How Much is E “N”OUGH? Optimizing Nitrification and Denitrification at the Water Reclamation Plants Joe Chang, Water Reclamation Plants LA County Sanitation Districts: Background Information • Established in 1923 • Provide Wastewater and Solid Waste Management for ~ 5.7 million people • 1400 miles of main trunk sewers • 11 wastewater treatment plants • 3 active landfills Presentation Outline • • • Regulatory Requirements Nitrification/Denitrification Basics Case Studies: • Valencia WRP New Nitrogen Discharge Limits • In 1994, Los Angeles RWCQB set new nitrogen discharge limits effective in 2003: • Ammonia: Nominally 2 mg/L • Nitrate + Nitrite: 10 mg/L (in some cases lower) Biological Removal of Nitrogen Nitrification/ Denitrification (NDN) Process Nitrification/Denitrification ++ NH NH44 -- N N Nitrifying Nitrifying Bacteria Bacteria (Nitrosomonas) (Nitrosomonas) Ammonia Ammonia Aerobic Aerobic -- NO22 - N Nitrifying Nitrifying Bacteria Bacteria (Nitrobactor) (Nitrobactor) Aerobic Aerobic Nitrite -- NO33 - N Nitrate Denitrifying Denitrifying Bacteria Bacteria & & Carbon Source Carbon Source Anoxic N22 Nitrogen Gas Oxidation Reaction Reduction Reaction Nitrification Nitrification (Aerobic) (Aerobic) Denitrification Denitrification (Anoxic) (Anoxic) • Modified Ludzack Ettinger (MLE) NDN Process Primary Effluent Anoxic AnoxicZone Zone Aerobic AerobicZone Zone Final Clarifier Tertiary Treatment Internal Recycle Waste Activated Sludge (WAS) Return Activated Sludge • Step Feed NDN Process Primary Effluent Anoxic Anoxic Aerobic Aerobic Anoxic Aerobic Aerobic Anoxic RAS Final Clarifier Tertiary Treatment Waste Activated Sludge (WAS) Valencia Water Reclamation Plant Valencia JAO Valencia WRP Aerial Aerial Photo Photo Six Flags Magic Mountain Santa Clara River Golden State Freeway North Valencia Water Reclamation Plant: Background Information • Built in 1967 • Serves ~ 170,000 residents in Santa Clarita Valley • Rated for 21.6 MGD • Current influent flow ~16 MGD • Discharges to Santa Clara River • Handles all solids from Valencia and Saugus WRPs Nitrogen Discharge Limits at Valencia WRP • In 1994: RWQCB set new nitrogen limits effective in June 2003: Ammonia: 2.0 mg/L Nitrate + Nitrite: 10 mg/L Valencia WRP Stage Five Expansion and NDN Facilities GO BEARS Valencia WRP Aeration Modifications RAS/Filtrate RAS/Filtrate Treatment Treatment Tanks Tanks it 1 n U it 2 n U it 5 n U it Un it 3 n 4U Valencia WRP Filtrate Raw Raw and and Waste Waste Activated Activated Sludge Sludge (Valencia (Valencia & & Saugus Saugus WRPs) WRPs) Solids dewatering filter press Anaerobic digesters Valencia WRP Filtrate Raw Raw and and Waste Waste Activated Activated Sludge Sludge (Valencia (Valencia & & Saugus Saugus WRPs) WRPs) Biosolids for land application Anaerobic digesters R A S/Filtrate treatment tanks Solids dewatering filter press Filtrate (1.5 MG/wk ammonia conc. ~900 mg/l) Valencia WRP Filtrate Raw Raw and and Waste Waste Activated Activated Sludge Sludge (Valencia (Valencia & & Saugus Saugus WRPs) WRPs) Biosolids for land application Anaerobic digesters Solids dewatering filter press R A S/Filtrate treatment tanks Aeration Units Filtrate (1.5 MG/wk ammonia conc. ~900 mg/l) Valencia WRP Ammonia Load 40 38.6 38.6 From From Filtrate Filtrate 30 Ammonia Conc. 13.0 13.0 25.6 22.6 23.7 SJC-E SJC-W 25.5 26.1 LC LB 24.8 24.1 24.1 20 25.6 (mg/L) 10 0 VAL POM Water WaterReclamation ReclamationPlants Plants WN SAUG Valencia WRP NDN Start -Up Start-Up •• •• Modified Modified Ludzack Ludzack Ettinger Ettinger (MLE) (MLE) Mode Mode Start -Up began Start-Up began in in May, May, 2003 2003 Pri Pri.. Effluent Effluent Anoxic Zone 150%Q 150%Q RAS/Filtrate RAS/Filtrate IR Aerobic Zone Aerobic Zone * To Final Clarifiers * Effluent Sample Goal Ammonia (NH4+-N) < 1 mg/L < 2 mg/L Nitrate (NO3--N) 14 mg/L < 10 mg/L Valencia WRP High Nitrate: Rising Sludge Rising Rising Sludge Sludge due due to to high high nitrate nitrate Normal Normal situation situation in in the the final final clarifier clarifier Mixed Mixed Liquor Liquor sample sample NO3- - N D DN N Anoxic Nitrate Anoxic Solids settle to the bottom of the tank N2 Nitrogen Gas Valencia WRP Start -Up Problems: Short Start-Up Circuiting Primary Primary Effluent Effluent Aerobic Aerobic Zone Zone Anoxic Anoxic Zone Zone RAS/Filtrate RAS/Filtrate II R R Aerobic Aerobic Zone Zone To To Final Final Clarifiers Clarifiers • Internal Recycle Pump Discharge piping: 30” diameter Short Circuiting Solution •• Eliminate Eliminate Internal Internal Recycle Recycle flow flow Short Short Circuiting Circuiting • When IR rate at 250%Q: Effluent Nitrate: ~10 mg/L Valencia WRP Start -Up Problems: Start-Up Incomplete Denitrification •• Not Not enough enough COD COD available available for for complete complete denitrification denitrification to to occur: occur: •• Typically Typically need need 55 grams grams COD COD per per gram gram NO N for for complete complete dentrification dentrification NO33--N •• Not Not enough enough retention retention time time in in anoxic anoxic zones zones Biological Removal of Nitrogen Nitrification/ Denitrification (NDN) Process Nitrification/Denitrification ++ NH NH44 -- N N Nitrifying Nitrifying Bacteria Bacteria (Nitrosomonas) (Nitrosomonas) Ammonia Ammonia Aerobic Aerobic -- NO22 - N Nitrifying Nitrifying Bacteria Bacteria (Nitrobactor) (Nitrobactor) Aerobic Aerobic Nitrite -- NO33 - N Nitrate Denitrifying Denitrifying Bacteria Bacteria & & Carbon Source Carbon Source Anoxic N22 Nitrogen Gas Oxidation Reaction Reduction Reaction Nitrification Nitrification (Aerobic) (Aerobic) Denitrification Denitrification (Anoxic) (Anoxic) Incomplete Denitrification Solutions •• Stopped Stopped anionic anionic polymer polymer addition addition at at Primary Primary Tanks Tanks •• Extended Extended anoxic anoxic zones zones from from ~33% ~33% of of tank tank volume volume to to ~50% ~50% of of tank tank volume volume Extended Anoxic Zone Pri. Effluent Anoxic Zone (33%) RAS/Filtrate Aerobic Zone IR Aerobic Zone (67%) To Final Clarifiers Pri. Effluent Anoxic Zone (50%) RAS/Filtrate IR Aerobic Zone (50%) To Final Clarifiers Effluent Nitrate Results: Before and After Modifications Before units modified After all units modified* * Six Month Average Unit 3 NO3-- N 13 mg/L Unit 4 NO3-- N 13.3 mg/L Unit 5 NO3-- N 12.1 mg/L 7.4 mg/L 6.3 mg/L 7.0 mg/L Nitrogen Limits at Valencia WRP • In 1994: RWQCB set new nitrogen limits effective in 2003: Ammonia: 2.0 mg/L Nitrate + Nitrite: 10 mg/L • In 2003: RWQCB revised nitrogen limits effective in 2009: Ammonia: 1.75 mg/L Nitrate + Nitrite: 6.8 mg/L Revised Permit Limits and New Performance Concerns 12 Effluent NO 3 -N (mg N/L) 10 2003 NO3-N limit 8 2009 NO3-N limit 6 4 2 0 Jul-03 Oct-03 Jan-04 Apr-04 Jul-04 Oct-04 Jan-05 Valencia WRP Aeration Units 1 and 2: MLE Mode To Final Clarifiers Aerobic Zone Aerobic Zone Primary Primary Effluent Effluent Anoxic Zone RAS RAS// Filtrate Filtrate Swing Zone IR IR Valencia WRP Aeration Units 1 and 2: Step Feed Anoxic Zone To Final Clarifiers Aerobic Zone Anoxic Zone Aerobic Zone Primary Primary Effluent Effluent RAS RAS// Filtrate Filtrate Anoxic Zone Valencia WRP Aeration Units 1 and 2: Hybrid Anoxic Zone To Final Clarifiers Aerobic Zone Anoxic Zone Aerobic Zone Primary Primary Effluent Effluent RAS RAS// Filtrate Filtrate Anoxic Zone IR IR • Step Feed NDN Process: Unit 1 Final Clarifier Primary Effluent Tertiary Treatment Waste Activated Sludge (WAS) RAS ••Hybrid Hybrid NDN Process: Unit 2 Primary Effluent Final Clarifier Tertiary Treatment Waste Activated Sludge (WAS) IR RAS ••MLE MLE NDN Process: Unit 3 Primary Effluent Final Clarifier Tertiary Treatment IR RAS Waste Activated Sludge (WAS) Performance Comparison Mid-day NO3-N Levels NO3-N Concentration (mg/L) 16.0 MLE Step Feed Hybrid 12.0 8.0 4.0 0.0 0.0 0.1 1.0 10.0 30.0 50.0 70.0 90.0 Cumulative Frequency 99.0 99.9 100.0 Unit 5: Convert from MLE to Hybrid MLE Mode Pri. Effluent Anoxic Zone RAS/Filtrate IR Aerobic Zone To Final Clarifiers Hybrid Mode Pri. Effluent Anoxic Zone RAS/Filtrate Aerobic Zone IR Aerobic Zone To Final Clarifiers Anoxic Zone GO BEARS Effluent Nitrate Results: Hybrid vs. MLE 6/2006 to 12/2006 Peak NO3– N Unit 3 MLE 8.2 mg/L Unit 4 MLE 8.3 mg/L Unit 5 Hybrid 6.4 mg/L Baffle Boxes and Internal Recycle Diffuser Pri. Effluent RAS/Filtrate IR Anoxic Zone Aerobic Zone To Final Clarifiers Aerobic Zone Anoxic Zone Filtrate Equalization Valencia WRP: Additional NDN Optimization • • • • Converted All Units to Hybrid Baffle Modifications and IR Diffusers Filtrate Equalization Optimized RAS and Internal Recycle Flow Rates • Higher MLSS • Permanent Submerged Mixers in New Anoxic Zones Valencia: Effluent Nitrogen Concentrations Effluent NO3-N and NH4-N (mg N/L) 10 Nitrate 8 Ammonia 2009 NO3-N limit 6 4 2009 NH4-N limit 2 0 Jun-03 Jun-04 Jun-05 Jun-06 Jun-07 Jun-08 Jun-09 Jun-10 Acknowledgements • WRP Operations, Maintenance, E&I, and Engineering • Wastewater Research Section • Laboratories • Monitoring Section • Wastewater Design Section
© Copyright 2026 Paperzz