Due Diligence Report November 2012 MFF 0026-AFG: Energy Sector Development Investment Program – Proposed Tranche 4 Prepared by Da Afghanistan Breshna Sherkat (Afghanistan Electricity Company) for the Asian Development Bank. Annexure 13 AFG: Grid Development and Distribution Extension Project Due Deligence Report of Land Acquisition and Resettlement for Distribution Component INTRODUCTION 1. The Government of Afghanistan proposes to include as a component of Tranche 4 of the AFG Energy Sector Development Investment Program the construction of power distribution networks on the south eastern part of the country, covering Pul-e-Alam the capital city of Logar Province and Gardez the capital city of Paktia Province. Da Afghanistan Breshna Sherkat (DABS) is the executing agency (EA) and will implement this component through its existing Program Management Office (PMO), supported by a Program Management and Project Implementation Consultants (PMPIC). Approximately, 20,000 households are expected to benefit from this component. The preliminery design of medium and low voltage distribution networks is being unmdertaken by Program Management and Project Implementation conusltnat (SMEC International). The project will be dovetailed with the 220 kv transmission line and 220 kv/20 kv sub-stations construction that is being undertaken by United States Army in these provinces. SCOPE OF THE DISTRIBUTION COMPONENT 2. The towns of Pul-e-Alam (Logar province) and Gardez (Paktiya province) are currently not connected to Afghanistan’s power grid and therefore have no distribution network installed. The Component’s physical works will comprise the installation of low/medium power distribution lines and erection of an estimated 7,000 concrete/steel electric poles, spread over the whole area of the two cities of Pul-e-Alam and Gardez. Other associated infrastructure facilities include the installation of distribution transformers, low voltage (LV) panels, LV/MV cables and accessories, ACSR conductors, aerial bundle cables and accessories, assembly accessories, electronic meter and meter boxes, medium voltage (MV) switches and fuses, etc., and installation of MV & LV network and equipment. 3. Based on this preliminary design, the advanced level design and the bidding document will be prepared by project preparatory consultant, who is expected to be fielded by December 2012. Upon contract award in 2013, the Engineering Procurement and Construction (EPC) contractor will undertake detailed design include network design and precise equipment and locations of towers. The detailed engineering design will be conducted by the design build contractor and due diligence report will be further updated at that stage of project implementation. METHODOLOGY 4. In the preparation of this due diligence report on land acquisition and resettlement (LAR) aspect, it has not been possible to visit the Project area because of severe restrictions due to the security situation. As an alternative working methodology, activities have basically been limited to consultant’s previous experience from areas similar to the Project area in Afghanistan, assessment of the condition of the area via Google map, supplemented with information derived from personnel involved in the Project. Data gathering was undertaken through detailed interviews with senior management and field staff in Ministry of Energy and Water and DABS. LAND ACQUISITION AND RESETTLEMENT IMPLICATIONS 5. The distribution lines will be constructed within the existing road alignment. Acquisition of land and of other assets will be avoided for establishment of these power distribution networks. Proper engineering design, and using established roadside reserve and tracks for the poles foundation and line stringing will be done to avoid impacting on any existing private or community assets/improvements. Consultation will be undertaken with the people living or owing land/property alongside the line corridor at the design stage in order to define the most acceptable alignment. This consultation will also help finding suitable time gap for using fallow land for implementing physical works at the time between the harvest of crop and the next planting season. 6. The civil works contract will require the contractors to obtain approval of respective City/District Government before they temporarily occupy any land for the purpose of construction material storage, equipments or construction site. The contractors will also be required to negotiate and reach an agreement with the owners of such land before these are used for temporary material storage or site construction. The condition of occupancy of such land with prior agreement will be clearly specified in the civil works contract. CONCLUSIONS AND RECOMMENDATIONS 7. The initial due diligence assessment confirms that the power distribution component for the MFF AFG Energy Sector Development Investment Program – Tranche 4 will have no adverse social impacts associated with land acquisition and resettlement (LAR). However, this assessment will have to be confirmed based on the detailed design. Physical works will only be allowed to commence after confirmation of the absence of any LAR impacts at the detailed design stage. 8. In the event that LAR impacts are identified at the detailed design stage or implementation stage, a LARP will be prepared and implemented following the MFF updated Land Acquisition and Resettlement Framework (LARF) dated November 2011. LIST OF PEOPLE MET 9. Follwing people were consulted during preparation of this document: i. ii. iii. iv. v. vi. vii. Mr. Ghulam Faruq Qazizadah, Deputy Minister Energy, Ministry of Energy and Water (MEW) Mr. Abdul Razique Samadi, Chief Executive Officer, DABS Ms. Zia Gul, Head of Planning, MEW Engineer Shah Mohammad, PMO director, MEW Mr. Shekeeb Nessar, Chief Operating Officer DABS Dr. Waheedullah Popalzai, PMO Director DABS Mr. Abdullah Sajid, Head of Engineering DABS Pul-e-Alam Gardez
© Copyright 2026 Paperzz