FACILITY COOL-DOWN US firm outlines its LNG terminal cool-down procedure at start-up Osifo Akhuemonkhan and Roberto Ruiperez Vara, CH•IV International, Baltimore, Maryland As companies around the world push forward with their plans to commission new LNG import facilities, it is common to see critical activities associated with the cool-down of such facilities given a low priority when compared to other commissioning activities. The push to make final preparations for cool-down often results in a “gap” between the level of preparation and detail included in procedures and the expectations at the engineering, procurement and construction phase. All too often the owner-operator does not recognize the “gap” until it is too late. The quality of operator training is often compromised and delays in commissioning are frequent, as late modifications are made to process piping and equipment to properly handle the cool-down. This article identifies commissioning strategies owner-operators can adopt to After the completion of LNG import terminals, such as the one above, modifications are made to process piping and equipment to handle the cool-down procedure. This is before the first LNG cargoes are delivered to the facility before start-up is defining what is “clean” should be cut diagonally at their ends so install heat tracing on the valve trunnions. when determining pipe cleanliness. as to prevent entry of water on rainy days. Valve seat durability is generally Valves: proportional to the price you pay for the bridge the potential “cool-down gap” and Depending on the party and the level ensure a smooth, safe and effective of usually Install a locking mechanism in each valve. But take into account that even terminal start-up and transition to somewhere between no hard hats or valve to avoid accidental opening or closing the highest quality valve seat may get operations. pieces of 2x4s in the lines to no of the valves during pipeline cleaning or damaged by foreign materials. microscopic dust. other construction activities. In most cases For the most part, companies that responsibility, clean is design and construct LNG storage tanks Clean may best be defined as having valves are delivered by vendors in an open Cryogenic dry-out have well-developed and well-established removed any foreign matter that could position, it is best that valves be installed To allow proper operation of the facility, procedures for clean-up, dry-out and cool- harm and locked in this position. all cryogenic piping must be thoroughly down of their tanks. commissioning and start-up activities. In particular, during the cleaning dried out. Small quantities of water, or equipment during ensuing It is not suggested that there are Although high flow pipe blows are process avoid blowing through butterfly even water vapor, can freeze in valve typically large gaps in expectation for the often the approach used to clean lengths valves, control valves or other valves with bodies, valve trunnions, pump parts and commissioning and cool-down of the of pipe, one must consider the effect of exposed seats. passages, tanks, but the facility owner-operator welding slag or foam glass dust on soft debris through butterfly valves can easily strainer media or any low point in the should still closely monitor all LNG tank- valve seals during these blows. damage the disc. In such situations a spool piping system. related commissioning activities. For example, blowing instrument connections, For example, most LNG pumps use the piece should be installed in place of these LNG itself to cool and lubricate the pump valves and, subsequent to cleaning, the operation of equipment and/or lead to Procedure bearings. Once in operation, if foreign butterfly valves should be “golden welded” failure of the bearing materials, such as Preparations for an LNG facility start-up materials plug the cooling paths or into the pipelines to prevent the need for the galling of trunnion bearings. require that detailed procedures be damage the bearings, the pump could pressure testing. Some vendors offer In addition particles of ice that developed and implemented for the suffer a total failure. additional protection for the moving parts breakaway and are carried through the In addition to vendor-specific pre- This could prevent or restrict of the valve to prevent damage from cryogenic system may clog strainers, Piping and equipment clean-up installation storage requirements, the impacts caused by high speed particles. block the cooling paths in the LNG Dry-out following are some other precautionary Unnecessary opening and closing of pumps or damage valve seats. Purge steps that will minimize issues arising valves may encourage build up of debris Once a system is inventoried with Pre-cool-down from poor cleaning and/ dry-out. and other particles present in piping. If LNG, these issues become extremely Cool-down Piping: valves need to be operated prior to or difficult Confirm that the design of the piping during pipe cleaning, these operations lines/components may have to be de- Piping clean-up includes low point drains throughout the should be properly supervised and proper inventoried, After construction, piping, valves and cryogenic system. procedures should be utilized for cleaning repaired, purged again, re-dried, re- vessels often contain certain amounts of Store piping components with end soft seats. cooled and re-inventoried. construction debris and possibly free caps in place until they are installed. A method to confirm that valve Such actions could also cause a delay water that has accumulated over the long Seal opens ends of piping during trunnions are absolutely dry (no free water) in the start-up schedule and become very months of construction. One of the first construction when access is not required. prior to initiation of piping dry-out should costly for the owner-operator or EPC gaps encountered in the closing months Large diameter vents to atmosphere be developed. One example would be to contractor. following activities: Reprinted with permission from LNG Journal. LNG journal to resolve purged, • February 2009 as these warmed-up, • 23 FACILITY COOL-DOWN Less obvious are the potential issues most effective method of assuring that the gas in petrochemical industries can systems that involve multiple elevations, a on how to re-cool the repaired section of cryogenic systems are properly dried out. freeze under cryogenic temperatures. significant number of elbows and/or a the plant with LNG present in other With the “Sweep and Soak” technique sections. Hence, it is very important that the tight envelope is less predictable. Final the drying medium (dry air or nitrogen commissioning team should have a well cool-down is not the time to find out that all piping systems expected to experience with a dew point of -60°C/-80°F) is prepared procedure detailing the method to the piping did not move as expected. cryogenic temperatures are dried out introduced at one or more points in the be used to purge the system and in Unexpected pipe movement can result in before placed in operation. cryogenic piping system and allowed to particular, the sequence and timing of steps, insulation It is also important that consideration flow through a large portion of the including rate of introduction of the purge misalignment and/or mechanical damage be given to drying out the facility long system and is then vented to atmosphere. medium and verification of end points. to the pipe and/or pipe support systems. A before mechanical completion of the As the name implies, the goal is to Once the amount of nitrogen needed test can confirm that piping will move as cryogenic piping as many problems in sweep the entire piping section or system has been accurately calculated a supply expected. Critical pipe supports should be dry-out can occur as a result of poor (or until the TDP is reached. of the whole amount has to be arranged. pre-marked with initial and expected hurried) planning and preparation. Starting process Perform visual inspection (may require specialized equipment) of large- Much as with dry-out, damage, pipe guide This by no means indicates that that The commissioning team will need to piping section is dry, it only indicates that decide whether a displacement or dilution/ 3. Confirmation dry media is available throughout the mixing method will be used for the purge. procedure: Often, cool-down of the LNG section or system to complete the dry-out procedure. movement before the start of the test. . of final cool-down In the former, the purging gas is transfer system is performed with an introduced to remove the existing gas LNG carrier connected to the unloading bore piping to verify that no stagnant Once the TDP is reached, the main without mixing both gases. Although system. water is found. It is important to start the vent point(s) is closed and a drying flow is some mixing cannot be avoided, with the difficult to test the cool-down procedure dry-out with as little water as possible in established to piping laterals, equipment, use of lower pressures and proper exit before the carrier arrives. On the other the system as this may greatly extend the instrument taps, etc. through various points it can be minimized. hand, if vaporized liquid nitrogen is to be time required to achieve dry-out. Pay ambient vent locations. In this scenario it is very The quantity of purge gas needed is used to cool down the LNG transfer special attention to dead legs and low As TDP is reached at each of these therefore about equal to the quantity of system prior to introducing LNG then points in the system as water is likely to locations the vent is closed such that the dry gas to be displaced. The latter method is pre-cool-down testing can take place. accumulate at these points. media is allowed to sit for a while i.e., “soak.” used when the piping limitations force This will be particularly useful if there Field confirm that the identified dew After a pre-determined period of time, you to pressurize and depressurize the are unique aspects to the cool-down path point sample points are readily accessible the dew point is checked again at these system to remove the gas to be purged. chosen or peculiarities with the location and, if not, viable alternatives are identified. various test points to confirm that the TDP Ensure an adequate number of has been maintained in the piping. of the cool-down equipment with respect Pre-cool-down test to the LNG transfer system. Does one quality dew point meters are available If the testing shows dew point has not For example, when purging LNG tanks, wait until a ship loaded with high-value during dry-out. They should be portable remained at the TDP or below, then water an effective way to proceed would be to cargo is sitting at the berth before with back-lit readouts and rated for vapor has been absorbed into the drying introduce the purge gas via the bottom confirming that the piping can be temperatures and pressures of the gas media. fill line at low pressures. This would properly cooled to commence unloading? slowly displace the total volume of air in Testing of the balance of plant may also the tank with little mixing. be beneficial if vaporized liquid nitrogen samples expected. Ease of use and rapid The effected sub-system should be response time are critical for large swept again and re-tested after soaking. system dry-outs with multiple dew point Once the dew point testing indicates the If there is to be a pre-cool-down test of sample points. If dry natural gas is to be pipe subsection has remained dry, the any portion of the facility, the purge can used for dry-out, the instruments must sub-system can be isolated until purge or be deferred until then as the test will also Why cool-down? also have proper electrical classification. cool-down commences. purge the system piping. Unless specifically designed for such a is used in the final cool-down. Dry media delivery equipment should If after multiple soaks, the piping A pre-cool-down test can help provide condition, when a small flow of LNG at - be thoroughly tested to confirm that it is section fails to maintain the TDP, it can be assurance that ensuing cool-down and 260°F [-160°C] flows into a large capable of guaranteeing the desired flow assumed that there is standing water in start-up diameter pipe that is at ambient at the required maximum dew point for the system and further action should be smoothly. extended periods of time. If the facility’s taken to resolve this. procedures will advance temperature, such as a 36" LNG transfer It requires additional costs and adds to line, the bottom of the line rapidly cools during the schedule during the commissioning/ due to the heat transfer from the LNG, used, it is important that the system is commissioning require detailed procedures start-up phases, however its benefits while the top of the pipe stays relatively fully commissioned and designed to and accurate record keeping to confirm the typically far outweigh any negatives. warm for some time. operate at continuous, high capacity for entire cryogenic piping system is properly The test involves cooling some or all of Stainless steel contracts at a rate of the duration of the entire facility dry-out. dried and that “wet” media has not been the cryogenic piping to near operating about 3" per 100 feet [125 mm per 50m]. pushed into previously dried sections. temperatures instrument air compressors are to be Many of these steps should be taken Dry-out activities the Such contraction results in the pipe objectives. The objectives typically are bowing upwards (the bottom of the pipe significantly affect the remainder of the categorized in three areas: shorter than the top of the pipe). schedule delays during initial and commissioning activities and subsequent 1. Confirmation of dry-out effectiveness: Depending on the pipe support/restraint subsequent commissioning activities. operations. By cooling the cryogenic piping system to system, substantial stresses can be temperatures well below freezing, such as - placed on the system or, if not restrained vertically, substantial upward movement. into consideration during the design of An inadequately dried system can the facility as this may reduce costs and depending on Preferred cryogenic dry-out procedure Purge 40°C/F, Assuming that LNG or LNG vapor is to be particularly those with valve trunnions, Although some large bore piping Dry-out of cryogenic piping is typically used for piping system cool-down, the piping can be stroked once cold to confirm that the systems, such as the deck piping on many considered complete when the Target Dew systems need to be purged of air to avoid valve is free to move, i.e., no ice formation. LNG carriers are designed for the “trickle Point (TDP) of -40°C/°F is reached. developing flammable concentrations. 2. Confirmation of pipe movement: In cool-down” approach, the piping systems the valves in the system, Although there exists a variety of dry-out Nitrogen gas is the preferred medium some cases pipe movement is predictable installed at LNG facilities typically are approaches, experience suggests that the for LNG terminal purging as carbon and not subject to concern. However, in not. “Sweep and Soak” approach provides the dioxide gas, the other predominant purge other cases the movement of piping 24 • LNG journal • The World’s Leading LNG journal Unless specifically designed for trickle Reprinted with permission from LNG Journal. FACILITY COOL-DOWN cooling with LNG, large-bore LNG piping There is no “one-size-fits-all” technique berthed at the facility for an extended installed with spring straps, it is very needs to be cooled with a cryogenic vapor for cooling down LNG piping. There are period of time the cool-down process is unlikely that all the detectors installed flow prior to the introduction of LNG to three main sources for cool-down vapor and susceptible to interruptions in the case of will provide accurate readings and once minimize pipe stresses. the suitability of each source is dependent bad sea conditions. insulation has been installed it becomes Additionally, LNG is “sneaky fast,” i.e., on the facility and the circumstances 3. Vaporized Liquid Nitrogen (LIN): The costly to replace the detectors. once introduced into “warm” piping, surrounding cool-down and commissioning. most likely method of getting LIN into Therefore, although installing a large because of its low viscosity and high The three main sources are: the cryogenic piping would be via trucks. number of temperature detectors on the differential temperature with the base 1. Vapor tank(s): Since the trucks are generally mobile piping marginally increases construction metal, LNG can move very quickly Depending on the piping design features, there is an advantage in terms of costs, the improved indication of cool-down throughout the piping system riding on a cold vapor can be sourced from LNG tanks accessibility to favorable injection points. status can actually result in savings. vapor blanket as it vaporizes. during the tank cool-down or from tanks Of the three sources discussed, the from the LNG method provides the coldest It is important to note that This means that LNG can reach areas of with existing liquid levels in the case of an LIN the piping system long before volumetric expansion facility cool-down. In either injection temperature i.e., -275°F. This using calculations or even elevation would suggest. case, a large volume of gas will be available temperature can also be controlled to be installation methods may accumulate temperature detectors installed on piping spring straps or similar differential for piping cool-down. A significant fraction cooler or warmer using the vaporizer some ice between the device and the temperature the lower the likelihood that of these volumes can also be recovered if installed on the truck. piping during contraction and expansion. a cold vapor front will flow in advance of pipeline compressors are installed and Using LIN also provides an advantage The method of installation should ensure the LNG helping pre-cool the piping. have already been commissioned in the from the standpoint of venting during that there is always a dry, continuous The larger the collapses facility. One of the drawbacks of this source cool-down. With this advantage, cool- contact between the pipeline and metal underneath the LNG there can be rapid of vapor is the relatively low pressure (if down of deadlegs in the system becomes skin temperature detectors to minimize bowing of the piping due to the large boil-off gas compressors are not used) and less of a problem. inaccurate temperature readings. temperature differential between the the instability of the temperature of the However, there are some drawbacks to bottom and top of the pipe. As the vapor blanket vapor. Lower pressures in the piping the use of LIN for cool-down. The major Procedures to reduce residence time of the gas and drawback is the logistics of utilizing LIN LNG facility commissioning activities temperatures that are close to operating consequently larger volumes are required trucks. should not be attempted without properly temperatures the to cool down the piping. In the case where For example, for a world-scale LNG potential of pipe bowing by reducing the the cold vapor is sourced from an LNG import terminal scores of trucks may be Cool-down and purging procedures are top-to-bottom differential temperature, tank that is itself being cooled down, the required. The facility would also need to explicitly mandated by section 14 of while collapsing the vapor blanket more initial erratic behavior of the vapor space have sufficient real estate around the NFPA 59A (2006 ed.) and to a lesser quickly thereby promoting a cold vapor in the tank will greatly affect the injection point(s) for the pumper/vaporizer extent by section 17 of EN-1473. front moving down the piping as the effectiveness of the vapor as a cool-down truck to set up. piping is inventoried with LNG. medium. In the other case where the cold Cooling the LNG helps piping minimize Procedures should be finalized early If nitrogen cooling is contemplated, and/or i.e., several weeks before cool-down is vapor is sourced from an idle tank with an motor operating scheduled to begin. The procedures Cool-down criteria established liquid level, the vapor may not conditions must be considered due to the should be written in a format that can be As stated before, the general rule is that be cold enough to get all the facility piping higher molecular weight of nitrogen. easily modified during the process. The cryogenic liquid piping of a certain size to the target temperature. and larger be cooled down using cold 2. Vapor from an LNG carrier: LNG chosen, the cool-down flow may be “once- information should include: vapor prior to the introduction of LNG. carriers can supply cold vapor via boil-off through” or “recirculated”. LNG vapors, A pre-start valve checklist which indicates Another general rule is that cool-down gas or vaporized LNG. A full carrier will by themselves, rarely provide adequate valve positions just before cool-down begins is considered complete when all piping is have or be able to generate a large enough cooling to achieve total cool-down. cooled to or below a pre-determined volume of vapor to cool a facility. The Consideration needs to be given to Other pre-start activities. For example, temperature. Therefore, two questions carrier will be directly connected to the methods to further desuperheat these confirm inventories of cool-down media, need to be answered as preparations are LNG transfer system hence the longest and flows such that there is ample cooling confirm blinds have been removed, etc. made for cool-down: largest piping system would be cooled first driving force. An instrument operability checklist 1) What pipe size should cool-down in and thoroughly. One strategy that can be Often, if so designed, vapor return used by operators to determine the adopted would be to cool the transfer blowers or BOG compressors can be used accuracy or functionality ofinstruments 2) What is the target temperature? system and the LNG storage tanks then to provide a re-circulating capability of especially control valve and temperature The answer to these questions lies in the use the vapor from the tanks to cool-down the cool-down vapors, taking into account detectors/monitors, design of the terminal. What did the over the remaining piping systems as the heat of compression. A PSV checklist to confirm that PSVs engineer set as the basis for various previously described. A significant fraction This may also make the use of LIN stress calculations? of the vapors used in this method can be more attractive as the full cooling energy Details of the facility’s car seal program by clearly identifying steps this manner be limited to? and, capacities written and reviewed procedures. Additionally, regardless of the medium cool-down procedure and the appended and a valve isolation philosophy, have been set up for service, Unfortunately, far too often it is found recovered if pipeline compressors are from the LIN can be used if the LIN is that the engineer(s) did not specifically available. An issue that should be injected for desuperheating. address these cool-down criteria in their considered for this method is the pressure of analysis. Combine this with the fact that the vapor flow through the piping system. Monitoring all too often the “How large?” and “How Usually, vapor from a carrier is available at Accurate temperature monitoring is moving data (direction as well as length), cold?” questions are asked very late in the low pressures hence the cooling process important in conducting a smooth cool- Sketches planning process confusion is created. would be inefficient as a greater volume down. It is prudent to be liberal with the installed as well as marked up P&IDs for where car seals are to be broken , A list of cryogenic piping supports (“cold shoes”) with the corresponding expected of temporary piping Unless other design specifications would be needed to cool segments of piping. amount of surface mounted (bottom and different stages in the procedure, exist, practical experience suggests all Heat leakage into the vapor via the un- top) temperature detectors installed on Narratives LNG piping 8 inches [200 mm] and above insulated LNG unloading arms would also large diameter piping. (operators, cool-down team) understand should be cooled down to -200°F [-130°C] have to be accounted for. Additionally, since Regardless of the installation method the ultimate goal each section of the with cold vapor before introducing LNG. this method will require that the carrier be i.e., whether welded to the pipe or procedure is meant to accomplish, and Reprinted with permission from LNG Journal. LNG journal • that help February 2009 the • user 25 FACILITY COOL-DOWN instructions Finally it is imperative that all plant Conclusion up is based on well planned and executed The procedures operations personnel involved in the There are a number of ways to commission programs. In the case of commissioning commissioning the and cool down LNG facilities. This paper and final cool-down, adequate preparation statements about potential hazards/ procedures created. This will reduce the has identified some key considerations that and planning should begin as early as the mistakes applicable to each section of the chances are prudent to take into account during design phase of the project. procedure. commissioning. this process. Successful LNG facility start- Osifo Akhuemonkhan and Roberto Ruiperez Vara work for CH•IV International, a major player in LNG terminal projects. CH•IV is a joint venture between MPR Associates, Inc. of Alexandria, Virginia, USA, and CH•IV Corp. of Hanover, Maryland. MPR, founded in 1964, specializes in technical services for the development, design, construction and operation of power facilities and equipment for energy, industrial, and government clients. CH•IV Corp., founded in 1991 had been providing LNG engineering and consulting services to a wide base of clients ranging from international LNG trading to LNG vehicle fleets until the formation of CH•IV International. CH•IV International builds on the “Owner’s Engineer” model applied by MPR in the power industry and transfers it to the LNG industry. The firm’s current LNG activities include providing the front-end engineering and design for six North American projects and one Central America LNG import venture. CH•IV is also currently acting as the Regulatory Engineer for the State of Connecticut and LNG Technical Advisor for the Government of Jamaica. The firm also successfully supported the permitting process of three new import terminals, including Cameron LNG in Louisiana. Among other projects, CH•IV was very actively involved in supporting the reactivation of the US LNG import terminal at Cove Point, Maryland. CH•IV has also provided FEEDs for the US import projects at Downeast, Sparrows Point and Oregon LNG; all three are well into the FERC permitting process. In Asia, CH•IV worked for India’s Petronet on the Dahej LNG terminal expansion and for World Energy Corp on a planned LNG liquefaction plant in Sulawesi, Indonesia. Detailed step-by-step (with contingencies). should also include cautionary of be trained human error on during References American Gas Association (AGA), Purging Principles and Practices (3rd edition, 2001) 26 • LNG journal • The World’s Leading LNG journal Reprinted with permission from LNG Journal.
© Copyright 2025 Paperzz