Electric Transmission Line Guide For State Fish and Wildlife Agencies Prepared by AFWA Energy and Wildlife Committee Wind and Transmission Subcommittee May 2010 Contents INTRODUCTION ......................................................................................................................... 5 HOW CAN A STATE NATURAL RESOURCE AGENCY ENGAGE IN TRANSMISSION PLANNING AND SITING? ...................................................................................................................................... 7 Planning and Project Review..................................................................................................................... 7 Internal Wildlife Agency Considerations................................................................................................. 8 REFERENCES ............................................................................................................................. 11 APPENDIX A- TECHNICAL GUIDANCE ...................................................................................... 13 APPENDIX B – WILDLIFE RECOMMENDATIONS ....................................................................... 15 APPENDIX C – TRANSMISSION INDUSTRY OVERVIEW .............................................................. 19 APPENDIX D – APPLICATION FOR A CERTIFICATE OF CONVENIENCE AND NECESSITY (EXAMPLE FROM TEXAS) .......................................................................................................... 25 APPENDIX E - USEFUL LINKS ................................................................................................... 35 APPENDIX F - USEFUL ABBREVIATIONS AND ACRONYMS......................................................... 36 March 11 iii Energy and Wildlife Policy Committee – Wind and Transmission Subcommittee Transmission Guidance for State Fish and Wildlife Agencies Introduction After a period of strong growth in the mid-1980s, the U.S. wind industry leveled out during the electricity restructuring period in the 1990s and then regained momentum in 1999. Now, the U.S. wind industry is growing rapidly, driven by incentives like sustained production tax credits (PTCs), and state renewable portfolio standards (RPS) in roughly half the states; these RPS require states to obtain a certain percentage of their energy from renewables by a designated year. There is now wind generation operating in almost every state (Figure 1). In addition, rising concerns about climate change are increasing the momentum for non-combustion renewable power (DOE 20% Wind). Similar growth is occurring in Canada, and new wind installations are also underway in Mexico and Central America. The 20% Wind Scenario outlined by the Bush Administration would require U.S. wind power capacity to grow from 11.6 GW in 2006 to more than 300 GW over the next 23 years. The best wind resources are often far from the load and population centers where the energy will be used, and will therefore require new transmission capacity. In other words, new wind capacity will require expanding the U.S. transmission grid to access the best wind resource regions of the country and to relieve current congestion on the grid (Figure 2). This means increasing capacity on existing lines, and adding new lines to deliver wind power to electricity consumers. Siting within one State can be a difficult challenge. Concerns about land use impacts, property values, technical considerations, environmental impacts, jurisdiction, and the appropriate allocation of costs and benefits can delay or derail a proposed project. On an interstate basis, these issues are multiplied by the number of States the line traverses. Regional Transmission Organizations (RTOs) operating in many parts of the country plan and operate the regional energy system and recommend and implement transmission solutions that ensure a reliable supply of electricity within that region and help coordinate transmission development across state lines. Most RTOs are working on transmission planning at this time. However, RTOs do not operate in all areas of the country and coordination there occurs on a state by state basis (see Appendix C). Congress has enacted provisions in the Energy Policy Act of 2005 to give the federal government overriding authority over transmission line siting decisions when state authorities fail to meet critical system needs. Some proposals in pending federal transmission expansion legislation (eg: American Clean Energy and Security Act) could provide that authority. Because wildlife issues are only one of many issues a transmission developer must address, collaboration early in planning is important. By engaging when potential transmission projects are being planned and developed, wildlife agencies can influence the outcome before a siting application is filed. By the time a company has prepared a siting application, they have identified a specific route for the line and may have invested millions of dollars, in investigating that route. If a state can influence the company in the early stages of development, it is more likely to have an impact on their decision making; and would help avoid formal intervention and litigation. Electric transmission planning and development is a complex process and can potentially have tremendous impact on fish and wildlife resources. The Association of Fish and Wildlife Agencies realizes the need for wildlife agencies to engage in transmission planning and has developed this document to aid in that effort. The document attempts to provide some general guidance to state fish and wildlife agencies on how to engage in transmission planning and review, and also provides an overview of the processes and players behind developing transmission (see Appendices). March 11 5 Energy and Wildlife Policy Committee – Wind and Transmission Subcommittee Transmission Guidance for State Fish and Wildlife Agencies Figure 1: Existing Power Capacity (source: AWEA, 12/2009) Figure 2: Wind Power Classification including Transmission Lines (Source NREL) 6 Energy and Wildlife Policy Committee – Wind and Transmission Subcommittee Transmission Guidance for State Fish and Wildlife Agencies March 11 How can a State Natural Resource Agency Engage in Transmission Planning and Siting? PLANNING AND PROJECT REVIEW In most jurisdictions, there will be an agency with primary responsibility for either advising the developer, or deciding whether the project is acceptable, based on any of several standards of review. These may be economic (most utilities commissions), engineering (Public Utilities Commission (PUC) or siting board), environmental (Natural Resources, Environmental Quality and general public welfare), or a combined agency that has environmental functions plus resource management. If it is not the wildlife agency itself, then the wildlife agency will have to interact with the review agency in ways that best integrate wildlife and habitat concerns into the decision process. The following describes the basic steps and strategies to engage with an entity reviewing and approving transmission development. 1) Determine which agency has regulatory authority over transmission lines, and the type of permit or certificate to build that it issues. This is usually the PUC but may be another body, like a siting board (eg: the California Energy Commission regulates siting but not utility rates, a traditional PUC function). Most PUCs attempt to avoid, minimize or mitigate impacts to wildlife. Some PUCs have a staff and data base to analyze natural resources information and others need the expertise of the wildlife agency to assess impacts. a. Many utility commissions or siting boards operate under a state law or code, such as the Public Utility Regulatory Act, under the Utility Code. 2) Determine if your agency’s authority or responsibility affects the application or review process. a. If the regulatory authority requires a permit or certificate (Certificate of Public Convenience and Necessity-Appendix D) it will outline the application process required, and whether an environmental review is conducted (i.e. whether there is a State environmental impact law). b. If the project receives any federal funding, or requires another major action (eg: a permit), it may be subject to a National Environmental Policy Act (NEPA) review. c. If the wildlife agency doesn’t have a regulatory or legal nexus to participate consider developing a formal or informal agreement to work cooperatively with the federal agency or utility regulator on environmental analyses. These generally address subject responsibilities, participating in agency processes and conflict resolution. 3) If none of these are possible the agency could make a decision to become involved in the PUC’s review process. This may be done cooperatively, or as a party with a specific interest, if the wildlife agency had found that substantial wildlife interests may be affected by the PUC’s decision. Important objectives are to ensure that no state or federal environmental or wildlife laws will be violated as a result of the permit issuance, and to minimize the impacts to habitats and fish and wildlife resources in the state. March 11 7 Energy and Wildlife Policy Committee – Wind and Transmission Subcommittee Transmission Guidance for State Fish and Wildlife Agencies Strategies to engage with the Regulatory Authority 1. Identify and get on the mailing list of any RTO and ISO operating within the State, as well as in-state transmission utilities and develop relationships with their environmental and planning staff (see Appendix C for more information on RTOs). 2. Establish regular contact with your state’s utilities regulator and establish communications with their transmission review and environmental staff. Learn their processes, priorities and information requirements. 3. Identify larger scale transmission planning efforts and organizations in progress in your region, or beyond to monitor their planning and review their plan (E.g.: Upper Midwest Transmission Development Initiative). 4. Multi-entity transmission planning groups organized under regional energy coordinating bodies (eg: Western Electric Coordinating Council (WECC)) or equivalent, hold planning meetings that are usually open to the public. Find out which, if any, are operating in your region and what their scope of activities is. Determine whether they apply environmental screening in their reviews and planning, what criteria they use to support decision, and whether there are opportunities to advocate for environmental screening processes and criteria in their process. INTERNAL WILDLIFE AGENCY CONSIDERATIONS A specific program within the wildlife agency may review development projects under NEPA, a state equivalent, or a state regulatory process. This program may or may not be routinely reviewing electric transmission line projects1. Therefore, initiating a review of this type of project may require discussion with the review program and/or the agency’s legal counsel. Other wildlife agencies have responsibility for management of fish and wildlife resources, but little authority over outside activities. However, even with limited authority, the wildlife agency’s resource management responsibility should qualify it to review and comment on the electric utility transmission lines, related facilities, and their impacts on the fish and wildlife resources and their habitats. If the wildlife agency decides to take on the review of these projects, several issues should be considered including: 1) increased workload, 2) increased exposure of staff to scrutiny regarding the basis for their comments, and 3) increased chance of being called as an expert witness if the transmission lines are contested. If the agency decides to become involved, legal staff should be ready to support any technical staff called upon as an expert witness, or if they are called before a legislative oversight body like a wildlife and natural resources committee. Wildlife agencies may want to develop tools to assist in reviewing and commenting, and an internal protocol specifying how these projects and review comments are handled (Sample protocol in Appendix A). The tools could include: 1) Standardized or project-specific recommendations (e.g., BMPs) to provide when commenting on transmission line projects (see Appendix B for example). For example, the Office of Energy in the Wisconsin DNR is assigned review of utility projects and liaison with other agencies involved in the industry, including the PSC of Wisconsin and the FERC. 1 8 Energy and Wildlife Policy Committee – Wind and Transmission Subcommittee Transmission Guidance for State Fish and Wildlife Agencies March 11 2) Pre-screened development corridors where transmission lines, pipelines, etc. could be routed to avoid sensitive species and habitats, natural areas, etc. Maps that delineate areas of concern or that identify sensitive or important habitats could be provided to the regulatory authority, utilities, and other developers. Maps can assist utilities in making their route selections environmentally sensitive at the earliest possible stage of development. Ideally this consultation will assist the developers in selecting more environmentally-sensitive projects, and expedite their process by giving an early indication of routes or segments that may require additional reviews from other state or federal agencies (due to listed species, their habitat, or wetlands, etc.) and should probably be avoided by the project. The appendices to this report provide more detail on how to focus reviews and input to utility decision making processes to be more effective. March 11 9 Energy and Wildlife Policy Committee – Wind and Transmission Subcommittee Transmission Guidance for State Fish and Wildlife Agencies References Federal Energy Regulatory Commission. Updated: January 11, 2010. accessed January 2010. http://www.ferc.gov/ Holland and Hart LPP. August 2009. Transmission Siting in the Western United States: Overview and Recommendations Prepared as Information for the Western Interstate Energy Board. 75 pp. www.nrel.gov/docs/fy08osti/41869.pdf ISO/RTO Council (IRC). 2009. accessed January 2010. http://www.isorto.org National Association of Regulatory Utility Commissioners. 2007. accessed January 2010. http://www.naruc.org/ North American Electric Reliability Corporation. 2010. accessed January 2010. http://www.nerc.com/ U.S. Department of Energy; July 2008, 20% Wind Energy by 2030. March 11 References 11 Energy and Wildlife Policy Committee – Wind and Transmission Subcommittee Transmission Guidance for State Fish and Wildlife Agencies Appendix A- Technical Guidance __________ Wildlife Agency Procedures for Providing Technical Guidance and Recommendations Concerning Energy Projects on Private Lands Purpose This memorandum establishes the procedures to be followed by (agency name) staff when responding to a request for technical guidance, information or recommendations concerning proposed energy development projects on private lands, including but not limited to electric transmission lines, pipelines, and power plants (projects). Background ________ is the state agency with primary responsibility for protecting the state’s wildlife resources, and has statutory authority to provide relevant information and project-specific recommendations for the protection of wildlife resources. See (statutory authority). Information and recommendations are currently provided to governmental bodies, such as the Public Utility Commission (PUC) and the Department of Transportation (DOT) that approve, permit, license, or construct projects (regulatory authority). Private landowners affected by proposed projects also request technical guidance from this agency, often seeking an evaluation of the impacts that proposed projects will have on their property. Information collected by _____ while providing technical guidance to private landowners is confidential by law and cannot be released without written landowner consent. See (confidentiality statute). It is likely these requests from private landowners will increase as the development of wind energy, other renewable sources, and other energy-related natural resources in (state) continues. The agency’s role in evaluating proposed projects is to identify the wildlife resources that may be impacted and provide information, recommendations and comments for the protection and management of these wildlife resources. The agency does not represent or advocate for private landowners, or developers before governmental bodies that approve, permit, license, or construct projects. The agency may, however, make recommendations to governmental bodies to protect the state’s wildlife resources. Procedures 1) ___________(responsible unit) staff shall have primary responsibility for providing information and recommendations to governmental bodies, most commonly the PUC, or DOT, upon request or as directed by the (responsible official (RO)). 2) The RO will have primary responsibility for providing technical guidance to landowners regarding projects that may impact private lands. The (unit) staff shall coordinate with the March 11 Appendix A 13 Energy and Wildlife Policy Committee – Wind and Transmission Subcommittee Transmission Guidance for State Fish and Wildlife Agencies appropriate Regional Director. If the property is currently covered by a (agency) wildlife management plan, the RO will ensure that the technical guidance recommendations related to the project are consistent with the landowner’s goals for the property. 3) If field staff is contacted by a governmental body, private landowner, or developer regarding a project that may impact private land, field staff shall collect contact information from the requestor and notify the RO staff responsible for that county per the attached map or the RO director. Private landowners should also be informed that (agency name) has a formal process for evaluating projects that may impact private lands. (See Attachment ___) if the formal process is in written form 4) Except as provided in this paragraph, correspondence to a governmental body regarding a project shall only come from RO staff, the RO, or a staff attorney. Recommendations made to the agency in connection with a water right or water quality permit matter will come from, or be coordinated with the fisheries and water quality management programs. 5) Landowners must be informed that technical guidance cannot be provided to private landowners unless the landowner signs an agreement with the agency, and that information collected by the agency while providing technical guidance on private lands is confidential by law and cannot be used to provide information or recommendations to any regulatory body unless the landowner consents to the release of the information. 6) All site visits regarding a project shall be coordinated by the local District Leader and RO staff. A narrative of what is observed during site visits should be provided to RO staff. 7) In response to a landowner request for technical guidance regarding a project, (agency name) will provide a letter to the landowner with (agency name) recommendations for the protection and management of the wildlife and habitat resources affected by the proposed project (and any relevant guidelines or procedures). The wildlife agency may send its own letter to the reviewing agency providing its analysis and recommendations for avoiding, minimizing or mitigating any adverse impacts of the project. 8) Staff may not agree to serve or appear as an expert witness or otherwise testify on behalf of any party, except for (agency name), in connection with a permit, license, or construction project. If staff receives a subpoena to produce documents or provide testimony regarding a project, they should contact the Legal Counsel immediately. The Legal Counsel will provide support for the person testifying. 9) Landowners who wish to contest the location of electric transmission facilities on their property should contact the Public Utility Commission or a private attorney. 14 Energy and Wildlife Policy Committee – Wind and Transmission Subcommittee Transmission Guidance for State Fish and Wildlife Agencies March 11 Appendix A Appendix B – Wildlife Recommendations Recommendations for Electrical Transmission/Distribution Line Design and Construction Construction of the line should be designed and implemented to avoid or minimize adverse impacts to the environment and the local wildlife populations and to restore or enhance environmental quality to the greatest extent practical. In order to minimize the possible project effects upon wildlife, the following measures are recommended. THE AGENCY recommends that each power utility develop an Avian Protection Plan to minimize the risks to avian species that are protected by the Migratory Bird Treaty Act, as well as bat species, and other species protected by the Endangered Species Act, and State Conservation Statutes. Avian Electrocution Risks Birds can be electrocuted by simultaneously contacting energized and/or grounded structures, conductors, hardware, or equipment. Electrocutions may occur because of a combination of biological factors and electrical design. Biological factors are those that influence avian use of poles, such as habitat, prey and species behaviors. The electrical design factor that is most crucial to avian electrocutions is the physical separation between energized and/or grounded structures, conductors, hardware, or equipment that can be bridges by birds to complete a circuit. As a general rule, electrocution can occur on structures with the following: Phase conductors separated by less than the wrist-to-wrist or head-to-foot (flesh-to-flesh) distance of a bird; Distance between grounded hardware (e.g. grounded wires, metal braces) and any energized phase conductor that is less than the wrist-to-wrist or head-to-foot (flesh-toflesh) distance of a bird (Avian Power Line Interaction Committee 2006). To protect raptors and eagles, procedures should be followed as outlined in: Suggested Practices for Raptor Protection on Power Lines: The State of the Art in 2006. by Avian Power Line Interaction Committee (APLIC). 2006. Distributed by the Avian Power Line Interaction Committee (APLIC). Mitigating Bird Collisions with Power Lines: the State of the Art in 1994. Avian Power Line Interaction Committee (APLIC). 1994. Edison Electric Institute. Washington D.C. The APP Guidelines are intended to serve as a “tool box” from which a utility can select and tailor components applicable to its specific needs. These guidelines are intended to be used in conjunction with APLIC’s Suggested Practices for Raptor Protection on Power Lines: The State March 11 Appendix B 15 Energy and Wildlife Policy Committee – Wind and Transmission Subcommittee Transmission Guidance for State Fish and Wildlife Agencies of the Art in 1996 and Mitigating Bird Collisions with Power Lines: The State of the Art in 1994, or the most current editions of these documents, which contain more detail on construction design standards and line siting recommendations. This is a dynamic document and will be periodically updated as new information and resources become available. Additional copies of the APP Guidelines and current information on related issues can be downloaded. See: http://www.eei.org/ourissues/TheEnvironment/Land/Documents/AvianProtectionPlanGuidelines. pdf Line alterations to prevent bird electrocutions should not necessarily be delayed until after such events occur, as all electrocutions may not be known or documented. Rather, preventative measures should be routinely installed along portions of the routes that are most heavily used by birds (as indicated by frequent sightings) before any electrocutions occur. Preventative measures include: phase covers, bushing cover, arrester covers, cutout covers, jumper wire hoses, and covered conductors. In addition, perch discouragers (guards) may be used to deter birds from landing on hazardous (to birds) pole locations where isolaters, covers, or other insulating techniques cannot be used (Avian Power Line Interaction Committee 2006). When possible, use wood or non-conducting cross arms, for distribution lines, to minimize the possibility of electrical contact with perching birds. When possible, for distribution lines, install electrical equipment on the bottom cross arm to leave top cross arm free for perching. Recommend using nest management strategies such as installing nesting platforms on or near power structures which can provide nesting sites for protected species while minimizing the risks of electrocution, equipment damage, or outages (Avian Power Line Interaction Committee 2006). Avian Collision Risks Birds typically establish flight corridors along and within river and creek drainages and other directing features. Transmission lines that cross or are located very near these features should have line markers or bird flight diverters installed at the crossings or closest points to the feature to reduce the potential for collisions by birds flying along or near them. Transmission lines should be located to avoid passing through areas with tall trees, and if no alternative exists, they should be distinctly above or below the height of the trees to reduce collision risks, as well as habitat fragmentation. Transmission lines should be located to avoid separating areas regularly used by the same species, including feeding, resting, courting and nesting areas. If this cannot be avoided, lines should be clearly marked to minimize avian collisions with the lines (Avian Power Line Interaction Committee 1994). When practical, transmission lines should be buried to reduce the risks of avian collisions. 16 Energy and Wildlife Policy Committee – Wind and Transmission Subcommittee Transmission Guidance for State Fish and Wildlife Agencies March 11 Appendix B Habitat Impacts Construction activities should avoid identified wetland areas to the maximum extent possible. Early coordination with appropriate agencies should be accomplished to ensure regulatory compliance. Construction should occur during dry periods, or periods with the least wildlife use, when possible. Construction should attempt to minimize the area of habitat and numbers of flora and fauna disturbed. Reclamation of construction sites to non-human-dominated uses should emphasize replanting with native species appropriate to the pre-project habitat type. Existing rights-of-way should be used to upgrade or add facilities, where possible, in order to avoid additional clearing and prevent adverse impacts associated with habitat loss and fragmentation of existing blocks of wooded habitat. Forest and woody areas provide food and cover for wildlife, and these cover types should be preserved to the maximum extent possible. Mature trees, particularly those which produce mast, should be retained. Shrubs and trees should be trimmed rather than cleared whenever possible. Development and implementation of wildlife management plans along rights-of-way should be considered whenever feasible. Transmission lines should be designed to cross streams at right angles, at points of narrowest width, and/or at the lowest banks whenever feasible to minimize disturbance to stream corridor habitat. Pole designs should favor single circuit (without arms), where possible, to reduce impacts to the aesthetics of the area. Double circuits may be considered to prevent additional clearing to install new lines. Whenever possible, corridor sharing with other linear features should be considered. March 11 Appendix B 17 Energy and Wildlife Policy Committee – Wind and Transmission Subcommittee Transmission Guidance for State Fish and Wildlife Agencies Appendix C – Transmission Industry Overview The regulatory authorities for siting new electric transmission facilities vary from state to state. Some states have a centralized siting authority that has jurisdiction over a proposed project regardless of whether the developer is a regulated public utility, a municipality, or an independent operator. Others have regulatory authority that is fragmented, depending on whether the proponent of a project is subject to state regulatory commission jurisdiction. Some states require the siting authority to consider regional needs for transmission development in connection with a proposal, while others only require that state and local interests be considered. Some state siting authorities not only preempt but actually make decisions for the local governments affected by a proposed project, while other states provide the siting authority or another entity a mechanism to override unduly restrictive local government requirements (Holland and Hart LPP 2009). General Overview Interconnection Queues – Before new electric facilities can be sited, the transmission system operator generally must perform a system interconnection study that is a technical study to determine if the project can be integrated into the electric system reliably and if so, what, if any, system upgrades are required. This does not look at feasibility of siting or whether there is a need for the project. Every ISO/RTO maintains an “Interconnection Queue” ( www.isorto.org). Transmission Planning – Every ISO/RTO has an umbrella planning process that plans for bulk system (230 kV and above) upgrades. Also entities such as the Western Electric Coordinating Council (WECC) also have a planning function (www.wecc.biz). FERC is currently implementing transmission planning transparency at lower levels of the system Transmission Siting – Most states have centralized siting processes for generation and transmission siting. Generally, the Utility Commission is the siting authority or the lead agency. Some states use an energy facilities siting board that includes members from the utility commission, DNR and other critical authorities. – Others depend on local permitting process March 11 Appendix C 19 Energy and Wildlife Policy Committee – Wind and Transmission Subcommittee Transmission Guidance for State Fish and Wildlife Agencies Figure 3 – Overview of Transmission Planning in the West* UTILITY LEVEL SUB-REGIONAL LEVEL PROJECT LEVEL REGIONAL (WECC) STATE LEVEL SITING & ROUTING PUBLIC MEETNGS ENVIRONMENTAL IMPACT STATEMENT PUBLIC LANDS ENERGY CORRIDORS NIETC DESIGNATIONS INPUT & MITIGATION DESIGN (5-10 YEARS/PROJECT) PLANNING & DESIGN PERMITTING & ROW ACQUISITION NATIONAL CONSTRUCTION OPERATIONS & MAINTENANCE DECOMISSIONING & RECLAMATION MONITORING & PERMIT REVISIONS (40+ YEARS) STATE & COUNTY *these timeframes may vary from state to state and region to region Key Entities in Transmission Planning and Siting Regional Transmission Organizations and Independent System Operators Regional Transmission Organizations (RTOs) have been created that operate regional energy markets in many parts of the country and recommend transmission solutions that ensure a reliable supply of electricity within that region. They are independent, unbiased transmission operators charged to ensure equal access to the power grid for new, non-utility competitors. Today, there are 10 Independent System Operators and Regional Transmission Organizations (ISO/RTOs) in North America. They are the organizations that are established to control and manage the transportation and flows of electricity over an area that is generally larger than the typical power company’s distribution system (see Figure 4). ISOs and RTOs typically perform the same functions; usually ISOs operate within a single State. Regional State committees have been established within a few of these RTOs to discuss, many other issues, including interstate coordination and communication 20 Energy and Wildlife Policy Committee – Wind and Transmission Subcommittee Transmission Guidance for State Fish and Wildlife Agencies March 11 Appendix C relating to transmission within a region. These include the Organization of Midwest Independent Transmission System Operator, Inc. (Midwest ISO/MISO) States, Organization of PJM States, Inc. (OPSI), and Southern Power Pool Regional State Committee (SPP RSC). A handful of statutes provide explicit direction for commission interactions with an RTO. RTOs provide many electric utility stakeholders, including utilities and their customers, a means of developing and operating unified, coordinated power systems The ISO/RTO Council (IRC) is an industry organization consisting of representatives of North American ISO/RTOs. The IRC works collaboratively to develop effective processes, tools, and standard methods for improving competitive electricity markets across North America. The IRC’s goal is to balance reliability considerations with market practices, resulting in efficient, robust markets that provide competitive and reliable service to electricity users. Figure 4. RTO Map North American Electric Reliability Corporation The North American Electric Reliability Corporation’s (NERC) (http://www.nerc.com/) mission is to “improve the reliability and security of the bulk power system in North America. To achieve that, NERC develops and enforces reliability standards; monitors the bulk power system; assesses future adequacy; audits owners, operators, and users for preparedness; and educates and trains industry personnel. NERC is a self-regulatory organization that relies on the diverse and collective expertise of industry participants. Compliance with NERC’s regional reliability standards is mandatory and enforceable. NERC works with regional affiliates. Eight Regional Reliability Councils work to advance NERC’s goal of improving the reliability of the bulk power system. Members of these councils include March 11 Appendix C 21 Energy and Wildlife Policy Committee – Wind and Transmission Subcommittee Transmission Guidance for State Fish and Wildlife Agencies investor-owned utilities, federal power agencies, rural electric cooperatives, State, municipal and provincial utilities, independent power producers, power marketers, and end-use customers. The following are the names of the councils throughout the country: Florida Reliability Coordinating Council (FRCC) Midwest Reliability Organization (MRO) Northeast Power Coordinating Council (NPCC) Reliability First Corporation (RFC) SERC Reliability Corporation (SERC) Southwest Power Pool, RE (SPP) Texas Regional Entity (TRE) Western Electricity Coordinating Council (WECC) Figure 5. North American Electric Reliability Corporation National Association of Regulatory Utility Commissioners’ The National Association of Regulatory Utility Commissioners’ (NARUC) (http://www.naruc.org/) affiliate groups are yet another set of organizations in the regional transmission discussion. Founded in 1889, the National Association of Regulatory Utility Commissioners (NARUC) is a non-profit organization dedicated to representing the State public service commissions who regulate the utilities that provide essential services such as energy, telecommunications, water, and transportation (NARUC Website). The 5 regulatory affiliates in the U.S. include: • Mid-America Regulatory Conference (MARC) • Mid-Atlantic Conference of Regulatory Utility Commissioners (MACRUC) • New England Conference of Regulatory Utility Commissioners (NECPUC) • Southeastern Association of Regulatory Utility Commissioners (SEARUC) 22 Energy and Wildlife Policy Committee – Wind and Transmission Subcommittee Transmission Guidance for State Fish and Wildlife Agencies March 11 Appendix C • Western Conference of Public Service Commissioners (WCPSC) Today, every State in the nation belongs to one of these affiliate groups, which meet regularly, although without a formal interest in interstate transmission siting. None of the affiliates have any regulatory authority to compel States to comply with their decisions. Federal Energy Regulatory Commission The Federal Energy Regulatory Commission, or FERC, (www.ferc.gov) is an independent agency that regulates the interstate transmission of electricity, natural gas, and oil. FERC also reviews proposals to build liquefied natural gas (LNG) terminals and interstate natural gas pipelines as well as licensing hydropower projects (FERC website). Normally, FERC works with the state utility regulators which have internal regulatory authority, and state wildlife agencies may also participate in FERC reviews in different capacities, depending on their level of interest in the projects. Interstate Compacts Interstate compacts enable States to act jointly and collectively, generally outside the confines of the federal legislative or regulatory process while respecting the view of Congress on the appropriateness of joint action. Unlike federal actions that impose unilateral, rigid mandates, compacts afford States the opportunity to develop dynamic, self regulatory systems over which States can maintain control through a coordinated legislative and administrative process. Interstate compacts enable the States to develop adaptive structures that can evolve to meet new and increased challenges which naturally arise over time. For example, Idaho, Montana, Oregon, and Washington entered into an interstate compact as a means of coordinating the usage of key resources common to all four. Authorized by the Northwest Power Act of 1980, and approved by a vote in the four State legislatures, the States established the Northwest Power and Conservation Council. One of the Council’s responsibilities is to maintain a regional power plan to balance the Northwest’s energy and environment needs . March 11 Appendix C 23 Energy and Wildlife Policy Committee – Wind and Transmission Subcommittee Transmission Guidance for State Fish and Wildlife Agencies Appendix D – Application For A Certificate of Convenience and Necessity (Example from Texas) DOCKET NO._____________ Submit seven (7) copies of the application and all attachments including all direct testimony supporting the application to: Public Utility Commission of Texas Attn: Filing Clerk 1701 N. Congress Ave. Austin, Texas 78711-3326 Note: As used herein, the term “joint application” refers to an application for proposed transmission facilities for which ownership will be divided. All applications for such facilities should be filed jointly by the proposed owners of the facilities. 1. Applicant (Utility) Name: For joint applications, provide all information for each applicant. Certificate Number: Street Address: Mailing Address: 2. Please identify all entities that will hold an ownership interest or an investment interest in the proposed project but which are not subject to the Commission’s jurisdiction. 3. Person to Contact: For joint applications, provide all information for each applicant. Title/Position: Phone Number: Mailing Address: Email Address: Alternate Contact: Title/Position: Phone Number: Mailing Address: Email Address: March 11 Appendix D 25 Energy and Wildlife Policy Committee – Wind and Transmission Subcommittee Transmission Guidance for State Fish and Wildlife Agencies Legal Counsel: Phone Number: Mailing Address: Email Address: 4. Project Name or Designation of Project Description: Provide a general description of the project, including the design voltage rating (kV), the operating voltage (kV), the CREZ Zone(s) (if any) where the project is located (all or in part), any substations and/or substation reactive compensation constructed as part of the project, and any series elements such as sectionalizing switching devices, series line compensation, etc. For HVDC transmission lines, the converter stations should be considered to be project components and should be addressed in the project description. If the project will be owned by more than one party, briefly explain the ownership arrangements between the parties and provide a description of the portion(s) that will be owned by each party. Provide a description of the responsibilities of each party for implementing the project (design, Right-Of-Way acquisition, material procurement, construction, etc.). Identify and explain any deviation in transmission project components from the original transmission specifications in ERCOT’s CREZ Transmission Optimization (CTO) Study. 5. Conductor and Structures: Conductor Size and Type Number of conductors per phase Continuous Summer Static Current Rating (A) Continuous Summer Static Line Capacity at Operating Voltage (MVA) Continuous Summer Static Line Capacity at Design Voltage (MVA) Type and composition of Structures Height of Typical Structures Explain why these structures were selected; include such factors as landowner preference, engineering considerations, and costs comparisons to alternate structures that were considered. Provide dimensional drawings of the typical structures to be used in the project. For joint applications, provide and separately identify the above-required information regarding structures for the portion(s) of the project owned by each applicant. 6. Right-of-way: Miles of Right-of-Way Miles of Circuit Width of Right-of-Way Percent of Right-of-Way Acquired 26 Energy and Wildlife Policy Committee – Wind and Transmission Subcommittee Transmission Guidance for State Fish and Wildlife Agencies March 11 Appendix D For joint applications, provide and separately identify the above-required information for each proposed alternative route (including the preferred route) for the portion(s) of the project owned by each applicant. Provide a brief description of the area traversed by the proposed transmission line. Include a description of the general land uses in the area and the type of terrain crossed by the proposed line. 7. Substations or Switching Stations: List the name of all existing HVDC converter stations, substations or switching stations that will be associated with the proposed new transmission line. Provide documentation showing that the owner(s) of the existing HVDC converter stations, substations and/or switching stations have agreed to the installation of the required project facilities. List the name of all new HVDC converter stations, substations or switching stations that will be associated with the proposed new transmission line. Provide documentation showing that the owner(s) of the new HVDC converter stations, substations and/or switching stations have agreed to the installation of the required project facilities. 8. Estimated Schedule: Estimated Dates of: Start Completion Right-of-way and Land Acquisition Engineering and Design Material and Equipment Procurement Construction of Facilities Energize Facilities 9. Counties: For each proposed alternative route (including the preferred route) list all counties in which the route is proposed to be constructed. 10. Municipalities: For each proposed alternative route (including the preferred route) list all municipalities in which the route is proposed to be constructed. For each applicant, attach a copy of the franchise, permit or other evidence of the city's consent held by the utility. If franchise, permit, or other evidence of the city's consent March 11 Appendix D 27 Energy and Wildlife Policy Committee – Wind and Transmission Subcommittee Transmission Guidance for State Fish and Wildlife Agencies has been previously filed, provide only the docket number of the application in which the consent was filed. Each applicant should provide this information only for the portion(s) of the proposed project which will be owned by the applicant. 11. Affected Utilities: Identify any other electric utility served by or connected to facilities proposed in this application. Describe how any other electric utility will be affected and the extent of the other utilities' involvement in the construction of this project. Include any other utilities whose existing facilities will be utilized for the project (vacant circuit positions, ROW, substation sites and/or equipment, etc.) and provide documentation showing that the owner(s) of the existing facilities have agreed to the installation of the required project facilities. 12. Financing: Describe the method of financing this project. For each applicant that is to be reimbursed for all or a portion of this project, identify the source and amount of the reimbursement (actual amount if known, estimated amount otherwise) and the portion(s) of the project for which the reimbursement will be made. 13. Estimated Costs: Provide cost estimates for the proposed project in the following table for the preferred route and for each alternative route presented in this application. Provide a breakdown of “Other” costs by major cost category and amount. Transmission Substation Facilities Facilities Right-of-way and Land Acquisition Engineering and Design (Utility) Engineering and Design (Contract) Procurement of Material and Equipment (including stores) Construction of Facilities (Utility) 28 Energy and Wildlife Policy Committee – Wind and Transmission Subcommittee Transmission Guidance for State Fish and Wildlife Agencies March 11 Appendix D Construction of Facilities (Contract) Other (all costs not included in the above categories) Estimated Total Cost For joint applications, provide and separately identify the above-required information for the portion(s) of the project owned by each applicant. 14. Need for the Proposed Project: Provide a specific reference to the pertinent portion(s) of an appropriate commission CREZ order specifying that the facilities are needed. 15. Routing Study: Provide a brief summary of the routing study that includes a description of the process of selecting the study area, identifying routing constraints, selecting potential line segments, and the selection of the preferred and alternate routes. Provide a copy of the complete routing study conducted by the utility or consultant. 16. Public Meeting or Public Open House: Provide the date and location for each public meeting or public open house that was held in accordance with P.U.C. PROC. R. 22.52. Provide a summary of each public meeting or public open house including the approximate number of attendants, and a copy of any survey provided to attendants and a summary of the responses received. For each public meeting or public open house provide a description of the method of notice, a copy of any notices, and the number of notices that were mailed and/or published. 17. Routing Maps: Base maps should be a full scale (one inch = not more than one mile ) highway map of the county or counties involved, or other maps of comparable scale denoting sufficient cultural and natural features to permit location of all proposed alternative routes (including the preferred route) in the field. Provide a map (or maps) showing the study March 11 Appendix D 29 Energy and Wildlife Policy Committee – Wind and Transmission Subcommittee Transmission Guidance for State Fish and Wildlife Agencies area, routing constraints, and all routes or line segments that were considered prior to the selection of the preferred and alternate routes. Identify the preferred and alternate routes and any existing facilities to be interconnected or coordinated with the proposed project. Identify any taps, ties, meter points, or other facilities involving other utilities on the routing map. Show all existing transmission facilities located in the study area. Include the locations of radio transmitters and other electronic installations, airstrips, irrigated pasture or cropland, parks and recreational areas, historical and archeological sites, and any environmentally sensitive areas. Provide aerial photographs of the study area displaying the date that the photographs were taken or maps that show (1) the location of each proposed alternative route (including the preferred route) with each route segment identified, (2) the locations of all major public roads including, as a minimum, all federal and state roadways, (3) the locations of all known habitable structures or groups of habitable structures (see Question 18 below) on properties directly affected by any route, and (4) the boundaries (approximate or estimated according to best available information if required) of all properties directly affected by any route . For each proposed alternative route (including the preferred route), cross-reference each habitable structure (or group of habitable structures) and directly affected property identified on the maps or photographs with a list of corresponding landowner names and addresses and indicate which route segment affects each structure/group or property. 18. Permits: List any and all permits and/or approvals required by other governmental agencies for the construction of the proposed project. Indicate whether each permit has been obtained. 19. Habitable structures: For each proposed alternative route (including the preferred route) list all single-family and multi-family dwellings and related structures, mobile homes, apartment buildings, commercial structures, industrial structures, business structures, churches, hospitals, nursing homes, schools, or other structures normally inhabited by humans or intended to be inhabited by humans on a daily or regular basis within 300 feet of the centerline if the proposed project will be constructed for operation at 230kV or less, or within 500 feet of 30 Energy and Wildlife Policy Committee – Wind and Transmission Subcommittee Transmission Guidance for State Fish and Wildlife Agencies March 11 Appendix D the centerline if the proposed project will be constructed for operation at greater than 230kV. Provide a general description of each habitable structure and its distance from the centerline of the alternative route. In cities, towns or rural subdivisions, houses can be identified in groups. Provide the number of habitable structures in each group and list the distance from the centerline of the alternative route to the closest and the farthest habitable structure in the group. Locate all listed habitable structures or groups of structures on the routing map. 20. Electronic Installations: For each proposed alternative route (including the preferred route), list all commercial AM radio transmitters located within 10,000 feet of the center line of the alternative route, and all FM radio transmitters, microwave relay stations, or other similar electronic installations located within 2,000 of the center line of the alternative route. Provide a general description of each installation and its distance from the center line of the alternative route. Locate all listed installations on a routing map. 21. Airstrips: For each proposed alternative route (including the preferred route), list all known private airstrips within 10,000 feet of the center line of the project. List all airports registered with the Federal Aviation Administration (FAA) with at least one runway more than 3,200 feet in length that are located within 20,000 feet of the center line of any alternative route. For each such airport, indicate whether any transmission structures will exceed a 100:1 horizontal slope (one foot in height for each 100 feet in distance) from the closest point of the closest runway. List all listed airports registered with the FAA having no runway more than 3,200 feet in length that are located within 10,000 feet of the center line of any alternative route. For each such airport, indicate whether any transmission structures will exceed a 50:1 horizontal slope from the closest point of the closest runway. List all heliports located within 5,000 feet of the center line of any alternative route. For each such heliport, indicate whether any transmission structures will exceed a 25:1 horizontal slope from the closest point of the closest landing and takeoff area of the heliport. Provide a general description of each listed private airstrip, registered airport, and heliport; and state the distance of each from the center line of each alternative route March 11 Appendix D 31 Energy and Wildlife Policy Committee – Wind and Transmission Subcommittee Transmission Guidance for State Fish and Wildlife Agencies (including the preferred route). Locate and identify all listed airstrips, airports, and heliports on a routing map. 22. Irrigation Systems: For each proposed alternative route (including the preferred route) identify any pasture or cropland irrigated by traveling irrigation systems (rolling or pivot type) that will be traversed by the alternative route. Provide a description of the irrigated land and state how it will be affected by each alternative route (number and type of structures etc.). Locate any such irrigated pasture or cropland on a routing map. 23. Notice: Notice is to be provided in accordance with P.U.C. PROC. R. 22.52. A. Provide a copy of the written direct notice to owners of directly affected land. Attach a list of the names and addresses of the owners of directly affected land receiving notice. B. Provide a copy of the written notice to utilities that are located within five miles of the proposed transmission line. C. Provide a copy of the written notice to county and municipal authorities. D. Provide a copy of the notice that is to be published in newspapers of general circulation in the counties in which the proposed facilities are to be constructed. Attach a list of the newspapers that will publish the notice for this application. After the notice is published, provide the publisher's affidavits and tear sheets. In addition to the requirements of P.U.C. PROC. R. §22.52 the applicant shall, not less than twenty-one (21) days before the filing of the application, submit to the Commission staff a “generic” copy of each type of proposed published and written notice for review. Staff’s comments, if any, regarding the proposed notices will be provided to the applicant not later than seven days after receipt by Staff of the proposed notices, Applicant may take into consideration any comments made by Commission staff before the notices are published or sent by mail. 32 Energy and Wildlife Policy Committee – Wind and Transmission Subcommittee Transmission Guidance for State Fish and Wildlife Agencies March 11 Appendix D 24. Parks and Recreation Areas: For each proposed alternative route (including the preferred route), list all parks and recreational areas owned by a governmental body or an organized group, club, or church and located within 1,000 feet of the center line of the alternative route. Provide a general description of each area and its distance from the center line. Identify the owner of the park or recreational area (public agency, church, club, etc.). List the sources used to identify the parks and recreational areas. Locate the listed sites on a routing map. 25. Historical and Archeological Sites: For each proposed alternative route (including the preferred route), list all historical and archeological sites known to be within 1,000 feet of the center line of the alternative route. Include a description of each site and its distance from the center line. List the sources (national, state or local commission or societies) used to identify the sites. Locate all historical sites on a routing map. For the protection of the sites, archeological sites need not be shown on maps. 26. Coastal Management Program: For each proposed alternative route (including the preferred route), indicate whether the alternative route is located, either in whole or in part, within the coastal management program boundary as defined in 31 T.A.C. §503.1. If any proposed alternative route (including the preferred route) is, either in whole or in part, within the coastal management program boundary, indicate whether any part of the proposed route is seaward of the Coastal Facilities Designation Line as defined in 31 T.A.C. §19.2(a)(21). Using the designations in 31 T.A.C. §501.3(b), identify the type(s) of Coastal Natural Resource Area(s) impacted by any part of the proposed route and/or facilities. 27. Environmental Impact: Provide copies of any and all environmental impact studies and/or assessments of the proposed project. If no formal study was conducted for this project, explain how the routing and construction of this project will impact the environment. List the sources used to identify the existence or absence of sensitive environmental areas. Locate any environmentally sensitive areas on a routing map. In some instances, the location of the March 11 Appendix D 33 Energy and Wildlife Policy Committee – Wind and Transmission Subcommittee Transmission Guidance for State Fish and Wildlife Agencies environmentally sensitive areas or the location of protected or endangered species should not be included on maps to ensure preservation of the areas or species. Within seven days after filing the application for the proposed project, provide a copy of each environmental impact study and/or assessment to the Texas Parks and Wildlife Department (TPWD) for its review at the address below. Include with this application a copy of the letter of transmittal with which the studies/assessments were or will be sent to the TPWD. Provide an affidavit within nine days after filing the application confirming that the letter of transmittal and studies/assessments were sent to TPWD. Wildlife Habitat Assessment Program Wildlife Division Texas Parks and Wildlife Department 4200 Smith School Road Austin, Texas 78744 AFFIDAVIT Attach a sworn affidavit from a qualified individual authorized by the applicant to verify and affirm that, to the best of knowledge, all information provided, statements made, and matters set forth in this application and attachments are true and correct. 34 Energy and Wildlife Policy Committee – Wind and Transmission Subcommittee Transmission Guidance for State Fish and Wildlife Agencies March 11 Appendix D Appendix E - Useful Links Midwest Independent System Operator (MISO): http://www.midwestmarket.org/page/Renewable+Energy+Gateway American Wind Energy Association (AWEA) http://www.awea.org/policy/regulatory_policy/siting_policy.html Joint Coordinated System Plan (JCSP) http://www.jcspstudy.org/ Edison Electric Institute (EEI) http://www.eei.org/ourissues/ElectricityTransmission/Documents/State_Generation_Transmissio n_Siting_Directory.pdf Federal Energy Regulatory Commission (FERC) http://www.ferc.gov/industries/electric/indus-act/siting.asp Nat’l Assoc of Regulatory Util. Commissions (NARUC) 2009 presentations on transmission issues http://www.naruc.org/committees.cfm?c=17 Pennsylvania/Jersey/Maryland Interconnection http://www.pjm.com/about-pjm/newsroom/renewable-dashboard.aspx Southwest Power Pool (SPP) with links to the other RTOs’ http://www.isorto.org/site/c.jhKQIZPBImE/b.2604617/k.C42E/SPP.htm California Renewable Energy Transmission Initiative http://www.energy.ca.gov/reti/index.html Electric Reliability Council of Texas (ERCOT) http://www.ercot.com/about/index March 11 Appendix E 35 Energy and Wildlife Policy Committee – Wind and Transmission Subcommittee Transmission Guidance for State Fish and Wildlife Agencies Appendix F - Useful Abbreviations and Acronyms AWEA - American Wind Energy Association NYSERDA - New York State Energy Research and Development Authority CEC - California Energy Commission PNM - Public Service Company of New Mexico CEQA - California Environmental Quality Act DOE - U.S. Department of Energy EEI - Edison Electric Institute EERE - Office of Energy Efficiency and production tax credit PUC - Public Utility Commission RPS - Renewable Portfolio Standards RTO - Regional Transmission Organization Renewable EPRI - Electric Power Research Institute ERCOT - Electric Reliability Council of Texas SEPA - Southeastern Power Administration SERC - Southeastern Electric Reliability Council FERC - Federal Energy Regulatory Commission ISO - Independent system operator MAPP - Mid-Continent Area Power Pool SPP - Southwest Power Pool SWPA - Southwestern Power Administration WECC - Western Electricity Coordinating Council Midwest ISO - Midwest Independent System Operator WGA – Western Governors’ Association NEPA - National Environmental Policy Act NERC - North American Electric Reliability Corporation NREL - National Renewable Energy Laboratory 36 Energy and Wildlife Policy Committee – Wind and Transmission Subcommittee Transmission Guidance for State Fish and Wildlife Agencies March 11 Appendix F
© Copyright 2026 Paperzz