Pinnacle of Burj Khalifa, Dubai – UAE Lifting of the pinnacle that tops the world’s tallest building ▲ Careful planning was required to install the lifting equipment Scope of work performed • Lifting of the pinnacle Weight: 450 t Lifting distance: 89 m Lifting speed: 10 m/hour Equipment 3 units SLU 220/550 The pinnacle features: In a city of superlatives, the Burj Khalifa is the latest shining example - Length: 143m (30% remaining inside the of the prosperous and dynamic building for the connection) Middle East. It is the world’s tallest - Weight: 450t building and is also the tallest man(including architectural cladding made structure, breaking all previous and base connection beam) records on its completion in 2009. The building features: -Tallest structure - 828m (record previously held by the 628.8m KVLY-TV mast, which is not free-standing) - Tallest free-standing structure 828m (beating the 553m CN Tower) - Tallest building/skyscraper – the top floor’s roof is at 623m (beating Taipei 101’s record of 449m) - Building with most floors: 160 (the World Trade Center had 110) Lifting the pinnacle was a major exercise. It consists of a rolled steel pipe with a diameter of 2.1m and 60 mm wall thickness. Segments with a length of 5m were brought up by crane and assembled inside the tower itself at level 156, which is at a height of +585m. Welding was carried out to full depth to increase resistance against fatigue caused by the continuous oscillating movement of the pinnacle. ID 2923 Lifting the pinnacle for the Burj . Khalifa, formerly named Burj Dubai, is the latest example of VSL’s expertise being applied to the world’s tallest structures. The Burj Khalifa joins a portfolio that includes Taipei 101, Toronto’s CN Tower and Kuala Lumpur’s Petronas Twin Towers, as well as other landmark buildings in Dubai and the rest of the UAE. Temporary openings were let into the slabs between levels 157 and 162 in order to assemble the pinnacle. They were closed on completion of the lift. The top main crane operated at high speed but the time required to complete each cycle to +700m height was quite long. VSL therefore optimised the crane operation by preassembling the jacks on the ground together with the 120m-long strand bundles and the jack support beams. The assemblies for the 3 lifting points weighed each 9.5t. Space constraints and a clearance under the crane hook of 32m meant that VSL’s lifting equipment had to be installed on the building as soon as construction reached the level of the lifting platform. ▲ Construction of the tower has broken many records. The pinnacle was lifted by 3 strand jack SLU 220/550 evenly located around the pinnacle and connected together. There were 3 pick-up points at the base of the pinnacle, below its centre of gravity. Lateral guides ensured the lateral and Pinnacle (after 5 lifting steps) Platform for cladding assembly OWNER / DEVELOPER: EMAAR PROJECT MANAGER of main contract: TURNER. MAIN CONTRACTOR in JV: SAMSUNG Eng. & Const. (South Korea) with BESIX (Belgium) and ARABTEC (UAE). STEELWORK CONTRACTOR for the steel top structure and pinnacle: EVERSENDAI Eng. VSL ENTITY VSL Heavy Lifting department DATE 2009 vertical stability. The lift had been conducted in 8 steps – each between 9 to 12 m due to the installation of the Pinnacle’s cladding. Construction continued all around, enclosing the lifting equipment. As a consequence, there was no crane access for the subsequent dismantling. The equipment had to be deposed and transported to platforms on the façade, where the crane picked them up and lower them to the ground. Construction of the Burj Khalifa began in Sept.2004 and was completed in December 2009. VSL’s work was carried out between July 2007 and February 2009. Dubai inaugurated Burj Khalifa in January 2010. +713m Stairs +695m VSL Strand Lifting Jacks Lifting platform 4th lift /elevator Level 160 Steel structure ▲ Lower anchorage and openings in slabs +585m Level 156 Base of the spire during preassembly VSL anchorages. Pickup points on the spire Concrete structure 1/1 Edited 2008 www.vsl.com ▲ Construction of the tower has broken many records. ID 2923 3rd lift /elevator
© Copyright 2026 Paperzz