Chapter Eleven Termination Ann B. Graff and Ryan P. Stewart 11.01Introduction. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 182 11.02Termination. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 182 11.03 For Convenience. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 182 11.04 Damages for Termination for Convenience . . . . . . . . . . . . . . . . . . . . . . . . . . 185 11.05 Backcharges and Termination for Convenience . . . . . . . . . . . . . . . . . . . . . . 187 11.06 Constructive Termination. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 189 11.07 For Default (or Cause)—Common-law. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 190 11.08 Contractual Termination for Default after Notice . . . . . . . . . . . . . . . . . . . . . 191 11.09 Damages for Termination for Cause. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 192 11.10 Opportunity to Cure. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 194 11.11 Required Notice. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 195 11.12 Wrongful Termination. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 196 11.13 Damages for Wrongful Termination . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 197 181 Beutler_MJI_20150519_11-07_FinalPass.indd 181 5/19/15 11:13 AM 182 Model Jury Instructions: Construction Litigation, 2nd Edition Chapter 11: Termination 11.01 Introduction A party’s right to terminate its contract may originate from the general principles of contract law, or it may arise out of the terms of the contract itself. In general, the effect of the termination is to discharge the parties from their unperformed obligations under the contract. The reasons for termination will determine whether a contractor is entitled to payment for work performed prior to termination and whether the contractor is responsible for increased costs to complete the remainder of the project. 11.02 Termination In the construction context, “termination” means to stop a contract before it is fully performed or completed. The contract terms or applicable law determine whether or when each party has a right to terminate the contract. 11.03 For Convenience Normally, a party to a contract cannot unilaterally terminate a contract with another without just cause. In this case, the contract contains a “termination for convenience” clause. This clause gives the owner the right to terminate the contract without cause or for any reason. Even though the contract has this provision, the contractor may recover full breach of contract damages if it can show that the owner acted in bad faith by invoking the termination clause. To show bad faith in this context, the contractor must show that the owner (1) acted with malicious intent or animus toward the contractor or Beutler_MJI_20150519_11-07_FinalPass.indd 182 5/19/15 11:13 AM Termination 183 (2) entered into the contract knowing full well that it had no intention of honoring the contract. Comment Many public contracts, and a growing number of private contracts, contain termination for convenience clauses that give the owner the unilateral right to terminate the contract if it deems the termination to be in its best interest. See, e.g., Federal Acquisition Regulations FAR 52-249-1. Although these clauses typically require that the owner pay the contractor for the value of the work installed and typical contract closeout costs, the owner is usually saved from paying for damages for actual breach of contract, profit and overhead and work not performed, or punitive damages. See Krygoski Constr. Co. v. United States, 94 F.3d 1537 (Fed. Cir. 1996), cert. denied, 137 L. Ed. 2d 819 (1996). While the government’s right to terminate a contract for convenience is not unlimited, the government is entitled to considerable latitude in making such a decision to terminate. Id. at *6. Under the “traditional standard,” a contracting officer’s convenience termination is conclusive absent the contractor’s showing that the termination decision either was a product of bad faith or constituted clear abuse of discretion. Id.; see also John Reiner & Co. v. United States, 325 F.2d 438, 442 (Ct. Cl. 1963). It is the terminated contractor’s burden to show bad faith. Nat’l Factors Inc. v. United States, 492 F.2d 1383 (Ct. Cl. 1974). But see U.S. Genes v. Vial, 923 P.2d 1322 (Or. Ct. App. 1996) (implied covenant of good faith does not limit the right to terminate the contract for its convenience). Contractors asserting claims of bad faith must overcome the strong presumption that in the absence of clear, contrary evidence, public officials act conscientiously in the discharge of their duties. Cont’l Collection & Disposal Inc. v. United States, 29 Fed. Cl. 644, 652 (Ct Cl. 1993). Since good faith is presumed unless bad faith is demonstrated, the government is prevented only from engaging in actions motivated by a specific intent to harm the plaintiff. Id. The difficult burden of proof for a contractor attempting to show that a government act was undertaken in bad faith has been described as follows: “It requires ‘well-nigh irrefragable proof’ to induce the court to abandon the presumption of good faith dealing.” Kalvar Corp. v. United Beutler_MJI_20150519_11-07_FinalPass.indd 183 5/19/15 11:13 AM 184 Model Jury Instructions: Construction Litigation, 2nd Edition States, 543 F.2d 1298, 1301–02 (Ct. Cl. 1976), cert. denied, 434 U.S. 830 (1977). In the cases where the court has considered allegations of bad faith, the necessary irrefragable proof has been equated with evidence of some specific intent to injure the plaintiff, motivated solely by malice, or actuated by animus toward the plaintiff. Id. Unsubstantiated suspicions and allegations of bad-faith actions are not enough. To demonstrate bad faith, the contractor must identify specific instances of the government’s ill will directed toward it. Id. The state of mind of the contracting officer is critical to determining whether a convenience termination was made in bad faith. No less than knowing and intentional conduct on the part of the contracting officer can support a finding of bad faith. Thus, claims of bad faith have been rejected when the contractor can only prove that the convenience termination was an outgrowth of negligent conduct by the contracting officer. Salsbury Indus. v. United States, 905 F.2d 1518, 1521 (Fed. Cir. 1990). Moreover, mere error on the part of the government, even if it would constitute sufficient ground for contractual breach, is insufficient to demonstrate bad faith. Kalvar Corp. v. United States, 543 F.2d 1298 (Ct. Cl. 1976). A contractor may also attack a contracting officer’s decision to invoke a termination for convenience clause on the grounds that the decision to terminate was an abuse of discretion or arbitrary and capricious. Darwin Constr. Co. v. United States, 811 F.2d 593, 598 (Fed. Cir. 1987). The contractor has the burden of proving arbitrary and capricious conduct. Embry v. United States, 17 Cl. Ct. 617, 625–26 (1989) (holding that two bases of termination—ruined business relations and inadequate performance—supported government’s termination of contractor for convenience). In determining whether a contracting officer has abused his discretion, the Federal Circuit has generally examined the following factors: (1) subjective bad faith on the part of the procuring officials, depriving a bidder of the fair and honest consideration of his proposal; (2) proof that there was no reasonable basis for the decision; (3) the degree of proof of error is ordinarily related to the amount of discretion entrusted to the procurement officer; and (4) proven violation of pertinent statutes or regulations. Id. In Torncello v. United States, 681 F.2d 756 (Ct. Cl. 1982), the court appeared to alter the “Traditional Standard” described above by requiring Beutler_MJI_20150519_11-07_FinalPass.indd 184 5/19/15 11:13 AM Termination 185 the government to demonstrate “changed circumstances” as a precondition to terminating a contract for convenience. According to the plurality opinion, unless the government’s ability to terminate a contract under a termination for convenience clause was limited, the inclusion of the clause created an unenforceable illusory promise. In order to prevent such a result, the court stated that the use of a termination for convenience clause must be limited to situations when “the circumstances of the bargain or the expectations of the parties have changed sufficiently that the clause only serves to allocate risk.” Id. at 771–74. In adopting the changed circumstances test, the plurality rejected the government’s argument that the traditional standard provided an adequate check on the government’s use of termination for convenience clauses so as to provide consideration for the bargain. However, since Torncello, most courts have declined to apply the changed circumstances test, stating that Torncello merely “stands for the unremarkable proposition that when the government contracts with a party knowing full well that it will not honor the contract, it cannot avoid a breach claim by adverting to the convenience termination clause.” Salsbury Indus. v. United States, 905 F.2d 1518, 1521 (Fed. Cir. 1990). 11.04 Damages for Termination for Convenience The termination for convenience clause limits the owner’s liability for a termination that would otherwise constitute a breach of contract. Option A: (specific contract provision): According to the contract, if the owner terminates the contractor for convenience, the owner must pay the contractor the following amounts: [list damages from contract: (1) the cost of the work performed, (2) demobilization and closeout costs, and/or (3) a premium for work not performed] The contractor must prove the amount of such costs with reasonable certainty. Beutler_MJI_20150519_11-07_FinalPass.indd 185 5/19/15 11:13 AM 186 Model Jury Instructions: Construction Litigation, 2nd Edition Option B: (no specific contract provision): The measure of damages available to a contractor terminated for convenience is the cost the contractor actually incurred up to the date of termination, plus a reasonable profit on the work performed prior to termination. The contractor bears the burden of proof to establish its termination for convenience damages. Comment When the government terminates a contractor for convenience, instead of receiving full expectation damages, the contractor’s recovery is defined by the termination for convenience clause. Linan-Faye Constr. Co. v. Hous. Auth. of City of Camden, 49 F.3d 915 923 (3d Cir. 1995). The overall purpose of a termination for convenience settlement is to fairly compensate the contractor and to make the contractor whole for the costs incurred in connection with the terminated work. Nicon Inc. v. United States, 331 F.3d 878, 885 (Fed. Cir. 2003). Generally, the contractor is entitled to damages in the amount of the cost of the contract work performed before the termination, plus a fair and reasonable profit on the work performed. United Partition Sys. Inc. v. United States, 90 Fed. Cl. 74, 89 (2009); Rhen v. United States, 17 Cl. Ct. 140, 143 (1989). Unless provided in the contract, many courts determine a contractor terminated for convenience is not entitled to recover anticipated, but unearned, profit. Rhen, 17 Cl. Ct. at 143; Century Marine Inc. v. United States, 153 F.3d 225, 227 (5th Cir. 1998); Mega Constr. Co. v. United States, 29 Fed. Cl. 396, 475 (1993). The contractor bears the burden of proof to establish termination for convenience damages. White Buffalo Constr. Inc. v. United States, 52 Fed. Cl. 1, 13 (2002); United Partition Sys. Inc., 90 Fed. Cl. at 89. “[A] termination for convenience unequivocally terminates the contract and relieves (the terminated party) from incurring any further obligation associated with the project.” Pub. Bldg. Auth. of City of Huntsville v. St. Paul Fire & Marine Ins. Co., 80 So. 3d 171 (Ala. 2010). Beutler_MJI_20150519_11-07_FinalPass.indd 186 5/19/15 11:13 AM Termination 187 11.05 Backcharges and Termination for Convenience If the owner terminates the contractor for convenience, the owner cannot recover damages or withhold money from the contractor associated with either (1) defective work that the contractor was not given an opportunity to cure or (2) the cost to complete the contractor’s work by other parties. Comment “[A] termination for convenience unequivocally terminates the contract and relieves (the terminated party) from incurring any further obligation associated with the project.” Id. Further, there is “no applicable legal authority to support a position that a termination for convenience may be converted to a termination for cause. A party cannot resuscitate a dead contract so that it may re-terminate it.” Id. After a termination for convenience, it is not appropriate to backcharge the contractor for completion or work not completed or billed by the contractor. Richerson Constr. Corp. v. Gen. Servs. Admin., 93-1 B.C.A. (CCH) ¶ 25,239 (1992). Rather, it is well recognized in the industry that an offset for costs to complete is only available when the contractor is terminated for default. See Tishman Constr. Corp. v. City of N.Y., 228 A.D.2d 292, 293 (N.Y. 1996); Fruin Corp. v. Niagara Frontier Transp. Auth., 180 A.D.2d 222, 233 (N.Y. 1992). “[W]here a party has terminated a contract for convenience, that party may not then counterclaim for the cost of curing any alleged default.” Shelter Prods. v. Steelwood Constr. Inc., 257 Or. App. 382, 401–03 (2013); see also N.Y. Shipbuilding Co., ASBCA No. 15443, 73-1 BCA ¶ 9852; W. States Painting Co., ASBCA No. 13843, 69-1 BCA ¶ 7616, at 35,379; Paragon Restoration Grp. Inc. v. Cambridge Square Condos., 42 A.D.3d 905, 906 (2007); Tishman Constr., 228 A.D.2d at 293. This rule was upheld in Paragon Restoration Group Inc. v. Cambridge Square Condominiums, 42 A.D.3d 905 (N.Y. 2007), in which the court held that when an owner terminates a construction contract for convenience, the owner loses its right to counterclaim for the cost of curing alleged defects Beutler_MJI_20150519_11-07_FinalPass.indd 187 5/19/15 11:13 AM 188 Model Jury Instructions: Construction Litigation, 2nd Edition in the contractor’s performance. Similarly, in Steelwood, the terminating party placed the contractor on notice of potential claims related to deficiencies in the work. Then, immediately after sending the letter and prior to allowing an opportunity to cure, the terminating party “terminated the agreement pursuant to [the termination for convenience provision ‘without cause.’” Steelwood Constr., 257 Or. App. at 402. “Under those circumstances, nothing in the contract permits Catamount to receive an offset against Steelwood’s costs for allegedly defective work done by Steelwood prior to the termination.” Id. The court determined the remedy for the terminating party to charge the contractor for costs to repair was available “pursuant to its right to terminate for cause.” Id. at 401. Yet, the right to terminate was only available after satisfying the contractor’s “opportunity [] to ‘correct, replace and/or re-execute faulty or defective work.’” Id. at 401. As a result, the court upheld the district court’s entry of summary judgment determining that the terminating party “was not entitled to offset any amounts it owed [the contractor] with amounts it incurred in correcting [the contractor’s] allegedly defective work.” Id. at 403. Similarly, in Fruin-Colnon, the court determined that when the contractor was terminated (purportedly for cause) without the contractually required notice and opportunity to cure, the terminating party could not recover costs to repair deficient work from the contractor. Fruin-Colnon, 180 A.D.2d at 233–34. In upholding the lower court’s denial of such repair damages, the court stated as follows: “[D]efendant had the right to remedy any defect at plaintiff’s expense, but only if plaintiff first had been granted the opportunity to cure the defect and had failed to do so.” Id. (emphasis added). Another court held, “Where the City elects to terminate for convenience, as provided in section 15, whether with or without cause, it cannot counterclaim for the cost of curing any alleged default.” Tishman Constr. Corp., 228 A.D.2d at 292–93. The court explained, “Had the City wished to pursue these claims, plaintiff should have been terminated [for default], which provides for recouping the expense of curing plaintiff’s default.” Id. Beutler_MJI_20150519_11-07_FinalPass.indd 188 5/19/15 11:13 AM Termination 189 11.06 Constructive Termination The contract between the owner and contractor provides that the owner may terminate the contractor for cause or for its convenience. The contract also provides that in the event the owner wrongfully terminates the contract for cause, such termination shall be deemed to be a termination for convenience. Here, the owner terminated the contractor for cause. If you find that the owner’s termination for cause was wrongful, you must consider the termination to have been for the owner’s convenience, unless you also find that the termination was in bad faith. “Bad faith” in this context means that the owner acted with malicious intent or animus toward the contractor or by entering into the contract knowing full well that it had no intention of honoring the contract. Comment Under most federal government contracts, as well as many state, municipal, and private contracts, a termination for default that is found to be wrongful is automatically converted to a termination for convenience. See Federal Acquisition Regulations FAR 52.249-8(g), FAR 52.249-10(c). Thus, where a contracting officer has not explicitly invoked the termination for convenience clause, courts have held that if the contract contains a termination for convenience clause and the contracting officer could have invoked the clause instead of terminating, rescinding, or repudiating the contract on some other invalid basis, the court will constructively invoke the clause to retroactively justify the government’s actions, avoid breach, and limit liability. Praecomm Inc. v. United States, 2007 WL 2317519 (Fed. Cl. 2007); see also Best Foam Fabricators Inc. v. United States, 38 Fed. Cl. 627 638 (1997); Hancock Elec. Corp. v. Washington Metro. Area Transit Auth., 81 F.3d 451, 454 (4th Cir. 1996). Courts have imposed limits, however, on the use of the constructive termination for convenience doctrine. As discussed in Part 11.03, to avoid application of the constructive termination for convenience doctrine, most courts require the contractor to demonstrate that the termination decision either was a product of bad faith or constituted clear abuse of discretion. Kavlar Corp. v. United States, 543 F.2d 1298, 1301 (Ct. Cl. 1976); see Beutler_MJI_20150519_11-07_FinalPass.indd 189 5/19/15 11:13 AM 190 Model Jury Instructions: Construction Litigation, 2nd Edition also John Reiner & Co. v. United States, 325 F.2d 438, 442 (Ct. Cl. 1963). But see Torncello v. United States, 681 F.2d 756 (Ct. Cl. 1982) (holding that the constructive application of a termination for convenience clause requires some kind of change from the circumstances of the bargain or in the expectations of the parties). 11.07 For Default (or Cause)—Common Law As a general rule, a party to a contract is entitled to terminate the contract if the other party breached a material term of the agreement and failed to perform as agreed. To demonstrate the termination was proper, [terminating party] has the burden to demonstrate the following: (1) [The terminated party] has an obligation under the agreement. (2) The obligation was a material term. (3) [The terminated party] failed to perform the obligation. (4) [The terminating party] performed all of its responsibilities under the contract. Comment This instruction is appropriate where contractual language provides that an owner may terminate the contract for dissatisfaction or cause. Some contracts allow an owner to terminate a contract for its convenience, at will, or for no reason whatsoever. In such a circumstance, the owner can usually terminate for any reason. See U.S. Genes v. Vial, 923 P.2d 1322 (Or. Ct. App. 1996). If the contract intends to leave a decision to one party, subject only to the requirement of good faith, the court should not impose an additional requirement of reasonableness. See Action Eng’g v. Martin Marietta Aluminum, 670 F.2d 456, 460 (3d Cir. 1982). A contract may be terminated for default only on a material breach of contract. See Wells Benz Inc. v. United States ex rel. Mercury Elec. Co., 333 F.2d 89, 92 (9th Cir. 1964) (default termination is proper only if “the other’s breach is so gross that the very object of the contract is defeated”); Beutler_MJI_20150519_11-07_FinalPass.indd 190 5/19/15 11:13 AM Termination 191 Daff v. United States, 31 Fed. Cl. 682, 689–91 (1994), aff’d, 78 F.3d 1556 (Fed. Cir. 1996). Virginia courts have determined that any breach of a contract that jeopardizes future interests of the other contracting party is by definition a material breach. Clevert v. Soden, 400 S.E.2d 181, 182 (Va. 1991). An owner may also be estopped from terminating the contract for a contractor’s failure to perform according to the contractual terms if the owner, after becoming aware of this failure, continued to encourage or allow the contractor to continue. See Indem. Ins. Co. v. United States, 14 Cl. Ct. 219 (1988). 11.08 Contractual Termination for Default after Notice In this case, [the owner] had a right, under the express terms of the contract, to terminate the contract for cause if the contractor failed to perform a material obligation of the contract. Here, the owner contends that it was entitled to terminate the contractor because [list reason]. In order to terminate for cause, the owner was required to provide the contractor written notice and [list time frame] to cure the default. The owner must demonstate the following: (1) The contractor had an obligation to [list breach]. (2) The contractor failed to [list breach]. (3) The owner provided the contractor written notice and [list time frame] days to cure the default. (4) The contractor failed to make reasonable efforts to cure the default. (5) The owner provided the contractor written notice that the contract was terminated. Even if you find that the contractor [list breach], the owner was not entitled to terminate the contract for default unless it gave the contractor written notice of the breach and an opportunity to cure. Beutler_MJI_20150519_11-07_FinalPass.indd 191 5/19/15 11:13 AM 192 Model Jury Instructions: Construction Litigation, 2nd Edition 11.09 Damages for Termination for Cause If you find that the owner’s termination of the contractor for cause was proper, then you may award the owner damages as follows: cost to complete the project [minus] unpaid balance of the owner’s contract with the contractor [plus] owner’s reasonable and foreseeable costs arising from the contractor’s failure If the owner completed the project for less money that it would have cost the contractor to complete the project, the owner is not entitled to any damages from the contractor. Comment The general rule for the measure of recovery by an owner for an incomplete performance by a defaulting contractor is the reasonable cost of construction and completion in accordance with the contract. Kirkpatrick v. Temme, 654 P.2d 1011, 1012–13 (Nev. 1982). Courts are split, however, as to which party bears the burden of proving the “reasonable” costs of construction. One line of cases holds that, in determining damages based on cost to complete, the actual costs expended by an owner in completing the work are “presumed to be reasonable absent a showing [by the contractor] to the contrary.” LBL Skysystems (USA) Inc. v. APG-Am. Inc., 2006 U.S. Dist. LEXIS 65142, at *79 (E.D. Pa. Sept. 6, 2006) (citing 24 Williston on Contracts § 66:17 (4th ed. 1999); see also Fetzer v. Vishneski, 582 A.2d 23, 26–27 (Pa. Super. Ct. 1990). In Fetzer, the court held that when the owner has presented evidence as to the cost of remedying the defects, the burden is on the contractor to challenge this evidence. Specifically, the court stated: “[I]f the owner has had the repair or completion performed at the time of trial, the amount paid by the owner may be presumed to be reasonable, subject to rebuttal evidence by the contractor. The amount actually paid by the owner to Beutler_MJI_20150519_11-07_FinalPass.indd 192 5/19/15 11:13 AM Termination 193 another contractor for correction of the defective work, within a reasonable time after the breach, is strong and reliable evidence in determining the time and amount of damages.” Fetzer v. Vishneski, 582 A.2d 23, 26–27 (Pa. Super. Ct. 1990) (emphasis added); see also Darger v. Nielsen, 605 P.2d 1223, 1225 (Utah 1979) (contractor bore the burden of proof concerning allegations that the cost was unreasonable or that the owner added construction beyond the contract specifications); Carlin v. Comstock, 450 A.2d 875 (Conn. Super. Ct. 1982) (if the owner has had the repair or completion performed at the time of trial, the amount paid by the owner may be presumed to be reasonable, subject to rebuttal evidence by the contractor); Webster v. Culver Roadways Inc., 79 Misc. 2d 256, 258 (N.Y. Sup. Ct. 1974) (when contractor defectively performs “the . . . amount actually paid by the plaintiff to another contractor for correction of the defective work . . . is strong and reliable evidence in determining the . . . amount of damages”). Other courts, however, have held that the owner bears the burden of proving the reasonableness of its costs to complete the work. Ferris v. Mann, 210 A.2d 121 (R.I. 1965) (holding that even though owner introduced evidence of the nature and cost of the additional work done to complete construction, in the absence of any evidence as to the reasonableness of such costs, the owner could not recover for the installed materials). The standard for federal government contracting provides that when a contractor is properly terminated for default, the government is entitled to recover the excess cost of re-procuring the uncompleted work where it demonstrates those completion costs were reasonably incurred. Cascade Pac. Int’l v. United States, 773 F.2d 287, 293–94 (Fed. Cir. 1985). Courts following the federal standard hold that excess re-procurement costs may be imposed only when the government meets its burden of persuasion that the following conditions are met: (1) the re-procured supplied are the same as or similar to those involved in the termination, (2) the government actually incurred excess costs, and (3) the government acted reasonably to minimize the excess costs resulting from the default. 41 C.F.R. § 1-8.602-6(a), AstroSpace Labs. Inc. v. United States, 470 F.2d 1003, 1018 (Ct. Cl. 1972). The first condition is demonstrated by comparing the item re-procured with the item specified in the original contract. Envtl. Tectonics Corp., ASBCA No. 21204, 78-1 BCA 12,986, 63,308. The second condition requires the Beutler_MJI_20150519_11-07_FinalPass.indd 193 5/19/15 11:13 AM 194 Model Jury Instructions: Construction Litigation, 2nd Edition government to show what it spent in re-procurement. Fairfield Scientific Corp. v. United States, 611 F.2d 854, 863–66 (Ct. Cl. 1979). The third condition requires that the government act within a reasonable time of the default, use the most efficient method of re-procurement, obtain a reasonable price, and mitigate its losses. Astro-Space Labs. Inc., 470 F.2d at 1018. In jurisdictions following the federal standard and holding that the owner must prove reasonableness, the most desirable evidence for the owner to proffer is a firm competitive bid. If that is not available, courts prefer expert testimony, based on computation of the work undertaken. Additionally, the owner can present testimony or documentary evidence by those qualified to estimate the cost of repair and reconstruction, such as a contractor’s written repair estimate. John Ludington, Modern Status of Rule as to Whether Cost of Correction or Difference in Value of Structures Is Proper Measure of Damages for Breach of Construction Contract, 41 A.L.R.4th 131 (1986); see also Henson v. Gonzalez, 326 So. 2d 396 (La. App. 1976); Ferris-Prabhu v. Dave & Son Inc., 457 A.2d 631 (Vt. 1983). 11.10 Opportunity to Cure Cure is a well-established and fundamental right. If you find that the breach was capable of being cured, then the breaching party must have been given the opportunity to cure it. If the non-breaching party terminated the contract without providing a reasonable opportunity for the other party to cure the default, that termination itself is a material breach and renders the termination wrongful. Comment Some breaches cannot be cured, such as a contractor’s failure to substantially complete the work before to the expiration of an unwaived completion date; thus, an owner need not provide a cure notice. See Abcon Assocs. Inc. v. United States, 44 Fed. Cl. 625 (1999) (cure notice not required when contract completion date not met); Bd. of Water & Sewer Comm’rs of City of Mobile v. Bill Harbert Constr. Co., 27 So. 3d 1223 (Ala. 2009) (acknowledging that when “termination is for failure to meet a performance deadline, Beutler_MJI_20150519_11-07_FinalPass.indd 194 5/19/15 11:13 AM Termination 195 the law eliminates the notice requirement”); L.K. Comstock & Co. v. United Eng’rs & Constructors Inc., 880 F.2d 219, 232 (9th Cir. 1989) (cure notice is not required because it would have been a “useless gesture”). However, if a breach can be cured, then the breaching party must be given the opportunity to do so. See Burras v. Canal Constr. & Design Co., 470 N.E.2d 1362, 1367 (Ind. Ct. App. 1st Dist. 1984) (because the subcontractor “was not given an opportunity to remedy any alleged defects, any incidence of defective performance did not constitute a breach of the construction contract”); Gulf Ins. Co. v. Fid. & Deposit Co. of Md., 847 N.Y.S.2d 896 (2007) (termination was wrongful because the subcontractor was not provided notice and an opportunity to cure); Bruning Seeding Co. v. McArdle Grading Co., 439 N.W.2d 789, 791 (Neb. 1989) (contractor’s failure to give opportunity to cure before termination constituted a material breach of the subcontract); Blaine Econ. Dev. Auth. v. Royal Elec. Co., 520 N.W.2d 473 (Minn. Ct. App. 1994) (owner wrongfully terminated a construction contract by failing to first give a opportunity to cure). The opportunity to cure is implied in every contract as a matter of law. U.S. for Use & Benefit of Cortolano & Barone Inc. v. Morano Constr. Corp., 724 F. Supp. 88, 98 (S.D.N.Y. 1989) (“Despite the absence of any contractual provision, a subcontractor alleged to be in default is entitled to receive more notice than [the subcontractor] received here.”); Bates v. Benedetti, E2010-01379-COA-R3-CV, 2011 WL 978195 (Tenn. Ct. App. 2011) (recognizing owner’s common-law duty to give notice and an opportunity to cure before termination). 11.11 Required Notice Termination of a contract for default without providing notice is a material breach. The notice must describe the inadequate performance and must fairly advise the contractor that the owner considers the inadequate performance serious enough that, without prompt correction, the contract will be terminated. Beutler_MJI_20150519_11-07_FinalPass.indd 195 5/19/15 11:13 AM 196 Model Jury Instructions: Construction Litigation, 2nd Edition A contract can only be terminated for default for reasons that the contractor was provided notice of and an opportunity to cure. If an owner notifies the contractor of one default (that is cured) and then terminates the contractor for a separate default (without notice and an opportunity to cure), the owner failed to comply with its notice obligations. Comment Failure to give required notice operates as a material breach of the contract. Madden Phillips Constr. v. GGAT Dev. Corp., 315 S.W.3d 800, 823–24 (Tenn. Ct. App. 2009); Cuddy & Mountain Concrete v. Citadel Constr., 824 P.2d 151 (Idaho Ct. App. 1992); Bruning Seeding Co. v. McArdle Grading, 439 N.W.2d 789 (Neb. 1989); U.S. for Use of Cortolano & Barone v. Morano Constr., 724 F. Supp. 88 (S.D.N.Y. 1989); Burras v. Canal Constr. & Design Co., 470 N.E.2d 1362 (Ind. Ct. App. 1984). Virtually all termination clauses require the owner to provide the contractor with a notice of default. Courts have imposed an implied obligation to provide notice and an opportunity to cure, even when the contract does not contain a notice provision. McClain v. Kimbrough Constr. Co., 806 S.W.2d 194 (Tenn. Ct. App. 1990). Notice gives the contractor an opportunity to cure the default, correct deficiencies, and stave off the threatened termination. A cure notice that thoroughly sets out the extent of the deficiencies is adequate and advises that they are serious enough to warrant termination unless corrected promptly is sufficient. Hannon Elec. Co. v. United States, 31 Fed. Cl. 135, 148 (1994); Blaine Econ. Dev. Auth. v. Royal Elec. Co., 520 N.W.2d 473, 477 (Minn. App. 1994). 11.12 Wrongful Termination The burden of proof to demonstrate that a termination was proper is on the party who termiated the contract. The owner’s termination is wrongful if you find any of the following: (1) The contractor did not materially breach the contract. Beutler_MJI_20150519_11-07_FinalPass.indd 196 5/19/15 11:13 AM Termination 197 (2) The owner failed to provide the contractor with notice of the breach. (3) The owner failed to provide the contractor a reasonable opportunity to cure the breach. If you found any of the above occurred, the contractor can recover damages from the owner for the wrongful termination. Comment The legal standard for determining when a breach is material is not always clear in construction cases. See Walker & Co. v. Harrison, 81 N.W.2d 352, 355 (Mich. 1957) (the decision to terminate a contract “is fraught with peril for should such determination, as viewed by a later court in the calm of its contemplation, be unwarranted, the repudiator himself will have been guilty of material breach and himself have become the aggressor, not an innocent victim”). Depending upon the language of the subcontract termination clauses, the termination of the prime contract also may result in termination of subcontracts. See Carolina Cas. Ins. Co. v. Ragan Mech. Contractors Inc., 584 S.E.2d 646 (Ga. Ct. App. 2003), cert. denied (Oct. 20, 2003) (holding that a subcontract was terminated by virtue of an owner’s termination of a prime contract for default and that the subcontractor had no obligation to continue performance of the subcontract under the prime contractor’s take over of surety). 11.13 Damages for Wrongful Termination If you find that the owner wrongfully terminated the contractor, then you may award the contractor damages as follows: (1) the unpaid portion of the work it performed and/or materials it furnished as of the date of termination; plus Beutler_MJI_20150519_11-07_FinalPass.indd 197 5/19/15 11:13 AM 198 Model Jury Instructions: Construction Litigation, 2nd Edition (2) the profit the contractor would have earned on the remaining work if it had been completed. In order to award the contractor profit on work not performed, the contractor must show with reasonable certainty the amount of profit it would have earned. Comment Wrongful termination is a material breach of the contract for which the contractor is entitled to damages. Generally, the measure of the contractor’s damages is the lost profit it would have realized, had it completed the project, plus the costs reasonably incurred in good-faith partial performance of the contract. Ballard v. Krause, 248 So. 2d 233, 234 (Fla. App. Ct. 1971); Liner v. Armstrong Homes of Bremerton Inc., 579 P.2d 367, 371 (Wash. Ct. App. 1978); Sweeney Co. of Md. v. Eng’rs-Constructors Inc., 823 F.2d 805, 812 (4th Cir. 1987); Imaging Sys. Int’l Inc. v. Magnetic Resonance Plus Inc., 490 S.E.2d 124, 126 (Ga. Ct. App. 1997); Ark Constr. Co. v. City of Florissant, 558 S.W.2d 418, 423 (Mo. Ct. App. 1977); Edvard Dev. Tompkins Inc. v. City of Bridgeport, 110 A. 183 (Conn. 1920). Lost profits due to the wrongful termination of a construction contract may be established by showing the total cost that would have been incurred in performing the contract, had the contractor been permitted to complete the job, and subtracting that amount from the contract price. Johnson Enters. of Jacksonville v. FPL Grp. Capital Inc., 162 F.3d 1290, 1325 (11th Cir. 1998). The loss, however, “must be proven with a reasonable degree of certainty” before it is recoverable. Id. The contractor bears the burden of proving its wrongful termination damages with reasonable certainty. Ballard v. Krause, 248 So. 2d 233, 234 (Fla. App. Ct. 1971). Where the owner’s wrongful termination results in the contractor’s inability to obtain future work due to lack of bonding capacity, the contractor may also recover its future lost profits. However, a contractor seeking to recover on a claim for damages allegedly resulting from lost bonding capacity bears a heavy burden. It must establish proximate causation (e.g., that the termination was the cause of its inability to maintain its bonding capacity); Beutler_MJI_20150519_11-07_FinalPass.indd 198 5/19/15 11:13 AM Termination 199 as a consequence of that diminished capacity, it lost profits; reasonable certainty (e.g., the actual losses are not speculative but can be quantified with a reasonable degree of accuracy); and reasonable foreseeability (e.g., the purported damages were within the contemplation of the parties at the time they entered into the contract). Delahanty v. First Pa. Bank NA, 464 A.2d 1243, 1258 (Pa. Super. Ct. 1983) (citing R.I. Lampus Co. v. Neville Cement Prods. Corp., 378 A.2d 288 (Pa. 1977)). Beutler_MJI_20150519_11-07_FinalPass.indd 199 5/19/15 11:13 AM Beutler_MJI_20150519_11-07_FinalPass.indd 200 5/19/15 11:13 AM
© Copyright 2026 Paperzz