Solar Challenger Future starts now Tim van Leeuwen & Jesper Haverkamp V6 Hermann Wesselink College Advisor: F. Hidden March 2010 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Abstract Main goal of this project was to make calculations and respective designs to create an electric airplane prototype, capable of powering its flight either entirely or partially using solar energy. This project intended to stimulate research on renewable energy sources for aviation. In future solar powered airplanes could be used for different types of aerial monitoring and unmanned flights. First, research was done to investigate properties and requirements of the plane. Then, through a number of sequential steps and with consideration of substantial formulas, the aircraft‟s design was proposed. This included a study on materials, equipment and feasibility. Finding a balance between mass, power, force, strength and costs proved to be particularly difficult. Eventually predictions showed a 50% profit due to the installation of solar cells. The aircraft‟s mass had to be 500 grams at the most, while costs were aimed to be as low as €325. After creating a list of materials and stipulating a series of successive tests, construction itself started. Above all, meeting the aircraft‟s target mass, as well as constructing a meticulously balanced aircraft appeared to be most difficult. Weight needed to be saved on nearly any element. We replaced the battery, rearranged solar cells and adjusted controls. Though setbacks occurred frequently, we eventually met our goals with the aircraft completed whilst weighing in at 487 grams. Testing commenced with verifying the wings‟ actual lift capacities. Results were satisfying. In addition, further testing on drag and propulsion was gratifying as well. Finally, the aircraft truly took to the skies, but sadly crashed due to flaws in steering. Testing on solar cells however, was disappointing. Instead of the expected 50 %, we only managed to achieve 10 % profit. In addition, one can pose the question if leaving out the solar cells entirely would have meant saving such considerable weight, that there would have been more profit after all. Final costs of the project were €515. Ultimately we can conclude purely solar powered flight is impossible, at least with the materials available and taking Dutch climate into account. Further developments in solar technology might create possibilities for solar planes in future. For now, in order to install solar cells, too many aspects of the plane are sacrificed to save weight. This for example resulted in a frame far too fragile. Still, it should be noted that the plane we manufactured was a prototype only. Many adjustments can be made. During the project we have seen that there is quite some room for improvement. That is obvious, as this was the very first airplane we ever build. We gathered enormous amounts of knowledge and we hope that in future this knowledge will be used to continue working on solar powered planes. For if development continues, solar powered aircraft might truly be used in future. Bear in mind: Future starts now. 2 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Introduction As we both enjoy aviation and are considering a study involving the aircraft industry, it had soon become clear we wanted to do our research project about a topic related to flying. Though aviation is a complex part of technology, we thought our expertise on physics and our passion for flying would guide us through this project. Our first concern was finding a topic both interesting, challenging and future-proof. Due to current turbulence in aviation we decided on the following: The desire to fly is nearly as old as humanity itself. Ever since we walked the earth, we longed to get airborne, just like the birds above us did. In 1783 this dream became reality 1 . “Historians credit France's Montgolfier brothers with the first pioneering balloon flight ” 2 . Aviation‟s next revolution was in 1903, when Orville and Wilbur Wright took off with their „Flyer 1‟ and flew 36 metres with their plane 3 . Flyer 1 was powered by a petrol engine, just like later aircraft. Nowadays, aviation accounts for three percent of all CO 2 -emissions produced by mankind 4 . This doesn‟t seem much, but more important is that profit of commercial aviation strongly relies on the oil price. Due to high prices 5 of crude oil lately, profits of commercial aviation have been diminished and aviation industry is now looking for alternative energy sources to propel modern-day aircraft. Options that are being considered are bio fuels, hydrogen and ethanol6 . An option which is rarely considered is solar energy, an option we wanted to investigate. 1 http://adventure.howstuffworks.com/first-flight-attempt.htm Robert Lamb, 2008 3 http://www.wright-brothers.org/History/Just%20the%20Facts/1903fly.ht m 4 http://www.rotterdamairport.nl/nl/generalmenu/Over_Rotterdam_Airport/In_de_samenleving/Feiten_en_cijfers 5 http://images.angelpub.com/2009/03/1606/oil-price-chart-1-12-09.png 6 http://www.faa.gov/news/conferences_events/aviation_ forecast_2007/agenda_presentation/media/9 %20Rich%20Alt man.pdf 2 3 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Table of contents Front page Page 1 Abstract Page 2 Introduction Page 3 Table of contents Page 4 Introduction phase Phases Main goal, purpose and expectations Research questions Requirements Page Page Page Page 5 6 7 8 Design phase Design proposal Construction proposal Test proposal Page 9 Page 30 Page 32 Construction phase Media attention International aspect Construction Page 35 Page 36 Page 41 Test phase Test results Page 54 Conclusion phase Conclusion Evaluation Page 60 Page 62 Additional sources Page 68 Acknowledgements Page 69 Jesper‟s log Page 70 Tim‟s log Page 73 4 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Phases In order to minimize chances of failure, we set up the following scheme. It divides up the project in five different phases, all having their own planning, goals and requirements: Phase Elements Introduction phase Determine main goal, research questions, requirements, planning. Design phase Research, orientation, plans, calculations, proposals. Construction phase Description of construction itself: what succeeded, what went wrong and in which way did we alter our designs and plans. Test phase Observations and experiences during testing and test results. Conclusion phase Interpretation of test results, conclusion, evaluation, recommendations for future projects. Goal Provide a starting point for our project. Set up a design proposal, construction proposal and test proposal. Give an accurate description of the progress of our project. Provide an accurate description of occurrences during testing. Describe what can be learned from this project, why it succeeded or not and how this project can be used later. 5 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Main goal, purpose and expectations The main goal of this project is to make calculations and respective designs to create an electric airplane prototype, capable of powering its flight either entirely or partially using solar energy. This project intends to stimulate research on renewable energy sources for aviation. Hopefully this will result in the environment no longer suffering due to emissions of burning oil products. In future solar powered airplanes could be used for different types of aerial monitoring and unmanned flights. Due to their light weight, silent engines and infinite flying time, they might also be used as spy planes in inhospitable areas. By doing broad research and making appropriate calculations, we hope to design an aircraft which is actually able to fly. Our first concern is composing the right electrical system to be used in our aircraft. Selecting suitable equipment and making useful drawings and schemes will provide us with the basis for our project. Extensive testing will show how effective our system functions in different circumstances. Once completed, our circuit will be combined with the aircraft‟s frame. If we manage to correctly set up our calculations, the aircraft should be able to fly. In case testing shows the aircraft is not able to take off, we will first investigate how we can improve the plane‟s properties. Though, when nothing seems to help anymore, we will slightly shift our main goal and try to create a controllable, energy efficient vehicle using all equipment we gathered so far. This will only be done in case all goes wrong. This project runs over an extensive period of time, which will provide us with sufficient opportunities to do research and create designs. We will make a strict planning and a precise proposal to make sure our project will run smoothly. Assuming we will be able to make accurate calculations, our expectations are that we will actually produce an aircraft capable of flying on solar power. Even though we try to plan and predict everything as well as possible, setbacks might occur. To prevent failure, we shall make sure there is enough room for unexpected events. 6 Research questions Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 From our main goal we can derive the main research question involved in our project: Is it possible to create an electric airplane prototype capable of using solar power to partly or entirely power its flight? Sub questions In order to answer our main question completely, we need to look at several sub questions: 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. Is it possible to let the aircraft fly on solar power only? How do you make sure no precious energy is spilled when the solar panels generate very little energy? How do you deal with the cells’ varying output in cloudy or sunny circumstances? Which extra equipment is needed to make the solar cells function properly? Which circuit is needed to make the plane remote controllable? Which equipment and components are needed to control the plane? What will be the plane’s size, mass, speed? Which airfoil do you use, how big is it and how does it work? How much lift do you need? Which engine and propeller do you need? Which solar cells generate most electricity with fewest mass and how big are they? How do you mount the solar cells on the aircraft (inside or outside, wing or body)? What will be the structure’s design? Which materials do you need to construct the plane? Where do you place all electrical equipment, making sure the aircraft is balanced and what will the fuselage be like? What will be the shape of the tail and elevator and how are they controlled? In which order are you going to construct the plane? Which effect does the position of the solar cells have on the efficiency of both the plane and panels? How much profit do the solar cells provide? 7 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Requirements Before writing a design proposal, a complete set of requirements is needed. In this way we know which limitations there are during construction. Not only will these requirements be a guideline throughout our project, they will provide us with a starting point as well. After all, mass, power, size and costs of an aircraft are all related. You need to fill in one first in order to determine the others. Element Available time Available materials Number of participants Final product’s size Number of products Budget Requirements At least 100 hours of which 50 are before the summer holidays, 20 after the summer holidays. Nearly everything as long as we can afford it and it‟s available in shops (on the internet) and not custom made. Plenty of tools are available. Two Notes Construction will be before and during summer holidays. Experts, teachers and other sources not included. Between 1.0 and 1.5 metres in width in order to Length and height depend not let it be too small or too big. These on mass and balance, measurements can vary slightly if needed. which will be determined later. One (prototype) No more than €400 in total as long as no sponsor has been found. Environment Outside Media attention www.solarchallenger.tk, website with our progress, sponsors, TU Delft? No rainy circumstances 8 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Design proposal When designing, there are three things to be considered. First there is the main goal, secondly there are the research questions and thirdly there are the requirements. When combined, those three elements form the basis of making a design proposal. To start out, we use the requirements and see how we can implement them in our ma in goal and research questions. The requirement we are currently most interested in, is the model aircraft‟s size. We intend to construct an aircraft with a span measuring 1.5 metres. In this way the aircraft will not be too large to handle and at the same time it will be large enough to provide us with enough room for mounting solar cells and other equipment without space becoming too crowded. We will use this very measurement as a basis throughout the design proposal. To design the plane in an organized way, we set up a plan consisting of a number of steps. These steps deal with several sub questions and will be filled in as we go: Step 1: Step 2: Step 3: Step 4: Step 5: Step 6: Step 7: Step 8: Step 9: Step 10: Designing the right basic electrical system (no sizes, properties, etc. included). Research on the size of the aircraft and probable mass. Feedback on the engine, solar cells, battery etc. Final decision on mass and thus the size of the aircraft. Designing the final electrical system including properties and components. Determining where to place the solar cells. Designing the wing and doing a final check on lift, mass, size, etc. Determining construction materials. Designing the aircraft itself, keeping mass, centre of gravity, etc. in mind. Calculating final costs Step 1 Before continuing with calculations involving the size of the aircraft, we will look at the electrical system involved. After all, our plane would be useless without properly functioning electronics. This implies we will start out with answering sub questions 1, 2, 3, 4, 5 and 6: 1. 2. 3. 4. 5. 6. Is it possible to let the aircraft fly on solar power only? How do you make sure no precious energy is spilled when the solar panels generate very little energy? How do you deal with the cells’ varying output in cloudy or sunny circumstances? Which extra equipment is needed to make the solar cells function properly? Which circuit is needed to make the plane remote controllable? Which equipment and components are needed to control the plane? To start, we will answer question 6. A properly controllable plane needs several pieces of equipment 7 . 7 http://www.mvccolu mb ia.nl/hoebeginik.htm# 07 9 The answer to question 1 was very obvious once we investigated the power consumed by an engine. A website 8 showing engine characteristics listed a considerable number of engines. All of those appeared to consume quite a lot of energy. Besides the fact that our engine needs an enormous amount of power (which will unlikely be generated by our solar cells due to Dutch climate 9 ) the engine also needs a steady energy flow. We don‟t want our aircraft to crash due to one cloud and for that reason we will use a battery combined with solar cells. Then the answer to question 2: When the solar panels are not generating lots of energy, we must prevent energy from flowing from battery to solar panels. Therefore we will install a diode between the solar panels and the battery. The diode will unfortunately consume some power, but this is the only way to get things working. In order to keep voltage loss as low as possible, we are going to use a „Schottky diode‟. This specific type of diode only uses 0.1-0.2 volts compared to a regular diode which contributes to the loss of 0.7-1.7 volts 10 . Since we found a solution to question 1, the answer to question 3 has already been given. Using a battery will not only help us keeping the plane airborne when limited energy is being delivered by the solar panels, but it will also make sure that whenever the output of the solar cells drops (for example due to a cloud passing by) the engine still receives enough power. Knowing all the information we gathered so far, we can draw a circuit basically showing the electronics inside the aircraft, which answers question 5 up to a certain extent. Since we don‟t know anything about power, mass, battery size etc. yet, we are not able to draw all details. The following scheme just provides us with a basic idea of which elements are needed to control the aircraft, thus giving us a starting point for calculating the aircraft‟s mass in future. - + - - Servo Controller Solar Cells + Battery + Receiver Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 First there are a transmitter and receiver, which are used to send and receive signals from a control panel. The receiver, located inside the plane, will send signals to elements called servos. They can move the rudder, ailerons and elevator. Besides, the receiver also controls the engine throttle. We will come back to question 6 in more details later, when we know more about the mass, size and power of the aircraft. Servo Servo M 8 http://www.rctechnics.eu/-c-130.ht ml http://www.nlp lanet.com/nlgu ides/dutch-climate 10 http://www.absoluteastronomy.com/topics/Schottky_diode 9 10 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Step 2 Having completed the basics of our circuit, we can resume calculations about the aircraft‟s size. When combined with the circuit, we can derive the engine‟s, battery‟s and solar cells‟ requirements. As proposed in „Requirements‟ (page 8), we intended to construct an aircraft with a span measuring 1.5 metres. The influence of the wingspan on the plane‟s other measurements will be investigated next. Research questions involved are: 7. 8. 9. What will be the plane’s size, mass, speed? Which airfoil do you use, how big is it and how does it work? How much lift do you need? These three research questions are related to each other as much as can be, namely lift comes with speed and determines mass and size, but it relies on the airfoil used. We will look at the aircraft‟s size first. Size We determined the aircraft‟s span should be about 1.5 metres. In order to make calculations and construction of the wings easier, we change the span into 1.6 metres. The ratio between span and chord (illustrated 11 right) in average model aircraft is between 1:7 and 1:8 12 . In our airplane this would imply: Width is 1.6 : 8 = 0.2 metres Knowing both the wing‟s width and span, we can calculate the wing‟s surface area. This size will later be used in several calculations. Surface area= 1.6 metres × 0.2 metres = 0.32 square metres Airfoil Not only surface area is important for a well functioning wing, but having a correct airfoil is important too. It is the airfoil‟s shape that provides the aircraft‟s lift. All airfoils rely on same principle 13 , Bernoulli‟s principle. It 14 describes the relationship between velocity and pressure in a moving liquid or gas: 11 http://www.myaero modelling.co m/wp/wp-content/uploads/2008/01/ar.jpg http://www.mvccrash.nl/overons/00000097940bbf72d/ 13 http://library.thinkquest.org/27948/bernoulli.html 14 http://www.daviddarling.info/encyclopedia/B/Bernoullis_law.html 12 11 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 P + ½ρv2 + gρh = k P = Pressure (Pa) ρ = Density (kg / m3 ) v = Velocity (m / s) g = Acceleration due to gravity (m / s2 ) h = Distance from reference, measured in opposite direction of the gravitational force (m) k = constant (kg / ms2 ) The formula proofs that if gravity, air density and position remain unchanged, pressure will drop when flow velocity increases. In other words: if you have an airflow of high velocity and low velocity under the same circumstances, the area containing the high airspeed, will show a lower pressure. This implies that if the air flowing over the wing moves faster than under the wing, the air pressure above the wing will be lower, thus sucking the wing up into the sky. For this reason wings are shaped in such a way that air moves faster along the upper surface. This is done through making the air above the wing move a longer distance in the same time than the air underneath the wing. Therefore the wing‟s upper surface is more curved than its lower surface. 15 Throughout the years many airfoils have been developed 16 . Every single one of them had excellent properties for different purposes, like low or high speeds, or stability. Concorde‟s wing was quite different from a Boeing 747‟s for example. Still, there is no such thing as „the perfect airfoil‟. Properties needed simply depend on the characteristics of the aircraft. Our plane just needs a simple and ergonomic airfoil. It will be „Clark-Y‟ 17 : Clark-Y18 basically is an airfoil with a flat bottom and a curved top. Not only have there been many experiments about this type of wing, it is also easy to construct. The following table19 shows certain numbers defined as lift coefficient. These statistics will later be used in calculations on lift. 15 http://www.yes mag.ca/focus/flight/bernoulli.gif http://www.ae.illinois.edu/m-selig/ads/coord_database.html 17 http://upload.wikimedia.org/wikipedia/en/6/6a/ Clark_y.JPG 18 http://www.gliders.dk/clark_y.ht m 19 http://www.gerritentiny.nl/documenten/Microsoft%20Word%20-%20VLIEGEN4.GER.pdf 16 12 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Angle of attack 0 1 2 3 4 5 6 7 8 9 10 11 12 Lift coefficient 0.29 0.36 0.43 0.50 0.57 0.64 0.71 0.78 0.85 0.92 0.99 1.06 1.12 Speed Before we determine the aircraft‟s mass, we will take a look at its speed. Investigation on several model aircraft shows the approximate flying speed is between 25 and 100 kilometres per hour. 20 Taking into account the limited capacity of our solar cells, we aim to let the aircraft fly at 30 kilometres per hour. 30 kilometres per hour= 30 × 1000 metres : 60 minutes : 60 seconds = 8.3 metres per second. Mass & lift At this very point in our investigation there are two options. Either we determine the probable mass of the aircraft and try to design the appropriate plane in order to ga in enough lift or we determine the lift we will probably gather and try to match the corresponding weight. We choose the latter, since it is easier to make a plane lighter than to increase its lift. Making a plane lighter can be done through removing several pieces of equipment or replacing them by lighter ones (saving on the battery for example). On the other hand, trying to increase lift takes a great effort, because it requires redesigning and manufacturing the entire wings. Lift can be calculated precisely through „aviation‟s most important formula‟ 21 : L = ½ c ×  × A × v2 L = Lift in Newtons c = Lift coefficient (no unit) = Air density (kg / m3 ) A = Wing‟s surface area (m2 ) v = Velocity (m / s) 20 21 http://www.aeroclub-drachten.nl/pagina's/modelvliegen.html http://www.grc.nasa.gov/WWW/K-12/WindTunnel/Activities/lift_formu la.ht ml 13 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 This formula should not be confused with the formula for calculating drag 22 . This formula is based on the same parameters, although when calculating drag the „drag coefficient‟ is used and the letter A represents the frontal area of the object. From our previous investigation we can derive the wing‟s surface area and the plane‟s velocity. The lift coefficient is taken from the table previously shown by assuming that the angle of attack is larger than one degree at take off. At ground level the air density23 is approximately 1.23 kg / m3 . When filling in all numbers the results are as follows: L = 0.5 × 0.36 × 1.23 × 0.32 × 8.32 = 4.88 N The lift generated by our wings will be able to compensate for 4.88N of gravitational force. Since 9.81 Newtons of gravitational force correspond to one kilogram of mass 24 , we can calculate the mass of our aircraft: 4.88 N = 4.88N : 9.81N/kg = 0.497 kg The second calculation shows us the answers to sub questions 7 and 9. When travelling at take off speed the wings of our aircraft generate 4.88 N of lift, thus being able to lift 497 grams. We will make a slight margin concerning mass. Therefore our target mass will be 450 grams. Reynolds number Besides determining if our wings generate enough lift, we must also know if our wings actually generate lift at all. Namely, gently and laminar airflow over a wing will only start at a certain velocity. In addition, when flying too fast, the airflow will also become too irregular and turbulent. The speed range at which the airflow will be smooth and laminar, can be estimated using a value called the Reynolds number. 25 Reynolds number 26 is a value given to the flow conditions around objects. For any object the optimal Reynolds number differs, but as a rule of thumb we can assume the Reynolds number is supposed to be between 5.0 × 104 and 2.0 × 105 for aircraft wings 27 . The Reynolds number can be calculated through the following formula 28 : Re = ρ × v × L × μ-1 Re = Reynolds number (no unit) Ρ = Density (kg / m3 ) v = Velocity of fluid or gas (m / s) L = Travelled length of fluid or gas (m) μ = Dynamic viscosity (Pa × s) 22 http://en.wikipedia.org/wiki/ Drag_equation http://en.wikipedia.org/wiki/Density_of_air 24 http://en.wikipedia.org/wiki/Mass 25 http://home.earthlink.net/~x-plane/FAQ-Theory-Reynolds.html 26 http://en.wikipedia.org/wiki/ Reynolds_number 27 http://www.personal.psu.edu/lnl/097/belg iu m.pdf 28 http://www.aerodrag.co m/Articles/ReynoldsNumber.ht m 23 14 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 The air density is 1.23 kg / m3 as determined previously (page 14). The travelled length of the air is just over the wing‟s chord: 0.205 m. The dynamic viscosity differs according to temperature and air pressure. At room temperature it 29 is 1.85 × 10-5 Pa×s. When filling in all numbers, the results are as follows: Minimum speed = Re × p-1 × L-1 × μ = 5.0 × 104 × 1.23-1 × 0.205-1 × 1.85 ×10-5 = 3.8 m/s Maximum speed = Re × p-1 × L-1 × μ = 2.0 × 105 × 1.23-1 × 0.205-1 × 1.85 × 10-5 = 14.7 m/s Fortunately our take-off speed is within those boundaries. The airflow over the wings should be smooth and laminar. Step 3 Having determined mass, size and the electrical system, we no longer need to estimate things, but we can calculate values precisely. The first thing to do now, is to combine mass and size with the electrical system. In this way we can start to create a list of materials and equipment needed. Parts included in the electrical system are the battery, servo engines, controller, engine and solar cells. These elements are linked in the following way: The size of the aircraft determines the engine‟s size. The engine requires certain power supply, which determines battery size and controller size. Because of this order we will look at a suitable engine first. The sub question involved is: 10. Which engine and propeller do you need? Engine Engines vary in certain ways . There are engines for high speed and engines for much force at lower velocity. Namely, the power of an engine is described in rotations per minute per volt. The lower this number, the more powerful the engine. A slow turning engine will be able to pull heavier aircraft at lower speeds, whereas fast turning engines will pull lighter (stunt) aircraft at higher speeds. Compared to other model aircraft, we intend to fly rather slow. Therefore we will use an engine with a low volts to turns ratio. 30 Initially we found an engine which met some of our requirements: a speed 400 engine. Then we discovered there are several other types of engines 31 . On one hand there are brushed engines (e.g. speed 400), on the other hand there are brushless engines. The latter is a modern invention and consumes considerably less power than the initial one. Brushless engines come in two types 32 : inrunner and outrunner. 29 http://www.ce.utexas.edu/prof/kinnas/319LA B/Book/ CH1/PROPS/ GIFS/dynair.gif http://adamone.rchomepage.co m/guide5.ht m 31 http://www.dynetic.co m/brushless%20vs%20brushed.htm 32 http://www.rcuniverse.com/foru m/outrunner_versus_inrunner%3F/ m_2371948/t m.ht m 30 15 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 An inrunner consists of a several magnets covered by a metal casing. This creates a powerful engine, which unfortunately produces lots of heat, thus loosing efficiency and requiring a cooler. As we cannot afford extra mass, we decided to go for a less powerful, but more efficient „brushless outrunner’. Taking mass and all other requirements into account, the following engine 33 seems most suitable to us: 2208/17 Brushless Outrunner 1100KV Price: €14.50 Element KV (RPM / V) Voltage Nominal current Maximal current Efficiency (at 4-7A) No load current (at 10V) Internal resistance Axle diameter Dimension (Øxl) Mass Recommended model mass Maximal propeller Value 1100 6-12V 3-6A 8A (max 60 s) 74% 0.6A 225 mΩ 3mm 27.5 x 26 mm 36 g 200-500 g 8.5 x 5 inch Propeller As shown in the scheme above, a recommendation has been given on the maximal propeller size, with the first number being the propeller‟s maximal diameter and the second being maximal lead. A propeller with its lead being similar to its diameter is best suited for fast flying airplanes, whereas a propeller with small lead and larger diameter is excellent at providing maximal force, thus being perfect for heavy, slow flying aircraft. 34 As our plane flies rather slow, the following propeller 35 seems most suited: Master Airscrew Electric Propeller 8 X 5 Price: € 3.35 Element Mass Diameter Lead Value Unknown 20.3 cm 13 cm To be absolutely sure this propeller is perfectly suited to propel our aircraft, we can apply the following formula and rule of thumb 36 , which shows the relation between speed, rotations and lead. The propeller‟s speed must be two to three times as high as the airplane‟s take-off speed. 33 http://www.rctechnics.eu/220817-brushless-outrunner-1100kv-p-1692.ht ml http://www.zinin mijnleven.nl/hobby/propellors/index.ht m 35 http://www.rctechnics.eu/electric-propellor-p-116.ht ml 36 http://www.modelbouwforu m.nl/ foru ms/%5Bfaq%5D-modelvliegen-electro/21998-welke-spoed-moet-mijnprop-hebben.html 34 16 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 vprop = l × f v = Velocity (m / s) l = lead (m) f = Rotations per second (Hz) Our engine is rated to provide 1100 rotations per minute per volt. As our system functions at 8.5 volts (see below), we expect to operate at 9350 rotations per minutes, which is 156 rotations per second. Propeller speed = l × f = 0.13 metres/rotation × 156 rotations/second = 20.3 m/s Ratio propeller speed : airplane speed = 20.3 / 8.3 = 2.45 The propeller we selected should be perfectly suited, since its speed is approximately two and a half times as high as the aircraft‟s speed. Therefore its torque is sufficient to propel the aircraft. Batteries The engine requires a voltage ranging from six to twelve volts. This voltage should be provided by both our solar cells and our battery. Another key aspect of the battery is mass. In our quest for suitable batteries we first had a look at lithium- ion polymer batteries due to their excellent power to mass ratio. However, LiPo batteries bring notable risks with them, such as spontaneous combustion when overloaded 37 . LiPo batteries work best at a steady power supply, but since the output of our solar cells varies heavily, we decided not to take the chance of our airplane catching fire in mid-air, but doing extra research on alternative batteries instead. The second option is nickel-metal hydrate batteries. These batteries have the disadvantage of being much heavier than LiPo batteries, but their reliability made us favour nickel- metal hydrate batteries over LiPo batteries. We will install seven „high output‟ batteries, producing a total of 8.4 volts, weighing in at 175 grams and having a capacity of 2500 mAh38 . This capacity means that the cells will be able to provide a continuous current of 2.5 A during one hour. Solar cells (1) The solar cells should provide enough power during flight to extend flying range drastically or even power the aircraft entirely. Just as with all materials used on our plane, mass is a crucial element, so the solar cells can‟t be too heavy. The research question involved is: 11. Which solar cells generate most electricity with fewest mass and how big are they? 37 38 http://www.rctoys.com/pr/2006/ 10/ 20/safe-use-document-thunder-power-lithiu m-poly mer-batteries/ Battery packet, HEMA Photo batteries 17 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 There are very few companies selling single solar cells. Cells are often being integrated in glass, something that would contribute far too much weight. Eventually we found a German company, Lemo-Solar 39 , selling single cells. Fortunately their shop contained a variety of cells, including one that meets our requirements: Single solar cell Price: €10.60 Element Dimensions Soldering strip Polarity front Polarity back Nominal voltage Nominal current Maximal output Mass Value 100 x 100 mm Tinned, 2 mm Minus Plus 0.5 V 3200 mA 1600 mW 6.4 g Because of the chosen batteries and the 0.1-0.2 volts lost over the diode, solar cells we use on the airplane must have a total output of 8.5 volts. This would require seventeen solar cells. Besides the financial aspect, seventeen solar cells will also weigh too much and will probably not fit in the airplane (more information in step 6). Therefore we will need smaller solar panels besides the ones mentioned above. The cells will be soldered together with flexible wiring. This will be no problem, as the cells are already equipped with soldering strips. Solar cells (2) Single solar cell Price: €3.- Element Dimensions Soldering strip Polarity front Polarity back Nominal voltage Nominal current Maximal output Mass Value 29 x 78 mm Tinned, 2 mm Minus Plus 0.5 V 630 mA 340 mW 1.6 g In total we plan to use twelve solar cells measuring 10 by 10 centimetres and six cells measuring 29 by 78 millimetres. When adding properties of all solar cells, the results are as follows: Mass: 12×6.4g + 6×1.6g = 87 g 39 http://www.lemo-solar.de/default_1.ht m 18 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Output: 12×1600mW + 6×340mW = 21240 mW ≈ 21 W Engine power: 5A× 8.4V = 42 W This implies that under ideal circumstances the solar cells will provide 50% of the engine‟s power supply. Of course this would be an utopia, since we didn‟t take power loss by the receiver, servo‟s and controllers into account. Tests will eventually show how close we can get to our 50% energy reduction goal. We will go into more details about testing in the „Test proposal‟. Servos The next step after investigating the right materials for energy supply and propulsion, is finding the right equipment for controlling the aircraft during flight. This equipment includes the receiver, engine controller and servos. First, we have a look at the servos, devices operating the plane‟s ailerons and rudder 40 , which control vertical and horizontal movement. These machines come in different sizes and shapes. Since our plane is lightweight and forces on the aircraft won‟t be tremendous, we decided to go for the lightest servos 41 : Micro Servo 3.7 grams Price: € 7.50 Element Dimensions Mass Speed (4.8V) Torque (4.8 V) Operating voltage 40 41 Value 19.7 x 17.44 x 8.37 mm 3.7 g 0.1 sec / deg 0.5 kg / cm 4.8 – 6.0 V http://www.rc-airplane-world.co m/rc-airp lane-controls.html http://www.rctechnics.eu/micro-servo-gram-p-2497.html 19 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Every flap, rudder or aileron needs a servo to operate. A regular airplane is co ntrolled using ailerons 42 for rolling movements, the elevator 43 for up and down movements and the rudder44 for crosswind compensations. This is illustrated by the drawings on the previous page 45 . We are unlikely to fly at high wind speeds due to expected fragility of our aircraft. Therefore we will eliminate the servo for the rudder. It will not only save us weight by not using a servo, but also through the removal of wiring. The total mass of our servo engines will be: Mass: 3 × 3.7g = 11.1 grams Engine regulator Next up in the controlling equipment is the engine regulator. It controls throttle given by the engine. Again, this part should weigh as little as possible and should be able to cope with current and voltage in our circuit. We found the following suitable engine regulator 46 : 12A FLY Brushless ESC Price: € 16.95 Element Operating voltage Continuous load Peak load Dimensions Mass Low voltage turn off 47 Value 7.2-12 V 12 A 15 A (Max 5 s) 22 x 18 x 5 mm 7.1 g Automatic Receiver Of course the airplane doesn‟t control itself. We want a person on the ground to be able to remotely control the aircraft. For this reason, we need a remote controller and a receiver. The controller will send signals to the receiver, which will instruct the servo engines and the engine regulator. We found the following suitable parts 48 : E-Sky receiver, 6 channels, 35Mhz Price: € 13.50 Element Frequency Mass Dimensions Voltage Current Antenna Length Value 35 Mhz 14 g 45 x 23 x 13 mm 5V 11.5 mA 100 cm 42 http://www.rc-airplane-world.co m/image-files/rc-airplane-ailerons.gif http://www.rc-airplane-world.co m/image-files/rc-airplane-elevators.gif 44 http://www.rc-airplane-world.co m/image-files/rc-airplane-controls-rudder.gif 45 http://www.rc-airplane-world.co m/image-files/rc-airplane-controls.gif 46 http://www.rctechnics.eu/12a-fly-brushless-esc-p-393.ht m 47 Once voltage drops below 7.2 volts, the controller switches off power to the engine, thus preventing batteries fro m d ischarging too much. 48 http://www.rctechnics.eu/esky-ontvanger-kanaals-35mh z-p-1367.ht ml 43 20 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Remote control Both the sender and receiver should function at the same frequency. Therefore our options for choosing a suitable remote control were slightly reduced. Additionally there are great differences between remote controls operating at the same frequency. Some are equipped for controlling helicopters only, whereas others are best suited for controlling petrol powered planes only. This difference originates from different controls needed for different planes. A helicopter for example does not have a retractable undercarriage, while a large aircraft does. Eventually we found the following49 : E-Sky remote control, EK2-0404A Price: € 29.95 Element Channels Frequencies Energy source Servo reverse Voltage indicator Dimensions Colour Antenna length Usage Value 4 35, 40, 72 MHz 8 x 1.5 AA battery Manually Automatic, Led 185 x 205 x 55 mm Black 100 cm Airplane, helicopter, Glider Step 4 We can now make a decision on size and mass of the plane. At the start of our research project, the wingspan we were striving for was 1.6 metres. Looking at the dimensions of the equipment we will be putting in the airplane, there is no reason to change this plan. Element Engine Battery Servos Receiver Propeller Engine Wiring Solar cells 1 Solar cells 2 Frame Unforeseen Total 49 50 Mass (grams) 7.1 175 11.1 14 5 36 10 76.8 9.6 70 10.4 425 Now we‟ve decided on the parts to be used, we can also give a more informed prediction of the mass of the plane. All the parts we just summed up add to a total of 335 grams, well below our target mass of 450 grams. However, we haven‟t included all elements yet (such as the frame, wiring and unforeseen additional mass). In addition, we aren‟t certain yet about the mass of the propeller, but we estimate it weighs 5 grams. We reserve 70 grams for the frame, a reasonable amount according to experts on internet forums 50 . Furthermore we reserve 10 grams for wiring and 10 grams for unforeseen mass. All these numbers add up to a total of 425 grams, so we should be well under our target mass. http://www.rctechnics.eu/esky-zender-kanaals-35mhz-ek20404a-p-2784.ht ml http://www.modelbouwforu m.nl/ foru ms/bouwverslagen-vliegen/59216-bouw-van-een-fijn-zwevertje.ht ml 21 Step 5 + - + 18 in series: 9.0 V 3200 mA 7 in series: 8.4 V 2500 mAh + Solar cells Batteries: 1.2 V each, 2500 mAh Batteries: Solar Cells: 0.5 V each, 3200 mA - Servo Controller Receiver Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 The electrical system has now been completed. Knowing mass, size and properties we are able to draw the final circuit: Servo M Servo - Step 6 12. How do you mount the solar cells on the aircraft (inside or outside, wing or body?) With the solar cells being a critical part of the plane, it is logical to have a good thought about the solar cells‟ position in the plane. The solar cells account for a large part of the total mass, so their position has to be well considered to keep the plane balanced, both on the ground and during flight. Since the plane‟s fuselage will be very slim and the solar cells measure 10 square centimetres, it is most obvious to place the solar cells on the plane‟s wings. With the plane being 160 centimetres in wingspan, we have plenty of space to place all solar cells. In addition, placing solar cells on the tail will not only be impossible due to the tail‟s size, but the plane‟s centre of gravity will also be shifted too much to the back. 22 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 We have to determine whether we will place the solar cells on top of the wings or inside the wings. The choice was made quickly: we will place our solar cells inside the wings, since it offers multiple advantages:    The assembly of the solar cells becomes much easier. If we would place the solar cells on top of the wings, we would have to attach the solar cells to the covering foil which might pierce the foil and possibly ruin lift properties. Placing the solar cells inside the wings will leave aerodynamic properties of our wings intact, whereas putting solar cells outside the wings would drastically increase the drag of the wings and could reduce the lift they provide. Placing the solar cells inside the wings largely eliminates the risk of damaging the highly vulnerable solar cells, since they will now be protected by foil. The schematic drawing below gives an impression of the right wing: The six big yellow squares represent the six big solar cells in the wing; the small yellow squares represent the smaller cells. We will leave some space between the solar cells to place the ribs of the wing. All these ribs will give the wing its structural integrity. In step 7 we will go into more details about the construction‟s design. Step 7 13. What will be the structure’s design? 14. Which materials do you need to construct the plane? Now that the solar cells‟ placing has been determined, we can make a list of all the additional equipment we will be placing in the wings. Parts that will be put in the wings are:         Solar cells Servos Wiring Foil Ribs & cornices Triplex beams Axle for aileron Ailerons 23 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Our plane‟s wings will have a wingspan of 160 centimetres, a width of 20 centimetres and an expected height of 2.5 centimetres. To prevent the wing from bending we will place two triplex beams running through the wings. The front and rear cornice have already been preshaped 51 . In the diagram below you can find an overview of the wing. The numbers above the wing represent the rib that is placed there: The ribs will be made out of balsa wood, the lightest type of wood known to men 52 . Each rib measures three millimetres in thickness. We will cover the wings using a covering foil called Mylar. This material can be applied to the wing loosely, but will be tightened around the frame by ironing it 53 . It weighs approximately seven grams per square metre and is strong enough to lift the aircraft. Cross section 1 The drawing below shows one of the wing‟s regular ribs. The yellow circles represent holes in the ribs for wiring. The black rectangles in the middle of the wing represent two triplex girders running through the wing. On top of these we will mount the solar cells. Besides providing a base for the solar cells, the girders also give the wing structural integrity. The black semi-circle and triangle show the pre-shaped front and rear cornice. The blue rectangle shows the position of a solar cell in between the ribs. 1 Our solar cells will be mounted inside the wing. This requires the ribs to be placed eleven centimetres apart, for else the solar cells won‟t fit. We also need to make sure there is enough room to construct the ailerons. Besides, some space must be kept free to install a servo engine. These demands result in three alternative ribs which will be used in the aft of the wing: 51 http://muco-modelbouw.n l/index.php?lang_id=1&c_id=590&ref_change=outside http://pldaniels.com/fly ing/balsa/balsa-properties.html 53 http://www.modelbouwforu m.nl/ foru ms/verlijming-constructie/44864-mylar-folie-hoe-verwerk-je-dat.html 52 24 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Cross section 2 In the second cross section we see the servo‟s placing in the wing. Cross section 3 The third cross section represents the last rib before the aileron, the element in the wing which allows us to steer the plane. You may notice an extra beam just before the hole for the aileron. This beam provides a surface around which the covering foil can be wrapped. Cross section 4 The fourth cross section is the rib that can be found in the part of the wing where the aileron is placed. As you can see, the rear cornice of the wing has been cut off. Instead we will place the aileron there. In addition, the large solar cell isn‟t shown, because in this part of the wing we will locate the smaller cells instead. They are too small to rest on top of the triplex beams. Therefore they will be suspended on top of a little piece of rope attached to the triplex girders. 4 Step 8 & 9 Fuselage The aircraft‟s fuselage is among the most important parts of the plane. All electronic equipment is to be installed here. Moreover, wings and landing gear are connected to the plane‟s fuselage. As weight and balance are crucial to an aircraft, it is important to make a detailed drawing showing where all equipment will be placed. To monitor the balance the plane‟s fuselage will be suspended by one thread during construction. In that way a flaw in balance will be noticed quickly as the plane flips over when not properly loaded. Sub questions involved in parts 8 and 9 are: 25 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 15. Where do you place all electrical equipment, making sure the aircraft is balanced and what will the fuselage be like? 16. What will be the shape of the tail and elevator and how are they controlled? Fuselage First up is the fuselage. Since drag is an important factor when co ncerning the engine‟s capacity, we should keep drag as low as possible. We intend to construct a frame measuring seven centimetres wide. In order to keep the structure both light weight and strong, we shall construct a triangular shaped fuselage. The fuselage will be 28 centimetres long, thus providing us with enough room to place all electrical equipment. However, our seven AA batteries measure 54 five centimetres each. Therefore they can‟t be installed in one line. The entire scheme of our plane‟s fuselage can be found below. Due to heat produced by several pieces of equipment 55 the back side will be left open. As shown in the drawing, the centre of gravity is to be located at ⅓ of the wing‟s depth. This is a rule of thumb 56 for building aircraft. With the equipments‟ mass being so low and exact mass of the frame yet unknown, it is impossible for us to calculate the momentum for each element in the plane. Therefore the scheme shown above will be used as a guideline to position all equipment. Once our aircraft has been completed, its centre of gravity will be determined precisely by slightly moving the equipment inside the plane‟s fuselage. Another rule of thumb 57 is to rather position the plane‟s centre of gravity slightly too far in front than too far to the rear. This is due to the plane getting in stall position too easy when the centre of gravity is located in the rear. 54 http://en.wikipedia.org/wiki/AA_battery http://www.modelv liegclub-swentibold.nl/To_BEC.ht m 56 http://www.modelbouwforu m.nl/ foru ms/zweefv liegen/74239-afstellen-zwaartepunt-zwever.ht ml 57 http://www.fms-spaarnwoude.nl/home/content/view/272/ 88888915/ 55 26 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 The fuselage‟s frame will be constructed with balsa wood and covered with Mylar foil. However, due to safety reasons, we will manufacture the fuselage‟s base out of a plate of balsa wood, for else the equipments‟ heat will melt the Mylar foil. The frame itself will feature triangular shaped parts. The holes in between the 2nd and 3rd and between the 4th and 5th triangle are points to attach the wing to the fuselage. As shown in the diagram below, the main gear will be placed slightly in front of the centre of gravity. This will make the aircraft fall over to the back when landed. A little wheel mounted underneath the tail will prevent the aircraft from sustaining damage. Besides, when on the ground the aircraft will always stand in a tilted position, thus providing more lift at take off (see diagram page 13). Another important element of our aircraft is the positioning of two supporting triplex beams for the wings. They can be seen in the diagram below. The triplex beams will be attached to the landing gear, to provide maximum support for our wings. The beams will measure 10 x 5 millimetres. Tail and elevator Up so far there are still two vital airplane parts we haven‟t mentioned. They are the horizontal and vertical stabilizer, better known as tail and elevator. They provide stability for our aircraft. In addition they are vital elements in controlling the plane. Just like the fuselage, elevator and tail will be constructed with balsa wood and Mylar foil. Strength is once again provided by triangular shaped balsa frames. The tail‟s and elevator‟s size are determined by the wing‟s area. The ratio 58 between elevator and wing is 4:1, whereas the ratio between tail and wing is 25:1. This implies the areas of both the tail and elevator will be as follows: Wing area: 1.6 × 0.2 = 0.32 m² Elevator area: 0.32 × 0.25 = 0.08 m² Tail area: 0.32 × 0.04 = 0.0128 m² Elevator size: 60 centimetres wide and 13 centimetres in depth. Tail size (triangular): 18 centimetres in depth and 15 centimetres high. 58 http://www.auf.asn.au/groundschool/umodule6.ht ml 27 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 The tail will be connected to the fuselage with a triplex beam. For extra structural integrity the beam will run all the way from tail to engine. The diagram below shows the entire aircraft, including the tail, wings and fuselage. As a final check we will calculate the balsa wooden frame‟s mass. Every rib will weigh half a gram. Twenty ribs weigh 10 grams. Triplex beams, front cornice and rear cornice will weigh approximately 30 grams. In addition, the fuselage and landing gear weigh 20 grams, compared to 10 grams for the tail. Mylar will come in with just several grams. This adds up to a total of 70 grams. Step 10 As our design proposal has nearly been finished, we can now determine the costs of our project. Our budget is €400. The table below shows we should be well under that amount. Element Solar cells 1 Solar cells 2 Engine Propeller Remote control Receiver Servos Engine controller Battery Frame Wiring Unforeseen Total Cost € 127.20 € 18.00 € 14.50 € 3.35 € 29.95 € 13.50 € 22.50 € 16.95 € 25.00 € 35.00 € 5.00 € 14.05 € 325.00 28 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Another crucial issue is weight. Having a clear picture of which elements we will be using, it is time to add up the masses of all individual components. The results show we are still well on track to reach our target mass. Element Engine controller Battery Servos Receiver Propeller Engine Wiring Solar cells 1 Solar cells 2 Frame Unforeseen Total Mass (grams) 7.1 175.0 11.1 14.0 5.0 36.0 10.0 76.8 9.6 70.0 10.4 425 = estimated 29 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Construction proposal After having done thorough research on the plane‟s design, it is time to start thinking about construction itself. Just as we did in the design proposal, we set up a plan dealing with the order of construction: Step 11: Step 12: Research on where to order construction materials. Determining the order of construction. The sub question being answered is: 17. In which order are you going to construct the plane? Step 11 To start with, we will order the parts of the electrical system. We try to keep mailing costs as low as possible. Therefore we must order as many items as possible at the same supplier. We composed the following list of materials needed. All supplies will be ordered on the web. Electronics All the electronics are to be ordered at rctechnics.eu. Their shop features a broad range of items, all good quality products according to people on internet forums. The following items will be ordered at rctechnics.eu:      Receiver Engine regulator Servos and wiring Engine Remote control Construction materials Just as the electronics, the propeller and landing gear wheels will be ordered at rctechins.eu. Unfortunately this shop doesn‟t sell other construction materials. In addition, finding a web shop which sells and ships balsa wood is extremely difficult. Eventually we found a supplier in Groningen, who could offer us balsa wood and beams for the ailerons and rudder: netshop.nl/shop/krikkem. Glue is available at a local DIY shop and batteries will be bought at the local HEMA. In contrast, Mylar is not available in any shop in Holland. At last we found a shop in Great Britain selling Mylar: indoorflyer.co.uk. The shopping list for construction materials is as follows:    Propeller (rctechnics.eu) Landing gear wheels(rctechnics.eu) Balsa (netshop.nl/shop/krikke) 30 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010     Beams for ailerons and rudder (netshop.nl/shop/krikke) Glue (Praxis) Mylar (indoorflyer.co.uk) Batteries (HEMA) Solar cells As told in our design proposal, the solar cells will be ordered at lemosolar.de. Step 12 Once we receive our supplies, we will put together the electrical system. After composing it, we will run several tests as described in the „Test proposal‟. We will collect data we need and make amendments to the system if desired. After such possible adjustments we will make a new estimation of the plane‟s mass and, if needed, adjust the wings‟ size or the plane‟s design. With the electrical system being complete, it is time to focus on the plane‟s body. A crucial element here is design and construction of the wing. This is the next step in our process of construction. We will construct two separate wings out of balsa wood, place solar cells on the correct places and then wrap the wings with Mylar foil to secure their shape. Once completed, we can test the lift the wings generate. The test is described in our „Test proposal‟. If the wings don‟t produce the lift required, we will have to make adjustments. With the wings and electrical system now completed, we will construct the rest of the aircraft, which consists of the elevator, tail and fuselage. Next, we will mount the electrical system in the plane‟s fuselage, glue the landing gear onto the plane and determine the centre of gravity. The last step in construction is to fasten the wings to the fuselage. If needed, we will move items inside the plane in order to get the centre of gravity in the right position. If all goes well, we have built a complete plane by now and we can start testing. If required, adjustments will be made during and after testing. 31 Test proposal Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 To make an organized test proposal we have to follow the steps we‟ve set ourselves: Step 13: Step 14: Determining what needs to be tested and in which order. Set up plans on how to run tests, where and with which materials required. Step 13 & 14 Throughout the project several tests need to be run. We will investigate the following data:     Solar cells’ output and profit Lift test Drive test Flight test The solar cells‟ output and profit 18. Which effect does the position of the solar cells have on the efficiency of both the plane and panels? 19. How much profit do the solar cells provide? To answer the two sub questions concerning the solar cells‟ profit, we came up with the following test setting. After we ordered components such as solar cells and the engine, we will compose the electrical system. At this point we haven‟t started construction of the plane yet. First, we will fully charge the batteries, connect them to the engine and then let the engine run at full throttle. We will record the time it takes for the batteries to run out. In order to minimize errors, we will redo the test three times. In a second test we will add solar cells to our electrical system. We make sure the solar cells receive plenty of light and then we let the engine run at full throttle again. We will write down the time it takes for the batteries to run out and compare this to the previously clocked time. In this way we will be able to tell something about the profit of the solar cells. A third test aims to determine the effect of Mylar foil on the solar cells‟ output. We will run the second experiment again, but now, we will place Mylar foil over the solar cells. This will probably decrease their power supply. Through this experiment we will be able to say something about the influence of the Mylar foil. Unfortunately the solar cells‟ output strongly depends on weather. If time is available we will do the second and third test several times in both cloudy and sunny conditions. Unfortunately a photo meter to measure sunlight intensity59 is not available. 59 http://en.wikipedia.org/wiki/Photometer 32 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Lift test Once construction of the wing has been completed, it is time to test lift. At this point we still have two separate wings. Before both parts are glued together, we will take one of the wings and attach it to a force meter. This composition will be mounted into a free ly moveable frame. The frame, composed of K‟nex parts, will be fit on a bicycle‟s basket. One of us will cycle at 30 kilometres per hour, the intended take-off speed. Speed will be measured with an odometer on the bicycle itself. If calculations have been correct, the force meter should measure a difference of approximately 2.5 Newton. Of course we will take into account influences that could disturb our test, like wind, loss of surface area due to K‟nex frame, etc. Drive test Eventually we reach a point where the aircraft is finished. We will have determined the centre of gravity and will have made sure the controls function properly. Before it is actually time to take off, we will perform several driving tests. We will position the airplane on a smooth surface, for example a gym floor. Then we will slowly increase throttle to let the aircraft „taxi‟. Now it is time to make final adjustments. Drive tests might show deviation in driving direction, lack of power or other defects. Once those problems have been solved, we will do a final driving test. We will keep increasing throttle until the tail will get airborne. Namely, the tail coming off the ground is a first indication of taking off. This is because the mass of the aircraft is no longer supported by the wheels, but by the wings. The centre of gravity is slightly behind the wheels, thus making the aircraft falling over to the back. When the mass of the aircraft is no longer supported by the wheels, but by the wings, the centre of gravity is at ⅓ of the wing, thus balancing the aircraft. This process is shown by the following pictures 60/61 . Taxiing Take-off Fn Fn Fg 60 61 Flif t Fg http://media.photobucket.com/image/ph-pba/AirKas1/PH-PBA_GRQ_12-07-09kj.jpg http://farm4.static.flickr.co m/3135/2768004875_d48345f8bc_o.jpg 33 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Flight test At this point in our research project we know whether or not our wings produce enough lift and the engine and propeller generate enough power to propel the plane. Still, there is one big challenge left: flying. According to people on internet forums, flying a model aircraft is a very difficult discipline. It requires extensive expertise and experience with flying. As we don‟t want to crash our aircraft during its maiden flight, we will bring in an experienced person from a flying club. He will fly our aircraft at first. With his help we will eventually learn how to control the plane. The last problem that needs to be solved is finding a suitable runway. As our plane is probably going to be fragile, it is unlikely we can take off from any parking lot. Currently we plan to use an artificial turf field as a runway. 34 Media attention Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Website We intended to launch a website on the internet. Here people would be able to follow our progress and see pictures of the airplane. However, we didn‟t want to spend any money on an expensive internet domain, so once the free testing period had expired, unfortunately the website was cancelled. Sponsors Since this project is quite costly, we had to take a look at possible sponsors. Being environmentally friendly is a major aspect in our project. We searched for companies that present themselves as environmentally friendly. Companies we ended up looking at were Triodos and ASN bank. However, Triodos only sponsors five major projects on a yearly basis and the ASN bank rejected our proposal. Another effort we made was with the company that supplied us with solar cells. We asked them if they were willing to provide us with solar cells or give us discount on solar cells in return for some promotion. Luckily, they gave discount on the solar cells, but mailing costs proved to cancel out our „profit‟. Logo Just like any plane, ours will feature a company logo on its tail. We chose to create the following logos: Ai rcra ft Cons truction Company Ai rline „JET‟ is not only a synonym for airplane, it also represents our initials: J(esper) E(n) T(im). The globe shown on the logo represents JET‟s internationally orientated roots. 35 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 International aspect As part of our internationally orientated education, our research project should include a piece in which we discuss how our research project is internationally relevant. We think our research project is internationally relevant, because it is based on a world-wide hot topic. Energy demands The issue of meeting the worldwide energy demands is currently high on any politician‟s shortlist. Right now we are able to fulfil our needs, but knowing we consume 85 million barrels of oil a day62 , it is clear we will run out of our energy supplies one day. That day is coming closer by the minute. Engineers worldwide are searching for a lternatives to meet our demands. Their focus mainly lies on the renewable energy sources, such as wind and solar power 63 . Their reasoning to focus on these sources of energy is simple: such sources won‟t run out for billions of years and are capable of meeting the world‟s energy demand. Covering 10% of the Sahara desert area with solar cells for example would be sufficient to supply energy to the whole world 64 and wind turbines in shallow coastal waters could account for 20% of energy demands in the USA 65 . Solar power thus is an interesting option. Recent years have seen solar power production climb with a staggering 40% per year 66 , but when looking at statistics showing67 shares in total energy supply, we will notice that solar power production does not even account for one percent. We should realise that there still is a long way to go. Our solar powered plane could let people come to realize just what the possibilities of renewable energy sources are, especially solar cells. If we can make a plane fly using solar power, other possibilities are nearly endless! People might consider placing solar panels on their roof or on their carport to supply part of the power for their houses. There are a lot of advantages to solar panels: four square metres of solar panels supply 10% of the annual energy consumption of an average household 68 . In addition, solar panels could recover 69 their costs in about ten years and solar panels can increase the value of your house, since a home becomes friendlier to the environment and has considerably lower energy costs. Not only is solar power being looked at as an option to supply energy we use in our households, solar power has also come into picture for powering vehicles. This mostly shows through all sorts of contests being held for technical institutions. 62 http://peakoil.b logspot.com/2006/03/peak-o il-is-closing-in.ht ml http://en.wikipedia.org/wiki/ Renewable_energy 64 http://en.wikipedia.org/wiki/Desert#Solar_energy_resources 65 http://www.motherearthnews.com/ Renewable -Energy/Offshore-Wind-Po wer.asp x 66 http://en.wikipedia.org/wiki/Solar_power#Develop ment.2C_deploy ment_and_economics 67 http://www.iea.org/textbase/nppdf/free/2008/key_stats_2008.pdf 68 http://www.milieucentraal.nl/pagina?onderwerp=Zonnepanelen 69 http://www.olino.org/articles/2006/ 07/ 31/de-terugverdientijd-van-zonnepanelen 63 36 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Solar cars The most serious option being looked at is solar energy to power cars. With hybrid and plugin electric cars being introduced to the market, solar power becomes an interesting option to supply energy. A famous contest between solar powered cars is the World Solar Challenge, a race across the Australian desert being held every two years 70 . This race catches worldwide attention. Technology used in cars involved can be replicated in other cars. In recent years the race has become well-known in The Netherlands because of success of the Technical University of Delft with their NUNA 71 solar powered car. The TU Delft has won the World Solar Challenge four times in a row 72 , each time with a modified and upgraded car. When the team entered competition with NUNA 1, they won the race with an average speed of 92 kilometres per hour 73 . Two editions later NUNA 3 74 won the World Solar Challenge with an average speed of 103 kilometres an hour 75 . In fourth edition NUNA 4 won with an average speed of 93 kilometres an hour, even though this car had only 6 m2 of solar panels, instead of 9 m2 used in previous editions 76 . Cars competing in the World Solar Challenge distinguish 77 themselves from normal cars because of their extremely low drag and low mass. The cars are very aerodynamic (up to 6 times more aerodynamic than cars driven today) and have a very low rolling resistance, thanks to thin and well lubricated wheels. Moreover, the cars are as light as a feather compared to normal cars. Namely, a regular car usually weighs 78 around 1000 kilograms, whereas the newest version of the NUNA (NUNA 5) weighs 79 just 160 kilograms. Solar panels used on these cars are of very high quality and have an extremely high output compared to normal solar cells. Although the NUNA 5 doesn‟t have the luxurious items we might want in our cars, such as a radio or air conditio ning, we can still learn a lot on how to make our cars lighter and how to lower their drag. Besides, we can learn how to incorporate solar cells in our cars. All these aspects could make present day cars more fuel efficient. 70 http://www.wsc.org.au/ http://www.tudelft.n l/live/pagina.jsp?id=a43ae927-9cc7-4716-ab01-c4795f6c11a3&lang=nl 72 http://www.globalg reenchallenge.com.au/wsc-evolution/previous-winners 73 http://en.wikipedia.org/wiki/ Nuna_1 74 http://c0378172.cdn.cloudfiles.rackspacecloud.com/12227_15070993902.jpg 75 http://en.wikipedia.org/wiki/ Nuna_3 76 http://en.wikipedia.org/wiki/ Nuna_4 77 http://nl.wikipedia.org/wiki/Categorie:Zonnewagen 78 http://www.cbs.nl/nl-NL/ menu/themas/verkeer-vervoer/publicaties/artikelen/archief/ 1999/1999-0361-wm.ht m 79 http://www.nuonsolarteam.nl/ 2009/06/nuna5-onthuld/ 71 37 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Solar boats Solar power has become an interesting option for small boats too, mainly due to the Frisian Solar Challenge held in 2006 and 2008 80 . The organizers of this event wanted to create a counterpart of the World Solar Challenge and have done so by making solar powered boats race on the very same water used for the famous „Eleven cities‟ speed skating race 81 . Since small boats need a relatively small engine to power them (a five horsepower engine is sufficient to power a small vessel 82 ) an electric power source is a serious option to be considered. A solar panel might just be the ideal way to power the engine since most boats have a large area to place the solar cells on and spend all their time outdoor in sunlight. The hydrodynamics used in the Frisian Solar Challenge can be applied to commercial yachts as well, no matter what size they are. A streamlined hull is a key element for a vessel to achieve low fuel consumption and streamlining is just what the Frisian Solar Challenge is all about. Powering freighters using solar power is no realistic option since big carriers require tremendous power 83 . Giant kites would be more suitable to propel these ships 84 . Still, we could reduce global carbon dioxide emissions drastically by making vessels more efficient, since naval traffic accounts for five percent 85 of worldwide CO 2 emissions, nearly twice as much as aviation. Solar planes Last of all, attempts have been made in the last decades to power aeroplanes using solar cells. One of the biggest organisations researching the feasibility of a solar powered plane is NASA with their ERAST program86 . This program resulted in four prototype electrical planes (NASA Pathfinder 87 , NASA Pathfinder Plus, Centurion88 and Helios 89 ) which all four flew using solar cells. The planes got increasingly bigger as the project went on and several records, such as the altitude and endurance records 90 , were broken. These planes, however, were unmanned planes, steered through radio controls. Although Helios could carry up to 230 kilograms of mass, there was no place for a pilot. 80 http://www.frisiansolarchallenge.nl/ http://www.frisiansolarchallenge.nl/route-en-reglementen/route 82 http://www.s malloutboards.com/choose.htm 83 http://www.howstuffworks.com/ floating-city1.ht m 84 http://iloapp.seamanshiptutor.com/blog/blog?ShowFile&image=1201089418.jpeg 85 http://www.guardian.co.uk/environ ment/2007/ mar/ 03/travelsenviron mentalimpact.transportintheuk 86 http://www.nasa.gov/centers/dryden/history/pastprojects/Erast/index.ht ml 87 http://en.wikipedia.org/wiki/NASA_Pathfinder 88 http://www.dfrc.nasa.gov/gallery/ movie/Centurion/HTM L/ EM -0003-01.ht ml 89 http://www.pvresources.com/en/helios.php 90 http://askmagazine.nasa.gov/pdf/pdf11/48741main_FIG1.pdf 81 38 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Planes that did succeed in carrying a person with it were Sunseeker 91 and Solar Challenger 92 . In 1981 Solar Challenger crossed the Channel93 , whereas in December 2008 Sunseeker was the first solar powered plane to cross the Alps. In 2010 the successor of Sunseeker, Sunseeker II 94 , will make a tour across Europe to demonstrate the possibilities of the plane. Sola r Challenger In June 2009 a new solar powered plane was revealed 95 to the world: Solar Impulse 96 . This plane has a wingspan of 64 metres (larger than most commercial aircraft 97 ), can carry one person and weighs just 1600 kilograms. If all tests go according to plan, the successor of Solar Impulse will make a flight around the world in 2011. The designers reckon this will take approximately 25 days, since the plane flies at just 90 kilometres an hour. The examples above illustrate that it is still impossible for mankind to transport hundreds of people in a plane over large distances using solar energy. One of NASA‟s aircraft could carry three persons, but the ride wouldn‟t be very comfortable due to the plane‟s shape. Also speed is an issue: whereas current planes have a cruising speed of 900 kilometres per hour, solar powered planes travel at approximately 80 kilometres per hour. At this speed a trip from London to Sydney would take about 216 hours, or 9 days! To keep aviation the way it is today, we have to use fossil fuels, just because the amount of energy they deliver is unmatched. Investigation aircraft Although solar powered airplanes are not useful for passenger transport at this moment, it might offer new possibilities to other brands of aviation. Solar planes have features common planes don‟t have. The most useful ability is that solar powered planes could stay airborne forever, for they, rather than carrying their fuel with them, gather their energy while flying. This ability provides lots of opportunities for solar powered planes. NASA already fitted their Pathfinder plane with measuring devices to observe coral reefs around Hawaii, forest regrowth after damage by a hurricane and sediment concentrations in coastal waters 98 . As the examples illustrate, solar powered planes could be used for research because of their long flight time, low flying speed and ability to fly at nearly any altitude. 91 http://solar-flight.com/sunseeker/index.ht ml http://www.donald monroe.com/gallery/albums/solar-challenger/sc126_01.jpg 93 http://www.donald monroe.com/gallery/solar-challenger/ 94 http://solar-flight.com/sunseekerII/index.ht ml 95 http://www.solarimpulse.co m/sitv/pictures.php?lang=en&group=med ia 96 http://www.kennislin k.nl/publicaties/solar-impule-v liegt-op-zonlicht 97 http://en.wikipedia.org/wiki/File:Giant_planes_comparison.svg 98 http://www.nasa.gov/centers/dryden/news/FactSheets/FS-034-DFRC.html 92 39 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Commercial use of solar planes Solar powered planes have been tested for commercial use as well. In 2002, NASA‟s Pathfinder Plus was fitted with communication relay equipment and was sent to fly at an altitude of 19 kilometres. From there it was able to send television signals back to earth, making the plane equivalent to a radio tower with a height of 19 kilometres 99 . Military purposes World-wide military organizations could also be interested in solar powered aircraft. A solar powered plane satisfies many of the needs of military organizations. It doesn‟t use any fuel, is silent because of the electric engines, can fly at high altitudes (which makes it difficult to detect on radar), can fly without refuelling, is relatively cheap compared to modern day planes and can fly unmanned so no human lives are risked. All these properties will make a solar powered plane desirable. Also, military organizations can mount a camera or measuring devices on the plane to use it for purposes like observation, an aspect o f warfare which has become more and more important the last decades. Model aviation Our solar powered plane could also inspire a whole new branch to be formed in the mode l flight industry. Right now model flight industry is mainly based on aircraft with an electric engine or a combustion engine and few planes with an electric engine charge their batteries using solar cells. After having shown flying with solar cells with a relatively small budget is possible, our plane could inspire many people around the world to build an aircraft of their own. When we posted questions on a forum asking whether other people, whom mostly had extensive experience with model aircraft, thought our project was feasible, we got numerous reactions of people asking us to let them know if and how we had succeeded, so they could try building a plane of their own. 99 http://en.wikipedia.org/wiki/ NASA_Pathfinder#Atmospheric_satellite_tests 40 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Construction Electrical system When all electrical components had been received, we made an appointment at Jesper‟s place to construct the electrical circuit and run some tests. These tests included operating the engine at full throttle to see how long the batteries would last when fully charged and some weighing of the components to see if their masses matched those of specifications. Below you will find an account of our findings during construction of the electrical system. Electri cal components Constructing the electrical system wasn‟t much of a problem, since all components included a clear manual. The construction process was straight forward as well. All components simply had to be linked together according to scheme. Then we ran the first test. Results of the endurance test can be found in the „testing‟ part of this document. After having constructed the electrical system and having done the first engine test, we had some time left. We decided to get ourselves a scale and weigh the components we already had. We wanted to achieve two things: in first place we wanted to check the mass we were given by the manufacturers of components we had received. In second place we wanted to check if our assumptions of unknown masses of components had been right. Overall the test turned out pretty dissatisfactory, with most components proving to be heavier than we thought they would be. Below you find a table showing components‟ masses. Element Engine controller Battery Servos Receiver Propeller Engine Wiring Solar cells 1 Solar cells 2 Frame Unforeseen Total First plan (grams) Actual mass (grams) 7.1 8 175.0 220 11.1 20 14.0 11 5.0 11 36.0 43 10.0 60 76.8 76.8 9.6 9.6 70.0 150 10.4 10.4 425.0 619.8 New plan (grams) 8 50 20 11 11 43 70 120 0 165 2 500 = estimated 41 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 In the second column you find data that was shown in the design proposal. It displays masses we started with during this project. The third column shows the actual masses as measured during testing. It appeared all components we measured turned out to be heavier, with batteries, frame and wiring being significantly heavier than assumed. With the total mass being over 600 grams now, we were forced to think of a new plan. This new plan was all about saving weight, since 600 grams was way above our maximum take-off weight. The easiest way to save a lot of weight was changing power source. In the beginning of the project we decided to go for NiMH-batteries, because we thought they were more reliable than LiPo-batteries. Because of disappointing results during mass testing we were forced to go for a LiPo-battery after all. The decision to use a LiPo-battery brings three drawbacks however. First of all capacity of the LiPo-battery is smaller, so we won‟t be able to run the engine for as long as we could using NiMH-batteries. A second drawback concerns the reliability 100 of the power source: LiPobatteries are prone to exploding 101 . We will have to be careful. A third drawback is the need for alternative charging equipment 102 . LiPo batteries can‟t be charged using regular chargers. They require equipment dividing power equally over the battery‟s numerous segments. Still, we decided to continue our testing with the NiMH-batteries. We would build the entire plane and then replace the battery. Once we changed the power source into a LiPo-battery, we would attempt to make the plane roll and eventually fly. In this way we keep risks of something going wrong with the LiPo battery as low as possible. We wanted a battery as light as possible, yet powerful enough to supply sufficient energy for our airplane. In the end we found the following 103 : Conrad energy LiPo Pack 7,4V/ 800 mAh/ 10C Price: €19.95 Element Mass Dimensions Capacity Voltage Plug Value 38 grams 50 × 30 ×10 mm 800 mAh 7.4V Mini Tamiya As shown, voltage of the LiPo-battery is not equal to the voltage of NiMH-batteries. Therefore we would have to alter the number of solar cells in the wings in order to get an equal voltage from both the solar cells and the battery. If we don‟t, either the battery or solar cells will blow up. 100 http://www.norfo lkhelicopterclub.co m/index.php?option=com_content&view=art icle&id =59&Itemid =66 http://www.utahflyers.org/index.php?option=com_content&task=view&id=22&Itemid=28 102 http://www.seven-segments.com/index.php?action=pageshow&id=67&idcat=44 103 http://www.conrad.nl/goto.php?artikel=229994 101 42 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Number of solar cells = 7.5 : 0.5 = 15 In total the solar cells will provide us with 7.5 volts, 0.1 volt more than the LiPo-battery. This difference will be cancelled out by the Schottky diode, which consumes approximately 0.10.2 volts. After finding out we would now need fifteen solar cells, we had to choose which type of cells we would use. We will now use big solar cells only, measuring 10 cm by 10 cm. Fifteen such solar cells would fit in our wings exactly. Still, in order to keep the centre of gravity in the correct position we would have to put seven solar cells in each wing and one solar cell in the middle of the wings. Wing construction One week after testing the electrical system we met again to start construction of the wings. First, we decided to manufacture various ribs of the wing, which had to be cut out of a board of balsa wood. Cutting demanded much Balsa wood precision and carefulness, since balsa wood is very vulnerable and thus can be broken easily. Because of this the first part of the afternoon was spent on considering options to cut ribs, e.g. cutting it with scissors, sawing it with a fretsaw or cutting it with a Stanley-knife. After some testing on leftover pieces of wood, we went for the Stanleyknife, for it proved to be easiest to cut corners. In addition it turned out to be very precise. Since we couldn‟t cut sections randomly, we needed some kind of template. We printed a model of the wing (page 12) and used it as a template. In the end we were able to construct twenty solid ribs. We then marked spots where supporting beams would have to be placed. Since we now finished the ribs and already had the front and rear cornice available, we tried to visualise the wing. When we laid down all the components of the wing we noticed straight away that all aligned perfectly. This was greatly satisfying. 43 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 That very afternoon we also had some discussion on which rear cornice to use. Originally we planned to use a cornice measuring 10 by 15 millimetres. Now, we also had a cornice available measuring 5 by 3 millimetres. Both of us were worried that when using the smaller one, contact area would be too small for gluing ribs and cornice together. Eventually we used the smaller one, but, to be able to use this cornice, we would have to make incisions in the wood in which to glue the ribs. This increased the contact area for the glue. After cutting ribs, it was time to make incisions in the correct positions. We started with holes through which we would run wiring for the solar cells and servo engine (1). This didn‟t prove to be too difficult since the holes didn‟t have to be at an exact position and could vary in size. We did decide to make only one big rectangular hole instead of the three holes shown on the picture. Main reason was that cutting such small holes with a Stanley knife is pretty difficult, while cutting straight went so smoothly that we could easily manufacture a rectangular hole. Next, we set out to construct the incisions through which the main supporting beams should run (2). Making these incisions proved to be way more difficult since more accuracy was required. All the incisions had to line up perfectly in order to make the wing straight and uncurled. We already marked places on each rib where incisions would have to be made (the red dots). We did so by lining up all ribs, locking them in a clamp and drawing a perpendicular line across the ribs using a try square. Since not all twenty ribs fitted properly in the clamp, we split the ribs in two groups, one group of nine ribs for every wing. The two ribs left were put away to be used as spare parts or test parts later. After cutting holes, we tried to fit the ribs over the supportive beams. The holes proved to be too narrow. Some filing made sure the holes became a bit wider, allowing the support beams to fit neatly. When fitting the beams, we discovered that the incisions were not deep enough. To compensate, we made small incisions in the supporting beams. This plan gave the advantage that the ribs could no longer slide over the supporting beams and we had a larger surface area to glue the parts together. Next we had to make the hole for the piston which would connect the aileron to the servo engine (3). By now we had already ordered the beam, which was made out of carbon, and we discovered its amazing low mass. It weighed so little, that it would be better to place the servo engine at the beginning of the wing, eliminating the need for relatively heavy wiring. 44 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Unfortunately the new plan demanded a hole in every rib, so again we fitted the ribs in the clamp and we drilled a hole at the right place. Again we faced a minor problem: some of the ribs fractured because the new hole required to be drilled very close to the edge of the rib. Luckily cracks were only minor, so we could fix the problem with a piece of tape. As a precaution measure, we used some tape to reinforce the unbroken ribs. Ri bs, includi ng holes When we put the beam through the newly drilled holes we discovered that there was too much friction, because the holes were too small. When neglected, this would possibly result in the servo engine not being able to turn the aileron. Again we used a file to widen the holes a bit. The only thing left to do now was think about the ribs between the ailerons. Initially we planned to cut off a part of them, but still leave the hole for the beam in place. After we saw the beam was still strong enough without the extra support, we decided to cut the ribs at the place the closing bar would be placed as shown below. This had the advantage that the ailerons could be constructed out of a single piece of wood. Ori ginal plan New plan With all ribs finished, we could start gluing the ribs to the supporting beams. This was done pretty quickly and we soon could start attaching the front cornice and rear cornice as well. 45 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 The front cornice was glued fairly easy but the rear cornice proved to be time-consuming. It turned out the ribs didn‟t align perfectly at the back, so we had to make small incisions in the rear cornice. This gave us the additional advantage that contact surface between the ribs and the rear cornice drastically increased. After we inserted the beams for the a ilerons, fabricated closing beams, and measured the ailerons, we had ourselves complete frames for the wings. Landing gear With wings completed now, we could think of how we would let the plane stand on its own. The metal frame accompanying the supplied wheels proved to be far too heavy, so we had to come up with another solution. By now we had also discovered that when only supported in the middle, the wings would bend down. We decided to build two small gears underneath the wings. They would be installed at one third of each wing. In this way the plane would be supported by wheels during taxiing and supported by its wings during flight. In both situations forces on the plane are equal and located at the same spot. Fg Fg Fg Fg Fg Fg 46 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Wing construction (2) Still, we had two separate wings. We somehow had to connect the left wing to the right wing, whilst maintaining structural integrity. We decided to cut off half of both supporting beams in order to increase surface area. We then glued together both parts and inserted pins into the beams to create both a glued and mechanical joint. This process is illustrated in the diagram below. Tail construction Construction on the tail started out with a triangular wooden beam which connects the tail section to the wings. We then manufactured the horizontal and vertical tail section by using a few sticks of balsa wood as a frame. A small rear wheel had to be attached to this beam as well. Construction was easy and fast. Sequentially, it took us a long time to figure out how we would have to control the elevator. We had to think of a way to convert the circular motion of the servo engine into the up and down motion of the elevator. Obviously we couldn‟t use the same system as we did in the wings. Not only there was no space available to mount a servo engine near the tail, but in addition, mounting the servo engine at the rear would make locating the centre of gravity even more difficult. 47 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Eventually we found out that we would need a so-called push-rod to control the elevator 104 . A push-rod is a device that links the elevator with the servo engine. It took us a while to figure out exactly how the push-rod functioned. When we had put it together, we came up with an alternative idea, which might save some weight. We could replace the push-rod with an ordinary piece of iron wire. In the end this turned out not to save any weight at all. When testing the beam connecting the tail and wings on strength, we noticed the beam gave way more than we liked. We decided to glue another triangular beam on top of the one we already used. With this final adjustment the tail had been completed. Work in progress Fuselage construction Our plane‟s fuselage is where we would put most of our electronics. Earlier on we had decided to construct a balsa wooden frame with a sheet of wood at the bottom to put all the electronics on. As we now had expertise on construction using balsa wood and balsa glue, we knew that just a few beams would be enough to carry the electronics. First however, we had to think about where we would want to put all our equipment on the wooden sheet. It involved some puzzling, because we changed batteries and several wires proved to be quite short. Secondly, we had to think about how the fuselage‟s interior would affect the centre of gravity of our plane. After all, our initial plan (see page 28) on positioning electronics had been changed drastically. We determined placing of all equipment by balancing the plane on one finger. Balancing the plane 104 http://www.airfield models.com/ informat ion_source/model_aircraft_hardware/pushrods_and_pull_pull_control s.htm 48 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 When the engine runs at full throttle, it will produce quite some thrust, which has to be transferred to the plane. To accomplish a smooth transfer, we decided to mount the engine to the plane at two points. One attachment will be connecting the engine to the main beam running from wings to tail. The other attachment will be between the engine and the sheet of balsa wood at the bottom of the fuselage. We do not want to take any risk with the LiPo battery. S ince the near engine regulator can become very hot 105 , we chose to mount it on the bottom of the wooden sheet. Here it will not be able to contact the LiPo-battery. In addition, it would be cooled by the airflow generated by the propeller. To fix the servo engine regulating the elevator to the fuselage, we had to cut a hole measuring the exact size of the servo engine in the wooden sheet of the fuselage. First we fixed the servo engine upside down to reduce drag, but later Servo in the wing we chose to mount it straight, since it would then be easier to fit the push-rod. With this servo engine in place, we looked at how to mount the other two servo engines into the wings. Unfortunately screws available were too short. Therefore we filed a hole in the first rib of the wing, just large enough to squeeze through the heads of the servo engines. Finally we fixed the servo engines into position using glue and new screws. Mylar foil The plane‟s frame had been completed now. Next steps would consist of putting solar cells in place and wrapping the wings and tail with Mylar foil. Since Mylar foil was delivered much earlier than the solar cells, we decided to cover the tail with Mylar foil first. This section of the aircraft is relatively minor. It was perfect for us to get used to working with Mylar. We were informed one should apply glue to the ribs and then wrap Mylar around the frame106 . So we did. By heating the Mylar foil, it was supposed to shrink and wrap itself tight around the frame. First, we attempted to heat the foil using a hairdryer, but this turned out to not be hot enough. Though we had read one should use an iron to heat the Mylar foil, we tried the hairdryer first, since we didn‟t want to damage the Mylar foil. Ultimately we went for the iron, but we decided to keep some space between the iron and the foil. Even this didn‟t work out. We finally discovered what really to do. Jesper touched the foil with the iron. Instantly the foil shrank. We put the iron on the lowest temperature and ironed the foil with it. Using this technique, we managed to cover the vertical and horizontal tail section with Mylar foil. 105 106 http://www.rctechnics.eu/download/MAN-HM-FLY.pdf http://www.modelbouwforu m.n l/foru ms/verlijming-constructie/44864-my lar-folie-hoe-verwerk-je-dat.ht ml 49 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Ironing Myla r Before (ri ght) and after i roning (left) After this, we could mount the rudder itself. We glued two small wooden segments onto the aft of the elevator to support the rudder‟s axle. We did have to solve one small problem, since the tail had deformed slightly under the force of the Mylar foil and was now slightly bent. With the rudder positioned, we could install the push-rod to attach the servo engine to the elevator rudder. At the aft we had some trouble mounting the push-rod to the rudder. Moreover, cutting the push-rod at the right length was extremely difficult. This proved to be a time-consuming job. Fi nal resul t Link between eleva tor and push-rod Solar cells Up so far we seemed to be able to keep to our tight planning. Then we hit a major delay concerning the solar cells. Due to holidays in Germany, they were delivered three weeks late. Once delivered, we immediately wanted to join all solar cells together. We went about by soldering them using the soldering strips. This wasn‟t done however before we tested a solar cell‟s output by using a multimeter. This test really satisfied us, since the solar cell proved to provide us with an even higher voltage than expected (0.6 volts instead of 0.5 volts). Although the electric current may still vary, this reading could be considered a good sign. Another positive finding was that the solar cells turned out to be as heavy as specifications told us. We were yet another step closer to achieving our goals. 50 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Whilst trying to solder the solar cells, we stumbled upon some problems. It appeared the solar cells couldn‟t be soldered. At first we assumed our old soldering equipment was to blame. Then, after using state of the art soldering equipment offered by Computer Services Alphen, we were still puzzled by unconnected solar cells. It turned out ordinary solder tin was not suitable for soldering solar cells. We would need soldering tin containing silver. We had nearly bought this expensive substance, when an expert on soldering noted that the strips on the solar cells had probably been chromed, which implied that they couldn‟t be soldered at all. Not only did these events consume considerable amounts of time, also this setback meant we would have to resort to more primitive methods when connecting the solar cells. We figured out that the easiest way to link all solar cells would be to place wires between the cells and tape the wires to the cells using duct tape. Before we could do this however, we had to glue the solar cells to the two supporting beams. Otherwise they would come off when sticking tape on them. Drilling new holes The wires demanded new holes in the ribs, which we drilled between the front cornice and the first supporting beam. Wiring all the cells demanded great care since the cells proved to be extremely fragile. Another setback occurred when we discovered our wiring was so stiff, it would rip itself off the solar cells. Luckily we still had servo extension cables left, as we had replaced wiring by carbon beams. Those cables were much more flexible, thus perfectly suiting our demands. The new wi ring When we tested all cells after they were connected, we found out the circuit wasn‟t complete. One cell had cracked and thus disconnected the circuit. We solved this by taking the tape and the wire off the cell and attaching the wire to the solar cell again behind the crack. When all solar cells were tested outside, we found out that the fifteen solar cells produced eight volts, 0.5V more than we expected. Last thing we had to do concerning the electric circuit was to include the Schottky diode in the circuit. Figuring out which way to mount the diode took some time, since our multimeter didn‟t function properly. After soldering the diode into our circuit, the last thing we had to do was to wrap the diode in duct tape, so our circuit wouldn‟t shortcut when the diode touched one of the solar cells. All cells in pla ce 5151 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Mylar foil (2) With all solar cells and the diode in place, we could finish the wings by wrapping them with Mylar foil. Because of the experiences we had while applying Mylar to the tail section, this was done quickly. However, we couldn‟t apply Mylar foil to the wings in one go. First we had to cover the wing sections at which the ailerons are located, because we could only mount the aileron itself after these sections had been covered. We had to choose whether we would literally wrap the Mylar foil around the wings or apply two big strips of Mylar foil, one for the top and one for the bottom half. Eventually we decided to wrap the wings at the ailerons sections and to cover the rest of the wings in two parts. After we had applied the foil, we heated it with the iron to let it shrink. Something concerning we noticed, was that the shape of the wing altered when we ironed the segments in front of the ailerons. Because of the shrinking foil, wrapping around the aileron‟s closing beam too tight, the wing had become a little dented. Luckily the ironing didn‟t affect the shape of the rest of the wing. Finishing off Finishing off consisted of mounting the wings to the fuselage to create one completed aircraft. The joint between fuselage and wings is the plane‟s most important joint, since it deals with the greatest forces in the aircraft. Before we could mount the wings to the fuselage however, we had to determine the centre of gravity for both wings and tail. This was done by balancing the fuselage on our fingers. We knew the wings had to be placed on the fuselage at one third of their chord. Next we had to check whether in fact it was possible to mount the wing at this position. It turned out not to be possible to mount the wing in the desired spot, since wiring for the servo engines would be too short to reach the receiver. To fix this problem we positioned the receiver slightly to the back and moved the wings one centimetre forward to make sure the servo engines‟ wiring would reach the receiver. This action would not be harmful for the plane‟s centre of gravity, for we could still alter the centre of gravity a little by positioning the wheels in the proper place. 52 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Once position of the wings on the fuselage had been dec ided, we prepared to fix the wings in place. First we had to file minor segments out of the fuselage to make sure contact area between the wings and the fuselage would be as big as possible. Next, we turned the wings upside down and laid them on the table, so we could glue the fuselage onto the wings. We applied a good amount of glue to both segments. Still, in order to provide extra strength to the joint, we wrapped around duct tape as well. Finally we went to mounting the wheels. We had already decided we would place the wheels at some distance from each other. In the end we placed the wheels under the fourth rib of each wing. Because the wings had been covered in Mylar foil by now, we would have to glue the wheels onto the foil and reinforce them by sticking pins into the wood. However, we still found the wheels to be unstable, so we mounted them with an extra supporting beam to prevent them from wobbling forwards and backwards. With these reinforcements in place, we lifted the airplane and put it on the ground, where it proudly stood on its own wheels, finally finished. Most important, the plane‟s final mass was 487 grams!! Wi thout reinforcements Wi th reinforce ments Our plane when suspended 53 Test results Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Electrical system testing During a first test on the electrical system we investigated how long the batteries could keep the engine running at full throttle. This was the first part of a series of tests in which we wanted to investigate the difference between using and not using solar cells as an additional power source. During the second test, we would redo the first test but with solar cells included. Comparing both runs would give us an indication of the extra flying time the solar cells provided. Our first test didn‟t run as smooth as we had hoped for, since the engine shut down abruptly several times. This was caused by not tightening all wiring very securely due to the test setting being temporally. Although we had mounted the engine secure ly to a wooden board, a wire disconnected once in a while. Now and then the engine shut off. After reconnecting the wiring we were able to continue testing. In the end we found out that using battery supplies only, the engine could run for about 15 minutes. At this point we still used NiMH-batteries, so when we would repeat the test with solar cells, we would have to use NiMH-batteries as well. Unfortunately we hadn‟t received the solar cells yet, so we weren‟t able to run the test with solar cells immediately. When we had finally received the solar cells, we found that we could run the test in an alternative way as well. Earlier on, we had calculated that the engine would consume about 42 watts of power and that the solar cells would produce 21 watts of power under ideal circumstances. We had also found our solar cells‟ output was 8 volts under reasonably sunny conditions. The only thing left now was to determine the electric currents produced by the solar cells. This was done by completing the circuit with the solar cells by inserting a small light bulb between the wires of the solar cells and measuring the current that went through it. The current turned out to be only 0.3 Amps in sunny autumn conditions. This meant: Power of solar cells = 8V × 0.3A = 2.4W Using another calculation, we could now find out how much the solar cells would contribute to the total power supply. First we needed to measure the engine‟s power consumption. We presume that during flight the engine will run at about 75%, which means that the current is 3.5 Amps, as shown in the table. Engine speed No load current 25% 50% 75% 100% Current (Amps) 0.166 0.513 1.2 3.5 6 Amount of energy supplied by solar cells = 0.3A :3.5A × 100% = 8.6% 54 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 This value is way under what we had estimated, since we had expected that under ideal circumstances solar cells would account for 50% of the total energy supply. Still, this setback didn‟t mean the end of our project. We can still charge batteries using the solar cells when the plane is on the ground and the solar cells can provide a little extra power during flight. With the data we gathered, we can also calculate how long it will take to recharge the batteries using solar energy under reasonably sunny circumstances: Time to charge = capacity of battery : current of solar cells = 800 mAh : 300 mA = 2.67 hours = 2 hours and 40 minutes. Charging the batteries for 2 hours and 40 minutes will fully load them and will allow us to fly for about a quarter of an hour. This is shown through the following calculation: Flight time= capacity battery : energy consumption= 800 mAh : 3500mA= 0.228 hours = 14 minutes This would mean that we could fly for about 14 minutes. When we take the solar cells into account, which we had found out to generate 300 mA, the calculation for the flying time is as follows: Flying time= capacity battery : energy consumption= 800 mAh : (3500-300)mA= 0.25 hours = 15 minutes Extent flying time = (0.25-0.228) : 0.228 × 100% = 9.6% Our flight time has been prolonged with 1.2 minutes, which is an extension of 9.6% Lift test After testing the electrical system, it was time for a lift test. Initially we had thought of a construction to place one wing in a K‟nex frame and cycle with it. However, when we manufactured the wings, we decided to construct the wing segment as a whole. This meant we had already connected the wings when we installed the solar cells and applied the Mylar foil. Because of the fragility of the wings it was irresponsible to carry out the initial plan. We were forced to think of a new plan. We decided to finish the entire plane before performing the lift test. Because we would now be testing with the complete and extremely fragile aircraft, we had to come up with a new setup for testing. Since we didn‟t want to test lift with a moving plane we needed to perform the test with the plane standing still. This implied we would have to blow air over the wings. We thought of several options, such as placing the airplane on a big wooden board which would be placed on scales and then positioning fans in front of the aircraft. When turning on the fans, we should see a decrease in weight indicated by the scales. Another option was to hang a force meter from the ceiling and then hang the board under the force meter. The force meter should show a drop in reading when the fans would be turned on. In the end however, we did decide to use the force meter, but we made the plane hang underneath a wooden stick attached to the force meter instead (see picture on following page) 55 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 We lifted the plane with four belts wrapped around the wing and the wooden stick. This would make sure no unnecessary forces worked on the plane as it hovered. A last thing to think of was to make sure the plane wouldn‟t start swinging once the fans were turned on. We resolved this by fixing a small piece of wire to a hole in the nose cone. We still needed to arrange fans. We were told our school possessed two big fans. When testing the fans however, we discovered that maximal wind speed they could produce was six metres per second, or 21.6 kilometres an hour. This was short of our take off speed, which is over eight metres per second. Still, at these wind speeds we should already see some lift. When setup was finally complete, we could start testing. First results were disappointing. At a fairly low wind speed (about two metres per second) the wings didn‟t seem to provide any lift. This confirms calculations on the Reynolds number (see page 15). Then we increased wind speed (the fans turned out to accelerate the air to four metres per second at full power), which showed some results. In total the wings generated about 0.4 N of lift, nowhere near the 5 N of lift we need. However, when we tilted the aircraft to 15° (maximal angle of attack) we found the wings already generated 1.2 N of lift. These results were promising, since we found out that not every part of the wings had wind blowing over it. The fans didn‟t have a range large enough. In addition, the suspension cables covered several inches of wing. This implied we were only able to use 60% of the wing. Furthermore, we had assumed the plane‟s speed would be higher at take-off. In fact, we calculated the speed of our plane would be twice as high as the wind speed produced by the fans. This would mean that the lift of our wings would be four times as high, since the variable „speed‟ has a quadratic influence in the lift formula. 1.2 N × 4 = 4.8 N 0.4 N × 4 = 0.8 N 4.8 : 60% × 100 = 8 N (at 15°) 0.8 : 60% × 100 = 1.3 N (at 0°) After this test we may conclude that our wings should be able to generate e nough lift to let the plane fly. Only, the angle of attack needs to be bigger than expected. This could be due to the shape of the wing not being perfectly according to plan, as explained on page 52. 56 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Drive test After the successful lift test, we went on to the next test: driving. The first part consisted of making sure all controls worked properly and making sure the plane would be remotely controllable. The test was performed at school, where we showed the plane to our supervisor and other interested people. However, we couldn‟t perform the actual driving test yet since we had discovered a problem. Because the wheels were placed some distance from each other, the middle part of the airplane had slightly dropped, which meant there was very little clearance between the propeller and the ground. If we would drive at such a speed that the tail would lift off, we would risk the propeller hitting the ground, possible destroying the propeller and the aircraft itself. It was clear an adjustment would have to be made, which we did by installing a third wheel in the middle of the plane to support the fuselage. This adjustment meant that the propeller now had a clearance of about a centimetre. In addition, the third wheel was placed slightly to the front, so risk of the plane toppling over was largely eliminated. Putting the plane on the ground had shown however that the wheels were prone to movement to the left or right. This problem was overcome by placing reinforcing beams to the wheels. The supporting wheel With all the problems concerning the landing gear now sorted out, we could perform the drive test. We had managed to find a fully flat floor, namely the floor of the school‟s auditorium. This room was large enough to drive the plane without the risk of crashing and was long enough to drive in a straight line. During the test we stumbled on some more problems though. It turned out that our plane didn‟t drive in a straight line. The cause was quickly found. Friction in each wheel had to be exactly equal in order to let the plane drive in a straight line. This friction could be adjusted by tightening or loosening the nuts that held the wheels. It resulted in another problem though. Tightening the wheels too much would make friction too big to let the plane drive. Loosening the nuts too much in order to decrease friction, resulted in the nuts coming off because of the vibrations caused by the engine. Whenever the nuts came off, so did the wheels. This sent our plane spinning several times. When we had found the right setup, it was time to perform the driving test. It was an absolute success. With the engine not even at full throttle, we could see the tail coming off the ground, a first indication of the plane taking off. Luckily, we were able to catch this moment on camera (see page 65). 57 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Flight test With the first three tests now completed and all results suggesting that our plane is capable to fly, it was time to get airborne. Weather conditions made us postpone the maiden flight several times. Eventually, on the 3rd of March 2010, flight JET001 was ready for take-off. After having made some adjustments on the wheels and doing some checks on controls, we hit our last problem. One of the ailerons malfunctioned, probably due to a fractured joint between its axle and the servo engine. We had to keep this aileron in place through tape. Steering the aircraft could only be done now using the sole remaining aileron. We gently opened throttle, made the airplane role and then opened throttle fully. Within seven metres the plane took to the skies, reaching an approximate altitude of six metres. Then the nose pitched up, the aircraft stalled and crashed just moments after take-off. Initially we were greatly satisfied. Our hard work had paid off, our calculations, predictions and constructions had been correct. Later we started wondering why the aircraft stalled so quickly. There were two possibilities: either the plane‟s centre of gravity had been shifted too much to the back or the plane was steered into a stall position. It appeared we are to blame for the aircraft‟s crash. In order to not let the propeller hit the athletics track used as a runway, we ordered the rudder to push the plane‟s nose up as much as could be. Being so excited by the plane actually taking off, we forgot to move the rudder into neutral. The plane steered itself into stall position. Disaster was inevitable. Another noticeable fact was the aircraft taking off so quickly. It had not yet reached a speed anywhere near the 8.3 metres per second required. When looking at the formula for lift, this situation can easily be explained: L = ½ × c ×  × A × v2 58 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Analysis showed the angle of attack was about twelve degrees at take-off, whereas in our calculations we had assumed it would be one degree. At twelve degrees the lift coefficient is 1.12, compared to 0.36 at one degree. In addition, when taking off, head wind speed was approximately two Beaufort, which corresponds to 1.7 metres per second. This results in: Take-off speed = √(½-1 × 1.12-1 × 1.23-1 × 0.32-1 × 4.88) – 1.7m/s = 3.0 m /s Off course the Reynolds formula (page 15) predicted we cannot fly at speeds lower than 3.8 metres per second. It should be noted that the velocity mentioned above is the ground speed. The airspeed is the plane‟s groundspeed, plus its headwind. For our take-off situation this would be 4.7 metres per second. That would perfectly be possible according to the Reynolds formula. The noticeable difference in angle of attack therefore explains why our plane took to the skies so quickly. Moreover, the angle of attack might have been even higher than the angle used in calculations. Namely, the angle of attack is said to be zero degrees in the following situation107 We assumed zero degrees would be the following situation. This would imply the values used for the angle of attack in all our previous calculations were too low, which would confirm an ever lower take off speed. In the end, the low flying speed and high angle of attack turned into a devastating stall and crash. Luckily damage was only minor and mostly concerned the landing gear. Most important after all: our solar powered plane had taken off. 107 http://marlongofast.tripod.com/zipped_aeronotes/clarky.ht m 59 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Conclusion It is now time to draw conclusions. Extensive tests and respective calculations showed our model aircraft is capable of flying, even partly solar powered. Tests also showed the wings are capable of producing the desired amount of lift. Furthermore, observations showed the engine is capable of propelling the aircraft to take-off speed. Most satisfying of course was the moment when the plane truly took off. One conclusion we can draw is that purely solar powered flight is impossible. In theory the maximum power our solar cells can produce is 21 watts, nowhere near the 40 watts required. Unfortunately our solar cells produced far less than the 21 watts they were meant to produce. Main reason for this is Dutch climate. Moreover, difficulties in connecting the solar cells contributed to power loss as well. Therefore flying on solar cells only is not possible. At the most, solar cells will lengthen flight with 10%. When used as a charger for the battery, it will take the cells two hours and forty minutes to fully load the battery. Maybe in future solar cells‟ efficiency will be higher. For now, technology is not advanced enough. A second conclusion concerns the weight aspect. With the solar cells already having a mass of 120 grams, it was extremely difficult to not exceed our target mass of 500 grams. Current solar cells have a power to weight ratio far too low. In order to fit the number of solar cells required, we were forced to cut weight on many other elements. In the end, we managed to create a plane weighing in at 487 grams, but the aircraft was extremely fragile. A third conclusion is that it is impossible to fly a solar powered plane using NiMH-batteries. This power source proves to be too heavy. The current battery pack in our airplane, a LiPo battery, weighs about 40 grams, whereas the original NiMH-battery pack weighed 225 grams. That is nearly half the mass of the entire plane! Even though LiPo batteries bring considerable risks with them, it still is the best option for our aircraft. One simply needs to be very careful when handling the plane. A fourth conclusion is that our methods of testing worked well and our calculations and expectations have been correct. Especially the lift test gave results we expected. Although the angle of attack needed to be bigger than expected, the wings still generated enough lift. This confirms formulas we used have been both correct and accurate. Moreover, provided data has been correct. Also we constructed the wings in a proper way. Therefore tests results were satisfying. The most satisfying test was of course when the aircraft truly took off. Cheer went up as we realised our assumptions, calculations, measurements and constructions had been correct. But most satisfying after all was that the plane took off completely balanced. Analysis showed the aircraft took to the skies at a far lower speed than expected due to factors like wind and the angle of attack. Sadly the aircraft‟s fragile frame didn‟t fully survive the crash landing. A final conclusion we can draw is that even though they can‟t be used to entirely power aircraft, solar cells are a serious option when trying to extend flight times of airplanes. As we have seen, solar cells can keep our plane in the air for a nine percent longer period of time. 60 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 However, we can pose the question whether the weight savings following the exclusion of solar cells wouldn‟t have had the same effect, since the plane would have been much lighter without solar cells. In future projects further research could be done on this topic. Last of all it should be noted that this version of our model aircraft is only the first version to be built. This project has, more than anything, learned us a lot about building model aircraft and has provided us with valuable experiences to use in future projects. 61 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Evaluation Our research project has provided us with numerous experiences and insights to be used later when constructing a better, second version of our plane. Our experiences and insights include knowledge about what materials we should have used, what should be done differently and which parts of the plane we could have upgraded. What should be done different, what didn’t go as well as could be? Weight savings Mass of our aircraft has been a key factor in the project. Put simply, we have been trying to save weight on every part of the plane. In the end, we have been pretty successful in doing so, but there are some aspects of the plane on which more weight could have been saved. First of all, we could have saved quite some weight on the two supporting beams in each wing. Initially we decided on using triplex beams as girders. While constructing the wings, now being familiar with the strength of balsa wood, we decided to use balsa wooden beams instead. They saved us relatively much weight, while proving to be strong enough as well. When connecting the ailerons to the servo using a carbon beam, we found out that we should have used yet another type of material instead. We could use these carbon beams to replace the supporting balsa beams, as they are as strong as balsa beams, but weigh half as much. The carbon rods can also solve another problem concerning the wings. Since the balsa beams were not long enough to run over the full length of the wings, we were forced to build each wing individually and then glue the both of them together. The joint between the two wings proved to be a very fragile one. Using two long carbon rods will eliminate the need of making a joint at all. Talking of the frame, we have to note that a more realistic estimation of masses should be made at the start of the project. In the beginning we didn‟t exactly know what the mass of balsa wood was. We estimated the frame would eventually weigh 70 grams. When the plane was finished though, we ended up with a frame weighing nearly 160 grams. The frame wasn‟t the only part of the plane that was heavier than expected. Numerous components, such as the engine, batteries, propeller, engine controller, servo engines and wiring turned out to be heavier than expected or promised. In future projects we should be more pessimistic about components‟ masses, which would result in solely positive findings rather than mostly negative findings. Structural improvement Because we did our utmost best to save weight, we might have pushed it a bit too far on some aspects of the plane. This affected the strength of the plane. During lift test we noticed that our tail looks pretty fragile, especially at high wind speeds. The rudder does seem to function, but the tail section can only be described as wobbly. The connection we made between tail section and wing is a bit too weak. 62 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 A second structural improvement is the landing gear. During the design of the plane we hardly spent any attention on the landing gear. This proved at the end of the construct ion phase, when we were faced with the problem of what to do with the landing gear. We managed to construct a suitable landing gear but it wasn‟t actually up to its job. This was demonstrated when our plane crashed during its test flight. After the crash most damage was done to the landing gear. Besides, we suffered a minor lapse in concentration whilst mounting the wheels. This resulted in us placing one wheel slightly more forward than another. It shouldn‟t be a real problem, but as mentioned before, our plane tends to drive in a curve. The placing of the wheels might have to do with this. Second of all, suspension of the wheels could have been more secure. Because we didn‟t have enough nuts and bolts at our disposal, we mounted two wheels using pins. This resulted in the wheels getting into a tilted position easily, thus creating more friction. Using bolts of the right dimension on every wheel would have increased the stability of our plane and would have reduced friction. A third improvement involving the landing gear is making sure distance between wheels and suspension is wide enough. Currently we put a piece of balsa wood between the wheel and the supportive structure. The wooden parts separate the wheels from their suspension, but dramatically increase friction. Instead, we could have used some of the tubing left over from the push-rod to maintain distance between wheels and supporting structure. This would have resulted in significantly lower drag and increased stability. A last improvement to the wheels, is to make the wheel supports higher, in order to give the plane a bigger ground clearance. This would eliminate the need to construct a third wheel (thus adding extra mass and friction) and would make it safer to drive the plane. A final structural improvement has to do with materials available. As we had to build the plane all by ourselves and in our own house, we didn‟t have every material and tool at our disposal. Because of this we had to resort to using pins and other „primitive‟ materials. If we would have had more materials available, we might have been able to manufacture a more rigid aircraft. Solar cell improvements Our plane‟s solar cells can also be improved in several ways. When doing our project, we discovered how fragile solar cells are. Unfortunately we learned by failure. During our project several pieces of solar cell cracked, due to too much pressure being exerted on the cells. This might have resulted in the cells supplying a far lower current than the 3300 mA they should have provided according to specifications. Solar cells we used simply were too fragile. Next time we should consider using a different type of solar cell. The high-performance cells we used are originally designed to be placed on cars or in glass solar panels; places where they would have had support all over. We just had two supporting beams. This resulted in a serious amount of pressure being exerted on the cells. In future we could use solar which are more flexible and fracture less easily. Currently those cells are not available. 63 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 A second method to provide more support for the solar cells is to simply add more supporting balsa wood or use a different construction material. Some model planes are built using a sort of polystyrene foam to fill up spaces between the wooden frame. In future projects this method should be used. It will allow the solar cells to be laid onto the foam. Another proposal is using a different airfoil. The wings should have a flat rear on which to put the solar cells. A second improvement of our solar cells is the connection between them. We faced problems with soldering and had to resort to connecting solar cells with ordinary tape and wire. This wire seems to disconnect occasionally, thus stopping the electrical circuit. Tape blocks some of the precious sunlight as well. Next time we should go for soldering strips Lemo Solar offers. This will result in better connections between cells. Cost savings Another aspect of the project we could have improved on, was the cost aspect. After the project we still had numerous materials left we hadn‟t used at all. Not all balsa wood we bought was used for example. The final costs of this project are: Element Balsa Glue Engine controller Propeller Shipping costs Battery holder Landing gear LiPo battery LiPo balancer Diode Belts for testing Costs (€) 41.09 10.16 16.95 3.35 54.96 3.50 22.95 19.99 12.99 1.12 4.95 TOTAL 515.00 Element Battery (NiMH) Receiver Servos Wiring Engine Remote control Switch LiPo charger Solar cells Mylar Pushrod Costs (€) 8.95 13.50 30.00 7.80 14.50 59.00 5.95 29.99 135.00 6.00 12.30 Parts that cost a lot were accessories for the LiPo-battery. Initially we planned on using a battery balancer when charging the LiPo-battery, but when the battery was charged, we found out it either didn‟t work or was unnecessary. Charging can be done without a balancer, although it drastically shortens the battery‟s life expectancy. Another part we didn‟t use was the adapter, which would transform the 230V mains into 12V. When we received the adapter however, it turned out 230V mains was not transformed into 12 volts, but into 8 volts. We had to send back the adapter and resort to using a car battery charger. Although we did get our money back, we had to pay shipping costs. The remote control and receiver also gave us some problems. We wanted to order a separate controller and receiver, but when the receiver had been delivered, we discovered we would need a crystal to place in the controller and receiver. It turned out the easiest way of getting a pair of crystals was to order a set containing a controller, a receiver and a pair of crystals. This left our initial receiver unused. 64 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Another financial improvement is the shipping costs. During the project we ordered materials from several companies in several stages. Of course we intended to order all materials at the same time, thus having to pay only once. However, as we needed several unforeseen parts such as the LiPo battery, ordering was done in several stages. We can save quite some money on shipping costs next time, as we now know which elements are really needed. Test improvements Last part of our research project that could be improved, is testing. Improvement mainly lies in the lift test. We went about it as well as we could, but still it wasn‟t a very professional setup. It would have been better if we had been able to test the plane in a wind tunnel, using a device producing smoke, so we could take a look at the airflow. However, we didn‟t have a wind tunnel at our disposal and arranging one would have been very expensive. Or so we thought. Thinking „it is always worth a try‟, we sent an e-mail to the faculty of Aerospace Engineering at the TU Delft in which we presented our finished Solar Challenger. In the e-mail we requested using one of the faculty‟s wind tunnels. A bit to our own amazement the faculty replied by stating that „the use of the wind tunnels for these purposes can rarely be accepted. However, since our project looked very complete and we even had a complete prototype, the faculty was happy to make an exception for us‟. Because our Solar Challenger would need to be tested in the biggest wind tunnel, which has a full schedule until July, we‟ll have to wait some more time to perform this test. This will give us the opportunity to fix the plane after the crash during the test flight. A second improvement for testing, is the time of the year. As this project was finished in October, we had to deal with Dutch autumn weather during testing. This especially affected the test concerning the solar cells‟ output, because the angle of the sun‟s rays in autumn differs from the angel in summer and the sun‟s rays aren‟t as intense either. For this reason we can‟t say for sure what the solar cells‟ maximum output is. Besides, recharging the battery in summer will take less time than recharging during autumn. Another improvement to be made when measuring the cells‟ output, is to have a light meter available. Using such a device enables us to draw a graph about voltage and current produced by the solar cells under various light intensities. Right now we can only describe weather as „sunny‟, „cloudy‟ or „reasonably sunny‟. Camera data A last setback we encountered during test phase had to do with our camera footage. We filmed all tests we ran, including the plane‟s driving test. Video footage would have enabled us to show fragments of video in our presentation. Furthermore it contains the evidence of the existence of our plane in case something bad happens to it. However, even though we explicitly requested the TOA to put the video on computer immediately, it didn‟t happen. When we returned after bringing home the plane, we discovered video recordings were lost. They were erased by accident. 65 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 What we nt well? We have seen quite some elements to improve during our research project. On the other hand we also came across several techniques and designs which we think should definitely be repeated in future projects. Mylar foil One of the absolute successes of this project, is the use of Mylar foil. When we received the roll of foil, we thought we could have used kitchen foil as well. It was only when we applied the foil when surprise came in. We were especially shocked when Mylar foil turned out to shrink so well when being heated by an iron. Mylar foil is one of the key factors in the success of the project. Wing shape Another good design used in our project, is the airfoil. Our choice to use a „Clark-Y‟ wing profile has been a very good one, for numerous reasons. First of all, the ribs of the wing were relatively easy to construct when compared to other airfoils. Second of all, the ribs connected well to the front and rear cornice and proved to be strong. Our wing frame together with the Mylar foil has proven to generate enough lift, thus sending our plane skywards. Engine & propeller The choice for an engine was a very difficult one, especially due to so many types being available. This choice we made turned out to be a very good one. The engine fits nicely in the frame, the propeller has the correct ratio with the frame and the engine doesn‟t consume too much power. More importantly though, the engine is capable of propelling our aircraft to high speeds. Controls & steering Controls are one of the most crucial aspects of the plane, since the plane is helpless without them. After extensive research, a suitable receiver and remote controller had been found. Both function properly. We haven‟t tested yet what the maximum distance between the remote controller and the receiver can be, but it certainly is more than 100 metres. The servo engines turn out to function properly as well. We had some small concerns about the servo engines‟ torque, but it turned out all servo engines are capable of tilting the ailerons and elevator. One small drawback is that one of the ailerons slightly drops once in a while due to gravitational forces. Luckily this can be corrected easily. Using carbon rods is a very good way of connecting servo engines with ailerons and is a good way to save weight. Also the push-rod is a good solution to control the rudder. Although installing is quite tricky, it works well. Moreover, the push-rod looks professional. Last of all, the engine controller we used also functioned properly. We haven‟t had any problems dealing with heat production or too high currents going through. 66 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Our opinion The past months, especially the past weeks, we have been working intensely on this project. It has been a great challenge to us. Setbacks occurred on a daily basis and delays were unavoidable. Still, we eventually managed to attain our goals. This project has, more than anything, taught us lots about building model aircraft and provided us with valuable experiences to use in future projects. We didn‟t construct a €500.plane, we gathered €500.- of knowledge and we are very satisfied with all results. Last of all, this project has been an absolute success. Not only has it been great fun building the plane, the reactions to the project have been overwhelming and Solar Challenger even managed to pick up a prestigious price at our school. The whole project was a great experience but of course, there was one moment that stood out specifically: the airplane taking off. It was simply breathtaking. 67 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Additional sources Report writing: http://www.ruf.rice.edu/~bioslabs/tools/report/reportform.html Research project discussion on fuel savings for commercial aircraft, including on solar panels http://www.wetenschapsforum.nl/index.php?showtopic=94691&pid=466140&st=0& Solar powered model aircraft built by students from Puerto Rico: http://www.youtube.com/watch?v=uzu2Y2kbPZw&feature=related http://ceic.pupr.edu/html/Capstone/HybridWings/index.html Students attempting to build a solar powered model aircraft as a research project: http://www.modelbouwforum.nl/forums/electro-vliegtuigen/66600-modelvliegtuig-opzonnecellen-pws.html Building the frame of a model airplane: http://anjo.com/rc/aircraft/elder/ http://www.airfieldmodels.com/information_source/how_to_articles_for_model_builders/con struction/wing_construction/index.htm http://picasaweb.google.com/jaspapens/Charter#5154316415791691170 http://plans.rcmodell.hu/planelect.html About model flying: http://www.mvccrash.nl/overons/00000097940bbf72d/ Forum: http://www.circuitsonline.net/forum/view/66253 http://www.modelbouwforum.nl/forums/accu-laad-techniek/69411-batterij- laden-dmvzonnecellen-2.html Technical tips: www.amcor-modelbouw.nl 68 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Acknowledgements Solar Challenger was a success. Still, completing our project would not have been possible without the efforts, support and help of the following people, companies and organizations:            F. Hidden, our advisor. Though he was quite skeptical about feasibility of our project, he approved with our ideas and plans. His critical thinking and expertise prevented us from making unnecessary mistakes and taking inaccurate steps. R.J.W. Haverkamp, Jesper‟s father. He provided us with all equipment we needed for construction. This included tools and several instruments. P.A. van Leeuwen, Tim‟s father. He helped through critical think ing and cooperation. His tips and hints appeared to be pretty constructive. Moreover, ordering components abroad would not have been possible without his credit card. I.M. Prange and L.C. van Staveren, Jesper‟s and Tim‟s mothers. They were willing to transport our fragile plane to and from testing locations. In addition they supported other logistics and finances. R. van der Laan, for providing us with his LiPo battery charger and safety equipment. Lemo Solar, a German supplier of electronics. They gave us €24 discount on the solar cells. Athletics Club Startbaan, whose track was available as a runway for our plane. TU Delft, for the usage of the lay out and style as far as the report and presentations are concerned. Computer Services Alphen aan de Rijn, for using all of their soldering equipment. A.Ch. van Steen, for donating €15 to stimulate progress and development of our solar powered plane. All people from Modelbouwforum.nl and circuitsonline.net, for all their useful tips. 69 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Jesper‟s log Day Date Wednesday 01-04-09 Thurs day 02-04-09 Friday 03-04-09 Saturday 04-04-09 Sunday 05-04-09 Wednesday 08-04-09 Thurs day 09-04-09 Friday 10-04-09 Sunday Wednesday Saturday Wednesday Monday 12-04-09 15-04-09 18-04-09 22-04-09 27-04-09 Wednesday 29-04-09 Sunday 17-05-09 Wednesday Tuesday Thurs day 10-06-09 16-06-09 18-06-09 Start time 17:00 19:00 10:15 17:00 19:00 11:30 10:45 11:35 16:00 18:30 13:55 End time 18:00 21:00 11:15 18:00 21:00 11:45 11:30 11:50 18:00 19:30 14:10 Total time 1 2 1 1 2 0.25 0.75 0.25 2 1 0.25 18:15 10:00 12:00 17:00 14:00 19:00 17:00 19:00 18:45 10:30 13:00 17:15 15:30 20:00 18:00 21:45 0.5 0.5 1 0.25 1.5 1 1 2.75 8:45 17:30 9:00 13:30 16:00 13:30 10:00 13:00 10:00 14:00 14:00 17:00 13:30 10:30 11:45 9:15 18:00 11:00 15:30 19:00 16:00 12:00 16:00 12:00 16:00 15:30 18:00 15:30 11:00 12:45 0.5 0.5 2 2 3 2.5 2 3 2 2 1.5 1 2 0.5 1 Description Orientation on subject (websites universities, forum, etc.) Orientation on subject (decision: solar challenger) Discussion about subject (decision on solar challenger) Information on feasibility (engine, solar panels) Information on feasibility (propeller, balsa wood) Discussion with Mr. Hidden Looking up information on costs (solar panels, engine) Discussion about subject (time, costs, size) Possibilities of electrical system (servo, battery, engine) Possibilities for construction (wood, glue, foil) Consultation on possibilities (Who will do what? Jesper: wing construction, loading batteries. Tim: Wireless system, servo engines) Possibilities of the wing (construction of frame, foil) Take a closer look at wing design (Clark Y) Take a closer look at electrical system (batteries) Determine planning and research questions Discuss electrical system (also on forum) Read tips on forum and execute them Found new engine and parts Made a list of electrical equipment, made a list of requirements Drawing a scheme of electrical system Writing on documentation Update website Start research proposal Determine airfoil Work on research proposal Work on research proposal Work on research proposal Work on website Work on research proposal Work on research proposal Work on research proposal Work on research proposal Work on research proposal Work on research proposal 70 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Monday Wednesday 22-06-09 24-06-09 09-07-09 18-07-09 10:30 10:30 18:45 8:30 10:30 20:30 15:00 11:00 13:00 19:15 9:45 13:00 22:00 18:00 0.5 2.5 0.5 1.25 2.5 1.5 3 Thurs day 25-06-09 Thurs day Sunday Tuesday 21-07-09 14:15 17:45 3.5 Thurs day Friday 23-07-09 24-07-09 15:00 10:15 11:00 16:30 10:45 13:30 1.5 0.5 2.5 Saturday Saturday Saturday Sunday Thurs day Saturday 01-08-2009 08-08-2009 15-08-2009 16-08-2009 20-08-09 22-08-09 14:00 14:00 9:00 10:00 19:30 14:00 17:15 17:00 12:00 13:00 20:00 18:00 3.25 3 3 3 0.5 4 Monday Wednesday Thurs day 24-08-09 26-08-09 27-08-09 14:00 8:30 13:30 17:00 10:45 16:30 3 2.25 3 Sunday 30-08-09 17:00 16:45 17:15 17:45 0.25 1 Tuesday 01-09-09 20:00 21:00 1 Thurs day Monday Thurs day Sunday Thurs day Saturday 03-09-09 07-09-09 09-09-09 20-09-09 24-09-09 26-09-09 19:00 10:30 21:30 10:00 14:00 19:00 20:00 13:00 22:30 13:00 16:30 21:30 1 2.5 1 3 2.5 2.5 Sunday 27-09-09 19:00 22:30 3.5 Monday 28-09-09 15:15 18:15 3 19:00 20:00 1 16:30 18:30 2 Tuesday 29-09-09 Work on research proposal Round off research proposal Round off research proposal Round off research proposal Round off research proposal Order various components, update website Unpack components, read manuals, connect components, test them First test electrical system (engine & batteries), check mass of components Research on new battery, solar panels and mass savings Catch up with report Investigation about Mylar, diode and other materials yet to order Start construction of wing Continue construction of wing Continue construction of wing Continue construction of wing Purchase carbon beams & push-rod in Amsterdam Continue construction of wing + investigate push-rod elevator Construction of tail Put wings together, start construction of fuselage WeCo time: Continue construction of tail, wheels, fuselage Ordering batteries and final equipment Making adjustments to engine mounting + preparing wiring and electronics for new battery Sending back wrong adaptor, testing LiPo battery charger and components Purchase rear cornice + supporting wooden beam Continue construction Spelling check + catch up with research project file Apply Mylar + finish elevator & push-rod Attempt soldering solar cells Second attempt to solder solar cells, no results, silver tin needed. Drilling new holes, gluing solar cells, connecting wire to cells with tape Soldering diode, finishing wiring, testing voltage, applying Mylar and ailerons Soldering diode, finishing wiring, testing voltage, applying Mylar and ailerons Applying Mylar to wing 71 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Wednesday 30-09-09 Thurs day 01-10-09 Friday 02-10-09 Saturday 03-10-09 Sunday 04-10-09 Monday 05-10-09 Tuesday 06-10-09 Wednesday 07-10-09 Thurs day 08-10-09 TOTAL 19:00 22:00 3 13:30 15:30 2 16:00 10:00 19:00 8:30 20:00 9:30 16:00 19:00 9:00 11:00 17:00 19:00 17:00 19:00 17:00 19:00 17:30 19:00 17:00 10:30 19:30 12:00 22:00 12:30 18:00 22:00 10:00 13:00 18:30 22:15 18:30 23:15 18:30 01:30 18:30 23:30 1 0.5 0.5 3.5 2 3 2 3 1 2 1.5 3.25 1.5 4.25 1.5 6.5 1 4,5 156 Gluing landing gear, determining centre of gravity, gluing fuselage, wings and rudder together Transporting plane to school, showing it at school, testing controls Installing new gear, doing final checks Arranging equipment for testing Setting up frame for testing Lift test, drive test Spelling check + catch up with research project file Working on file Working on file Working on file Working on file Testing solar cells' profit Working on file Working on file Working on file Working on file Working on file Working on file Working on file Working on file 72 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Tim‟s log Day Begin time Wednesday 01-04-2009 13:45 End time 16:00 Total time 2.25 19:45 20:00 0.25 20:00 21:00 1 10:15 11:15 1 20:00 21:00 1 11:35 11:50 0.25 18:00 19:00 1 Thurs day Friday Date 02-04-2009 03-04-2009 Saturday 04-04-2009 13:55 14:10 0.25 Sunday 05-04-2009 20:00 20:30 0.5 Tuesday 07-04-2009 9:45 10:15 0.5 Wednesday 08-04-2009 13:30 16:00 2.5 Thurs day 09-04-2009 Friday 10-04-2009 Wednesday 15-05-09 Wednesday 22-05-09 Wednesday 20-05-09 9:00 10:50 13:30 13:30 13:30 9:15 11:05 16:00 16:00 16:00 0.25 0.25 2.5 2.5 2.5 22:15 9:00 10:30 22:30 10:15 11:00 0.25 1.25 0.5 Wednesday 10-06-2009 13:30 16:00 2.5 Wednesday 24-06-2009 Thurs day 25-06-2009 10:00 10:00 13:00 13:00 3 3 18:00 15:45 18:30 16:30 0.5 0.75 Thurs day Friday Friday Sunday Monday 21-05-09 22-05-09 22-05-09 28-06-2009 29-06-2009 Description Introduction to research project, explanations on possibilities and brainstorming on topic Telephone call with Jesper, idea of solar powered airplane Orientation on topic, look at possible materials and parts, look up information, check out others ideas Discuss findings with Jesper, brainstorm on topic, come up with topics to be investigated Look at feasibility of project, focussing on solar cells, mass and engine Discuss finding, determine size of aircraft, discuss first materials Search for materials and parts on the internet, look at engines, look at forums Telephone call with Jesper, divide first tasks for looking up information. Tim will focus on controls, Jesper on wings & electrical system Orientation on controls, search the internet for possibilities and available materials/parts Discuss findings on ways of controls and number of solar cells. Determine aimed mass WeCo-time, report topic, look up parts together, investigate battery overload problems, post questions on forums and look at answers Look at further answers on forum Catch up with log WeCo-time: Work on research proposal WeCo-time: Work on research proposal WeCo-time: Work on research proposal, step three (engine, batteries, propeller & solar cells) Catch up with log Work on research proposal, step three (controls) Work on research proposal, step four (determining final mass & size) Work on research proposal, finish step four and start step six (placing of solar cells) Work on research proposal, step seven (design of wing) Work on research proposal, step seven (design of wing) and finishing of research proposal Research on international aspect of project Research on international aspect of project 73 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Tuesday 30-06-2009 Wednesday 31-06-09 Thurs day 01-07-2009 Friday 02-07-2009 Sunday 19-07-2009 20:00 22:30 9:30 10:15 19:00 19:45 20:30 8:00 11:15 13:30 15:30 11:00 17:30 22:15 23:00 10:00 10:30 18:30 23:15 23:15 9:30 11:45 15:30 15:45 11:45 18:15 2.25 0.5 0.5 0.25 1.5 3.5 2.75 1.5 0.5 2 0.25 0.75 0.75 18:45 19:00 0.25 20:30 22:15 1.75 Tuesday 21-07-2009 14:15 17:45 3.5 Tuesday 28-07-2009 19:15 22:00 2.75 Thurs day Saturday Saturday Saturday Sunday Monday 30-07-2009 01-08-2009 08-08-2009 15-08-2009 16-08-2009 17-08-2009 15:15 14:00 14:00 9:00 10:00 13:30 15:45 17:15 17:00 12:00 13:00 15:45 0.5 3.25 3 3 3 2.25 16:15 16:45 0.5 Friday Saturday 21-08-2009 22-08-2009 11:15 14:00 11:45 18:00 0.5 4 Monday Tuesday Wednesday Thurs day 24-08-2009 25-08-2009 26-08-2009 27-08-2009 14:00 22:00 8:30 13:30 17:00 22:15 10:45 16:30 3 0.25 2.25 3 Friday 28-08-2009 15:45 17:00 1.25 03-09-2009 05-09-2009 07-09-2009 20:00 20:30 20:00 10:30 19:00 20:30 20:45 20:30 13:00 20:30 0.5 0.25 0.5 2.5 1.5 Thurs day Sunday Monday Work on international aspect of project Work on international aspect of project Work on international aspect of project Research lending solar cells Research on international aspect of project Work on international aspect of project Work on international aspect of project Work on international aspect of project Work on international aspect of project Research / work on international aspect of project Start spelling & grammar check Work on international aspect of project Work on international aspect of project (spelling & grammar check) Work on international aspect of project (spelling & grammar check) Work on international aspect of project (spelling & grammar check) First test electrical system (engine & batteries), check mass of components Adjust 'construction' part in the research project document after test, research Mylar Buy beams at Praxis Start construction of wing Continue construction of wing Continue construction of wing Continue construction of wing Work on 'construction' part in the research project document Work on 'construction' part in the research project document Send e- mails concerning solar cells and Mylar foil Continue construction of wing + investigate push-rod elevator Construction of tail E- mail for information on Mylar foil Put wings together, start construction of fuselage WeCo time: Continue construction of tail, wheels, fuselage Look for suitable sponsors, E- mail ASN + Triodos for sponsoring Order Mylar foil Order solar cells Look at Schipholfonds as a sponsor Continue construction Update construction report 74 Research Project – Solar Challenger – JeT Productions – Tim van Leeuwen & Jesper Haverkamp - 2010 Monday Tuesday Wednesday Sunday 14-09-2009 15-09-2009 16-09-2009 20-09-2009 21-09-2009 16:30 22:45 13:15 10:00 21:30 19:15 16:45 23:00 13:30 13:00 22:00 20:45 0.25 0.25 0.25 3 0.5 1.5 Monday Thurs day Monday 24-09-2009 28-09-2009 14:00 15:15 16:30 18:15 2.5 3 19:00 20:00 1 29-09-2009 16:30 19:00 18:30 22:00 2 3 Wednesday 30-09-2009 13:30 15:30 2 15:30 10:00 16:30 8:30 13:00 17:00 10:30 17:30 12:00 16:00 1.5 0.5 1 3.5 3 16:00 18:45 2.75 19:30 21:30 2 21:30 10:15 22:00 13:00 0.5 2.75 16:45 17:45 1 06-10-2009 16:30 17:45 1.25 Wednesday 07-10-2009 10:15 17:00 19:00 21:00 14:00 11:30 18:30 21:00 0:30 15:30 1.25 1.5 2 3,5 1,5 139,25 Tuesday Thurs day 01-10-2009 Friday Sunday 02-10-2009 04-10-2009 Monday Tuesday Thurs day TOTAL 05-10-2009 08-10-2009 E- mail school for information on finances E- mail solar cell supplier for information on delivery E- mail school for information on moving the deadline Apply Mylar + finish elevator & push-rod Update construction report Update construction report + start spelling & grammar check on research project document Attempt soldering solar cells Solder diode, finish wiring, test the voltage of solar cells, apply Mylar to end of wings, install ailerons Solder diode, finish wiring, test the voltage of solar cells, apply Mylar to end of wings, install ailerons Apply Mylar to rest of wing Glue landing gear, determine centre of gravity, glue wings, fuselage and rudder together, charge battery Transport plane to school, show the plane, bring plane back home Install extra wheel, do final checks on plane Arrange equipment for lift test Film plane while driving, think of set-up for lift test Perform lift test, drive test Catch up with adjustments to research project document, check spelling and grammar Work on 'construction' part in the research project document Work on 'construction' part in the research project document Check international aspect Work on testing part and media attention part in research project document Write conclusion for research project document + add new data in testing part Write about media attention, Start with evaluation in research project document Continue evaluation in research project document Continue evaluation in research project document Finish conclusion and evaluation Order sources, finish logs, check document Working on file 75
© Copyright 2025 Paperzz