The Wildlife Call is a project of the Association of Fish & Wildlife Agencies' Legal Strategy in partnership with Michigan State University College of Law. Please add [email protected] to your address book to ensure our Legal Strategy updates land in your inbox. You may unsubscribe if you no longer wish to receive our emails. Wildlife Law Call CASE UPDATES Spring 2015 Focus on energy development and its impacts on fish and wildlife U.S. Circuit Courts Aransas Project v. Shaw, 774 F.3d 324 (5th Cir. 2014) Submitted by Morsheda Hashem The Aransas Project, an environmental organization, filed a suit against the Texas Commission on Environmental Quality (TCEQ) under the Endangered Species Act (ESA), alleging that the agency failed to adequately manage the freshwater flows into the bay, consequently resulting in takes of endangered whooping cranes. TCEQ administers the state surface water use permitting program. Plaintiff claimed TCEQ issued water use permits in 2008 and 2009 that proximately caused many whooping cranes to die. Plaintiff sought an injunction that would prevent TCEQ from issuing permits to withdraw water from the rivers that ultimately fed the estuary where the cranes reside. The lower court granted the injunction; however, this court reversed and found that the injunction was an abuse of discretion. The court reasoned that the issue of whether TCEQ administering licenses to take water as being the proximate cause of the deaths of whooping cranes had not been proven, and that there could have been other reasons why the cranes died. For example, the cranes could have died from lack of sufficient food or by the mere forces of nature. Thus, the court held that the correlation between water licensing and crane deaths was too attenuated, and, therefore, reversed the injunction against TCEQ. Google Scholar link to case Conservation Congress v. Finley, 774 F.3d 611 (9th Cir. 2014) Submitted by Eric Hughey Conservation Congress filed suit against the United States Forest Service (USFS) and the Fish and Wildlife Service (FWS), alleging that the agencies violated the Endangered Species Act (ESA), the National Forest Management Act, and the National Environmental Policy Act (NEPA) by failing to adequately consult as to a lumber thinning and fuel reduction project, known as the Beaverslide Project, and its potential effects on the Northern Spotted Owl. The district court granted summary judgment for the government and Conservation Congress appealed. First, the 9th Circuit considered defendants' arguments that the notice of suit was not specific enough and that the suit was moot because of new consultation USFS and FWS conducted in connection with a 2012 redesignation of critical habitat. The court affirmed the district court's ruling that Conservation Congress properly noticed the suit. It also affirmed the district court's ruling for the plaintiff on the mootness issue, noting that the work done under the 2012 redesignation did not adequately address plaintiffs' allegations regarding the 2011 recovery plan. Then, the court turned to the merits of the ESA issues. It determined that the Forest Service adequately considered new information obtained from the 2011 Recovery Plan, and also used the best scientific and commercial data available as required by the ESA. Similarly, the court also determined that consultations provided a thorough examination of the possible effects of the Beaverslide Project on the owl's habitat, and was therefore adequate under NEPA's hard look standard. The court affirmed summary judgment in favor of the government. Google Scholar link to case Friends of Merrymeeting Bay v. Hydro Kennebec, LLC, 759 F.3d 30 (1st Cir. 2014) Submitted by Justin Walton Plaintiff environmental groups brought an action under the Endangered Species Act and Clean Water Act (CWA) against operators of hydroelectric dams. Plaintiffs claimed that defendants failed to comply with the Kennebec Hydro Developers Group Settlement Agreement regarding endangered Atlantic salmon passage through the hydroelectric dams' turbines. The Settlement Agreement gave dam operators two options to accommodate fish passage. If the hydroelectric dam operator chooses not to install fish bypass systems and instead desires that fish pass through turbines, it must conduct studies that show that passage will not significantly harm or injure salmon. Otherwise, it must install fish bypass systems. The defendants chose to construct fish bypass systems so that the fish would not pass through the turbines. Despite bypass structures, plaintiffs alleged, fish continue to pass through the turbines and were harmed, and the defendants knew and therefore were in violation of the Agreement and the CWA. The defendants moved the trial court for summary judgment on the CWA claims, which it granted, finding that plaintiffs could not allege sufficient facts to show that defendants' desired that the fish pass through the turbines and thus defendants did not violate the Agreement and the CWA. On appeal, the court held that when determining whether the Defendant desired passage through the turbines, evidence of the Defendants' knowledge of passage through the turbines and effectiveness of the bypass methods are relevant when considering a motion for summary judgment. It vacated the district court's judgment and remanded the case for further consideration of the evidence Google Scholar link to case U.S. District Courts Bundorf v. Jewell, No. 2:13-CV-00616-MMD-PAL, 2015 WL 430600 (D. Nev. Feb. 3, 2015) Submitted by Justin Walton After consulting with the U.S. Fish and Wildlife Service, the Bureau of Land Management approved a wind energy development project in southern Nevada. The project area is home to threatened desert tortoise and some bird species such as golden eagles. Plaintiff individuals and environmental groups filed suit to challenge the decision. Plaintiffs alleged that defendants violated the National Environmental Policy Act (NEPA), the Endangered Species Act, the Federal Land Policy and Management Act, the Bald and Golden Eagle Protection Act, the Administrative Procedure Act, and the Migratory Bird Treaty Act. The court required further explanation regarding impacts on tortoises and eagles from the defendants before ruling on whether the final environmental impact statement was insufficient and violated NEPA. The court also found that a Supplemental Environmental Impact Study (SEIS) was necessary given a new study on golden eagles. It remanded the decision to BLM to supplement the administrative record and to prepare a SEIS. Google Scholar link to case Cape Fear River Watch, Inc. v. Duke Energy Progress, Inc., 25 F.Supp.3d 798 (E.D.N.C. 2014) Submitted by Corrinna Bailey Plaintiff environmental groups alleged Duke Energy Progress's coal-fired electric plant violated the Clean Water Act (CWA) by discharging polluted water from its coal ash lagoon into Sutton Lake, where people fished, and into groundwater. Defendant responded with a motion to dismiss arguing that the court lacked subject matter jurisdiction, as the CWA prohibits citizens from filing suit for the same violation filed by the federal or state government; and that the affected sources were not waters of the United States. The court rejected the first argument, distinguishing the current claim from the state agency's claims against defendant. Secondly, the court granted the motion to dismiss in part and denied it in part, finding that the groundwater was not jurisdictional, but that the lake was. In reaching this conclusion, the court considered two standards to define waters of the United States. The permanent waters standard requires a relatively permanent body of water ordinarily described as a stream, ocean, river, or lake connected to traditional interstate navigable waters; or a wetland with a continuous surface connection to such water. The significant nexus standard requires a significant nexus such that the waters or wetlands either alone or in combination with similarly situated regional lands significantly affect the chemical, physical, and biological integrity of waters readily understood as navigable. Considering these standards, the court reasoned groundwater was not a water of the United States as it did not fall within the meaning of the CWA, but that the lake was because, despite the lake's creation as a cooling pond, it fit squarely within common understanding as a lake, and other public lakes used as cooling reservoirs were classified as waters of the United States. Google Scholar link to case Center for Biological Diversity v. Export Import Bank for the U.S., No. C 12-6325 SBA, 2015 WL 738641 (N.D. Cal. Feb. 20, 2015) Submitted by Leslie Garrison Plaintiff environmental group brought action against the Export-Import Bank of the U.S., alleging that the Bank did not comply with the Endangered Species Act (ESA), the National Historic Preservation Act, or the Administrative Procedure Act when approving $4.8 billion in financing to two liquefied natural gas construction projects in Australia. The projects would partially be located in the Great Barrier Reef World Heritage Area. Plaintiffs contended that the projects would harm listed wildlife including dugongs, whales, saltwater crocodiles, and sea turtles. Defendant filed for a motion to dismiss based on a failure to allege sufficient facts to support a claim, arguing that the ESA does not require agencies to consult for projects in foreign countries. The court denied defendant's motion because "agency actions" requiring action under ESA are defined very broadly and defendant did not provide sufficient facts that the financing was relegated only to construction activities taking place in Australia and not to post-construction facilities that involve the export of materials on the high seas. Google Scholar link to case Center for Biological Diversity v. Hagel, No. C-03-4350 EMC,2015 WL 1568838 (N.D. Cal. Feb. 13, 2015), appeal docketed, No. 15-15766 (9th Cir. Apr. 16, 2015) Submitted by Jason Statler The Center for Biological Diversity (CBD) sued the Department of Defense (DOD) for injunctive relief, alleging that DOD's construction on an airbase in Japan would alter or destroy the feeding and breeding grounds of the Okinawa Dugong, an endangered species. Specifically, CBD alleged that DOD "failed to take into account" adverse effects to the dugong under the National Historic Preservation Act (NHPA). DOD countered that the proposed construction falls under the political question doctrine and accordingly is an executive branch decision regarding foreign policy and is not enjoinable by the court. The court held that the political questions doctrine controlled and so it lacked the power to enjoin or prohibit the construction of an overseas military facility that was being built in accordance with treaty obligations. Furthermore, the court also held that the CBD did not have standing, as any declaratory relief the court granted would not address CBD's alleged injury because the specific NHPA provision that plaintiff is suing under "neither forbids destruction of a protected property nor commands its preservation." In other words, even if the court ruled in plaintiff's favor, that ruling would not require DOD to stop or alter its construction plans, and so there was no guarantee that CBD's alleged injury would be redressed. Google Scholar Link to Case Defenders of Wildlife v. Jewell, No. 3:13-cv-698-PLR-CCS, 2015 WL 402680 (E.D. Tenn. Jan. 28, 2015) Submitted by Eric Hughey Defenders of Wildlife and other environmental groups brought suit against the Office of Surface Mining and Reclamation (OSM), the Department of the Interior, and the Fish and Wildlife Service under the Endangered Species Act and the Administrative Procedure Act. Plaintiffs alleged that contaminated coal mine water was seeping into waterways and harming endangered fish. The defendants moved to dismiss the case for lack of standing and for mootness. The court held that plaintiffs did not allege site-specific injuries on some of their claims, and therefore, plaintiffs failed to establish standing on those claims. The defendants moved to dismiss some claims as moot because the mine to which the claims pertained had been closed and was undergoing remediation. The court refused to dismiss these claims as moot, holding that the OSM could still revise or revisit the reclamation plan or issue an enforcement order for further remedial work. Google Scholar Link to Case Kentucky Coal Association, Inc. v. Tennessee Valley Authority, No. 4:14-CV-00073JHM, 2015 WL 461402 (W.D. Ky. Feb. 3, 2015), appeal docketed, No. 15-5163 (6th Cir. Feb. 19, 2015) Submitted by Samantha Reasner Plaintiffs filed a complaint seeking a declaratory judgment that defendant, Tennessee Valley Authority, violated the National Environmental Policy Act (NEPA), the Administrative Procedure Act, and the Tennessee Valley Authority Act by failing to issue an environmental impact statement (EIS) regarding its decision to retire two coal-fired electric generating units and replace them with a natural gas-powered generation facility. Instead, the Defendant issued an Environmental Assessment (EA) with a Finding of No Significant Impact. Plaintiffs argued that an EIS was required because TVA had previously said the action taken would "normally" require one. The court held that TVA had discretion to determine whether an EIS was necessary, regardless of its statement that this action would normally require one. Additionally, plaintiffs alleged that TVA segmented its analysis of the effect of the action. Plaintiffs argued that the EA had to analyze the cumulative effects of the retirement of both coal units. The court held that TVA's conclusion that the effects were too speculative was appropriate because the timing of retirement was not yet established. The court also held that TVA's NEPA analysis adequately addressed wetlands, endangered and threatened species, historical and cultural concerns, and greenhouse gas emissions. Plaintiffs also argued that TVA had a predetermined outcome in mind when it did the NEPA analysis, but the court found that NEPA does not require an agency to be impartial -- only that it not make an irreversible and irretrievable commitment of resources before doing the analysis. Defendant's motion for judgment on the administrative record was granted. Plaintiffs' appeal is currently pending before the 6th Circuit. Google Scholar Link to Case National Parks Conservation Association v. U.S. Department of the Interior, No. 2:11cv-578-FtM-29CM, 2015 WL 476163 (M.D. Fla. Feb. 5, 2015), appeal docketed, No. 15-11599 (11th Cir. April 14, 2015) Submitted by Jason Statler In September 2014, the district court entered summary judgment for the government on plaintiff environmental groups' challenge to the National Parks Service's (NPS) decision to allow off-road vehicle use in part of a national preserve in Florida. The groups petitioned the court for reconsideration, arguing in part that the NPS violated the National Park Service Organic Act by failing to include an impairment determination with respect to existing visitor use and experience. The court determined that the Organic Act was silent on the issue of park management and therefore gave the Secretary broad discretion on how to implement the statutory mandate. The Plaintiffs' argument that NPS's management policies created a duty for NPS to include an impairment determination was also unavailing, the court determined, as the management policies do not create an enforceable duty against NPS. The court also ruled that it had previously adequately dealt with the other issues on which plaintiffs requested reconsideration. Accordingly, the court denied the motion for reconsideration. Google Scholar Link to Case Oceana v. Bureau of Ocean Energy Management, 37 F.Supp.3d 147 (D.D.C. 2014) Submitted by Morsheda Hashem Various environmental organizations filed a lawsuit against the Bureau of Ocean Energy Management (BOEM) and the National Marine Fisheries Service (NMFS), challenging BOEM's approval of two oil and gas leases in the Gulf of Mexico where the Deepwater Horizon oil spill occurred. Oil producers intervened as defendants. The plaintiffs made National Environmental Policy Act (NEPA) and Endangered Species Act (ESA) claims against BOEM and Administrative Procedure Act (APA) claims against NMFS. Specifically, Plaintiffs claimed that BOEM violated NEPA by failing to take a hard look at the environmental consequences of the lease sale and by failing to consider a no-action alternative, that BOEM violated the ESA by failing to prevent jeopardy to listed species by approving the lease sale, and that NMFS violated APA by delaying in preparing a biological opinion (BO). The court found for defendants on all claims. First, it found that BOEM complied with NEPA by doing appropriate analysis with the information it had, incorporated new data when it came available, considered the possibility of another spill, and did consider a no-action alternative. It also found that BOEM followed the ESA by ensuring that it used the best available science and acted to ensure that protected species would not be jeopardized, and it could act without waiting for NMFS to finish the BO as it did not make an irreversible or irretrievable commitment of resources. NMFS's delay in producing the BO was not unreasonable, the court decided, so it granted summary judgment for NMFS on the APA claim as well. Google Scholar Link to Case Ohio Valley Environmental Coalition v. Fola Coal Company, LLC, No. 2:13-5006, 2014 WL 3743597 (S.D.W.Va. July 30, 2014) Submitted by Samantha Reasner Plaintiffs alleged the Fola Coal Company violated the Clean Water Act and the Surface Mining Control and Reclamation Act by discharging ionic pollution from its surface mine into Twentymile Creek in violation of its permits. Plaintiffs moved for summary judgment on jurisdictional issues, alleging that they have standing; defendants filed a cross-motion for summary judgment on standing and four other issues, which the court handled summarily. The court then turned to standing. It found that two members of plaintiffs' organizations could show injury in fact through alleged harm to their aesthetic and recreational interests - they visited the area and had concerns about the discharges' effects on the area. Their injuries were also "fairly traceable" to the discharges and a court can enjoin the discharges. It also found that plaintiffs had associational standing. It granted plaintiffs' motion. Google Scholar Link to Case Protect Our Lakes v. U.S. Army Corps of Engineers, No. 1:13-CV-402-JDL, 2015 WL 732655 (D. Me. Feb. 20, 2015) Submitted by Corrinna Bailey The Maine Department of Environmental Protection approved Evergreen for the construction of a wind energy farm after considering impacts to bald eagles, Atlantic salmon, and other species. Evergreen also informally consulted with the United States Army Corps of Engineers (Corps) to fill wetlands for the wind farm's construction. During the public comment period on the permit, the National Marine Fisheries Service (NMFS) recommended mitigation measures for potential impacts on salmon and the Corps informally consulted with the U.S. Fish and Wildlife Service (FWS) regarding potential impacts on eagles and other species. Plaintiff environmental groups alleged the Corps violated several environmental statutes, including the Endangered Species Act (ESA) and the Bald and Golden Eagle Protection Act (BGEPA), by issuing a Clean Water Act (CWA) § 404 permit for the wind farm's construction without first complying with these laws. Since plaintiffs did not sue NMFS or FWS, they could only prevail on their ESA consultation claim if they alleged additional information regarding impacts of the project on listed species that contrasts with the information in those consulting agencies' opinions. The court found that plaintiffs did not meet their burden of proof on this claim. The plaintiffs also claimed that ESA required issuance of an incidental take statement, but the court disagreed. BGEPA does not have a citizen suit provision, so the court treated plaintiffs' BGEPA claim as an Administrative Procedure Act claim. Plaintiffs essentially claimed that it was arbitrary and capricious for the Corps to issue a CWA 404 permit without an eagle take permit, but the law does not require this, nor did plaintiffs show that eagle take had occurred. The court granted summary judgment for the defendants. Google Scholar Link to Case Public Employees for Environmental Responsibility v. Beaudreau, 25 F.Supp.2d 67 (D.D.C. 2014) Submitted by Ethan Shirley Wind developing companies sought approval for various projects in Nantucket Sound from the Bureau of Ocean Energy Management (BOEM). During the approval process, BOEM had to consult with several other agencies, including the Coast Guard, the Fish and Wildlife Service (FWS), and the National Marine Fisheries Service (NMFS) as it reviewed the projects. BOEM ultimately issued decisions approving aspects of the projects. Several Plaintiffs filed separate suits to challenge the agency reviews of the projects. These claims were consolidated. Plaintiffs brought claims under several federal statutes, including the Administrative Procedure Act, the Endangered Species Act (ESA), the Migratory Bird Treaty Act (MBTA), the National Environmental Policy Act, the Outer Continental Shelf Lands Act, the Clean Water Act, the Rivers and Harbors Act, the Coast Guard and Maritime Transportation Act of 2006, the National Historic Preservation Act, and the Energy Policy Act. Of particular interest is the court's review of BOEM's work under ESA and the MBTA. Some Plaintiffs made ESA claims against FWS for the wind turbines' potential impacts to protected seabirds, and the court found that FWS had improperly deferred to BOEM and Cape Wind on operational adjustments to turbines to limit bird kills. The court also examined claims against NMFS regarding impacts on right whales and sea turtles. It found that NMFS's biological opinion with regard to right whales met the ESA's requirements, but that NMFS improperly failed to issue an incidental take statement with the opinion. It also approved NMFS's analysis with respect to impacts on sea turtles. The court also held that BOEM did not need to get an MBTA take permit for its approval of the project, as its approval was too far removed from the causal chain of any future bird takes. The court remanded the case to the FWS to make an independent determination on operational adjustments to turbines relating to protecting seabirds and remanded to NMFS to issue an incidental take statement for right whales. A subsequent appeal in June 2014 to the U.S. Court of Appeals for the D.C. Circuit was dismissed. Google Scholar Link to Case Reese River Basin Citizens Against Fracking, LLC v. U.S. Bureau of Land Management, No. 3:14-CV-00338-MMD-WG, 2014 WL 4425813 (D. Nev. Sept. 8, 2014) Submitted by Ethan Shirley Plaintiff, a group whose members included farmers and ranchers who have property interests or water or grazing rights in land that the Bureau of Land Management (BLM) has proposed for oil and gas leasing, brought suit to enjoin BLM from issuing some oil and gas leases. BLM started the mineral leasing process for this land, releasing a preliminary Environmental Impact Statement (EIS) under the National Environmental Policy Act (NEPA) for public comment. BLM's preliminary EIS showed that development would cause no significant environmental impact. BLM then conducted a lease sale, but did not issue any leases. Plaintiff then petitioned the court for a preliminary injunction, alleging that BLM had not conducted appropriate NEPA reviews. In its analysis, the court noted that for it to have jurisdiction over the claim, final agency action was required. Final agency action requires "consummation of the agency's decisionmaking process" and determination of legal rights or obligations. BLM was still in the process of revising its environmental analysis through public comment, and had not issued any leases. Therefore, the court did not have jurisdiction to issue an injunction and it denied Plaintiff's injunction. Google Scholar Link to Case Rocky Mountain Wild v. U.S. Fish and Wildlife Service, No. CV 13-42-M-DWM, 2014 WL 7176384 (D. Mont. Sept. 29, 2014) Submitted by Jourdan Rasmussen Plaintiff environmental groups filed suit in response to U.S. Fish and Wildlife Service's (FWS) 12-month finding that the prairie dog was not threatened or endangered in response to a petition to list the white-tailed prairie dog under the Endangered Species Act (ESA). Both sides moved for summary judgment. The court found for plaintiffs on some counts and for defendants on others. First, the court considered whether FWS did adequate analysis to determine whether the prairie dog was at risk throughout a significant portion of its range. It found that FWS failed to adequately consider historic range, but that it adequately evaluated abundance and distribution. The court also considered FWS's threats analysis, determining that FWS inappropriately dismissed some threats after determining that they were individually insignificant and that it inappropriately concluded that the regulatory framework to protect the prairie dog was sufficient given the threats posed by oil and gas development. On the other hand, the court found other aspects of FWS's prairie dog threats analysis, such as cumulative impacts, to be adequate. Finally, the court found that FWS disregarded available data, which violated the ESA's mandate that FWS use the best available science in its analysis. The court remanded the case to FWS for reconsideration on the aspects of its findings that the court deemed deficient. Link to Case San Francisco Herring Association v. Pacific Gas and Electric Co., No. 14-cv-04393-WHO, 2015 WL 859420 (N.D. Cal. Feb. 26, 2015) Submitted by Leslie Garrison Plaintiffs, a local homeowner and a fishermen's association, allege that Pacific Gas & Electric Company violated both the Clean Water Act (CWA) and the Resource Conservation and Recovery Act (RCRA), as the defendant operated manufactured gas plants over one hundred years ago that continue to pollute the San Francisco Bay and some plaintiffs' homes. Defendant allegedly dumped waste residues from the manufacturing process on nearby sites and into nearby waterways. The homeowner now resides on a waste deposit site. Additionally, the waste has been proven to be present in groundwater, which moves into the storm sewer and then into the Bay. Once in the Bay, it may kill fertilized herring eggs, causing potentially devastating impacts on the herring that breed there and the economic value they bring to the community. Defendants sought a motion to dismiss alleging a deficient notice of suit under the CWA, that the plaintiff Association lacked standing, that plaintiffs inadequately stated a claim under the CWA, and that the plaintiffs inadequately stated a claim under RCRA. The court found that the plaintiffs pleaded their CWA claim with enough specificity to meet the CWA notice requirement and that the Association met the standing requirements. Further, it found that the plaintiffs adequately alleged ongoing violations and not wholly past violations, that the plaintiffs appropriately identified the alleged point sources in question, and that they showed the Bay was affected such that the plaintiffs alleged a discharge into a navigable water and not just groundwater. Finally, the court found that the plaintiff sufficiently pleaded RCRA claims and they were not precluded by the CWA claims. The court denied the motion to dismiss. Google Scholar Link to Case Sierra Club v. U.S. Army Corps of Engineers, Civil Action No. 13-cv-1239 (KBJ), 2014 WL 4066256 (D.D.C. Aug. 18, 2014), appeal docketed, No. 14-5205 (D.C. Cir. Aug. 27, 2014) Submitted by Jourdan Rasmussen Plaintiff environmental groups filed suit against the U.S. Army Corps of Engineers, U.S. Fish and Wildlife Service, and the U.S. Pipeline and Hazardous Materials Safety Administration (PHMSA), alleging that these agencies violated the National Environmental Policy Act (NEPA), the Administrative Procedure Act (APA), and the Clean Water Act (CWA) by allegedly failing to do a full environmental review of an oil pipeline project. The 589-mile-long pipeline was slated for construction from Pontiac, Illinois to Cushing, Oklahoma and almost entirely on private land. The pipeline would only cross 27.28 miles of federal land. Finding that PHMSA had not even received an application for approval of an oil spill response plan, the court dismissed claims against PHMSA. The court found that a construction of a domestic pipeline on private lands simply did not qualify as a "federal government action," and therefore reasoned that the agencies' failure to consider the actions of a private company on private lands did not violate NEPA or the CWA. The court further held that Congress intended NEPA to cover major federal actions, not "federal evaluation and oversight of a private construction project," and so neither agency had a duty to review the pipeline. Finally, the court found that the Corps' cumulative impacts analysis comported with NEPA and the APA. Thus, the court entered summary judgment in favor of the governmental agencies. Plaintiffs are appealing to the D.C. Circuit. Google Scholar Link to Case Union Neighbors United, Inc. v. Jewell, Civil Case No. 13-01435 (RJL),2015 WL 1285741 (D.D.C. March 18, 2015) Submitted by Erin Elizabeth Sweeney Union Neighbors United sued the Department of the Interior, the U.S. Fish and Wildlife Service ("FWS") and the Midwest Region of the FWS over the final approval and issuance of an incidental take permit for endangered Indiana bats. Under the permit, Buckeye Wind Project was approved for 26 individual takes over a five-year period or 130 individual takes over a 25-year period. Union Neighbors United asserted that the issuance of the incidental take permit violated the National Environmental Policy Act, the Endangered Species Act (ESA), and the Administrative Procedure Act as arbitrary and capricious, and abuse of discretion, and not in accordance with the ESA's mitigation requirements. Ruling on a motion for summary judgment, the court held that the FWS followed proper procedure in determining that the wind project will, "to the maximum extent practicable, minimize and mitigate" the impacts of the taking. The court further held that once FWS determined that the taking was fully offset, the agency was not required to investigate measures that could further minimize or mitigate the impact of the taking. Because FWS "used the best available scientific evidence and modeling, as well as its expertise, to conclude that the [p]roposal will adequately protect the Indiana bat," its decision is entitled to deference. The court granted summary judgment for the government. Google Scholar Link to Case United States of America v. PacifiCorp Energy, No. 14-CR-301-KHR, Plea Agreement, ECF No. 2 (D. Wyo. Dec. 19, 2014) Submitted by Erin Elizabeth Sweeney In December 2014, PacifiCorp pleaded guilty to violating the Migratory Bird Treaty Act (MBTA) due to the deaths of protected birds at four wind projects in Wyoming, Seven Mile Hills and Glen Rock/Rolling Hills. Pursuant to the plea agreement, the company will pay $1.9 million in community service payments, $200,000 in restitution, and $400,000 in fines. The agreement also requires PacifiCorp to implement a comprehensive compliance plan negotiated with the U.S. Fisheries and Wildlife Service aimed at preventing migratory bird deaths. Additionally, the company must also apply for Eagle Take Permits for each wind project. The settlement agreement provides that the federal government will not criminally prosecute subsequent violations of the MBTA by either wind project as long as PacifiCorp complies with the negotiated plan and seeks Eagle Take Permits. Compliance costs are estimated at $600,000 per year. Google Scholar Link to Case List of Selected Federal Statutes Cited in Cases Administrative Procedure Act (APA): Sets framework by which federal agencies can establish rules, as well as provides for judicial review of agency action. http://www.gpo.gov/fdsys/pkg/USCODE-2013-title5/pdf/USCODE-2013title5-partI.pdf Bald and Golden Eagle Protection Act (BGEPA): Protects bald and golden eagles. http://www.gpo.gov/fdsys/pkg/USCODE-2013-title16/pdf/USCODE2013-title16-chap5A-subchapII.pdf Clean Water Act (CWA): Regulates discharges of pollutants into and quality standards for surface waters. http://www.gpo.gov/fdsys/pkg/USCODE-2013-title33/pdf/USCODE-2013-title33chap26.pdf Endangered Species Act (ESA): Sets procedures for listing species of conservation concern as "endangered" or "threatened" as well as designating habitat "critical" to these species' survival, prohibits "take" of endangered species, and provides exceptions to take prohibitions. http://www.gpo.gov/fdsys/pkg/USCODE-2013-title16/pdf/USCODE-2013-title16chap35.pdf Energy Policy Act (EPAct) of 2005: Gives the Federal Energy Regulatory Commission additional authority to ensure the electricity industry is competitive, to protect consumers, and to strengthen the U.S.'s energy infrastructure. http://www.gpo.gov/fdsys/pkg/USCODE-2013-title42/pdf/USCODE-2013-title42chap149-subchapXII.pdf Federal Land Policy and Management Act (FLPMA): The framework for the Bureau of Land Management's management of federal public lands. http://www.gpo.gov/fdsys/pkg/USCODE-2013-title43/pdf/USCODE-2013-title43chap35.pdf Migratory Bird Treaty Act (MBTA): Originally passed to implement an international treaty on migratory birds, the MBTA protects many species of migratory birds. http://www.gpo.gov/fdsys/pkg/USCODE-2013title16/pdf/USCODE-2013-title16-chap7-subchapII.pdf National Environmental Policy Act (NEPA): Establishes national environmental policy and requires federal agencies to consider the environmental impacts of their actions. http://www.gpo.gov/fdsys/pkg/USCODE2013-title42/pdf/USCODE-2013-title42-chap55-subchapI.pdf National Historic Preservation Act (NHPA): Legislation intended to preserve historical and archaeological sites in the U.S. It requires federal agencies to evaluate the impact of proposed projects on historic properties. It is enforced through a review process by which the federal agency must "take into account" the building project's impact on the historic site. http://www.gpo.gov/fdsys/pkg/USCODE-2013-title16/pdf/USCODE-2013-title16chap1A.pdf National Park Service Organic Act (NPSOA): The act that set up the National Park Service and sets forth NPS's duties and authorities. http://www.gpo.gov/fdsys/pkg/USCODE-2013-title16/pdf/USCODE-2013-title16chap1-subchapI.pdf Outer Continental Shelf Lands Act (OCSLA): The Outer Continental Shelf Lands Act, created on August 7, 1953, defines the OCS as all submerged lands lying seaward of state coastal waters (3 miles offshore) which are under U.S. jurisdiction. Under the OCSLA, the Secretary of the Interior is responsible for the administration of mineral exploration and development of the OCS. http://www.gpo.gov/fdsys/pkg/USCODE-2013-title43/pdf/USCODE-2013-title43chap29-subchapIII.pdf Resource Conservation and Recovery Act (RCRA): The primary federal statute regulating solid and hazardous wastes. http://www.gpo.gov/fdsys/pkg/USCODE-2013-title42/pdf/USCODE-2013-title42chap82.pdf Surface Mining Control and Reclamation Act (SMCRA): A Federal Act that created the Office of Surface Mining Reclamation and Enforcement to regulate surface coal mining operations and the reclamation of abandoned mines. http://www.gpo.gov/fdsys/pkg/USCODE-2013-title30/pdf/USCODE-2013-title30chap25.pdf Tennessee Valley Authority Act (TVAA): Act that set up the Tennessee Valley Authority (TVA). The TVA is incorporated as the largest public power provider in the United States. Congress established TVA in 1933 to address a wide range of environmental, economic, and technological issues, including the delivery of low-cost electricity and the management of natural resources. http://www.gpo.gov/fdsys/pkg/USCODE-2013-title16/pdf/USCODE-2013-title16chap12A.pdf About the Student Contributors Originally from Alaska, Corinna Bailey is a second year law student at Michigan State University College of Law. Her focus is on Environmental Law and Indian Law, which she hopes to apply toward a future career in the conservation of her home state's natural resources. Leslie Garrison is a JD/MBA candidate at Michigan State University concentrating on corporate law and supply chain management. Prior to attending graduate school, Leslie worked as a wind energy developer, which gave her experience in project management, lobbying and regulatory compliance. After graduation, Leslie will be working in a business development role at Intel Corporation in the San Francisco Bay Area. Morsheda Hashem is a third year JD student at Michigan State University College of Law. She is interested in practicing family law, immigration law, and international law in the greater Chicago area of Illinois. Additionally, Ms. Hashem hopes to travel abroad and work for international organizations in the legal and humanitarian arena. Eric Hughey is a third year law student at Michigan State College of Law. He is planning on practicing in his home state of Michigan in the field of social security disability law. Jourdan Rasmussen is a third year JD student at Michigan State University College of Law from the great state of Michigan. Jourdan has previously served as a law clerk for the Association of Fish and Wildlife Agencies in Washington, D.C. He has traveled to 46 states and is looking forward to a future in environmental and wildlife law, wherever the next endeavor may lie. Samantha Reasner is a second year student at Michigan State University College of Law. Originally from northern Michigan, Samantha is interested in Agricultural and Environmental Law. Samantha will spend the summer of 2015 interning in the legal services division of the Michigan Department of Agriculture and Rural Development. Ethan Shirley is an EMT, biologist, and educator. He is a J.D. candidate in the College of Law and a M.S. candidate in the Department of Fisheries and Wildlife at Michigan State University. His research looks at environmental laws, compliance with environmental laws and alternate means of enforcement in the Pantanal region of Brazil. Jason Statler is a rising 3L at Michigan State University School of Law. He is interested in practicing in his home state of Pennsylvania in the field of Insurance Defense. Erin Elizabeth Sweeney is a third year student at Michigan State University College of Law pursuing a career in commercial negotiation and dispute resolution. Her substantive practice interests include energy, oil and gas, and water law. Prior to attending law school, she taught English in Croatia at both the M.A. and B.A. levels on a 2011-2012 Fulbright Fellowship. Ms. Sweeney will take the July 2015 Texas bar exam. Justin Walton is a joint JD/MBA candidate. His legal studies have focused on business law. Justin's MBA focus is Supply Chain Management. Prior to entering law school, Justin worked for a biodiesel fuel company, which gave him exposure to environmental concerns in the energy field. Justin will spend the summer of 2015 interning at Dell, Inc. as a Graduate Senior Advisor. Upon graduation in 2016, Justin plans to pursue a career in sourcing and procurement. About the WILDLIFE LAW CALL Professor Carol Bambery assigned these case summaries to her Spring 2015 Legal Issues with Wildlife and Energy Development class at Michigan State University College of Law as a class project. The students chose recent fish- and wildlife-related decisions - most with an energy nexus issued by federal courts and summarized them for this newsletter. The Wildlife Law Call does not report every recent case, but we hope that you will find the included summaries interesting and informative. Prof. Bambery is general counsel for the Association of Fish & Wildlife Agencies (AFWA) in Washington, DC. AFWA is a professional association; its members are the fish and wildlife agencies of the 50 U.S., U.S. territories, some Canadian provinces and Mexican states, as well as some U.S. federal agencies. AFWA staff members Parks Gilbert and Laura MacLean assisted with the production of the Wildlife Law Call. Association of Fish & Wildlife Agencies 202-838-3460 [email protected] www.fishwildlife.org The Voice of Fish & Wildlife Agencies Copyright © 2015. All Rights Reserved. Bald Eagle Photo by George Andrejko.
© Copyright 2026 Paperzz