NSW WATER METERING SCHEME – MURRAY PILOT The NSW Water Metering Project How will the Project take place? The Australian Government has agreed in principle to commit up to $221 million to the NSW Water Metering Scheme to improve the measurement of water extracted from groundwater, regulated and unregulated rivers throughout the Murray Darling Basin. Water licence holders within the area of the Pilot Project will be contacted by State Water or its representative to arrange a visit to assess their water meter(s) on-site. Ultimately, the NSW Metering Project will see the installation of high accuracy, tamper proof and low maintenance meters across the NSW Murray-Darling Basin. The Australian Government, through the ‘Water for the Future Program’, is funding the $22.4 million Murray Pilot Project to install metering in the Upper Murray catchment. The Murray Pilot will be used to evaluate installation options and techniques prior to roll-out of the Project across MurrayDarling Basin in NSW. The Murray Pilot Project is being jointly undertaken by the NSW Office of Water and State Water Corporation. State Water Corporation has been contracted to manage the implementation of the Murray Pilot Project, on behalf of both organisations. Comdain Infrastructure Pty Ltd has been contracted to design and manage the process of installing the new meters and telemetry. The Murray Pilot Project This important Project consists of upgrading or replacing up to 1200 water meters as the precursor to rolling out the Metering Scheme in the rest of the Murray-Darling Basin. Benefits of the Pilot Project • • • • • • Improved water measurement accuracy that will save water Improvements to installation options and techniques Consistent metering Reduced meter reading operating costs Regional employment opportunities Improved water security and delivery For more information visit www.statewater.com.au Any water licence holders outside the pilot area who might be involved in the wider Metering Scheme will be contacted at a later date. Most sites with an existing meter will have a new compliant meter installed. Many sites which are currently not metered will require a meter, based on the assessment of usage, entitlment size and installed pump capacity. State Water, as program manger, will advise individual licence holders if anew meter will be installed. When will the Project take place? Meter installation will commence mid to late 2011 and is expected to be completed by June 2012. Where is it taking place? The pilot area covers the area upstream of Torrumbarry Weir near Moama/Echuca and extends along the Murray River through Barham, Tocumwal, Yarrawonga, Corowa, Howlong, Albury, Jingellic as far as Tooma. It extends north from the Murray River to Stevens Weir on the Edward River near Deniliquin, to Culcairn along Billabong Creek and includes the area around Tumbarumba. The pilot area covers regulated rivers, unregulated tributaries and groundwater bores. It extends north from the Murray River to Stevens Weir on the Edward River near Deniliquin, to Culcairn along Billabong Creek and includes the area around Tumbarumba. The pilot area covers regulated rivers, unregulated tributaries and groundwater bores. A NATIONAL WATER INITIATIVE – A STATE SOLUTION In 2004, all governments in Australia agreed to establish a national approach to water management, and thus created the National Water Initiative (NWI). Under the Initiative, new national standards for water meters and meter data collection systems were established. Agreed standards for rural water meters were confirmed in 2009 and Australian governments will oversee the replacement of all non-conforming meters by 30 June 2016. The following overview outlines the NWI metering priorities and the intent of the NSW Metering Scheme – Murray Pilot. Implementation plan Under the NWI, States are required to develop implementation plans that detail how the new water meters will be rolled out. In the case of NSW the draft plan proposes metering a minimum of 95 percent of extraction in any given area. Electromagnetic flow meters Electromagnetic flow meters (also known as magflow meters) have been selected for their accuracy and their comparatively low maintenance. This type of meter does not have any moving parts in the water that can impose restrictions in the pipe. Electromagnetic meters are generally less susceptible to sand and vegetation contamination than mechanical meters which have been the predominant meter type in use along the Murray system. In some situations meters of a non electromagnetic type may be used where site conditions are suitable. 2 WHAT WATER SOURCES WILL BE METERED? Telemetry Telemetry will transmit meter data to databases instantaneously, and reduces the need for a person to physically go to the site to read the meter. The availability of real time readings will enable many customers to have access to better water account information and improve their business decisions. It will also enable State Water Corporation to manage the regulated rivers more efficiently and the NSW Office of Water to monitor usage and manage the unregulated and groundwater systems. Maintenance Landowners will not be responsible for maintaining the new water meters. Instead, State Water will own the meters on the regulated river system, and NSW Office of Water will own the meters on the unregulated river and groundwater systems. State Water and NOW will be responsible for ensuring consistent maintenance, prompt repair and ongoing accuracy. Owning a large fleet of meters means that both State Water and NSW Office of Water can take advantage of cost effective methods to ensure accuracy rather than each privately owned meter requiring individual certification. Further information on NWI More information on the National Water Initiative and new standards is available from the Australian Government’s National Water Commission: www.nwc.gov.au The NSW Metering Scheme’s Murray Pilot Project will provide many licensed users of water from regulated, unregulated streams and groundwater sources with new telemetry-enabled water meters. Metering water entitlement The Murray Pilot Project will see meters installed on sites on regulated rivers, unregulated rivers and groundwater systems. Water extracted for town water supplies will also be metered by the Project. Metering of basic landholder rights and on-farm dams are not part of this Project. Which water sources will be included? Preparation for meter installation for water users extracting water from the regulated system, unregulated system and groundwater will commence from July 2011. Will shallow groundwater bores be included? Many shallow groundwater bores or spear point systems were installed in the 1990s specifically to manage high watertables. State Water Corporation is collecting information on these sites but the decision on whether to install meters on these sites will depend upon a number of factors including available funding. What about customers of Murray Irrigation? The Murray Pilot Project includes Murray Irrigation’s bulk water offtakes from the river but does not include internal customers of Murray Irrigation who receive regulated water supply from the Murray Irrigation channel system. However, Murray Irrigation customers who have deep aquifer irrigation bores or shallow groundwater bores in the pilot area may require a meter on these bores. State Water, as program manager, will advise if this is the case. Licence holders downstream of the Hume Dam, and those extracting water from the Murray and Edward River systems are part of the regulated system. Licence holders along the upper reaches of Billabong Creek and the smaller tributaries above Hume Dam (i.e. around Holbrook, Tumbarumba and Tooma) are part of the unregulated system. The groundwater system includes zones 014, 015 and 016. Taking care of it 3 SELECTING SITES FOR NEW METERS A combination of factors including water usage, entitlement volume and size of pump installations will be considered to identify sites that require a new meter Review of water extraction data The Murray Pilot Project is aiming to meter the vast majority of extractions from each water source (regulated, unregulated and groundwater), which means that a large number of water extractors will receive a new meter. In the first instance, State Water Corporation, NSW Office of Water and the Managing Contractor (Comdain Infrastructure Pty Ltd) will use historical water usage information to determine sites that will receive a new meter. Other factors such as water entitlement and the size of pump installations will also be considered. WHEN WILL THE NEW METERS BE INSTALLED? Consultation Comdain Infrastructure will visit each water user to confirm specific site requirements, expected future water usage patterns and the potential to rationalise multiple extraction points. During this consultation phase Comdain Infrastructure will ensure that any potential changes to future water usage patterns or any other issues not readily identifiable from licence information are considered in preparation for the meter installations. There are several phases to the NSW Metering Scheme’s Murray Pilot Project, from preliminary planning through to installation. Site visits for the Murray Pilot Project will commence in mid 2011. The Project is expected to be completed and functional by June 2012. It is likely that the initial list of sites may be varied after consultation. Comdain Infrastructure Pty Ltd has been contracted to design and manage the process of installing the new meters on behalf of State Water Corporation and NSW Office of Water. Confirmation The planning phase Following the consultation, NSW Office of Water will confirm which sites will require a new meter and will notify the relevant licence holders. During the planning phase, Comdain Infrastructure will: • prepare concept designs and installation details; Ranking • determine the resources and capital items needed, including meters and fittings; Water extraction statistics and information on licence and pump capacity have been analyzed to identify sites that are likely to require a new meter. The resulting draft list of likely sites to be metered is then used for planning purposes. After field inspections specific circumstances may mean that the initial list of sites is varied. • outline a schedule of works specifying sites and their date of completion; Most sites with an existing meter will have a new compliant meter installed. Many sites which are currently not metered will require a meter, based on the assessment of usage, entitlement size and installed pump capacity. State Water, as program manger, will advise individual licence holders if a new meter will be installed. Installation Once designs are complete, Comdain Infrastructure will work with licence holders to arrange the most mutually convenient times (taking into account irrigation schedules and other on-site conditions) for installation to occur. The time taken to install a meter varies; a standard meter is expected to take up to three days, while longer installation times might be needed for larger or more complex sites. Most meters will operate on 12 volt solar power and be self contained without needing to connect to mains power. While access to water pumping may be affected during installation, works will be scheduled to minimise any disruption to pumping. Completion All meters and telemetry are expected to be installed by June 2012. • address other planning requirements including consultation and environmental assessments. Information will be made available to licence holders and details of the proposed installation process will be made available by State Water Corporation, as program manager at the completion of the planning phase, which is expected to be by August 2011. On-site visits Comdain Infrastructure’s irrigation designers expect site visits to commence in August 2011. However, a small number of landholders will be contacted by Comdain Infrastructure earlier to field-test the planning process. During the visits, Comdain Infrastructure will inspect each site, discuss any specific site requirements (like access, irrigation schedules, etc) and any unique characteristics that are likely to impact the proposed design. 4 Taking care of it 5 WHO PAYS FOR THE NEW METER? The purchase and installation cost of the new meters and telemetry will be paid by the Project. Landholders will be responsible for annual maintenance charges through a meter service charge as determined by the independent body, IPART (Independent Pricing and Regulatory Tribunal of New South Wales). DOES EVERYONE NEED A NEW METER? Current 2011/12 metering service charges (per meter, per annum) as set by IPART are: State Water NSW Office of Water Cost ($) Cost ($)* n/a $226.74 Locally read, electromagnetic meter without telemetry $219.78 $297.00 Installation Remotely read, electromagnetic meter with mobile phone modem $296.80 $387.48 Licence holders will not be liable for the initial capital costs of installing the new water meters – these costs will be covered by the Australian Government. Remotely read, electromagnetic meter with satellite telemetry modem $620.31 $722.80 Remotely read, channel meter with mobile or satellite modem $620.31 $722.80 Ownership State Water Corporation and NSW Office of Water will own the new meters and be responsible for ensuring their effective operation and accurate measurement. Meanwhile, customers will remain responsible for the cost of metering through a new meter service charge, which also covers the cost of telemetry. How are costs determined? Costs for State Water and NSW Office of Water are reviewed and determined by IPART (Independent Pricing and Regulatory Tribunal) an independent body in New South Wales. In determining meter service charges, IPART considers submissions from all stakeholders, including individuals and representative industry bodies. What costs will apply? IPART reviewed the submissions and set meter service charges to cover the operation and maintenance of each meter installed. The determination is subject to CPI with the charge to be invoiced at the same time as customers’ water usage and entitlement charges. Meter Facility Locally read, mechanical meter *Costs will be adjusted annually by the CPI. State Water charges are for regulated customers; NSW Office of Water charges are for unregulated and groundwater customers. Differences between the two charges reflect the fact that regulated customers already pay for some meter readings undertaken by State Water. Whilst new meters will be mandatory in most circumstances, there may be opportunity for some licence holders to rationalise the number of meters and lessen the annual meter service charges. How does this affect you? Read on… An opportunity to rationalise The NSW Metering Scheme’s Murray Pilot Project’s replacement of water meters provides an ideal opportunity for licence holders to review and rationalise both the number and location of water meters on their properties. Managing contractor, Comdain Infrastructure Pty Ltd will be able to advise on this having reviewed each licence holder’s water use, their capacity for pumping and the size of their water entitlement before conducting on-site visits. What if my meter already complies with new metering standards? Meter service charges At the heart of this Project is telemetry-enabled metering that provides the ability to accurately measure and report water flow information in real time for improved on-site and systemwide water management. The meter service charge is based on the number of meters installed for each licence holder. The more meters a customer has, the greater the meter service charge. As all meters must be fully compatible with the new standards, it’s likely that most existing meters – even some that have been installed relatively recently – will need replacing. The meter service charge covers repairs and maintenance of meters and telemetry, costs of collecting and processing meter readings and periodic validation of meter accuracy. The new national standards for water meters and their data collection systems developed under the National Water Initiative (NWI), require all non conforming meters to be replaced with complying devices – such as those installed by the Project – by 30 June 2016. Future charges In their next submissions to IPART, State Water Corporation and NSW Office of Water will continue to review all costs associated with metering, including any efficiencies delivered by the Murray Pilot Project. Do I need my water meter? Comdain Infrastructure will visit licence holders to discuss the design and location of the new meter(s). Before this visit, licence holders are encouraged to consider: • Whether the meter to be replaced will be used now and in the future (a meter should be installed even if the pump is not used every year). If a site will no longer be used, it is important to let Comdain Infrastructure’s representative know this during the visit. • Whether multiple installations are needed or if any could be decommissioned to reduce costs (multiple meters incur multiple meter service charges). The ability of a single meter to cover multiple pumps will be considered. Channel measurement is also being considered to reduce installation costs where multiple units connect to a single channel. What do I do if a meter is no longer required? Licence holders should write to State Water Corporation, as program manager, if they believe a meter site is no longer required. This information will be forwarded to the NSW Office of Water for action to amend the work approval. Note that dismantling and removing any decommissioned pumping equipment may be required in some cases. Can I refuse a new meter? The NSW Office of Water will write to all licence holders deemed to require a new meter under the relevant legislation... If a licence holder refuses to have a meter installed and they subsequently extract water from that site, they may be in breach of licence conditions and penalties may apply. Any breach of licence conditions will be reported by State Water Corporation, as program manager, to the NSW Office of Water. During the IPART submission process, all licence holders will be able to provide comment. Further information on metering costs can be found on the IPART website: www.ipart.nsw.gov.au 6 Taking care of it 7 SOME COMMON QUESTIONS ANSWERED… Here are some responses to common questions regarding the new metering system. Can the new meters be serviced with minimal disruption to watering? The metering system is not broken so why fix it? Yes. New meters will have low maintenance requirements, and the telemetry device will assist in identifying when servicing is required in order to minimise disruption. Accurate metering is crucial to good water management and important for fairness and equity amongst licence holders. Investigations by State Water Corporation shows very few existing meters comply with the new national standards. Meters funded and installed as part of the Project will comply with the new national standards. My meter already complies with the new standards, are any changes necessary? Meters installed as part of the Project will meet the new standards but importantly will also be compatible with a telemetry based meter reading system which will enable improved water management The technology ultimately allows for highly accurate, real-time measurement and reporting of water flows. If an existing meter complies with the national standards, and is compatible with the telemetry system, the meter will be retained where possible and telemetry added. Some compliant meters may require modifications to connecting pipework to make the meter installation fully compliant. If I decide to decommission one of my pumps, what do I need to do? Licence holders will be asked to identify any sites on their property where pumping is no longer required. State Water, as program manager, will advise NSW Office of Water to commence action to modify work approvals. If one of my meters needs to be replaced in the future, will I get a say in the type of meter? No. State Water or NSW Office of Water will replace the meter with one that is compatible with the existing installation. Is everyone getting a new meter? The Project aims to meter the vast majority of water extracted in the Project area. Sites to receive new meters are determined by historical water usage, water entitlement and size of works. When will my meter be installed? Meter installation will occur before June 2012. A typical meter installation should take about three days. Licence holders will be contacted before installation is scheduled so that minimal disruption to licence holders can be ensured. Taking care of it
© Copyright 2026 Paperzz