers are numerous throated along the east coast of Britain and they are known to overwinter in Diver Pegwell Bay. Only four individuals were observed during the TEP winter bird survey and these were seen towards the middle of the bay, swimming south. They feed on a wide range of fish species. Great Numbers of great crested grebe peak within the Thanet Coast and Crested Sandwich Bay Ramsar/SPA site during winter, however, no Grebe individuals were observed in Pegwell Bay during the TEP winter bird survey suggesting individuals tend to reside elsewhere within the wider designated area. Great crested grebe dive to catch fish as well as to escape, tending to prefer this to flying. Sanderling Sanderling overwinter in the UK in places such as Pegwell Bay. Over 172 Bird Species Species Information 100 individuals were observed in Pegwell Bay during the TEP winter bird survey. The birds were observed in various locations, appearing not to be restricted to certain areas of the Bay. 8.140 Of the birds utilising Pegwell Bay, lapwing, golden plover, turnstone and grey plover using Pegwell Bay will be most sensitive to disturbance between October and March when they are present in large numbers. Turnstone, sanderling and grey plover will also be sensitive during May when numbers of these species peak within the bay for the spring migration. These migratory species also exhibit autumn migration during several weeks in August and September. Breeding Birds 8.141 Little tern traditionally nest at Shell Ness in Pegwell Bay approximately 1.1km south of the offshore cable route across the bay and approximately 800m east of the cable route at its closest point. Little tern nest in small, single-species colonies on areas of shingle and sand. In addition to their breeding grounds little tern feed in the shallow coastal waters on small fish (e.g. sand eel, pipefish, and gobies) and crustaceans (shrimps, prawns and crabs). It has been observed through the ongoing surveys undertaken by KWT and other groups that numbers of little terns have been decreasing dramatically in recent years and this is thought to be largely as a result of increased disturbance. Although little terns are not present in the UK over winter, a survey visit was also undertaken in May to include the spring migration period. Little tern were not identified at any point during the TEP surveys. 8.142 During the 2009 breeding bird transect survey, 34 bird species were observed at the Country Park and within Stonelees Nature Reserve; 27 species in the early visit (May 2009) and 21 species in the late visit (June 2009). 8.143 No Schedule 1 species were observed during the 2009 surveys. Seven UKBAP species (bullfinch, dunnock, herring gull, reed bunting, song thrush, starling and turtle dove) were recorded on site during the survey. Dunnock and song thrush have been classified as probable breeders within Pegwell Bay Country Park. 8.144 Species addressed by the LBAP and which were recorded during the survey include lapwing, reed bunting and turtle dove. 8.145 Eight amber list species which are not UKBAP species (lapwing, kestrel, housemartin, meadow pipit, mistle thrush, swallow, whitethroat and wheatear) were also recorded during the survey. 8.146 The Country Park and Stonelees Nature Reserve are considered to have local importance for breeding birds, since these sites support a range of bird species including a number of declining Birds of Conservation Concern bird species. Although some species may not be breeding within the survey area, those that do not nest will likely use the habitats to support nesting elsewhere outside the development area. Plantation, scrub, rough grassland and saltmarsh habitats have potential to support species of breeding birds. In particular, the Country Park and Stonelees Nature Reserve support good numbers of breeding whitethroat which 173 breed in tall herbs or low shrubby growth in open habitats, hedgerows and scrubland. 8.147 Surveys to identify the location of nesting redshank were also undertaken in 2009 (Appendix 8.7). These identified three main areas of redshank nesting activity within Pegwell Bay: 8.148 The lagoon north of Pegwell Bay Country Park; Saltmarsh east of Pegwell Bay Country Park; and Saltmarsh South of Pegwell Bay Country Park. The lagoon north of Pegwell Bay Country Park is of most relevance to this assessment, as it is approximately 5m east of the proposed cable route, between the TJP and the Country Park. Fish 8.149 Information received from the Environment Agency identifies the River Stour as a migration route for the following protected species of fish: European Eel (NERC); Atlantic Salmon (Habitat Regulations); and River Lamprey (Habitat Regulations). 8.150 European eel, Atlantic salmon and river lamprey are all listed as UK BAP priority species. 8.151 No part of the River Stour is located within the site, however the river is located within 15m of the southern boundary of the converter station and substation site. Seals 8.152 Two species of seals breed within British waters: 8.153 Harbour Seal; and Grey Seal. Both species of seal occur within the waters off the coast of Pegwell Bay and records received from KMBRC indicate the presence of Harbour seal within Pegwell Bay. There are believed to be approximately 50 harbour seals within the Stour Estuary. Baseline Projections 8.154 An integral part of ecological impact assessment is to consider the predicted trends of each of the ecological features if no development were to be carried out. 8.155 In the absence of the development, the ecological interest of each part of the site would remain more or less at existing levels. Habitats along the majority of the cable corridor are currently managed by KWT. Management of these habitats would continue, maintaining existing ecological interest. Habitats at the former power 174 station, comprising hardstanding are unlikely to alter significantly from their current state within a reasonable timeframe. Selection of Key Receptors 8.156 There will be no impact on the Ash Level and South Richborough Pasture LWS as part of the construction or operation phases of the development. No part of the site is located within the LWS and standard construction working practices will avoid any environmental effects from noise, lighting and pollution. 8.157 There will be no impact on the Wood and Grasslands, Minster Marshes LWS as part of the construction or operation phase of the Proposed Development due to its location 500m west of the site. Similarly, there will be no impact in the RNR within the country park, due to its location approximately 25m west of the proposed cable corridor. These features are therefore not considered key receptors. 8.158 Plantation, woodland and scrub within the survey area are widespread and are of value as nesting bird habitat. A very small area of these habitats will however be affected by the proposed works. These habitats will therefore be assessed along with impacts to breeding birds. 8.159 The plantation, woodland and scrub habitats also hold some potential value for foraging and commuting bats. Removal of the small areas of these habitats is unlikely to result in any impact on bats. Bats are therefore excluded from the assessment. 8.160 Although evidence of otters has previously been identified using the River Stour, southwest of the converter station and substation, it is not anticipated that any significant impact on otters periodically using the river will be caused during construction or operation. Otters are therefore not considered to be a receptor. 8.161 The Key Receptors, identified on the basis of their size and range in relation to local and national trends, are listed in Table 8.4. Table 8.4: Ecological Receptors Receptor Pegwell Bay Designated Areas: Thanet Coast and Sandwich Bay Sandwich Bay Thanet Coast Sandwich and Pegwell Bay (including Pegwell Bay Country Park) Stonelees Nature Reserve habitats (part of the wider Sandwich and Designation/Protection/Status Value SPA/Ramsar SAC SAC International NNR National SSSI Local 175 Receptor Pegwell Bay KWT reserve) Unit 11 Sandwich Bay and Hacklinge Marshes Wintering birds Breeding birds (including redshank) Protected Flora (Lizard Orchid, Martin’s Ramping fumitory, Bedstraw Broomrape Natterjack Toads Reptiles (common lizard, slow worm and grass snake) Water voles River Stour, European Eel, Atlantic Salmon and River Lamprey Seals Designation/Protection/Status Value SSSI National Wildlife and Countryside Act Habitat Regs Wildlife and Countryside Act Regional Wildlife and Countryside Act Local Wildlife and Countryside Act Wildlife and Countryside Act International Local Wildlife and Countryside Act NERC Habitat Regs Local National Habitat Regs National Local Prediction and Assessment of Significance of Potential Impacts 8.162 Only those habitats and species of at least local value have been considered as significant effects on ecological features of less than local value are not likely to be considered by the local planning authority as material to the decision to proceed with the Proposed Development. The characterisation of the impacts on valued ecological features and significance of effects during construction and operation are described in the absence of mitigation. Construction 8.163 The description of construction is set out in Chapter 2. Potential environmental effects upon water and air quality which may arise from spillages or dust generated during construction are discussed in other chapters (Chapter 7 – Hydrology and Flood Risk, Chapter 12 Noise and Vibration and Chapter 13 Air Quality). This chapter identifies the potential ecological effects that may result upon the ecological receptors identified in Table 8.4, including sites designated for nature conservation and protected species. 8.164 The cables route has been carefully considered to avoid affecting sensitive habitats where possible and to exploit opportunities to enhance biodiversity. Potential predictable effects (prior to mitigation) on Key Receptors of ecological importance arising from the construction phase works are as follows: 176 Temporary loss and disturbance of saltmarsh habitats within Ramsar, SPA, SAC, SSSI and NNR areas; Temporary disturbance of birds overwintering within the saltmarsh and mudflat habitats within Ramsar, SPA, SAC, SPA, Ramsar, SSSI and NNR areas; Loss of nesting habitat and temporary disturbance of nesting birds; Temporary loss of grassland habitats within Stonelees Nature Reserve (SPA, Ramsar, SSSI and NNR); Temporary disturbance of reptiles and temporary loss of reptile habitat; Temporary disturbance of natterjack toads and temporary loss of natterjack toad terrestrial habitat; and Temporary disturbance of water voles. Pegwell Bay Designated Areas 8.165 Table 8.2 provides a list of the designated sites or features for which they are designated may be affected by the proposed works. 8.166 The subsea cables would pass through approximately 1,900m of designated areas including Thanet Coast and Sandwich Bay SPA and Ramsar, Sandwich Bay SAC, Sandwich Bay to Hacklinge Marshes SSSI and Sandwich and Pegwell Bay NNR before connecting to the onshore cables in a below ground TJP within an area of saltmarsh. The onshore underground cables would run from the TJP and pass through further saltmarsh and modified grassland for approximately 260m before entering the Pegwell Country Park. In total the cable corridor passes through 2,160m of the designated areas of Pegwell Bay. Works that could potentially affect the intertidal mudflats, saltmarsh and modified neutral grassland habitats during the construction phase of the development include: Trenching and installation of the subsea cable across mudflats and saltmarsh habitats; Excavation and installation of TJP within saltmarsh habitat; Excavation of joint pit within Pegwell Bay Country Park; Excavation and installation of onshore cable within saltmarsh and modified grassland habitats; and Reinstatement of excavated areas. 8.167 The trenching works will result in the temporary disturbance of sediments within the intertidal area and the removal of saltmarsh within the offshore cable corridor and the temporary removal of saltmarsh and grassland vegetation within the onshore cable corridor. The effects will however be short term, temporary and reversible, and would affect a very small area of the Pegwell Bay designated site 8.168 In addition to the above effects, temporary disturbance to wintering birds, breeding birds and intertidal invertebrates is also likely. These effects have been assessed separately below. 8.169 The important sand dune and grazing marsh habitats within the designated areas are generally south of the River Stour, between 800m and 1,300m from the cable route. There will therefore be no direct effect and no anticipated pathway that may result in indirect effects on these habitats. 177 8.170 A full assessment of the predicted impacts on the internationally designated sites (SAC, SPA and Ramsar sites) has also been undertaken within the ‘Information for Habitats Regulations Assessment’ document (see Appendix 8.9). National Nature Reserve (NNR) and Pegwell Bay Country Park 8.171 The habitats within the NNR that also fall within the Pegwell Bay designated sites are described above. The onshore cables would pass through approximately 1,100m of Pegwell Bay Country Park, which is also part of the NNR. The habitats within this area comprise semi-improved grassland, broadleaved plantation with occasional scattered scrub which will be affected by: Surface laying of the cable in the northern section of the Country Park (and burying with chalk); Trenching and installation of the onshore cable through semi-improved grassland plantation and scrub habitats in the southern section of the Country Park; Scrub and tree removal to allow cable installation works; Installation of onshore underground cables; and Reinstatement of excavated areas. 8.172 The trenching works will result in the temporary removal of grassland, and permanent removal of scrub and woodland habitats within the Country Park. 8.173 In the northern section of Pegwell Bay Country Park, the cable will be laid on top of the existing ground level to avoid disturbing the underlying landfill. Chalk will be used to cover the cables and will be graded into the surrounding ground levels. The graded chalk will then be used to create a swathe of chalk grassland through the north of the park, connecting to the area of existing chalk capped area in the southern section of the Country Park. This will increase habitat and provide habitat for more diverse range of native species. 8.174 In the north of the Country Park a temporary works compound will be created within grassland adjacent to the proposed cable route. An access track to the compound will link to the adjacent A256 Sandwich Road. 8.175 The effects on the grassland will be short term and temporary, while the effects on plantation and scrub will be permanent. Stonelees Nature Reserve 8.176 The onshore underground cables would pass through approximately 330m of Stonelees Nature Reserve which is also part of the Thanet Coast and Sandwich Bay SPA and Ramsar site, Sandwich Bay to Hacklinge Marshes SSSI, Sandwich and Pegwell Bay NNR and Sandwich and Pegwell Bay KWT reserve. The habitats within this area comprise unimproved grassland and broadleaved woodland with occasional scattered scrub which will be affected by: Trenching and installation of the onshore cable through unimproved grassland and broad-leaved woodland habitats; Scrub and tree removal to facilitate trenching works; Installation of onshore cable; and 178 Reinstatement of excavated areas. 8.177 The trenching works will result in the temporary removal of grassland and permanent removal of scrub and woodland habitats within the nature reserve. 8.178 The effects on the grassland habitats will be short term and temporary, while the effects on woodland and scrub will be permanent. The works will impact a relatively small area of the Nature Reserve. Unit 11 Sandwich Bay to Hacklinge Marshes Site of Special Scientific Interest (SSSI) 8.179 The onshore underground cables would be installed from the BayPoint sports complex under the A256, Minster Stream and Unit 11 of Sandwich Bay to Hacklinge Marshes SSSI which consists of unimproved neutral grassland and scrub. The proposed cable will be installed using horizontal directional drilling, which will avoid affecting the habitats within this area. There will be no impact upon the SSSI or Minster Stream as a result of installation of the onshore underground cables. 8.180 No part of the converter station and substation falls within the SSSI and there will be no direct habitat loss or disturbance impacts from the converter station and substation station construction. Wintering Birds 8.181 The subsea cable cables and onshore underground cables will take up to 12 weeks to install. The cable installation works therefore have the potential to disturb birds using the habitats as an overwintering site, or passage birds temporarily present within the bay through: Visual disturbance of birds through the physical presence of machinery and people within the mudflats and saltmarsh; Disturbance of birds from noise generated during cable installation works; and Disturbance or removal of prey items through trenching works within mudflat habitats. 8.182 The Intertidal Sediment and Invertebrate Survey (Appendix 8.8) identified four distinct areas of importance to wintering birds within Pegwell Bay based on the invertebrate species range and abundance. The most important feeding area is avoided by the subsea cable route which is approximately 400m metres to the south of the offshore cable. The patchy distribution of diverse invertebrate communities and the widespread abundance of prey items such as cockle and Annelid species will ensure that waders are not dependent on limited or specific feeding locations. Displaced birds would therefore be able to feed elsewhere in the bay during cables installation. 8.183 Cables installation will only disturb a very small proportion of the total prey species in the bay. The trench across the intertidal area will be 1m wide and 1.2m deep. Overall, it is expected that the magnitude of change will be low. Although bird numbers of national and international importance visit the site, the impact of the temporary disturbance effect on wintering bird species, in combination with feeding 179 opportunities across the intertidal area on wintering bird species is likely to be of minor significance. 8.184 The assessment undertaken as part of the ‘Information for Habitat Regulations Assessment’ document (Appendix 8.9) concludes that localised simplification of habitats may result in a reduced range of prey species and reduction of prey items within areas of the mudflats directly affected by excavation. Excavation within the mudflats will affect approximately 0.065% of the mudflat habitats and is therefore unlikely to have a significant effect on the available prey items across the total available habitat. 8.185 The proposed converter station and substation would be approximately 400m from important wintering bird areas. The construction site is visually screened from the internationally designated habitats. There will be no impacts on overwintering birds as a result of the converter station and substation construction or operation. Breeding Birds including Redshank 8.186 Pegwell Bay Country Park is of local importance for breeding bird species including redshank and whitethroat. The Breeding Bird and Nesting Redshank Survey (Appendix 8.7) identified a total of 34 bird species during the survey although it was noted that some species may not have been breeding in the survey area. 8.187 Three redshank nesting areas were identified by the survey in Pegwell Bay and one of these is located at the ephemeral pool within the saltmarsh. This nesting area is within 20m of the onshore underground cable route so there is potential for temporary disturbance to breeding redshank if works take place during the nesting season. 8.188 Works within areas containing dense vegetation, including Pegwell Bay Country Park and Stonelees Nature Reserve have potential to disturb nesting birds. Removal of trees, scrub and tall herbs through cables installation has the potential to disturb a range of passerine birds using the habitats for nesting. Installation works will result in temporary disturbance of nesting habitats, while the loss of nesting and foraging habitat in the form of trees and scrub would be permanent. Only a small area of nesting habitat however would be lost as part of the scheme and would not result in a significant reduction in nesting habitat. 8.189 There is a small area of suitable nesting habitat within the site of the proposed converter station and substation, consisting of a group of trees in the southeast corner of the site. The proposed removal of these trees has the potential to directly impact upon birds nesting within this habitat if undertaken during the nesting season. The removal of the trees will also reduce the amount of nesting habitat available within the site. Visual and noise disturbance also has the potential to disturb birds nesting within the adjacent habitats, including Unit 11 of Sandwich Bay to Hacklinge Marshes SSSI. Activity and noise levels are unlikely to be significantly different to those experienced during demolition works at the site. Additionally, birds become habituated to this kind of disturbance and nesting activities are unlikely to be affected. 180 Protected Flora 8.190 No protected species of plants were identified within the development application boundary during the Phase 1 Habitat surveys. Lizard orchid, bedstraw broomrape and Martin’s ramping fumitory have previously been recorded in the Country Park and Stonelees Nature Reserve. 8.191 Cable installation works have the potential to affect individuals of these species which could result in their loss. The impacts of the cable installation works on protected species of flora would be temporary and reversible, affecting only a very small area of suitable habitat. Following reinstatement, suitable recolonisation opportunities would be provided. Natterjack Toads 8.192 There is potential for the cable installation works to affect natterjack toads within Stonelees Nature Reserve through disturbance of a small area of grazed grassland in the northern section of the Reserve. The works will result in the temporary loss of terrestrial habitat and may potentially result in injury or death of natterjack toads, were they to be present within the working areas at the onset or during works. Construction impacts on natterjack toad habitat will be temporary, and reversible, affecting a small proportion of the overall surrounding habitat. The impact of causing injury or death to individual natterjack toads would be permanent. Reptiles 8.193 Cable installation works between the landfall and the southern edge of Stonelees Nature Reserve will result in the temporary loss of reptile habitat in the form of grassland and plantation/woodland edge and scrub habitats. Cabling works also have the potential to result in injury or death of common lizard, slow worm and grass snake. The impact of cable installation works on reptile habitat will be temporary, and reversible, affecting a small proportion of the overall surrounding habitat. The impact of causing injury or death to individual reptiles would be permanent. Following reinstatement, reptiles will be able to recolonize along the cable route. 8.194 There will be no effect on reptile habitats within Unit 11 of Sandwich Bay to Hacklinge Marshes SSSI, north of the converter station, as the cable will be installed using HDD methods between the BayPoint sports complex and the converter station and substation site. Watercourses, Ditches and Water Vole 8.195 Minster Stream and ditches within Unit 11 of Sandwich Bay to Hacklinge Marshes SSSI are the only watercourses and ditches that will be crossed by the onshore underground cables. HDD will be used to install the cables under the stream and SSSI; ditch habitats and water vole populations will not be affected in these areas. 8.196 The onshore cables installation working area within Stonelees Nature Reserve is approximately 5m from the bank of the ditch that runs parallel to Sandwich Road. Water voles have previously been identified within this ditch (TOWF, 2005). The ditch has however deteriorated since water voles were detected, the banks have become heavily shaded and the ditch is dry for long periods. If water voles are still present, disturbance to water voles is unlikely. 181 8.197 The construction of the converter station and substation will not directly affect any ditches within Unit 11 of Sandwich Bay to Hacklinge Marshes SSSI or the River Stour as the boundary of the site is a minimum of 15m from each of these sites. River Stour, European Eel, Atlantic Salmon and River Lamprey 8.198 The construction of the converter station and substation will not directly affect the River Stour. Impacts may however be caused through sediments and pollution being washed into the river within surface water runoff. Impacts to migratory life stages of fish species may also be caused through the lighting of the site during construction. Seals 8.199 Due to the presence of seals within the Stour Estuary and Pegwell Bay, there is some potential for disturbance of seals during works within the intertidal zone. Disturbance will be limited to the presence of vessels, machinery and personnel during cable installation within the intertidal zone. Disturbance will be localised and temporary and is likely to cause low levels of disturbance to seals. 8.200 There is further potential for disturbance to seals during the offshore cable installation works. These potential impacts are assessed in the marine cable Environmental Statement (see Appendix 16.1 for non-technical summary). 8.201 There is no potential for disturbance to seals during the installation of the onshore cables or construction of the converter station or substation due to the isolation from suitable habitats. Construction Impact Summary 8.202 Table 8.5 summarises the predicted impacts of cables installation and construction of the converter station and substation on identified ecological receptors, prior to mitigation. 182 Table 8.5: Construction Impacts Magnitude and Extent Pegwell Bay Designated Areas Loss of saltmarsh Moderate (approx. habitat through 180m) trenching works during cable installation Disturbance of mudflat Moderate (approx. habitats during 1750m potentially trenching works and affected although cable installation actual working area likely to be far less). Impact Description Loss of modified Moderate (approx. grassland habitats 230m) through installation of cable NNR and Country Park Loss of semi improved Moderate (approx. grassland, plantation 1100m) and scrub habitats Stonelees Nature Reserve Loss of grassland Moderate (approx. habitats through 330m) trenching and installation of cable Reversibility Temporary, during cable installation only Temporary, during cable installation only Reversible Impact would be Certain (recolonisation by constant during saltmarsh vegetation) cable installation only Reversible Impact would be Certain (recolonisation of constant during trenched areas of cable installation mudflats is likely to only extend beyond the cable installation period) Irreversible Impact would be Certain constant during construction Adverse Temporary, during cable installation only Reversible Impact would be Certain (recolonisation of constant grassland vegetation) throughout cable installation within the Country Park Adverse Temporary, during cable installation only Reversible Impact would be Certain (recolonisation of constant grassland vegetation) throughout cable installation within nature reserve Adverse Permanent 183 Frequency Probability Direction of Significance Duration Adverse Adverse Impact Description Wintering Birds Disturbance of birds using Pegwell Bay during winter period (October - May) during installation of cable Magnitude and Extent Minor (cable route avoids key feeding areas but would likely result in displacement of birds to alternative feeding areas around the bay) Breeding Birds including Redshank Disturbance of nesting Minor (small areas of birds during tree and nesting habitat scrub removal affected by cable required ahead of installation works) cable installation within the Country Park and Stonelees Nature Reserve Disturbance of nesting Minor (small areas of birds during tree and nesting habitat scrub removal affected) required prior to construction within converter station and substation site. Disturbance of nesting Minor (habitats redshank during cable adjacent to saltmarsh installation within pool next to the cable proximity of saltmarsh corridor) lagoon Reversibility Frequency Temporary during cable installation Reversible (disturbance will cease following completion of cable installation) Impact would be Probable constant during cable installation only Adverse Temporary during cable installation Reversible (disturbance will cease following completion of cable installation) Impact would be Probable constant through cable installation period Adverse Temporary during cable installation Irreversible (removal of trees) Impact would be Certain constant through construction period Adverse Temporary during cable installation Reversible (disturbance will cease following completion of cable installation) Impact would be Probable constant through cable installation period Adverse 184 Probability Direction of Significance Duration Magnitude and Extent Protected Flora – Local Value Removal of protected Minor (loss of plant species during individuals) cable installation works Natterjack Toads Removal of habitats Moderate (grazed used by natterjack unimproved toads within Stonelees grassland) Nature Reserve during cable installation Direct impact on Minor Natterjack toads causing injury or death. Reptiles Removal of habitats Moderate (approx. used by reptiles within 1,700m of cable Pegwell Bay, Pegwell corridor through Bay Country Park and modified grassland, Stonelees Nature semi improved reserve during cable grassland, unimproved installation grassland and scrub habitats) Direct impact on Moderate reptiles during cable installation causing injury or death. Impact Description Reversibility Frequency Permanent Irreversible Constant during Unlikely cable installation Adverse Temporary during construction period only Reversible (through reinstatement of habitats) Constant during Probable cable installation Adverse Permanent Reversible (risk will cease following completion of cable installation) Constant during Probable cable installation Adverse Temporary during cable installation only Reversible (recolonisation of vegetation) Constant during Probable cable installation Adverse Temporary during cable installation only Reversible (risk will cease following completion of cable installation) Constant during Probable cable installation Adverse 185 Probability Direction of Significance Duration Impact Description Magnitude and Extent Duration Reversibility Water Voles Disturbance of ditches Minor Temporary Reversible (will cease that support water following completion vole within Stonelees construction) Nature Reserve River Stour, European Eel, Atlantic Salmon and River Lamprey Pollution of river Moderate Temporary Reversible (risk will habitats used by cease following protected species of completion of fish during migration construction period) through surface runoff carrying sediments and chemicals. Disturbance of Major Temporary Reversible (risk will migrating fish species cease following through lighting completion of impacting upon river construction period) habitats Seals Disturbance of seals Negligible Temporary Reversible (risk will during cable cease following installation across the completion of intertidal zone. construction period) 186 Frequency Probability Direction of Significance Constant Unlikely Adverse Intermittent Probable Adverse Intermittent Probable Adverse Intermittent during cable installation Probable Negligible Operation 8.203 Once installed, the cables will not be visible and will not require any maintenance or further works except in the unlikely event of failure necessitating repair. In this case the likely location of any works will be at the TJP or the two other joint pits along the cable route. 8.204 No effects on designated sites, habitats or protected species are anticipated during operation of the cable. 8.205 Some minor disturbance of habitats and species within the Pegwell Bay designated habitats will be caused through surveys that will be undertaken to monitor the recolonisation of the working areas by saltmarsh species. This will involve occasional access by surveyors and will be timed to avoid impacts of wintering and breeding birds. Converter Station and Substation 8.206 Only six staff will be required to access the converter station and the substation will be unmanned except for infrequent maintenance inspections and emergencies. Potential lighting and noise impacts that may disturb habitats and protected species in adjacent areas will be reduced using standard methods such as lighting regimes and noise mitigation measures. Operation Impact Summary 8.207 Table 8.6 summarises the predicted impacts of the development during operation on identified ecological receptors, prior to mitigation. 187 Table 8.6: Operational Period Impacts Impact Description Magnitude / Extent Duration Reversibility Frequency Probability Direction of Significance Temporary (3 visits over 3 years following installation) Reversible Intermittent Negligible Pegwell Bay Designated Areas Monitoring surveys of saltmarsh recolonisation Negligible 188 Certain Mitigation 8.208 This section identifies the mitigation measures proposed to minimise impacts upon ecological receptors. It considers the effectiveness of the mitigation and the time required for the mitigation to become effective. Time is an important factor, as works such as planting would require an establishment period and a maturation period before they have the potential to replace mature and structured habitats lost during construction activities. In some instances though, mitigation measures may have an immediate effect. Time periods are considered as follows: Immediate – effective immediately; Short term – effective within 2 years; Medium term – effective within 2 to 5 years; and Long term – effective within 5 to 10 years. 8.209 Mitigation is required for each significant effect upon receptors in order to reduce the specific impacts of the proposed development to acceptable levels. 8.210 Method Statements will be produced prior to any works within designated areas detailing how impacts on the habitats and species within the area will be reduced or avoided. These will be produced in consultation with NE and KWT. Pegwell Bay Designated Areas 8.211 The route of the subsea and onshore underground cables and location of the TJP and other joint pits have been chosen to avoid ecologically sensitive receptors wherever possible. The subsea cable and landfall are within areas of saltmarsh south of the area previously disturbed by the installation of the Thanet Offshore Wind Farm cable. This will avoid disturbance to the more extensive areas of saltmarsh habitats south of the cable corridor. 8.212 Site compounds will be located outside of the Pegwell Bay designated areas. No equipment, materials, chemicals or fuel will be stored within or adjacent to designated areas. Compounds within the Richborough Site and Pegwell Bay Country Park will be used for the storage of equipment, materials and chemicals. All refuelling of plant will be undertaken within the site compounds, within the Richborough Site and Pegwell Bay Country Park 8.213 Prior to the start of installation works the saltmarsh areas that are to remain untouched by the works shall be visibly segregated from the works area using temporary fencing. An ecologist shall advise as to locations of these habitats and placement of protective fencing. 8.214 Machinery required to access the intertidal areas will be restricted to set routes to limit the area impacted. 8.215 Drip trays or plant nappies will be used under all mobile or small plant such as generators etc. 8.216 Delivery vehicles will deliver to the site compounds to reduce disturbance and risk of spillages and leaks within the designated areas or wider areas. 8.217 All plant and equipment working in the vicinity of the shore line shall be clean on delivery. If not all tracks, wheels etc. shall be thoroughly cleaned before entering the 189 working area. Generation of silt shall be minimised by excavators/dumpers etc. by limiting movements by machinery. 8.218 A contingency plan for spillages etc. shall be produced prior to start on site. Spill kits will be available in the site compound and all working plant such as dumpers/excavators. 8.219 Vegetation that will be directly affected by cable installation works will be removed by cutting turves. The turves will be stored locally and will be replaced following completion of cable installation and backfilling of the trench. Different saltmarsh and grassland communities will be stored separately and replaced based on the NVC habitat types in each part of the saltmarsh. Removal, storage and replacement arrangements and removal will be determined through production of a Method Statement in consultation with NE. 8.220 All suitable plant and equipment working in the designated sites will be bio oil based. A site checklist will be used for traffic management and plant to ensure they are all in good working order. 8.221 Excavated material on the mudflat habitats will be replaced as quickly as possible to avoid leaving exposed trenches at times of high tide. There will be no loss of mudflat habitats as part of the works but the disturbance of the mudflats through excavation of sediments will be unavoidable. 8.222 Reinstatement of habitats will be undertaken in sections as the cable installation is completed and immediately following backfilling. 8.223 Following installation of the cable and TJP the working area within the saltmarsh will be fenced to allow saltmarsh vegetation to re-establish without further disturbance. This method was used following installation of the Thanet Offshore Wind Farm cable and has resulted in positive recolonisation of the affected areas by saltmarsh species. This mitigation will be effective in the medium term. 8.224 Monitoring surveys of the affected saltmarsh will be undertaken for five years following construction and the results will be submitted to NE and KWT. 8.225 Monitoring surveys of intertidal invertebrates will be undertaken annually for a period of 5 years following the cable installation works to determine the recolonisation rates of the disturbed areas of mudflat habitats. 8.226 Full details of the proposed mitigation for cable installation within the Pegwell Bay internationally designated areas is provided in the ‘Information for Habitat Regulations Assessment’ document (Appendix 8.9). Pegwell Bay Country Park 8.227 In the northern section of Pegwell Bay Country Park, the cable will be laid on top of the existing ground level to avoid disturbing the underlying landfill. Chalk will be used to cover the cables and will be graded into the surrounding ground levels. The graded chalk will then be used to create a swathe of chalk grassland through the north of the Country Park, connecting to the area of existing chalk capped area in the southern section of the Country Park. This will increase habitat and provide habitat for more diverse range of native species. The aspect of the mitigation will be effective immediately. 190 Stonelees Nature Reserve Habitats 8.228 Within Stonelees Nature Reserve, as far as is practical, the working width associated with cables installation will be kept to a minimum and be kept close to the existing cycle path. Impacts will be reduced to habitats within the previous working area of the cycle path, affecting as little of the previously undisturbed habitats as possible. 8.229 Site compounds will not be located within Stonelees Nature Reserve. No equipment, materials, chemicals or fuel will be stored within or adjacent to designated areas. Compounds within the Richborough Site and Pegwell Bay Country Park will be used for the storage of equipment, materials and chemicals. All refuelling of plant will be undertaken within the site compounds, within the Richborough Site and Pegwell Bay Country Park 8.230 All suitable plant and equipment working in the designated sites will be bio oil based. A site checklist will be used for traffic management and plant to ensure they are all in good working order. 8.231 Drip trays or plant nappies will be used under all mobile or small plant such as generators etc. 8.232 All plant and equipment working in the vicinity of the shore line shall be clean on delivery. If not all tracks, wheels etc. shall be thoroughly cleaned before entering the working area. Generation of silt shall be minimised by excavators/dumpers etc. by limiting movements by machinery. 8.233 A contingency plan for spillages etc. shall be produced prior to start on site. Spill kits will be available in the site compound and all working plant such as dumpers/excavators. 8.234 To inform the production of a mitigation Method Statement for works within Stonelees Nature Reserve, an NVC survey will be undertaken of areas to be affected by the proposals. Information obtained as part of the survey will be used to produce a Method Statement in consultation with NE detailing mitigation and working methods to be used during installation of the cable. 8.235 Prior to commencement of works within Stonelees Nature Reserve, temporary fencing will be installed around the site working areas to ensure encroachment into surrounding habitats is avoided. 8.236 Grassland habitats to be affected by trenching and cable installation works will be removed in turves and replaced following reinstatement of subsoil areas. Removal, storage and replacement arrangements will be determined through production of a Method Statement in consultation with NE. 8.237 Reinstatement of habitats will be undertaken in sections as the cable installation is completed and immediately following backfilling. 8.238 Full details of the proposed mitigation for cable installation within the Pegwell Bay internationally designated areas is provided in the ‘Information for Habitat Regulations Assessment’ document (Appendix 8.9). 191 Wintering Birds 8.239 Cable installation works within the designated areas saltmarsh and modified grassland of Pegwell Bay will commence outside the months that peak numbers of birds using the intertidal and saltmarsh habitats are present. The wintering bird assessment identified the most sensitive times periods of disturbance for wintering birds within the intertidal areas as being October to February (for lapwing, golden plover, turnstone and grey plover) and May (for turnstone, sanderling and grey plover). Cable installation works within the intertidal and saltmarsh areas will not be undertaken during this period. This will also apply to any cable installation works within 50m of the seaward edge of the Country Park to prevent disturbance from the use of machinery on the edge of the park. 8.240 In the event of delays resulting in the cable installation works within the intertidal area extending into the sensitive period for wintering birds, further mitigation will be supplied. Where possible, wooden hoarding will be used to visually screen the works from birds using the bay. For the duration of the extended working period an additional warden will be supplied to help deter members of the public entering the intertidal area during works. 8.241 Cable installation within this area will be undertaken following a Method Statement produced in consultation with KWT and NE. This mitigation will be effective immediately. Breeding Birds including Redshank 8.242 Installation of the onshore cable, TJP and subsea cable within the saltmarsh habitats north of the Country Park will be phased to avoid the peak nesting period for species, such as redshank, that use the saltmarsh habitats for nesting purposes (Mid April to July). During this period no works will be undertaken within 100m of the pool within the saltmarsh habitats to avoid disturbance to nesting redshank. Prior to the commencement of works within the saltmarsh habitats, a walkover survey will be undertaken (with a KWT warden if required) to determine the presence of any active nests and if necessary works will be postponed until nests are no longer active. Methods used during this survey and works within the saltmarsh will be detailed in a Method Statement. This aspect of the mitigation will be effective immediately. 8.243 Removal of vegetation for cables installation within Pegwell Bay Country Park and Stonelees Nature Reserve will be undertaken outside of the bird nesting season (March-August inclusive) or will be preceded by an inspection by an ecologist for active nests immediately prior to vegetation removal. 8.244 Removal of vegetation within the converter station and substation site will be undertaken outside of the bird nesting season (March-August inclusive) or will be preceded by an inspection by an ecologist for active nests immediately prior to vegetation removal. Replacement planting within the converter station and substation site will replace nesting habitat removed prior to the start of the development. Protected Flora 8.245 Pre-commencement surveys of the cable route will be undertaken to identify any protected species of flora within the working area. In the event that any protected plants are discovered, these plants will either be fenced out of the working area or 192 transplanted to undisturbed locations as appropriate to their requirements. Where practical, measures will be implemented to encourage recolonisation of the working areas by these species (e.g. seed selection). These methods will be detailed within Method Statements covering the working methods of cable installation. Natterjack Toads 8.246 A licence will be obtained from NE to allow the cable installation works that may affect suitable natterjack toad habitats within 500m of the reintroduction site within Stonelees Nature Reserve. As part of the licence application, a Method Statement will be produced in consultation with KWT and NE. The details of the licence will be determined during the licence application process, but are likely to include a combination of the timing of works to avoid disturbance to potential hibernation features during the winter months (Nov-Feb), habitat management and controls to reduce disturbance effects and translocation. Additionally arisings from the trench excavation works can be used to create suitable amphibian refugia, following agreements with KWT and NE. This element of the mitigation will be effective immediately. Reptiles 8.247 A repeat survey of suitable reptile habitats will be undertaken prior to the cable installation works. This information will be used to produce a reptile Method Statement detailing the methods that will be used to install cables within these areas and the locations of these methods. The Method Statement will be produced in consultation with KWT. 8.248 Vegetation within areas affected by works between Pegwell Bay Country Park and the TJP and within Pegwell Bay Country Park and Stonelees Nature Reserve will be managed prior to works to degrade habitat suitable for use by reptiles. Potential refugia will also be removed from the working area and placed within suitable undisturbed habitats. Vegetation removal will be implemented outside of the bird nesting period (March to August inclusive) or will be subject to inspections by an ecologist prior to removal. Habitat management and cable installation will be undertaken between April and September when reptiles are most active due to higher temperatures. 8.249 Following completion of cable installation the ground will be reinstated either through seeding the chalk bunds in the north of the Country Park or by replacing original topsoil where excavations have taken place. 8.250 Arisings from the excavation works can be used to create reptile refugia in suitable undisturbed areas of the Country Park. Bats 8.251 The converter station and substation external lighting scheme would typically only be used for emergencies and during maintenance activities required outside hours of daylight. This will ensure that potential bat foraging and commuting habitats are not detrimentally affected. This mitigation will be effective immediately. Watercourses, Ditches, and Water Vole 8.252 The working area for cables installation within Stonelees Nature Reserve will be maintained as a minimum of 5m from the ditch that runs parallel to the proposed 193 onshore cable route. This will avoid disturbing any water voles that may be present within the ditch. River Stour, European Eel, Atlantic Salmon and River Lamprey 8.253 The converter station and substation external lighting scheme would typically only be used for emergencies and during maintenance activities required outside hours of daylight. This will ensure that fish migration along the River Stour is not detrimentally affected. This mitigation will be effective immediately. Seals 8.254 Due to the predicted negligible impacts on seals within the intertidal zone there is no specific mitigation proposed. Residual Impacts 8.255 Following mitigation no significant effects on ecological features are predicted, and there are opportunities to provide features that could provide a benefit for biodiversity. Cable installation works will be timed to avoid or minimise impacts on breeding birds, nesting birds and natterjack toads. Different sections of the cable will be installed at different times depending on the timing constraints within each section. Table 8.7: Residual Impacts to Ecological Receptors Receptor Pegwell Bay Designated Areas NNR and Country Park Stonelees Nature Reserve Habitats Wintering birds Breeding birds including redshank Protected flora Natterjack toads Reptiles Receptor Value Potential Impact Magnitude International Moderate adverse Residual Impact Magnitude Phase Negligible Construction National Moderate adverse Moderate adverse Minor beneficial Construction Minor adverse Construction Regional Minor adverse Negligible Construction Local Minor adverse Negligible Construction Local Minor adverse Negligible Construction County Moderate adverse Moderate adverse Negligible Construction Negligible Construction Local Local 194 Receptor Receptor Value Potential Impact Magnitude Minor adverse Residual Impact Magnitude Phase Negligible Construction Moderate adverse Negligible Construction Negligible Negligible Construction International Negligible Negligible Operation Watercourses, Local ditches, water vole River Stour, National European Eel, Atlantic Salmon and River Lamprey Local Seals Pegwell Bay Designated Areas Cumulative Impacts 8.256 Potential cumulative effects on ecology from the onshore elements of the Nemo Link in combination with other components of the Nemo Link (i.e. UK, French and Belgian subsea cables and Belgian onshore infrastructure) are described in Chapter 16. 8.257 Potential cumulative effects of the Nemo Link UK onshore infrastructure in combination with the grid connection required to facilitate the operation of the Nemo Link are described in Chapter 17. 8.258 There is potential for cumulative ecological effects to arise from other projects and plans in the vicinity of the Proposed Development (see Table 1.2, Chapter 1 for full details). 8.259 The effects on ecology arising from the Proposed Development are anticipated to be primarily temporary and reversible in that mitigation will include restoration of disturbed habitats. 8.260 The following paragraphs consider the cumulative effect of the proposed converter station, substation and underground cable, in combination with each of the six development proposals referred to above. 8.261 An assessment of cumulative impacts of the six development proposals has also been undertaken as part of the Assessment of Likely Significant Effects included on European Designated Sites (Information for Habitat Regulation Assessment – see Appendix 8.9). Richborough A Limited Estate Road and Landscaping 8.262 The new estate road will comprise additional concrete hardstanding around the perimeter of the former Richborough Power Station. Construction of the road layout is likely to result in the loss of trees at the northeast boundary of the Richborough Site, a loss of a small number of trees along the site boundary with the River Stour and a further loss of trees and shrubs along the east boundary of the site. Areas of 195 modified grassland will also be lost along the east, north-east and southeast boundaries of the site. 8.263 Due to the location of the new road adjacent to the SSSI north of the site and River Stour southwest of the site, there is potential for construction activities to impact upon these receptors. Water voles and their burrows present within the SSSI habitats may be affected by construction adjacent to the SSSI, north of the site. 8.264 The anticipated impact of the construction of the estate road is anticipated to be minor adverse. Cumulatively with the Nemo Link scheme the predicted impact on ecological receptors is predicted to remain minor adverse. 8.265 As part of the landscaping proposals for the estate road, replacement trees will be planted along the new road layout at the eastern and north east boundaries of the site. Areas of native shrubs and trees will be planted adjacent to the site entrance and along the southeast boundary. Existing vegetation along the north boundary of the Richborough site will also be retained and enhanced. Additional planting at the south west corner of the site (as part of this converter station and substation planning application) will also be provided. 8.266 Additionally, the landscaping proposals also include areas of species rich grassland adjacent to the road layout in the east of the site, along the north access road and along the new access road in the northwest of the site. 8.267 Ecology corridors are also proposed along the access road in the north west and leading away from the Nemo Link site to the west, although details of the landscaping proposed for these areas is unknown. 8.268 Overall, the proposed landscaping is anticipated to result in a slight increase in areas of habitats within the site and result in a minor beneficial impact on ecological value of the site. Cumulatively with the Nemo Link schemes landscaping proposals, which also include planting areas of habitat, along the southwest boundary of the site, the impact on the sites ecology is predicted to be minor beneficial. 8.269 There will be no temporary cumulative construction effects on ecology as the estate road network will be constructed prior to commencement of construction works in relation to the proposed converter station, substation and underground cable works. 8.270 Habitats losses within each of the sites will be offset through the landscaping schemes. During operation, no impact on the adjacent SSSI and River habitats is anticipated from the Road Layout and landscaping and suitable mitigation implemented as part of the Nemo Link scheme will avoid further impacts. On completion, the cumulative impacts of the estate road and landscaping works with the Nemo Link scheme are predicted to be negligible. Richborough Site - Peaking Plant Facility 8.271 The Peaking Plant Facility will be located to the south of the Nemo Link development at the former power station site and will comprise fifty three diesel fired generators (approximately 2.6 m high) and a chimney stack (approximately 35m high) with associated fuel storage, parking and access. The facility will occupy an area of approximately 3.37 hectares (8.3 acres). 196 8.272 The Peaking plant facility is expected to remove areas of trees, scrub and grassland within the Richborough site. Cumulatively this will result in a greater area of habitat loss within the Richborough site resulting in a predicted minor adverse impact 8.273 There will be no temporary construction cumulative effects on ecology as the Peaking Plant Facility will be constructed prior to the commencement of the construction of the converter station and substation. 8.274 There is potential for the cumulative impacts on the River Stour through disturbance and light pollution from both the Peaking Plant and Nemo Link schemes. Overall, the potential cumulative impact of the Richborough Peaking plant with the Nemo Link scheme is predicted to be minor adverse. However, both schemes will implement mitigation to reduce impacts on the River Stour, resulting in a negligible cumulative impact. Pegwell Bay Flood Defences 8.275 The Flood Defence Scheme will comprise two new flood defence elements; a new concrete flood wall (141m long and up to 1.2m high) to the north of the petrol station on the A256 Sandwich Road; and an earth embankment (257 metres long and up to 1 metre high) to the south of the petrol station. 8.276 Consultation has identified that NE is of the opinion that the flood defence scheme will not adversely affect the European Designated sites. There is potential for combined construction activity to create higher levels of disturbance to overwintering birds within the bay. However, the proposed completion period for the flood defence is during 2013, whereas the proposed start date for the UK onshore elements of the Nemo Link is late 2014/early 2015. Specifically the HVDC underground cable and TJP works are unlikely to commence before 2016. There will therefore be no temporary cumulative effects on ecology during construction as the flood defence works will be completed before HVDC underground cable and TJP installation works commence. 8.277 On completion cumulative effects on ecology will be negligible as the impacts of the cable installation are temporary and habitats will be reinstated upon completion. 8.278 During operation, both the Flood Defence Scheme and the HVDC underground cable and TJP are passive and will not impact upon ecology within Pegwell Bay. 8.279 There will be no cumulative effects on ecology from construction and operation of the converter station and substation, due to the isolation of the flood defences by a distance of approximately 1.76km. Erection of Glasshouses, Water Storage Tanks and Pack House 8.280 The scheme proposed on Ebbsfleet Lane will comprise the erection of glasshouses (4.7m high to the apex), three rainwater storage tanks (3.04m above ground) and a pack house (5.52 metres to ridge height) for the grading and packing of roses, storage of equipment and to provide staff facilities at Ebbsfleet Lane. No potential impacts on ecology within the Glasshouses site or surrounding area have been identified during construction or operation of the scheme. 8.281 There will be no temporary construction cumulative effects on ecology as the construction of the proposed glasshouses, water storage tanks and pack house will 197 be completed before converter station and substation construction works and HVDC underground cable installation works commence. 8.282 On completion cumulative effects on ecology are not anticipated due to the distance (400m) of the greenhouses development from the converter station and substation development and separation by the East Kent Link Road. Through implementation of standard mitigation measures, the proposed development is not anticipated to impact ecology in the wider area during operation. There is therefore not anticipated to be any cumulative impact on ecology resulting from the operation of Greenhouses development on Ebbsfleet Lane. Solar Farm South of River Stour 8.283 A Solar Farm is proposed for an area of land to the southwest of the River Stour opposite the proposed converter station and substation. The foot print of the solar farm is in the Ash Level and South Richborough Pasture LWS and will result in the partial and temporary loss of grazing marsh habitats within this site. Grazing marsh is a UK BAP priority habitat. No ecological impact on the grazing marsh habitats has been identified as a result of the construction and operation of the Nemo Link scheme and so there would be no cumulative effects on grazing marsh habitats. 8.284 The solar farm development borders the River Stour and there is potential for effects on the river during construction through pollution and sediment creation, although no impact is predicted from operation of the solar farm. 8.285 There is potential for disturbance and light pollution impacting the River Stour during the construction of the Nemo Link. Cumulatively therefore the construction activities of the solar farm and Nemo Link scheme are predicted to result in potential pollution and disturbance impacts on the River Stour which flows between the two developments. A cumulative moderate adverse impact is therefore predicted. 8.286 Mitigation will be implemented for both schemes reducing the impacts on the River Stour, resulting in a negligible cumulative impact on this receptor. Cumulative Effect of All Unrelated Developments 8.287 The cumulative effect on ecology of the proposed converter station and substation, and underground HVDC cables, in combination with all six development proposals discussed above will result in an adverse impact on ecological receptors in the local area. The residual impacts of the onshore elements of the Nemo Link are assessed to be minor adverse, neutral and minor beneficial, and as such there will be no significant increase in cumulative impacts as a result of the proposed UK onshore Nemo Link works. 198 References Froglife (1999); Reptile Survey: An introduction to planning, conducting and interpreting surveys for snake and lizard conservation. Froglife Advice Sheet 10, 1999, Froglife, Halesworth. Institute of Ecology and Environmental Management, (2006). Guidelines for Ecological Impact Assessment in the United Kingdom (7th July 2006). http://www.ieem.org.uk/ecia/index.html. Joint Nature Conservation Committee (2003). Handbook for Phase 1 habitat Survey: A Technique for Environmental Audit. JNCC, Peterborough. Joint Nature Conservation Committee (2008). Thanet Coast and Sandwich Bay Ramsar Information Sheet: UK11070 Rodwell, J.S. 2006. National Vegetation Classification: Users’ Handbook. JNCC. Royal Society for the Protection Birds (2009). Birds of Conservation Concern 3. RSPB, Sandy. Strachan, R. and Moorhouse, T. (2006). Water Vole Conservation Handbook (2nd edition). Wildlife Conservation Research Unit, University of Oxford http://www.kentbap.org.uk/ http://www.MAGIC.gov.uk http://www.natureonthemap.org.uk 199 200 9.0 ARCHAEOLOGY AND CULTURAL HERITAGE Introduction 9.1 This chapter presents a summary of the findings of a desk-based assessment (DBA) and field observations and considers the potential impacts from the construction and operation of the Proposed Development upon known archaeological, built heritage and historical sites both with and without statutory protection and impacts upon previously unrecorded archaeological sites. A detailed report of the baseline information forms Appendix 9.1. 9.2 The archaeological potential of the development site has been assessed by reference to a Study Area which comprises a 1.5km buffer zone from the maximum extents of the development. The buffer zone includes the intertidal area between the landfall and low water mark where there is an overlap with an area examined by Wessex Archaeology (2010) in relation to the marine components of the development. The assessment of effects of the marine aspects of the proposal are contained in the Marine Environmental Statement which has been submitted as part of the Marine Application; however consideration of the heritage assets noted between the landfall and low water mark has also been included as part of the onshore cultural heritage assessment. Legislation and Planning Policy Context National 9.3 Table 9.1 provides a summary of statutory legislation relevant to the historic environment. Table 9.1: Statutory Legislation with Regard to the Historic Environment Act or Regulations Relevant Provisions Ancient Monuments and Archaeological Areas Act 1979 It is a criminal offence to carry out any works on or near to a Scheduled Monument without Scheduled Monument Consent (SMC) Treasure Act 1996 The act defines what constitutes Treasure and states that any finds of treasure and objects found in association with treasure must be reported to the local coroner Planning (Listed Buildings and Conservation Areas) Act 1990 No works can be carried out in relation to a Listed building without consent. Designation of an area as a Conservation Area introduces general controls over demolition and development The act establishes principles of the development control process Burial Act 1857 Under section 25 of the 1857 act, it is generally a criminal offence to remove human remains from any place of burial without an appropriate licence issued by the Ministry of Justice (MoJ), although recent legislative changes indicate that some cases are exempt from this requirement 201 A local authority can prohibit the removal of an ‘important’ hedgerow. Hedgerows can be considered important on grounds of historical or archaeological value or association Hedgerow Regulations 1997 9.4 Table 9.2 summarises the relevant non-statutory protection relating to the historic environment. Table 9.2: Non-Statutory Protection of the Historic Environment Policy or Legislation Relevant Provisions National Planning Policy Framework (NPPF), Section 12 Section 12 of the NPPF outlines government policy on the treatment of ‘heritage assets’ (including Scheduled Monuments, Listed buildings, Conservation Areas, World Heritage Sites, Historic Parks and Gardens and Historic Battlefields, but also non-Scheduled sites, including buried or suspected buried remains), within the local plan and development control process. Register of Parks and Gardens of Special Historic Interest The Register identifies important Historic Parks and Gardens, which should then be considered by the local planning authority in accordance with NPPF. Register of Historic Battlefields The Register identifies important battlefield sites, which should then be considered by the local planning authority in accordance with Section 12 of the NPPF. Local 9.5 The Proposed Development falls within the administrative districts of both Thanet District Council and Dover District Council. Policies with regard to the safeguarding of heritage relevant to the current proposals (HE11, HE 12) have been saved from the Thanet District Local Plan (2006) and described in Table 9.3. Dover District’s Core Strategy (2010) does not contain policies specific to the historic environment, but instead, refers to relevant regional and national policies (Section 12 of NPPF, see Table 9.2). Table 9.3: Thanet District Local Plan – Historic Environment Policies Policy Relevant Issues Policy HE11 Archaeological Assessment In order to determine planning applications, the district Council may require the developer/applicant to provide additional information, in the form of an assessment of the archaeological or historic importance of the site in question and the likely impact of development. In certain cases such assessment may involve fieldwork or an evaluation excavation. (…) Planning permission will be refused 202 Policy HE12 Archaeological Sites and Preservation Archaeological sites will be preserved and protected on those archaeological sites where permanent preservation is not warranted, planning permission will only be granted if arrangements have been made by the developer to ensure that time and resources are available to allow satisfactory archaeological investigation and recording by an approved archaeological body to take place, in advance or during development. No work shall take place until the specification and programme of work for archaeological investigation, including its relationship to the programme of development, has been submitted and approved. Method 9.6 The archaeological assessment was undertaken by an Institute for Archaeologist (IfA) qualified practitioner in accordance with the IfA Code of Conduct 2010, as well as with current best practice (as described in English Heritage’s Management of Research Projects in the Historic Environment (MoRPHE) Planning Notes, 2008). 9.7 Relevant IfA guidelines were consulted which included IfA, 2010: Standard and Guidance for Archaeological Desk-Based Assessment and English Heritage. 2008: Conservation Principles. Field observations were conducted in line with the IfA’s Guidelines for Archaeological Field Evaluation (revised 2009). Desk-Based Assessment 9.8 Section 2 of the Baseline Report (see Appendix 9.1) details the full data collection method. A summary of the method is provided below. Data Sources 9.9 Cultural heritage data was collected from the following sources for two Study Areas (Study Area A and Study Area B): National Monument Record (NMR); Kent Historic Environment Record (KHER); Superseded Ordnance Survey (OS) mapping; Relevant secondary sources (including online sources); Other specialist reports prepared for this assessment; Field observations; and Wessex Archaeology Marine Archaeological Environmental Assessment Report (2010). Impact Study Areas 9.10 The two study areas were defined as: Study Area A: This is centred on the application boundary with an additional buffer of approximately 1.5km (Figure 9.1). This has been defined in order to identify known and potential unknown heritage assets within or close to the development site upon which physical impacts could potentially occur. The buffer zone includes the intertidal zone between the landfall and low water 203 mark. Data for this area has been summarised from information provided in the marine archaeological report produced by Wessex Archaeology (2010) which is being submitted as part of the Marine Application. An assessment of heritage assets within the intertidal zone has been included within this chapter. Study Area B: This has been defined in order to identify designated heritage assets within a wider study area based on a Zone of Visual Influence (ZVI) to a maximum radius of circa 10km (Figure 9.2) within which visual impacts of the above ground elements of the Proposed Development i.e. the converter station and substation, could potentially occur. 9.11 For the determination of visual (indirect) impacts, World Heritage Sites, Scheduled Monuments (SMs), Grade I and Grade II* Listed Buildings (LBs), Historic Battlefields, and Registered Parks and Gardens (RPGs) in Study Area B. Potential effects on long views from or including these heritage assets can be significant depending on their location, elevation, landscape scale and intervisibility. Visual impacts on Grade II LBs and conservation areas (CAs) were assessed for a 3km maximum study area, as long-views are not likely to contribute towards the significance of such designated assets. 9.12 Heritage asset information, including current status and an initial assessment of asset importance/sensitivity, was compiled into two gazetteers which are within Appendix 1 and 2 of the Baseline Report (Appendix 9.1). Field Observations 9.13 A site visit was undertaken by a qualified RSK archaeologist on 24th April 2012 and photographs and site notes were taken and maps sketch annotated as appropriate. The current state of preservation was recorded for areas of known archaeology as highlighted through previously gathered desk-based sources, and the potential for hitherto unknown heritage assets assessed. 9.14 A visual assessment of the setting of designated heritage assets potentially subject to visual impact was also undertaken on 24th April 2012. Heritage assets were assessed in terms of ·intended sight-lines and/or intervisibility with contemporaneous heritage assets; views towards, from and within heritage assets as relevant; landscape situation; dominance or prominence; the degree of alteration to historic cultural landscapes; and the anticipated scale of proposals in relation to the heritage assets. Photographs and site notes were taken and maps sketch annotated as appropriate. Assessment of Significance 9.15 The assessment of the significance of potential impacts on heritage asset was determined by comparing the relative receptor importance/sensitivity with the anticipated magnitude of effect. Receptor Importance 9.16 The importance of each heritage asset (receptor) within the gazetteers has been determined to provide a framework for comparison. The categories of importance do not reflect a definitive level of importance or value of an asset, but a provisional one based on criteria such as evidential, historical, aesthetic and communal values, as outlined in English Heritage’s Conservation Principles (2008). Consideration combining the four value sets offers representation of the importance of a given 204 heritage asset and provides an analytical tool that can inform later stages of archaeological assessment and the development of appropriate mitigation strategies. Table 9.4: Criteria Determining Relative Receptor Importance Receptor importance Description Very high (international) World Heritage sites (including nominated sites) Scheduled Monuments and Grade I listed buildings of acknowledged international importance Assets that can contribute significantly to acknowledged international research objectives High (national) Scheduled Monuments, listed buildings and conservation areas Assets that can contribute significantly to acknowledged national research objectives Medium (regional) Undesignated heritage assets that contribute to regional research objectives Low (local) Assets compromised by poor preservation and/or poor survival of contextual associations Assets of limited value, but with potential to contribute to local research objectives Negligible (minor) Assets with very little or no surviving archaeological interest Unknown The importance of the resource is not currently known Effect Magnitude 9.17 The magnitude of impacts has been assessed according to the scale set out below: Table 9.5: Definitions of Magnitude Level of Magnitude Definition of Magnitude Major Total loss or substantial harm to important elements, or features or characteristics of the baseline (pre-development) conditions such that post development character or composition or attributes of baseline will be fundamentally changed. Moderate Partial loss or harm to one or more important elements or features or characteristics of the baseline (pre-development) conditions such that post development character or composition or attributes of baseline will be partially changed. Minor Minor loss. Change arising from the loss or alteration will be discernible but underlying character or composition or attributes of the baseline condition will be similar to pre-development circumstances or patterns. 205 No Change No loss or alteration. Change not distinguishable. Unknown The exact location, extent or nature of the baseline receptor is not known and therefore the magnitude of change cannot be discerned. 9.18 The potential physical (direct) impacts of the Proposed Development on the heritage resource have been assessed by comparing the land-take and construction methodology against the location, nature and vulnerability of each known heritage asset. 9.19 With regard to indirect impacts, initial screening was implemented through comparison with the ZVI and subsequently through consideration of each receptor’s proximity, intervisibility, and sensitivity in relation to the development area. Visual verification of the assessment results were subsequently undertaken by means of site visits to those receptors identified as the most vulnerable to visual impacts. Significance of Potential Impacts 9.20 The significance of potential direct and indirect impacts has been assessed by examining the importance of each known receptor in relation to the anticipated impact magnitude upon it, and quantified according to the criteria in Table 9.6. Table 9.6: Significance of Impacts Matrix Magnitude Receptor Importance Very High High Medium Low Negligible Unknown Major Very significant Very significant Significant Low Negligible Unknown Moderate Very significant Significant Moderate Low Negligible Unknown Minor Moderate Moderate Low Negligible Negligible/ none Unknown No Change None None None None None None Unknown Unknown Unknown Unknown Unknown Unknown Unknown 9.21 For the purposes of this assessment, impact significance is addressed as follows: Very significant and significant impacts would be considered equivalent to ‘substantial harm to’ or the ‘total loss of significance of’ a heritage asset (as defined in NPPF [para 132-4]); Moderate impacts, whilst harmful, are not significant or substantial; and Low and Negligible impacts are not significant or substantial. Limitations of the Assessment 9.22 Generally, information held by public data sources is considered to be reliable however certain limitations, common to any baseline report, should be borne in mind: 206 9.23 Any HER can be limited because it depends on opportunities for research, fieldwork and discovery. There can often be a lack of dating evidence for heritage assets (specifically archaeological sites); Documentary sources are rare before the medieval period, and many historic documents are inherently biased; Primary sources, especially older records, often fail to accurately locate heritage assets and can be subjective in any interpretation; By its nature, field reconnaissance survey (FRS) can only identify evidence of buried archaeological remains with an above-ground signature - other buried remains may exist; and Assessments for indirect impacts are conditioned by the time of day, weather and seasonal conditions of the survey. The limitations of any impact assessment include: The lack of clarity surrounding the extent of some heritage assets which makes it difficult to provide a precise assessment of potential impact; and The possibility that unknown heritage assets will be encountered during construction. Existing Environment 9.24 The Isle of Thanet is situated on a promontory forming the easternmost part of Kent within a coastal region that has undergone significant landform changes in the past, which would have influenced occupation and landuse throughout all periods. The most significant change in this respect is the silting up of the Wantsum Channel, which had rendered Thanet an island off the mainland coast from the end of the last ice age (c. 12,000 years ago) until the medieval period (14th century). 9.25 The land generally slopes westwards from the chalk cliffs along the North Sea coast and southwards to the low lying marshland around Pegwell Bay. The south side of the Isle of Thanet features three low lying hills rising out of a flat plain of alluvium, including Ebbsfleet Hill and Cottington Hill. These hills formed a low peninsula known as the Ebbsfleet peninsula during the times that the Wantsum was open and navigable. The sides of the Ebbsfleet peninsula to the east and the west formed two natural havens for cross Channel sea traffic in the past, which reflects its historic significance as a landing place for the Saxons in the 5th century AD and St Augustine in the 6th century AD. 9.26 An outline of the archaeological and historic development of the region over time is included in Section 3.2 of Appendix 9.1. Known Heritage Resource – Study Area A 9.27 From the data sources outlined above, seven designated and 158 non-designated heritage assets were recorded. 9.28 All entries are described in full in the sites gazetteer for Study Area A contained in the Baseline Report (Appendix 9.1) and shown on Figure 9.1. All heritage assets are referred to only in summary form in the discussions below. 9.29 There are no Scheduled Monuments, World Heritage Sites, Registered Parks and Gardens or Registered Battlefields within Study Area A. 207 Receptors of High Importance 9.30 There are seven receptors of high importance in Study Area A: one Grade II* Listed building (RSK D1) and six Grade II Listed buildings (RSK D2-7). Receptors of Medium Importance 9.31 Twenty-eight non-designated receptors are of a medium importance (RSK 1-2, 4, 68, 12-13, 15-16, 78-79-83, 87-88, 91-97, 141, LIN 1-3). These mostly comprise archaeological occupation and burial sites, often featuring multiple periods, recorded as part of modern development control regimes and focussed on the highlying areas of the Ebbsfleet peninsula. Several prehistoric ‘founders’ hoards (RSK 6, 7, 12) are also known. In the light of the significance of the development of the landscape in relation to the coastline and rivers, medieval sea defences (RSK 96, 97, LIN 1-2) and a transport route of that period (RSK LIN 3) are also included in this category. Receptors of Low Importance 9.32 One hundred and twenty one non-designated receptors in Study Area A are of low importance (RSK 3, 5, 9-11, 14, 17-77, 84-86, 89, 92, 98-101, 103-108, 111-131, 133-135, 137-140, IZ1-2). These can be broadly divided into prehistoric and early historic (medieval) individual finds or isolated features (RSK 3, 5, 9, 10, 11, 14, 17, 18-77, 88, 92, 98, 100,101, 103, 104, 105, 110); historically attested sites or those with a traditional association (such as the landing site of the Saxons at Ebbsfleet), RSK 89 & 99; a large number of military installations (or their former sites) from the two world wars (RSK 113-118, 122-125, 129, 131-135, 137-138, 140); and sites related to the industrial development of the landscape in the post-medieval and modern periods, RSK 106-108, 111, 119-121, 127-128, 130, 139, LIN 4-7); as well as those related to general rural living (RSK HM2-5). 9.33 Two of these receptors, IZ1 and IZ2, identified by Wessex Archaeology (2010), are in the intertidal zone between the TJP and low water mark. Both are of low importance. RSK IZ1 is the findspot of a Roman cup considered a chance overboard loss and RSK IZ2 is a section of medieval wall function situated near the coast at Cliffs End. Both records have uncertain locational data. Receptors of Negligible Importance 9.34 There are five non-designated receptors of negligible importance (RSK 90, 109, 132, 136, HM1) in Study Area A; these are all now demolished sites of a postmedieval and modern date for which no significant below ground remains are anticipated. Receptors of Unknown Importance 9.35 There are four non-designated receptors of unknown importance (RSK 102, 142144). These include two suspected archaeological sites identified from aerial photographic evidence (RSK 143-144), one site with an inconsistent KHER entry (RSK 102), and one poorly provenanced site of graves recorded at Weatherlees during the installation of WWII defences (RSK 142). 208 Historic Map Regression 9.36 Superseded OS mapping provided by Envirocheck at 1:10,560/1:10,000 (including a 100m buffer around the proposal area) and 1:2500 scale maps were also consulted as part of the assessment. 9.37 Historic map regression shows a rural landscape that has experienced limited episodic and localised changes from post-medieval and modern industries, the development of transport infrastructure, and residential development, which leaves much of the historic structure and character of the landscape intact, if fragmented. Historic map regression enabled the tracing of changes to the coastline, its sea defences and associated installations over the recorded period. With respect to the current proposals, the most notable change is the recording of alignments of a former coastal or riverine seawall predating the late 19th century (RSK HM5) in relation to the still partially extant Boarded Groyne (RSK LIN2). The latter is thought to date from the 14th century. This suggests the cable route lies within an area of land most likely reclaimed in post-medieval times. Aerial Photographic Evidence 9.38 The majority of the application boundary lies in an area of reclaimed coastal and marshland. Where archaeological deposits are present in such areas, these are likely to lie buried deeply and cannot normally be detected through aerial photographic examination. Historic Landscape Characterisation 9.39 Historic Landscape Characterisation has been undertaken by Kent County Council (2004). The two Study Areas fall mainly within two landscape character areas as defined by the assessment, namely Thanet to the north and Wantsum and the Lower Stour Marshes to the south. The limits of each area are distinctly defined by the southern coastline of the former island (Figures 9.1 and 9.2). The application boundary falls entirely within the Wantsum and Lower Stour Marshes character area. 9.40 Thanet’s island quality is preserved by the way it rises out of the marshes to a modest height of approximately 50m AOD. Its landscape divides into two distinct areas, a flat plateau and the slope along the chalk outlier to the marshes at the south and west. With the exception of the urban conurbation of Ramsgate-MargateBroadstairs, settlements are generally nucleic and centre on former mills and ports or ferry landings at the edge of the former Wantsum Channel. Two of the main characteristics of the historic landscape character are the long views to and from the former island across the marshland and its open, unenclosed nature in general, which is partly the result of a historic lack of vegetation. A sense of place in Thanet is very strong, in part due to its persistent island quality where historic and ancient characteristics associated with settlements and road patterns, farming and cultural use all survive. Thanet is a landscape with a high sensitivity to visual change. The coherence of the landscape character has already been denuded in the past, rendering Thanet’s landscape character in need of restoration. 9.41 The marshlands around the north-east Kent coast are the reclaimed and silted up course of the Wantsum Channel and the former mouth of the River Stour. The land was originally reclaimed as summer pasture for sheep with much of this work being 209 undertaken by wealthy ecclesiastical estates in the area. There is also historic evidence for former salt production. There is no settlement within the marsh, and the road network derives its character from former crossing places and drove roads. The marshes’ main characteristics form a flat and open landscape with long views and isolated stretches of farmland crossed by drainage channels. It has reasonable coherence as a reclaimed marsh in visual terms, however of poor cultural integrity and with a weak and indistinct sense of place. Sensitivity to visual changes is high due to the open nature of the historic landscape, and it has been concluded that new road patterns and land-use has resulted in a denudation of the landscape character, leaving a need to restore and create. Site Visit 9.42 The site visit confirmed that the majority of the cable route is within low-lying reclaimed coastal land. No surface indicator for RSK LIN 1, 125, HM1, 140 or 116 was identified. The subsurface preservation level is unknown. Archaeological Potential 9.43 The island of Thanet has a rich archaeological and historic resource, and this is reflected in the high number of sites contained in Study Area A. However, with the exception of earlier historic sea defences, or later historic sites related to modern warfare and agriculture, these are exclusively contained within the limits of the former island, and the changes of the palaeo-environment over time are important for the assessment of the archaeological potential of the Proposed Development area in particular. The cable route and converter and substation site lie entirely within the limits of the former Wantsum Channel as delineated by the HLC character areas and therefore within land reclaimed since the medieval period. The majority of the cable route lies outside a late historic sea wall recorded on the 1877 1st edition OS map, and therefore in land reclaimed in the post-medieval period. 9.44 The Wantsum Channel was formed at the end of the last Ice Age about 12,000 years ago from melting waters from the shrinking ice caps and glaciers that made sea levels rise. Prior to this time, the area of the channel would have been part of the mainland landmass and there is therefore an unconfirmed potential for the presence of archaeological artefacts and palaeo-environmental evidence from the Pleistocene period below the later channel silts. Such horizons are likely to be at considerable depth. 9.45 The Channel was a navigational route from later prehistoric times and given the known prehistoric, Roman and Saxon assets on the adjoining dry land areas it is possible that evidence for its use and the use of the marginal areas will survive in subsurface deposits. After reclamation, the proposal site would have been peripheral marshland, most likely used as grazing land, with little potential for any significant archaeological remains. 9.46 In summary, it is considered that between the landfall and the converter station, there is an unproven potential for deposits of archaeological interest at depth from the very early (Pleistocene) prehistoric period (500,000-12,000 years ago), that there is a negligible potential for archaeological remains from all (Holocene) prehistoric periods, and medium potential for the later prehistoric, Roman and earliest historic periods. The potential for significant remains from all later historic periods from the medieval period onwards is considered low. 210 Known Heritage Resource – Study Area B 9.47 In line with the method outlined above, all higher-grade designated heritage asset (Scheduled Monuments, Grade I and II* Listings) were plotted within the ZVI of the above ground elements of the development to a maximum distance of 10km, whilst the plotting of Grade II listed buildings and conservation areas was limited to 3km (Figure 9.2). 9.48 Eleven of the designated heritage assets fall within the ZVI (RSK V1-11). The distance of separation between the converter station and substation site and these assets is over 1.6km. 9.49 Heritage assets with the highest sensitivity to visual impact are Richborough Castle, RSK V3, and the archaeological remains within it, RSK V1. These have a shared history and form one historic complex approximately 2km south of the proposed converter and substation site. 9.50 The significance of the archaeological and historic complex at Richborough Castle is equally shared between its evidential, historic, aesthetic and communal values, all of which are high. This is reflected in its designation as a Scheduled Monument and its Grade I Listing, as well as its status as a tourist attraction. The site represents an important event in relation to the Roman occupation of Britain, and has a strategic relationship with the landscape it is situated within. The historic complex provides a prominent visible link with the modern as well as the former landscape, and with events of national importance having taken place within it. Views related to these heritage assets, particularly their imposing upstanding remains, are a fundamental part of the significance of this important group of assets. Prediction and Assessment of Significance of Potential Impacts Construction General Direct Impacts (Study Area A) 9.51 The onshore underground cables will be buried for their entire length between the low water mark and the proposed converter station and substation site. Installation by means of open trenching will involve the excavation of a 1.2m wide by 1m deep trench within a working width of 5-10m, and a permanent easement of 5m. Horizontal Directional Drilling (HDD) will be used between the BayPoint sports complex and Richborough Power Station site. The following construction activities have the potential to impact on archaeological and cultural heritage remains: Preparatory groundworks of the working width associated with cables installation; Trench excavation; Excavation of HDD launch and receptor pits and transition joint pit (TJP); Site clearance at the proposed converter station and substation site, including demolition of the cooling tower bases; Foundation installation for the converter station and substation; and Reinstatement and landscaping. 211 Site-Specific Direct Impacts (Study Area A) 9.52 The majority of the heritage assets within Study Area A are sufficiently distant from the onshore elements of the Proposed Development so as not to be directly affected through the construction programme. The thirteen assets potentially affected during construction are shown in Table 9.7. Table 9.7: Site-Specific Direct Impacts Site ID Description Importance Magnitude of Effect Significance of Effect Proposed Further Assessment or Mitigation 96 14 century sea wall (site of) Medium No Change None None 116 WWII pillbox (site of) Low No Change None None 119 Richborough power station (disused) Low Major Low Record during construction phase watching brief 125 RAF salvage yard (site of) Low Minor Negligible None 130 1960s sculpture (site of) Low No Change None None 140 WWII pillbox (site of) Low No Change None None HM1 Post-medieval coastguard station (site of) Low Major Low Record during constructionphase watching brief HM2 Ebbfleet House (post-medieval dwelling) Low No Change None None HM3 Stonelees House (post-medieval dwelling) Low No Change None None HM5 Seawall observed on st 1 edition OS map (site of) Low No Change None None th 212 LIN 2 Boarded Groyne th (14 century, partially extant), survival within converter station site boundary/cable route destroyed through modern development Medium No Change None None LIN 7 East Kent Railway Low No Change None None IZ1 Recovery of Roman cup from dredging Low No Change None None Archaeological Potential 9.53 Artefacts and palaeo-environmental deposits of a Palaeolithic date (i.e. pre-dating the Wantsum Channel) may be present at considerable depth below channel silts so there is some potential for deep excavations, such as the HDD launch and receptor pits, to reach such remains. The development site is situated in reclaimed land within the former Wantsum Channel which was navigable throughout the later prehistoric periods and onwards. The archaeological potential for the later prehistoric, Roman and earliest historic periods is considered medium, and low for significant remains from all later historic periods. 9.54 Following reclamation, the development area would have been utilised as grazing marshland, and archaeological and cultural heritage remains related to these activities, where present, are likely to be of a negligible or low value. Indirect Impacts (Study Areas A and B) 9.55 Visual and indirect effects to the settings of designated heritage assets may arise during the construction phase. These effects are predicted to be temporary, shortterm, and minimal in magnitude and significance. An assessment of the effects on specific heritage assets of the presence of the converter station and substation during operation is presented below. Operation Direct Impacts (Study Area A) 9.56 It is not anticipated that the operation of the interconnector will have any impact on buried archaeology. 9.57 Repairs and refurbishment of the underground cables, converter station and substation are anticipated to be above ground or to affect areas where the ground has already been disturbed, investigated and mitigated during construction. Consequently, no effects on buried archaeology are anticipated during the operational phases of the Proposed Development. General Indirect Impacts (Study Area B) 9.58 The operational phase of the Proposed Development could result in an on-going effect on the setting of heritage assets and historic landscape character. 213 Site-Specific Indirect Impacts (Study Area B) 9.59 The ZVI indicates that the above ground elements of the Proposed Development potentially affect the setting of 11 designated heritage assets. An assessment has been made to determine the magnitude of change that the Proposed Development could have on these assets, in terms of loss of significance through development within their setting. The results are summarised in Table 9.8 below: Table 9.8: Site-Specific Indirect Impacts Site ID Description Receptor Importance Magnitude of Effect Significance of Effect Proposed Further Assessment or Mitigation V1 Richborough Castle– Saxon shore fort (archaeological remains) SCHEDULED MONUMENT Very High No Change None None V2 Anglo-Saxon cemetery at Ozengell Grange SCHEDULED MONUMENT High No Change None None V3 Richborough Castle GRADE I LISTED BUILDING Very High No Change None None V4 Paramour Grange GRADE II* LB High No Change None None V5 Stourmouth House GRADE II* LB High No Change None None Richborough Farm GRADE II LB High No Change None None V7 Guston Court GRADE II LB High No Change None None V8 Kings End Farmhouse GRADE II LB High No Change None None V9 Mulberry House GRADE II LB High No Change None None V10 Stables about 5m SW of Guston Court GRADE II LB High No Change None None V11 Castle Farm GRADE II LB High No Change None None V6 9.60 The setting of Richborough Castle including the proposed location of the substation and converter station makes a positive contribution to the significance of the upstanding remains of the heritage asset. However, the visual baseline situation to the east and north east of Richborough Castle comprises ‘Industrial complexes and factories’ (Ref. Kent HLC) including the site of the former Richborough power 214 station; the proposed converter station and substation would be located on the site of the former turbine hall and cooling towers of the former Richborough power station. The impact upon the setting of Richborough Castle from the Proposed Development would not cause any greater harm than the baseline situation. The magnitude of change is therefore Negligible and the significance of effect is None. 9.61 For the other designated heritage assets within the ZVI of the proposed converter station and substation, the contribution made by that part of their setting affected by the Proposed Development is negligible or neutral. Consequently, and also for the reasons outlined above in relation to Richborough Castle, there will be no loss of significance as a result of the Proposed Development and the significance of effect is None. 9.62 The historic landscape character of the site of the proposed converter station and substation is recorded by Kent County Council as ‘modern industrial’. The addition of modern infrastructure to the former power station site will have a neutral effect on the historic landscape character of the site and surrounding area. Mitigation Strategy Physical Impacts 9.63 No significant impacts on heritage assets are predicted. However, through consultation with the Principal Archaeological Officer at Kent County Council (KCC, S. Mason, 26th July 2012), mitigation with regard to cables installation via open trenching is proposed for predicted impacts to the post-medieval coastguard station (RSK HM1) and Richborough Power Station (disused) (RSK 119) in the form of a watching brief during construction works. 9.64 A watching brief will also be maintained during the cable installation to ensure that any previously unrecorded archaeological remains are identified and recorded during groundworks. 9.65 In addition, a watching brief with regard to Pleistocene and Palaeolithic remains will be undertaken during any deep excavations (i.e. excavations beyond the modern overburden) related to the scheme. Both phases of the watching brief would be undertaken in line with a Written Scheme of Investigation agreed with KCC in advance of the fieldwork, and followed by a programme of analysis and reporting also to be agreed with and delivered with KCC. Indirect (Visual) Impacts 9.66 The assessment has concluded that the development of the substation and converter station will not result in any loss of significance to designated heritage assets through development within their setting. Consequently, no mitigation is proposed in relation to designated heritage assets. Residual Impacts 9.67 It is anticipated that after the programme of archaeological mitigation has been implemented, the archaeological and cultural heritage resource within and close to the development area will remain unaffected and the overall residual impact of the scheme is therefore neutral. 215 Cumulative Impacts 9.68 Potential cumulative effects on archaeology and cultural heritage from the onshore elements of the Nemo Link in combination with other components of the Project (i.e. UK, French and Belgian subsea cables and Belgian onshore infrastructure) are described in Chapter 16. 9.69 Potential cumulative effects of the Nemo Link UK onshore infrastructure in combination with the grid connection required to facilitate the operation of the Nemo Link are described in Chapter 17. 9.70 There is the potential for cumulative effects to arise during the construction and operation phase of the proposed works due to the construction and operation of other developments as detailed in Table 1.2. Direct Impacts 9.71 Richborough Energy Park will be constructed on the former power station site. Mitigation has been proposed and agreed with Kent County Council in relation to the adverse effects of these works on the former power station site. On completion of an appropriate programme of archaeological mitigation in relation to both proposed developments, effects on buried archaeology will be neutral and no direct cumulative impacts on the historic environment are predicted as a result of these developments. 9.72 Similarly, for other developments within the cable route corridor, the individual effects of each development on previously unknown buried archaeology can be mitigated. On completion of an appropriate programme of archaeological mitigation in relation to each proposed development and the installation of the cables, effects on buried archaeology will be neutral and no direct cumulative impacts on the historic environment are predicted as a result of these developments. Indirect Impacts 9.73 This assessment concludes that the construction of the converter station and substation will not result in any harm to the historic environment through historic landscape impacts or development within the setting of a heritage asset. Therefore the Proposed Development will not contribute to any cumulative effects on the historic environment in combination with other proposed developments. 216 217 218 10.0 LANDSCAPE AND VISUAL EFFECTS Introduction 10.1 This chapter assesses the anticipated effects on landscape and views of the Proposed Development (i.e. the converter station and substation at the former Richborough Power Station site and the underground and overground cable connection between Pegwell Bay and the converter station and substation site). It provides a description of the landscape in which the development is proposed and includes reference to published landscape assessments relating to the general locality, before considering the anticipated effects of the Proposed Development on landscape character during construction and on completion. It describes the nature of existing views and includes a prediction of the visual effects of the Proposed Development during construction and operation. 10.2 The converter station will comprise a principal building which will re-use the derelict steel frame structure of the existing former turbine hall. This part of the building will extend to the existing height of the steel frame, at approximately 30.8m. The converter station building would also be extended to the north (by approximately 65m) with a maximum height of 25m; a further building extension approximately 45m in length and 18m high. The outdoor equipment associated with the converter station would be a maximum height of 12m and would be constructed to the north of the building. The proposed 400kV substation to the northwest of the converter station would consist of outdoor electrical equipment, with a centrally located building containing gas insulated switchgear (GIS) at a maximum height of 15m. The maximum height of the outdoor electrical equipment within the substation will be 13m. Colour graded cladding is proposed to the converter station building, ranging from a muted green at the building’s base to off-white at the roofline. Due to its lower height the substation building will be clad in a single colour (muted green). External lighting to the converter station and substation site will be required for safety and security purposes (for maintenance purposes, in emergencies and triggered by intruder detection) but will be kept to the absolute minimum necessary. A 1.6 hectare temporary lay-down area for materials and plant will be located to the immediate west of the substation during the construction period. This temporary area will also be on land which was part of the former power station and now forms part of the Richborough Energy Park. Refer to Chapter 2 for a full description of the Proposed Development. 10.3 This landscape and visual impact assessment also considers the effects of the subsea underground cable connection between the low water mark and the Transition Joint Pit (TJP) at Pegwell Bay and the onshore underground and overground cable connection between the TJP at Pegwell Bay and the converter station and substation site. Refer to Chapter 2 for a description of the Proposed Development. Planning Policy Context 10.4 Chapter 4 includes a review of National, Regional and Local Planning Policy relevant to the site and the surrounding area. The following paragraphs summarise planning policy relevant to landscape and views. 219 National Planning Policy Framework, March 2012 10.5 The following aspects of the National Planning Policy Framework (NPPF) are applicable to the Proposed Development and relevant to landscape character and visual amenity. 7. Requiring Good Design 10.6 The Government emphasises the importance of the design of the built environment. The NPPF outlines that good design is a key aspect of sustainable development and should contribute to making places better for people. The NPPF lists qualities that developments should achieve, including: 10.7 Functions well and add to the overall quality of the area; Establishes a strong sense of place; Optimises the potential of the site to accommodate development; Responds to local character and history, and reflects the identity of local surroundings and materials, whilst not preventing or discouraging appropriate innovation; Creates safe and accessible environments; and Is visually attractive as a result of good architecture and appropriate landscaping. The NPPF emphasises the importance of applicants working closely with those directly affected by proposals to evolve designs and take account of the views of the community. 11. Conserving and Enhancing the Natural Environment 10.8 The NPPF identifies the importance for developments to enhance the natural and local environment by protecting and enhancing valued landscapes, geological conservation interests and soils, recognising the wider benefits of ecosystems, minimising the impacts on biodiversity and increasing the net gains in biodiversity, and preventing risk from unacceptable levels of effects on soil, air, water, noise pollution and land instability. Regional Planning Policy The South East Plan: Regional Spatial Strategy for the South East of England, May 2009 10.9 At the time of writing, the South East Plan continues to be a material consideration in the planning process although relatively little weight should be given to the policies it contains. RSS policies relevant to landscape character and visual amenity are identified and briefly discussed below. RSS policies below are discussed further in Chapter 4. Policy CC6: Sustainable Communities and Character of the Environment Policy CC6 states that ‘actions and decisions associated with the development and use of land will actively promote the creation of sustainable and distinctive communities. This will be achieved by developing and implementing a local shared vision which ‘respects, and where appropriate enhances, the character and distinctiveness of settlements and landscapes throughout the region, and uses 220 innovative design processes to create a high quality built environment which promotes a sense of place. This will include consideration of accessibility, social inclusion, the need for environmentally sensitive development and crime reduction’. The South East is described in Policy CC6 as having a ‘high quality environment with a rich heritage of historic buildings, landscapes and habitats’. Policy C4: Landscape and Countryside Management Policy C4 states that ‘outside nationally designated landscapes, positive and high quality management of the region’s open countryside will be encouraged and supported by local authorities and other organisations, agencies, land managers, the private sector and local communities, through a combination of planning policies, grant aid and other measures. In particular, planning authorities and other agencies in their plans and programmes should recognise, and aim to protect and enhance, the diversity and local distinctiveness of the region’s landscape, informed by landscape character assessment’. Policy C4 requires that ‘Local authorities should develop criteria-based policies to ensure that all development respects and enhances local landscape character, securing appropriate mitigation where damage to local landscape character cannot be avoided’. Policy C6: Countryside Access and Rights of Way Management This policy requires that local authorities should encourage access to the countryside, particularly by maintaining, enhancing and promoting the Public Rights of Way system, and permissive and longer distance routes. Policy BE6: Management of the Historic Environment Policy BE6 encourages local authorities and other bodies to ‘adopt policies and support proposals which protect, conserve and, where appropriate, enhance the historic environment and the contribution it makes to local and regional distinctiveness and sense of place. The region's internationally and nationally designated historic assets should receive the highest level of protection’. The RSS qualifies that ‘The historic environment includes the physical evidence of past human activity’. ‘It is not limited to the built environment and archaeological sites, but includes landscapes, both urban and rural and as an example of its great diversity, marine heritage sites around the coast. These environments are fragile and require protection’. Local Planning Policy Thanet District Council and Dover District Council 10.10 The application site falls within two administrative boundaries; Thanet District Council and Dover District Council. The application site is predominantly in Thanet District, although part of the eastern edge of the converter station and substation site and a small section of the underground cable route fall within Dover District. 10.11 The saved planning policies of the Thanet Local Plan relevant to landscape character and visual amenity and the Proposed Development are detailed in ES 221 Chapter 4 (Planning Context) and the Planning Statement and illustrated where possible on Figure 10.1. Relevant planning policies from the emerging Thanet District Draft Core Strategy and the Dover Development Plan which incorporates saved policies from the Local Plan and policies from the adopted Core Strategy Development Plan Document have also been included. Kent Design Guide 05/06 (December 2005) 10.12 Both Thanet and Dover District Councils have adopted the Kent Design Guide prepared by Kent County Council. This guide emphasises the value of good design and stresses the importance of respecting landscape context and character in new development, stating that ‘the design of new developments should evolve from the special local or Kentish character’. Method 10.13 The assessment of landscape and visual effects has been undertaken in accordance with the Guidelines for Landscape and Visual Assessment, Second Edition (Landscape Institute/Institute of Environmental Management and Assessment, 2002). 10.14 The baseline assessments were undertaken by Chartered Landscape Architects from The Environment Partnership Limited (TEP) Limited, experienced in landscape and visual assessment. The assessment of landscape character included consideration of published landscape assessments, map based information and aerial photography together with a site survey. The visual assessment was primarily undertaken through site visits to identify the visual receptors and to experience the existing views. Site survey was undertaken for both assessments in early August 2011 and late April 2012 when weather conditions were generally dry with sunny spells, and visibility was good. 10.15 The study area used for the assessment of landscape and visual effects equates to the Zone of Theoretical Visibility (ZTV) of the Proposed Development. The ZTV defines the approximate area from which the existing site is visible and from which the Proposed Development would be visible. This has been determined through a combination of computer generated mapping, which has been subsequently refined through desk-based study and field survey work taking into account the localised screening effects of built form and vegetation (see Figure 10.2). 10.16 Consultation has taken place with the planning case officers at Thanet and Dover District Councils, primarily to agree photomontage viewpoint locations. The agreed photomontage viewpoint locations are shown at Figure 10.3; also included are photograph viewpoint locations. 10.17 The methods of baseline assessment and the assessment of effects and significance are described below. Method for Landscape Character Assessment 10.18 Desk study and field survey were undertaken to identify the landscape features or elements which form the key characteristics of the study area. 10.19 An evaluation was made of the importance or value of elements and character, the condition or quality of the landscape and its capacity to accommodate change without greatly affecting its character. 222 10.20 Landscape value assessment considers the relative value that is attached to different landscapes. In a policy context the usual basis for recognising certain highly valued landscapes is through the application of local or national designations. In non-designated landscapes, assessment seeks to identify the value of the landscape at a specific scale; identify the receptors to which it is important; and identify why the landscape is important to them. 10.21 Landscape condition (or quality) is a factual description of the physical state of the landscape, and about its intactness, from visual and functional perspectives. 10.22 Landscape sensitivity or capacity refers to the degree to which a landscape can accommodate change without suffering detrimental effects on its character. This sensitivity varies with: Existing land use; The pattern and scale of the landscape; Visual enclosure/openness of views, and distribution of visual receptors; The scope for mitigation, which would be in character with the existing landscape (where appropriate); and The value placed on the landscape. 10.23 The capacity of a landscape to accommodate change is generally expressed in relation to specific types or nature of development and a specific type of development generally needs to be known in order to determine the magnitude of effect. 10.24 Magnitude considers the scale of effect (i.e. large/medium/small); its nature (adverse or beneficial); and its duration (short, medium, long-term/permanent or temporary). More weight is usually given to effects that are greater in scale and permanent or long-term in duration. In assessing the duration of the effect, consideration is given to the effectiveness of mitigation, particularly where planting is proposed as part of the works which would change or reinforce landscape character. The criteria for assessment of effects on landscape character are outlined in Table 10.1 below. 223 Table 10.1: Criteria for Assessment of Magnitude of Effects on Landscape Magnitude of Effect Typical Criteria High Total loss of or major alteration to key elements/features/ characteristics of the baseline i.e. pre-development landscape or view and/or introduction of elements considered to be totally uncharacteristic when set within the attributes of the receiving landscape. Moderate Partial loss of or alteration to one or more key elements/features/ characteristics of the baseline landscape or view and /or introduction of elements that may be prominent but may not necessarily be considered to be substantially uncharacteristic when set within the attributes of the receiving landscape. Low Minor loss or alteration to one or more key elements/features/characteristics of the baseline landscape. Introduction of elements that are generally characteristic with the surrounding landscape. Negligible Very minor loss or alteration to one or more key elements/features/ characteristics of the baseline landscape. Introduction of elements characteristic with the surrounding landscape – approximating to the ‘no change’ situation. Source: LI/IEMA 2002, p145 Assessment of Significance 10.25 The significance of the effect of a development is not related to an absolute scale but is a judgement based on the magnitude of the anticipated effect (or scale of change), the importance or value of the landscape and the sensitivity or capacity of the landscape to accommodate a specific development. 10.26 The significance of effect also considers the nature of the effect. Change can be consistent with or can enhance the landscape. Conversely it may be at odds with or harmful to the landscape’s key features or character. The significance of landscape effects has been considered according to the criteria adapted from examples given in LI/IEMA (2002) pp140 – 141, outlined below in Table 10.2 below. 224 Table 10.2: Guidance on Significance of Landscape Effects Significance Definition Major adverse A proposed scheme would result in effects that: cannot be fully mitigated and may cumulatively amount to a severe adverse effect; are at a considerable variance to the landscape degrading the integrity of the landscape; will be substantially damaging to a high quality landscape. Moderate adverse A proposed scheme would: be out of scale with the landscape or at odds with the local pattern and landform; leave an adverse impact on a landscape of recognised quality. A proposed scheme would: Minor adverse Neutral not quite fit into the landform and scale of the landscape; affect an area of recognised landscape character. A proposed scheme would: complement the scale, landform and pattern of the landscape; maintain existing landscape quality. A proposed scheme has the potential to: Minor beneficial 10.27 improve the landscape quality and character; fit in with the scale, landform and pattern of the landscape; enable the restoration of valued characteristic features partially lost through other land uses. Moderate beneficial A proposed scheme would: fit very well with the landscape character; improve the quality of the landscape through removal of damage caused by existing land uses. Major beneficial A proposed scheme would: enhance and redefine the landscape character in a positive manner repair or restore landscape badly damaged or degraded through previous uses The significance of the effect of a development on the landscape is a judgement based on the capacity of the landscape to accommodate change and the magnitude of the anticipated effect. Method for Visual Impact Assessment 10.28 The first stage in visual impact assessment is to establish the extent and nature of existing views of the site from principal representative viewpoints, and the nature and character of the visual amenity of the potentially sensitive visual receptors (or viewers). This involves defining the approximate area from which the existing site is 225 visible and from which the Proposed Development would be visible. As described above the ZTV was initially determined by computer generated mapping, desk study of Ordnance Survey mapping and aerial photography. 10.29 This was followed by field survey to verify the extent of potential visibility and to identify features which might screen views (such as built form and vegetation), and to identify potential visual receptors. The existing steel frame of the turbine hall on site forms a useful reference for determining the extent of visibility. 10.30 The field survey work for the visual assessment was carried out at the same time as the landscape assessment. No access to properties was sought and the assessment of views from properties is therefore based on a best assumption from publicly accessible locations outside or close to the properties. 10.31 Visual receptors may include: Users of recreational landscapes, public footpaths and bridleways including tourists and visitors; Residents; Users of sports grounds and amenity open space; Users of public roads, railways, canals or navigable waterways; and Workers (in their workplace). 10.32 An analysis of the importance of the view and the sensitivity of visual receptor is relevant to assessment of effects on views. Importance of views is generally considered in the context of values placed on scenes, alternatives available and the relative scenic quality (for example, its appearance in guidebooks, on tourist maps, by facilities such as viewpoints provided for its enjoyment and references to it in literature or art). 10.33 Sensitivity of visual receptors depends upon the location of viewpoint, the activity of the receptor, expectations and the importance of the view. For example, a person may be considered a receptor of low sensitivity when engaged in work in a factory or when driving, where attention is not generally paid to the view, whereas the same person may be considered a receptor of high sensitivity when visiting a viewpoint in a National Park. 10.34 In visual assessment, lower storey views from residential properties are generally considered to be more sensitive than upper storey views, as these are the rooms in which residents spend more time experiencing the view. (This is not universally the case as some residences have living rooms on upper storeys). 10.35 The land use planning system considers that public views are of greater value than views from private property. In this assessment, sensitivity was generally assigned to receptors as shown in Table 10.3 below. 226 Table 10.3: Relative Sensitivity of Receptors Receptors Relative Sensitivity Residential properties (lower storey views) High Residential properties (upper storey views) Moderate Users of recreational paths and other public rights of High way Users of open space High Golf course users Moderate Sports pitch/playing field users Low Workers/visitors at businesses Low Motorists/rail users Low 10.36 The importance of the view and the sensitivity of the receptor are considered in determining the magnitude of effect (the scale of change) and in making a judgement assessment of the significance of effect. 10.37 The assessment of effects determines the scale or magnitude of visual effects by considering the scale of change of view (proportion occupied by development); the degree of contrast or integration; the duration and nature of change; the angle of view; the distance from the receptor; and the extent of area over which changes are visible. 10.38 The magnitude of effect is considered in accordance with criteria as presented in Table 10.4 below. Table 10.4: Criteria for Assessment of Magnitude on Effects of Views Magnitude of Effect Typical Criteria High Total loss of or major alteration to key elements, features or characteristics of the existing view and/or introduction of elements considered totally uncharacteristic. Moderate Partial loss of or alteration to one or more key elements/features/ characteristics of the baseline view and/or introduction of elements that are prominent. The alteration in view may not necessarily be considered substantially uncharacteristic when set within the context of the existing view. Low Minor loss of or alteration to one or more key elements/features/ characteristics of the baseline view. Introduction of elements which are generally characteristic of or similar to features in existing view. Negligible Very minor loss or alteration to one or more key elements/features/ characteristics of the baseline view. Introduction of elements characteristic of or similar to features in existing view – approximating to the ‘no change’ situation. 227 Source: LI/IEMA 2002, p145 Assessment of Significance 10.39 Assessment of the significance of visual effects is a judgement of the scale or magnitude of effect and the sensitivity of the receptor. In establishing a judgement, general guidance given in LI/IEMA 2002 has been adopted. Large-scale changes which introduce new, discordant or intrusive elements into the view are considered to be more likely to be significant than small changes or changes involving features already present in the view. Changes in views from recognised and important viewpoints or amenity routes are likely to be more significant than changes affecting other less important paths and roads. Changes affecting large numbers of people are generally more significant than those affecting a relatively small group of users. (However, in wilderness landscapes the sensitivity of the people who use these areas may be very high and this would be reflected in the significance of the change). 10.40 The significance of effects has been considered in the context of the comparative scale at Table 10.5 overleaf. Table 10.5: Criteria for Assessment of Visual Effects Significance of Visual Effect Typical Criteria Major An effect of major significance is generally recorded where a high magnitude of effect occurs to a highly sensitive receptor. In this instance, this could be where the new development would appear clearly in a view which at present has open land as a large part of its view. Moderate An effect of moderate significance is generally recorded where a medium magnitude of effect is experienced by a receptor of high or moderate sensitivity. In this instance, this could be where parts of the development would be visible in a view but the new development would not comprise a large part of the view. Minor An impact of minor significance generally relates to a low magnitude of effect and often relates to a change in a distant view or a change in only a small part of view, possibly because the view is already screened to a large extent. Neutral A neutral impact is generally recorded where there is no discernible change to the existing view, or where adverse and beneficial impacts balance. Source: LI/IEMA 2002 10.41 To illustrate the anticipated effect on views for some of the nearest and most sensitive visual receptors, seven photomontage views have been prepared (see Figure 10.3 for photomontage viewpoint locations). These viewpoints were agreed with the Thanet and Dover District Councils. ‘Before’ and ‘after’ views are shown in 228 Figures 10.17 to 10.23. Further detail of the method used to prepare photomontages is provided at Appendix 10.1. Existing Environment Site Location and Context 10.42 The application site includes the proposed converter station and substation site at the former Richborough Power Station. This part of the application site is approximately 7.65ha and is approximately 3km southwest of Ramsgate and 4km north of Sandwich. 10.43 The application site also includes the subsea underground cable route, between the low mean water mark and Transition Joint Pit in Pegwell Bay, which is the buried point of connection between the onshore and subsea cables. The length of the subsea cable route between the low mean water mark and Transition Joint Pit is 1.8km. The onshore underground cables will run from the Transition Joint Pit on the coastal side of the existing footpath and cycleway which runs parallel to the A256 Sandwich Road, through Pegwell Bay Country Park, then into Stonelees Nature Reserve and the former BayPoint sports complex. From the sports complex, the cables will be routed by horizontal directional drilling beneath the A256, Minster Stream, and a compartment of Hacklinge Marshes SSSI terminating in the converter station. The length of the underground cable route between the Transition Joint Pit and converter station is 2.3km. 10.44 The application site occupies low lying ground near Pegwell Bay where the River Stour enters the sea. The application site is also closely associated with the A256, which runs around Pegwell Bay and connects Ramsgate and Sandwich. As well as residential settlement and outdoor leisure facilities associated with the coastal location (such as the beach at Pegwell Bay, Pegwell Bay Country Park and golf courses), south of the former power station there are a number of industrial land uses. This includes the substantial Pfizer site at Great Stonar which sits between the application site and Sandwich and is comprised of laboratories, production facilities, offices and a combined heat and power plant. Inland, to the west, arable land use predominates. 10.45 The converter station and substation site is derelict. The three cooling towers and tall chimney, which stood on the site were demolished in March 2012, leaving the steel frame of the former turbine hall as the only remaining structure. Existing Landscape Character 10.46 This section summarises the findings of the desk-top review of published documents and assesses the existing landscape character of the surrounding area. The assessment has been undertaken using a combination of desk based resources and field survey. Desk study consists of a review of the following: Natural England National Landscape Character Assessment; The Landscape Assessment of Kent, October 2004; Thanet District Landscape Character Assessment 2001; and Dover District Council Landscape Character Assessment, January 2006. 229 Natural England National Landscape Character Assessment 10.47 The site of the redundant Richborough power station is on the eastern edge of the North Kent Plain National Character Area (NCA) as characterised by Natural England. National Character Area 113: North Kent Plain 10.48 The North Kent Plain NCA comprises land between the Thames Estuary to the north and the chalk of the Kent Downs to the south. This area is described as open, low and gently undulating dominated by very productive agricultural land uses. Traditional orchards, soft fruits, and agricultural crops are identified in central and eastern areas and are noted as often being enclosed by poplar or alder shelterbelts and scattered small woodlands. Agricultural land is however recorded as mostly devoid of hedgerows. Field boundaries are often marked by changes in crop rather than hedgerows. There are extensive areas of ancient woodland including on higher ground around Blean. The River Stour is the main catchment in the area and its tributaries and associated wetland habitats (including areas of grazing marsh, reedbeds, lagoons and gravel pits) are noted as an important feature in the east. 10.49 Large settlements and urban infrastructure (including lines of pylons) are noted as often being visually dominant in the landscape, referring to development around Greater London and the Medway Towns in the west and around towns further east and along the coast. Towns in the east are connected with London via major rail and road links. The NCA profile for the North Kent Plain also comments that industrial and commercial developments including associated pylons and masts have impacted significantly on character, especially in flat, open landscapes such as Thanet and the North Kent fruit belt. The Landscape Assessment of Kent, October 2004 10.50 The application site mainly falls within ‘The Wantsum and Lower Stour Marshes’ Landscape Character Area (LCA), although the underground cable connection crosses a small section of the ‘Thanet’ LCA, which is to the north of ‘The Wantsum and Lower Stour Marshes’ LCA. Less than 1.5km south west of Richborough Power Station is the ‘East Kent Horticultural Belt’ LCA. These LCAs are illustrated on Figure 10.1 and brief descriptions are provided below. The Wantsum and Lower Stour Marshes 10.51 This character area refers to marshlands in north-east Kent, which are the reclaimed and silted up course of the Wantsum Channel and the former mouth of the River Stour. The flat large-scale landscape is noted as having very long views but is bordered by the gentle slopes of the Thanet chalk to the north and east, and the horticultural belt to the south and west. This higher ground is described as abutting the marsh in a very irregular pattern, softening and adding interest to an otherwise uniform expanse, and providing some backgrounding by landform in all views. A viewpoint at Upstreet is identified where the eye is drawn to the twin towers of the Richborough power station (now demolished) and the wind turbine, and to the church tower of St Nicholas at Wade on Thanet. 10.52 The defining characteristics of this area are described as: 230 10.53 Flat, open and remote landscape; No settlement on marshland; Reculver Towers and Richborough Fort marking the end of the Wantsum Channel; Regular field pattern fringed with dykes and drainage ditches; Flood defences are characteristic elements; River courses, flooding and waterlogging; and Coastal influences relating to climate, sand dunes and seabirds. The condition of this landscape character area has been determined as being poor, and the area has been assessed as being moderately sensitive to landscape change. The area’s landscape strategy refers to actions that restore and create, including the restoration of the ecological and visual interest of the area’s drainage channels, restoration of the land patterns of drainage and sea defences and the creation of wetland/marsh/grassland and new reed beds. Thanet 10.54 Thanet is described as a distinct landscape area defined by the former limits of the island that was cut off from the mainland by the Wantsum Channel before it was silted up approximately 1,000 years ago. Local topography has been noted as resulting in two distinct landscape types; the flat plateau top above the 40 metre contour and the sloping backdrop to the marshes between 20 and 40 metres above ordnance datum. 10.55 The defining characteristics of this area are described as: 10.56 Open, large scale arable fields; Lack of vegetation, in part historic due to early intensive agriculture; Long views both to the ‘island’ from the main routes onto it, and back from Thanet over the old Wantsum Channel, now the Chislet Marshes; The central domed ridge to the island, with an aerodrome dominant on the crest; Exposed landscape, historically long denuded seaside/coastal influence with big skies; Open cliff-tops, bleak, grassy spaces; and Existing power lines form a significant visual intrusion in the open landscape, as do new lighting columns along the improved Thanet Way, notably at night. The condition of this landscape character area has been determined as being poor, and the area has been assessed as having a very high degree of sensitivity to landscape change. The landscape strategy for Thanet refers to restoring the area’s characteristics including for example, restoring and enhancing views, including sea views from key locations, restoring the scale and containment of small settlements on the edge of the marshes, and ensuring that development and associated planting respect and enhance the landform. East Kent Horticultural Belt 10.57 This character area is a generally flat and farmed landscape that lies approximately between 10 and 40 metres above ordnance datum. Significant areas of orchard and horticultural crops are referred to at East Stourmouth, Preston, Elmstone, Westmarsh, Upper Goldstone and Perry and to the east at Woodnesborough. 231 10.58 Some of the orchards north of Ash are noted as being grubbed up and growers are diversifying, for example into viticulture; changing the character of the countryside in this area. 10.59 The area is mainly large-scale arable with limited grassland, and is mostly open. The area slopes gently down to the adjacent marshland and the Stour river valley. Views are recorded as often very long, for instance from the Roman road at Hersden across to Thanet, and from Grove Hill across to Stodmarsh and the Stour valley. 10.60 Between Wingham and Ash is an enclosed and secluded landscape with occasional fruit and even hops scattered among the arable fields. A small scale agricultural landscape persists around small hamlets with hedged lanes, shelterbelts and a narrow twisting road network. 10.61 The landscape is increasingly open east of Ash with long views to Richborough Power Station. The few undulations disappear, field boundaries are less in evidence, and the landscape becomes increasingly level as it grades towards the Wantsum and Lower Stour Marshes. Small pockets of industry do occur such as the proposed business use for the old Chislet and Betteshanger Collieries. 10.62 The defining characteristics of this area are described as: 10.63 Medium scale landscape enclosed by hedgerows and shelterbelts, gradually sloping or flat; Some contained, small-scale landscapes in the central area; Mainly large-scale arable with limited grassland around Richborough, Wingham, Stodmarsh, Upstreet, Maypole and Ford south-east of Hunters Forstal; Long views from higher ground and for instance from the Roman Road at Hersden across to Thanet, and from Grove Hill across to Stodmarsh and the Stour valley; Coastal and marsh edges; Diverse agriculture with vineyards, soft fruit, orchards and glasshouses; Small isolated linear villages, some piecemeal development along roads based on original small hamlets or farms; Isolated, square, buff-coloured farm cottages; Very narrow winding roads following the field and drainage pattern; Regimented, intensive feel to farmland; and Some blocks of unmanaged land, particularly towards the marginal wetlands. The condition of this landscape character area has been determined as being moderate, and the area has been assessed as having low sensitivity to landscape change. The area’s landscape strategy refers to creating and reinforcing including the creation of nuclei of small-scale landscapes, reinforcing the character of the marsh-edge by encouraging the development of wetland areas, and by reinforcing drainage patterns and shelterbelts as functional and visual elements within the landscape. Thanet District Landscape Character Assessment 2001 10.64 This detailed landscape character assessment was carried out by Thanet District Council as part of the preparation of the Isle of Thanet Local Plan. The landscape character assessment has since been fully reviewed as part of the Local Plan 232 review and in light of new guidance. The district has been divided into six landscape character areas. Landscape character areas relevant to the Proposed Development are illustrated on Figure 10.1 and are briefly described below. 10.65 The application site at and in the vicinity of the former Richborough power station site is located at the eastern extent of ‘The Former Wantsum Channel’ character area. The majority of the onshore and intertidal underground cable route is within the ‘Pegwell Bay’ character area. The Former Wantsum Channel 10.66 ‘The Former Wantsum Channel’ character area runs inland as an east-west corridor of approximately 1km width. This area includes all the flood plain of the River Stour and is of historic, cultural and visual significance because it represents the former sea channel that used to separate the Isle of Thanet from the mainland. This has silted up over several centuries to form a vast, flat, open landscape with an ancient field system. The area is defined by an extensive ditch and dyke system, the former sea walls and isolated groups of trees, which provide visual evidence of the physical evolution of the landscape. Pegwell Bay 10.67 The ‘Pegwell Bay’ character area lies to the east of former Richborough Power Station site and ‘The Former Wantsum Channel’ character area referred to above. Pegwell Bay is described as an extensive area of mixed coastal habitats, including mudflats, saltmarsh and coastal scrub, which form an open and relatively unspoilt landscape, with a sense of remoteness and wildness despite the relative proximity of development and large open skies. One of its most important features is identified as being the unique sweep of chalk cliffs viewed across Pegwell Bay from the south. The Former Wantsum North Shore 10.68 ‘The Former Wantsum North Shore’ character area is immediately north of ‘The Former Wantsum Channel’ and forms a narrow broadly east-west corridor. The area is characterised by distinctive and often quite steep hill slopes leading down from the Central Chalk Plateau to The Former Wantsum Channel. The landscape is described as being very open with few features and the former shoreline is more distinct in some places than others. From the upper slopes there are extensive views over the whole of ‘The Former Wantsum Channel’ and toward ‘Pegwell Bay’ character area and the sea. The area also provides the setting for a number of former channel-side villages, including Minster which lies just over 2km to the northwest of Richborough Power Station. The area contains a large number of archaeological sites (including Minster Abbey and the historic landing site at St Augustine). These elements all contribute in providing visual evidence of the growth of human activity in the area. The Central Chalk Plateau 10.69 ‘The Central Chalk Plateau’ is to the north of ‘The Former Wantsum Channel’ and is surrounded on its northern and eastern sides by ‘The Urban Coast’ character area. This central part of the district ‘is characterised by a generally flat or gently undulating landscape, with extensive, unenclosed fields under intensive arable cultivation’. This open landscape is fragmented by the location of large-scale 233 developments, such as the airport and is influenced by its proximity to ‘The Urban Coast’ character area. The Urban Coast 10.70 ‘The Urban Coast’ character area is a largely heavily urbanised area that includes Ramsgate (approx. 3km northeast of Richborough Power Station) and forms almost a continuous conurbation on the north and eastern coast. ‘The Urban Coast’ is characterised by traditional seaside architecture, active harbours, beaches and some open clifftop areas, and the pattern of bays and headlands is described as providing long sweeping views of the coast. Dover District Council Landscape Character Assessment, January 2006 10.71 The application site is in Thanet District, although part of the eastern edge of the converter station and substation site and a small section of the underground cable route fall within Dover District. A Landscape Character Assessment is available for Dover District (prepared by Jacobs Babtie), excluding land within the Kent Downs Area of Outstanding Natural Beauty (AONB). 10.72 The Landscape Character Assessment for Dover identifies six landscape types and twelve landscape character areas across Dover District. Part of the converter station and substation site and underground cable route referred to above is within Dover Landscape Type 1 and within LCA 4, ‘The Sandwich Corridor’. Landscape Type 1 is described as a flat visually open landscape with small to medium scale fields divided by ditches with none or only occasional hawthorn and willow scrub. Land use includes grazing, mostly improved pasture, and some arable. Much of the land is ‘reclaimed’ and traditionally unsettled. Former landfill and industrial development is identified north of Sandwich. 10.73 Landscape Type 2 is east of the converter station and substation site extending east of the River Stour. Key characteristics of this landscape type are noted as comprising an irregular and low landform, typically devoid of tree cover and visually unenclosed. Land use within this landscape type is varied including golf courses, a nature reserve and beach. 10.74 Landscape Type 3 is southwest of the converter station and substation site, beyond the ‘Ash Levels’ (LCA 3 referred to below), and extending across agricultural land towards the A257 running west from Sandwich and to the north of Ash. This landscape character type is described as a very gently undulating to nearly flat landscape, enclosed by high hedges and shelterbelts, although more open across arable land. Hedgerows are dominant with mature trees generally associated with buildings and settlement. Small to medium scale arable fields (away from marshland edge) occasionally have few internal boundaries and are defined by narrow enclosed roads. Land use also includes orchards, market gardening and occasional pasture and horse grazing. There are numerous small villages, hamlets, groups of buildings, small churches and large timber barns across the landscape. 10.75 Dover Landscape Character Areas (LCAs) within the site’s context include: The Sandwich Corridor (LCA 4); Sandwich Bay (LCA 6); Ash Levels (LCA 3); Richborough Castle (LCA 4); 234 Preston and Ash Horticultural Belt (LCA 2); and Little Stour Marshes (LCA 1). 10.76 The above are illustrated on Figure 10.1 and the key characteristics of the LCAs are provided below. 10.77 The ‘Sandwich Corridor’ (LCA 4), the ‘Ash Levels’ (LCA 3), ‘Richborough Castle’ (LCA 5) and ‘Little Stour Marsh’ (LCA 1) landscape character areas are within landscape character type 1. 10.78 Key characteristics of The Sandwich Corridor (LCA 4) are described as: 10.79 Key characteristics of the Ash Levels (LCA 3) are described as: 10.80 Flat landscape; Broad native hedgerows and tall metal fencing along roads; Huge, modern buildings with brick and glass dominant; Large car parks; River Stour and boat culture; Associated mudflats and bird life; Large lake; Industrial pockets; Straight, wide main road; and Limited views due to buildings dominating landscape. Low lying, flat and open landscape; Farmland used as permanent grassland and for winter cereals; Sheep and cattle graze the open, improved pasture land; No obvious field pattern, fields are of varying shapes of a smaller size than agricultural land to the west and south; Drainage ditches along field boundaries; Little built development creating a predominantly horizontal landscape with little to interrupt the view or focus the eye; Views extend across the fields due to the flat topography and lack of tree cover and are possible to the higher ground of Thanet to the north of the former Wantsum Channel; and Development in the east is visible, in particular Pfizer and the former Richborough power station within what is described as the Sandwich Corridor. Key characteristics of the ‘Richborough Castle’ landscape character area (LCA 5) are described as: Roman Fort and amphitheatre built on a higher knoll of land in comparison to the surrounding flat ‘Ash Levels’; Arable agricultural land surrounding the Castle, divided by native hedgerow, into medium sized flat fields with no significant shape or pattern; The settlement of Richborough is to the west of the Castle and comprises a scattering of houses of mixed character; Views are relatively far reading from the Castle due to its slightly elevated position; Sandwich and the Sandwich Corridor are visible, but screened in parts by hedgerows; and 235 10.81 Key characteristics of the ‘Little Stour Marshes’ landscape character area (LCA 1) are described as: 10.82 Three separate areas: The Stourmouth Valley; The Preston and Deerson Valley, and the North Wingham Valley; Similar to the Ash Levels, the area is flat and mainly used as permanent grassland with some winter cereal, in particular to the south; No obvious field pattern, fields are of varying shapes although of consistent size; Drainage ditches define field boundaries; and Footpaths follow the waterways, for example the Saxon Shore Way along the Little Stour in the Stourmouth Valley. The ‘Sandwich Bay’ landscape character area (LCA 6) is within landscape character type 2. Key characteristics of Sandwich Bay (LCA 6) are described as: 10.83 Pfizer industrial buildings are noted as being dominant in the view, as well as out of scale and character. Flat to gently undulating topography; Dunes; Sand and shingle; Occasional scrub; Birdlife; Wide expanse of sea; Golf courses; Coarse coastal grasses; Some farmland; Large houses in open plan estate; Few roads; Seasonal change; and Exposed landscape with extensive views out to sea. The ‘Preston and Ash Horticultural Belt’ landscape character area (LCA 2) is within landscape character type 3. Key characteristics of the Preston and Ash Horticultural Belt (LCA 2) are described as: Includes the settlements of Stourmouth, Preston Ash, Marshborough, Woodnesborough and Worth; Relatively flat, although slightly undulating landscape compared to the ‘Stour Marshes’ and ‘Ash Levels’; A variety of agricultural land uses including orchards, vineyards, greenhouses, vegetables, pasture and arable land; Tree cover with some native hedgerows and clumps of native trees and shrubs in places; and Poplar windbreaks and orchard plantations add to the tree cover. Landscape Designations 10.84 There are no landscape designations within or surrounding the Proposed Development site. 236 10.85 There is no land in the area surrounding the Proposed Development that qualifies for conditional exemption from capital taxes on the grounds of outstanding scenic, scientific or historic interest. Description of the Site and Surrounding Landscape Character 10.86 The converter station and substation site comprises 7.65ha of previously developed land. Following the demolition of the former power station cooling towers and chimney, the steel frame of the former turbine hall is the only built structure left on the proposed converter station and substation site and the site is being cleared of demolition debris. 10.87 The 1.8km subsea underground cable route runs in a westerly direction across Pegwell Bay between the low mean water mark and Transition Joint Pit (TJP), which is in saltmarsh (covered by a number of wildlife designations). The 2.3km onshore underground cable route runs in a westerly direction from the TJP across saltmarsh before turning southward at a point just south of Pegwell Bay Service Station and crossing grassland on the coastal side of the existing footpath and cycleway (a Sustrans Regional Route) which runs parallel to the old A256 Sandwich Road. The cable route then crosses into Pegwell Bay Country Park which is public open space comprising amenity grassland, rough grassland, scrub and trees which has been established on land reclaimed following landfill. The cable route continues southward and parallel with the A256 Sandwich Road through Stonelees Nature Reserve which consists of a mixture of grassland, scrub and occasional trees (and is covered by a number of wildlife designations) and into the western edge of the former BayPoint sports complex. From the sports ground, the cable would be routed by horizontal direction drilling to the south west, passing beneath the A256, Minster Stream, and a compartment of Hacklinge Marshes SSSI (an area of scrub with trees), entering the converter station and substation site at the northeastern corner. 10.88 To the west of the converter station and substation site a narrow strip of land separates the converter station and substation site from the River Stour. A concrete wall and metal railings (remnants of the previous land use) form the eastern edge of the river at this point and this boundary is open. 10.89 To the south of the converter station and substation site there are a number of industrial sites on each side of the A256, including the Thanet Offshore Windfarm 132kV Substation to the immediate south. The River Stour sits behind industrial land uses on both the eastern and western sides of the A256 and is hidden from view for road users. 10.90 The A256 lies close to the converter station and substation site’s eastern boundary. This part of the application site is separated from the main road by a petrol filling station and rough grass verge and there are also some tree groups close to the eastern site boundary. 10.91 To the north of the converter station and substation site is an area of scrub with trees, which is designated a SSSI. Beyond this is Weatherlees Hill Wastewater Treatment Works, Richborough Solar Farm and the new A256 bypass. 10.92 A 500kW anaerobic digestion plant is being built (November 2012) adjacent the new roundabout on the A256 and the new bypass, between the new lane (off the roundabout) leading to Ebbsfleet Farm to the north and Minster stream in the south. The anaerobic digestion plant comprises an agricultural building (maximum height 237 12m), a cylindrical digestate storage tank (with a 6m high wall, measuring 14.82m high to the peak of the gas collection roof), and two cylindrical digesters, (also with a 6m high wall, but not as tall at approximately 12.2m high to the peak of the dome). Digester tanks and the storage tank will be clad in green aluminium. The anaerobic digestion plant will also comprise a covered CHP generator and control room, hardstanding, mounding to the north western site boundary with Minster stream and mixed native shrub mix planting to the north eastern site boundary. 2.4m high green palisade fencing is proposed to secure the site. 10.93 North of the anaerobic digestion plant, between the new A256 bypass and Ebbsfleet Lane is a new solar park including 10 rows of solar panels positioned 0.6m above ground with an overall height of 2.3m. The site is secured by 2 metre high fencing. 10.94 To the northwest of the converter station and substation site, the former power station site continues as a narrow strip of cleared land adjacent to the River Stour. This land is part of the proposed Richborough Energy Park and the 1.6 hectare temporary laydown area required for the construction of the converter station and substation development would be on the land to the immediate west of the application site. In the western part of Richborough Energy Park and to the north of the river there is a single wind turbine and two masts, which are prominent vertical features in the landscape. 10.95 The application site is part of an area of low lying ground (less than 5m AOD) associated with the River Stour, close to where it enters the sea at Pegwell Bay. The low lying river floodplain (or marshes) west of the former power station is drained by a network of ditches and is mainly under arable use, although fields of pasture and rough grazing flank the river. Fields are regularly sized and broadly geometric. Occasional hedgerows and hedgerow trees are found within this lower lying ground, but the landscape is generally open and remote, being devoid of roads or built form, with the exception of two high voltage (132kV) overhead powerlines which run from the former power station westward broadly along the path of the River Stour and are prominent features in views from low ground looking along the valley floor. A further overhead line runs southward from the former power station and crosses the southern valleyside to the west of Richborough Roman Fort and Amphitheatre. There are also two railway lines, which are flanked by mature vegetation belts. There is a railway line running southward across the valley from Minster to Sandwich, which passes the converter station and substation site approximately 0.5km to the west. A second railway line runs east-west along the northern edge of the Stour floodplain through Minster, connecting with Ramsgate. 10.96 The southern valleyside is gently sloping and there are a number of fruit orchards on this side of the valley, interspersed with some arable fields. The orchards are protected by tall hedgerows and shelterbelts, which create an enclosed character in contrast to the open marshes to the north. The area is crossed by a series of narrow winding lanes which follow field patterns. Along the network of lanes are linear villages, small hamlets and farmsteads. 10.97 The northern valleyside is more steeply sloping than the southern valley slopes with larger-scale arable fields. Fields boundaries are often open, allowing extensive views across the valley (the former Wantsum Channel) and out to Pegwell Bay. The transition from the floodplain marshes to the northern valley side is defined by the southern edge of the historic village of Minster and the railway line which runs along this edge. Apart from Minster, other residential settlement occurs as linear 238 development along a network of minor roads. A number of these minor roads have been severed at their northern extents where the A253 and A299 run along the ridgeline toward Ramsgate. Suburban and ‘out of town’ development associated with the southwestern edge of Ramsgate has an urban influence on landscape character and the edge of Ramsgate is visible on the skyline from locations within the landscape to the southwest. Kent International Airport is also positioned on the ridgeline and is a prominent feature, with views of aeroplane activity on the skyline possible from a number of locations. 10.98 The former power station site forms part of a number of industrial sites and urban influences, associated with the old A256, which runs past Pegwell Bay and connects Ramsgate with Sandwich. At the northern end of the A256 corridor, the landscape consists of a mixture of arable land extending to clifftops, residential suburban development at Cliffs End and the southwestern edge of Ramsgate and recreational open space associated with the beach at Pegwell Bay. Further south the A256 urban corridor is separated from the coast by a combination of mud flats, salt marsh and scrub around the southern edge of Pegwell Bay and the mouth of the Stour. Pegwell Bay Country Park, established over landfill as an area of scattered trees and scrub with amenity and rough grassland, sits within this landscape. On the west side of the old A256 is St Augustine’s Golf Course and Stonelees Golf Centre, which contain established tree planting in groups and around their boundaries. The converter station and substation site sits to the south of this area, and from this point southward industrial units and land uses are visible to either side of the A256. East of the A256 corridor, a mixture of rough grazing land with a few arable fields and golf courses extend along the coast toward Sandwich. Although devoid of mature woodland and tall trees, this landscape appears well vegetated in views across Pegwell Bay and from higher ground on the valley sides, although some of the low lying salt marshes and intertidal area are open in themselves. The presence of industry, other urban influences and coastal habitats partly bring a bleak feel to the coastal landscape. 10.99 Key characteristics identified within the published landscape character assessments are evident in the landscape within the study area. Along the coast between Ramsgate and Sandwich these characteristics include: Flat landscape; Industrial pockets; Straight wide main road; Mixed coastal habitats, including mudflats, saltmarsh and coastal scrub; Sense of remoteness and wildness despite the relative proximity of development; Large open skies; and Sweep of chalk cliffs viewed across Pegwell Bay from the south. 10.100 Within the low lying ground of the Stour Valley (former Wantsum Channel) these characteristics include: Flat, open and remote landscape; Small to medium scale fields divided by ditches; Land use includes grazing, mostly improved pasture, with some arable land; Much of the land is ‘reclaimed’ and traditionally unsettled; Occasional hawthorn or willow, reeds and flax along ditch lines; No roads or buildings and few footpaths in north-south direction; Former landfill and industrial development is identified north of Sandwich; and 239 Lines of pylons are noted as dominating the open and often treeless landscape. 10.101 On the northern side of the Stour Valley these characteristics include: Open, large scale arable fields; Long views both to the ‘island’ from the main routes onto it, and back from Thanet over the old Wantsum Channel, now the Chislet Marshes; The central domed ridge to the island, with an aerodrome dominant on the crest; and Suburban character to towns. 10.102 On the southern side of the Stour Valley these characteristics include: Medium scale landscape enclosed by hedgerows and shelterbelts, gradually sloping or flat; Diverse agriculture with vineyards, soft fruit, orchards and glasshouses; Small isolated linear villages, some piecemeal development along roads based on original small hamlets or farms; Very narrow winding roads following the field and drainage pattern; Regimented, intensive feel to farmland; and Some blocks of unmanaged land, particularly towards the marginal wetlands. Landscape Value, Condition and Sensitivity 10.103 The landscape within and surrounding the application site is not covered by any landscape designations and is generally judged to be of local value to nearby residents. Pegwell Bay is promoted as a tourist destination although primarily for its wildlife interest. 10.104 The landscape condition of the application site and immediate surroundings is generally poor. This reflects recent development along the coastline and changes in agricultural practices in the surrounding landscape. The orchard landscape on the southern valleyside is in moderate condition, as this area is broadly intact with only some encroachment of arable land and hedgerow loss. 10.105 In terms of the overall sensitivity of the landscape within and surrounding the application site to this type of development, the application site borders the eastern edge of an agricultural landscape, and is associated with a well vegetated landscape between Ramsgate and Sandwich which already contains industrial development to either side of the A256. The converter station and substation site is on brownfield land, which contains the steel frame structure of a derelict building. The converter station and substation development would be consistent with the existing landscape character and would match the scale of existing industrial built form. The landscape is of local value and although the landscape is open to the west, existing vegetation along the coastline would help accommodate this development in the landscape and mitigation by way of tree planting would not be out of character. The underground cable route, which will be reinstated following construction, runs close to the A256 and across restored land at Pegwell Bay Country Park. Overall the landscape is of low sensitivity to change. Existing Views 10.106 The visual influence of the Proposed Development site has been determined through a combination of computer generated mapping, topographic analysis and 240 field evaluation of features affecting visibility such as built form and trees, hedgerow and woodland that would filter and screen views of the development. This work determined the potential visibility of the Proposed Development site and identified visual receptors. Visual receptors identified were also discussed with the Planning Case Officers from Thanet and Dover District Councils as part of the agreement as to which viewpoints photomontage views should be prepared. 10.107 Field survey has considered all receptors from where views of the Proposed Development are likely and what existing views comprise. No access has been sought to private properties or land and an assessment has been made from the nearest publicly accessible viewpoint. Single frame and panoramic photographic views were taken from a number of these locations (see Figures 10.4 to 10.16). These images illustrate the current views in the area and form part of the baseline against which the proposed converter station and substation and underground cable route is assessed. 10.108 There are views towards the Proposed Development from public viewpoints which would be experienced by visitors to public open space or heritage open space, walkers on Public Rights of Way, road users and rail users in the surrounding area. Private receptors refer to residential properties, businesses and private golf courses and sports grounds anticipated to have views towards the Proposed Development. 10.109 The approximate Zone of Visual Influence (ZVI) of the Proposed Development extends to elevated viewpoints on the western edge of Ramsgate and along the valley slope to encompass visual receptors in the vicinity of Minster and Monkton. The ridgeline to the Isle of Thanet Plateau coincides with the A299 and Kent International Airport and marks the extent of the ZVI to the north. 10.110 To the west of the Proposed Development, the generally flat and open nature of the Stour Valley (former Wantsum Channel) allows some distant views toward the converter station and substation site for public and private receptors as far west as Sarre, St Nicholas at Wade, and Upstreet (which is approximately 10km distant). Beyond this the Stour Valley turns southward and distance, intervening topography and vegetation prevent further views. Within the ZVI the reclaimed marshes to either side of the River Stour have few visual receptors apart from the public right of way network and the occasional minor road crossing or dwelling. 10.111 To the south of the Proposed Development, visibility from higher ground on the south side of the Stour Valley is generally restricted by orchards and the tall hedgerows and shelter belts associated with them. Apart from the more extensive views available from the Roman Fort and Amphitheatre at Richborough, visual receptors are generally limited to the residents’ views from those dwellings on the edge of the open marshland to the north, as well as the occasional glimpsed view from the public right of way and minor road network further south. To the immediate south of the Proposed Development, other industrial and urban development near Sandwich prevents views from extending much beyond the BayPoint sports complex, with some slightly more distant views possible from the long distance footpath routes on the coast and within the Prince’s Links Golf Course and Royal St George’s Golf Course. 10.112 To the east of the Proposed Development nearer views are possible from amenity open space along the coastline and the ZVI also extends out into Pegwell Bay. 241 Visual Receptors 10.113 For this site, public and private visual receptors are anticipated to comprise the following (see Figure 10.2 for visual receptor locations): Public Views Walkers along the following Public Rights of Way (PROW): 1.1a – Saxon Shore Way at former Richborough Power Station; 1.1b – Saxon Shore Way near Roman Fort; 1.1c - Saxon Shore Way at Boxlees Hill (south of Minster) including footpath connections south of Marsh Farm Road; 1.1d - Saxon Shore Way at Plucks Gutter; 1.1e – Saxon Shore Way at Royal St George’s Golf Club; 1.2a – Stour Valley Walk at Sandwich Flats/Prince’s Golf Links; 1.2b – Short section of Stour Valley Walk at Cooper Street; 1.3a – Thanet Coastal Path at Pegwell Bay Country Park to Cliffs End; 1.3b - Thanet Coastal between Cliffs End and the edge of Ramsgate; 1.4 – PROW at Potts Farm Drove; 1.5 - PROW at Goldstone Drove (and PROW which runs parallel 0.2km to the west); 1.6 - PROW at Westmarsh Drove (and PROW which runs broadly parallel to the east); 1.7a and 1.7b - PROW network east of Minster (1.7a - north of the railway line and 1.7b – south of the railway line); 1.7c – PROW west of Cliffs End; 1.8 - PROW southwest of Minster; 1.9a - PROW south of Manston/Manston Road; 1.9b – PROW south of Nethercourt; 1.10 - Network of PROW around Monkton Marshes/Docker Hill; 1.11 - PROW between Brookestreet Farm and East Street; and 1.12 – PROW north of Monkton and Minster. Users of the following public open spaces and outdoor tourist attractions: 2.1 – Pegwell Bay Country Park; 2.2 – Stonelees Nature Reserve; 2.3 – St Augustine’s Cross; 2.4 – Richborough Roman Fort; 2.5 – Richborough Roman Amphitheatre; 2.6 – Pegwell Bay picnic area and beach; 2.7 - Sandwich boat trips up River Stour; 2.8 - Sandwich boat trips to Pegwell Bay; and 2.9 - West Cliff, Ramsgate. 242 Users of the following roads and railway lines: 3.1a - A256 Sandwich Road (North of the converter station and substation site, including site entrance) including the adjacent Sustrans Regional Route; 3.1b – A256 new bypass (East Kent Access Road Phase 2); 3.1c - A256 Ramsgate Road (south of the converter station and substation site) including the adjacent Sustrans Regional Route; 3.2 - Ebbsfleet Lane (north and south of the new A256 bypass); 3.3 – Rural lane south of Minster (Marsh Farm Road); 3.4 – Richborough Road between Roman Amphitheatre and Roman Fort; 3.5 - Grinsell Hill and other rural lanes northeast of Minster, and Cottington Rd and Thorne Hill; 3.6 - Pegwell Road, Ramsgate; 3.7 - A299 Canterbury Road West between Mount Pleasant and Ramsgate; 3.8 - A256 Haine Road (on western side of Ramsgate, north of intersection with A299); 3.9 - Other minor roads south of River Stour; 3.10 - Manston Road (either side of A256); 3.11 - A299 Canterbury Road West (between Monkton roundabout and Mount Pleasant) and also a footpath and cycleway route which runs parallel and to the south; 3.12 - A253 Island Rd (between Sarre and Monkton roundabout); 3.13 - Minor road between Plucks Gutter and Gore Street; 3.14 - A28 Canterbury Road at St Nicholas at Wade; 3.15 - Railway line from Ramsgate to Minster; 3.16 - Railway line from Minster to Sandwich; and 3.17 - Railway line west of Minster (along Stour Valley). Private Views Residents living at the following properties: A1 - Houses on Ebbsfleet Lane near the junction with Sandwich Road (A256); A2a – Ebbsfleet Farm; A2b – No. 1 Ebbsfleet Farm Cottages on Ebbsfleet Lane; A3 – House between industrial units on Ramsgate Road; A4a – Houses at Sevenscore; A4b – Houses at/near Thorne Farm; A5 - Houses on Whitehouse Drove; A6a - Cliffs End (south of railway line); A6b – Cliffs End (north of railway line); A7 - Castle Road, Richborough; A8 - Houses on Rubery Drove; A9 - House at/west of Richborough Farm; A10 - Houses near Guston Farm, Potts Farm and Lower Goldstone; A11 - Minster and surrounds; A12 - House at Little Cliffsend Farm and Coastguard Cottages; A13 - Nethercourt, Ramsgate; A14 - Pegwell, Ramsgate; A15 - Houses at Hoo; A16 - Stanner Court residential tower block and new housing development on Manston Road, Ramsgate; 243 A17 - East Stourmouth and surrounds; A18 – Sandwich; A19 – Sarre; A20 - Upstreet; A21 – East Street; and A22 – St Nicholas at Wade. Users of the following golf courses and sports facilities: B1 – Stonelees Golf Centre; B2 – St Augustine’s Golf Course; B3 – Manston Golf Centre near Ramsgate; B4 – Prince’s Golf Links near Sandwich; B5 – Royal St George’s Golf Club near Sandwich; and B6 – BayPoint sports complex. Workers and customers at the following businesses: C1 – Businesses and industrial units near the site entrance and to the south of the converter station and substation site on the A256; C2 – BayPoint sports complex; C3a - The Sportsman Inn Public House, Sandwich Road (old A256); C3b – Pegwell Bay Service Station, Sandwich Road (old A256); C4 - Pegwell Bay Hotel, Pegwell Road; C5 - The Sir Stanley Gray and Belle Vue Public Houses, Pegwell Road; C6 - Lord of the Manor Public House off A299; C7 - Industrial Park, Laundry Road, Minster; C8 – Holiday Inn and Premier Inn, Minster; C9 – Wayside Caravan Park, Minster; and C10 – Sarre Windmill. Sensitivity of Visual Receptors Identified 10.114 Sensitivity of visual receptors depends upon location of viewpoint, expectations and activity of the receptor and the importance of the view. Leisure walkers using Public Rights of Way and users of public open space within the ZVI have been assessed as being of high sensitivity to visual change. Visual receptors using the local road network within the ZVI are anticipated to be primarily motorists and are assigned a low sensitivity to visual change, with the exception of users of ‘rural lanes’ (designated under saved policy within Thanet District Council’s Local Plan 2006) which have been assigned a moderate sensitivity. 10.115 Residents with lower storey views are judged to be receptors of high sensitivity to visual change, whilst residents with upper storey views towards the site are considered to have a moderate sensitivity to visual change. 10.116 Generally workers and visitors to private businesses are considered to have a low sensitivity to visual change, unless appreciation of the setting of the business premises and the views from it are part of the customer experience. ‘Wayside Caravan Park’ in Minster, Pegwell Bay Hotel and Sarre Windmill have been assessed as being of high sensitivity to visual change, and other pubs and visitor accommodation which would contain visual receptors have been assessed as being of moderate sensitivity to visual change. 244 10.117 Golf course users are considered to have a moderate sensitivity to visual change, as the setting and views from a golf course may be part of the enjoyment of the sport, whereas users of sports pitches are considered to have a low sensitivity to visual change as the focus would be on the sport being played. Importance of Views 10.118 The majority of views are of local (low) importance to local residents and a relatively small number of tourists. The views from Richborough Roman Fort and Amphitheatre (an English Heritage visitor attraction) have been recorded as being of moderate importance. (Views from Richborough Roman Fort and Amphitheatre are also considered as part of the archaeology and cultural heritage assessment – see chapter 9). No views in the study area are recorded as being of high (national) importance. Nature of Existing Views 10.119 Tables 10.10 to 10.15 in Appendix 10.2 provide a description of the existing views from each of the visual receptors identified. Figures 10.4 to 10.16 include site photographs taken from viewpoint locations identified on Figure 10.3 and Figures 10.17 to 10.23 present ‘before’ views from the photomontage viewpoint locations shown on Figure 10.3. In summary, all of the visual receptors identified within the ZVI have existing views of the derelict frame of the former turbine hall building within the converter station and substation site. Apart from the existing views experienced by a few visual receptors immediately adjacent to the converter station and substation site, it is the upper part of the derelict frame that is visible above intervening vegetation. From elevated viewpoints on the Stour valleysides the derelict frame is set below the horizon and is not visually prominent. In views from lower ground the former turbine hall sits on the skyline, including in more distant views across the lower lying marshes. In near views of the converter station and substation site, the derelict nature of the former turbine hall is apparent. A number of these existing views also comprise nearby industry and built form, such as the BayPoint sports complex to the south of the Proposed Development and the wind turbine and masts located west of the converter station and substation site. These features create a complex pattern, in views from elevated viewpoints, of vegetation with glimpses of built form along the coastline. 10.120 Existing views of the underground cable route are generally restricted to visual receptors close to the route, which include users of the Sustrans Regional Route, Stonelees Nature Reserve and Pegwell Bay Country Park. The exception is the route across the intertidal mudflats which are open and visible from a number of more distant visual receptors surrounding Pegwell Bay. Although the underground cable route crosses ecological habitat and green space, the nearby A256 and urban development along the coast are already components in a number of the views of the cable route. Prediction and Assessment of Significance of Potential Impacts Construction Phase Effects on Landscape Character 10.121 Construction effects would be associated largely with the introduction and movement of site vehicles and construction machinery, site preparation and build, 245 some tree removal to accommodate the cable route within Pegwell Country Park, excavated underground cable trenches, stockpiled material, site compounds, storage buildings, temporary fencing and signage. Construction activity would not be uncharacteristic or out of context with the landscape character of the coastal corridor between Ramsgate and Sandwich. 10.122 The magnitude of effect on landscape character as a result of the Proposed Development (including works to the underground cable route) during the construction period would be moderate adverse. The landscape generally has a low sensitivity to change and is of local value or importance, resulting in a moderate adverse significance of effect on landscape character during construction. Effects on Views 10.123 Some receptors with views towards the application site (including the underground and overground cable route) would experience negative visual effects during construction. However, these would be temporary short term effects. Visual effects anticipated during the construction phase are identified in Tables 10.10 to 10.15 in Appendix 10.2 and range from moderate to minor adverse effects for a small number of visual receptors closest to the site and those at elevated viewpoints, with more distant and also low lying visual receptors experiencing a neutral effect. On Completion Effects on Landscape Character 10.124 Following reinstatement of the cable swathe the magnitude of effect on landscape character as a result of the proposed cable route (including the overground section of cable through the northern part of Pegwell Country Park and along the A256 in this locality), would be negligible. The overground cable route through the northern part of Pegwell Country Park cleared of trees and scrub, will be capped with chalk, (similar to capping across the former landfill which Pegwell Country Park encompasses), and will be quickly re-established as grassland. The overground cable route would comprise a low adverse magnitude of effect on the landscape. The landscape has a low sensitivity to change and overall the underground cable route would result in a neutral significance of effect. 10.125 As assessed above in relation to temporary construction effects, the magnitude of effect on landscape character during any maintenance or repair works required in relation to the overground and underground cable route would be no greater than moderate adverse in a localised area due to ground disturbance, stockpiling and construction activity. The significance of this short term effect on landscape character would be moderate adverse. 10.126 Implementing the Proposed Development at the converter station and substation site would be consistent with the existing character of the A256 coastal corridor between Ramsgate and Sandwich, which already comprises industrial development and includes the derelict site of the former Richborough Power Station. Vegetation associated with open space, golf courses, nature reserves, designated wildlife habitats and the railway lines assists in accommodating existing development within the coastal landscape and wider landscape context, including the open and low lying marshes to the west. Although the development would introduce elements that are generally characteristic of the surrounding landscape, it would extend built development across the existing derelict site, which would increase the extent of industrial development presently evident in the locality. 246 10.127 The magnitude of effect on the landscape character of the converter station and substation site on completion (and prior to mitigation) would be low adverse. The landscape has a low sensitivity to change which would result in a minor adverse significance of effect (prior to mitigation). Effects on Views 10.128 On completion (and prior to mitigation) some receptors with views towards the application site (including the underground and overground cable route) would experience negative visual effects. Visual effects anticipated on completion are identified in Tables 10.10 to 10.15 (in Appendix 10.2) and range from moderate to minor adverse effects for a small number of visual receptors closest to the application site and those at elevated viewpoints, with more distant and also low lying visual receptors generally experiencing a neutral effect. 10.129 Figures 10.17 to 10.23 present views of converter station and substation proposals from the photomontage viewpoint locations shown on Figure 10.3. 10.130 Table 10.6 below summarises judgements made when assessing anticipated visual effects of the Proposed Development (including the underground and overground cable route) on each of the identified visual receptors on completion. Table 10.6: Summary of Anticipated Visual Effects on Completion Visual Receptor Sensitivity Importance of view Magnitude of Effect Significance of Effect On Completion Effects on Views from Public Rights of Way 1.1a Saxon Shore Way at Former Richborough Power Station High Low Moderate adverse Moderate adverse 1.1b Saxon Shore Way near Roman Fort High Low Negligible Neutral 1.1c Saxon Shore Way at Boxlees Hill (south of Minster) including footpath connections south of Marsh Farm Road High Low Negligible Neutral 1.1d Saxon Shore Way at Plucks Gutter High Low Negligible Neutral 1.1e Saxon Shore Way at Royal St George’s Golf Club High Low Negligible Neutral 1.2a Stour Valley Walk at Sandwich Flats/Prince’s Golf Links High Low Negligible Neutral 247 Visual Receptor Sensitivity Importance of view Magnitude of Effect 1.2b Short section of Stour Valley Walk at Cooper Street High Low Negligible Significance of Effect On Completion Neutral 1.3a Thanet Coastal Path at Pegwell Bay Country Park High Low Low adverse Minor adverse 1.3b Thanet Coastal Path between Cliffs End and the edge of Ramsgate High Low Negligible Neutral 1.4 PROW at Potts Farm Drove High Low Negligible Neutral 1.5 PROW at Goldstone Drove (and PROW which runs parallel 0.2km to the west) High Low Negligible Neutral 1.6 PROW at Westmarsh Drove (and PROW which runs broadly parallel to the east) High Low Negligible Neutral 1.7a &b PROW network east of Minster High Low Negligible Neutral 1.7c PROW west of Cliffs End High Low Low adverse Minor adverse 1.8 PROW southwest of Minster High Low Negligible Neutral 1.9a PROW south of Manston/Manston Road High Low Negligible Neutral 1.9b PROW south of Nethercourt (Chalk Hill) also Sustrans Regional Route 15 High Low Negligible Neutral 1.10 Network of PROW around Monkton Marshes/Docker Hill High Low Negligible Neutral 1.11 PROW between Brookestreet Farm and East Street High Low Negligible Neutral 1.12 PROW north of Monkton/Minster High Low Negligible Neutral Effects on Views from Public Open Space and Outdoor Tourist Attractions 2.1 Pegwell Bay Country Park High Low Low adverse Minor adverse 2.2 Stonelees Nature Reserve High Low Low adverse Minor adverse 248 Visual Receptor Sensitivity Importance of view Magnitude of Effect 2.3 St Augustine’s Cross High Low Low adverse Significance of Effect On Completion Minor adverse 2.4 Richborough Roman Fort High Moderate Low adverse Minor adverse 2.5 Richborough Roman Amphitheatre High Moderate Negligible Neutral 2.6 Pegwell Bay picnic area and beach High Low Negligible Neutral 2.7 Sandwich boat trips up River Stour High Low Moderate adverse Moderate adverse 2.8 Sandwich boat trips to Pegwell Bay High Low Negligible Neutral 2.9 West Cliff, Ramsgate High Low Negligible Neutral Effects of Views from Roads and Rail 3.1a Old A256 Sandwich Road (north of converter station and substation site, including site entrance) also Sustrans Regional Route 15 Low/ Moderate Low Low adverse Neutral (Minor adverse for footpath and cycleway users) 3.1b New A256 bypass (East Kent Access Road Phase 2) Low Low Negligible Neutral 3.1c A256 Ramsgate Road (south of converter station and substation site) also Sustrans Regional Route 15 Low Low Negligible Neutral 3.2 Ebbsfleet Lane (north and south of new A256 bypass) Low Low Negligible Neutral 3.3 Marsh Farm Road (rural lane south of Minster) Moderate Low Negligible Neutral 3.4 Richborough Road between Roman Amphitheatre and Roman Fort Low Low Negligible Neutral 3.5 Grinsell Hill and other rural lanes northeast of Minster and Cottington Road and Thorne Hill (Sustrans Regional Route 15) Moderate Low Low adverse Minor adverse 249 Visual Receptor Sensitivity Importance of view Magnitude of Effect Significance of Effect On Completion Neutral 3.6 Pegwell Road, Ramsgate Low Low Negligible 3.7 A299 Canterbury Road West between Mount Pleasant and Ramsgate Low Low Low adverse Neutral 3.8 A256 Haine Road (on western side of Ramsgate, north of intersection with A299) Low Low Negligible Neutral 3.9 Other minor roads south of River Stour Low Low Negligible Neutral 3.10 Manston Road (either side of A256) Low Low Negligible Neutral 3.11 A299 Canterbury Road West (between Monkton roundabout and Mount Pleasant) including the footpath and cycleway to the south Low/ Moderate Low Negligible Neutral 3.12 A253 Island Road (Gore Street to Monkton roundabout) Low Low Negligible Neutral 3.13 Minor road between Plucks Gutter and Gore Street Low Low Negligible Neutral 3.14 A28 Canterbury Road at St Nicholas at Wade Low Low Negligible Neutral 3.15 Railway line from Ramsgate to Minster Low Low Negligible Neutral 3.16 Railway line from Minster to Sandwich Low Low Low adverse Neutral 3.17 Railway line west of Minster (along Stour Valley) Low Low Negligible Neutral Effects on Views from Private Residences A1 Houses on Ebbsfleet Lane near the junction with Sandwich Road (old A256) Moderate Low Low adverse Minor adverse A2a Ebbsfleet Farm Moderate Low Low adverse Minor adverse A2b No. 1 Ebbsfleet Farm Cottages on Ebbsfleet Lane Moderate Low Low adverse Minor adverse 250 Visual Receptor Sensitivity Importance of view Magnitude of Effect A3 House between industrial units on Ramsgate Road (A256) High Low Low adverse Significance of Effect On Completion Minor adverse A4a Houses at Sevenscore High Low Negligible Neutral A4b Houses at/near Thorne Farm Moderate Low Low adverse Minor adverse A5 Houses on Whitehouse Drove High Low Negligible Neutral A6a Cliffs End (south of railway line) Moderate/ High Low Negligible Neutral A6b Cliffs End (north of railway line) Moderate/ High Low Low adverse Minor adverse A7 Castle Road, Richborough Moderate Low Low adverse Minor adverse A8 Houses on Rubery Drove Moderate/ High Low Negligible Neutral A9 House west of Richborough Farm High Low Negligible Neutral A10 Houses near Guston Farm, Potts Farm and Lower Goldstone Moderate Low Negligible Neutral A11 Minster and surrounds Moderate Low Low adverse Minor adverse A12 House at Little Cliffsend Farm and Coastguard Cottages Moderate/ High Low Negligible Neutral A13 Nethercourt, Ramsgate High Low Negligible Neutral A14 Pegwell, Ramsgate Moderate Low Negligible Neutral A15 Houses at Hoo Moderate Low Negligible Neutral A16 Stanner Court residential tower block and new housing development on Manston Road, Ramsgate High Low Negligible Neutral A17 East Stourmouth and surrounds Moderate Low Negligible Neutral A18 Sandwich Moderate Low Negligible Neutral A19 Sarre High Low Negligible Neutral A20 Upstreet Moderate Low Negligible Neutral A21 East Street Moderate Low Negligible Neutral 251 Visual Receptor Sensitivity Importance of view Magnitude of Effect A22 High Low Negligible St Nicholas at Wade Significance of Effect On Completion Neutral Effects on Views from Private Golf Courses and Sports Facilities B1 Stonelees Golf Centre Moderate Low Negligible Neutral B2 St Augustine’s Golf Club Moderate Low Negligible Neutral B3 Manston Golf Centre near Ramsgate Moderate Low Negligible Neutral B4 Prince’s Golf Links near Ramsgate Moderate Low Negligible Neutral B5 Royal St George’s Golf Club near Sandwich Moderate Low Negligible Neutral B6 BayPoint sports complex Low Low Low adverse Neutral Effects on Views from Private Businesses C1 Businesses and industrial units near the site entrance and to the south of the converter station and substation site on the A256 Ramsgate Road Low Low Low adverse Neutral C2 BayPoint sports complex Low Low Negligible Neutral C3a The Sportsman Inn Public House, old A256 Sandwich Road Moderate Low Negligible Neutral C3b Pegwell Bay Service Station, Sandwich Road Low Low Negligible Neutral C4 Pegwell Bay Hotel, Pegwell Road High Low Negligible Neutral C5 The Sir Stanley Gray and Belle Vue Public Houses, Pegwell Road Moderate Low Negligible Neutral C6 Lord of the Manor Public House off A299 Moderate Low Negligible Neutral C7 Industrial Park, Laundry Road, Minster Low Low Low adverse Neutral C8 Holiday Inn and Premier Inn, Minster Moderate Low Low adverse Minor adverse C9 Wayside Caravan Park, Minster High Low Low adverse Minor adverse 252 Visual Receptor Sensitivity Importance of view Magnitude of Effect C10 High Low Negligible Sarre Windmill Significance of Effect On Completion Neutral Mitigation Construction Phase 10.131 Mitigation of likely construction effects on landscape and views would be largely achieved through the implementation of a Construction Environmental Management Plan which would include the following measures: Protection of trees to be retained to BS 5837 (2005), for the duration of the construction works; Screening on-site activity where practical whilst at the same time not being a highly negative visual distraction in itself; Management of site traffic to and from site, minimising excessive traffic movement on the surrounding road network; and Management of working times to minimise visual effects of construction in evenings and at weekends when residential and sports and leisure receptors may be most likely to be present. Operational Phase 10.132 Mitigation of likely long-term effects on landscape and views would be largely achieved through the following measures: The use of colour graded cladding to the converter station building, ranging from a muted green at the building’s base to off-white at the roofline. This will minimise landscape and visual effects and particularly the effect on views where the building sits on the horizon. Due to its lower height the substation building will be clad in a single colour (muted green); and Tree and shrub planting proposed on the western boundary of the converter station and substation site to partly filter and screen some views of the converter station from the west and northwest (in particular from the Saxon Shore Way and from River Stour) and to filter and screen views of the substation proposals from the south (in particular from the Saxon Shore Way). See Figure 10.4 Planting Proposals. 10.133 In addition to the above, the wider proposals for Richborough Energy Park include the implementation of new planting as part of a separate but closely related planning application (submitted by Richborough A Limited (RAL)) for a new estate road to the perimeter of the former Richborough Power Station site (see section on cumulative effects below). These planting proposals have been referenced as part of this planning application and will include replacement tree planting along the eastern and north eastern site boundaries (partly mitigating trees loss to accommodate the new road), new native trees, shrubs and fruit trees near the site entrance, existing trees and shrubs on the northern site boundary being retained and enhanced with new native tree planting, and new native trees and shrubs along part of the sites western boundary adjacent the River Stour in front of new fencing. In the unlikely event that the estate road landscaping proposals are not 253 implemented, National Grid Nemo Link Limited (NGNLL) proposes to enter into arrangements with RAL to ensure the landscaping and estate road proposals are delivered and would be prepared to enter into a planning obligation to this effect. These landscape proposals are considered below as part of the proposed converter station and substation development. Residual Impacts Residual Effects on Landscape Character during the Construction Period 10.134 With mitigation the residual temporary effects on landscape character during the construction period would remain moderate adverse. Residual Effects on Views during the Construction Period 10.135 Mitigation measures would help reduce temporary construction effects on visual receptors, although the significance of effect on views (as identified in Tables 10.10 to 10.15 in Appendix 10.2) would remain the same. These visual effects would range from moderate to minor adverse effects for a small number of visual receptors closest to the site and those at elevated viewpoints, with more distant and also low lying visual receptors experiencing a neutral effect. Residual Effects on Landscape (with mitigation and after 15 years establishment) 10.136 Mitigation measures would reduce the significance of effect of the proposed converter station and substation on landscape character to minor adverse to neutral. New planting around the site and at the site entrance would improve the landscape quality of the site and would assist in integrating the Proposed Development into the site’s context. 10.137 The significance of effect on landscape of the underground cable route, and overground section capped with chalk, would remain neutral on completion with mitigation and after establishment. Residual Effects on Views (with mitigation and after 15 years establishment) 10.138 The residual effects of the Proposed Development, including the implementation of planting proposed to the western site boundary and planting proposed as part of the wider Richborough Energy Park (relating to the estate road to the site perimeter), have been taken to be those effects still remaining after approximately 15 years when new tree and shrub planting will be maturing. 10.139 The greatest residual effects anticipated on public receptors, following mitigation and 15 years’ establishment would be moderate to minor adverse. This moderate to minor negative significance of effect on views would be experienced from the section of the Saxon Shore Way (receptor 1.1a) adjacent to the converter station and substation site and by river users on the Stour (receptor 2.7) adjacent to the converter station and substation site. Although it would be difficult to screen the development entirely from these viewpoints, tree and shrub planting along the riverside would screen the majority of the substation GIS building and external equipment, external equipment relating to the converter station and part of the converter station building in some views looking north, east, and southeast. Three public receptors would experience a minor adverse to neutral significance of effect on views following mitigation and 15 years’ establishment, including PRoW west of Cliffs End (receptor 1.7c), Richborough Roman Fort (receptor 2.4) and Grinsell Hill 254 and other rural lanes northeast of Minster and Cottington Road and Thorn Hill (receptor 3.5). All other public receptors would experience a neutral significance of effect on views following mitigation and 15 years establishment. New tree planting to the site perimeter (part of the wider Richborough Energy Park estate road works) and new tree and shrub planting along part of the western site boundary, in addition to existing intervening vegetation in the view, would screen the majority of the substation development and external equipment associated with the converter station, resulting in views of the upper part of the converter station building only. Generally these views would not be different to existing views and some aspects of the views would improve. 10.140 The greatest residual effects anticipated on private receptors, following mitigation and 15 years’ establishment would be minor adverse to neutral and relates to views from five receptors: Ebbsfleet Farm (A2a), No.1 Ebbsfleet Farm Cottages (A2b), Castle Road, Richborough (A7), Minster and the surrounds (A11), and Wayside Caravan Park, Minster (C9). The significance of residual effects of the Proposed Development on all other private views following the establishment of planting mitigation measures would be neutral. Although it would be difficult to screen the development entirely from these viewpoints, new tree and shrub planting to the site perimeter would screen the majority of the substation development and external equipment associated with the converter station, resulting in views of the upper part of the converter station building only, which would not be discernibly different to existing views. 10.141 Table 10.7 overleaf summarises the anticipated residual visual effects on each identified receptor following 15 years’ establishment post mitigation, alongside the visual effects on completion of the Proposed Development previously identified. 255 Table 10.7: Summary of Anticipated Residual Visual Effects Visual Receptor Significance of Visual Effect On Completion Significance of Visual Effect – with mitigation and after approximately 15 years Effects on Views from Public Rights of Way 1.1a Saxon Shore Way at Former Richborough Power Station Moderate adverse Moderate to Minor adverse 1.1b Saxon Shore Way near Roman Fort Neutral Neutral 1.1c Saxon Shore Way at Boxlees Hill (south of Minster) including footpath connections south of Marsh Farm Road Neutral Neutral 1.1d Saxon Shore Way at Plucks Gutter Neutral Neutral 1.1e Saxon Shore Way at Royal St George’s Golf Club Neutral Neutral 1.2a Stour Valley Walk at Sandwich Flats/Prince’s Golf Links Neutral Neutral 1.2b Short section of Stour Valley Walk at Cooper Street Neutral Neutral 1.3a Thanet Coastal Path at Pegwell Bay Country Park Minor adverse Neutral 1.3b Thanet Coastal Path between Cliffs End and the edge of Ramsgate Neutral Neutral 1.4 PROW at Potts Farm Drove Neutral Neutral 1.5 PROW at Goldstone Drove (and PROW which runs parallel 0.2km to the west) Neutral Neutral 1.6 PROW at Westmarsh Drove (and PROW which runs broadly parallel to the east) Neutral Neutral 1.7a &b PROW network east of Minster Neutral Neutral 1.7c PROW west of Cliffs End Minor adverse Minor adverse to Neutral 1.8 PROW southwest of Minster Neutral Neutral 1.9a PROW south of Manston/Manston Road Neutral Neutral 1.9b PROW south of Nethercourt (Chalk Hill) also Sustrans Regional Route 15 Neutral Neutral 1.10 Network of PROW around Monkton Marshes/Docker Hill Neutral Neutral 256 Visual Receptor Significance of Visual Effect On Completion 1.11 PROW between Brookestreet Farm and East Street Neutral Significance of Visual Effect – with mitigation and after approximately 15 years Neutral 1.12 PROW north of Monkton/Minster Neutral Neutral Effects on Views from Public Open Space and Outdoor Tourist Attractions 2.1 Pegwell Bay Country Park Minor adverse Neutral 2.2 Stonelees Nature Reserve Minor adverse Neutral 2.3 St Augustine’s Cross Neutral Neutral 2.4 Richborough Roman Fort Minor adverse Minor adverse to Neutral 2.5 Richborough Roman Amphitheatre Neutral Neutral 2.6 Pegwell Bay picnic area and beach Neutral Neutral 2.7 Sandwich boat trips up River Stour Moderate adverse Moderate to Minor adverse 2.8 Sandwich boat trips to Pegwell Bay Neutral Neutral 2.9 West Cliff, Ramsgate Neutral Neutral Effects of Views from Roads and Rail 3.1 Old A256 Sandwich Road (north of converter a station and substation site, including site entrance) also Sustrans Regional Route 15 Neutral (Minor adverse for footpath and cycleway users) Neutral 3.1 New A256 bypass (East Kent Access Road b Phase 2) Neutral Neutral 3.1 A256 Ramsgate Road (south of converter station c and substation site) also Sustrans Regional Route 15 Neutral Neutral 3.2 Ebbsfleet Lane (north and south of new A256 bypass) Neutral Neutral 3.3 Marsh Farm Road (rural lane south of Minster) Neutral Neutral 3.4 Richborough Road between Roman Amphitheatre and Roman Fort Neutral Neutral 3.5 Grinsell Hill and other rural lanes northeast of Minster and Cottington Road and Thorne Hill (Sustrans Regional Route 15) Minor adverse Minor adverse to Neutral 3.6 Pegwell Road, Ramsgate Neutral Neutral 3.7 A299 Canterbury Road West between Mount Pleasant and Ramsgate Neutral Neutral 3.8 A256 Haine Road (on western side of Ramsgate, north of intersection with A299) Neutral Neutral 257 Visual Receptor Significance of Visual Effect On Completion 3.9 Other minor roads south of River Stour Neutral Significance of Visual Effect – with mitigation and after approximately 15 years Neutral 3.1 Manston Road (either side of A256) 0 Neutral Neutral 3.1 A299 Canterbury Road West (between Monkton 1 roundabout and Mount Pleasant) including the footpath and cycleway to the south Neutral Neutral 3.1 A253 Island Road (Gore Street to Monkton 2 roundabout) Neutral Neutral 3.1 Minor road between Plucks Gutter and Gore 3 Street Neutral Neutral 3.1 A28 Canterbury Road at St Nicholas at Wade 4 Neutral Neutral 3.1 Railway line from Ramsgate to Minster 5 Neutral Neutral 3.1 Railway line from Minster to Sandwich 6 Neutral Neutral 3.1 Railway line west of Minster (along Stour Valley) 7 Neutral Neutral Effects on Views from Private Residences A1 Houses on Ebbsfleet Lane near the junction with Sandwich Road (old A256) Minor adverse Neutral A2 Ebbsfleet Farm a Minor adverse Minor adverse to Neutral A2 No. 1 Ebbsfleet Farm Cottages on Ebbsfleet b Lane Minor adverse Minor adverse to Neutral A3 House between industrial units on Ramsgate Road (A256) Minor adverse Neutral A4 Houses at Sevenscore a Neutral Neutral A4 Houses at/near Thorne Farm b Minor adverse Neutral A5 Houses on Whitehouse Drove Neutral Neutral A6 Cliffs End (south of railway line) a Neutral Neutral A6 Cliffs End (north of railway line) b Neutral Neutral A7 Castle Road, Richborough Minor adverse Minor adverse to Neutral A8 Houses on Rubery Drove Neutral Neutral 258 Visual Receptor Significance of Visual Effect On Completion A9 House west of Richborough Farm Neutral Significance of Visual Effect – with mitigation and after approximately 15 years Neutral A1 Houses near Guston Farm, Potts Farm and0Lower Goldstone Neutral Neutral A1 Minster and surrounds 1 Minor adverse Minor adverse to Neutral A1 House at Little Cliffsend Farm and Coastguard 2 Cottages Neutral Neutral A1 Nethercourt, Ramsgate 3 Neutral Neutral A1 Pegwell, Ramsgate 4 Neutral Neutral A1 Houses at Hoo 5 Neutral Neutral A1 Stanner Court residential tower block and new6housing development on Manston Road, Ramsgate Neutral Neutral A1 East Stourmouth and surrounds 7 Neutral Neutral A1 Sandwich 8 Neutral Neutral A1 Sarre 9 Neutral Neutral A2 Upstreet 0 Neutral Neutral A2 East Street 1 Neutral Neutral A2 St Nicholas at Wade 2 Neutral Neutral Effects on Views from Private Golf Courses and Sports Facilities B1 Stonelees Golf Centre Neutral Neutral B2 St Augustine’s Golf Club Neutral Neutral B3 Manston Golf Centre near Ramsgate Neutral Neutral B4 Prince’s Golf Links near Ramsgate Neutral Neutral B5 Royal St George’s Golf Club near Sandwich Neutral Neutral B6 BayPoint sports complex Neutral Neutral Effects on Views from Private Businesses 259 Visual Receptor Significance of Visual Effect On Completion C1 Businesses and industrial units near the site entrance and to the south of the converter station and substation site on the A256 Ramsgate Road Neutral Significance of Visual Effect – with mitigation and after approximately 15 years Neutral C2 BayPoint sports complex (Great Stonar) Neutral Neutral C3 a The Sportsman Inn Public House, old A256 Sandwich Road Neutral Neutral C3 b Pegwell Bay Service Station, Sandwich Road Neutral Neutral C4 Pegwell Bay Hotel, Pegwell Road Neutral Neutral C5 The Sir Stanley Gray and Belle Vue Public Houses, Pegwell Road Neutral Neutral C6 Lord of the Manor Public House off A299 Neutral Neutral C7 Industrial Park, Laundry Road, Minster Neutral Neutral C8 Holiday Inn and Premier Inn, Minster Minor adverse Neutral C9 Wayside Caravan Park, Minster Minor adverse Minor adverse to Neutral C1 0 Sarre Windmill Neutral Neutral Cumulative Impacts 10.142 Potential cumulative effects on landscape and views from the onshore elements of the Nemo Link in combination with other components of the Project (i.e. UK, French and Belgian subsea cables and Belgian onshore infrastructure) are described in Chapter 16. 10.143 Potential cumulative effects of the Nemo Link UK onshore infrastructure in combination with the grid connection required to facilitate the operation of the Nemo Link are described in Chapter 17. 10.144 The converter station and substation site falls within the wider Richborough Energy Park, which occupies the site of the former Richborough power station. Consideration has been given to other Richborough Energy Park proposals that require planning permission, listed below: 1 2 Estate road and structural planting around the perimeter of the former Richborough Power Station; and Richborough Peaking Plant Facility to the south of the proposed converter station. 10.145 Other proposals, at different stages of the planning process, exist in the site’s context. These proposals include; a Materials Recycling Facility (with planning permission) proposed south of the converter station and substation site; a flood defence scheme in the vicinity of the proposed underground cable route at Pegwell 260 Bay (with planning permission); glasshouses, rainwater storage tanks and a pack house at Ebbsfleet Lane, north-east of the converter station and substation site (awaiting a planning decision); and a proposal for a 5MW solar farm on land west of the converter station and substation site, not yet submitted for planning permission. Table 1.2 of Chapter 1 provides full details of other unrelated projects subject to the cumulative assessment below. 10.146 The following paragraphs consider the cumulative effect of the proposed converter station, substation and underground and overground cable on completion (with mitigation and after establishment), in combination with each of the six development proposals referred to above. Richborough A Ltd Estate Road and Structural Planting (awaiting planning decision) 10.147 The new estate road will comprise new concrete hardstanding around the perimeter of the former Richborough power station site, partial removal of trees along the eastern, north eastern and northern boundaries of the former power station site and new planting to the site perimeter. Residual landscape and visual effects (with mitigation and following establishment) recorded above in relation to the proposed converter station and substation includes consideration of new planting associated with the new estate road. 10.148 There will be no temporary construction effects on landscape and views as the estate road will be constructed before construction works commence in relation to the proposed converter station, substation and underground cable works. 10.149 The new road and proposed converter station and substation would be concentrated within the former Richborough power station site and new tree planting will partly mitigate for tree loss resulting from the new road. Cumulative residual effects on landscape character (with mitigation and after establishment) would be minor adverse to neutral, as recorded in relation to the proposed converter station and substation. 10.150 There will be cumulative effects on views from receptors in close proximity to the site, including the Saxon Shore Way and River Stour to the northwest, west and south of the converter station and substation site, and from the A256 to the east (including motorists and footpath and cycleway users). Concrete hardstanding and site traffic would be visible from these receptors along with the converter station and substation and associated outdoor equipment. Tree removal on the eastern boundary will increase the extent of both developments visible in the view from the A256. New tree and shrub planting along the eastern boundary and at the site entrance will provide some filtering and screening of site traffic using the new road and the converter station and substation proposals, particularly as planting matures overtime. 10.151 Southerly views of site traffic on the new road are anticipated to be glimpsed at most (in front of the proposed converter station and substation development) between intervening trees and above intervening scrub vegetation. Oblique views from the rear garden belonging to a residential property to the south between industrial units on the A256 are anticipated of both the new road and Proposed Development. However tree and shrub planting proposed to the western site boundary would mature overtime, partly filtering and screening the substation GIS building and outdoor substation elements. 261 10.152 The significance of cumulative residual visual effects (with mitigation and after establishment) will be no greater than recorded for the proposed converter station and substation, including new planting associated with the estate road and the converter station site. Cumulative residual visual effects will range between moderate to minor adverse and neutral for receptors in close proximity to the site. Cumulative residual effects are not anticipated at greater distances and on low lying ground due to screening of the new road by intervening vegetation and development. Richborough Peaking Plant Facility, South of the Proposed Converter Station (awaiting planning decision) 10.153 The Peaking Plant Facility will occupy an area of approximately 1.13 hectares compared to over 7 hectares occupied by the proposed converter station and substation site. The Peaking Plant will comprise fifty three diesel fired generators (approximately 2.6m high) and four chimney stacks (approximately 35m high) with associated fuel storage, parking and access. A 4m high fence will secure the site perimeter and a 3m high acoustic barrier will be installed around the facility beyond site planting. 10.154 Planting will comprise densely planted native trees, shrubs and fruit trees, (minimum 10m wide planting area) on the eastern and north eastern site boundary with the A256. Along the southern boundary (adjoining the site of the proposed Materials Recycling Facility discussed below) will be a mix of scattered trees within a minimum 5m wide planting area. Existing trees along the eastern and southern boundaries of the site will be retained where possible. Planting on the western site boundary with the River Stour will include densely planted shrub planting beneath existing overhead lines, and shrubs and or fruit trees adjacent. Planting around the proposed Peaking Plant Facility will provide partial filtering and screening of the proposed 3m high acoustic fence beyond proposed perimeter fencing. 10.155 There will be no temporary construction effects on landscape and views as the proposed Peaking Plant Facility will be constructed before construction works commence in relation to the proposed converter station, substation and underground (and overground) cable works. 10.156 The proposed Peaking Plant will be consistent with the character of the A256 coastal corridor between Ramsgate and Sandwich; the landscape has a low sensitivity to this type of change. The Peaking Plant chimney stacks will be the tallest component of both the Peaking Plant and the proposed converter station and substation; however, the proposed chimneys will be seen within the context of the 30.8m high converter station building. The scale and massing of the proposed Peaking Plant will result in a relatively small addition to the built form of the converter station located to the north. Cumulative residual effects (with mitigation and after establishment) on landscape character will be minor adverse to neutral, as recorded in relation to the proposed converter station and substation. 10.157 On completion there will be intervisibility between the proposed Peaking Plant and the proposed converter station and substation. However visual receptors will not be sensitive to cumulative visual effects as they will be workers at their workplace and both developments are industrial in character. 10.158 On completion views of the proposed converter station and substation in combination with the Peaking Plant Facility would extend across the approximate ZVI identified in Figure 10.2. However, in the majority of views within the ZVI, the 262 proposed converter station and substation, and the Peaking Plant at Richborough Energy Park, would form a very minor component of the view, which will be of the upper part of the converter station building and the top of Peaking Plant chimneys in some views set within a well vegetated and already industrial landscape. It is anticipated that visitors to Richborough Roman Fort and nearby residents, residents on Ebbsfleet Lane, and residents and the PROW network between Minster and Cliffs End will experience cumulative visual effects. In each case these views will be similar to existing views, and from some of these locations views are already restricted to an extent by built form and vegetation. 10.159 Residual cumulative visual effects will be experienced by a few sensitive visual receptors in closer proximity, particularly users of the Saxon Shore Way and river users to the immediate south of Richborough Energy Park. Overtime planting along the western boundary of the converter station site and proposed to the perimeter of the Peaking Plant Facility will mature reducing visibility of part of these developments, particularly from the Saxon Shore Way and River Stour. 10.160 Overall the cumulative residual visual effects (with mitigation and after establishment) of the proposed converter station and substation development with the Peaking Plant will be no greater than moderate to minor adverse. Materials Recycling Facility, South of the Proposed Converter Station Site (planning permission granted) 10.161 The proposed Materials Recycling Facility (MRF) comprises two sites south of the proposed converter station and substation site (and proposed Peaking Plant referred to above). Development proposed on Site A (south of the Stonar Cut) will comprise the replacement of the existing materials processing facility with an ‘Lshaped’ building (17.2m high) of a similar scale and appearance to the existing waste processing shed at the northern end of this site. The northern part of the site will remain as existing. 10.162 Development proposed on Site B (immediately south of the proposed Peaking Plant) will comprise the transfer of the existing materials processing facility from the southern part of Site A to the central part of Site B, and two new buildings to house an anaerobic digester plant (85m x 37m x 14.25m high) and a maturation shed (75m x 37m x 14.4m high). Other components include a staff and office building, a soil washing plant, and alterations to the site access road. 8 metre high steel sheet walling (similar to that used at Site A) is proposed to the Ramsgate Road frontage and at the northern and southern ends of the site. Vehicle parking, a weighbridge and wheel washing facilities will also be provided within the site. 10.163 Residual cumulative effects on landscape and views during construction are not anticipated as the proposed Materials Recycling Facility is likely to be constructed before the converter station and substation construction works commence. Should construction works be undertaken at the same time, cumulative landscape and visual effects will be concentrated in an existing industrial area adjacent the A256 and will be temporary, for a short period of time. 10.164 Development proposed within sites A and B above will relocate the existing materials processing facility within site A to site B further north on the A256, and will introduce new buildings to cleared brownfield land south of the proposed converter station and substation site. The MRF will develop an existing gap in development, on brownfield land, within the A256 corridor between Ramsgate and Sandwich, and will be of a similar type and character as existing adjacent development; the 263 landscape has a low sensitivity to this type of change. Cumulative residual effects (with mitigation and after establishment) on landscape character of the proposed Materials Recycling Facility and proposed converter station and substation will be minor adverse to neutral, as recorded in relation to the proposed converter station and substation. 10.165 On completion (with mitigation) there will be some intervisibility between the proposed MRF on site B, and the proposed converter station and substation. Views would also comprise the proposed Peaking Plant sited between these developments. Visual receptors will not be sensitive to cumulative visual effects as they will be workers at their workplace, surrounded by development of a similar industrial character. 10.166 On completion (with mitigation) there will be residual cumulative visual effects on motorists, pedestrians and cyclists along the A256, walkers along the Saxon Shore Way including near the Roman Fort, boat users on the River Stour, rail passengers on the Minster to Sandwich railway line, and residents living at the house on the A256 between industrial units. In general Proposed Development will be visible in a greater extent of some views than existing; however development will be similar in character to existing industry in the surrounding area. 10.167 The significance of cumulative residual visual effects (with mitigation and after establishment) will be no greater than recorded for the proposed converter station and substation. Cumulative residual visual effects will range between moderate to minor adverse and neutral for receptors in close proximity to the site. Cumulative residual effects are not anticipated at greater distances and on low lying ground due to screening of the new road by intervening vegetation and development. Pegwell Bay Flood Defence Scheme (planning permission granted) 10.168 The proposed flood defence scheme (along the Pegwell Bay coastline where the flood defences are at their lowest elevation) will comprise two new flood defence elements; a new concrete flood wall (141 metres long and up to 1.2 metres high) to the north of the petrol station on the A256; and an earth embankment (257 metres long and up to 1 metre high) to the south of the petrol station. 10.169 No temporary cumulative effects on landscape and views are anticipated as the flood defence works will likely be completed before cable installation works start in the vicinity of flood defence works. 10.170 On completion and following reinstatement works, there will be no cumulative residual effects on landscape and views where the cable is proposed underground. Where the cable route is proposed overground and capped with chalk (approximately 1m high), cumulative residual effects on landscape and views will be neutral. Raised ground and tree removal within the northern part of Pegwell Bay Country Park to accommodate the proposed cable route will be seen within the context of the proposed flood defence, (comprising an earth embankment up to 1 metre high in this locality) from Pegwell Bay including part of the Thanet Coastal Path (1.3a) and the A256 (3.1a). 10.171 Residual cumulative effects on landscape and views on completion of the proposed flood defence scheme and the proposed converter station will also be neutral where the top of the converter station is visible above intervening trees in combination with the flood defence scheme from Pegwell Bay. 264 Erection of Glasshouses, Water Storage Tanks and Pack House (awaiting planning decision) 10.172 A planning application has been submitted for glasshouses (4.7m high to the apex), three rainwater storage tanks (3.04m above ground) and a pack house (5.52 metres to ridge height) for the grading and packing of roses, storage of equipment and to provide staff facilities at Ebbsfleet Lane. This application site is northeast of the proposed converter station and substation site. 10.173 Temporary cumulative effects on landscape and views during construction are not anticipated as proposed glasshouses, water storage tanks and pack house will likely be constructed before converter station and substation construction works and cable installation works commence. 10.174 On completion residual cumulative effects (with mitigation) on landscape will be minor adverse to neutral, as recorded in relation to the proposed converter station and substation development. Proposed Developments will be consistent with the character of the A256 coastal corridor between Ramsgate and Sandwich, which comprises industrial and agricultural development and includes the larger scale anaerobic digester being built on the opposite side of the new A256 bypass to the glasshouse site, and existing solar farms; one adjacent the proposed glasshouse site and the other west of the new A256 bypass between the wastewater treatment works and the anaerobic digester. 10.175 Residual cumulative effects are anticipated in views from receptors including: Houses on Ebbsfleet Lane near the junction with the old A256 Sandwich Road looking west (A1); Ebbsfleet Farm looking southwards (A2a); No. 1 Ebbsfleet Farm Cottages on Ebbsfleet Lane looking southwards (A2b); Stonelees Golf Centre looking southwest (B1); New A256 bypass looking southwards (3.1b); and Ebbsfleet Lane, where not screened by intervening roadside hedgerow (3.2). 10.176 Cumulative residual visual effects (with mitigation and after establishment) will be no greater than effects recorded in relation to the proposed converter station and substation on completion (with mitigation), ranging from minor adverse to neutral (recorded for Ebbsfleet Farm and No.1 Ebbsfleet Farm Cottages), to neutral effects for visual receptors closest to both sites. Overtime new tree planting along the new A256 bypass will mature. Solar Farm on the ‘Banana Land’ West of the River Stour (planning application not yet submitted) 10.177 A 5MW solar farm is proposed across approximately 13.68 hectares of land to the west of the River Stour, (referred to as the ‘Banana Land’) compared to over 7 hectares occupied by the proposed converter station and substation site. 10.178 Residual cumulative effects on landscape and views during construction are not anticipated as the proposed solar farm will likely be built before construction works start in relation to the proposed converter station and substation. 10.179 On completion (with mitigation and after establishment) residual cumulative effects on landscape will result in a slightly greater adverse effect than reported for the 265 proposed converter station and substation in isolation, but no greater than minor adverse overall. The proposed solar farm will introduce rows of photovoltaic panels to open grazing land in the Ash Levels landscape character area, on the opposite side of the River Stour to the proposed converter station and substation site. The proposed solar farm site is within the context of existing solar farms to the northwest (west and east of the new A256 bypass) and would be seen in the context of existing larger scale development (including the windfarm substation south of the former power station site, overhead lines, a wind turbine and adjacent masts and industrial units on the A256) so as to appear as part of the industrial corridor in this locality. 10.180 Minor adverse residual cumulative effects on landscape are considered to be temporary as the proposed solar farm site can be returned to grazing land following cessation of the solar farm. 10.181 On completion, there will be intervisibility between the proposed converter station and substation and the solar farm west of the River Stour. However visual receptors will not be sensitive to cumulative visual effects as they will be workers at their workplace in an area characterised by industry. Existing solar farms are also visible in the sites’ surroundings when travelling along the new A256 bypass. 10.182 Residual cumulative effects are anticipated in views from receptors including: Saxon Shore Way; River Stour; the A256 (Ramsgate Road); and Railway line between Minister and Sandwich. 10.183 A slightly greater adverse magnitude of effect is anticipated on walkers along the Saxon Shore Way and boat users along the River Stour as the solar farm will restrict some views across previously open grazing land within the context of the converter station and substation site. The significance of cumulative residual visual effects on these receptors adjacent and in the vicinity of the solar farm and converter station and substation site will be no greater than moderate adverse. 10.184 Other cumulative residual visual effects are anticipated to be no greater than effects recorded in relation to the proposed converter station and substation, ranging from moderate to minor adverse effects for a small number of visual receptors closest to the site to neutral or no effects on other identified visual receptors. Cumulative Effect of all Above Developments 10.185 The significance of residual cumulative effects on landscape character and on views of the proposed converter station and substation in combination with all six development proposals (excluding the solar farm) is considered as being no greater than residual effects (with mitigation and after establishment) recorded in relation to the proposed converter station and substation. Upon completion (with mitigation and after establishment) residual cumulative effects of the solar farm on landscape will result in a slightly greater adverse effect than reported for the proposed converter station and substation in isolation, but no greater than minor adverse overall. Development proposals will increase the extent of development in the area; however the scale of Proposed Developments will be smaller than the proposed converter station and substation buildings, and proposals are sited within an area already affected by the derelict turbine hall at the former Richborough power station 266 site, a wind turbine and associated masts; electricity overhead lines, industrial units on the A256 (Ramsgate Road), Pfizer development, Weatherlees Hill Wastewater Works, an aerobic digester, and a solar farm to the east and west of the new A256 bypass. 10.186 Residual effects on landscape character (with mitigation) will be minor adverse to neutral and residual visual effects (with mitigation) will range between moderate to minor adverse and neutral. Walkers along the Saxon Shore Way and boat users on the River Stour would experience the most significant visual effects of moderate to minor adverse. 267 268 11.0 TRAFFIC AND TRANSPORT Introduction 11.1 This chapter assesses the potential construction and operation traffic and transport related impacts of the Proposed Development (i.e. the UK onshore elements of the Nemo Link (see Chapter 2 Project Description). 11.2 The topics listed below are discussed in detail within this chapter: Relevant transport and environmental policy; Description of proposed access routes and arrangements; Types, volumes and timings of vehicles accessing the site during construction and operation; The likely significance of environmental effects; The likely environmental impacts of the vehicles accessing the site; and Measures to be undertaken to mitigate against environmental impacts. Legislation and Planning Policy Guidance 11.3 The following relevant national and local planning policy and legislation have been considered during the preparation of this assessment: National Traffic Management Act 2004; and National Planning Policy Framework 2012. Local 11.4 In addition, this chapter has been produced in line with the Design Manual for Roads and Bridges (DMRB), Volume 11 taking into account UK legislation with regard to Environmental Impact Assessment (EIA) regulations, namely: 11.5 Kent Local Transport Plan 3 2011-2016. Section 105 of the Highways Act 1980, as amended by the Highways (Assessment of Environmental Effects) Regulations 1988; The Highways (Assessment of Environmental Effects) Regulations 1994 and 1999; and The Highways (Environmental Impact Assessment) Regulations 2007. Other relevant guidance used in the production of this assessment includes: Guidance on Transport Assessment” Department for Transport, 2007; “Guidelines for the Environmental Assessment of Road Traffic” Institute of Environmental Assessment (IEA) 1993. (Now known as the Institute of Environmental Management and Assessment (IEMA)); and Design Bulletin 32 (1992), Appendix 2: Passing places on narrowed carriageways. 269 Method 11.6 The need for an Environmental Assessment of the transport related implications of the Proposed Development is highlighted in several documents and guidance notes. The Department for Transport’s (DFT’s) document, “Guidance on Transport Assessments” (2007), states: “The environmental impacts of any significant development need to be addressed. This might include it being covered by a separate Environmental Statement (ES), which involves an assessment of a development’s potential environmental implications, including those that are transport related. This will help ensure the impacts and the scope for mitigating them are properly addressed.” 11.7 The above guidance precedes a key document called “Guidelines for the Environmental Assessment of Road Traffic” produced by the Institute of Environmental Assessment, (1993). This follows a Government White Paper on The Environment in September 1990. The White Paper was a reflection of the growing concern amongst the general public, business and government that the environment needed to be protected. 11.8 The basic principles for environmental assessment originated with Directive 337, issued by the European Community in 1985. These were confirmed in the regulations published by the Department of the Environment in 1988. 11.9 These regulations were amended into highways legislation through the Highways (Assessment of Environmental Effects) Regulations 1999 which were amended in 2007. Assessment of Significance 11.10 Quantifying the environmental impact of traffic from a Proposed Development depends on several key factors. In this instance the main factors influencing the significance of the impact relate to the magnitude of change, (taking into account the time frame of change) and the number, and sensitivity of any receptors in the area of interest. Once the significance of the impact is understood then the correct level of assessment can be undertaken, and mitigation can be considered where necessary. 11.11 This is described within the Design Manual for Roads and Bridges (DMRB) Volume 11, Section 2, Part 5 (2008), which states: “The significance of the effect is formulated as a function of the receptor or resource environmental value (or sensitivity) and the magnitude of project impact (change). “ “The approach to assigning significance of effect relies on reasoned argument, professional judgement and taking on board the advice and views of appropriate organisations.” 11.12 The DMRB Volume 11, Section 2, Part 5 (2008) sets out a table for helping to define the significance of change. This has been included below. 270 Table 11.1: Determining the Significance of Effects Environmental Value (Sensitivity) Magnitude of Impact (Degree of Change) No Change Negligible Minor Moderate Major Very High Neutral Slight Moderate or Large Large or Very Large Very Large High Neutral Slight Slight or Moderate Moderate or Large Large or Very Large Medium Neutral Neutral or Slight Slight Moderate Moderate or Large Low Neutral Neutral or Slight Neutral or Slight Slight Slight or Moderate Negligible Neutral Neutral Neutral or Slight Neutral or Slight Slight Percentage Increases in Traffic 11.13 The IEA document “Guidelines for the Environmental Assessment of Road Traffic” states that the following criteria should be adopted to determine the need for environmental assessment of traffic impacts associated with a development: “Include highway links where traffic flows will increase by more than 30% (or the number of heavy goods vehicles will increase by more than 30%); and Include any other specifically sensitive areas where traffic flows have increased by 10%, or more.” 11.14 Increases in traffic flows of less than 10% have a negligible impact as daily variance in traffic flows can be of equal magnitude. This is again stated within the IEA document. 11.15 The 30% threshold relates to the level at which humans may perceive change and there may therefore be an effect. Impacts above this level therefore do not suggest that there is a significant impact, only that further consideration is required. 11.16 In this instance the site is located off key primary routes with direct links to the wider highway and motorway network. Therefore the scope of this assessment includes these key links that will be used to transport plant and material to the site. 11.17 The construction and operation impacts of the development are discussed separately. 271 Existing Environment 11.18 To understand and quantify the future impacts of the Proposed Development, an assessment of existing local highway characteristics and trends has been undertaken. 11.19 The nature of the highways likely to be affected, the proximity of any residential dwellings or receptors to the proposed construction traffic route, the local highway accident record and the existing traffic levels on key links have been considered. East Kent Access Road 11.20 Over the past number of years a number of significant highway projects have been carried out in the vicinity of the site including the A256 and the Richborough Roundabout. These works formed the East Kent Access Phase 1 & 2 which is briefly discussed below. 11.21 The East Kent Access Road Phase 1 involved the improvement of the A256 from the Richborough Roundabout south to the Sandwich bypass and also included a link road around the south side of the BayPoint sports complex. 11.22 To the south of the upgraded Phase 1 section, the A256 Ramsgate Road continues as a single carriageway towards Sandwich, while to the south of Sandwich, the A256 forms a junction with the A2 at Dover. 11.23 As part of the improvement scheme works started in the 1980s, the A256 was developed into a dual-carriageway and improved pedestrian, cycle and lighting facilities were introduced. 11.24 As part of Phase 2, improvements have been undertaken along the A256 from the Richborough Roundabout to a new roundabout located 400m to the north at Ebbsfleet Lane. 11.25 Ebbsfleet Lane now forms two separately accessible sections, at A256 Sandwich Road, and Grinsell Hill/Cottington Road. The road then continues north-east to bridge Cottington Road and an adjacent railway line, before forming a new four-arm roundabout approximately 400m north of Cottington Road (known as Sevenscore Roundabout). 11.26 At Sevenscore Roundabout, the western arm is a single-carriageway link road which provides access to residential properties via Cottington Road. The northern arm of Sevenscore Roundabout continues northwards to connect to the A299 Canterbury Road West via a further three-arm roundabout (known as Cliffsend Roundabout). 11.27 From here a new 8km, dual-carriageway link has been provided from the new roundabout north to the A299. A key feature of this link is an underpass beneath Foads Hill and a local railway line. 11.28 The purpose of the scheme is to improve accessibility and safety as well as support the economy of east Kent connecting the ports of Dover and Ramsgate with Kent International Airport. The East Kent Link Phase 2 opened in early 2012. 11.29 A plan showing the highways works in the vicinity of the site has been included as Figure 11.1. 272 A256 Sandwich Road 11.30 The A256 Sandwich Road was previously the primary north-south route through Cliffsend prior to the completion of Phase 2 of the East Kent Link. Sandwich Road is a single carriageway, with one lane in each direction. The road extends from the Lord of the Manor Roundabout to the north, passing through the Cliffsend residential area and forming one arm of the new Ebbsfleet Roundabout to the south. 11.31 The Lord of the Manor Roundabout has recently been remodelled as part of the Stage 2 works, and now forms a large signalised junction linking the A299 Canterbury Road West, the A256 Haine Road, the A299 Canterbury Road East, and the A256 Sandwich Road. 11.32 Sandwich Road between Cliffsend Road and Foads Lane is predominately a residential area forming part of Cliffsend. To the south of the junction with Foads Lane, there is a service station located on the south-eastern side of Sandwich Road. A traffic calming measure which reduces the carriageway to one lane, giving priority to traffic travelling northbound, has recently been installed immediately south of this service station, as well as an additional installation to the north of Cliffsend, between Cliffs End Road and Chalk Hill. This is to encourage non-access traffic to use the new A256 to the west of Cliffs End, for routeing between Ramsgate and Sandwich. 11.33 To the south of Cliffsend, Sandwich Road is more rural in character. The 1.2km section between Cliffsend and the Ebbsfleet Roundabout provides access to Pegwell Bay Country Park and a priority junction at Ebbsfleet Lane. Otherwise, this section of the road is fronted by Stonelees Golf Centre on the north-western side, and by Pegwell Bay Country Park on the southern side. A299 11.34 The A299 Canterbury Road West connects to the new A256 link road to the north of the proposed Interconnector site, and the M2 to the west, and is a primary distributor link in the area. The route begins at Junction 7 of the M2 motorway, and follows an alignment past Chestfield, Herne Bay, Hawthorne, St-Nicolas-at-Wade and Manston Airport, and forms a roundabout junction with Royal Harbour Approach to the west of Ramsgate, across a distance of approximately 35 miles. 11.35 The A299 is comprised of Canterbury Road West, and Canterbury Road East. Canterbury Road West is a single carriageway road, which connects the Minster Roundabout to the Lord of the Manor roundabout. The road is predominantly rural, being mostly bound by open land. 11.36 At the double-roundabout junction with Haine Road and Sandwich Road the A299 continues eastwards along Canterbury Road East for approximately 750m and connects to a four-arm roundabout with Windermere Avenue and Royal Harbour Approach (known as the Royal Harbour Roundabout). Existing Traffic Flows 11.37 Both the A256 and the A299 are designated as primary routes connecting to the national road network and as such carry large volumes of traffic. 273 11.38 Annual Average Daily Traffic (AADT) flows have been obtained for the key links to be used for access to and from the development during construction. These include the following: A299 West Canterbury Road; A256 Richborough Road adjacent to the Interconnector site; A256 Dover Road to the south of the site; and Sandwich Road close to the Pegwell Country Park. Table 11.2: Existing Traffic Flows Location AADT % HGVs A299 West Canterbury Road A256 Richborough Road A256 Dover Road Sandwich Road 23,994 20,053 10,756 6,779 6% 4% 4% 4% Personal Injury Accidents 11.39 An analysis of personal injury accident data has been undertaken in the vicinity of the development to inform the baseline assessment of the local highway links. 11.40 Data was obtained for the following links: The A256 from the location of the new Ebbsfleet Roundabout, south to the A256 junction with Ash Road and the A257; A section of Sandwich Road through Cliffsend; and The A299 from the junction with A253/Minster Road/Tothill Street, to the location of the new junction with the A256. 11.41 As the East Kent Phase 2 link was not opened until May 2012 no accident data was available for the link. 11.42 Overall, the data contains 95 accidents within the study area in the 5 year period. These were comprised of 1 fatal accident, 10 serious accidents 84 slight accidents. 11.43 During the assessment work undertaken as part of the East Kent Phase 2 project it was identified that there was an unsatisfactory road safety record along the A256 and A299 through Cliffsend. This should be significantly improved due to the creation and opening of the new link road as through traffic will avoid built up areas and stick to primary routes designed for large volumes of traffic. 11.44 Overall, there were no correlations in the data to suggest that highway condition, layout or design were significant contributory factors in the pattern of accidents. The data instead suggests that pedestrian or driver behaviour were the primary contributory factors in the accidents recorded. 274 Public Transport Facilities 11.45 The converter station and substation site is close to a number of existing bus routes on the A526 Ramsgate Road. The nearest bus stops to the site are located on the section between the Richborough Roundabout and the roundabout at Ebbsfleet Lane constructed as part of East Kent Phase 2. The stops are situated adjacent to the petrol filling stations on both sides of the carriageway, and are therefore also in proximity to the site entrance. 11.46 Services 87, 88 and 88A all operate between Dover – Sandwich – Ramsgate, on Mondays to Saturdays only. Service 87 operates 5 times per day; service 88 operates between 5 and 10 times per day (school term time dependent); and service 88A operates up to 4 times per day (school term time only). Together, the three services provide an approximately hourly service between Dover and Ramsgate throughout the day. 11.47 Service 954 operates between Birchington-on-Sea and Sandwich, on school days only, passing the site at approximately 08:10 in the direction of Sandwich. 11.48 Accessing the site outside of network peak times will minimise disruption to the above services, as services are most frequent during morning and evening hours, when there are sometimes additional term-time services. Public Footpaths and Cycle Paths Cycle Routes 11.49 Regional Cycle Route 15 “The Viking Coastal Trail” is located in the vicinity of the site. The route has an extensive traffic-free section to the east of the site, following a coastal route parallel to Sandwich Road and Cliff’s End to the north-east of the site, and parallel to the A256 to the east of the site. The Viking Coastal Trail passes through Pegwell Bay Country Park which is located to the east of the site. 11.50 The section of the Viking Coastal Trail passing Cliffsend, parallel to Sandwich Road, exists as a shared footway/cycleway, which is surfaced in gravel and is approximately 3m to 3.5m wide. The section of the Trail passing through Pegwell Bay Country Park is also surfaced and is again approximately 3m to 3.5m wide within the Country Parkit crosses over the car park access with give way markings in place for cyclists. 11.51 To the south of Pegwell Bay Country Park, the Viking Coastal Trail bends and follows an alignment parallel to the A256 Ramsgate Road. This section of the Trail exists on a shared footway and cycleway, which is surfaced in asphalt, rather than the gravel surfacing used on the northern section. 11.52 There is also a cycle route between Cliffsend and St Nicolas-at-Wade, Minster and Sevenscore, which is also named as part of the Viking Coastal Trail. There is a short section of shared footway/cycleway on Foad’s Lane, at the junction with the A256 Sandwich Road, providing a connection to the coastal cycle track. The remainder of the route between Cliffsend and St Nicolas-at-Wade is on-street where cycles share space with general highway traffic. 275 Footpaths 11.53 There are a number of existing Public Rights of Way (PROWs) in the vicinity of the site. 11.54 Footpath TE39, a PROW, is located to the north of the site, and connects Ebbsfleet Farm to the south with a further footpath, TE37, to the north. Footpath TE37 is itself another PROW and exists parallel to a railway line which crosses Ebbsfleet Lane. 11.55 Footpath EE26 is located to the south-west of the site, parallel to the Great Sour River, on the northern side. The PROW exists between the water treatment works off of Marsh Farm Road to the west, and a (wind turbine) which is located to the west of the site. 11.56 Footpath EE42 is located close to the south-west of the site, however, the footpath is located parallel to the southern side of the Great Sour River, and is not accessible from the immediate vicinity of the site. 11.57 There are a number of footpaths through Pegwell Bay Country Park, which are not registered PROWs, but which nonetheless provide potential routes between the A256 and the coast, and which can be accessed from the park. The footpaths within the park also connect to Saxon Shore Way, which passes through the park using the same shared footway/cycleway as the Viking Coastal Trail cycle route. The Saxon Shore Way extends across a total distance of 160 miles, from Gravesend in North Kent, to Hastings in East Sussex. Potential Local Receptors 11.58 As the Proposed Development is located on the site of the former Richborough Power Station there are few receptors in close proximity. 11.59 The A526 which will provide access to the site is a key traffic link in the area and as such it is currently used by large volumes of traffic. Local Residential Dwellings 11.60 There are approximately seven residential dwellings, located close to the Ebbsfleet Roundabout with access of Ebbsfleet Lane and Sandwich Road. These are located around 100m from the new A256 and approximately 500m from the Proposed Development site. These properties are set back from the highway with large amounts of mature screening along the property boundaries. The Stonelees Golf Centre 11.61 The Stonelees Golf Centre is north of Ebbsfleet Lane approximately 700m from the site. Access to this facility is not from a primary highway link; access is from Ebbsfleet Lane off Sandwich Road. The old A256 Sandwich Road forms the facility’s eastern boundary as the golf centre extends away from the site towards Cliffsend. Pegwell Bay Country Park 11.62 Pegwell Bay Country Park covers an area of approximately 29 hectares, and is open from 9am or dusk, to 9pm. The park is located within Sandwich and Pegwell Bay National Nature Reserve, which covers an area totalling 628 hectares adjacent 276 to the coast. The Country Park is within the western part of the National Nature Reserve (NNR), with the A256 Sandwich Road forming part of the western boundary for the NNR. 11.63 Natural England’s website gives the following description of the NNR: “Natural habitats include; eroding chalk cliffs and wave cut platforms to the north of Pegwell Bay, intertidal mudflats, developing beaches, sand dunes and saltmarsh. Semi-natural habitats include; ancient dune pasture and coastal scrubland while the re-created grassland of the Pegwell Bay Country Park, along with ponds, dykes and ditches are artificial habitats. The intertidal mudflats support nationally and internationally important numbers of waders and wildfowl, both on migration and over-winter. The sand dunes and ancient dune pasture contain large numbers of southern marsh orchid, marsh helleborine, pyramidal orchid and the occasional lizard orchid.” 11.64 The primary part of the NNR which could be affected would be the area comprising Pegwell Bay Country Park, specifically around the existing traffic-free cycle route (Viking Coastal Trail), under which the interconnector cable would be laid. This is a small area of the overall NNR, and is close to the area’s boundary, being adjacent to an existing highway, the A256. Prediction and Assessment of Significance of Potential Impacts Construction Methodology Converter Station and Substation Construction 11.65 The converter station and substation will be on part of the site of the former Richborough Power Station. Access to the site will be from an existing vehicular access off the A256 at the Richborough Roundabout. 11.66 The Richborough Energy Park external estate road is subject to a recently submitted and pending planning application submitted by Richborough A Limited. Once constructed, this will enable access to the proposed converter station and substation site via the A256 Richborough Roundabout. 11.67 Before construction of the proposed converter station and substation can commence, re-profiling of the site is required which will involve the cutting and filling of material to ensure the site is suitable for construction to commence. 11.68 The re-profiling of the site could take up to 12 months to complete and will generate a number of heavy goods vehicle (HGV) movements associated with the removal of material from the site. 11.69 Both the converter station and the substation will require the delivery of large transformers, four for the converter station and two for the substation. It is proposed that these will be delivered to the site by road and are anticipated to arrive by sea at Dover. 11.70 These loads will constitute abnormal loads and the feasibility of delivery has been considered in detail in a separate study included as Appendix 11.1. 277 11.71 It is anticipated that the largest transformers will weigh up to 260 tonnes while others will weigh in the region of 183 tonnes. 11.72 All abnormal loads will be transported by specialist vehicles and haulage contractors. Investigations to date have indicated a number of routeing options to transport the transformers to the site. All construction traffic routeing has been discussed in detail within this chapter. 11.73 New internal access roads will be constructed to access the proposed development site and will allow the delivery of the transformers. Turning facilities for large vehicles and parking areas will also be provided. 11.74 It is anticipated that the Proposed Development will take approximately 36-42 months to complete and the site will be operational by October 2018. Onshore Cables Installation 11.75 The proposed route of the onshore cables is shown in Figures 2.1 and 2.5. The cables will be installed by open trenching; the surface will be cleared of trees, scrub and other vegetation prior to installation. 11.76 The trenches will be excavated by hydraulic excavators, except where it is proposed close to existing underground services where excavation will be done by hand. All excavated material will be stored on site for reinstatement following the introduction of the cables. The excavated material will be used to ensure that the profile of the trench is restored to the previous condition. Any unused excavated material will be removed from the site. 11.77 To the south of the Country Park there is an area of known contaminated land. Through this section the cables will be laid on top of the existing ground. A chalk capping layer will then be built up on top of the cables. This will enhance the vegetation and biodiversity of the interest of the Country Park and prevent the need to disturb contaminated ground and risk opening up potential contamination pathways during cable installation. 11.78 The cables will continue through the Country Park to the BayPoint sports complex where Horizontal Directional Drilling (HDD) will be used to install the cables beneath Minster Stream to the former Richborough Power Station site. This will also avoid any disturbance to the new East Kent Link Road which has been described in detail within this chapter. 11.79 During the laying of the cables a 10m – 15m working area will be required to construct the trench and lay the cables. A temporary compound area will be housed within the Country Park and will be used to deliver plant and materials required for laying the cables as well as storing equipment. This area utilises an existing vehicular access into the park and an area of vacant land adjacent to the access. This area is shown in Figures 11.3 and 2.5. 11.80 As part of the construction compound an area will be provided for vehicles to be able to turn within the site ensuring vehicles will be able to enter and exit the site in forward gear. A parking area for a small number of vehicles will be provided. 11.81 The laying of the onshore cables and associated works is anticipated to take approximately one to two months to complete. With regard to the phasing of the Proposed Development, the site preparation works will occur first, followed by the 278 construction of the site access roads. After these have been constructed the construction of the converter station and substation will begin. 11.82 The greatest number of vehicle movements is anticipated to occur at the start of the construction works. The anticipated volume of vehicles required during construction is detailed below. Development Trip Generation Construction Trips 11.83 These have been calculated for each of the four distinct phases of work as follows: Site Preparation Works; Site Access Road Construction; Converter Station and Substation Construction; and Cable Installation. 11.84 The total number of anticipated loads required for each phase of construction is provided. These have been divided by the number of months construction is due to occur and then divided by 20 to give an indication of the likely volume of loads, and therefore trips required to access the site per day. 11.85 To ensure a robust assessment, 70% of the total loads anticipated to occur during the construction of the converter station and the substation have been calculated to occur within a six month construction period. However, the anticipated overall construction period for the converter station and substation is approximately 24 months. 11.86 Table 11.3 below shows the anticipated peak number of HGV two-way trips associated with each phase of construction per month and per day. 11.87 It is likely a number of the anticipated plant, equipment and material deliveries will be by light goods vehicle (LGV), however, for this assessment all have been assumed to be by HGV. Table 11.3: Anticipated Two-Way HGV Trips Development Phase Total TwoWay HGV Trips Peak Two-Way HGV Trips per Month Peak Two-way HGV Trips per Day Site Preparations 5,417 903 45 Internal Access Road Construction 8,765 1,461 73 Converter Station and Substation Construction 8,425 982 49 HVDC Cable Installation 65 65 6 279 11.88 The above table indicates that during the peak phases of construction, a total of 73 two-way HGV trips will be generated per day. 11.89 In addition to the HGV deliveries anticipated during construction, it is envisaged that 30 two-way car trips and two bus/coach trips will be generated per day throughout construction associated with staff accessing/egressing the site. 11.90 It is difficult to ascertain the exact number of construction trips as this is dependent on the appointment of a contractor and any changes to the programme. Figures provided are considered to represent a reasonable worst case scenario. Operational Trips 11.91 Once constructed it is anticipated that the converter station will generate a small number of vehicular trips. These types of facilities are typically unmanned, however, if manned it is anticipated that six members of staff will be based at the site with two people working shifts over a 24 hour period. This would result in approximately 12 two-way trips per day. 11.92 It is anticipated that there could be in the region of 28 two-way maintenance trips per year. In some situations up to 20 members of staff may be present on site during maintenance and there may be a number of deliveries made by HGV. This may occur once or twice a year. 11.93 The substation will be unmanned. However, it will on average generate approximately four staff trips a week made by car or Light Goods Vehicle (LGV). Again a small number of trips may be generated during maintenance; however, this is anticipated to occur infrequently. Vehicle Routeing General Construction Traffic 11.94 It is anticipated that all vehicles will access the site via the primary highway routes in the region. These include the A256, the A299 the A2 and the M2. 11.95 Routeing agreements will be formally agreed with the construction contractor once appointed. A plan showing the proposed access routes for construction vehicles is included as Figure 11.2. 11.96 During the installation of the cables a small number of vehicles will be required to access Pegwell Bay Country Park. To do this they will have to leave the primary highway network and utilise the former A256 towards Cliffsend. It is anticipated that all access to this site will be via the Ebbsfleet Roundabout to avoid the residential areas of Cliffsend. 11.97 It is anticipated that only three HGVs will be required per day to access the park as well as a small number of cars/LGVs associated with staff undertaking the laying of the cables. Abnormal Vehicle Routeing 11.98 A separate assessment has been undertaken by to identify suitable routes to transport the required abnormal loads to the site. This has been included as Appendix 11.1. Investigations are currently on-going, however, the following route 280 has provisionally been suggested for the transportation of the transformers to the site: Leave Dover Docks complex; Join the A20 eastbound; From the A20 access the A2; Turn right onto the A256 and continue north to the site; and Exit the A256 at the Richborough Roundabout. 11.99 The movement of abnormal vehicles is controlled by The Motor Vehicles (Authorisation of Special Types) General Order 2003 and subject to management and prior agreement with the Police, Highways Agency and Kent County Council. 11.100 It is envisaged that all abnormal vehicles would be escorted by a pilot car and Police escort and be scheduled to travel during off-peak hours where possible. This would ensure the safety of other road users and result in minimal disruption. Construction Vehicle Impacts 11.101 To understand and quantify the future impacts of the Proposed Development a number of potential transport effects have been considered. Percentage Increase in Traffic 11.102 Total daily (all traffic), peak, two-way vehicle movements is likely to equate to 73 HGVs, 30 cars/LGVs and two bus movements during the construction programme. 11.103 It is only expected that 3 HGVs per day will be required to access the Country Park form the Old A256 Sandwich Road plus a small number of staff in either cars or LGVs. 11.104 Based on the existing traffic flows collected in the vicinity of the site, this would result in the following percentage increase on key highway links during peak construction activity. A256 Ramsgate Road - 0.5% increase in total traffic and a 9% increase in HGV traffic; A299 Canterbury Road West – 0.4% increase in total traffic and a 5% increase in HGVs; A256 Dover Road – 0.9% increase in total traffic and a 17% increase in HGVs; and Old A256 Sandwich Road – 0.3% increase in total traffic and a 1.1% increase in HGVs. 11.105 In each instance the percentage increase with regard to total traffic on each of the routes assessed is under 1%. 11.106 The highest percentage increase in daily traffic is calculated to be 17% along A256 Dover Road. In all other instances the percentage increase in HGV traffic would be under 10%. 11.107 To ensure a robust assessment, the above percentage impacts have been calculated assuming that all vehicles will use the same highway link to access the 281 site. In all likelihood, a number of key local links will be used throughout the construction period. 11.108 It is also commonly accepted that daily traffic flows can vary as much as 10%. As such, given the temporary nature of the increases plus the existing high daily traffic flows, the anticipated temporary increase in traffic is likely to be negligible. Noise 11.109 The anticipated noise that will be generated by the traffic accessing the site is expected to be negligible given the low percentage increase in vehicle volumes on the proposed access routes to the site and the volume of existing vehicles utilising the highway links. In addition, the scheduling of construction vehicles will ensure that noise associated with site traffic will not occur before 07.00 or after 19.00. Severance 11.110 Severance is the perceived division that can occur within a community when it becomes separated by a major traffic artery. In this instance, due to the low increase in daily traffic volumes and the low number of potentially sensitive receptors separated by the main transport links proposed to be used for construction traffic, the potential severance impacts associated with the development are considered to be negligible. Driver Delay 11.111 During the peak delivery period periods it is recognised that some small driver delay may occur as an increased number of vehicles turn into and out of the site onto the A256 Ramsgate Road. In addition, there may be some minor driver delay during the delivery of the large transformers required on-site. 11.112 Due to the temporary nature of the increase in vehicle movements and the low percentage increase in traffic the potential impacts on local road users is considered to be minor. Pedestrian and Cyclist Delay 11.113 Due to the low percentage increase in vehicles along the primary routes to be used to access the site, and the temporary nature of the development, it is anticipated that there will a negligible impact on pedestrians and cyclists crossing these links. 11.114 Furthermore there are signalised Toucan crossing facilities located across Sandwich Road close to where the cycle route leaves the Country Park and also across Ramsgate Road to the south of the Ebbsfleet Roundabout. 11.115 It is acknowledged that there will likely be some pedestrian and cyclist delay during the laying of the cables through the Country Park. 11.116 To access the working area from the temporary construction compound within the Country Park some vehicles may be required to cross over the cycle way in some instances to turn and exit the park, or to gain access to the cable laying working area. Where this occurs, it is envisaged that banks men with appropriate signage will stop any pedestrian or cycle traffic to allow a vehicle to manoeuvre and exit. 282 11.117 In addition, a small number of footpaths (approximately five) will have to be temporally closed for approximately one month while a section of the cable is laid. This may lead to pedestrians having to find alternative routes to travel through the park adding time to their journey. 11.118 The detailed route of the cables including where any footpaths will have to be temporarily closed is shown on Figure 11.3. 11.119 Given that it is anticipated that the laying of the cables through the Country Park will take approximately one month to complete, it is envisaged that any potential impacts with regard to pedestrian and cyclist delay will be minor. Fear and Intimidation 11.120 The scale, fear and intimidation experienced by receptors along the route is subjective and influenced by the volume and type of vehicle but also the level of protection available, such as having a property set back from the highway, or wide footways. 11.121 There are no identified sensitive receptors aligning the A256 and the new East Kent Phase 2 access road in the proximity of the site. 11.122 There are, however, a number of identified receptors along Sandwich Road leading to the Country Park. These include a small number of residential dwellings as well as the Stonelees Golf Centre and the Country Park itself. 11.123 In respect to the residential developments, these are set back from the highway with large amounts of mature screening in place between the properties and the highway. 11.124 There is also some significant screening between the Country Park and Sandwich Road, however, some traffic will be required to enter the Country Park during construction. This could result in impacts associated with fear and intimidation by pedestrians and cyclists within the park. 11.125 There are patches of screening between Sandwich Road and the golf course; however, for some small sections there is none. 11.126 Given the low volume of construction vehicles utilising this route and the short time frame over which access to the Country Park is required, minor impacts are anticipated during construction. Accidents and Safety 11.127 An analysis of personal injury accident data has been undertaken in the vicinity of the Proposed Development. 11.128 No correlations in the data suggest that highway condition, layout or design were significant contributory factors in the pattern of accidents. It is therefore considered that there is unlikely to be any increased risk of accidents along the proposed routes that vehicles will take to access the works. 283 Air Pollution 11.129 Due to the daily increase in total vehicles being relatively low compared to existing traffic flows and the short time frame of development, the level of pollution surrounding the development is not anticipated to materially change as a result of the development proposals. 11.130 A detailed assessment of the potential impacts of road traffic on air quality has been undertaken. This is included as Appendix 11.2. 11.131 The air quality assessment identified that the anticipated road traffic associated with the development will have a negligible impact on existing sensitive receptor locations. Therefore, it is not considered necessary to recommend measures to mitigate road traffic emissions. Dust and Dirt 11.132 It is possible that some dust and dirt may collect on the wheels and chassis of the vehicles making deliveries to the site. Without appropriate management, this could lead to some minor environmental impacts on the surrounding local highway network. Construction Vehicle Impact Conclusions 11.133 Given the number of vehicles that will use the identified delivery routes to access the works and the temporary nature of the traffic increase, it is considered that although there is the potential for some temporary minor adverse impacts, the majority of impacts associated with the development will be negligible. Operational Vehicle Impacts 11.134 Once operational the development is anticipated to generate minimal vehicle trips. As such, once constructed the impacts anticipated from the generated traffic are likely to be imperceptible and therefore negligible. Mitigation 11.135 A number of traffic management measures are proposed to minimise any potential effects of construction traffic accessing/egressing the site and the Country Park. 11.136 Construction traffic is of a temporary nature and as a result it would be inappropriate to provide permanent infrastructure as mitigation. 11.137 During construction, wheel washing facilities will be provided both at the main site entrance and also the vehicular entrance to the construction compound located at the Country Park. This will ensure mud/debris is not deposited on the surrounding carriageway. In addition, all HGVs will be covered and sheeted as appropriate. 11.138 Mitigation measures will also include the introduction of delivery management strategies to ensure that HGVs travel outside of peak periods where possible, avoid sensitive residential areas and stick to agreed routeing plans. 11.139 In addition, appropriate road signage will be provided as required; suitable signage will be placed within the Country Park to inform local users. 284 11.140 A number of additional mitigation measures will be introduced for abnormal load movements. These include: Police escorts and delivery programmes timed to cause minimal disruption; Vehicles will be marked as abnormal or long vehicles and where necessary temporary warning signs will be placed at required locations along the roads being used by site traffic; and It is also proposed to undertake a full condition survey before and after the delivery of any abnormal load. The condition of the carriageway will be reinstated to the same or better condition following the use of the route. 11.141 Details of the proposed mitigation strategy would be developed in detail during the preparation of a Transport Management Plan. Residual Impacts 11.142 It is anticipated that a number of potential minor environmental impacts would, following the introduction of the mitigation measures detailed above, result in negligible environmental impacts. 11.143 There are, however, likely to be a number of minor residual environmental impacts that cannot be fully mitigated. These primarily include those relating to pedestrian and cyclist delay. However, these impacts are only likely to be temporary during the construction works and are not associated with the operation of the proposed converter station and substation. 11.144 All anticipated environmental impacts are summarised in Table 11.4 and Table 11.5 below. . Table 11.4: Residual Construction Traffic Impacts Potential Impact Noise Significance of Impact Negligible Mitigation Measure Severance Negligible Driver Delay Minor Signage and Delivery Agreements - Timing and Routeing Negligible Pedestrian and Cyclist Delay Minor Signage and Delivery Agreements - Timing and Routeing Minor Fear and Intimidation Accidents and Safety Minor Suitable signage Minor Negligible Negligible Air Pollution Negligible Signage and Delivery Agreements - Timing and Routeing - Dust and Dirt Minor Wheel Washing and Vehicle Sheeting. Negligible Delivery Agreements - Timing and Routeing - 285 Residual Impact After Mitigation Negligible Negligible Negligible Table 11.5: Residual Operational Traffic Impacts Potential Impact Significance of Impact Mitigation Measure Residual Impact After Mitigation Noise Negligible None Necessary Negligible Severance Negligible None Necessary Negligible Driver Delay Negligible None Necessary Negligible Pedestrian and Cyclist Delay Negligible None Necessary Negligible Negligible None Necessary Negligible Negligible None Necessary Negligible Air Pollution Negligible None Necessary Negligible Dust and Dirt Negligible None Necessary Negligible Fear and Intimidation Accidents and Safety Cumulative Impacts 11.145 Potential cumulative effects on traffic and transport from the onshore elements of the Nemo Link in combination with other components of the Project (i.e. UK, French and Belgian subsea cables and Belgian onshore infrastructure) are described in Chapter 16. 11.146 Potential cumulative effects of the Proposed Development in combination with the connection required to facilitate the operation of the Nemo Link are described in Chapter 17. 11.147 A number of unrelated developments are proposed in proximity of the works subject to this planning application (see Table 1.2 in Chapter 1). These developments have been briefly discussed below including any potential cumulative traffic impacts. Richborough Energy Park Estate Road 11.148 A planning application has recently been submitted for a 2.60ha estate road network and structural/estate landscaping around the perimeter of the former Richborough Power Station site. The construction of the access roads and the Proposed Development will not occur simultaneously. 11.149 The scheme would be expected to improve access to the site during operation, and can therefore be viewed as a benefit to the Nemo Link scheme. Peaking Plant Facility 11.150 A planning application has recently been submitted for a facility which will be designed to provide top-up supply to the local electricity distribution network at short notice; for example, during periods of high electricity demand or low energy generation. This will comprise of 53 diesel fired generators, along with associated 286 fuel storage, parking and access, and will occupy an area of approximately 3.37 hectares. 11.151 It is possible that there may be some overlap in the construction of the peaking plant facility and the site preparation works for the proposed substation and converter station. The peaking plant facility is due to be operational in late 2014; some of the site substation and converter station site preparation works may have commenced at this time. As the construction of the peaking plant will be drawing to a close, cumulative effects are anticipated to be minor. 11.152 The level of operational traffic at the peaking plant facility would be expected to be low and infrequent due to the development’s nature as a “back up” facility. Therefore, the cumulative operational impacts of both the peaking plant facility and the onshore elements of the Nemo Link scheme are expected to be negligible. Pegwell Bay Flood Defence Scheme 11.153 An application was submitted in September 2012 for the installation of a new concrete wall to the north of Pegwell Bay Service Station and installation of an earth embankment, to the south of the service station. Construction would be expected during 2013. 11.154 Works on the onshore elements of the Nemo Link are scheduled to commence in 2015. Therefore, if the flood defence scheme is completed during 2013 as expected, there would be no cumulative highways impact. Waste Development 11.155 An application was approved by Kent County Council in July 2011 for a waste related development on land west of Ramsgate Road, Richborough. This will include the construction of a materials recycling facility, soil washing plant, anaerobic digestion plant and inert materials processing facility plus construction of a building to house the anaerobic digester. 11.156 The construction of the onshore elements of the Nemo Link and the waste facility are not anticipated to overlap; therefore no cumulative impacts are anticipated. 11.157 Once operational, there will be some vehicular movements associated with the waste development. However, combined with the very low operational vehicle generation associated with the onshore elements of the Nemo Link, cumulative effects are anticipated to be negligible. Solar Farm 11.158 A future application is expected for a 5MW Solar Farm on land to the west of the River Stour adjacent to the site, with an area of 13.36 ha. The proposals will include rows of photovoltaic panels, ancillary equipment, security fencing and associated landscaping. 11.159 The construction of the onshore elements of the Nemo Link and the solar farm are not anticipated to overlap; therefore no cumulative impacts are anticipated. 11.160 Once operational, it is anticipated that vehicle movements associated with the solar farm will be very low; cumulative effects are anticipated to be negligible. 287 Glasshouses, Three Water Storage Tanks and Pack House 11.161 An application was submitted in October 2012 for the erection of glasshouses, three water storage tanks and a pack house at Ebbsfleet Lane, Ebbsfleet, Ramsgate. 11.162 While there would be trips associated with the construction, they are anticipated to be low; therefore the potential cumulative impact would be expected to be negligible. Overall Cumulative Impacts 11.163 In the one instance where the construction of a neighbouring development (the Peaking Plant Facility) may overlap with the construction of the Nemo development the cumulative impacts are expected to be minor. 11.164 Careful consideration of all construction programmes will be required to keep all impacts associated with the construction of the two developments to a minimum. 11.165 With regard to operational traffic, all of the sites described above have a relatively low operational traffic generation. Therefore, the combined traffic generation of all proposed works is anticipated to negligible and as such no significant cumulative effects are anticipated. References Department for Transport, 2007. Guidance on Transport Assessment. London: Department for Transport. Department for Transport, 2008. Design Manual for Roads and Bridges. London: Department for Transport Highways Act 1980. s.105. London: HMSO. Highways (Assessment of Environmental Effects) Regulations 1988. London: HMSO. Highways (Assessment of Environmental Effects) Regulations 1994. London: HMSO. Highways (Assessment of Environmental Effects) Regulations 1999. London: HMSO. Highways (Environmental Impact Assessment) Regulations 2007. London: HMSO. Institute of Environmental Assessment, 1993. Guidelines for the Environmental Assessment of Road Traffic. London: Institute of Environmental Assessment. 288 289 290 12.0 NOISE AND VIBRATION Introduction 12.1 This chapter considers the potential noise and vibration effects of the Proposed Development i.e. the UK onshore elements of the Nemo Link (see Chapter 2 – Project Description) on noise sensitive receptors. The assessment identifies, establishes and quantifies expected noise and vibration emissions associated with the installation of the onshore cables and the construction and operation of the converter station and substation. The operation of the onshore underground cables and the subsea cables from mean low water has been scoped out of the assessment, as they will not generate noise or vibration. There will be no vibration from the operation of the substation and converter station; this has also been scoped out of this assessment 12.2 The assessment is generated from the results of baseline noise monitoring and predictive calculations of noise impact. The chapter identifies mitigation measures that will be incorporated into the construction and operation of the development to avoid, reduce or offset potential effects. Legislation and Planning Policy Context 12.3 The National Planning Policy Framework (NPPF) has replaced Planning Policy Guidance (including PPG 24 Planning and Noise), as the means by which noise is considered in the planning regime. The NPPF does not contain assessment criteria but instead provides a series of policies giving local authorities flexibility in meeting the needs of local communities. The NPPF states: ‘The planning system should contribute to and enhance the natural and local environment by […] preventing both new and existing development from contributing to or being put at unacceptable risk from, or being adversely affected by unacceptable levels of […] noise pollution. Planning policies and decisions should aim to […] 12.4 avoid noise from giving rise to significant adverse impacts on health and quality of life as a result of new development; mitigate and reduce to a minimum other adverse impacts on health and quality of life arising from noise from new development, including through the use of conditions; recognise that development will often create some noise and existing businesses wanting to develop in continuance of their business should not have unreasonable restrictions put on them because of changes in nearby land uses since they were established; and identify and protect areas of tranquillity which have remained relatively undisturbed by noise and are prized for their recreational and amenity value for this reason.’ Guidance outlined in Table 12.1 is generally used by local authorities to determine the acceptability of noise associated with developments. 291 Table 12.1: Legislation and Policy Context BS7445:2003 - Description and measurement of environmental noise - guide to quantities and procedures BS 7445 provides the framework within which environmental noise should be quantified. Part 1 provides a guide to quantities and procedures and Part 2, a guide to the acquisition of data pertinent to land use. Part 3 provides a guide to the application of noise limits. The standard also refers to BS EN 61672, which prescribes the equipment necessary for such measurements. BS 5228-1:2009 - Calculation for noise from open and construction sites - Part 1: Noise Construction noise impacts arising from equipment, vehicular movements and processes related to the construction phase of a development are assessed by calculating the change in ambient noise level (LAeq,1hr) resulting from such processes with methods described in BS5228-1. The assessment predicts noise emissions from various construction activities, which are then compared against background noise levels at residential receptors. Full details of the process are contained in Section E.3 of this standard. Annex E of the standard also provides criteria for the assessment of significance. Exceedances of threshold levels trigger a responsibility on the developer to provide noise insulation or a scheme to facilitate temporary rehousing. The standard suggests that noise insulation should be provided if trigger levels are predicted to be exceeded for a period of ten or more days of working in any fifteen consecutive days, or for a total of days exceeding 40 in any 6 month period. BS 5228-2:2009 - Calculation for noise from open and construction sites - Part 2: Vibration BS 5228-2 describes methods of mitigation that can be employed for construction groundborne vibration and provides historical library data of vibration levels measured during various activities on various ground types. BS 5228-2 reiterates the transient vibration guide values in the 4 – 15 Hz and 15 Hz and above frequency bands that lead to cosmetic damage of BS 7385. BS 5228-2 also discusses the assessment of the vulnerability of ground-related structures and services -1 concluding that a maximum PPV for intermittent or transient vibration of 30 mms and a -1 maximum PPV for continuous vibration of 15 mms . BS 5228 also discusses the vulnerability of building contents and activities within buildings to vibration, concluding that they too should be assessed on an individual basis. BS 4142: 1997 - Method for rating industrial noise affecting mixed residential and industrial areas Comparison of the difference between the industrial noise level including any rating penalty (the rating level) and the background noise level indicates the likelihood of complaint. The greater the difference, the greater the likelihood of complaints arising. A difference of around +10 dB or more indicates that complaints are likely. A difference of around +5 dB is of marginal significance. A difference of -10dB indicates that complaints are unlikely. BS 4142 is not suitable for use in situations where both the industrial noise and the background noise are very low (below 35 and 30 dB(A) respectively). Where this occurs, a suitable alternative assessment method (such as criteria based on WHO guidelines) should be utilised. World Health Organisation Night Noise Guidelines for Europe 2009 Provides a target night-time noise level of 40 dB(A) outside of bedrooms in order to protect the public. 292 Calculation of Road Traffic Noise (CRTN) & Design Manual for Roads and Bridges (DMRB) The ‘Calculation of Road Traffic Noise’ (CRTN) produced by the Department of Transport / Welsh Office provides a method for the prediction of noise from road traffic. The Highways Agency Design Manual for Roads and Bridges, Volume 11, Section 3, Part 7 Had 213/11 Noise and Vibration, provides guidance on the assessment of noise impacts from roads and contains guidance for assessing the likely impact of noise generated by road traffic. The criteria from DMRB for short-term effects have been used in the assessment of changes to traffic noise as a result of proposed construction HGV traffic. 12.5 National Grid policy requires that the Rating Noise Level from their development should not exceed the background noise level (LA90) at residential receptors. The lowest background noise level measured at the nearest residential receptor has therefore been used as a target for noise emissions. For the purposes of this assessment, the noise level target is: Assessed levels of cumulative noise from 1) the Proposed Development and 2) from other proposed industrial developments, should not exceed the lowest existing background noise levels; Or, if the other (item 2 above) proposed assessed level of industrial noise is predicted to exceed the lowest existing background noise levels and would not be considered very low in accordance with BS4142 (i.e. very low Rating Level equating to <35 dB(A)), Noise from the Proposed Development should not contribute to total noise levels at receptors from these other proposed industrial developments. Method Establishment of Baseline Environment 12.6 Environmental Health Officers at Thanet District Council and Dover District Council agreed with the proposed monitoring methods and monitoring locations. 12.7 Monitoring locations were selected to measure ambient noise levels at sensitive receptors (e.g. residential receptors and outdoor activity places) that might be exposed to noise from cable installation works and the operation of the converter station and substation. These locations are representative of other sensitive receptors around the proposed substation and convertor station and cable route. 12.8 Monitoring and receptor locations are described in Table 12.2 and presented on Figure 12.1. The monitoring location P4 represents receptors near to the junction between Ebbsfleet Lane and Sandwich Road. Receptor points at R4a and R4b face in the direction of the converter station and substation (and are used to assess noise from the construction and operation of these aspects), while receptor point at R4c faces the cable route (and is used to assess noise from cable installation). 12.9 Noise measurements were undertaken at eight agreed locations along the proposed cable route and in the vicinity of the proposed converter station and substation sites on 2nd May 2012 during day and night-time periods. 293 Table 12.2: Baseline Noise Monitoring Locations Receptor R1 R2 Monitoring Associated Aspect of Location Assessment P1 Operation of converter station and substation P2 Operation of converter station and substation R3 P3 Operation of converter station and substation R4a R4b 12.10 R4c R5 P5 R6 P6 R7 P7 R8 P8 Construction of converter station and substation. Operation of converter station and substation Cable installation Construction of converter station and substation and installation of cables and operation of converter station and substation Operation of converter station and substation Construction of converter station and substation and cables installation. Operation of converter station and substation Operation of converter station and substation Residential property to the north of Kings End farm house Residential property to the north east of Richborough Roman Fort and Amphitheatre. Residential property on Ramsgate Road, at Stonar Cut adjacent to Stevens & Carlotti Ltd Residences near to the junction of Sandwich Road and Ebbsfleet Lane Ebbsfleet Farm, Ebbsfleet Lane Entrance of Pegwell Bay Country Park off Sandwich Road Residential property opposite Jet Garage to the west of St Augustine’s Golf Course, approximately 129, Sandwich Road Entrance of BayPoint sports complex Sound level measurements were made with the following equipment: 12.11 P4 Monitoring Location Description Norsonic Nor-118 (serial number 31677) with pre-amplifier and microphone protected by the manufacturers approved foam windshield; and Norsonic acoustic calibrator type 1251, serial number 037732. Measurements were taken in free-field conditions, i.e. 1.5m above the ground and away from reflective building facades. Microphones were fitted with foam windshields to protect against extraneous wind noise. Weather conditions at the time of survey were noted as being dry and calm during the night-time measurements, but with elevated wind speeds during the daytime measurements. 294 12.12 Wind speeds during measurements at location P2 were unsuitable for purpose (> 5m/s). This measurement has been excluded. 12.13 Field calibration checks of the sound level meter were made before and after each measurement session using an acoustic calibrator. No significant calibration drift was noted. 12.14 The sound level meter used conforms to the requirements of BS EN 61672-1: 2003 Electroacoustics, Sound level meters, Specifications and the calibrator conforms to the requirements of BS EN 60942: 2003 Electroacoustics, Sound calibrators. The equipment used has a calibration history that is traceable to a certified calibration institution. Construction 12.15 Noise levels from the construction elements of the Proposed Development have been calculated based on the method set out in BS5228: 2009. This method uses information on the plant and equipment used during the construction phase to predict noise levels at the sensitive receptors. 12.16 Noise levels at receptors as a result of construction are affected by the distance between the source and receiver, the presence of noise screening (whether inherent or purposely provided), meteorological conditions, and the duration of activity. For the purposes of predicting noise from construction work the following have been considered: 12.17 Soft ground condition between source and receiver; No screening; and Continuous operation of all equipment throughout the day. The impact of the construction noise levels is determined by comparing total noise levels (ambient plus predicted plant noise) with existing ambient noise levels, having due regard to the predicted duration of the construction activities. Operation 12.18 Noise levels from the operation of the proposed converter station and the substation have been calculated based on the method set out in ISO 9613. This methodology uses information on the plant and surrounding environment to calculate noise levels at sensitive receptors within the CadnaA (4.2.140) software. 12.19 CadnaA software predicts noise using industry standard propagation method ISO 9613, which takes into account intervening screening and atmospheric and ground absorption. The parameters used within the model for these aspects were: Screening = No screening considered due to the flat terrain surrounding the substation locations; Air Absorption = 10C / 70% Relative Humidity; and Ground absorption = 0.1 coefficient for site (hard) ground, 0.7 coefficient for surrounding (soft) ground. 295 12.20 The impacts of the operational aspects of the proposed development on residential receptors have been determined with reference to the guidance set out in BS4142: 1997. This method compares the predicted ‘industrial’ noise assessment level to the existing background level, to determine the likelihood of complaints 12.21 For the assessment of the effect of plant noise on leisure areas, a comparison between the LAeq of the plant noise and the LAeq measured during the daytime at leisure areas has been made and the resulting difference assessed with reference the criteria provided in Tables 12.3-12.5. Assessment of Significance 12.22 The significance of noise effects from construction and operation has been assessed using the criteria outlined in Table 12.3 and Table 12.4. A combination of receptor sensitivity and magnitude of effect has been used to determine the overall significance of the effect (Table 12.5). Table 12.3: Sensitivity of Noise Receptor Receptor Sensitivity Description High Residential area. Medium Area formally designated for leisure activities (in this case the golf course, BayPoint sports complex and Country Park) Low Area not formally designated for leisure activities (for example most countryside and land remote from habitation) Negligible All other areas such as those used primarily for industrial or agricultural purposes. Table 12.4: Magnitude of Effect Magnitude Examples Large Construction noise levels predicted to exceed BS 5228 levels to a degree and for a duration triggering noise insulation requirements or temporary re-housing. Increase in short-term traffic noise from construction at residential receptors >5 dB(A). Construction vibration levels persistently exceed 10 mm/s ppv at the nearest houses. Complaints considered likely from operation in accordance with BS4142 or predicted rating noise levels exceed 35 dB(A) if receptor background levels are <=30 dB(A). Intrusive increase in noise at non-residential receptors. 296 Magnitude Examples Medium Construction noise levels predicted to exceed BS 5228-1 threshold values, but not trigger noise insulation or temporary rehousing requirements. Increase in short-term traffic noise from construction at residential receptors 3-4.9 inclusive dB(A). Construction vibration levels occasionally exceed 10 mm/s ppv at the nearest houses. Complaints considered of marginal significance from operation in accordance with BS4142 and above National Grid criteria of no increase above the background noise. Clearly perceptible increase in noise at non-residential receptors. Small Noise levels will cause some minor temporary disturbance, but noise levels do not exceed BS 5228-1 threshold values. Increase in short-term traffic noise from construction at residential receptors 1-2.9 inclusive dB(A). Minor perceptible vibration below 10 mm/s ppv at the nearest houses. Complaints not considered likely from operation. Just perceptible increase in noise at non-residential receptors. Negligible Construction noise levels unlikely to cause any disturbance. Increase in short-term traffic noise from construction at residential receptors <1 dB(A). No perceptible vibration at the nearest houses. Complaints unlikely from operation in accordance with BS4142 or predicted rating noise levels are <= 35 dB(A) if receptor background levels are <=30 dB(A). Imperceptible increase in noise at non-residential receptors. Table 12.5: Overall Significance Magnitude Sensitivity High Medium Low Negligible Large Significant Significant/ Moderate Moderate Neutral Medium Significant/ Moderate Moderate Moderate/Minor Neutral Small Moderate / Minor Minor Minor/Neutral Neutral Negligible Minor/Neutral Minor/Neutral Neutral Neutral 297 Existing Environment 12.23 Attended measurements were obtained at selected monitoring locations during day and night time periods. Noise measurements are summarised in Table 12.6. Table 12.6: Summary of Attended Measurements Time Period Day Duration Dominant Noise Time (minutes) LAeq, T dB LA90, T dB Source Location Date P1 02/05/2012 P2 During the daytime, the exposed nature of this location meant that wind speed was too high to obtain representative results. P3 02/05/2012 10:20 30 70.3 60.9 Road traffic noise P4 02/05/2012 10:59 30 66.6 55.8 Road traffic noise P5 02/05/2012 12:15 30 50.5 44.1 Road traffic noise and car park noise P6 02/05/2012 12:52 30 53.8 47.7 Road traffic noise and birdsong P7 02/05/2012 13:33 30 64.2 52.5 Road traffic noise and birdsong P8 02/05/2012 P1 02/05/2012 P2 02/05/2012 09:21 30 48.2 40.3 11:36 20 55.6 53.4 Road traffic noise, shorter measurement taken due to high wind speed 00:47 15 31.5 27.3 Industrial noise from the north 01:09 15 34.1 27.6 Distanced Road traffic noise 01:40 15 52.2 32.5 Industrial noise ('hum') from existing substation 02:14 15 52.0 32.9 Road traffic noise and air traffic noise Night P3 02/05/2012 P4 02/05/2012 Agricultural noise and nature 12.24 The general noise climate at sensitive receptors along the proposed cable route and in the vicinity of the proposed converter station and substation is primarily affected by road traffic noise, existing industrial noise, noise from agricultural activities and birdsong. 12.25 Given the distance to the substation and converter station site, receptors represented by measurement P7 would be only potentially affected by the installation of the cable (assumed to be daytime only near to this location); therefore a night-time measurement was not taken at this location. 12.26 P6 and P8 represent leisure areas, users of which would only be affected during the day by noise from the construction and operation of the Proposed Development; therefore night-time measurements were not taken at these locations. Noise levels at location P2 during the night are considered representative of a worst-case noise environment at location of P5. 298 12.27 Measurements were taken during times when wind speeds would be considered acceptable for a noise survey, however at P2 (during the daytime), wind speeds were above 5m/s which was likely due to be the exposed nature of this location. Noise levels at location P1 during the day are considered representative of a worstcase noise environment at location of P2. Prediction and Assessment of Significance of the Potential Impacts Construction 12.28 The target threshold levels at locations referred to in Table 12.2 for the assessment of construction noise (based on proximity to works and sensitivity of receptor) have been identified based on measured ambient noise levels using the method set out in Annex E of BS5228:2009. The thresholds are presented in Table 12.7. Table 12.7: Target Threshold Levels for Construction Noise Location P4 P5 P7 Measured Ambient Noise Levels dB(A) Day Night 67 52 51 64 - Target Threshold Levels, dB(A) Day Night 72 57 65 69 - Construction Noise – Cable Installation 12.29 Equipment that will be used during cable installation is shown in Table 12.8. Noise level data has been taken from Annex C of BS 5228-1: 2009. All sound pressure levels are given at a distance of 10m from the measured plant. Table 12.8: Noise Levels of Construction Equipment – Cables Installation Plant No# BS5228 ref. Operational A-weighted Hours SPL (dB(A) at 10 m Tracked excavator (22t) 2 C.2.3 90 % 73 Dozer 3 C.2.1 90 % 75 Construction of Wheeled backhoe loader (8t) 1 temporary site Dumper (5t) 2 access road Vibratory roller (3t) 1 C. 2.8 90 % 68 C. 4.7 90 % 78 C. 2.40 90 % 73 Activity Topsoil strip Trench excavation Tracked excavator (16t) 1 C. 2.5 90 % 76 Tracked mobile crane 1 C.3.29 90 % 70 Sheet Piling – Hydraulic jacking 1 C.3.9 Power Pack 1 C.3.10 3 C.3.28 1 C. 4.88 Side boom (Use tracked Lower and lay mobile crane data) Water pump 299 90 % 90 % 90 % 90 % 63 68 67 68 Activity Backfilling trench Reinstatement BS5228 ref. Operational A-weighted Hours SPL (dB(A) at 10 m Wheeled backhoe loader (8t) 1 C. 2.8 90 % 68 Wheeled backhoe loader (8t) 1 C. 2.8 90 % 68 Tracked excavator (16t). 1 C. 2.5 90 % 76 Dumper (5t) 2 C. 4.7 90 % 78 Vibratory roller (3t) 2 C. 2.40 90 % 73 Dumper (5t) 2 C. 4.7 90 % 78 Wheeled backhoe loader (8t) 1 C. 2.8 90 % 68 Welding generator 3 C. 3.32 90 % 73 Welder 3 C. 3.31 90 % 73 3 C. 4.94 90 % 75 2 C. 4.93 90 % 80 Plant No# Transition Joint Generator Pit Angle grinder Cable pulling Horizontal Directional Drilling 12.30 Side boom (Use tracked mobile crane data) 90 % 1 C.3.28 Conveyor drive unit 1 C.10.20 90 % 77 Field conveyor (rollers) 2 C.10.23 90 % 53 Power Auger (Crawler Mounted Rig) 1 C.3.21 67 100 % 79 Noise levels at the nearest sensitive receptors have been calculated according to the method presented within BS 5228. Based on plant type, number and forecast operational time of the equipment, Tables 12.9-12.11 provide calculated ‘worstcase’ construction noise levels for each aspect of cabling installation works (with the exception of horizontal directional drilling (HDD) during the day at the nearest receptors to the works. The ‘combined noise level’ is derived by logarithmically adding the construction noise level to the ambient noise level. Table 12.9: Predicted Construction Noise at Receptors near to the Junction of Ebbsfleet Lane and Sandwich Road (R4c), 45m from Onshore Underground Cable Route Construction Aspect Topsoil strip Construction of temporary site access road Trench excavation Predicted Construction Noise Level dB(A) 65.3 Ambient Noise Level dB(A) Target Threshold Level dB(A) Combined Noise Level dB(A) 69.3 Increases over Threshold dB -3 67.7 70.4 -2 65.9 69.5 -3 67.9 -4 Lower and lay 60.7 Backfilling trench Reinstatement Pipe welding Cable pulling Horizontal Directional Drilling 69.3 66.6 70.7 65.2 71.3 69.8 72.2 69.2 -1 -2 0 -3 67.2 70.1 -2 67 300 72 Table 12.10: Predicted Construction Noise at R7, 78m from Onshore Underground Cable Route Construction Aspect Topsoil strip Construction of temporary site access road Trench excavation Lower and lay Backfilling trench Reinstatement Pipe welding Cable pulling Predicted Construction Noise Level dB(A) 59.4 Ambient Noise Level dB(A) Target Threshold Level dB(A) Combine Noise Level dB(A) 65.3 Increases over Threshold dB -4 66.0 -3 65.4 -4 64.5 -5 63.4 66.7 -2 60.7 64.7 59.3 65.7 67.4 65.3 -3 -2 -4 61.8 59.9 54.7 64 69 Table 12.11: Predicted Construction Noise at R5, 580m from Onshore Underground Cable Route Construction Aspect Topsoil strip Construction of temporary site access road Trench excavation Lower and lay Backfilling trench Reinstatement Pipe welding Cable pulling Predicted construction noise level dB(A) 37.6 Ambient noise level dB(A) Target threshold level dB(A) Combined noise level dB(A) 51.2 Increases over threshold dB -14 51.3 -14 51.2 -14 51.1 -14 41.6 51.5 -14 38.9 42.9 37.5 51.3 51.6 51.2 -14 -13 -14 40.0 38.1 32.9 51 65 12.31 The results show that noise levels are predicted not to exceed target threshold levels during the day at nearby residential receptors. As noise is attenuated with distance, noise levels at receptors further away from the construction than those identified at R4, R5 and R7 would also not be anticipated to exceed threshold levels. Results in Tables 12.9 to 12.11 represent the highest predicted noise levels, which will only be temporarily at this level, decreasing as the cable installation passes by. 12.32 HDD will be used to install cables between BayPoint sports complex and the proposed converter station and substation site. The nearest receptors to the HDD 301 works are residences at the junction of Sandwich Road and Ebbsfleet Lane (R4c). Technical requirements associated with HDD operations mean that the installation of each cable will likely need to take place continuously to remove the risk of hole collapse. Installation is anticipated to consist of a maximum of 33 hours for each cable (reasonable worst case which also allows for any unforeseen complications during drilling). There are 3 cables in total and there will be a day of no drilling whatsoever between each of the 3 cable installation phases. Based on the predicted plant type, number and forecast operational time of the equipment, Table 12.12 provides a calculated construction noise level for HDD during the day and night at R4c. Table 12.12: Predicted HDD Noise at Receptors at the Junction of Ebbsfleet Lane and Sandwich Road (R4c) Time Day Night Predicted Construction Noise Level dB(A) 67.2 67.2 Ambient Noise Level dB(A) 67 52 Target Threshold Level dB(A) 72 57 Combined Increases Noise over Level Threshold dB(A) dB 70.1 -2 67.4 +10 12.33 Results show that HDD noise levels are predicted to exceed the target threshold levels during the night at R4a and R4b. However, HDD is anticipated to be for a maximum of 2 days and 1 night for each cable (3 cables, maximum of 3 nights of HDD works). 12.34 The time over which these worst-case noise levels would be experienced at an individual receptor is likely to be 3 nights. This period of time is less than that which needs to be exceeded for residential receptors to be eligible for sound insulation (within the criteria suggested by BS5228). However, National Grid will implement mitigation measures during HDD works (see mitigation section below) to ensure noise is minimised. 12.35 Worst-case noise levels from the cable installation would result in a small and medium magnitude of effect on receptors of high sensitivity for excavated cable installation and HDD respectively. Construction Vibration – Cable Route 12.36 All residential properties are greater than 10m from the onshore underground cables route and the converter station and substation site. The nature of the construction equipment used means that, where works occur more than 10m from buildings, the risk of construction vibration generating significant impacts is negligible for receptors of high sensitivity. Construction Noise – Substation and Converter Station 12.37 The noise levels of equipment anticipated to be used for the construction of the substation and converter station are shown in Table 12.13. 302 Table 12.13: Noise Level of Construction Equipment – Substation and Converter Station Plant No# Front end loaders (wheeled) Tracked excavator Wheeled backhoe loader Wheeled loader Dozer Articulated dump truck Road roller Graders Material Handling Cement mixer truck Truck mounted concrete pump and boom arm Wheeled mobile telescopic crane Diesel generator for site cabins 1 1 1 1 1 1 1 1 1 1 1 1 1 Operational hours A-weighted SPL (dB(A) at 10 m 90 % 90 % 90 % 90 % 90 % 90 % 90 % 90 % 90 % 90 % 90 % 82 77 68 79 80 74 80 75 86 75 90 % 100 % 78 65 80 12.38 Noise emission levels at the nearest residential receptor from the construction work of the substation and converter station have been calculated according to the method presented within BS 5228. 12.39 The closest residential receptor is 340m to the northeast of the proposed substation and converter station site boundary. Resultant worst-case noise levels would be 54 dB(A). This is below the BS5228 target threshold of 72 dB(A), and as such would result in a small impact on receptors of high sensitivity. Construction Vibration – Substation and Converter Station 12.40 The large distance between the converter station and substation site and sensitive receptors means that there is no potential for vibration from these works to affect sensitive receptors. The impact of vibration will therefore be negligible on receptors of high sensitivity. Construction Noise and Vibration – Traffic 12.41 There will be a small number of traffic movements (Heavy Goods Vehicle) associated with the construction of the substation and converter station and cable route. For a significant impact to occur, traffic noise levels would have to increase in the short-term by >1 dB(A), which would result from an approximate 25% increase in traffic. As construction traffic flows would be well below this level, the impact from traffic noise would be negligible on receptors of high sensitivity. 303 Operation Operational Noise – Substation and Converter Station 12.42 The proposed substation and converter station have been modelled using CadnaA noise prediction software (version 4.2.140) based on an indicative layout. The components to be installed, which are potential sources of noise, are listed in Table 12.14. The location of the noise sources are described in Chapter 2 (Project Description) and shown on Figure 12.2. 12.43 A 5 dB ‘rating penalty’ has been applied to the modelled noise levels of transformers and reactors to account for their tonality. Cooling fans (including air handling unit (AHU) fans) produce a broadband noise and therefore do not have a tonal penalty applied. Based on a careful consideration of likely operational requirements, it is assumed that Super Grid Transformer coolers would only be required in emergency situations and that MSCDNs are only operational during the day. A full list of equipment details and assumptions are presented in Appendix 12.1. Table 12.14: Modelled Sound Power Levels of Major Equipment within the Proposed Substation and Converter Station (No Mitigation Measures) Sound Power Level [for individual plant items] including tonal penalty (5 dB(A)) where appropriate Plant Name & Quantity SUBSTATION SITE 1 x Static Compensator Transformer (SCT) 1 x SCT Cooler 9 x valve cooling fans for Static Variable Compensator (SVC) 2 x Super Grid Transformers (SGT) 1 x Thyristor Controlled Reactor set (TCR) 1 x Substation Mechanically Switched Capacitor with Damping Network set (MSCDN) 2 x Harmonic Filter set CONVERTER STATION SITE 3 x Converter Station Transformer 3 x Converter Station Transformer coolers 1 x Converter station 200MVA Shunt Reactor 1 x Converter Station Shunt Reactor cooler 40 x Converter Station Valve Cooling Fans 1 x Converter Station Mechanically Switched Capacitor with Damping Network set (MSCDN) 3 x Converter Station Air Handling Units (AHU) 12.44 100 + 5 90 80 90 + 5 105 + 5 per set 85 + 5 per set 85 + 5 per set 90 + 5 90 91 + 5 84 80 85 + 5 per set 87 Resultant noise levels from the substation and converter station at residential locations and BS4142 assessment are presented in Table 12.15. 304 Table 12.15: Converter Station and Substation BS4142 Assessment (dB) at Residential Receptors [No Mitigation] Location Background Level (LA90) dB Day R1 R2 R3 R4a R4b R5 R7 40 40 61 56 56 44 53 Rating Level, dB Night Day Night 27 28 33 33 33 28 33 29 29 32 47 44 38 30 29 29 32 47 44 38 30 Assessment level (Difference of Rating Level over LA90, dB) Day Night -11 -11 -29 -9 -12 -6 -23 +2 +1 -1 +14 +11 +10 -3 12.45 Results show that complaints would be considered likely at three locations (R4a, R4b and R5) in accordance with BS4142 as a result of cumulative unmitigated noise levels from both the substation and converter station. This would represent an operational noise impact of large magnitude on receptors of high sensitivity. 12.46 Resultant noise levels from the substation and converter station at locations used for leisure activities and a comparison assessment with the existing noise levels is presented in Table 12.16 based on daytime LAeq noise levels. Table 12.16: Plant Noise at Locations used for Leisure (dB) Location R6 R8 Baseline Level (LAeq) dB 54 56 Plant Noise Level dB 38 46 Assessment Level (Difference of Rating Level over LAeq, dB) -16 -10 12.47 Results show that noise levels would not have an effect on the existing baseline. This level of effect would be considered of negligible magnitude on receptors of medium and low sensitivity. 12.48 The noise models are ‘worst case’ because they assume that plant is operating continuously on full load (with the exception of the SGT coolers and MSCDNs). This will not be the case at all times. For example, the plant will not be 100% utilised for all of the time and because ambient temperatures will be lower during the night and in winter; therefore cooling plant that is in service may not need to operate at full capacity. Significance 12.49 The assessment of the significance of potential impacts is summarised in Table 12.17. 305 Table 12.17: Significance of Impact of Noise Effects (No Mitigation) Aspect Sensitivity* Magnitude Significance Construction Noise – Cable route excavation High Small Moderate Construction Noise – HDD High Medium Moderate Construction Noise – Substation and converter station High Small Moderate Construction Noise (substation, converter station and cable) – Traffic High Negligible Minor Construction (substation and converter station) - Vibration High Negligible Neutral Operation Noise (substation and converter station) - Residential High Large Significant Operation Noise (substation and converter station) – Formal leisure areas Medium Negligible Neutral Operation Noise (substation and converter station) – Informal leisure areas Low Negligible Neutral *Where receptor type unspecified, highest sensitivity chosen Mitigation Construction 12.50 Best practice construction noise methods will be used to minimise noise associated with cables installation and construction of the substation and converter station. Such best practice measures include: 12.51 Site vehicles will not be over revved, or left with engines idling in close proximity to residential neighbours; and All plant and machinery to be properly maintained and silenced in accordance with manufacturer's instructions; Development of a Construction Management Plan detailing the mitigation to be used throughout each stage of construction; and Regular communication with residents living close to the cable route and converter station and substation site. The communication will include details of expected work schedules and activities taking place, and contact details in case of query or complaint. In addition the following measures will be used to ensure that disturbance due to construction noise is minimised: Screening of HDD noise emission points at HDD using layout of temporary structures (such as site offices) and hoarding; and 306 Although the assessment of vibration effects from cables installation at a distance of 10m or more has been assessed as negligible, where cabling works pass within 20m of properties pre and post construction building surveying will be undertaken. This would be used to demonstrate no adverse effect have occurred or, very unlikely, would inform any future assessments for making good any damage caused by vibration. In addition, vibration monitoring will be undertaken at the start of the construction works in order to more accurately quantify the risk of vibration generated by each stage of the works giving rise to a significant impact at varying distances. This data will be used, if necessary, to modify the distance from the route at which building surveys are triggered. Operation 12.52 Without mitigation, there is potential for the operation of both the converter station and substation to give rise to complaints from neighbouring properties. Mitigation will be incorporated into the design of the converter station and substation to ensure that the noise target (assessed noise levels of the proposed converter station and substation are no higher than the background noise levels) is achieved. This assessment will be based on, in many cases, worst case operational scenarios; therefore it is considered to be appropriately conservative. 12.53 Prior to commencement of works on the converter station and substation, modelling will be undertaken on the final design and layout of the plant to verify that the above noise target is met. Sound power levels can be reduced through design, selection of equipment and by employing mitigation measures, which, as examples, could include: For Substation: TCRs housed within noise shields or a full noise enclosures; Noise shields to Harmonic Filters; Enclosures around the SCT and SGTs; and Low noise fans, silencers on cooling fans or barriers around cooling fans. For Converter Station: Enclosures around the Shunt Reactor and Converter Station transformers Low noise fans, silencers on cooling fans or barriers around cooling fans Residual Impacts 12.54 Residual noise levels from the substation and converter station and a BS4142 assessment are presented in Table 12.18. Table 12.18: Converter Station and Substation BS412 Assessment (dB) at Residential Receptors with Mitigation Location R1 R2 R3 Background Level (LA90) dB Rating Level, dB Day 40 40 61 Day 19 19 16 Night 27 28 33 307 Night 19 19 15 Assessment level (Difference of Rating Level over LA90, dB) Day Night -21 -8 -21 -9 -45 -18 Location Background Level (LA90) dB Rating Level, dB R4a R4b R5 Day 56 56 44 Day 30 26 23 Night 29 25 22 Assessment level (Difference of Rating Level over LA90, dB) Day Night -26 -4 -30 -8 -22 -6 R7 53 12 11 -41 Night 33 33 28 33 -22 12.55 The above results show that complaints as a result of substation and converter station noise would not be considered likely, after mitigation is applied. 12.56 The maximum noise effect would be considered of small magnitude on receptors of high sensitivity. 12.57 Table 12.19 shows a summary of the residual impacts after mitigation has been taken into consideration. Table 12.19: Residual Impacts Potential Impact Significance of Impact Mitigation Measure Residual Significance of Impact After Mitigation Moderate Best practice techniques, communications with residences Minor Moderate Best practice techniques, communications with residences, screening Moderate Construction Noise – Substation and converter station Moderate Best practice techniques, communications with residences Minor Construction Noise (substation, converter station and cable) – Traffic Negligible N/A Minor Neutral Potential measurements if properties within 20 m Neutral Construction Construction Noise – Cable route excavation Construction Noise – HDD Construction Vibration 308 Operation Operation Noise (substation and converter station) -Residential 12.58 Significant Operation Noise (substation and converter station) - Formal leisure areas Neutral Operation Noise (substation and converter station) - Informal leisure areas Neutral Minor Reduction of sound power at source by design or by application of mitigation measures Neutral Neutral With the identified measures in place it has been shown that all significant impacts would be appropriately mitigated such that the overall effect of the Proposed Development is not considered significant. Cumulative Impacts 12.59 The following planned or permitted industrial developments have the potential to contribute to total noise levels in combination with predicted noise from the proposed substation and converter station plant: Richborough Energy Park Peaking Plant (PP); Thanet Waste Recycling Sites (TWS); and CHP Plant at the Ebbsfleet Farm Anaerobic Digestion Plant (CHP) Site Descriptions 12.60 A planning application including a supporting Environmental Impact Assessment was submitted in December 2012 for a ‘peaking plant’, comprised of 53 diesel generators (50 generators assumed to be running at any one time), which will be used to provide peak electricity supplies to the local distribution network This peaking plant is expected to run for 100-300 hours per year (4 to 12.5 days). 12.61 The existing Thanet Waste site at Richborough Hall on Ramsgate Road is to be expanded with an additional location developed on land to the north of Stevens and Carlotti off Ramsgate Road. Proposals include the construction of a materials recycling facility on the existing site and the construction of an inert waste materials recovery and processing facility and a soil washing plant on the new site. TW Services appointed SLR Consulting Limited to undertake the noise assessment for the site. 12.62 The Ebbsfleet Farm Anaerobic Digestion Plant is planned for the area of land between the Minster Stream and the recently built A256 bypass, north of the proposed converter station. The notable noise source within the Anaerobic Digestion Plant is the Combined Heat and Power (CHP) Plant. Laurence Gould 309 Partnership prepared a supporting statement for the site, including a noise assessment. Construction 12.63 It is likely that construction of the three sites considered above would occur only during normal daytime working hours. 12.64 Detailed information on construction of the peaking plant is not available at present. The supporting statement for the Ebbsfleet Farm Anaerobic Digestion Plant does not include an assessment of noise from the construction of the site. If it were assumed that the construction plant and methods for these sites would be similar to, and occur simultaneously to those of the Proposed Development, construction noise levels would be 59dB(A) at the closest property to the substation and convertor station site (R4). 12.65 The cumulative construction noise from both of the Thanet Waste sites was predicted by SLR as 57 dB(A)1 at the nearest residential receptor on Ramsgate Road, R3 within this assessment. Based just on distance attenuation, the predicted noise level from the construction of the Thanet sites would be 53 dB(A) at the closest property to the substation and converter site, R4. Based just on distance attenuation, the predicted noise level from the construction of the Proposed Development, CHP and peaking plant at receptor R3 would be 53 dB(A). The resulting cumulative noise at R3 and R4 would be 60 dB(A) and 59 dB(A) respectively, both below the target threshold levels for the daytime. This would result in a small, but not significant impact. Operation 12.66 An indicative layout (spread equally throughout the peaking plant site as shown on Figure 12.2) of 50 generators has been modelled using CadnaA noise software with a sound power level of 87 dB(A) for each generator (including a 5dB tonal penalty). Peaking plant use will be during times of the day of peak energy demand (for instance, during breakfast and early evening). 12.67 Predicted operational noise from both Thanet Waste sites at the nearest residential receptor, R3, is a Rating Level (including a 5 dB penalty) of 54 dB(A).2 Noise levels at other receptors identified within this assessment have been predicted by adjusting the noise level of 54 dB(A) according to the difference in distances between the sites to R3 and the sites to other receptors. 12.68 The noise level from the CHP is stated as 65 dB(A)2 at 10m. The CHP has been modelled as a point source within CadnaA software based on the sound pressure level at 10m and an indicative sound spectrum based on RSK [the author] experience of similar CHP equipment. 12.69 Resultant noise levels and BS4142 assessment for the substation, converter station, peaking plant, Thanet Waste Sites and the Ebbsfleet Farm CHP at residential locations are presented in Table 12.20. 1 SLR Consulting Limited, Noise Assessment, Sept 2010 (Ref: 409-03301-00001), https://shareweb.kent.gov.uk/Documents/environment-and-planning/planning-and-land-use/Thanet%20waste%20services%20%20major%20proposal/application%20documents/Environmental%20statements/noise-assessment.pdf 2 Laurence Gould Partnership Ltd, Ebbsfleet Farm Anaerobic Digestion Plant Supporting Statement (Feb, 2012) 310 Table 12.20: Cumulative Mitigated Converter Station and Substation BS4142 Assessment (dB) at Residential Receptors Loc. R1 R2 R3 R4a R4b R5 R7 Background Level (LA90) dB Day 40 40 61 56 56 44 53 PP (Day) Night 27 28 33 33 33 28 18 19 26 29 26 21 33 16 Rating Level, dB(A) TWS CHP (Day) (Day & Night) 40 15 42 15 54 22 42 46 42 40 38 29 34 18 Day 40 42 54 48 44 39 Total + NEMO Night 20 20 23 46 40 30 34 19 Assessment level (Difference of Rating Level over LA90, dB) Day Night 0 -7 +2 -8 -7 -10 -8 +13 -12 +7 -5 +2 -19 -14 12.70 Results show that the cumulative noise from all planned and permitted industrial developments would exceed the target level during the day at R2 and during the night at R4 (a & b) and R5. Noise levels at R5 during the night would be considered very low in reference to BS4142; therefore this exceedance by the cumulative noise would be an impact of negligible magnitude and not significant. 12.71 At those locations where the cumulative noise assessment level exceeds the background noise level (and where the cumulative and background noise are not considered very low in BS4142), the predicted Proposed Development noise would not contribute to total noise levels as Proposed Development noise would be 10 dB less than the cumulative noise from other sites (i.e. if the planned and permitted industrial developments were operational, the target noise level would be exceeded regardless of whether the Proposed Development was operational or not). This relationship is shown in Table 12.21. Therefore the cumulative noise impact of the Proposed Development would be considered small and not significant. Table 12.21: Differences between Proposed Development Rating Level (dB(A)) and Other Planned and Permitted Industrial Noise Sources in the Area Loc. R2 R4a R4b 12.72 Background Level (LA90) dB Proposed Development Rating Level, dB(A) Cumulative Rating Level, dB(A) Of Other Noise Sources Difference Between Proposed Development Rating Level & Other Noise Sources, dB(A) Day Night Day Night Day Night Day Night 40 56 56 28 33 33 19 30 26 19 29 25 42 48 44 15 46 40 -23 -18 -18 +4 -17 -15 Table 12.21 shows that Proposed Development Rating Noise Levels would not significantly contribute to other proposed industrial noise sources in the area where these would result in exceedances of existing background noise level. At location R2 during the night, where Proposed Development Rating Noise Levels are 4 dB higher than other proposed industrial noise sources, the Proposed Development noise level is 9 dB lower than the existing background level, which would be considered an impact of small magnitude and minor significance. 311 12.73 Resultant noise levels from the substation and converter station at locations used for leisure activities and a comparison assessment with the existing noise levels is presented in Table 12.22 based on daytime LAeq noise levels. Table 12.22: Cumulative Plant Noise at Locations used for Leisure with Mitigation (dB) Location 12.74 Ambient Noise Level (LAeq) dB Rating Level, dB(A) Daytime PP TWS CHP Total + Proposed Development Assessment Level (Difference of Rating Level over LAeq, dB) R6 54 23 39 30 40 -14 R8 56 30 40 45 46 -10 Results above show that noise levels would not have an effect on the existing baseline. This level of effect would be considered of negligible magnitude on receptors of medium and low sensitivity and not significant. References BS 4142: 1997 - Method for rating industrial noise affecting mixed residential and industrial areas BS 5228-1:2009 - Calculation for noise from open and construction sites - Part 1: Noise BS 5228-2:2009 - Calculation for noise from open and construction sites - Part 2: Vibration BS7445:2003 - Description and measurement of environmental noise - guide to quantities and procedures Siemens report ‘Audible Noise Study Report – Grain Converter Station’ (E T PS/P-100010/ED1.088.G-B) 312 313 314 13.0 AIR QUALITY Introduction 13.1 This chapter provides an assessment of the potential impacts on air quality during the construction of the Proposed Development (i.e. the UK onshore elements of the Nemo Link - see Chapter 2, Project Description). 13.2 The Proposed Development will make no emissions to air during operation and as such is not included in this assessment. This approach was detailed in the EIA scoping report and agreed by the Local Planning Authorities as appropriate to be scoped out. 13.3 The potential construction effects arise from two sources which are considered in this chapter: construction traffic including the operation of motor vehicles and plant; and dust arising from construction works. 13.4 An air quality assessment of the effects arising from construction traffic has been undertaken and is included as Appendix 11.2 to be read in conjunction with the Traffic and Transport Assessment (Chapter 11). 13.5 Effects on air quality from emissions of onsite plant such as generators, excavators and trucks were scoped out from further assessment at the EIA scoping stage due to the small numbers of plant distributed across a large area. This approach was also detailed in the EIA scoping report and agreed by the Local Planning Authorities as appropriate to be scoped out. Legislation and Planning Policy Context National Legislation 13.6 The principal air quality legislation within the United Kingdom is the Air Quality Standards Regulations 2010 which transpose the European Directive 2008/50/EC in relation to limit values for air quality. 13.7 This legislation is further supported by the Air Quality Strategy for England, Scotland, Wales and Northern Ireland (Defra, 2007) which provides the overarching strategic framework for air quality management in the UK with quality standards and objectives designed to protect human health. The standards apply to outdoor locations which have regular use. Local Authorities have a duty to undertake a tiered appraisal of air quality to establish compliance with the standards. Where the limits set out in the standards are likely to be exceeded, the Local Authority must designate an Air Quality Management Area (AQMA) and establish an Air Quality Action Plan (AQAP). National Planning Policy Framework (NPPF) 13.8 Section 11 of the NPPF refers to the conservation and enhancement of the natural environment and states policies should: “…sustain compliance towards EU limit values or national objectives for pollutants, taking into account the presence of Air Quality Management Areas and the cumulative impacts on air quality from individual sites in local areas” 315 13.9 Planning decisions in an Air Quality Management Area will need to adhere to the local air quality plan by ensuring that any new development does not produce emissions which exceed local limits. Local Planning Policy 13.10 The site to which this application relates includes land in the Thanet District Council (TDC) and Dover District Council (DDC) administrative boundaries. TDC is in the process of producing its Core Strategy; until this is adopted decision making will be based on the saved policies from the adopted 2006 Local Plan. DCC Core Strategy was adopted in February 2010 although there are no specific policies addressing air quality. Thanet District Adopted Local Plan 2006 13.11 Saved policy EP5 - Local Air Quality Monitoring states that: “Proposals for new development that would result in the national air quality objectives being exceeded will not be permitted….development proposals that might lead to such exceedance…will require the submission of an air quality assessment…” 13.12 Thanet District Council(TDC) began the review and assessment procedure of air quality in 1998. TDC have undertaken three detailed assessments, declaring two AQMAs in the process, for exceedances of the annual mean objective for NO 2 and PM10. In 2011, both AQMAs were revoked and replace by a single Thanet Urban AQMA. 13.13 The 2012 Air Quality Updating and Screening Assessment (USA), the most recent available from TDC, considers monitoring data since the previous report in 2011. The USA concluded that although there had been exceedances of the annual mean objective of both NO2 and PM10, these were within the existing AQMA. Mitigation measures to reduce concentrations were therefore included in the new Air Quality Action Plan (AQAP). 13.14 TDC undertakes air quality monitoring within the area, operating four continuous analysers and approximately 22 diffusion tubes in both background and roadside locations. The background monitoring locations are not considered to be representative of the Proposed Development site. Background pollutant concentrations have therefore been obtained from Defra maps. There are no representative roadside locations within the vicinity of the Proposed Development and it is therefore not possible to undertake verification. 13.15 The site also lies on the boundary of Dover District Council (DDC). There are three AQMAs located within the jurisdiction of DDC; however none of these are located within the vicinity of site. DDC undertakes air quality monitoring within the area, operating three continuous analysers and approximately 11 diffusion tubes. The monitoring locations are not considered representative as they are not located within the vicinity of the site. Method 13.16 Nitrogen dioxide and oxides of nitrogen (NOX) gases are formed as a by-product of temperature combustion of fossil fuels (such as petrol and diesel) by the oxidation of nitrogen in the air. NOX primarily comprises nitrogen oxide(NO) and NO2. Once 316 emitted the former can be oxidised in the atmosphere to produce further NO2.NO2 is associated with health impacts, which can affect lung function and airway responsiveness and may also increase reactivity to natural allergens. 13.17 PM10, size fractions are defined as particulate matter with an aerodynamic diameter of less than 10 microns (µm). The full extent of health impacts of fine particulate matter is currently unclear. However research has found that exposure to increased levels of matter is associated with respiratory and sustained cardiovascular illness and mortality. 13.18 Dust is defined as all particulate matter up to 75μm in diameter as set out in BS 6069 and comprises both suspended and deposited dust. 13.19 The assessment of air quality effects arising from construction traffic includes 3 representative existing sensitive receptor locations referenced as ESR1 (Ebsfleet House - 633657, 162412), ESR2 (16 Canterbury Road West – 634624, 165055) and ESR3 (67 Sandwich Road – 634869, 164166) (see Appendix 11.2). NO2 and PM10 concentrations at these sensitive receptors have been predicted for 1) a 2012 base year, 2) 2014 without the Proposed Development and 3) 2014 with the Proposed Development. 13.20 The air quality significance criteria (taken from Environmental protection UK (EPUK) document ‘Development Control: Planning for Air Quality’ relate only to NO2 and PM10as these are the pollutants most likely to exceed the air quality objectives. The EPUK document indicates that the concentration at the receptor locations should be taken into account in combination with the magnitude of change. This approach is appropriate for the assessment of annual mean concentrations of NO2 and PM10where the objective concentration is 40μg/m3. 13.21 The assessment of potential effects arising from construction activities has referred to experience of similar construction and cables installation projects. Existing Environment 13.22 It has not been possible to undertake verification of the NO or PM10 concentrations as there is no representative data available from a location close to the Proposed Development. In the absence of such data, background concentrations for the 3 receptor locations have been obtained from the latest 2010 Defra Background Maps which provide an estimate for PM10 concentrations of between 15.55 and 16.14μg/m3 and concentrations of NO2 of between 12.84 and 14.33μg/m3. 13.23 In the absence of monitoring data for dust deposition, it is assumed to be absent from the local environment (this is a very conservative assessment because dust deposition will be occurring naturally in the surrounding environment). Prediction and Assessment of Significance of Potential Impacts Construction Traffic 13.24 Pollutants associated with exhaust emissions from construction equipment and vehicles have the potential to impact on local air quality during the construction phase. 13.25 The full results of the potential air quality effects of construction traffic are shown at Appendix 11.2. 317 13.26 The 2014 ‘with development’ annual mean NO2 concentrations (uncorrected) are predicted to range between 16.14 to 23.67µg/m3 for the 3 existing sensitive receptor locations modelled. Exceedance of the annual mean objective concentration for NO2 (40µg/m3) is not predicted to occur. 13.27 The 2014 ‘with development’ annual mean PM10 concentrations (uncorrected) are predicted to range between 16.70 to 17.99µg/m3 for the 3 existing sensitive receptor locations modelled. Exceedance of the annual mean objective concentration for PM10 (40µg/m3) is not predicted to occur. 13.28 All of the existing sensitive receptor locations are considered moderately sensitive. When the magnitude of impact is considered along with the sensitivity of the receptor, all existing receptor locations are predicted to experience a ‘negligible/not significant’ impact as a result of the Proposed Development. Such effects will be of a temporary nature during the construction phase of the proposed works only. Dust 13.29 Dust also has the potential to affect local air quality during construction. The potential for dust nuisance is most likely to arise from topsoil stripping and storage, trench digging and storage of excavated subsoil, material transfers to and from lorries and material spills during transportation and handling, particularly during prolonged periods of dry weather. 13.30 Dust will be a short-term nuisance caused by the deposition of dust settling on properties, vehicles, street furniture and nearby crops. Construction traffic leaving the site may also bear dust and mud from the working areas which can be spread as vehicles move along the local highway network, causing increases in dust and debris along the adjacent roads. 13.31 The number of potential sensitive receptors has already been minimised by the avoidance of urban areas and residential properties during the cable routeing process. The laying of cables is relatively short-term and there are less than 10 properties within 100m of the cable route, converter station and substation site. For these properties a negligible impact would be expected due to dust in the construction phase. Mitigation 13.32 The construction of the Proposed Development is a rolling process of site preparation, excavation, cable installation and remediation over short periods of time. To minimise potential impacts from dust and air quality emissions during these periods, a range of mitigation measures will be considered and implemented where appropriate. These include: Restriction of site vehicle speeds. All vehicles will be required to adhere to site speed limits which will be designed to minimise on site dust generation; Limitation of vehicle movements during cables installation to the working width wherever possible; All plant equipment will be correctly adjusted and maintained to minimise emissions; 318 Materials recycling will reduce the extent of off-site disposal and the use of fresh materials, thus reducing the need to load, unload and transport potentially dust gathering materials. Minimisation of dust generation from the loading of trucks. The potential for dust generation associated with the transfer of materials on to vehicles can be controlled by the wetting of very fine or dry materials and the minimisation of drop heights; Covering lorries carrying potentially dust generating materials; Where necessary, materials stored on site will be wetted, covered or profiled to minimise dust generation by the wind. Storage areas will be sited away from potentially sensitive receptors where practicable; Stationary equipment with the potential for dust generation (such as soil sieving equipment) will be sited away from sensitive receptors. Where dust generating operations are near to sensitive receptors, enclosures will be provided if appropriate; Access roads and crossing points of highways along the route will be swept periodically to remove dust from hard surfaces; Unsurfaced working areas will be watered when necessary (such as during prolonged periods of dry weather) to maintain moisture content and hence reduce dust generation; Vehicle wheel washes will be used at the site exits. Water from wheel washes will be collected and appropriately disposed of. Visual site inspections carried out by responsible staff to ensure that the buildup of materials with the potential to generate dust on site is prevented; Prompt reinstatement of topsoil and vegetation upon completion of construction to minimise risk of windblown dust; Limited predetermined areas for construction workers parking, from which workers will be transported to the active construction section; and All plant will be switched off when not in use for long periods. Residual Impacts 13.33 Following the implementation of mitigation measures, effects on air quality resulting from construction traffic and dust generating activities will be negligible. Cumulative Impacts 13.34 Potential cumulative effects on air quality from the onshore elements of the Nemo Link in combination with other components of the Project (i.e. UK, French and Belgian subsea cables and Belgian onshore infrastructure) are described in Chapter 16. 13.35 Potential cumulative effects of the Nemo Link UK onshore infrastructure in combination with the grid connection required to facilitate the operation of the Nemo Link are described in Chapter 17. 13.36 There is the potential for cumulative air quality effects to arise during the construction phase of the proposed works due to the construction and operation of other developments as detailed in Table 1.2. 13.37 The majority of the other unrelated developments are scheduled to have been completed before site preparation works for the substation and converter station are due to commence in late 2014. However, traffic levels are anticipated to be relatively low for all developments for both construction and operation phases and 319 effects on air quality are anticipated to be minor. Where overlap of the construction traffic associated with the onshore elements of the Nemo Link may occur with construction and operation traffic associated with other projects, significant air quality effects can be avoided through the implementation of industry standard mitigation measures as detailed above. 13.38 All cumulative effects will be of a temporary nature during the construction phase of the Proposed Development. References 2012 Air Quality Updating and Screening Assessment: Dover District Council http://www.dover.gov.uk/environment/environmental_health/air_quality.aspx DEFRA. (January 2000, Addendum 2003 and 2007). The Air Quality Strategy for England, Scotland, Wales and Northern Ireland. Working Together for Clean Air DEFRA. (2009). Local Air Quality Management Guidance LAQM.PG (09) Dover District Council (2010) Core Strategy National Planning Policy Framework (NPPF) Paragraph 124 Office of Public Sector Information (OPSI). (2010). The Air Quality Standards (England) 2010 Regulations. Statutory Instrument No. 1001. London Thanet District Council (no date) Core Strategy (online) Available at: http://www.thanet.gov.uk/environment__planning 320 321 322 14.0 COASTAL TOURISM, RECREATION AND SOCIO-ECONOMICS Introduction 14.1 This chapter presents a high-level appraisal of the potential effects arising from the construction and operation of the Proposed Development (i.e. the UK onshore elements of the Nemo Link Project: see Chapter 2 Project Description) on coastal tourism, recreation and socio-economics. Mitigation measures that will be adopted to avoid or reduce potential adverse effects are also described. 14.2 This assessment acknowledges that there is the potential for effects to arise on coastal tourism and recreation due to part of the Proposed Development taking place in areas of public open space used for tourism and leisure activities. These effects would be temporary and short-term and were identified as not significant at the Environmental Statement Scoping Stage. 14.3 The assessment also acknowledges that there would be a very small number of permanent employment opportunities resulting from the Proposed Development and that these are likely to be recruited from existing skilled persons in the electricity industry. These effects were identified at the Scoping Stage as not significant. 14.4 There would be a large number of construction jobs which would be temporary and short-term. These will be valuable to the local economy and it is inherent in the nature of the construction industry that each project comprises a temporary and short-term opportunity. There will be secondary effects anticipated because of accommodation and other services required by construction employees. These would be positive and welcome contributions to the local economy. However these benefits to the local economy will not endure beyond the construction of the Proposed Development and at the Scoping Stage were identified as not significant. 14.5 The assessment undertaken is a high-level appraisal of anticipated effects to demonstrate that the relevant issues have been considered. Method 14.6 This assessment of potential effects draws on experience from the similar converter station construction and cables installation project of the BritNed Interconnector between the Isle of Grain, Kent and the Netherlands which was commissioned in 2011. 14.7 Effects were assessed by predicting changes in baseline conditions that would be caused by the construction and operation of the proposed converter station and substation site and the installation of the onshore underground cables. 14.8 Effects on communities arising from environmental aspects and activities including landscape and views, traffic and transport, and noise are reported in other relevant parts of the ES (Chapters 10, 11 and 12 respectively). Existing Environment 14.9 Land use within the development area and surrounding area is described in Chapter 5 - Land Use. 323 14.10 The main tourist destinations in Thanet District include the coastal towns of Ramsgate, Broadstairs and Margate. Sandwich and Deal are important tourist destinations in Dover District. Richborough Fort (see Chapter 9, Archaeology and Cultural Heritage) is a Scheduled Monument promoted as a tourist attraction. 14.11 A number of recreational activities take place along the Thanet and Dover coast including bathing, beach and water sports, sea angling, bird watching and appreciation of the natural environment. 14.12 As described in Chapter 8 - Ecology, Pegwell Bay is subject to several conservation designations and parts of the Sandwich Bay and Pegwell Bay National Nature Reserve are accessible to the public. The main recreational activities at Pegwell Bay include bird watching, bait digging at low tide and kite surfing at high tide. Pegwell Bay also attracts visitors with a special interest in geology because of its chalk cliffs. 14.13 Other activities in Pegwell Bay and Sandwich Bay include walking and dog walking along the coast as well as cycling along the Viking Coastal Trail. Pegwell Bay Country Park offers facilities including parking, refreshments, toilets and a picnic area. 14.14 The subsea cables route between low water and the transition joint pit (TJP) is part of the very large extent of Pegwell Bay and mainly comprises inter-tidal mudflats and a small area of saltmarsh as shown on Figure 2.7. This is part of the area used for bait-digging, walking and birdwatching although the opportunities it offers for these activities are not distinguished from other very large areas of the Bay. The Thanet Coastal Trail long distance footpath and the Viking Coastal Trail Sustrans Route 15 runs through this area to the west of Pegwell Bay Country Park. 14.15 The TJP would be installed in an area of poor quality saltmarsh close to the Pegwell Bay Service Station. This area is used for casual access to the inter-tidal area and (as for the subsea cables route above) is not materially distinguished from other adjacent areas which offer this access. 14.16 The onshore underground cables route between the TJP and the stile entrance to Pegwell Bay Country Park includes a strip of land used for casual access along desire line footpaths on the shore side of the tarmacadam surfaced footpath and cycleway. This strip of land is used by pedestrians including dog walkers as an alternative to sharing the relatively narrow footpath and cycleway with cyclists. 14.17 In Pegwell Bay Country Park, through which the proposed cable routes run, there are footpaths separate from the footpath and cycleway which allow pedestrians (including those with dogs and children) to be sufficiently remote from cyclists, risk of collision is very low. Along the footpath and cycleway between the Country Park and Pegwell Bay Service Station, the single shared path gives a perception of risk of collision which means that pedestrians have created a ‘desire line’ path on the lower land to the shore side of the footpath and cycleway. This is used by walkers although it has led to degradation of vegetation in this area. 14.18 Pegwell Bay Country Park has a car park, toilets and refreshments facilities. It is used for walking and casual recreation and as the ‘base’ for walks in the wider area along the shoreline and beach. The footpath and cycleway runs through the Park, parallel with the A256 Sandwich Road although separated from it by planting which screens users from some of the views and some of the traffic noise from the road. 324 There are a number of footpaths in the Country Park offering pedestrians walking routes separate from the cycleway. 14.19 The onshore underground cables route runs through Stonelees Nature Reserve which is used by those on the footpath and cycleway. This route runs through the majority of the site parallel to the A256 before turning to run directly alongside the road opposite Ebbsfleet Lane. Walkers and visitors use the Stonelees Nature Reserve site for appreciation of nature including bird watching. 14.20 The onshore underground cables route passes through part of the BayPoint sports complex which has playing fields, tennis courts a bowling green and buildings including changing rooms and a social club. The cables route passes through an area presently used as a football pitch. 14.21 The onshore underground cables will be installed by horizontal directional drilling from the BayPoint sports complex to the converter station site. The land above which the onshore cables will pass is not publicly accessible beyond the A256 and has no role in tourism or recreation. This land is not included in the assessment of potential effects on coastal tourism and recreation. 14.22 The converter station and substation site is a private site to which there is no public access. It has no coastal tourism or recreation functions and is not included in the assessment of potential effects on coastal tourism and recreation. The former Richborough power station site (and the surrounding area) is allocated in the Kent Waste Local Plan as suitable in principle for waste uses. 14.23 The visual effects of the development of the former Richborough Power Station site have been addressed in Chapter 10 - Landscape and Views. Prediction and Assessment of Potential Impacts Coastal Tourism and Recreation Construction 14.24 During the installation of the subsea cables there will be restricted access to a small area of the mudflats and salt marsh area. Activities such as bait digging, walking and bird watching in this area will be restricted for the duration of cable installation works which is anticipated to be approximately 4 weeks, although the wider area of the bay provides undisturbed opportunities. 14.25 Between the intertidal area and TJP is the main area that will be impeded during construction. The onshore underground cables route will be installed close to the route of the Thanet Coastal Trail and the Viking Coastal Trail. There will be clearly signed temporary diversions in place to ensure the cycle route remains open throughout the duration of the installation works. The cycleway diversion will be diverted onto the A256 Sandwich Road with robust ‘Heras’ fencing or similar delineating the cycle route. Temporary traffic management will be installed at each end of the diversion with cyclists separated from motor vehicle traffic. Further information on Traffic and Transport is presented in Chapter 11. Disruption could be significant between the TJP and the stile into Pegwell Bay Country Park if not appropriately mitigated. However, access from adjacent areas to the Country Park will be possible throughout the duration of the works. 325 14.26 The construction works to install the cables are similar to those carried out by any utility company in its day-to-day business and would be of short duration (approximately 12 weeks) and limited in geographic effect. The proposals are unlikely to have the potential to adversely affect coastal tourism or recreation due to their temporary nature. 14.27 Disruption to traffic may also be experienced during the installation of onshore underground cables. These effects are discussed in detail in Chapter 11 - Traffic and Transport. 14.28 There will be temporary disruption to users of the BayPoint sports complex facilities during installation of the onshore underground cables which will have an adverse effect for users of the BayPoint sports complex. The duration of construction works at the Sports Ground is expected to be approximately 2 weeks. Operation 14.29 The siting of the proposed converter station and substation on the former Richborough power station site has the potential to result in adverse effects on tourism and recreation during its operation, largely due to any effect the presence of relatively large scale infrastructure may have on the attractiveness of the area for locals and visitors. 14.30 However, the previous occupation of the site by the former power station (a prominent and well-known structure of which the cooling towers were only recently demolished in March 2012) together with the wider proposals to develop the site as the Richborough Energy Park has established the site and the surrounding area for such industrial uses both historically and for the foreseeable future. In addition, the presence of other similar industrial infrastructure in the surrounding area currently under construction or awaiting planning permission has further established the area for such industrial uses. There will be no permanent direct effects on recreation areas. Therefore, potential adverse effects on tourism and recreation are considered unlikely to occur. Economic Activity 14.31 The potential beneficial impacts from the construction of the Proposed Development will depend largely on the location of prefabrication activities and resourcing of a skilled workforce. Awards of contracts for construction and cables supply and installation will be subject to competitive tendering under the European procurement legislation, following receipt of the required consents and approvals. Construction 14.32 Construction works on the converter station and substation will fall into two broad categories: civil engineering; and technical works of fit-out, equipment installation and commissioning. 14.33 Civil engineering works for the converter station and substation such as site levelling, construction of foundations and main engineering structures are likely to be sourced by the main contractor via sub-contracts with suppliers within the local area or sub-region because the skills required are those generally available within the construction industry. An important consideration will be cost-effective supply and it is likely that locally sourced materials and labour will be most cost-effective. 326 In this phase of the work there is likely to be the greatest direct effect from employment within the sub-region comprising likely ‘travel-to-work’ area. 14.34 Staff employed will use local goods and services during the construction period which will be provided by local businesses, catering or hotel facilities. The purchase of materials, equipment and services during the construction phase may have a minor beneficial effect on the creation of temporary and permanent jobs locally and nationally within the supply chain. 14.35 During technical fit-out, installation and commissioning of the converter station and substation, there are likely to be relatively few opportunities for local construction staff because the work is highly skilled and the persons involved would travel long distances, within the UK and from elsewhere, to apply specialist skills and experience to tasks. In this phase of work there is likely to be relatively low direct effect on employment from the local area but there would remain positive effects from indirect activity including accommodation and services for workers, particularly those staying locally who live elsewhere. Operation 14.36 The converter station is likely to operate with approximately 6 personnel per day divided between 3 shifts over a 24 hour period. The substation will operate unmanned with only occasional inspection and maintenance required. Converter station and substation staff are skilled workers and are likely to be recruited from existing workers in the electricity industry which will assist job retention. 14.37 On completion of cables installation, the present land uses above the cables will resume as previously, with the exception of a restriction on planting trees along the cable route. 14.38 The former Richborough power station site is allocated in the Kent Waste Local Plan as suitable in principle for waste uses whilst the Proposed Development consists of sui generis energy-related infrastructure. However, as detailed in Chapter 4 of this ES (Planning Context) and the Planning Statement, the site is not exclusively reserved for waste–related development and due to the similarity of the Proposed Development to waste uses in terms of type and scale, is not considered to cause substantial harm to such waste allocations. Therefore significant adverse effects on economic activity are not anticipated. Mitigation 14.39 During installation of the onshore underground cables, access to the Viking Trail and Thanet Coastal Path will be retained. Where there is a Health and Safety requirement to prevent or reduce access, appropriately signed diversions will be put in place. Any restriction on access will be minimised and limited only to periods of major construction activity such as earthworks. 14.40 Temporary signage advising visitors of construction activities will be erected. This will include signs within the car park of Pegwell Bay Country Park to ensure that visitors are aware of construction activities being undertaken. 14.41 To minimise construction disturbance, working hours during periods where recreational activity is greatest (i.e. evenings and weekends), will be limited as much as possible. 327 14.42 All land take associated with cables installation will be reinstated following completion of cable laying activities so will not adversely affect future recreational land use. 14.43 Creation of chalk grassland habitat within Pegwell Bay Country Park will enhance botanical biodiversity and increase the wildlife amenity for visitors. 14.44 During the works at the BayPoint sports complex, it may be possible to re-orientate affected sports pitches that would be affected by the works so that use is not impeded. Works will take place as quickly as possible and reinstatement will be to a high standard. If appropriate, the applicant would fund the use of an alternative available pitch during the works to allow team fixtures to be fulfilled. Residual Impacts 14.45 With the implementation of mitigation measures, there will be no significant adverse effects on tourism, recreation and socio-economic. The Proposed Development will bring benefits to the area during construction through some direct employment and through use of local businesses. Cumulative Impacts 14.46 Potential cumulative effects on coastal tourism, recreation and socio-economics from the onshore elements of the Nemo Link in combination with other components of the Project (i.e. UK, French and Belgian subsea cables and Belgian onshore infrastructure) are described in Chapter 16. 14.47 Potential cumulative effects of the Nemo Link UK onshore infrastructure in combination with the grid connection required to facilitate the operation of the Nemo Link are described in Chapter 17. 14.48 There is little scope for cumulative effects on coastal tourism, recreation and socioeconomics arising from the UK onshore elements of the Nemo Link in combination with unrelated planned developments described in Table 1.2, Chapter 1. 14.49 The construction phases of all other projects are anticipated to be complete before the proposed onshore elements of the Nemo Link are scheduled to commence construction. Continued cumulative construction effects from all developments i.e. construction duration effects for individual projects following on from one another increasing the overall estimated duration of generic construction works in general has been considered. Although there are likely to be effects associated with general disturbance and associated recreation (namely through the use of Public Rights of Way), such cumulative effects are not anticipated to be significant due to the projects being located in different geographic locations and their temporary nature during construction. 14.50 During operation, cumulative effects on costal tourism and recreation are not anticipated to arise. The site and the surrounding area (which includes other unrelated developments detailed at Table 1.2) is a well-established industrial area consisting of the former power station, a previously dominant and well-known structure of which the cooling towers were recently demolished in 2012. No direct effects on recreation areas are anticipated from any of the unrelated developments together with the Proposed Development. 328 14.51 During operation, cumulative effects on economic activity are not anticipated to arise. The presence of other industrial uses, some of which are also on land allocated as suitable in principle for waste uses is not expected to be detrimental to such waste policies; indeed some of the unrelated developments detailed at Table 1.2 are for waste uses and as such will likely result in a beneficial economic impact in accordance with local planning policy 14.52 The presence of the proposed onshore elements of the Nemo Link together with other unrelated development as detailed in Table 1.2 is not anticipated to result in any significant cumulative effects on coastal tourism, recreation and socioeconomics during construction or operation. 329 330 15.0 ELECTRIC AND MAGNETIC FIELDS (EMF) AND ELECTROMAGNETIC COMPATIBILITY (EMC) Introduction 15.1 This assessment considers electric and magnetic fields (EMFs) produced by the Proposed Development which consists of a converter station and onshore high voltage direct current (HVDC) bipole cables and a 400kV alternating current (AC) substation. This development forms the onshore elements of the Nemo Link Project – see Chapter 2 (Project Description). The new 400kV substation will be a gas insulated switchgear (GIS) design, with associated reactive compensation equipment. The converter station will be voltage source converter (VSC) technology and operate using both direct current (DC) and AC frequencies. The HVDC cables will operate in a bipole arrangement at 400kV carrying 1000 Megawatts (MW) of power. 15.2 All equipment that generates, distributes or uses electricity produces EMFs. The power frequency of alternating current equipment in the UK is 50 Hz, and AC equipment will produce electric and magnetic fields with a principal frequency of 50Hz. These EMFs are known as Extremely Low Frequency (ELF) EMFs. DC equipment produces steady state electric and magnetic fields and these are referred to as static fields. 15.3 All static and alternating fields can have different effects, but in both cases, there are exposure limits set by independent organisations, designed to prevent all established effects of EMFs on people. 15.4 The Nemo Link uses both AC and DC technology, so both static and alternating electric and magnetic fields will be produced. The effects are discussed in this chapter. 15.5 The electric and magnetic fields produced by transmission assets may potentially interfere with other electronic or electrical products in close proximity, such as pacemakers and visual display units. These potential electro magnetic compatibility (EMC) issues, or indirect effects, are discussed in relation to the Proposed Development. Electric Fields 15.6 Electric fields depend on the operating voltage of the equipment producing them. They are measured in V/m (volts per metre). The operating voltage of the equipment is a relatively constant value. Electric fields are shielded by most common building materials, trees and fences. Electric fields diminish rapidly with distance from the source. 15.7 As a consequence of their design, some types of equipment do not produce an external electric field. This applies to underground cables (both AC and DC) and gas insulated switchgear (GIS), which are enclosed in a metal sheath (a protective metal layer within the cable) and have solid metal enclosures respectively. This equipment will be used for the Nemo Interconnector. 331 15.8 The converter station may have some bare conductors in the central portion of the site. These will produce an electric field which drops quickly with distance. The palisade security fencing and buildings, however, will screen the electric field at the boundary of the site. These types of bare conductors have been demonstrated to be inherently compliant with exposure guideline. Evidence for this is maintained at http://www.energynetworks.org/electricity/she/emfs.html. As such, electric fields have not been considered further in the assessment. Magnetic Fields 15.9 Magnetic fields depend on the electrical currents flowing and these vary according to the electrical power requirement at any given time. Magnetic fields are measured in µT (microteslas). They are not significantly shielded by most common building materials or trees but they diminish rapidly with distance from the source. 15.10 AC magnetic fields arising from electric cabling and equipment are found in all areas where electricity is in use (e.g. in offices and homes). In UK houses, typical AC magnetic fields will be in the range of 0.01 – 0.2 µT, with higher values in localised areas close to electrical appliances. 15.11 The earth also produces its own DC magnetic field, which in the UK is around 48 µT, but this can vary due to geomagnetic material such as rocks. Legislation and Policy Guidance 15.12 There are no statutory limits on EMFs in the UK. It is the responsibility of the Health Protection Agency (HPA) to recommend guidelines for exposure to EMFs. In 2004 it recommended that the UK adopt the 1998 guidelines from the International Commission on Non-Ionizing Radiation Protection (ICNIRP, 1998) which cover 50 Hz frequencies. The Government accepted this recommendation, stating that the guidelines should be applied in the terms of EU Recommendation 1999/519/EC. The EU recommendation also includes guidance on static field exposure limits, taken from ICNIRP’s guidance on static magnetic fields (1994). These are the guidelines that currently apply in the UK. 15.13 The 50 Hz guidelines and their application are explained in the Code of Practice, ‘Power Lines: Demonstrating compliance with EMF public exposure guidelines – a voluntary Code of Practice’ (DECC, 2011c) published by the Department of Energy and Climate Change (DECC). It is the electricity industry’s policy to comply with Government guidelines on EMF, and this Code of Practice forms an integral part of this policy. This application does not include new overhead lines. However, this assessment has been performed in line with the principles of the Code of Practice. This Code of Practice covers 50 Hz fields specifically, but the overall principles of demonstrating compliance have been applied to the DC assessment also, using the appropriate exposure limits. 15.14 There is also a second Code of Practice, Optimum Phasing of high voltage doublecircuit Power Lines (DECC, 2011d), which sets out the principles for optimum phasing of overhead lines. The application is not proposing a new overhead line, so an assessment against the optimum phasing code of practice is not required. 332 15.15 There has been extensive research to establish whether or not long term exposure to fields at lower levels than the ICNIRP guidelines might be a cause of ill health in humans, and this research has been extensively reviewed by bodies such as the HPA and the World Health Organization (WHO). There is some evidence to suggest that high magnetic fields may be associated with an increased risk of one particular disease, childhood leukaemia. However, the weight of scientific evidence is against electric and magnetic fields causing ill health in humans at levels below the ICNIRP guideline limits. The government has addressed this uncertainty by adopting precautionary measures set out in the Code of Practice ‘Optimum Phasing of high voltage double-circuit Power Lines’ (DECC, 2011d), which the electricity industry follows, where appropriate. 15.16 The evidence that leads to some health concerns about EMFs from electric power systems is specific to AC fields, at 50 Hz, and does not apply to DC fields. The fact that humans have evolved in the Earth’s DC magnetic field makes it unlikely that there are any adverse health effects from any sources of fields at levels below the guideline limits. 15.17 The policies followed in this chapter result from a comprehensive risk assessment performed at a National Level. The Codes of Practice (DECC, 2011c, d) effectively represent the conclusions of a health impact assessment conducted nationally and applied generically to all power lines, cables and substations. Method Study Area 15.18 The assessment included all areas where the magnetic fields could potentially extend from the electrical assets proposed by the Project. Extensive operational experience has shown that equipment operating at this voltage and rating will not produce magnetic fields greater than background levels at distances of more than 100m. 100m corridors around the substation, converter station and HVDC cables were defined as an appropriate assessment area. 15.19 All magnetic fields were calculated at 1m above ground level as set out in the Code of Practice (DECC, 2011c). 15.20 As external electric fields are not produced by equipment enclosed in metal sheaths or which have solid metal enclosures, the assessment does not consider electric fields from the GIS substation, fenced converter station, HVDC cables or bare conductors within the substation due to the reasons set out in section 15.7. Assessment of Significance 15.21 The assessment considers magnetic fields produced by the proposed 400 kV GIS substation and associated reactive equipment, the HVDC converter station and the onshore HVDC cables. The final asset configuration and manufacturer for the substation and converter station equipment are not finalised, so the worst case assumption in terms of magnetic field exposure has been considered for this assessment. 15.22 Magnetic fields have been assessed as per the conditions set out in the Code of Practice (DECC, 2011c) and compared with UK Government exposure guideline levels. The onshore underground HVDC cables are a bipole design with a maximum cable rating of 1000 MW. The cables will be installed onshore in three 333 distinct ways along the length of the route and each of these configurations has been considered separately. These are: Trough installation - Cables buried at 1m depth with cables 500mm apart; Surface laid with capping - Cables will be a minimum of 1m from the closest possible point, and installed with 500mm cable centres. Capping will include a 1:5 sloped approach meaning that the effective worst case will be standing directly on top of the cables, In magnetic field terms this assessment is the same as for the trough installation; Horizontal directional drilling (HDD) - Cables will be installed at 2.5m apart, and the depth will vary between approximately 1.2m and 10m. The worst and best case depths of 1.2m and 10m were used for the calculations giving the potential range of exposures. 15.23 The 1998 ICNIRP guidelines are based on the avoidance of known adverse effects of exposure to EMF at frequencies up to 300 GHz, which includes the 50 Hz EMF associated with electricity transmission. This equates to public exposure limit for uniform AC magnetic fields exposure of 360 µT (DECC, 2011c). 15.24 For static magnetic fields, the recommended exposure limit used in the EU recommendation is 40 000 µT (40 millitesla). However ICNIRP’s 1994 guidance (ICNIRP, 1994) states that there are potential indirect effects, such as injuries due to flying ferromagnetic objects and potential interactions with implantable medical devices which could occur at the levels below the exposure limits. Therefore a lower restriction of 500 µT should be considered where indirect effects may be an issue. The assessment would demonstrate a significant impact if non-compliance with the EMF exposure limits was demonstrated using the principles set of in Codes of Practice ‘Power Lines: Demonstrating compliance with EMF public exposure guidelines – a voluntary Code of Practice’ (DECC, 2011c). Assessment of Significance of Potential Impacts Alternating Current 400kV Substation 15.25 The proposed substation is a 400kV GIS design with associated air-cored reactive equipment. 15.26 Due to its design, GIS equipment does not produce an external electric field, therefore electric fields were not considered further. 15.27 It has been reported that magnetic fields produced by GIS are 20 to 60 % smaller than those of an equivalent air insulated design (Electric Power Research Institute, 1999). The metallic grounded GIS enclosures carry currents that oppose those of the high voltage conductors inside, so offer a degree of cancellation. 15.28 As part of the Code of Practice (DECC, 2011c), the Energy Networks Association maintains a list of types of equipment where the design is such that it is not capable of exceeding the ICNIRP exposure guidelines, i.e. a list of equipment that is therefore compliant with the guidelines. GIS substations without reactive equipment are deemed compliant with the exposure limits. Evidence for the demonstration of compliance with exposure guidelines is maintained at http://www.energynetworks.org/electricity/she/emfs.html. 334 15.29 The new GIS components of the substations will not result in a measurable change in the background magnetic field (see above) at the nearest residential properties located over 100m away. This is due to the rate at which magnetic fields reduce with distance from electrical transmission assets (see http://www.energynetworks.org/electricity/she/emfs.html for evidence). 15.30 At this stage the detailed configuration for the air-cored equipment cannot be confirmed until a supplier has been contracted and therefore a full assessment for the reactors cannot be performed. However, the configuration of this equipment during project implementation will ensure that the ICNIRP public exposure limit is not exceeded at the perimeter of the substation. Converter Station 15.31 The proposed converter station will be VSC technology. Until a manufacturer for the equipment has been appointed and the detailed configuration for the equipment confirmed a full assessment cannot be performed. However, specific EMF design criteria will be incorporated into the proposed converter station’s technical specification to ensure that the finalised design is compliant with public exposure limits at and beyond the converter station boundary. These specifications will ensure the following criteria are employed in the design: Static magnetic fields at the boundary fence of the proposed converter station site will not exceed the ICNIRP public exposure limits defined above; and AC magnetic fields at the boundary fence of the proposed converter station site shall not exceed the general public exposure limit defined above. High Voltage Direct Current Cables 15.32 The onshore underground HVDC cables will be installed using three separate techniques described in section 15.22. As the cables operate as a bipole system, the current in each cable runs in opposition leading to a significant cancellation of the magnetic field. The magnetic field for each design has been calculated at 1m above ground using the maximum current rating of the cable. Table 15.1 and Table 15.2 show the calculated magnetic field in the 3 different cable installations, including the maximum field and the field at perpendicular distances from the centre of the cables. All of the calculations are independent of the Earth’s geomagnetic field. Table 15.1: Calculated Magnetic fields for Trough and Surface Installed HVDC Cables Calculated DC Magnetic Field 1 m above Ground Cable Burial Depth Maximum Calculated Field 10m from Centre of Cables 50m from Centre of Cables 100m from Centre of Cables 1m 17.7 µT 1.47 µT 0.06 µT 0.02 µT 335 Table 15.2: Calculated Magnetic Fields for Horizontal Directional Drilling (HDD) Installed HVDC Cables Calculated DC Magnetic Field 1 m above Ground Cable burial depth Maximum Calculated field 10m from Centre of Cables 50m from Centre of Cables 100m from Centre of Cables 1.2 m 67.8 µT 7.34 µT 0.32 µT 0.08 µT 10.0 m 5.50 µT 3.27 µT 0.30 µT 0.08 µT 15.33 The calculations of magnetic fields demonstrate that the highest field produced by the onshore HVDC cables would be 67.8 µT when the cables are installed via HDD and at the minimum depth of 1.2m. At a burial depth of 10m, the maximum calculated magnetic field would be 5.5 µT. The closest residential property to the HDD installation is 80m away where the magnetic field is calculated to be 0.13 µT. All calculations were performed in accordance with the conditions set out in the Code of Practice (DECC, 2011c); using the maximum rating of the cables at 1 m above ground and ignoring harmonics. 15.34 The calculated magnetic fields for all installation methods are all below the precautionary level of 500 µT for static fields and are therefore compliant with exposure limits and present no indirect effects. Indirect Effects including EMC 15.35 Magnetic fields can affect Active Implantable Medical Devices (AIMDs), such as pacemakers, insulin pumps and defibrillators if the field strength exceeds the immunity of the device. All modern AIMDs should operate unaffected in field levels below the General Public Reference Levels (100 µT at 50 Hz) of 1999/519/EC and 500 µT static fields, where the AIMD has been implanted and programmed in a standard manner. 15.36 EU directive 90/385/EEC states that ‘Devices must be designed and manufactured in such a way as to remove or minimise as far a possible…risks connected with reasonably foreseeable environmental conditions such as magnetic fields, external electrical influences …’ 15.37 The maximum magnetic fields in a public area will be below 500 µT for static fields and the ICNIRP public exposure reference levels for 50 Hz will not be exceeded in areas where the public would frequent. Therefore, no interference with Active Implantable Medical Devices is expected. The Department of Energy and Climate Change (DECC) document National Policy statement for electricity infrastructure (EN-5, DECC, 2011b) states that “The Department of Health’s Medicines and Healthcare Products Regulatory Agency (MHRA) does not consider that transmission line EMFs constitute a significant hazard to the operation of pacemakers”. 15.38 One potential EMC issue arising from magnetic fields is the potential distortion of images on Cathode Ray Tube Visual Display Units (VDU) screens although these are less commonly used with modern television and computer equipment. The distortion to Cathode Ray Tube VDUs may occur, depending on the design and 336 orientation, in magnetic fields greater than 0.5µT. Liquid Crystal Displays (LCD) and plasma VDUs are immune to this interference. It is unlikely that VDU interference will occur, given the distance to the nearest business premises and properties. Mitigation 15.39 No mitigation is required for the proposed substation, converter station or cables as the assessment has demonstrated EMFs are within UK Government guideline levels. 15.40 If VDU interference is reported, it will be investigated and remedied if found to be due to the project. 15.41 There is potential for induction effects to arise on other metallic infrastructure from the magnetic fields of underground electricity cables. In the case of the HVDC onshore underground cables, there will be relatively weak magnetic fields and low probability of such effects arising. Where there are other installations such as cables and pipes which may run near or be crossed by the onshore underground cables, the Nemo Link developers will liaise with the owners and operators of these services to ensure that no adverse effects arise. This liaison and subsequent mitigation of potential effects by separation or other measures is standard practice for utility installations. Cumulative Impacts 15.42 Potential cumulative effects of EMF produced from the onshore elements of the Nemo Link in combination with other components of the Project (i.e. UK, French and Belgian subsea cables and Belgian onshore infrastructure) are described in Chapter 16. 15.43 Potential cumulative effects of the Nemo Link UK onshore infrastructure in combination with the grid connection required to facilitate the operation of the Nemo Link are described in Chapter 17. 15.44 In relation to potential cumulative effects from unrelated planned developments described in Table 1.2, Chapter 1, fields produced from the onshore infrastructure will combine with the fields already present in the area from other sources, which will vary with time depending on electricity usage. The way in which the fields combine with each other is complex; however, in this situation, where all the fields are well below guideline levels, it is not necessary to assess this in more detail as the combined field will also be well below guideline levels. Conclusion 15.45 The new 400kV GIS substation and converter station will be designed to ensure that both are compliant with ICNIRP public exposure guidelines for EMFs. The proposed substation’s GIS design already meets the Government adopted exposure limits demonstrated using the DECC code of practice. With all three installation techniques, it has been demonstrated that the HVDC cables would be compliant with exposure limits so there will be no significant EMF effects resulting from the Nemo Link. There is some scientific evidence of possible effects at lower levels, and the electricity industry takes this evidence seriously and recognises that it can generate public concern however the evidence has been extensively 337 reviewed, and the UK Government have not considered it appropriate to implement any restrictions or guidelines on the basis of this evidence. EMF Advice 15.46 National Grid takes the concerns of the public seriously, and operates a team of EMF Advisers to answer questions and address any concerns. The EMF Unit can be contacted on 0845 702 3270. Members of the public can speak to an EMF adviser directly on this number, and if necessary a home visit can be arranged to discuss queries and take measurements of electric and magnetic fields. The company also maintains a website with further information on all aspects of EMFs: www.emfs.info References International Commission on Non Ionising Radiation Protection (1998) Guidelines for Limiting Exposure to Time-Varying Electric, Magnetic and Electromagnetic Fields, Health Physics EU Council (1999) Recommendation of 12 July 1999 on the limitation of exposure of the general public to electromagnetic fields (0 Hz to 300 GHz) (1999/519/EC) International Commission on Non Ionising Radiation Protection (1994) Guidelines on limits of exposure to static magnetic fields, Health Physics Department of Energy and Climate Change (2011c) Power Lines: Demonstrating compliance with EMF public exposure guidelines. A voluntary Code of Practice Department of Energy and Climate Change (2011d) Optimum Phasing of high voltage double-circuit Power Lines. A voluntary Code of Practice Electric Power Research Institute (1999) Electric and magnetic fields management reference report TR-114200, 1st Edition Department of Energy and Climate Change (2011b) NPS for Electricity Network Infrastructure (EN-5) 338 339 340 16.0 PROJECT-WIDE ASSESSMENT OF EFFECTS Introduction 16.1 The Proposed Development for which planning permission is being sought forms part of a wider project known as the Nemo Link. The elements of the Project that fall outside the jurisdiction of the local planning authorities in Kent comprise high voltage direct current (HVDC) subsea cables passing through UK, French and Belgian waters, and onshore infrastructure in Zeebrugge, Belgium consisting of a converter station, substation and onshore cables (see Figure 1.1 and Chapter 2 Project Description). 16.2 Applications for consent for the other elements of the Project are being submitted to the relevant national authorities and each element has been subject to environmental assessment. Non-technical summaries of the environmental assessment documents for the other elements of the Project are appended to this ES (see Appendix 16.1. Please note the NTS documents for the marine cable in French waters is currently in the original language; a translation will be made available on the project website). The full environmental assessment documents for all elements of the Project can be viewed at http://www.nationalgrid.com/uk/Interconnectors/Belgium/Nemo+interconnect or/index.htm 16.3 This chapter summarises, for all technical areas, the likely significant effects that may arise from the construction and operation of these other components of the Nemo Link. This chapter also considers potential cumulative effects which may arise from construction and operation activities of the Proposed Development with any other element of the Nemo Link detailed above. Assessment of Potential Environmental Effects UK Subsea Cable 16.4 A summary of the effects of the UK subsea cable on the physical, biological and human environment is provided below. Physical Environment 16.5 The EIA considered impacts on geology, bathymetry & seabed processes and water quality with the conclusion that installation of the subsea cable would have no significant impacts. 16.6 The key sensitive and important geological area identified in the Sandwich Bay to Hacklinge Marshes Site of Special Scientific Interest (SSSI) will be avoided and therefore effects on geology are considered minor. Any effects of construction on bathymetry and water quality are also minor and not significant as the seabed will recover quickly with no long term effects predicted. Biological Environment 16.7 There are several conservation sites of importance within the subsea cable installation area, including Thanet Coast and Sandwich SPA, Sandwich Bay SAC, Thanet Coast SAC and the Thanet Coast and Sandwich Bay Ramsar Site. Effects on these designated sites and ornithology have been limited by routing the subsea 341 cable to avoid areas of greatest sensitivity. Effects will be further reduced by avoiding installation works within the intertidal areas during periods of greatest sensitivity to birds. 16.8 To avoid disturbance of areas of Ross worm Sabellariaspinulosa, the subsea cable has been routed away from Sabellariaspinulosa aggregations at distances agreed by Natural England. 16.9 Rock replacement at cable crossings will be limited so as to avoid substrate change however, where rock placement is necessary it is likely to have a beneficial effect on the local abundance and diversity of fish species. 16.10 Herring spawning areas may be moderately affected by subsea cable installation works however, as herring only spawn upon gravel seabed sediments for three months of the year, the key spawning period (November to January) will be avoided. 16.11 The subsea cable will not result in any significant effects on marine mammals. Human Environment 16.12 A 500m by 1000m safety zone will be established around installation vessels and the spread will be assigned two guard vessels to reduce any effects on shipping and navigation. 16.13 Vessels will comply with Collision Regulations lighting and marking requirements. There is potential for moderate impacts/risks upon shipping and navigation from vessel anchors snagging the subsea cable. The subsea cable will be adequately buried and the location of the cable will be marked on navigational charts. 16.14 All known wrecks have been avoided by the subsea cable route. Limited prehistoric material of interest has been identified. Where practicable temporary exclusion zones will be placed around important geophysical anomalies during construction and buffers with a radius of 100m will be placed around wrecks of archaeological potential. An archaeological reporting protocol will ensure that any material discovered during construction will be reported, recorded, stabilised and conserved. 16.15 During subsea cable installation, a Fisheries Liaison Officer will be employed to ensure that interactions between cable installation vessels, personnel and equipment and fishing activity are appropriately managed. 16.16 Effects on commercial fishing may occur from the use of rock placement that prevents the use of fishing gear at the seabed. Rock placement will be required at one crossing in the UK therefore the effect will be localised. 16.17 The subsea cable installation is not expected to have any impacts on socioeconomics offshore beyond those discussed in relation to commercial fisheries, recreation and tourism and other sea users. 16.18 There will be some temporary, site specific disturbance to recreation and leisure activities such as sailing, kite surfing and bird watching. There will also be some temporary, local impacts upon the natural character and visual amenity of the landfall area due to the presence of installation vessels and equipment. 342 French Subsea Cable Physical Environment 16.19 In France, the cable route crosses the borders of two of the sandbanks forming part of the area known as ‘Bancs des Flandres’. The sandbanks are composed of fine and gravelly sand, similar to that found in the Belgian and UK sections of the cable route. Although the cable route only crosses the borders of the sandbanks, the changes in the seabed processes could influence the movement of sediments around the borders or on the summits of the sandbanks. However, the terrain will quickly return to its natural state once cable laying activities are completed. Consequently there will be no long term change to the topography of the seabed. Biological Environment 16.20 In France it is recognised that the diversity of fish species is greater towards the south of the North Sea than in the central areas. The species found along the cable route are a heterogeneous coastal mix and it is difficult to identify with precision the exact species that could be impacted by the cable. 16.21 The effect on benthic organisms, one of the main food sources for the fish population, will be temporary, with the area quickly being recolonised post-cable lay by the surrounding communities. The cable route also avoids the most sensitive of the fish feeding and breeding areas as well as the zones frequented by protected marine mammals. 16.22 The cable route passes to the north of the protected Natura 2000 zone of the ‘Bancs des Flandres’. This is designated an area of importance by Directive 79/409 as a bird feeding zone, a passage of migration and an area of hibernation. The vessels linked to both installation and operation should not however have any more impact on the migration or feeding habits of birds than the vessels routinely using this area. 16.23 With regard to the Habitats Directive, the impacts on the flora and fauna will be temporary and localised. No protected marine mammal species frequent the sandbanks of this area. Human Environment 16.24 In France the cable route crosses an important navigational channel used to separate the vessels entering and leaving the Belgian ports. The impacts on shipping traffic are linked to the presence of cable laying vessels which have restricted capacity for manoeuvre and travel at low speeds crossing the path of vessels using the navigational channel. The presence of vessels could therefore create a temporary disruption to the control of shipping traffic in this area, both during the cable laying process with slow moving vessels crossing the path of navigation and during operation when maintenance vessels will be stationary with a safety zone of 2km. 16.25 This impact will be reduced by ensuring that cable joints, which will require the presence of stationary vessels for connection and maintenance, are not placed in the navigational channel. In addition, shipping routes are submitted in advance to CROSS Gris-Nez and the Préfecture Maritime de Cherbourg; during cable laying operations this information can be used to redirect marine traffic. 343 16.26 As with the navigational channel, the presence of installation or maintenance vessels may cause a temporary disruption to vessels accessing commercial fishing zones. The distribution of fishing zones is however vast and local fishing has a tendency to be situated in coastal areas. In addition, the season with the greatest fishing activity tends to be between October and December (inclusive), whereas the most favourable period for cable laying is from April to October. The impact on fishing will therefore depend upon whether the cable laying activities can be limited to a timescale outside the main fishing season. Belgian Subsea Cable Physical Environment 16.27 In Belgium, sand waves are located at several locations along the route, rising up to 6m above the surrounding seafloor. The sand waves are usually covered with smaller ripples. Pre-sweeping will result in an increased turbidity and sedimentation in the vicinity of the works. Due to the limited volume of sand to be moved and because of the high mobility and dynamics that sand waves already naturally exhibit, the impacts on sediment from pre-sweeping is considered small. 16.28 At crossings with other cables and pipelines, protective measures and bridges are proposed. In Belgian waters five existing cables and one pipeline need to be crossed. The protective measures disturb the original geological structure. However, given the very limited size of the protective measures, this effect is very limited. 16.29 No effect is expected on sediment quality from accidental discharges from ships and machinery during construction or due to loss of pollutants from the cables or from crossing infrastructures. 16.30 During pre-sweeping operations for cable burial and cable burial itself, there is potential for an impact on water quality arising from the release of existing heavy metals and organic pollutants within the sediment. As the pre-sweeping involves removal of coarse sediments with a low percentage of fine and organic material and consequently low concentrations of heavy metals, this effect is considered negligible. A temporary increase in localised turbidity will also arise from these activities. No long term effects are expected and this will be minimised by carrying out installation in quiet (low flow) weather when the natural turbidity is low and which will allow for quicker sedimentation of the disturbed seabed material. 16.31 As part of the overall safety system, there will be a clear procedure available which defines the roles and responsibilities and actions to be taken if an emergency should arise during installation, operation or decommissioning that could adversely affect water quality (e.g. oil spill). Biological Environment 16.32 In Belgium, both during the preparatory work and during cable laying the impacts upon the benthic habitat is considered negligible due to the size of the area affected and the temporary nature of the activities. Permanent habitat loss is unlikely to occur as the cables are entirely laid below the seabed at a minimum depth of 1 m and the benthic communities mainly occur in the first 20 cm of the sediment. It is anticipated that following construction, a natural recovery of the benthic community will occur in areas where there has been small scale disturbance. The effects on 344 fish in relation to ground disturbance are less pronounced due to the mobility of the species. 16.33 The potential effects of localised and temporary increases in turbidity upon benthic communities and habitat are considered negligible due to the existing ecosystem being well adapted to a sandy surface that is naturally in motion, the high mobility of fish species present and the limited size of the impact zone. Local seabird populations are accustomed to foraging in turbid water, and most species feed close to the surface. The effects of increased turbidity and sedimentation on birds are considered to be small. 16.34 There are considered to be no significant impacts upon benthic species and the surrounding seabed due to warming of the cable during operation due to the burial depth and, as the majority of benthic species reside within 20 cm of the surface of the seabed, the cooling effects of the seawater. 16.35 During the operational phase, an electromagnetic field (EMF) will be generated around the HVDC interconnector. The effects of EMF on the benthos is largely unknown. EMF can be detected by and affect certain sensitive species, but the extent of the impacts are not yet fully understood and there are thought to be variations at the individual level within species. Given the very local nature of the generated EMF during operation, the rapid decrease of field strength in relation to distance from the cables and the reduction of exposure of sensitive species as a result of cable burial (which creates a physical barrier of some thickness), the potential effects are considered to be negligible. 16.36 The increased presence of vessels and machinery can cause a temporary disturbance of birds, especially at the landfall. Due to the proximity of the port of Zeebrugge to the landfall area, the area already contains a relatively high activity/disturbance level primarily from busy shipping traffic. The effects upon birds are thought to be negligible. 16.37 No long term effects due to disturbance or noise are anticipated upon marine mammals or their migratory patterns in Belgian waters. It is expected that marine mammals will temporarily avoid the area during construction. Short term effects from this avoidance of the area are considered minor to negligible. 16.38 No significant impacts are predicted on the special protection areas SPA3 and SPA2 or the future SAC ‘VlaamseBanken’. Similarly no significant impacts on the quality of the habitat of porpoises are predicted during the construction, operation or decommissioning phases. Human Environment 16.39 In Belgium during the preparation work and the actual installation of the HVDC interconnector there will be a short term visual change of the seascape due to passage of several vessels and a temporary landscape change at the landfall. The perception of these activities can be assessed as negative (disturbance) or positive (point of interest). Both impacts are temporary and the impact is therefore considered to be negligible. Methods of communication with the public are to be explored to provide informative information regarding construction activities. 16.40 The positions of known wrecks were avoided during cable routing following consideration of the available data. Existing data was verified against the Side Scan Sonar data originating from the geophysical surveys which also served to identify 345 previously unknown wrecks to maximize avoidance of these historic features and minimise any potential impacts. If a previously unidentified wreck is discovered during construction, the competent authorities will be informed as soon as possible. 16.41 Disturbance to fishing grounds during construction is considered to be limited and temporary during the construction phase. Fishing grounds will be inaccessible during construction within a given distance from installation activity and associated works. 16.42 Potential damage to the cable caused by use of fishing gear is considered to pose a minimal risk at the burial depths anticipated. The Project is located in an area with existing subsea cables present. 16.43 No safety risks arising from damage to the cables are expected given the small risk of occurrence and the security mechanisms within the converter station. 16.44 Only minor negative effects are anticipated on tourism and recreation offshore during construction. The use of safety zones during construction means that a short term disturbance to recreational sea users may be experienced. The effects of this disturbance will be temporary and are considered to constitute a minor impact. The safety zones will be actively monitored during construction and communication with the coastguard will be maintained. 16.45 Communication will be maintained with the maritime agencies during the installation of the HVDC interconnector in the vicinity of the designated military areas. 16.46 If necessary, out of service telecommunication cables may be cut to allow for cable installation during construction. If this occurs, the appropriate health and safety and environmental precautions will be taken. Belgian Onshore Infrastructure 16.47 A summary of the effects of the Belgian onshore infrastructure on the physical, biological and human environment is provided below. Physical Environment 16.48 There will be no significant soil profile degradation in the area of the cable trenches. During construction, the top layer of soil will be removed and stored for later re-use. Once the trench is filled in, the top layer will be restored. No significant effects are expected at the converter station site. The site is, for the most part, already paved and the only soils present are of anthropogenic origin. 16.49 The re-use of excess soil from the trenches will be recorded in a Technical Report to avoid the risk of spreading any soil that is subsequently identified as being polluted. Any soils previously identified as being polluted will be decontaminated before work commences. 16.50 The site for the proposed converter station is mostly paved. The proposed development will result in an increase in permeable hard landscaping and consequently, the proposed development will lead to an increase in infiltration and a decrease in surface area run-off. The proposed development will meet the urban regulation on rain water wells, infiltration facilities, buffer facilities and separate discharge of sewage and rain water. 346 16.51 Groundwater drainage is necessary while making open trenches and can have an effect on the groundwater level and groundwater flow. The influence on pools and low-lying grounds is relatively small because of the low permeability. 16.52 The proposed route of the cables lies in a zone with shallow salinized groundwater (0-2m ground level). The duration and depth of the expected drainage is not of the nature that salinity will increase. A contribution to increased salinity can occur indirectly if freshwater is pulled from under the nature reserve, de Fonteintjes. Poor hydraulic contact between GraafJansader and the dunes to the north could cause significant groundwater and surface water reduction in the nature reserve. Considering the natural characteristics of de Fonteintjes, this should be avoided and any necessary mitigation measures will be applied. 16.53 Groundwater fluctuations during the exploitation phase can be avoided by the use of dolomite fragmentation and the application of clay stops. Consequently, significant effects to the groundwater level and groundwater flow will be avoided. 16.54 For the cables that are laid through directional drilling, the risk of impacts on archaeological heritage is deemed quite limited. An archaeological investigation will be carried out for the part of the HVDC cable that will be installed in an open trench. The archaeological investigation will be conducted in consultation with the Heritage Agency. 16.55 As a result of the previous activities pursued at the site where the converter station is proposed, it is expected that the soil has already been quite disturbed, which further reduces the likelihood of an impact on archaeological potential. No archaeological investigation is deemed necessary at this location. Biological Environment 16.56 The proposed development will cause temporary habitat loss as a result of the temporary storage of the cable ducts, creation of the construction area, excavation of the trenches for the HVDC cables, and construction of the underground jointing pits. 16.57 When drilling from the land, the ducts bundle would not be temporarily stored onshore, but would prepared at sea or installed on the beach. This would ensure only a temporary loss of habitat. 16.58 The HVDC cable will be installed through directional drilling underneath the beach, the special habitat protection area, the nature reserve and the ‘De Fonteintjes’ and ‘Oudemaarspolder’ ecological network. Directional drilling will not cause a loss of habitat within these protected areas. 16.59 Because of the temporary nature of the loss of habitat, and the restoration of habitat upon the completion of these works, significant effects will not occur. 16.60 Permanent loss of habitat occurs only as a result of the construction of the underground jointing pits and the converter station. 16.61 Because of the minimal area of permanent loss, the impact of the construction of the jointing pits is considered negligible. At the converter station, there is only permanent loss of the biologically less-valuable habitats. 347 16.62 Lowering of the groundwater level during drainage may have a drying-out impact on the local groundwater-dependent vegetation and species habitats. Increased salinity of shallow ground water is also a possible effect to be taken into account. The establishment of a dolomite base may also have a draining, and therefore drying-out effect. This effect might reach as far as into the De Fonteintjes nature reserve. 16.63 With regard to the possible effects to groundwater, additional investigations (which will include an Appropriate Assessment for the Natura 2000 areas), will be undertaken; appropriate mitigation measures will be identified to prevent significant adverse effects on the natural characteristics of these areas. Human Environment 16.64 The audible noise impact of the converter station (including the recommended mitigation measures) on the original ambient audible noise is negligible throughout the daytime and the evening. During the night, an increase in ambient audible noise perceptible by the human ear may occur at one measuring point. It can be concluded that during the day and the evening the total audible noise impact of the converter station (including the recommended mitigation measures) and the substation is negligible. 16.65 The HVDC cables will generate electric and magnetic fields. The electric field is completely screened by the metal sheath on the outside of the insulation around each conductor. Magnetic fields, however, are not screened by the metal sheath. 16.66 The magnetic fields produced by each cable have a cancelling effect as a result of laying the two cables close to one another. Because of the opposite flow direction of the two separate cables, the magnetic fields are also opposite and largely cancel out each other. In this way, the field strengths remain of the same order of magnitude as the earth's natural magnetic field. 16.67 Magnetic and electric fields will be produced by the converter station and substation equipment. At the site perimeter, the magnetic and electric field reduced reply from their sources and will comply with Government exposure limits set out in Chapter 15. No impact is expected as a result of the combination of the converter station and the substation. 16.68 The visual disruption during the construction phase is caused by the presence of temporary site buildings and soil storage. Upon completion of the work, the surface will be restored to its original condition. Because of the temporary nature of the impact, this is not considered significant. The work may cause disruption for people spending their leisure time on the beach, cyclists using the coastal cycle route, people living along Evendijk West, and residents of Veerbootstraat. The impact is considered limited due to the temporary nature of the works. 16.69 The jointing pits are constructed completely underground. The inspection pit will however be visible. As the size of the pit and the height of the structure above ground level are limited, there will be no significant visual disruption. 16.70 The trench itself and the construction area will take up land. After the trench has been backfilled, farming activities can be resumed, for both grazing and crop cultivation. Because of the temporary nature of this claim on land, this impact is considered limited. 348 16.71 The former military area has an industrial character, which is further enhanced by the presence of the harbour infrastructure and activities in the surrounding area. It is expected that the erection of a converter station in this area will have little impact on the character of the surrounding landscape. The architectural and landscaping design of the converter station is however being developed to fit the building into the landscape as naturally as possible. Cumulative Effects Land Use 16.72 There is no potential for cumulative effects on land use to arise from the UK onshore elements and any other aspect of the Nemo Link (subsea cables and Belgium onshore elements). Subsea cables are in the marine environment, rather than the land environment and in any case, once installed land and marine cables will have no cumulative effects on land use. Ground Conditions, Contamination and Hydrology 16.73 There is limited potential for cumulative effects on ground conditions or contamination effects; however, there is the potential for cumulative contamination effects during the installation of the onshore cables in the intertidal area and the subsea cables close to the foreshore through the release of contaminants into the water environment. Subsea cable installation procedures such as cable route clearance, sweeping and excavation have the potential to result in contamination effects. 16.74 Industry standard mitigation measures will be adopted during both installation phases to ensure individual and cumulative effects are not significant. For the intertidal cable, secure bunded areas for fuels, lubricants and chemicals as part of a detailed Construction Environmental Management Plan for the cables in the intertidal area will be implemented. For the subsea cables, effects are likely to be small in scale and localised; the potential for contamination affecting water quality has been assessed as not significant. 16.75 There is unlikely to be any significant cumulative effects on ground conditions, contamination and hydrology resulting from the UK onshore elements and the subsea cable works of the Nemo Link. Ecology 16.76 There is an area of overlap within the intertidal zone between the elements assessed under the UK Onshore Infrastructure and UK Subsea Cable elements. Ecological impacts within the intertidal zone during the construction phase are therefore included in both onshore and subsea assessments but as they only occur once, do not constitute cumulative impacts. No operational impacts are anticipated in the intertidal zone. 16.77 The onshore and intertidal construction and operational phases of the UK Onshore Infrastructure element of the scheme are not anticipated to impact upon any of the receptors including Sabellariaspinulosa reefs due to their physical isolation within subsea areas. No S. spinulosa reefs were identified within the intertidal zone during survey or consultation. No impacts are anticipated for herring spawning grounds or marine mammals due to physical isolation of the onshore works from the subsea habitats. 349 16.78 The geographical isolation of the UK onshore construction and operational components of the Nemo Link will ensure that there is no scope for significant cumulative impacts with construction and operational impacts of the French Subsea Cable, Belgian Subsea Cable and Belgian Onshore Infrastructure elements. Archaeology and Cultural Heritage 16.79 There is very limited potential for cumulative effects on archaeology and cultural heritage. The design of the cables includes mitigation through avoidance of known heritage assets to reduce direct impacts as far as reasonably possible. It is, however, likely that each element of the project could have physical impacts on geographically distinct non-designated heritage assets. While it is acknowledged that a documentary record is not as valuable as retaining the asset, these effects can be mitigated. The overall cumulative effect is therefore no greater than each individual residual effect, which is neutral assuming that suitable mitigation measures are implemented. 16.80 There is a recorded findspot of a Roman cup in the foreshore. The heritage asset does not indicate archaeological potential, and since it has already been removed, the site is considered of low importance. No effects are anticipated. All known wrecks have been avoided during subsea cable routeing; an archaeological reporting protocol will ensure that any material discovered during the installation will be reported, recorded, stabilised and conserved. 16.81 No significant cumulative effects on archaeology and cultural heritage are anticipated. Landscape and Views 16.82 Temporary cumulative landscape and visual effects are anticipated during installation of the underground cable (proposed as part of the UK onshore components) and the subsea cable works proposed within the UK intertidal area. The contractor’s compound, temporary fencing, construction plant and equipment (e.g. a winch), vehicle movements and cable trenching will be visible on shore, along with construction activity at the Transition Joint Pit (TJP). Large vessels required for laying and burying the subsea cable will be visible from the shore, and the sea where recreational sea users have views. Construction activities will temporarily disrupt landscape character and will reduce the visual amenity of the area. The significance of these temporary cumulative effects on landscape character and views will be minor adverse. On completion there will be negligible cumulative effects on landscape and views as proposed cables would not be visible in the landscape/seascape. 16.83 There will be no cumulative effects on landscape and views during construction and on completion of the UK onshore components and the subsea cable works within French and Belgian waters, and with Belgian onshore components, due to distance and no intervisibility between these development proposals. Traffic and Transport 16.84 Construction traffic will be localised and distant from traffic associated with other elements of the Nemo Link. During operation, traffic impacts on the local highway networks in Belgium and the UK are not significant. The geographical separation of 350 the UK and Belgium operational components will also ensure that there is no scope for significant cumulative impacts. Noise and Vibration 16.85 The operation of the converter stations and substations in both the UK and Belgium are not predicted to give rise to significant adverse noise or vibration effects. Noise and vibration during the construction phase (both UK and Belgium) are also not predicted to give rise to significant adverse effects. Their geographic isolation ensures that cumulative effects are unable to occur. 16.86 There may be temporary cumulative noise and vibration effects associated with the installation of the UK cables in the intertidal area (installation plant and machinery) and the installation of the subsea cables close to the intertidal area (installation plant and machinery and marine vessels). Such effects will however be of a temporary nature, localised and highly unlikely to result in significant cumulative effects. Air Quality 16.87 There is the potential for cumulative effects arising from construction traffic and plant and machinery associated with the UK intertidal and land cable installation works and marine vessels associated with the subsea cable installation works close to the intertidal area. Dust and vehicle emissions will be controlled during construction; none of the components of the Nemo Link will result in significant air quality impacts during operation as effects are temporary, of very low quantities and localised. No significant cumulative impacts on air quality will occur. Socio-Economics, Tourism and Recreation 16.88 The combination of the onshore UK intertidal cable installation works and the subsea cable installation works close to the intertidal area has the potential to give rise to cumulative effects on socio-economics, tourism and recreation. The main potential effect is likely to result from temporary disturbance to activities such as water sports and recreational activities including bird watching. 16.89 With the implementation of mitigation measures, there will be no significant adverse effects on tourism, recreation and socio-economic associated with the UK onshore works. The addition of the subsea cables installation is highly unlikely to result in adverse effects above the UK onshore effects due to their temporary nature. EMFs and EMCs 16.90 All components of the Nemo Link project will operate below public exposure guidelines for EMFs. There will be no individual or cumulative EMF effects resulting from the Nemo Link project as a whole. Conclusion 16.91 No significant cumulative adverse effects resulting from any aspect of the UK onshore elements with any other aspect of the Nemo Link are anticipated to arise during the construction or operation phases. 351 352 17.0 ASSESSMENT OF EFFECTS OF THE NATIONAL ELECTRICITY TRANSMISSION SYSTEM CONNECTION Introduction 17.1 This chapter provides an assessment of the potential effects of the connection of the Nemo Link to the national electricity transmission system (NETS). It also includes an assessment of the potential cumulative environmental effects arising from the UK onshore elements of the Nemo Link and the NETS connection. 17.2 A connection is required to enable the 1000MW capacity of the Nemo Link to be connected to the existing NETS. A site has been selected by NGNLL at Richborough for the proposed converter station and substation. There is no existing National Grid Electricity Transmission plc (NGET) 400kV infrastructure in the area surrounding Richborough to enable a connection to be made. There is therefore a requirement for a high voltage connection from the proposed substation to the existing NETS. 17.3 The NETS connection is required as a direct result of the Nemo Link; therefore it is appropriate to consider its isolated effects and cumulative effects with the UK onshore elements of the Nemo Link as part of this Environmental Statement (ES). 17.4 The NETS connection is the responsibility of NGET. NGET has a duty to connect electricity generators to the NETS and providing a connection is part of its statutory function as the holder of a licence to transmit electricity under Section 6(1)(b) of the Electricity Act 1989. 17.5 The form (type of technology) and route of the NETS connection are not yet known, do not form part of this planning application under the TCPA 1990, and will be promoted separately by NGET in due course. The type of consent required will depend on the type(s) of technology proposed for the connection. If an overhead line is proposed for all or part of the connection, a development consent order (‘DCO’) will be required under the Planning Act 2008. If an underground cable is proposed for all of the connection, the proposed installation would be undertaken as permitted development under Part 17, Class G of the Town and Country Planning (General Permitted Development) Order 1995. Should an underground cable be proposed for part of the connection however, it would form part of a DCO application. 17.6 In developing the NETS connection, NGET assesses and examines strategic options and, based on this, develops route corridor options before the selection of the preferred route corridor option. As part of developing the NETS connection, NGET would carry out appropriate consultation and environmental studies. If an application for development consent under the Planning Act 2008 is required, NGET would undertake the consultation process prescribed under the Planning Act 2008 and Environmental Impact Assessment as set out in the Infrastructure Planning (Environmental Impact Assessment) (EIA) Regulations 2012. NGET anticipates that, if a DCO application is required, it will be submitted to the Planning Inspectorate in the third quarter of 2015. Should a proposed connection consist entirely of underground cables installed as permitted development, EIA would not be an automatic statutory obligation. In those circumstances, NGET would come to a view as to whether an EIA was required under the Town and Country Planning (Environmental Impact Assessment) Regulations 2011. Appropriate consultation 353 and environmental studies would be undertaken in the event that EIA was not applicable for underground cables. 17.7 Although the consortium promoting the Nemo Link includes a National Grid group company, it is important to understand that NGNLL and NGET are separate legal entities and their statutory roles in relation to the Nemo Link and the NETS connection are clearly segregated under the Electricity Act 1989. The operation of an electricity interconnector is a separately licensable activity under section 6(1)(e) of the Electricity Act 1989. The Act expressly provides that the same person (which includes a company) may not hold an interconnector licence and a transmission licence. NGET is obliged to enter into a Bilateral Connection Agreement with NGNLL as would be the case for all other customers seeking a NETS connection. Connection Options 17.8 The NETS connection is required to be made at a point on the system where capacity is either available or can be achieved and can be made in accordance with NGETs statutory obligations under the Electricity Act 1989. NGET’s obligations under Section 9 and Schedule 9 of the Electricity Act 1989 respectively are: ‘Develop and maintain an efficient, co-ordinated and economical system of electricity transmission’; and ‘To have regard to the desirability of preserving natural beauty, of conserving flora, fauna and geological or physiographical features of special interest and of protecting sites, buildings and objects of architectural, historic or archaeological interest’. 17.9 The proposed substation from which the NETS connection is to be made is part of the Proposed Development the subject-matter of this application and is to be sited adjacent to the proposed converter station at the former Richborough Power Station site. Due to the lack of existing high voltage electricity infrastructure in the area surrounding the proposed Nemo Link substation, NGNLL considers that it is likely that the NETS connection could be made between the proposed substation at Richborough and one of the following three existing high voltage NGET substations on the NETS (see Figure 17.1): Canterbury North; Cleve Hill; or Kemsley. 17.10 NGNLL understands that all three connection options would offer the appropriate capacity for the required connection and that if any additional reinforcement work is required for any option, it would be limited to localised works. 17.11 The NETS connection could be made using a variety of technology options as follows: 17.12 AC overhead line; AC underground cable (cross linked polyethylene - XLPE); or AC gas insulated line (GIL). The NETS connection could be made using one of the technology options detailed above for its entirety, or a combination of two or all three technology options. 354 Method of Assessment 17.13 As stated above, the NETS connection could be made via AC overhead line, AC underground XLPE cable or AC underground GIL. An overhead line would likely consist of a 400kV double circuit connection using pylons approximately 50m high and spaced approximately 360m apart. An XLPE underground cable would typically comprise a construction swathe for two AC circuits, consisting of two cables per phase, between 35-50 m wide. Underground GIL is a new technology option not yet installed as part of the UK transmission system other than for very short lengths in substations. It would also consist of a trench installation, using a slightly smaller trench than the underground XLPE cable. There would be little difference between the two types of underground technology in terms of potential environmental effects (both during construction and operation). For the purpose of this assessment, reference from this point forward is made to a potential overhead line or underground NETS connection option; the latter may be by XLPE underground cables or GIL. Assessment of Potential Environmental Effects of NETS Connection Options 17.14 This section provides an assessment undertaken by NGNLL of the potential environmental effects of the NETS connection options detailed above. Land Use 17.15 Effects on land use (regardless of the connection option selected) during construction will be localised and temporary. Any land temporarily affected during construction would be reinstated to enable previous land uses to continue. Whilst there would be some permanent land take associated with overhead line connection options, this would be insignificant in terms of the local land resource. Permanent land take associated with an underground option would also be very small; most existing land uses above the completed works would be able continue including farming, roads, open space and public rights of way. 17.16 An underground installation would, in some circumstances result in permanent constraints to future land uses. The permanent easement above would need to be kept clear of buildings and structures to allow access for repairs or maintenance. Careful routeing could ensure minimal impact on existing and future land uses. Specific land uses within employment and housing sites (such as open spaces and footpaths) would be able to be accommodated above an underground connection. Significant land use effects are considered unlikely to occur. Ground Conditions and Contamination 17.17 There are no sites designated nationally for their geological/geomorphological interest in the area and the local geology and soils pose no particular constraint to either underground options or the construction of an overhead line. There is a Regionally Important Geological site north of the former power station site but there should be no effects on it from the NETS connection (regardless of the connection option selected)). Contamination risk will be very low and could be addressed through the adoption of typical construction mitigation measures. Significant effects on ground conditions and contamination are considered unlikely to occur. 355 Hydrology and Flood Risk 17.18 Once operational, neither underground cables nor overhead line options are anticipated to have significant effects on water resources or flood risk. Underground technologies will be installed below ground and overhead line tower foundations would occupy a very small footprint; therefore the potential for adverse effects on surface water run-off is low. Whilst there is the potential for different effects on surface water and groundwater during construction, depending on the nature and extent of construction activity a number of pollution prevention, flood protection and attenuation mitigation techniques can be implemented in accordance with policy and guidance notes to ensure no significant risks occur. Ecology 17.19 There is the potential for all potential connection options (whether by overhead line or underground) to have the following effects on nature conservation designations: 17.20 Thanet Coast and Sandwich Bay SPA and Ramsar - Potential for disturbance of breeding and overwintering bird species and potential for bird collision risk through construction and operation of overhead lines. 17.21 Stodmarsh SAC and Blean Complex SAC - There is the potential for habitat impacts arising from loss of Annex I habitats. There is also the potential for impacts on Annex II species through direct construction activities, habitat loss and habitat alteration resulting from changes in hydrology. 17.22 Stodmarsh SPA – There is potential for disturbance of breeding and overwintering bird species and potential loss of habitats supporting breeding and overwintering birds. Potential collision risk through construction and operation of overhead lines only. 17.23 Stodmarsh Ramsar Site - Potential loss of wetland habitats affecting wetland invertebrates. Potential changes in habitats through direct impacts and changes in hydrology. Potential disturbance of breeding and overwintering bird species and potential loss of habitats supporting breeding and overwintering birds. Potential collision risk through construction and operation of overhead lines only. 17.24 East Blean Woods SSSI - Potential loss of areas of primary deciduous woodland in the Blean Woods complex north of Canterbury. This may also impact insect fauna. 17.25 West Blean and Thorndon Woods SSSI - Potential loss of ancient semi-natural woodland and conifer plantation; also potential impacts on breeding birds and invertebrates. 17.26 Stodmarsh SSSI - Potential loss of wetland habitats, impacting invertebrate fauna and nationally significant breeding bird populations. 17.27 Sandwich Bay to Hacklinge Marshes SSSI - Potential temporary loss and disturbance of mudflats, saltmarsh and grassland habitats. Potential disturbance of migrating birds and wintering populations of waders. 17.28 Preston Marshes SSSI - Potential loss of fen vegetation. 356 17.29 Chequers Wood & Old Park SSSI – Potential loss of woodland and unimproved acidic grassland. 17.30 There is the potential for four potential connection options (Cleve Hill and Kemsley; overhead line or underground) to have the following effects on nature conservation designations: 17.31 The Swale SPA – Potential for disturbance of breeding and overwintering bird species and potential loss of habitats supporting breeding and overwintering birds. Potential for bird collision risk through construction and operation of overhead lines only. 17.32 The Swale Ramsar - The potential loss of wetland habitats affecting wetland invertebrates. Potential changes in habitats through direct impacts and changes in hydrology. Potential disturbance of breeding and overwintering bird species and potential loss of habitats supporting breeding and overwintering birds. Potential collision risk through construction and operation of overhead lines only. 17.33 The Swale SSSI - Potential loss of areas of freshwater grazing marsh notable for the internationally important numbers of wintering and passage wildfowl and waders, important breeding populations of a number of bird species and outstanding assemblages of plants and invertebrates. 17.34 Church Woods, Blean SSSI - This site is one of the most extensive areas of broadleaved woodland remaining in the Forest of Blean. No direct impacts anticipated. 17.35 Ellenden Wood SSSI - Potential loss of ancient woodland. 17.36 Careful route alignment would likely ensure that the potential for significant adverse effects on such designated nature conservation areas could be avoided or minimised as far as possible (subject to detailed routeing at a later date). Archaeology and Cultural Heritage 17.37 Careful route alignment (both overhead line and underground) and the siting of towers would minimise effects to the extent that significant effects on archaeology and cultural heritage could likely be avoided (to be determined at detailed routeing stage). The following potential environmental effects have been identified. Canterbury North Overhead Line and Underground Connection 17.38 There is the potential for adverse permanent (overhead line) and temporary (underground construction) effects on the setting of the World Heritage Site of Canterbury, the Schedule Monument (SM) of Richborough Castle and the Sarre Anglo-Saxon Cemetery SM. There is also the potential for adverse permanent and temporary effects on the setting of a number of Conservation Areas, Listed Buildings and as yet unidentified below ground archaeology. 357 Cleve Hill Overhead Line and Underground Connection 17.39 There is the potential for adverse permanent (overhead line) and temporary (underground construction) effects on the setting of the World Heritage Site of Canterbury, the SM of Richborough Castle, the Sarre Anglo-Saxon Cemetery SM, the Thornden Wood Bowlbarrows SM and the Graveney Marshes Medieval Salterns SM. There is also the potential for permanent and temporary adverse effects on the setting of a number of Conservation Areas, Listed Buildings and as yet unidentified below ground archaeology. Kemsley Overhead Line and Underground Connection 17.40 There is the potential for adverse permanent (overhead line) and temporary (underground construction) effects on the setting of the World Heritage Site of Canterbury, the SM of Richborough Castle, the Sarre Anglo-Saxon Cemetery SM, the Thornden Wood Bowlbarrows SM, the Graveney Marshes Medieval Salterns SM and the Castle Rough Medieval Moated Site SM. There is also the potential for permanent and temporary adverse effects on the setting of a number of Conservation Areas, Listed Buildings and as yet unidentified below ground archaeology. Landscape and Views 17.41 Adverse effects on landscape and views could be mitigated by the careful siting of towers and overhead lines at the detailed design stage. The following potential environmental effects have been identified. Overhead Line Connection 17.42 The main designations in the area are the Kent Downs AONB, the North Kent Plain National Character Area and the North Downs National Character Area; the Greater Thames Estuary National Character Area is in the area around a connection option to Cleve Hill and Kemsley. There is the potential for the overhead line (all connection options) to be viewed from within the AONB; however, the OHL would not be routed directly through it and would be unlikely to affect its wider setting. There is the potential for effects on landscape and views, including from nearby settlements; the extent of adverse visual effects would be greater for a Cleve Hill connection and greater still for a Kemsley connection due to the increased length of the overhead line. The loss of woodland would be difficult to avoid near Canterbury (Cleve Hill and Kemsley connection options only) (subject to detailed design). Underground Connection 17.43 An underground connection is not likely to have any landscape or visual effects on the North Downs AONB, the North Kent Plain National Character Area, the North Downs National Character Area or the Greater Thames Estuary National Character Area (the latter relevant to Cleve Hill and Kemsley connection options only). There would be temporary effects on landscape character and views during the construction phase; there is also the potential for additional effects associated for example with the loss of trees. Traffic and Transport 17.44 Once operational, the effects on traffic and transport will be negligible for all options as traffic movements would only be required for infrequent routine repair and 358 maintenance. Construction works will involve the transport of plant and machinery and work personnel to sites. The effects will be temporary and such movements are not expected to result in increases in traffic on the local highway network above thresholds where significant effects are considered to occur. Traffic during construction can be appropriately managed via the production and implementation of a Transport Management Plan. Significant traffic and transport effects are considered unlikely to occur. Noise and Vibration 17.45 Underground options would not give rise to noise and vibration during operation. The National Policy Statement for Electricity Networks (EN-5) states that noise from overhead lines is unlikely to lead an application to be refused as a variety of mitigation measures are possible, such as the positioning of lines and the design and maintenance of conductors. Noise during the construction phase for underground and overhead options would be temporary and localised and is capable of mitigation using well established industry-standard techniques. Significant noise and vibration effects are considered unlikely to occur. Air Quality 17.46 Neither underground nor overhead line options would have any effects on air quality during the operational phase. During construction, both cable laying and the construction of an overhead line have the potential to generate dust and emissions from plant and machinery and associated traffic movements. These effects however would be temporary and localised. Dust and other emissions are capable of mitigation using well established industry-standard techniques. Significant air quality effects are considered unlikely to occur. Coastal Tourism, Recreation and Socio-Economics 17.47 None of the connection options would affect any major areas of economic activity or tourist assets of national importance. During the detailed design stage for the connection, any effects on recreation areas during construction (e.g. temporary closure and diversion of footpaths) will be appropriately managed to ensure disturbance and inconvenience is kept to a minimum. Effects will be localised and temporary and are considered unlikely to result in significant adverse effects. There may be some temporary beneficial effects during the construction period; personnel employed will use local goods and services which will be provided by local businesses, catering or hotel facilities. The purchase of materials, equipment and services during the construction phase may have a minor beneficial effect on the creation of temporary and permanent jobs locally and nationally within the supply chain. Electric and Magnetic Fields 17.48 Electric and magnetic fields from overhead or underground connections will combine with the fields already present in the area from other sources, which vary with time depending on electricity usage. The way in which the fields combine with each other is complex, however, in this situation, where all the fields are well below guideline levels, it is not necessary to consider the details of this, as the combined field will also be below guideline levels. 359 Assessment of Cumulative Potential Effects of the UK Onshore Elements of the Nemo Link and the NETS Connection 17.49 Project related cumulative impacts have been considered in this section; these are the combined potential impacts that may occur between the UK onshore elements of the Nemo Link to which this application relates with the NETS connection project. The construction of the NETS connection is anticipated to take place in 2017 at which point the construction of the converter station and substation will either be complete or largely complete. The extent of construction overlap is therefore anticipated to be small. Land Use 17.50 There is little potential for cumulative effects on land use during any simultaneous construction of both developments. The onshore cable route, converter station and substation site associated with the Nemo Link have been carefully selected to minimise disruption on the future use of land. The proposed Nemo Link assets comprise underground cables that would be installed in land distinct from and without any substantial relationship with the land which may be affected by the NETS connection. The other Nemo Link assets would be constructed on the site of the former Richborough Power Station which is distinct and does not have any material land use relationship with land outside of the site which may be affected by an NETS connection. 17.51 There would be some permanent land take associated with NETS overhead line connection options (comprising the land at the base of the pylons) although this would be insignificant in terms of the local land resource. Permanent land take associated with an underground connection would also be very small; generally existing land uses above the completed works would be able to continue including roads, open space and public rights of way. An underground installation would, in some circumstances result in permanent constraints to future land uses. A permanent easement above the cables would be required to enable equipment to be accessed for repair or possible maintenance. A permanent easement would prevent buildings or structures being installed above the cables. Careful routeing should ensure minimal impact on existing and future land uses (including land allocated for development). Some land uses in employment and housing sites (such as some open spaces and footpaths) would be able to be provided where underground cables have been installed, subject to appropriate masterplanning. 17.52 Effects on land use from the Nemo Link and from the NETS connection would be low in magnitude and importance and would be localised. Cumulative effects on land use are not anticipated as there is little ‘overlap’ or relationship between the land which would be affected in each case. Ground Conditions and Contamination 17.53 There is little scope for any cumulative effects arising from ground conditions and contaminated land associated with construction of the NETS connection and construction of the Nemo Link. 17.54 There are no sites designated nationally for their geological or geomorphological interest in the surrounding area or on the former power station site and the local geology and soils pose no particular constraint to installation of underground options or the construction of an overhead line. There is a Regionally Important Geological site north of the former power station site but there should be no direct 360 or indirect effects on it from the Proposed Development of the Nemo Link or the NETS connection. 17.55 There will be a small part of the NETS connection (the connection to the proposed substation, relevant to all connection options) at the former power station site that could theoretically give rise to cumulative effects if contamination was encountered during those works whilst works on the Nemo Link also encountered contamination. Contamination risk in this area will however be very low and is capable of being addressed through the adoption of typical construction mitigation measures as detailed at Chapter 6. 17.56 Outside of the former power station site, there is no known pathway or mechanism by which there would be interaction between works required for a connection and the works for the Nemo Link. When the route of the NETS connection is known, an assessment will be undertaken of the potential for contamination and mitigation measures will be identified where appropriate. 17.57 As the Nemo Link will not adversely affect soils, geology and contamination and there is little scope for the connection to result in adverse effects, cumulative effects are not anticipated. Hydrology and Flood Risk 17.58 There is the potential for cumulative effects on surface water, groundwater and flood risk, depending on the nature and extent of construction activities associated with the connection options. It is considered that cumulatively the effects will be insufficient to result in adverse effects on water resources as appropriate mitigation measures will be implemented during construction to prevent the occurrence of adverse isolated and cumulative effects. 17.59 Current planning policy, government and EA guidance (National Planning Policy Framework, National Policy Statements and EA Pollution Prevention Guidance) control development in terms of attenuation, flood protection levels and discharge quality. Additionally, the quality standards of the Water Framework Directive quality standards are being introduced through legislation and the pending introduction of the National SUDS Standards. 17.60 Upon completion of the NETS connection, underground cables and the foundations of overhead line towers occupy a relatively small footprint and are very unlikely to result in significant flood risk due to loss of flood storage. 17.61 As both the NETS connection and Nemo Link development will pose no significant effects in relation to flooding, drainage and water quality to the surrounding area (assuming construction standard mitigation measures are implemented correctly – see Chapter 7 for further details of mitigation measures), no cumulative effects are predicted to occur during construction or operation. Ecology 17.62 Potential impacts on Natura 2000 sites from works relating to the onshore elements of the Nemo Link and the different NETS connection options are identified in paragraphs 17.19 – 17.36 above, ES Chapter 8 (Ecology) and ES Appendix 8.9 (Information for Habitats Regulations Assessment). 361 17.63 Although the sites are generally designated for different habitats and species, Thanet Coast and Sandwich Bay, Stodmarsh and The Swale Natura 2000 sites all support important populations of breeding and overwintering birds. There is therefore potential for habitat loss and disturbance impacts at multiple sites (from any of the potential connection options) resulting in a greater cumulative impact on birds using these sites and moving between them. Such effects could be mitigated by careful routeing of the NETS connection to avoid such direct and indirect effects. Installation works could also be timed to be undertaken outside of the main migratory periods. Assuming such mitigation can be implemented, there are no anticipated cumulative effects on Natura 2000 sites. 17.64 Sandwich Bay to Hacklinge Marshes SSSI is the only nationally designated site that may potentially be affected by both the UK onshore elements of the Nemo Link and NETS connection options. 17.65 Due to the proximity of Sandwich Bay to Hacklinge Marshes SSSI to the former power station site, the installation of overhead lines or underground cables (for any of the potential connection options) has the potential to adversely impact on this site; however direct effects are considered unlikely to occur. The Nemo Link HVDC underground cable would pass through a separate part of this designated area bringing potential for cumulative effects. Additionally the HVDC underground cable passes through the Sandwich Bay to Hacklinge Marshes SSSI within the intertidal area of Sandwich Bay and Stonelees Nature Reserve, and will result in temporary losses of saltmarsh and grassland habitats. It is considered that with careful routeing, the connection route could avoid the SSSI, avoiding risk of cumulative effects occurring on this site. 17.66 The connections options are a separate project to the Nemo Link and appropriate consents will be sought separately by NGET if required under the relevant legislation. NGET’s proposed connection (once selected) will be subject to similar environmental assessments to the UK onshore elements of the Nemo Link; this will also enable effects on localised flora and fauna to be assessed and mitigation measures to be identified where appropriate. Significant impacts on the identified receptors will be avoided through design and mitigation, without which the necessary consents for the works will not be obtained. Following the implementation of mitigation measures, potential cumulative effects are considered to be of negligible significance. Archaeology and Cultural Heritage 17.67 For all connection options, it is assumed that an overhead connection would leave Richborough and head west. The potential for cumulative effects on the setting of heritage assets will only occur where effects of the substation and converter station overlap with the effects of the overhead line. Infrastructure more remote from the converter station and substation could have separate effects on the setting of cultural heritage features (see paragraphs 17.37 – 17.40 above); however, such effects would be assessed by NGET as part of the connection proposal and would not result in cumulative effects with the UK onshore elements of the Nemo Link. 17.68 As the NETS connection project is in the early stages of development by NGET, it is not possible to assess specific potential effects in detail. There is however potential for an overhead line to affect the setting of designated heritage assets. The assessment has determined that the construction of the converter station and substation will not result in any harm to the historic environment through historic landscape impacts or development within the setting of a heritage asset. Therefore, 362 the Proposed Development will not contribute to any cumulative effects on the historic environment in combination with a NETS connection. 17.69 An underground connection and foundations of an overhead line tower have the potential to affect buried archaeology. The design of the underground connection would reduce direct impacts as far as reasonably possible, but physical impacts on geographically distinct non-designated heritage assets are possible. While it is acknowledged that a documentary record is not as valuable as retaining the asset, these effects can be mitigated. The overall cumulative effect is therefore no greater than each individual effect, assuming that suitable mitigation measures are implemented. Landscape and Views 17.70 If the NGET connection were to be delivered by underground cable, provided significant tree and hedgerow clearance could be avoided by careful routing, there would be no cumulative effects on landscape and views following reinstatement of the land above the cable swathe. The potential for cumulative effects by an underground connection is not considered further in this assessment 17.71 If the connection were to be provided by an overhead line, there would be cumulative landscape and visual effects in combination with the proposed converter station and substation. The western extent of the connection option i.e. whether the connection extends to Canterbury North, Cleve Hill or Kemsley does not affect cumulative landscape and visual effects. Cumulative effects will only occur where effects of the proposed substation and converter station overlap with the effects of the overhead line (relevant for all overhead line connection options), which is discussed below. 17.72 The extent of the area within which landscape and visual cumulative effects, as a result of the converter station and substation development and a 400kV overhead line connection, would be experienced extends across the approximate Zone of Visual Influence (ZVI) identified in Figure 10.2. The anticipated residual visual effects of the converter station and substation beyond approximately 3km are neutral and the anticipated residual landscape effects on the landscape at this distance would also be neutral. Accordingly cumulative effects on landscape and views are only of direct relevance within approximately 3km of the proposed converter station and substation site. 17.73 The magnitude of effect that would be experienced by the landscape within approximately 3km would be reduced by the presence of three existing 132kV overhead lines. Two of the 132kV overhead lines run parallel and close to one another in a westerly direction from the former Richborough Power Station site along the valley floor. The third 132kV overhead line runs south west from the former power station site, avoiding the higher ground at Richborough Roman Fort before continuing south. The landscape also contains a single wind turbine and two masts (the masts are approximately 90m high) which are west of the converter station and substation site. Overall the cumulative landscape effects of a 400kV overhead line connection and the proposed converter station and substation development would be no greater than moderate adverse. 17.74 Cumulative visual effects would be experienced by a few sensitive visual receptors in closer proximity, particularly users of the Saxon Shore Way and river users immediately south of the converter station and substation site which would have unobscured views of both developments. In addition, it is anticipated that visitors to 363 Richborough Roman Fort and nearby residents, residents on Ebbsfleet Lane, and the PROW network between Minster and Cliffs End would also experience cumulative visual effects. In some of these locations, views are already restricted to an extent by existing built form and vegetation. 17.75 The magnitude of effect that will be experienced by visual receptors within this area would be reduced by the presence of three existing 132kV overhead lines, referred to above. Although, a 400kV tower could be approximately 20m taller than the existing 132kV towers, depending on the alignment of a potential new overhead line connection, existing 132kV towers could form a larger component in some views. Existing views also include the single wind turbine and two masts west of the proposed converter station and substation site. Overall the significance of cumulative visual effects would be no greater than moderate adverse. Traffic and Transport 17.76 Construction works for the UK onshore elements of the Nemo Link and the connection (overhead or underground) will involve the transportation of plant and machinery and personnel. Cumulative effects on the road network are only likely to arise in the surrounding area of the converter station and substation where travel routes are shared for the two developments. 17.77 Traffic movements associated with the construction of the converter station and substation are expected to be far greater than those associated with the connection (overhead or underground). The traffic and transport assessment for the converter station and substation concludes that the construction phase will result in a maximum increase in road traffic of 0.9% and a maximum increase in HGV traffic of 17%. Potential effects for both the NETS connection and the UK onshore elements of the Nemo Link will be temporary and localised and will be subject to appropriate mitigation(via a Transport Management Plan) to ensure that effects are not significant. Overall the significance of residual cumulative effects on traffic and transport would be unlikely to be greater than those reported for the converter station and substation. 17.78 Once operational, the NETS connection and the UK onshore elements of the Nemo Link will not result in any adverse individual or cumulative traffic and transport effects as vehicles will only be required infrequently for repair and maintenance. In addition, the substation will be unmanned and only six workers will operate the converter station per day. Noise and Vibration 17.79 The underground NETS connection options would not give rise to noise and vibration during the operational phase. Overhead lines are generally quiet but can make a slight crackling noise in damp weather conditions; however, this noise quickly dissipates within tens of metres from the source. The National Policy Statement for Electricity Networks notes that noise from overhead lines is unlikely to result in an application being refused as a variety of mitigation measures are possible, such as the positioning of lines and the design and maintenance of conductors. No significant individual or cumulative noise effects are anticipated during the operation phase. 17.80 Construction activities associated with both undergrounding and the erection of an overhead line have the potential to generate noise and vibration. These effects would be temporary and localised and can be appropriately mitigated via the 364 implementation of industry standard measures and by using well established best practice techniques discussed at Chapter 12 – Noise. It is anticipated that in the vicinity of the former power station site (where cumulative effects are most likely to occur), such mitigation measures will ensure that cumulative effects can be appropriately managed to ensure noise and vibration effects are not significant. Air Quality 17.81 Construction activities associated with both the UK onshore elements of the Nemo Link and either an overhead or underground NETS connection have the potential to generate dust and emissions from plant and traffic movements that could adversely affect air quality. These effects would be temporary and once away from the former power station site, construction traffic would rapidly disperse across the local road network. Significant air quality effects can be avoided through the implementation of industry standard mitigation measures as detailed in Chapter 13. 17.82 Underground or overhead line NETS connection options would have no effects on air quality during the operational phase. The operation of the Nemo Link will not result in adverse effects on air quality. No cumulative effects on air quality are therefore predicted. Coastal Tourism, Recreation and Socio-Economics 17.83 With the implementation of mitigation measures (see Chapter 14), there will be no significant adverse effects of the UK onshore elements of the Nemo Link on tourism, recreation and socio-economics. None of the NETS connection options would affect any major areas of economic activity or tourist assets of national importance; there is little scope for any cumulative effects from the NETS connection in combination with the Nemo Link development. During the detailed design stage for the connection, any effects on recreation areas during construction (e.g. closure and diversion of footpaths) will be appropriately managed to ensure disturbance and inconvenience is kept to a minimum. Effects will be localised and temporary and will not result in significant adverse cumulative effects. Electric and Magnetic Fields 17.84 Electric and magnetic fields from overhead or underground connections and the UK onshore components of the Nemo Link will combine with the fields already present in the area from other sources, which vary with time depending on electricity usage. The way in which the fields combine with each other is complex, however, in this situation, where all the fields are well below guideline levels, it is not necessary to consider the details of this, as the combined field will also be below guideline levels. Conclusion 17.85 For the majority of the environmental topic areas, potential adverse effects will be temporary and localised. Adverse construction effects can also be avoided or reduced through the implementation of best practice industry standard mitigation and prevention measures. 17.86 Potential temporary and permanent effects on ecology (including loss of habitat and collision risk), archaeology and cultural heritage (including Scheduled Monuments, Conservation Areas and Listed Buildings) and landscape and views (including the Kent Downs AONB and a number of National Character Areas) could arise from any of the connection options. 365 17.87 Careful route alignment by NGET would likely ensure that the potential for significant adverse effects on designated areas could be avoided or minimised as far as possible (subject to detailed routeing at a later date). 17.88 The construction and operation of the NETS connection, which is required for the operation of the Nemo Link, has the potential to result in cumulative environmental effects when considered together with the construction and operation of the UK onshore elements of the Nemo Link. 17.89 Potential cumulative effects during the construction period are largely localised and of a temporary nature. Appropriate mitigation measures can be implemented by NGET to ensure that no significant cumulative effects occur. For construction effects with the potential to be longer lasting and/or permanent (e.g. ground conditions and hydrology), the implementation of best practice industry standard mitigation and preventative measures will also ensure that significant cumulative effects can be avoided. 17.90 Potential cumulative effects during the operation period are largely minimal and localised and are not anticipated to be significant. There is potential for cumulative ecological effects on Thanet Coast and Sandwich Bay, Stodmarsh and The Swale Natura 2000 sites (disturbance to breeding and wintering birds using these sites and moving between them). Such effects could potentially be mitigated through the development of the detailed design of the connection and identification of mitigation measures. Environmental assessment work will also be undertaken for the connection option to determine the significance of likely effects and appropriate mitigation. The cumulative operation effects on landscape and views (if an overhead line is proposed) are anticipated to be no greater than moderate adverse due to the presence of existing infrastructure in the surrounding area including three 132kV overhead lines, a wind turbine and two masts. 17.91 At a time when the nature and extent of the NETS connection is finalised, consent under the relevant legislation will be applied for by NGET separately (as detailed above at paragraphs 17.5-17.7) to this planning application for the UK onshore elements of the Nemo Link. All potential relevant environmental effects and appropriate mitigation of the connection will be assessed and identified separately by NGET to provide sufficient information to the relevant authority to enable consents (if required) to be granted under the relevant legislation. 366 367 368 18.0 SUMMARY AND CONCLUSIONS Introduction 18.1 This concluding chapter presents a summary of the proposed development. It also provides a summary of the main conclusions arising from the environmental assessment of the Proposed Development. 18.2 The Nemo Link is a proposed high voltage direct current (HVDC) electrical interconnector which will allow the transfer of electrical power via subsea cables between the UK and Belgium. The UK onshore elements, for which planning permission under the Town and Country Planning Act 1990 is being sought, comprise a converter station, substation and cables installed below the ground between the converter station and the mean low water mark. 18.3 Alternative converter station sites, underground cable routes, landfalls and subsea cable routes were considered as part of the development of the Nemo Link. This established that a converter station site at Richborough and an underground cables route to a landfall at Pegwell Bay was the preferred option as this best meets the project objective relating to technically feasibility, economic viability, deliverability and the least disturbance to the environment and people. Alternative options are included at Appendix 3.1 of the Environmental Statement 18.4 Following selection of the preferred option, further detailed environmental and technical studies as well as consultation have been used to refine the preferred option and further reduce the potential environmental effects of the Nemo Link project including the substation which the convertor station is required to connect to. This included considering emerging results from environmental assessments with initial technical designs and results of consultation with stakeholders, land owners and local communities. Proposed Development 18.5 The components forming the Nemo Link Interconnector in the UK requiring planning permission under the Town and Country Planning Act 1990 will comprise: Two HVDC subsea cables between the landfall and the low water mark; Two HVDC onshore underground cables from the converter station to the landfall on the coast at Pegwell Bay where they will be joined to the subsea HVDC cables; Fibre optic cables installed with the onshore and subsea HVDC cables for the purposes of operational telemetry and communications; An HVDC converter station on part of the site of the former Richborough Power Station; A 400kV electricity substation on part of the site of the former Richborough Power Station; and Three 400 kilovolts (kV) high voltage alternating current (HVAC) underground electricity land cables to connect the above substation to the high voltage direct current (HVDC) converter station and up to two telecommunications cables for telemetry, control and protection purposes only. 369 HVDC Subsea Cables 18.6 The cables will be one of two subsea cable types: Cross Linked Polyethylene (XLPE) or Mass Impregnated (MI). The cables will be rated between 350kV and 500kV. The size of the subsea cables will depend on the final design and rating but will be approximately 15cm diameter. The cables will be bundled together in the same trench and jointed to the HVDC onshore underground cables in the transition joint pit (TJP), an excavated pit (15m long x 5m wide x 2.5m deep) with a reinforced concrete plinth laid in its base. HVDC Onshore Cables 18.7 The onshore underground cables will be of the same type as the HVDC subsea cables (XLPE or MI) which will minimise the complexity of the joint at the TJP. The diameter of each of the onshore underground cables will be approximately 15cm. The distance from the TJP to the converter station is approximately 2.3km. The fibre optic cables will be installed with the onshore underground cables and will be approximately 50cm in diameter. 18.8 The onshore underground cables will be installed onshore in three distinct ways along the length of the route as follows: Standard trenching; Surface laid with capping; and Horizontal directional drilling (HDD). Converter Station 18.9 The converter station will occupy a footprint of approximately 5 hectares (ha) and it is proposed that the main building will be constructed around the steel frame of the former Richborough Power Station’s turbine hall. The converter station will be designed for a 40 year lifespan and will be approximately 30.3m tall at its highest point. 18.10 Other components of the converter station include a service building, a storage building, converter transformers, a mechanically switched capacitor (MSC) approximately 11.75m high, a shunt reactor, a distribution network operator (DNO) substation (providing 11kV auxiliary power), a diesel generator and outdoor high voltage electrical equipment which consists of busbars, circuit breakers, switches, insulators and other connecting equipment. The tallest elements of the converter station (other than the main building) will be the service building and the overhead gantries which are approximately 15m high. Substation 18.11 A new 400kV Gas Insulated Switchgear (GIS) substation is required to connect the interconnector to the national grid electricity transmission system. The 400kV substation forms part of this planning application, however, the connection between the substation and the national grid is still in early development and does not form part of this planning application. 18.12 The substation will be built in a separately fenced compound immediately west of the proposed converter station and will be connected to the converter station by underground high voltage alternating current (HVAC) cables. 370 18.13 The proposed substation will occupy a footprint of approximately 2.65ha, and will contain indoor and outdoor electrical equipment. It includes a GIS Hall containing the switchgear, outdoor Gas Insulated Busbars (GIB), overhead line gantries, two Supergrid Transformers (SGTs), a Mechanically Switched Capacitor (MSC) and a Static Var Compensator (SVC) compound. The MSC and SVC are specific types of equipment used to regulate and stabilise transmission voltages. 18.14 The GIS Hall will be approximately 52.2m long, 21.5m wide and 15m high and clad similar to the external appearance of the converter station. The maximum height of the outdoor electrical equipment will be approximately 12.7m. HVAC Cables 18.15 Three 400kV HVAC cables and two telecommunications cables will connect the converter station to the 400kV substation. The HVAC cables will be cross-linked polyethylene (XLPE) type and will be approximately 150mm in diameter. The total length of the HVAC cables route is approximately 200m. Environmental Impact Assessment 18.16 The Proposed Development to which this planning application relates is not considered to fall under Schedule 1 or Schedule 2 of the Town and Country Planning (Environmental Impact Assessment) Regulations 2011 and therefore EIA is not required. However, taking into account the environmental obligations imposed on the holder of an interconnector licence by Schedule 9 and Section 9 of the Electricity Act 1989, and the relationship of the Proposed Development (subject to this planning application) to the wider Project (part of which is subject to formal EIA under Belgian law), National Grid Nemo Link Ltd has decided to prepare and submit a voluntary Environmental Statement to accompany this application for planning permission. Summary of Potential Environmental Effects 18.17 The site selection and response to the technical constraints have resulted in a development proposal in which the environmental effects have been reduced or eliminated in the majority of disciplines to such an extent that there are few significant residual effects. A summary of the likely effects is described below and any effects that are not considered to be significant have been described within the preceding chapters and are not included here. 18.18 Land Use – Predicted effects from the installation and construction of the Proposed Development are localised, temporary and of minor significance. These include effects on including effects on Stonelees Nature Reserve, BayPoint sports complex, Pegwell Bay County Park, associated open space and recreation routes and part closure of the foreshore and traffic disturbance associated with an increase in construction traffic movement. The onshore underground cables have been routed so that they will not prevent any future development proposals within Pegwell Bay Country Park; however, there will be restrictions on planting above the cables route. The proposed converter station and substation would make a positive contribution as it would result in the re-use of derelict land contributing to national and local policy sustainability objectives. 371 18.19 Ground Conditions – Any potential effects will be eliminated through the implementation of appropriate best practice and industry standard mitigation both during construction and operation. 18.20 Hydrology and Flood Risk - Any potential effects will be reduced to minor significance through the implementation of appropriate best practice and industry standard mitigation both during construction and operation. A sustainable drainage system will be implemented on site to ensure surface water run-off is adequately controlled and will not result in a pollution risk to nearby watercourses and groundwater. 18.21 Ecology – the construction and operation of the converter station and substation will not have a significant impact on nature conservation due to the lack of ecologically sensitive features within the site. The cable has been routed to minimise effects on important species and habitats and cable installation works will be timed to avoid or minimise impacts on breeding birds, nesting birds and natterjack toads. Different sections of the cable will be installed at different times depending on the timing constraints within each section. Overall a minor adverse to minor benefical impact is predicted during construction. No impacts have been identified during operation. 18.22 Archaeology and Cultural Heritage – No significant impacts on above ground or shallow archaeological deposits are predicted; however, a watching brief is proposed during cables installation to identify the presence of unknown archaeological deposits. Following the implementation of a programme of mitigation, the archaeological and cultural heritage resource within, and close to, the development site will remain unaffected and the overall impact of the scheme is neutral. 18.23 Landscape and Views – The construction and operation of the converter station and substation will result in moderate adverse visual effects on recreational users of the Saxon Shore Way and the River Stour but the residual impact will be reduced to moderate/minor by mitigation, including landscaping, and is not considered to be significant. Mitigation measures would reduce the significance of effect of the proposed converter station and substation on landscape character to minor adverse to neutral. New planting around the site and at the site entrance would improve the landscape quality of the site and would assist in integrating the proposed development into the sites context. The significance of effect on landscape of the underground cable route, and above ground section capped with chalk, would remain neutral on completion with mitigation and after establishment. 18.24 Traffic and Transport – Minor adverse effects will be limited to the construction phase and will be localised and temporary. The percentage increase with regard to total traffic on each of the routes assessed is under 1%; the highest percentage increase in HGV traffic was calculated to be 17% along A256 Dover Road. In all other instances the percentage increase in HGV traffic was under 10%. There will be no significant residual effects following the implementation of mitigation measures including the preparation and implementation of a Transport Management Plan. 18.25 Noise and Vibration – Mitigation will be incorporate into the design of the converter station and substation to ensure that the noise target (assessed noise levels no higher than the background noise levels) is achieved. Construction noise will be minor to neutral significance with the exception of horizontal directional drilling which will be of moderate significance; this activity is temporary and would be expected to occur over 6 days and 3 nights. 372 18.26 Air Quality – Following the implementation of mitigation measures, which consist of well-established industry-standard techniques, effects on air quality resulting from construction traffic and dust generating activities will be localised, temporary and of negligible significance. 18.27 Coastal Tourism, Recreation and Socio-Economics - With the implementation of mitigation measures, there will be no significant adverse effects on tourism, recreation and socio-economics. The proposed development will bring benefits to the area during construction through some direct employment and through use of local businesses. 18.28 Electric and Magnetic Fields - The assessment has demonstrated that no mitigation will be required because the EMFs are within UK Government guidance levels and there will not be any significant effects arising from the NEMO link. 18.29 Cumulative Impacts – No significant cumulative adverse effects resulting from any aspect of the UK onshore elements with any other aspect of the Nemo Link are anticipated to arise during the construction or operation phases. There are no predicted long-term cumulative effects resulting from the Proposed Development and other development proposals in the study area. Any potential effects are likely to be localised and temporary during construction and can be mitigated by the use of well-established techniques. No significant cumulative adverse effects resulting from any aspect of the Proposed Development with the grid connection that will be required to connect the Nemo substation to the national electricity transmission system (whether by overhead line or underground cable) are anticipated to arise during the construction or operation phases. Mitigation 18.30 Mitigation measures have been proposed to avoid, offset or reduce impacts where these are predicted. A schedule of the proposed mitigation measures is included below. 373 Table 18.1: Schedule of Mitigation Measures Mitigation Schedule Land Use The working width associated with cables installation will be kept to a minimum to reduce disturbance to adjacent land; Temporary working areas and access roads will be fully reinstated following construction; The laydown area will be reinstated to its current standard and it will be made available for future use by the developers of Richborough Energy Park; Access to the Viking Trail and Thanet Coastal Path will be retained where possible during the construction period. Where there is a Health and Safety requirement to prevent or reduce access, appropriately signed diversions will be agreed and put in place; Any public access restrictions will be minimised as much as possible and limited only to periods of major construction activity such as earthworks; Temporary signage advising visitors of construction activities will be erected. This will include signs within the car park of Pegwell Bay Country Park to ensure that visitors are aware of construction activities being undertaken; Contractors will prepare a Construction Environmental Management Plan (CEMP) prior to the commencement of construction. This will include measures to ensure good construction practices are adopted on site; Measures to ensure construction activities do not result in any disturbance to land users surrounding the former power station site will be developed in consultation with the site owners and operators. This will include ongoing communication and liaison, measures to address site access and movement and working hours; A Transport Management Plan (TMP) will be prepared and implemented prior to the commencement of construction activities; Working hours during periods where recreational activity is greatest (i.e. evenings and weekends) will be limited as much as possible; and Measures to control dust and noise will be adopted during the construction period. Ground Conditions and Contamination Prior to construction works commencing, targeted investigation works will be undertaken in agreement with an Environmental Health Officer to assess the nature and extent of potential groundwater contamination associated with the historic pollution incidents at the northern and southern ends of the cable route. Where pollutant linkages are identified, a robust remediation method statement will be compiled to detail the necessary mitigation measures. Within Pegwell Bay Country Park, investigation works will be undertaken to assess the nature and depth of capping materials overlying the landfill area. Should investigation works identify a need for the construction phase to penetrate the landfill materials (i.e. in the vicinity of the proposed joint pit) then a robust remediation method statement will be compiled to detail the necessary mitigation measures. 374 Mitigation Schedule Fuels, lubricants, and chemicals required during construction and operation will be stored in secure bunded areas at appropriate distances from watercourses with refuelling restricted to these areas. Spill kits will be available on site in case of emergency. Standard design criteria will ensure components containing oil and lubricants are contained within bunded areas. Pollution prevention measures will be adopted including measures to intercept and treat run-off prior to leaving site and the use of cut-off ditches and filtration systems. A CEMP will be prepared which will set out methods which contractors will be required to undertake as a minimum. The CEMP will include quality control procedures to be employed for the import and export of materials to and from site. Methods for controlling surface water run-off and dust and measures to remove contaminated materials off site to licensed treatment or disposal sites will also be detailed. Should apparently contaminated material be found during excavation works, where this has previously not been identified, work will cease until the material has been characterised and appropriate measures to dispose of contaminated materials have been identified. Contaminated materials will be characterised both chemically and physically in line with BS EN 14899:2005 –‘Characterization of Waste Sampling of Waste Materials - Framework for the Preparation and Application of a Sampling Plan’. Registered waste carriers will only be used to convey any contaminated waste materials off site to suitably permitted facilities. All relevant documentation will be completed and kept in line with regulations. The laying of cables over the surface of the ground within Pegwell Bay Country Park will prevent potential contamination pathways being opened and prevent migration of landfill gas and leachate should these be present within the landfilled area. Measures will be undertaken to reduce the amount of water entering excavations so as to minimise dewatering activities. Should dewatering be required, the Environment Agency will be consulted and appropriate abstraction and discharge licences will be obtained if necessary. Prior to disposal to surface water bodies, water will be treated to ensure it meets appropriate water quality standards. Soils excavated through areas of open trenching will be monitored to ensure they are free from contamination and suitable for re-use. Upon completion of the HDD works, surplus-drilling fluids will be pumped out of the launch and receptor pits by vacuum tanker and removed from site to a suitable registered waste disposal facility by a registered waste carrier. Where elevated concentrations of sulphates have been identified through the area of the proposed converter station and substation, appropriate classes of concrete, resistant to sulphate attack will be used to mitigate this. 375 Mitigation Schedule Hydrology and Flood Risk General Measures to prevent pollution of the water environment (including measures to control and manage silt-laden run-off, control mud deposits and prevent spillages/leaks) will be set out within a Construction Environmental Management Plan (CEMP). Good practice guidance will be based on EA Pollution Prevention Guidance. The following measures will be included in the CEMP: Where feasible, suitable construction techniques will be adopted to ensure that no migration pathways are created to jeopardise groundwater quality; Appropriate storage and handling measures for all hydrocarbon fuels and lubricating oils, including the use of bunded storage areas or the use of double-skinned storage tanks; The use of drip trays for static plant and designated refuelling areas for mobile plant; The implementation of appropriate spillage contingency measures to mitigate the effect of such spillages on the surface water; and Appropriate personnel awareness training of the potential environmental implications of all construction work on site. The prevention of silt-laden run-off and mud entering the surrounding surface water drains and watercourses by: o Timely site phasing and engineering, thus minimising un-surfaced and un-vegetated areas of the site; o The provision of measures to intercept and treat run-off prior to it leaving site, including the use of peripheral cutoff ditches, settlement facilities, filtration and/or use of flocculants to effect the removal of water borne particulates; and o The provision of wheel-cleaning equipment for site plant to prevent the tracking of mud onto the public highway and therefore into the off-site surface water drainage systems. A Storage and Spillage Emergency Response Plan will be in place, which will include: The storage and use of fuel and oils on site in accordance with the Control of Pollution (Oil Storage) (England) Regulations 2001; Fuel and other potentially polluting chemicals stored well away from watercourses in a secure impermeable and bunded storage area (minimum capacity 110% of the storage capacity of the tank); Refuelling of plant in a designated area at the site compound only; Maintenance of vehicles in a designated area at the site compound only; Fixed plant will be self bunded and/or part of a controlled containment system in accordance with EA Pollution Prevention Guidance; Mobile plant will be in good working order, kept clean and fitted with drip trays where appropriate; Spillage kits and absorbent material will be carried by mobile plant; The site will be secured to prevent vandalism that could lead to a pollution incident; 376 Mitigation Schedule Designated concrete wash out areas will be constructed in accordance with good practice guidance and will be clearly identified and used; An Emergency Response Plan will be prepared and construction workers trained to respond to spillages; and Construction waste or debris will be prevented from entering any waterbody. Surface Water HDD is proposed for the cables between the BayPoint sports complex sports fields and the former power station. This will avoid surface disturbance of the recently constructed roundabout on the A256, avoid disturbance to Minster Stream and also avoid disturbance to a compartment of Hacklinge Marshes Site of Special Scientific Interest (SSSI). Cables installation by HDD will not require modifications (temporary or permanent) to the stream or interruptions in its flow. All utility services associated with the development, including re-use of existing surface water outfalls from the former power station site, will be designed to ensure their long-term fitness for the purpose, and will be appropriately tested prior to commission to demonstrate their integrity and maintained throughout their use. Appropriate sustainable drainage methods will be implemented as part of the detailed drainage strategy for the converter station and substation site to ensure surface water run-off is effectively managed and discharge rates are no greater than pre-development levels. Appropriate methods will be adopted during construction to contain and control runoff from the temporary laydown facility and provide pollution control. Water Quality In accordance with the draft Sustainable Drainage Standards, the storage and handling of materials on site would require at least three levels of treatment prior to discharge to a sensitive watercourse (River Stour identified by the EA as sensitive). These levels could be provided by; d) e) f) The infiltration trench; Settlement/containment lagoon; and Petrol interception prior to the outfall. A further source of potentially contaminated waters will be the oily water associated with the petrol interceptors and sumps within the main sites. Each will be a contained structure and will require off-site removal to a suitably licensed disposal facility (or ultimately to a suitable off-site foul sewer, subject to Southern Water approval). 377 Mitigation Schedule Flood Risk Appropriate mitigation measures will be put in place during construction works in accordance with legislative requirements and good site practice guidance to prevent flooding during construction from the risks identified. Measures will be put in place during construction to ensure that the runoff from site is not increased. Temporary drainage systems may be required to ensure that this is met. The temporary drainage systems and systems of work will also take account of the potential for overland flow from outside of the site to cause flooding on site. Measures will be implemented during construction to prevent debris and other material entering temporary or permanent drainage systems or watercourses. This can be achieved through provision of temporary drainage, construction stage SuDS, and appropriate site management. During the construction phase, if groundwater levels are high, appropriate techniques will be utilised to mitigate the risk, such as dewatering and ground freezing. If groundwater dewatering is required, it is likely pumps will be used to abstract the water from the excavations, and it is likely that the pumped water will be discharged into the River Stour. Consent will be sought from the EA for any temporary discharge to the watercourse. The CEMP will describe the main construction compound locations and storage areas. Flood risk is to be part of the consideration in determining the locations of these elements of the works. A Flood Plan will detail appropriate actions in the event of a flood and will include suitable evacuation procedures, safe egress route and a plan showing the location of assembly points. The substation building and MSC and SVC compound will be raised above the 1 in 1000 year (plus climate change) level and the converter station building and compound and the remaining substation compound will be raised above the 1 in 200 year (plus climate change) level. The impact on the extent of flooding outside the site area due to land raising will be negligible for most flood events. Ecology Method Statements will be produced prior to any works within designated areas detailing how impacts on the habitats and species within the area will be reduced or avoided. These will be produced in consultation with NE and KWT. Pegwell Bay Designated Areas The route of the subsea and onshore underground cables and location of the TJP and other joint pits have been chosen to avoid ecologically sensitive receptors wherever possible. The subsea cable and landfall are within areas of saltmarsh south of the area previously disturbed by the installation of the Thanet Offshore Wind Farm cable. This will avoid disturbance to the more extensive areas 378 Mitigation Schedule of saltmarsh habitats south of Pegwell Bay Country Park the cable corridor. Prior to commencement of works within the saltmarsh habitats, an inspection of the habitats will be undertaken by an ecologist to determine the presence of on-going nesting activity. If active nests are identified, the commencement of works in the vicinity of the nest site will be delayed until the nest is no longer in use. A Method Statement will be agreed with NE prior to commencement of works. Works within the intertidal areas will be timed to avoid the periods most sensitive to wintering birds and nesting birds using the habitats. Works within the intertidal areas will therefore be undertaken between June and August. Site compounds will be located outside of the Pegwell Bay designated areas. No equipment, materials, chemicals or fuel will be stored within or adjacent to designated areas. Compounds within the Richborough Site and Pegwell Bay Country Park will be used for the storage of equipment, materials and chemicals. All refuelling of plant will be undertaken within the site compounds, within the Richborough Site and Pegwell Bay Country Park. All suitable plant and equipment working in the designated sites will be bio oil based. A site checklist will be used for traffic management and plant to ensure they are all in good working order. Drip trays or plant nappies will be used under all mobile or small plant such as generators etc. Delivery vehicles will deliver to the site compounds to reduce disturbance and risk of spillages and leaks within the designated areas or wider areas. All plant and equipment working in the vicinity of the shore line shall be clean on delivery. If not all tracks, wheels etc. shall be thoroughly cleaned before entering the working area. Generation of silt shall be minimised by excavators/dumpers etc. by limiting movements by machinery. Plant will be regularly washed down in a bunded area and issuing water will be collected and disposed of off-site. Dedicated skips shall be provided for disposal of materials off-site (segregated where possible). A contingency plan for spillages etc. will be produced prior to start on site. Spill kits will be available in the site compound and all working plant. Prior to the start of installation works the saltmarsh areas that are to remain untouched by the works shall be visibly segregated from the works area using temporary fencing. An ecologist shall advise as to locations of these habitats and placement of protective fencing. 379 Mitigation Schedule Machinery required to access the intertidal areas will be restricted to set routes to limit the area impacted. Vegetation that will be directly affected by cable installation works will be removed by cutting turves. The turves will be stored locally and will be replaced following completion of cable installation and backfilling of the trench. Different saltmarsh and grassland communities will be stored separately and replaced based on the NVC habitat types in each part of the saltmarsh. Removal, storage and replacement arrangements and removal will be determined through production of a Method Statement in consultation with Natural England. Reinstatement of habitats will be undertaken in sections as the cable installation is completed and immediately following backfilling. Excavated material on the mudflat habitats will be replaced as quickly as possible to avoid leaving exposed trenches at times of high tide. There will be no loss of mudflat habitats as part of the works but the disturbance of the mudflats through excavation of sediments will be unavoidable. Following installation of the cable and TJP the working area within the saltmarsh will be fenced to allow saltmarsh vegetation to reestablish without further disturbance. Monitoring surveys of the affected saltmarsh will be undertaken for five years following construction and the results will be submitted to NE and KWT. Monitoring surveys of intertidal invertebrates will be undertaken annually for a period of 5 years following the cable installation works to determine the recolonisation rates of the disturbed areas of mudflat habitats. Pegwell Bay Country Park In the northern section of Pegwell Bay Country Park, the cable will be laid on top of the existing ground level to avoid disturbing the underlying landfill. Chalk will be used to cover the cables and will be graded into the surrounding ground levels. The graded chalk will then be used to create a swathe of chalk grassland through the north of the park, connecting to the area of existing chalk capped area in the southern section of the Country Park. This will increase habitat and provide habitat for more diverse range of native species. Stonelees Nature Reserve Habitats As far as is practical, the working width associated with cables installation will be kept to a minimum and be kept close to the existing cycle path. Impacts will be reduced to habitats within the previous working area of the cycle path, affecting as little of the previously undisturbed habitats as possible. Site compounds will not be located within Stonelees Nature Reserve. No equipment, materials, chemicals or fuel will be stored within or 380 Mitigation Schedule adjacent to designated areas. Compounds within the Richborough Site and Pegwell Bay Country Park will be used for the storage of equipment, materials and chemicals. All refuelling of plant will be undertaken within the site compounds, within the Richborough Site and Pegwell Bay Country Park All suitable plant and equipment working in the designated sites will be bio oil based. A site checklist will be used for traffic management and plant to ensure they are all in good working order. Drip trays or plant nappies will be used under all mobile or small plant such as generators etc. All plant and equipment working in the vicinity of the shore line shall be clean on delivery. If not all tracks, wheels etc. shall be thoroughly cleaned before entering the working area. Generation of silt shall be minimised by excavators/dumpers etc. by limiting movements by machinery. A contingency plan for spillages etc. shall be produced prior to start on site. Spill kits will be available in the site compound and all working plant such as dumpers/excavators. To inform the production of a Method Statement for works within Stonelees Nature Reserve, an NVC survey will be undertaken of areas to be affected by the proposals. Information obtained as part of the survey will be used to produce a Method Statement in consultation with Natural England detailing mitigation and working methods to be used during installation of the cable. Prior to commencement of works within Stonelees Nature Reserve, temporary fencing will be installed around the site working areas to ensure encroachment into surrounding habitats is avoided. Grassland habitats to be affected by trenching and cable installation works will be removed in turves and replaced following reinstatement of subsoil areas. Removal, storage and replacement arrangements and removal will be determined through production of a Method Statement in consultation with Natural England. Reinstatement of habitats will be undertaken in sections as the cable installation is completed and immediately following backfilling. Wintering Birds Cable installation works within the designated areas saltmarsh and modified grassland of Pegwell Bay will commence outside the months that peak numbers of birds using the intertidal and saltmarsh habitats are present (October to February for lapwing, golden plover, turnstone and grey plover and May for turnstone, sanderling and grey plover). Cable installation works within the intertidal and saltmarsh areas will not be undertaken during this period. This will also apply to any cable installation works within 50m of the seaward edge of the 381 Mitigation Schedule Country Park to prevent disturbance from the use of machinery on the edge of the park. In the event of delays resulting in the cable installation works within the intertidal area extending into the sensitive period for wintering birds, further mitigation will be supplied. Where possible, wooden hoarding will be used to visually screen the works from birds using the bay. For the duration of the extended working period an additional warden will be supplied to help deter members of the public entering the intertidal area during works. Cable installation within this area will be undertaken following a Method Statement produced in consultation with KWT and NE. Breeding Birds including Redshank Installation of the onshore cable, TJP and subsea cable within the saltmarsh habitats north of the Country Park will be phased to avoid the peak nesting period for species, such as redshank, that use the saltmarsh habitats for nesting purposes (Mid April to July). During this period no works will be undertaken within 100m of the pool within the saltmarsh habitats to avoid disturbance to nesting redshank. Prior to the commencement of works within the saltmarsh habitats, a walkover survey will be undertaken to determine the presence of any active nests and if necessary works will be postponed until nests are no longer active. Methods used during this survey and works within the saltmarsh will be detailed in a Method Statement. Removal of vegetation for cables installation within Pegwell Bay Country Park and Stonelees Nature Reserve will be undertaken outside of the bird nesting season (March-August inclusive) or will be preceded by an inspection by an ecologist for active nests immediately prior to vegetation removal. Removal of vegetation within the converter station and substation site will be undertaken outside of the bird nesting season (MarchAugust inclusive) or will be preceded by an inspection by an ecologist for active nests immediately prior to vegetation removal. Replacement planting within the converter station and substation site will replace nesting habitat removed prior to the start of the development. Protected Flora Pre-commencement surveys of the cable route will be undertaken to identify any protected species of flora within the working area. In the event that any protected plants are discovered, these plants will either be fenced out of the working area or transplanted to undisturbed locations as appropriate to their requirements. Where practical, measures will be implemented to encourage recolonisation of the working areas by these species (e.g. seed selection). These methods will be detailed within Method Statements covering the working methods of cable installation. 382 Mitigation Schedule Natterjack Toads A licence will be obtained from Natural England to allow the cable installation works that may affect suitable natterjack toad habitats within 500m of the reintroduction site within Stonelees Nature Reserve. As part of the licence application, a Method Statement will be produced in consultation with KWT and NE. The details of the licence will be determined during the licence application process, but are likely to include a combination of the timing of works to avoid disturbance to potential hibernation features during the winter months (NovFeb), habitat management and controls to reduce disturbance effects and translocation. Arisings from the trench excavation works can be used to create suitable amphibian refugia, following agreements with KWT and NE. Reptiles A repeat survey of suitable reptile habitats will be undertaken prior to the cable installation works. This information will be used to produce a reptile Method Statement detailing the methods that will be used to install cables within these areas and the locations of these methods. The Method Statement will be produced in consultation with Kent Wildlife Trust. Vegetation within areas affected by works between Pegwell Bay Country Park and the TJP and within Pegwell Bay Country Park and Stonelees Nature Reserve will be managed prior to works to degrade habitat suitable for use by reptiles. Potential refugia will also be removed from the working area and placed within suitable undisturbed habitats. Vegetation removal will be implemented outside of the bird nesting period (March to August inclusive) or will be subject to inspections by an ecologist prior to removal. Habitat management and cable installation will be undertaken between April and September when reptiles are most active due to higher temperatures. Following completion of cable installation the ground will be reinstated either through seeding the chalk bunds in the north of the Country Park or by replacing original topsoil where excavations have taken place. Arisings from the excavation works can be used to create reptile refugia in suitable undisturbed areas of the Country Park. Bats The converter station and substation external lighting scheme would typically only be used for emergencies and during maintenance activities required outside hours of daylight. This will ensure that potential bat foraging and commuting habitats are not detrimentally affected. Watercourses, Ditches and Water Vole The working area for cables installation within Stonelees Nature Reserve will be maintained as a minimum of 5m from the ditch that runs parallel to the proposed onshore cable route. This will avoid disturbing any water voles that may be present within the ditch. River Stour, European Eel, Atlantic Salmon and River Lamprey 383 Mitigation Schedule The converter station and substation external lighting scheme would typically only be used for emergencies and during maintenance activities required outside hours of daylight. This will ensure that fish migration along the River Stour is not detrimentally affected. Archaeology and Cultural Heritage Mitigation with regard to cables installation via open trenching is proposed for predicted impacts to the post-medieval coastguard station (RSK HM1) in the form of a watching brief during construction works. A watching brief will also be maintained during the cable installation to ensure that any previously unrecorded archaeological remains are identified and recorded during groundworks. A watching brief with regard to Pleistocene and Palaeolithic remains will be undertaken during any deep excavations (i.e. excavations beyond the modern overburden) related to the scheme. Both phases of the watching brief would be undertaken in line with a Written Scheme of Investigation agreed with KCC in advance of the fieldwork, and followed by a programme of analysis and reporting also to be agreed with and delivered with KCC. Landscape and Views The mitigation of likely construction effects on landscape and views would be largely achieved through the implementation of a Construction Environmental Management Plan which would include the following measures: Protection of trees to be retained to BS 5837 (2005), for the duration of the construction works; Screening on-site activity where practical whilst at the same time not being a highly negative visual distraction in itself; Management of site traffic to and from site, minimising excessive traffic movement on the surrounding road network; and Management of working times to minimise visual effects of construction in evenings and at weekends when residential and sports and leisure receptors may be most likely to be present. The mitigation of likely long-term effects on landscape and views would be largely achieved through the following measures: The use of colour graded cladding to the converter station building, ranging from a muted green at the building’s base to off-white at the roofline. This will minimise landscape and visual effects and particularly the effect on views where the building sits on the horizon. Due to its lower height the substation building will be clad in a single colour (muted green); and Tree and shrub planting proposed on the western boundary of the converter station and substation site to partly filter and screen some views of the converter station from the west and northwest (in particular from the Saxon Shore Way and from River Stour) and to filter and screen views of the substation proposals from the south (in particular from the Saxon Shore Way). The wider proposals for Richborough Energy Park include the implementation of new planting as part of a separate but closely related planning application for a new perimeter site road. Planting proposals will include replacement tree planting along the eastern and north eastern site boundaries (partly mitigating trees loss to accommodate the new road), new native trees, shrubs and fruit trees near the site 384 Mitigation Schedule entrance, existing trees and shrubs on the northern site boundary being retained and enhanced with new native tree planting, and new native trees and shrubs along part of the sites western boundary adjacent the River Stour in front of new fencing. Traffic and Transport During construction, wheel washing facilities will be provided both at the main site entrance and also the vehicular entrance to the construction compound located at the Country Park. This will ensure mud/debris is not deposited on the surrounding carriageway. All HGVs will be covered and sheeted as appropriate. Mitigation measures will also include the introduction of delivery management strategies to ensure that HGVs travel outside of peak periods where possible, avoid sensitive residential areas and stick to agreed routing plans. Appropriate road signage will be provided as required; suitable signage will be placed within the Country Park to inform local users. Details of the proposed mitigation strategy would be developed in detail during the preparation of a Transport Management Plan. Abnormal load movements mitigation measures include: Police escorts and delivery programmes timed to cause minimal disruption; Vehicles will be marked as abnormal or long vehicles and where necessary temporary warning signs will be placed at required locations along the roads being used by site traffic; and It is also proposed to undertake a full condition survey before and after the delivery of any abnormal load. The condition of the carriageway will be reinstated to the same or better condition following the use of the route. Noise and Vibration Best practice construction noise methods will be used to minimise noise associated with cables installation and construction of the substation and converter station, to include: Site vehicles will not be over revved, or left with engines idling in close proximity to residential neighbours; All plant and machinery to be properly maintained and silenced in accordance with manufacturer’s instructions; Development of a Construction Management Plan detailing the mitigation to be implemented throughout each stage of construction; Regular communication with residents living close to the cables route and converter station and substation site. The communication will include details of expected work schedules and activities taking place, and contact details in case of query or complaint; Screening of HDD noise emission points using layout of temporary structures (such as site offices) and hoarding; and Where cabling works pass within 20m of properties pre and post construction building surveying will be undertaken. Vibration 385 Mitigation Schedule monitoring will be undertaken at the start of the construction works to more accurately quantify the risk of vibration generated by each stage of the works giving rise to a significant impact at varying distances. This data will be used, if necessary, to modify the distance from the route at which building surveys are triggered. Mitigation will be incorporated into the design of the converter station and substation to ensure that the noise target (assessed noise levels no higher than the background noise levels) is achieved. Prior to commencement of works on the converter station and substation, modelling will be undertaken on the final design and layout of the plant to verify that the above condition is met. Sound power levels can be reduced through design, selection of equipment and by employing mitigation measures, which could include: Substation TCRs housed within noise shields or full noise enclosures; Noise shields to harmonic filters; Enclosures around the SCT and SGTs; and Low noise fans, silencers on cooling fans or barriers around cooling fans. Converter Station Enclosures around the Shunt Reactor and converter station transformers; and Low noise fans, silencers on cooling fans or barriers around cooling fans. Air Quality The following mitigation measures will be implemented where appropriate (depending on the construction phase being undertaken at that time): All vehicles will be required to adhere to site speed limits which will be designed to minimise on site dust generation; Limitation of vehicle movements during cables installation to the working width wherever possible; All plant equipment will be correctly adjusted and maintained to minimise emissions; Materials recycling will reduce the extent of off-site disposal and the use of fresh materials, thus reducing the need to load, unload and transport potentially dust gathering materials; Minimisation of dust generation from the loading of trucks. The potential for dust generation associated with the transfer of materials on to vehicles can be controlled by the wetting of very fine or dry materials and the minimisation of drop heights; Covering lorries carrying potentially dust generating materials; Where necessary, materials stored on site will be wetted, covered or profiled to minimise dust generation by the wind. Storage areas will be sited away from potentially sensitive receptors where practicable; 386 Mitigation Schedule Stationary equipment with the potential for dust generation (such as soil sieving equipment) will be sited away from sensitive receptors. Where dust generating operations are near to sensitive receptors, enclosures will be provided if appropriate; Access roads and crossing points of highways along the route will be swept periodically to remove dust from hard surfaces; Unsurfaced working areas will be watered when necessary (such as during prolonged periods of dry weather) to maintain moisture content and hence reduce dust generation; Vehicle wheel washes will be used at the site exits; Visual site inspections will be undertaken to ensure that the build-up of materials with the potential to generate dust on site is prevented; Prompt reinstatement of topsoil and vegetation upon completion of construction to minimise risk of windblown dust; Limited predetermined areas for construction workers parking, from which workers will be transported to the active construction section; and All plant will be switched off when not in use for long periods. Coastal Tourism, Recreation and Socio-Economics During installation of the onshore underground cables, access to the Viking Trail and Thanet Coastal Path will be retained where possible. Where there is a Health and Safety requirement to prevent or reduce access, appropriately signed diversions will be put in place. Any restriction on access will be minimised and limited only to periods of major construction activity such as earthworks. Temporary signage advising visitors of construction activities will be erected. This will include signs within the car park of Pegwell Bay Country Park to ensure that visitors are aware of construction activities being undertaken. To minimise construction disturbance, working hours during periods where recreational activity is greatest (i.e. evenings and weekends), will be limited as much as possible. All land take associated with cables installation will be reinstated following completion of cable laying activities so will not adversely affect future recreational land use. The creation of chalk grassland habitat within Pegwell Bay Country Park will enhance botanical biodiversity and increase the wildlife amenity for visitors. Arboricultural Implications Tree surgery works to T48, T60, G3, G6, G13, G24 and G38 will be discussed and agreed with each Council’s Arboricultural Officer. To reinforce the required tree protection measures and avoid the requirement for ongoing arboricultural supervision a pre-start meeting will be arranged between the site contractor, a qualified Arboricultural Consultant and each Council’s Arboricultural Officer. 387 Mitigation Schedule During the meeting the alignment of protective fencing will be confirmed and trees for removal and retention within woodland plantation groups will be marked. Special construction methods around T50 and T51 and around the chalk capping area will also be discussed prior to the production of an Arboricultural Method Statement. An Arboricultural Method Statement will be produced to cover site access and movements, tree removals, works within Root Protection Areas and other tree protection measures. In the northern part of the Country Park, the cables will be covered with a chalk capping layer and seeded with approved seed mix (local seed will be used where available). The chalk capping will cover a length of approximately 477m (area of approximately 0.46ha) and will improve the vegetation and biodiversity interest of Pegwell Bay Country Park. This is consistent with the approach to management that has been undertaken favouring the establishment of chalk grassland (rather than extensive tree planting. Offsite planting is proposed on land at the south west boundary of the proposed converter station and substation site. This will occupy an area of approximately 0.12ha and will comprise a native woodland mix including Crataegus monogyna, Prunus spinosa and Corylus avellana. This area will also incorporate approximately 77nr. Lombardy Poplar (TBC and subject to agreement with the local planning authorities) to provide screen planting similar to existing planting at the northern boundary of the proposed converter station and substation site. The planting schedule will be established during the construction phase and subject to a long term management plan. 388 Conclusions 18.31 The construction of the Nemo Link is in accordance with European Union and UK policy to increase transmission capacity between countries and to ensure robust electricity supplies. A UK-Belgium interconnector will provide enhanced opportunities for the UK to trade with wider European power markets. 18.32 The construction and operation of the proposed development will not give rise to any significant long term effects. Any impacts identified as part of the assessment are considered to be localised and temporary and appropriate mitigation measures will be implemented to avoid, offset or reduce impacts. 18.33 The table below provides a summary of the residual environmental effects of the proposed UK onshore elements of the Nemo Link to which this application relates. Table 18.2: Summary of EIA Results SUMMARY OF EIA RESULTS Topic Area Residual Effects* Construction Land Use Minor Adverse Ground Conditions and No Effect Contamination Hydrology and Flood Risk Minor Adverse Ecology Minor Adverse-Minor Beneficial Archaeology and Cultural Low/Negligible Heritage Landscape Moderate Adverse Views Moderate/Minor Adverse Traffic and Transport Noise Air Quality Coastal Tourism, Recreation and SocioEconomics Electric and Magnetic Fields Minor Adverse Moderate Negligible Minor Adverse-Minor Beneficial No Effect Operation No Effect No Effect Minor Adverse Negligible No Effect Minor Adverse Moderate/Minor Adverse Negligible Minor No Effect No Effect No Effect * Summarises residual effects on the basis of the ‘worst’ or most significant effect identified. 389 390 GLOSSARY AND ABBREVIATIONS Alternating Current (AC) An electric current that reverses its direction at regularly recurring intervals. Ancient Woodland Ancient woodland is designated as being land which has been continuously wooded since AD1600 in England and Wales or AD 1750 in Scotland. Area of Outstanding Natural Beauty (AONB) Areas of special landscape character and value, of national importance. Such areas are considered to represent landscapes of high sensitivity. Their care has been entrusted to local authorities, organisations, community groups and the individuals who live and work within them or who value them. Baseline A standard by which things are measured or compared. Biodiversity Action Plan (BAP) A set of future actions that will lead to the conservation enhancement of biodiversity. Cable Ducts Pipe through which cables are drawn. Cable Drums Reel on which a cable is kept and for transportation. Climate Change A term used to refer to all forms of climate inconsistency but especially change from one prevailing climatic condition to another. The term is usually used synonymously with the term global warming. Combined Heat and Power (CHP) A plant designed to produce both heat and electricity from a single heat source. Conservation Areas A local designation of area of land and buildings of special architectural or historic interest, the character or appearance of which local authorities consider should be preserved or enhanced. Construction Environmental Management Plan (CEMP) Converter Station Document which sets out a variety of control measures for managing the potential environmental effects of construction works including control and management of noise, dust, surface water runoff, waste and pollution control. Terminal equipment for high voltage direct current transmission line in which direct current is converted into alternating current and vice versa. Converter Transformers These change AC voltage to an appropriate level for conversion within a valve hall. Current A flow of electrons in an electrical conductor. 391 Development Plan A document setting out the local planning authority’s policies and proposals for the development and use of land and buildings on the authority area. It includes unitary, structure and local plans prepared under transitional arrangements and development plan documents prepared under the Planning and Compulsory Purchase Act 2004. Dewatering Removing water from a system. Department for Energy and Climate Change (DECC) DECC is a British Government department which brings together the work of the Climate Change Group, previously housed within the Department for Environment, Food and Rural Affairs (Defra), with the Energy Group from the Department for Business, Enterprise and Regulatory Reform (BERR). Direct Current (DC) The unidirectional flow of electric charge. Discharge To release water into a natural or manmade system. Distribution System The portion of the transmission and facilities of an electric system that is dedicated to delivering electric energy to the end user. Disturbance A variation in normal conditions. Dust Dust is made up of solid particles between 1 and 75 microns in size. The term is used to describe particles resting on the ground or other surfaces that can become airborne before returning to the surface. Electromagnetic Field (EMF) A physical field produced by electrically charged objects. English Heritage The Government’s statutory adviser on the historic environment. Environmental Clerk of Works Also referred to as the Site Environmental Manager (SEM). Person appointed to be responsible for the preparation and implementation of the CEMP and ensuring that mitigation measures identified are appropriately implemented. Environment Agency Executive non-departmental public body responsible to the sectary of state for the environment, food and rural affairs. Environmental Impact Assessment (EIA) A statutory assessment of the possible positive or negative impact that a proposed project may have on the environment, together consisting of the natural, social and economic aspects. Environmental Statement Document containing the findings of the Environmental Impact 392 (ES) Assessment (EIA). Fauna All of the animals found in a given area. Flora All plant life found in a given area. Habitat Ecological or environmental areas that is inhabited by a particular species of animal, plant or other type of organism. Horizontal Directional Drilling (HDD) The drilling of non-vertical wells for the installation of underground cables. High Voltage Direct Current (HVDC) Cable transmitting direct current bulk electrical power, typically over long distances. Infrastructure Planning Commission An independent body that examines applications for nationally significant infrastructure projects. Interconnector HVDC cable linking two separate transmission systems. Joint Nature Conservation Committee (JNCC) A public body that advises the UK Government and devolved administrations on IK wide and international nature conservation. Landfall A cable landing point, where a submarine cable joins the land. Landscape Character Assessment This is an approach to understanding the differences between landscapes, and can serve as a framework for decisionmaking that respects the local distinctiveness. Listed Building A building of special architectural or historic interest. Local Biodiversity Action Plan (LBAP) Outline the actions to be taken at a local level. Local Development Frameworks (LDF) A non-statutory term used to describe a folder of documents, which includes all the local planning authorities’ local development documents. Local Nature Reserves (LNR) Sites with wildlife or geological features that are of a special interest locally. Local Planning Authorities The local authority or Council that is empowered by law to exercise planning functions. Marine Cable Route Proposed marine part of the project which includes the marine cable route from the UK to Belgium through UK, French and Belgian waters. Mitigation Measures and actions taken to minimise, reduce, remedy and/or compensate for the adverse impacts of development. 393 Natural England Independent public body whose purpose is to protect and improve England’s natural environment. Permitted Development Rights to carry out certain limited forms of development without the need to make an application for planning permission. Planning Permission Formal approval sought from a Council, often granted with conditions, allowing a proposed development to proceed. Power Station Facility for the generation of power/electricity. Public Right of Way (PROW) The most widely known right to cross private land is known as a 'right of way'. If this is a right granted to everyone it is a 'public right of way'. Ramsar Wetland sites that are protected under the Conservation of Wetlands (Ramsar, 1971) called the Ramsar Convention. It is an intergovernmental treaty that embodies the commitments of its member states to maintain the ecological character of their Wetlands of International Importance. Renewable Energy Energy resources that are naturally replenishing. Scheduled Monuments These are monuments which range from the prehistoric standing stones, burial mounds, through to many types of medieval site, castles, monasteries, abandoned farmsteads and villages to the more recent results of human activity such as colliers that are of national importance. Site Environmental Manager Also referred to as the Environmental Clerk of Works (ECoW). Person appointed to be responsible for the preparation and implementation of the CEMP and ensuring that mitigation measures are appropriately implemented. Sites of Biological Importance Non statutory designations used locally by a number of local authorities in England. Sites of Importance to Nature Conservation (SINC) Sites applied to areas of most importance for nature conservation within a local authority area in England. Species A group of interbreeding organisms that seldom or never interbreed with individuals in other such groups, under natural conditions. Special Area of Conservation (SAC) Strictly protected sites designated under the EC Habitats Directive. Special Protection Area (SPA) Strictly protected sites classified in accordance with Article 4 of the EC Birds Directive which came into force in April 1979. 394 Outline Waste Management Plan Document prepared by the Contractor in consultation with XXXX which details how waste will be managed during construction of the development. Sites of Special Scientific The country’s very best wildlife and geological sites. Interest (SSSI) Subsea Technology and methods employed for cable installation in the marine environment. Substation Facility equipment that switches, changes, or regulates electricity voltage. Transformer An electrical device for changing the voltage of an alternating current. Transmission The movement or transfer of electric energy over an interconnected group of lines and associated equipment between points of supply and points at which it is transformed for delivery to consumers or is delivered to other electric systems. Transmission is considered to end when energy is transformed for distribution to the consumer. Transition Joint Pit Transmission System Area within which two sections of cable are joined together. An interconnected group of electrical transmission lines and associated equipment for moving or transferring electric energy in bulk between points of supply and points as which it is transformed for delivery over the distribution system lines to consumers or is delivered to other electrical systems. Transport Management Plan Document which sets out a variety of control measures for managing the potential transport effects during the construction period. A mechanism for securing the preservation of single or groups of trees of acknowledged amenity value. A tree that is subject to an order may not normally be topped, lopped or felled without the consent of the Local Planning Authority. Tree Preservation Orders (TPOs) Trunk Road Strategic or major road usually containing high volumes of heavy goods vehicles. Valve Halls Contain power electronics equipment that converts from AC to DC (or vice versa). Voltage The difference in electrical potential between any two conductors or between a conductor and ground. It is measure of the electric energy per electron that electrons can acquire and/or give up as they move between the two conductors. Water Framework European Union directive which commits European Union 395 Directive (WFD) member states to achieve good qualitative and quantitative status of all water bodies (including marine waters up to one nautical mile from shore) by 2015. It is a framework in the sense that it prescribes steps to reach the common goal rather than adopting the more traditional limit value approach. World Heritage Site (WHS) A cultural or natural site of outstanding universal value designated by the International Council on Monuments and Sites (ICOMOS) 396
© Copyright 2026 Paperzz